KR20100033685A KR1020080092673A KR20080092673A KR20100033685A KR 20100033685 A KR20100033685 A KR 20100033685A KR 1020080092673 A KR1020080092673 A KR 1020080092673A KR 20080092673 A KR20080092673 A KR 20080092673A KR 20100033685 A KR20100033685 A KR 20100033685A
Authority
KR
South Korea
Prior art keywords
wall
underground outer
groove
grooves
underground
Prior art date
Application number
KR1020080092673A
Other languages
Korean (ko)
Inventor
이종민
정호완
Original Assignee
(주)연우피씨엔지니어링
창조개발 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)연우피씨엔지니어링, 창조개발 주식회사 filed Critical (주)연우피씨엔지니어링
Priority to KR1020080092673A priority Critical patent/KR20100033685A/en
Publication of KR20100033685A publication Critical patent/KR20100033685A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Electromagnetism (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Building Environments (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE: A PC wall for an underground outer wall with a hollow groove for preventing condensation is provided to improve construction performance and workability by preventing condensation and a water leakage. CONSTITUTION: A PC wall for an underground outer wall with a hollow groove for preventing condensation comprises multiple hollow grooves, joints, and a sealing material. The hollow grooves are formed inside a PC underground outer wall, and prevent dew condensation. The joints are formed in the left and right sides of the PC underground outer wall, and filled with the sealing material. The sealing material prevents water from flowing inside.

Description

PC wall for basement of side wall with hollow groove to prevent condensation

The present invention is formed to improve the condensation, leakage, cracking and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building, which is to form the wall construction of the PC, Inside the PC Underground Wall (PC Wall), a number of hollow condensation prevention grooves are provided, and the connection joints with neighboring PC Underground Walls are formed to fill the concave-convex, groove-coupled coupling parts and leak-proof water stops. The workability and productivity (air shortening) according to the construction of the outer wall is improved, while condensation, leakage and cracks are prevented. .

In general, as shown in Figure 1, the underground building is generally made after the excavation (civil engineering) and the foundation (floor), and then using the formwork on the construction of the outer wall with the site concrete by RC method slab on the upper end of the outer wall It is formed by raising (half PC slab).

However, in the exterior wall construction by the RC method, after the formwork is installed to erect the wall, the concrete wall must be cured by placing concrete in the formwork so that the following process can proceed, so that the formwork must be installed and removed every day. In addition, there is a disadvantage in that the construction period is long according to this, as well as the construction wastes used when constructing the site-casting concrete was generated, causing the environment pollution.

In addition, condensation occurs on the outer circumferential surface of the conventional outer wall, which is constructed by the site concrete, and condensation occurs when the water flows to the interior outer wall in severe cases, while cracks occur on the outer wall that is not sufficiently dried. There is a problem that leads to leakage.

The present invention is to solve the above-mentioned problems, the technical gist of the construction is to improve the condensation, leakage, cracking and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building It is to be formed, the wall construction to form a PC, but the inside of the PC underground outer wall (PC wall) to provide a plurality of hollow grooves for preventing condensation, the connection joint with the neighboring PC underground outer wall of the concave-convex, groove groove type Condensation is characterized in that the workability and productivity (shortening of air) are improved due to the construction of the coupling part and the water repellent material for preventing leakage, while condensation and leakage and cracks are prevented to improve the workability. It is an object of the present invention to provide a PC wall for an underground outer wall having a hollow groove for prevention.

In order to achieve the above object, the present invention includes a plurality of hollow grooves (100) formed to penetrate in the vertical direction inside the PC underground outer wall (P) to prevent condensation on the indoor side; A joint part 200 formed in a left and right direction of the PC underground outer wall P and formed to be coupled to a neighboring PC underground outer wall P; An index member 300 filled in the joint part or introduced to both ends in a width direction to block water from flowing from the outside to the inside; .

At this time, the hollow groove 100 is formed with a diameter of 30 ~ 150mm, it is preferable that 3 to 20 dogs are arranged at equal intervals in the longitudinal left and right sides of the PC underground outer wall.

Meanwhile, the joint 200 has grooves 210 formed at both ends of the PC underground outer walls facing each other so as to connect and couple neighboring PC underground outer walls P to the left and right, and at the center of the groove 210. A plurality of 'U' shaped reinforcement reinforcement reinforcement 220 branched to the outside is formed so as to overlap the upper and lower neighboring reinforcement (220a) based on the support reinforcement 10, the width except the groove At both ends of the direction, it is preferable that the index member 300 is formed so as to be poured by the site concrete (C).

Thus, as another embodiment, the joint 200 forms grooves 210 inwardly at one end of the PC underground outer walls facing each other to connect and couple neighboring PC underground outer walls P to the left and right, and the other end. It is also possible to form a fitting protrusion 230 corresponding to the groove 210, the field concrete (C) is poured after the index material is embedded in both ends of the width direction except the groove and the fitting protrusion.

In addition, the joint 200 as another embodiment, the grooves 210 are formed inwardly at both ends of the PC underground outer wall facing each other to connect and couple the neighboring PC underground outer wall (P) from side to side, the groove At the center of the 210, a plurality of 'U' shaped reinforcing bars 220 branched outward are arranged to overlap with the reinforcing bars 220a adjacent to each other based on the supporting bars 10. , The index member 300 is embedded at one end of the width direction except for the groove, the other end is formed to be formed by the field concrete (C) after the expansion opening is formed, blocked by the form 500 It is also possible.

As described above, the present invention is to form the construction of the basement outer wall of the building in the PC, the interior of the PC underground outer wall is provided with a plurality of hollow grooves for preventing condensation, and the joint joint with the neighboring PC underground outer wall, irregularities, groove coupling type Formed to fill the coupling portion and the water leakage preventing material to improve the workability and productivity (shortening the air) according to the construction of the basement outer wall, while condensation and leakage and cracks are prevented, the construction properties are excellently improved.

DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the accompanying drawings.

First, as shown in Figure 2, the present invention is formed to improve the condensation, leaks, cracks and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building, This is to form a wall construction (PC wall), the inside of the PC underground outer wall is provided with a plurality of hollow grooves for preventing condensation, the connection joint with the neighboring PC underground outer wall and the coupling portion of the uneven, groove coupling type and Formed to fill the leakage preventing water to improve the workability and productivity (shortening the air) according to the construction of the basement outer wall, while condensation and leakage and cracks are prevented to be configured to improve the workability is excellent.

At this time, the plurality of hollow grooves (100) formed so as to penetrate in the vertical direction inside the PC underground outer wall 10 to prevent the condensation of the interior side; A joint part 200 formed in left and right directions of the PC underground outer wall to be connected and coupled to neighboring PC underground outer walls; An index member 300 filled in the joint part or introduced to both ends in a width direction, and formed to block water from flowing from the outside to the inside; .

At this time, the hollow groove 100 is formed with a diameter of 30 ~ 150mm, it is preferable that 3 to 20 dogs are arranged at equal intervals in the longitudinal left and right sides of the PC underground outer wall.

Thus, the joint 200 is formed with grooves 210 at both ends of the PC underground outer walls facing each other to couple the neighboring PC underground outer wall 10 to the left and right, the groove 210 as an embodiment. In the center of the plurality of 'U (yu)' reinforcement reinforcement reinforcement (220) is reinforcement is formed to overlap the upper and lower neighboring reinforcement (220a) based on the support reinforcement 10, the groove Except for the width direction both ends may be formed to be poured by the field concrete (C) after the index member 300 is embedded.

In addition, the joint 200 as another embodiment, the groove 210 is formed inward at one end of the PC underground outer wall facing each other to connect and couple the neighboring PC underground outer wall 10 to the left and right, the other end It is also possible to form a fitting protrusion 230 corresponding to the groove 210, the site concrete (C) is poured after the water injecting material 300 is embedded in both ends of the width direction except the groove and the fitting protrusion Do.

In addition, the joint 200 as another embodiment, the grooves 210 are formed inwardly at both ends of the PC underground outer wall facing each other to connect and couple the neighboring PC underground outer wall (P) from side to side, In the center of the groove 210, a plurality of 'U' shaped reinforcement reinforcing bars 220 branched to the outside are arranged to overlap with the reinforcing bars 220a adjacent to the support reinforcing bar 10, up and down And, one end of the width direction except the groove in one end portion of the index member 300 is embedded, the other end is formed to be cast by the field concrete (C) after the expansion opening is formed is blocked by the formwork 500 It is also possible.

As described above, the present invention is to form a construction (PC) wall of the basement of the outer wall of the building, the inside of the PC wall is provided with a plurality of hollow grooves for preventing condensation, irregularities, grooves in the connection joint with the neighboring PC wall Formed to fill the coupling part of the coupling type and the water-proof material for preventing leakage improves workability and productivity (shortening of air) due to the construction of the underground outer wall, and prevents condensation, leakage, and cracks, and improves workability. have.

The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by those skilled in the art without departing from the gist of the present invention as claimed in the claims. Of course, such changes will fall within the scope of the claims.

1 is an exemplary view showing that the outer wall is constructed by the RC construction method when construction of a general underground building,

Figure 2 is a side view showing that the underground building is constructed using the PC wall according to the present invention,

3 is a plan view of FIG.

4 is an enlarged detailed view of the joint part according to FIG. 3;

5 is another exemplary embodiment of FIG. 4;

6 is another exemplary view of FIG. 4.

<Description of Major Symbols in Drawing>

100 ... hollow groove 200 ... joint

210 ... recess 220 ... rebar

230 ... fitting 300 ... index material

Claims (5)

A plurality of hollow grooves 100 penetrating in the vertical direction in the PC underground outer wall P to prevent indoor condensation; A joint part 200 formed in a left and right direction of the PC underground outer wall P and formed to be coupled to a neighboring PC underground outer wall P; An index member 300 filled in the joint part or introduced to both ends in a width direction to block water from flowing from the outside to the inside; PC wall for the underground outer wall having a hollow groove for preventing condensation, characterized in that made. The method of claim 1, wherein the hollow groove 100 30 ~ 150mm in diameter, the base wall PC wall having a condensation prevention hollow groove, characterized in that 3 to 20 pieces are arranged at equal intervals in the longitudinal left and right sides of the PC underground outer wall. The method according to claim 1 or 2, wherein the joint 200 Grooves 210 are formed at both ends of the PC underground outer walls facing each other so as to connect and couple neighboring PC underground outer walls P to the left and right, and a plurality of 'U' branches outward in the center of the grooves 210. The 'shaped' reinforcement reinforcing bar 220 is arranged to overlap with the reinforcing bar 220a adjacent to the support reinforcing bar 10 based on the reinforcing bar 10, and the index member 300 at both ends in the width direction excluding the grooves. After the embedded PC wall for underground outer wall having a hollow groove for preventing condensation, characterized in that is formed to be cast by the site concrete (C). The method according to claim 1 or 2, wherein the joint 200 One side of the PC underground outer wall facing each other to connect and combine neighboring PC underground outer wall (P) to the left and right to form a groove 210 inward, the other end fitting groove 230 corresponding to the groove 210 Forming, the PC wall for underground outer wall with condensation prevention hollow groove, characterized in that the field concrete (C) is formed to be poured after the index material is embedded in the width direction both ends except the groove and the fitting projection. The method according to claim 1 or 2, wherein the joint 200 Grooves 210 are formed at both ends of the PC underground outer walls facing each other so as to connect and couple neighboring PC underground outer walls P to the left and right, and a plurality of 'U' branches outward in the center of the grooves 210. It is formed so that the reinforcement reinforcing bar 220 is reinforced and overlaps the neighboring reinforcing bar 220a up and down based on the support bar 10, and at one end of the width direction excluding the groove, 300 is embedded, the other end is formed with an expanded opening is blocked by the formwork 500 is blocked by the concrete concrete (C) is formed so as to be cast by the site concrete (C) for the underground outer wall PC wall .
KR1020080092673A 2008-09-22 2008-09-22 Pc wall for basement of side wall KR20100033685A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080092673A KR20100033685A (en) 2008-09-22 2008-09-22 Pc wall for basement of side wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080092673A KR20100033685A (en) 2008-09-22 2008-09-22 Pc wall for basement of side wall

Publications (1)

Publication Number Publication Date
KR20100033685A true KR20100033685A (en) 2010-03-31

Family

ID=42182484

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080092673A KR20100033685A (en) 2008-09-22 2008-09-22 Pc wall for basement of side wall

Country Status (1)

Country Link
KR (1) KR20100033685A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101934804B1 (en) * 2018-02-22 2019-03-18 주식회사 케이씨산업 Double wall structure and fabrication and installation method of structures using the same
CN115450254A (en) * 2022-09-29 2022-12-09 中国建筑第八工程局有限公司 Construction method for horizontal construction joint water-stop steel plate non-through counterfort steel column

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101934804B1 (en) * 2018-02-22 2019-03-18 주식회사 케이씨산업 Double wall structure and fabrication and installation method of structures using the same
CN115450254A (en) * 2022-09-29 2022-12-09 中国建筑第八工程局有限公司 Construction method for horizontal construction joint water-stop steel plate non-through counterfort steel column

Similar Documents

Publication Publication Date Title
KR100743369B1 (en) Precast culvert assembly for both culvert and utility-pipe conduit
KR100920204B1 (en) Constructing method of precast pier footing for bridge
KR20070072417A (en) Panel module for tunnel lining and method of tunnel lining using the same
KR100909277B1 (en) Pier foundation with steel pipe and assembly structure
KR20080061580A (en) Precast concrete file and method for constructing thereof
KR102193147B1 (en) Precast Concrete Culvert and Method for Constructing The same
KR100952608B1 (en) Concrete pipe structure
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
KR101863627B1 (en) Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system
KR20200104531A (en) Water resist increasing built-up PC concrete culvert box and waterway and underground duct using it
KR101038945B1 (en) A filling structure of upper part of a tunnel and its procedure
KR20100033685A (en) Pc wall for basement of side wall
KR101774865B1 (en) A double wall
KR102263318B1 (en) Arch-type Precast Structure with Improved Assembly Structure and Construction Method Thereof
KR102364207B1 (en) Precast culverts and the construction method thereof
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
KR20100042441A (en) Inducing waterproof structure of underground diaphragm wall
CN114045880A (en) Basement post-cast strip treatment process
KR200464844Y1 (en) Instrument structure of A valve room base
KR102298267B1 (en) Precast culvert blocks for underground power cable conduits
KR100302684B1 (en) A method of constructing valve room
CN220057988U (en) Junction structure of basement outer wall and foundation pit horizontal support
CN215594122U (en) Waterproof structure of pipe jacking pipe joint and pipe jacking well
KR102125014B1 (en) Reinforcement and waterproof structure of vertical shafts for utility interface
KR200329055Y1 (en) Structure of side coupling part of pc wall member with function of waterproof in corner part and pc wall member therefor