KR20110101546A - Process scheduling apparatus for painting process - Google Patents

Process scheduling apparatus for painting process Download PDF

Info

Publication number
KR20110101546A
KR20110101546A KR1020100020609A KR20100020609A KR20110101546A KR 20110101546 A KR20110101546 A KR 20110101546A KR 1020100020609 A KR1020100020609 A KR 1020100020609A KR 20100020609 A KR20100020609 A KR 20100020609A KR 20110101546 A KR20110101546 A KR 20110101546A
Authority
KR
South Korea
Prior art keywords
plan
monthly
batch
block
schedule
Prior art date
Application number
KR1020100020609A
Other languages
Korean (ko)
Inventor
백태현
하승진
김정생
이상협
이병열
Original Assignee
현대중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대중공업 주식회사 filed Critical 현대중공업 주식회사
Priority to KR1020100020609A priority Critical patent/KR20110101546A/en
Publication of KR20110101546A publication Critical patent/KR20110101546A/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Game Theory and Decision Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Manufacturing & Machinery (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

월단위 공정 스케줄링 장치는 전체 선박건조 일정에 따른 중일정계획 데이터를 제공하고, 월간계획 일정 데이터를 반영하여 도장공정 중심으로 여유일이 확보되도록 중일정계획 데이터를 조정하는 중일정계획 관리부와, 중일정계획 데이터를 통해 물량이 확정되는 월별 소지대기 블록들을 도장공정 내 작업셀들에 배치하되, 셀별 부하 균등화가 이루어지도록 자체 월간계획을 수립하고, 그 결과를 중일정계획 관리부로 제공하는 자체 월간계획 수립부와, 월간계획 일정 데이터를 가공하여 표시하는 자체 월간계획 조회부를 포함한다. 일단위 공정 스케줄링 장치는 월단위의 소지대기 블록들 중 각 일자의 배치대상 블록들을 사용자 입력에 따라 도장공장 내 작업셀로 배치하여 일별 배치계획 수립 데이터를 생성하는 블록배치 실행부와, 일별 배치계획 수립 데이터를 생성하는데 필요한 블록정보 및 배치환경정보를 생성하여 제공하는 블록정보 관리부를 포함한다. 이러한 구성에 따르면, 효율적인 월간/일일계획의 수립의 가능하고, 작업셀별 부하균등화를 이룰 수 있다.The monthly process scheduling device provides the mid-schedule plan data according to the entire ship building schedule, and the mid-schedule plan management unit that adjusts the mid-schedule plan data so that the spare days are secured centering on the painting process by reflecting the monthly plan schedule data. Placement of monthly holding blocks, which are determined by the regular plan data, are placed in the work cells in the painting process, but their own monthly plan is established so that the load is equalized by cell, and the result is provided to the central schedule management department. It includes an establishment unit and its own monthly plan inquiry unit that processes and displays the monthly plan schedule data. The daily process scheduling apparatus includes a block batch execution unit that generates daily batch planning data by arranging blocks of each day of the monthly waiting blocks to work cells in the paint shop according to user input, and daily batch planning. And a block information management unit for generating and providing block information and layout environment information necessary for generating establishment data. According to this configuration, it is possible to establish an effective monthly / daily plan, it is possible to achieve load equalization for each work cell.

Description

도장공정을 위한 공정 스케줄링 장치{PROCESS SCHEDULING APPARATUS FOR PAINTING PROCESS}Process Scheduling Equipment for Painting Process {PROCESS SCHEDULING APPARATUS FOR PAINTING PROCESS}

본 발명은 선박건조 공정에 관한 것으로, 더욱 상세하게는 선박건조 공정 중 도장공정을 위한 공정 스케줄링 장치에 관한 것이다.The present invention relates to a ship drying process, and more particularly to a process scheduling apparatus for the painting process of the ship drying process.

조선의 생산공정은 조선소의 시설배치나 장비위치 등에 따라 달라지고, 선박의 종류에 따른 시공방법에 의해서도 달라지므로 일률적으로 표현할 수는 없다. 그러나 조선공업도 일반적인 제품과 마찬가지로 수주단계로부터 제품설계, 자재조달, 생산, 시운전 및 인도의 제반단계를 거치게 된다. 이 중 생산공정은 크게 선체의 골격과 외형을 만드는 선각공정(Hull Construction)과 추진, 운항, 거주환경 등 중요기관과 이를 연결하는 기능을 만드는 의장공정(Outfitting)과 부식을 방지하기 위한 도장공정(Painting)으로 구분된다.The production process of shipbuilding cannot be expressed uniformly because it depends on the shipyard's facility arrangement and equipment location, and also depends on the construction method according to the type of ship. However, shipbuilding industry, like general products, goes through various stages of product design, material procurement, production, commissioning, and delivery. Among these, the production process consists of the hull construction process, which makes the hull skeleton and appearance, and the outfitting process that connects it with important institutions such as propulsion, operation, and living environment. Painting).

도장공정은 부분품 및 블록단계에서 이루어지는 블록 도장공정과 선체상태에서의 도장공정으로 구분된다. 전자는 가공공정이나 도장용 샵 내부에서 이루어지며 후자는 도크 및 의장 안벽에서 이루어진다.The painting process is divided into a block painting process performed at parts and a block stage and a painting process in a hull state. The former is done inside the machining process or painting shop, while the latter is done on the dock and the rigging walls.

도장공장을 효율적으로 활용하기 위해서는 계획수립 과정이 선행되어야 하는데, 종래의 계획수립 과정은 계획수립에 필요한 정보를 수작업으로 일일이 조사/수집하고, 이를 다시 분석한 후 분석 결과를 정해진 양식에 맞게 정리하는 과정을 거쳐야 한다. 따라서, 계획수립 시 필수적으로 거쳐야 하는 이러한 과정으로 인해 시간, 인력 및 비용의 낭비가 많고, 계획수립에 걸리는 기간 또한 길어지게 되는 문제점이 있었다.In order to effectively use the painting factory, the planning process must be preceded. In the conventional planning process, the information required for the planning process is manually investigated / collected manually, analyzed again, and the analysis results are arranged in a predetermined form. You have to go through the process. Therefore, there is a problem in that a lot of waste of time, manpower, and cost due to this process, which must be passed during planning, and the length of the planning also becomes long.

본 발명은 전술한 문제점을 해결하기 위해 안출된 것으로서, 신속한 월간계획 수립이 가능하고, 도장공장 내의 작업셀별 부하균등화를 이룰 수 있으며, 월단위의 일정변동사항을 쉽고 편리하게 확인할 수 있는 월단위 공정 스케줄링 장치를 제공함에 그 목적이 있다.The present invention has been made in order to solve the above problems, it is possible to quickly establish a monthly plan, to achieve a load equalization for each work cell in the painting factory, monthly process to easily and conveniently check the monthly schedule changes Its purpose is to provide a scheduling device.

또한, 본 발명은 수작업을 대체하여 일일계획의 수립 시간을 단축하고, 효율적인 일일계획을 통해 도장공장 내 작업셀들의 정반 사용율을 최대화하며, 작업셀들 간의 작업부하를 균등화할 수 있고, 상호 간의 작업진행상황을 공유하여 능률을 높일 수 있는 일단위 공정 스케줄링 장치를 제공함에 그 목적이 있다.In addition, the present invention can replace the manual work to shorten the establishment time of the daily plan, maximize the use rate of the work cells in the painting factory through efficient daily planning, can equalize the workload between the work cells, mutual work The purpose is to provide a daily process scheduling apparatus that can increase the efficiency by sharing the progress.

본 발명이 이루고자 하는 기술적 과제는 이상에서 언급한 기술적 과제들로 제한되지 않으며, 언급되지 않은 또 다른 기술적 과제들은 아래의 기재로부터 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명확하게 이해될 수 있을 것이다.The technical problem to be achieved by the present invention is not limited to the technical problems mentioned above, and other technical problems not mentioned above will be clearly understood by those skilled in the art from the following description. Could be.

본 발명에 따른 도장공정을 위한 월단위 공정 스케줄링 장치는 전체 선박건조 일정에 따라 생성된 중일정계획 데이터를 제공하고, 월간계획 일정 데이터를 반영하여 도장공정 중심으로 여유일이 확보되도록 상기 중일정계획 데이터를 조정하는 중일정계획 관리부; 전체 선박건조 일정에 따라 정해진 상기 중일정계획 데이터를 통해 물량이 확정되는 월별 소지대기 블록들을 도장공정 내 작업셀들에 배치하되, 셀별 부하 균등화가 이루어지도록 자체 월간계획을 수립하여 상기 월간계획 일정 데이터를 생성하고, 상기 중일정계획 데이터를 조정할 수 있도록 상기 월간계획 일정 데이터를 상기 중일정계획 관리부로 제공하는 자체 월간계획 수립부; 및 상기 자체 월간계획 수립부로부터 상기 월간계획 일정 데이터를 제공받아서 호선별 또는 작업셀별로 소팅하여 표시하는 자체 월간계획 조회부를 포함한다.The monthly process scheduling apparatus for the painting process according to the present invention provides the middle schedule planning data generated according to the entire ship drying schedule, and reflects the monthly schedule schedule data so that the extra days are secured around the painting process. A schedule planning management unit for adjusting data; The monthly plan schedule data is arranged by arranging monthly holding blocks in which the quantity is determined through the medium schedule plan data determined according to the entire ship construction schedule in the work cells in the painting process, and establishing a monthly plan for equalizing loads by cell. A monthly plan establishment unit which provides the monthly plan schedule data to the middle schedule plan management unit so as to generate and adjust the middle schedule plan data; And a monthly plan inquiry unit which receives the monthly plan schedule data from the own monthly plan establishment unit and sorts and displays each line or work cell.

한편, 본 발명에 따른 도장공정을 위한 일단위 공정 스케줄링 장치는 월단위의 소지대기 블록들 중 각 일자의 배치대상으로 선정된 블록들을 사용자 입력에 따라 도장공장 내 작업셀로 배치하여 일별 배치계획 수립 데이터를 생성하는 블록배치 실행부; 및 상기 블록배치 실행부의 요청에 따라 상기 일별 배치계획 수립 데이터를 생성하는데 필요한 블록정보 및 배치환경정보를 생성하여 제공하는 블록정보 관리부를 포함한다.Meanwhile, the daily process scheduling apparatus for the painting process according to the present invention arranges blocks selected as batch targets for each day of the monthly waiting blocks to work cells in the painting factory according to user input to establish a daily arrangement plan. Block batch execution unit for generating data; And a block information management unit for generating and providing block information and batch environment information necessary for generating the daily batch planning data at the request of the block batch execution unit.

본 발명의 공정 스케줄링 장치에 따르면, 신속한 월간계획 수립이 가능하고, 도장공장 내의 작업셀별 부하균등화를 이룰 수 있으며, 월단위의 일정변동사항을 쉽고 편리하게 확인할 수 있다.According to the process scheduling apparatus of the present invention, it is possible to quickly establish a monthly plan, to achieve load equalization for each work cell in the paint shop, and to easily and conveniently check the monthly schedule changes.

또한, 본 발명의 공정 스케줄링 장치에 따르면, 수작업을 대체하여 일일계획의 수립 시간을 단축하고, 효율적인 일일계획을 통해 도장공장 내 작업셀들의 정반 사용율을 최대화하며, 작업셀들 간의 작업부하를 균등화할 수 있고, 상호 간의 작업진행상황을 공유하여 능률을 높일 수 있다.In addition, according to the process scheduling apparatus of the present invention, it is possible to replace the manual work to shorten the establishment time of the daily plan, to maximize the utilization rate of the work cells in the painting factory through efficient daily planning, and to equalize the workload among the work cells. It is possible to increase efficiency by sharing work progress with each other.

도 1은 본 발명의 일 실시예에 따른 도장공정을 위한 공정 스케줄링 시스템의 구성도이다.
도 2는 본 발명의 일 실시예에 따른 월단위 공정 스케줄링 장치의 세부 구성도이다.
도 3 내지 도 5는 도 2에 나타난 장치의 동작을 설명하기 위한 화면 예시도이다.
도 6은 본 발명의 일 실시예에 따른 일단위 공정 스케줄링 장치의 세부 구성도이다.
도 7 내지 도 10은 도 6에 나타난 장치의 동작을 설명하기 위한 화면 예시도이다.
1 is a block diagram of a process scheduling system for a painting process according to an embodiment of the present invention.
2 is a detailed block diagram of a monthly process scheduling apparatus according to an embodiment of the present invention.
3 to 5 are screen examples for explaining the operation of the apparatus shown in FIG.
6 is a detailed block diagram of a daily process scheduling apparatus according to an embodiment of the present invention.
7 to 10 are screen views for explaining the operation of the device shown in FIG.

이하에서는, 본 발명의 바람직한 실시예에 따른 도장공정을 위한 공정 스케줄링 장치에 대하여 첨부된 도 1 내지 도 10을 참조하여 상세히 설명한다.Hereinafter, a process scheduling apparatus for a painting process according to a preferred embodiment of the present invention will be described in detail with reference to FIGS. 1 to 10.

도 1은 본 발명의 일 실시예에 따른 도장공정을 위한 공정 스케줄링 시스템의 구성도이다.1 is a block diagram of a process scheduling system for a painting process according to an embodiment of the present invention.

도 1을 참조하면, 공정 스케줄링 시스템은 운영정책 수집부(100), 공정운영 제어부(200), 정보분석 실행부(300), 공정데이터 관리부(400), 공정실행 정보 데이터베이스(500)를 포함한다.Referring to FIG. 1, the process scheduling system includes an operation policy collection unit 100, a process operation control unit 200, an information analysis execution unit 300, a process data management unit 400, and a process execution information database 500. .

공정 스케줄링 시스템은 도장공장의 장기계획을 위한 전략기능, 월간계획 기능을 두어 이들을 이용하여 전체 선박건조 일정에 따른 물량배정을 분석하고 중일정 결정 시 도장공장의 입장을 반영할 수 있다. 또한 소일정계획 영역의 일일계획과 작업지시 기능을 두어 공장의 실제 운영업무를 지원할 수 있으며, 공정업무와 연계하여 예산을 관리하는 기능을 제공하여 능률을 관리할 수 있다. 또한 낭비가 많을 수 있는 도료의 관리를 위한 기능을 제공하여 전체적으로 원가절감을 위한 기틀을 제공한다.The process scheduling system has a strategic function and a monthly plan function for the long-term planning of the paint shop, and analyzes the volume allocation according to the entire ship building schedule, and reflects the paint shop's position in determining the mid-term schedule. In addition, it can support the actual operation of the plant by providing daily planning and work order functions in the small schedule planning area, and manage efficiency by providing the function to manage the budget in connection with the process work. In addition, by providing a function for the management of the paint can be a lot of waste, it provides a framework for reducing the overall cost.

운영정책 수집부(100)는 장기적인 부서 운영정책 결정을 위한 물량 및 일정분석을 수행하는 전략계획 관리부(110)와 월단위의 부서 자체 운영계획을 수립하는 월간계획 관리부(120)를 포함한다. 전략계획 관리부(110)는 전략 시뮬레이션 기능 중 일정생성 결과를 관리하고, 월간계획 관리부(120)는 물량조정 결과, 월간일정 및 배치계획을 관리한다.The operation policy collection unit 100 includes a strategic plan management unit 110 for performing a quantity and schedule analysis for long-term department operation policy determination and a monthly plan management unit 120 for establishing a monthly department's own operation plan. The strategic plan management unit 110 manages a schedule generation result among the strategic simulation functions, and the monthly plan management unit 120 manages a quantity adjustment result, a monthly schedule, and a layout plan.

공정운영 제어부(200)는 블록의 작업일정, 작업셀(작업장), 작업팀 등의 결정 및 운반신청 등 지원업무를 수행하는 일일계획 관리부(210)와, 작업자에 작업물량을 지시하고 실적을 처리하는 배원기능을 수행하는 작업 지시부(220)를 포함한다. 일일계획 관리부(210)는 일일일정 및 배치계획 운반 신청서, 작업 지시부(220)는 인원배정 및 작업지시, 소지/도장실적 및 검사신청 자료를 관리한다.The process operation control unit 200 instructs the daily work management unit 210 to perform support tasks such as determining the work schedule of the block, work cell (workshop), work team, and transport application, and instructs the quantity of work to the worker and processes the results. It includes a work instruction unit 220 to perform the discharge function. Daily plan management unit 210 manages the daily schedule and batch plan transport application, work ordering unit 220 manages the assignment of personnel and work orders, possession / painting performance and inspection application data.

정보분석 실행부(300)는 작업결과에 따른 각종 분석 자료를 제공하는 통계 분석부(310), 도료사용량을 효과적으로 관리하는 도료 관리부(320), 신속하고 정확한 예산분계 기능을 제공하는 예산 관리부(330)를 포함한다. 통계 분석부(310)는 공정기간, 시퀀스 분석, 진도율 및 공정진행 현황, 도료 관리부(320)는 도료손실율 분석, 추가도료 원인 분석, 예산 관리부(330)는 원단위관리, 공수추정, 능력분석 등을 수행한다.The information analysis execution unit 300 includes a statistical analysis unit 310 for providing various analysis data according to the work result, a paint management unit 320 for effectively managing paint usage, and a budget management unit 330 for providing a quick and accurate budget division function. ). Statistical analysis unit 310 process period, sequence analysis, progress rate and process progress status, paint management unit 320 paint loss rate analysis, additional paint cause analysis, budget management unit 330 unit management, karate estimation, capacity analysis, etc. To perform.

공정데이터 관리부(400)는 운영정책 수집부(100), 공정운영 제어부(200), 정보분석 실행부(300) 등 외부와의 데이터 인터페이스 기능을 수행한다.The process data manager 400 performs a data interface function with the outside such as the operation policy collector 100, the process operation controller 200, and the information analysis execution unit 300.

공정실행 정보 데이터베이스(500)는 공정데이터 관리부(400)를 통해 운영정책 수집부(100), 공정운영 제어부(200), 정보분석 실행부(300) 등과 통신하여 결정변수(D510), 물량정보(D520), 블록정보(D530), 조직정보(D540), 블록도장관리도(D550), 실적정보(D560), 부하정보(D570), 면적정보(D580) 등을 등록하거나 출력한다. 공정데이터 관리부(400)는 블록도장관리도(D550), 조직정보(D540), 공정/일정/형상이나 기타 기초데이터 등을 공정실행 정보 데이터베이스(500)로 저장한다.
The process execution information database 500 communicates with the operation policy collection unit 100, the process operation control unit 200, the information analysis execution unit 300, and the like through the process data management unit 400, and the decision variable D510 and quantity information ( D520), block information (D530), organization information (D540), block painting management chart (D550), performance information (D560), load information (D570), area information (D580), or the like, are registered or output. The process data management unit 400 stores the block painting management chart D550, organization information D540, process / schedule / shape or other basic data as the process execution information database 500. FIG.

도 2는 본 발명의 일 실시예에 따른 월단위 공정 스케줄링 장치의 세부 구성도로서, 도 1에 나타난 월간계획 관리부(120)의 내부 구성을 예시하고 있다. 도 3 내지 도 5는 도 2에 나타난 장치의 동작을 설명하기 위한 화면 예시도이다.FIG. 2 is a detailed configuration diagram of a monthly process scheduling apparatus according to an embodiment of the present invention, illustrating an internal configuration of the monthly plan management unit 120 shown in FIG. 1. 3 to 5 are screen examples for explaining the operation of the apparatus shown in FIG.

월간계획 관리부(120)는 선박의 건조일정에 따라 생성된 블록별 중일정 정보와 블록도장관리도의 물량정보를 이용하여 월단위 도장 일정 및 배치계획을 수립하기 위한 것으로, 크게 중일정계획 관리부(130), 자체 월간계획 수립부(140), 자체 월간계획 조회부(150)로 구분된다.The monthly plan management unit 120 is to establish a monthly painting schedule and layout plan by using the middle schedule information for each block generated according to the ship's construction schedule and the quantity information of the block coating management chart, and the middle schedule plan management unit 130 ), It is divided into its own monthly plan establishment unit 140, its own monthly plan inquiry unit 150.

중일정계획 관리부(130)는 전체 선박건조 일정에 따라 생성된 중일정계획 데이터를 제공하고, 월간계획 일정 데이터를 반영하여 도장공정 중심으로 여유일이 확보되도록 중일정계획 데이터를 조정한다. 중일정계획 데이터는 선택된 월에 해당하는 전체 선박건조 중일정을 조회하거나 변동사항을 확인할 수 있도록 하는 데이터이다. 중일정계획 관리부(130)는 일정계획 추출부(131), 마스터 스케줄 관리부(132), 중일정 조정부(133)를 포함할 수 있다.The middle schedule plan management unit 130 provides the middle schedule plan data generated according to the entire ship building schedule, and adjusts the middle schedule plan data so that the spare days are secured around the painting process by reflecting the monthly plan schedule data. The mid-schedule plan data is the data that allows you to search the entire schedule of shipbuilding or check the changes for the selected month. The middle schedule manager 130 may include a schedule plan extractor 131, a master schedule manager 132, and a middle schedule adjuster 133.

일정계획 추출부(131)는 현재일 기준의 선박건조 중일정을 조회하여 중일정계획 데이터를 화면으로 제공한다. 사용자는 해당 화면에서, 이월물량, 실적현황, 선작업물량, 착수계획물량, 완료계획물량 등의 정보를 확인할 수 있다. 초기 중일정 저장 시, 저장일자 현재의 선박건조 중일정이 등록되며, 현재 월을 기준으로 선 1개월에서 후 2개월 기간(총 4개월) 기간 동안의 도장공정 일정과 선공정 일정을 공정실행 정보 데이터베이스(500)에 별도 저장할 수 있다. 예컨대, 2월에 초기 중일정을 저장하게 되면, 1월에서 4월까지의 중일정계획이 저장되는 것이다. 이와 같이 저장된 초기 중일정계획 데이터는 차후 사용자가 중일정 변경사항을 파악하기 위한 비교 기준이 된다.The schedule plan extractor 131 inquires the ship schedule of the current day based on the ship schedule and provides the schedule schedule data on the screen. On the screen, the user can check information such as carryover quantity, performance status, pre-work quantity, initiation plan quantity, and completion plan quantity. When saving the initial middle schedule, the shipbuilding middle schedule as of the storage date is registered, and the coating process schedule and preprocess schedule for the first one month to the next two months (total four months) based on the current month Can be stored separately at 500. For example, if the initial mid-day schedule is stored in February, the mid-day schedule from January to April is stored. The initial mid-schedule plan data stored in this way becomes a comparison standard for the user to identify mid-schedule changes.

마스터 스케줄 관리부(132)는 사용자가 원하는 호선의 블록공정을 조립에서 탑재까지 화면으로 보여준다. 해당 화면에는 각 공정이 서로 다른 형태의 이미지로 표시되며, 이미지의 길이는 공정기간에 따라 조정된다. 도 3은 블록별 공정기간 현황을 확인할 수 있는 마스터 스케줄 조회화면을 예시한 것이다. 예컨대, 해당 화면에서, 조립공정, 선행의장, 선행도장, 탑재공정 등 각 공정은 공정의 종류에 따라 서로 다른 이미지로 표현된다.The master schedule management unit 132 shows the block process of the ship desired by the user on the screen from assembly to mounting. The screen displays each process as an image of a different type, and the length of the image is adjusted according to the process period. 3 illustrates an example of a master schedule inquiry screen for checking a process period status for each block. For example, in the screen, each process such as an assembling process, a preceding design, a preceding painting, and a mounting process is represented by different images according to the type of the process.

중일정 조정부(133)는 자체 월간계획 수립부(140)가 제공하는 월간계획 일정 데이터를 반영하여 초기 중일정계획을 비롯한 기 등록된 중일정계획 데이터를 조정한다. 사용자는 중일정 조정부(133)가 제공하는 중일정 변경사항을 통해 기본 중일정과 현재 기준의 중일정을 비교해 도장공정을 기준으로 변경된 일정을 정리해 보여주며, 사용자가 블록의 변경 전/후 일정의 차이를 각 공정별로 확인할 수 있도록 한다.The middle schedule adjustment unit 133 adjusts the previously registered middle schedule data, including the initial middle schedule plan, by reflecting the monthly plan schedule data provided by the own monthly planner 140. The user compares the basic schedule and the current schedule's mid schedule through the mid schedule changes provided by the mid schedule adjustment unit 133, and shows the changed schedule based on the painting process, and the user changes the schedule before / after the block change. Make sure to check for each process.

자체 월간계획 수립부(140)는 전체 선박건조 일정에 따라 정해진 중일정계획 데이터를 통해 물량이 확정되는 월별 소지대기 블록들을 도장공정 내 작업셀들에 배치하되, 셀별 부하 균등화가 이루어지도록 자체 월간계획을 수립하여 월간계획 일정 데이터를 생성하고, 중일정계획 데이터를 조정할 수 있도록 월간계획 일정 데이터를 중일정계획 관리부(130)로 제공한다. 이러한 자체 월간계획 수립부(140)는 조건 선택부(141), 월간 배치계획 실행부(142), 월간 배치결과 관리부(143)를 포함할 수 있다.The monthly plan establishment unit 140 arranges monthly holding blocks in which the quantity is determined through the medium schedule plan data determined according to the entire ship construction schedule in the work cells in the painting process, but the monthly plan is made to equalize loads by cells. Produces monthly plan schedule data, and provides the monthly plan schedule data to the middle schedule plan management unit 130 to adjust the middle schedule plan data. The monthly plan establishment unit 140 may include a condition selection unit 141, a monthly batch plan execution unit 142, and a monthly batch result management unit 143.

조건 선택부(141)는 자체 월간계획을 수립할 계획기간을 등록하는 것으로, 자체 월간계획을 수립하기 위해 선택 기간에 해당하는 블록정보를 로딩한다.The condition selection unit 141 registers a planning period for establishing its own monthly plan, and loads block information corresponding to the selection period for establishing its own monthly plan.

월간 배치계획 실행부(142)는 1개월에 해당하는 블록을 작업셀에 배치하여 월간계획을 수립하는 것으로, 사용자 입력에 따라 셀별 부하 균형배치가 실행되도록 월별 소지대기 블록들을 도장공장의 작업셀들에 배치하여 월간계획 일정 데이터를 생성한다. 도 4는 배치계획 수립 화면을 예시한 것이다. 사용자는 해당 화면에서 도장공정을 위한 작업셀들에 블록을 배치함으로써 배치계획을 수립하며 잘못 배치하였을 경우 마우스를 드래그(drag)하여 배치된 블록을 작업셀 밖으로 끌어낸다. 예컨대, 사용자는 이전날/다음날 버튼(M141)을 이용하여 계획시작일로 이동한 후, 화면 하단의 소지대기 블록 영역(M142)에서 블라스팅 작업계획 블록을 선택한 후 블라스팅 작업셀(M143)에 배치한다. 해당일자의 배치계획 수립을 완료하면 다음날로 이동하여 배치를 계속하고, 1개월치 배치계획을 모두 수립한 후 수립된 1개월치 배치계획을 월간계획 일정 데이터로서 저장한다. 수립 중인 배치계획을 다시 처음부터 수립하고자 하는 경우 초기화 메뉴를 통해 이전에 배치한 결과를 모두 초기화할 수 있다.Monthly batch plan execution unit 142 is to establish a monthly plan by placing a block corresponding to a month in the work cell, the work cells of the painting plant waiting for the monthly holding blocks to execute the load balancing arrangement for each cell according to the user input To generate monthly plan schedule data. 4 illustrates an arrangement planning screen. The user establishes a layout plan by placing blocks in the work cells for the painting process on the corresponding screen. If the user places them incorrectly, the user drags the mouse out of the work cells by dragging the mouse. For example, the user moves to the planning start date by using the previous day / next day button M141, selects a blasting work plan block in the holding block area M142 at the bottom of the screen, and places the blasting work plan block in the blasting work cell M143. After completing the placement plan on the date, move on to the next day and continue the deployment. After completing the one-month deployment plan, save the established one-month deployment plan as monthly schedule schedule data. If you want to re-establish the layout plan being built from the beginning, you can initialize all the previously deployed results through the initialization menu.

아울러, 월간 배치계획 실행부(142)는 전체 선박건조 일정에 따른 중일정계획을 도장공장에 맞게 재조정하여 자체 월간계획을 수립할 수 있다. 이러한 경우, 월간 배치계획 실행부(142)는 선박건조 중일정계획을 로딩하여 화면으로 표시한다. 사용자가 해당 화면에서 일정을 변경하려는 블록을 선택하여 공정일자를 옮길 수 있으며, 월간 배치계획 실행부(142)는 이러한 중일정 조정에 따른 계획변경 여부를 반영하여 월간계획 일정 데이터를 다시 생성한다.In addition, the monthly layout plan execution unit 142 may re-adjust the mid-schedule plan according to the entire ship building schedule to the painting factory to establish its own monthly plan. In this case, the monthly batch plan execution unit 142 loads the ship building schedule schedule and displays it on the screen. The user can select a block to change the schedule on the screen to move the process date, the monthly batch planning execution unit 142 regenerates the monthly plan schedule data to reflect whether the plan changes due to such a mid-scaling adjustment.

월간 배치결과 관리부(143)는 월간 배치계획 실행부(142)로부터 월간계획 일정 데이터를 제공받아서 사용자 명령에 따라 가공한다. 예컨대, 사용자가 조회하고자 하는 계획기간을 선택한 후 확인버튼을 누르면 파일로 저장된 월간계획 일정 데이터를 불러와 화면으로 표시한다.The monthly batch result management unit 143 receives the monthly plan schedule data from the monthly batch plan execution unit 142 and processes it according to a user command. For example, if a user selects a planning period to be inquired and presses the OK button, the monthly plan schedule data stored as a file is called and displayed on the screen.

자체 월간계획 조회부(150)는 자체 월간계획 수립부(140)로부터 월간계획 일정 데이터를 제공받아서 호선별 또는 작업셀별로 소팅하여 표시한다. 이러한 자체 월간계획 조회부(150)는 자체 월간계획 수립부(140)가 제공하는 월간계획 일정 데이터를 호선별로 소팅하여 출력하는 호선별 월간계획 조회부(151), 월간계획 일정 데이터를 작업셀별로 소팅하여 출력하는 작업셀별 월간계획 조회부(152)를 포함할 수 있다. 도 5는 자체 월간계획 조회부(150)가 제공하는 자체 월간계획 호선별 조회화면을 예시한 것이다.
The self-monthly plan inquiry unit 150 receives the monthly plan schedule data from the self-monthly plan planning unit 140 and sorts and displays each line or work cell. The self monthly plan inquiry unit 150 sorts and outputs the monthly plan schedule data provided by the own monthly plan establishment unit 140 for each ship, and the monthly plan inquiry unit 151 for each ship, and the monthly plan schedule data for each work cell. It may include a monthly plan inquiry unit 152 for each work cell to be sorted and output. 5 is a diagram illustrating an inquiry screen for each monthly plan line provided by the monthly plan inquiry unit 150.

도 6은 본 발명의 일 실시예에 따른 일단위 공정 스케줄링 장치의 세부 구성도로서, 도 1에 나타난 일일계획 관리부(210)의 내부 구성을 예시하고 있다. 도 7 내지 도 10은 도 6에 나타난 장치의 동작을 설명하기 위한 화면 예시도이다.6 is a detailed configuration diagram of a daily process scheduling apparatus according to an embodiment of the present invention, illustrating an internal configuration of the daily plan management unit 210 illustrated in FIG. 1. 7 to 10 are screen views for explaining the operation of the device shown in FIG.

일일계획 관리부(210)는 블록배치 실행부(240), 블록정보 관리부(250)를 포함하며, 추가적으로 기상정보 설정부(231), 기간정보 설정부(232), 셀별 입고계획 분석부(233)를 포함할 수 있다.The daily plan management unit 210 includes a block batch execution unit 240 and a block information management unit 250, and additionally, a weather information setting unit 231, a period information setting unit 232, and a receipt plan analysis unit for each cell 233. It may include.

블록배치 실행부(240)는 사용자가 원하는 블록을 작업셀에 배치하여 그 블록에 대한 일정과 해당 작업팀에 대한 정보를 생성하는 것으로, 셀 운영계획 수립, 블록 작업팀 지정, 운반신청 등의 기능을 수행한다. 여기서, 월단위의 소지대기 블록들 중 각 일자의 배치대상으로 선정된 블록들이 사용자 입력에 따라 도장공장 내 작업셀로 배치됨에 따라 일별 배치계획 수립 데이터가 생성된다. 이러한 블록배치 실행부(240)는 배치모드 설정부(241), 일별 배치계획 실행부(242), 일별 배치결과 관리부(243)를 포함할 수 있다.The block arrangement execution unit 240 generates a schedule for the block and information on the work team by placing a block desired by the user in a work cell, and establishes a cell operation plan, designates a block work team, and a transport application. Do this. Here, daily batch planning data is generated as blocks selected as batch targets for each day of the monthly waiting blocks are placed into work cells in the paint shop according to user input. The block batch execution unit 240 may include a batch mode setting unit 241, a daily batch plan execution unit 242, and a daily batch result management unit 243.

배치모드 설정부(241)는 도장공정을 수행하기 위한 작업셀들, 스톡장, 블록출고영역, 소지대기 블록 영역을 포함하는 일별 배치계획 수립 화면을 로딩하여 화면으로 표시한다. 도 7은 배치모드 설정부(241)가 제공하는 배치화면을 예시한 것이다. 배치화면은 크게 도장공정(블라스팅, 페인팅)의 작업셀(A 내지 G), 스톡장(H, I, J), 블록 출고 영역(K), 소지대기 블록 영역(L) 등으로 나누어지며, 그 외 배치계획 수립에 필요한 각종 기능 버튼으로 구성된다. 도 7에서, A, B, C는 블라스팅 1공장, 2공장, 3공장이고, D, E, F, G는 페이팅 1공장, 2공장, 3공장, 4공장이다. H는 가변 스톡장, I는 스톡장, J는 선행의장 스톡장이다. 가변 스톡장(H)은 배치화면의 가운데 부분에 위치한 타원형의 스톡장으로, 지정된 위치가 아닌 곳에서 작업셀에 블록이 입고될 경우 이를 운반신청 하기 위해 추가된 영역이다.The batch mode setting unit 241 loads and displays a daily batch plan establishment screen including work cells, a stock sheet, a block shipping area, and a holding block area for performing a painting process. 7 illustrates an arrangement screen provided by the arrangement mode setting unit 241. The layout screen is largely divided into work cells (A to G) of the painting process (blasting, painting), stock sheets (H, I, J), block delivery area (K), holding block area (L), and the like. In addition, it consists of various function buttons necessary for establishment of layout plan. In FIG. 7, A, B, and C are blasting plants 1, 2, and 3, and D, E, F, and G are painting plants 1, 2, 3, and 4, respectively. H is the variable stock, I is the stock, and J is the leading stock. Variable stock field (H) is an oval stock field located in the center of the batch screen, the area is added to apply for transport if a block is received in the work cell in a place other than the designated position.

일별 배치계획 실행부(242)는 배치모드 설정부(241)가 제공하는 일별 배치계획 수립 화면에서, 소지대기 블록 영역에 표시된 배치대상 블록들을 사용자 입력에 따라 작업셀들로 배치하여 일별 배치계획 수립 데이터를 생성한다. 사용자는 블록을 작업셀에 배치하기 위하여, 소지대기 블록 영역(L)에서 대상블록을 선정한 후 선정한 대상블록을 마우스로 드래그하여 배치할 작업셀로 이동시킨다. 대상블록을 작업셀에 배치한 후 선택된 대상블록을 다음날 동일 위치에 저장하거나, 블록회전, 작업공정 선택, 전담조직 선택 등의 추가 동작을 수행할 수 있다. 일별 배치계획 수립 데이터는 배치현황, 입고정보 및 운반신청정보 등을 포함할 수 있다. 배치현황은 금일야간 블록입고 계획을 위해 야간 입고 전 상황으로 배치화면을 구성한 것이다. 배치현황 정리가 끝나면 사용자가 입고방향을 지정하여 야간에 입고될 블록이 현재 위치에서 어느 지점으로 이동하는지에 대한 세부위치를 입력하게 되며, 이후 블록의 입고순서를 지정한다. 도 8은 배치현황 정리, 입고방향 지정, 입고순서 지정의 과정을 거친 배치계획 출력 화면을 예시한 것이다.The daily batch plan execution unit 242 establishes the daily batch plan by arranging the batch target blocks displayed in the holding block area as work cells according to a user input on the daily batch plan setting screen provided by the batch mode setting unit 241. Generate data. In order to place the block in the work cell, the user selects the target block in the holding block area L, and then drags the selected target block to the work cell to be placed. After placing the target block in the work cell, the selected target block may be stored in the same location the next day, or additional operations such as block rotation, work process selection, and dedicated organization selection may be performed. Daily batch planning data may include batch status, goods receipt information and transport application information. The batch status is a batch screen composed of all the night before the arrival of the block for planning plans today. After arranging the arrangement status, the user specifies the goods receipt direction and inputs the detailed position on which point the block to be received at night moves from the current location, and then specifies the goods receipt order of the blocks. Figure 8 illustrates a batch plan output screen that went through the process of the arrangement status arrangement, receipt direction designation, receipt order designation.

일별 배치결과 관리부(243)는 일별 배치계획 실행부(242)가 제공하는 일별 배치계획 수립 데이터를 외부와 공유하여 배치대상 블록들 각각의 공정현황 데이터를 생성한다.The daily batch result management unit 243 shares the daily batch planning data provided by the daily batch plan execution unit 242 with the outside to generate process status data of each of the batch blocks.

블록정보 관리부(250)는 블록배치 실행부(240)의 요청에 따라 일별 배치계획 수립 데이터를 생성하는데 필요한 블록정보 및 배치환경정보를 생성하여 블록배치 실행부(240)로 제공한다. 이러한 블록정보 관리부(250)는 기본 블록정보 설정부(251), 블록정보 변경부(252), 배치환경 연동부(253)를 포함할 수 있다.The block information manager 250 generates block information and batch environment information necessary for generating daily batch planning data according to a request of the block batch executing unit 240 and provides the block batch executing unit 240 to the block batch executing unit 240. The block information management unit 250 may include a basic block information setting unit 251, a block information changing unit 252, and a layout environment linking unit 253.

기본 블록정보 설정부(251)는 배치계획에 필요한 블록정보를 관리하는 것으로서, 소지대기 블록들의 식별정보 및 형상정보를 포함한 블록정보를 등록하여 일별 배치계획 수립 화면에 반영한다. 도 9는 기본 블록정보 설정부(251)가 제공하는 형상 및 블록정보 수정화면을 예시한 것이다. 사용자는 해당 화면에서 소지대상 블록의 형상 등을 자신이 원하는 형태로 변경할 수 있다. 도 9에서, A는 소지대기 블록들의 정보를 나타내는 부분이고, B는 후보블록의 형상을, C는 선삽입된 형태의 기본 블록형상정보를 나타낸다.The basic block information setting unit 251 manages the block information necessary for the layout plan, and registers block information including the identification information and the shape information of the holding blocks and reflects it on the daily layout plan establishment screen. 9 illustrates an example of a shape and block information modification screen provided by the basic block information setting unit 251. The user may change the shape of the block to be possessed on the screen as desired. In FIG. 9, A is a part indicating information of the holding blocks, B is the shape of the candidate block, C is the basic block shape information of the pre-inserted form.

블록정보 변경부(252)는 소지대기 블록들의 삽입, 검색, 생성, 정보추가, 형상복원에 따라 등록된 블록정보를 갱신하여 일별 배치계획 수립 화면에 반영한다. 예컨대, 블록삽입은 소지대기 블록에 배치하고자 하는 블록이 없을 경우 원하는 블록을 추가 배치하는 기능이고, 블록검색은 배치화면에 배치된 블록들 중 사용자가 원하는 블록을 찾는 기능이다.The block information changing unit 252 updates the registered block information according to the insertion, search, generation, addition of information, and restoration of the waiting blocks, and reflects them on the daily arrangement planning screen. For example, block insertion is a function of additionally placing a desired block when there is no block to be placed in the holding block, and block search is a function of searching for a block desired by a user among blocks arranged on the layout screen.

배치환경 연동부(253)는 각 블록의 공정현황 데이터를 이용해 소지대기 블록들의 목록을 관리하고, 배치환경정보를 관리하여 일별 배치계획 수립 화면에 반영한다. 배치환경 연동부(253)는 소지대기 블록들 중 대상블록을 선정하며, 품질검사가 완료된 블록들을 선택하여 대상블록 리스트를 구성하고, 이를 배치계획에 반영한다. 도 10은 배치환경 연동부(253)가 제공하는 소지대기 블록 관리화면을 예시한 것이다.The batch environment interworking unit 253 manages a list of holding blocks by using process status data of each block, and manages batch environment information and reflects them on the daily batch planning screen. The batch environment interworking unit 253 selects a target block among the holding blocks, selects blocks for which quality inspection is completed, constructs a target block list, and reflects the same in the layout plan. 10 illustrates a holding block management screen provided by the deployment environment interworking unit 253.

예컨대, 배치환경 연동부(253)는 품질검사가 완료된 블록들 중 현재일부터 15일전까지의 검사완료 블록정보를 가져오고, 여기서 기 배치된 블록, 이미 대상블록으로 선택된 블록을 제외시킨 후 남은 검사완료 블록들 중 선각 및 의장완료블록을 정해진 위치(A)에 표시하며, 나머지 검사완료 블록들은 다른 위치(B)에 표시한다. 사용자가 품질검사현황에서 추가할 블록을 더블 클릭으로 선택한 후 추가 버튼(C)을 클릭하면, 우측 대상블록 리스트에 선택한 블록이 추가된다. 사용자는 삭제/저장 버튼(D)을 통해 대상블록 리스트에 특정 블록을 삽입하거나 현재의 대상블록 리스트를 검사일과 함께 저장할 수 있다.For example, the batch environment interworking unit 253 imports inspection completed block information from the current day to 15 days before among the blocks for which quality inspection is completed, and the remaining inspection after excluding the blocks already selected as blocks that are already arranged as target blocks. Among the completed blocks, the hull angle and the design completion block are displayed at a predetermined position (A), and the remaining inspection completed blocks are displayed at another position (B). If the user double-clicks a block to add in the quality inspection status and clicks the add button (C), the selected block is added to the right target block list. The user may insert a specific block in the target block list or store the current target block list with the inspection date through the delete / store button D.

기상정보 설정부(231)는 지정된 기간의 기상정보를 등록하여 일별 배치계획 수립 시 블록배치 실행부(240)로 사용자가 필요로 하는 기상정보를 제공한다. 기상정보는 기상청의 일기정보로서, 특정지역의 기상정보, 주간예보, 단기예보, 기상특보, 태풍정보 등을 포함한다.The weather information setting unit 231 registers weather information of a specified period and provides the weather information required by the user to the block batch execution unit 240 when establishing a daily arrangement plan. The weather information is weather information of the Korea Meteorological Agency, and includes weather information, weekly forecast, short-term forecast, weather report, typhoon information, etc. of a specific region.

기간정보 설정부(232)는 블록배치 실행부(240)의 일별 배치계획 수립 시 사용자 입력에 따라 대상일자를 선택하여 등록한다.The period information setting unit 232 selects and registers a target date according to a user input when establishing a daily arrangement plan of the block batch execution unit 240.

셀별 입고계획 분석부(233)는 블록배치 실행부(240)가 제공하는 일별 배치계획 수립 데이터로부터 금일소지 입고 블록정보, 내일소지 입고 블록정보, 소지대기 블록정보, 블록의 물량 및 출고일 등을 확인하여 화면으로 표시한다.
Receiving plan analysis unit 233 for each cell checks the receipt of block information holding information today, the receipt of block holding information tomorrow, holding block information holding, block quantity and shipment date, etc. from the daily batch planning data provided by the block batch execution unit 240 To display on the screen.

이상 첨부된 도면을 참조하여 본 발명의 실시예를 설명하였지만, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자는 본 발명이 그 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다.Although the embodiments of the present invention have been described above with reference to the accompanying drawings, those skilled in the art to which the present invention pertains may implement the present invention in other specific forms without changing the technical spirit or essential features thereof. I can understand that.

따라서, 이상에서 기술한 실시예들은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이므로, 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 하며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다.Therefore, it should be understood that the above-described embodiments are provided so that those skilled in the art can fully understand the scope of the present invention. Therefore, it should be understood that the embodiments are to be considered in all respects as illustrative and not restrictive, The invention is only defined by the scope of the claims.

Claims (6)

전체 선박건조 일정에 따라 생성된 중일정계획 데이터를 제공하고, 월간계획 일정 데이터를 반영하여 도장공정 중심으로 여유일이 확보되도록 상기 중일정계획 데이터를 조정하는 중일정계획 관리부;
전체 선박건조 일정에 따라 정해진 상기 중일정계획 데이터를 통해 물량이 확정되는 월별 소지대기 블록들을 도장공정 내 작업셀들에 배치하되, 셀별 부하 균등화가 이루어지도록 자체 월간계획을 수립하여 상기 월간계획 일정 데이터를 생성하고, 상기 중일정계획 데이터를 조정할 수 있도록 상기 월간계획 일정 데이터를 상기 중일정계획 관리부로 제공하는 자체 월간계획 수립부; 및
상기 자체 월간계획 수립부로부터 상기 월간계획 일정 데이터를 제공받아서 호선별 또는 작업셀별로 소팅하여 표시하는 자체 월간계획 조회부를 포함하는 도장공정을 위한 월단위 공정 스케줄링 장치.
A middle schedule plan management unit which provides the middle schedule plan data generated according to the entire ship construction schedule, and adjusts the middle schedule plan data so as to secure a spare date centering on the coating process by reflecting the monthly plan schedule data;
The monthly plan schedule data is arranged by arranging monthly holding blocks in which the quantity is determined through the medium schedule plan data determined according to the entire ship construction schedule in the work cells in the painting process, and establishing a monthly plan for equalizing loads by cell. A monthly plan establishment unit which provides the monthly plan schedule data to the middle schedule plan management unit so as to generate and adjust the middle schedule plan data; And
A monthly process scheduling apparatus for a painting process including a monthly plan inquiry unit for receiving the monthly plan schedule data from the own monthly plan establishment unit and sorting and displaying each line or work cell.
제1항에 있어서, 상기 자체 월간계획 수립부는,
자체 월간계획을 수립할 계획기간을 등록하는 조건 선택부;
사용자 입력에 따라 셀별 부하 균형배치가 실행되도록 상기 월별 소지대기 블록들을 도장공장의 작업셀들에 배치하여 상기 월간계획 일정 데이터를 생성하는 월간 배치계획 실행부; 및
상기 월간계획 일정 데이터를 제공받아서 사용자 명령에 따라 가공하는 월간 배치결과 관리부를 포함하는 도장공정을 위한 월단위 공정 스케줄링 장치.
The method of claim 1, wherein the monthly plan establishment unit,
A condition selection unit that registers a planning period for establishing a monthly plan of its own;
A monthly batch plan execution unit for generating the monthly plan schedule data by arranging the monthly holding blocks in the work cells of the paint shop to execute the load balancing arrangement for each cell according to a user input; And
A monthly process scheduling apparatus for a painting process including a monthly batch result management unit for receiving the monthly plan schedule data and processing according to a user command.
월단위의 소지대기 블록들 중 각 일자의 배치대상으로 선정된 블록들을 사용자 입력에 따라 도장공장 내 작업셀로 배치하여 일별 배치계획 수립 데이터를 생성하는 블록배치 실행부; 및
상기 블록배치 실행부의 요청에 따라 상기 일별 배치계획 수립 데이터를 생성하는데 필요한 블록정보 및 배치환경정보를 생성하여 제공하는 블록정보 관리부를 포함하는 도장공정을 위한 일단위 공정 스케줄링 장치.
Block batch execution unit for generating the daily batch planning data by arranging the blocks selected for the batch of each day of the monthly holding block to the work cell in the painting factory according to the user input; And
And a block information management unit for generating and providing block information and batch environment information necessary for generating the daily batch planning data according to a request of the block batch executing unit.
제3항에 있어서,
지정된 기간의 기상정보를 등록하여 일별 배치계획 수립 시 상기 블록배치 실행부로 상기 기상정보를 제공하는 기상정보 설정부;
상기 블록배치 실행부의 일별 배치계획 수립 시 사용자 입력에 따라 대상일자를 선택하는 기간정보 설정부; 및
상기 블록배치 실행부가 제공하는 상기 일별 배치계획 수립 데이터로부터 금일소지 입고 블록정보, 내일소지 입고 블록정보, 소지대기 블록정보, 블록의 물량 및 출고일을 확인하여 표시하는 셀별 입고계획 분석부를 포함하는 도장공정을 위한 일단위 공정 스케줄링 장치.
The method of claim 3,
A weather information setting unit that registers weather information of a specified period and provides the weather information to the block batch execution unit when establishing a daily arrangement plan;
A period information setting unit for selecting a target date according to a user input when establishing a daily batch plan of the block batch executing unit; And
Painting process including a cell-specific receipt plan analysis unit to check and display the stock receipt block information, the stock receipt block information, the holding block information, the quantity of the block and the date of shipment from the daily batch planning data provided by the block batch execution unit Daily process scheduling apparatus for the.
제3항에 있어서, 상기 블록배치 실행부는,
도장공정을 수행하기 위한 작업셀들, 스톡장, 블록출고영역, 소지대기 블록 영역을 포함하는 일별 배치계획 수립 화면을 로딩하여 표시하는 배치모드 설정부;
상기 배치모드 설정부가 제공하는 상기 일별 배치계획 수립 화면에서, 상기 소지대기 블록 영역에 표시된 배치대상 블록들을 사용자 입력에 따라 작업셀들로 배치하여 배치현황, 입고정보 및 운반신청정보를 포함하는 상기 일별 배치계획 수립 데이터를 생성하는 일별 배치계획 실행부; 및
상기 일별 배치계획 실행부가 제공하는 상기 일별 배치계획 수립 데이터를 외부와 공유하여 상기 배치대상 블록들 각각의 공정현황 데이터를 생성하는 일별 배치결과 관리부를 포함하는 도장공정을 위한 일단위 공정 스케줄링 장치.
The method of claim 3, wherein the block arrangement execution unit,
A batch mode setting unit configured to load and display a daily batch plan establishment screen including work cells for performing a painting process, a stock sheet, a block release area, and a holding block area;
In the daily batch plan establishment screen provided by the batch mode setting unit, the batch target blocks displayed in the holding block area are arranged as work cells according to a user input to include the batch status, goods receipt information, and transport request information. A daily batch planning execution unit for generating batch planning data; And
And a daily batch result management unit for generating process status data of each of the blocks to be disposed by sharing the daily batch planning data provided by the daily batch plan executing unit with the outside.
제3항에 있어서, 상기 블록정보 관리부는,
상기 소지대기 블록들의 식별정보 및 형상정보를 포함한 블록정보를 등록하여 상기 일별 배치계획 수립 화면에 반영하는 기본 블록정보 설정부;
상기 소지대기 블록들의 삽입, 검색, 생성, 정보추가, 형상복원에 따라 상기 등록된 블록정보를 갱신하여 상기 일별 배치계획 수립 화면에 반영하는 블록정보 변경부; 및
각 블록의 공정현황 데이터를 이용해 상기 소지대기 블록들의 목록을 관리하고, 상기 배치환경정보를 관리하여 상기 일별 배치계획 수립 화면에 반영하는 배치환경 연동부를 포함하는 도장공정을 위한 일단위 공정 스케줄링 장치.
The method of claim 3, wherein the block information management unit,
A basic block information setting unit which registers block information including identification information and shape information of the holding blocks and reflects them on the daily arrangement planning screen;
A block information change unit for updating the registered block information according to the insertion, search, generation, information addition, and restoration of the holding blocks to be reflected on the daily arrangement planning screen; And
And a batch environment linkage unit configured to manage the list of the holding blocks using process status data of each block, and manage the batch environment information and reflect the batch environment information on the daily batch planning screen.
KR1020100020609A 2010-03-09 2010-03-09 Process scheduling apparatus for painting process KR20110101546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100020609A KR20110101546A (en) 2010-03-09 2010-03-09 Process scheduling apparatus for painting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100020609A KR20110101546A (en) 2010-03-09 2010-03-09 Process scheduling apparatus for painting process

Publications (1)

Publication Number Publication Date
KR20110101546A true KR20110101546A (en) 2011-09-16

Family

ID=44953545

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100020609A KR20110101546A (en) 2010-03-09 2010-03-09 Process scheduling apparatus for painting process

Country Status (1)

Country Link
KR (1) KR20110101546A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200032908A (en) * 2018-09-19 2020-03-27 오스템임플란트 주식회사 Method, System and Recording Medium For Establishing Business Plan
KR20240044125A (en) 2022-09-28 2024-04-04 주식회사 현대미포조선 Automatic Painting Equipment Control System

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200032908A (en) * 2018-09-19 2020-03-27 오스템임플란트 주식회사 Method, System and Recording Medium For Establishing Business Plan
KR20240044125A (en) 2022-09-28 2024-04-04 주식회사 현대미포조선 Automatic Painting Equipment Control System

Similar Documents

Publication Publication Date Title
Szalavetz Industry 4.0 in ‘factory economies’
Rebentisch et al. Agility factors and their impact on product development performance
Rosa et al. Lean accounting: Accounting contribution for lean management philosophy
CN115660261B (en) Production order information processing method, computer device and storage medium
CN106156987A (en) The equalization methods of inventory variance and device
SANIUK et al. Management of production orders in metalworking production
CN110796416A (en) Industrial networking based order processing method and computer storage medium
Sahin et al. A simulation case study on supply chain management of a construction firm adopting cloud computing and RFID
Florentina Abreu et al. Collaborative process mapping to improve work instructions and standardized work
Monostori et al. Digital enterprise solution for integrated production planning and control
KR100944760B1 (en) Online processing system of value engineering process
KR20110101546A (en) Process scheduling apparatus for painting process
Mitsuyuki et al. Design of production strategy considering the cutting peak demand of electricity in the shipbuilding industry
Hwang et al. Automation of block assignment planning using a diagram-based scenario modeling method
US20130205224A1 (en) Electronic data plate system for collaboration amongst multiple disparate parties
Harjunkoski et al. Industrial scheduling solution based on flexible heuristics
JP2006244000A (en) Process management device and process management program
KR20110045496A (en) Process management apparatus for painting process
KR20130001757A (en) Simulation system for valuating a middle schedule
KR102018162B1 (en) System for managing workfront and blocking point related with piping insulation and method thereof
Teufl et al. Optimised–developing a state of the art system for production planning for industry 4.0 in the construction industry using simulation-based optimisation
Kim et al. Computational shipyard dynamics
US20040103015A1 (en) Method and system for production planning
Garner et al. Leveraging industrie 4.0 to extend Lean Manufacturing gains
Bányai Cloud logistics

Legal Events

Date Code Title Description
WITN Withdrawal due to no request for examination