KR20130082870A - Construction work management system for which a matrix technique was shown to the risk ranking - Google Patents
Construction work management system for which a matrix technique was shown to the risk ranking Download PDFInfo
- Publication number
- KR20130082870A KR20130082870A KR1020110139030A KR20110139030A KR20130082870A KR 20130082870 A KR20130082870 A KR 20130082870A KR 1020110139030 A KR1020110139030 A KR 1020110139030A KR 20110139030 A KR20110139030 A KR 20110139030A KR 20130082870 A KR20130082870 A KR 20130082870A
- Authority
- KR
- South Korea
- Prior art keywords
- construction
- work
- information
- management
- risk
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 508
- 239000011159 matrix material Substances 0.000 title claims abstract description 173
- 238000000034 method Methods 0.000 title claims abstract description 52
- 230000010365 information processing Effects 0.000 claims abstract description 11
- 238000009430 construction management Methods 0.000 claims description 79
- 238000004091 panning Methods 0.000 claims description 9
- 239000004035 construction material Substances 0.000 claims description 8
- 238000012217 deletion Methods 0.000 claims 1
- 230000037430 deletion Effects 0.000 claims 1
- 239000000284 extract Substances 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 6
- 238000004886 process control Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000015556 catabolic process Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/18—Numerical control [NC], i.e. automatically operating machines, in particular machine tools, e.g. in a manufacturing environment, so as to execute positioning, movement or co-ordinated operations by means of programme data in numerical form
- G05B19/4093—Numerical control [NC], i.e. automatically operating machines, in particular machine tools, e.g. in a manufacturing environment, so as to execute positioning, movement or co-ordinated operations by means of programme data in numerical form characterised by part programming, e.g. entry of geometrical information as taken from a technical drawing, combining this with machining and material information to obtain control information, named part programme, for the NC machine
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0635—Risk analysis of enterprise or organisation activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04N—PICTORIAL COMMUNICATION, e.g. TELEVISION
- H04N1/00—Scanning, transmission or reproduction of documents or the like, e.g. facsimile transmission; Details thereof
- H04N1/0035—User-machine interface; Control console
- H04N1/00405—Output means
- H04N1/00408—Display of information to the user, e.g. menus
- H04N1/00472—Display of information to the user, e.g. menus using a pop-up window
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Educational Administration (AREA)
- Human Computer Interaction (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Signal Processing (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Health & Medical Sciences (AREA)
- Multimedia (AREA)
- Geometry (AREA)
- Manufacturing & Machinery (AREA)
- Automation & Control Theory (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
In the present invention, the work classification system for displaying the entire work items to be performed in the construction work to be progressed, and the space of the work items in which the actual work is carried out among the total work items to be performed in the construction work to be displayed is displayed. The work performed in the space of the work category in which the actual work is performed among all the work items indicated on the work classification system axis, which is the area of the spatial classification system where the facility classification system axis and the facility classification system axis intersect the facility classification system axis. It is easy to identify and manage the construction conditions, construction period, pre and post-relationship of the construction site, and the photographic scale through the matrix technique based on the object for displaying the construction work of the construction. First-line practitioners by guiding and prioritizing the priority management of risks associated with construction work This relates to the construction of a matrix-based construction management device that smoothly guide the risk management priority ranking to respond to the risks arising.
In general, the schedule management of construction works is a technique that classifies and defines construction details for construction contracts into activities to be actually implemented, and manages the defined tasks to achieve a given goal within a given period of time. (Program Evaluation & Review Technique) / CPM (Critical Path Method) method or Bar-Chart method is used for process control chart.
However, if you want to manage your work in ordinary construction work, you need to express it as a two-dimensional process control chart by PERT / CPM or Bar-Chart method for every hundred or thousands of activities. Due to the large number of management charts, it is difficult to grasp the construction conditions, construction period, post-relationship relationship of construction site, and construction scale through the two-dimensional process control chart by PERT / CPM or Bar-Chart technique. Priority management of the risks involved in the construction is not guided, there is a problem that front-line practitioners do not respond smoothly to the risks caused during construction.
In addition, since construction-related information related to activity expressed in the two-dimensional process control chart by PERT / CPM technique or Bar-Chart technique is only one-dimensional work information over time, Construction construction detail code information, construction construction detailed name information, construction worker name information, construction construction detailed schedule information, construction materials information, construction construction detailed specifications information, construction CAD drawing information, construction construction construction cost details information, construction construction It is also difficult to express various construction-related information such as process information.
