KR20070030013A - Assembly structure of square pipe for prefab building - Google Patents

Assembly structure of square pipe for prefab building Download PDF

Info

Publication number
KR20070030013A
KR20070030013A KR1020050084738A KR20050084738A KR20070030013A KR 20070030013 A KR20070030013 A KR 20070030013A KR 1020050084738 A KR1020050084738 A KR 1020050084738A KR 20050084738 A KR20050084738 A KR 20050084738A KR 20070030013 A KR20070030013 A KR 20070030013A
Authority
KR
South Korea
Prior art keywords
square pipe
hole
pillar
fixing piece
fastened
Prior art date
Application number
KR1020050084738A
Other languages
Korean (ko)
Other versions
KR100712465B1 (en
Inventor
채일수
Original Assignee
채일수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 채일수 filed Critical 채일수
Priority to KR1020050084738A priority Critical patent/KR100712465B1/en
Publication of KR20070030013A publication Critical patent/KR20070030013A/en
Application granted granted Critical
Publication of KR100712465B1 publication Critical patent/KR100712465B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • E04B1/5825Connections for building structures in general of bar-shaped building elements with a closed cross-section
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • E04B1/5825Connections for building structures in general of bar-shaped building elements with a closed cross-section
    • E04B1/5837Connections for building structures in general of bar-shaped building elements with a closed cross-section of substantially circular form
    • E04B1/585Connections for building structures in general of bar-shaped building elements with a closed cross-section of substantially circular form with separate connection devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • E04B1/5825Connections for building structures in general of bar-shaped building elements with a closed cross-section
    • E04B2001/5856Connections for building structures in general of bar-shaped building elements with a closed cross-section using the innerside thereof

Abstract

An assembly structure of a square pipe for a prefabricated building is provided to ease a construction of a building by installing a fixing piece at the side part of the column like a H-beam, a welding shape steel, a P.E.B system, or a square frame structure and by easily combining with the square pipe at the fixing piece. An assembly structure of a square pipe for a prefabricated building comprises a slant cutting part(212) formed by slantly cutting the end of a squire pipe(200); a combining hole(211) perforated to a body(210), opened through the slant cutting part; a bolt(260) and a nut(261) fixed through the slant cutting part; a spreading hole and the combining hole perforated at the body formed on the end of the squire pipe; the combining hole opened through the spreading hole; and the bolt and the nut fixed through the spreading hole.

Description

조립식 건축물의 사각파이프 조립구조{ASSEMBLY STRUCTURE OF SQUARE PIPE FOR PREFAB BUILDING}ASSEMBLY STRUCTURE OF SQUARE PIPE FOR PREFAB BUILDING}

도 1 : 본 발명의 요부분해사시도1: Partial exploded perspective view of the present invention

도 2 : 본 발명의 요부분해사시도2 is a partial partial perspective view of the present invention

도 3 : 도 2의 측단면구성도3 is a side cross-sectional view of FIG.

도 4 : 본 발명 타실시예의 요부분해사시도4 is a partial partial perspective view of another embodiment of the present invention

도 5 : 도 4의 측단면구성도5 is a side cross-sectional view of FIG.

도 6 : 본 발명 타실시예의 요부분해사시도6 is a partial partial perspective view of another embodiment of the present invention

도 7 : 본 발명 타실시예의 측면구성도7 is a side view of another embodiment of the present invention

도 8 : 본 발명을 이용한 조립건축물의 사시도8 is a perspective view of the assembly building using the present invention

도 9 : 종래 조립구조의 요부사시도9 is a perspective view of a conventional assembly structure

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

(100)--기둥 (110)--고정편(100)-pillar (110)-pinning

(111)--체결공 (113)--수직간(111)-The fastener (113)-vertical

(114)--관통공 (115)--수평간(114)-Through Hole (115)-Horizontal

(120)--관통공 (121)--볼트(120)-Through Hole (121)-Bolt

(122)--너트 (200)--사각파이프(122)-Nut (200)-Square Pipe

(210)--본체 (211)--체결공(210)-Main Body (211)-Fighter

(212)--경사절단부 (215)--확개공(212)-Slant Cut (215)-Expanded

(260)--볼트 (261)--너트(260)-Bolt (261)-Nut

본 발명은 물류창고나 공장건물, 쇼핑센타등과 같은 건축물을 시공함에 있어서, 주기둥 사이에 설치되는 보조기둥을 사각파이프로 시공될 수 있게 한 것이다.In the present invention, when constructing a building such as a warehouse, a factory building, a shopping center, or the like, the auxiliary pillars installed between the main pillars can be constructed as square pipes.

일반적으로 물류창고나 공장건물, 쇼핑센타등과 같은 건축물은 주로 H빔이나 용접형강 혹은 P.E.B시스템(Pre-Engineered Building System)으로 주기둥을 설치하고, 상기 주기둥 사이에는 보조기둥을 설치하여 주기둥의 내력을 보완케 할 뿐 아니라 마감판넬의 시공시 판넬의 내력보강 및 조립을 용이하게 하고 있다.In general, a building such as a warehouse, a factory building, a shopping center, or the like is mainly installed with a H beam, a welded steel, or a PEB system (Pre-Engineered Building System), and an auxiliary pillar is installed between the main pillars. In addition to supplementing the strength of the panel, it is easy to reinforce and assemble the panel's strength when constructing the finishing panel.

상기에서 보조기둥으로 사용되고 있는 구조로서는 주로 H빔을 사용하거나 H빔과 함께 철판을 포밍하여 제작한 경량골조를 주로 사용하게 된다.As the structure that is used as an auxiliary pillar in the above is mainly to use a light frame made by using the H beam or forming the steel plate with the H beam.

따라서 H빔의 경우 내력보강에는 유리한 점이 있으나 H빔의 가격이 고가인 단점이 있을 뿐 아니라 H빔 외면에 마감판넬을 시공하고자 할 경우에는 H빔측부에 C형강과 같은 골조를 용착구성한 다음 C형강을 통하여 마감판넬이 고정되는 구조이므로 판넬의 시공에 어려움이 있는 것이었다.Therefore, in the case of H beam, there is an advantage in bearing strength, but the price of H beam is not only high, but also when constructing finishing panel on the outside surface of H beam, C-shaped steel is welded on the H beam side Because the finishing panel is fixed through the construction of the panel was difficult.

또한 철판을 포밍하여 제작한 경량골조를 사용할 경우에는 내구성 보완을 위하여 경량골조에 여러형태의 요철과 절곡부를 구성하게 되므로 외관이 미려하지 못 한 단점이 있는 것이었다.In addition, in the case of using a lightweight frame made by forming a steel plate to form a variety of irregularities and bent portion in the lightweight frame to complement the durability was a disadvantage that the appearance was not beautiful.

이러한 제반 단점을 보완하기 위하여 가벼우면서 내구성이 우수하고, 외관이 미려한 사각파이프의 사용이 시도된바 있으나 조립작업에 어려움이 있어 현실적으로 시공에 많은 제약이 따르게 되는 것이었다.In order to make up for these shortcomings, the use of square pipes with light, durable and beautiful appearance has been attempted, but there are difficulties in assembling work, which leads to many restrictions in construction.

다시 설명하면 종래 주기둥이나 주보조기둥과 같은 구조물에 사각파이프를 조립하기 위한 수단은 다음과 같다.In other words, the conventional means for assembling a square pipe in a structure such as a main pillar or a secondary auxiliary pillar is as follows.

즉 도 9에서와 같이 사각파이프(10) 일측 단부에 마감판(20)을 용접구성하고, 상기 마감판(20) 일측에 다시 연결판(30)을 용접구성하되, 상기 연결판(30)을 이용하여 주기둥이나 보조기둥에 용접구성된 연결판(40) 상에 위치시킨 다음 볼트(50)와 너트(51)로 사각파이프(10)가 조립되게 한 구성이다.That is, as shown in FIG. 9, the welded end plate 20 is welded to one end of the square pipe 10, and the joining plate 30 is welded to one side of the ended plate 20, but the connecting plate 30 is welded. It is a configuration that the square pipe 10 is assembled on the connecting plate 40 welded to the main pillar or auxiliary pillar using the bolt 50 and the nut 51.

상기한 구성의 사각파이프(10) 조립구조는 다음과 같은 단점이 있다.Square pipe 10 assembly structure of the above configuration has the following disadvantages.

즉 사각파이프(10) 일측 단부에 별도의 연결수단을 구성하기 위하여 마감판(20)을 용접하고, 상기 마감판(20) 일측에 다시 연결판(30)을 용접하여야 하는 번거로움이 있어 작업의 효율성 및 인력이 낭비되는 등의 단점이 있는 것이었다.That is, there is a hassle to weld the finishing plate 20 to form a separate connection means at one end of the square pipe 10, and to weld the connecting plate 30 to one side of the closing plate 20 again. There were disadvantages such as waste of efficiency and manpower.

본 발명은 이러한 종래의 제반 단점을 시정하기 위하여 물류창고나 공장건물, 쇼핑센타등과 같은 건축물을 시공함에 있어서, 주기둥 혹은 보조기둥 사이에 내력보강을 위하여 사각파이프를 연결시공토록 하되, 사각파이프를 주기둥과 보조기둥과의 연결설치가 신속용이하면서 견고한 결합이 이루어질 수 있도록 한 것이다.In the present invention, in the construction of a building such as a warehouse, a factory building, a shopping center, etc., in order to rectify all the disadvantages of the related art, a square pipe is connected to the square pipe for reinforcement of strength between the main pillar or the auxiliary pillar. The connection between the main pillar and the auxiliary pillar is quick and easy to achieve a solid coupling.

상기 목적을 달성하기 위하여 본 발명은 H빔이나 용접형강, P.E.B시스템(Pre- Engineered Building System), 사각골조등으로 주기둥 혹은 보조기둥을 설치하되, 주기둥 및 보조기둥 일측에 고정편을 고정설치하고, 상기 고정편 상에 사각파이프가 신속용이하게 고정될 수 있게 하는 것이다.In order to achieve the above object, the present invention is to install a main pillar or an auxiliary pillar by H beam or welded steel, PEB system (Pre- Engineered Building System), square frame, etc., and fixing the fixing piece on one side of the main pillar and the auxiliary pillar. In addition, the square pipe is to be quickly and easily fixed on the fixing piece.

이때 사각파이프를 주기둥 또는 보조기둥에 용접구성된 고정편 상에 신속용이하게 체결고정되게 하기 위한 수단으로서는 사각파이프의 연결단부를 경사지게 절단하여 일측 본체가 개방되게 하되, 개방된 일측 본체 상에 체결공을 뚫어 구성하고, 상기한 상태의 사각파이프를 주기둥이나 보조기둥 일측에 고정된 고정편 상에 위치시킨 다음 볼트와 너트로 체결고정되게 하거나 사각파이프의 본체 상에 확개공과 체결공을 뚫은 다음 상기 사각파이프를 주기둥이나 보조기둥에 고정된 고정편 상에 위치시킨 다음 볼트와 너트로 체결고정되게 한다.In this case, as a means for quickly fastening and fastening the square pipe on the fixed piece welded to the main pillar or the auxiliary pillar, the connecting end of the square pipe is inclined to be inclined so that one side main body is opened, and a fastening hole on the opened one side main body. After constructing the hole, place the above-mentioned square pipe on the fixed piece fixed to one side of the main pillar or the auxiliary pillar, and then fix it with bolts and nuts, or drill the expansion hole and the fastening hole on the body of the square pipe. The square pipe is placed on a fixed piece fixed to a main pillar or an auxiliary pillar, and then fastened with bolts and nuts.

본 발명의 다른 실시예로서는 주기둥이나 보조기둥 일측에 고정편을 용접구성하지 않고, 수직간과 수평간으로 구성된 고정편을 볼트와 너트로 체결고정되게 하고 상기 고정편 상에 사각파이프를 체결고정되게 하여 사용할 수도 있다.According to another embodiment of the present invention, without fixing the fixing piece on one side of the main pillar or the auxiliary pillar, the fixing piece consisting of the vertical and horizontal parts is fastened by bolts and nuts, and the square pipe is fastened and fixed on the fixing piece. Can also be used.

이하 본 발명의 실시예를 첨부도면에 따라 상세히 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에서 제공하고자 하는 조립식 건축물의 사각파이프 조립구조를 도시한 상태의 사시도로서, H빔이나 용접형강, P.E.B시스템(Pre Engineered Building System) 혹은 사각형상의 골조를 이용하여 주기둥이나 보조기둥과 같은 기둥(100)를 설치하되, 기둥(100) 측부에 사각파이프(200)를 신속용이하게 결합할 수 있도록 하는 것이다.1 is a perspective view showing a rectangular pipe assembly structure of a prefabricated building to be provided by the present invention, using a H beam or welded steel, a PEB system (Pre Engineered Building System) or a rectangular frame, a main pillar or an auxiliary pillar To install the pillar 100, such as, to be able to quickly combine the square pipe 200 to the pillar 100 side.

즉 기둥(100) 일측에 고정편(110)을 용착구성하고, 상기 고정편(110) 상에는 체결공(111)을 뚫어 구성한다.That is, the fixing piece 110 is welded to one side of the pillar 100, and the fastening hole 111 is formed on the fixing piece 110.

기둥(100)의 고정편(110) 상에 연결되는 사각파이프(200)의 구조는 다음과 같다.The structure of the square pipe 200 connected on the fixing piece 110 of the pillar 100 is as follows.

즉 사각파이프(200) 단부를 경사지게 절단하여 경사절단부(212)를 구성하므로서 사각파이프(200)의 본체(210)의 일부가 개방되게 하고, 상기 본체(210)에는 체결공(211)을 뚫어 구성한다.In other words, by cutting the end of the square pipe 200 inclined to form the inclined cut portion 212, a part of the main body 210 of the square pipe 200 is opened, and the fastening hole 211 is drilled in the main body 210 do.

상기한 구성의 사각파이프(200)를 기둥(100) 일측에 용착구성된 고정편(110) 상에 안치하여 사각파이프(200)에 구성된 체결공(211)과 고정편(110)에 구성된 체결공(111)이 나란히 일치되게 하고, 상기한 상태에서 사각파이프(200)의 경사절단부(212)를 통하여 개방된 본체(210)의 체결공(211)에 볼트(260)를 끼워 고정편(210)의 체결공(211)을 관통되게 한 다음 너트(261)로 체결고정되게 하므로서, H빔이나 용접형강, P.E.B시스템 혹은 사각골조등으로 구성되는 기둥(100) 일측에 사각파이프(200)의 결합이 완료된다.The square pipe 200 having the above-described configuration is placed on the fixed piece 110 welded to one side of the pillar 100 so that the fastening hole 211 formed in the square pipe 200 and the fastening hole configured in the fixed piece 110 ( 111 is aligned side by side, and the bolt 260 is inserted into the fastening hole 211 of the main body 210 opened through the inclined cut portion 212 of the square pipe 200 in the above state of the fixing piece 210 The coupling of the square pipe 200 to one side of the pillar 100 composed of H beam, welded steel, PEB system, or square frame is completed by allowing the fastening hole 211 to be penetrated and then fastened with a nut 261. do.

이때 사각파이프(200)에 구성된 경사절단부(212)는 볼트(260)를 체결하기 위한 공구가 체결공(211)에 끼워진 볼트(260) 머리부를 파지고정할 수 있도록 작업공간을 부여하는 것이다.At this time, the inclined cutting portion 212 configured in the square pipe 200 is to give a working space so that the tool for fastening the bolt 260 can be broken and fixed to the head of the bolt 260 inserted into the fastening hole 211.

본 발명을 실시함에 있어서, 사각파이프(200)를 기둥(100)에 고정설치함에 있어서 용접구성없이 결합할 수도 있다.In the practice of the present invention, in the fixed installation of the square pipe 200 to the column 100 may be combined without welding configuration.

즉 도 4에서와 같이 기둥(100)에 관통공(120)을 뚫고, 상기 관통공(120)에 수직간(113)과 수평간(115)으로 구성된 고정편(110)을 위치시켜 수직간(113)에 구성된 관통공(114)이 기둥(100)의 관통공(120)과 일치되게 하고, 상기한 상태에서 관통공(114)(120)에 볼트(121)를 끼운 다음 너트(122)로 체결고정되게 하므로서 고정편(110)이 기둥(100) 일측에 고정되게 한다.That is, as shown in FIG. 4, the through hole 120 is drilled in the pillar 100, and the fixing piece 110 composed of the vertical gap 113 and the horizontal gap 115 is positioned in the through hole 120. The through hole 114 configured at 113 is coincided with the through hole 120 of the pillar 100, and in the above state, the bolt 121 is inserted into the through hole 114 and 120, and then the nut 122 is inserted into the through hole 114. Fixing piece 110 is to be fixed to one side of the column 100 by being fastened.

상기한 상태에서 고정편(110)의 수평간(115) 상에 경사절단부(212)에 의해 일측 본체(210)가 개방된 사각파이프(200)를 위치시켜 본체(210)에 구성된 체결공(211)이 고정편(110)의 체결공(111)과 일치되게 하고, 상기한 상태에서 볼트(260)과 너트(261)로 이들이 체결고정되게 하므로서 고정편(110) 상에 사각파이프(200)의 결합이 완료되게 할 수도 있다.In the above state, a fastening hole 211 configured in the main body 210 by placing a square pipe 200 on which one main body 210 is opened by the inclined cutting portion 212 on the horizontal section 115 of the fixing piece 110. ) Is matched with the fastening hole 111 of the fixing piece 110, and in the above state by the bolt 260 and the nut 261 so that they are fastened and fixed by the square pipe 200 on the fixing piece 110 You can also make the join complete.

상기에서와 같이 기둥(100) 일측에 고정편(110)을 볼트(121)와 너트(122)로 체결고정하고, 상기 고정편(110) 상에 사각파이프(200)를 체결고정케 하므로서 용접없이 편리하게 연결할 수 있게 된다.As described above, the fixing piece 110 is fastened to one side of the pillar 100 by bolts 121 and nuts 122, and the square pipe 200 is fastened and fixed on the fixing piece 110 without welding. It can be connected conveniently.

본 발명을 실시함에 있어서, 도 6에서와 같이 사각파이프(200)를 결합할 수도 있다.In the practice of the present invention, it is also possible to combine the square pipe 200 as shown in FIG.

즉 사각파이프(200)를 경사절단하지 않고 본체(210) 상에 확개공(215)과 체결공(211)을 뚫고 상기한 구성의 사각파이프(200)를 기둥(100) 일측에 용접구성된 고정편(110) 상에 안치한 다음 볼트(260)와 너트(261)로 체결고정되게 할 수도 있다.That is, the fixed piece is constructed by welding the square pipe 200 of the above-described configuration by drilling the expansion hole 215 and the fastening hole 211 on the main body 210 without obliquely cutting the square pipe 200. It may be settled on 110 and then fastened with bolts 260 and nuts 261.

이때에도 확개공(215)은 체결공(211)에 끼워진 볼트(260) 파지를 위한 공구 가 끼워질 수 있는 작업공간확보를 위한 것이며, 상기한 경우 사각파이프(200)에 구성되는 확개공(215)은 최소한 볼트(260)의 머리부보다 크게 구성되어야 한다.In this case, the expansion hole 215 is for securing a work space into which a tool for gripping the bolt 260 inserted into the fastening hole 211 may be inserted, and in this case, the expansion hole 215 formed in the square pipe 200. ) Should be at least larger than the head of bolt 260.

또다른 실시예로서는 도 7에서와 같이 기둥(100)의 측면에 수직간(113)과 수평간(115)으로 구성되는 고정편(110)을 볼트(121)로 체결고정하고, 상기 고정편(110)의 수평간(115) 사이에 사각파이프(200)를 끼운 다음 볼트(260)와 너트(261)로 체결고정되게 하여 사용할 수도 있다.In another embodiment, as shown in FIG. 7, the fixing piece 110 consisting of the vertical section 113 and the horizontal section 115 is fastened and fixed to the side surface of the column 100 by bolts 121, and the fixing piece 110. The square pipe 200 may be inserted between the horizontal sections 115), and then may be fastened and fixed by the bolt 260 and the nut 261.

미설명부호 (300)은 건축물이다.Reference numeral 300 is a building.

이와 같이 구성된 본 발명은 도 8에서와 같이 물류창고나 공장건물, 쇼핑센타등과 같은 건축물(300)을 시공하고자 할때 H빔이나 용접형강, P.E.B시스템 혹은 사각골조등으로 기둥(100)을 설치하고, 상기 기둥(100)에 고정편(110)을 고정한 다음 고정편(110) 상에 사각파이프(200)를 신속용이하게 결합할 수 있게 된다.When the present invention configured as described above is intended to construct a building 300 such as a warehouse, a factory building, a shopping center, or the like, as shown in FIG. 8, the pillar 100 is installed by an H beam, a welded steel, a PEB system, or a square frame. Then, the fixing piece 110 is fixed to the pillar 100, and then the square pipe 200 can be quickly and easily coupled to the fixing piece 110.

상기에서와 같이 기둥(100) 측면에 구성된 고정편(110) 상에 사각파이프(200)를 신속용이하게 결합할 수 있는 것은 사각파이프(200)의 본체 단부에 볼트를 직접 체결고정할 수 있게 하였기 때문이다.Being able to quickly couple the square pipe 200 on the fixing piece 110 configured on the side of the pillar 100 as described above was able to directly fasten the bolt to the body end of the square pipe 200 Because.

다시 설명하면 도 1에서와 같이 사각파이프(200)의 단부에 경사절단부(212)를 구성하여 일측 본체(210)가 경사절단부(212)를 통하여 노출되게 하고, 노출된 본체(210) 상에 체결공(211)을 뚫고, 상기 체결공(211)을 고정편(110)에 뚫린 체결공(111)과 일치시킨 다음 볼트(260)과 너트(261)를 이용하여 이들이 체결고정되게 하므로서, 기둥(100) 측부에 사각파이프(200)를 신속용이하게 결합할 수 있게 된다.In other words, as shown in FIG. 1, the inclined cutout 212 is formed at the end of the square pipe 200 so that one side body 210 is exposed through the inclined cutout 212 and fastened on the exposed main body 210. Drill the ball 211, match the fastening hole 211 with the fastening hole 111 drilled in the fixing piece 110, and then using the bolts 260 and nuts 261 to fasten and fasten them, the column ( 100) it is possible to quickly combine the square pipe 200 to the side.

또한 도 4의 경우에는 기둥(100) 측부에 고정편(110)을 용접구성하지 않고, 볼트(121)와 너트(122)로 체결고정되게 하므로서 용접작업없이 사각파이프(200)를 기둥(100)에 체결고정할 수 있게 되므로 작업여건에 따라 선택하여 사용할 수 있게 된다.In addition, in the case of FIG. 4, the square pipe 200 is connected to the pillar 100 without welding by fixing the bolt 110 and the nut 122 without fixing the fixing piece 110 to the side of the pillar 100. Since the fastening can be fixed to, it can be selected and used according to the working conditions.

도 6의 경우에는 고정편(110)이 용접구성된 기둥(100) 측부에 사각파이프(200)를 체결고정함에 있어서, 사각파이프(200)의 단부에 경사절단부(210)를 구성하지 않고 본체(200) 상에 확개공(215)과 체결공(211)을 뚫고, 상기 확개공(215)을 통하여 볼트(260)를 끼워 사각파이프(200)의 체결공(211)과 고정편(110)의 체결공(111)을 관통되게 한 다음 너트(261)로 체결고정되게 할 수도 있다.In the case of FIG. 6, in the fastening and fixing the square pipe 200 to the side of the pillar 100 on which the fixing piece 110 is welded, the main body 200 does not constitute the inclined cut portion 210 at the end of the square pipe 200. ) And drills the expansion hole 215 and the fastening hole 211, and fastens the fastening hole 211 and the fixing piece 110 of the square pipe 200 by inserting the bolt 260 through the expansion hole 215. The ball 111 may be penetrated and then fastened with a nut 261.

도 7의 경우에는 기둥(100) 측면 상하부에 수직간(113)과 수평간(115)으로 구성된 고정편(110)을 볼트(212)로 체결고정하고, 동시에 고정편(110)에 구성된 수평간(115) 사이에 사각파이프(200)를 끼워 볼트(260)과 너트(261)로 체결고정되게 할 경우에도 기둥(100)이나, 사각파이프(200)에 용접부위없이 이들을 신속하고 용이하게 결합할 수 있게 된다.In the case of FIG. 7, the fixing piece 110 composed of the vertical groove 113 and the horizontal groove 115 is fastened and fastened by bolts 212 at the upper and lower sides of the pillar 100, and at the same time, the horizontal blade configured in the fixing piece 110. Even when the square pipe 200 is sandwiched between the 115 and the bolt 260 and the nut 261 are fastened and fastened, the pillar 100 or the square pipe 200 can be quickly and easily coupled to the square pipe 200 without welding. It becomes possible.

이상 설명한 바와 같이 본 발명은 물류창고나 공장건물, 쇼핑센타등과 같은 건축물을 시공함에 있어서, H빔이나 용접형강, P.E.B시스템, 혹은 사각골조와 같은 기둥측부에 고정편을 고정설치하고, 상기 고정편 상에 사각파이프를 신속용이하게 결합할 수 있게 구성하므로서, 건축물의 시공을 신속용이하게 할 뿐 아니라 사각파이프 사용에 따른 건축물의 외관을 미려하게 유지할 수 있게 되고, 또한 견고한 시 공을 기대할 수 있게 되는 등의 효과가 있는 것이다.As described above, in the present invention, when constructing a building such as a warehouse, a factory building, a shopping center, or the like, the fixing piece is fixedly installed at a column side such as an H beam, a welded steel, a PEB system, or a square frame, By constructing the square pipe on the side for quick and easy construction, not only can the construction of the building be quick and easy, but also the beautiful appearance of the building can be maintained by the use of the square pipe, and a solid construction can be expected. It will be effective.

Claims (4)

물류창고나 공장건물, 쇼핑센타등과 같은 건축물을 시공함에 있어서, H빔이나 용접형강, P.E.B시스템 혹은 사각골조등으로 기둥(100)을 설치하고, 상기 기둥(100) 측부에 체결공(111)이 뚫린 고정편(110)을 고정설치하되, 상기 고정편(110) 상에 본체(210)에 체결공(211)이 뚫린 사각파이프(200)를 위치시킨 다음 체결공(111)(211)을 관통하게 볼트(260)를 끼워 너트(261)로 체결고정되게 하므로서 기둥(100) 측부에 사각파이프(200)가 체결고정되게 하여서 됨을 특징으로 하는 조립식 건축물의 사각파이프 결합구조.In constructing a building such as a warehouse, a factory building, or a shopping center, a pillar 100 is installed by an H beam, a welded steel, a PEB system, or a square frame, and a fastening hole 111 is provided at a side of the pillar 100. The fixed fixing piece 110 is fixedly installed, but the square pipe 200 having the fastening hole 211 drilled in the main body 210 is placed on the fixing piece 110, and then the fastening holes 111 and 211 are disposed. The square pipe coupling structure of the prefabricated building, characterized in that the square pipe 200 is fastened and fixed to the side of the column 100 by inserting the bolt 260 to be fastened by the nut 261. 제1항에 있어서, 사각파이프(200) 단부를 경사지게 절단하여 경사절단부(212)를 구성하므로서 본체(210)에 뚫린 체결공(211)이 경사절단부(212)를 통하여 개방되게 하고, 상기 경사절단부(212)를 통하여 볼트(260)와 너트(261)가 체결고정될 수 있게 하여서 됨을 특징으로 하는 조립식 건축물의 사각파이프 결합구조.According to claim 1, the end of the square pipe 200 to be inclined cutting to form the inclined cut portion 212, so that the fastening hole 211 is opened through the inclined cut portion 212, the inclined cut portion 212, the inclined cut portion Square pipe coupling structure of the prefabricated building, characterized in that the bolt (260) and the nut (261) through the (212) to be fastened. 제1항에 있어서, 사각파이프(200) 단부에 구성된 본체(210) 상에 확개공(215)과 체결공(211)을 뚫어 구성하므로서, 체결공(211)이 확개공(215)을 통하여 개방되게 하고, 상기 확개공(215)을 통하여 볼트(260)와 너트(261)가 체결고정되게 하여서 됨을 특징으로 하는 조립식 건축물의 사각파이프 조립구조.The fastening hole 211 is opened through the expansion hole 215 by forming the expansion hole 215 and the fastening hole 211 on the main body 210 formed at the end of the square pipe 200. And the bolt 260 and the nut 261 are fastened and fastened through the extension hole 215. 제1항에 있어서, 기둥(100) 측부에 고정되는 고정편(110)은 수직간(113)과 수평간(115)으로 구성되게 하되, 상기 수직간(113)에는 관통공(114)이 뚫려지게 하고, 수평간(115)에는 체결공(111)이 뚫려지게 구성하므로서, 수직간(113)의 관통공(114)에 볼트(121)를 끼운 다음 너트(122)로 체결고정하여 고정편(110)이 기둥(100) 측부에 체결고정되게 하고, 상기 고정편(110)의 수평간(115)에 체결공(211)이 뚫린 사각파이프(200)를 위치시킨 다음 볼트(260)와 너트(261)로 체결고정되게 하여서 됨을 특징으로 하는 조립식 건축물의 사각파이프 조립구조.According to claim 1, The fixing piece 110 is fixed to the column 100 side to be composed of the vertical interval 113 and the horizontal interval 115, the through hole 114 is drilled through the vertical interval 113 The fastening hole 111 is formed in the horizontal space 115 so that the fastening hole 111 is inserted into the through hole 114 of the vertical space 113, and then the fastening hole is fixed by fastening with a nut 122. 110 to be fastened to the side of the pillar 100, and the square pipe 200 in which the fastening hole 211 is drilled is placed in the horizontal section 115 of the fixing piece 110, and then bolts 260 and nuts ( 261) square pipe assembly structure of a prefabricated building, characterized in that fastening is fixed.
KR1020050084738A 2005-09-12 2005-09-12 Assembly structure of square pipe for prefab building KR100712465B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050084738A KR100712465B1 (en) 2005-09-12 2005-09-12 Assembly structure of square pipe for prefab building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050084738A KR100712465B1 (en) 2005-09-12 2005-09-12 Assembly structure of square pipe for prefab building

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0026239U Division KR200402355Y1 (en) 2005-09-12 2005-09-12 Assembly structure of square pipe for prefab building

Publications (2)

Publication Number Publication Date
KR20070030013A true KR20070030013A (en) 2007-03-15
KR100712465B1 KR100712465B1 (en) 2007-05-02

Family

ID=38101925

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050084738A KR100712465B1 (en) 2005-09-12 2005-09-12 Assembly structure of square pipe for prefab building

Country Status (1)

Country Link
KR (1) KR100712465B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101506481B1 (en) * 2012-04-03 2015-03-27 채일수 Prefab building square pipe with firmess and simple assembling means

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102054432B1 (en) 2019-05-16 2019-12-10 임헌긍 Steel frame assembly and construction method of the same
CN112049252A (en) * 2020-09-09 2020-12-08 甘肃建投科技研发有限公司 Energy-consuming and shock-absorbing type assembled beam column node structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0674611B2 (en) * 1987-07-25 1994-09-21 栗山 寛 Structural material joining device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101506481B1 (en) * 2012-04-03 2015-03-27 채일수 Prefab building square pipe with firmess and simple assembling means

Also Published As

Publication number Publication date
KR100712465B1 (en) 2007-05-02

Similar Documents

Publication Publication Date Title
KR101975774B1 (en) Composite Girder Structure integrated with Cover Plate, Temporary Bridge using such Structure, and Constructing Method of such Temporary Bridge
KR100712465B1 (en) Assembly structure of square pipe for prefab building
JP2007032117A (en) Fastener
KR200402355Y1 (en) Assembly structure of square pipe for prefab building
JP4124073B2 (en) Wood fittings
JP2008014123A (en) Vertical lumber member installation hardware
KR100579702B1 (en) Architectural beam with differ materials
KR101506481B1 (en) Prefab building square pipe with firmess and simple assembling means
KR20040102500A (en) Compound Construction Material
JP2006322278A (en) Aseismatic reinforcement device
JP3477074B2 (en) Connection structure of horizontal members and vertical members on upper and lower floors
JP4696936B2 (en) Beam-column joint structure
JP5147552B2 (en) Junction structure used for portal wood frame
JP2005248487A (en) Reinforcing structure by splice round material for hollow steel pipe steel tower
JP4478102B2 (en) Through column structure
JP2001049741A (en) Wooden rigid frame
JP5314417B2 (en) Bonding hardware, metal fittings for bonding hardware, and wooden frame members
KR200323902Y1 (en) Compound Construction Material
JP3117009U (en) L-shaped corner hardware for wood joints
KR100975237B1 (en) A handrail for construction
JP5432326B2 (en) Reinforcing metal fittings for wooden buildings, reinforcing structure and reinforcing method
JP2002356917A (en) Joining hardware for wooden framework and joining structure using the same
JPH10311096A (en) Wood connecting metal fitting
JP3416757B2 (en) Noise barrier
JP2022051464A (en) Wall surface structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130404

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140520

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150310

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160310

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170310

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180406

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190326

Year of fee payment: 13