KR101690003B1 - Open rock bolt construction method - Google Patents

Open rock bolt construction method Download PDF

Info

Publication number
KR101690003B1
KR101690003B1 KR1020140167169A KR20140167169A KR101690003B1 KR 101690003 B1 KR101690003 B1 KR 101690003B1 KR 1020140167169 A KR1020140167169 A KR 1020140167169A KR 20140167169 A KR20140167169 A KR 20140167169A KR 101690003 B1 KR101690003 B1 KR 101690003B1
Authority
KR
South Korea
Prior art keywords
bolt
rock
tunnel
shotcrete
locking bolt
Prior art date
Application number
KR1020140167169A
Other languages
Korean (ko)
Other versions
KR20160064279A (en
Inventor
김준영
Original Assignee
(주)케이씨엠티
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)케이씨엠티 filed Critical (주)케이씨엠티
Priority to KR1020140167169A priority Critical patent/KR101690003B1/en
Publication of KR20160064279A publication Critical patent/KR20160064279A/en
Application granted granted Critical
Publication of KR101690003B1 publication Critical patent/KR101690003B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 노출식 락볼트 시공방법에 관한 것으로, 더욱 상세하게는 락볼트캡을 사용하여 락볼트를 용이하게 식별할 수 있도록 하여 감리시 시간적 제약 없이 육안으로 수량을 파악하고 확인할 수 있는 노출식 락볼트 시공방법에 관한 것이다.
상기한 기술적 과제를 해결하기 위해 본 발명은 기초터널 형성에 따른 터널을 구축하기 위한 노출식 락볼트 시공방법에 있어서, (a) 기초터널의 암반 표면에 제 1 숏크리트(shotcrete)를 타설하는 제 1 숏크리트 형성단계; (b) 천공장치를 이용하여 암반에 설계된 수만큼 락볼트가 삽입될 암반공을 천공하는 천공단계; (c) 천공된 암반공에 락볼트의 선단측을 진입시켜 암반공의 끝지점까지 안내하여 락볼트를 삽입하되 락볼트의 후단측이 돌출되게 하는 락볼트삽입단계; (d) 락볼트가 삽입된 상태에서 암반공의 초입에 지압플레이트를 설치하고 너트를 체결하여 고정하는 락볼트고정단계; (e) 제 2 숏크리트(shotcrete) 타설로 도포층을 형성하고 상기 도포층 상부로 락볼트 후단측의 종단부가 노출되게 하는 제 2 숏크리트 형성단계; 및 (f) 락볼트의 후단측 종단부에 락볼트캡을 체결하는 락볼트캡체결단계;를 포함하여 구비되는 것을 특징으로 하는 노출식 락볼트 시공방법을 제공한다.
The present invention relates to a method of constructing an exposed rock bolt, and more particularly, to a rock bolt construction method capable of easily identifying a rock bolt using a rock bolt cap, And a bolt construction method.
According to an aspect of the present invention, there is provided an exposed rock bolt construction method for constructing a tunnel according to the formation of a base tunnel, the tunnel bolt construction method comprising the steps of: (a) installing a first shotcrete on a rock surface of a foundation tunnel; A shotcrete forming step; (b) a perforating step of perforating a rocking bolt to be inserted into the rock bolts as many as the designed number of rock bolts by using a punching device; (c) a locking bolt inserting step of inserting the locking bolt into the perforated arm anticlock by guiding the distal end side of the locking bolt to the end point of the arm anticlocking so that the rear end side of the locking bolt protrudes; (d) a lock bolt fixing step in which an acupressure plate is installed at the beginning of arm anti-hole while the lock bolt is inserted, and the nut is fastened and fixed; (e) a second shotcrete forming step of forming a coating layer by a second shotcrete pouring and exposing a rear end of the rock bolt to an upper portion of the coating layer; And (f) a locking bolt cap fastening step of fastening the locking bolt cap to the rear end of the locking bolt.

Description

노출식 락볼트 시공방법{Open rock bolt construction method}Open rock bolt construction method.

본 발명은 노출식 락볼트 시공방법에 관한 것으로, 더욱 상세하게는 락볼트캡을 사용하여 락볼트 설치 위치를 용이하게 식별할 수 있도록 하여 감리시 시간적 제약을 최소로 하고 육안으로 수량을 파악하며 확인할 수 있는 노출식 락볼트 시공방법에 관한 것이다.The present invention relates to a method of constructing an exposed rock bolt, and more particularly, to a rock bolt installation method capable of easily identifying a rock bolt installation position, To a method of constructing an exposed rock bolt.

일반적으로 터널 공사 시에 암반을 굴착한 후에는 암반의 균열, 절리 등의 변형이 발생되므로 역학적인 불연속면을 갖는 암반을 일종의 봉합 구조로 연결하여 변형을 조기에 억지시킴으로써 암반을 안정시켜야 하며, 이와 같이 터널의 안정성을 유지하는 방법의 일환으로 터널의 암반에 락볼트를 설치하는 것이다.Generally, after excavation of a rock during tunnel construction, deformation such as cracks and joints of rocks occurs. Therefore, it is necessary to stabilize the rock by connecting rocks with mechanical discontinuities to a kind of sealing structure and suppressing deformation early. In order to maintain the stability of the tunnel, rock bolts are installed on the rocks of the tunnels.

또한 건설공사 절개면이나 터널 굴착면 등은 시공 전후로 항상 붕괴의 위험을 가지고 있다. 따라서 건설공사 절개면이나 터널 굴착면 등의 붕괴를 방지하기 위해서는 락볼트(또는 락앵커) 등의 시공이 필수적이다.In addition, there is always a risk of collapse before and after construction, such as construction site or tunnel excavation site. Therefore, it is necessary to construct rock bolts (or rock anchors) in order to prevent collapse of construction cut surfaces and tunnel excavation surfaces.

한편, 한국특허등록번호 제10-1383277호(등록일자 2014.04.02) 발명의 명칭 '락볼트 설치장치 및 이를 이용한 락볼트 설치방법', 한국특허등록번호 제10-1196889호(등록일자 2012.10.26), 발명의 명칭 '락볼트 및 그 시공방법' 등 여러 가지 락볼트 시공 방법이 개시되어 있다.Korean Patent Registration No. 10-1383277 (Registration date 2014.04.02) entitled " Lock bolt installation device and method of installing a lock bolt using the same, " Korean Patent Registration No. 10-1196889 ), The name of the invention 'Rock bolt and its construction method', and the like.

그런데, 2014년 10월 9일자(목) 시민일보 기사에 따르면 다음과 같다.By the way, according to the Citizen Daily report on Thursday, October 9, 2014, it is as follows.

"한국도로공사가 발주한 고속국도 터널공사 과정에서 암석이나 토사 붕괴 방지 역할을 하는 핵심부품인 락볼트를 설계수량보다 적게 시공하고도 공사대금을 허위 청구한 건설사 현장소장들이 무더기로 적발됐다."During the construction of the highway tunnel under the Korea Highway Corporation, even the construction of a rock bolt, which is a core part that prevents the collapse of rocks and earth slags, was carried out, but a lot of construction site engineers who were charged with the construction charge were found.

서울중앙지검 특수3부(부장검사 문홍성)는 락볼트 공사대금을 허위로 과다 청구한 혐의(특정경제범죄가중처벌법상 사기)로 선산토건 현장소장 이 모씨(56·구속기소) 등 시공사·하도급 업체 현장소장 3명을 구속 기소하고 계룡건설산업 현장소장 신 모씨(55) 등 6명을 불구속 기소했다고 9일 밝혔다.The Seoul Central District Prosecutor's Office, special division 3 (head supervisor Moon Hong-sung), is suspected of fraudulently charging the price of rock bolt construction (a fraud in the specific economic crime punishment law), construction worker, subcontractor (55), who was arrested on suspicion of arresting three colleagues at the site, and the director of the Kyeryong Construction Industrial Site.

또 락볼트 시공 과정에서 허위 거래명세표, 세금계산서 등을 도로공사에 제출한 혐의(사문서위·변조 등)로 동부건설 현장소장 김 모씨(48)와 대우건설 현장소장 박 모씨(50)를 포함, 대기업 시공업체 현장소장 등 7명을 불구속 기소했다.In addition, Kim Moo (48), director of the Dongbu construction site, and Park Moo (50), the head of Daewoo construction site, including the allegation of submitting a false transaction statement and tax bill to the road construction during rock bolt construction, Seven of them were indicted without charge.

검찰에 따르면 이들은 영동-옥천 1공구, 주문진-속초 5공구, 담양-성산 6공구, 동홍천-양양 6공구, 동홍천-양양 11공구, 동홍천-양양 14공구, 동홍천-양양 16공구, 상주-영덕 5공구 등 총 8개 공구 터널공사에서 락볼트를 부실 시공한 혐의다.According to the prosecutors, they were divided into two groups: Yeongdong-Okcheon 1, Jungjin-Sokcho 5, Damyang-Seongsan 6, Donghocheon-Yangyang 6, Donghocheon-Yangyang 11, Donghocheon-Yangyang 14, Sangju-Young-duk 5, etc. The construction of the rock bolt is under construction.

특히 영동-옥천 1공구의 경우 락볼트의 부실시공 등으로 인해 40억원이 넘는 혈세가 낭비됐다.In particular, in Yeongdong-Okcheon 1, waste of more than 4 billion won was wasted due to the construction of rock bolts.

검찰 수사결과 선산토건 현장소장 이씨와 계산건설산업 현장소장 신씨는 2011년 7월부터 2012년 2월까지 락볼트 설계수량 1만7310개 중 4046개를 쓰지 않고 공사대금을 과다 청구하는 수법으로 모두 8억5935만여원의 부당이득을 챙긴 혐의다.As a result of the prosecution investigation, Shin, a director of the Sunsan Construction Site, Lee Shin-hyun, the head of the Calculation & Construction Industry Division, said that from July 2011 to February 2012, 4046 out of 17,710 rock bolts were designed. He is accused of taking unfair advantage of 59.35 million won.

구산토건 현장소장 양 모씨(47·구속기소)는 주문진-속초 5공구의 락볼트 설계수량 1만8350개 중 1만2420개를 시공하지 않고 2009년 10월부터 2011년 1월까지 총 8억3681만여원의 기성금을 허위 청구한 혐의를 받고 있다.Yang Moo (47, arresting prosecutor), the head of the Kusan construction site, did not install 12,420 out of 18,350 rock bolts designed for Jumunjin-Sokcho 5, but from October 2009 to January 2011, He is accused of falsely claiming a monetary contribution of 10,000 won.

동부건설이 시공을 맡은 동홍천-양양 11공구 구간에서도 기성금 5억8358만여원이 과다 지급됐다. 이 구간 현장소장 정 모씨(49·불구속 기소)는 지난해 2월부터 올해 3월까지 설계도면상 투입해야하는 락볼트 2만9190개 중 8390개를 시공하지 않은 것으로 파악됐다.Dongbu Engineering & Construction Co., Ltd. has overpaid 583.88 million won for the construction of the Dongcheng-Yangyang 11 section. Chung Moo, 49, a prosecutor at the site, said that he did not construct 8390 out of the 29,909 rock bolts to be used in the design phase from February last year until March of last year.

같은 구간의 현장소장 김 모씨(48·불구속기소)와 공무과장 고 모씨(43·불구속기소)는 락볼트 사용대금을 과다 청구한 사실이 적발될 것을 우려해 거래관련 증빙서류를 위·변조했다.Kim Mo (48, detention charge) and Ko Moo (43, detention charge) in the same section falsified the documents related to the transaction because of the fact that they charged the excessive use of rock bolts.

삼성물산의 품질관리팀 대리 이 모씨(36·불구속기소)도 담양-성산 6공구에서 주요자재검사 및 수불부 양식에 반입수량 등을 허위 기재하고 검측감리원 서명까지 도용해 도로공사에 제출했고, 대우건설 동홍천-양양 6공구 현장소장 박 모씨(50·불구속기소)도 주요자재검사(수불)대장 양식 등을 위조한 자료를 도로공사에 낸 사실이 검찰 수사에서 드러났다.The quality control team of Samsung C & T's quality management team delegated false information to the main material inspections and wage forms at Damyang-Seongsan 6, Daegu Construction & Engineering Co., The prosecutor's investigation revealed that Park Moo (50, non-detention indictment), the head of the Hongcheon-Yangyang 6th Division, also made materials for the main material inspections.

검찰은 이처럼 과다 청구한 공구의 기성금이 총 187억원 상당으로 락볼트 미시공 비율은 평균 27%에 달했다고 보고 있다.The prosecution believes that the overpayment of the overcharged tools amounted to 18.7 billion won, which means that the average rate of non-locking bolts reached 27%.

검찰은 한국도로공사에 터널공사 락볼트 부실시공과 관련한 기성금 과다 청구액과 락볼트 미시공 현황 등을 송부해 터널의 정밀안전진단 및 향후 관리감독 강화 필요성을 통보했다.The prosecution notified the Korea Highway Corporation of the necessity of enhancing the precise safety diagnosis of the tunnel and the future supervision of the tunnel by sending the excess amount of the overcharge for the rock bolt construction of the tunnel construction and the unfinished construction of the rock bolt.

이와 함께 락볼트 부실시공으로 과다 청구된 기성금 187억원에 대해서도 한국도로공사와 협조해 전액 환수조치할 예정이다.In addition, it plans to cooperate with Korea Highway Corporation in return for a total of 18.7 billion won of overcharge for construction of rock bolts.

한편 이 같은 터널공사의 락볼트 부실시공 발생 원인으로 발주처의 관리·감독 소홀, 터널공사 업체들의 현장적자 보전을 위한 관행적 기성금 과다 청구 등을 지적했다.On the other hand, it pointed out that the construction of the rock bolts in the tunnel construction is neglected due to the lack of management and supervision of the contractor, and the excessive burdens of customary funds for the maintenance of the deficit of the tunnel construction companies.

한국도로공사 현장감독 인력과 도로공사와 감리용역 계약을 체결한 검측감리원은 락볼트 등 주요자재의 반입 수량과 품질 등을 확인하지 않고 거래명세표 등 송장만 확인하는 등 실제 반입 물량을 제대로 검수하지 않은 것으로 검찰은 확인했다.The inspection supervisor who concluded the construction supervision contract with the road construction supervisor of the Korea Highway Corporation did not confirm the quantity of actual materials such as rock bolts and quality, The prosecution confirmed.

또 락볼트 시공 후 특수 콘크리트인 숏크리트를 타설하면 터널 안쪽에 묻힌 락볼트의 실제 시공 여부를 육안으로 확인하기 쉽지 않고, 24시간 진행되는 터널공사의 특성상 현장감독인력 부족 등이 락볼트 시공에 대한 관리·감독으로 이어진다는 게 검찰의 설명이다."It is not easy to visually confirm the actual construction of the rock bolts buried in the inside of the tunnels when the concrete bolts are installed after the rock bolts are installed. Due to the nature of the tunnel works conducted 24 hours, It is the prosecutor's explanation that it leads to the director. "

또한, 2014년 10월 15일자 경북일보 기사에 따르면 다음과 같다.In addition, according to the article of Kyungbuk Ilbo on October 15, 2014, it is as follows.

"한국도로공사가 발주한 고속도로 터널공사과정에서 터널 암반이 무너지는 것을 방지하는 '락볼트' 부실시공이 전국 전체 121개 터널의 64%인 78개 터널에서 시공된 것으로 드러났다."It has been revealed that the construction of the 'Rock bolt', which prevents tunnel collapse during the highway tunnel construction project ordered by KEC, was carried out in 78 tunnels, 64% of 121 tunnels nationwide.

터널 보강자재인 락볼트를 설계수량보다 적게 시공한 것이다. 이 중 롯데건설과 두산건설, SK건설 등이 시공하고 있는 포항~울산 고속도로 터널 3개 공구 등 경북지역에도 11개구간, 25개 터널에서 부실시공된 것으로 확인됐다.The rock bolt that reinforced the tunnel was constructed less than the design quantity. Of these, it was confirmed that construction was carried out in 11 tunnels and 25 tunnels in Gyeongbuk area including Lotte Construction, Doosan E & C, SK Engineering & Construction, and 3 Pohang-Ulsan Expressway Tunnels.

락볼트는 터널 굴착과정에서 암반이 무너지는 것을 방지하기 위해 암반에 구멍을 뚫어 삽입하는 지반 보강자재다.Rock bolts are ground reinforcement materials that are drilled into rock to prevent rocks from collapsing during tunnel excavation.

경북지역 11개 부실시공 구간은 상주~안동 5공구(안사2터널·안평1터널), 안동~영덕 18공구(영덕터널), 함양~성산 14공구(고령2~4터널), 안동~영덕 16공구(지품6~10터널), 상주~영덕 11공구(길안2~3터널), 안동~영덕 15공구(지품1~3터널), 안동~영덕 13공구(파천1~2터널), 상주~안동 8공구(단촌2~4터널)이며, 특히 포항~울산 4공구(외동터널), 포항~울산 7공구(양남터널), 포항~울산 9공구(용두1, 2터널)로 조사됐다.(Yeongdeok Tunnel), Yangyang ~ Sungsan 14th tunnel (Goryeong 2nd ~ 4th Tunnel), Andong ~ Yeongdeok 16th tunnel (Anseong 2 tunnel, Anpyeong 1 tunnel) (Tunnels 6 ~ 10 Tunnels), Sangju ~ Youngdeok 11 Tunnels (Gilan 2 ~ 3 Tunnels), Andong ~ Youngdeok 15 Tunnels (Pohang-Ulsan), Pohang-Ulsan (Pohang-Ulsan), and Pohang-Ulsan (Pohang-Ulsan) tunnel (1 and 2 tunnels).

포항~울산 구간 시공사는 롯데건설, 두산건설, SK건설 등으로 확인됐다.Lotte E & C, Doosan E & C, SK E & C and other construction companies in the Pohang-Ulsan area were confirmed.

락볼트 부실시공업체는 고속도로 터널 암반 '락볼트'를 부실시공한 뒤 정상처럼 대금을 청구해 187억여원을 빼돌려 현장 관계자들이 무더기로 검찰에 기소됐다.Rock bolt trouble maker charged rock bolt of highway tunnel rock bolt, and demanded price like 187 million won, and prosecutor was indicted by a lot of field related people.

이같은 사실은 검찰이 한국도로공사 의뢰로 2010년 이후 착공한 76개 공구, 121개 터널에 대한 전수조사를 시행하는 과정에서 드러났다.The investigation was conducted during a survey conducted by the prosecution on a survey of 76 tunnels and 121 tunnels commissioned by the Korea Highway Corporation in 2010.

락볼트는 터널 안쪽에 묻혀 부실시공 여부를 눈으로 확인하기는 어려운 점을 이용해 실제 설계수량보다 적은 수를 사용한 뒤 설계대로 사용한 것처럼 속여 건설사들이 차액을 챙기는 것으로 드러났다.Rock bolts are buried inside the tunnel and it is difficult to confirm whether the construction is bad or not, so it is proved that the contractors cheat the contractors as they used the design as few as the actual design quantity.

하지만 락볼트의 부실 축소 시공은 터널의 안전에 심각한 결함이 있을 수 있는 것이어서 부실이 드러난 터널에 대한 철저한 안전조치가 있어야 할 것으로 지적되고 있다.However, it is pointed out that the construction of the rock bolt can be seriously flawed in the safety of the tunnel.

한편 검찰은 도로공사에 터널 정밀안전진단을 의뢰하는 한편 건설사들이 과다 청구한 공사비를 전액 환수토록 할 계획이다."Meanwhile, the prosecution will ask the road construction for a precise safety diagnosis of the tunnel, while the construction companies plan to return the overcharged construction expenses to the full amount. "

상기와 같이 락볼트 시공방법에 있어서, 현재에도 여전히 부실시공 가능성이 내재되어 있으며 그 문제점을 분석하면 다음과 같다.In the rock bolt construction method as described above, there is still a possibility of insufficient construction, and the problem is analyzed as follows.

첫째 락볼트 시공수량을 파악하는 데 어려움이 있으며, 터널 내 24시간 작업으로 관리 감독을 위해 야간에도 상주하여 감리하여야 하는 어려움이 있다. 이는 락볼트 시공 완료 후 2차 숏크리트(shotcrete) 타설로 락볼트가 매립되어 그 수량을 파악하기 어렵기 때문이다.First, there is a difficulty in understanding the quantity of construction of the rock bolt, and there is a difficulty in staying in the nighttime to supervise and supervise with 24 hours work in the tunnel. This is because it is difficult to grasp the quantity of rock bolts buried by the second shotcrete installation after the completion of the rock bolt construction.

둘째 터널 사이클 타임을 확보하기 어렵기 때문에 즉, 2회/일 사이클 타임 유지를 위해 예기치 못한 작업대기 발생시 락볼트 시공 일부가 포기하는 경우가 발생하며 2차 숏크리트(shotcrete) 타설 후에는 매립된 락볼트 수량을 확인하는 데 어려움이 있기 때문이다.Second, it is difficult to secure the tunnel cycle time. In other words, in case of an unexpected waiting time for maintenance of 2 times / day cycle time, a portion of the rock bolt construction may be abandoned. After the second shotcrete pouring, It is difficult to confirm the quantity.

셋째 근로자의 부정행위가 있을 수 있기 때문이다. 즉, 가장 보편화 된 스틸 락볼트는 무거운 자중으로 시공성이 떨어지며 근로자의 피로도가 높아 야간 작업시 불량시공을 발생시킬 수 있는 여지가 있고 스틸 락볼트를 고철로 처리하여 개인적으로 이윤을 추구하는 경우가 발생하기 때문이다.Thirdly, there may be cheating of workers. In other words, the most commonly used steel lock bolts have poor workability due to heavy weight, and there is a possibility of causing bad construction during night work due to high fatigue of workers, and there is a case where the steel lock bolt is treated with scrap iron to pursue personal profit .

한국특허등록번호 제10-1383277호(등록일자 2014.04.02), 발명의 명칭 '락볼트 설치장치 및 이를 이용한 락볼트 설치방법'Korean Patent Registration No. 10-1383277 (Registered on Apr. 20, 2014), entitled " Lock bolt installation device and method of installing lock bolt using the same " 한국특허등록번호 제10-1196889호(등록일자 2012.10.26), 발명의 명칭 '락볼트 및 그 시공방법'Korean Patent Registration No. 10-1196889 (registered on October 26, 2012), the name of the invention 'Rock bolt and its construction method'

본 발명은 상기한 문제점을 해결하기 위하여 안출된 것으로, 락볼트를 설치한 후 숏크리트(shotcrete) 타설을 하여도 락볼트 상단부가 상기 숏크리트(shotcrete) 도포층 위로 노출되게 하고 락볼트가 설치되어 있는지 확인할 수 있는 락볼트캡을 부착하여 용이하게 볼 수 있도록 하는 노출식 락볼트 시공방법을 제공하는 것을 목적으로 한다.SUMMARY OF THE INVENTION The present invention has been conceived to solve the above-described problems, and it is an object of the present invention to provide a method of mounting a rock bolt on a shotcrete coating layer, Which can be easily seen by attaching a lock bolt cap which can be attached to a rock bolt.

상기한 기술적 과제를 해결하기 위해 본 발명은 기초터널 형성에 따른 터널을 구축하기 위한 노출식 락볼트 시공방법에 있어서,According to an aspect of the present invention, there is provided a method of constructing an exposed rock bolt for constructing a tunnel by forming a base tunnel,

(a) 상기 기초터널의 암반 표면에 제 1 숏크리트(shotcrete)를 타설하는 제 1 숏크리트 형성단계;(a) a first shotcrete forming step of placing a first shotcrete on a rock surface of the foundation tunnel;

(b) 천공장치를 이용하여 상기 암반에 설계된 수만큼 락볼트가 삽입될 암반공을 천공하는 천공단계;(b) a perforating step of perforating a rocking bolt to be inserted into rock bolts as many as the designed number of rock bolts are inserted into the rock bolt using a punching device;

(c) 상기 천공된 암반공에 상기 락볼트의 선단측을 진입시켜 상기 암반공의 끝지점까지 안내하여 상기 락볼트를 삽입하되 상기 락볼트의 후단측이 돌출되게 하는 락볼트삽입단계;(c) a locking bolt inserting step of inserting the locking bolt into the perforated arm anticlock by guiding the distal end side of the locking bolt to the end point of the arm anticlock, so that the rear end side of the locking bolt protrudes;

(d) 상기 락볼트가 삽입된 상태에서 상기 암반공의 초입에 지압플레이트를 설치하고 너트를 체결하여 고정하는 락볼트고정단계;(d) a locking bolt securing step of securing an acupressure plate at the initial position of the arm rest and inserting the nut while the locking bolt is inserted;

(e) 제 2 숏크리트(shotcrete) 타설로 도포층을 형성하고 상기 도포층 상부로 상기 락볼트 후단측의 종단부가 노출되게 하는 제 2 숏크리트 형성단계; 및(e) a second shotcrete forming step of forming a coating layer by a second shotcrete pouring and exposing a rear end of the rock bolt to an upper portion of the coating layer; And

(f) 상기 락볼트의 후단측 종단부에 락볼트캡을 체결하는 락볼트캡체결단계;를 포함하여 구비되는 것을 특징으로 하는 노출식 락볼트 시공방법을 제공한다.
(f) a locking bolt cap fastening step of fastening a locking bolt cap to a rear end side end portion of the locking bolt.

본 발명에 따르면 락볼트 설치 완료 후 2차 숏크리트 타설로 락볼트가 완전히 매립되지 않고 노출되어 락볼트을 확인하기 용이하며 터널 내 24시간 작업으로 관리 감독을 위해 야간에도 상주하여 감리할 필요가 없는 이점이 있다.According to the present invention, after the installation of the rock bolt, the rock bolt is not fully buried due to the second shotcrete pouring, and it is easy to identify the rock bolt, and it is advantageous that the rock bolt does not need to be held at night for supervision have.

또한 터널 사이클 타임을 확보하기 어려워 즉, 2회/일 사이클 타임 유지를 위해 예기치 못한 작업대기 발생시 락볼트 시공 일부 포기하는 경우가 발생할 경우, 다음 공정에서 락볼트 수량을 파악할 수 있어 부실 시공을 예방할 수 있는 이점이 있다.In addition, it is difficult to secure tunnel cycle time. In case of unexpected work waiting for maintenance of 2 times / day cycle time, if lock bolt construction is partially abandoned, the quantity of rock bolts can be detected in the next process, There is an advantage.

또한 락볼트 설치 완료 후 2차 숏크리트 타설 후에도 락볼트캡으로 인하여 용이하게 그 수량을 파악할 수 있어 근로자의 부정행위를 예방할 수 있는 이점이 있다.In addition, after the installation of the rock bolt, even after the second shotcrete is laid, it is possible to easily grasp the quantity due to the lock bolt cap, which is advantageous in preventing cheating of workers.

도 1은 터널 내부를 도시한 개략도이다.
도 2는 본 발명의 실시 예에 따른 노출식 락볼트의 구성을 도시한 개략적인 단면도이다.
도 3은 본 발명의 제 1, 제2 실시 예에 따른 노출식 락볼트 시공방법을 도시한 개략적인 공정흐름도이다.
도 4는 본 발명의 실시 예를 적용한 예시적인 확인 시트지(sheet)를 나타내는 도면이다.
1 is a schematic view showing the inside of a tunnel.
2 is a schematic cross-sectional view illustrating the configuration of an exposed rock bolt according to an embodiment of the present invention.
3 is a schematic process flow chart showing a method of applying an exposed rock bolt according to the first and second embodiments of the present invention.
4 is a view showing an exemplary verification sheet to which an embodiment of the present invention is applied.

본 발명을 실시하기 전에 이해를 돕기 위해 터널굴착방식(Tunnel excavation system)에 대해 설명하면 다음과 같다.A tunnel excavation system will now be described in order to facilitate understanding before the present invention is implemented.

터널굴착방식(Tunnel excavation system)은 철도, 도로, 용수로, 하수도 등을 통과시키기 위한 통로를 말하는 것으로, 터널공사 시는 지형, 지질, 시공성, 터널의 길이 등을 고려하여 안전하고 경제적인 굴착방식을 선정해야 한다. 이러한 굴착방식에는 재래공법, 최신공법, 기타공법이 있다. 재래공법은 목재나 steel rib로 하중을 지지토록 하는 공법으로서 안전성이 낮으며 종래에 광산에서 많이 사용하던 공법이다. 최신공법으로는 NATM공법(new austrian tunneling method), TBM공법(tunnel boring machine)공법, 실드공법(shield driving method)이 있다. Tunnel excavation system is a passage for passing through railway, road, waterway, sewer etc. In tunnel construction, safe and economical excavation method considering the topography, geology, construction, and length of tunnel Should be selected. These excavation methods include the conventional method, the latest method, and other methods. The conventional method is a method of supporting the load with wood or steel rib, which is low in safety and has been widely used in mines. The latest methods include a new austrian tunneling method, a TBM tunnel boring machine method, and a shield driving method.

(1) NATM공법은 지반 자체를 주지보재로 이용하는 공법으로, 이는 적용지반의 범위가 넓으며 경제성이 우수한 공법으로서 주로 산악 터널공사에 적용한다. (1) The NATM method is a method of using the ground itself as main support material, which is widely applied to the mountain tunnel construction.

(2) TBM공법은 폭약을 사용하지 않고 Hard rock tunnel boring machine의 회전 cutter에 의해 터널전단면을 절삭 또는 파쇄하는 공법으로서, 주로 암반터널굴착공사에 적용한다.(2) The TBM method is a method of cutting or crushing the tunnel cross section by using a rotary cutter of hard rock tunnel boring machine without using explosives, and is mainly applied to rock tunnel excavation work.

(3) 실드공법은 지반 내에 실드라고 하는 강제 원통 굴삭기를 추진시켜 터널을 굴착하는 공법으로 연약한 토질, 용수가 있는 지반을 굴착하는데 유용하다.(3) The shielding method is a method of excavating a tunnel by propelling a forced cylindrical excavator called a shield in the ground, which is useful for excavating the soil with soft soil and water.

기타 공법으로는 개착식 공법(open cut method)와 침매(immersed method)가 있다. 개착식 공법은 일명 절개공법으로서 지표면 아래로부터 일정깊이까지 개착하여 터널본체를 완성한 후 매몰하여 터널을 만드는 공법으로 주로 지하철 터널에서 많이 사용하고 있다. 침매공법은 일명 하저터널로서 해저 또는 지후수면하에 터널을 굴착하는 공법으로 지상에서 터널박스를 제작하여 물에 띄워 현장에 운반한 후 소정의 위치에 침하시켜 터널을 구축하는 공법이다.Other methods include open cut method and immersed method. The open type method is a method of making a tunnel by constructing a tunnel body from the bottom of the earth to a certain depth and buried it as a cutting method. It is mainly used in a subway tunnel. The soaking method is a so-called "bottom tunnel", which is a method of excavating a tunnel under the seabed or underground water. A tunnel box is made on the ground, floated in the water, and transported to the site.

본 발명은 상기 NATM공법을 적용한 락볼트 시공방법에 관한 것으로, 지하구조물, 터널 등의 암반에 소정의 지름으로 소정깊이만큼 각각 여러 각도 상에서 천공을 하고, 그 천공된 홀(이하, 이를 암반공이라 총칭함)에 락볼트를 끼워 고정하는 공정을 포함하는 시공방법이다.[0001] The present invention relates to a rock bolt construction method using the NATM method, in which a rock bolt is inserted into rocks of an underground structure, a tunnel or the like at predetermined angles at predetermined angles, And a step of securing the lock bolts to each other by clamping the lock bolts.

이러한 락볼트의 사용되는 지점은 토목건축공사, 특히 터널공사 등에 있어서는 산의 암반을 포함하는 지중에 암반공에 삽입하여 내측으로부터 구근을 형성시켜 암반과 터널의 내부를 이어 보강하여 주도록 한 일종의 지지하는 방법이다.These rock bolts are used in civil engineering construction work, especially in tunnel construction, etc. They are inserted into the anti-cavities in the ground including the rocks in the mountains, forming a bulb from the inside to reinforce the inside of the rocks and tunnels. Method.

보통 터널공사에 있어 터널 주위의 암반에 대략 지름 36-40mm, 깊이 2m~4m이상의 암반공을 뚫고 그 암반공에 락볼트를 끼워 터널측을 구축하기 위한 것으로, 이 락볼트의 원리는 2가지로서, 암반에 접착하는 방법은 선단(先端)접착방식과 전면(全面)접착방식이 있다. 접착방법을 근거로 한다면 2가지 방식이 공통적으로 기계식(쐐기식)·수지식(樹脂式)·몰탈식 등으로 나누어진다. 이때의 락볼트는 암반의 상황에 따라서 굵기·길이 등 여러 종류의 것이 사용된다 하겠다.
In general tunnel construction, it is intended to construct a tunnel side by inserting rock bolts in a rock anticollage having a diameter of about 36-40 mm and a depth of 2 m to 4 m in the rock around the tunnel, , And the method of bonding to the rock is a tip bonding method and a front surface bonding method. Based on the bonding method, the two methods are commonly divided into mechanical type (wedge type), water type (resin type), and mortar type. In this case, various kinds of rock bolts may be used depending on the condition of the rock, such as thickness and length.

이하에서는 본 발명의 실시 예를 첨부 도면을 참조하여 상세히 설명하고자 한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

이하의 실시 예는 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 본 발명의 사상을 충분히 전달하기 위해 제시하는 것이다. 본 발명은 여기서 제시한 실시 예만으로 한정되지 않고 다른 형태로 구체화될 수도 있다. 도면은 본 발명을 명확히 하기 위해 설명과 관계없는 부분의 도시를 생략하고, 이해를 돕기 위해 구성요소의 크기를 다소 과장하여 표현할 수 있다.The following embodiments are provided to fully convey the spirit of the present invention to a person having ordinary skill in the art to which the present invention belongs. The present invention is not limited to the embodiments shown herein but may be embodied in other forms. For the sake of clarity, the drawings are not drawn to scale, and the size of the elements may be slightly exaggerated to facilitate understanding.

첨부된 도 1에서 도시된 바와 같이 기초터널(A)에 형성된 수개의 암반공(1)에 설치되는 노출식 락볼트(100)는 기초터널의 붕괴를 방지하기 위하여 기초터널 안쪽 면에 무수히 많은 락볼트(기초볼트)를 박고, 메쉬 형상의 망사체를 설치한 다음, 보조 보강 콘크리트물 공사로서 숏크리트(shotcrete) 도포층(F1), 방수시트(B) 및 복공(lining) 도포층(F2)의 시공으로 기본적으로 터널의 보강막을 형성시켜 터널을 완성하게 된다.1, an exposed rock bolt 100 installed in several female anti-cavities 1 formed in a base tunnel A has a large number of rocks on the inner surface of a base tunnel to prevent collapse of the root tunnel The shotcrete application layer F1, the waterproof sheet B, and the lining application layer F2 as the auxiliary reinforced concrete waterworks work after the bolts (foundation bolts) By constructing the tunnels, basically a reinforcement film of the tunnel is formed to complete the tunnel.

이 보강막 공사는 먼저 착암기나 파쇄기를 이용하여 암반에 락볼트가 삽입될 암반공을 뚫은 다음 해당하는 암반공에 시멘트 몰탈을 타설하고 락볼트를 삽입하거나, 락볼트를 삽입한 후 시멘트 몰탈을 타설한다. 시멘트 몰탈가 완전히 굳으면 락볼트는 암반 속에 견고하게 고정된다. 여기서 락볼트는 소정간격으로 복수 개 설치함으로써 망사체에 분사된 콘크리트 하중을 충분히 견디면서 견고하게 고정상태를 유지함으로써 터널을 구축하게 되는 것이다.This reinforcing membrane construction should be made by first drilling a rocking bolt to be inserted into a rock bolt by using a rock drill or a crusher, then inserting a cement mortar into the corresponding rock bolt, inserting a rock bolt, or inserting a rock bolt, do. When the cement mortar is completely hardened, the rock bolt is firmly fixed in the rock. In this case, a plurality of rock bolts are provided at predetermined intervals to sufficiently endure the concrete load injected into the mesh body, and to firmly maintain the fixed state, thereby constructing the tunnel.

위와 같은 공정 중 본 발명의 기술적 사상은 락볼트를 설치한 후 숏크리트(shotcrete) 타설을 하여도 락볼트 상단부가 상기 숏크리트(shotcrete) 도포층 위로 소정 높이 돌출되게 하여 락볼트가 설치되어 있는지 확인할 수 있는 락볼트캡을 부착할 수 있는 자리를 형성하게 하고 부착된 락볼트캡을 통하여 용이하게 확인할 수 있도록 하는 것이다.The technical idea of the present invention is that the upper part of the rock bolt protrudes above the shotcrete coating layer by a predetermined height even after the shot bolts are installed after the rock bolts are installed so that the rock bolts are installed So that a seat for attaching the lock bolt cap can be formed and easily confirmed through the attached lock bolt cap.

이렇게 하므로 락볼트 시공수량을 파악하고 확인하는 데 어려움이 해소되고, 터널 내 24시간 작업으로 관리 감독을 위해 야간에도 상주하여 감리하여야 하는 어려움도 해결되며, 락볼트 설치 후 숏크리트(shotcrete) 타설된 후에도 락볼트캡을 설치하고 볼 수 있도록 하여 그 수량을 파악하는데 용이하게 한다.Therefore, it is solved the difficulty to grasp and confirm the quantity of rock bolt construction, and it is solved the difficulty to stay in the night to supervise and supervise with 24 hours work in tunnel, and after shotcrete is put after rock bolt installation The lock bolt cap is installed and made visible so that the quantity can be easily determined.

또한 터널 사이클 타임을 확보하기 어려움 때문에 즉, 2회/일 사이클 타임을 유지하기 위해 예기치 못한 작업대기 발생시 락볼트 시공 일부가 포기하는 경우에는 숏크리트(shotcrete) 타설 이후에도 다음 공정에서 매립된 락볼트 수량을 확인할 수 있게 된다.In addition, it is difficult to secure the tunnel cycle time. In other words, in case of unexpected waiting time to maintain the 2 times / day cycle time, if the rock bolt construction part is abandoned, the quantity of rock bolts buried in the next process after shotcrete pouring .

또한 근로자의 부정행위를 원천 차단할 수 있다. 즉, 가장 보편화 된 스틸 락볼트는 무거운 자중으로 시공성이 떨어지며 근로자의 피로도가 높아 야간 작업시 불량시공을 발생시킬 수 있는 여지가 있고 스틸 락볼트를 고철로 처리하여 개인적으로 이윤을 추구하고자 하여도 숏크리트(shotcrete) 타설 후에도 락볼트캡으로 용이하게 확인할 수 있으므로 부정행위의 차단이 가능하다.It can also prevent workers from cheating. In other words, the most commonly used steel lock bolts have poor workability due to their heavy weight, and there is a possibility of causing bad construction during night work due to the high fatigue of workers. Even if the steel lock bolts are treated with scrap iron for personal profit, (shotcrete) can be easily confirmed with a rock bolt cap even after the installation, cheating can be blocked.

따라서 현재에도 여전히 부실시공의 가능성이 내재하고 있으나 본 발명의 실시로 상기한 문제점을 해결할 수 있다.
Therefore, although the possibility of insufficient construction still exists, the above-mentioned problem can be solved by the practice of the present invention.

도 2에 도시된 바와 같이, 본 발명의 일실시 예에 따른 노출식 락볼트(100)는 길이방향의 나사부가 형성되어 있는 락볼트(10)와; 상기 락볼트(10) 상에 관통 설치되되, 암반으로부터 천공된 암반공(1)의 터널 내벽 면에 밀착 설치되는 아치형의 지압플레이트(20)와; 상기 락볼트(10)의 나사부에 체결되어 지압플레이트(20)를 고정하는 너트(30)를 포함하고 이를 이용하여 기초터널(A) 내에 제1 숏크리트(shotcrete) 타설 후 천공하여 암반공(1)을 형성된 곳에 매입 시공한 다음, 터널 내에 망사체 작업과 함께 제2 숏크리트(shotcrete)작업으로 콘크리트 도포층(F1)을 형성한 다음, 도포층(F1) 외측으로 노출된 락볼트에 용이하게 구별할 수 있는 이색 또는 형광의 락볼트캡(40)을 구비한다.As shown in FIG. 2, the exposed rock bolt 100 according to an embodiment of the present invention includes a rock bolt 10 having a threaded portion formed in a longitudinal direction thereof; An arch-shaped pressure plate 20 installed on the rock bolt 10 so as to be closely attached to the inner wall surface of the tunnel of the cancer arm 1 punctured from the rock; And a nut 30 which is fastened to the threaded portion of the lock bolt 10 and fixes the pressure plate 20. The first shotcrete is inserted into the base tunnel A, A concrete application layer F1 is formed by a second shotcrete operation together with a mesh work in the tunnel and then easily distinguished from the rock bolts exposed to the outside of the application layer F1 And a lock bolt cap 40 of a different color or fluorescence.

이렇게 구비된 노출식 락볼트(100)를 설치하므로 후공정 전에 락볼트 수량을 용이하게 파악 및 확인할 수 있도록 한다.Since the exposed rock bolt 100 is provided, the quantity of the rock bolt can be easily grasped and confirmed before the post-process.

즉, 기초터널(A) 내부에 제1 숏크리트(shotcrete) 작업 후에 각 천공된 암반공(1)에 락볼트(10)의 선단측를 암반공(1)의 끝 지점까지 안내시키는 상태에서 락볼트(10)의 나사부를 통해 너트(30)로서 체결하되, 락볼트(10)의 후단은 상기 너트(30)의 체결에 의해 지압플레이트(20)를 통해 암반공(1)의 초입에서 지지되어 고정되도록 한 다음 제2 숏크리트(shotcrete) 작업 후에 노출된 락볼트의 후단을 락볼트캡(40)으로 씌워 보호하여 후공정에 방해되지 않으면서 락볼트 수량을 파악 및 확인하는데 용이하다.That is to say, after the first shotcrete operation is performed in the base tunnel A, the rock bolts 10 are guided to the end points of the rock bolts 10 in the state where the tip ends of the rock bolts 10 are guided to the end points of the rock bolts 10 10 so that the rear end of the lock bolt 10 is supported and fixed at the top of the arm half 1 through the pressurizing plate 20 by fastening the nut 30 After the second shotcrete operation, the rear end of the exposed rock bolt is covered with the lock bolt cap 40, which is easy to grasp and confirm the quantity of the rock bolt without being disturbed by the post-process.

이후, 콘크리트 도포층의 표면상에 방수시트(B)를 부착하고, 방수시트(B) 부착 완료 후 콘크리트 도포층(F2) 터널 내의 곡면을 갖게 하는 복공(lining)작업을 실시하여 터널을 구축한다.
Thereafter, a waterproof sheet B is attached to the surface of the concrete application layer, and a tunnel is formed by performing a lining operation to have a curved surface in the concrete application layer (F2) tunnel after completion of the attachment of the waterproof sheet (B) .

그럼, 도 3에 도시된 바와 같이 본 발명의 제 1 실시 예에 따른 노출식 락볼트 시공방법을 단계적으로 설명하면 다음과 같다.As shown in FIG. 3, the exposed rock bolt construction method according to the first embodiment of the present invention will be described in detail as follows.

본 발명의 제 1실시 예는 락볼트 재질을 스틸 등과 같은 금속재를 사용할 경우에 적용한다.The first embodiment of the present invention is applied to a case where a rock bolt material is made of a metal material such as steel.

(가) 먼저, 기초터널의 형성에 따른 터널의 구축이 이루어지기 위해서 굴착된 암벽 표면에 제1 숏크리트(shotcrete)를 타설한다.(SA01)(A) First, a shotcrete is cast on a rock surface excavated in order to construct a tunnel according to the formation of a foundation tunnel (SA01).

참고로 숏크리트(Shotcrete)는 접착력과 초기 응결이 빠른 액상형의 급결제로서 법면이나 터널공법에 필수적으로 사용하는 제품이다.For reference, shotcrete is a liquid-phase type quick-setting material with fast adhesion and early condensation, and is an essential product for use in the surface and tunnel works.

(나) 다음, 착암기나 파쇄기를 이용하여 암반에 설계된 수만큼 락볼트(10)가 삽입될 암반공(1)을 천공한다.(SA02)(B) Next, by using a rock drill or a crusher, the rock bolts 10 to be inserted into the rock bolts 10 as many as designed are drilled. (SA02)

(다) 다음, 천공된 암반공(1)에 락볼트(10)의 선단측을 진입시켜 암반공의 끝지점까지 안내시켜 락볼트(10)를 삽입한다.(SA03)(C) Next, the rock bolt 10 is inserted by guiding the tip end of the lock bolt 10 to the perforated arm anticlock 1 to the end point of the arm anticlock (SA03).

이때 후술하는 제2 숏크리트(shotcrete) 타설 후에도 락볼트(10)가 소정 높이(약 4 ~ 5cm정도) 노출될 수 있도록 소정 길이 돌출되도록 삽입한다.At this time, the rock bolt 10 is inserted so as to protrude by a predetermined length so as to be exposed at a predetermined height (about 4 to 5 cm) after the second shotcrete installation, which will be described later.

(라) 다음, 락볼트가 삽입된 상태에서 암반공의 초입에 지압플레이트(20)를 설치하고 너트(30)를 체결하여 고정한다.(SA04)(D) Next, in the state where the lock bolt is inserted, the acupressure plate 20 is installed at the beginning of the arm anti-hole, and the nut 30 is fastened and fixed.

즉, 락볼트(10) 시공 시 후술하는 제2 숏크리트 단계의 도포층보다 약 4 ~ 5cm정도 돌출되도록 지압플레이트(20)와 너트(30)를 체결한다.That is, when the rock bolt 10 is constructed, the pressure-sensitive plate 20 and the nut 30 are tightened so as to protrude about 4 to 5 cm from the coating layer of the second shotcrete stage described later.

(마) 다음, 상기 SA03단계 전이나 후 중 어느 하나에서 암반에 천공된 다수개의 암반공(1)에 시멘트 몰탈을 락볼트(10)가 정착되거나 되었을 때에 암반공(1)의 내부와 락볼트(10)의 틈새에 충전될 정도로 설정된 량만큼 각 암반공(1)의 내측부에 주입한다.(SA05)(E) Next, when the rock bolt 10 is fixed to the plurality of the arm rests 1 drilled in the rock in either of the SA03 step and the SA03 step, the inside of the arm rest 1 and the rock bolt (SA05) is injected into the inner side of each female antirejection (1) by an amount which is set so as to be filled in the clearance of the male connector (10)

즉, 암반공(1)에 시멘트 몰탈을 타설하고 락볼트(10)를 삽입하거나, 락볼트(10)를 삽입한 후 시멘트 몰탈을 타설한다. 시멘트 몰탈가 완전히 굳으면 락볼트(10)는 암반 속에 견고하게 고정된다.That is, the cement mortar is placed in the female counter-hole 1 and the rock bolt 10 is inserted, or the rock bolt 10 is inserted, and then the cement mortar is poured. When the cement mortar is completely hardened, the rock bolt (10) is firmly fixed in the rock.

(바) 다음, 제2 숏크리트(shotcrete) 타설로 콘크리트 도포층(F1)을 형성한다.(SA06)(F) Next, a concrete shot layer F1 is formed by a second shotcrete placement (SA06)

이때 락볼트캡(40)을 씌울 수 있는 정도로 암반공(1)의 입구 상단으로 락볼트(10)가 노출되어 있는지 확인한다.At this time, it is checked whether the lock bolt 10 is exposed to the upper end of the entrance of the female anti-hole 1 so as to cover the lock bolt cap 40.

(사) 다음, 상기 SA03단계 전, 상기 SA06단계 전이나 후 중 어느 하나에서 락볼트가 노출될 부위에 부식 방지 처리를 한다.(SA07)(SA) Next, the anti-corrosive treatment is performed on the site where the rock bolt is to be exposed in any of SA03, SA06, and SA07. (SA07)

락볼트(10)가 스틸(Steel) 등과 같은 금속재질로 인하여 용이하게 부식되지 않도록 방지 처리를 하며 방지 처리시 에폭시 등과 같은 방지액으로 코팅하거나 도포할 수 있다.The lock bolt 10 is prevented from being easily corroded due to a metal material such as steel or the like, and can be coated or coated with a preventive liquid such as epoxy in the prevention process.

(아) 다음, 노출된 락볼트(10)에 라운드진 아치형의 락볼트캡(40)을 체결한다.(SA08)(A) Next, the rounded arch bolt cap 40 is fastened to the exposed rock bolt 10 (SA08).

특히 락볼트캡(40)은 발광, 형광, 식별이 용이한 이색의 색상으로 도포 또는 코팅되어 있을 수 있으며 암벽과 후공정인 방수시트 사이에 위치하므로 부식에도 강한 소재를 사용하는 것이 바람직하다.Particularly, the lock bolt cap 40 may be coated or coated with light-emitting, fluorescent, and distinguishable two-color hue. Since the rock bolt cap 40 is located between the rock wall and the waterproof sheet as a back-end process, it is preferable to use a material resistant to corrosion.

이때 극한의 환경(소량의 불빛이나 자욱한 먼지 속)에서도 락볼트 장착 여부를 확인할 수 있도록 하고 가독성을 높여 수량 파악이 용이하도록 한다.At this time, it is possible to confirm whether or not the lock bolt is attached even in the extreme environment (a small amount of light or dust), and the readability is increased to make it easy to grasp the quantity.

또한, 락볼트캡(40)은 작업 중 충격에 파손되지 않는 강도 또는 쉽게 파손되지 않는 연성을 보유하도록 한다.Further, the lock bolt cap 40 has a strength that is not damaged by impacts during operation or a softness that is not easily broken.

또한, 후공정인 방수시트 작업시에도 락볼트의 돌출된 날카로운 부분을 부드럽게 감싸 보호하는 역할도 한다.In addition, it protects the protruding sharp part of the lock bolt smoothly while protecting the waterproof sheet.

이와 같이 노출식 락볼트(100)는 락볼트(10), 지압플레이트(20), 너트(30) 및 락볼트캡(40)을 포함하여 구성된다.Thus, the exposed rock bolt 100 includes the rock bolt 10, the pressure applying plate 20, the nut 30, and the lock bolt cap 40.

(자) 다음, 제 2차 숏크리트 작업이 완료되어 경화된 상태에서는 방수시트(B)의 부착작업이 이루어진다.(SA09)(SA09) Next, the waterproof sheet B is adhered in the cured state after the second shotcrete operation is completed. (SA09)

이에 본 발명의 제 1 실시 예에 따른 노출식 락볼트 시공방법이 완성된다.
Thus, the method of constructing the exposed rock bolt according to the first embodiment of the present invention is completed.

다음, 도 3에 도시된 바와 같이 본 발명의 제 2실시 예에 따른 노출식 락볼트 시공방법을 단계적으로 설명하면 다음과 같다.Next, as shown in FIG. 3, a method of constructing an exposed rock bolt according to a second embodiment of the present invention will be described step by step.

본 발명의 제 2실시 예는 락볼트 재질을 부식에 강하고 경량인 유리섬유강화플라스틱(GFRP) 등과 같은 유리섬유재질을 사용할 경우에 적용한다.The second embodiment of the present invention is applied to a case where a glass fiber material such as glass fiber reinforced plastic (GFRP) or the like, which is resistant to corrosion and light in weight, is used as the lock bolt material.

(가') 먼저, 기초터널의 형성에 따른 터널의 구축이 이루어지기 위해서 굴착된 암벽 표면에 제1 숏크리트(shotcrete)를 타설한다.(SB01)First, a shotcrete is placed on the excavated rock wall in order to construct a tunnel according to the formation of the foundation tunnel (SB01).

참고로 숏크리트(Shotcrete)는 접착력과 초기 응결이 빠른 액상형의 급결제로서 법면이나 터널공법에 필수적으로 사용하는 제품이다.For reference, shotcrete is a liquid-phase type quick-setting material with fast adhesion and early condensation, and is an essential product for use in the surface and tunnel works.

(나') 다음, 착암기나 파쇄기를 이용하여 암반에 설계된 수만큼 락볼트(10)가 삽입될 암반공(1)을 천공한다.(SB02)(B ') Next, by using a rocker arm or a crusher, the rock bolts 10 to be inserted into the rock bolts 10 as many as designed are drilled. (SB02)

(다') 다음, 천공된 암반공(1)에 락볼트(10)의 선단측을 진입시켜 암반공의 끝지점까지 안내시켜 락볼트(10)를 삽입한다.(SB03)The lock bolt 10 is inserted by inserting the tip end of the lock bolt 10 into the perforated arm protrusion 1 and guiding it to the end point of the arm protrusion (SB03).

이때 후술하는 제2 숏크리트(shotcrete) 타설 후에도 락볼트(10)가 소정 높이(약 4 ~ 5cm정도) 노출될 수 있도록 소정 길이 돌출되도록 삽입한다.At this time, the rock bolt 10 is inserted so as to protrude by a predetermined length so as to be exposed at a predetermined height (about 4 to 5 cm) after the second shotcrete installation, which will be described later.

(라') 다음, 락볼트(10)가 삽입된 상태에서 암반공의 초입에 지압플레이트(20)를 설치하고 너트(30)를 체결하여 고정한다.(SA04)(LA ') Next, in the state where the lock bolt 10 is inserted, the acupressure plate 20 is installed at the beginning of the arm anti-hole, and the nut 30 is fastened and fixed.

즉, 락볼트(10) 시공 시 후술하는 제2 숏크리트 단계의 도포층보다 약 4 ~ 5cm정도 돌출되도록 지압플레이트(20)와 너트(30)를 체결한다.That is, when the rock bolt 10 is constructed, the pressure-sensitive plate 20 and the nut 30 are tightened so as to protrude about 4 to 5 cm from the coating layer of the second shotcrete stage described later.

(마') 다음, 상기 SA03단계 전이나 후 중 어느 하나에서 암반에 천공된 다수개의 암반공(1)에 시멘트 몰탈을 락볼트(10)가 정착되거나 되었을 때에 암반공(1)의 내부와 락볼트(10)의 틈새에 충전될 정도로 설정된 량만큼 각 암반공(1)의 내측부에 주입한다.(SB05)Next, the rock bolts 10 are fixed to the plurality of rock heights 1 pierced in the rock at one of the rock heights before and after SA03 step, And is injected into the inner side of each female antireflection 1 by an amount so set as to be filled in the clearance of the bolt 10. (SB05)

즉, 암반공(1)에 시멘트 몰탈을 타설하고 락볼트(10)를 삽입하거나, 락볼트(10)를 삽입한 후 시멘트 몰탈을 타설한다. 시멘트 몰탈가 완전히 굳으면 락볼트(10)는 암반 속에 견고하게 고정된다.That is, the cement mortar is placed in the female counter-hole 1 and the rock bolt 10 is inserted, or the rock bolt 10 is inserted, and then the cement mortar is poured. When the cement mortar is completely hardened, the rock bolt (10) is firmly fixed in the rock.

(바') 다음, 제2 숏크리트(shotcrete) 타설로 콘크리트 도포층(F1)을 형성한다.(SB06)(Bar ') Next, a concrete shot layer F1 is formed by a second shotcrete placement (SB06)

이때 락볼트캡(40)을 씌울 수 있는 정도로 암반공(1)의 입구 상단으로 락볼트(10)가 노출되어 있는지 확인한다.At this time, it is checked whether the lock bolt 10 is exposed to the upper end of the entrance of the female anti-hole 1 so as to cover the lock bolt cap 40.

(사') 다음, 노출된 락볼트(10)에 라운드진 아치형의 락볼트캡(40)을 체결한다.(SB07)Next, the rounded arch bolt cap 40 is fastened to the exposed rock bolt 10 (SB07).

특히 락볼트캡(40)은 발광, 형광, 식별이 용이한 이색의 색상으로 도포 또는 코팅되어 있을 수 있으며 암벽(A)과 후공정인 방수시트(B) 사이에 위치하므로 부식에도 강한 소재를 사용하는 것이 바람직하다.Particularly, the lock bolt cap 40 may be coated or coated with light-emitting, fluorescent, and distinguishable two-color colors. Since it is located between the rock wall A and the waterproof sheet (B) .

이때 극한의 환경(소량의 불빛이나 자욱한 먼지 속)에서도 락볼트 장착 여부를 확인할 수 있도록 하고 가독성을 높여 수량 파악이 용이하도록 한다.At this time, it is possible to confirm whether or not the lock bolt is attached even in the extreme environment (a small amount of light or dust), and the readability is increased to make it easy to grasp the quantity.

또한, 락볼트캡(40)은 작업 중 충격에 파손되지 않는 강도 또는 쉽게 파손되지 않는 연성을 보유하도록 한다.Further, the lock bolt cap 40 has a strength that is not damaged by impacts during operation or a softness that is not easily broken.

또한, 후공정인 방수시트 작업시에도 락볼트의 돌출된 날카로운 부분을 부드럽게 감싸 보호하는 역할도 한다.In addition, it protects the protruding sharp part of the lock bolt smoothly while protecting the waterproof sheet.

이와 같이 노출식 락볼트(100)는 락볼트(10), 지압플레이트(20), 너트(30) 및 락볼트캡(40)을 포함하여 구성된다.Thus, the exposed rock bolt 100 includes the rock bolt 10, the pressure applying plate 20, the nut 30, and the lock bolt cap 40.

(아') 다음, 제 2차 숏크리트 작업이 완료되어 경화된 상태에서는 방수시트(B)의 부착작업이 이루어진다.(SB08)(A ') Next, the waterproof sheet B is attached in a state where the second shotcrete work is completed and hardened (SB08)

이에 본 발명의 제 2 실시예에 따른 노출식 락볼트 시공방법이 완성된다.
Thus, the exposed rock bolt construction method according to the second embodiment of the present invention is completed.

상기와 같은 본 발명의 실시 예들에 따르면 다음과 같은 효과를 예상할 수 있다.According to the embodiments of the present invention as described above, the following effects can be expected.

락볼트 설치 완료 후 2차 숏크리트 타설로 락볼트가 매립되지 않고 노출되어 그 수량 파악이 용이하고, 터널 내 24시간 작업으로 관리 감독을 위해 야간에도 상주하여 감리할 필요가 없는 이점이 있다.After the installation of the rock bolt, the rock bolt is not buried due to the second shotcrete pouring, and it is easy to grasp the quantity of the rock bolt, and there is an advantage that it is not necessary to reside at night to supervise the operation by the 24 hour operation in the tunnel.

또한 터널 사이클 타임을 확보하기 어려워 즉, 2회/일 사이클 타임 유지를 위해 예기치 못한 작업대기 발생시 락볼트 시공 일부 포기하는 경우가 발생할 경우, 다음 공정에서 락볼트 수량을 파악할 수 있어 부실 시공을 예방할 수 있는 이점이 있다.In addition, it is difficult to secure tunnel cycle time. In case of unexpected work waiting for maintenance of 2 times / day cycle time, if lock bolt construction is partially abandoned, the quantity of rock bolts can be detected in the next process, There is an advantage.

또한 락볼트 시공 완료 후 2차 숏크리트 타설 후에도 락볼트캡이 노출되어 그 수량을 파악할 수 있어 근로자의 부정행위를 예방할 수 있는 이점이 있다.In addition, after the rock bolt is completed, the rock bolt cap is exposed even after the second shotcrete is laid, and the quantity of the rock bolt cap can be grasped, which is advantageous in preventing cheating of workers.

도 4는 본 발명의 실시 예를 적용한 예시적인 확인 시트지(sheet)를 나타내는 것으로 상기와 같은 서식을 통하여 락볼트 설치 여부를 용이하게 확인하고 그 수량을 파악할 수 있게 된다.
FIG. 4 shows an exemplary verification sheet to which the embodiment of the present invention is applied. Through the above-described format, it is possible to easily check whether or not a lock bolt is installed, and to know the quantity thereof.

이상에서는 특정의 실시 예에 대하여 도시하고 설명하였다. 그러나, 본 발명은 상기한 실시 예에만 한정되지 않으며, 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 이하의 청구범위에 기재된 발명의 기술적 사상의 요지를 벗어남이 없이 얼마든지 다양하게 변경 실시할 수 있을 것이다.The foregoing has shown and described specific embodiments. However, it is to be understood that the present invention is not limited to the above-described embodiment, and various changes and modifications may be made without departing from the scope of the technical idea of the present invention described in the following claims It will be possible.

100 : 노출식 락볼트
10 : 락볼트
20 : 지압플레이트
30 : 너트
40 : 락볼트캡
100: exposed rock bolt
10: Rock bolt
20: Chiropractic plate
30: Nut
40: Rock bolt cap

Claims (4)

기초터널 형성에 따른 터널을 구축하기 위한 노출식 락볼트 시공방법에 있어서,
(a) 상기 기초터널의 암반 표면에 제 1 숏크리트(shotcrete)를 타설하는 제 1 숏크리트 형성단계;
(b) 천공장치를 이용하여 상기 암반에 설계된 수만큼 락볼트가 삽입될 암반공을 천공하는 천공단계;
(c) 상기 천공된 암반공에 상기 락볼트의 선단측을 진입시켜 상기 암반공의 끝지점까지 안내하여 상기 락볼트를 삽입하되 상기 락볼트의 후단측이 돌출되게 하는 락볼트삽입단계;
(d) 상기 락볼트가 삽입된 상태에서 상기 암반공의 초입에 지압플레이트를 설치하고 너트를 체결하여 고정하는 락볼트고정단계;
(e) 상기 락볼트 돌출된 부위에 부식 방지 처리를 하는 부식방지처리단계;
(f) 제 2 숏크리트(shotcrete) 타설로 도포층을 형성하고 상기 도포층 상부로 상기 락볼트 후단측의 종단부가 노출되게 하는 제 2 숏크리트 형성단계; 및
(g) 상기 락볼트의 후단측 종단부에 용이하게 구별할 수 있는 이색 또는 형광의 락볼트캡을 체결하는 락볼트캡체결단계;를 포함하고,
상기 락볼트캡으로 인하여 상기 락볼트 장착 여부를 용이하게 파악할 수 있는 것을 특징으로 하는 노출식 락볼트 시공방법.
A method of constructing an exposed rock bolt for constructing a tunnel according to the formation of a base tunnel,
(a) a first shotcrete forming step of placing a first shotcrete on a rock surface of the foundation tunnel;
(b) a perforating step of perforating a rocking bolt to be inserted into rock bolts as many as the designed number of rock bolts are inserted into the rock bolt using a punching device;
(c) a locking bolt inserting step of inserting the locking bolt into the perforated arm anticlock by guiding the distal end side of the locking bolt to the end point of the arm anticlock, so that the rear end side of the locking bolt protrudes;
(d) a locking bolt securing step of securing an acupressure plate at the initial position of the arm rest and inserting the nut while the locking bolt is inserted;
(e) a corrosion prevention treatment step of performing a corrosion prevention treatment on the protruding portion of the rock bolt;
(f) a second shotcrete forming step of forming a coating layer by a second shotcrete pouring and exposing a rear end of the rock bolt to an upper portion of the coating layer; And
(g) a lock bolt cap fastening step of fastening a lock bolt cap of a different color or fluorescence which can be easily distinguished to the rear end of the lock bolt,
Wherein the locking bolt cap is easily grasped by the locking bolt cap.
제 1 항에 있어서,
상기 (b) 단계와 (c) 단계 사이에는 몰탈을 상기 암반공의 내부로 주입하는 몰탈주입단계를 더 구비하는 것을 특징으로 하는 노출식 락볼트 시공방법.
The method according to claim 1,
Further comprising a mortar injecting step between the step (b) and the step (c) to inject the mortar into the interior of the cancer anticollonity.
삭제delete 제 1 항에 있어서,
상기 락볼트의 재질은 금속재 또는 유리섬유강화플라스틱(GFRP)인 것을 특징으로 하는 노출식 락볼트 시공방법.
The method according to claim 1,
Wherein the rock bolt is made of metal or glass fiber reinforced plastic (GFRP).
KR1020140167169A 2014-11-27 2014-11-27 Open rock bolt construction method KR101690003B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140167169A KR101690003B1 (en) 2014-11-27 2014-11-27 Open rock bolt construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140167169A KR101690003B1 (en) 2014-11-27 2014-11-27 Open rock bolt construction method

Publications (2)

Publication Number Publication Date
KR20160064279A KR20160064279A (en) 2016-06-08
KR101690003B1 true KR101690003B1 (en) 2016-12-28

Family

ID=56193315

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140167169A KR101690003B1 (en) 2014-11-27 2014-11-27 Open rock bolt construction method

Country Status (1)

Country Link
KR (1) KR101690003B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190029020A (en) 2017-09-11 2019-03-20 주식회사 포스코건설 High strength steel pipe lock bolt construction method using underwater non-separation grout material
KR20210084761A (en) 2019-12-27 2021-07-08 주식회사 포스코건설 Support using adhesion enhancement steel pipe

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104857A (en) * 2018-01-31 2018-06-01 南京品臻精密模具有限公司 Anchor pole head protection cover
CN111535832A (en) * 2020-04-28 2020-08-14 南京地铁集团有限公司 Construction method of high-strength shield tunnel reinforcing structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101192604B1 (en) * 2011-08-19 2012-10-18 웅 방 Epoxy coating rock bolt and manufacture method
KR101247702B1 (en) * 2010-07-09 2013-03-28 (주)한국투아치 Multi-Step Tunnel Constructing Method Using Pilot Tunnel

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100612731B1 (en) * 2003-12-31 2006-08-18 재 술 나 Removable lock bolt serving as anchor
KR101317332B1 (en) * 2011-03-22 2013-10-11 심석래 A protective cap for bolt and nut having connection component and sealing part
KR101196889B1 (en) 2011-06-07 2012-11-01 주식회사 티에스테크노 Rockbolt and construction method for the same
KR101383277B1 (en) 2012-07-19 2014-04-08 삼성물산 주식회사 Rock Bolt Installation Apparatus And Rock Bolt Installation Method Using The Same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101247702B1 (en) * 2010-07-09 2013-03-28 (주)한국투아치 Multi-Step Tunnel Constructing Method Using Pilot Tunnel
KR101192604B1 (en) * 2011-08-19 2012-10-18 웅 방 Epoxy coating rock bolt and manufacture method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190029020A (en) 2017-09-11 2019-03-20 주식회사 포스코건설 High strength steel pipe lock bolt construction method using underwater non-separation grout material
KR20210084761A (en) 2019-12-27 2021-07-08 주식회사 포스코건설 Support using adhesion enhancement steel pipe

Also Published As

Publication number Publication date
KR20160064279A (en) 2016-06-08

Similar Documents

Publication Publication Date Title
Wyllie Stabilisation of rock slopes
CN106837352A (en) Fault belt surrounding rock tunnel construction method
KR101690003B1 (en) Open rock bolt construction method
CN104213509B (en) A kind of cable hoisting anchor cable formula anchorage construction method
CN102654056A (en) Shield construction method for clearing obstacles by punching rock stratum section
CN113774917B (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN105970970A (en) Pre-stressed anchor cable supporting construction method for near-railway deep foundation pit
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device
CN107130964A (en) Small-sized tunnel mud stone excavation construction method
British Tunnelling Society Specification for tunnelling
CN212563261U (en) Half cut single-pressure type open cut tunnel advances hole protective structure fast
CN116497830A (en) Foundation pit engineering construction method
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN106284410A (en) The complete rapid constructing method of covered back-digging subway transfer station
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering
CN115012957A (en) Safe and efficient tunneling construction process for large-section extra-long tunnel under complex condition
Dann et al. Unlined Tunnels of the Snowy Mountains Hydro-Electric Authority, Australia
CN208251118U (en) Slope reinforcement device
Herranz et al. SEM crossover cavern in Downtown LA
Kramer et al. The Sequential Demolition Method–Underground Replacement of a 100 Year Old Tunnel
Müller et al. The Linth-Limmern hydro-power plant-design and construction of a large pumped storage scheme
CN108487908A (en) A kind of basil device and its construction method of the shoveling of jacking construction auxiliary
Agaiby et al. Integration of design and risk management in large soft-ground NATM tunnels
Albrecht-Vogelsang et al. High-Voltage Power Cable Project--the SuedLink Line Goes Underground at the Südwestdeutsche Salzwerke Salt Mine near Heilbronn.
McEwan et al. THE PERGAU HYDROELECTRIC PROJECT. PART 2: CIVIL ENGINEERING CONSTRUCTION.

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20191031

Year of fee payment: 4