The present invention is to solve the problems of the prior art, the object of the present invention is the axis of the classification system that displays the entire work item that should be performed in the construction work to proceed, the entire work to be performed in the construction work to proceed Actual among all work items displayed on the facility classification system axis, where the space of the work item in which the actual work is being carried out, and on the classification system axis, which is the area of the spatial coordinates where the work classification axis and the facility classification system axis intersect. Construction conditions or construction period of the construction site through the matrix technique based on the object for displaying construction work for the construction work of the relevant work item performed in the space of the work item in which the work is carried out. In addition, it facilitates the identification and management of post-relationship relations and photography scales of construction work. By providing the priority management of risks accompanying the company, it is to provide a matrix-based construction management device that guides the priority management of risks so that front-line practitioners can respond to the risks incurred during construction.
Another object of the present invention is the work item that is performed in the space of the work item in which the actual work is carried out among all the work items displayed on the work classification system axis, which is the spatial coordinate area where the work classification system axis and the facility classification system axis intersect. Construction construction construction related information, construction order number code information, construction construction detail name information, construction worker name information, construction construction schedule information, construction material information, construction specification information, construction CAD information, construction work It is to provide a matrix-based construction construction management device that guides the priority of risk management, which displays various construction-related information such as construction cost breakdown information and construction process information.
As a technical concept for achieving the present invention, the matrix-based construction work management device, which guides the priority of risk management of the present invention, displays the entire work items to be performed in the construction work to be proceeded on the work classification system axis. The space of the work item in which the actual work is to be performed is displayed in the facility classification system axis among all the work items to be carried out in the construction work to be progressed, and the displayed work classification system axis and facility classification system axis This is the area of the intersecting spatial coordinates, and the construction-related information of the corresponding work item which is performed in the space of the work item in which the actual work is carried out among all the work items displayed on the work classification system axis is displayed. The construction sheet management matrix displayed as an object for displaying construction work is stored. Beam storage means; Output of the construction request management matrix sheet stored in the information storage means, input of the entire work item information to be performed in the construction work to proceed to the work classification system axis of the construction construction management matrix sheet output by the output request Request the input of the space information of the work item in which the actual work is performed among all the work items to be performed in the construction work to be carried out on the facility classification system axis, and the work classification system axis and the facility classification system axis. Information input means for requesting the intersecting performance work display object to input construction work related information of the work item; Information output means for outputting construction-related information including a matrix sheet for construction construction management; According to the output request of the construction construction management matrix sheet requested through the information input means, the construction construction management matrix sheet stored in the information storage means is extracted and output-controlled through the information output means, and the information input means After processing and controlling the input request information of the work classification system axis of the construction sheet management matrix sheet requested through the project, the input request information of the facility classification system axis, and the construction work related information of the corresponding work item of the object for displaying construction work. The main control means for controlling the output through the output information output means; consisting of, the risk associated with the construction work-related information of the corresponding work item that is input to the performing construction work display object of the construction construction management matrix sheet If present, the construction management mat output through the information output means The object for displaying the construction work performed by the Rick Sheet shall indicate priority management according to the risk ranking of the risks associated with the construction work-related information of the work item, and request the viewing of the risk-related contents of the construction work-related information of the work item. Characterized in that the risk item request icon is displayed.
The present invention is the axis of the work classification system in which the entire work items to be carried out in the construction work to proceed, the facility classification is displayed in the space of the work items in which the actual work is carried out of the total work items to be carried out in the construction work to proceed Information related to the construction work of the relevant work item that is carried out in the space of the work item in which the actual work takes place among the total work items displayed on the work classification system axis, which is the spatial coordinate area where the system axis and the work classification system axis and the facility classification system axis intersect. Since it is expressed by matrix technique based on the object for displaying work on the construction work, it is easy to intuitively grasp the construction conditions, construction period, post-relationship relationship of construction work, and photographic scale, and accordingly management is convenient. In addition, the priority management of risks associated with construction works By doing so, front-line practitioners can effectively respond to risks caused during construction work.
In addition, the present invention of the work item that is carried out in the space of the work item in which the actual work is carried out of the total work items displayed on the work classification system axis, which is the spatial coordinate area where the work classification system axis and the facility classification system axis intersect Construction construction related information, construction code number, construction construction detail name information, construction construction worker name information, construction construction schedule information, construction materials information, construction specifications, construction CAD information, construction CAD construction cost Various construction-related information such as breakdown information and construction process process information can be controlled to be displayed in a layer, so that various construction-related information can be recognized.
In addition, the present invention has an effect that can be modified in the form of a pop-up window of the two-dimensional (including three-dimensional) CAD drawings linked to the object for performing construction work display of the matrix sheet for construction construction management.
In addition, the present invention sequentially the work schedule for the detailed work list corresponding to the object for displaying the construction work performed in the area of the spatial coordinates intersecting the work classification system axis and the facility classification system axis as a matrix on the matrix sheet for construction work management It also has a noticeable effect.
In addition, the present invention can be easily moved and read by allowing the movement to the desired performing construction work display object among the many performing construction work display objects displayed in a matrix form on the matrix sheet for construction construction management through zoom-in, zoom out and panning There is also an effect that makes it possible.
1 is a system configuration diagram showing a matrix-based construction construction management device to guide the risk priority management of the present invention,
2 is a view showing a matrix sheet for construction construction management included in a matrix-based construction construction management apparatus is guided the risk priority management of the present invention,
3 is a pop-up window for risk item guidance on a construction sheet management matrix sheet by clicking an icon for requesting a risk item on a matrix sheet for construction construction management included in a matrix-based construction construction management apparatus in which risk priority management of the present invention is guided; A drawing showing this popup display,
FIG. 4 is a construction line performed on objects for performing construction work display displayed on a matrix sheet for construction construction management by an implementation construction leading and trailing guide engine included in a matrix-based construction construction management apparatus in which a risk priority management priority of the present invention is guided. A drawing showing trailing recognition information,
5 is a view showing that the CAD drawing pop-up window is displayed on the construction sheet management matrix sheet pop-up by the construction drawing drawing engine included in the matrix-based construction construction management device to guide the risk priority management of the present invention,
6 to 8 are a plurality of objects stored in the object for displaying construction work performed by the multi-dimensional layer processing engine included in the matrix-based construction management apparatus guides the risk priority management of the present invention; A drawing showing a layer (Layer) showing the overlapping information related to the construction work of the work item,
9 to 11 are zoomed out, zoomed in, or panned in a matrix sheet for construction construction management by an object moving processing engine for performing construction work display included in a matrix-based construction construction management apparatus to which risk priority management of the present invention is guided. Drawing showing implementation,
12 is a matrix-based construction construction management device that guides the risk priority management of the present invention.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a configuration and an operation of an embodiment of the present invention will be described in detail with reference to the accompanying drawings.
1 is a system configuration diagram showing a matrix-based construction construction management apparatus guides the risk priority management of the present invention, Figure 2 is included in the matrix-based construction construction management apparatus guides the risk priority management of the
As shown, the matrix-based construction management apparatus guides the risk priority management of the present invention is largely information storage means 100, information input means 200, information output means 300 and the main control means 400 )
First, the information storage means 100 is displayed so as to be able to input the entire work items to be performed in the construction work to proceed to the work
Here, in the case of the information displayed on the work
In other words, the construction work of the highway No. 40 Chungju-Jecheon
In addition, in the case of the information displayed on the facility
Here, the space of the work item in which the actual work is performed among the entire work items of the construction work to be displayed on the facility
The header node and each of the lower nodes are processed by the matrix X / Y axis node input
In addition, the pop-up menu also includes a “Rename” menu to change the name of the currently selected node. A “Delete Node” menu is also provided to delete the currently selected node. Provides a way to set the properties shown on the screen of each node.
The matrix X / Y axis node input
The detailed configuration of the information storage means 100 for performing such a database function should be performed in the construction
Here, the construction work related information of the work item stored in the construction
In addition, if there is a risk associated with the construction work related information of the work item input to the performing construction
Information input means 200 is an output request of the construction sheet
The information output means 300 is provided with a display as a user interface (UI) for outputting the construction-related information, including the construction sheet
The main control means 400 is a construction construction
First, the main control means 400 is operated by the main control means 400, the input of the work
Here, in the case of the object input
In addition, the performing construction work display object input
In addition, the manager who is a front-line practitioner of the construction work, if there is a risk associated with the construction-related information of the work item can be viewed.
To this end, the main control means 400 is equipped with a
Here, the
As such, the
The risk information guide pop-up
In addition, the manager can repeatedly input a number of construction-related information displayed on the object construction
To this end, the main control means 400 is equipped with a multi-dimensional
FIG. 6 shows details of construction work among construction work related information of the corresponding work item, in which the multi-dimensional
7 is a construction worker among the construction work related information of the corresponding work item that the multi-dimensional
FIG. 8 shows details of construction work among construction work-related information of the corresponding work item in which the multi-dimensional
In addition, the manager corresponds to the object construction
To this end, the main control means 400 is equipped with a leading
Here, the performing construction leading and trailing
In addition, the manager may modify a CAD drawing of two-dimensional (including three-dimensional) linked to the performance construction
To this end, the main control means 400 is equipped with a construction
At this time, the construction
In addition, the manager can easily perform the movement to the desired performing construction
To this end, the main control means 400 is equipped with the object moving
9 is a construction schedule of the construction construction
10 shows the construction work display of the construction construction
11 shows construction performed on one side of the construction sheet
100: information storage means 101: new matrix sheet DB
102: processing matrix sheet DB 103: construction risk DB
104: CAD construction drawing DB
105: icon for requesting risk items
110: matrix sheet for construction construction management 111: work classification system axis
112: facility classification system
113: object for displaying construction work
114: precedence of the construction work recognition information 115: CAD drawing pop-up window
120: pop-up window for risk items
200: information input means
300: information output means 400: main control means
410: matrix X / Y axis node input information processing engine
420: object input information processing engine for performing construction work display
430 modeling engine
440: Leading Information Engine
450: construction drawing drawing engine
460: Multidimensional Layer Processing Engine
470: Object moving processing engine for performing construction work display
Claims (8)
The output request of the construction construction management matrix sheet 110 stored in the information storage means 100, to proceed to the work classification system axis 111 of the construction construction management matrix sheet 110 output by the output request Request input of all work item information to be performed in construction work, and space information of work item in which actual work is performed among all work items to be performed in construction project to proceed to facility classification system axis 112 Information input means for requesting input of the construction work and requesting input of construction work related information of the corresponding work item to the object construction object display object 113 in which the work classification system axis 111 and the facility classification system axis 112 intersect. 200;
Information output means (300) for outputting construction-related information including a matrix sheet (110) for construction construction management;
The construction construction management matrix sheet 110 stored in the information storage means 100 is extracted by the output request of the construction construction management matrix sheet 110 requested through the information input means 100, and then the information is extracted. Output control through the output means 300, input request information of the work classification system axis 111 of the construction sheet management matrix sheet 110 requested through the information input means 100, facility classification system axis 112 Main control means for controlling the input request information and the construction request for the construction work related information of the corresponding work item of the performing construction work display object 113 and outputs it through the output information output means (300) Consisting of (400);
If there is a risk associated with the construction-related information of the corresponding work item input to the performing construction work display object 113 of the construction construction management matrix sheet 110 is output through the information output means 300 Performing the construction management matrix sheet 110 The construction work display object 113 is to display the priority management according to the risk ranking of the risks associated with the construction work related information of the work item, the construction work related to the work item A matrix-based construction construction management device is guided by the risk priority management, characterized in that the icon for requesting risk items requesting the viewing of the risk-related content of the information 105 is displayed.
In the information storage means 100, the work classification system axis 111, in which the entire work item to be performed in the construction work to be displayed is displayed, the actual work of all the work items to be performed in the construction work to proceed It is the area of the spatial coordinates where the facility classification system axis 112 and the work classification system axis 111 and the facility classification system axis 112 intersect the space of the work item to be displayed. An object for performing construction work display in which construction-related information of a corresponding work type ª 수행 performed in a space of a work item in which an actual work is performed among all the work items displayed on the work classification system axis 111 is displayed to be inputable ( A new matrix sheet DB 101 having a new construction construction management matrix sheet 110 formed of an object (113); The construction work related information of the relevant work item is input to the work classification system axis 111, the facility classification system axis 112, and the performing construction work display object 113 of the new construction work management matrix sheet 110, and processed. A processing matrix sheet DB 102 in which the constructed construction sheet management matrix sheet 110 is stored; Of the processed construction sheet management matrix sheet 110 stored in the processing matrix sheet DB 102 as information associated with the construction work related information of the work item stored in the object for performing construction work display (Object), the work item Construction risk DB (103), which contains risk information guide information consisting of the risks involved in the construction work of the company, risk occurrence probability information and risk risk ranking information that guides the possibility of the risks involved in the construction work of the relevant work item. Wow; Of the processed construction sheet management matrix sheet 110 stored in the processing matrix sheet DB 102 is information linked to the object for performing construction work display (Object), the construction of the corresponding work item of the corresponding work item Construction drawing CAD drawing DB 104 is stored; made of;
The construction work related information of the work item stored in the work construction display object 113 among the processed construction work management matrix sheets 110 stored in the processing matrix sheet DB 101 is detailed construction code information, construction work Construction name information, construction worker name information, construction schedule details, construction materials information, construction specifications specification information, construction CAD drawing information, construction construction cost details information, construction construction process information, etc. are stored.
The main control means 400, which is operated by the main control means 400, of the work classification system axis 111 of the matrix sheet 110 for construction work management requested through the information input means 100. Create, modify, or delete all work item names of the construction work to be requested to be entered into the work classification system axis 111 of the matrix sheet 110 for construction work management based on the input request information. Processing and the facility of the construction sheet management matrix sheet 110 based on the input request information of the facility classification system axis 112 of the construction sheet management matrix sheet 110 requested through the information input means 100. The space name of the work item in which the actual work is performed among all the work items of the construction work requested to be inputted to the classification system axis 112 may be generated, modified, or deleted. A matrix X / Y-axis node input information processing engine 410 for processing with; Display the construction work performed by the construction management matrix sheet 110 on the basis of the input request information of the construction work management display object 113 of the construction construction management matrix sheet 110 requested through the information input means 100. Creating, modifying, or constructing construction-related information of the corresponding work item, which is performed in the space of the work item in which the actual work is performed, among all the work items displayed on the work classification system axis 111 requested for input to the object 113. An object input information processing engine (420) for performing construction work display for processing by deletion, etc .; The matrix-based construction construction management device is guided by the risk priority management, characterized in that it comprises a.
The main control means 400 is operated by the main control means 400, by selecting the risk ranking of the risk with reference to the risk content guide information and risk occurrence probability information stored in the construction risk DB (103) And a risk management engine 430 for displaying this as risk risk ranking information and storing it in the construction risk DB 103.
By clicking on the risk item request icon 105 displayed on the construction work display object 113 of the construction work management matrix sheet 110 through the information input means 200 and the construction work related information of the corresponding work item When a request is made to view the risk-related contents of the corresponding work item to be linked, the risk management engine 430 operated by the main control means 400 is the risk content guide information and risk occurrence probability in the construction risk DB 103. After extracting the information and risk risk priority information is inserted into the risk item guide pop-up window 120, and control the pop-up output from the matrix sheet 110 for the construction construction management, the matrix is guided by the risk priority management, characterized in that Based construction management device.
The risk generation probability information stored in the construction risk DB (103) is a matrix-based construction construction management device that guides the risk priority management, characterized in that the percentage is displayed.
The main control means 400 further includes a leading construction leading and trailing guide engine 440 operated by the main control means 400;
By selecting the performing construction work display object 113 of the construction sheet management matrix sheet 110 through the information input means 200 of the construction details of the construction that is the actual work corresponding to the performing construction work display object 113 If you are asked for guidance,
The performing construction leading and trailing guidance engine 440 operated by the main control means 400 performs performing construction leading and trailing recognition information for guiding recognizing the selection order of the performing construction work displaying objects 113 which have been requested. 114 is displayed on the construction work display object 113 for the construction work management matrix sheet 110 to control the output through the information output means 300, the matrix of the risk priority management guided Based construction management device.
The main control means 400 further includes a construction drawing drawing engine 450 operated by the main control means 400;
CAD output of the CAD drawing information of the corresponding work item linked to the execution construction work display object 113 of the construction construction management matrix sheet 110 through the information input means 200 and the CAD output by the output request When requesting processing of drawing information,
Construction drawing drawing engine 450 operated by the main control means 400 is the construction CAD drawing DB (by the request for output of the CAD drawing information of the corresponding work item requested through the information input means 200 ( After extracting the CAD drawing information of the corresponding work item that is requested to be output in the 104, it is controlled to be output through the information output means 300 in the form of the CAD drawing pop-up window 115, and requested through the information input means 200 Process the CAD drawing information of the work item according to the processing request of the CAD drawing information of the work item to control the output to the output through the CAD drawing pop-up window 115 of the information input means (200) Matrix-based construction management device that guides management rankings.
The main control means 400 further includes a multi-dimensional layer processing engine 460 operated by the main control means 400,
The multi-dimensional layer processing engine 460 operated by the main control means 400 is a construction work related information of the corresponding work item stored in the object construction work display object 113 of the construction sheet management matrix sheet 110 Construction construction detailed sequence code information, construction construction detailed name information, construction worker name information, construction construction detailed schedule information, construction materials information, construction construction detailed specification information, construction CAD drawings information and construction construction cost details information, construction construction Control to be displayed in a layer (Layer) to display the process information, such as superimposed, and outputs the construction construction-related information of any one of the desired work item of the construction work related information through the information input means 200 When the display request is made, the information related to the construction work of any one of the requested work items can be activated and displayed. Matrix-based construction management device guides the risk priority management, characterized in that.
The main control means 400 further includes an object movement processing engine 470 for performing construction work display operation operated by the main control means 400,
The object construction processing object display processing engine 470 operated by the main control means 400 is transferred to the object construction object displaying object 113 displayed at the intersection of each axis of the matrix sheet 110 for construction construction management. Zoom out, zoom in and panning is implemented in the matrix management sheet 110 for construction construction for easy movement, and zooming out, zooming in or panning in the matrix sheet 110 for construction construction management through the information input means 200. When requesting any one, the matrix-based construction management device guides the risk priority management, characterized in that any one of the requested zoom out, zoom in or panning is controlled to be implemented in the matrix management sheet 110 for construction work management. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110139030A KR20130082870A (en) | 2011-12-21 | 2011-12-21 | Construction work management system for which a matrix technique was shown to the risk ranking |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110139030A KR20130082870A (en) | 2011-12-21 | 2011-12-21 | Construction work management system for which a matrix technique was shown to the risk ranking |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20130082870A true KR20130082870A (en) | 2013-07-22 |
Family
ID=48994048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020110139030A KR20130082870A (en) | 2011-12-21 | 2011-12-21 | Construction work management system for which a matrix technique was shown to the risk ranking |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20130082870A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2017283867B2 (en) * | 2016-06-15 | 2020-07-02 | Sony Corporation | Information processing device, method, and program |
-
2011
- 2011-12-21 KR KR1020110139030A patent/KR20130082870A/en not_active Application Discontinuation
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2017283867B2 (en) * | 2016-06-15 | 2020-07-02 | Sony Corporation | Information processing device, method, and program |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10248387B2 (en) | Integrated system for software application development | |
US5577188A (en) | Method to provide for virtual screen overlay | |
US7999810B1 (en) | System and method for animated computer visualization of historic events | |
Wang et al. | 4D dynamic management for construction planning and resource utilization | |
US8321475B2 (en) | System and method for contextual data modeling utilizing tags | |
US8994732B2 (en) | Integration of sketch-based interaction and computer data analysis | |
US5630069A (en) | Method and apparatus for creating workflow maps of business processes | |
US6282514B1 (en) | Device and method for project management | |
US20080033777A1 (en) | System and method for visually organizing, prioritizing and updating information | |
EP0586227A2 (en) | Object oriented computer system | |
US20040017400A1 (en) | Method for project planning | |
JPH08249357A (en) | Information processor | |
US20120246565A1 (en) | Graphical user interface for displaying thumbnail images with filtering and editing functions | |
JP7463315B2 (en) | Facility management method, facility management device, facility management program, and recording medium | |
CA2780330A1 (en) | System, method and computer program for creating and manipulating data structures using an interactive graphical interface | |
US20110148918A1 (en) | Information processing apparatus and control method therefor | |
JP2003330733A (en) | Information temporarily disposing place management method, information temporarily storing place management device, image forming apparatus, program and storage medium | |
US20130205275A1 (en) | Integrated development environment and method | |
KR20130082869A (en) | Construction work management system for which a matrix technique related to building information modeling | |
KR101235467B1 (en) | Construction work management system with four dimension | |
JP4148721B2 (en) | Shared terminal for conference support, information processing program, storage medium, information processing method, and conference support system | |
KR20130082870A (en) | Construction work management system for which a matrix technique was shown to the risk ranking | |
KR20130082872A (en) | Construction work management system for which a matrix technique was shown to the price of construction materials | |
KR101204356B1 (en) | Construction work management system for which a matrix technique was used and method thereof | |
US8255416B2 (en) | System and method for contextual data modeling utilizing tags |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |