KR20120019175A - Method for installing flare tower - Google Patents

Method for installing flare tower Download PDF

Info

Publication number
KR20120019175A
KR20120019175A KR1020100082411A KR20100082411A KR20120019175A KR 20120019175 A KR20120019175 A KR 20120019175A KR 1020100082411 A KR1020100082411 A KR 1020100082411A KR 20100082411 A KR20100082411 A KR 20100082411A KR 20120019175 A KR20120019175 A KR 20120019175A
Authority
KR
South Korea
Prior art keywords
flare tower
flare
tower
crane
booms
Prior art date
Application number
KR1020100082411A
Other languages
Korean (ko)
Other versions
KR101213756B1 (en
Inventor
정재호
조동현
한일국
정이용
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR1020100082411A priority Critical patent/KR101213756B1/en
Publication of KR20120019175A publication Critical patent/KR20120019175A/en
Application granted granted Critical
Publication of KR101213756B1 publication Critical patent/KR101213756B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
    • B66C1/34Crane hooks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • E02B2017/0043Placing the offshore structure on a pre-installed foundation structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

PURPOSE: A flare tower installation method is provided to minimize additional facilities and costs by integrating processes for erecting and mounting a flare tower. CONSTITUTION: A flare tower installation method is as follows. A pair of booms(11) provided on a first sea crane(10) are located in parallel above a flare tower laid on a carrier so that the flare tower is located between the booms. The hooks of the booms are connected to both sides of the flare tower and the hook of a second sea crane(20) is connected to the flare tower. The flare tower is lifted off the carrier using the first and second sea cranes, and then erected between the booms and mounted on a marine structure at the same time.

Description

플레어 타워의 설치 방법{METHOD FOR INSTALLING FLARE TOWER}Installation method of flare tower {METHOD FOR INSTALLING FLARE TOWER}

본 발명은 플레어 타워의 직립과 탑재를 단일화하여 연속적으로 수행할 수 있도록 함으로써 추가적인 설비 운용과 비용을 최소화하도록 구성된 플레어 타워의 설치 방법에 관한 것이다.The present invention relates to a method for installing a flare tower configured to minimize the additional equipment operation and costs by enabling the unified and mounted flare tower to be carried out unified continuously.

일반적으로, 원유나 LNG(Liquefied Natural Gas) 등을 저장하는 선박에는 원유나 가스를 소각시키기 위한 플레어 타워(flare tower)가 마련된다.In general, a vessel storing crude oil or LNG (Liquefied Natural Gas) is provided with a flare tower (flare tower) for incineration of crude oil or gas.

이러한 플레어 타워는 크게 직립형과 경사형으로 구분되는데, 직립형의 플레어 타워는 육상에서 대형 크롤러 크레인(crawler crane)을 이용하여 직립시킨 다음, 고정 작업을 거친 후, 해상크레인을 이용하여 다시 본 탑재하는 방법이 사용된다. These flare towers are largely divided into upright and inclined types. The upright flare tower is erected by a large crawler crane on land, and then fixed and then mounted again using a marine crane. This is used.

이와 같은 종래의 플레어 타워 설치 방법은 플레어 타워의 직립을 위한 육상 작업장의 확보 및 고정 작업이 필요하고, 큰 중량을 가진 리프팅 프레임(lifting frame)과 리깅(rigging) 등을 필요로 하며, 크레인의 사용 횟수 및 작업 일수가 많이 소요되기 때문에 비용 증가를 초래하는 원인이 되었다.Such a conventional flare tower installation method requires the securing and fixing of the on-shore workshop for the upright flare tower, requires a heavy lifting frame (rigging) and rigging (rigging), and the use of a crane The high frequency and number of working days contributed to the increased cost.

특히, 종래의 플레어 타워 설치 방법은 제작 작업과 설치 작업이 별개의 프로세스로 이원화되어 시행됨에 따라 추가적인 비용, 예를 들면 전용 작업장 및 직립을 위한 크레인을 필요로 하고, 육상 직립 후 고정 작업 등의 추가 작업이 발생하게 되어 설비 운용비용 및 기간, 그리고 추가적인 작업 시수의 투입이 불가피하며, 육상에서의 작업시 고소 작업이 동반됨으로써 작업성 및 안전성 확보가 어렵고, 작업기간이 길어지는 문제점을 가지고 있었다. In particular, the conventional flare tower installation method requires an additional cost, for example, a dedicated workshop and a crane for upright, as the manufacturing work and the installation work are carried out in a separate process, additionally, such as fixed work after the land upright. As the operation occurred, the operation cost and duration of the facility and the addition of additional working hours were inevitable, and it was difficult to secure workability and safety due to the accompanying height work when working on the land, and the working period was long.

또한, 종래의 플레어 타워 설치에 사용되는 리프팅 프레임은 사용을 마치면 플레어 타워로부터 해체됨으로써 이로 인한 많은 노력과 시간이 소요되며, 고중량화로 인해 비용 증가를 유발하는 문제점을 가지고 있었다.In addition, the lifting frame used in the conventional flare tower installation is dismantled from the flare tower when finished using it takes a lot of effort and time due to this, there was a problem causing an increase in cost due to high weight.

본 발명은 상기한 바와 같은 종래의 문제점을 해결하기 위한 것으로서, 플레어 타워의 직립과 탑재를 위한 설치 작업을 연속적으로 수행하도록 단일화시킴으로써 추가적인 설비 운용 및 비용을 최소화하고, 작업에 소요되는 시간을 줄여서 생산성을 향상시키도록 한다.The present invention is to solve the conventional problems as described above, by minimizing the additional equipment operation and cost, by reducing the time required to work by uniting the installation work for the upright and mounting of the flare tower continuously To improve it.

또한, 플레어 타워의 설치를 위해 사용되는 리프팅 프레임의 경량화를 가능하도록 하여 비용 발생을 감소시키도록 한다.In addition, it is possible to lighten the lifting frame used for the installation of the flare tower to reduce the cost incurred.

본 발명의 일 측면에 따른 플레어 타워의 설치 방법은, 플레어 타워를 설치하는 방법에 있어서, 제 1 해상크레인에 마련된 한 쌍의 붐이 운반선에 눕혀진 플레어 타워의 상측에 나란하도록 위치하되, 상기 붐 사이에 상기 플레어 타워가 위치하도록 하는 정렬단계; 상기 붐 각각의 후크를 상기 플레어 타워의 양측에 각각 연결하고, 제 2 해상크레인의 후크를 상기 플레어 타워에 연결하는 연결단계; 상기 제 1 및 제 2 해상크레인에 의해 상기 플레어 타워를 상기 운반선으로부터 인양하여 상기 붐 사이를 통해서 수직으로 세우는 직립단계; 및 상기 직립단계에 의해 세워진 상기 플레어 타워를 해상 구조물에 탑재하는 탑재단계를 포함하는 것을 특징으로 한다.In the method for installing a flare tower according to an aspect of the present invention, in the method for installing a flare tower, a pair of booms provided in the first offshore crane is located so as to be parallel to the upper side of the flare tower lying on the carrier ship, the boom An alignment step of positioning the flare tower in between; Connecting the hooks of each of the booms to both sides of the flare tower, and connecting the hooks of the second marine crane to the flare towers; An upright step of lifting the flare tower from the carrier by the first and second marine cranes and standing vertically between the booms; And a mounting step of mounting the flare tower erected by the upright step on an offshore structure.

또한, 상기 연결단계는 상기 붐 각각의 후크를 상기 플레어 타워에서 무게 중심의 상측에 연결하고, 상기 제 2 해상크레인의 후크를 상기 플레어 타워에서 무게 중심의 하측에 연결하는 것을 특징으로 한다.In addition, the connecting step is characterized in that the hook of each of the boom is connected to the upper side of the center of gravity in the flare tower, and the hook of the second marine crane is characterized in that connected to the lower side of the center of gravity in the flare tower.

또한, 상기 연결단계는 상기 플레어 타워에 수평되게 양측으로 연장되는 지지바를 가지고, 상기 지지바 각각의 끝단에 상기 붐의 후크가 체결되는 체결부가 마련되는 리프팅 프레임을 이용하여 상기 플레어 타워가 상기 제 1 해상크레인에 연결되는 것을 특징으로 한다.In addition, the connecting step has a support bar extending horizontally on both sides of the flare tower, the flare tower is the first by using a lifting frame provided with a fastening portion for fastening the hook of the boom at each end of the support bar It is characterized in that it is connected to the marine crane.

