KR200483165Y1 - Cage for construction of side wall of structure - Google Patents
Cage for construction of side wall of structure Download PDFInfo
- Publication number
- KR200483165Y1 KR200483165Y1 KR2020150006272U KR20150006272U KR200483165Y1 KR 200483165 Y1 KR200483165 Y1 KR 200483165Y1 KR 2020150006272 U KR2020150006272 U KR 2020150006272U KR 20150006272 U KR20150006272 U KR 20150006272U KR 200483165 Y1 KR200483165 Y1 KR 200483165Y1
- Authority
- KR
- South Korea
- Prior art keywords
- frame
- wall surface
- point
- fixed
- worker
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/20—Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
And a work table on which an operator can stand up and perform work. The work table includes a first frame to which an upward supporting force is applied; A second frame coupled to the first frame and opposed to the wall surface; And a third frame supported by the footrest for the operator, the second frame comprising: a main frame spaced from the wall surface; And a fixing frame having a distance from the wall surface smaller than a distance between the main frame and the wall surface and being fixed to the wall surface by a fixing member, The fixing member may be fixed at different positions, which are provided below the first point and are selected in the interval between the second points, which is one point on the fixed frame.
Description
The present invention relates to a workbench for constructing a wall of a building, and relates to a workbench for constructing a wall of a building, which provides a space for an operator to construct the wall surface while rising or falling along a wall of the building.
Workbenches are widely used to construct the walls of buildings. Especially, in case of high-rise buildings, a method of forming a skeleton by using reinforcing bars, installing a formwork, and pouring concrete is widely used. Also, in order to improve the working efficiency, a method of raising the number of layers while increasing the form used for concrete pouring of a specific layer is also applied.
In addition, a structure capable of performing a construction such as finishing a wall of a building is additionally provided with a workbench at the lower part of the elevated formwork.
However, conventionally, there has been a problem that the work table is not stably supported on the wall surface, the convenience of the work table fixing work is low, and the construction of the wall surface where the work table is contacted is difficult. In fact.
A problem to be solved by the present invention is to provide a workbench for building wall construction which is improved at least one of safety, convenience, and work efficiency.
A work table for building wall construction according to one embodiment of the present invention is a work table for building wall construction for providing a space for an operator to work the wall surface while rising or falling along a wall surface of a building, One frame; A second frame coupled to the first frame and opposed to the wall surface; And a third frame supported by the footrest for the operator, the second frame comprising: a main frame spaced from the wall surface; And a fixing frame having a distance from the wall surface smaller than a distance between the main frame and the wall surface and being fixed to the wall surface by a fixing member, The fixing member may be fixed at different positions selected from the interval between the first points, which are provided below the first point and the second point, which is one point on the fixed frame.
At this time, the fixed frame may be supported at least in a section from the first point to the second point in contact with the wall surface.
Preferably, the fixed frame includes a receiving groove provided on a region from the first point to the second point to receive the holding member, wherein the receiving groove has a length twice or more the diameter of the holding member Do.
A workbench for building wall construction according to an embodiment of the present invention provides a space for an operator to work the wall surface while rising or falling along a wall surface of a building, wherein an upper unit and a second worker, The upper unit comprising: a first frame to which an upward supporting force is applied; A second frame coupled to the first frame and opposed to the wall surface; And a third frame supported by the footrest for the first worker, wherein the lower unit comprises: a fourth frame coupled to at least one of the second frame or the third frame; And a fifth frame supported by the second operator's footrest, wherein the second frame comprises: a main frame spaced from the wall surface; And a fixed frame, at least a part of which is in contact with the wall surface and is fixed to the wall surface by a fixing member, wherein a first point, which is a point on the fixed frame, and a second point, The fixing member may be fixed at different positions selected from the interval between the first point and the second point.
According to one embodiment of the present invention, there is provided a beneficial effect that at least one of safety, convenience and operational efficiency can be improved.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view for explaining a work table for building wall construction according to an embodiment of the present invention; FIG.
