KR20050102552A - Constructing panel and constructing method using the same - Google Patents

Constructing panel and constructing method using the same Download PDF

Info

Publication number
KR20050102552A
KR20050102552A KR1020040027966A KR20040027966A KR20050102552A KR 20050102552 A KR20050102552 A KR 20050102552A KR 1020040027966 A KR1020040027966 A KR 1020040027966A KR 20040027966 A KR20040027966 A KR 20040027966A KR 20050102552 A KR20050102552 A KR 20050102552A
Authority
KR
South Korea
Prior art keywords
thickness
panel
polyurethane foam
tube
building panel
Prior art date
Application number
KR1020040027966A
Other languages
Korean (ko)
Inventor
김중삼
Original Assignee
김중삼
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김중삼 filed Critical 김중삼
Priority to KR1020040027966A priority Critical patent/KR20050102552A/en
Publication of KR20050102552A publication Critical patent/KR20050102552A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/26Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups
    • E04C2/284Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups at least one of the materials being insulating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/04Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)

Abstract

본 발명은 건축용 패널(Panel) 및 이것을 이용한 시공방법에 관한 것으로서, 콘크리트(Concrete)를 이용한 벽체의 시공 뿐만 아니라, 천정의 시공에도 활용할 수 있고, 상기 시공시 거푸집을 필요로 하지 않고 간단하게 시공할 수 있도록 하는 것을 목적으로 한다. The present invention relates to a building panel (Panel) and a construction method using the same, and can be used not only for the construction of walls using concrete, but also for the construction of the ceiling, and can be easily installed without the need for formwork during the construction. The purpose is to make it possible.

본 발명의 건축용 패널은, 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱(Embossing) 구멍(24)이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔(Beam, 20)과; 상기 각 엠보싱 구멍에 접합되는 제1두께유지관(30)과; 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(Wire Net, 40)와; 그리고, 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼(Polyurethane Foam, 50)을 포함하여 이루어진다. 따라서, 철근 골조(70)를 설치한 후, 그 양쪽에 본 발명의 건축용 패널(10)을 각각 배치하고, 상기 엠보싱 구멍, 제1두께유지관 및 제2두께유지관을 통해 볼트(90) 및 너트(92)를 체결한 다음, 패널(10)들 사이의 공간에 콘크리트(80)를 타설 및 양성함으로써, 간단하게 벽체를 시공완료할 수 있다. In the building panel of the present invention, both ends in the longitudinal direction are bent inwardly, and protrusions 22 are formed along the longitudinal direction in the center by recesses, and a plurality of embossing holes 24 are formed in the protrusions. A plurality of beams 20 arranged side by side at predetermined intervals; A first thickness retaining tube (30) joined to each of the embossing holes; A wire net (40) bonded over the first thickness holding tubes; And, it comprises a polyurethane foam (Polyurethane Foam, 50) foamed from the beam to the first thickness maintenance tube. Therefore, after installing the reinforcing frame 70, the building panels 10 of the present invention are disposed on both sides thereof, and the bolts 90 and the through-embossed holes, the first thickness holding pipes, and the second thickness holding pipes are disposed. After fastening the nut 92, the concrete 80 can be simply completed by pouring and nurturing the concrete 80 in the space between the panels 10. FIG.

Description

건축용 패널 및 이것을 이용한 시공방법{CONSTRUCTING PANEL AND CONSTRUCTING METHOD USING THE SAME}Building panel and construction method using the same {CONSTRUCTING PANEL AND CONSTRUCTING METHOD USING THE SAME}

본 발명은 건축용 패널(Panel) 및 이것을 이용한 시공방법에 관한 것으로서, 콘크리트(Concrete)를 이용한 벽체나 천정 등의 시공시 거푸집이 불필요하며, 간단하게 시공할 수 있는 건축용 패널 및 이것을 이용한 시공방법에 관한 것이다. The present invention relates to a building panel (Panel) and a construction method using the same, and to the construction panel and the construction method using the same is not necessary, the formwork is required when constructing a wall or ceiling using concrete (Concrete) will be.

콘크리트를 이용하여 벽체나 천정을 시공할 때에는, 일반적으로 합판, 철판, 각목 등의 재료로 한 거푸집으로 형틀을 만들고, 형틀 내부에 철근으로 배근공사를 한 다음, 콘크리트를 타설하게 된다. 그리고, 콘크리트가 양생된 후, 상기 거푸집을 제거하게 된다. 따라서, 형틀을 만드는 데 시간과 비용이 많이 들 뿐만 아니라, 형틀을 제거하는 데에도 시간과 비용이 많이 들고, 또 다량의 건축폐기물을 양산하게 된다. When constructing walls or ceilings using concrete, molds are generally made of formwork made of plywood, steel plates, or lumber, and reinforcement works are carried out with reinforcing bars inside the molds before concrete is poured. Then, after the concrete is cured, the formwork is removed. Therefore, not only is it time-consuming and expensive to make the mold, but it is also time-consuming and expensive to remove the mold, and mass-produces a large amount of construction waste.

이러한 점을 고려하여, 한국 등록실용신안 제172351호에 개시된 바와 같은 패널이 제안된 바 있다. 상기 패널은, 스티로폼의 일측면에 와이어메쉬(Wire-mesh)를 모르타르(Mortar)로 접착시켜 이루어진 것이다. 따라서, 2매의 패널 사이에 콘크리트를 타설하여 양생시킨 후, 패널의 외면을 마감재로 처리하여 벽체를 완성하면, 전술한 바와 같은 문제점이 해소될 수 있다. In view of this, a panel as disclosed in Korean Utility Model Registration No. 172351 has been proposed. The panel is made by bonding a wire mesh to one side of the styrofoam with mortar. Therefore, after the concrete is poured between the two panels to cure, the outer surface of the panel is treated with a finishing material to complete the wall, the problem as described above can be solved.

그러나, 상기한 선행기술에 있어서는, 모르타르를 이용하여 패널을 제조함으로써, 제조시간이 많이 들고, 대량생산이 어려우며, 운반 등의 취급시 양생된 모르타르가 깨져 패널이 손상되기 쉽다. 또한, 모르타르로 인하여 패널의 중량이 커져, 취급이 힘들게 된다. 또한, 벽체 시공시 2매의 패널을 체결수단으로 고정할 때, 패널에 구멍을 뚫는 작업이 수행되어야 하는 문제점도 있다. 또한, 시공된 벽체의 외벽면을, 예컨대 대리석 등의 고중량 외장재로 마감하고자 할 경우에, 모르타르층의 강도가 약하여 시공이 불가능한 문제점이 있다. However, in the above-mentioned prior art, by manufacturing a panel using mortar, it takes a lot of manufacturing time, it is difficult to mass-produce, and the hardened mortar at the time of handling, such as transportation, is easily broken and the panel is damaged. In addition, the mortar increases the weight of the panel, making handling difficult. In addition, when fixing the two panels in the wall construction by the fastening means, there is also a problem that the operation of punching the panel should be performed. In addition, when the outer wall surface of the constructed wall is to be finished with a heavy weight packaging material such as marble, for example, there is a problem that the strength of the mortar layer is weak and the construction is impossible.

본 발명은 상기한 바와 같은 종래 문제점을 고려하여 이루어진 것으로서, 콘크리트를 이용한 벽체의 시공 뿐만 아니라, 천정의 시공에도 활용할 수 있고, 상기 시공시 거푸집을 필요로 하지 않고도 간단하게 시공할 수 있도록 하는 것을 목적으로 한다. The present invention has been made in consideration of the conventional problems as described above, and can be used not only for the construction of the wall using concrete, but also for the construction of the ceiling, and to provide a simple construction without the need for formwork during the construction. It is done.

본 발명의 다른 목적은 벽체나 천정의 시공후, 다양하게 활용할 수 있는 건축용 패널을 제공하는 것이다. Another object of the present invention is to provide a building panel that can be variously used after the construction of the wall or ceiling.

상기 목적을 달성하기 위하여, 본 발명에 따른 건축용 패널은, 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱(Embossing) 구멍이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔(Beam)과; 상기 각 엠보싱 구멍에 접합되는 제1두께유지관과; 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(Wire Net)와; 그리고, 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼(Polyurethane Foam)을 포함하여 이루어지는 것을 특징으로 한다. In order to achieve the above object, the building panel according to the present invention, both ends in the longitudinal direction is bent inward, the projection is formed along the longitudinal direction in the center by the concave, a plurality of embossing holes projected on the projection A plurality of beams formed and arranged side by side at predetermined intervals; A first thickness retaining tube joined to each of the embossed holes; A wire net joined over the first thickness holding tubes; And it is characterized in that it comprises a polyurethane foam (Polyurethane Foam) that is foamed from the beam to the first thickness maintenance tube.

또한, 상기 폴리우레탄폼의 좌/우측면에는 서로 대응하는 결합홈 및 결합돌기가 차례로 형성되는 것이 바람직하다. In addition, it is preferable that coupling grooves and coupling protrusions corresponding to each other are sequentially formed on the left / right sides of the polyurethane foam.

또한, 상기 패널의 외면쪽에, 폴리우레탄폼 발포에 의하여 석고보드(Board)가 더 접합될 수 있다. In addition, a gypsum board may be further bonded to the outer surface side of the panel by polyurethane foam foaming.

또한, 본 발명에 따른 건축용 패널을 이용한 시공방법은, 철근 골조를 수직으로 설치하는 단계와; 상기 철근 골조를 따라 소정의 간격으로 제2두께유지관을 설치하는 단계와; 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트와, 그리고 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼을 가지는 패널들을, 상기 제1두께유지관들이 제2두께유지관들과 일치하도록 상기 철근 골조의 양쪽에 배치하는 단계와; 상기 제1두께유지관들과 제2두께유지관을 볼트(Bolt) 및 너트(Nut)로 체결함으로써, 서로 대응하는 패널들을 고정하는 단계와; 그리고, 상기 패널들 사이에 콘크리트를 타설 및 양생하는 단계;를 포함하여 이루어지는 것을 특징으로 한다. In addition, the construction method using the building panel according to the present invention comprises the steps of: installing the reinforcing bar vertically; Installing a second thickness maintaining tube at predetermined intervals along the reinforcing steel frame; A plurality of beams in which both ends in the longitudinal direction are bent inwardly, and protrusions are formed along the longitudinal direction in the center by recesses, and a plurality of embossed holes are formed in the protrusions, and arranged side by side at predetermined intervals; Panels having a first thickness retaining tube bonded to an embossing hole, a wire net bonded over the first thickness retaining tubes, and polyurethane foam foamed from the beam to the first thickness retaining tube, Placing the first thickness retainers on both sides of the reinforcing steel frame so as to coincide with the second thickness retainers; Fixing the panels corresponding to each other by fastening the first thickness retaining tubes and the second thickness maintaining tubes with bolts and nuts; And, placing and curing the concrete between the panels; characterized in that it comprises a.

이 시공방법에 있어서, 좌우로 이어지는 패널들의 고정상태가 더욱 견고해질 수 있도록 하기 위하여, 좌우로 이어지는 패널들에 결합된 서로 대응하는 제2두께유지관들은 양쪽에 고리가 형성된 타이 바(Tie Bar)로 연결되는 것이 바람직하다. In this construction method, in order that the fixed state of the panels leading to the left and right can be further strengthened, the corresponding second thickness retaining tubes coupled to the panels leading to the left and right are formed with tie bars formed with rings on both sides. It is preferable to be connected to.

또한, 콘크리트가 양생된 후, 상기 볼트 및 너트를 푼 다음, 수직부에 구멍이 형성된 L자형 브래킷(Bracket)을, 건물 외벽을 이루는 패널의 엠보싱 구멍쪽에 상기 볼트 및 너트로 체결하고, 상기 L자형 브래킷의 수평부에 외장재를 지지시키는 단계가 더 포함될 수 있다. After the curing of the concrete, the bolts and nuts are loosened, and then an L-shaped bracket having a hole formed in a vertical portion is fastened with the bolts and nuts to the embossed hole of the panel forming the building wall, and the L-shaped. Supporting the exterior member in the horizontal portion of the bracket may be further included.

또한, 상기 패널들중 건물의 내측에 배치되는 패널의 외면쪽에, 폴리우레탄폼의 발포에 의하여 석고보드가 접합된 것이 사용될 수 있다. In addition, a gypsum board is bonded to the outer surface of the panel disposed inside the building of the panel by the foaming of polyurethane foam.

또한, 상기 패널의 외면쪽에, 폴리우레탄폼의 발포에 의하여 석고보드가 접합된 것이 사용될 수 있다. In addition, the gypsum board is bonded to the outer surface side of the panel by the foam of polyurethane foam can be used.

또한, 본 발명에 따른 건축용 패널을 이용한 시공방법은, 철근 골조를 수직으로 설치하는 단계와; 상기 철근 골조를 따라 소정의 간격으로 제2두께유지관을 설치하는 단계와; 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트와, 그리고 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼을 가지는 패널들을, 상기 제1두께유지관이 제2두께유지관과 일치하도록 상기 철근 골조의 한 쪽에 배치하는 단계와; 내면에 박리소재가 덮인 판재를 상기 철근 골조의 다른 쪽에 배치하는 단계와; 상기 제1두께유지관과 제2두께유지관을 통하여, 패널과 판재를 볼트 및 너트로 체결함으로써, 서로 대응하는 패널과 판재를 고정하는 단계와; 상기 패널 및 판재 사이에 콘크리트를 타설 및 양생하는 단계와; 그리고, 상기 볼트 및 너트를 풀어, 판재 및 박리소재를 제거하는 단계를 포함하여 이루어지는 것을 특징으로 한다. In addition, the construction method using the building panel according to the present invention comprises the steps of: installing the reinforcing bar vertically; Installing a second thickness maintaining tube at predetermined intervals along the reinforcing steel frame; A plurality of beams in which both ends in the longitudinal direction are bent inwardly, and protrusions are formed along the longitudinal direction in the center by recesses, and a plurality of embossed holes are formed in the protrusions, and arranged side by side at predetermined intervals; Panels having a first thickness retaining tube bonded to an embossing hole, a wire net bonded over the first thickness retaining tubes, and polyurethane foam foamed from the beam to the first thickness retaining tube, Arranging on one side of the reinforcing bar frame such that the first thickness retaining tube coincides with the second thickness retaining tube; Disposing a plate covered with a peeling material on an inner surface of the reinforcing steel frame; Fixing the panel and the plate corresponding to each other by fastening the panel and the plate with bolts and nuts through the first and second thickness holding tubes; Placing and curing concrete between the panel and the plate; And, by loosening the bolt and nut, characterized in that it comprises a step of removing the plate and peeling material.

이 시공방법에 있어서도, 상기 패널의 외면쪽에, 폴리우레탄폼의 발포에 의하여 석고보드가 접합된 것이 사용될 수 있다. Also in this construction method, a gypsum board bonded to the outer surface side of the panel by foaming polyurethane foam can be used.

또한, 본 발명에 따른 건축용 패널을 이용한 시공방법은, 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트와, 그리고 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼을 가지는 패널들을 수평으로 설치하는 단계와; 상기 패널들의 상부에 철근 골조를 수평으로 설치하는 단계와; 상기 철근 골조에 콘크리트를 타설하여 양생시키는 단계;를 포함하여 이루어진다. In addition, in the construction method using the building panel according to the present invention, both ends in the longitudinal direction is bent inward, the projection is formed along the longitudinal direction in the center by the concave, a plurality of embossed holes are formed in the projection, the predetermined A plurality of beams arranged side by side at intervals of: a first thickness retaining tube joined to each of the embossing holes, a wire net joined over the first thickness retaining tubes; and a first thickness retaining tube from the beam Horizontally installing the panels having the polyurethane foam to be foamed up to; Horizontally installing a reinforcing bar frame on top of the panels; And curing the concrete by pouring the reinforcing frame.

이 시공방법에 있어서, 콘크리트가 양생된 후, 상단에 구멍이 형성된 유틸리티(Utility) 설비용 서포트(Support)를, 볼트로 엠보싱 구멍쪽에 체결하고, 상기 서포트의 하단에 천정재 부착용 천정프레임을 설치하는 단계가 더 포함될 수 있다. In this construction method, after the concrete is cured, a support for utility equipment having a hole formed at the upper end thereof is fastened to the embossed hole with a bolt, and a ceiling frame for attaching the ceiling material is installed at the lower end of the support. Steps may be further included.

또한, 상기 패널의 저면쪽에, 폴리우레탄폼의 발포에 의하여 석고보드가 접합된 것이 사용될 수 있다. In addition, the gypsum board is bonded to the bottom of the panel by the foam of polyurethane foam can be used.

또한, 콘크리트가 양생된 후, 천정프레임이 볼트로 엠보싱 구멍쪽에 체결되고, 천정프레임들 사이에는 천정프레임과 직교하도록, 상하로 요철구조로 굴곡된 데크 플레이트(Deck Plate)가 설치될 수 있다. In addition, after the curing of the concrete, the ceiling frame is fastened to the embossed hole side with a bolt, a deck plate bent in a concave-convex structure up and down so as to be orthogonal to the ceiling frame between the ceiling frames may be installed.

본 발명의 특징 및 이점들은 첨부도면에 의거한 다음의 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는, 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. The features and advantages of the present invention will become more apparent from the following detailed description based on the accompanying drawings. Prior to this, the terms or words used in the present specification and claims are based on the principle that the inventor can appropriately define the concept of terms in order to explain the invention in the best way. It should be interpreted as meanings and concepts corresponding to

도 1에 도시된 바와 같이, 본 발명에 따른 건축용 패널(10)은, 다수의 빔(20)과, 다수의 제1두께유지관(30)과, 와이어 네트(40)와, 그리고 폴리우레탄폼(50)이, 발포성형에 의하여 일체로 접합되어 이루어진다. As shown in FIG. 1, the building panel 10 according to the present invention includes a plurality of beams 20, a plurality of first thickness maintaining tubes 30, a wire net 40, and polyurethane foam. 50 is integrally joined by foam molding.

상기 빔(20)은, 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되어 이루어지며, 도 2에 도시된 바와 같이, 상기 돌출부(22)에 다수의 엠보싱 구멍(24)이 돌출형성되어 있다. 상기 각 엠보싱 구멍(24)에는 제1두께유지관(30)이 접합된다. 이 제1두께유지관(30)은 폴리우레탄폼(50)의 두께를 규정하는 기능을 한다. The beam 20, both ends in the longitudinal direction is bent inward, the projection 22 is formed by the concave in the longitudinal direction in the center, as shown in Figure 2, a plurality of the projection 22 The embossed hole 24 is protruded. The first thickness maintaining tube 30 is joined to each of the embossed holes 24. The first thickness maintaining tube 30 functions to define the thickness of the polyurethane foam 50.

상기 엠보싱 구멍(24)은, 예컨대 3∼5mm 정도 돌출되고, 이 엠보싱 구멍(24)의 돌출된 부분 둘레로 제1두께유지관(30)의 일단이 끼워져 용접될 수 있다. 상기 빔(20)은 아연도강판으로 절곡형성되는 것이 바람직하다. The embossed hole 24 is protruded, for example, about 3 to 5 mm, and one end of the first thickness holding tube 30 can be inserted and welded around the protruding portion of the embossed hole 24. The beam 20 is preferably bent to a galvanized steel sheet.

빔의 다른 형태로, 도 3에 도시된 바와 같이, 상기 돌출부(22)의 양쪽 가장자리로부터 빔(20)의 안쪽방향으로 더 연장되어 바깥으로 굴곡되는 한 쌍의 돌출리브(Rib, 26)를 가진 것이 채용될 수 있다. In another form of the beam, as shown in FIG. 3, there is a pair of protruding ribs (Rib) 26 extending further inwardly of the beam 20 from both edges of the protrusion 22 to bend outwardly. May be employed.

와이어 네트(40)는 격자형으로 이루어져, 상기 제1두께유지관(30)들에 걸쳐 접합된다. 예컨대, 와이어 네트(40)는 제1두께유지관(30)의 끝단에 용접될 수 있을 뿐만 아니라, 제1두께유지관(30)의 중간부에 용접될 수 있다. 상기 와이어 네트(40)는 아연도강선으로 이루어지는 것이 바람직하다. The wire net 40 has a lattice shape and is joined over the first thickness maintaining tubes 30. For example, the wire net 40 may not only be welded to the end of the first thickness maintaining tube 30, but may be welded to an intermediate portion of the first thickness maintaining tube 30. The wire net 40 is preferably made of galvanized steel wire.

그리고, 폴리우레탄폼(50)은 상기 빔(20)으로부터 제1두께유지관(30)까지 발포성형된다. 따라서, 와이어 네트(40)가 제1두께유지관(30)의 끝단에 용접되어 있을 경우에는, 와이어 네트(40)는 폴리우레탄폼(50)의 외면쪽을 보강하게 되고, 와이어 네트(40)가 제1두께유지관(30)의 중간부에 용접되어 있을 경우에는, 와이어 네트(40)는 폴리우레탄폼(50)에 매립된 상태로 폴리우레탄폼(50)을 보강하게 된다. In addition, the polyurethane foam 50 is foamed from the beam 20 to the first thickness maintaining tube 30. Therefore, when the wire net 40 is welded to the end of the first thickness maintaining tube 30, the wire net 40 reinforces the outer surface side of the polyurethane foam 50, the wire net 40 When is welded to the middle portion of the first thickness maintenance tube 30, the wire net 40 is to reinforce the polyurethane foam 50 in a state embedded in the polyurethane foam (50).

상기 폴리우레탄폼(50)의 좌/우측면에는, 본 발명에 따른 건축용 패널(10)들을 좌우로 연결하기 위하여, 도 1에 도시된 바와 같이, 서로 대응하는 결합홈(52) 및 결합돌기(54)가 차례로 형성되는 것이 바람직하다. On the left / right side of the polyurethane foam 50, in order to connect the building panels 10 according to the present invention from side to side, as shown in Figure 1, the coupling groove 52 and the coupling protrusion 54 corresponding to each other. ) Is preferably formed one after the other.

또한, 상기 패널(10)의 외면쪽(즉, 빔(20)들쪽)에, 도 4에 도시된 바와 같이, 폴리우레탄폼(50) 발포에 의하여 석고보드(60)가 더 접합될 수 있다. 이 경우, 상기 석고보드(60)에는 엠보싱 구멍(24)과 대응하는 구멍(62)이 형성되는 것이 바람직하다. In addition, as shown in FIG. 4, the gypsum board 60 may be further bonded to the outer surface side of the panel 10 (that is, toward the beams 20) by foaming the polyurethane foam 50. In this case, the gypsum board 60 is preferably formed with a hole 62 corresponding to the embossed hole 24.

다음에, 상기한 바와 같이 구성된 본 발명에 따른 건축용 패널(10)을 공장에서 제조하는 제조과정에 대하여 설명한다. Next, a manufacturing process of manufacturing a building panel 10 according to the present invention configured as described above in a factory will be described.

먼저, 와이어들을 격자형으로 배치하여 서로 교차하는 부분을 용접함으로써, 와이어 네트(40)를 제작한다. 상기 와이어 네트(40)는, 공장에서 와이어 네트를 규격화하여 생산할 수 있는 소정의 지그 및 용접장치를 제작하여 일시에 용접하는 것이 바람직하다. First, the wire net 40 is manufactured by arranging the wires in a lattice shape and welding the portions that cross each other. The wire net 40 is preferably welded at a time by manufacturing a predetermined jig and welding apparatus that can be produced by standardizing the wire net in the factory.

또한, 성형된 빔(20)의 각 엠보싱 구멍(24)에 제1두께유지관(30)을 차례로 용접하고, 이 제1두께유지관(30)에 상기 와이어 네트(40)를 도 5에 도시된 바와 같이 용접하여 조립체를 만든다. 상기 조립체도 와이어 네트(40)를 제작하는 방법과 동일하게 공장에서 규격화하여 생산하는 것이 바람직하다.Further, the first thickness holding tube 30 is welded in turn to each of the embossed holes 24 of the formed beam 20, and the wire net 40 is shown in FIG. 5 in the first thickness holding tube 30. The assembly is made by welding as shown. The assembly is also preferably produced by standardizing in the factory in the same manner as the wire net 40 manufacturing method.

다음에, 금형에 상기 조립체를 투입하고, 금형에 폴리우레탄 원료를 주입하여 발포시킴으로써, 본 발명에 따른 건축용 패널(10)의 제조를 완료한다. Next, the assembly is put into a mold, a polyurethane raw material is injected into the mold, and foamed, thereby completing the manufacture of the building panel 10 according to the present invention.

외면에 석고보드(60)가 설치된 건축용 패널(10)(도 4 참조)을 제조할 경우에는, 금형에 석고보드(60)를 투입하고, 상기 석고보드(60) 위에 상기 조립체를 놓은 다음, 발포과정을 거침으로써, 석고보드(60)가 부착된 건축용 패널(10)을 제조할 수 있다. 따라서, 접착제를 사용하여 석고보드(60)를 부착할 필요가 없는 이점이 있다. 이 경우, 현장시공시 석고보드(60)에 구멍을 내는 일을 방지하기 위하여, 엠보싱 구멍(24)들과 대응하는 구멍(62)들이 형성된 석고보드(60)를 이용하여 발포과정을 거치는 것이 바람직하다. When manufacturing a building panel 10 (see FIG. 4) having a gypsum board 60 installed on an outer surface thereof, a gypsum board 60 is placed in a mold, the assembly is placed on the gypsum board 60, and then foamed. By going through the process, the building panel 10 to which the gypsum board 60 is attached can be manufactured. Therefore, there is an advantage that it is not necessary to attach the gypsum board 60 using an adhesive. In this case, it is preferable to go through the foaming process using the gypsum board 60 formed with embossed holes 24 and the corresponding holes 62 in order to prevent the hole in the gypsum board 60 at the time of construction site Do.

다음의 실시예들을 통하여, 상기한 바와 같이 구성된 본 발명에 따른 건축용 패널(10)을 이용하여 건물의 벽체나 천정을 시공하는 방법에 대하여 설명한다. Through the following embodiments, a method for constructing the wall or ceiling of a building using the building panel 10 according to the present invention configured as described above will be described.

<실시예 1><Example 1>

본 실시예에 따른 시공방법은 건물의 벽체를 시공하는 방법에 대한 것이다. The construction method according to the present embodiment relates to a method for constructing a wall of a building.

도 6에 도시된 바와 같이, 벽체 설계에 따라 철근 골조(70)를 수직으로 설치한다. 철근 골조(70)를 설치하는 방법으로는, 묶음선으로 수평철근(72) 및 수직철근(74)의 교차부를 묶는 방법과, 도 7에 도시된 바와 같이, 2개의 스냅링(77, 78)이 서로 반대방향에서 직교하도록 일체로 형성된 클립(76)으로 수평철근(72) 및 수직철근(74)의 교차부를 결속하는 방법 등이 채용될 수 있다. As shown in Figure 6, the reinforcing bar frame 70 is installed vertically according to the wall design. As a method of installing the reinforcing frame 70, a method of tying the intersection of the horizontal reinforcing bar 72 and the vertical reinforcing bar 74 with a bundle line, and two snap rings 77 and 78, as shown in FIG. A method of binding the intersections of the horizontal rebar 72 and the vertical rebar 74 with the clip 76 integrally formed to be orthogonal to each other in the opposite direction may be employed.

상기 철근 골조(70)를 설치할 때, 벽체의 좌우연장 또는 상부연장이 필요한 경우, 연장 철근 골조(70)를 연결할 수 있도록, 도 8에 도시된 바와 같이, 후술하는 패널(10)의 좌우측 또는 상부쪽으로 철근(72, 74)이 돌출되도록 철근 골조(70)를 설치하는 것이 바람직하다. When installing the reinforcing bar frame 70, when the left and right or upper extension of the wall is required, as shown in Figure 8, so as to connect the extended reinforcing bar frame 70, the left and right or the top of the panel 10 to be described later It is preferable to install the reinforcing frame 70 so that the reinforcing bars 72 and 74 protrude toward the side.

다음에, 상기 철근 골조(70)를 따라 소정의 간격으로 제2두께유지관(79)을 설치한다. 이 제2두께유지관(79)은 도 6에 도시된 바와 같이, 후술하는 콘크리트(80)의 두께를 규정하는 기능을 한다. 즉, 상기 제2두께유지관(79)의 길이만큼의 두께로 콘크리트(80)가 타설되는 것이다. 상기 철근 골조(70)에 제2두께유지관(79)을 설치하는 방법으로는, 철근 골조(70)에 제2두께유지관(79)을 용접하는 방법이 채용될 수 있다. Next, along the reinforcing frame 70, a second thickness maintaining tube 79 is provided at predetermined intervals. As shown in Fig. 6, the second thickness maintaining tube 79 serves to define the thickness of the concrete 80 to be described later. That is, the concrete 80 is poured to the thickness of the length of the second thickness maintenance tube (79). As a method of installing the second thickness maintenance tube 79 on the rebar frame 70, a method of welding the second thickness maintenance tube 79 to the rebar frame 70 may be employed.

물론, 상기한 바와 같은 철근 골조(70)와, 제2두께유지관(79)의 설치과정은 제조공장에서 미리 패널(10)에 맞추어 제조될 수 있으며, 따라서 현장에서는 운반되어 온 철근 골조(70) 및 제2두께유지관(79) 조립체를 그대로 설치하기만 하면 된다. Of course, the installation process of the reinforcing bar frame 70 and the second thickness maintaining tube 79 as described above can be manufactured in advance in accordance with the panel 10 in the manufacturing plant, and thus the reinforcing bar frame 70 has been transported in the field ) And the second thickness retaining tube 79 assembly may be installed as it is.

다음에, 빔(20), 제1두께유지관(30), 와이어 네트(40) 및 폴리우레탄폼(50)으로 이루어진 패널(10)들을, 상기 제1두께유지관(30)들이 제2두께유지관(79)들과 일치하도록, 상기 철근 골조(70)의 양쪽에 배치한다. 이 경우, 좌우로 이어지는 패널(10)들은 서로 대응하는 결합홈(52)(도 1 참조)에 결합돌기(54)(도 1 참조)가 삽입되므로, 패널(10)들을 손쉽게 배치할 수 있다. 직선상으로 서로 이웃하는 패널(10)들을 연결할 경우, 서로 접촉하는 끝단부 모서리는 도 9에 도시된 바와 같이, 체결공(102)들이 형성된 직선형 채널(Channel)(100)로 연결한다. 또한, 도 10에 도시된 바와 같이, 서로 교차하는 패널(10)을 연결할 경우에는 도 10에 도시된 바와 같이, 서로 접촉하는 모서리부를 체결공(112)들이 형성된 앵글형 채널(110)로 연결한다. 상기 채널(100, 110)은, 예컨대 스크류(114)로 패널(10)에 고정될 수 있다. Next, the panels 10 made of the beam 20, the first thickness holding tube 30, the wire net 40, and the polyurethane foam 50 are formed. The first thickness holding tubes 30 are formed of a second thickness. It is arranged on both sides of the reinforcing bar 70 to coincide with the retaining tubes 79. In this case, the panels 10 extending from side to side are inserted into the coupling grooves 54 (see FIG. 1) corresponding to each other, so that the panels 10 may be easily disposed. When the adjacent panels 10 are connected to each other in a straight line, the end edges contacting each other are connected to a straight channel 100 in which the fastening holes 102 are formed, as shown in FIG. 9. In addition, as shown in FIG. 10, when connecting the panels 10 that cross each other, as shown in FIG. 10, the corners contacting each other are connected to the angle channel 110 in which the fastening holes 112 are formed. The channels 100, 110 may be fixed to the panel 10 with, for example, screws 114.

다음에, 도 6에 도시된 바와 같이, 상기 제1두께유지관(30)들과 제2두께유지관(79)을 볼트(90) 및 너트(92)로 체결함으로써, 서로 대응하는 패널(10)들을 고정한다. 상기 너트(92)로, 도시된 바와 같은 일반적인 너트 뿐만 아니라 캡너트(Cap Nut)가 채용될 수 있다. 또한, 이 너트(92)는 엠보싱 구멍(24)쪽에 용접될 수 있고, 이 경우 패널(10)의 제조과정중 발포과정 전에 너트(92)가 엠보싱 구멍(24)쪽에 용접되는 것이 바람직하다. Next, as shown in FIG. 6, the first and second thickness maintaining tubes 30 and 79 are fastened with bolts 90 and nuts 92 to thereby correspond to each other. )). As the nut 92, a cap nut as well as a general nut as shown may be employed. The nut 92 may also be welded to the embossed hole 24, in which case it is preferred that the nut 92 be welded to the embossed hole 24 prior to the foaming process during the manufacturing of the panel 10.

다음에, 좌우로 이어지는 패널(10)들의 고정상태가 더욱 견고해질 수 있도록 하기 위하여, 좌우로 이어지는 패널(10)들에 결합된 서로 대응하는 제2두께유지관(79)들은, 도 11에 도시된 바와 같이, 양쪽에 고리(122)가 각각 형성된 타이 바(120)로 연결되는 것이 바람직하다. 상기 타이 바(120)는 철근으로 형성될 수 있다. Next, in order to make the fixing state of the panels 10 leading to the right and left more secure, the second thickness retaining tubes 79 corresponding to each other coupled to the panels 10 leading to the left and right are shown in FIG. 11. As shown, it is preferable that the ring 122 is formed on each side of the tie bar 120, respectively. The tie bar 120 may be formed of rebar.

다음에, 상기 패널(10)들 사이(즉, 철근 골조(70) 설치 부분)에 콘크리트(80)를 타설 및 양생함으로써 벽체를 완성한다. Next, the wall is completed by pouring and curing the concrete 80 between the panels 10 (that is, the reinforcing frame 70 installation portion).

이 시공방법에 있어서, 콘크리트(80)가 양생된 후, 상기 볼트(90) 및 너트(92)를 푼 다음, 도 12에 도시된 바와 같이, 수직부(132)에 구멍(134)이 형성된 L자형 브래킷(130)을, 건물 외벽을 이루는 패널(10)의 엠보싱 구멍(24)쪽에 상기 볼트(90) 및 너트(92)로 체결하고, 상기 L자형 브래킷(130)의 수평부(136)에 외장재(150)를 지지시키는 단계가 더 포함될 수 있다. 외장재(150)로는 다른 소재에 비하여 상대적으로 고중량인 대리석 등의 소재가 채용될 수 있다. In this construction method, after the concrete 80 is cured, the bolt 90 and the nut 92 are loosened, and then as shown in FIG. 12, the hole 134 is formed in the vertical portion 132. The female bracket 130 is fastened to the embossed hole 24 of the panel 10 forming the outer wall of the building with the bolt 90 and the nut 92, and to the horizontal portion 136 of the L-shaped bracket 130. Supporting the exterior member 150 may be further included. As the exterior material 150, a material such as marble having a relatively high weight than other materials may be employed.

<실시예 2><Example 2>

본 실시예의 시공방법은 건물의 벽체를 시공하는 방법으로서, 도 13에 도시된 바와 같이, 전술한 실시예 1에 있어서, 패널(10)로서, 빔(20), 제1두께유지관(30), 와이어 네트(40), 폴리우레탄폼(50) 및 석고보드(60)로 이루어진 것이 사용된다는 것을 제외하고, 실시예 1과 모두 동일하게 이루어져 있다. The construction method of the present embodiment is a method of constructing a wall of a building, as shown in FIG. 13, in the above-described Embodiment 1, as the panel 10, the beam 20, the first thickness maintaining tube 30. It is made in the same manner as in Example 1, except that the wire net 40, polyurethane foam 50 and gypsum board 60 is used.

이 예에 있어서는, 외장재(150) 설치 단계를 별도로 수행하지 않아도 좋다. 즉, 별도로 내/외장재(150)를 설치할 필요없이 석고보드(60)가 내/외장재(150)의 기능을 할 수 있다. In this example, it is not necessary to separately perform the step of installing the exterior material 150. That is, the gypsum board 60 may function as the interior / exterior material 150 without the need to separately install the interior / exterior material 150.

<실시예 3><Example 3>

본 실시예의 시공방법은 건물의 벽체를 시공하는 방법에 대한 것으로서, 예컨대 건물의 외벽면에 콘크리트(80)를 그대로 노출시키고자 할 때 채용될 수 있는 시공방법이다. The construction method of the present embodiment relates to a method for constructing a wall of a building, and is, for example, a construction method that can be employed when the concrete 80 is to be exposed to the outer wall of the building as it is.

즉, 도 14에 도시된 바와 같이, 실시예 1에 있어서, 철근 골조(70) 및 제2두께유지관(79)을 설치한 후에, 빔(20), 제1두께유지관(30), 와이어 네트(40) 및 폴리우레탄폼(50)으로 이루어진 패널(10)을, 상기 제1두께유지관(30)이 제2두께유지관(79)과 일치하도록, 상기 철근 골조(70)의 한 쪽(즉, 건물 내측)에 배치한다. That is, as shown in FIG. 14, in Example 1, after installing the reinforced frame 70 and the 2nd thickness maintenance pipe 79, the beam 20, the 1st thickness maintenance pipe 30, and the wire The panel 10 made of the net 40 and the polyurethane foam 50 has one side of the reinforcing frame 70 such that the first thickness maintaining tube 30 coincides with the second thickness maintaining tube 79. (Ie inside the building).

다음에, 내면에 박리소재(142)가 덮인 판재(140)를, 상기 철근 골조(70)의 다른 쪽(즉, 건물 외측)에 배치한다. 상기 박리소재(142)로 비닐이 채용될 수 있다. Next, the plate 140 covered with the peeling material 142 on the inner surface is disposed on the other side (that is, outside the building) of the reinforcing frame 70. Vinyl may be employed as the release material 142.

다음에, 상기 제1두께유지관(30)과 제2두께유지관(79)을 통하여, 패널(10)과 판재(140)를 볼트(90) 및 너트(92)로 체결함으로써, 서로 대응하는 패널(10)과 판재(140)를 고정한다. 시공의 편의성을 위하여, 엠보싱 구멍(24)들과 대응하여 볼트(90)를 끼울 수 있는 구멍(144)들이, 상기 판재(140)에 미리 형성되는 것이 바람직하다. 상기 판재(140)로 합판이나 철판, 합성수지판 등 다양한 소재가 사용될 수 있다. Next, the panel 10 and the plate 140 are fastened with the bolts 90 and the nuts 92 through the first and second thickness holding tubes 30 and 79 to correspond to each other. The panel 10 and the plate 140 are fixed. For ease of construction, it is preferable that holes 144 through which the bolts 90 can be fitted in correspondence with the embossing holes 24 are formed in the plate member 140 in advance. As the plate material 140, various materials such as plywood, iron plate, and synthetic resin plate may be used.

다음에, 상기 패널(10) 및 판재(140) 사이에 콘크리트(80)를 타설 및 양생한다. Next, the concrete 80 is poured and cured between the panel 10 and the plate 140.

다음에, 상기 볼트(90) 및 너트(92)를 풀어, 판재(140) 및 박리소재(142)를 제거한다. 이 판재(140) 및 박리소재(142)가 제거됨으로써, 양생된 콘크리트(80)가 건물 외부로 노출될 수 있다. Next, the bolt 90 and the nut 92 are loosened to remove the plate 140 and the peeling material 142. By removing the plate 140 and the peeling material 142, the cured concrete 80 can be exposed to the outside of the building.

<실시예 4><Example 4>

본 실시예의 시공방법은 건물의 벽체를 시공하는 방법으로서, 도 15에 도시된 바와 같이, 전술한 실시예 3에서, 패널(10)로, 빔(20), 제1두께유지관(30), 와이어 네트(40), 폴리우레탄폼(50) 및 석고보드(60)로 이루어진 것을 사용한다는 것을 제외하고, 실시예 3과 모두 동일하게 이루어져 있다. The construction method of the present embodiment is a method for constructing a wall of a building, as shown in FIG. 15, in the above-described Embodiment 3, the panel 10, the beam 20, the first thickness maintaining tube 30, Except for using a wire net 40, polyurethane foam 50 and gypsum board 60 is made the same as in the third embodiment.

<실시예 5>Example 5

본 실시예의 시공방법은 건물의 천정을 시공하는 방법에 대한 것이다. The construction method of this embodiment relates to a method for constructing the ceiling of a building.

도 16에 도시된 바와 같이, 빔(20), 제1두께유지관(30), 와이어 네트(40) 및 폴리우레탄폼(50)으로 이루어진 패널(10)들을 수평으로 설치한다. 패널(10)들을 연결하는 방법은 실시예 1과 동일한 방법으로 수행될 수 있다. As shown in FIG. 16, the panel 10 including the beam 20, the first thickness maintaining tube 30, the wire net 40, and the polyurethane foam 50 is horizontally installed. The method of connecting the panels 10 may be performed in the same manner as in the first embodiment.

다음에, 상기 패널(10)들의 상부에 철근 골조(70)를 수평으로 설치한다. 상기 철근 골조(70) 설치방법 역시 실시예 1과 동일한 방법으로 수행될 수 있으며, 제2두께유지관(79)의 설치는 배제하여도 좋다. Next, the reinforcing bar frame 70 is installed horizontally on the upper part of the panels 10. The method of installing the reinforcing frame 70 may also be performed in the same manner as in Example 1, and the installation of the second thickness maintaining tube 79 may be excluded.

다음에, 상기 철근 골조(70)에 콘크리트(80)를 타설하여 양생시킴으로써 천정의 시공을 완료한다. Next, the concrete 80 is poured into the reinforced frame 70 to cure the ceiling.

이 시공방법에 있어서, 콘크리트(80)가 양생된 후, 상단에 구멍(162)이 형성된 유틸리티(Utility) 설비(190)용 서포트(160)를, 볼트(90)로 엠보싱 구멍(24)쪽에 체결하고, 상기 서포트(160)의 하단에 천정재(180) 부착용 천정프레임(170)을 설치하는 단계가 더 포함될 수 있다. In this construction method, after the concrete 80 is cured, the support 160 for the utility equipment 190 having the hole 162 formed thereon is fastened to the embossed hole 24 with the bolt 90. In addition, a step of installing the ceiling frame 170 for attaching the ceiling material 180 may be further included at the lower end of the support 160.

예컨대, 상기 서포트(160)의 중간부에는 전기배선관로, 에어컨 관로 등의 유틸리티 설비(190)가 지지될 수 있으며, 천정프레임(170)의 저면에는 천정재(180)로 석고보드 등이 설치될 수 있다. For example, the utility unit 190 such as an electric wiring line, an air conditioning line, etc. may be supported in the middle of the support 160, and a gypsum board may be installed on the bottom of the ceiling frame 170 as the ceiling material 180. Can be.

<실시예 6><Example 6>

본 실시예의 시공방법은, 도 17에 도시된 바와 같이, 전술한 실시예 5에 있어서, 패널(10)로, 빔(20), 제1두께유지관(30), 와이어 네트(40), 폴리우레탄폼(50) 및 석고보드(60)로 이루어진 것을 사용한다는 것을 제외하고, 실시예 5와 모두 동일하게 이루어져 있다. According to the construction method of the present embodiment, as shown in FIG. 17, in the above-described Embodiment 5, the panel 10 includes a beam 20, a first thickness maintaining tube 30, a wire net 40, and a poly. Except for using the urethane foam 50 and the gypsum board 60 is made the same as in Example 5.

<실시예 7><Example 7>

본 실시예의 시공방법은, 도 18 및 도 19에 도시된 바와 같이, 실시예 5에 있어서, 콘크리트(80)가 양생된 후, 천정프레임(170)을 볼트(90)로 엠보싱 구멍(24)쪽에 체결하고, 천정프레임(170)들 사이에는 천정프레임(170)과 직교하도록, 상하로 요철구조로 굴곡된 데크 플레이트(Deck Plate, 200)를 설치한다는 것을 제외하고, 모두 실시예 5와 동일하게 이루어져 있다. 18 and 19, in the fifth embodiment, after the concrete 80 is cured, the ceiling frame 170 is bolted to the embossed hole 24 toward the embossed hole 24. Fastening and between the ceiling frame 170 is made in the same manner as in Example 5, except that the deck plate (Deck Plate, 200) bent in a concave-convex structure up and down to be orthogonal to the ceiling frame 170, have.

사이 천정프레임(170)은 길이방향 양단이 바깥쪽으로 굴곡된 채널형 부재로 형성되고, 이 천정프레임(170)에 대하여 직교하는 방향으로 데크 플레이트(200)가 설치됨으로써, 천정프레임(170)의 강성을 증가시킬 수 있다. Between the ceiling frame 170 is formed of a channel-like member whose both ends in the longitudinal direction bent outward, the deck plate 200 is installed in a direction orthogonal to the ceiling frame 170, the rigidity of the ceiling frame 170 Can be increased.

그리고, 패널(10)과, 천정프레임(170) 및 데크 플레이트(200)와의 사이의 공간에는, 전기배선관로, 에어컨 관로 등의 유틸리티 설비(190)가 설치될 수 있다. In addition, a utility facility 190 such as an electric wiring line and an air conditioning line may be installed in the space between the panel 10, the ceiling frame 170, and the deck plate 200.

상기한 바와 같이 구성된 본 발명에 따른 건축용 패널(10) 및 이것을 이용한 시공방법에 의하면, 콘크리트(80) 양생후, 건축용 패널(10)을 해체할 필요가 없기 때문에, 별도의 거푸집 사용이 불필요하다. 따라서, 거푸집 재료의 손실이 없고, 형틀을 만들기 위한 인력과, 거푸집을 해체하기 위한 인력이 불필요하다. According to the building panel 10 and the construction method using the same according to the present invention configured as described above, since it is not necessary to dismantle the building panel 10 after curing the concrete 80, it is unnecessary to use a separate formwork. Therefore, there is no loss of formwork material, and no manpower for forming the mold and no manpower for dismantling the formwork.

또한, 폴리우레탄폼(50)이 단열/차음재의 기능을 하므로, 별도의 단열/차음재 시공을 할 필요가 없다. In addition, since the polyurethane foam 50 functions as a heat insulation / sound insulation material, there is no need to perform a separate heat insulation / sound insulation material construction.

또한, 건축용 패널(10) 뿐만 아니라, 철근 골조(70) 및 제2두께유지관(79)의 조립체도 단일의 조립체로 공장에서 제조되고, 또 건축용 패널(10)이 규격화 및 경량화되어 있으며, 철근 골조(70)도 규격화되어 있으므로, 수송이 용이하고, 제품을 이동시키는데 필요한 인력, 수송비 및 이동장비를 줄일 수 있다. In addition, not only the building panel 10 but also the assembly of the reinforcing frame 70 and the second thickness maintaining tube 79 are manufactured at the factory as a single assembly, and the building panel 10 is standardized and lightweight, Since the frame 70 is also standardized, it is easy to transport and can reduce the manpower, transportation costs and moving equipment required to move the product.

또한, 시공현장에서의 설치시간 및 설치인력도 줄일 수 있으므로, 공기 및 시공비를 크게 줄일 수 있다. In addition, the installation time and installation manpower in the construction site can also be reduced, thereby significantly reducing the air and construction costs.

또한, 해체되어야만 하는 거푸집을 사용할 필요가 없으므로, 건축폐기물이 줄어든다. 따라서, 폐기물 처리문제가 줄어들고, 예컨대 석고보드(60)를 부착하기 위한 접착제가 사용되지 않으므로, 친환경적이다. In addition, there is no need to use formwork that must be dismantled, thereby reducing construction waste. Therefore, the waste disposal problem is reduced, and for example, an adhesive for attaching the gypsum board 60 is not used, which is environmentally friendly.

또한, 제조공장에서 건축용 패널(10) 및 철근 골조(70)가 대량으로 생산될 수 있을 뿐만 아니라, 규격화되어 생산될 수 있으므로, 원가절감을 도모할 수 있다. In addition, the building panel 10 and the reinforcing frame 70 in the manufacturing plant can be produced not only in large quantities, but also can be standardized production, it is possible to reduce the cost.

또한, 규격화된 제품을 사용함으로써, 평탄도, 수직도, 수평도 등의 품질이 확보되어 하자발생 요인을 사전에 차단할 수 있다. In addition, by using a standardized product, the quality such as flatness, verticality, horizontality, and the like can be secured to prevent the occurrence of defects in advance.

또한, 취급이 용이하고, 중량이 가벼우며, 해체 등으로 인한 위험요소가 차단되며, 콘크리트(80) 타설시 공간으로 흘러내림 현상이 없으므로, 시공 안전성을 높일 수 있다. In addition, it is easy to handle, light in weight, risk factors due to dismantling, etc. are blocked, there is no phenomenon of falling into the space when the concrete 80 is placed, it is possible to increase the construction safety.

또한, 관리가 편리하고, 규격화되어 있으므로, 애프터 서비스(AS) 해결이 용이하다. In addition, since the management is convenient and standardized, it is easy to solve the after-sales service (AS).

도 1은, 본 발명에 따른 건축용 패널을 나타내는 일부 평단면도이다. 1 is a partial cross-sectional view showing a building panel according to the present invention.

도 2는, 도 1의 Ⅱ-Ⅱ선에 따른 단면도이다. FIG. 2 is a cross-sectional view taken along the line II-II of FIG. 1.

도 3은, 본 발명에 따른 건축용 패널을 구성하는 빔(Beam)의 다른 예를 나타내는 단면도이다. 3 is a cross-sectional view showing another example of a beam constituting the building panel according to the present invention.

도 4는, 본 발명에 따른 건축용 패널의 다른 예를 나타내는 일부 평단면도이다. 4 is a partial cross-sectional view showing another example of the building panel according to the present invention.

도 5는, 와이어 네트(Wire Net)와 제1두께유지관의 용접상태를 나타내는 일부 정면도이다. 5 is a partial front view showing a welding state between a wire net and a first thickness holding tube.

도 6은, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 1을 나타내는 일부 평단면도이다. 6 is a partial sectional view showing the first embodiment of the construction method using the building panel according to the present invention.

도 7은, 철근 골조를 조립하는 예를 설명하기 위한 도면이다. 7 is a view for explaining an example of assembling a reinforcing bar frame.

도 8은, 철근 골조를 배근하는 예를 설명하기 위한 도면이다. 8 is a view for explaining an example of reinforcing the reinforcing bar frames.

도 9는, 본 발명에 따른 건축용 패널을 좌우로 이어 연결하기 위한 채널(Channel)의 예를 나타내는 사시도이다. 9 is a perspective view showing an example of a channel for successively connecting the building panel according to the present invention from side to side.

도 10은, 본 발명에 따른 건축용 패널을 교차시켜 연결하기 위한 채널의 예를 나타내는 단면도이다. Fig. 10 is a cross-sectional view showing an example of a channel for crossing and connecting a building panel according to the present invention.

도 11은, 본 발명에 따른 건축용 패널을 타이 바(Tie Bar)를 이용하여 좌우로 연결하는 상태를 설명하기 위한 도면이다. FIG. 11 is a view for explaining a state in which a building panel according to the present invention is connected left and right using a tie bar. FIG.

도 12는, 본 발명에 따른 건축용 패널을 이용한 벽체 시공완료후, 외장재를 설치하는 상태를 나타내는 일부 종단면도이다. 12 is a partial longitudinal sectional view showing a state in which an exterior member is installed after completion of wall construction using a building panel according to the present invention.

도 13은, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 2를 나타내는 일부 평단면도이다. 13 is a partial cross-sectional view showing a second embodiment of a construction method using a building panel according to the present invention.

도 14는, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 3을 나타내는 일부 평단면도이다. 14 is a partial sectional view showing a third embodiment of a construction method using a building panel according to the present invention.

도 15는, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 4를 나타내는 일부 평단면도이다. 15 is a partial cross-sectional view showing a fourth embodiment of a construction method using a building panel according to the present invention.

도 16은, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 5를 나타내는 일부 종단면도이다. 16 is a partial longitudinal sectional view showing the fifth embodiment of the construction method using the building panel according to the present invention.

도 17은, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 6을 나타내는 일부 종단면도이다. 17 is a partial longitudinal sectional view showing the sixth embodiment of a construction method using a building panel according to the present invention.

도 18은, 본 발명에 따른 건축용 패널을 이용한 시공방법의 실시예 7을 나타내는 일부 종단면도이다. 18 is a partial longitudinal sectional view showing a seventh embodiment of a construction method using a building panel according to the present invention.

도 19는, 도 18의 ⅩⅨ-ⅩⅨ선에 따른 단면도이다. 19 is a cross-sectional view taken along the line VII-VII of FIG. 18.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for main parts of the drawings>

10 : 패널, 20 : 빔(Beam), 10: panel, 20: beam,

22 : 돌출부, 24 : 엠보싱(Embossing) 구멍, 22: protrusion, 24: embossing hole,

30 : 제1두께유지관, 40 : 와이어 네트(Wire Net), 30: first thickness holding tube, 40: wire net,

50 : 폴리우레탄폼(Polyurethane Foam), 52 : 결합홈, 50: polyurethane foam, 52: bonding groove,

54 : 결합돌기, 60 : 석고보드(Board), 54: engaging projection, 60: gypsum board (Board),

79 : 제2두께유지관, 80 : 콘크리트(Concrete), 79: second thickness maintenance pipe, 80: concrete,

90 : 볼트(Bolt), 92 : 너트(Nut), 90: Bolt, 92: Nut,

120 : 타이 바(Tie Bar), 130 : L자형 브래킷(Bracket), 120: tie bar, 130: L-shaped bracket,

132 : 수직부, 134 : 구멍, 132: vertical portion, 134: hole,

136 : 수평부, 140 : 판재, 136: horizontal portion, 140: plate,

142 : 박리소재, 150 : 외장재, 142: peeling material, 150: exterior material,

162 : 구멍, 160 : 서포트, 162: hole, 160: support,

170 : 천정프레임(Frame), 180 : 천정재, 170: ceiling frame (Frame), 180: ceiling material,

200 : 데크 플레이트(Deck Plate)200: Deck Plate

Claims (13)

길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱(Embossing) 구멍(24)이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔(Beam, 20)과; Both ends in the longitudinal direction are bent inwardly, and protrusions 22 are formed along the longitudinal direction in the center by recesses, and a plurality of embossing holes 24 are formed in the protrusions, and are arranged side by side at predetermined intervals. A plurality of beams 20 arranged; 상기 각 엠보싱 구멍에 접합되는 제1두께유지관(30)과; A first thickness retaining tube (30) joined to each of the embossing holes; 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(Wire Net, 40)와; 그리고, A wire net (40) bonded over the first thickness holding tubes; And, 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼 (Polyurethane Foam, 50)을 포함하여 이루어지는 것을 특징으로 하는 건축용 패널. Building panel comprising a polyurethane foam (Polyurethane Foam, 50) that is foamed from the beam to the first thickness maintenance tube. 제 1 항에 있어서, The method of claim 1, 상기 폴리우레탄폼(50)의 좌/우측면에는 서로 대응하는 결합홈(52) 및 결합돌기(54)가 차례로 형성되어 있는 것을 특징으로 하는 건축용 패널. Building panel, characterized in that the left / right side of the polyurethane foam 50, the coupling groove 52 and the coupling protrusion 54 corresponding to each other are formed in sequence. 제 1 항에 있어서, The method of claim 1, 상기 패널(10)의 외면쪽에, 폴리우레탄폼(50) 발포에 의하여 석고보드(Board, 60)가 더 접합되어 있는 것을 특징으로 하는 건축용 패널. Building panel, characterized in that the gypsum board (Board, 60) is further bonded to the outer surface side of the panel 10 by foaming polyurethane foam (50). 철근 골조(70)를 수직으로 설치하는 단계와; Installing the reinforcing frame 70 vertically; 상기 철근 골조를 따라 소정의 간격으로 제2두께유지관(79)을 설치하는 단계와; Installing a second thickness maintaining tube (79) at predetermined intervals along the reinforcing bar frame; 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍(24)이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔(20)과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관(30)과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(40)와, 그리고 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼(50)을 가지는 패널(Panel, 10)들을, 상기 제1두께유지관들이 제2두께유지관들과 일치하도록 상기 철근 골조의 양쪽에 배치하는 단계와; The both ends in the longitudinal direction are bent inward, the projection 22 is formed along the longitudinal direction in the center by the concavity, the plurality of embossed holes 24 are formed in the projection, and the plurality arranged side by side at a predetermined interval Beam 20, a first thickness retaining tube 30 bonded to each of the embossing holes, a wire net 40 bonded over the first thickness holding tubes, and a first thickness maintaining from the beam Placing panels (10) having polyurethane foam (50) foamed up to the tubes on both sides of the reinforcing frame such that the first thickness retaining tubes coincide with the second thickness retaining tubes; 상기 제1두께유지관들과 제2두께유지관을 볼트(90) 및 너트(92)로 체결함으로써, 서로 대응하는 패널들을 고정하는 단계와; 그리고, Fixing the panels corresponding to each other by fastening the first thickness holding tubes and the second thickness holding tubes with bolts (90) and nuts (92); And, 상기 패널들 사이에 콘크리트(Concrete, 80)를 타설 및 양생하는 단계;를 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. A method of constructing with a building panel comprising the; step of placing and curing concrete (Concrete, 80) between the panels. 제 4 항에 있어서, The method of claim 4, wherein 상기 콘크리트(80)가 양생된 후, 상기 볼트(90) 및 너트(92)를 푼 다음, 수직부(132)에 구멍(134)이 형성된 L자형 브래킷(Bracket, 130)을, 건물 외벽을 이루는 패널(10)의 엠보싱 구멍(24)쪽에 상기 볼트 및 너트로 체결하고, 상기 L자형 브래킷의 수평부(136)에 외장재(150)를 지지시키는 단계를 더 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. After the concrete 80 is cured, the bolts 90 and the nuts 92 are loosened, and then the L-shaped brackets 130 having holes 134 formed in the vertical portions 132 form the outer wall of the building. And fastening the bolts and nuts to the embossed holes 24 of the panel 10 and supporting the exterior member 150 on the horizontal portion 136 of the L-shaped bracket. Construction method used. 철근 골조(70)를 수직으로 설치하는 단계와; Installing the reinforcing frame 70 vertically; 상기 철근 골조를 따라 소정의 간격으로 제2두께유지관(79)을 설치하는 단계와; Installing a second thickness maintaining tube (79) at predetermined intervals along the reinforcing bar frame; 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍(24)이 돌출형성되고, 소정의 간격으로 나란하게 배치되는 다수의 빔(20)과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관(30)과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(40)와, 그리고 상기 빔으로부터 제1두께유지관(30)까지 발포성형되는 폴리우레탄폼(50)을 가지는 패널(10)들을, 상기 제1두께유지관이 제2두께유지관과 일치하도록, 상기 철근 골조의 한 쪽에 배치하는 단계와; The both ends in the longitudinal direction are bent inward, the projection 22 is formed along the longitudinal direction in the center by the concavity, the plurality of embossed holes 24 are formed in the projection, and the plurality arranged side by side at a predetermined interval Beam 20, a first thickness retaining tube 30 bonded to each of the embossing holes, a wire net 40 bonded over the first thickness holding tubes, and a first thickness maintaining from the beam Arranging panels (10) having polyurethane foam (50) foamed up to the tube (30) on one side of the reinforcing frame so that the first thickness holding tube coincides with the second thickness holding tube; 내면에 박리소재(142)가 덮인 판재(140)를 상기 철근 골조의 다른 쪽에 배치하는 단계와; Disposing a plate (140) covered with a peeling material (142) on an inner side of the rebar frame; 상기 제1두께유지관과 제2두께유지관을 통하여, 패널과 판재를 볼트(90) 및 너트(92)로 체결함으로써, 서로 대응하는 패널과 판재를 고정하는 단계와; Fixing the panel and the plate corresponding to each other by fastening the panel and the plate with the bolts (90) and the nut (92) through the first and the second thickness holding tubes; 상기 패널 및 판재 사이에 콘크리트(80)를 타설 및 양생하는 단계와; 그리고, Placing and curing concrete (80) between the panel and the plate; And, 상기 볼트 및 너트를 풀어, 판재 및 박리소재를 제거하는 단계를 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Loosening the bolts and nuts, removing the plate and peeling material construction method comprising the building panel comprising a. 제 4 항 또는 제 6 항에 있어서, The method according to claim 4 or 6, 상기 패널(10)들중 건물의 내측에 배치되는 패널의 외면쪽에, 폴리우레탄폼(50)의 발포에 의하여 석고보드(60)가 접합되는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Construction method using a building panel, characterized in that the gypsum board (60) is bonded to the outer surface side of the panel disposed in the interior of the panel of the panel 10 by the foaming of the polyurethane foam (50). 제 4 항에 있어서, The method of claim 4, wherein 상기 각 패널(10)의 외면쪽에, 폴리우레탄폼(50)의 발포에 의하여 석고보드(60)가 접합되는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Construction method using a building panel, characterized in that the gypsum board 60 is bonded to the outer surface side of each panel 10 by the foaming of the polyurethane foam (50). 길이방향 양단이 안쪽으로 굴곡되고, 요입에 의하여 돌출부(22)가 중앙에 길이방향을 따라 형성되며, 상기 돌출부에 다수의 엠보싱 구멍(24)이 돌출형성되며, 소정의 간격으로 나란하게 배치되는 다수의 빔(20)과, 상기 각 엠보싱 구멍에 접합되는 제1두께유지관(30)과, 상기 제1두께유지관들에 걸쳐 접합되는 와이어 네트(40)와, 그리고 상기 빔으로부터 제1두께유지관까지 발포성형되는 폴리우레탄폼(50)을 가지는 패널(10)들을 수평으로 설치하는 단계와; The both ends in the longitudinal direction are bent inward, the projections 22 are formed along the longitudinal direction in the center by the concavity, the plurality of embossed holes 24 are formed in the projections, a plurality arranged side by side at a predetermined interval Beam 20, a first thickness retaining tube 30 bonded to each of the embossing holes, a wire net 40 bonded over the first thickness holding tubes, and a first thickness maintaining from the beam Horizontally installing the panels 10 having the polyurethane foam 50 to the tube; 상기 패널들의 상부에 철근 골조(70)를 수평으로 설치하는 단계와; 그리고, Horizontally installing a reinforcing frame 70 on top of the panels; And, 상기 철근 골조에 콘크리트(80)를 타설하여 양생시키는 단계;를 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Placing concrete 80 in the reinforcing frame to cure; Construction method using a building panel comprising a. 제 4 항, 제 6 항 또는 제 9 항중 어느 한 항에 있어서, The method according to any one of claims 4, 6 or 9, 좌우로 이어지는 패널(10)들에 결합된 서로 대응하는 제2두께유지관(79)들은, 양쪽에 고리가 형성된 타이 바(Tie Bar, 120)로 연결되는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Construction method using a building panel, characterized in that the second thickness maintaining pipes 79 corresponding to each other coupled to the panels 10 leading to the left and right, are connected by tie bars (120) having a ring formed on both sides . 제 9 항에 있어서, The method of claim 9, 상기 콘크리트(80)가 양생된 후, 상단에 구멍(162)이 형성된 유틸리티(Utility) 설비용 서포트(Support, 160)를, 볼트(90)로 엠보싱 구멍(24)쪽에 체결하고, 상기 행거(160)의 하단에 천정재(180) 부착용 천정프레임(Frame, 170)을 설치하는 단계를 더 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. After the concrete 80 is cured, the support 160 for the utility equipment having a hole 162 formed thereon is fastened to the embossed hole 24 with a bolt 90, and the hanger 160. Construction method using a building panel, characterized in that it further comprises the step of installing a ceiling frame (Frame, 170) for attaching the ceiling member 180 at the bottom. 제 9 항에 있어서, The method of claim 9, 상기 패널(10)의 저면쪽에, 폴리우레탄폼(50)의 발포에 의하여 석고보드(60)가 접합되는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. Construction method using a building panel, characterized in that the gypsum board 60 is bonded to the bottom surface of the panel 10 by the foaming of the polyurethane foam (50). 제 9 항에 있어서, The method of claim 9, 상기 콘크리트(80)가 양생된 후, 천정프레임(170)을 볼트(90)로 엠보싱 구멍(24)쪽에 체결하고, 상기 천정프레임들 사이에는 천정프레임과 직교하도록, 상하로 요철구조로 굴곡된 데크 플레이트(Deck Plate, 200)를 설치하는 단계를 더 포함하여 이루어지는 것을 특징으로 하는 건축용 패널을 이용한 시공방법. After the concrete 80 is cured, the ceiling frame 170 is fastened to the embossed hole 24 with the bolt 90, and the deck bent in a concave-convex structure up and down so as to be perpendicular to the ceiling frame between the ceiling frames. Construction method using a building panel, characterized in that further comprising the step of installing a plate (Deck Plate, 200).
KR1020040027966A 2004-04-22 2004-04-22 Constructing panel and constructing method using the same KR20050102552A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040027966A KR20050102552A (en) 2004-04-22 2004-04-22 Constructing panel and constructing method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040027966A KR20050102552A (en) 2004-04-22 2004-04-22 Constructing panel and constructing method using the same

Publications (1)

Publication Number Publication Date
KR20050102552A true KR20050102552A (en) 2005-10-26

Family

ID=37280734

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040027966A KR20050102552A (en) 2004-04-22 2004-04-22 Constructing panel and constructing method using the same

Country Status (1)

Country Link
KR (1) KR20050102552A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102230783B1 (en) * 2020-03-25 2021-03-22 (주)렉스코 Noncomposite Fireproof Concrete Structures With Pre-construction Fireproof Cover And Method Of It
CN115126150A (en) * 2021-03-26 2022-09-30 奥动新能源汽车科技有限公司 Warehouse board, warehouse board combined unit and power conversion station or energy storage station

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102230783B1 (en) * 2020-03-25 2021-03-22 (주)렉스코 Noncomposite Fireproof Concrete Structures With Pre-construction Fireproof Cover And Method Of It
CN115126150A (en) * 2021-03-26 2022-09-30 奥动新能源汽车科技有限公司 Warehouse board, warehouse board combined unit and power conversion station or energy storage station

Similar Documents

Publication Publication Date Title
KR200481707Y1 (en) The outer wall for easy construction
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
KR20130113315A (en) A building structure
KR101645462B1 (en) Precast crossing beam manufacturing method for bridge and precast crossing beam construction method for bridge
KR102178461B1 (en) Hollow precast concrete slab with inside partition wall, and manufacturing method for the same
KR101663132B1 (en) Self-supporting type column structure
KR101889644B1 (en) Framework for beam bottom
KR101523987B1 (en) H type fixture used wall mold and manufacture method of eco mold for wall using it
KR20170111300A (en) Form Panel with Sub-panel for Form Removal
KR20050102552A (en) Constructing panel and constructing method using the same
KR100747665B1 (en) Concrete mold for slab and construction method of slab using the same
JP5921176B2 (en) Installation foundation construction method
KR101954387B1 (en) Grid precast concrete structure and constructing method thereof
KR200383489Y1 (en) System for constructing composite reinforced concrete girders and beams using FRP
KR101880813B1 (en) A sandwitch pc pannel structure and construction method of structure using thereof
JP3759142B2 (en) Assembled formwork unit
JP2007332631A (en) Reinforced concrete structure and method of constructing reinforced concrete structure
CN109208900B (en) Formwork system for assembled building and construction method thereof
KR100612938B1 (en) A construction system of the wall/dome and the the method thereof it
KR101140627B1 (en) Construction method of concrete building
KR101078292B1 (en) Concrete slab mold assembly and method for constructing slab
KR100664965B1 (en) Carbon-glass fiber composite concrete mold, its manufacturing method and construction method
KR20140130808A (en) The outer wall for easy construction
CN211473012U (en) Prefabricated assembled box type stripping-free dense rib composite floor slab
JP2567805B2 (en) Method for constructing multi-lattice slab, forming form for multi-lattice beam used in the constructing method, fixing jig for parallel flap square timber, reinforcing bar frame arrangement method, break-away forming form for multi-lattice beam, and multi-lattice beam Fixing jig for removing mold