또한, 상기 리프팅 프레임은 상기 지지바가 상기 플레어 타워의 세로부재와 가로부재에 다수의 보강바에 의해 연결됨으로써 상기 플레어 타워에 일체를 이루도록 고정되는 것을 특징으로 한다.In addition, the lifting frame is characterized in that the support bar is fixed to be integral to the flare tower by being connected to the vertical member and the horizontal member of the flare tower by a plurality of reinforcing bars.

또한, 상기 직립단계는 상기 제 1 및 제 2 해상크레인이 상기 플레어 타워를 수평을 유지한 상태로 정해진 높이까지 인양하는 단계; 및 상기 제 2 해상크레인이 상기 플레어 타워를 기울어지게 가이드하면서 상기 제 1 해상크레인이 상기 붐 사이에 상기 플레어 타워를 인양하여 직립되도록 하는 단계를 포함하는 것을 특징으로 한다.In addition, the upright step may include the first and second marine cranes lifting up to a predetermined height while keeping the flare tower level; And allowing the first marine crane to lift the flare tower upright between the booms while guiding the second marine crane inclined to the flare tower.

본 발명에 따르면, 플레어 타워의 제작과 직립 및 탑재를 단일화하여 연속적으로 수행할 수 있도록 함으로써 추가적인 설비 운용과 비용을 최소화할 수 있고, 해상크레인의 소요 시간을 단축시킴과 아울러 육상 작업장의 회전을 통한 생산성을 향상시킬 수 있으며, 리프팅 프레임의 경량화를 가능하도록 하여 설치 작업의 용이성과 경제성을 높일 수 있다.According to the present invention, it is possible to minimize the additional equipment operation and cost, and to reduce the time required for offshore cranes, as well as to be able to continuously perform the production, upright and mounting of the flare tower unified, and through the rotation of the land workshop Productivity can be improved, and the lifting frame can be lightened, thereby increasing the ease of installation and economy.

도 1 내지 도 6은 본 발명에 따른 플레어 타워의 설치 방법을 순서적으로 설명하기 위한 도면.
도 7은 본 발명에 따른 플레어 타워의 설치 방법에서 제 1 해상크레인이 플레어 타워를 연결하는 모습을 도시한 정면도.
도 8은 본 발명에 따른 플레어 타워의 설치 방법에 이용되는 리프팅 프레임을 도시한 사시도.
1 to 6 are views for sequentially explaining the installation method of the flare tower according to the present invention.
7 is a front view showing a state in which the first marine crane is connected to the flare tower in the installation method of the flare tower according to the present invention.
8 is a perspective view showing a lifting frame used in the installation method of the flare tower according to the present invention.

이하 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대한 구성 및 작용을 상세히 설명하면 다음과 같다. 또한 하기 실시예는 여러 가지 다른 형태로 변형될 수 있으며, 본 발명의 범위가 하기 실시예에 한정되는 것은 아니다. Hereinafter, the configuration and operation of the preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings. In addition, the following examples can be modified in various forms, and the scope of the present invention is not limited to the following examples.

도 1 내지 도 6은 본 발명에 따른 플레어 타워의 설치 방법을 순서적으로 설명하기 위한 도면이다.1 to 6 are views for sequentially explaining the installation method of the flare tower according to the present invention.

도 1 내지 도 6에 도시된 바와 같이, 본 발명에 따른 플레어 타워의 설치 방법은 제 1 해상크레인(10)과 플레어 타워(flare tower; 1)를 정렬시키는 정렬단계와, 제 1 해상크레인(10)과 제 2 해상크레인(20)을 플레어 타워(1)에 연결시키는 연결단계와, 제 1 및 제 2 해상크레인(10,20)에 의해 플레어 타워(1)를 수직으로 세우는 직립단계와, 직립된 플레어 타워(1)를 해상 구조물(50)에 탑재하는 탑재단계를 포함할 수 있다.As shown in Figures 1 to 6, the installation method of the flare tower according to the present invention is an alignment step of aligning the first marine crane 10 and the flare tower (flare tower 1), and the first marine crane (10) ) And a connecting step of connecting the second marine crane 20 to the flare tower 1, an upright step of vertically setting the flare tower 1 by the first and second marine cranes 10, 20, and an upright It may include a mounting step for mounting the flared tower (1) to the offshore structure (50).

도 1에 도시된 바와 같이, 정렬단계에 의하면, 제 1 해상크레인(10)에 마련된 한 쌍의 붐(11)이 운반선(30)에 눕혀진 플레어 타워(1)의 상측에 나란하도록 위치하되, 붐(11) 사이에 플레어 타워(1)가 위치하도록 한다. 또한, 붐(11)과 플레어 타워(1)를 서로 정렬시키기 위하여 운반선(30)을 접안시킨 상태에서 제 1 해상크레인(10)이 이동하도록 할 수 있는데, 운반선(30)은 안벽(2)에 접안된 상태에서 계류라인(31)으로 고정되며, 제 1 및 제 2 해상크레인(10,20)도 작업을 위하여 계류라인(13,23)으로 정해진 위치에 고정된다.As shown in FIG. 1, according to the alignment step, the pair of booms 11 provided on the first marine crane 10 are positioned side by side on the flare tower 1 lying on the carrier ship 30, The flare tower 1 is positioned between the booms 11. In addition, the first marine crane 10 can be moved while the carrier ship 30 is docked to align the boom 11 and the flare tower 1 with each other. In the docked state, it is fixed to the mooring line 31, and the first and second marine cranes 10 and 20 are also fixed to the position defined by the mooring lines 13 and 23 for work.

도 2에 도시된 바와 같이, 연결단계에 의하면, 제 1 해상크레인(10)에 마련된 붐(11) 각각의 후크(미도시)를 플레어 타워(1)의 양측에 각각 연결(도 7 참조)하고, 제 2 해상크레인(20)의 후크(미도시)를 플레어 타워(1)에 연결한다. 이때, 연결단계는 제 1 해상크레인(10)에 마련된 붐(11) 각각의 후크를 플레어 타워(1)에서 무게 중심의 상측에 연결함으로써, 제 1 해상크레인(10)이 플레어 타워(1)를 인양시 플레이어 타워(1)가 세워지는 방향으로 인양되도록 할 수 있다. 또한, 제 2 해상크레인(20)의 후크를 플레어 타워(1)에서 무게 중심의 하측에 연결함으로써, 제 2 해상크레인(20)이 플레어 타워(1)가 수직이 되도록 가이드하는 역할을 할 수 있다. 제 1 및 제 2 해상크레인(10,20)에서 각각의 후크는 케이블(12,22)의 끝단에 위치하며, 이에 대한 도면 부호는 생략하기로 하겠다.As shown in FIG. 2, according to the connecting step, each hook (not shown) of each of the booms 11 provided on the first marine crane 10 is connected to both sides of the flare tower 1 (see FIG. 7). , The hook (not shown) of the second marine crane 20 is connected to the flare tower (1). At this time, in the connecting step, the hooks of each of the booms 11 provided in the first marine crane 10 are connected to the upper side of the center of gravity in the flare tower 1, so that the first marine crane 10 connects the flare tower 1. At the time of lifting, the player tower 1 may be lifted in the direction in which it is erected. In addition, by connecting the hook of the second marine crane 20 to the lower side of the center of gravity in the flare tower 1, the second marine crane 20 can serve to guide the flare tower (1) to be vertical. . In the first and second marine cranes (10, 20), each hook is located at the ends of the cable (12, 22), the reference numerals will be omitted.

한편, 도 7에 도시된 바와 같이, 제 1 해상크레인(10; 도 2에 도시)의 붐(11)으로부터 인출되는 케이블(12)이 서로 교차되지 않도록 대략 나란하게 플레어 타워(1)의 양측에 연결되며, 이를 위해 리프팅 프레임(lifting frame; 40)을 이용하여 제 1 해상크레인(10)이 플레어 타워(1)에 연결되도록 할 수 있다.On the other hand, as shown in FIG. 7, the cables 12 drawn out from the boom 11 of the first marine crane 10 (shown in FIG. 2) are substantially parallel to both sides of the flare tower 1 so as not to cross each other. For this purpose, the first marine crane 10 may be connected to the flare tower 1 by using a lifting frame 40.

도 8에 도시된 바와 같이, 리프팅 프레임(40)은 플레어 타워(1)에 수평되게 양측으로 연장되는 지지바(41)를 가지고, 지지바(41)의 끝단에 붐(11;도 7에 도시)으로부터의 후크(혹은 와이어)가 각각 체결되는 체결부(42)가 마련되는데, 이러한 지지바(41)가 플레어 타워(1)의 세로부재(1a)와 가로부재(1b)에 다수의 보강바(43)에 의해 연결됨으로써 플레어 타워(1)에 일체를 이루도록 고정될 수 있다. 한편, 플레어 타워(1)는 통상 3개의 세로부재(1a)를 가지는데, 리프팅 프레임(40)이 설치된 하나의 세로부재(1a)를 제외한 나머지 2개의 세로부재에는 체결부(42)와 마찬가지로 제 1 해상크레인(10)으로부터의 후크(혹은 와이어)가 연결될 수 있는 또 다른 체결부(44)가 각각 설치될 수 있다.As shown in FIG. 8, the lifting frame 40 has a support bar 41 extending horizontally on both sides of the flare tower 1, and at the end of the support bar 41 a boom 11 (shown in FIG. 7). Fastening part 42 to which hooks (or wires) from each other are fastened to each other, and the support bar 41 is provided with a plurality of reinforcing bars on the vertical member 1a and the horizontal member 1b of the flare tower 1. By being connected by 43 can be fixed to the flare tower (1) integrally. On the other hand, the flare tower (1) usually has three vertical members (1a), except for one vertical member (1a) in which the lifting frame 40 is installed, the same as the fastening portion (42) Each of the fastening portions 44 to which hooks (or wires) from the 1 marine crane 10 may be connected may be installed.

도 3 내지 도 5에 도시된 바와 같이, 직립단계에 의하면, 제 1 및 제 2 해상크레인(10,20)에 의해 플레어 타워(1)를 운반선(30)으로부터 인양하여 제 1 크레인(10)의 붐(11) 사이를 통해서 수직으로 세우도록 한다.As shown in FIGS. 3 to 5, according to the upright step, the flare tower 1 is lifted from the carrier ship 30 by the first and second marine cranes 10 and 20 to lift the first crane 10. Stand vertically through the booms (11).

직립단계는 일례로, 도 3에 도시된 바와 같이, 제 1 및 제 2 해상크레인(10,20)이 플레어 타워(1)를 수평을 유지한 상태로 정해진 높이, 예컨대, 플레어 타워(1)를 세울 때 플레어 타워(1)의 하부가 운반선(30)에 충돌하지 않을 정도의 높이까지 인양하는 단계와, 도 4 및 도 5에 도시된 바와 같이, 제 2 해상크레인(20)이 플레어 타워(10)를 기울어지게 가이드하면서, 제 1 해상크레인(10)이 플레어 타워(1)의 중량을 대부분 부담하도록 인양하여 붐(11) 사이에 플레어 타워(1)가 직립되도록 하는 단계를 포함할 수 있다. The upright step is, for example, as shown in Figure 3, the first and second marine cranes (10, 20) to maintain the height of the flare tower 1, for example, the flare tower (1) Lifting it to a height such that the lower portion of the flare tower 1 does not collide with the carrier ship 30 when standing up, and as shown in FIGS. 4 and 5, the second marine crane 20 is flared tower 10. ), The first offshore crane 10 may be lifted to bear most of the weight of the flare tower 1 to allow the flare tower 1 to stand upright between the booms 11.

도 6에 도시된 바와 같이, 탑재단계에 의하면, 직립단계에 의해 세워진 플레어 타워(1)를 탑재를 필요로 하는 선박이나 부유식 구조물 등과 같은 해상 구조물(50)에 탑재한다. 여기서, 플레어 타워(1)의 탑재를 위하여 제 1 해상크레인(10)과 제 2 해상크레인(20; 도 5에 도시)이 해상 구조물(50)로 이동할 수 있으며, 이와 달리, 플레어 타워(1)의 안정적인 탑재와 작업의 신뢰성을 높이기 위하여 제 1 해상크레인(10)과 제 2 해상크레인(20; 도 5에 도시)의 위치를 고정시킨 상태에서 플레어 타워(1)가 해상 구조물(50)에 탑재되도록 할 수 있다. 또한, 탑재단계는 해상 구조물(50)에 직립되도록 탑재된 플레어 타워(1)를 해상 구조물(50)에 고정시키는 작업을 연속해서 수행할 수 있다.As shown in FIG. 6, according to the mounting step, the flare tower 1 erected by the upright step is mounted on a marine structure 50 such as a ship or a floating structure that requires mounting. Here, the first offshore crane 10 and the second offshore crane 20 (shown in FIG. 5) may move to the offshore structure 50 to mount the flare tower 1. Alternatively, the flare tower 1 The flare tower 1 is mounted on the offshore structure 50 in a state where the positions of the first offshore crane 10 and the second offshore crane 20 (shown in FIG. 5) are fixed in order to ensure stable mounting and operation reliability. You can do that. In addition, the mounting step may continuously perform the operation of fixing the flare tower (1) mounted so as to stand up to the offshore structure 50 to the offshore structure (50).

이와 같은 본 발명에 따른 플레어 타워의 설치 방법은 플레어 타워의 제작과 직립 및 탑재를 단일화하여 연속적으로 수행할 수 있으며, 이로 인해 추가적인 설비 운용과 비용을 최소화한다. 또한, 해상크레인의 소요 시간을 단축시킴과 아울러 육상 작업장의 회전을 통한 생산성을 향상시키며, 리프팅 프레임이 플레어 타워에 일체를 이루게 됨으로써 경량화를 가능하도록 하여 작업의 용이성과 경제성을 높인다.Such installation method of the flare tower according to the present invention can be carried out continuously by unifying the production and upright and mounting of the flare tower, thereby minimizing additional equipment operation and costs. In addition, it reduces the time required for offshore cranes and improves productivity through the rotation of the on-shore workshop, and the lifting frame is integrated with the flare tower to enable light weight, thereby increasing the ease of operation and economy.

본 발명은 상기 실시예에 한정되지 않고 본 발명의 기술적 요지를 벗어나지 아니하는 범위 내에서 다양하게 수정 또는 변형되어 실시될 수 있음은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 있어서 자명한 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit and scope of the invention will be.

1 : 플레어 타워 1a : 세로부재
1b : 가로부재 2 : 안벽
10 : 제 1 해상크레인 11 : 붐
12 : 케이블 13 : 계류라인
20 : 제 2 해상크레인 21 : 붐
22 : 케이블 23 : 계류라인
30 : 운반선 31 : 계류라인
40 : 리프팅 프레임 41 : 지지바
42, 44 : 체결부 43 : 보강바
50 : 해상 구조물
1: flare tower 1a: vertical member
1b: horizontal member 2: inner wall
10: first offshore crane 11: boom
12 cable 13 mooring line
20: second offshore crane 21: boom
22 cable 23 mooring line
30: carrier ship 31: mooring line
40: lifting frame 41: support bar
42, 44: fastening portion 43: reinforcing bar
50: offshore structures

Claims (5)

플레어 타워를 설치하는 방법에 있어서,
제 1 해상크레인에 마련된 한 쌍의 붐이 운반선에 눕혀진 플레어 타워의 상측에 나란하도록 위치하되, 상기 붐 사이에 상기 플레어 타워가 위치하도록 하는 정렬단계;
상기 붐 각각의 후크를 상기 플레어 타워의 양측에 각각 연결하고, 제 2 해상크레인의 후크를 상기 플레어 타워에 연결하는 연결단계;
상기 제 1 및 제 2 해상크레인에 의해 상기 플레어 타워를 상기 운반선으로부터 인양하여 상기 붐 사이를 통해서 수직으로 세우는 직립단계; 및
상기 직립단계에 의해 세워진 상기 플레어 타워를 해상 구조물에 탑재하는 탑재단계
를 포함하는 것을 특징으로 하는 플레어 타워의 설치 방법.
In the method of installing a flare tower,
An alignment step in which a pair of booms provided on a first marine crane are positioned side by side on a flare tower lying on a carrier, and the flare towers are positioned between the booms;
Connecting the hooks of each of the booms to both sides of the flare tower, and connecting the hooks of the second marine crane to the flare towers;
An upright step of lifting the flare tower from the carrier by the first and second marine cranes and standing vertically between the booms; And
Mounting step for mounting the flare tower erected by the upright step in the offshore structure
Installation method of the flare tower comprising a.
청구항 1에 있어서,
상기 연결단계는 상기 붐 각각의 후크를 상기 플레어 타워에서 무게 중심의 상측에 연결하고, 상기 제 2 해상크레인의 후크를 상기 플레어 타워에서 무게 중심의 하측에 연결하는 것을 특징으로 하는 플레어 타워의 설치 방법.
The method according to claim 1,
The connecting step is the installation method of the flare tower, characterized in that for connecting the hooks of each of the boom to the upper side of the center of gravity in the flare tower, the hook of the second marine crane from the flare tower to the lower side of the center of gravity .
청구항 1 또는 청구항 2에 있어서,
상기 연결단계는 상기 플레어 타워에 수평되게 양측으로 연장되는 지지바를 가지고, 상기 지지바 각각의 끝단에 상기 붐의 후크가 체결되는 체결부가 마련되는 리프팅 프레임을 이용하여 상기 플레어 타워가 상기 제 1 해상크레인에 연결되는 것을 특징으로 하는 플레어 타워의 설치 방법.
The method according to claim 1 or 2,
The connecting step has a support bar extending horizontally on both sides of the flare tower, the flare tower is the first marine crane by using a lifting frame provided with a fastening portion for fastening the hook of the boom at each end of the support bar Installation method of the flare tower, characterized in that connected to.
청구항 3에 있어서,
상기 리프팅 프레임은 상기 지지바가 상기 플레어 타워의 세로부재와 가로부재에 다수의 보강바에 의해 연결됨으로써 상기 플레어 타워에 일체를 이루도록 고정되는 것을 특징으로 하는 플레어 타워의 설치 방법.
The method according to claim 3,
The lifting frame is installed on the flare tower, characterized in that the support bar is fixed to be integral to the flare tower by being connected to the vertical member and the horizontal member of the flare tower by a plurality of reinforcing bars.
청구항 1에 있어서, 상기 직립단계는
상기 제 1 및 제 2 해상크레인이 상기 플레어 타워를 수평을 유지한 상태로 정해진 높이까지 인양하는 단계; 및
상기 제 2 해상크레인이 상기 플레어 타워를 기울어지게 가이드하면서 상기 제 1 해상크레인이 상기 붐 사이에 상기 플레어 타워를 인양하여 직립되도록 하는 단계
를 포함하는 것을 특징으로 하는 플레어 타워의 설치 방법.
The method of claim 1, wherein the upright step
Lifting the first and second marine cranes to a predetermined height while keeping the flare tower level; And
Guiding the second offshore crane to tilt the flare tower while the first offshore crane lifts the flare tower between the boom to stand upright.
Installation method of the flare tower comprising a.
KR1020100082411A 2010-08-25 2010-08-25 Method for installing flare tower KR101213756B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100082411A KR101213756B1 (en) 2010-08-25 2010-08-25 Method for installing flare tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100082411A KR101213756B1 (en) 2010-08-25 2010-08-25 Method for installing flare tower

Publications (2)

Publication Number Publication Date
KR20120019175A true KR20120019175A (en) 2012-03-06
KR101213756B1 KR101213756B1 (en) 2012-12-18

Family

ID=46128201

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100082411A KR101213756B1 (en) 2010-08-25 2010-08-25 Method for installing flare tower

Country Status (1)

Country Link
KR (1) KR101213756B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101253411B1 (en) * 2011-03-31 2013-04-11 현대중공업 주식회사 Mounting method for derrick of drillship
KR101280464B1 (en) * 2011-03-25 2013-07-01 삼성중공업 주식회사 METHOD for MOUNTING TOWER STRUCTURE
KR101280521B1 (en) * 2011-06-02 2013-07-01 삼성중공업 주식회사 A marin structure for flare tower and method for mounting flare tower
KR20140030476A (en) * 2012-08-30 2014-03-12 대우조선해양 주식회사 Divided erection method of flare tower
KR20160103407A (en) * 2015-02-24 2016-09-01 대우조선해양 주식회사 Loading method of structure and crane-linking apparatus for the same
WO2017092051A1 (en) * 2015-12-04 2017-06-08 深圳智慧能源技术有限公司 Skid-mount structure for ejector-type combustion device
WO2017092058A1 (en) * 2015-12-04 2017-06-08 深圳智慧能源技术有限公司 Ejection combustion apparatus having movable support frame
CN107201846A (en) * 2017-05-23 2017-09-26 中建安装工程有限公司 A kind of installing flare tower frame and its modularization installation method
CN109083489A (en) * 2018-10-12 2018-12-25 上海市机械施工集团有限公司 Self-unloading cluster overhead torch assembling and disassembling device, installation method and method for dismounting
CN113128077A (en) * 2021-05-25 2021-07-16 上海建工四建集团有限公司 Digital simulation optimization method for group tower vertical climbing plan

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005082249A (en) 2003-09-04 2005-03-31 Takenaka Doboku Co Ltd Method for erection of exterior elevator

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101280464B1 (en) * 2011-03-25 2013-07-01 삼성중공업 주식회사 METHOD for MOUNTING TOWER STRUCTURE
KR101253411B1 (en) * 2011-03-31 2013-04-11 현대중공업 주식회사 Mounting method for derrick of drillship
KR101280521B1 (en) * 2011-06-02 2013-07-01 삼성중공업 주식회사 A marin structure for flare tower and method for mounting flare tower
KR20140030476A (en) * 2012-08-30 2014-03-12 대우조선해양 주식회사 Divided erection method of flare tower
KR20160103407A (en) * 2015-02-24 2016-09-01 대우조선해양 주식회사 Loading method of structure and crane-linking apparatus for the same
WO2017092051A1 (en) * 2015-12-04 2017-06-08 深圳智慧能源技术有限公司 Skid-mount structure for ejector-type combustion device
WO2017092058A1 (en) * 2015-12-04 2017-06-08 深圳智慧能源技术有限公司 Ejection combustion apparatus having movable support frame
CN107201846A (en) * 2017-05-23 2017-09-26 中建安装工程有限公司 A kind of installing flare tower frame and its modularization installation method
CN109083489A (en) * 2018-10-12 2018-12-25 上海市机械施工集团有限公司 Self-unloading cluster overhead torch assembling and disassembling device, installation method and method for dismounting
CN113128077A (en) * 2021-05-25 2021-07-16 上海建工四建集团有限公司 Digital simulation optimization method for group tower vertical climbing plan
CN113128077B (en) * 2021-05-25 2024-04-23 上海建工四建集团有限公司 Digital simulation optimization method for vertical climbing plan of group tower

Also Published As

Publication number Publication date
KR101213756B1 (en) 2012-12-18

Similar Documents

Publication Publication Date Title
KR101213756B1 (en) Method for installing flare tower
CN109689561B (en) Crane, vessel comprising such a crane and method for erecting a longitudinal structure
US7112010B1 (en) Apparatus, systems and methods for erecting an offshore wind turbine assembly
KR101722595B1 (en) Divided Erection Method Of Flare Tower
KR20120047740A (en) Deck ascent and descent type worktable ship and construction method of shore wind power generation facility using the same
KR101401985B1 (en) Floating crane with jack-up system for floating structure
US20220234697A1 (en) A floating structure and method of installation
WO2009041812A1 (en) Method and structure for lifting and attaching a composite structure to a vertical support
JP2013063767A (en) Installation special vessel of windmill equipment of sea wind power generation, installation jig and installation method
CN103193163A (en) Entrance dock installation method for gantry crane of shipyard
US20240229771A9 (en) Method and blade installation device for installing a blade of an offshore wind turbine
US20220177081A1 (en) Vessel and method for installation of a pile adapted to support an offshore wind turbine
JP2024519473A (en) Erection crane and installation vessel
CN111852400A (en) Combined PLET for connecting flexible vertical pipe
JP7475345B2 (en) Crane, crane assembly method, and crane disassembly method
KR20140098362A (en) Apparatus for guiding winch
WO2020225157A1 (en) Compact jib crane
CN114857358B (en) Suspension type cable reversing system
EP2865631B1 (en) Lifting jig and method
KR20130073117A (en) Tower structure construction process
JP2024513316A (en) Offshore wind turbine with floating platform
CN109665445B (en) Loading, transporting and conveying process for torch tower crane
CN103058083B (en) Bolt sphere truss gig
KR102046810B1 (en) Suction hose installing method into cassion of ocean facility
KR20120134269A (en) A marin structure for flare tower and method for mounting flare tower

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20151117

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20161202

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20171129

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20181207

Year of fee payment: 7