2 is an enlarged perspective view of a portion A in Fig.
3 is a view for explaining an example of utilization of a work table for building wall construction according to an embodiment of the present invention.
FIGS. 4A and 4B are views for explaining the principle of use of a work surface for building wall construction according to an embodiment of the present invention.
5 is a view for explaining the principle of use of a work table for building wall construction according to an embodiment of the present invention.
6 is a view for explaining a work table for building wall construction according to another embodiment of the present invention.
BRIEF DESCRIPTION OF THE DRAWINGS The advantages and features of the present invention, and how to accomplish them, will become apparent with reference to the embodiments described in detail below with reference to the accompanying drawings. However, the present invention is not limited to the embodiments disclosed below, but may be embodied in various forms. These embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of design to those skilled in the art to which the present invention belongs. Like reference numerals refer to like elements throughout the specification.
The terminology used herein is for the purpose of describing the embodiments and is not intended to limit the present invention. In the present specification, the singular form includes plural forms unless otherwise specified in the specification. It is to be understood that the terms 'comprise', and / or 'comprising' as used herein may be used to refer to the presence or absence of one or more other components, steps, operations, and / Or additions.
In addition, the embodiments described herein will be described with reference to cross-sectional views and / or plan views, which are ideal illustrations of the present invention. In the drawings, the detailed size, shape, thickness, curvature, etc. of each structure are exaggerated or schematized for effective explanation of technical contents, and the shape may be modified by tolerance or the like.
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.
FIG. 1 is a view for explaining a
1 to 5, a
The
In one embodiment, the
The
In one embodiment, the
The main frame may be spaced apart from the wall by a predetermined distance, and the fixed frame FP may be provided so as to be in contact with the wall surface or a distance shorter than the distance between the main frame and the wall surface. In addition, the fixed frame FP can be fixedly coupled to the wall surface by the
2, the main frame may be a rectilinear rectangular pipe, and the fixed frame FP may include a first fixed frame FP1 and a second fixed frame FP2 coupled to both sides of the main frame, (FP2). In one embodiment, the first fixed frame FP1 includes a
The main frame MP1 is divided into the first main frame MP1 and the second main frame MP2 and the first main frame MP1 and the second main frame MP2 are connected to each other, It can be done as well. However, in this case, it may be inconvenient to work to fix the
In addition to the upper unit U1 including the
The other end of the
This allows the first worker W1 to perform the construction in the upper unit U1 and the second worker W2 to perform the construction in the lower unit U2 so that the construction speed can be improved .
Meanwhile, the
3 and the like, the third worker W3 and the fourth worker W4 are carried on the
4A and 4B, since the fixing frame FP is fixed to the
5, the
As described above, in the working
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art. It will be understood. It is therefore to be understood that the above-described embodiments are illustrative and not restrictive in every respect.
1: basic operation part
2: Wall
3:
10: First frame
20: second frame
30: Third frame
40: fourth frame
45:
50: fifth frame
60: first rear frame
70: second rear frame
80:
90: Fixing member
100, 200: Workbench for building wall construction
U1: upper unit
U2: Lower unit
MP1: First main frame
MP2: Second main frame
FP: fixed frame
SF1: 1st scaffold
SF2: 2nd scaffold
W1: First worker
W2: Second worker
W3: Third worker
W4: The fourth worker
Claims (4)
The upper unit includes:
A first frame receiving an upward bearing force;
A second frame coupled to the first frame and opposed to the wall surface; And
And a third frame supported by the footrest for the first worker,
The lower unit includes:
A fourth frame coupled to at least one of the second frame or the third frame;
A fifth frame supported by the footrest for the second worker; And
And a wall supporting portion provided at a lower portion of the fourth frame and contacting the wall surface,
Wherein the second frame comprises:
A main frame spaced from the wall surface; And
And a fixing frame having a distance from the wall surface smaller than a distance between the main frame and the wall surface and being fixed to the wall surface by a fixing member,
The fixed frame includes:
A second section that is bent toward the wall surface, a third section that is parallel to the wall surface and is held in contact with the wall surface, and a third section that is in contact with the wall surface, A first stationary frame having a fourth section bent in an opposite direction and a fifth section being in contact with the first side of the main frame; And
And a second fixing frame corresponding to the first fixing frame and being in contact with the other side of the main frame,
Wherein the fixing member is inserted into a space between the first fixing frame and the second fixing frame and includes a first point which is a point on the third section and a second point which is located below the first point, The second point being fixed at a position selected in a section between the first point and the second point,
Wherein at least a region of the main frame, which is in contact with the fixed frame, and the fixed frame are realized as a square column pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020150006272U KR200483165Y1 (en) | 2015-09-21 | 2015-09-21 | Cage for construction of side wall of structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020150006272U KR200483165Y1 (en) | 2015-09-21 | 2015-09-21 | Cage for construction of side wall of structure |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20170001145U KR20170001145U (en) | 2017-03-29 |
KR200483165Y1 true KR200483165Y1 (en) | 2017-04-10 |
Family
ID=58496607
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR2020150006272U KR200483165Y1 (en) | 2015-09-21 | 2015-09-21 | Cage for construction of side wall of structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR200483165Y1 (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101553609B1 (en) * | 2014-11-24 | 2015-09-16 | 주식회사 에스지이엔지 | Strong exterior working platform in the wind |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200184793Y1 (en) * | 1998-03-27 | 2000-06-01 | 김종우 | Prefabricated steel pipe scaffold frame |
KR200375135Y1 (en) | 2004-11-19 | 2005-03-11 | 태원공영 (주) | station |
-
2015
- 2015-09-21 KR KR2020150006272U patent/KR200483165Y1/en active IP Right Grant
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101553609B1 (en) * | 2014-11-24 | 2015-09-16 | 주식회사 에스지이엔지 | Strong exterior working platform in the wind |
Also Published As
Publication number | Publication date |
---|---|
KR20170001145U (en) | 2017-03-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101641340B1 (en) | Gang form cage having safety upper and lower worktable | |
CN105113786A (en) | Pad block support system for supporting fixed adjustable cast-in-situ stair formwork | |
CN110681803A (en) | Wall body steel reinforcement cage establishment bed-jig | |
KR200483165Y1 (en) | Cage for construction of side wall of structure | |
JP6208090B2 (en) | Temporary support structure for seismic isolation work and seismic isolation method for existing buildings | |
JP2008179469A (en) | Guide rail arranging method in elevator device | |
CN203475835U (en) | Fixing part for concrete surface slab staggering beamed formwork | |
KR200331403Y1 (en) | Lower working desk of gang form for a building | |
JP2016050413A (en) | Raising tool and raising method | |
CN209413302U (en) | Movable side wall form support system with operation platform | |
JP4855311B2 (en) | Precast erection method | |
JP6320242B2 (en) | How to install temporary pillars | |
KR101341618B1 (en) | Concrete form apparatus | |
CN205840326U (en) | A kind of stair template fixing device | |
KR20170039553A (en) | Formwork supporting system for beam forming a slab of the building | |
JP5574335B2 (en) | Seismic reinforcement method for roof | |
KR102516781B1 (en) | Footrest All-in-one Fixture | |
CN106270310A (en) | The manufacture method of a kind of shield duct piece steel reinforcement cage and manufacture stand thereof | |
JP5995822B2 (en) | Beam reinforcing method and structure, and auxiliary beam support | |
JP2006274670A (en) | Temporary column structure, building unit with temporary columns, and method of constructing unit building | |
KR101319065B1 (en) | Grating construction method | |
CN214696127U (en) | Fixing mechanism and column base thereof | |
JP4891459B1 (en) | Home widening method and guide members | |
JP6913471B2 (en) | How to change the floor height of an existing building | |
JP2018178648A (en) | Positioning jig |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
REGI | Registration of establishment |