KR20110018581A - Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same - Google Patents

Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same Download PDF

Info

Publication number
KR20110018581A
KR20110018581A KR1020090076112A KR20090076112A KR20110018581A KR 20110018581 A KR20110018581 A KR 20110018581A KR 1020090076112 A KR1020090076112 A KR 1020090076112A KR 20090076112 A KR20090076112 A KR 20090076112A KR 20110018581 A KR20110018581 A KR 20110018581A
Authority
KR
South Korea
Prior art keywords
steel pipe
square steel
reinforcing member
brace
connection
Prior art date
Application number
KR1020090076112A
Other languages
Korean (ko)
Other versions
KR101117546B1 (en
Inventor
김동준
이승원
김현숙
강창우
김광복
배수성
Original Assignee
(주)피에스테크
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)피에스테크 filed Critical (주)피에스테크
Priority to KR1020090076112A priority Critical patent/KR101117546B1/en
Publication of KR20110018581A publication Critical patent/KR20110018581A/en
Application granted granted Critical
Publication of KR101117546B1 publication Critical patent/KR101117546B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1628Shapes rectangular
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PURPOSE: A structure for connecting and joining square steel pipe for temporary sheathing construction and connecting/welding reinforcement members for the same are provided to facilitate connection and disassembly of struts in an installation place, since one end of a strut to be connected is placed on a connecting reinforcement member. CONSTITUTION: A structure for connecting and joining square steel pipe strut(10) for temporary sheathing construction comprises following steps. Square steel pipe struts are connected to each other by connecting reinforcement members(20) in ground drilling. The connected square steel pipe strut is welded with a wale or a jack support through a welding reinforcement member. An insertion portion is formed on one side of the welding reinforcement member for the insertion of the end of the square steel pipe strut, and a coupling plate, which is welded with the wale or the jack support, is formed on the other side of the welding reinforcement member. A support partition plate and the reinforcing member are connected between the insertion portion and the coupling plate. The support partition plate is fixed to one side of the insertion portion.

Description

가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조 및 그 시공구조를 위한 연결보강부재와 접합보강부재 {Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same}Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same}

본 발명은 도심지 굴착 공사에 적용되는 가설 흙막이 공법에 있어 사각강관으로 된 버팀보를 서로 연결하기 위한 연결보강부재 및 이들 버팀보와 띠장 또는 잭써포트 간의 접합을 위한 접합보강부재를 이용한 사각강관의 시공구조에 관한 것으로서, 더욱 상세하게는 상,하 대향 체결되는 형태의 연결보강부재를 통해 사각강관 버팀보의 설치위치에서 사각강관 버팀보 간의 용이한 연결이 가능한 것이고, 접합보강부재는 사각강관 버팀보와 띠장 또는 띠장에 결합된 잭써포트와의 안정적이고 용이한 접합이 이루어지도록 함으로써, 가설 흙막이 공사에서의 사각강관 버팀보에 대한 시공 시간의 단축 및 연결 및 접합강도가 향상되게 한 것이다.The present invention in the construction structure of rectangular steel pipe using a joint reinforcing member for connecting the reinforcement of the square steel pipe to each other and the joint reinforcing member for the connection between the support and the belt or jack support in the temporary earthquake construction method applied to the urban excavation construction In more detail, the connecting reinforcing member in the form of fastening facing up and down in more detail, it is possible to facilitate the connection between the square steel pipe brace at the installation position of the square steel pipe brace, the joint reinforcing member is connected to the square steel pipe brace and the belt or belt By making stable and easy joining with the combined jack support, the construction time for the square steel pipe brace in the temporary construction of the construction and the connection and joint strength is improved.

통상의 건설현장에서는 구조물 축조(토목/건축현장)를 위한 지반굴착시 굴착 배면의 토사 붕괴방지 및 변위억제를 위해 통상적인 방법으로 가설 흙막이 공사를 시행하게 되며 이때 굴착 배면에 작용하는 토압을 지지하기 위한 지지공법을 적용하게 되는데 일반적으로 버팀보 공법이나 앵커 공법 등을 적용하게 된다.In the general construction site, temporary earthquake works are carried out in the usual way to prevent soil collapse and suppress displacement of the back of the excavation during ground excavation for structural construction (civil engineering / construction site), and to support the earth pressure acting on the back of the excavation. The support method for this is applied, and generally the support method or anchor method is applied.

이때 버팀보 공법은 토류벽에 대하여 횡방향으로 고정된 띠장을 설치하고, 서로 마주보는 상기의 띠장을 가로지르는 다수의 버팀보를 설치하여 토류벽에 작용하는 토압을 지지하도록 하는 공법으로서 H-Pile과 원형강관을 적용하는 공법이 적용되고 있다. 이러한 버팀보 공법은 마주보는 띠장의 간격에 따라 버팀보의 길이가 연장되어야 할 것이다.At this time, the reinforcement method is to install the bands fixed in the transverse direction with respect to the earth wall, and install a plurality of reinforcement beams crossing the bands facing each other to support the earth pressure acting on the earth wall. The application method is applied. Such a bracing method would have to extend the length of the bracing beam according to the spacing of the facing bands.

그러나, 가설 흙막이 공사에서 가장 많이 사용되고 있는 H-Pile 버팀보 공법은 버팀보 간의 연결에 대한 문제점은 없으나, H-Pile의 강재 특성상 상,하 방향과 좌,우 방향으로의 강성 차이가 발생함에 따라 강축과 약축이 존재하게 되며, 약축방향으로는 좌굴이 발생하여 H-Pile에 대한 변위가 발생하므로 굴착 배면에 대한 토압을 효과적으로 지지할 수 없게 된다. 이에 따라 상기의 좌굴을 예방하기 위해 약축 방향에 수평 및 수직의 보강재를 설치하는 보강작업이 필수적으로 요구되어 강재 사용량의 증가와 보강재 설치작업이 추가로 필요하다는 단점이 있다.However, the H-Pile brace method, which is used most frequently in the construction of temporary fences, does not have a problem about the connection between the braces. The weak axis is present, and because the buckling occurs in the weak axis direction, displacement of the H-Pile occurs, so that the earth pressure on the rear surface of the excavation cannot be effectively supported. Accordingly, in order to prevent the buckling, a reinforcement work for installing horizontal and vertical reinforcement materials in the weak axis direction is required. Therefore, an increase in the amount of steel used and reinforcement installation work are additionally required.

상기 H-Pile과는 달리 원형강관을 이용한 버팀보 공법은 약축과 강축이 존재하지 않으므로 약축에 대한 좌굴 문제가 발생하지 않아 약축 보강이 필요 없다는 장점이 있으나, H-Pile 공법과 같이 작업자가 버팀보를 밟고 다니며 이동할 수 있는 통로 역할을 전혀 수행할 수 없다. Unlike the H-Pile, the reinforcement method using the circular steel pipe has the advantage that the weak axis and buckling does not exist, so there is no need for reinforcement of the weak axis because there is no buckling problem for the weak axis, but the worker steps on the reinforcement like the H-Pile method. It can't serve as a path to move around.

또한, 버팀보를 연결하기 위한 작업을 버팀보가 직접 설치되는 공중에서 수행할 수 없으므로 별도의 작업장에서 버팀보를 조립한 후 대형 크레인 등의 인양 장비에 의해 거대한 전체 버팀보 시스템을 설치위치에 거치하게 되며 해체시에도 동일과정을 역순으로 시행해야 하므로 작업공정이 매우 복잡할 뿐만 아니라 항상 사고위험이 존재하게 된다.In addition, since the work for connecting the braces cannot be performed in the air where the braces are directly installed, the braces are assembled in a separate workshop, and then the entire entire brace system is mounted at the installation position by lifting equipment such as a large crane. The same process must be carried out in reverse order, so the work process is very complicated and there is always an accident risk.

또한, 원형강관을 이용한 버팀보 공법은 H-Pile 버팀보 공법과는 달리 볼트의 체결에 있어 볼트 또는 너트를 회전시킬 수 있는 공간이 확보되지 아니하므로 별도의 브라켓 장치나 연장 체결부 등을 추가로 구성하여 이들을 통해 상호 간의 연결이 이루어지도록 해야 하므로 부수적인 많은 사전 및 예비 작업을 요구하는 것이며, 이와 같은 사전 및 예비작업은 공기의 지연은 물론 추가 인건비의 발생과 많은 량의 강재 사용으로 인해 공사비를 가중시키는 원인으로 지적되고 있는 실정이다.In addition, unlike the H-Pile brace method, since the brace method using the circular steel pipe does not secure a space for rotating the bolt or nut in the fastening of the bolt, an additional bracket device or an extension joint is additionally configured. They require a lot of additional preliminary and preliminary work because they need to be connected to each other, and this preliminary and preliminary work adds to the cost of construction due to the delay of air as well as the occurrence of additional labor costs and the use of a large amount of steel. It is pointed out as the cause.

본 발명은 전기한 바와 같은 문제점을 개선한 것으로서, 상하 대향의 체결구조를 갖는 연결보강부재와 사각강관 버팀보와의 결합 및 띠장과의 결합이 가능한 접합보강부재를 구비하여, 상기 연결보강부재를 통해서는 설치위치에서 연결하고자 하는 버팀보를 앉혀 놓은 상태로 상호 간의 연결이 이루어지도록 하는 것이고, 상기 접합보강부재를 통해서는 사각강관 버팀보와 띠장 또는 사각강관 버팀보와 잭써포트와의 용이하면서도 안정적인 체결 접합이 이루어지도록 함으로써, 종래의 일반적인 버팀보 공법이 갖고 있던 제반의 문제점을 합리적으로 극복한 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조 및 그 시공구조를 위한 연결보강부재와 접합보강부재를 제공함에 본 발명의 목적이 있는 것이다.The present invention has been made to solve the problems described above, and provided with a joint reinforcing member having a coupling structure of the upper and lower facing structure and the joint reinforcement member and the coupling of the band length, and through the connection reinforcing member Is to make the connection between each other in a state to sit the brace to be connected at the installation position, and through the joint reinforcing member made of easy and stable fastening of the square steel pipe brace and the band or square steel pipe brace and jack support The present invention provides a connection reinforcement member and a connection reinforcing member and a connection reinforcing member for the construction structure of the rectangular steel pipe reinforcement for a temporary earthquake method, which rationally overcomes the problems of the conventional general reinforcement method. There is a purpose.

상기한 바와 같은 목적을 달성하기 위한 본 발명은, 지반굴착시 굴착 배면에 대하여 서로 마주하는 띠장 간에 결합되는 사각강관 버팀보의 시공구조에 있어서,In the present invention for achieving the object as described above, in the construction structure of the square steel tube support beam coupled between the bands facing each other with respect to the excavation back when ground excavation,

서로 마주하는 띠장 간의 거리에 따라 사각강관 버팀보를 연결하고자, 제1의 사각강관 버팀보의 일측단 하측으로 제1의 연결보강부재를 돌출되도록 결합 형성하고, 제1의 사각강관 버팀보에 연결되기 위한 제2의 사각강관 버팀보의 일측단 상측에는 제2의 연결보강부재가 돌출되도록 결합 형성하여, 제1의 사각강관 버팀보 상에 결합된 제1의 연결보강부재 상에 제2의 사각강관 버팀보의 단부를 얹혀 놓아 상 기 제1의 연결보강부재와 제2의 연결보강부재가 상,하로 대향되면 이들 제1의 연결보강부재와 제2의 연결보강부재를 체결 고정함에 따라 제1 및 제2의 사각강관 버팀보에 대한 연결 시공이 이루어지도록 하고,In order to connect the square steel pipe brace according to the distance between the bands facing each other, the first connecting reinforcing member is formed to protrude to the lower side of one side of the first square steel pipe brace, and the first square steel pipe brace for connecting to The second connecting reinforcing member is formed to protrude from one side end upper side of the square steel pipe brace of 2, and the end of the second square steel pipe brace on the first connecting reinforcing member coupled to the first square steel pipe brace. When the first connecting reinforcing member and the second connecting reinforcing member face each other up and down, the first and second square reinforcing pipes are fastened by fastening and fixing the first connecting reinforcing member and the second connecting reinforcing member. To make the connection to the brace

사각강관 버팀보의 단부를 띠장이나 잭써포트와 접합하고자, 사각강관 버팀보의 끝단부가 수용되는 삽입부를 갖는 접합보강부재를 구비하여 상기 삽입부와 사각강관 버팀보와의 체결이 이루어지도록 하고, 접합보강부재의 타측부는 띠장이나 잭써포트와 체결 형성함에 따라 사각강관 버팀보와 띠장 및 잭써포트가 접합보강부재를 통해 서로 접합 시공이 이루어지도록 하여 되는 것이다.In order to join the end of the rectangular steel tube brace with a strip or jack support, the joint reinforcing member having an insertion portion for accommodating the end of the rectangular steel tube brace is made to be fastened to the insertion portion and the square steel tube brace, The other side is to be formed to be joined to each other through the joint reinforcement member and the rectangular steel pipe brace and the strip and jack support by forming a joint with the belt or jack support.

본 발명은, 서로 마주하는 띠장 간에 설치되는 버팀보를 연결함에 있어 연결하고자 하는 버팀보의 일단을 연결보강부재 상에 앉혀 놓을 수 있어 버팀보에 대한 설치위치에서의 연결 및 해체가 가능한 것이고, 띠장 또는 띠장에 체결된 잭써포트와 사각강관으로 된 버팀보를 접합함에 있어서도 안정적이고 효율적인 접합이 이루어질 수 있도록 한 것이다.In the present invention, in connecting the braces installed between the bands facing each other, one end of the braces to be connected can be seated on the connecting reinforcing member so that the connection and dismantling at the installation position for the braces is possible, It is to make stable and efficient joining even when joining fastened jack support and square steel pipe.

또한, 본 발명은 버팀보의 연결부에 위치하는 연결보강부재 및 버팀보와 띠장 또는 버팀보와 잭써포트와의 접합부에 위치하는 접합보강부재에 작용하는 고도의 응력에 효과적으로 대비할 수 있도록 보강 설계됨에 따라 이들 연결보강부재나 접합보강부재에 대한 좌굴 및 변형에 대한 예방이 가능하여 이들의 사용 수명을 크게 연장시킬 수 있는 것이다.In addition, the present invention is reinforcement designed to effectively prepare for the high stress acting on the connection reinforcing member and the reinforcing member located in the joint portion of the brace and the belt or the support and jack support and the reinforcement member located in the connection portion of the brace It is possible to prevent the buckling and deformation of the member or bonded reinforcing member can greatly extend their service life.

본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니 되며, 발명자는 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary meanings and the inventor may properly define the concept of the term to describe its invention in the best possible way And should be construed in accordance with the principles and meanings and concepts consistent with the technical idea of the present invention.

이하 첨부된 도면을 참조하여 본 발명의 바람직한 실시예를 상세히 설명하기로 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 사각강관 버팀보의 시공상태를 보인 사시도이고, 도 2는 본 발명에 따른 사각강관 버팀보의 시공상태를 보인 분리 사시도이다.1 is a perspective view showing a construction state of the square steel tube brace according to the present invention, Figure 2 is an exploded perspective view showing a construction state of the square steel tube brace according to the present invention.

본 발명의 시공구조에서 적용되는 사각강관 버팀보(10)(10')는 기존의 H-Pile과는 달리 강축과 약축이 존재하지 아니하므로 약축에 대한 보강이 전혀 필요없는 것이고, 약축 보강을 위한 보강편을 덧대는 용접공정이나 브레이싱 설치로 인한 구조적, 경제적 문제가 전혀 없는 것이며, 원형강관과는 달리 작업자가 사각강관으로 된 버팀보(10)(10')의 상부면을 이용하여 자유롭게 이동할 수 있으므로 작업성이 크게 개선되는 것이다.Square steel pipe braces (10) (10 ') applied in the construction structure of the present invention does not require any reinforcement for the weak axis because there is no steel axis and weak axis unlike the existing H-Pile, reinforcement for weak axis reinforcement There are no structural and economic problems due to the welding process or brazing installation.The worker can move freely using the upper surface of the braces 10 and 10 'made of square steel pipes, unlike circular steel pipes. Sex is greatly improved.

