KR20130082870A - Construction work management system for which a matrix technique was shown to the risk ranking - Google Patents

Construction work management system for which a matrix technique was shown to the risk ranking Download PDF

Info

Publication number
KR20130082870A
KR20130082870A KR1020110139030A KR20110139030A KR20130082870A KR 20130082870 A KR20130082870 A KR 20130082870A KR 1020110139030 A KR1020110139030 A KR 1020110139030A KR 20110139030 A KR20110139030 A KR 20110139030A KR 20130082870 A KR20130082870 A KR 20130082870A
Authority
KR
South Korea
Prior art keywords
construction
work
information
management
risk
Prior art date
Application number
KR1020110139030A
Other languages
Korean (ko)
Inventor
황희석
Original Assignee
(주) 명진소프트컨설팅
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 명진소프트컨설팅 filed Critical (주) 명진소프트컨설팅
Priority to KR1020110139030A priority Critical patent/KR20130082870A/en
Publication of KR20130082870A publication Critical patent/KR20130082870A/en

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/18Numerical control [NC], i.e. automatically operating machines, in particular machine tools, e.g. in a manufacturing environment, so as to execute positioning, movement or co-ordinated operations by means of programme data in numerical form
    • G05B19/4093Numerical control [NC], i.e. automatically operating machines, in particular machine tools, e.g. in a manufacturing environment, so as to execute positioning, movement or co-ordinated operations by means of programme data in numerical form characterised by part programming, e.g. entry of geometrical information as taken from a technical drawing, combining this with machining and material information to obtain control information, named part programme, for the NC machine
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N1/00Scanning, transmission or reproduction of documents or the like, e.g. facsimile transmission; Details thereof
    • H04N1/0035User-machine interface; Control console
    • H04N1/00405Output means
    • H04N1/00408Display of information to the user, e.g. menus
    • H04N1/00472Display of information to the user, e.g. menus using a pop-up window

Abstract

PURPOSE: A matrix based construction work management device is provided to facilitate the understanding and management of the construction condition, construction period, the precedence relation, and the construction progress of the construction work field through a matrix method. The matrix method is based on an object for the performance construction task indication which indicates the construction work related information of the task item, which is performed in the corresponding task item space where the real work is being progressed. CONSTITUTION: A matrix based construction work management device comprises an information storage method (100), an information input method (200), an information output method (300), and a main control method (400). The information storage method indicates the whole task items on a common type classification system shaft (111) to be able to input; indicates the task item space where the real work is being progressed on a facility classification system shaft (112) to be able to input; and stores a matrix sheet (110) for the construction work management indicated as an object (113) for the performance construction task indication. The information input method requests an output of the matrix sheet for the construction work management, the whole task items information, and an input of the task item space information. The information output method is an output user interface for outputting the construction work related information which includes the matrix sheet for the construction work management, and provides a display unit. The main control method extracts the matrix sheet for the construction work management and outputs/controls through the information output method; processes and controls an input request of the construction work related information of the corresponding task item; and outputs/controls through the information output method. If the risk, which is followed by the construction work related information of the corresponding task item inputted in the object for the performance construction task indication of the matrix sheet for the construction work management, exists, the object for the performance construction task indication of the matrix sheet for the construction work management outputted through the information output method indicates the priority management of the risk ranking of the risk followed by the construction work related information of the corresponding task item. [Reference numerals] (101) New matrix sheet DB; (102) Processing matrix sheet DB; (103) Construction work risk DB; (104) Construction work CAD drawing DB; (200) Information input method; (300) Information output method; (410) Engine for inputting matrix X/Y axis node and processing information; (420) Object input information processing engine; (430) Risk management engine; (440) Performance construction guide engine; (450) Engine for making a drawing for the construction work; (460) Engine for processing multi dimensional layers; (470) Engine for transferring and processing an object which is used to display the construction work

Description

Construction work management system for which a matrix technique was shown to the risk ranking}

In the present invention, the work classification system for displaying the entire work items to be performed in the construction work to be progressed, and the space of the work items in which the actual work is carried out among the total work items to be performed in the construction work to be displayed is displayed. The work performed in the space of the work category in which the actual work is performed among all the work items indicated on the work classification system axis, which is the area of the spatial classification system where the facility classification system axis and the facility classification system axis intersect the facility classification system axis. It is easy to identify and manage the construction conditions, construction period, pre and post-relationship of the construction site, and the photographic scale through the matrix technique based on the object for displaying the construction work of the construction. First-line practitioners by guiding and prioritizing the priority management of risks associated with construction work This relates to the construction of a matrix-based construction management device that smoothly guide the risk management priority ranking to respond to the risks arising.

In general, the schedule management of construction works is a technique that classifies and defines construction details for construction contracts into activities to be actually implemented, and manages the defined tasks to achieve a given goal within a given period of time. (Program Evaluation & Review Technique) / CPM (Critical Path Method) method or Bar-Chart method is used for process control chart.

However, if you want to manage your work in ordinary construction work, you need to express it as a two-dimensional process control chart by PERT / CPM or Bar-Chart method for every hundred or thousands of activities. Due to the large number of management charts, it is difficult to grasp the construction conditions, construction period, post-relationship relationship of construction site, and construction scale through the two-dimensional process control chart by PERT / CPM or Bar-Chart technique. Priority management of the risks involved in the construction is not guided, there is a problem that front-line practitioners do not respond smoothly to the risks caused during construction.

In addition, since construction-related information related to activity expressed in the two-dimensional process control chart by PERT / CPM technique or Bar-Chart technique is only one-dimensional work information over time, Construction construction detail code information, construction construction detailed name information, construction worker name information, construction construction detailed schedule information, construction materials information, construction construction detailed specifications information, construction CAD drawing information, construction construction construction cost details information, construction construction It is also difficult to express various construction-related information such as process information.

The present invention is to solve the problems of the prior art, the object of the present invention is the axis of the classification system that displays the entire work item that should be performed in the construction work to proceed, the entire work to be performed in the construction work to proceed Actual among all work items displayed on the facility classification system axis, where the space of the work item in which the actual work is being carried out, and on the classification system axis, which is the area of the spatial coordinates where the work classification axis and the facility classification system axis intersect. Construction conditions or construction period of the construction site through the matrix technique based on the object for displaying construction work for the construction work of the relevant work item performed in the space of the work item in which the work is carried out. In addition, it facilitates the identification and management of post-relationship relations and photography scales of construction work. By providing the priority management of risks accompanying the company, it is to provide a matrix-based construction management device that guides the priority management of risks so that front-line practitioners can respond to the risks incurred during construction.

Another object of the present invention is the work item that is performed in the space of the work item in which the actual work is carried out among all the work items displayed on the work classification system axis, which is the spatial coordinate area where the work classification system axis and the facility classification system axis intersect. Construction construction construction related information, construction order number code information, construction construction detail name information, construction worker name information, construction construction schedule information, construction material information, construction specification information, construction CAD information, construction work It is to provide a matrix-based construction construction management device that guides the priority of risk management, which displays various construction-related information such as construction cost breakdown information and construction process information.

As a technical concept for achieving the present invention, the matrix-based construction work management device, which guides the priority of risk management of the present invention, displays the entire work items to be performed in the construction work to be proceeded on the work classification system axis. The space of the work item in which the actual work is to be performed is displayed in the facility classification system axis among all the work items to be carried out in the construction work to be progressed, and the displayed work classification system axis and facility classification system axis This is the area of the intersecting spatial coordinates, and the construction-related information of the corresponding work item which is performed in the space of the work item in which the actual work is carried out among all the work items displayed on the work classification system axis is displayed. The construction sheet management matrix displayed as an object for displaying construction work is stored. Beam storage means; Output of the construction request management matrix sheet stored in the information storage means, input of the entire work item information to be performed in the construction work to proceed to the work classification system axis of the construction construction management matrix sheet output by the output request Request the input of the space information of the work item in which the actual work is performed among all the work items to be performed in the construction work to be carried out on the facility classification system axis, and the work classification system axis and the facility classification system axis. Information input means for requesting the intersecting performance work display object to input construction work related information of the work item; Information output means for outputting construction-related information including a matrix sheet for construction construction management; According to the output request of the construction construction management matrix sheet requested through the information input means, the construction construction management matrix sheet stored in the information storage means is extracted and output-controlled through the information output means, and the information input means After processing and controlling the input request information of the work classification system axis of the construction sheet management matrix sheet requested through the project, the input request information of the facility classification system axis, and the construction work related information of the corresponding work item of the object for displaying construction work. The main control means for controlling the output through the output information output means; consisting of, the risk associated with the construction work-related information of the corresponding work item that is input to the performing construction work display object of the construction construction management matrix sheet If present, the construction management mat output through the information output means The object for displaying the construction work performed by the Rick Sheet shall indicate priority management according to the risk ranking of the risks associated with the construction work-related information of the work item, and request the viewing of the risk-related contents of the construction work-related information of the work item. Characterized in that the risk item request icon is displayed.

The present invention is the axis of the work classification system in which the entire work items to be carried out in the construction work to proceed, the facility classification is displayed in the space of the work items in which the actual work is carried out of the total work items to be carried out in the construction work to proceed Information related to the construction work of the relevant work item that is carried out in the space of the work item in which the actual work takes place among the total work items displayed on the work classification system axis, which is the spatial coordinate area where the system axis and the work classification system axis and the facility classification system axis intersect. Since it is expressed by matrix technique based on the object for displaying work on the construction work, it is easy to intuitively grasp the construction conditions, construction period, post-relationship relationship of construction work, and photographic scale, and accordingly management is convenient. In addition, the priority management of risks associated with construction works By doing so, front-line practitioners can effectively respond to risks caused during construction work.

In addition, the present invention of the work item that is carried out in the space of the work item in which the actual work is carried out of the total work items displayed on the work classification system axis, which is the spatial coordinate area where the work classification system axis and the facility classification system axis intersect Construction construction related information, construction code number, construction construction detail name information, construction construction worker name information, construction construction schedule information, construction materials information, construction specifications, construction CAD information, construction CAD construction cost Various construction-related information such as breakdown information and construction process process information can be controlled to be displayed in a layer, so that various construction-related information can be recognized.

In addition, the present invention has an effect that can be modified in the form of a pop-up window of the two-dimensional (including three-dimensional) CAD drawings linked to the object for performing construction work display of the matrix sheet for construction construction management.

In addition, the present invention sequentially the work schedule for the detailed work list corresponding to the object for displaying the construction work performed in the area of the spatial coordinates intersecting the work classification system axis and the facility classification system axis as a matrix on the matrix sheet for construction work management It also has a noticeable effect.

In addition, the present invention can be easily moved and read by allowing the movement to the desired performing construction work display object among the many performing construction work display objects displayed in a matrix form on the matrix sheet for construction construction management through zoom-in, zoom out and panning There is also an effect that makes it possible.

1 is a system configuration diagram showing a matrix-based construction construction management device to guide the risk priority management of the present invention,
2 is a view showing a matrix sheet for construction construction management included in a matrix-based construction construction management apparatus is guided the risk priority management of the present invention,
3 is a pop-up window for risk item guidance on a construction sheet management matrix sheet by clicking an icon for requesting a risk item on a matrix sheet for construction construction management included in a matrix-based construction construction management apparatus in which risk priority management of the present invention is guided; A drawing showing this popup display,
FIG. 4 is a construction line performed on objects for performing construction work display displayed on a matrix sheet for construction construction management by an implementation construction leading and trailing guide engine included in a matrix-based construction construction management apparatus in which a risk priority management priority of the present invention is guided. A drawing showing trailing recognition information,
5 is a view showing that the CAD drawing pop-up window is displayed on the construction sheet management matrix sheet pop-up by the construction drawing drawing engine included in the matrix-based construction construction management device to guide the risk priority management of the present invention,
6 to 8 are a plurality of objects stored in the object for displaying construction work performed by the multi-dimensional layer processing engine included in the matrix-based construction management apparatus guides the risk priority management of the present invention; A drawing showing a layer (Layer) showing the overlapping information related to the construction work of the work item,
9 to 11 are zoomed out, zoomed in, or panned in a matrix sheet for construction construction management by an object moving processing engine for performing construction work display included in a matrix-based construction construction management apparatus to which risk priority management of the present invention is guided. Drawing showing implementation,
12 is a matrix-based construction construction management device that guides the risk priority management of the present invention.

DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a configuration and an operation of an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

1 is a system configuration diagram showing a matrix-based construction construction management apparatus guides the risk priority management of the present invention, Figure 2 is included in the matrix-based construction construction management apparatus guides the risk priority management of the present invention 3 is a view illustrating a matrix sheet for construction construction management, and FIG. 3 illustrates a construction process by clicking an icon for requesting a risk item on a matrix sheet for construction construction management included in a matrix-based construction construction management apparatus to which the risk priority management guide of the present invention is guided. Figure 4 is a diagram showing a pop-up window for the risk item guidance pop-up window in the construction management matrix sheet, Figure 4 is performed by the leading construction engine leading information engine included in the matrix-based construction construction management device guides the risk priority management of the present invention For displaying the construction work performed on the matrix sheet for construction management FIG. 5 is a view illustrating that objects are preceded by construction recognition information, and FIG. 5 is for construction work management by a construction drawing drawing engine included in a matrix-based construction work management device to which the risk priority management priority of the present invention is guided. CAD drawing pop-up window is displayed on the matrix sheet, Figures 6 to 8 are for construction work management by the multi-dimensional layer processing engine included in the matrix-based construction work management device to guide the risk priority management of the present invention Figure 9 is a view showing a layer (Layer) to display the overlapping information related to the construction work of a plurality of the corresponding work items stored in the object for performing construction work display of the matrix sheet, Figures 9 to 11 are risk priority management of the present invention Performed work included in a matrix-based construction management device with rankings FIG. 12 is a view illustrating that a zoom out, a zoom in, or a panning is implemented in a matrix sheet for construction construction management by a non-display object moving processing engine, and FIG. 12 is a matrix-based construction construction management apparatus to which the risk priority management priority of the present invention is guided. .

As shown, the matrix-based construction management apparatus guides the risk priority management of the present invention is largely information storage means 100, information input means 200, information output means 300 and the main control means 400 )

First, the information storage means 100 is displayed so as to be able to input the entire work items to be performed in the construction work to proceed to the work classification system axis 111, the actual work of all work items to be performed in the construction work to proceed The space of the work item in which the work proceeds is displayed in the facility classification system axis 112 so as to be inputted, and the area of the spatial coordinates where the displayed work classification system axis 111 and the facility classification system axis 112 intersect. An object for performing construction work display that displays information related to construction work of the relevant work item that is performed in the space of the work item in which the actual work is carried out among all the work items displayed on the work classification system axis. It is a database in which the matrix sheet 110 for construction construction management indicated by 113 is stored.

Here, in the case of the information displayed on the work classification system axis 111 corresponding to the Y axis of the matrix sheet 110 for construction work management, the entire work item name of the construction work to be progressed is classified into a header node and each lower node. Provide the indication.

In other words, the construction work of the highway No. 40 Chungju-Jecheon Section 2 construction project is displayed as a header node, and the lower part of the header node displays the first subnode such as excavation, gang block processing, and ground stopping, which are ongoing construction items. In the lower part of each first lower node, the subdivided works of the construction work corresponding to the first lower node are represented as the second lower node.

In addition, in the case of the information displayed on the facility classification system axis 112 corresponding to the X-axis of the construction sheet management matrix sheet 110, the space of the work item in which the actual work is carried out among all the work items of the construction work to proceed ( space) The name is divided into the header node and each of the lower nodes, and the marking is provided. As shown in the drawing, the construction work of the highway No. 40 Chungju-Jecheon Section 2 construction work is indicated as the header node, and the lower portion of the header node The first subnode of OPEN TBM tunnel, pilot, and quasi-skills material base, which is a space of construction items, is displayed, and the second subnode, which is a detailed space of the ongoing construction item corresponding to the first lower node, is displayed at the bottom of each first subnode. It has a structure represented by.

Here, the space of the work item in which the actual work is performed among the entire work items of the construction work to be displayed on the facility classification system axis 112 may be divided into a construction area or a construction site.

The header node and each of the lower nodes are processed by the matrix X / Y axis node input information processing engine 410 which will be described later. A pop-up menu (not shown) implemented by an administrator operating the information input means 200 described below. It can be displayed through the node creation menu such as "Add Subnode", "Add Before", and "Add After". Here, adding a subnode is a menu in which a node is added from a current node to a lower node, a previous add is a menu added from a current node to a previous neighbor node, and a subsequent addition is a menu in which a subsequent neighbor node of the current node is added. to be.

In addition, the pop-up menu also includes a “Rename” menu to change the name of the currently selected node. A “Delete Node” menu is also provided to delete the currently selected node. Provides a way to set the properties shown on the screen of each node.

The matrix X / Y axis node input information processing engine 410 controls the size of the object crossing the X axis and the Y axis to be automatically adjusted as the manager adds the node to be reflected in the construction sheet management matrix sheet 110. do.

The detailed configuration of the information storage means 100 for performing such a database function should be performed in the construction classification system axis 111, the work classification system axis 111 is displayed to be able to input the entire work items to be performed in the construction work to proceed The space where the facility classification system axis 112 and the work classification system axis 111 and the facility classification system axis 112 intersect each other, in which the space of the work item in which the actual work is carried out is displayed. A construction work in which the construction work related information of the work item that is performed in the space of the work item in which the actual work is performed among all the work items displayed on the work classification system axis 111 as being an area of coordinates is displayed. A new matrix sheet DB 101 in which a new construction construction management matrix sheet 110 composed of a work display object 113 is stored; Matrix sheet for construction construction management processed by inputting corresponding information into the work classification system axis 111 of the construction sheet management matrix sheet 110, the facility classification system shaft 112, and the object construction object displaying object 113. 110 of the work matrix sheet 102 stored therein and the work item stored in the construction work display object of the processed construction work management matrix sheet 110 stored in the work process matrix sheet DB 102. Information related to the construction work, risk content guidance information consisting of the risks involved in the construction work of the work item, risk occurrence probability information to guide the possibility of the risks involved in the construction work of the work item and Among construction risk DB 103 in which risk risk ranking information is stored and processed construction sheet management matrix sheet 110 stored in processing matrix sheet DB 102. Row-construction information that is linked to the business for a display object (Object), consists of construction drawings CAD DB (104) construction-related information which the CAD drawing information of the job categories of the job stored stocks.

Here, the construction work related information of the work item stored in the construction work display object 113 of the processed construction work management matrix sheet 110 stored in the processing matrix sheet DB 101 is detailed construction code number construction information, Construction name details, construction worker name information, construction schedule details, construction materials information, construction specifications specifications information, construction CAD drawing information, construction cost details information, construction process information, etc. are stored.

In addition, if there is a risk associated with the construction work related information of the work item input to the performing construction work display object 113 of the construction sheet management matrix 110 output through the information output means (300). The construction work display object 113 of the construction management matrix sheet 110 for the construction management to be displayed is to display the priority management according to the risk level of the risk accompanying the construction construction-related information of the work item, the construction work of the work item The risk item request icon 105 requesting to view the risk-related contents of the related information is displayed and provided.

Information input means 200 is an output request of the construction sheet management matrix sheet 110 stored in the information storage means 100, the work classification system axis of the construction sheet management matrix sheet 110 output by the output request ( Request input of the total work item information to be performed in the construction work to proceed to 111), and the work item that the actual work is carried out among the total work items to be performed in the construction work to proceed to the facility classification system axis 112. Requests the input of space information of the space, and inputs the construction construction related information of the corresponding work item in the object construction object display 113 for the work classification system axis 111 and the facility classification system axis 112 to intersect. A keyboard, a mouse, a light pen, etc. are provided in combination as an input user interface (UI) for requesting a request.

The information output means 300 is provided with a display as a user interface (UI) for outputting the construction-related information, including the construction sheet management matrix sheet 110.

The main control means 400 is a construction construction management matrix sheet 110 stored in the information storage means 100 by the output request of the construction construction management matrix sheet 110 requested through the information input means 100. After extraction and output control through the information output means 300, input request information of the construction classification system axis 111 of the construction sheet management matrix sheet 110 requested through the information input means 100, facility classification system After processing and controlling the input request information of the shaft 112, the input request of the construction work-related information of the work item of the construction work display object 113 as a control module for output control through the information output means (300) In order to perform these control functions, various engines are operated.

First, the main control means 400 is operated by the main control means 400, the input of the work classification system axis 111 of the matrix sheet 110 for construction construction management requested through the information input means 100 Input to the work classification system axis 111 of the construction sheet management matrix sheet 110 on the basis of the request information by creating, modifying or deleting the entire work item name of the construction work to be requested in the header node and each subnode. Processing and classifying the facilities of the construction management matrix matrix 110 based on the input request information of the facility classification system axis 112 of the construction management matrix matrix 110 requested through the information input means 100. The space name of the work item in which the actual work is performed among all the work items of the construction work requested to be inputted to the system axis 112 is processed by creating, modifying, or deleting the header node and each subnode. Input request information of the matrix construction X / Y axis node input information processing engine 410 and the construction work display object 113 of the construction construction management matrix sheet 110 requested through the information input means 100. Performing the construction sheet management matrix sheet 110 based on the construction Work display space (Space) of the actual work proceeding of the total work items displayed on the work classification system axis 111 requested to be input to the object 113 for display work The object input information processing engine 420 for performing construction work display for processing processing by generating, modifying or deleting the construction construction related information of the corresponding work item to be performed is mounted.

Here, in the case of the object input information processing engine 420 for performing construction work display object, the execution construction work display object 113 which is an area of spatial coordinates where the work classification system axis 111 and the facility classification system axis 112 intersect. ), The construction related information of the relevant work item mentioned above includes construction sequence number code information, construction construction detail name information, construction worker name information, construction construction schedule information, construction material information, construction construction specification information, Controls the output processing of various construction-related information that the manager wants to display, such as construction CAD drawing information, construction construction cost details information, and construction construction process information. That is, it processes not only general text but also an expression that can refer to the values of other cells in the same way as a formula value and a spreadsheet.

In addition, the performing construction work display object input information processing engine 420 processes even when the administrator individually applies the background color, font type, and style of the specific performing construction work display object 113.

In addition, the manager who is a front-line practitioner of the construction work, if there is a risk associated with the construction-related information of the work item can be viewed.

To this end, the main control means 400 is equipped with a risk management engine 430 operated by the main control means 400.

Here, the risk management engine 430 refers to the risk content guide information and the risk occurrence probability information stored in the construction risk DB 103, selects a risk ranking of the risk, and displays it as risk risk ranking information. The module stores in the DB 103.

As such, the risk management engine 430 operated by the main control means 400 is displayed on the object construction object display object 113 of the construction sheet management matrix sheet 110 processed through the information input means 200. When the request is made to view the risk-related contents of construction work-related information of the work item linked to the construction work-related information of the work item by clicking the icon for requesting a risk item, the main control means 400 is requested. The operational risk management engine 430 extracts the risk content guide information, risk occurrence probability information, and risk risk ranking information from the construction risk DB 103 and inserts it into the risk item guide pop-up window 120 and then manages the construction work. The pop-up output to the matrix sheet 110 for control.

The risk information guide pop-up window 120 outputted in a pop-up form on the matrix sheet 110 for management of construction work includes risk information guide information, 'risk occurrence, when the bridge is installed and a risk of collapse of the rock and a gap between the bridge and the rock'. Risk occurrence probability information expressed as '30% probability 'Risk risk priority information displayed as' Risk Risk Priority 1' is displayed so that front-line practitioners can recognize and perform the work carefully.

In addition, the manager can repeatedly input a number of construction-related information displayed on the object construction object display object 113 of the construction construction management matrix sheet 110 for multiple items in one area for each layer, the desired layer of The selection allows you to view the selected layer.

To this end, the main control means 400 is equipped with a multi-dimensional layer processing engine 460 operated by the main control means 400. As such, the multi-dimensional layer processing engine 460 operated by the main control means 400 is Performance of the construction sheet management matrix sheet 110 construction construction work display information related to the construction work of the corresponding work item stored in the object 113 for construction work display information, construction construction detailed name information, construction worker name information, Detailed construction schedule information, construction material information, construction specification specification information, construction CAD drawing information, construction construction cost history information and construction process process information to be displayed in a layer (layer) overlapping display, and control Through the input means 200, the output display of the construction work related information of any one of the corresponding work items of the desired construction work related information When requested, it performs a function of controlling to display only the construction information related to the construction of any one of the requested work items.

FIG. 6 shows details of construction work among construction work related information of the corresponding work item, in which the multi-dimensional layer processing engine 460 is stored in the performance work display object 113a of the construction sheet management matrix sheet 110 at the request of an administrator. This shows that the name information is controlled to be displayed by layering it.

7 is a construction worker among the construction work related information of the corresponding work item that the multi-dimensional layer processing engine 460 is stored in the performance work display object 113b of the construction sheet management matrix sheet 110 at the request of an administrator This shows that the name information is controlled by being processed by layer processing.

FIG. 8 shows details of construction work among construction work-related information of the corresponding work item in which the multi-dimensional layer processing engine 460 is stored in the performance work display object 113c of the construction sheet management matrix sheet 110 at the request of an administrator. This shows that the construction cost information is controlled by displaying the layer processing.

In addition, the manager corresponds to the object construction work display object 113 which is an area of spatial coordinates where the work classification system axis 111 and the facility classification system axis 112 intersect each other on the matrix sheet 110 for construction work management. Work schedules can be recognized for detailed task lists.

To this end, the main control means 400 is equipped with a leading construction guide engine 440, which is operated by the main control means 400, the matrix sheet 110 for construction construction management through the information input means 200 By requesting the guidance of the predecessor relationship of the construction details of the construction, which is the actual work corresponding to the performing construction work display object 113 by selecting the performing construction work display objects 113 of the), by the main control means 400 The operating construction leading and trailing guidance engine 440 guides the construction construction leading and trailing recognition information 114 for recognizing the input sequence of the selected construction construction work display objects 113 to be requested. Performs a function of controlling to display on the construction work display object 113 of the 110 to be output through the information output means (300).

Here, the performing construction leading and trailing recognition information 114 may be provided in consideration of various leading and trailing identification means, such as shown in the image information such as a leader line, or not shown in the figure, but also displayed as image information such as numbers. Can be.

In addition, the manager may modify a CAD drawing of two-dimensional (including three-dimensional) linked to the performance construction work display object 113 of the construction sheet management matrix sheet 110.

To this end, the main control means 400 is equipped with a construction drawing drawing engine 450 which is operated by the main control means 400, the construction sheet management matrix sheet 110 through the information input means 200 When the request for output of the CAD drawing information of the corresponding work item linked to the performing work display object 113 of the work and the processing of the CAD drawing information output by the output request are requested, the main control means 400 operates. The construction drawing drawing engine 450 is a CAD of the corresponding work item output request from the construction CAD drawing DB 104 by the output request of the CAD drawing information of the corresponding work item requested through the information input means 200 After extracting the drawing information and control it to be output through the information output means 300 in the form of a CAD drawing pop-up window 115, to the processing request of the CAD drawing information of the corresponding work item requested through the information input means 200 Accordingly, the CAD drawing information of the corresponding work item is processed to control the output through the CAD drawing pop-up window 115 of the information input means 200.

At this time, the construction drawing drawing engine 450 is provided to be implemented through a vector-based engine for the processing of the CAD drawing.

In addition, the manager can easily perform the movement to the desired performing construction work display object 113 among the many performing construction work display objects 113 displayed in a matrix form on the construction sheet management matrix sheet 110.

To this end, the main control means 400 is equipped with the object moving processing engine 470 for performing construction work display operation operated by the main control means 400, the performing construction work operated by the main control means 400 The display object movement processing engine 470 may be configured in the construction construction management matrix sheet 110 so as to easily move to the performing construction work display object 113 displayed at the intersection of each axis of the construction construction management matrix sheet 110. When zoom out, zoom in, and panning are controlled and any one of zoom out, zoom in, or panning is requested by the construction sheet management matrix sheet 110 through the information input means 200, the requested zoom out, zoom in, or panning is requested. Any one performs a function of controlling to be implemented in the matrix sheet 110 for construction management.

9 is a construction schedule of the construction construction management matrix sheet 110 by holding the construction construction management matrix sheet 110 in a zoomed out state of the construction construction management matrix sheet 110 performed at the request of the manager; It is used at the time of movement between each performance construction work display object 113 with a big difference in gap.

10 shows the construction work display of the construction construction management matrix sheet 110 in a state where the object movement processing engine 470 for construction work display zooms in on the construction construction management matrix sheet 110 at the request of an administrator. The dragon object 113 is used for management one by one.

11 shows construction performed on one side of the construction sheet management matrix sheet 110 in a state in which a construction work display object movement processing engine 470 performs a panning on the construction sheet management matrix sheet 110 at the request of an administrator. It is used when moving from the work display object 113 to the other performing construction work display object 113.

100: information storage means 101: new matrix sheet DB
102: processing matrix sheet DB 103: construction risk DB
104: CAD construction drawing DB
105: icon for requesting risk items
110: matrix sheet for construction construction management 111: work classification system axis
112: facility classification system
113: object for displaying construction work
114: precedence of the construction work recognition information 115: CAD drawing pop-up window
120: pop-up window for risk items
200: information input means
300: information output means 400: main control means
410: matrix X / Y axis node input information processing engine
420: object input information processing engine for performing construction work display
430 modeling engine
440: Leading Information Engine
450: construction drawing drawing engine
460: Multidimensional Layer Processing Engine
470: Object moving processing engine for performing construction work display

Claims (8)

