KR20090127789A - Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof - Google Patents

Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof Download PDF

Info

Publication number
KR20090127789A
KR20090127789A KR1020080056086A KR20080056086A KR20090127789A KR 20090127789 A KR20090127789 A KR 20090127789A KR 1020080056086 A KR1020080056086 A KR 1020080056086A KR 20080056086 A KR20080056086 A KR 20080056086A KR 20090127789 A KR20090127789 A KR 20090127789A
Authority
KR
South Korea
Prior art keywords
concrete girder
girder
overcompression
load
control load
Prior art date
Application number
KR1020080056086A
Other languages
Korean (ko)
Inventor
고관석
Original Assignee
(주)에스엔티엔지니어링
이선애
한명숙
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)에스엔티엔지니어링, 이선애, 한명숙 filed Critical (주)에스엔티엔지니어링
Priority to KR1020080056086A priority Critical patent/KR20090127789A/en
Publication of KR20090127789A publication Critical patent/KR20090127789A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • E04C3/26Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members prestressed
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Abstract

PURPOSE: A prestressing method of a concrete girder loading load for controlling excessive compression, and a bridge construction method using the same are provided to prevent applying excessive compressive stress to the concrete girder. CONSTITUTION: A bridge construction method using a prestressed concrete girder is as follows. A main tendon(11) is arranged on the tension side of a girder for removing load for controlling excessive compression, and a concrete girder(10) is manufactured. A part of the main tendon is strained and fixed on the ground by using an anchorage device(20). Prestress is applied to the concrete girder as much as excessive compressive stress is not generated, and is temporarily reduced by loading load for controlling excessive compression(12). The loading state is released in a state load is applied to the concrete girder so that tension stress is reduced by compressive stress.

Description

과압축 제어용 하중을 재하한 콘크리트 거더의 프리스트레싱 방법 및 이를 이용한 교량의 시공방법{Method for Prestressing Concrete Girder Using temporary loading and Method for Constructing Bridge Using thereof}Method for prestressing concrete girder using temporary loading and method for constructing bridge using

도 1은 제작장에 놓여 있는 종래의 콘크리트 거더의 개략도이다.1 is a schematic view of a conventional concrete girder placed in a fabrication site.

도 2는 도 1에 도시된 종래의 콘크리트 거더 주 긴장재 전체에 순차적으로 프리스트레스를 도입하지 않고 동시에 전체 긴장재를 프리스트레싱한 상태에서의 응력을 보여주는 응력상태도이다.FIG. 2 is a state diagram showing stresses in a state in which prestressing is performed at the same time without prestressing the entire concrete girder main tension member shown in FIG.

도 3 과 도 4a 내지 도 4e 는 각각 본 발명에 따라 콘크리트 거더에 프리스트레스 및 과압축 제어용 하중을 도입하는 방법 및 이를 이용하여 콘크리트 거더 교량을 시공하는 방법의 각 단계를 보여주는 개략도이다.3 and 4a to 4e are schematic views showing each step of the method for introducing the pre-stress and over-compression control load to the concrete girder and the method for constructing the concrete girder bridge using the same according to the present invention, respectively.

도 5는 본 발명에 따라 주 긴장재 전체를 동시에 프리스트레싱 하고 과압축 제어용 하중을 재하하였을 경우의 응력을 보여주는 콘크리트 거더의 응력상태도이다.5 is a state diagram of the stress of the concrete girder showing the stress when the entire main tension material is prestressed simultaneously and the overcompression control load is carried out according to the present invention.

도 6a 와 도 6b는 각각 본 발명에 있어서, 상기 과압축 제어용 하중의 재하형태를 달리한 실시 예를 보여주는 개략도로서 도 3에 대응되는 도면이다.6A and 6B are diagrams corresponding to FIG. 3 as schematic views showing an embodiment in which the loading form of the overcompression control load is different in the present invention, respectively.

<도면의 주요 부분에 대한 부호의 설명><Description of the code | symbol about the principal part of drawing>

10...콘크리트 거더10 ... concrete girder

11...주 긴장재11 ... main tension

12...과압축 제어용 하중12.Load for overcompression control

본 발명은 과압축 제어용 하중을 이용한 콘크리트 거더의 프리스트레싱 방법 및 이를 이용한 교량의 시공방법에 관한 것으로서, 더욱 상세하게는 콘크리트 거더에 프리스트레싱을 도입하고, 이를 이용하여 교량을 시공함에 있어서, 콘크리트 거더의 제작시에 프리스트레스의 도입으로 인하여 콘크리트 거더에 과도한 압축응력이 작용하는 것을 방지하면서도 콘크리트 거더가 사용상태에 있을 때는 필요한 정도의 충분한 프리스트레스 압축응력이 도입될 수 있도록, 과압축 제어용 하중을 이용하여 콘크리트 거더에 프리스트레싱을 가하는 방법 및 이를 이용하여 교량을 시공하는 방법에 관한 것이다.The present invention relates to a prestressing method of a concrete girder using a load for overcompression control and a method of constructing a bridge using the same, and more particularly, to introduce a prestressing to a concrete girder and to construct a bridge using the same, to manufacture a concrete girder In order to prevent excessive compressive stress from acting on the concrete girders due to the introduction of prestress at the same time, the pre-stress control load is applied to the concrete girders so that sufficient prestress compressive stress can be introduced when the concrete girders are in use. It relates to a method of applying prestressing and a method of constructing a bridge using the same.

도 1에는 제작장에 놓여 있는 종래의 콘크리트 거더(100)의 개략도가 도시되어 있는데, 도면에 도시된 것처럼, 일반적으로 콘크리트 거더 교량을 시공하기 위하여 콘크리트 거더(100)를 제작할 때는 긴장재(110)를 배치하여 거더(100)의 인장측에 소정의 프리스트레스 압축응력이 도입되도록 한다. 도 1에서 긴장재(110)는 상기 거더(100)의 내측에 배치되는 것이나, 설명을 위하여 실선으로 도시하였다.1 is a schematic view of a conventional concrete girder 100 is placed in the manufacturing site, as shown in the drawing, in general, when producing the concrete girder 100 in order to construct a concrete girder bridge tension material 110 Arranged so that a predetermined prestressed compressive stress is introduced to the tension side of the girder 100. In FIG. 1, the tension member 110 is disposed inside the girder 100, but is illustrated by a solid line for explanation.

그런데 이러한 일반적인 종래의 콘크리트 거더(100)에 있어서는, 추후 교각에 거치되어 하중이 작용하는 상태가 되었을 때 인장측에 발생하는 인장응력이 허 용범위 내에 있도록 하기 위하여, 종종 거더(100)의 제작시에 과도한 프리스트레스를 도입하는 경우가 있다. 도 2에는 이와 같이 콘크리트 거더(100)의 제작시에 과도한 프리스트레스를 도입함으로써, 거더(100)의 인장측에 오히려 허용범위를 벗어나는 과도한 압축응력이 발생한 상태를 보여주는 응력상태도가 도시되어 있다.By the way, in such a conventional conventional concrete girder 100, in order to ensure that the tensile stress generated on the tension side when the load is applied to the pier later in the allowable range, often during the manufacture of the girder 100 Excessive prestress is sometimes introduced into the system. 2 is a state diagram showing the state in which the excessive compressive stress out of the allowable range on the tensile side of the girder 100 by introducing an excessive prestress at the time of manufacturing the concrete girder 100 in this way is shown.

종래의 콘크리트 거더(100)의 경우에는, 이와 같이 콘크리트 거더(100)의 제작시에 거더(100)의 인장측에 허용범위를 벗어나는 과도한 압축응력이 발생하지 않도록 하기 위해서는 결국 프리스트레스의 도입량을 줄여야 하는데, 만일 프리스트레스 도입량을 줄이게 되면 반대로 거더(100)의 사용상태에서 거더(100)에 충분한 압축력이 작용하지 못하게 되는 문제점이 발생할 수 있다.In the case of the conventional concrete girder 100, in order to prevent excessive compressive stress beyond the allowable range on the tensile side of the girder 100 in the production of the concrete girder 100 in this way, the introduction amount of prestress should be reduced. If the prestressing amount is reduced, on the contrary, a sufficient compression force may not be applied to the girder 100 in the use state of the girder 100.

본 발명은 상기와 같은 종래의 문제점을 해결하기 위하여 개발된 것으로서, 콘크리트 거더의 제작시에는 인장측에 과도한 압축응력이 발생하지 않도록 하면서도 콘크리트 거더의 하중 작용 상태에서는 인장측에 충분한 압축응력이 작용할 수 있도록 과압축 제어용 하중을 이용하여 콘크리트 거더에 프리스트레스를 가하는 방법 및 이를 이용하여 콘크리트 거더 교량을 시공하는 새로운 방법을 제공하는 것을 목적으로 한다.The present invention was developed in order to solve the above-mentioned problems, and the sufficient compression stress can act on the tension side in the load action state of the concrete girder while preventing excessive compression stress on the tension side during the production of the concrete girder. The purpose of the present invention is to provide a method of prestressing a concrete girder using an overcompression control load and a new method of constructing a concrete girder bridge using the same.

상기와 같은 본 발명의 목적을 달성하기 위하여 본 발명에서는, 교량 또는 건축구조물에서 하중을 지지하는 주형이나 거더로서 기능하는 콘크리트 거더의 프리스트레싱 방법으로서, 주(主) 긴장재를 거더의 인장측에 배치하고, 하중 작용상 태에서 휨압축응력이 발생하게 되는 상기 거더의 압축측에는 상기 주 긴장재에 의한 프리스트레스를 일시적으로 일정량 상쇄시킬 수 있는 과압축 제어용 하중을 재하한 상태로 콘크리트 거더를 제작하는 단계; 주 긴장재를 긴장한 후 정착장치를 이용하여 정착함으로써 콘크리트 거더에 주 긴장재에 의한 프리스트레스를 도입하고, 이와 병행하여 상기 과압축 제어용 하중을 재하한 후 해제 가능한 장치를 이용하여 장착함으로써 과압축 제어용 하중에 의하여 상기 콘크리트 거더에, 상기 주 긴장재에 의한 프리스트레스를 일시적으로 저감시켜 프리스트레스를 도입하는 단계; 및 하중 작용 후에는, 주 긴장재에 의한 프리스트레스만이 콘크리트 거더에 작용하여 하중에 의한 콘크리트 거더 인장측의 인장응력을 상쇄하도록, 콘크리트 거더의 하중 작용상태에서 상기 과압축 제어용 하중의 재하 상태를 해제하여 상기 과압축 제어용 하중에 의한 프리스트레스 저감을 제거하는 단계를 포함하는 것을 특징으로 하는 과압축 제어용 하중을 이용한 콘크리트 거더의 프리스트레싱 방법이 제공된다.In order to achieve the object of the present invention as described above, in the present invention, as a pre-stressing method of a concrete girder functioning as a mold or a girder supporting a load in a bridge or a building structure, a main tension member is disposed on the tension side of the girder. Manufacturing a concrete girder on the compression side of the girder, in which bending compression stress is generated under a load action state, with an overcompression control load capable of temporarily canceling a predetermined amount of prestress by the main tension member; After tensioning the main tension member, the prestress by the main tension member is introduced into the concrete girder by fixing using the fixing device, and in parallel with this, the overcompression control load is loaded and then mounted using a releasable device. Introducing prestress into the concrete girder by temporarily reducing prestress caused by the main tension member; And after the load action, the overload control load is released from the load action state of the concrete girder such that only prestress by the main tension member acts on the concrete girder to cancel the tensile stress on the tension side of the concrete girder due to the load. There is provided a prestressing method of a concrete girder using an overcompression control load, comprising the step of removing the prestress reduction caused by the overcompression control load.

또한 본 발명에서는, 주(主) 긴장재를 거더의 인장측에 배치하고, 하중 작용상태에서 휨압축응력이 발생하게 되는 상기 거더의 압축 측에는 상기 주 긴장재에 의한 프리스트레스를 일시적으로 일정량 상쇄시킬 수 있는 과압축 제어용 하중을 재하한 상태로 콘크리트 거더를 제작하는 단계; 주 긴장재를 긴장한 후 정착장치를 이용하여 정착함으로써 콘크리트 거더에 주 긴장재에 의한 프리스트레스를 도입하고, 이와 병행하여 상기 과압축 제어용 하중을 재하한 후 해체 가능한 장치를 이용하여 장착함으로써 과압축 제어용 하중에 의하여 상기 콘크리트 거더에, 상기 주 긴장재에 의한 프리스트레스를 일시적으로 저감시켜 프리스트레스를 도입하는 단계; 상기 콘크리트 거더를 교각과 교대 사이 또는 교대와 교대 사이에 거치하는 단계; 상기 콘크리트 거더의 상부에 슬래브를 설치하는 단계; 및 슬래브에 의하여 전달되는 하중이 콘크리트 거더에 작용하는 상태에서 콘크리트 거더에 주 긴장재에 의한 프리스트레스만이 작용하도록 하여 하중에 의하여 발생하는 콘크리트 거더 인장측의 인장응력이 주 긴장재의 프리스트레스에 의하여 상쇄되도록, 상기 과압축 제어용 하중의 재하 상태를 해제하여 상기 과압축 제어용 하중에 의한 프리스트레스 저감을 제거하는 단계를 포함하는 것을 특징으로 하는 프리스트레스트 콘크리트 거더를 이용한 교량의 시공방법이 제공된다.Further, in the present invention, the main tension member is disposed on the tension side of the girder, and on the compression side of the girder where the bending compressive stress is generated in the load action state, an overstress capable of temporarily offsetting a predetermined amount of prestress by the main tension member Manufacturing a concrete girder with a load for controlling compression; After tensioning the main tension member, the prestress by the main tension member is introduced into the concrete girder by fixing using the fixing device, and in parallel with this, the overcompression control load is loaded and then mounted using a dismountable device. Introducing prestress into the concrete girder by temporarily reducing prestress caused by the main tension member; Mounting the concrete girders between piers and shifts or between shifts and shifts; Installing a slab on top of the concrete girder; And the prestress by the main tension member acting on the concrete girder while the load transmitted by the slab acts on the concrete girder so that the tensile stress caused by the load is canceled by the prestress of the main tension member. A method of constructing a bridge using a prestressed concrete girder is provided by releasing a loading state of the overcompression control load to remove prestress reduction caused by the overcompression control load.

위와 같은 본 발명에 따른 콘크리트 거더의 프리스트레싱 방법 및 교량 시공방법에 있어서, 상기 과압축 제어용 하중은 거더 중앙부 혹은 특정 부위나 거더 전체에 걸쳐 도입될 수 있다. 또한 상기 과압축 제어용 하중은 거더 중간이나 상단 또는 하단 어느 위치에서나 도 6a 와 도 6b에서 보여주는 것보다 다양한 방법으로 재하할 수 있다.In the prestressing method and bridge construction method of the concrete girder according to the present invention as described above, the overcompression control load may be introduced over the center of the girder or a specific portion or the entire girder. In addition, the overcompression control load can be loaded in various ways than shown in Figure 6a and 6b at any position in the middle, top or bottom of the girder.

이하, 콘크리트 거더 교량을 시공하는 방법을 예시하여 본 발명의 바람직한 실시예에 따른 콘크리트 거더의 프리스트레싱 방법을 상세하게 설명한다.Hereinafter, a method for constructing a concrete girder bridge will be described in detail with reference to a method of prestressing a concrete girder according to a preferred embodiment of the present invention.

도 4a 내지 도 4e는 본 발명에 따라 콘크리트 거더에 프리스트레스를 도입하는 방법 및 이를 이용하여 콘크리트 거더 교량을 시공하는 방법의 각 단계를 보여주는 개략도이다.Figures 4a to 4e is a schematic diagram showing each step of the method of introducing prestress to the concrete girder and the method of constructing the concrete girder bridge using the same according to the present invention.

도 4a에 도시된 것처럼, 우선 제작장에서 콘크리트 거더(10)를 제작한다. 이 때, 도면에 도시된 것처럼 프리스트레스를 가하여 압축응력을 도입하기 위한 통상적인 주(主) 긴장재(11)를 거더(10)의 인장측에 배치하게 되는데, 본 발명에서는 상기한 주 긴장재(11)를 전부 긴장하지 않고 허용압축응력 이내가 될 수 있을 만큼의 프리스트레스만을 도입하고 도 4a에 도시한 것처럼 과압축 제어용 하중을 재하하고 나머지 긴장재에 프리스트레스를 가하여 목표한 전(全) 프리스트레스를 도입한다. 상기 주 긴장재(11) 및 과압축 제어용 하중(12)은 상기 콘크리트 거더(10) 외부 어디에든 어떤 형태로도 재하할 수 있고 상기 과압축 제어용 하중(12)을 먼저 재하한 후에 전(全) 긴장재(11)를 동시에 긴장하거나 아니면 어떠한 순서로든 프리스트레스 도입과 과압축 제어용 하중을 재하할 수 있다.As shown in Figure 4a, first to produce a concrete girder 10 in the fabrication site. At this time, a conventional main tension member 11 for introducing a compressive stress by applying prestress as shown in the drawing is arranged on the tension side of the girder 10. In the present invention, the main tension member 11 is described above. Only the prestress is introduced so as to be within the allowable compressive stress without all the tension, and the target all prestress is introduced by applying the overcompression control load and prestressing the remaining tension members as shown in FIG. 4A. The main tension member 11 and the overcompression control load 12 may be loaded in any form anywhere outside the concrete girder 10, and the full tension material after the overcompression control load 12 is loaded first. Either tension (11) may be applied at the same time or the loads for prestress introduction and overcompression control may be loaded in any order.

본 발명에 있어서, 상기 과압축 제어용 하중(12)은 추후 설명하는 것처럼 소거된 프리스트레싱을 회복할 수 있도록 하기 위하여 설치, 해체가 용이하도록 구성된다.In the present invention, the overcompression control load 12 is configured to be easy to install and dismantle in order to recover the erased prestressing as described later.

이와 같이 주 긴장재(11)를 배치한 상태로 콘크리트 거더(10)를 제작한 후에는, 주 긴장재(11)를 긴장한 후 도 3에 도시된 것처럼 거더(10)의 양단에서 정착장치(20)를 이용하여 정착함으로써 콘크리트 거더(10)에 주 긴장재(11)에 의한 프리스트레스를 도입한다. 이와 병행하여, 상기 과압축 제어용 하중(12)도 재하 함으로써, 콘크리트 거더(10)에 상기 주 긴장재(11)에 의한 프리스트레스를 일시적으로 저감되도록 한다. 이 때, 상기 과압축 제어용 하중(12)은 추후 장착상태를 해제할 수 있도록, 해제 가능한 장치(21)를 이용하여 장착한다. 도 5에는 이와 같이 주 긴장재(11)와 과압축 제어용 하중(12)을 모두 긴장하고 재하하여 프리스트레스를 도 입한 상태의 응력을 보여주는 거더(10)의 응력상태도이다. 도 2에 도시된 것처럼, 종래의 거더에서는 주 긴장재(11)의 전(全) 프리스트레싱에 의하여 거더(10)의 중앙부 하연에서 허용압축응력을 초과하는 압축응력이 발생하지만, 과압축 제어용 하중(12)을 재하하게 되면 하연에서 반대 방향의 응력이 작용하게 되어, 거더(10)의 중앙부 하연에서 발생하는 압축응력은 허용압축응력 이내에 있게 된다. 따라서 종래의 거더에 비하여, 본 발명에서는, 허용압축응력을 넘지 않는 범위내에서 주 긴장재(11)에 의한 충분한 프리스트레스를 콘크리트 거더(10)에 가할 수 있으며, 그에 따라 거더(10)의 높이 등을 축소할 수 있게 된다.After the concrete girder 10 is manufactured in the state where the main tension member 11 is disposed as described above, after the main tension member 11 is tensioned, the fixing device 20 is mounted at both ends of the girder 10 as shown in FIG. 3. Prestress by the main tension material 11 is introduce | transduced into the concrete girder 10 by fixing using it. In parallel with this, the overcompression control load 12 is also loaded to temporarily reduce the prestress caused by the main tension member 11 in the concrete girder 10. At this time, the overcompression control load 12 is mounted using the releasable device 21 so as to release the mounting state later. 5 is a stress state diagram of the girder 10 showing the stress in the state in which the prestress is introduced by tensioning and loading both the main tension member 11 and the overcompression control load 12 in this way. As shown in FIG. 2, in the conventional girder, compressive stress exceeding the allowable compressive stress occurs at the lower edge of the center of the girder 10 due to the entire prestressing of the main tension member 11, but the overcompression control load 12 When the load) is applied, the opposite stress acts on the lower edge, and the compressive stress generated at the lower edge of the center of the girder 10 is within the allowable compressive stress. Therefore, in comparison with the conventional girder, in the present invention, sufficient prestress by the main tension member 11 can be applied to the concrete girder 10 within the range not exceeding the allowable compressive stress, so that the height of the girder 10 and the like can be adjusted. You can zoom out.

이와 같이 주 긴장재(11)와 과압축 제어용 하중(12)의 재하가 완료되면 콘크리트 거더(10)를 현장에 거치하여 하중 작용 상태에 놓이게 한다. 교량 시공의 경우에는 도 4c에 도시된 것처럼, 교각(30)과 교대(31) 사이, 또는 교각(30)과 교각(30) 사이에 콘크리트 거더(10)를 거치하고, 도 4d에 도시된 것처럼, 콘크리트 거더(10)의 상부에 슬래브(40)를 타설한다. 이와 같이 슬래브(40)를 타설하여 콘크리트 거더(10)가 하중 작용 상태에 놓이게 되면 콘크리트 거더(10)의 인장측에는 작용하중으로 인한 인장력이 발생하게 되며 이때 상기 과압축 제어용 하중(12)의 재하 상태를 해제하여 과압축 제어용 하중(12)에 의한 프리스트레싱 감소를 복원하게 된다. 즉, 거더(10)에 재하되었던 상기 과압축 제어용 하중(12)의 장착장치를 해제하게 되면 과압축 제어용 하중(12)의 재하 상태가 해제되고, 그에 따라 거더(10)에는 과압축 제어용 하중(12)에 의한 프리스트레스 감소가 소멸된다. 따라서 콘크리트 거더(10)에는 주 긴장재(11)에 의한 전(全) 프리스트레스가 작용하게 되고, 사 용하중에 의하여 발생하는 콘크리트 거더(10) 인장측의 인장응력은 이러한 주 긴장재(11)의 프리스트레싱에 의한 압축응력에 의하여 상쇄된다. 자중의 경감과 자원 재활용을 위하여 과압축 제어용 하중(12)을 제거한 후에는 다른 거더에 장착하여 재사용한다.As such, when loading of the main tension member 11 and the overcompression control load 12 is completed, the concrete girder 10 is mounted on the site to be placed in a load action state. In the case of bridge construction, the concrete girder 10 is mounted between the bridge 30 and the bridge 31 or between the bridge 30 and the bridge 30, as shown in FIG. , The slab 40 is poured on top of the concrete girder 10. As such, when the slab 40 is placed and the concrete girder 10 is placed in a load action state, a tensile force is generated on the tensile side of the concrete girder 10 due to the action load, and at this time, the load state of the overcompression control load 12 is By canceling the prestressing reduction by the overcompression control load 12 is restored. That is, when the mounting device of the overcompression control load 12 loaded on the girder 10 is released, the loading state of the overcompression control load 12 is released, whereby the overcompression control load ( The prestress reduction by 12 is eliminated. Therefore, the pre-stress by the main tension member 11 acts on the concrete girder 10, and the tensile stress on the tension side of the concrete girder 10 generated by the working load is applied to the pre-stressing of the main tension member 11. Offset by the compressive stress. After the overcompression control load 12 is removed to reduce its own weight and recycle resources, it is mounted on another girder and reused.

이와 같이 본 발명에서는, 콘크리트 거더(10)를 제작할 때에는, 주 긴장재(11)의 프리스트레싱에 의하여 콘크리트 거더(10)의 인장측에 작용하는 압축응력을 과압축 제어용 하중(12)에 의한 인장응력으로 일시적으로 감소시켜 허용압축응력 범위 내에 있도록 한 후, 실제 하중 작용 상태에서는 과압축 제어용 하중(12)을 제거하여 주 긴장재(11)의 프리스트레싱에 의한 압축응력이 작용하도록 함으로써 사용하중에 의한 인장응력을 충분히 상쇄시키게 된다.As described above, in the present invention, when the concrete girder 10 is manufactured, the compressive stress acting on the tension side of the concrete girder 10 by prestressing the main tension member 11 is converted into the tensile stress by the overcompression control load 12. Temporarily reduce the pressure within the allowable compressive stress range, and remove the overcompression control load 12 in the actual loading state so that the compressive stress due to prestressing of the main tension member 11 acts to reduce the tensile stress due to the working load. It is offset enough.

도 4e에 도시한 사용상태에 후속하여, 슬래브 상면의 포장작업, 방호벽 설치작업 등과 같은 통상의 교량 시공에서 수행하게 되는 추가적인 작업들을 수행하게 된다.Subsequent to the use state shown in FIG. 4E, additional operations to be performed in conventional bridge construction, such as paving work on the upper surface of the slab, installation of a firewall, and the like, are performed.

한편, 도 3에서는 과압축 제어용 하중(12)을 거더 중앙부의 하부 플랜지에 거치하는 것으로 예시하였으나, 상기 과압축 제어용 하중(12)의 재하는 이에 한정되는 것이 아니다. 도 6a 내지 도 9b에는 상기 과압축 제어용 하중(12)의 배치형태를 달리한 실시 예를 보여주는 개략도로서 도 3에 대응되는 도면이다. 도 6a에 도시된 것처럼, 상기 과압축 제어용 하중(12)은 지간 중앙부에 배치될 수 있다. 또한, 상기 과압축 제어용 하중(12)은 콘크리트 거더(10)의 길이 방향으로 지간 전체에 대하여 배치되거나 또는 지간의 일부분 또는 지간 중앙부분에 분산되서 배치될 수도 있다. 한편, 상기 과압축 제어용 하중(12)은 콘크리트 거더(10)의 하부 플랜지에 거치하는 것으로 배치될 수도 있다. 도 6b에는 상기 과압축 제어용 하중(12)이 원형 형태로 제작되거나 거더 복부를 관통하여 지지하거나 상부 플랜지 상단을 포함하여 하부 플랜지에 거치하는 것으로 배치된 형태가 도시되어 있다.In FIG. 3, the overcompression control load 12 is illustrated as being mounted on the lower flange of the girder center portion, but the load of the overcompression control load 12 is not limited thereto. 6A to 9B are schematic views showing an embodiment in which the arrangement of the overcompression control load 12 is changed, corresponding to FIG. 3. As illustrated in FIG. 6A, the overcompression control load 12 may be disposed at the center portion of the trunk. In addition, the overcompression control load 12 may be disposed in the longitudinal direction of the concrete girder 10 with respect to the entire interval, or may be disposed in a portion of the interval or in the central portion of the interval. On the other hand, the overcompression control load 12 may be arranged by mounting on the lower flange of the concrete girder 10. FIG. 6B shows the overcompression control load 12 manufactured in a circular shape or supported by penetrating the girder abdomen or mounted on a lower flange including an upper flange top.

이와 같이 상기 과압축 제어용 하중(12)은 다양한 위치에 다양한 형태로 다양하게 재하가 가능하다.As such, the overcompression control load 12 may be loaded in various forms in various positions.

상기한 설명에서는 교량의 시공방법을 예시하여 본 발명에 따른 콘크리트 거더의 프리스트레싱 방법을 설명하였으나, 본 발명은 이에 한정되는 것은 아니며 프리스트레스트 콘크리트 거더를 사용하는 구조물이나 시공현장이라면 본 발명을 적용할 수 있다.In the above description, the method of prestressing concrete girder according to the present invention has been described by illustrating a construction method of a bridge, but the present invention is not limited thereto, and the present invention may be applied to a structure or a construction site using prestressed concrete girder. have.

이상에서 설명한 바와 같이, 본 발명에서는, 콘크리트 거더(10)를 제작할 때에는, 주 긴장재(11)의 프리스트레싱에 의하여 콘크리트 거더(10)의 경간 중앙부 하단에 작용하는 압축응력을 과압축 제어용 하중(12)에 의한 인장응력으로 감소시켜 허용압축응력 범위 내에 있도록 한 후, 실제 하중 작용 상태에서는 과압축 제어용 하중(12)을 제거하여 주 긴장재(11)의 프리스트레싱에 의한 압축응력이 작용하도록 함으로써 하중에 의한 인장응력을 충분히 상쇄시키게 된다.As described above, in the present invention, when the concrete girder 10 is manufactured, the compressive stress acting on the lower end of the span center portion of the concrete girder 10 by prestressing the main tension member 11 is applied to the overcompression control load 12. After reducing the tensile stress to be within the allowable compressive stress range, in the actual load action state, the over-compression control load 12 is removed so that the compressive stress due to prestressing of the main tension member 11 acts. This is enough to offset the stress.

따라서 본 발명에 의하면, 콘크리트 거더(10)의 제작시에는 경간중앙부 하단에 작용하는 프리스트레싱에 의한 압축응력은 허용압축응력 범위 내에 있도록 하면서도, 실제 사용상태에서는 사용하중에 의한 인장응력을 상쇄시킬 만큼의 충분한 압축응력이 작용할 수 있도록 하는 효과가 발휘되며, 그에 따라 거더의 높이를 줄이는 등의 거더 단면 감소 효과가 발휘된다.Therefore, according to the present invention, the compressive stress due to the prestressing acting on the lower end of the span section at the time of manufacturing the concrete girder 10 is within the allowable compressive stress range, while in actual use state to offset the tensile stress due to the working load The effect of sufficient compressive stress is exerted, thereby reducing the girder cross section, such as reducing the height of the girder.

Claims (5)

교량 또는 건축구조물에서 하중을 지지하는 주형이나 거더로서 기능하는 콘크리트 거더(10)의 프리스트레싱 방법으로서,As a prestressing method of the concrete girder 10, which functions as a mold or girder that supports the load in a bridge or building structure, 주(主) 긴장재(11)를 거더(10)의 인장측에 배치하고, 과압축 제어용 하중(12)을 재하하여 상기 주 긴장재(11)에 의한 프리스트레스를 일시적으로 일정량 상쇄시킬 수 있도록 하는 과압축 제어용 하중(12)을 재하한 상태로 콘크리트 거더(10)를 제작하는 단계;The over-compression which arrange | positions the main tension material 11 at the tension side of the girder 10, and loads the overcompression control load 12 so that the prestress by the said main tension material 11 can be temporarily canceled by a certain amount. Manufacturing a concrete girder 10 with a control load 12 loaded; 주 긴장재(11)를 긴장한 후 정착장치(20)를 이용하여 정착함으로써 콘크리트 거더(10)에 주 긴장재(11)에 의한 프리스트레스를 도입하고, 이와 병행하여 상기 과압축 제어용 하중(12)을 재하한 후 해체 가능한 장착장치를 이용하여 장착함으로써 과압축 제어용 하중(12)에 의하여 상기 콘크리트 거더(10)에, 상기 주 긴장재(11)에 의한 프리스트레스 효과를 저감시키는 단계; 및After the main tension member 11 is tensioned and fixed using the fixing device 20, prestress by the main tension member 11 is introduced into the concrete girder 10, and in parallel thereto, the overcompression control load 12 is loaded. Reducing the prestress effect by the main tension member (11) on the concrete girder (10) by the overcompression control load (12) by mounting using a dismountable mounting device afterwards; And 하중 작용 후에는, 주 긴장재(11)에 의한 프리스트레스만이 콘크리트 거더(10)에 작용하여 하중에 의한 콘크리트 거더(10) 인장측의 인장응력을 상쇄하도록, 콘크리트 거더(10)의 하중 작용 상태에서 상기 과압축 제어용 하중(12)의 재하 상태를 해제하여 상기 과압축 제어용 하중(12)에 의한 프리스트레스 저감효과를 제거하는 단계를 포함하는 것을 특징으로 하는 과압축 제어용 하중을 이용한 콘크리트 거더의 프리스트레싱 방법.After the load action, in the load action state of the concrete girder 10, only the prestress by the main tension member 11 acts on the concrete girder 10 to cancel the tensile stress on the tension side of the concrete girder 10 due to the load. And releasing the loading state of the overcompression control load (12) to remove the prestress reduction effect by the overcompression control load (12). 제1항에 있어서,The method of claim 1, 상기 과압축 제어용 하중(12)은 탈부착이 용이한 구조를 갖는 것을 특징으로 하는 과압축 제어용 하중을 이용한 콘크리트 거더의 프리스트레싱 제어 방법.The overcompression control load (12) is a prestressing control method of the concrete girder using the overcompression control load, characterized in that having a structure that is easy to attach and detach. 제1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 과압축 제어용 하중(12)은 지간 중앙부에 배치되거나 콘크리크 거더(10)의 길이 방향으로 지간 전체에 대하여 배치될 수도 있으며 지간의 일부분 또는 지간 중앙부에 분산되서 배치될 수도 있을 뿐만 아니라 사각형이나 원형, 타원형 등의 다양한 형태로의 제작도 가능하며 하부플랜지에 거치하거나 거더 복부를 관통하여 체결할 수도 있을 뿐만 아니라 거더 상부플랜지 상단 등에 다양하게 거치하여 구성되는 것을 특징으로 하는 과압축 제어용 하중을 이용한 콘크리트 거더의 프리스트레싱 제어 방법.The overcompression control load 12 may be disposed in the center of the trunk or in the longitudinal direction of the concrete girder 10, and may be disposed in a portion of the trunk or distributed in the center of the trunk, as well as a quadrangle or a circle. It is also possible to manufacture in various forms such as oval, and can be mounted on the lower flange or fastened through the girder abdomen, as well as variously mounted on the top of the upper girder, the concrete using the over-compression control load How to control prestressing of girders. 주(主) 긴장재(11)를 더(10)의 인장측에 배치하고, 과압축 제어용 하중(12)을 재하하여 상기 주 긴장재(11)에 의한 프리스트레스를 일시적으로 일정량 상쇄시킬 수 있도록 하는 과압축 제어용 하중(12)을 재하한 상태로 콘크리트 거더(10)를 제작하는 단계;And a state (主) tendons (11) the girder (10) disposed on the tension side, and by loading the compression control loads 12 to be temporarily fixed amount offset by the prestressing due to the main tendons 11 of the Manufacturing a concrete girder 10 in a state where the compression control load 12 is loaded; 주 긴장재(11)를 긴장한 후 정착장치(20)를 이용하여 정착함으로써 콘크리트 거더(10)에 주 긴장재(11)에 의한 프리스트레스를 도입하고, 이와 병행하여 상기 과압축 제어용 하중(12)을 재하한 후 해체 가능한 장착장치를 이용하여 장착함으로 써 과압축 제어용 하중(12)에 의하여 상기 콘크리트 거더(10)에, 상기 주 긴장재(11)에 의한 프리스트레스 효과를 저감시키는 단계;After the main tension member 11 is tensioned and fixed using the fixing device 20, prestress by the main tension member 11 is introduced into the concrete girder 10, and in parallel thereto, the overcompression control load 12 is loaded. Reducing the prestress effect by the main tension member (11) on the concrete girder (10) by the overcompression control load (12) by mounting using a dismountable mounting device afterwards; 상기 콘크리트 거더(10)를 교각과 교대 사이 또는 교대와 교대 사이에 거치하는 단계;Mounting the concrete girder 10 between a piers and shifts or between shifts and shifts; 상기 콘크리트 거더(10)의 상부에 슬래브(40)를 설치하는 단계; 및Installing a slab (40) on top of the concrete girder (10); And 슬래브(40)에 의하여 전달되는 하중이 콘크리트 거더(10)에 작용하는 상태에서 콘크리트 거더(10)에 주 긴장재(11)에 의한 프리스트레스만이 작용하도록 하여 하중에 의하여 발생하는 콘크리트 거더(10) 인장측의 인장응력이 주 긴장재(11)의 프리스트레스에 의하여 상쇄되도록, 상기 과압축 제어용 하중(12)의 재하 상태를 해제하여 상기 과압축 제어용 하중(12)을 제거하는 단계를 포함하는 것을 특징으로 하는 프리스트레스트 콘크리트 거더를 이용한 교량의 시공방법.The tension of the concrete girder 10 generated by the load by allowing only the prestress by the main tension member 11 to act on the concrete girder 10 in a state in which the load transmitted by the slab 40 acts on the concrete girder 10. And removing the overcompression control load 12 by releasing the loading state of the overcompression control load 12 so that the tensile stress on the side is canceled by the prestress of the main tension member 11. Construction method of bridge using prestressed concrete girder. 제4항에 있어서,The method of claim 4, wherein 상기 과압축 제어용 하중(12)은 탈부착이 용이한 구조를 갖는 것을 특징으로 하는 프리스트레스트 콘크리트 거더를 이용한 교량의 시공방법.The overcompression control load (12) is a bridge construction method using a prestressed concrete girder, characterized in that having a structure that is easily removable.
KR1020080056086A 2008-06-09 2008-06-09 Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof KR20090127789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080056086A KR20090127789A (en) 2008-06-09 2008-06-09 Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080056086A KR20090127789A (en) 2008-06-09 2008-06-09 Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020100113433A Division KR20100135692A (en) 2010-11-15 2010-11-15 Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof

Publications (1)

Publication Number Publication Date
KR20090127789A true KR20090127789A (en) 2009-12-14

Family

ID=41688400

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080056086A KR20090127789A (en) 2008-06-09 2008-06-09 Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof

Country Status (1)

Country Link
KR (1) KR20090127789A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877419A (en) * 2012-11-01 2013-01-16 河北益铁机电科技有限公司 Pre-stress construction system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877419A (en) * 2012-11-01 2013-01-16 河北益铁机电科技有限公司 Pre-stress construction system
CN102877419B (en) * 2012-11-01 2014-07-16 河北益铁机电科技有限公司 Pre-stress construction system

Similar Documents

Publication Publication Date Title
KR100541965B1 (en) Manufacturing apparatus for steel composite girder whose self weight is loaded on steel girder and manufacturing method thereof
KR101237000B1 (en) Precast concrete panel construction technique
KR100923409B1 (en) Construction method of Spliced Prestressed Concrete Girder Bridge in consideration of the construction sequence
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
KR20090127789A (en) Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof
KR100795920B1 (en) Construction method for steel plate girder
JP4030994B2 (en) Girder structure and method for constructing girder structure
KR20100135692A (en) Method for prestressing concrete girder using temporary loading and method for constructing bridge using thereof
KR101376484B1 (en) Steel box manufacturing method using elastic recovering force adjustment and steel box girder and bridge construction method therewith
KR101339367B1 (en) Fabrication and reinforcing method for pre-flex girder
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
KR20050095049A (en) Continuous bridge construction method using a psc girder
KR20130090455A (en) Construction method for continuous bridge using confined concrete
KR20130095528A (en) Construction method for girder using confined concrete
KR100474640B1 (en) Method for protecting the loss of prestress in prestressed beam by temporary load
KR20060110685A (en) The method for construction of bridge
KR20070082435A (en) Temporary bridge consruction method using composite slab girder
KR101172442B1 (en) Construction method for girder using confined concrete
KR102295050B1 (en) Improved psc beam improved work efficiency and workability and prevent cracking of girder upper when removing basepanel
KR101325230B1 (en) Manufacturing method for turn-over composite girder
KR100995114B1 (en) Method for introducing tension pre-stress using the slab
KR100431589B1 (en) The method of decreasing tensile stress during construction for Movable Scaffolding System in Double-T girder bridge
KR101431582B1 (en) Girder and rahmen bridge construccting method using chain block apparatus
CN220450677U (en) Be applied to and hang equipment of irritating continuous beam number 0 section

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application
J201 Request for trial against refusal decision
AMND Amendment
A107 Divisional application of patent
B601 Maintenance of original decision after re-examination before a trial
E801 Decision on dismissal of amendment
WITB Written withdrawal of application
J301 Trial decision

Free format text: TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20101108

Effective date: 20110114