이와 같은 사각강관 버팀보(10)(10')는 굴착지에 기 설치되어 서로 마주하는 형태의 띠장을 가로질러 고정 설치되는 것으로, 상기의 띠장 간 폭이 단 하나의 버팀보가 갖고 있는 길이보다 긴 경우가 일반적일 것이므로 이때에는 적어도 2개 이 상의 사각강관 버팀보(10)(10')를 서로 연결 시공하여야 하는 것이다.Such square steel braces (10, 10 ') is installed in the excavation site is fixed across the bands of the form facing each other, the width between the bands is longer than the length of a single brace. Since it will be general, at this time, at least two or more square steel braces (10) (10 ') should be connected to each other construction.

이에 따라, 제1의 사각강관 버팀보(10)를 설치하기 전에 제1의 연결보강부재(20)를 상기 제1의 사각강관 버팀보(10)의 단부 하측에 볼트와 너트를 이용하여 체결한 상태로 1차적인 설치가 이루어지는 것이고, 제2의 사각강관 버팀보(10') 역시 또 다른 제2의 연결보강부재(20')를 제2의 사각강관 버팀보(10')의 단부 상측에 볼트와 너트를 이용하여 고정한 상태에서 상기 제1의 사각강관 버팀보(10)와의 연결 작업을 수행하게 된다.Accordingly, before the first square steel pipe brace 10 is installed, the first connecting reinforcing member 20 is fastened by using a bolt and a nut at the lower end of the first square steel pipe brace 10. The primary installation is made, and the second square steel tube brace 10 'also has a second connection reinforcing member 20' with a bolt and nut on the upper end of the second square steel tube brace 10 '. In the fixed state by using the first square steel tube support 10 and the connection work is performed.

즉, 상기의 연결보강부재(20)(20')는 도 3 및 도 4의 도시와 같이 금속판재를 절곡 형성하거나 사각강관의 절단 또는 주물 생산하여 만들어진 것으로서, 사각강관 버팀보(10)(10')의 수평 외면이 맞닿는 수평부(24)(24')와 이들 수평부(24)(24')로부터 양측으로 절곡 형성된 수직부(23)(23')를 갖고 있고 상기 수직부(23)(23')의 끝단에는 수평의 결합플랜지(22)(22')가 형성되어 있는 것이다. 또한, 상기의 결합플랜지(22)(22')와 수평부(24)(24')에는 관통의 체결공(25)(25')이 다수 형성되어 있는 것이다.That is, the connecting reinforcing member (20, 20 ') is made by bending or forming a metal plate, as shown in Figures 3 and 4, or by cutting or casting a square steel pipe, square steel tube support (10, 10') And horizontal portions 24, 24 'which abut the horizontal outer surface thereof, and vertical portions 23, 23' which are bent to both sides from the horizontal portions 24, 24 ', and the vertical portions 23 ( At the end of 23 ', horizontal coupling flanges 22 and 22' are formed. In addition, a plurality of through holes 25 and 25 'are formed in the coupling flanges 22 and 22' and the horizontal portions 24 and 24 '.

이에 따라 상기의 사각강관 버팀보(10)(10')의 끝단부에 체결공(11)(11')을 천공한 상태에서, 연결보강부재(20)(20')의 체결공(25)(25')과 상기 사각강관 버팀보(10)(10')의 체결공(11)(11')을 서로 일치시켜 이들을 볼트와 너트를 이용하여 견고하게 체결하면 되는 것이다. 이때 상기의 하측에 위치하는 연결보강부재(20)는 전체 길이에 대하여 절반에 해당하는 길이만큼만 일측의 사각강관 버팀보(10)에 체결되는 것이고, 상기와 같이 돌출된 연결보강부재(20) 상에 얹혀지는 또 다른 사각 강관 버팀보(10')에는 상측에 위치하는 또 다른 연결보강부재(20')가 체결되어 있는 상태이므로 이와 같이 서로 이웃하는 사각강관 버팀보(10)(10')의 대향 단부에 대하여 각기 상,하측에 체결된 상태의 연결보강부재(20)(20')의 결합플랜지(22)(22')를 서로 체결함에 따라 상기 사각강관 버팀보(10)(10')에 대한 연결 시공이 이루어지는 것이다.Accordingly, in the state in which the fastening holes 11 and 11 'are drilled at the end portions of the square steel pipe braces 10 and 10', the fastening holes 25 of the connecting reinforcing members 20 and 20 '( 25 ') and the fastening holes 11 and 11' of the rectangular steel tube braces 10 and 10 'are matched with each other, so that they can be firmly fastened using bolts and nuts. At this time, the connecting reinforcing member 20 located at the lower side is fastened to one side of the rectangular steel pipe brace 10 by the length corresponding to half of the total length, and on the connecting reinforcing member 20 protruding as described above. The other square steel pipe braces 10 'are placed on the opposite end of the adjacent square steel pipe braces 10' and 10 '. The connection construction for the square steel tube braces 10, 10 'by fastening the coupling flanges 22, 22' of the connecting reinforcing members 20, 20 'in the state of being fastened to the upper and lower sides, respectively. This is done.

따라서, 선행의 제1의 사각강관 버팀보(10)에 결합된 상태의 제1의 연결보강부재(20)는 제2의 사각강관 버팀보(10') 단부가 얹혀 질 수 있는 받침부의 역할을 수행하게 되므로 상기 제2의 사각강관 버팀보(10')의 단부를 제1의 연결보강부재(20) 상에 올려놓아 임시 거치가 이루어진 상태에서, 사각강관 버팀보(10)(10')의 상부면을 작업자가 밟고 이동하여 상,하로 대향 위치하고 있는 제1의 연결보강부재(20)와 제2의 연결보강부재(20')의 결합플랜지(22)(22')를 체결공(25)(25')을 통해 볼트와 너트를 사용하여 서로 견고하게 체결하면 사각강관 버팀보(10)(10')에 대한 연결 작업이 용이하게 이루어질 수 있는 것이다.Accordingly, the first connecting reinforcing member 20 coupled to the first first rectangular steel tube brace 10 serves to support the end portion of the second rectangular steel tube brace 10 '. Therefore, the end of the second square steel tube brace 10 'is placed on the first connecting reinforcing member 20 in the temporary mounting state, the upper surface of the square steel tube brace 10 (10') Is stepped and moved to engage the coupling flanges 22 and 22 'of the first connecting reinforcing member 20 and the second connecting reinforcing member 20' which are positioned up and down to face the fastening holes 25 and 25 '. When fastened firmly to each other using bolts and nuts through it can be easily connected to the square steel tube braces (10) (10 ').

또한, 상기와 같은 연결 작업을 역순으로 수행함에 따라 가설 흙막이 시설에서의 버팀보를 제거하고자 하는 경우 사각강관 버팀보(10)(10')를 서로 연결 고정하고 있는 연결보강부재(20)(20') 간의 볼트와 너트를 풀어낸 후, 제2의 사각강관 버팀보(10')의 인양 제거 및 제1의 사각강관 버팀보(10)의 안양 제거를 통해 빠르고 효과적으로 사각강관 버팀보에 대한 해체작업이 이루어질 수 있는 것이다.In addition, the connection reinforcing member (20, 20 ') that is fixed to the square steel pipe braces 10, 10' connected to each other if you want to remove the braces in the temporary earthquake facilities by performing the above connection work in the reverse order After loosening the bolts and nuts of the liver, the lifting and removing of the second square steel tube brace (10 ') and the removal of the first square steel tube brace 10 can be quickly and effectively dismantled the square steel tube brace will be.

이와 같이, 크레인 등의 중장비에 의해 버팀보 시스템 전체를 설치위치에 거치하는 기존의 원형강관 설치방법과는 달리 설치위치에서 사각강관 버팀 보(10)(10')에 대한 직접 연결이나 해체가 가능하여 작업공정이 빨라지며 장비 대수나 크기도 작아질 수 있어 시공성이 개선되므로 작업 공기를 크게 단축할 수 있으며 경제적 시공이 가능해진다.As such, unlike the existing circular steel pipe installation method in which the entire brace system is mounted at the installation position by heavy equipment such as a crane, the direct connection or disassembly of the square steel pipe braces 10, 10 'is possible at the installation position. Work process is faster and equipment number and size can be smaller, which improves workability, which can greatly reduce work air and enable economic construction.

여기서, 상기의 연결보강부재(20)(20')는 전기한 바와 같이 사각강관 버팀보(10)(10')를 단순히 연결 지지하기 위한 역할뿐만 아니라, 이들 사각강관 버팀보(10)(10')의 연결부에 작용하는 고도의 응력을 효과적으로 지지함에 따라 자체의 좌굴이나 변형이 방지되도록 설계가 이루어진 것이다.Here, the connection reinforcing member (20, 20 ') is not only a role for simply connecting and supporting the square steel pipe braces 10, 10' as described above, these square steel pipe braces 10, 10 ' It is designed to prevent its buckling or deformation as it effectively supports the high stress acting on the joints of.

즉, 상기의 연결보강부재(20)(20')의 내측에는 서로 마주하는 사각강관 버팀보(10)(10')의 끝단부의 사이에 위치하는 보강격판(21)(21')을 형성함에 따라, 상기의 보강격판(21)(21')은 축방향으로 압축응력을 받는 버팀보의 연결 성능을 크게 향상시킬 수 있는 것이고, 연결보강부재(20)(20')에 대하여 사각강관 버팀보(10)(10')의 축방향 좌굴응력이 발생하는 경우에도 상기의 보강격판(21)(21')이 안전판 역할을 수행함에 따라 좌굴 및 변형으로부터 안전할 수 있어 구조적 성능이 크게 개선되는 것이다. 또한, 상기의 보강격판(21)(21')은 연결보강부재(20)(20')의 양측단에 형성된 결합플랜지(22)(22')의 강성을 증가시켜주는 역할 등을 수행하므로 결국 사각강관 버팀보(10)(10')의 구조적 강성 및 연결 성능을 크게 향상시켜 주는 역할을 담당하는 것이다.In other words, the inner side of the connecting reinforcing member 20, 20 'by forming the reinforcing plate 21, 21' between the end portions of the square steel tube braces 10, 10 'facing each other , The reinforcing plate 21, 21 'is to significantly improve the connection performance of the brace receiving the compressive stress in the axial direction, the square steel pipe brace 10 with respect to the connection reinforcing member (20, 20') Even when the axial buckling stress of (10 ') occurs, as the reinforcing plate 21, 21' serves as a safety plate can be safe from buckling and deformation, structural performance is greatly improved. In addition, since the reinforcing plate 21, 21 'is responsible for increasing the rigidity of the coupling flanges 22, 22' formed at both ends of the connecting reinforcing member (20, 20 '), and so on. It is to play a role that greatly improves the structural rigidity and connection performance of the square steel tube brace (10, 10 ').

또한, 동일 형상을 갖고 제1의 사각강관 버팀보(10)와 제2의 사각강관 버팀보(10')의 대향 단부에서 상,하방향으로 대향 결합된 상태의 연결보강부재(20)(20')는 사각강관 버팀보(10)(10')를 일직선상으로 배치한 상태에서 이들 상,하의 연결보강부재(20)(20')에 형성된 결합플랜지(22)(22')가 서로 소정의 이격 간격을 갖도록 설계함에 따라 이들 상,하의 연결보강부재(20)(20')를 볼트와 너트를 사용하여 체결하는 경우 연결보강부재(20)(20') 전체가 사각강관 버팀보(10)(10')의 외면을 가압하여 조여주는 작용을 하므로 결국 이들 상호 간의 결합력이 크게 증대하는 것이다.In addition, the connecting reinforcing members 20 and 20 'having the same shape and coupled up and down in opposite directions at opposite ends of the first square steel tube brace 10 and the second square steel tube brace 10'. The coupling flanges 22 and 22 'formed on the upper and lower connection reinforcing members 20 and 20' in a state in which the rectangular steel pipe braces 10 and 10 'are disposed in a straight line are spaced apart from each other by a predetermined distance. When the upper and lower connecting reinforcing members 20, 20 'is fastened by using bolts and nuts, the entire connecting reinforcing members 20, 20' are square steel tube supports 10 and 10 '. Pressing the outer surface of the) acts to tighten, so that the bonding force between them is greatly increased.

또한, 상기의 연결보강부재(20)(20')의 결합플랜지(22)(22')와 수직부(23)(23')의 사이를 연결 고정하고 있는 다수의 보강편(26)(26') 역시 상기 연결보강부재(20)(20')에 대한 구조적이고 물리적인 강성을 증대시켜주어 연결보강부재(20)(20')에 대하여 작용하는 고도의 압축응력으로부터 좌굴이나 변형 등이 발생하지 않도록 함은 물론 상기 결합플랜지(22)(22')에 대한 강성을 크게 증대시켜 상기 사각강관 버팀보(10)(10')를 더욱 견고하게 연결 고정할 수 있는 것이다.In addition, a plurality of reinforcing pieces (26) and (26), which are connected and fixed between the coupling flanges (22) and (22 ') and the vertical portions (23) and (23') of the connecting reinforcing members (20, 20 '). ') Also increases the structural and physical rigidity of the connecting reinforcing members (20, 20'), resulting in buckling or deformation from the high compressive stress acting on the connecting reinforcing members (20, 20 '). Of course, the rigidity of the coupling flanges 22 and 22 'is greatly increased, and thus the square steel tube braces 10 and 10' can be more firmly connected and fixed.

이상과 같은 본 발명의 연결보강부재(20)(20')는 소정의 두께를 갖는 강판을 절곡 형성하거나 주물 형태로의 제작이 가능할 것이고, 적정 두께의 사각강관을 절단한 후 결합플랜지(22)(22')를 용접 등의 방법으로 연결하여 제작할 수도 있는 것이며, 상기의 보강격판(21)(21')은 중량 절감을 위해 중앙부에 살빼기 홈을 형성한 상태에서 이를 용접하여 고정시킬 수 있을 것이다.The connection reinforcing member 20, 20 'of the present invention as described above will be able to be bent or formed into a cast steel sheet having a predetermined thickness, after cutting the square steel pipe of the appropriate thickness coupling flange 22 The 22 'may be manufactured by welding or the like, and the reinforcing plate 21 and 21' may be welded and fixed in a state where a fat groove is formed in the center for weight reduction. .

도 5 내지 도 7은 이미 가설된 띠장(40)과 사각강관 버팀보(10)(10')를 서로 직접 접합하거나 기존에 사용되는 잭써포트(50)과 결합하기 위한 접합보강부재(30)를 도시한 것이다.5 to 7 illustrate a joint reinforcing member 30 for directly joining the already installed strip 40 and the square steel tube braces 10 and 10 'to each other or to a jack support 50 used in the related art. It is.

상기의 접합보강부재(30)는, 사각강관 버팀보(10)(10')의 단부가 삽입되기 위한 내폭을 갖는 사각의 삽입부(31)를 갖고 있고 삽입부(31)의 일측에는 보강재(32)가 형성되어 있으며, 보강재(32)의 끝단에는 체결판(33)이 형성되어 있는 것이다.The joint reinforcing member 30 has a rectangular insertion portion 31 having an inner width for inserting the end portions of the square steel tube braces 10 and 10 ', and on one side of the insertion portion 31, a reinforcing material 32 ) Is formed, and the fastening plate 33 is formed at the end of the reinforcing material (32).

또한, 상기의 삽입부(31)와 체결판(33)에는 각각 사각강관 버팀보(10)(10') 및 띠장(40) 또는 잭써포트(50)와 서로 결합시키시 위한 체결공(34)(34')이 관통 형성되어 있는 것이고, 상기 삽입부(31)와 체결판(33)의 사이에는 보강재(32)의 외면에 해당하는 위치의 지지편(35)(35')이 사방으로 연결 형성되어 있는 것이다.In addition, the insertion portion 31 and the fastening plate 33, respectively, fastening holes 34 and 34 for coupling with the square steel tube braces 10, 10 'and the strip 40 or the jack support 50, respectively. ') Is formed through, and between the insertion portion 31 and the fastening plate 33, support pieces 35 and 35' at positions corresponding to the outer surface of the reinforcing material 32 are connected in all directions. It is.

특히, 상기의 보강재(32)는 금속판재를 절곡 형성하여 된 다면체로 이루어져 있는 것으로서, 다면체로 된 보강재(32)는 축방향에 작용하는 고도의 압축응력으로부터 효과적인 지지력을 제공하므로 상기 접합보강부재(30)의 물리적 강성을 크게 증대시키므로 좌굴이나 변형으로부터 안전한 것이고, 상기 지지편(35)(35') 역시 축방향으로의 압축응력으로부터 접합보강부재(30)의 좌굴이나 변형이 방지되게 하는 역할을 수행하므로 고도의 물리적 강성을 갖는 접합보강부재(30)를 통해 사각강관 버팀보(10)(10')와 띠장(40) 또는 사각강관 버팀보(10)(10')과 잭써포트(50)와의 견고한 접합이 이루어질 수 있는 것이다.In particular, the reinforcing member 32 is composed of a polyhedron formed by bending a metal plate, the polyhedron reinforcing member 32 provides an effective support force from the high compressive stress acting in the axial direction so that the joint reinforcing member ( 30) greatly increases the physical stiffness and thus is safe from buckling or deformation, and the support pieces 35 and 35 'also serve to prevent buckling or deformation of the joint reinforcing member 30 from compressive stress in the axial direction. As a result, the rigidity of the square steel pipe braces (10) (10 ') and the band 40 or the square steel pipe braces (10) (10') and the jack support (50) through the joint reinforcing member 30 having a high physical rigidity. Bonding can be made.

이때, 상기의 삽입부(31)는 금속판재를 절곡 형성하거나 사각강관을 절단 형성하여 이루어진 것이어서 양측이 모두 개방되어 있을 것이므로 일측에 대한 마감작업을 수행하게 되는데, 이때에는 상기 삽입부(31)와 동일한 폭과 넓이를 갖는 별도의 지지격판(36)을 사용하게 된다. 이에 따라 상기의 보강재(32)와 지지 편(35)(35')은 상기 지지격판(36) 상에 용접 등을 이용하여 고정될 것이고, 상기 체결판(33)은 이와 같은 보강재(32)와 지지편(35)(35')의 끝단부에 용접 형성될 것이므로 결국 이들 삽입부(31)와 보강재(32) 및 체결판(33)과 지지편(35)(35') 그리고 지지격판(36)은 일체화된 연결 구조를 갖고 있어 구조적인 강성이 크게 증대하게 된다.At this time, the insertion part 31 is formed by bending the metal plate or cutting the rectangular steel pipe, so that both sides will be open, so that the finishing work for one side will be performed. In this case, the insertion part 31 and Separate support plates 36 having the same width and width are used. Accordingly, the reinforcing material 32 and the support piece 35, 35 ′ will be fixed on the supporting plate 36 by welding or the like, and the fastening plate 33 may be fixed with such a reinforcing material 32. Since the end portions of the support pieces 35 and 35 'will be welded, these inserts 31 and the reinforcement 32 and the fastening plate 33 and the support pieces 35 and 35' and the support plate 36 will eventually be formed. ) Has an integrated connection structure, which greatly increases the structural rigidity.

또한, 상기의 보강재(32)는 다면체로 이루어진 것으로서 바람직하게는 체결판(33)과 지지격판(36)의 사이에 사다리꼴 단면을 갖는 8각 기둥의 형상으로 제작하여 고정 형성함에 따라 축방향으로 작용하는 압축력에 저항할 수 있는 구조로 설계하는 것이 이상적인 것이고, 상기와 같은 8각의 사다리꼴 기둥의 평평한 측면부에 전기한 지지편(35)(35')을 덧대어 보강 형성함에 따라 상기의 접합보강부재(30)는 축방향으로 작용하는 고도의 압축응력으로부터 효과적인 지지력을 갖게 되는 것이다.In addition, the reinforcing material 32 is made of a polyhedron, preferably in the form of an octagonal column having a trapezoidal cross section between the fastening plate 33 and the support plate 36 to form a fixed action to act in the axial direction It is ideal to design the structure to be able to resist the compressive force, and the joint reinforcing member is formed by reinforcing and forming the support pieces 35 and 35 'which are described in the flat side portions of the octagonal trapezoidal columns as described above. 30 is effective bearing force from the high compressive stress acting in the axial direction.

이상과 같은 연결보강부재(20)(20') 및 접합보강부재(30)를 통한 사각강관 버팀보(10)(10')에 대한 연결 및 접합 시공이 합리적이면서도 효과적으로 이루어질 수 있는 것인데, 상기의 연결보강부재(20)(20') 및 접합보강부재(30)에 대하여 구조적인 강성을 증대시키기 위한 목적으로 적용된 보강편(26)(26') 및 지지편(35)(35')은 버팀보 간의 연결이나 버팀보와 띠장 간의 접합 또는 버팀보와 잭써포트와의 접합과정에서 볼트 및 너트를 회전시켜 상호 간의 체결 작업을 수행하는데 간섭이 되기도 한다.Connection and joint construction for the square steel pipe braces (10, 10 ') through the connection reinforcing member 20, 20' and the joint reinforcing member 30 as described above can be made reasonably and effectively, the above connection The reinforcing pieces 26, 26 'and the support pieces 35, 35' applied for the purpose of increasing the structural rigidity with respect to the reinforcing members 20, 20 'and the joint reinforcing member 30 are formed between the braces. It may interfere with each other's fastening by rotating bolts and nuts in the process of connection or jointing between the brace and the belt or the brace and the jack support.

즉, 사각강관 버팀보(10)(10')와 연결보강부재(20)(20')를 서로 체결함에 있어, 연결보강부재(20)(20')의 외측으로부터 체결공(25)(25')으로 끼워지는 볼트는 공구의 회전 조임에 방해를 받지 않을 것이나, 사각강관 버팀보(10)(10')의 내측에 위치하게 될 너트의 경우에는 손이 닿지 않거나 공구를 투입할 수 없는 상황에 직면할 수 있을 것이고, 접합보강부재(30)와 띠장(40) 또는 잭써포트(50)를 접합하고자 하는 경우에는 볼트 또는 너트 중 하나의 요소는 상기의 보강편(26)(26')이나 지지편(35)(35')으로부터 간섭하여 견고한 체결력을 제공할 수 없는 상태에 이르게 될 것이다. 이는, 기존의 접합장치가 면 좌굴 발생의 문제에도 불구하고 별도의 보강편 등을 추가할 수 없었던 주된 이유인 것이다.That is, in fastening the rectangular steel pipe braces 10, 10 'and the connecting reinforcing members 20, 20' to each other, the fastening holes 25, 25 'from the outside of the connecting reinforcing members 20, 20'. Bolts that are fitted with) will not interfere with the rotational tightening of the tool, but in the case of nuts that will be placed inside the square steel braces (10) (10 '), they cannot be reached or faced with situations where the tool cannot be inserted. In the case where the joint reinforcing member 30 and the strip 40 or the jack support 50 are to be joined, one of the bolts or nuts may be the reinforcing piece 26 or 26 'or the supporting piece. Interference from (35) (35 ') will lead to a state in which it cannot provide a firm clamping force. This is the main reason why the conventional joining device was not able to add a separate reinforcing piece, etc. despite the problem of surface buckling.

이에 따라, 본 발명에서는 상기와 같이 작업자의 손이나 공구 등의 진입이나 접근이 어려운 부분에서는 도 8의 도시와 같은 별도의 고정너트(60)를 사용함에 따라 볼트(70)의 회전만으로도 상호 간의 견고한 체결이 이루어질 수 있도록 한 것이다.Accordingly, in the present invention, the use of a separate fixing nut 60 as shown in Figure 8 in the difficult to enter or access the operator's hand or tool, as described above, even with the rotation of the bolt 70 is firmly mutually The fastening is to be made.

즉, 상기의 고정너트(60)는 일측으로 끼움부(61)가 돌출되어 있는 것이고 상기 끼움부(61)의 외면에는 간섭돌기(62)가 형성되어 있는 상태로 만들어져 있는 것이다.That is, the fixing nut (60) is a state in which the fitting portion 61 protrudes to one side, and the interference protrusion 62 is formed on the outer surface of the fitting portion 61.

이에 따라 작업자의 손이나 공구의 진입 또는 접근이나 회전반경이 허락되지 않는 협소한 체결부에서는 사각강관 버팀보(10)(10')에 형성된 체결공(11)(11')이나 연결보강부재(20)(20')에 형성된 체결공(25)(25') 또는 접합보강부재(30)에 형성된 체결공(34)(34')으로 상기 고정너트(60)의 끼움부(61)를 강제로 가압 결합시 키면 상기의 고정너트(60)는 끼움부(61)의 간섭돌기(62)가 사각강관 버팀보(10)(10')의 체결공(11)(11')이나 연결보강부재(20)(20')의 체결공(25)(25') 또는 접합보강부재(30)(30')의 체결공(34)(34') 내면에 강제로 결합되면서 회전력이 억제된 상태로 고정될 것이므로 별도의 볼트(50) 만을 회전시켜 서로 나사 체결할 수 있도록 한 것이다.Accordingly, in the narrow fastening portion where the operator's hand or tool is not allowed to enter or approach or have a radius of rotation, the fastening holes 11, 11 ′ or connecting reinforcing members 20 formed in the square steel braces 10, 10 ′. ) 20 'to the fastening holes 25 and 25' or the fastening holes 34 and 34 'formed in the joint reinforcing member 30 to force the fitting portion 61 of the fixing nut 60. When the pressure coupling is applied, the fixing nut 60 is the interference protrusion 62 of the fitting portion 61 is fastening holes 11, 11 'or connection reinforcing member 20 of the square steel tube braces 10, 10'. (20 ') of the fastening holes 25, 25' or bonding reinforcing members 30, 30 'of the fastening holes (34, 34') of the inner surface is forcibly coupled to the fixed state can be fixed It will be so that only the separate bolt 50 is rotated to be screwed together.

이를 상세히 살펴보면, 기존의 체결방식으로 H-Pile 또는 원형강관 등에서는 사용되는 일반볼트를 이용하여 볼트구멍에 삽입 체결하려면 볼트 또는 너트 회전을 위한 공간 확보문제가 발생하며, 이러한 문제의 대안으로 원형강관 등에서는 다음과 같은 2가지 대안을 일반적으로 채택하고 있다.Looking at this in detail, to insert into the bolt hole using a conventional bolt used in the conventional fastening method H-Pile or round steel pipe, there is a problem of securing a space for the bolt or nut rotation, alternatively round steel pipe Et al. Generally employ two alternatives:

그 첫 번째 대안이 볼트구멍을 너트 대용으로 사용하는 방법으로 이 방법을 적용하기 위해서는 볼트구멍이 형성되는 부재의 두께가 20㎜이상 증가해야 하는 문제가 발생한다. 상기의 다른 대안으로 적용되고 있는 또 다른 방법은 너트를 강관에 용접 등으로 결합하는 방법으로 이 방법 역시 볼트 변형 발생 시 볼트 머리만을 제거하는 방법으로 볼트의 해체가 불가능하여 원형강관을 절단해야하며 이로 인해 연결보강부재의 재사용이 어렵게 된다.The first alternative is to use the bolt hole as a substitute for the nut. In order to apply the method, the thickness of the member on which the bolt hole is formed must increase by 20 mm or more. Another method applied to the other alternative is to join the nut to the steel pipe by welding or the like. This method also removes the bolt head only when the bolt deformation occurs. This makes it difficult to reuse the connecting reinforcement member.

이에 따라 본 발명은 도 9의 도시와 같이 사각강관 버팀보(10)(10')와 연결보강부재(20)(20')를 결합하고자 하는 경우 또는 사각강관 버팀보(10)(10')와 접합보강부재(30)를 서로 접합하고자 하는 경우 또는 도 10의 도시와 같이 접합보강부재(30)와 띠장(40)을 접합하고자 하는 경우 또는 접합보강부재(30)와 잭써포트(50)를 접합하고자 하는 경우에 있어, 서로 일치하는 체결구멍 중 어느 하나의 체결구 멍(작업자의 손이나 공구의 접근이나 회전이 어려운 위치의)에 상기의 고정너트(60)를 가압 고정한 상태에서 별도의 볼트(70)를 상호 간에 나사 결합시키면 어렵지 않게 견고한 결속력을 얻을 수 있는 것이다.Accordingly, the present invention is to join the square steel pipe braces 10, 10 'and connecting reinforcing members 20, 20' or square steel pipe braces 10, 10 'as shown in FIG. When bonding the reinforcing member 30 to each other or to join the bonding reinforcing member 30 and the strip 40 as shown in Figure 10 or to join the bonding reinforcing member 30 and the jack support 50 In this case, the additional bolt 70 in the state in which the fixing nut 60 is pressed and fixed to any one of the fastener yoke (which is difficult to access or rotate the operator's hand or tool) among the matching holes. ) Can be screwed together to obtain a solid binding force without difficulty.

또한, 상기의 고정너트(60)는 해머 등의 타입력에 의해 임시 고정된 상태이므로 상기의 고정너트(60)가 불필요한 경우 타격에 의해 간편하게 분리 및 제거할 수 있으므로 사각강관 버팀보(10)(10')나 연결보강부재(20)(20') 또는 접합보강부재(30)를 본래의 형태 그대로 반복하여 재사용할 수 있는 것이고, 분리된 고정너트(60) 역시 외형을 그대로 유지하고 있을 것이므로 고정너트(60)가 필요한 부분에서 재사용이 가능하여 매우 경제적이면서도 합리적인 것이다.In addition, since the fixing nut 60 is temporarily fixed by a type force such as a hammer, the fixing nut 60 may be easily removed and removed by a blow when the fixing nut 60 is unnecessary. ') Or connecting reinforcing member 20, 20' or bonded reinforcing member 30 can be repeatedly reused as it is in its original form, and the fixed nut 60 is also retaining its appearance since the fixing nut 60 remains fixed as it is. It is very economical and reasonable because it can be reused where it is needed.

이상과 같은 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 이들을 대체할 수 있는 다양한 균등물과 변형 예들이 있을 수 있음을 이해하여야 한다.It is to be understood that both the foregoing general description and the following detailed description of the present invention are exemplary and explanatory and are intended to provide further explanation of the present invention as defined by the appended claims. Examples should be understood.

도 1은 본 발명에 따른 사각강관 버팀보의 시공상태를 보인 사시도1 is a perspective view showing a construction state of the square steel tube brace according to the present invention

도 2는 본 발명에 따른 사각강관 버팀보의 시공상태를 보인 분리 사시도Figure 2 is an exploded perspective view showing a construction state of the square steel tube brace in accordance with the present invention

도 3은 본 발명에 따른 사각강관 버팀보의 연결보강부재에 대한 사시도Figure 3 is a perspective view of the connection reinforcing member of the square steel tube brace according to the present invention

도 4는 본 발명에 따른 사각강관 버팀보의 연결보강부재에 의한 연결시공도Figure 4 is a connection construction by the connecting reinforcing member of the square steel tube brace according to the present invention

도 5는 본 발명에 따른 사각강관 버팀보의 접합보강부재에 대한 사시도5 is a perspective view of a joint reinforcing member of the square steel tube brace according to the present invention

도 6은 본 발명에 따른 사각강관 버팀보의 접합보강부재에 대한 분리 사시도Figure 6 is an exploded perspective view of the joint reinforcing member of the square steel tube brace in accordance with the present invention

도 7은 본 발명에 따른 사각강관 버팀보의 접합보강부재에 의한 접합시공도7 is a joint construction diagram of the joint reinforcing member of the square steel tube brace according to the present invention

도 8은 본 발명에 따른 사각강관 버팀보의 체결을 위한 고정너트의 사시도8 is a perspective view of a fixing nut for fastening the square steel tube brace according to the present invention

도 9는 본 발명에 따른 사각강관 버팀보의 연결보강부재의 체결부 단면도9 is a cross-sectional view of the fastening portion of the connection reinforcing member of the square steel tube brace according to the present invention

도 10은 본 발명에 따른 사각강관 버팀보의 접합보강부재의 체결부 단면도10 is a cross-sectional view of the fastening portion of the joint reinforcing member of the square steel tube brace according to the invention

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10,10' : 사각강관 버팀보 11,11' : 체결공10,10 ': Square steel pipe brace 11,11': Fastener

20,20' : 연결보강부재 21,21' : 보강격판20,20 ': Reinforcement member 21,21': Reinforcement plate

22,22' : 결합플랜지 23,23' : 수직부22,22 ': Combined flange 23,23': Vertical part

24,24' : 수평부 25,25' : 체결공24,24 ': Horizontal section 25,25': Fastening hole

26,26' : 보강편26,26 ': Reinforcement piece

30 : 접합보강부재 31 : 삽입부30: joint reinforcing member 31: insertion portion

32 : 보강재 33 : 체결판32: reinforcing material 33: fastening plate

34,34' : 체결공 35,35' : 지지편34,34 ': Fastener 35,35': Supporting piece

36 : 지지격판36: support plate

40 : 띠장40: Sash

50 : 잭써포트50: Jack Support

60 : 고정너트 61 : 끼움부60: fixing nut 61: fitting part

62 : 간섭돌기62: interference protrusion

70 : 볼트70: bolt

Claims (8)

지반굴착시 굴착 배면에 대하여 서로 마주하는 띠장 간에 결합되는 사각강관 버팀보의 시공구조에 있어서,In the construction structure of the square steel pipe braces coupled between the bands facing each other with respect to the back of the excavation when ground excavation, 서로 마주하는 띠장 간의 거리에 따라 사각강관 버팀보를 연결하고자, 제1의 사각강관 버팀보의 일측단 하측으로 제1의 연결보강부재를 돌출되도록 결합 형성하고, 제1의 사각강관 버팀보에 연결되기 위한 제2의 사각강관 버팀보의 일측단 상측에는 제2의 연결보강부재가 돌출되도록 결합 형성하여, 제1의 사각강관 버팀보 상에 결합된 제1의 연결보강부재 상에 제2의 사각강관 버팀보의 단부를 앉혀 놓아 상기 제1의 연결보강부재와 제2의 연결보강부재가 상,하로 대향되면 이들 제1의 연결보강부재와 제2의 연결보강부재를 서로 체결 고정함에 따라 제1 및 제2의 사각강관 버팀보에 대한 연결 시공이 이루어지도록 하고,In order to connect the square steel pipe brace according to the distance between the bands facing each other, the first connecting reinforcing member is formed to protrude to the lower side of one side of the first square steel pipe brace, and the first square steel pipe brace for connecting to The second connecting reinforcing member is formed to protrude from one side end upper side of the square steel pipe brace of 2, and the end of the second square steel pipe brace on the first connecting reinforcing member coupled to the first square steel pipe brace. When the first connection reinforcing member and the second connection reinforcing member face each other up and down, the first connection reinforcing member and the second connection reinforcing member are fastened to each other to fix the first and second square steel pipes. To make the connection to the brace 사각강관 버팀보의 단부를 띠장이나 잭써포트와 접합하고자, 사각강관 버팀보의 끝단부가 수용되는 삽입부를 갖는 접합보강부재를 구비하여 상기 삽입부와 사각강관 버팀보와의 체결이 이루어지도록 하고, 접합보강부재의 타측부는 띠장이나 잭써포트와 체결 형성함에 따라 사각강관 버팀보와 띠장 및 잭써포트가 접합보강부재를 통해 서로 접합 시공이 이루어지도록 함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조.In order to join the end of the rectangular steel tube brace with a band or jack support, the joint reinforcing member having an insertion portion for accommodating the end of the rectangular steel tube brace is made to be fastened to the insertion portion and the square steel tube brace, Connection and joint construction of the rectangular steel pipe brace for the temporary soil construction . 제 1항에 있어서,The method of claim 1, 사각강관 버팀보와 연결보강부재 간의 체결 또는 상,하 대향의 연결보강부재 간의 체결 또는 사각강관 버팀보와 접합보강부재 간의 체결 또는 접합보강부재와 띠장 간의 체결 또는 접합보강부재와 잭써포트 간의 체결 중 어느 하나의 체결부를 볼트와 너트로 결합 시공함에 있어,Either the connection between the square steel pipe brace and the connecting reinforcement member or the connection between the upper and lower facing reinforcing members or the connection between the square steel pipe brace and the joint reinforcing member or the connection between the joint reinforcing member and the band or the connection between the joint reinforcing member and the jack support In the joint construction of bolts and nuts, 상호 간의 일치된 체결공 중 손이나 공구의 접근이 어려운 위치에 해당하는 체결공으로 별도의 고정너트를 가압 고정하여 볼트의 회전만으로 상호 간의 견고한 체결이 이루어지도록 하되, 상기 고정너트는 외면에 간섭돌기가 형성된 끼움부가 돌출 형성되어 상기 끼움부를 체결공으로 가압하여 고정되게 함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조.Among the fastening holes matched with each other, a fastening hole corresponding to a position where a hand or a tool is difficult to access is press-fixed so that a solid fastening is achieved only by the rotation of the bolts. Connection and connection construction structure of the rectangular steel pipe brace for the temporary earthquake construction method characterized in that the formed fitting portion is formed to protrude to press the fitting portion to be fastened by the fastening hole. 지반굴착시 굴착 배면에 대하여 서로 마주하는 띠장 간에 결합되는 사각강관 버팀보를 연결보강부재에 의해 서로 연결하고, 연결된 사각강관 버팀보는 접합보강부재를 통해 띠장이나 잭써포트에 접합 시공함에 있어,In the case of ground excavation, the square steel pipe braces coupled between the bands facing each other with respect to the back of the excavation are connected to each other by connecting reinforcing members, and the connected square steel pipe braces are connected to the band or jack support through the joint reinforcing members. 연결보강부재는 서로 이웃하는 사각강관 버팀보의 끝단 상,하부에 각기 대향 체결되도록 분할 구성하되, 이들 연결보강부재는 사각강관 버팀보의 수평면에 밀착되는 수평부를 형성하고 수평부의 양측으로는 수직부가 형성되며 수직부의 끝단에는 수평의 결합플랜지가 각기 형성되고, 상기 수평부와 결합플랜지에는 체결공을 관통 형성하여 구성함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연 결 및 접합 시공구조를 위한 연결보강부재.The connecting reinforcing members are divided so that the upper and lower ends of the adjacent rectangular steel pipe braces are respectively opposed to each other, but these connecting reinforcing members form a horizontal part that is in close contact with the horizontal plane of the square steel pipe brace and the vertical parts are formed on both sides of the horizontal part. A horizontal coupling flange is formed at each end of the vertical portion, and the horizontal portion and the coupling flange are formed by penetrating through a fastening hole. absence. 제 3항에 있어서,The method of claim 3, wherein 연결보강부재는, 내면에 양측의 수직부를 서로 연결하면서도 수평부와 연결된 보강격판을 형성하여 구성됨을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조를 위한 연결보강부재.Connection reinforcement member, the connecting reinforcement member for the construction and connection construction of the square steel pipe brace for the temporary earthquake construction method characterized in that it is configured to form a reinforcing plate connected to the horizontal portion while connecting the vertical portions of both sides on the inner surface. 제 3항에 있어서,The method of claim 3, wherein 연결보강부재는, 수직부와 결합플랜지를 연결하는 보강편을 형성하여 구성함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조를 위한 연결보강부재.The connecting reinforcing member is a connecting reinforcing member for connecting and joining construction structure of the rectangular steel pipe brace for the temporary earthquake construction method characterized in that it is formed by forming a reinforcing piece connecting the vertical portion and the coupling flange. 지반굴착시 굴착 배면에 대하여 서로 마주하는 띠장 간에 결합되는 사각강관 버팀보를 연결보강부재에 의해 서로 연결하고, 연결된 사각강관 버팀보는 접합보강부재를 통해 띠장이나 잭써포트에 접합 시공함에 있어,In the case of ground excavation, the square steel pipe braces coupled between the bands facing each other with respect to the back of the excavation are connected to each other by connecting reinforcing members, and the connected square steel pipe braces are connected to the band or jack support through the joint reinforcing members. 접합보강부재는, 일측으로 사각강관 버팀보의 끝단부가 수용되기 위한 삽입부를 형성하고, 타측으로는 띠장이나 잭써포트와 접합되는 체결판을 형성하며, 삽 입부와 체결판의 사이에는 지지격판과 보강재를 연결 형성하되,The joint reinforcing member forms an insert for accommodating the end portion of the square steel tube brace on one side, and forms a fastening plate joined to the strip or jack support on the other side, and between the insert and the fastening plate, a support plate and a reinforcing material are provided. Make connections, 지지격판은 삽입부의 일측에 고정되고 상기의 보강재는 지지격판과 체결판을 서로 연결하여 고정되며, 상기 보강재는 다면체로 된 각관으로 구성됨을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조를 위한 접합보강부재.The support plate is fixed to one side of the insertion portion and the reinforcement is fixed by connecting the support plate and the fastening plate to each other, the reinforcement is connected and bonded construction of the rectangular steel pipe brace for the temporary earthquake method, characterized in that consisting of a rectangular polyhedron pipe Bonded reinforcement member for the structure. 제 6항에 있어서,The method of claim 6, 보강재는, 사다리꼴 외표면을 갖는 8각의 각관으로 구성함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조를 위한 접합보강부재.The reinforcing member is a joint reinforcing member for connecting and joining construction of the rectangular steel pipe brace for the temporary earthquake construction method, characterized in that composed of octagonal tube having a trapezoidal outer surface. 제 6항에 있어서,The method of claim 6, 접합보강부재는, 지지격판과 체결판의 사이에 보강재와 함께 연결되는 지지편을 방사상으로 결합 구성함을 특징으로 하는 가설 흙막이 공법용 사각강관 버팀보의 연결 및 접합 시공구조를 위한 접합보강부재.Joining reinforcing member is a joining reinforcing member for connecting and joining construction of the rectangular steel pipe brace for the temporary earthquake construction method characterized in that the coupling between the support plate and the fastening plate connected with the reinforcement radially configured.
KR1020090076112A 2009-08-18 2009-08-18 Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same KR101117546B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090076112A KR101117546B1 (en) 2009-08-18 2009-08-18 Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090076112A KR101117546B1 (en) 2009-08-18 2009-08-18 Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020110070477A Division KR20110096107A (en) 2011-07-15 2011-07-15 Apparatus for holding strut

Publications (2)

Publication Number Publication Date
KR20110018581A true KR20110018581A (en) 2011-02-24
KR101117546B1 KR101117546B1 (en) 2012-03-07

Family

ID=43776186

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090076112A KR101117546B1 (en) 2009-08-18 2009-08-18 Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same

Country Status (1)

Country Link
KR (1) KR101117546B1 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012165669A1 (en) * 2011-05-27 2012-12-06 (주)피에스테크 Earth retaining temporary structure and construction method for same
KR101289149B1 (en) * 2011-08-10 2013-07-23 재단법인 포항산업과학연구원 Structure and apparatus for connecting steel pipe struts
KR101322122B1 (en) * 2011-12-01 2013-10-28 재단법인 포항산업과학연구원 Connection Apparatus of Steel Pipe for Strut, Steel Pipe Strut Using Thereof and Method of Constructing The Steel Pipe Strut
KR200471055Y1 (en) * 2011-09-27 2014-01-29 윤희정 Supporting unit for wale
KR101357775B1 (en) * 2012-04-04 2014-02-04 (주)피에스테크 Apparatus for connecting struts using end plate
KR101502772B1 (en) * 2013-05-20 2015-03-18 주식회사 케이씨이엔지니어링 Connector Between Struts
WO2016003208A1 (en) * 2014-07-04 2016-01-07 (주)피에스테크 Temporary soil retaining structure using steel pipe strut and method for constructing same
KR20170036920A (en) 2015-09-24 2017-04-04 주식회사 씨케이 Connection apparatus of steel pipe for strut
CN108677965A (en) * 2018-05-25 2018-10-19 云南建投基础工程有限责任公司 Foundation pit assembled steel supports adjustable pressure device and its application method
KR20190116624A (en) 2018-04-05 2019-10-15 (주)대우건설 Support structure of temporary strut for construction period reduction
CN110607794A (en) * 2019-10-22 2019-12-24 山西省工业设备安装集团有限公司 Stable safety structure is protected to combined type deep basal pit support dimension
KR20230020874A (en) * 2021-08-04 2023-02-13 자이에스앤디 주식회사 Connection tool for steel pipe strut

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101448390B1 (en) * 2013-06-14 2014-10-07 고형배 Connecting structure of square steel strip and square steel supporting beam
KR101941818B1 (en) 2018-05-08 2019-01-23 유승열 Connection and junction structure of steel pipe for strut
KR102421264B1 (en) * 2020-05-07 2022-07-14 강용길 Beam Assembly Made of Sheet Pile and Manufacturing Method Thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001214543A (en) 2000-02-02 2001-08-10 East Japan Railway Co Joint for tie
KR100733719B1 (en) 2006-02-15 2007-07-04 (주)핸스건설 Length control type steel pipe strut

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012165669A1 (en) * 2011-05-27 2012-12-06 (주)피에스테크 Earth retaining temporary structure and construction method for same
KR101289149B1 (en) * 2011-08-10 2013-07-23 재단법인 포항산업과학연구원 Structure and apparatus for connecting steel pipe struts
KR200471055Y1 (en) * 2011-09-27 2014-01-29 윤희정 Supporting unit for wale
KR101322122B1 (en) * 2011-12-01 2013-10-28 재단법인 포항산업과학연구원 Connection Apparatus of Steel Pipe for Strut, Steel Pipe Strut Using Thereof and Method of Constructing The Steel Pipe Strut
KR101357775B1 (en) * 2012-04-04 2014-02-04 (주)피에스테크 Apparatus for connecting struts using end plate
KR101502772B1 (en) * 2013-05-20 2015-03-18 주식회사 케이씨이엔지니어링 Connector Between Struts
WO2016003208A1 (en) * 2014-07-04 2016-01-07 (주)피에스테크 Temporary soil retaining structure using steel pipe strut and method for constructing same
KR20170036920A (en) 2015-09-24 2017-04-04 주식회사 씨케이 Connection apparatus of steel pipe for strut
KR20190116624A (en) 2018-04-05 2019-10-15 (주)대우건설 Support structure of temporary strut for construction period reduction
CN108677965A (en) * 2018-05-25 2018-10-19 云南建投基础工程有限责任公司 Foundation pit assembled steel supports adjustable pressure device and its application method
CN110607794A (en) * 2019-10-22 2019-12-24 山西省工业设备安装集团有限公司 Stable safety structure is protected to combined type deep basal pit support dimension
KR20230020874A (en) * 2021-08-04 2023-02-13 자이에스앤디 주식회사 Connection tool for steel pipe strut

Also Published As

Publication number Publication date
KR101117546B1 (en) 2012-03-07

Similar Documents

Publication Publication Date Title
KR101117546B1 (en) Structure for connecting and jointing square still supporting beam in temporary soil sheathing and reinforcing members for the same
KR101357775B1 (en) Apparatus for connecting struts using end plate
KR100838736B1 (en) Connection and junction apparatus of steel pipe for strut
KR101289149B1 (en) Structure and apparatus for connecting steel pipe struts
KR101354857B1 (en) Strut having angle pipe section symmetrical with neural axis
KR102066926B1 (en) Connecting Structure of Steel Pipe Strut
KR20120055236A (en) Prefabricated strut connection structure
KR200381589Y1 (en) A pile head reinforcement structure of precastconcrete pile
KR101322020B1 (en) Connection apparatus of Steel pipe for strut, steel pipe strut using thereof and method of constructing the steel pipe strut
JP2005282339A (en) Structure for reinforcing hollow-steel-pipe steel tower by using splice l-shaped material
KR20120104798A (en) Apparatus for connecting struts to each other
JP3564669B2 (en) Reinforcement spacer and foundation pile method
JP4131467B2 (en) Tunnel support structure and tunnel support method
JP2927402B2 (en) Column-beam joint structure of concrete building
KR101325383B1 (en) Steel Pipe Strut Connection Structure
KR200386881Y1 (en) A pile head reinforcement structure of precast concrete pile
KR200378210Y1 (en) A pile head reinforcement structure of precastconcrete pile
JP2005248487A (en) Reinforcing structure by splice round material for hollow steel pipe steel tower
JP2003232077A (en) Beam reinforcing fixture and beam through hole reinforcing structure using the same
KR101958768B1 (en) Structure for Constructing the Lagging Board using Strut Beam having Reinforcement Bar
KR20180087701A (en) Concrete Filled steel Tube of Aseismic Reinforcement and Method of Aseismic Reinforcement for Existing Building Structure using the Same
JP6736830B2 (en) Reconstruction method for concrete structure with underground structure
JP3347942B2 (en) Unit building and its construction method
KR101359159B1 (en) Jointing element for steel pipe support strut of retaining wall and joint structure using thereof
JP2006299584A (en) Aseismatic reinforcing joining structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
A107 Divisional application of patent
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160211

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170224

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180209

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190211

Year of fee payment: 8