All the work items to be performed in the construction work to be proceeded are displayed in the work classification system axis 111 so as to be inputted, and the space of the work items in which the actual work is carried out among all the work items to be carried out in the construction work to proceed. Space is displayed on the facility classification system axis 112, and the area of the spatial coordinates at which the displayed classification system axis 111 and the facility classification system axis 112 intersect. Construction work management represented by the object (113) for displaying construction work for the construction work of the relevant work item that is carried out in the space of the work item in which the actual work is carried out among all the work items. Information storage means (100) in which the matrix sheet (110) is stored;
The output request of the construction construction management matrix sheet 110 stored in the information storage means 100, to proceed to the work classification system axis 111 of the construction construction management matrix sheet 110 output by the output request Request input of all work item information to be performed in construction work, and space information of work item in which actual work is performed among all work items to be performed in construction project to proceed to facility classification system axis 112 Information input means for requesting input of the construction work and requesting input of construction work related information of the corresponding work item to the object construction object display object 113 in which the work classification system axis 111 and the facility classification system axis 112 intersect. 200;
Information output means (300) for outputting construction-related information including a matrix sheet (110) for construction construction management;
The construction construction management matrix sheet 110 stored in the information storage means 100 is extracted by the output request of the construction construction management matrix sheet 110 requested through the information input means 100, and then the information is extracted. Output control through the output means 300, input request information of the work classification system axis 111 of the construction sheet management matrix sheet 110 requested through the information input means 100, facility classification system axis 112 Main control means for controlling the input request information and the construction request for the construction work related information of the corresponding work item of the performing construction work display object 113 and outputs it through the output information output means (300) Consisting of (400);
If there is a risk associated with the construction-related information of the corresponding work item input to the performing construction work display object 113 of the construction construction management matrix sheet 110 is output through the information output means 300 Performing the construction management matrix sheet 110 The construction work display object 113 is to display the priority management according to the risk ranking of the risks associated with the construction work related information of the work item, the construction work related to the work item A matrix-based construction construction management device is guided by the risk priority management, characterized in that the icon for requesting risk items requesting the viewing of the risk-related content of the information 105 is displayed.
The method of claim 1,
In the information storage means 100, the work classification system axis 111, in which the entire work item to be performed in the construction work to be displayed is displayed, the actual work of all the work items to be performed in the construction work to proceed It is the area of the spatial coordinates where the facility classification system axis 112 and the work classification system axis 111 and the facility classification system axis 112 intersect the space of the work item to be displayed. An object for performing construction work display in which construction-related information of a corresponding work type ª 수행 performed in a space of a work item in which an actual work is performed among all the work items displayed on the work classification system axis 111 is displayed to be inputable ( A new matrix sheet DB 101 having a new construction construction management matrix sheet 110 formed of an object (113); The construction work related information of the relevant work item is input to the work classification system axis 111, the facility classification system axis 112, and the performing construction work display object 113 of the new construction work management matrix sheet 110, and processed. A processing matrix sheet DB 102 in which the constructed construction sheet management matrix sheet 110 is stored; Of the processed construction sheet management matrix sheet 110 stored in the processing matrix sheet DB 102 as information associated with the construction work related information of the work item stored in the object for performing construction work display (Object), the work item Construction risk DB (103), which contains risk information guide information consisting of the risks involved in the construction work of the company, risk occurrence probability information and risk risk ranking information that guides the possibility of the risks involved in the construction work of the relevant work item. Wow; Of the processed construction sheet management matrix sheet 110 stored in the processing matrix sheet DB 102 is information linked to the object for performing construction work display (Object), the construction of the corresponding work item of the corresponding work item Construction drawing CAD drawing DB 104 is stored; made of;
The construction work related information of the work item stored in the work construction display object 113 among the processed construction work management matrix sheets 110 stored in the processing matrix sheet DB 101 is detailed construction code information, construction work Construction name information, construction worker name information, construction schedule details, construction materials information, construction specifications specification information, construction CAD drawing information, construction construction cost details information, construction construction process information, etc. are stored.
The main control means 400, which is operated by the main control means 400, of the work classification system axis 111 of the matrix sheet 110 for construction work management requested through the information input means 100. Create, modify, or delete all work item names of the construction work to be requested to be entered into the work classification system axis 111 of the matrix sheet 110 for construction work management based on the input request information. Processing and the facility of the construction sheet management matrix sheet 110 based on the input request information of the facility classification system axis 112 of the construction sheet management matrix sheet 110 requested through the information input means 100. The space name of the work item in which the actual work is performed among all the work items of the construction work requested to be inputted to the classification system axis 112 may be generated, modified, or deleted. A matrix X / Y-axis node input information processing engine 410 for processing with; Display the construction work performed by the construction management matrix sheet 110 on the basis of the input request information of the construction work management display object 113 of the construction construction management matrix sheet 110 requested through the information input means 100. Creating, modifying, or constructing construction-related information of the corresponding work item, which is performed in the space of the work item in which the actual work is performed, among all the work items displayed on the work classification system axis 111 requested for input to the object 113. An object input information processing engine (420) for performing construction work display for processing by deletion, etc .; The matrix-based construction construction management device is guided by the risk priority management, characterized in that it comprises a.
The method of claim 2,
The main control means 400 is operated by the main control means 400, by selecting the risk ranking of the risk with reference to the risk content guide information and risk occurrence probability information stored in the construction risk DB (103) And a risk management engine 430 for displaying this as risk risk ranking information and storing it in the construction risk DB 103.
By clicking on the risk item request icon 105 displayed on the construction work display object 113 of the construction work management matrix sheet 110 through the information input means 200 and the construction work related information of the corresponding work item When a request is made to view the risk-related contents of the corresponding work item to be linked, the risk management engine 430 operated by the main control means 400 is the risk content guide information and risk occurrence probability in the construction risk DB 103. After extracting the information and risk risk priority information is inserted into the risk item guide pop-up window 120, and control the pop-up output from the matrix sheet 110 for the construction construction management, the matrix is guided by the risk priority management, characterized in that Based construction management device.
The method of claim 3,
The risk generation probability information stored in the construction risk DB (103) is a matrix-based construction construction management device that guides the risk priority management, characterized in that the percentage is displayed.
The method of claim 2,
The main control means 400 further includes a leading construction leading and trailing guide engine 440 operated by the main control means 400;
By selecting the performing construction work display object 113 of the construction sheet management matrix sheet 110 through the information input means 200 of the construction details of the construction that is the actual work corresponding to the performing construction work display object 113 If you are asked for guidance,
The performing construction leading and trailing guidance engine 440 operated by the main control means 400 performs performing construction leading and trailing recognition information for guiding recognizing the selection order of the performing construction work displaying objects 113 which have been requested. 114 is displayed on the construction work display object 113 for the construction work management matrix sheet 110 to control the output through the information output means 300, the matrix of the risk priority management guided Based construction management device.
The method of claim 2,
The main control means 400 further includes a construction drawing drawing engine 450 operated by the main control means 400;
CAD output of the CAD drawing information of the corresponding work item linked to the execution construction work display object 113 of the construction construction management matrix sheet 110 through the information input means 200 and the CAD output by the output request When requesting processing of drawing information,
Construction drawing drawing engine 450 operated by the main control means 400 is the construction CAD drawing DB (by the request for output of the CAD drawing information of the corresponding work item requested through the information input means 200 ( After extracting the CAD drawing information of the corresponding work item that is requested to be output in the 104, it is controlled to be output through the information output means 300 in the form of the CAD drawing pop-up window 115, and requested through the information input means 200 Process the CAD drawing information of the work item according to the processing request of the CAD drawing information of the work item to control the output to the output through the CAD drawing pop-up window 115 of the information input means (200) Matrix-based construction management device that guides management rankings.
The method of claim 2,
The main control means 400 further includes a multi-dimensional layer processing engine 460 operated by the main control means 400,
The multi-dimensional layer processing engine 460 operated by the main control means 400 is a construction work related information of the corresponding work item stored in the object construction work display object 113 of the construction sheet management matrix sheet 110 Construction construction detailed sequence code information, construction construction detailed name information, construction worker name information, construction construction detailed schedule information, construction materials information, construction construction detailed specification information, construction CAD drawings information and construction construction cost details information, construction construction Control to be displayed in a layer (Layer) to display the process information, such as superimposed, and outputs the construction construction-related information of any one of the desired work item of the construction work related information through the information input means 200 When the display request is made, the information related to the construction work of any one of the requested work items can be activated and displayed. Matrix-based construction management device guides the risk priority management, characterized in that.
The method of claim 2,
The main control means 400 further includes an object movement processing engine 470 for performing construction work display operation operated by the main control means 400,
The object construction processing object display processing engine 470 operated by the main control means 400 is transferred to the object construction object displaying object 113 displayed at the intersection of each axis of the matrix sheet 110 for construction construction management. Zoom out, zoom in and panning is implemented in the matrix management sheet 110 for construction construction for easy movement, and zooming out, zooming in or panning in the matrix sheet 110 for construction construction management through the information input means 200. When requesting any one, the matrix-based construction management device guides the risk priority management, characterized in that any one of the requested zoom out, zoom in or panning is controlled to be implemented in the matrix management sheet 110 for construction work management. .
KR1020110139030A 2011-12-21 2011-12-21 Construction work management system for which a matrix technique was shown to the risk ranking KR20130082870A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110139030A KR20130082870A (en) 2011-12-21 2011-12-21 Construction work management system for which a matrix technique was shown to the risk ranking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110139030A KR20130082870A (en) 2011-12-21 2011-12-21 Construction work management system for which a matrix technique was shown to the risk ranking

Publications (1)

Publication Number Publication Date
KR20130082870A true KR20130082870A (en) 2013-07-22

Family

ID=48994048

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110139030A KR20130082870A (en) 2011-12-21 2011-12-21 Construction work management system for which a matrix technique was shown to the risk ranking

Country Status (1)

Country Link
KR (1) KR20130082870A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2017283867B2 (en) * 2016-06-15 2020-07-02 Sony Corporation Information processing device, method, and program

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2017283867B2 (en) * 2016-06-15 2020-07-02 Sony Corporation Information processing device, method, and program

Similar Documents

Publication Publication Date Title
US10248387B2 (en) Integrated system for software application development
US5577188A (en) Method to provide for virtual screen overlay
US7999810B1 (en) System and method for animated computer visualization of historic events
US20210304113A1 (en) Digital processing systems and methods for auto-recognition and aggregation of similar columns in collaborative work systems
CA2780330C (en) System, method and computer program for creating and manipulating data structures using an interactive graphical interface
Wang et al. 4D dynamic management for construction planning and resource utilization
US8321475B2 (en) System and method for contextual data modeling utilizing tags
US8108241B2 (en) System and method for promoting action on visualized changes to information
US8994732B2 (en) Integration of sketch-based interaction and computer data analysis
US5630069A (en) Method and apparatus for creating workflow maps of business processes
EP0586227A2 (en) Object oriented computer system
US20040017400A1 (en) Method for project planning
JPH08249357A (en) Information processor
US20110148918A1 (en) Information processing apparatus and control method therefor
JP7463315B2 (en) Facility management method, facility management device, facility management program, and recording medium
US10467782B2 (en) Interactive hierarchical bar chart
KR20130082869A (en) Construction work management system for which a matrix technique related to building information modeling
KR101235467B1 (en) Construction work management system with four dimension
US20190212904A1 (en) Interactive time range selector
KR20130082870A (en) Construction work management system for which a matrix technique was shown to the risk ranking
KR20130082872A (en) Construction work management system for which a matrix technique was shown to the price of construction materials
KR101204356B1 (en) Construction work management system for which a matrix technique was used and method thereof
US8255416B2 (en) System and method for contextual data modeling utilizing tags
US10672287B2 (en) Method and system for managing assessments
EP2602712A1 (en) Program-producing device and image control system

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application