KR20110095693A - Coupling apparatus of concrete pile - Google Patents

Coupling apparatus of concrete pile Download PDF

Info

Publication number
KR20110095693A
KR20110095693A KR1020100015301A KR20100015301A KR20110095693A KR 20110095693 A KR20110095693 A KR 20110095693A KR 1020100015301 A KR1020100015301 A KR 1020100015301A KR 20100015301 A KR20100015301 A KR 20100015301A KR 20110095693 A KR20110095693 A KR 20110095693A
Authority
KR
South Korea
Prior art keywords
head
bracket
pile
tip
cap
Prior art date
Application number
KR1020100015301A
Other languages
Korean (ko)
Other versions
KR101174273B1 (en
Inventor
최성희
Original Assignee
최성희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최성희 filed Critical 최성희
Priority to KR1020100015301A priority Critical patent/KR101174273B1/en
Publication of KR20110095693A publication Critical patent/KR20110095693A/en
Application granted granted Critical
Publication of KR101174273B1 publication Critical patent/KR101174273B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B7/00Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
    • F16B7/18Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE: A coupling apparatus for a concrete pile is provided to simplify the construction of a pile by easily assembling a tip coupling unit and a head coupling unit using a bolt and a nut. CONSTITUTION: A coupling apparatus for a concrete pile comprises a tip member(200), a head member(300), a bolt(400), and a nut(410). The tip member comprises a tip coupling unit(220) and a guide protrusion. The tip coupling unit a tip cap(210) and a through hole. The tip cap covers the tip of a concrete pile(100). The guide protrusion is protruded along the outer edge of the tip cap. The head member comprises a head cap(310), a head coupling unit, and a guide groove. The head cap covers the head of the pile. The head coupling unit is protruded from the outer edge of the head cap and has multiple through holes. The guide groove is formed in the top end of the head coupling unit and corresponds to the guide protrusion of the tip member. The bolt is coupled to the nut to couple the tip member and the head member.

Description

콘크리트 말뚝의 이음장치{Coupling apparatus of concrete pile}Coupling apparatus of concrete pile

본 발명은 콘크리트 말뚝의 이음장치에 관한 것으로, 말뚝의 선단금구와 두부금구에 각각 설치되는 선단결합부와 두부결합부를 볼트로 결합하여 이음 시공하고자 하는 말뚝을 매우 간단하게 연결해줄 수 있는 콘크리트 말뚝과 말뚝의 이음장치에 관한 것이다.
The present invention relates to a joint device for a concrete pile, and the concrete pile that can connect the pile to be connected very simply by connecting the head coupling portion and the head coupling portion installed in the front end bracket and the head bracket of the pile with bolts and It relates to the joint of the pile.

일반적으로 토목공사나 건설공사를 할 때 연약 지반이 있는 경우 콘크리트말뚝을 암반까지 항타한 후 그 위에 구조물을 시공하여 왔다.In general, when there is a soft ground in civil engineering or construction work, the concrete pile has been driven to the rock and then the structure has been constructed on it.

이러한 콘크리트말뚝은 그 길이가 한정되어 있기 때문에 다수의 콘크리트말뚝을 수직 이음시공하면서 연약지반에 타설해야 한다.Since these concrete piles have a limited length, they must be laid on the soft ground while vertically constructing a plurality of concrete piles.

이때 콘크리트말뚝의 선단 및 두부에는 콘크리트말뚝을 보호할 수 있도록 금속재질의 선단캡과 두부캡이 설치되어 있다.At this time, the front end cap and the head cap of the metal pile are installed to protect the concrete pile and the head cap.

종래에는 상기와 같은 콘크리트말뚝을 이음 시공하기 위해서 선단캡과 두부캡을 맞닿도록 위치한 상태에서 선단캡과 두부캡의 접합부위를 현장 용접하여 콘크리트말뚝을 연결하였으나, 이와 같이 선단캡과 두부캡을 용접 연결할 경우에는 기후조건이나 현장조건, 작업자의 숙련도 등에 따라 품질이 좌우되어 일정한 품질을 유지할 수 없는 문제점이 있다.
Conventionally, in order to joint the concrete piles as described above, in the state where the tip caps and the head caps are in contact with each other, the joints of the tip caps and the head caps are welded on site, but the concrete piles are connected. When connecting, there is a problem in that the quality is dependent on the weather condition, the site condition, the skill of the worker, and the like, and thus the quality cannot be maintained.

상기와 같은 문제점을 해결하기 위한 본 발명의 목적은, 두부캡과 선단캡에 구비된 두부결합부와 선단결합부를 볼트 및 너트로 결합함으로써 말뚝이 견고히 결합되고 시공이 간편하여 누구나 손쉽게 말뚝을 연결해줄 수 있으며, 가이드돌기와 가이드홈을 통해 말뚝의 중심축을 간단하게 일치시켜 빠른 시공이 가능하도록 하는 콘크리트 말뚝의 이음장치를 제공함에 있다.
An object of the present invention for solving the above problems, by combining the head and the head coupling portion and the tip coupling portion provided in the head cap and the tip cap with bolts and nuts, the pile is firmly coupled and the construction is easy, anyone can easily connect the pile In addition, through the guide protrusion and the guide grooves to provide a joint device for the concrete pile to simply match the central axis of the pile to enable fast construction.

