KR20120005680A - Multi-step tunnel constructing method using pilot tunnel - Google Patents

Multi-step tunnel constructing method using pilot tunnel Download PDF

Info

Publication number
KR20120005680A
KR20120005680A KR1020100066247A KR20100066247A KR20120005680A KR 20120005680 A KR20120005680 A KR 20120005680A KR 1020100066247 A KR1020100066247 A KR 1020100066247A KR 20100066247 A KR20100066247 A KR 20100066247A KR 20120005680 A KR20120005680 A KR 20120005680A
Authority
KR
South Korea
Prior art keywords
tunnel
excavation
pilot
pilot tunnel
section
Prior art date
Application number
KR1020100066247A
Other languages
Korean (ko)
Other versions
KR101247702B1 (en
Inventor
박재현
Original Assignee
(주)한국투아치
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한국투아치 filed Critical (주)한국투아치
Priority to KR1020100066247A priority Critical patent/KR101247702B1/en
Publication of KR20120005680A publication Critical patent/KR20120005680A/en
Application granted granted Critical
Publication of KR101247702B1 publication Critical patent/KR101247702B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE: A tunnel construction method of a multi-stage excavation mode applying a pilot tunnel is provided to improve work efficiency and to improve the stability of a tunnel. CONSTITUTION: A tunnel construction method of a multi-stage excavation mode applying a pilot tunnel is composed like next. A pilot tunnel(51) is dug in the longitudinal direction using a blasting mode. The excavation works is performed after excavating a part of the pilot tunnel. The residual tunnel portions(52,53) reaching the cross section excluding the pilot tunnel is divided to be excavated in the longitudinal direction of a tunnel.

Description

파일럿 터널을 적용한 다단 굴착 방식의 터널 시공방법{Multi-Step Tunnel Constructing Method Using Pilot Tunnel}Multi-Step Tunnel Constructing Method Using Pilot Tunnel}

본 발명은 터널 시공방법에 관한 것으로서, 보다 상세하게는 전체 터널의 시공기간의 단축을 가져옴과 동시에 작업효율을 향상시킨 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공방법에 관한 것이다.The present invention relates to a tunnel construction method, and more particularly, to a tunnel construction method of a multi-stage excavation method using a pilot tunnel that brings a shortening of the construction period of the entire tunnel and improves work efficiency.

터널은 내부를 통행하는 차량에 따른 왕복 2차선 또는 4차선 등과 같은 전체 크기를 결정하여 시공하게 된다.The tunnel is constructed by determining the overall size, such as a round-trip two-lane or four-lane according to the vehicle passing through the interior.

일반적으로는 왕복 2차선 정도의 터널은 소단면 터널로, 왕복 4차선 이상의 터널은 대단면 터널로 분류하여 구성되며, 경우에 따라서 상기 소단면 터널은 양측 두 개의 소단면 터널을 병렬 터널로 이루어지도록 하여 일측 터널은 상행선으로 타측 터널은 하행선으로 구성하기도 한다.In general, the two-lane round trip tunnel is divided into small cross-section tunnels, and the four-lane round-trip tunnel is divided into large cross-section tunnels. In some cases, the small cross-section tunnel includes two small cross-section tunnels in parallel tunnels. Therefore, one tunnel may be configured as an upline and the other tunnel may be configured as a downline.

한편, 도 1에서와 같이, 종래의 대단면 터널의 경우는 시공 시 하루에 수회의 발파를 통하여 시공될 터널의 길이방향에 따라 일정 구간(l1)에 걸쳐 굴착작업이 이루어지게 되는데, 보통 2m 정도씩 2회의 굴착작업이 이루어지는 과정을 거쳐 전체 터널 시공이 이루어졌다. 즉, 하루 4m 정도의 길이로 굴착하는 작업이 이루어져 전체 터널이 완성되도록 하였다.On the other hand, as shown in Figure 1, in the case of a conventional large cross-section tunnel, the excavation work is made over a predetermined length (l1) in the longitudinal direction of the tunnel to be constructed through several blasting per day, usually about 2m The entire tunnel construction was carried out through two excavation works. In other words, the excavation was carried out to a length of about 4m per day to complete the entire tunnel.

그런데, 이와 같은 종래의 터널 시공 방법에 있어서, 특히 대단면 터널의 경우는 하루 굴착구간이 너무 짧은 관계로 터널의 전체적인 시공 기간이 너무 오래 걸린다는 문제점이 있었다.By the way, in the conventional tunnel construction method, in particular, in the case of large cross section tunnel, there is a problem that the whole construction period of the tunnel takes too long because the excavation section is too short per day.

이를 해결하기 위하여 최근 들어서는 지반의 진동문제를 감안하고, 굴착속도를 증가시키기 위하여 먼저 TBM을 이용하여 파일롯 터널을 굴착하고 그 주위를 발파를 통해 확대 굴착하여 최종터널을 완성하는 TBM을 이용한 터널 시공공법이 국내외 여러 터널현장에 적용되고 있다.In order to solve this problem, considering the vibration problem of the ground recently, in order to increase the excavation speed, the tunnel construction method using the TBM is completed by digging the pilot tunnel using TBM and expanding the excavation through blasting around to complete the final tunnel. It is applied to various tunnel sites at home and abroad.

간략하게 이와 같은 TBM을 이용한 터널 시공방법을 간략히 설명하면 다음과 같다.Briefly describing the tunnel construction method using such a TBM as follows.

종래 TBM 터널 시공방법은 TBM을 이용하여 시공될 터널의 중심부를 횡방향으로 굴착하여 TBM 파일롯 터널을 일정 길이만큼 굴착한 후, 그리고, 상기 TBM 파일롯 터널의 천정부와 측부에 발파를 위해 발파공을 천공한다.Conventional TBM tunnel construction method by excavating the center of the tunnel to be constructed using the TBM in the transverse direction to excavate the TBM pilot tunnel by a certain length, and then drills the blast hole for blasting to the ceiling and sides of the TBM pilot tunnel. .

다음으로, 상기 발파공의 천공작업이 완료되면, 완성된 발파공에 화약을 장약하고 계획된 순서대로 발파하여 잔여터널부를 굴착한다.Next, when the drilling operation of the blast hole is completed, charge the gunpowder to the completed blast hole and blast in the planned order to excavate the remaining tunnel portion.

그리고, 발파과정에서 발생된 암버럭을 제거하게 되며, 이와 같은 방식에 따라서 상기 파일롯 터널의 내부는 점진적으로 확대되는데, 터널의 내부가 시공할 최종 대단면 터널면에 도달할 때까지 상기와 같은 발파작업을 반복적으로 실시한다.In addition, the interior of the pilot tunnel is gradually enlarged according to such a method. The blasting process is removed until the interior of the tunnel reaches the final large cross section tunnel surface to be constructed. Repeat the work.

이후, 다시 TBM을 이용하여 다시 일정 길이만큼 천공하고 상기의 과정을 계속적으로 반복하여 굴착하여 전체 터널을 완성한다.After that, again drilling by a certain length using TBM again and repeatedly repeating the above process to complete the entire tunnel.

그런데, 상기와 같은 종래의 TBM을 이용한 터널의 시공방법은 파일롯 터널을 시공할 터널의 중앙부를 관통한 후에 확공 시공하게 되는데, 이때 굴착 속도가 느려지게 되며, 이는 곧 전체 터널 시공기간까지 지연되는 결과를 초래하였다.By the way, the conventional construction method of the tunnel using TBM is to expand the construction after passing through the central portion of the tunnel to be installed pilot tunnel, at this time the excavation speed is slowed, which is delayed until the entire tunnel construction period Resulted.

또한, 터널을 발파 방식으로 굴착한 경우 생기는 암버럭은 별도의 도로 포장이나 기타 조경을 위한 시설물 등에 사용하여 재활용되도록 하였었으나, 이와 같은 TBM을 이용하여 굴착되어 생성되는 암버럭은 그 입자가 상당히 작은 관계로 재활용이 불가능하게 된다는 문제점 등도 있었다.In addition, the amber buckle produced when the tunnel was blasted was recycled using a separate road pavement or other landscaping facility, but the buff produced by excavation using such TBM has a considerably smaller particle size. As a result, there was a problem that recycling is impossible.

본 발명은 상술한 종래의 문제점 및 제결점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은 다음과 같다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the aforementioned problems and drawbacks of the prior art, and an object of the present invention is as follows.

첫째, 4차선 이상의 터널과 같은 대단면 터널의 시공 기간을 단축할 수 있는 터널 시공방법을 제공하는데 그 목적이 있다.First, the purpose of the present invention is to provide a tunnel construction method that can shorten the construction period of large section tunnels such as four-lane or more tunnels.

둘째, 시공기간을 단축하면서도 암버럭을 재활용도를 증대시킬 수 있는 터널의 시공방법을 제공하는데 그 목적이 있다.Second, its purpose is to provide a tunnel construction method that can shorten the construction period and increase the recyclability of the cancer bag.

셋째, 터널의 안정성이 향상되도록 하면서 이를 위한 보강 시설물을 효율적으로 설치할 수 있도록 하는 터널 시공방법을 제공하는데 그 목적이 있다.Third, the purpose is to provide a tunnel construction method that can efficiently install the reinforcement facilities for this while improving the stability of the tunnel.

넷째, 터널이 시공되는 주위의 지형물의 피해를 최소화하여 민원 발생 등도 줄일 수 있도록 한 터널 시공방법을 제공하는데 그 목적이 있다.Fourth, the purpose of the present invention is to provide a tunnel construction method that can reduce the occurrence of civil complaints by minimizing damage of the surrounding terrain where the tunnel is constructed.

상기한 목적을 달성하기 위하여, 본 발명은 시공될 대단면 터널의 길이방향을 따라서 발파방식으로 파일럿 터널을 다수 회에 걸쳐 굴착하는 단계 및 상기 파일럿 터널을 일부 길이 굴착한 후에 굴착작업이 시행되며, 상기 파일럿 터널 이외의 대단면에 이르는 잔여터널부를 단면상 적어도 1단면 이상으로 나누어 터널의 길이방향을 따라서 굴착하는 단계를 포함하여 구성되는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공방법을 제공한다.In order to achieve the above object, the present invention is a step of excavating the pilot tunnel a plurality of times in a blasting manner along the longitudinal direction of the large cross-section tunnel to be constructed and after excavating the pilot tunnel some length, It provides a tunnel construction method of the multi-stage excavation method applying a pilot tunnel comprising a step of digging along the longitudinal direction of the tunnel dividing the remaining tunnel portion to at least one end surface in cross section other than the pilot tunnel.

여기서, 상기 파일럿 터널의 굴착과 상기 잔여터널부의 굴착은 병행하여 진행될 수 있다.Here, excavation of the pilot tunnel and excavation of the remaining tunnel portion may be performed in parallel.

그리고, 상기 파일럿 터널의 굴착단계마다, 상기 파일럿 터널의 상부를 보강하는 단계를 더 포함할 수 있다.The method may further include reinforcing the upper portion of the pilot tunnel for each excavation step of the pilot tunnel.

상기 파일럿 터널의 상부를 보강하는 단계는 상기 파일럿 터널의 상부에 천공홀을 형성하는 단계와 상기 형성된 천공홀에 그라우팅 보강유닛을 설치하는 단계 및 상기 그라우팅 보강유닛이 설치된 천공홀에 그라우팅 시공을 하는 단계를 포함하여 구성될 수 있다.The step of reinforcing the upper part of the pilot tunnel may include forming a hole in the upper part of the pilot tunnel, installing a grouting reinforcing unit in the formed hole, and grouting construction in the hole in which the grouting reinforcing unit is installed. It may be configured to include.

상기 천공홀에 설치되는 그라우팅 보강유닛은, 스틸보강부재와 GRP보강부재가 연결된 형태로 이루어지며, 상기 GRP보강부재가 상기 대단면 터널의 하측으로 위치되도록 설치될 수 있다.The grouting reinforcing unit installed in the drilling hole is made of a form in which a steel reinforcing member and a GRP reinforcing member are connected, and the GRP reinforcing member may be installed to be positioned below the large end face tunnel.

상기 파일럿 터널의 굴착위치는, 시공될 대단면 터널의 중앙으로부터 편심된 위치에 굴착될 수 있다.The excavation position of the pilot tunnel may be excavated at a position eccentric from the center of the large cross-section tunnel to be constructed.

그리고, 상기 잔여터널부의 굴착을 2회 이상으로 나누어 굴착하는 경우에는, 상기 각각의 잔여터널부의 굴착이 병행하여 이루어지도록 할 수 있다.In addition, when digging the residual tunnel portion in two or more times, excavation of each of the remaining tunnel portions may be performed in parallel.

상기와 같이 구성된 본 발명 파일럿 터널을 적용한 다단 발파 방식 터널 시공방법의 효과에 대하여 설명하면 다음과 같다.Referring to the effect of the multi-stage blasting tunnel construction method to which the present invention pilot tunnel configured as described above is as follows.

첫째, 본 발명에 의하면 터널 전체 시공을 위해 필요한 공기 단축 효과를 가져오며 이는 결국 공사비 절감의 효과를 가져오게 된다.First, according to the present invention brings the air shortening effect required for the entire construction of the tunnel, which in turn brings the effect of reducing the construction cost.

둘째, 파일럿 터널의 굴착을 터널의 중앙으로부터 일부 편심된 위치로 할 수 있어 상황에 따라 최적의 작업환경 등을 확보하여 터널 시공이 가능하게 되며, 또한 시공기간 면에서도 유리한 효과를 가져올 수 있다. Second, the excavation of the pilot tunnel can be partly eccentric from the center of the tunnel, so it is possible to construct the tunnel by securing the optimum working environment according to the situation, and also bring a favorable effect in terms of construction period.

셋째, 발파방식의 파일럿 터널을 선 굴착하면서 주위의 암반 상태를 확인할 수 있으므로, 잔여터널부의 굴착 작업을 안정적으로 진행되도록 함과 동시에 그 잔여터널부의 굴착 속도를 조절할 수 있게 되는 효과가 있다.Third, since the rock conditions around can be checked while pre-exploring the blasting pilot tunnel, there is an effect that the excavation work of the remaining tunnel portion can be performed stably and the excavation speed of the remaining tunnel portion can be adjusted.

넷째, 파일럿 터널을 발파방식으로 굴착하므로 암버럭의 재활용에 있어 유리하게 된다.Fourth, since the pilot tunnel is excavated in a blasting manner it is advantageous in the recycling of the arm block.

도 1은 종래 터널의 굴착 과정을 설명하기 위하여 대단면 터널을 개략적으로 나타낸 사시도;
도 2는 본 발명에 따른 파일럿 터널의 굴착과정을 나타낸 정면도 및 측단면도;
도 3은 본 발명에 따른 파일럿 터널의 상부에 그라우팅 보강유닛이 설치된 모습을 개략적으로 정면도 및 측단면도;
도 4 및 도 5는 본 발명에 따른 파일럿 터널의 굴착과정을 나타낸 정면도 및 측단면도;
도 6은 본 발명에 따른 다단 굴착 방식의 터널 시공방법에 있어서 사용되는 차량이 설치된 모습을 나타낸 정면도 및 측단면도;
도 7은 본 발명에 따른 다단 굴착 방식의 터널 시공방법에 있어서 사용되는 그라우팅 보강유닛을 나타낸 측면도;
도 8은 본 발명에 따른 다단 굴착 방식의 터널 시공방법에 있어서 사용되는 그라우팅 보강유닛이 설치된 모습을 나타낸 측면도;
도 9는 본 발명에 따른 터널의 굴착 과정을 설명하기 위하여 대단면 터널 내 파일럿 터널의 굴착되는 모습을 개략적으로 나타낸 사시도; 및
도 10은 본 발명의 다른 실시예에 따른 대단면 터널의 시공을 위한 파일럿 터널의 굴착 모습을 나타낸 도면이다.
1 is a perspective view schematically showing a large cross-section tunnel to explain the excavation process of a conventional tunnel;
2 is a front view and a side cross-sectional view showing an excavation process of a pilot tunnel according to the present invention;
Figure 3 is a front and side cross-sectional view schematically showing a state in which the grouting reinforcement unit is installed on top of the pilot tunnel according to the present invention;
4 and 5 are a front view and a side sectional view showing an excavation process of the pilot tunnel according to the present invention;
6 is a front view and a side sectional view showing a state in which a vehicle used in the multi-stage excavation tunnel construction method according to the present invention is installed;
Figure 7 is a side view showing a grouting reinforcement unit used in the tunnel construction method of the multi-stage excavation method according to the present invention;
8 is a side view showing a state in which the grouting reinforcement unit used in the multi-stage excavation tunnel construction method according to the present invention is installed;
9 is a perspective view schematically showing the excavation of the pilot tunnel in a large cross-section tunnel to explain the excavation process of the tunnel according to the present invention; And
10 is a view showing the excavation of the pilot tunnel for the construction of a large cross-section tunnel according to another embodiment of the present invention.

이하 첨부된 도면들을 참조하여 본 발명의 바람직한 실시예들을 상세하게 설명하지만, 본 발명이 실시예들에 의해 제한되거나 한정되는 것은 아니다. 참고로, 이하 설명에서는 구성 및 기능이 거의 동일하여 동일하게 취급될 수 있는 요소는 동일한 참조번호로 특정될 수 있다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the like elements throughout. Note that, in the following description, components that are substantially the same in structure and function and can be handled identically can be identified by the same reference numerals.

첨부된 도면 중 도 2는 본 발명에 따른 다단 터널 굴착 방법에 있어서 파일럿 터널이 굴착된 모습을 나타낸 위한 도면들이다.2 is a view showing a pilot tunnel excavated in the multi-stage tunnel excavation method according to the present invention.

도시된 것처럼, 본 발명 파일럿 터널을 적용한 다단 굴착 방식의 터널 굴착 방법에 따르면, 대단면 터널 내측으로 시공할 터널의 길이방향을 따라서 일정 구간에 걸쳐 파일럿 터널(51)을 굴착한다.As shown, according to the tunnel excavation method of the multi-stage excavation method using the pilot tunnel of the present invention, the pilot tunnel 51 is excavated over a predetermined section along the longitudinal direction of the tunnel to be constructed inside the large cross-section tunnel.

이때, 일반적인 터널 시공 방식과 같은 발파공법이 사용될 것이며, 하루에 다수 회의 작업을 통하여 소정 길이에 이르기까지 굴착작업이 이루어질 수 있다.In this case, a blasting method such as a general tunnel construction method will be used, and the excavation work may be performed up to a predetermined length through a plurality of operations per day.

일반적으로, 본 발명에 따른 파일럿 터널(51)의 굴착은 작은 직경이 굴착되며, 종전의 2차선 터널 굴착 시에 소요되었던 한번에 3.5m 정도씩 2회에 걸쳐 7m 정도 또는 그 이상의 굴착 속도로 작업이 이루어질 수 있다.In general, the excavation of the pilot tunnel 51 according to the present invention is a small diameter excavation, the operation is carried out at an excavation speed of about 7m or more twice in about 3.5m at a time used in the conventional two-lane tunnel excavation Can be done.

다음으로는, 첨부된 도 3에 도시된 것처럼, 굴착된 파일럿 터널(51)의 상부구간을 그라우팅 보강유닛(100)과 그라우팅 작업 등을 통하여 보강시키는 작업을 수행한다.Next, as shown in FIG. 3, the upper section of the drilled pilot tunnel 51 is reinforced by the grouting reinforcing unit 100 and grouting.

여기서, 그라우팅(grouting)이라 함은 토목공사에서 누수방지나 토질안정 등의 목적으로 지반 내부에 시멘트 등과 같은 소정의 그라우팅재를 주입하여 지반을 안정화시키는 것을 말한다.Here, grouting refers to stabilizing the ground by injecting a predetermined grouting material such as cement into the ground for the purpose of leakage prevention or soil stability in civil works.

그리고, 별도의 장봉 형태의 그라우팅 보강유닛이 설치되는데, 이에 대한 자세한 도시 및 설명은 후술한다.Then, a separate rod-shaped grouting reinforcement unit is installed, which will be described later in detail and description.

다음으로, 상술한 보강작업이 완료된 후에는, 첨부된 도 4에 도시된 바와 같이, 상기 파일럿 터널(51)의 외부로 대단면 터널의 내면에 이르기까지 잔여터널부(52,53)를 굴착하는 단계를 거치게 된다.Next, after the above reinforcement work is completed, as shown in the accompanying FIG. 4, the remaining tunnels 52 and 53 are excavated to the outside of the pilot tunnel 51 up to the inner surface of the large cross-section tunnel. It goes through the steps.

이때, 상기 파일럿 터널(51)의 굴착작업이 병행하여 이루어지게 된다. 즉, 상기 파일럿 터널의 굴착작업은 상기 잔여터널부의 굴착작업과 동시에 또는 번갈아 이루어질 수 있게 된다.At this time, the excavation work of the pilot tunnel 51 is performed in parallel. In other words, the excavation work of the pilot tunnel may be performed simultaneously with or alternately with the excavation work of the remaining tunnel portion.

한편, 상기 잔여터널부는 단면상 다수 구간으로 나뉘어 굴착할 수 있는데, 즉, 첨부된 도 4 및 도 5에 도시된 바와 같이, 단면상 잔여터널부(52,53)를 파일럿 터널(51) 주위로 다수 단면에 걸쳐 굴착이 이루어질 수 있게 된다.On the other hand, the residual tunnel portion can be divided into a plurality of sections in the excavation, that is, as shown in the accompanying Figures 4 and 5, the cross section of the remaining tunnel portion 52, 53 in the cross section around the pilot tunnel 51 Excavation can be made over.

도 4 및 도 5에서는 파일럿 터널 이외의 잔여터널부를 2단으로 구성하여 굴착하는 모습을 도시한 것이며, 이에 한정되지 아니하고 단면상 세 개 이상으로 나뉘어 굴착작업이 이루어질 수도 있을 것이다.4 and 5 illustrate the excavation by configuring the remaining tunnel portion other than the pilot tunnel in two stages, and the excavation operation may be performed by dividing three or more sections in cross section.

그리고, 본 발명에 따른 다단 굴착 방식의 터널 시공방법은 첨부된 도 6에서와 같이, 파일럿 터널의 굴착과 잔여터널부의 굴착이 병행하여 이루어지도록 하는 경우에 그 작업 효율을 좋게 하기 위하여, 전기공급부(81) 및 용수공급부(82)가 동시에 구비된 전기 및 용수 공급차량(80)을 이용하여 굴착작업을 위한 전기 및 용수 공급이 이루어지도록 함이 바람직하다.And, in the tunnel construction method of the multi-stage excavation method according to the present invention, in order to improve the work efficiency when the excavation of the pilot tunnel and the excavation of the remaining tunnel portion are performed in parallel, as shown in FIG. 81) It is preferable to use the electric and water supply vehicle 80 provided at the same time and the water supply unit 82 to supply electricity and water for the excavation work.

여기서, 상기 전기 및 용수 공급차량(80)은 전/후진이 모두 쉽게 이루어지도록 하여 터널 내 발파 등을 통한 굴착 작업 시 보다 효율적인 작업동작이 가능하도록 함이 바람직할 것이다.In this case, the electric and water supply vehicle 80 may be easily made both forward / backward to enable more efficient working operation when the excavation work through the blasting in the tunnel.

한편, 상기 그라우팅 보강유닛(100)은 상기 파일럿 터널(51) 이외의 부분인 잔여터널부(52,53) 굴착 시에 대단면 터널 내면으로 노출되어 삽입된 부분에 위치되는 그라우팅 보강유닛은 잔여터널부의 굴착 시에 함께 굴착되도록 함이 바람직하다.On the other hand, the grouting reinforcement unit 100 is exposed to the inner surface of the large tunnel tunnel when excavation of the remaining tunnel portions 52 and 53, which are parts other than the pilot tunnel 51, and the grouting reinforcement unit is located in the remaining tunnel. It is desirable to be excavated together at the excavation of the part.

특히, 대단면 터널의 내면의 경우 별도의 절삭 장치를 이용하여 내면이 매끄럽게 되도록 하는데, 터널 상부의 보강을 위해서 터널 상측에 위치된 그라우팅 보강유닛은 강한 스틸(steel) 재질로 이루어지도록 하면서도, 터널 내측에 위치된 보강유닛은 절삭 장치로 터널 내면의 절삭 가공 시 함께 절삭되는 재질로 이루어짐이 바람직하다.In particular, in the case of the inner surface of the large-section tunnel to make the inner surface smooth by using a separate cutting device, the grouting reinforcement unit located above the tunnel for the reinforcement of the upper part of the tunnel is made of a strong steel (steel), The reinforcing unit located in the cutting device is preferably made of a material that is cut together when cutting the inner surface of the tunnel.

이를 위해, 첨부된 도 7에 도시된 것처럼, 본 발명 파일럿 터널을적용한 다단 굴착 방식의 터널에 사용되는 그라우팅 보강유닛(100)은 지반에 천공된 다수개의 천공홀 각각에 삽입되며 길이방향을 따라서 다수개가 나뉘어진 형태로 연결되는 보강부재(10,20)를 포함하여 구성되고, 상기 보강부재(10,20)는 각각 소정의 길이를 가지는 봉형상으로 이루어지며, 스틸재질로 이루어진 스틸보강부재(10)와 GRP(Glass Reinforced Plastic)재질로 이루어진 GRP보강부재(20)가 사용됨이 바람직하다.To this end, as shown in Figure 7 attached, the grouting reinforcement unit 100 used in the tunnel of the multi-stage excavation method applying the pilot tunnel of the present invention is inserted into each of a plurality of drilling holes drilled in the ground and a plurality of along the longitudinal direction The dog is configured to include a reinforcing member (10, 20) connected in a divided form, the reinforcing member (10, 20) is made of a rod-shaped having a predetermined length, respectively, steel reinforcing member (10) ) And GRP (Glass Reinforced Plastic) material GRP reinforcing member 20 is preferably used.

즉, 도시된 바와 같이, 터널의 시공 시에는 시공되는 터널의 상측 지반으로부터 하부의 시공되는 터널이 위치된 쪽으로 GRP보강부재(20)가 위치되며, 그 이외의 부분은 스틸보강부재(10)가 다수개 연결되어 구성되는 보강유닛(100)이 사용된다,That is, as shown in the construction of the tunnel, the GRP reinforcing member 20 is located from the upper ground of the tunnel to be installed toward the lower construction of the tunnel, the rest of the steel reinforcing member 10 is Reinforcement unit 100 is used is configured by a plurality of connected,

이때, 상기 스틸보강부재(10)는 다수개가 연결된 형태를 이루며 각각의 스틸보강부재(10) 또는 상기 GRP보강부재(20)와 스틸보강부재(10)는 모두 압축연결모듈(110)에 의하여 연결되는 형태를 이룸이 바람직하다.At this time, the steel reinforcing member 10 has a form in which a plurality is connected, each steel reinforcing member 10 or the GRP reinforcing member 20 and the steel reinforcing member 10 are all connected by a compression connection module 110. It is preferable that the form becomes.

상기 압축연결모듈(110)은 상기 각 보강부재(10,20)를 연결하는 역할을 함과 동시에 그라우팅 보강유닛이 설치되기 위한 천공홀에 인장력이 작동하는 상태로 고정되도록 하는 역할을 수행한다.The compression connection module 110 serves to connect the respective reinforcing members (10, 20) and at the same time serves to be fixed in a state in which the tensile force is operating in the drilling hole for installing the grouting reinforcement unit.

이와 같이 형성된 그라우팅 보강유닛은, 첨부된 도 8에 도시된 바와 같이, 시공되는 터널의 상측으로부터 미리 설계된 터널 내측 부분에까지 다다르도록 상기 다수개의 천공홀(H)을 시공하고, 차후 시공되는 터널의 내측으로 본 발명 그라우팅 보강유닛의 일부 특히 GRP보강부재(20)가 위치되도록 천공작업이 수행된다.The grouting reinforcement unit formed as described above, as shown in the accompanying FIG. 8, constructs the plurality of drilling holes (H) to reach a pre-designed tunnel inner part from the upper side of the tunnel to be constructed, and the subsequent construction of the tunnel A drilling operation is performed such that some of the grout reinforcing units of the invention in particular the GRP reinforcing members 20 are positioned inwardly.

다음으로는, 상기 천공된 천공홀(H)에 있어서 터널이 위치된 쪽으로 즉, 상기 천공홀(H)의 선단부 일부를 레진 또는 급결그라우팅재(130)로 충진한다.Next, in the perforated hole H, the tunnel is located, that is, a part of the tip of the perforated hole H is filled with the resin or the quick grouting material 130.

여기서, 상기 레진 또는 급결그라우팅재(130)는 빠른 시간 안에 굳어지는 재질로 이루어지며, 충진되는 깊이는 상기 그라우팅 보강유닛(100)의 GRP보강부재(20)가 일부 삽입될 정도의 깊이로 충진된다.Here, the resin or quenching grouting material 130 is made of a material that is hardened in a quick time, the filling depth is filled to a depth enough to insert a part of the GRP reinforcing member 20 of the grouting reinforcement unit 100. .

다음으로는, 상기와 같이 레진 또는 급결그라우팅재가 충진된 천공홀(H) 내측으로 상기 그라우팅 보강유닛(100)을 선단부가 GRP 보강부재(20)가 되도록 한 후 삽입하는 단계를 수행한다.Next, a step of inserting the grout reinforcing unit 100 into the GRP reinforcing member 20 is inserted into the drilling hole H filled with the resin or the quick grouting material as described above.

그리고 나서, 상기 충진시킨 레진 또는 급결 그라우팅재가 굳어짐에 따라서 상기 그라우팅 보강유닛(100)의 선단부 즉 GRP보강부재(20)가 상기 천공홀 내측에 고정된 상태를 이루게 되면, 지면상측으로 일부 돌출되게 설치된 스틸보강부재(10)를 외부로 잡아당겨 상기 그라우팅 보강유닛(100) 전체에 걸쳐서 인장력이 작용하는 상태를 이루도록 한다.Then, when the filled resin or the fastening grouting material is hardened, the front end portion of the grout reinforcing unit 100, that is, the GRP reinforcing member 20 is fixed to the inside of the drilling hole, is installed to partially protrude to the ground side. Pull the steel reinforcing member 10 to the outside to achieve a state in which the tensile force acts throughout the grouting reinforcement unit (100).

그리고 나서, 상기 천공홀(H) 내부에는 최종적으로 일반 그라우팅재를 충진하고, 최외곽에 위치하는 스틸보강부재(10)를 고정 캡 또는 고정볼트 등을 이용하여 지면에 고정시키는 작업을 수행한다.Then, the perforated hole (H) is finally filled with a general grouting material, and performs the operation of fixing the steel reinforcing member 10 located at the outermost to the ground using a fixing cap or fixing bolts.

상기와 같은 과정을 통하여 그라우팅 보강유닛의 설치작업 및 그라우팅 보강작업까지 모두 완료되면, 상기 천공홀(H) 내부의 그라우팅 보강유닛(100)은 그 길이방향을 따라서는 각각의 압축연결모듈 내 구비되는 스프링이 위치된 구간별로 압축력이 작용하는 상태를 이루게 된다.When the installation and grouting reinforcement work of the grouting reinforcement unit is completed through the above process, the grouting reinforcement unit 100 inside the drilling hole H is provided in each compression connection module along its length direction. Compression force is applied to each section where the spring is located.

더불어, 상기 그라우팅 보강유닛(100) 주위로 그라우팅재가 경화된 경우 지반 또한 상하로 압축력이 작용하는 상태를 이루게 되므로, 시공되는 터널 상측이 상부와 하부가 서로 압축된 상태를 이루므로 안정된 구조를 유지하게 된다.In addition, when the grouting material is hardened around the grouting reinforcing unit 100, the ground also forms a state in which the compressive force acts up and down, and thus the upper and lower tunnels are constructed to maintain a stable structure. do.

이 경우, 굴착하고자 하는 잔여터널부가 위치된 부위로는 유리강화 합성섬유 재질인 GRP보강부재(20)가 위치되므로, 잔여터널부의 굴착은 물론 터널의 모양을 형성하고 터널 내면을 형성하기 위한 커팅 및 절삭 작업을 하는 경우 그 작업이 종전의 스틸재질의 보강부재의 경우보다 쉽게 이루어진다.In this case, since the GRP reinforcing member 20, which is made of glass-reinforced synthetic fiber, is positioned as a portion of the remaining tunnel portion to be excavated, cutting and forming to form the tunnel inner surface as well as the excavation of the remaining tunnel portion and In the case of the cutting operation, the operation is made easier than in the case of the conventional steel reinforcement member.

상기와 같이 구성된 본 발명 파일럿 터널을 적용한 다단 굴착 방식의 터널 굴착 방법의 효과에 대하여 설명하면 다음과 같다.Referring to the effect of the tunnel excavation method of the multi-stage excavation method applying the present invention pilot tunnel configured as described above are as follows.

도 2 내지 도 5에 도시된 바와 같이, 먼저 파일럿 터널(51)을 굴착한 후에 잔여터널부(52,53)를 다단에 걸쳐 굴착하게 된다.As shown in FIGS. 2 to 5, the pilot tunnel 51 is first excavated, and then the remaining tunnel portions 52 and 53 are excavated in multiple stages.

즉, 본 발명에 의하면 첨부된 도 9에 도시된 바와 같이, 파일럿 터널(51)을 먼저 굴착하게 되는데 전체 대단면 터널에 비하여 작은 단면적으로 파일럿 터널이 이루어지므로 그 굴착길이(l2)를 하루 작업 시 상당한 길이로 굴착이 가능하게 된다.That is, according to the present invention, as shown in the accompanying FIG. 9, the pilot tunnel 51 is first excavated, and since the pilot tunnel is made with a smaller cross section compared to the entire large cross-section tunnel, the excavation length l2 is used during the day's work. Excavation is possible with considerable length.

특히, 상기 파일럿 터널(51)의 굴착을 진행하면서 주위의 암반 즉, 차후에 굴착할 잔여터널부(52,53)를 굴착할 암반의 특징 즉 암반의 종류나 경도 등을 파악할 수 있게 된다.In particular, while the pilot tunnel 51 is being excavated, it is possible to grasp the characteristics of the rock to excavate the surrounding rock, that is, the remaining tunnel portions 52 and 53 to be excavated, that is, the type and hardness of the rock.

한편, 상기 파일럿 터널(51)과 잔여터널부(52,53)의 굴착 작업은 동시에 병행하여 가능한데, 파일럿 터널(51)을 선 굴착하고 잔여터널부의 굴착이 이루어지게 되므로 잔여터널부(52,53)의 굴착을 위한 발파 정도나 굴착 진행 정도의 조절이 가능하게 되며, 장비의 효율 면에서도 안정적 작업이 가능하게 되며 결국 한번에 대단면의 넓이로 터널을 굴착할 때보다 그 굴착 작업이 빨라지게 되므로 전체 시공기간을 단축할 수 있게 된다.On the other hand, the excavation work of the pilot tunnel 51 and the remaining tunnels 52 and 53 is possible in parallel, but the pilot tunnel 51 is pre-excavated and the remaining tunnels are excavated so that the remaining tunnels 52 and 53 are excavated. It is possible to control the degree of blasting or the progress of excavation for the excavation of the), and the stable operation is possible in terms of the efficiency of the equipment, and eventually the excavation work is faster than when the tunnel is excavated with a large area at one time Construction period can be shortened.

나아가, 파일럿 터널의 선 굴착 작업을 통한 암반의 종류 등을 미리 파악할 수 있게 되므로 그라우팅 보강유닛의 설치를 주위 암반에 따라서 적당한 개수 및 배열로 설치할 수 있게 되어 잔여터널부의 굴착 시 안정성을 확보하면서 그라우팅 보강유닛의 설치 개수 조절을 통한 경제성도 확보할 수 있게 된다.Furthermore, the type of rock can be identified in advance through the pre-drilling operation of the pilot tunnel, so that the installation of the grouting reinforcement unit can be installed in an appropriate number and arrangement according to the surrounding rock. Economics can be secured by adjusting the number of units installed.

또한, 본 발명에 의하면, 파일럿 터널을 발파방식에 의하여 굴착하게 되므로, 크기가 큰 암버럭이 발생이 가능하게 되므로, TMB 굴착 시 문제점이었던 암버럭의 재활용 문제를 해결할 수 있게 된다.In addition, according to the present invention, since the pilot tunnel is excavated by the blasting method, a large size of a female bag may be generated, and thus, a problem of recycling a female bag that is a problem when digging a TMB can be solved.

한편, 첨부된 도 10은 본 발명의 다른 실시예에 따른 다단 굴착 방식의 터널 시공방법에 있어서 대단면 터널 내 파일럿 터널이 시공되는 모습을 나타낸 것이다.Meanwhile, FIG. 10 is a view illustrating a pilot tunnel in a large cross-section tunnel in a tunnel construction method of a multistage excavation method according to another embodiment of the present invention.

즉, 본 발명의 다른 실시예에서와 같이, 상황에 중앙으로부터 편심된 위치에 파일럿 터널(61)을 굴착한 후에 잔여터널부를 굴착하여 전체 터널을 완성할 수 있다.That is, as in another embodiment of the present invention, the entire tunnel can be completed by excavating the remaining tunnel part after excavating the pilot tunnel 61 at a position eccentrically from the situation.

이와 같이 파일럿 터널을 시공되는 터널의 중앙으로부터 편심된 위치로 굴착하는 경우는 터널이 시공되는 지형의 단면상 위치하는 암반의 경도에 따라 유용하게 적용될 수 있다. 즉, 일부 경도가 강한 암반이 존재 시에는 이를 피하여 파일럿 터널을 굴착하고 상대적으로 내부 작업공간 및 굴착범위를 넓게 확보한 상태에서 다양한 발파 공법 등을 이용하여 잔여터널부를 굴착할 수 있게 되므로 작업이 편해지고 되며 굴착작업 속도 또한 최대한으로 유지시킬 수 있는 효과를 가져올 수 있게 된다.As such, when the pilot tunnel is excavated to the eccentric position from the center of the tunnel to be constructed, it can be usefully applied depending on the hardness of the rock located on the cross section of the terrain in which the tunnel is constructed. In other words, when there is some hard rock, the pilot tunnel is avoided and the remaining tunnel part can be excavated using various blasting methods while securing a wide internal working space and excavation range. And the excavation work will also bring the effect that can be kept to the maximum.

본 발명의 다른 실시예의 경우에도 그 외의 그라우팅 보강유닛의 설치 및 잔여터널부의 굴착은 상술한 실시예와 같으므로 그 부분에 대한 자세한 설명은 생략한다.In the case of another embodiment of the present invention, the installation of the other grouting reinforcement unit and the excavation of the remaining tunnel portion are the same as the above-described embodiment, and thus a detailed description thereof will be omitted.

이상과 같이 본 발명에 따른 바람직한 실시예를 살펴보았으며, 앞서 설명된 실시예 이외에도 본 발명이 그 취지나 범주에서 벗어남이 없이 다른 특정 형태로 구체화 될 수 있다는 사실은 해당 기술에 통상의 지식을 가진 이들에게는 자명한 것이다. 그러므로, 상술된 실시예는 제한적인 것이 아니라 예시적인 것으로 여겨져야 하고, 이에 따라 본 발명은 상술한 설명에 한정되지 않고 첨부된 청구항의 범주 및 그 동등 범위 내에서 변경될 수도 있다.As described above, the preferred embodiments of the present invention have been described, and the fact that the present invention can be embodied in other specific forms in addition to the above-described embodiments without departing from the spirit or scope thereof has ordinary skill in the art. It is obvious to them. Therefore, the above-described embodiments should be regarded as illustrative rather than restrictive, and thus, the present invention is not limited to the above description and may be modified within the scope of the appended claims and their equivalents.

51,61: 파일럿 터널 52,53: 잔여터널부
80: 전기 및 용수 공급차량 81: 전기공급부
82: 용수공급부 100: 그라우팅 보강유닛
51,61: pilot tunnel 52,53: remaining tunnel part
80: electricity and water supply vehicle 81: electricity supply
82: water supply unit 100: grouting reinforcement unit

Claims (7)

시공될 대단면 터널의 길이방향을 따라서 발파방식으로 파일럿 터널을 다수 회에 걸쳐 굴착하는 단계; 및
상기 파일럿 터널을 일부 길이 굴착한 후에 굴착작업이 시행되며, 상기 파일럿 터널 이외의 대단면에 이르는 잔여터널부를 단면상 적어도 1단면 이상으로 나누어 터널의 길이방향을 따라서 굴착하는 단계;
를 포함하여 구성되는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공방법.
Digging the pilot tunnel a plurality of times in a blasting manner along the longitudinal direction of the large-section tunnel to be constructed; And
Excavation is performed after the pilot tunnel is partially excavated, and the excavation along the longitudinal direction of the tunnel is divided into at least one cross section of the remaining tunnel portion reaching a large cross section other than the pilot tunnel;
Tunnel construction method of a multistage excavation method applying a pilot tunnel configured to include a.
제1항에 있어서,
상기 파일럿 터널의 굴착과 상기 잔여터널부의 굴착은 병행하여 진행되는 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공방법.
The method of claim 1,
Excavation of the pilot tunnel and the excavation of the remaining tunnel portion is a tunnel construction method of the multi-stage excavation method to which the pilot tunnel is applied.
제1항에 있어서,
상기 파일럿 터널의 굴착단계마다,
상기 파일럿 터널의 상부를 보강하는 단계를 더 포함하는 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공 방법.
The method of claim 1,
Every excavation step of the pilot tunnel,
And a step of reinforcing the upper part of the pilot tunnel.
제3항에 있어서,
상기 파일럿 터널의 상부를 보강하는 단계는,
상기 파일럿 터널의 상부에 천공홀을 형성하는 단계;
상기 형성된 천공홀에 그라우팅 보강유닛을 설치하는 단계; 및
상기 그라우팅 보강유닛이 설치된 천공홀에 그라우팅 시공을 하는 단계;
를 포함하여 구성되는 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공 방법.
The method of claim 3,
Reinforcing the upper portion of the pilot tunnel,
Forming a hole in the upper part of the pilot tunnel;
Installing a grouting reinforcement unit in the formed hole; And
Grouting construction in the drilling hole in which the grouting reinforcement unit is installed;
Tunnel construction method of a multistage excavation method applying a pilot tunnel, characterized in that configured to include.
제4항에 있어서,
상기 천공홀에 설치되는 그라우팅 보강유닛은,
스틸보강부재와 GRP보강부재가 연결된 형태로 이루어지며,
상기 GRP보강부재가 상기 대단면 터널의 하측으로 위치되도록 설치되는 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공 방법.
The method of claim 4, wherein
The grouting reinforcement unit installed in the drilling hole,
The steel reinforcing member and the GRP reinforcing member is formed in the form,
The GRP reinforcing member is a tunnel construction method of the multi-stage excavation method applying a pilot tunnel, characterized in that the installation is located so as to be located below the large cross-section tunnel.
제1항에 있어서,
상기 파일럿 터널의 굴착위치는,
시공될 대단면 터널의 중앙으로부터 편심된 위치로 굴착되는 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공 방법.
The method of claim 1,
Excavation position of the pilot tunnel,
A multi-stage excavation tunnel construction method using a pilot tunnel, characterized in that excavation to the eccentric position from the center of the large-section tunnel to be constructed.
제1항에 있어서,
상기 잔여터널부의 굴착을 2회 이상으로 나누어 굴착하는 경우에는, 각각의 잔여터널부의 굴착이 병행하여 이루어지도록 한 것을 특징으로 하는 파일럿 터널을 적용한 다단 굴착 방식의 터널 시공 방법.
The method of claim 1,
When the excavation of the residual tunnel by dividing the excavation in two or more times, excavation of each of the remaining tunnels is performed in parallel.
KR1020100066247A 2010-07-09 2010-07-09 Multi-Step Tunnel Constructing Method Using Pilot Tunnel KR101247702B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100066247A KR101247702B1 (en) 2010-07-09 2010-07-09 Multi-Step Tunnel Constructing Method Using Pilot Tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100066247A KR101247702B1 (en) 2010-07-09 2010-07-09 Multi-Step Tunnel Constructing Method Using Pilot Tunnel

Publications (2)

Publication Number Publication Date
KR20120005680A true KR20120005680A (en) 2012-01-17
KR101247702B1 KR101247702B1 (en) 2013-03-28

Family

ID=45611677

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100066247A KR101247702B1 (en) 2010-07-09 2010-07-09 Multi-Step Tunnel Constructing Method Using Pilot Tunnel

Country Status (1)

Country Link
KR (1) KR101247702B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174430A (en) * 2013-04-10 2013-06-26 中国水利水电第十四工程局有限公司 Shallow-buried large-span water conveying tunnel three-stage five-step digging method
CN103244133A (en) * 2013-05-17 2013-08-14 贵州省公路工程集团有限公司 Coal measure strata tunnel milling digging and blasting combined construction method
KR20160149177A (en) * 2016-12-07 2016-12-27 서동현 Construction method of internal pre-support tunnel for complete blocking water of all directions of the tunnel
CN109236328A (en) * 2018-10-30 2019-01-18 广东省交通规划设计研究院股份有限公司 The reinforcement means of shallow embedding mountain tunnel suitable for rich water soft layer
CN112610224A (en) * 2021-01-07 2021-04-06 云南路桥股份有限公司 Steep wall tunnel core hole digging construction process
CN114320319A (en) * 2021-11-09 2022-04-12 珠海华昕开发建设有限公司 Construction method for expanding excavation from extremely-small section to extremely-large section of tunnel
US11913338B2 (en) * 2021-01-15 2024-02-27 Fuzhou University Support method of preset internal cable for in-situ tunnel expansion project

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101690003B1 (en) * 2014-11-27 2016-12-28 (주)케이씨엠티 Open rock bolt construction method
KR101612527B1 (en) 2015-10-01 2016-04-14 함정아 Construction method for tunneling
KR101671123B1 (en) * 2015-11-25 2016-10-31 서민규 Tunnel construction method by using pre-support and post-support, and suitable device therefor
CN106049418A (en) * 2016-06-22 2016-10-26 中铁二局集团有限公司 Combined grouting reinforcement method for tunnel surface in shallow buried traversing faultage
CN106351671B (en) * 2016-10-17 2019-02-15 中铁五局集团第五工程有限责任公司 A kind of weak surrounding rock large section tunnel excavation supporting structure and its construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3465202B2 (en) * 1994-12-16 2003-11-10 清水建設株式会社 Blasting method
KR20020024912A (en) * 2000-09-27 2002-04-03 고순방 Method of construct a tunnel
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
JP5203048B2 (en) * 2008-06-02 2013-06-05 株式会社カテックス Rock bolt structure and its tensile strength test method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174430A (en) * 2013-04-10 2013-06-26 中国水利水电第十四工程局有限公司 Shallow-buried large-span water conveying tunnel three-stage five-step digging method
CN103244133A (en) * 2013-05-17 2013-08-14 贵州省公路工程集团有限公司 Coal measure strata tunnel milling digging and blasting combined construction method
CN103244133B (en) * 2013-05-17 2016-01-20 贵州省公路工程集团有限公司 The milling of coal measure strata tunnel is dug and is combined construction with explosion
KR20160149177A (en) * 2016-12-07 2016-12-27 서동현 Construction method of internal pre-support tunnel for complete blocking water of all directions of the tunnel
CN109236328A (en) * 2018-10-30 2019-01-18 广东省交通规划设计研究院股份有限公司 The reinforcement means of shallow embedding mountain tunnel suitable for rich water soft layer
CN112610224A (en) * 2021-01-07 2021-04-06 云南路桥股份有限公司 Steep wall tunnel core hole digging construction process
CN112610224B (en) * 2021-01-07 2023-04-25 云南路桥股份有限公司 Steep wall tunnel core hole construction process
US11913338B2 (en) * 2021-01-15 2024-02-27 Fuzhou University Support method of preset internal cable for in-situ tunnel expansion project
CN114320319A (en) * 2021-11-09 2022-04-12 珠海华昕开发建设有限公司 Construction method for expanding excavation from extremely-small section to extremely-large section of tunnel
CN114320319B (en) * 2021-11-09 2024-05-03 珠海华昕开发建设有限公司 Construction method for expanding tunnel from minimum section to extra-large section

Also Published As

Publication number Publication date
KR101247702B1 (en) 2013-03-28

Similar Documents

Publication Publication Date Title
KR101247702B1 (en) Multi-Step Tunnel Constructing Method Using Pilot Tunnel
CN109339797B (en) Extremely-small-clear-distance tunnel exit shock absorption construction method
KR100847352B1 (en) Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
JP4958035B2 (en) Shield roof construction method
KR101827341B1 (en) Rock Excavation Method in Tunnel
KR101391218B1 (en) Construction methods of close-twin tunnel by blast shock-controlling and rebar reinforced shotcrete
CN105781572B (en) Deeps mines hard-rock tunnel stress adsorbed layer structure method for protecting support
KR101054380B1 (en) Tunnel Excavation Method
CN102562097A (en) Three-dimensional asymmetrical supporting system
KR102211018B1 (en) Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
KR101657143B1 (en) Non-vibration and rock splitting type constructing tunnel method for shortening of the construction time
KR101233794B1 (en) Tunnel reinforcing method by multi-forepoling
KR100844104B1 (en) Unit for supporting center of double tunnel
CN104775823B (en) Double-line mining method subway tunnel inclined well entering main tunnel structure and process thereof
KR101974183B1 (en) Construction methods of approaching dual tunnel
CN116658178B (en) Ultra-small clear distance tunnel subsection differential blasting vibration reduction and isolation construction method
CN109184752A (en) A kind of coal mine supporting construction and its method for protecting support for passing through old kiln goaf
KR101079075B1 (en) Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same
JP4730595B2 (en) Construction method of underground cavity
KR20190011887A (en) Method for digging huge tunnel using tnnnel boring mechine
KR101669669B1 (en) Construction methods of approaching dual tunnel
CN109386289B (en) Blasting, hole sealing and grouting integrated construction method
CN103046765A (en) Construction process for continued application of air-raid shelter
KR101511223B1 (en) Open-cut blasting using 6 freeface
KR100926501B1 (en) Roof and shield tunneling construction method (rsm) and tunnel structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160321

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170321

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee