KR20120135683A - Installation method of support axis over the water - Google Patents

Installation method of support axis over the water Download PDF

Info

Publication number
KR20120135683A
KR20120135683A KR1020110054531A KR20110054531A KR20120135683A KR 20120135683 A KR20120135683 A KR 20120135683A KR 1020110054531 A KR1020110054531 A KR 1020110054531A KR 20110054531 A KR20110054531 A KR 20110054531A KR 20120135683 A KR20120135683 A KR 20120135683A
Authority
KR
South Korea
Prior art keywords
water
installing
shaft
support shaft
steel
Prior art date
Application number
KR1020110054531A
Other languages
Korean (ko)
Other versions
KR101323942B1 (en
Inventor
우도영
Original Assignee
우도영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 우도영 filed Critical 우도영
Priority to KR1020110054531A priority Critical patent/KR101323942B1/en
Priority to JP2014514787A priority patent/JP5932989B2/en
Priority to CN201280027657.6A priority patent/CN103597143B/en
Priority to PCT/KR2012/002020 priority patent/WO2012169723A1/en
Priority to DK12796671.1T priority patent/DK2719834T3/en
Priority to ES12796671.1T priority patent/ES2599481T3/en
Priority to US14/123,750 priority patent/US9074339B2/en
Priority to EP12796671.1A priority patent/EP2719834B1/en
Publication of KR20120135683A publication Critical patent/KR20120135683A/en
Application granted granted Critical
Publication of KR101323942B1 publication Critical patent/KR101323942B1/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24SSOLAR HEAT COLLECTORS; SOLAR HEAT SYSTEMS
    • F24S20/00Solar heat collectors specially adapted for particular uses or environments
    • F24S20/70Waterborne solar heat collector modules
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01LSEMICONDUCTOR DEVICES NOT COVERED BY CLASS H10
    • H01L31/00Semiconductor devices sensitive to infrared radiation, light, electromagnetic radiation of shorter wavelength or corpuscular radiation and specially adapted either for the conversion of the energy of such radiation into electrical energy or for the control of electrical energy by such radiation; Processes or apparatus specially adapted for the manufacture or treatment thereof or of parts thereof; Details thereof
    • H01L31/04Semiconductor devices sensitive to infrared radiation, light, electromagnetic radiation of shorter wavelength or corpuscular radiation and specially adapted either for the conversion of the energy of such radiation into electrical energy or for the control of electrical energy by such radiation; Processes or apparatus specially adapted for the manufacture or treatment thereof or of parts thereof; Details thereof adapted as photovoltaic [PV] conversion devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0065Monopile structures
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/40Solar thermal energy, e.g. solar towers
    • Y02E10/47Mountings or tracking
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Chemical & Material Sciences (AREA)
  • Sustainable Energy (AREA)
  • Sustainable Development (AREA)
  • Power Engineering (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Computer Hardware Design (AREA)
  • Condensed Matter Physics & Semiconductors (AREA)
  • General Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Photovoltaic Devices (AREA)
  • Revetment (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A method for installing a supporting shaft on the water is provided to easily install a photovoltaic generating facility on the water and more firmly support a floating plate. CONSTITUTION: A method for installing a supporting shaft on the water comprises the steps of: installing a plurality of steel pipes(10) to be erected at regular distance on the bottom of a river, a lake or a sea(S110); inserting a drilling rod(20) into the inside of each steel pipe, excavating a bedrock with a bit attached to the end portion of the drilling rod, and fixing the drilling rod on the bedrock(S120); placing and curing concrete or mortar containing accelerating agent inside of each steel pipe(S130); installing a supporting plate which is penetrated and supported by each steel pipe, and integrally fixes the steel pipes on the bottom(S140); settling a shaft tube which accommodates the steel pipes altogether on the upper portion of the supporting plate and installing the shaft tube to be erected outside the surface of the water(S150); and placing and curing concrete or mortar containing accelerating agent inside of the shaft tube(S160). [Reference numerals] (S110) Burying steel pipe; (S120) Excavating rock and fixing boring member to rock; (S130) Pouring and curing quick setting admixture in steel pipe; (S140) Installing support plate; (S150) Installing shaft pipe in upright position; (S160) Pouring and curing quick setting admixture in shaft pipe

Description

수상 지지축 설치방법 {Installation method of support axis over the water}Installation method of support axis over the water}

본 발명은 강이나 호수 그리고 바다 수면에 부상 가능하게 설치되는 태양광 발전 장치를 수상에 견고하게 지지하기 위한 수상 지지축 설치방법에 관한 것이다.
The present invention relates to a water support shaft installation method for firmly supporting a photovoltaic device installed on the surface of a river, a lake and the sea so as to float on the water.

일반적으로 태양광 발전 장치는 빛이 조사(照射)되면 광전 효과에 의해 광 기전력을 발생하는 태양 전지를 이용하여 전기를 생산하는 방식이다. In general, a photovoltaic device is a method of producing electricity by using a solar cell that generates photovoltaic power by the photoelectric effect when light is irradiated.

도 1에 도시된 바와 같이, 수상에 설치되는 태양광 발전장치(100)는 수면 상에 부유하는 플로팅 플레이트(110), 플로팅 플레이트(110) 상에 장착된 태양광 발전 설비(도면에서는 태양 전지 모듈(120)만을 도시함), 플로팅 플레이트(110)를 관통하여 수면에 대하여 수직인 상태로 배치된 지지축(130), 지지축(130)의 상단부에 고정적으로 연결된 제 1 지지 수단(140) 및 지지축(130)의 하단부에 고정적으로 연결된 제 2 지지 수단(150)을 포함한다.As shown in FIG. 1, the photovoltaic device 100 installed in the water phase includes a floating plate 110 floating on the water surface and a photovoltaic facility installed on the floating plate 110 (a solar cell module in the drawing). 120 only), the support shaft 130 disposed in a state perpendicular to the water surface through the floating plate 110, the first support means 140 fixedly connected to the upper end of the support shaft 130 and The second support means 150 is fixedly connected to the lower end of the support shaft 130.

먼저, 상기 플로팅 플레이트(110)는 수면 상에 위치하는 플로팅 플레이트(110)는 부력을 갖는 소재로 제조되며, 소정 위치, 바람직하게는 중앙부에 관통 개구(111)가 형성되어 있다.First, the floating plate 110 is located on the surface of the floating plate 110 is made of a material having a buoyancy, a through opening 111 is formed in a predetermined position, preferably in the center.

한편, 상기 플로팅 플레이트(110)의 상부 면에는 태양 전지 모듈(120), 전력 변환 장치 및 축전지 등과 같은 태양광 발전 설비가 설치되어 있다. 태양광 발전 설비의 구성 및 기능을 일반적인 것이며, 따라서 이에 대한 상세한 설명은 생략한다. On the other hand, the upper surface of the floating plate 110 is provided with photovoltaic power generation equipment such as a solar cell module 120, a power converter and a storage battery. The configuration and function of the solar power plant is general, and thus detailed description thereof will be omitted.

또한, 상기 지지축(130)은 플로팅 플레이트(110)에 형성된 관통 개구(111)를 통과한다. 지지축(130)의 한 종단(하단)은 바닥에 대응하며, 또 다른 종단(상단)은 플로팅 플레이트(110)의 상부로 돌출된 상태이다. In addition, the support shaft 130 passes through the through opening 111 formed in the floating plate 110. One end (lower end) of the support shaft 130 corresponds to the bottom, and the other end (upper end) protrudes to the top of the floating plate 110.

이 지지축(130)은 플로팅 플레이트(110)를 지지할 수 있는 강도를 갖는 소정 직경의 스틸 로드(steel rod)이다.The support shaft 130 is a steel rod of a predetermined diameter having a strength capable of supporting the floating plate 110.

한편, 지지축(130)의 상단부에 연결된 제 1 지지 수단(140)은 다수의 케이블을 포함한다. 도 2는 2개의 제 1 및 제 2 케이블(141 및 142)이 제 1 지지 수단(140)을 구성한 것을 도시한다. On the other hand, the first support means 140 connected to the upper end of the support shaft 130 includes a plurality of cables. 2 shows that two first and second cables 141 and 142 constitute a first support means 140.

제 1 지지 수단(140)의 제 1 케이블(141)은 제 1 종단이 지지축(130)의 상단부에 고정되며, 제 2 종단은 강의 양안 중 한 강변에 설치된 구조체(141-1)에 고정되어 있다. 또한, 제 1 지지 수단(140)의 제 2 케이블(142)은 제 1 종단이 지지축(130)의 상단에 고정되며, 제 2 종단은 강의 양안 중 다른 강변에 설치된 구조체(142-1)에 고정되어 있다. The first cable 141 of the first support means 140 has a first end fixed to the upper end of the support shaft 130, the second end is fixed to the structure (141-1) installed on one river side of both sides of the steel have. In addition, the second cable 142 of the first support means 140 is the first end is fixed to the upper end of the support shaft 130, the second end is to the structure 142-1 installed on the other river side of the both eyes of the steel It is fixed.

여기서, 제 1 지지 수단(140)의 제 1 및 제 2 케이블(141 및 142)은 일직선 상태로 배치되는 것이 바람직하며, 가장 바람직하게는 제 1 및 제 2 케이블(141 및 142)은 강물의 흐름 방향에 수직인 방향으로 배치된다. 또한, 제 1 및 제 2 케이블(141 및 142)은 지지축(130)과 수직을 이루는 것이 바람직하다. Here, the first and second cables 141 and 142 of the first support means 140 is preferably arranged in a straight state, most preferably the first and second cables 141 and 142 are the flow of the river It is arranged in a direction perpendicular to the direction. In addition, the first and second cables 141 and 142 may be perpendicular to the support shaft 130.

제 1 케이블(141)의 제 2 종단은 구조체(141-1)에 설치된 윈치(141-2)에 고정되어 있으며, 따라서 윈치(142-1)의 작동에 따라 제 1 케이블(141)의 장력은 조절될 수 있다. The second end of the first cable 141 is fixed to the winch 141-2 installed in the structure 141-1, and accordingly, the tension of the first cable 141 according to the operation of the winch 142-1 Can be adjusted.

한편, 제 1 케이블(141)에는 케이블의 장력을 감지하는 센서(141-3)가 설치될 수 있으며, 이 센서(141-3)는 감지된 제 1 케이블(141)의 장력 관련 신호를 제어부(도시되지 않음)로 전송한다. 이 신호에 기초하여 제어부는 윈치(141-2)를 작동시켜 제 1 케이블(141)을 감거나 풀게 된다. On the other hand, the first cable 141 may be provided with a sensor (141-3) for detecting the tension of the cable, the sensor (141-3) is a control unit for controlling the tension-related signal of the detected first cable (141) (Not shown). Based on this signal, the controller operates the winch 141-2 to wind or unwind the first cable 141.

여기서, 제 2 케이블(142)의 종단이 고정된 윈치(142-2)가 구조체(142-1)에 설치될 수 있으며, 제 2 케이블(142)의 장력을 감지하는 센서(142-3)도 제 2 케이블(142)에도 설치될 수 있음은 물론이다. Here, the winch 142-2 having the end of the second cable 142 fixed thereto may be installed in the structure 142-1, and the sensor 142-3 for detecting the tension of the second cable 142 may also be installed. Of course, the second cable 142 may also be installed.

아울러, 지지축(130)의 하단부에 연결된 제 2 지지 수단(150)은 다수의 케이블을 포함한다. 도 2는 4개의 제 1, 제 2, 제 3 및 제 4 케이블(151, 152, 153 및 154)이 제 2 지지 수단(150)을 구성한 상태를 도시한다. 여기서, 제 2 지지 수단(150)을 구성하는 제 1 내지 제 4 케이블(151, 152, 153 및 154)은 동일한 구성을 가지며, 따라서 이하에서는 제 1 케이블(151)만을 예를 들어 설명한다. In addition, the second support means 150 connected to the lower end of the support shaft 130 includes a plurality of cables. 2 shows a state in which four first, second, third and fourth cables 151, 152, 153 and 154 constitute the second support means 150. Here, the first to fourth cables 151, 152, 153 and 154 constituting the second support means 150 have the same configuration, and therefore only the first cable 151 will be described below by way of example.

제 2 지지 수단(150)의 제 1 케이블(151)은 제 1 종단이 지지축(130)의 하단부에 고정되며, 제 2 종단은 하나의 강변에 인접한 바닥에 고정될 수 있다. 제 1 케이블(151)의 제 2 종단을 바닥에 고정하기 위하여 다양한 수단이 이용될 수 있다. 예를 들어, 제 1 케이블(151)의 제 2 종단에 앵커(151-1)를 고정한 상태에서 앵커(151-1)를 바닥에 고정함으로써 제 1 케이블(151)의 제 2 종단이 강바닥에 고정될 수 있다. 또 다른 수단으로서는, 바닥에 콘트리트 구조물을 구축한 후, 이 콘크리트 구조물에 제 1 케이블(151)의 제 2 종단을 고정할 수 있다. The first cable 151 of the second support means 150 may have a first end fixed to a lower end of the support shaft 130, and the second end may be fixed to a floor adjacent to one riverside. Various means may be used to secure the second end of the first cable 151 to the floor. For example, the second end of the first cable 151 is fixed to the river bottom by fixing the anchor 151-1 to the floor while the anchor 151-1 is fixed to the second end of the first cable 151. Can be. As another means, after the concrete structure is built on the floor, the second end of the first cable 151 can be fixed to the concrete structure.

한편, 제 2 지지 수단(150)을 구성하는 케이블의 수는 제한되지는 않지만, 플로팅 플레이트(110)를 효과적으로 지지하기 위하여, 즉 플로팅 플레이트(150)의 하류로의 이동 및 어느 한 강변으로의 이동을 억제하기 위하여 4개의 케이블(151, 152, 153 및 154)을 90도의 각도 간격을 둔 상태에서 강물의 흐름 방향에 대하여 45도 각도를 두고 배치하는 것이 바람직하다.On the other hand, the number of cables constituting the second supporting means 150 is not limited, but in order to effectively support the floating plate 110, that is, the movement downstream and the one riverside of the floating plate 150 In order to suppress the four cables (151, 152, 153 and 154) is preferably arranged at an angle of 45 degrees with respect to the flow direction of the river in an angle interval of 90 degrees.

이하, 도면을 참조하여 상술한 수상에 설치되는 태양광 발전장치(100)의 작용에 대해 살펴본다.Hereinafter, with reference to the drawings looks at the operation of the photovoltaic device 100 installed in the above-described water.

종래기술에 따른 수상에 설치되는 태양광 발전장치(100)에서는, 강, 호수 또는 바다의 수위가 변화함에 따라서 플로팅 플레이트(110)가 지지축(130)을 따라 상하로 이동할 수 있으며, 따라서 수위의 변화에 따라 자유롭게 상하 이동할 수 있다. In the photovoltaic device 100 installed in the water according to the prior art, the floating plate 110 can move up and down along the support shaft 130 as the water level of the river, lake or sea changes, so that the water level It can move up and down freely according to the change.

즉, 도 2에서의 점선은 수위가 변함에 따라 변화한 태양광 발전장치(100), 즉 플로팅 플레이트(110) 및 태양광 발전 설비의 위치를 도시한 것으로서, 수위에 따라 플로팅 플레이트(110)가 지지축(130)을 따라 하강한 상태를 도시하고 있다. That is, the dotted line in FIG. 2 shows the positions of the photovoltaic device 100, that is, the floating plate 110 and the photovoltaic power generation facility, which change as the water level is changed. The state which descended along the support shaft 130 is shown.

그런데, 종래의 수상에 설치되는 태양광 발전장치(100)에 있어, 지지축(130)의 한 종단(하단)이 바닥에 대응되어 기립되는바, 지지축(130)의 상단부 및 하단부에 각각 설치된 제 1 지지 수단(140) 및 제 2 지지 수단(150)을 통해 그 기립상태가 유지되는 구조이다.By the way, in the photovoltaic device 100 installed in the conventional water phase, one end (lower end) of the support shaft 130 stands up corresponding to the floor, and is installed at the upper end and the lower end of the support shaft 130, respectively. The standing state is maintained by the first supporting means 140 and the second supporting means 150.

따라서, 제 1 지지 수단(140) 및 제 2 지지 수단(150)의 어느 한 케이블의 장력이 달라질 경우에, 지지축(130)의 기립상태가 기울어져 플로팅 플레이트(110)의 지지상태가 불안정하게 될 우려가 있으며, 또 기구적으로도 복잡하여 시공이 어려운 단점이 있다.
Therefore, when the tension of any one cable of the first support means 140 and the second support means 150 is different, the standing state of the support shaft 130 is inclined so that the support state of the floating plate 110 is unstable. There is a fear that the construction is difficult because of the mechanical complexity.

본 발명은 상기한 문제점을 해결하기 위하여 창출된 것으로서, 수상에 설치되는 태양광 발전장치의 시공이 용이하며, 플로팅 플레이트를 보다 견고하게 지지할 수 있는 수상 지지축 설치방법을 제공하는데 그 목적이 있다.
The present invention has been made in order to solve the above problems, and the object of the present invention is to provide a method of installing a water support shaft that is easy to install a solar power device installed in the water, and can more firmly support the floating plate. .

상기한 목적을 달성하기 위해 본 발명의 일 측면에 따른 수상 지지축 설치방법은, 강, 호수 또는 바다의 바닥에 복수의 스틸관을 일정간격으로 기립되게 설치하는 제1단계; 천공로드를 각 스틸관의 내부로 인입하여 천공로드의 단부에 부착된 비트로 암반을 굴착하며, 상기 천공로드를 암반에 고정 설치하는 제2단계; 및 각 스틸관의 내부에 콘크리트 또는 몰타르가 포함된 급결제를 타설한 후 양생시키는 제3단계;를 포함하여 구성된다.In order to achieve the above object, the water support shaft installation method according to an aspect of the present invention, the first step of installing a plurality of steel tubes to stand at a predetermined interval on the bottom of the river, lake or sea; A second step of drilling the rock with a bit attached to an end of the drill rod by introducing the drill rod into each steel tube, and fixing the drill rod to the rock; And a third step of pouring and curing the fastener including concrete or mortar in each steel tube.

본 발명은, 각 스틸관이 관통 지지되어 상기 스틸관들을 일체로 고정시키는 지지 플레이트를 설치하는 제4단계를 더 포함하는 것을 특징으로 한다.The present invention is characterized in that it further comprises a fourth step of installing a support plate through which each steel tube is penetrated and fixed to the steel tube integrally.

본 발명은, 상기 스틸관들을 함께 수용하는 축관을 상기 지지 플레이트에 기립 설치하는 제5단계를 더 포함하는 것을 특징으로 한다.The present invention further includes a fifth step of standing up and installing the shaft tube accommodating the steel tubes together on the support plate.

본 발명은, 상기 축관의 내부에 콘크리트 또는 몰타르가 포함된 급결제를 타설한 후 양생시키는 제6단계를 더 포함하는 것을 특징으로 한다.The present invention is characterized in that it further comprises a sixth step of curing after pouring the fastener containing concrete or mortar inside the shaft tube.

본 발명은, 상기 축관의 하부를 상기 지지 플레이트의 상면에 체결시키는 제6'단계를 더 포함하는 것을 특징으로 한다.The present invention is characterized in that it further comprises a sixth step of fastening the lower portion of the shaft tube to the upper surface of the support plate.

본 발명은, 상기 지지 플레이트의 상부에 포스트를 기립 및 체결시키는 제5-1단계를 더 포함하는 것을 특징으로 한다.The present invention is characterized in that it further comprises a fifth step of standing and fastening the post on the upper portion of the support plate.

본 발명은, 앙카 플레이트를 포스트의 상부에 안착시키며, 복수의 스틸관을 앙카 플레이트의 상부로 관통시켜 고정시키는 제6-1단계를 더 포함하는 것을 특징으로 한다.
The present invention is characterized in that it further comprises a step 6-1 to seat the anchor plate on the upper part of the post, and to pass through a plurality of steel tubes to the upper part of the anchor plate to fix it.

전술한 바와 같이 본 발명에 따른 수상 지지축 설치방법에 의하면, 지지축(축관 및 포스트)을 안정되게 설치하여 플로팅 플레이트 상에 장착되는 태양광 발전 설비를 보다 안전하게 지지할 수 있다.
As described above, according to the method of installing the water support shaft according to the present invention, the support shaft (shaft tube and post) can be stably installed to more safely support the photovoltaic power generation equipment mounted on the floating plate.

도 1은 종래의 수상(강)에 설치되는 태양광 발전장치를 나타내 보인 평면 도면,
도 2는 도 2의 A-A선 단면도,
도 3은 본 발명의 일 실시예에 따른 수상 지지축 설치 상태를 나타내 보인 도면,
도 4는 본 발명의 일 실시예에 따른 수상 지지축 설치 방법을 나타내 보인 순서도,
도 5는 도 3의 수상 지지축 설치 상태의 변형된 예를 보인 도면,
도 6은 본 발명의 다른 실시예에 따른 수상 지지축 설치 상태를 나타내 보인 도면 및
도 7은 본 발명의 다른 실시예에 따른 수상 지지축 설치 방법을 나타내 보인 순서도이다.
1 is a plan view showing a photovoltaic device installed in a conventional water phase (steel),
2 is a cross-sectional view taken along the line AA of FIG.
Figure 3 is a view showing the installation state of the water support shaft according to an embodiment of the present invention,
Figure 4 is a flow chart showing a water support shaft installation method according to an embodiment of the present invention,
5 is a view showing a modified example of the water support shaft installation state of FIG.
Figure 6 is a view showing the installation state of the water support shaft according to another embodiment of the present invention and
7 is a flow chart showing a method of installing a water support shaft according to another embodiment of the present invention.

이하, 첨부된 도면을 참조로 본 발명의 일 실시예에 따른 수상 지지축 설치방법에 대해 상세하게 살펴본다.Hereinafter, with reference to the accompanying drawings looks at in detail with respect to the water support shaft installation method according to an embodiment of the present invention.

이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니 되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.Prior to this, terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary terms, and the inventor should appropriately interpret the concepts of the terms appropriately It should be interpreted in accordance with the meaning and concept consistent with the technical idea of the present invention based on the principle that it can be defined.

따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들은 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Therefore, the embodiments described in the present specification and the configurations shown in the drawings are only the most preferred embodiments of the present invention, and not all of the technical ideas of the present invention are described. Therefore, It should be understood that various equivalents and modifications may be present.

도 3 및 도 4에 도시된 바와 같이, 본 발명의 일 실시예에 따른 수상 지지축 설치방법은 강, 호수 또는 바다의 바닥(F)에 복수의 스틸관(10)을 일정간격으로 기립되게 설치하는 제1단계(S110)와, 천공로드(20)를 각 스틸관(10)의 내부로 인입하여 천공로드(20)의 단부에 부착된 비트(25)로 암반(R)을 굴착하며, 상기 천공로드(20)를 암반(R)에 고정 설치하는 제2단계(S120) 및 각 스틸관(10)의 내부에 콘크리트 또는 몰타르가 포함된 급결제(C)를 타설한 후 양생시키는 제3단계(S130)를 포함하여 구성된다.As shown in Figure 3 and 4, the water support shaft installation method according to an embodiment of the present invention is installed to stand a plurality of steel pipes 10 at a predetermined interval on the bottom (F) of the river, lake or sea. The first step (S110) and the drill rod 20 is introduced into each of the steel pipe 10 to excavate the rock (R) with a bit 25 attached to the end of the drill rod 20, The second step (S120) of fixing the drilling rod 20 to the rock (R) and the third step of curing after pouring a fastener (C) containing concrete or mortar in each steel pipe (10) It is configured to include (S130).

제1단계(S110)와 제2단계(S120)는 지하수 개발 등에 사용되는 시추기(도시 생략함)를 사용하여 실시되는데, 이 시추기는 바지선(도시 생략함) 등에 올려 시추 위치까지 운반될 수 있다.The first step (S110) and the second step (S120) is carried out using a drilling machine (not shown) used for groundwater development, etc., this drilling can be carried to the drilling position on a barge (not shown).

이와 같은 통상의 시추기는 천공로드, 비트, 비트회전부, 유압모터, 유압제어부 등으로 구성되며, 종래 널리 사용되는 장치이므로 이에 대한 상세한 설명은 생략하기로 한다. Such a conventional drilling machine is composed of a punching rod, a bit, a bit rotating part, a hydraulic motor, a hydraulic control part, and the like, and thus a detailed description thereof will be omitted.

상기한 종래의 시추기를 이용하면, 상기 제1단계(S110)와 제2단계(S120)는 동시에 실시될 수도 있다. 즉, 스틸관(10)을 바닥(F)에 매립함과 동시에 이 스틸관(10)의 내부에 천공로드(20)를 삽입 및 스틸관(10)의 저부로 비트(25)를 노출시켜 암반에 대한 천공을 실시하며, 이 천공로드(20)를 암반 상에 고정시키게 된다.Using the conventional drilling machine described above, the first step S110 and the second step S120 may be simultaneously performed. That is, while the steel tube 10 is embedded in the bottom (F), the drilling rod 20 is inserted into the steel tube 10 and the bit 25 is exposed to the bottom of the steel tube 10 to expose the rock. Perforations are performed, and the perforated rods 20 are fixed on the rock.

제3단계(S130)는 각 스틸관(10)의 내부에 콘크리트 또는 몰타르가 포함된 급결제(C)를 타설 및 양생하여 스틸관(10)을 바닥에 견고히 기립설치하게 된다.The third step (S130) is to place and cure the curing agent (C) containing concrete or mortar in each of the steel pipe (10) so that the steel pipe (10) is firmly installed on the floor.

한편, 본 발명은 각 스틸관(10)이 관통 지지되어 상기 스틸관(10)들을 바닥에 일체로 고정시키는 지지 플레이트(30)를 설치하는 제4단계(S140)(S240)를 더 포함할 수 있다.On the other hand, the present invention may further include a fourth step (S140) (S240) for installing the support plate 30 for each steel tube 10 is penetrated and fixed to the steel tube 10 to be integrally fixed to the floor. have.

따라서, 복수의 스틸관(10)들은 서로 지탱될 수 있어서 보다 견고하게 기립될 수 있다. 또, 지지 플레이트(30)의 상부에는 복수의 스틸관(10)들의 지지상태를 강화하기 위해 천근(I)을 스틸관(10)들의 외주에 감을 수도 있다.Therefore, the plurality of steel pipes 10 can be supported on each other and can stand more firmly. In addition, the upper portion of the support plate 30 may be wound around the outer periphery of the steel tube (I) to strengthen the support state of the plurality of steel tubes (10).

아울러, 본 발명은 상기 스틸관(10)들을 함께 수용하는 축관(40)을 강, 호수 또는 바다의 바닥(F), 바람직하게는 지지 플레이트(30)의 상부에 안착하여 수면(S) 외측으로 기립 설치하는 제5단계(S150) 및 상기 축관(40)의 내부에 콘크리트 또는 몰타르가 포함된 급결제(C)를 타설한 후 양생시키는 제6단계(S160)를 더 포함할 수 있다.In addition, the present invention is seated on the top of the bottom (F), preferably the support plate 30 of the shaft (40) for accommodating the steel pipes (10) to the water surface (S) outside A fifth step (S150) of standing up and the sixth step (S160) for curing after pouring a fastener (C) containing concrete or mortar in the shaft tube 40 may be further included.

여기서, 본 발명은 도 5에 도시된 바와 같이 급결제(C)를 타설한 후 양생시키는 제6단계(S160)를 대체하여 상기 축관(40)의 하부(플렌지(41))를 상기 지지 플레이트(30) 상에 공지된 체결수단(도면부호 생략)을 통해 관통 체결시키는 제6'단계를 포함하여 설치공정을 보다 용이하게 할 수도 있다.Here, the present invention replaces the sixth step (S160) of curing after pouring the fastener (C) as shown in Figure 5 to replace the lower portion (flange 41) of the shaft tube 40 to the support plate ( 30) may include a sixth step of fastening through a known fastening means (not shown) to facilitate the installation process.

이처럼, 본 발명의 일 실시예에 따른 수상 지지축 설치방법에 따르면, 상기 축관(40)은 종래의 지지축(130)에 상당하는 것으로 제1단계(S110) 내지 제6단계(S160)가 실시된 후, 매립된 방식의 축관(40)에 종래의 플로팅 플레이트(110)가 관통 설치될 경우, 플로팅 플레이트(110) 상에 장착되는 태양광 발전 설비를 보다 안전하게 지지할 수 있다.As such, according to the water support shaft installation method according to an embodiment of the present invention, the shaft tube 40 corresponds to the conventional support shaft 130, the first step (S110) to the sixth step (S160) is carried out Then, when the conventional floating plate 110 is installed through the buried shaft tube 40, it is possible to more safely support the photovoltaic power generation equipment mounted on the floating plate 110.

이하, 첨부된 도면을 참조로 본 발명의 다른 실시예에 따른 수상 지지축 설치방법에 대해 상세하게 살펴본다.Hereinafter, with reference to the accompanying drawings looks at in detail with respect to the water support shaft installation method according to another embodiment of the present invention.

도 6 및 도 7에 도시된 바와 같이, 본 발명의 다른 실시예에서 제1단계(S210) 내지 제4단계(S240)는 일 실시예의 제1단계(S110) 내지 제4단계(S140)와 동일 과정되므로 일 실시예를 참조하며, 상세한 설명은 생략하기로 한다.6 and 7, in another embodiment of the present invention, the first step S210 to the fourth step S240 are the same as the first step S110 to the fourth step S140 of the embodiment. Since the process is referred to an embodiment, a detailed description thereof will be omitted.

본 다른 실시예가 전술한 일 실시예와 차이나는 점은 일 실시예의 제5,6단계(S150)(S160)를 대체하여 제5-1단계(S250) 및 제6-1단계(S260)가 실시됨에 있다.The present embodiment differs from the above-described embodiment in that steps 5-1 (S250) and 6-1 (S260) are performed in place of the fifth and sixth steps S150 and S160 of the embodiment. Is in.

즉, 제5-1단계(S250)는 지지 플레이트(30)의 상부에 포스트(50)가 기립 설치되는 구성으로 볼팅, 용접 또는 급결제를 이용한 타설 등 다양한 방법으로 설치될 수 있다.That is, the fifth step (S250) may be installed in various ways such as bolting, welding, or pouring using a fastener as the post 50 is standing up on the support plate 30.

그 예로 도 6에 도시된 바와 같이, 포스트(50)의 하부에 플렌지(51)가 형성되어 포스트(50)가 지지 플레이트(30)의 상부에 공지된 체결수단을 통해 체결이 이루어진다.For example, as shown in FIG. 6, the flange 51 is formed at the lower portion of the post 50 so that the post 50 is fastened through a known fastening means on the upper portion of the support plate 30.

다음으로 상기 제6-1단계(S260)는 앙카 플레이트(60)를 포스트(50)의 상부에 안착시키며, 복수의 스틸관(10)을 상부로 관통시켜 고정시키게 된다. 이때, 앙카 플레이트(60)의 상면에는 종래의 제 2 지지 수단(150)의 각 케이블(151, 152, 153 및 154)이 연결되는 연결고리(65)가 더 설치된다.Next, the sixth step (S260) seats the anchor plate 60 on the upper part of the post 50, and fixes the anchor plate 60 through the plurality of steel pipes 10. At this time, the connecting ring 65 to which each cable 151, 152, 153 and 154 of the conventional second support means 150 is further provided on the upper surface of the anchor plate 60.

이처럼, 본 발명의 다른 실시예에 따른 수상 지지축 설치방법에 따르면, 종래의 지지축(130) 하단부에 고정적으로 연결되는 제 2 지지 수단(150)의 각 케이블(151, 152, 153 및 154)이 이 앙카 플레이트(60)의 연결고리(65)에 연결될 경우, 매립되지 않은 방식의 지지축(130) 하단을 안정되게 지지하여 플로팅 플레이트(110) 상에 장착되는 태양광 발전 설비를 보다 안전하게 지지할 수 있다.As such, according to the water support shaft installation method according to another embodiment of the present invention, each cable 151, 152, 153 and 154 of the second support means 150 is fixedly connected to the lower end of the conventional support shaft 130 When connected to the connecting ring 65 of the anchor plate 60, the lower end of the support shaft 130 of the buried manner is stably supported to more securely support the photovoltaic power generation equipment mounted on the floating plate 110 can do.

이상과 같이, 본 발명은 비록 한정된 실시예와 도면에 의해 설명되었으나 이에 한정되지 않으며, 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해 본 발명의 기술 사상과 아래에 기재될 특허청구범위의 균등범위 내에서 다양한 수정 및 변형 가능함은 물론이다. As described above, although the present invention has been described by way of limited embodiments and drawings, the present invention is not limited thereto, and it should be understood by those of ordinary skill in the art to which the present invention relates, Of course, various modifications and variations can be made within the equivalent range.

Claims (7)

강, 호수 또는 바다의 바닥(F)에 복수의 스틸관(10)을 일정간격으로 기립되게 설치하는 제1단계(S110)(S210);
천공로드(20)를 각 스틸관(10)의 내부로 인입하여 천공로드(20)의 단부에 부착된 비트(25)로 암반(R)을 굴착하며, 상기 천공로드(20)를 암반(R)에 고정 설치하는 제2단계(S120)(S220); 및
각 스틸관(10)의 내부에 콘크리트 또는 몰타르가 포함된 급결제(C)를 타설한 후 양생시키는 제3단계(S130)(S230);
를 포함하는 수상 지지축 설치방법.
First step (S110) (S210) to install a plurality of steel pipes (10) to stand at a predetermined interval on the bottom (F) of the river, lake or sea;
The drill rod 20 is introduced into each steel tube 10 to excavate a rock R with a bit 25 attached to an end of the drill rod 20, and the drill rod 20 is rock R. A second step (S120) (S220) fixedly installed; And
A third step (S130) (S230) of curing after pouring a fastener (C) containing concrete or mortar in each steel tube (10);
Water support shaft installation method comprising a.
제 1항에 있어서,
각 스틸관(10)이 관통 지지되어 상기 스틸관(10)들을 일체로 고정시키는 지지 플레이트(30)를 설치하는 제4단계(S140)(S240)를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
The method of claim 1,
The water support shaft is further provided with a fourth step (S140) (S240) for installing the support plate 30 for each steel tube 10 is supported through and fixed to the steel tube (10) integrally Way.
제 2항에 있어서,
상기 스틸관(10)들을 함께 수용하는 축관(40)을 상기 지지 플레이트(30)에 기립 설치하는 제5단계(S150)를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
The method of claim 2,
The water support shaft installation method characterized in that it further comprises a fifth step (S150) of standing on the support plate (30) to the shaft tube (40) for accommodating the steel tube (10).
제 3에 있어서,
상기 축관(40)의 내부에 콘크리트 또는 몰타르가 포함된 급결제(C)를 타설한 후 양생시키는 제6단계(S160)를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
In the third aspect,
The water support shaft installation method characterized in that it further comprises a sixth step (S160) to pour after curing the casting agent (C) containing concrete or mortar inside the shaft tube (40).
제 3항에 있어서,
상기 축관(40)의 하부를 상기 지지 플레이트(30)의 상면에 체결시키는 제6'단계를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
The method of claim 3,
And a sixth step of fastening the lower portion of the shaft tube (40) to the upper surface of the support plate (30).
제 2항에 있어서,
상기 지지 플레이트(30)의 상부에 포스트(50)를 기립 및 체결시키는 제5-1단계(S250)를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
The method of claim 2,
Water support shaft installation method characterized in that it further comprises a fifth step (S250) for standing and fastening the post (50) on the upper portion of the support plate (30).
제 6항에 있어서,
앙카 플레이트(60)를 포스트(50)의 상부에 안착시키며, 복수의 스틸관(10)을 앙카 플레이트(60)의 상부로 관통시켜 고정시키는 제6-1단계(S260)를 더 포함하는 것을 특징으로 하는 수상 지지축 설치방법.
The method according to claim 6,
The anchor plate 60 is seated on the upper portion of the post 50, and further comprises a sixth step (S260) for fixing the plurality of steel pipes 10 through the upper portion of the anchor plate 60. Water support shaft installation method.
KR1020110054531A 2011-06-07 2011-06-07 Installation method of support axis over the water KR101323942B1 (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
KR1020110054531A KR101323942B1 (en) 2011-06-07 2011-06-07 Installation method of support axis over the water
JP2014514787A JP5932989B2 (en) 2011-06-07 2012-03-21 Installation method of water support
CN201280027657.6A CN103597143B (en) 2011-06-07 2012-03-21 The method of underwater support column is installed
PCT/KR2012/002020 WO2012169723A1 (en) 2011-06-07 2012-03-21 Method for installing an underwater support column
DK12796671.1T DK2719834T3 (en) 2011-06-07 2012-03-21 Method for installing an underwater carrying pillar
ES12796671.1T ES2599481T3 (en) 2011-06-07 2012-03-21 Method to install an underwater support column
US14/123,750 US9074339B2 (en) 2011-06-07 2012-03-21 Method for installing an underwater support column
EP12796671.1A EP2719834B1 (en) 2011-06-07 2012-03-21 Method for installing an underwater support column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110054531A KR101323942B1 (en) 2011-06-07 2011-06-07 Installation method of support axis over the water

Publications (2)

Publication Number Publication Date
KR20120135683A true KR20120135683A (en) 2012-12-17
KR101323942B1 KR101323942B1 (en) 2013-10-31

Family

ID=47296256

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110054531A KR101323942B1 (en) 2011-06-07 2011-06-07 Installation method of support axis over the water

Country Status (8)

Country Link
US (1) US9074339B2 (en)
EP (1) EP2719834B1 (en)
JP (1) JP5932989B2 (en)
KR (1) KR101323942B1 (en)
CN (1) CN103597143B (en)
DK (1) DK2719834T3 (en)
ES (1) ES2599481T3 (en)
WO (1) WO2012169723A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982489A (en) * 2021-02-05 2021-06-18 深圳深安建筑工程有限公司 Underwater steel structure column construction positioning device
KR20220037117A (en) * 2020-09-17 2022-03-24 유장욱 Offshore wind power generator
EP4174768A1 (en) 2021-10-29 2023-05-03 Huvitz Co., Ltd. Method for differentiating retinal layers in oct image
EP4174767A1 (en) 2021-10-29 2023-05-03 Huvitz Co., Ltd. Method for measuring retinal layer in oct image

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2821565A1 (en) * 2012-02-28 2015-01-07 MS Enertech S.L. Connection between a wind turbine tower and its foundation
US9631779B2 (en) * 2013-08-15 2017-04-25 Star Headlight & Lantern Co., Inc. Optical system utilizing LED illumination for a light bar, and light bar having same
DE102015209661A1 (en) * 2015-05-27 2016-12-01 Rwe Innogy Gmbh Method for founding a tower construction as well as onshore tower construction
KR102306839B1 (en) * 2019-02-13 2021-09-30 우도영 Installation method of support axis over the water
CN112361178B (en) * 2020-11-25 2021-08-03 武汉大学 Model measurement system of irregular river channel

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3255591A (en) * 1961-08-23 1966-06-14 Thornley Beatrice Horizontally stabilized foundation
JPS5425727B2 (en) * 1974-05-27 1979-08-30
DE2747937C2 (en) * 1977-10-26 1985-11-14 Winfried 3063 Obernkirchen Rosenstock Method for driving sheet piles into a rock substrate
JPS5771928A (en) * 1980-10-22 1982-05-06 Nippon Steel Corp Center prestress type pile foundation
US4480944A (en) * 1981-04-30 1984-11-06 Raymond International Builders, Inc. Offshore drilling of large diameter holes in rock formations
US4558744A (en) * 1982-09-14 1985-12-17 Canocean Resources Ltd. Subsea caisson and method of installing same
JP3020742B2 (en) * 1992-07-28 2000-03-15 古河機械金属株式会社 Rod holding mechanism for submarine drilling equipment
JPH06146305A (en) * 1992-11-11 1994-05-27 Nippon Steel Corp Underwater foundation and installation method thereof
JPH0656149U (en) * 1993-01-08 1994-08-05 株式会社大林組 Underwater anchor structure
JP2000073349A (en) * 1998-09-02 2000-03-07 Nippon Steel Corp Jacket with rotary press-in steel pipe pile and its execution method
JP3639900B2 (en) * 2000-11-17 2005-04-20 ヤマモトロックマシン株式会社 Reinforcing method for reinforcing bars, etc. and drilling bit used for it
KR20050075929A (en) * 2004-01-19 2005-07-26 이오진 A improvement block for soft ground, and improvement structure for soft ground, and improvement method for soft ground
US7390144B2 (en) * 2006-02-02 2008-06-24 Nova Group Inc. Pre-cast/pre-stressed concrete and steel pile and method for installation
CN200958209Y (en) * 2006-03-10 2007-10-10 刘晓东 Base construction equipment at deep-water torrent
JP2007239420A (en) * 2006-03-13 2007-09-20 Kumagai Gumi Co Ltd Structure of foundation for preventing floating of structure, its execution method and structure of pile used for its foundation or execution method
KR101018289B1 (en) * 2008-07-16 2011-03-04 한국해양연구원 Pile-deck type Light Beacon Structure with Prestressed Anchor
JP2010074130A (en) * 2008-08-18 2010-04-02 Toshiaki Ota Power generator by solar power generation
CN201649118U (en) * 2010-04-07 2010-11-24 中国水电顾问集团华东勘测设计研究院 Foundation structure of jacket-type offshore wind turbine
CN201746849U (en) * 2010-06-24 2011-02-16 上海勘测设计研究院 Basic structure of offshore wind-power-station fan

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220037117A (en) * 2020-09-17 2022-03-24 유장욱 Offshore wind power generator
CN112982489A (en) * 2021-02-05 2021-06-18 深圳深安建筑工程有限公司 Underwater steel structure column construction positioning device
CN112982489B (en) * 2021-02-05 2022-04-22 深圳深安建筑工程有限公司 Underwater steel structure column construction positioning device
EP4174768A1 (en) 2021-10-29 2023-05-03 Huvitz Co., Ltd. Method for differentiating retinal layers in oct image
EP4174767A1 (en) 2021-10-29 2023-05-03 Huvitz Co., Ltd. Method for measuring retinal layer in oct image

Also Published As

Publication number Publication date
US20140126964A1 (en) 2014-05-08
CN103597143A (en) 2014-02-19
JP5932989B2 (en) 2016-06-08
JP2014518971A (en) 2014-08-07
EP2719834A4 (en) 2015-07-22
ES2599481T3 (en) 2017-02-01
EP2719834B1 (en) 2016-09-21
CN103597143B (en) 2016-02-03
EP2719834A1 (en) 2014-04-16
DK2719834T3 (en) 2016-11-21
WO2012169723A1 (en) 2012-12-13
KR101323942B1 (en) 2013-10-31
US9074339B2 (en) 2015-07-07

Similar Documents

Publication Publication Date Title
KR101323942B1 (en) Installation method of support axis over the water
PH12017500191A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
JP2008111406A (en) Offshore wind power generation facility and its construction method
KR101459649B1 (en) Double layered floating-gravity structure for installing offshore substructure, and method for constructing offshore substructure using the same
CN201785765U (en) Secondary leveling structure for multi-pile base of marine wind power generator set
CN105240221A (en) Semi-submersible raft type overwater wind power generation equipment turning along with wind
CN105926628A (en) Device for underwater pile foundation construction platform convertible in floating and fixing
CN204886790U (en) Surface of water floats power station
CN101769225B (en) Lift-type double floating body tidal power generating platform
CN101837929B (en) Operation method for lifting fan for barge in shoal area
KR20110092257A (en) Barge device for installation of tidal power structure
JP2017203305A (en) Foundation of offshore facility, offshore facility, and foundation construction method of offshore facility
CN114585809B (en) Method for setting offshore wind power generation floating body
JP2007160965A (en) Floating body structure
KR101573064B1 (en) Jig for constructing pile of green energy generating plant on the sea and method for constructing pile on the sea using this same
CN106381881A (en) Gravity-type single-pile foundation
JP2005351201A (en) Tidal power generation facility
KR101636960B1 (en) Offshore multi-piled concrete foundation using transition pieces and the construction method therefor
KR20140051531A (en) Structure of offshore structure, manufacturing and constructing method thereof
JP2001248535A (en) Wind force power generation device
JP7118473B1 (en) Method for constructing bottom-mounted offshore mounting system, bottom-mounted offshore mounting system, and offshore wind power generator
CN105443311A (en) Tidal current energy generating device fixed to water bottom
CN205804363U (en) A kind of floating, fixing convertible pile foundation in water construction platform device
CN105401564A (en) Construction method for fixing tidal current energy power generation device to water bottom and tidal current energy power generation device
CN204226097U (en) Be fixed on water-bed tidal current energy generating equipment

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161020

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20171019

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee