KR20090024035A - Current transformer changing method with extra transformer - Google Patents

Current transformer changing method with extra transformer Download PDF

Info

Publication number
KR20090024035A
KR20090024035A KR1020070089223A KR20070089223A KR20090024035A KR 20090024035 A KR20090024035 A KR 20090024035A KR 1020070089223 A KR1020070089223 A KR 1020070089223A KR 20070089223 A KR20070089223 A KR 20070089223A KR 20090024035 A KR20090024035 A KR 20090024035A
Authority
KR
South Korea
Prior art keywords
transformer
phase
construction
uninterruptible
wire
Prior art date
Application number
KR1020070089223A
Other languages
Korean (ko)
Inventor
하영숙
Original Assignee
하영숙
(주)한성전기
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 하영숙, (주)한성전기 filed Critical 하영숙
Priority to KR1020070089223A priority Critical patent/KR20090024035A/en
Publication of KR20090024035A publication Critical patent/KR20090024035A/en

Links

Images

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01FMAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
    • H01F29/00Variable transformers or inductances not covered by group H01F21/00
    • H01F29/02Variable transformers or inductances not covered by group H01F21/00 with tappings on coil or winding; with provision for rearrangement or interconnection of windings
    • H01F29/04Variable transformers or inductances not covered by group H01F21/00 with tappings on coil or winding; with provision for rearrangement or interconnection of windings having provision for tap-changing without interrupting the load current
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B5/00Non-enclosed substations; Substations with enclosed and non-enclosed equipment
    • H02B5/02Non-enclosed substations; Substations with enclosed and non-enclosed equipment mounted on pole, e.g. pole transformer substation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/20Spatial arrangements or dispositions of lines or cables on poles, posts or towers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A method for replacing a pole transformer in an uninterruptible state is provided to reduce a device cost by excluding a phase change bypass device or an uninterruptible transformer. An additional hanger(11) is installed in an electric pole(13). An extra transformer(8) is hung on the hanger. The extra transformer is installed in a transformer rack of the hanger. The capacity of the extra transformer is larger than the capacity of the replacement object transformer. The extra transformer is connected in parallel with the replacement object transformer. The load of a low voltage wire(2) or a service wire is transferred to the extra transformer. The replacement object transformer is replaced in the uninterruptible state.

Description

공사용 변압기를 이용한 주상변압기 무정전 교체공법{Current transformer changing method with extra transformer}Current transformer changing method with extra transformer

본 발명은 무정전으로 변압기(3) 교체공사를 하는데 있어, 공사용 변압기(8)를 이용한 주상 변압기 무정전 교체에 관한 것으로, 기존의 변압기 무정전 공법에 있어 고가의 이동형 무정전 변압기장치(7)를 이용하지 않고, 단순히 별도의 공사용 변압기(8)를 같은 전주(13)에 1대 추가 설치하는 것만으로도 변압기(3) 무정전 교체가 가능하도록 한 배전공법에 관한 것이다.The present invention relates to the uninterrupted transformer (3) replacement work, uninterrupted replacement of the columnar transformer using the transformer (8) for construction, without using an expensive mobile type uninterruptible transformer device (7) in the conventional transformer uninterruptible method In addition, simply by installing one additional transformer 8 for the same construction in the same pole 13 relates to a distribution method that allows the uninterruptible replacement of the transformer (3).

일반적으로 배전선로용 주상 변압기는 대부분 특고압(대지전압 13,200V, 상간전압 22,900V) 전선으로부터 각상별로 전원이 연결된 상태에서 특고압의 전기를 변압하여 저압 배전선로(2)나 인입선을 통하여 전력 사용자측으로 공급된다. 이때, 주상변압기를 이용한 저압 공급방식은 1상2선식 220V 공급방식과 3상4선식 380/220V 공급방식으로 나눌 수 있는데, 1상2선식 220V 의 전압을 공급하기 위해서는 단상 변압기 1대, 3상4선식 380/220V 의 전압을 공급하기 위해서는 단상 변압기 3대를 조합하여 변대를 구성한다. 변압기 3대를 전주에 설치할 때는 S-3 타입의 삼상 변대용 행거밴드(11)를 전주(13)에 부착하여 변압기를 거치하고, 변압기 1대를 전주에 설치할 때는 S-1 타입의 단상 변대용 행거밴드를 부착하여 변압기 1대만 설치할 수 있게 하였으나, 최근에는 3상 동력전원에 대한 수요가 증가하고 있고, 또한 향후 삼상 변대로의 변경을 대비하여 행거밴드(11)를 선정하는 것이 더 경제성이 있음을 인식하여, 단상 변대개소에도 S-3 타입의 3상 변대용 행거밴드(11)를 설치하는 것이 일반화되고 있다.In general, most of the pole-type transformer for distribution line converts electricity of extra-high voltage in the state that power is connected to each phase from the extra high voltage (earth voltage 13,200V, phase voltage 22,900V) wire, and then the power user side through low voltage distribution line (2) or lead wire. Supplied by. At this time, low voltage supply method using column transformer can be divided into 1-phase 2-wire 220V supply and 3-phase 4-wire 380 / 220V supply method. To supply voltage of 1-phase 2-wire 220V, 1 single-phase transformer, 3-phase To supply a 4-wire 380 / 220V voltage, three single-phase transformers are combined to form a sideband. When three transformers are installed on poles, the S-3 type three-phase hanger band 11 is attached to the poles 13 to mount the transformers. Although only one transformer can be installed by attaching a hanger band, the demand for a three-phase power source is increasing recently, and it is more economical to select a hanger band 11 in preparation for a change to a three-phase valve in the future. Recognizing this, it has become common to provide the S-3 type three-phase hanger band 11 in a single phase toilet location.

3상 변대용 행거밴드의 형상은 상부밴드와 하부밴드로 분리되어 있고 각상별 변압기걸이는 약 90°의 각도를 두고 3개로 구성되어, 변압기를 전주(14)에 설치하게 되면 3대의 변압기중 중앙의 변압기를 B상 변압기라고 가정하였을 시, A상과 C상의 변압기는 전주를 기준으로 보면, 각각 B상 변압기로 부터 90°정도의 각을 두고 양측에 시설되고, B상 변압기의 반대쪽은 빈 공간으로 남아있게 되어 있다.The shape of the three-phase hanger band is divided into an upper band and a lower band, and the transformer hangers for each phase are composed of three at an angle of about 90 °. Assuming that the transformer of is a B-phase transformer, the A-phase and C-phase transformers are installed on both sides with an angle of about 90 ° from the B-phase transformer, and the opposite side of the B-phase transformer is an empty space. It is supposed to remain.

1상 변대용 행거밴드의 형상은 3상 변대용 행거밴드와 마찬가지로 상부밴드와 하부밴드로 분리되어 있으나, 변압기 걸이가 1개만으로 구성되어, 변압기를 전주에 설치하게 되면 3상 변대를 기준으로 볼 때, A상이나 B상 또는 C상의 변압기 위치에 1대를 설치하게 되고 나머지의 위치는 빈 공간으로 남아있게 되어 있다. Like the 3-phase hanger band, the shape of the hanger band for 1-phase valve is divided into upper and lower bands, but the transformer hanger is composed of only one. At that time, one A, B, or C phase transformer is installed at one position, and the remaining positions are left as empty spaces.

도 1은 일반적인 주상 변압기의 1상2선식 공급방식의 결선방법을 도시한 것이며, 도 2는 주상 변압기의 3상4선식 공급방식의 결선방법을 도시한 것이다.Figure 1 shows a connection method of a one-phase two-wire supply method of a general column transformer, Figure 2 shows a connection method of a three-phase four-wire supply method of the columnar transformer.

도면을 참조하면, 도 1와 같은 변압기 결선방법은 특고압선로(1)의 A상, B상, C상 선로중 한 상에서 변압기 1차 특고압 리드선을 결선하고, 변압기(3)의 2차측 출력을 저압선로(2)의 전력선과 접지선에 결선하며, 도 2와 같은 변압기 결선방 법은 특고압선로(1)의 A상, B상, C상 선로에서 각 상별로 변압기 1차 특고압 리드선을 결선하고, 상기 3개의 변압기(3)의 접지 인하선(4)을 붓싱단자에서 공동접지하여 단독으로 인하하여 저압선로(2)의 N상 선로에 연결하고, 각 변압기(3)의 2차측 출력을 저압선로(2)의 전력선에 결선한다. Referring to the drawings, the transformer connection method as shown in FIG. 1 connects the primary primary high voltage lead wire on one of the A phase, B phase and C phase lines of the special high voltage line 1, and outputs the secondary side of the transformer 3. Is connected to the power line and the ground line of the low voltage line (2), and the transformer connection method as shown in FIG. 2 uses the transformer primary high voltage lead wire for each phase in the A phase, B phase, and C phase lines of the special high voltage line (1). The grounding wires (4) of the three transformers (3) are jointly grounded at the bushing terminals and lowered alone, connected to the N-phase line of the low voltage line (2), and the secondary output of each transformer (3). Is connected to the power line of the low voltage line (2).

주상 변압기를 노후 또는 과부하 등의 사유로 교체하고자 할 때 종래의 교체방법은 교체하고자 하는 변압기를 사선작업에 의해 수용가측으로 정전을 유발시키면서 작업하는 방법과 수용가측의 정전을 회피하기 위해 이동형 무정전 변압기장치(7)를 이용하여 작업대상 변압기(3)를 바이패스하여 무정전상태로 변압기(3)를 교체하는 방법을 활용하고 있었는데, 최근에는 위상변환장치에 의한 바이패스 공법이 개발되어 현장에서 시범적용되고 있다.When replacing the column transformer for reasons such as aging or overload, the conventional replacement method is to operate the transformer to be replaced while causing a power failure to the consumer side by a diagonal operation and to move the uninterruptible transformer device to avoid the consumer power failure. (7) was used to bypass the target transformer (3) to replace the transformer (3) in an uninterruptible state. Recently, a bypass method by a phase shifter has been developed and applied in the field. have.

사선작업에 의한 변압기(3) 교체는 전기공급자 입장에서는 전력공급 신뢰도를 저하시키고, 전기공사업자의 입장에서는 사전 정전합의와 정전안내에 따른 인력의 소모가 발생하며, 전기 사용자의 입장에서는 정전에 따른 불편과 물적 피해가 발생하였다. 정전에 따른 문제를 해소하기 위해 이동형 무정전 변압기장치(7)에 의한 바이패스 공법이 개발되었는데, 도 2가 이 이동형 무정전 변압기장치(7)에 의한 바이패스 공법을 적용한 변압기교체 방법을 설명하기 위한 것이다.Replacing the transformer (3) by oblique work deteriorates the reliability of power supply from the electricity supplier's point of view, and consumes manpower according to pre-outage agreements and outage guidance from the electrician's point of view. And physical damage occurred. In order to solve the problem caused by the power failure, the bypass method by the mobile uninterruptible transformer device 7 has been developed, and FIG. 2 illustrates a transformer replacement method using the bypass method by the mobile uninterruptible transformer device 7. .

도 2에 도시된 바와같이, 특고압선로(1)의 각상이 각각 3개의 변압기(3)의 1차측에 결선되고, 그 변압기(3)의 2차측이 저압선로(2)의 각상에 결선되어 있어서, 무정전 변압기장치(7)을 이용하여 3상변압기를 교체시 특고압선로(1)의 각상에 1차측에 특고압 바이패스선(5)을 각각 연결하고, 저압선로(2)에 2차측 저압 바이패스선(6)을 연결한 다음 무정전 변압기차(7)에 전압을 인가해 3상 주상변압기에 무정전 바이패스 회로를 구성한다. 이와 같이 3상 모두를 무정전 변압기장치(7)를 통해서 무정전 상태를 유지하면서 변압기를 교체하게 된다.As shown in Fig. 2, each phase of the extra high voltage line 1 is connected to the primary side of the three transformers 3, respectively, and the secondary side of the transformer 3 is connected to each phase of the low voltage line 2, When the three-phase transformer is replaced using the uninterruptible transformer device 7, the high-voltage bypass line 5 is connected to the primary side of each of the high-voltage line 1, and the secondary-side is connected to the low-voltage line 2. After connecting the low voltage bypass line 6, voltage is applied to the uninterruptible transformer car 7 to form an uninterrupted bypass circuit in the three-phase columnar transformer. In this way, all three phases are replaced by the transformer while maintaining the uninterrupted state through the uninterruptible transformer device (7).

그런데, 상기 무정전 변압기차(7)를 이용하는 경우 변압기(3)를 교체함에 있어서 However, in the case of using the uninterruptible transformer car 7 in replacing the transformer 3

정전에 따른 제반 문제는 해소되었으나, 이동형 무정전 변압기장치(7)의 1차 전원 인가를 위해 활선상태에서 특고압 전선(1)의 피복을 피박하고 특고압 바이패스 케이블(5)의 연결 및 분리 작업이 복잡하여 안전에 위험이 있고, 특고압 바이패스 케이블(5)이 지상에 포설되게 되어 작업과정에서 일반인에 대한 안전상의 위험이 상존하고 있었으며, 작업후에는 전선 손상이 발생하는 문제가 있을 뿐 아니라, 이동형 무정전 변압기장치(7)가 추가로 있어야 무정전으로 변압기 교체가 가능하므로 골목길 등 협소한 장소에는 작업이 번거롭고, 차량통행에 방해가 되고 작업시간과 경비가 너무 많이 들고 있고, 고가의 장비를 영세한 업체 입장에서 구비하는 것에 따른 경제적 부담도 무시할 수 없었다.Although the problems caused by the power failure have been solved, the sheath of the extra high voltage wire (1) in the live state and the connection and disconnection of the extra high voltage bypass cable (5) in live state for the primary power supply of the mobile uninterruptible transformer device (7) Due to this complexity, there is a safety risk, and since the high-voltage bypass cable 5 is installed on the ground, there is a safety risk for the general public in the course of the work, and there is a problem that the wire damage occurs after the work. In order to replace the transformer with an uninterruptible power supply, the mobile uninterruptible transformer device (7) must be additionally installed. Therefore, the work is cumbersome in a narrow place such as an alley, obstructs the traffic of the vehicle, takes too much time and expense, and uses expensive equipment. The economic burden of equipping one company could not be ignored.

최근에 개발된 위상변환장치(15)에 의한 바이패스 공법은 1상 변대에는 적용이 불가능 할 뿐 아니라, 3상 변대의 경우에도 교체대상 변압기(3)의 부하가 위상변환장치(15)를 통하여 다른 상의 변압기에 전가되어, 3상4석식 75KVA(등동 공용) 1대와 30KVA(동력전용) 2대와 같이 용량이 상이한 3상 변대의 대용량 변압기 과부하시에 이 공법을 적용하게 되면 다른 상의 변압기에는 과부하 내력을 초과하는 부하가 걸릴 수 있는 위험을 감당해야 하는 문제가 있기에, 전기공사업체의 입장에서 는 모든 변압기 교체 현장에 공용으로 적용할 수 있는 공법도 아닌 이 공법을 위해 고가의 위상변환장치(15)를 구비한다는 것은 경영의 효율성을 저해할 수 있고, 전기공급자 입장에서는 시공 과정에서 타 변압기의 과부하 소손이 우려되는 공법을 적극 활용할 수는 없는 것이 현실일 것이다. 또한 이 공법은 3대의 각 상별 변압기(3)의 2차측 접지 인하선(4)이 공용접지가 되어 인하되지 아니하고 단독으로 인하되어 있을 경우에만 적용이 용이하나 현시점의 배전설비에서 거의 전 3상 변대에서 접지 인하선이 공용으로 인하되고 있으므로 현실적인 적용은 곤란한 상황이다.The bypass method of the recently developed phase shifter 15 is not applicable to a single phase in addition, and in the case of a three phase shift, the load of the transformer 3 to be replaced is transferred through the phase shifter 15. It is transferred to another phase transformer, and this method is applied when overloading a large-capacity transformer of three phases with different capacities, such as one three-phase four-seat 75KVA (equal equivalent) and two 30KVA (power only) units. Since there is a problem in that a load exceeding an overload capacity can be taken, an electric contractor can use an expensive phase shifter for this method, which is not publicly applicable to all transformer replacement sites. 15) may impair the efficiency of management, and it is not possible for the electricity supplier to actively use the construction method that may cause overload damage of other transformers during the construction process. It will silil. In addition, this method is easy to apply only when the secondary grounding cut-off line 4 of each three phase transformers 3 is a common ground and is not cut, but is cut down by itself. Since the grounding down line is being cut down in common, the practical application is difficult.

종래의 이동형 무정전 변압기장치(7)나 위상변환 바이패스장치(15) 등과 같은 별도의 장치를 이용하는데 따른 작업상의 어려움이나, 비용적인 부담을 경감시키기 위하여, 교체설치할 변압기 그 자체나 공사용 변압기(8)를 철거대상 변압기와 동일 전주에 같은 방식으로 결선한 후 배전선로에 연결하여 병렬운전 형태가 되도록 한 뒤, 철거대상 변압기를 무정전으로 교체한다. In order to alleviate the difficulty or cost burden of using a separate device such as the conventional mobile uninterruptible transformer device 7 or the phase shift bypass device 15, the transformer itself or a construction transformer to be replaced (8) ) In the same way with the transformer to be demolished and connected to the distribution line so that it is in parallel operation form, then replace the transformer to be uninterrupted.

이상에서 상세히 설명한 바와 같이, 무정전으로 변압기를 교체시 기존의 무정전 공법에서는 활선차량과, 변압기 인상인하용 크레인과 무정전을 확보하기 위한 무정전변압기 장치 또는 위상변환 바이패스 장치가 소요되었으나, 본 발명에 의하면, 활선차량과 크레인 및 변압기 여유분 1대만 있으면 무정전 변압기 교체작업이 가능하므로, 작업이 간단할 뿐 아니라 골목길 등 협소한 장소에서도 변압기 교체작 업이 가능하고, 특히 무정전 변압기 장치 또는 위상변환 바이패스 장치가 필요 없어 장비구입에 따른 부담이 획기적으로 줄어드는 효과가 있다.As described in detail above, when replacing a transformer with an uninterrupted power, in the conventional uninterrupted method, a live vehicle, a crane for lowering a transformer, and an uninterruptible transformer device or a phase shift bypass device for securing an uninterruptible power are required. Uninterruptible transformers can be replaced by using a live vehicle, a crane, and one spare part of the transformer. Therefore, not only is the work simple, but also the transformer can be replaced in a narrow area such as an alley. There is no need to reduce the burden on equipment purchases.

본 발명은 종래의 이동형 무정전 변압기장치(7)나 위상변환 바이패스장치(15) 등과 같은 별도의 장치를 이용하지 않고, 교체설치할 변압기 그 자체나 공사용 변압기(8)를 이용하여 무정전으로 변압기를 교체할 수 있도록 한, 공사용 변압기를 이용한 주상 변압기 무정전 교체공법을 적용하는데 목적이 있다.The present invention does not use a separate device, such as the conventional mobile uninterruptible transformer device (7) or the phase shift bypass device (15), and replace the transformer by uninterrupted by using the transformer itself or construction transformer (8) to be installed and replaced The purpose of this is to apply the uninterrupted replacement method of the pole transformer using the construction transformer.

상기 목적을 달성하기 위한 본 발명은 교체대상 변압기(3)가 설치되어 있는 전주(13)에 공사용 변압기(8)를 걸 수 있는 별도의 행거(11)를 설치하고, 이 행거(11)의 변압기걸이(12)(또는 기설치되어 있는 행거밴드의 잉여 변압기걸이(12))에 교체대상 변압기(3) 용량 이상의 공사용 변압기(8)를 설치하여, 이 공사용 변압기(8)를 교체대상 변압기(3)와 병렬로 연결하여 교체 대상 변압기(3)에서 공급하던 저압선(2)이나 인입선의 부하를 공사용 변압기(8)에 전가하여, 수용가측에 정전이 발생하지 않는 무정전 상태를 유지하면서 교체한다,The present invention for achieving the above object is provided with a separate hanger (11) for hanging the construction transformer (8) in the electric pole 13 is installed a replacement target transformer (3), the transformer of this hanger 11 A construction transformer 8 having a capacity greater than or equal to that of the replacement target transformer 3 is installed on the hook 12 (or the redundant transformer hanger 12 of the hanger band that is already installed), thereby replacing the construction transformer 8 with the replacement target transformer 3 ) And transfer the load of the low voltage wire (2) or the lead wire supplied from the transformer to be replaced (3) to the construction transformer (8) and replace it while maintaining an uninterrupted state in which no power failure occurs at the consumer side.

변압기 3대를 조합하여 구성한 3상 변대에 있어서의 나머지 변압기도 이와 같은 방법으로 순차적으로 교체하면 1차측 특고압 바이패스(5)를 하지 않고 간단히 변압기(3)를 교체할 수 있다. If the remaining transformers in the three-phase transformer formed by combining three transformers are also sequentially replaced in this manner, the transformer 3 can be simply replaced without the primary side high-pressure bypass 5.

1상 변대의 경우에, 기존의 변압기와 90°의 각도로 측방에 설치되는 공사용 변압기(8)가 계속 설치되어 있어도 무방한 경우이거나, 기존의 행거밴드(11)가 S-3 타입의 3상 변대용이면, 공사용 변압기(8) 자체를 신설 변압기로 간주하여 교체대상 변압기(3)와 병렬로 연결된 상태에서 무정전으로 부하를 흡수하고, 교체대상 변압기를 철거하면 모든 작업 공정이 종료될 수도 있고, 공사용 변압기를 배전선로용 변압기로 활용하는 것이 곤란할 경우에는, 공사용 변압기의 병렬회로를 이용하여 무정전으로 변압기를 교체한 후 공사용 변압기를 철거함으로써 모든 작업공정이 종료된다. In the case of a one-phase inlet, the construction transformer 8 installed sideways at an angle of 90 ° with the existing transformer may be installed continuously, or the existing hanger band 11 is a three-phase S-3 type. In the case of a transformer, the construction transformer (8) itself is regarded as a new transformer and absorbs the load uninterrupted while being connected in parallel with the replacement transformer (3), and the removal of the replacement transformer may end all work processes, When it is difficult to use a construction transformer as a transformer for a distribution line, all work processes are terminated by replacing the transformer uninterrupted by using the parallel circuit of the construction transformer and then removing the construction transformer.

이러한 구성에 의하면, 종래의 이동형 무정전 변압기장치(7)나 위상변환 바이패스장치(15) 등과 같은 별도의 장치를 사용하지 않고 변압기(3)를 교체할 수 있어 작업이 간편할 뿐만 아니라, 변압기 교체 공사비 절감과 장비 구비에 따른 부담을 경감시킬 수 있으며, 협소한 장소에도 적용이 가능한 장점이 있다.According to such a configuration, the transformer 3 can be replaced without using a separate device such as the conventional mobile uninterruptible transformer device 7 or the phase shift bypass device 15, which not only makes the operation simple, but also replaces the transformer. Reduction of construction cost and burden of equipment can be reduced, and it can be applied to narrow places.

이러한 본 발명은 또한 종래의 1차측 특고압 바이패스에 필요한 장비로 특고압 1차바이패스 케이블(5), 특고압차단기, 특고압 변압기, 1차측과 2차측을 위상 검상장치 등 장치가 복잡한 것에 비해, 본 발명은 공사용 변압기(8)만 구비하면 되므로 시공 업체의 입장에서는 경제적 부담을 거의 무시할 수 있는 것이다The present invention is also a device required for the conventional primary-side high-pressure bypass, the high-pressure primary bypass cable (5), the extra-high voltage circuit breaker, the extra-high voltage transformer, the primary side and the secondary side of the complex device such as phase inspection device On the contrary, since the present invention only needs to be provided with a transformer for construction 8, the economic burden can be almost ignored from the perspective of the construction company.

이하, 본 발명에 의한 실시예를 첨부된 도면을 참조해서 상세히 설명하면 다음과 같다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 3은 종래의 무정전 변압기차를 이용한 3상 주상변압기 바이패스 결선도이다3 is a bypass connection diagram of a three-phase columnar transformer using a conventional uninterruptible transformer vehicle.

도 3은 종래의 변압기 교체방식으로, 무정전 변압기차(7)을 이용하여 변압기 각상 에 1차측에 특고압 바이패스(5)와 2차측에 저압 바이패스(6) 회로를 구성하여 변압기(3)를 교체하고 있었다3 is a conventional transformer replacement method, by using an uninterruptible transformer car (7) to configure a high-voltage bypass (5) circuit on the primary side and a low-pressure bypass (6) circuit on the secondary side of the transformer (3) Was replacing

도 6b는 본 발명에 의한 공사용 변압기를 이용한 주상 변압기 무정전 교체를 이용한 3상 주상변압기 바이패스 결선도이다.Figure 6b is a bypass connection diagram of a three-phase columnar transformer using an uninterruptible replacement of the columnar transformer using a construction transformer according to the present invention.

3상 변대에 있어 변압기를 교체하고자 하면, 도 6b에 도시된 바와 같이, 공사용 변압기(8)를 이용하여 교체대상 변압기(3)의 1차(9)와 2차(10)를 같은 결선방식으로 병렬 연결하면 공사용 변압기(8)에서 부하을 분담하게 되고, 교체대상 변압기(3)를 철거하면 병렬운전되던 공사용 변압기(8)로 철거대상 변압기(3)의 전부하가 전이되어 무정전으로 변압기를 철거할 수 있게 되며, 교체신설되는 변압기도 공사용 변압기(3)와 같은 결선방식으로 1차(9)와 2차(10)를 병렬 연결하면 공사용 변압기(8)에 전이되어 있던 부하의 일부가 전이되고, 공사용 변압기(8)의 2차(10)와 1차 리드선(9)을 선로로부터 분리하면 공사용 변압기(8)에 걸려있던 부하가 교체신설된 변압기로 모두 부하가 이전되어 해당 상의 변압기 공사가 완료되는 것이다. 해당 변대에서 추가적으로 다른 상의 변압기를 교체할 때는 위의 방법으로 순차적인 작업을 시행하면 작업이 원할하게 수행되는 것이다.If the transformer is to be replaced in the three-phase, as shown in Figure 6b, by using the construction transformer 8, the primary 9 and the secondary 10 of the replacement transformer 3 in the same connection method When connected in parallel, the load is shared by the construction transformer (8), and when the replacement target transformer (3) is removed, the full load of the demolition target transformer (3) is transferred to the construction transformer (8) which was operated in parallel to dismantle the transformer by uninterruption. When the replacement transformer is connected to the primary (9) and the secondary (10) in the same connection method as the construction transformer (3), a part of the load transferred to the construction transformer (8) is transferred, When the secondary 10 and the primary lead 9 of the construction transformer (8) are separated from the track, the load on the construction transformer (8) is replaced with the newly installed transformer, and the load is transferred to complete the transformer construction of the phase. will be. When additional transformers in other phases are replaced at the corresponding side, the sequential work can be performed smoothly.

1상 변대에 있어 변압기를 교체하고자 하면, 도 5b에 도시된 바와 같이, 공사용 변압기(8)를 이용하여 교체대상 변압기(3)의 1차(9)와 2차(10)를 같은 결선방식으 로 병렬 연결하면 공사용 변압기(8)에서 부하을 분담하게 되고, 교체대상 변압기(3)의 2차(10)와 1차 리드선(9)및 변압기(3) 자체를 철거하면 병렬운전되던 공사용 변압기(8)로 철거대상 변압기(3)의 전부하가 전이되어 무정전으로 변압기(3)를 철거할 수 있게 되며, 교체하여 신설하는 변압기도 공사용 변압기(8)와 같은 결선방식으로 1차(9)와 2차(10)를 병렬 연결하면 공사용 변압기(8)에 전이되어 있던 부하의 일부가 신설 변압기로 이전되고, 공사용 변압기(8)의 2차(10)와 1차 리드선(9) 및 공사용 변압기를 선로로부터 분리하여 철거하면 공사용 변압기 (8)에 걸려있던 부하가 교체신설된 변압기로 모두 이전되어 해당 변대의 변압기 공사가 무정전으로 완료되는 것이다. If you want to replace the transformer in the one-phase, as shown in Figure 5b, using the transformer for construction 8, the primary 9 and the secondary 10 of the replacement target transformer 3 in the same connection method In parallel, the load is shared by the construction transformer (8), and the construction transformer (8) which was operated in parallel when the secondary 10, the primary lead wire (9) and the transformer (3) itself of the replacement target transformer (3) were removed. The full load of the demolition target transformer (3) is transferred to) so that the transformer (3) can be dismantled by uninterruption, and the newly-installed transformer can also be replaced by the same wiring method as the construction transformer (8). When the car 10 is connected in parallel, part of the load transferred to the construction transformer 8 is transferred to the new transformer, and the secondary 10 and the primary lead wire 9 of the construction transformer 8 and the construction transformer are lined up. When dismantled from the transformer, the load on the construction transformer (8) is replaced with a new transformer. As a result, transformer construction of the corresponding side is completed uninterrupted.

만약 단상 변대에서 철거대상 변압기(3)의 90°각도의 위치에 신설 변압기를 설치하여 운영할 수 있는 현장 여건에서, 별도의 행거밴드(11)를 설치하거나, 행거밴드 (11)가 3상 변대용인 S-3이 설치되어 있으면, 철거대상 변압기(3)의 90°각도의 위치에 신설 변압기를 병렬로 설치하였다가, 철거대상 변압기(3) 철거를 하기만 하면 작업이 완료되는 것이다. If a single-sided transformer is installed at a 90 ° angle of the demolition target transformer (3) at a site where a new transformer can be operated, a separate hanger band (11) may be installed, or the hanger band (11) may be a three-phase valve. If a substitute S-3 is installed, the newly installed transformers are installed in parallel at a 90 ° angle of the demolished transformer 3, and the work is completed by simply removing the demolished transformer 3.

물론 이러한 전 과정에서 작업을 하지 않는 다른 변압기에 대해서는 1차 및 2차 리드선은 물론, 변압기 및 COS를 절연방호함으로써, 충분한 안전성과 작업의 용이성을 확보할 수 있게 되는 것이다. Of course, for other transformers that do not work in this whole process, by insulating protection of the transformer and COS as well as the primary and secondary leads, it is possible to ensure sufficient safety and ease of operation.

도 1은 1상2선식 변대에서의 변압기 결선 및 시공도1 is a diagram illustrating the wiring and construction of a transformer in a one-phase two-wire transformer.

도 2는 3상4선식 변대에서의 변압기 결선 및 시공도2 is a diagram illustrating the wiring and construction of a transformer in a three-phase four-wire toilet.

도 3은 무정전 변압기 장치를 이용한 변압기 무정전 교체작업 결선도3 is a connection diagram of a transformer uninterruptible replacement operation using an uninterruptible transformer device

도 4는 위상변환 바이패스 장치를 이용한 작업 결선도Figure 4 is a work connection diagram using a phase shift bypass device

도 5a는 1상 변대 작업전 평면결선도 및 회로도Figure 5a is a plan diagram and circuit diagram before the operation of the single phase toilet

도 5b는 본 발명에 의한 1상 변대의 변압기 교체 작업중의 평면 결선도 및 회로도 5B is a plan view and a circuit diagram of the transformer replacement operation of the one-phase valve according to the present invention.

도 6a는 3상 변대 작업전 평면결선도 및 회로도Figure 6a is a plan connection diagram and circuit diagram before the three-phase toilet operation

도 6b는 본 발명에 의한 3상 변대의 변압기 교체 작업중의 평면 결선도 및 회로도6B is a plan view and a circuit diagram of a three-phase transformer transformer replacement work according to the present invention.

[도면의 주요부분에 대한 부호의 설명][Explanation of symbols on the main parts of the drawings]

1 : 특고압 선로1: High voltage line

2 : 저압선로2: low voltage line

3 : 변압기3: transformer

4 : 접지 인하선4: ground cut line

5 : 무정전 변압기 장치 특고압 바이패스 케이블5: uninterruptible transformer unit extra high voltage bypass cable

6 : 무정전 변압기 장치 저압 바이패스 케이블6: uninterruptible transformer unit low voltage bypass cable

7 : 무정전 변압기 장치7: uninterruptible transformer device

8 : 공사용 변압기8: transformer for construction

9 : 공사용 변압기 1차 인상선9: construction transformer primary impression line

10 : 공사용 변압기 2차 인하선10: secondary transformer for construction transformer

11 : 행거밴드11: hanger band

12 : 행거밴드 변압기걸이12: hanger band transformer hanger

13 : 전주13: Jeonju

14 : 주상 변압기용 COS14: COS for pole transformer

15 : 위상변환 바이패스 장치15: phase shift bypass device

Claims (2)

3상4선식 380/220V 공급방식의 변대 또는 1상2선식 220V 공급방식의 변대에서 변압기를 교체하기 위하여, 배전선로에 사용되는 일반적인 변압기와 같은 사양의 공사용 변압기를 해당 전주에 설치하여 철거대상 변압기와 1차 및 2차 리드선이 동일하게 결선하여 병렬로 연결한 후, 철거대상 변압기를 무정전으로 철거하고, 새로운 변압기를 철거한 변압기와 같은 결선으로 신설하여 공사용 변압기와 병렬로 연결한 후, 공사용 변압기를 원상으로 철거함으로써, 무정전상태에서 변압기 교체공사를 할 수 있도록 하는 것을 특징으로 한, 주상변압기 무정전 교체용 배전공법To replace the transformer in the three-phase four-wire 380 / 220V supply or the one-phase two-wire 220V supply, install a transformer for the same specification as the general transformer used in the distribution line in the electric pole. After the primary and secondary lead wires are connected in the same way and connected in parallel, the transformer to be demolished is uninterrupted and the new transformer is newly connected with the same wiring as the demolished transformer and connected in parallel with the construction transformer. By dismantling the power supply in the original form, it is possible to perform transformer replacement work in the uninterrupted state. 1상2선식 220V 공급방식의 철거대상 변대와 90°정도 각도차의 위치에 신설 단상 변압기를 설치하여 운영할 수 있는 여건의 현장에서, 변압기를 교체하기 위하여, 배전선로에 사용되는 일반적인 변압기와 같은 사양의 공사용 변압기를 해당 전주에 설치하고 철거대상 변압기와 1차 및 2차 리드선이 동일하게 결선하여 병렬로 연결한 후, 철거대상 변압기의 2차, 1차 리드선 및 변압기 자체를 철거함으로써, 무정전상태에서 변압기 교체공사를 할 수 있도록 하는 것을 특징으로 한, 주상변압기 무정전 교체용 배전공법It is the same as a general transformer used in distribution lines to replace transformers at the site where a new single-phase transformer can be installed and operated at a position of 90 ° angle difference with a demolition target of 1-phase 2-wire 220V supply method. Uninterrupted state by installing the construction transformer of the specification on the pole and connecting the demolition transformer and the primary and secondary lead wires in the same way and connecting them in parallel, and then dismantling the secondary, primary lead wire and the transformer itself. Power distribution method for uninterruptible replacement of the columnar transformer, characterized in that the transformer replacement construction in
KR1020070089223A 2007-09-03 2007-09-03 Current transformer changing method with extra transformer KR20090024035A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070089223A KR20090024035A (en) 2007-09-03 2007-09-03 Current transformer changing method with extra transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070089223A KR20090024035A (en) 2007-09-03 2007-09-03 Current transformer changing method with extra transformer

Publications (1)

Publication Number Publication Date
KR20090024035A true KR20090024035A (en) 2009-03-06

Family

ID=40693159

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070089223A KR20090024035A (en) 2007-09-03 2007-09-03 Current transformer changing method with extra transformer

Country Status (1)

Country Link
KR (1) KR20090024035A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102053318B1 (en) 2019-10-25 2019-12-06 한국산업써비스 주식회사 Multi-purpose movable transformer
KR20200041535A (en) * 2018-10-12 2020-04-22 한국전력공사 Three Phases Pole Transformer for Uninterruptible Power Construction and Method Thereof
KR20230097404A (en) * 2021-12-24 2023-07-03 한국전력공사 Uninterruptible construction method using vehicle with transformer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200041535A (en) * 2018-10-12 2020-04-22 한국전력공사 Three Phases Pole Transformer for Uninterruptible Power Construction and Method Thereof
KR102053318B1 (en) 2019-10-25 2019-12-06 한국산업써비스 주식회사 Multi-purpose movable transformer
KR20230097404A (en) * 2021-12-24 2023-07-03 한국전력공사 Uninterruptible construction method using vehicle with transformer

Similar Documents

Publication Publication Date Title
KR100926445B1 (en) Uninterruptible bypassing method for underground power line using extension elbow
CN101064431B (en) Method for replacing 10kV distributing transformer with charge
CN202916384U (en) Improved voltage transformer zero sequence circuit system capable of improving precision of line selection and fault positioning
KR20100054948A (en) By-pass construction method for replacement of pole-top transformer (1phase/3phase) using 1phase portable transformer
CN102931661B (en) Alternating-current distribution method and power supply wiring device compatible to various power grid patterns
CN106451220A (en) Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower
KR101080680B1 (en) Exchange method for trasformer without interruption of electric service
CN109347134B (en) Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
KR20090024035A (en) Current transformer changing method with extra transformer
KR102598787B1 (en) Uninterruptible power distribution work method for low voltage line
CN102914683B (en) A kind of acquisition method of three-phase single cable single-phase-to-ground current
KR100415908B1 (en) Low Voltage a Phase Converter Bypass Connection Device Without Power Failure
KR102332571B1 (en) An electric power supply method of the control unit for pad mounted type switchgear for underground line
CN209948370U (en) Bypass node type PT cabinet
CN201616628U (en) Distribution box for construction technology
CN100401611C (en) Four-way power supply equalization switched transformer station wiring method
CN101859986A (en) Transformer substation main connection system based on single bus bar partition
KR101754043B1 (en) Uninterruptible power distribution method without intermediate connection of bypass cable using single-phase multi-branch switchgear with separately switching function
KR102622675B1 (en) The ground transformer uninterruptible replacement method using the ground transformer elbow connector three phase batch separation connection apparatus and feed through
CN102593826B (en) Wiring structure of high voltage distribution network
KR200264141Y1 (en) Invention of by-pass cable for interchanging P.Tr earth line
CN202435033U (en) High voltage distribution network connecting wire structure
KR200238278Y1 (en) Nothing power failure connection panel
KR100894881B1 (en) A replacing method of transformer for an electric consumption facility of high voltage without interrupting power supply and bypass connecting device thereof
KR20090012462A (en) A replacing method of transformer for an electric consumption facility of high voltage without interrupting power supply

Legal Events

Date Code Title Description
N231 Notification of change of applicant
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E601 Decision to refuse application