상기한 바와 같은 목적을 달성하고 종래의 결점을 제거하기 위한 과제를 수행하는 본 발명은, 내부가 중공 된 말뚝의 선단에 설치되는 선단금구와, 상기 선단금구에 맞물려 결합될 수 있도록 두부에 설치되는 두부금구를 포함하는 말뚝 이음장치에 있어서, 상기 말뚝의 선단을 덮어주도록 설치되고 내부가 중공되어 있는 선단캡과, 상기 선단캡의 내측 가장자리를 따라 수직방향으로 일정 높이까지 돌출되도록 설치되고, 수평방향으로 다수의 관통홀이 형성되어 있는 선단결합부와, 상기 선단캡의 외측 가장자리를 따라 소정의 간격으로 돌출 형성되어 선단금구와 두부금구의 결합 시 용이하게 적정위치에 위치될 수 있도록 하는 가이드돌기를 포함하여 구성되는 선단금구; 상기 말뚝의 두부를 덮어주도록 설치되고 내부가 중공되어 있는 두부캡과, 상기 두부캡의 외측 가장자리를 따라 수직방향으로 일정 높이까지 돌출되도록 설치되고, 수평방향으로 다수의 관통홀이 형성되어 있는 두부결합부와, 상기 두부결합부의 상단에 상기 가이드돌기가 삽입될 수 있도록 형성되어 있는 가이드홈을 포함하여 구성되는 두부금구; 상기 선단금구의 관통홀에 설치되는 너트와 상기 두부금구의 관통홀과 선단금구의 관통홀에 삽입되어 상기 너트에 결합됨으로써 선단금구와 두부금구를 체결해주는 볼트를 포함하여 구성되는 것을 특징으로 한다.The present invention to achieve the object as described above and to perform the problem for eliminating the conventional drawbacks, the inner end is installed on the tip of the hollow pile, and the head is provided to be coupled to the front end engaging In the piling device comprising a head bracket, the front end cap is installed to cover the front end of the pile and is hollow so as to protrude to a predetermined height in a vertical direction along the inner edge of the front end cap, the horizontal direction And a guide protrusion for protruding at predetermined intervals along the outer edge of the tip cap and the tip engaging portion having a plurality of through holes formed so as to be easily positioned at an appropriate position when the tip bracket and the head bracket are coupled. A tip bracket configured to include; The head cap is installed to cover the head of the pile and is hollow inside, and the head cap is installed to protrude to a predetermined height in the vertical direction along the outer edge of the head cap, and the head coupling is formed with a plurality of through holes in the horizontal direction. A head bracket comprising a part and a guide groove formed to insert the guide protrusion at an upper end of the head coupling part; The nut is installed in the through hole of the tip bracket and the through hole of the head bracket and the through hole of the tip bracket are coupled to the nut to be coupled to the nut to fasten the tip bracket and the head bracket.

한편, 본 발명은 내부가 중공 된 말뚝의 선단에 설치되는 선단금구의 선단결합부와, 상기 선단금구에 맞물려 결합될 수 있도록 두부에 설치되는 두부금구의 두부결합부를 포함하는 말뚝과 말뚝 수직 이음장치에 있어서, 상기 선단금구와 두부금구는 상호 대칭되는 요철 형태로 형성되고, 말뚝과 말뚝을 연결 시 선단금구와 두부금구가 서로 맞물려 결합되는 것을 특징으로 한다.On the other hand, the present invention is a pile and pile vertical jointing device including a head coupling portion of the head bracket is installed on the head to be coupled to the front end bracket and the front end bracket is installed on the tip of the hollow hollow inside; In the front end bracket and the head bracket is formed in a concave-convex shape that is symmetrical to each other, characterized in that the front end bracket and the head bracket is coupled to each other when connecting the pile and the pile.

또한 선단금구는 상기 말뚝의 선단에 설치되고 내부가 중공되어 있는 선단캡과, 상기 선단캡의 중심부를 따라 소정의 간격으로 수직방향으로 일정 높이까지 돌출되도록 설치되고 수평방향으로 다수의 관통홀이 형성되어 있는 선단결합부와, 상기 선단캡의 외측 가장자리에 돌출 형성되어 선단금구와 두부금구의 결합 시 적정위치에 위치될 수 있도록 하는 가이드돌기를 포함하여 구성되고, 상기 두부금구는, 상기 말뚝의 두부에 설치되고 내부가 중공되어 있는 두부캡과, 상기 선단결합부가 삽입될 수 있도록 두부캡의 내측 가장자리 및 외측 가장자리에 수직방향으로 일정 높이까지 돌출되도록 형성되고 수평방향으로 다수의 관통홀이 형성되는 한 쌍의 두부결합부와, 상기 가이드돌기에 대응되도록 외측 가장자리에 설치된 두부결합부의 상부에 형성되는 가이드홈을 포함하여 구성되며, 상기 두부금구의 내측 가장자리에 형성된 두부결합부의 관통홀 설치되는 너트와, 상기 두부금구의 외측 가장자리에 형성된 두부결합부의 관통홀을 통해 삽입되어 상기 선단금구의 관통홀을 관통하여 상기 너트에 결합되는 볼트에 의해 체결되는 것을 특징으로 한다.In addition, the distal end bracket is installed at the tip of the pile and the inside of the hollow end cap, and is installed to protrude up to a predetermined height in the vertical direction at a predetermined interval along the center of the tip cap and a plurality of through holes in the horizontal direction is formed And a guide protrusion configured to protrude from an outer edge of the tip cap and to be positioned at an appropriate position when the tip bracket and the head bracket are coupled to each other. The head bracket includes the head of the pile. As long as the head cap is installed at the inside of the head cap and protrudes to a certain height in the vertical direction to the inner edge and the outer edge of the head cap so that the distal end portion can be inserted therein and a plurality of through holes are formed in the horizontal direction. The head coupling portion of the pair, and the upper portion of the head coupling portion installed on the outer edge to correspond to the guide projection It is configured to include a guide groove, the through-hole of the head coupling portion formed in the through hole of the head coupling portion formed on the inner edge of the head bracket, inserted through the through hole of the head coupling portion formed in the outer edge of the head bracket through the through hole of the tip bracket It is characterized by being fastened by a bolt coupled to the nut through.

또한 상기 상기 선단결합부와 두부결합부는 적어도 3개 이상의 조각으로 분리되도록 설치 구성되는 것을 특징으로 한다.
In addition, the tip coupling portion and the head coupling portion is characterized in that the installation is configured to be separated into at least three or more pieces.

이상에서 설명한 바와 같이 본 발명에 의하면, 선단결합구와 두부결합구를 볼트 및 너트를 이용하여 손쉽게 조립함으로써 말뚝 이음시공이 간편하고 비숙련자라 하더라도 간편하게 시공할 수 있으며, 말뚝이 긴밀하게 결합되어 결합력이 우수하며, 가이드돌기와 가이드홈에 의해 말뚝의 중심축 일치가 용이하고 선단연결부와 두부연결부에 형성된 관통홀의 연통작업이 쉽게 이루어져 빠른 시공이 이루어질 수 있도록 하는 매우 유용한 발명이다.
As described above, according to the present invention, by easily assembling the front end coupler and the head coupler using bolts and nuts, it is easy to install the pile joint, even for unskilled people, the pile is tightly coupled and excellent bonding force In addition, the guide protrusion and the guide groove is easy to match the central axis of the pile is a very useful invention that can be made quickly through the communication work of the through-holes formed in the tip connection portion and the head connection portion.

도 1 은 본 발명의 일실시예에 의한 말뚝 이음장치의 선단금구를 나타낸 사시도,
도 2 는 본 발명의 일실시예에 의한 말뚝 이음장치의 두부금구를 나타낸 사시도,
도 3 은 본 발명의 일실시예에 의한 말뚝 이음장치의 볼트결합시 분리 상태를 나타낸 단면도,
도 4 은 본 발명의 일실시예에 의한 말뚝 이음장치의 볼트결합시 결합상태를 나타낸 단면도,
도 5 는 본 발명의 일실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 분리 단면도,
도 6 은 본 발명의 일실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 결합단면도,
도 7a 은 본 발명의 일실시예에 의한 말뚝 이음장치의 선단결합구의 분리구조를 나타낸 평면도,
도 7b 는 본 발명의 일실시예에 의한 말뚝 이음장치의 두부결합구의 분리구조를 나타낸 평면도,
도 8 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 선단금구를 나타낸 사시도,
도 9 는 본 발명의 다른 실시예에 의한 말뚝 이음장치의 두부금구를 나타낸 사시도,
도 10 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 볼트결합시 분리 상태를 나타낸 단면도,
도 11 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 볼트결합시 결합상태를 나타낸 단면도,
도 12 는 본 발명의 다른 실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 분리 단면도,
도 13 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 결합단면도,
도 14 는 본 발명에 다른 실시예에 의한 가이드 돌기를 나타내 예시도.
1 is a perspective view showing the distal end bracket of the pile joint according to an embodiment of the present invention,
Figure 2 is a perspective view showing the head bracket of the pile joint according to an embodiment of the present invention,
3 is a cross-sectional view showing a separation state when the bolt coupling of the pile joint according to an embodiment of the present invention,
Figure 4 is a cross-sectional view showing a coupling state when the bolt coupling of the pile joint according to an embodiment of the present invention,
5 is an exploded cross-sectional view showing a fixing structure by the guide projection when coupling the pile joint according to an embodiment of the present invention,
Figure 6 is a cross-sectional view showing a fixing structure by the guide projection when coupling the pile joint according to an embodiment of the present invention,
Figure 7a is a plan view showing a separation structure of the front end coupling of the pile joint according to an embodiment of the present invention,
Figure 7b is a plan view showing the separation structure of the head coupler of the pile joint according to an embodiment of the present invention,
8 is a perspective view showing the distal end bracket of the pile joint according to another embodiment of the present invention,
9 is a perspective view showing the head bracket of the pile joint according to another embodiment of the present invention,
10 is a cross-sectional view showing a separation state when the bolt coupling of the pile joint according to another embodiment of the present invention,
11 is a cross-sectional view showing a coupling state when the bolt coupling of the pile joint according to another embodiment of the present invention,
12 is an exploded cross-sectional view showing a fixing structure by the guide projection when coupling the pile joint according to another embodiment of the present invention,
Figure 13 is a cross-sectional view showing a fixing structure by the guide projection when coupling the pile joint according to another embodiment of the present invention,
14 is an exemplary view showing a guide protrusion according to another embodiment of the present invention.

이하 본 발명의 실시 예인 구성과 그 작용을 첨부도면에 연계시켜 상세히 설명하면 다음과 같다. 또한 본 발명을 설명함에 있어서, 관련된 공지기능 혹은 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명은 생략한다.
Hereinafter, the configuration and the operation of the embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the following description of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear.

도 1 은 본 발명의 일실시예에 의한 말뚝 이음장치의 선단금구를 나타낸 사시도, 도 2 는 본 발명의 일실시예에 의한 말뚝 이음장치의 두부금구를 나타낸 사시도, 도 3 은 본 발명의 일실시예에 의한 말뚝 이음장치의 볼트결합시 분리 상태를 나타낸 단면도, 도 4 은 본 발명의 일실시예에 의한 말뚝 이음장치의 볼트결합시 결합상태를 나타낸 단면도, 도 5 는 본 발명의 일실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 분리 단면도, 도 6 은 본 발명의 일실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 결합단면도로서,
1 is a perspective view showing the front end bracket of the pile joint according to an embodiment of the present invention, Figure 2 is a perspective view showing the head bracket of the pile joint according to an embodiment of the present invention, Figure 3 is an embodiment of the present invention 4 is a cross-sectional view showing a separated state when the bolt coupling device of the pile joint according to the example, Figure 4 is a cross-sectional view showing a coupling state when the bolt coupling device according to an embodiment of the present invention, Figure 5 is an embodiment of the present invention Separation cross-sectional view showing a fixing structure by the guide protrusion when the coupling of the pile coupling device, Figure 6 is a coupling cross-sectional view showing a fixing structure by the guide projection when coupling the pile coupling device according to an embodiment of the present invention,

본 발명의 말뚝 이음 장치는 중심부가 중공되어 있는 말뚝(100)의 선단에 설치되는 선단금구(200)와, 상기 선단금구(200)와 체결될 수 있도록 말뚝(100)의 두부에 설치되는 두부금구(300) 및 상기 선단금구(200)와 두부금구(300)를 체결시켜주는 볼트(400) 너트(410)를 포함하여 구성된다.
The pile joint device of the present invention has a head bracket 200 installed at the tip of the pile 100 having a hollow central portion, and a head bracket installed at the head of the pile 100 so as to be fastened to the tip bracket 200. 300 and the bolt 400 to fasten the tip bracket 200 and the head bracket 300 is configured to include a nut (410).

상기 선단금구(200)는 중심부가 중공되어 말뚝(100)의 선단에 부착되는 받침링(212)과 상기 받침링(212)의 가장자리를 따라 일정 높이로 형성되어 말뚝(100)의 외주면을 감싸주는 보강밴드(211)로 이루어진 선단캡(210)과, 상기 받침링(212)의 내측 가장자리를 따라 일정높이로 구비되고, 수평방향을 따라 소정의 간격으로 다수의 관통홀(221)이 형성되어 있는 선단결합부(220)와, 상기 받침링(212)의 외측 가장자리를 따라 소정의 간격으로 돌출 형성되어 선단금구(200)와 두부금구(300)의 결합시 말뚝의 중심일치가 가능한 위치에 놓여질 수 있도록 하는 가이드돌기(230)을 포함하여 구성된다.
The front end bracket 200 is hollow at the center thereof and is formed at a predetermined height along the edge of the support ring 212 and the support ring 212 attached to the tip of the pile 100 to surround the outer circumferential surface of the pile 100. A tip cap 210 made of a reinforcing band 211 and a predetermined height along an inner edge of the support ring 212, and a plurality of through holes 221 are formed at predetermined intervals along a horizontal direction. The tip coupling portion 220 and protruded at predetermined intervals along the outer edge of the support ring 212 may be placed in a position where the center of the pile can be matched when the tip bracket 200 and the head bracket 300 are coupled. It comprises a guide protrusion 230 to be.

상기 두부금구(300)는 중심부가 중공되어 말뚝(100)의 두부에 부착되는 받침링(312)과 상기 받침링(312)의 가장자리를 따라 일정 높이로 형성되어 말뚝(100)의 외주면을 감싸주는 보강밴드(311)로 이루어진 두부캡(310)과, 상기 받침링(312)의 외측 가장자리를 따라 일정 높이로 구비되고 수평방향을 따라 소정의 간격으로 다수의 관통홀(221)이 형성되어 있는 두부결합부(320)와, 상기 두부결합부(320)의 상단에 상기 가이드돌기(230)가 삽입될 수 있도록 오목하게 형성되어 있는 가이드홈(330)을 포함하여 구성된다.
The head bracket 300 is formed in a predetermined height along the edge of the support ring 312 and the support ring 312 attached to the head of the pile 100 is hollow in the center to surround the outer peripheral surface of the pile 100 A head cap 310 having a reinforcing band 311 and a head having a predetermined height along the outer edge of the support ring 312 and having a plurality of through holes 221 formed at predetermined intervals along a horizontal direction. It comprises a coupling portion 320, the guide groove 330 is formed concave so that the guide protrusion 230 can be inserted into the top of the head coupling portion 320.

상기 선단캡(210)과 두부캡(310)의 받침링(212)(312)에는 말뚝(100)의 제조시 말뚝 내부에 매설되는 강봉(500)이 연결될 수 있도록 땅콩형상의 강봉결합공(213)(313)이 일정간격으로 형성되어 있다.
Peanut-shaped steel rod coupling hole 213 is connected to the support ring (212, 312) of the front end cap 210 and the head cap 310 so that the steel bar 500 embedded in the pile when the pile 100 is connected ) 313 is formed at regular intervals.

이와 같이 구성되는 선단금구(200)와 두부금구(300)는 상기 선단결합부(220)의 관통홀(221) 내부에 너트(410)를 설치하고 선단결합부(220)와 두부결합부(320)의 관통홀(321)이 연통되도록 위치시킨 상태에서 두부결합부(320)의 관통홀(321)을 통해 볼트(400)를 삽입하여 선단결합부(220)의 관통홀(221) 내부에 설치된 너트(410)에 결합함으로써 선단금구(200)와 두부금구(300)가 상호 체결되어 말뚝(100)의 이음시공이 이루어지게 되는 것이다.The tip bracket 200 and the head bracket 300 configured as described above are provided with a nut 410 inside the through hole 221 of the tip coupling part 220 and the tip coupling part 220 and the head coupling part 320. ) Is installed in the through hole 221 of the front end coupling part 220 by inserting the bolt 400 through the through hole 321 of the head coupling part 320 in a state where the through hole 321 is in communication. By coupling to the nut 410, the distal end bracket 200 and the head bracket 300 are fastened to each other so that the joint construction of the pile 100 is performed.

또한 상기 선단금구(200)와 두부금구(300)의 결합시 선단금구(200)의 받침링(212)에 형성된 가이드돌기(230)가 두부금구(300)의 두부결합부(320)에 형성된 가이드홈(330)에 삽입됨으로써 이음시공되는 말뚝(100)의 중심축이 손쉽게 일치되고 이렇게 말뚝(100)의 중심이 일치됨으로써 서로 대응되도록 형성된 선단결합부(220)와 두부결합부(200)의 관통홀(221)(321)이 연통되도록 위치하여 볼트(400) 결합이 간단하게 이루어지게 되는 것이다.In addition, the guide protrusion 230 formed on the support ring 212 of the front end bracket 200 when the front end bracket 200 and the head bracket 300 are coupled to the head coupling part 320 of the head bracket 300. The center axis of the pile 100 to be jointed by being inserted into the groove 330 is easily matched, and thus the center of the pile 100 is matched so that the penetration of the tip coupling portion 220 and the head coupling portion 200 correspond to each other. The holes 221 and 321 are positioned so that the bolt 400 is easily coupled.

이와 같은 본 발명은 볼트(400) 및 너트(410)를 통해 선단금구(200)와 두부금구(300)를 조립하여 말뚝(100)의 이음시공을 함으로써 시공이 간편하고 가이드돌기(230)와 가이드홈(330)을 통해 말뚝(100)의 중심축이 일치됨과 동시에 볼트(400) 조립을 위한 관통홀(221)이 연통됨으로써 빠른 시공이 이루어지게 되는 것이다.As such, the present invention assembles the tip bracket 200 and the head bracket 300 through the bolt 400 and the nut 410 to perform the joint construction of the pile 100, and thus the construction is simple and the guide protrusion 230 and the guide. The central axis of the pile 100 coincides with the groove 330, and the through hole 221 for assembling the bolt 400 communicates with each other, thereby making rapid construction.

상기 선단결합부(220)와 두부결합부(320) 도 7a, 7b에서와 같이 적어도 3개 이상의 조각으로 분리되도록 구성할 수 있다.The front coupling portion 220 and the head coupling portion 320 may be configured to be separated into at least three pieces as shown in Figure 7a, 7b.

이렇게 선단결합부와 두부결합부를 각기 3개 이상의 조각으로 분리하여 선단 및 두부금구에 용접 결합할 경우에는, 선단결합부와 두부결합부 제작과정에서 필요로 하는 자재만을 가공함으로서, 넓은 철판을 일체로 가공하는 것 보다 자재손실이 없게 되며, 동시에 선단결합부와 두부결합부가 선단금구 및 두부금구에 전체적으로 설치되지 않고 일부분에만 설치되기 때문에 자재비를 절감할 수 있으며, 또한 가공도 용이하게 할 수 있다.
In this case, when the tip coupling part and the head coupling part are separated into three or more pieces and welded to the tip and the head bracket, only the materials required in the manufacturing process of the tip coupling part and the head coupling part are processed. There is no material loss than processing, and at the same time, the tip coupling part and the head coupling part are installed in only part of the tip bracket and the head bracket, thereby reducing the material cost and also facilitating the processing.

한편, 도 8 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 선단금구를 나타낸 사시도, 도 9 는 본 발명의 다른 실시예에 의한 말뚝 이음장치의 두부금구를 나타낸 사시도, 도 10 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 볼트결합 시 분리 상태를 나타낸 단면도, 도 11 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 볼트결합시 결합상태를 나타낸 단면도, 도 12 는 본 발명의 다른 실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 분리 단면도, 도 13 은 본 발명의 다른 실시예에 의한 말뚝 이음장치의 결합시 가이드돌기에 의한 고정구조를 나타낸 결합단면도로서,
On the other hand, Figure 8 is a perspective view showing the front end bracket of the pile joint according to another embodiment of the present invention, Figure 9 is a perspective view showing the head bracket of the pile joint according to another embodiment of the present invention, Figure 10 is Figure 11 is a cross-sectional view showing the separation state when the bolt coupling of the pile coupling apparatus according to another embodiment, Figure 11 is a cross-sectional view showing a coupling state when the bolt coupling device according to another embodiment of the present invention, Figure 12 is another embodiment of the present invention Separation cross-sectional view showing a fixing structure by the guide protrusion when the coupling of the pile joint according to the example, Figure 13 is a cross-sectional view showing a fixing structure by the guide projection when coupling the pile joint according to another embodiment of the present invention,

본 발명의 말뚝 이음장치는 중심부가 중공되어 있는 말뚝(100)의 선단에 설치되는 선단금구(200)와, 상기 선단금구(200)와 체결될 수 있도록 말뚝(100)의 두부에 설치되는 두부금구(300) 및 상기 선단금구(200)와 두부금구(300)를 체결시켜주는 볼트(400), 너트(410)를 포함하여 구성되며, 상기 선단금구(200)과 두부금구(300)는 요철형태로 결합된다.The pile fitting device of the present invention has a head bracket 200 installed at the tip of the pile 100 having a hollow central portion, and a head bracket installed at the head of the pile 100 so as to be fastened to the tip bracket 200. And a bolt 400 and a nut 410 for fastening the tip bracket 200 and the head bracket 300 to each other, wherein the tip bracket 200 and the head bracket 300 are uneven. Are combined.

상기 선단금구(200)는 중심부가 중공되어 말뚝(100)의 선단에 부착되는 받침링(212)과 상기 받침링(212)의 가장자리를 따라 일정 높이로 형성되어 말뚝의 외주면을 감싸주는 보강밴드(211)로 이루어진 선단캡(210)과, 상기 받침링(212)의 중심부를 따라 소정의 간격으로 수직하게 돌출되고 수평방향으로 다수의 관통홀(221)이 형성되어 있는 선단결합부(220)와, 상기 받침링(212)의 외측 가장자리를 따라 소정의 간격으로 돌출 형성되어 선단금구(200)와 두부금구(300)의 결합 시 적정 결합위치에 위치될 수 있도록 하는 가이드돌기(230)를 포함하여 구성된다.The tip bracket 200 has a reinforcing band formed at a predetermined height along the edge of the support ring 212 and the support ring 212 attached to the front end of the pile 100 to the center of the hollow to surround the outer peripheral surface of the pile ( A front end cap 210 and a front end coupling portion 220 which protrude vertically at predetermined intervals along a central portion of the support ring 212 and a plurality of through holes 221 are formed in a horizontal direction. In addition, the guide protrusion 230 is formed to protrude at predetermined intervals along the outer edge of the support ring 212 to be positioned at an appropriate coupling position when the front end bracket 200 and the head bracket 300 are coupled. It is composed.

한편 상기 두부금구(300)는 중심부가 중공되어 말뚝(100)의 두부에 부착되는 받침링(312)과 상기 받침링(312)의 가장자리를 따라 일정 높이로 형성되어 말뚝(100)의 외주면을 감싸주는 보강밴드(311)로 이루어진 두부캡(310)과, 상기 선단결합부(220)가 삽입될 수 있도록 두부캡(310)의 내측 및 외측 가장자리를 따라 수직하게 돌출 형성되고 수평방향으로 다수의 관통홀(321)이 형성되어 있는 한 쌍의 두부결합부(320)와, 상기 선단금구(200)의 가이드돌기(230)에 대응되도록 외측 가장자리에 위치한 두부결합부(320)의 상부에 소정의 간격으로 형성되어 있는 가이드홈(330)을 포함하여 구성된다.
On the other hand, the head bracket 300 is formed in a predetermined height along the edge of the support ring 312 and the support ring 312 attached to the head of the pile 100 is hollow in the center to surround the outer peripheral surface of the pile 100 The head cap 310 made of a reinforcing band 311 and the head coupling portion 310 are formed to protrude vertically along the inner and outer edges of the head cap 310 so that the front end coupling portion 220 can be inserted therethrough, and a plurality of penetrating in the horizontal direction. A predetermined distance between the pair of head coupling portions 320 in which the holes 321 are formed, and the head coupling portions 320 positioned at the outer edges thereof to correspond to the guide protrusions 230 of the tip bracket 200. It is configured to include a guide groove 330 is formed as.

상기 다른 실시예에 의한 선단캡(210)과 두부캡(310)의 받침링(212)(312)에도 말뚝(100)의 제조 시 말뚝 내부에 매설되는 강봉(500)이 연결될 수 있도록 땅콩 형상의 강봉결합공(213)(313)이 일정간격으로 형성되어 있다.Peanut-shaped so that the steel bar 500 embedded in the pile when the pile 100 is also connected to the support ring 212, 312 of the tip cap 210 and the head cap 310 according to another embodiment Steel bar coupling holes 213 and 313 are formed at regular intervals.

이와 같이 구성되는 다른 실시예에 의한 선단금구(200)와 두부금구(300)는 상기 선단결합부(220)가 두부결합부(330)의 사이에 끼워지도록 결합하고, 말뚝(100)을 소정의 각도로 회전시키면서 선단금구(200)의 가이드돌기(230)가 두부금구(300)의 가이드홈(330)에 삽입되도록 한다.
The tip bracket 200 and the head bracket 300 according to another embodiment configured as described above are coupled so that the tip coupling portion 220 is fitted between the head coupling portion 330, and the pile 100 is predetermined. The guide protrusion 230 of the tip bracket 200 is inserted into the guide groove 330 of the head bracket 300 while rotating at an angle.

이때 두부금구(300)의 내측 가장자리에 위치한 두부결합부(320)의 관통홀(221)의 내부에는 볼트(400)결합이 가능하도록 너트(410)를 설치한다.At this time, the nut 410 is installed in the through hole 221 of the head coupling part 320 located at the inner edge of the head bracket 300 to allow the bolt 400 to be coupled thereto.

상기 너트는 관통홀(221)의 내부에 삽입되도록 설치되거나, 또는 관통홀과 연통되도록 관통홀의 외부에 용접으로 부착되도록 설치된다.The nut may be installed to be inserted into the through hole 221 or may be installed to be welded to the outside of the through hole so as to communicate with the through hole.

이렇게 가이드돌기(230)가 가이드홈(330)에 삽입되면 선단결합부(220)와 두부결합부(330)의 관통홀(221)(321)이 서로 연통되도록 위치하고 외측 가장자리에 형성된 두부결합부(320)의 관통홀(321)을 통해 볼트(400)를 삽입하여 선단결합부(220)의 관통홀(221)을 관통한 후 내측 가장자리에 형성된 두부결합부(220)의 너트(410)에 조립함으로써 선단금구(200)와 두부금구(300)가 상호 체결되어 말뚝의 이음시공이 이루어지게 되는 것이다.
When the guide protrusion 230 is inserted into the guide groove 330 in this way, the head coupling part 220 and the head coupling part 220 formed at the outer edge thereof are positioned to communicate with each other through holes 221 and 321 of the head coupling part 330. The bolt 400 is inserted through the through hole 321 of the 320 to pass through the through hole 221 of the tip coupling part 220, and then assembled to the nut 410 of the head coupling part 220 formed at the inner edge thereof. By doing so, the front end bracket 200 and the head bracket 300 are fastened to each other, so that the construction of the pile is performed.

이와 같이 다른 실시예에 의한 본 발명은 두부금구(300)의 두부결합부(320)에 선단금구(200)의 선단결합부(220)가 끼움구조로 결합됨으로써 결합력이 우수하고, 볼트(400) 및 너트(410)를 통해 견고히 결합됨으로써 조립이 매우 간단하게 이루어지게 된다.As described above, the present invention according to another embodiment is coupled to the head coupling part 320 of the head bracket 300 by the tip coupling part 220 of the tip bracket 200 in a fitting structure, thereby providing excellent coupling force, and the bolt 400. And by being firmly coupled through the nut 410, the assembly is made very simple.

한편 상기 선단금구에 형성되는 관통홀은 장공형태로 형성되어 선단금구와 두부금구의 결합시 조금의 오차가 발생된다 하더라도 두부금구의 관통홀을 통해 끼워지는 볼트의 체결이 용이하게 이루어질 수 있도록 한다.On the other hand, the through hole formed in the tip bracket is formed in the form of a long hole so that even if a slight error occurs when the tip bracket and the head bracket is coupled to facilitate the fastening of the bolt fitted through the through hole of the head bracket.

이와 같은 각 실시예에 의한 본 발명은 말뚝(100)의 이음시공 시 가이드돌기(230)와 가이드홈(330)을 통해 말뚝(100)의 중심축을 용이하게 일치시켜주고, 중심축 일치에 따라 선단결합부(220)와 두부결합부(320)의 관통홀(221)(321)이 연통되어 볼트(400)를 너트(410)에 체결하는 것이 가능하며, 말뚝연결 조립이 용이하여, 짧은 시간에 말뚝 이음 시공이 가능하게 되는 것이다.
The present invention according to each embodiment as described above is easily matched the central axis of the pile 100 through the guide protrusion 230 and the guide groove 330 during the joint construction of the pile 100, the tip according to the center axis coincidence Through holes 221 and 321 of the coupling part 220 and the head coupling part 320 communicate with each other so that the bolt 400 can be fastened to the nut 410, and the pile connection assembly can be easily performed. Construction of pile joints is possible.

또한 각 실시예에 의한 선단결합부(220)와 두부결합부(320)는 선단캡(210)과 두부캡(310)에 용접 결합하거나, 또는 선단캡(210)과 두부캡(310)과 일체로 형성될 수 도 있다.
In addition, the front end coupling portion 220 and the head coupling portion 320 according to each embodiment is welded to the front end cap 210 and the head cap 310, or integrated with the front end cap 210 and the head cap 310 It may be formed as.

또한 상기 너트(410)는, 상기 각 실시 예에서와 같이, 관통홀(221)의 내부에 삽입되도록 설치하거나, 관통홀(221) 외부에 용접 등 의 방법으로 고정시키거나, 또는 관통홀(221)의 내부에 탭을 형성하여 구성할 수 있다.
In addition, the nut 410 is installed to be inserted into the through hole 221 as in each of the above embodiments, fixed to the outside of the through hole 221 by a welding method, or the through hole 221. It can be configured by forming a tab inside the).

한편 도 14 는 본 발명에 다른 실시예에 의한 가이드 돌기를 나타내 예시도로서, 도면에서와 같이 가이드돌기(230)는 가이드홈(330)에 삽입이 용이하게 이루어지도록 끝단이 뾰족한 쐐기 형태로 구성할 수 있다.
Meanwhile, FIG. 14 is an exemplary view showing guide protrusions according to another embodiment of the present invention. As shown in the drawing, the guide protrusion 230 may be configured in the shape of a wedge having a sharp end to be easily inserted into the guide groove 330. Can be.

본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.
The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. Of course, such changes will fall within the scope of the claims.

(100) : 말뚝 (200) : 선단금구
(210) : 선단캡 (211) : 보강밴드
(212) : 받침링 (213) : 강봉결합공
(220) : 선단결합부 (221) : 관통홀
(230) : 가이드돌기 (300) : 두부금구
(310) : 두부캡 (311) : 보강밴드
(312) : 받침링 (313) : 강봉결합공
(320) : 두부결합부 (321) : 관통홀
(330) ; 가이드홈 (400) : 볼트
(410) : 너트 (500) : 강봉
(100): pile (200): tip bracket
(210): Tip cap (211): Reinforcement band
(212): bearing ring (213): steel bar
220: tip coupling portion 221: through hole
(230): guide protrusion (300): tofu bracket
(310): head cap (311): reinforcement band
(312): Supporting ring (313): Steel bar coupling hole
(320): head coupling portion 321: through hole
330; Guide groove (400): bolt
410: nut 500: steel bar

Claims (4)

내부가 중공 된 말뚝의 선단에 설치되는 선단금구와, 상기 선단금구에 맞물려 결합될 수 있도록 두부에 설치되는 두부금구를 포함하는 말뚝과 말뚝 이음장치에 있어서,
상기 말뚝의 선단을 덮어주도록 설치되고 내부가 중공되어 있는 선단캡과, 상기 선단캡의 내측 가장자리를 따라 수직방향으로 일정 높이까지 돌출되도록 설치되고, 수평방향으로 다수의 관통홀이 형성되어 있는 선단결합부와, 상기 선단캡의 외측 가장자리를 따라 소정의 간격으로 돌출 형성되어 선단금구와 두부금구의 결합 시 용이하게 적정위치에 위치될 수 있도록 하는 가이드돌기를 포함하여 구성되는 선단금구;
상기 말뚝의 두부를 덮어주도록 설치되고 내부가 중공되어 있는 두부캡과, 상기 두부캡의 외측 가장자리를 따라 수직방향으로 일정 높이까지 돌출되도록 설치되고, 수평방향으로 다수의 관통홀이 형성되어 있는 두부결합부와, 상기 두부결합부의 상단에 상기 가이드돌기가 삽입될 수 있도록 형성되어 있는 가이드홈을 포함하여 구성되는 두부금구;
상기 선단결합부의 관통홀에 설치되는 너트와 상기 두부결합부의 관통홀 및 선단결합부의 관통홀에 삽입되어 상기 너트에 결합됨으로써 선단금구와 두부금구를 체결해주는 볼트를 포함하여 구성되는 것을 특징으로 하는 콘크리트 말뚝의 이음장치.
In the pile and the pile joint comprising a front end bracket which is installed at the tip of the hollow pile and the head bracket is installed on the head to be coupled to the front end bracket,
A tip cap installed to cover the tip of the pile and having a hollow inside, and protruded to a predetermined height in a vertical direction along an inner edge of the tip cap, and having a plurality of through holes formed in a horizontal direction. A protruding end portion including a protruding portion protruding at a predetermined interval along an outer edge of the distal end cap so as to be easily positioned at an appropriate position when the proximal end head and the head end head are coupled;
The head cap is installed to cover the head of the pile and is hollow inside, and the head cap is installed to protrude to a predetermined height in the vertical direction along the outer edge of the head cap, and the head coupling is formed with a plurality of through holes in the horizontal direction. A head bracket comprising a part and a guide groove formed to insert the guide protrusion at an upper end of the head coupling part;
The nut is installed in the through hole of the tip coupling portion and the head coupling portion of the through hole and the through hole of the tip coupling portion is inserted into the through nut coupled to the nut to fasten the front end bracket and the head bracket Pile joints.
내부가 중공 된 말뚝의 선단에 설치되는 선단금구와, 상기 선단금구에 맞물려 결합될 수 있도록 두부에 설치되는 두부금구를 포함하는 밀뚝과 말뚝 이음장치에 있어서,
상기 선단금구와 두부금구는 상호 대칭되는 요철 형태로 형성되고 말뚝을 연결 시 선단금구와 두부금구가 서로 맞물려 결합되는 것을 특징으로 하는 콘크리트 말뚝의 이음장치.
In the chimney and pile fitting device comprising a front end bracket which is installed at the front end of the hollow pile, and a head bracket which is installed on the head to be coupled to the front end bracket,
The distal end bracket and the tofu bracket are formed in a symmetrical concave-convex shape, and when the pile is connected, the distal end bracket and the tofu bracket are coupled to each other.
제 2 항에 있어서,
선단금구는 상기 말뚝의 선단에 설치되고 내부가 중공되어 있는 선단캡과, 상기 선단캡의 중심부를 따라 소정의 간격으로 수직방향으로 일정 높이까지 돌출되도록 설치되고 수평방향으로 다수의 관통홀이 형성되어 있는 선단결합부와, 상기 선단캡의 외측 가장자리에 돌출 형성되어 선단금구와 두부금구의 결합 시 적정위치에 위치될 수 있도록 하는 가이드돌기를 포함하여 구성되고,
상기 두부금구는, 상기 말뚝의 두부에 설치되고 내부가 중공되어 있는 두부캡과, 상기 선단결합부가 삽입될 수 있도록 두부캡의 내측 가장자리 및 외측 가장자리에 수직방향으로 일정 높이까지 돌출되도록 형성되고 수평방향으로 다수의 관통홀이 형성되는 한 쌍의 두부결합부와, 상기 가이드돌기에 대응되도록 외측 가장자리에 설치된 두부결합부의 상부에 형성되는 가이드홈을 포함하여 구성되며,
상기 두부금구의 내측 가장자리에 형성된 두부결합부의 관통홀에 설치되는 너트와, 상기 두부금구의 외측 가장자리에 형성된 두부결합부의 외측 가장자리에 형성된 관통홀과 상기 선단금구의 관통홀 및 두부결합부의 내측 가장자리에 형성된 관통홀의 너트에 결합되는 볼트에 의해 체결되는 것을 특징으로 하는 콘크리트 말뚝의 이음장치.
The method of claim 2,
The distal end bracket is installed at the distal end of the pile and has a hollow inner end, and protruded to a predetermined height in a vertical direction at predetermined intervals along a central portion of the distal end cap, and a plurality of through holes are formed in the horizontal direction. And a guide protrusion which protrudes from an outer edge of the tip cap to be positioned at an appropriate position when the tip bracket and the head bracket are coupled to each other.
The head bracket is installed on the head of the pile and the head cap is hollow inside, and formed so as to protrude to a certain height in the vertical direction perpendicular to the inner and outer edges of the head cap so that the tip coupling portion can be inserted and And a pair of head coupling portions having a plurality of through-holes formed therein, and guide grooves formed on top of the head coupling portions installed at outer edges thereof to correspond to the guide protrusions.
Nuts installed in the through holes of the head coupling portion formed on the inner edge of the head bracket, through holes formed on the outer edge of the head coupling portion formed on the outer edge of the head bracket, and through holes of the front end bracket and the inner edges of the head coupling portion. The joint of the concrete pile, characterized in that fastened by a bolt coupled to the nut of the through-hole formed.
제 1 항 또는 제 3 항에 있어,
상기 선단결합부와 두부결합부는 적어도 3개 이상의 조각으로 분리되도록 설치 구성되는 것을 특징으로 하는 콘크리트 말뚝의 이음장치.









The method according to claim 1 or 3,
The front coupling portion and the head coupling portion is a joint of the concrete pile, characterized in that the installation is configured to be separated into at least three pieces.









KR1020100015301A 2010-02-19 2010-02-19 Coupling apparatus of concrete pile KR101174273B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100015301A KR101174273B1 (en) 2010-02-19 2010-02-19 Coupling apparatus of concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100015301A KR101174273B1 (en) 2010-02-19 2010-02-19 Coupling apparatus of concrete pile

Publications (2)

Publication Number Publication Date
KR20110095693A true KR20110095693A (en) 2011-08-25
KR101174273B1 KR101174273B1 (en) 2012-08-16

Family

ID=44931286

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100015301A KR101174273B1 (en) 2010-02-19 2010-02-19 Coupling apparatus of concrete pile

Country Status (1)

Country Link
KR (1) KR101174273B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101300499B1 (en) * 2013-01-11 2013-08-26 문종화 A connection device to connect concrete piles
KR101714371B1 (en) * 2016-05-20 2017-03-14 (주)성심씨앤엠 Joints Appartus of The Concrete Piles and Steel Pipe
KR20170142595A (en) * 2016-06-20 2017-12-28 주식회사 에스비케이 Pile connector
KR20190001011U (en) 2017-10-20 2019-04-30 (주)성심씨앤엠 Connection Device For Ground Reinforced File
KR20190113056A (en) * 2018-03-27 2019-10-08 아이에스동서 주식회사 PHC pile connection device for non welded joint
CN110438982A (en) * 2019-08-12 2019-11-12 中国建筑第二工程局有限公司 A kind of pile end board and tubular pole connection method
KR102202611B1 (en) * 2020-07-21 2021-01-13 (주)성심씨앤엠 Pretentioned spun high strength concrete pile connection device
KR102267641B1 (en) * 2020-07-13 2021-06-22 피에이치씨탑다운(주) PHC pile construction method using joint PHC pile and detachable auxiliary pile
KR102268120B1 (en) * 2020-07-13 2021-06-25 피에이치씨탑다운(주) PHC pile construction method using casing guide and removeable auxiliary pile

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190082005A (en) 2017-12-29 2019-07-09 창신대학교 산학협력단 Coupling Apparatus of PHC Pile

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040022138A (en) 2002-09-06 2004-03-11 아츠시 니시와키 Joining structure of pile
KR100646258B1 (en) * 2005-10-24 2006-11-23 재단법인 포항산업과학연구원 Apparatus for connecting concrete piles
KR100835777B1 (en) * 2007-03-14 2008-06-05 정인배 Joint apparatus of concrete pile and steel pipe pile

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101300499B1 (en) * 2013-01-11 2013-08-26 문종화 A connection device to connect concrete piles
KR101714371B1 (en) * 2016-05-20 2017-03-14 (주)성심씨앤엠 Joints Appartus of The Concrete Piles and Steel Pipe
KR20170142595A (en) * 2016-06-20 2017-12-28 주식회사 에스비케이 Pile connector
KR20190001011U (en) 2017-10-20 2019-04-30 (주)성심씨앤엠 Connection Device For Ground Reinforced File
KR20190113056A (en) * 2018-03-27 2019-10-08 아이에스동서 주식회사 PHC pile connection device for non welded joint
CN110438982A (en) * 2019-08-12 2019-11-12 中国建筑第二工程局有限公司 A kind of pile end board and tubular pole connection method
KR102267641B1 (en) * 2020-07-13 2021-06-22 피에이치씨탑다운(주) PHC pile construction method using joint PHC pile and detachable auxiliary pile
KR102268120B1 (en) * 2020-07-13 2021-06-25 피에이치씨탑다운(주) PHC pile construction method using casing guide and removeable auxiliary pile
KR102202611B1 (en) * 2020-07-21 2021-01-13 (주)성심씨앤엠 Pretentioned spun high strength concrete pile connection device

Also Published As

Publication number Publication date
KR101174273B1 (en) 2012-08-16

Similar Documents

Publication Publication Date Title
KR101174273B1 (en) Coupling apparatus of concrete pile
KR101714371B1 (en) Joints Appartus of The Concrete Piles and Steel Pipe
KR200475119Y1 (en) System scaffold
KR20150017079A (en) Coupling apparatus for non-welding of pile
JP2014005652A (en) Construction method for pile type pier
JP4753426B2 (en) Steel pipe joints
KR20150055928A (en) Base Concrete Structure having a Fixing Connector for Fense Post
KR20150117791A (en) Coupling apparatus for non-welding of PHC pile
KR101252027B1 (en) Coupling apparatus of pile
JP4474430B2 (en) Pile joint structure
KR101845008B1 (en) Guard fence using band and connector, and method for constructing this same
KR101451164B1 (en) The clamping device for Concrete piles extending
KR101773434B1 (en) Coupling device for concrete and steel File
JP5142743B2 (en) Pile head joint structure
KR101205919B1 (en) Apparatus for connecting concrete piles
KR20140131648A (en) Coupling apparatus of pile using coupler integrated pc nut
KR20150105613A (en) The smart front end cap for adjusting phc file length and the method using thereof
KR200490635Y1 (en) Connection Device For Ground Reinforced File
KR20140096872A (en) Serial connection apparatus of pile
KR101127475B1 (en) Device for connecting wales
KR101774343B1 (en) Coupling apparatus of pile
JP5991622B2 (en) Pile-free welded joint
KR100492719B1 (en) Assembling supporting post for construction
KR20130004588U (en) A temporary structure for construction
KR20160075984A (en) Joint structure between column and horizontal member

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150601

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170209

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee