KR20100033685A - Pc wall for basement of side wall - Google Patents
Pc wall for basement of side wall Download PDFInfo
- Publication number
- KR20100033685A KR20100033685A KR1020080092673A KR20080092673A KR20100033685A KR 20100033685 A KR20100033685 A KR 20100033685A KR 1020080092673 A KR1020080092673 A KR 1020080092673A KR 20080092673 A KR20080092673 A KR 20080092673A KR 20100033685 A KR20100033685 A KR 20100033685A
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- underground outer
- groove
- grooves
- underground
- Prior art date
Links
- 230000005494 condensation Effects 0.000 claims abstract description 28
- 238000009833 condensation Methods 0.000 claims abstract description 28
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 11
- 230000002787 reinforcement Effects 0.000 claims description 14
- 230000003014 reinforcing effect Effects 0.000 claims description 11
- 238000000034 method Methods 0.000 claims description 10
- 238000009415 formwork Methods 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 7
- 230000002265 prevention Effects 0.000 claims description 4
- 230000000149 penetrating effect Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 22
- 239000003566 sealing material Substances 0.000 abstract 3
- 230000008878 coupling Effects 0.000 description 8
- 238000010168 coupling process Methods 0.000 description 8
- 238000005859 coupling reaction Methods 0.000 description 8
- 238000004904 shortening Methods 0.000 description 5
- 230000015556 catabolic process Effects 0.000 description 3
- 238000006731 degradation reaction Methods 0.000 description 3
- 241000282472 Canis lupus familiaris Species 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002940 repellent Effects 0.000 description 1
- 239000005871 repellent Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Electromagnetism (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Building Environments (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
The present invention is formed to improve the condensation, leakage, cracking and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building, which is to form the wall construction of the PC, Inside the PC Underground Wall (PC Wall), a number of hollow condensation prevention grooves are provided, and the connection joints with neighboring PC Underground Walls are formed to fill the concave-convex, groove-coupled coupling parts and leak-proof water stops. The workability and productivity (air shortening) according to the construction of the outer wall is improved, while condensation, leakage and cracks are prevented. .
In general, as shown in Figure 1, the underground building is generally made after the excavation (civil engineering) and the foundation (floor), and then using the formwork on the construction of the outer wall with the site concrete by RC method slab on the upper end of the outer wall It is formed by raising (half PC slab).
However, in the exterior wall construction by the RC method, after the formwork is installed to erect the wall, the concrete wall must be cured by placing concrete in the formwork so that the following process can proceed, so that the formwork must be installed and removed every day. In addition, there is a disadvantage in that the construction period is long according to this, as well as the construction wastes used when constructing the site-casting concrete was generated, causing the environment pollution.
In addition, condensation occurs on the outer circumferential surface of the conventional outer wall, which is constructed by the site concrete, and condensation occurs when the water flows to the interior outer wall in severe cases, while cracks occur on the outer wall that is not sufficiently dried. There is a problem that leads to leakage.
The present invention is to solve the above-mentioned problems, the technical gist of the construction is to improve the condensation, leakage, cracking and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building It is to be formed, the wall construction to form a PC, but the inside of the PC underground outer wall (PC wall) to provide a plurality of hollow grooves for preventing condensation, the connection joint with the neighboring PC underground outer wall of the concave-convex, groove groove type Condensation is characterized in that the workability and productivity (shortening of air) are improved due to the construction of the coupling part and the water repellent material for preventing leakage, while condensation and leakage and cracks are prevented to improve the workability. It is an object of the present invention to provide a PC wall for an underground outer wall having a hollow groove for prevention.
In order to achieve the above object, the present invention includes a plurality of hollow grooves (100) formed to penetrate in the vertical direction inside the PC underground outer wall (P) to prevent condensation on the indoor side; A
At this time, the
Meanwhile, the joint 200 has
Thus, as another embodiment, the joint 200 forms grooves 210 inwardly at one end of the PC underground outer walls facing each other to connect and couple neighboring PC underground outer walls P to the left and right, and the other end. It is also possible to form a
In addition, the joint 200 as another embodiment, the
As described above, the present invention is to form the construction of the basement outer wall of the building in the PC, the interior of the PC underground outer wall is provided with a plurality of hollow grooves for preventing condensation, and the joint joint with the neighboring PC underground outer wall, irregularities, groove coupling type Formed to fill the coupling portion and the water leakage preventing material to improve the workability and productivity (shortening the air) according to the construction of the basement outer wall, while condensation and leakage and cracks are prevented, the construction properties are excellently improved.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the accompanying drawings.
First, as shown in Figure 2, the present invention is formed to improve the condensation, leaks, cracks and workability degradation of the outer wall generated from the existing RC method using the formwork in the construction of the outer wall of the building, This is to form a wall construction (PC wall), the inside of the PC underground outer wall is provided with a plurality of hollow grooves for preventing condensation, the connection joint with the neighboring PC underground outer wall and the coupling portion of the uneven, groove coupling type and Formed to fill the leakage preventing water to improve the workability and productivity (shortening the air) according to the construction of the basement outer wall, while condensation and leakage and cracks are prevented to be configured to improve the workability is excellent.
At this time, the plurality of hollow grooves (100) formed so as to penetrate in the vertical direction inside the PC underground
At this time, the
Thus, the joint 200 is formed with
In addition, the
In addition, the
As described above, the present invention is to form a construction (PC) wall of the basement of the outer wall of the building, the inside of the PC wall is provided with a plurality of hollow grooves for preventing condensation, irregularities, grooves in the connection joint with the neighboring PC wall Formed to fill the coupling part of the coupling type and the water-proof material for preventing leakage improves workability and productivity (shortening of air) due to the construction of the underground outer wall, and prevents condensation, leakage, and cracks, and improves workability. have.
The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by those skilled in the art without departing from the gist of the present invention as claimed in the claims. Of course, such changes will fall within the scope of the claims.
1 is an exemplary view showing that the outer wall is constructed by the RC construction method when construction of a general underground building,
Figure 2 is a side view showing that the underground building is constructed using the PC wall according to the present invention,
3 is a plan view of FIG.
4 is an enlarged detailed view of the joint part according to FIG. 3;
5 is another exemplary embodiment of FIG. 4;
6 is another exemplary view of FIG. 4.
<Description of Major Symbols in Drawing>
100 ...
210
230
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080092673A KR20100033685A (en) | 2008-09-22 | 2008-09-22 | Pc wall for basement of side wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080092673A KR20100033685A (en) | 2008-09-22 | 2008-09-22 | Pc wall for basement of side wall |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20100033685A true KR20100033685A (en) | 2010-03-31 |
Family
ID=42182484
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020080092673A KR20100033685A (en) | 2008-09-22 | 2008-09-22 | Pc wall for basement of side wall |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20100033685A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101934804B1 (en) * | 2018-02-22 | 2019-03-18 | 주식회사 케이씨산업 | Double wall structure and fabrication and installation method of structures using the same |
CN115450254A (en) * | 2022-09-29 | 2022-12-09 | 中国建筑第八工程局有限公司 | Construction method for horizontal construction joint water-stop steel plate non-through counterfort steel column |
-
2008
- 2008-09-22 KR KR1020080092673A patent/KR20100033685A/en not_active Application Discontinuation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101934804B1 (en) * | 2018-02-22 | 2019-03-18 | 주식회사 케이씨산업 | Double wall structure and fabrication and installation method of structures using the same |
CN115450254A (en) * | 2022-09-29 | 2022-12-09 | 中国建筑第八工程局有限公司 | Construction method for horizontal construction joint water-stop steel plate non-through counterfort steel column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100743369B1 (en) | Precast culvert assembly for both culvert and utility-pipe conduit | |
KR100920204B1 (en) | Constructing method of precast pier footing for bridge | |
KR20070072417A (en) | Panel module for tunnel lining and method of tunnel lining using the same | |
KR100909277B1 (en) | Pier foundation with steel pipe and assembly structure | |
KR20080061580A (en) | Precast concrete file and method for constructing thereof | |
KR102193147B1 (en) | Precast Concrete Culvert and Method for Constructing The same | |
KR100952608B1 (en) | Concrete pipe structure | |
CN216131506U (en) | Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure | |
KR101863627B1 (en) | Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system | |
KR20200104531A (en) | Water resist increasing built-up PC concrete culvert box and waterway and underground duct using it | |
KR101038945B1 (en) | A filling structure of upper part of a tunnel and its procedure | |
KR20100033685A (en) | Pc wall for basement of side wall | |
KR101774865B1 (en) | A double wall | |
KR102263318B1 (en) | Arch-type Precast Structure with Improved Assembly Structure and Construction Method Thereof | |
KR102364207B1 (en) | Precast culverts and the construction method thereof | |
CN111335445B (en) | Construction method of concrete catch basin by using steel pipe as inner mold | |
KR20100042441A (en) | Inducing waterproof structure of underground diaphragm wall | |
CN114045880A (en) | Basement post-cast strip treatment process | |
KR200464844Y1 (en) | Instrument structure of A valve room base | |
KR102298267B1 (en) | Precast culvert blocks for underground power cable conduits | |
KR100302684B1 (en) | A method of constructing valve room | |
CN220057988U (en) | Junction structure of basement outer wall and foundation pit horizontal support | |
CN215594122U (en) | Waterproof structure of pipe jacking pipe joint and pipe jacking well | |
KR102125014B1 (en) | Reinforcement and waterproof structure of vertical shafts for utility interface | |
KR200329055Y1 (en) | Structure of side coupling part of pc wall member with function of waterproof in corner part and pc wall member therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |