KR20160144134A - The Construction Method of Continuous soil cement a Pile Walls - Google Patents
The Construction Method of Continuous soil cement a Pile Walls Download PDFInfo
- Publication number
- KR20160144134A KR20160144134A KR1020150080508A KR20150080508A KR20160144134A KR 20160144134 A KR20160144134 A KR 20160144134A KR 1020150080508 A KR1020150080508 A KR 1020150080508A KR 20150080508 A KR20150080508 A KR 20150080508A KR 20160144134 A KR20160144134 A KR 20160144134A
- Authority
- KR
- South Korea
- Prior art keywords
- ground
- stress
- wall
- type cutter
- stress members
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/10—Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The present invention discloses a continuous wall construction method of soil cement using a chain-type cutter. The present invention relates to a method of constructing a continuous wall construction method using a chain type cutter in which stress materials inserted into the ground are connected by a reinforcing material, While securing the structural stability while maintaining a wide width in the lateral direction, reducing the amount of the stress material used, thereby enabling economical construction and shortening the construction period.
Description
The present invention relates to a technique for constructing a continuous wall in a ground using a chain-type cutter, and more particularly, to a method for constructing a continuous wall by using a chain type cutter, In the construction of continuous wall filled with mixed gel type soil cement, by connecting the stressed materials inserted into the ground to the reinforcing material, it is possible to secure the structural stability while widening the gap between the stressed materials. Cement underground continuous wall construction method.
Generally, the continuous wall construction of soil cement using a chain-type cutter is performed by a trench cutting re-mixing deep wall method. Such a TRD method is applied to
That is, the TRD method as described above can be applied safely because the construction equipment is designed with a low center of gravity and the height of the construction equipment is remarkably low, and it is possible to carry out the construction with high precision, and it is possible to carry out the construction with high accuracy from straightness and verticalness, In addition to economical construction, it is possible to reduce costs by excavating and agitating ability. In addition, it can mix and mix all the vertical direction layers simultaneously. Therefore, The walls can be made up, down, left, and right so that the wall structure can be formed with high continuity and homogeneity.
However, in the conventional continuous wall construction method, when the gap L1 of the
Therefore, when the gap of the stress material is narrowly set, it is not only an uneconomical problem that requires a large amount of cost due to the excessive use of the stress material, but also has a disadvantage that the workability is decreased and the disclosure period is prolonged.
SUMMARY OF THE INVENTION The present invention has been made in order to solve the conventional problems as described above, and it is an object of the present invention to provide an apparatus and a method for constructing a structure, The present invention has been made to provide a continuous wall construction method of soil cement underground using a chain type cutter which can reduce the construction period and shorten the construction period.
Another object of the present invention is to provide a method of manufacturing a cement mortar composition which, when applied to a soil having a weak cohesive force such as a clay layer, additionally inserts a predetermined reinforcing aggregate such as sand together with cement through a chain- The present invention provides a continuous wall construction method of soil-cement underground using a chain-type cutter capable of widening a gap between stressed materials without being wasted.
It is still another object of the present invention to provide a slant measuring device on one side of a chain type cutter and form a wall construction space in a state where a chain type cutter is vertically installed when digging the ground using an excavation equipment, The present invention also provides a continuous cement underground continuous wall construction method using a chain type cutter that allows the stress agent to maintain verticality.
In order to accomplish the above object, there is provided a continuous cement floor continuous wall construction method using a chain type cutter, comprising: a first step of vertically excavating a floor using a chain type cutter; A second step of successively constructing a wall installation space having a predetermined depth from the ground along the ground excavated from the first process; A third step of horizontally inserting a stress material into the wall space while maintaining a gap of 1.5 to 2.0 m inside the wall space when the wall space is installed in the ground by the second step; A fourth step of connecting the stressed materials to the reinforcements while maintaining a gap of 1.5 to 2.0 m in the ground from the third step; And a fifth step of filling the wall construction space with the gel-like cement mixed with the soil gypsum in the state where the stress material and the reinforcing material connecting the stress materials are connected to construct a continuous wall; .
In the present invention, in the case where the wall is applied to the ground where the cohesive force of the gypsum is weak, such as the clay layer, the reinforcing aggregate is additionally supplied together with the cement through the chain type cutter in addition to the soil gypsum, So that the gap between the stress members can be widely applied.
The present invention is also characterized in that a slope measuring device is additionally provided on one side of the chain type cutter to form a wall construction space with the chain type cutter vertically installed when excavating the ground using excavation equipment, The stress applied to the space can be maintained in the vertical direction.
Further, the reinforcing member is a mesh net or a grid which is welded and fixed to the inside of the stress members to connect the stress members.
In addition, the stress members connected to each other by the reinforcing member are configured to be maintained at a constant interval (e.g., 1.8M or more) by the spacer for maintaining spacing.
In addition, the connecting member is a reinforcing bar or wire which is connected to one end of the stress members in an X-direction or horizontally.
Further, the reinforcing member is a mesh net or a grid which is welded to the outside of the stress members to connect the stress members and keep the spacing constant.
In addition, the reinforcing material is a mesh net or a grid which is welded and fixed to the inside of the stressed materials to join the stressed materials, and the mesh net or the grid has a multi-layered structure for keeping the spacing of the stressed materials constant.
Further, the connecting material is reinforcing steel or wire.
As described above, according to the present invention, the stress members inserted into the ground are connected by a reinforcing member, thereby securing the structural stability while widening the gap between the stress members, reducing the use of the stress material, , It is expected that the effect of shortening the construction period can be expected.
When the wall is applied to a ground having weak cohesive force, such as a clay layer, a predetermined reinforcing aggregate is added to the ground along with the cement through a chain-type cutter, So that the gap between the stress members can be widely applied.
1 and 2 show a conventional continuous wall construction method.
3 is an enlarged perspective view showing a continuous wall construction method of soil cement using a chain type cutter of a conventional continuous earth wall construction method.
Figure 4 is a schematic cross-sectional view of Figure 3 of a conventional underground continuous wall construction method.
5 is a view showing a warping phenomenon when a gap of a conventional stress material is widened.
6 is an enlarged perspective view showing a continuous wall construction method of soil cement underground using a chain type cutter as a first embodiment of the present invention.
Figure 7 is a schematic cross-sectional view of Figure 4 as a first embodiment of the present invention.
8 is an enlarged perspective view showing a continuous wall construction method of soil cement underground using a chain type cutter according to a second embodiment of the present invention.
Figure 9 is a schematic cross-sectional view of Figure 6 as a second embodiment of the present invention;
10 is an enlarged perspective view showing a continuous wall construction method of soil cement underground using a chain type cutter according to a third embodiment of the present invention.
Fig. 11 is a schematic cross-sectional view of Fig. 8 according to a third embodiment of the present invention; Fig.
FIG. 12 is a conceptual view showing a process of adding a predetermined reinforcing aggregate together with cement through a chain-type cutter in addition to on-site soil in construction of soft ground.
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.
FIG. 6 is an enlarged perspective view showing a continuous wall construction method of soil-cement underground using a chain-type cutter as a first embodiment of the present invention, and FIG. 7 is a schematic cross-sectional view of FIG. 6 as a first embodiment of the present invention .
Referring to FIGS. 6 and 7, the method for constructing the continuous wall of the earth according to the embodiment of the present invention includes the first to fifth steps.
The first step is to vertically excavate the ground using a chain-type cutter, and the second step is to continuously construct the wall construction space A having a certain depth from the ground along the ground excavated from the first step will be.
It is preferable to provide a slope measuring device on one side of the chain-
The inclination measuring device installed on one side of the
In the third step, when the wall construction space A having a predetermined depth is installed in the ground from the second step, the stress material 10 (for example, In the fourth step, the
That is, the reinforcing
Next, in the fifth step, in the state where the
That is, according to the present invention, as shown in FIG. 5, in the state where the gap L1 of the stress members is widened in the ground, the
8 and 9 show a second embodiment of the present invention in which a reinforcing member 20 'made of a mesh net or a grid is welded to the outside of the
10 and 11 show a third embodiment of the present invention in which a reinforcing
Fig. 12 shows a case in which a continuous continuous wall of soil cement using the
At this time, when a tilt measuring device (not shown) installed vertically on one side of the chain-
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed exemplary embodiments.
Therefore, it is intended that the present invention cover the modifications and variations of this invention that come within the scope of the appended claims. * * * * * Recently Added Patents
10; Stress material
20,20'20 "; stiffener
30,30 '; Connector
40; Wall
201; Chain type coater
Claims (9)
A second step of successively constructing a wall installation space having a predetermined depth from the ground along the ground excavated from the first process;
A third step of horizontally inserting a stress material into the wall space while maintaining a gap of 1.5 to 2.0 m inside the wall space when the wall space is installed in the ground by the second step;
A fourth step of connecting the stressed materials to the reinforcements while maintaining a gap of 1.5 to 2.0 m in the ground from the third step; And
A fifth step of filling the wall construction space with the gel-like cement mixed with the gypsum in the site in the state where the stress material and the reinforcing material connecting them are formed, to construct a continuous wall; Wherein the continuous cement grout continuous wall construction method is carried out using a chain type cutter.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150080508A KR20160144134A (en) | 2015-06-08 | 2015-06-08 | The Construction Method of Continuous soil cement a Pile Walls |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150080508A KR20160144134A (en) | 2015-06-08 | 2015-06-08 | The Construction Method of Continuous soil cement a Pile Walls |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20160144134A true KR20160144134A (en) | 2016-12-16 |
Family
ID=57735755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150080508A KR20160144134A (en) | 2015-06-08 | 2015-06-08 | The Construction Method of Continuous soil cement a Pile Walls |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20160144134A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200487881Y1 (en) * | 2018-06-15 | 2018-11-16 | 이강호 | Earth Retaining Structure |
CN112482358A (en) * | 2020-11-30 | 2021-03-12 | 中铁十一局集团有限公司 | Diaphragm wall construction method for diaphragm wall penetrating stratum |
-
2015
- 2015-06-08 KR KR1020150080508A patent/KR20160144134A/en not_active Application Discontinuation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200487881Y1 (en) * | 2018-06-15 | 2018-11-16 | 이강호 | Earth Retaining Structure |
CN112482358A (en) * | 2020-11-30 | 2021-03-12 | 中铁十一局集团有限公司 | Diaphragm wall construction method for diaphragm wall penetrating stratum |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1634999B1 (en) | Reinforced concrete column in a ground excavation and method for building said column | |
KR101691139B1 (en) | Construction method using soil retaining wall | |
AU2011202417B2 (en) | A wall formed in soil, the wall including a hollow prefabricated element, and a method of making such a wall | |
KR20110043017A (en) | The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used | |
KR100722665B1 (en) | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same | |
KR20180124795A (en) | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same | |
KR20160144111A (en) | Foundation block for retaining wall and reinforcing method of base ground using it | |
US4453366A (en) | Process of forming a continuous wall in the ground | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR101182704B1 (en) | Construction method of undergroud structure using PHC pile | |
JP2011106229A (en) | Method for constructing temporary pile | |
KR20160144134A (en) | The Construction Method of Continuous soil cement a Pile Walls | |
KR101612522B1 (en) | Construction method for tunneling | |
CN210195766U (en) | Underground structure is built in same direction as digging to hunch lid | |
US20060177279A1 (en) | Reinforcing wall in a deep excavation site | |
JP3829319B2 (en) | Construction method of underground hollow structure and its underground hollow structure | |
KR101462814B1 (en) | Gravity type earth retaining wall constructing method | |
US20220356663A1 (en) | Load Transfer System | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR20190012368A (en) | Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same | |
KR101437882B1 (en) | Tunnel excavating method having various cross sectional shapes | |
KR100654973B1 (en) | Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof | |
KR101612527B1 (en) | Construction method for tunneling | |
CN114482072B (en) | Soft soil close-connection double-foundation-pit combined anchor design method, supporting structure and construction method | |
KR102013783B1 (en) | Steel pipe, underground structure and cast messer shield method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
N231 | Notification of change of applicant | ||
E601 | Decision to refuse application |