KR200467345Y1 - A pile lifting structrue - Google Patents

A pile lifting structrue Download PDF

Info

Publication number
KR200467345Y1
KR200467345Y1 KR2020120008232U KR20120008232U KR200467345Y1 KR 200467345 Y1 KR200467345 Y1 KR 200467345Y1 KR 2020120008232 U KR2020120008232 U KR 2020120008232U KR 20120008232 U KR20120008232 U KR 20120008232U KR 200467345 Y1 KR200467345 Y1 KR 200467345Y1
Authority
KR
South Korea
Prior art keywords
pile
fixed
support body
ring groove
fixing
Prior art date
Application number
KR2020120008232U
Other languages
Korean (ko)
Inventor
진 영 이
Original Assignee
진 영 이
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 진 영 이 filed Critical 진 영 이
Priority to KR2020120008232U priority Critical patent/KR200467345Y1/en
Application granted granted Critical
Publication of KR200467345Y1 publication Critical patent/KR200467345Y1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/42Gripping members engaging only the external or internal surfaces of the articles
    • B66C1/44Gripping members engaging only the external or internal surfaces of the articles and applying frictional forces
    • B66C1/48Gripping members engaging only the external or internal surfaces of the articles and applying frictional forces to vertical edge portions of sheets, tubes, or like thin or thin-walled articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/62Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
    • B66C1/66Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled for engaging holes, recesses, or abutments on articles specially provided for facilitating handling thereof

Abstract

본 고안에 따른 파일 인양구조체는 지지본체가 일자형 또는 삼각형으로 형성되어 지지본체의 구조가 단순하게 형성되고 단순하게 형성된 만큼의 구조가 제외되게 되어 중량이 감소되게 되므로 1인의 노무자도 충분하게 들고서 이동시키는 것이 가능하게 되어 사용이 편리하게 되고 그 만큼 제조가 단순하게 되므로 제조공정이 단축되어 제조기간이 단축되고 제조가가 저렴하게 되는 등의 우수한 효과가 있게 되는 것이다.The pile lifting structure according to the present invention has a support body formed in a straight or triangular shape, so that the structure of the support body is simply formed and the structure of the support body is simply excluded so that the weight is reduced, so that one laborer can carry and move enough. Since it becomes possible to use and the manufacturing becomes simple by that much, the manufacturing process is shortened and the manufacturing period is shortened and manufacturing cost becomes low, and there exists the outstanding effect.

Description

파일 인양구조체{ A pile lifting structrue }A pile lifting structrue}

본 고안은 파일 인양구조체에 관한 것으로, 더욱 구체적으로 설명하면, 아파트를 신축하거나 도로를 신축할 경우에 지반을 견고히 하기 위하여 지반에 삽입되는 파일을 보다 용이하게 인양하고 설치할 수 있도록 파일의 단부에 용이하게 고정시킬 수 있도록 구조를 간단히 하여 파일을 보다 용이하게 설치하는 것이 가능한 파일 인양구조체에 관한 것이다.
The present invention relates to a pile lifting structure, and more specifically, to an end of a pile so that the pile inserted into the ground can be easily lifted and installed in order to firm the ground when the apartment is newly constructed or a road is newly constructed. The present invention relates to a file lifting structure capable of installing a file more easily by simplifying the structure so that it can be securely fixed.

일반적으로, 토목 기초공사 단계에서는 지면에 여러 개의 파일을 박아서 구조물이나 건축물 등을 지지할 수 있도록 하는 파일 시공이 이루어진다.In general, in the civil engineering foundation stage, piles are built to support structures, buildings, etc. by putting several piles on the ground.

이러한 건설현장에서 사용되는 파일 시공을 위해서는 여러가지 형태로 파일을 인양해야 하는 경우가 많이 발생되고 있으며, 예를 들면, 파일 운반시, 특히 트럭에 상차시킬 때나 바지선에 선적시킬 때, 또는 현장에서 파일을 하차시킬 때, 파일을 시공위치에 항타할 때 등과 같은 경우에 파일의 인양작업이 반드시 필요하며, 이러한 파일의 인양에 있어서는 시공성과 안전성이 매우 중요하다.There are many cases in which piles need to be lifted in various forms for the construction of piles used in such construction sites. For example, piles are transported, especially when loaded on trucks, loaded on barges, or on site. When unloading, when the pile is driven to the construction position, the lifting of the pile is essential, and the construction and safety are very important in lifting the pile.

이러한 파일의 인양을 위해서는 여러가지 방법이나 장치 등이 제시되어 있으며, 그 중에서 가장 대표적인 방법으로 홀치기 방법이 있다.Various methods, devices, and the like have been proposed for the salvage of such a file, and the most representative method is the hold method.

상기 홀치기 방법은 지면에 고정된 파일의 상부를 와이어를 사용하여 올가미 형식으로 묶은 다음, 와이어를 기중기의 훅에 연결하여 인양하는 방법이다.The hole punching method is a method of tying the upper portion of a pile fixed to the ground in a lasso form using a wire, and then connecting the wire to a hook of a crane to lift.

그러나, 상기 홀치기 방법은 파일의 직경이 대형이거나 또는 파일의 길이가 길 경우에는 설치하기가 매우 곤란하여 사용이 불가능하고, 와이어가 묶여 있는 파일부위가 변형되는 등 국부적으로 파일이 손상되는 문제가 있으며, 파일의 부식을 방지하기 위해 도포한 방청제가 와이어에 의해 벗겨지면서 표면 산화 등으로 인해 파일의 수명을 단축시키는 문제가 있으며, 특히, 작업자의 부주의나 과실에 의해 와이어의 매듭이 풀어지는 경우가 빈번하여 안전사고의 위험이 매우 높은 문제점이 있다. However, in the case of the punching method, when the diameter of the pile is large or the length of the pile is very difficult to install, it cannot be used, and there is a problem that the pile is damaged locally, such as the deformation of the pile where the wire is bundled. In addition, the anti-corrosive agent applied to prevent corrosion of the pile is peeled off by the wire, and there is a problem of shortening the life of the pile due to surface oxidation, etc. There is a problem that the risk of safety accidents is very high.

이러한 문제점을 해결하기 위하여, 대한민국 등록특허 제10-1038453호의 '파일 인양용 기구'에는 이러한 파일을 용이하게 인양하기 위하여, 파일의 상단에 볼트로 체결되는 링 모양의 파일 인양용 기구가 제안된 바가 있으나, 상기 파일 인양용 기구는 인양되는 파일의 직경이 최소가 400mm 에서 최대로 1000mm 까지가 사용되고 있으나, 이러한 최소 직경의 파일을 인양하기 위해서는 상기 특허에서는 링 모양으로 형성되어 있으므로 직경이 적어도 400mm 로 형성되게 되므로, 건설현장에서 현장의 노무자들이 적어도 2인이 많게는 3 내지 4인이 함께 운반하여 파일의 고정단부까지 이동시켜야 하므로 그 운반이 대단히 번거롭게 되고, 이러한 노무자들이 함께 작업을 하여야 하므로 노동생산성이 저하되게 되는 문제점이 있었다.
In order to solve this problem, in order to easily lift the file in the Republic of Korea Patent Registration No. 10-1038453, a ring-shaped file lifting device that is bolted to the top of the file has been proposed. However, the file lifting mechanism is used to the maximum diameter of the file to be lifted from 400mm to a maximum of 1000mm, but in order to lift the file of the minimum diameter, the patent is formed in a ring shape so that the diameter is formed at least 400mm At the construction site, at least two laborers on the construction site must carry three or four people together to move them to the fixed end of the pile, which makes the transportation very cumbersome, and these laborers must work together to reduce labor productivity. There was a problem.

한국 등록특허 10-1038453Korea Patent Registration 10-1038453

본 고안의 목적은, 이러한 문제점을 해결하기 위한 것으로, 1인의 노무자가 용이하게 운반하는 것이 가능하게 되고 아울러 구조가 간단하게 되어 제조가가 저렴하게 되어 염가의 구입이 가능하게 되어 누구라도 편리하게 사용하는 것이 가능한 파일 인양구조체를 제공하는 것이다.
The object of the present invention is to solve such a problem, and it is possible for one laborer to carry it easily, and the structure is simple, and the manufacturing cost becomes low, so that the purchase of cheapness is possible, and anyone can use it conveniently. To provide a file lifting structure that can be done.

본 고안의 이러한 목적은, 일(一)자형 또는 삼각 분기형의 지지본체와, 상기 지지본체의 단부인 모서리부에 파일에 고정되는 고정단부가 형성되고 중앙에는 고정고리홈이 형성된 파일인양구와, 상기 파일인양구의 고정고리홈에 착탈가능하게 고정되며 상단에는 인양장비의 훅에 걸리는 고리부가 형성되고 하단에는 상기 파일인양구의 고정고리홈에 삽입되는 삽입피스톤이 형성된 연결구를 포함하는 본 고안에 따른 파일 인양구조체에 의하여 달성된다.
This object of the present invention is a one-shaped or triangular branch-shaped support body, and a fixed end portion is formed in the corner portion of the end of the support body fixed to the pile and the pile lifting tool formed with a fixed ring groove in the center and The present invention includes a connector that is detachably fixed to the fixing ring groove of the pile lifting tool, and a hook portion is formed on the hook of the lifting equipment at the upper end, and an insertion piston formed at the bottom thereof is inserted into the fixing ring groove of the pile lifting tool. It is achieved by a pile lifting structure according to

본 고안에 따른 파일 인양구조체는 지지본체가 일자형 또는 삼각형으로 형성되어 지지본체의 구조가 단순하게 형성되고 단순하게 형성된 만큼의 구조가 제외되게 되어 중량이 감소되게 되므로 1인의 노무자도 충분하게 들고서 이동시키는 것이 가능하게 되어 사용이 편리하게 되고 그 만큼 제조가 단순하게 되므로 제조공정이 단축되어 제조기간이 단축되고 제조가가 저렴하게 되는 등의 우수한 효과가 있게 되는 것이다.
The pile lifting structure according to the present invention has a support body formed in a straight or triangular shape, so that the structure of the support body is simply formed and the structure of the support body is simply excluded so that the weight is reduced, so that one laborer can carry and move enough. Since it becomes possible to use and the manufacturing becomes simple by that much, the manufacturing process is shortened and the manufacturing period is shortened and manufacturing cost becomes low, and there exists the outstanding effect.

도 1은 본 고안의 제1실시예에 따른 파일 인양구조체의 분해 사시도
도 2는 본 고안의 제2실시예에 따른 파일 인양구조체의 파일인양구의 정면도
도 3은 본 고안의 제1실시예에 따른 파일 인양구조체의 파일인양구가 파일의 단부에 설치된 상태가 도시된 정면도
도 4a,4b는 도 3의 파일 인양구조체의 연결구가 파일인양구에 결합되기 전과 후의 상태가 도시된 종단면도
도 5는 본 고안의 제1실시예에 따른 파일 인양구조체가 파일에 설치된 상태가 도시된 사시도
1 is an exploded perspective view of a pile lifting structure according to a first embodiment of the present invention
2 is a front view of the pile lifting tool of the pile lifting structure according to the second embodiment of the present invention;
Figure 3 is a front view showing a state in which the pile lifting tool of the pile lifting structure according to the first embodiment of the present invention is installed at the end of the pile
Figures 4a, 4b is a longitudinal cross-sectional view showing the state before and after the connector of the pile lifting structure of Figure 3 is coupled to the pile lifting tool
5 is a perspective view showing a state in which the pile lifting structure according to the first embodiment of the present invention is installed in a pile

본 고안의 제1실시예에 따른 파일 인양구조체(A)는, 도 1에 도시된 바와 같이, 삼각 분기형의 지지본체(1)와, 상기 지지본체(1)의 단부인 각 모서리부에 파일(P)에 고정되는 고정단부(2)가 형성되고 중앙에는 고정고리홈(3)이 형성된 파일인양구(4)와, 상기 파일인양구(4)의 고정고리홈(3)에 착탈가능하게 고정되며 상단에는 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고 하단에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착된 연결구(7)를 포함한다. Pile lifting structure (A) according to the first embodiment of the present invention, as shown in Figure 1, the triangular branched support body 1 and the pile at each corner that is the end of the support body (1) Fixed end portion (2) is fixed to (P) is formed in the center of the pile lifting tool (4) having a fixing ring groove (3), and the detachable ring groove (3) of the pile lifting tool (4) It is fixed and the upper end is formed with a hook portion (5) is caught on the hook (H) of the lifting equipment and the lower end of the connector with an insertion piston (6) is inserted into the fixing ring groove (3) of the pile lifting tool (4) 7).

상기 지지본체(1)는 삼각 분기형으로 형성되어 지지본체(1)의 상부에는 보강대(11)가 삼각 분기형으로 형성되고 상기 고정단부(2)의 가장자리에는 외향으로 개방된 보강벽(12)이 형성되어 있다. The support body (1) is formed in a triangular branch shape, the reinforcing bar 11 is formed in a triangular branch shape on the upper portion of the support body (1) and the reinforcing wall (12) opened outward at the edge of the fixed end (2) Is formed.

상기 고정단부(2)는 지지본체(1)의 각 모서리부에 천공된 상태로 형성되어 파일(P)의 상단의 조립부(P1)에 볼트(8)로 고정되게 된다.The fixed end 2 is formed in a perforated state at each corner of the support body 1 is fixed to the assembly portion (P1) of the upper end of the pile (P) with a bolt (8).

상기 지지본체(1)의 상부에 형성된 보강대(11)의 중간에는 상방으로 돌출된 돌출보강대(11')의 중앙에 종방향으로 형성된 고정고리홈(3)이 형성되어 있다.In the middle of the reinforcing bar 11 formed on the upper portion of the support body 1, a fixing ring groove 3 formed in the longitudinal direction is formed at the center of the protruding reinforcing bar 11 'protruding upward.

이와 같이 지지본체(1)는 삼각 분기형으로 형성되어 있으므로, 파일(P)의 원통형의 조립부(P1)의 일부만이 형성되어 있으며, 다른 부분은 제외되게 되므로 제외된 다른 부분의 도 3에 이점쇄선으로 표기된 부분이 없게 되므로, 그 중량이 대폭적으로 감소되어 1인의 작업자가 용이하게 들고서 운반할 수 있게 되는 것이다.Thus, since the support body 1 is formed in a triangular branch, only a part of the cylindrical assembly portion P1 of the pile P is formed, and other parts are excluded, which is advantageous in FIG. Since no part is indicated by the dashed line, the weight is greatly reduced so that one worker can easily carry and carry it.

이와 같은 삭제된 부분은, 본 고안의 제2실시예가 도시된, 도 2에서는 이점쇄선으로 도시된 부분이 더욱 많이 표시되어 있게 되고, 이와 같이 더욱 많은 부분이 삭제되어 1인의 작업자가 더욱 용이하게 운반할 수가 있게 되는 것이다. Such a deleted portion, the second embodiment of the present invention is shown in Figure 2, the portion shown by the double-dot chain line is shown, more such a portion is deleted so that one worker more easily carried You can do it.

또한, 본 고안의 제1실시예에서 상기 지지본체(1)는 삼각 분기형으로 제조되므로 자투리로 사용되는 봉상의 재료들을 절단하고 용접시키는 작업을 통하여 간단하게 제조가 되게 되므로 제조가가 저렴하게 제조되는 것이 가능하게 되고, 본 고안의 제2실시예에 따른 지지본체(1)는 구조가 더욱 간단하므로 더욱 용이하고 저렴하게 제조하는 것이 가능하게 되는 것이라고 할 것이다.In addition, since the support body 1 is manufactured in a triangular branch type in the first embodiment of the present invention, it is easily manufactured by cutting and welding rod-like materials used as a rim, and thus, the manufacturing cost is low. It will be possible to, and the support body 1 according to the second embodiment of the present invention will be said to be able to manufacture more easily and inexpensively because the structure is simpler.

상기 지지본체(1)의 고정고리홈(3)에 착탈가능하게 고정되는 연결구(7)는 상부에는 상기 고리부(5)가 회동가능하게 고정되는 돌출고정부(71a)가 형성되고 하부에는 상기 삽입피스톤(6)의 고정되게 중간에 고정홈(71b)이 형성된 분기부(71c)가 형성된 연결본체(71)와, 상기 연결본체(71)의 상단에 회동가능하게 고정되며 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고, 연결본체(71)의 하단에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착되고, 상기 삽입피스톤(6)의 후방에는 상기 삽입피스톤(6)을 후방으로 후퇴시키는 작동와이어(61)가 설치되어 상기 삽입피스톤(6)을 후방으로 후퇴시키는 구조를 갖는다.  The connector 7 detachably fixed to the fixing ring groove 3 of the support body 1 is provided with a protruding fixing portion 71a in which the ring portion 5 is rotatably fixed, and a lower portion thereof. A connecting body 71 having a branching portion 71c having a fixing groove 71b formed in the middle of the insertion piston 6, and a hook of a lifting device being rotatably fixed to an upper end of the connecting body 71. H) hook portion (5) is formed, the lower end of the connecting body 71, the insertion piston (6) inserted into the fixing ring groove (3) of the pile lifting tool (4) is attached, the insertion piston At the rear of the (6), the operation wire 61 for retracting the insertion piston (6) is provided to have a structure for retracting the insertion piston (6) to the rear.

이와 같은 구성을 갖는 본 고안에 따른 파일 인양구조체(A)의 작동에 대하여 설명한다, The operation of the pile lifting structure A according to the present invention having such a configuration will be described.

우선, 인양하여 지중에 매설시킬 파일(P)을 선택하고, 상기 파일(P)의 하단의 원통형의 조립부(P1)상에 파일인양구(4)를 부착시키고 볼트(8)로 파일인양구(4)의 고정단부(2)와 조립부(P1)를 조립시켜 파일인양구(4)와 파일(P)을 고정시킨다.First, the pile P to be lifted and buried in the ground is selected, and the pile lifting tool 4 is attached to the cylindrical assembly portion P1 at the lower end of the pile P, and the pile lifting tool is mounted with the bolt 8. The fixed end 2 of (4) and the assembly part P1 are assembled, and the pile lifting tool 4 and the pile P are fixed.

이와 같이 파일인양구(4)와 파일(P)이 고정된 상태에서, 연결구(7)의 삽입피스톤(6)의 작동와이어(61)를 후방으로 잡아당겨서 삽입피스톤(6)이 후퇴하게 되고, 연결본체(71)의 고정홈(71b)이 하방으로 개방되게 하고, 이와 같이 연결본체(71)의 고정홈(71b)이 하방으로 개방된 상태에서, 파일인양구(4)의 보강대(11)의 중간에는 상방으로 돌출된 돌출보강대(11')의 중앙에 종방향으로 형성된 고정고리홈(3)에 연결본체(71)의 고정홈(71b)이 연통되게 하고(도 4a에 도시), 삽입피스톤(6)을 후퇴시킨 작동와이어(61)의 후퇴작동을 해재시키면, 삽입피스톤(6)이 고정고리홈(3)내로 전진 되면서 파일인양구(4)와 연결구(7)의 결합이 종료되게 되는 것이다(도 4b에 도시).In the state in which the pile lifting tool 4 and the pile P are fixed as described above, the insertion piston 6 is retracted by pulling the operation wire 61 of the insertion piston 6 of the connector 7 backward. The fixing groove 71b of the connecting body 71 is opened downward, and in this way, the fixing groove 71b of the connecting body 71 is opened downward, so that the reinforcing table 11 of the pile lifting tool 4 is open. The fixing groove 71b of the connecting body 71 is in communication with the fixing ring groove 3 formed in the longitudinal direction at the center of the protruding reinforcing bar 11 'protruding upwardly in the middle of the insertion (shown in FIG. When the retraction operation of the operation wire 61 with which the piston 6 is retracted is released, the insertion piston 6 is advanced into the fixing ring groove 3 so that the coupling of the pile lifting tool 4 and the connector 7 is terminated. (Shown in FIG. 4B).

이와 같이 파일인양구(4)와 연결구(7)의 결합이 종료된 상태에서, 인양장비의 훅(H)을 고리부(5)에 걸고서 인양장비를 작동시키면, 파일(P)은 인양장비에 의하여 들어 올려져서 설치될 지상의 천공부에 삽입되고, 이 상태에서 연결구(7)와 파일인양구(4)의 결합을 해제시키고, 다시 파일인양구(4)와 파일의 조립부(P1)와의 결합을 해제시킨 상태에서 드롭햄머(도시되지 않음)로 파일을 가격하여 원하는 깊이까지 파일을 박으면 파일의 설치가 완료되게 되는 것이다.
As described above, when the coupling of the lifting device 4 and the connector 7 is finished, the lifting device is operated by hooking the hook H of the lifting device to the hook portion 5 and the file P is lifted. Inserted into the perforation part of the ground to be lifted by the installation, in this state to release the coupling of the connector (7) and the pile lifting tool (4), and again the assembly portion (P1) of the pile lifting tool (4) and pile If you unbind with and hit the file with the drop hammer (not shown) and push the file to the desired depth, the installation of the file is completed.

본 고안에 따른 파일 인양구조체는 파일타설을 수행하는 산업분야에서 동일한 파일 인양구조체를 반복적으로 제조하는 것이 가능하다고 할 것이므로 산업상 이용가능성이 있는 고안이라고 할 것이다.
The pile lifting structure according to the present invention will be said to have an industrial applicability since it is possible to repeatedly manufacture the same pile lifting structure in an industrial field performing pile placing.

1. 지지본체 2. 고정단부 3. 고정고리홈
4. 파일 인양구 5. 고리부
1. Support body 2. Fixed end 3. Fixed ring groove
4. File salvage 5. Ring section

Claims (2)

파일 인양구조체(A)에 있어서,
상기 파일 인양구조체(A)는, 삼각 분기형의 지지본체(1)와,
상기 지지본체(1)의 단부인 각 모서리부에 파일(P)에 고정되는 고정단부(2)가 형성되고 중앙에는 고정고리홈(3)이 형성된 파일인양구(4)와,
상기 파일인양구(4)의 고정고리홈(3)에 착탈가능하게 고정되며 상단에는 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고 하단에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착된 연결구(7)를 포함하고,
상기 지지본체(1)는 삼각 분기형으로 형성되어 상부에는 지지본체(1)를 보강시키는 보강대(11)가 삼각 분기형으로 형성되고 상기 고정단부(2)의 가장자리에는 외향으로 개방된 보강벽(12)이 형성되고, 상기 지지본체(1)의 상부에 형성된 보강대(11)의 중간에는 상방으로 돌출된 돌출보강대(11')의 중앙에 종방향으로 형성된 고정고리홈(3)이 형성되고,
상기 고정단부(2)는 지지본체(1)의 단부인 각 모서리부에 나사공(21)이 형성되어 파일(P)의 상단의 조립부(P1)에 고정되는 볼트(8)가 나사조립되고,
상기 지지본체(1)의 고정고리홈(3)에 착탈가능하게 고정되는 연결구(7)는 상부에는 상기 고리부(5)가 회동가능하게 고정되는 돌출고정부(71a)가 형성되고 하부에는 상기 삽입피스톤(6)이 고정되게 중간에 고정홈(71b)이 형성된 분기부(71c)가 형성된 연결본체(71)와, 상기 연결본체(71)의 상단에 회동가능하게 고정되며 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고, 연결본체(71)의 하단의 일측 분기부(71c)에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착되고, 상기 삽입피스톤(6)의 후방에는 상기 삽입피스톤(6)을 후방으로 후퇴시키는 작동와이어(61)가 설치된 것을 특징으로 하는 파일 인양구조체.
In the pile lifting structure (A),
The pile lifting structure (A) is a triangular branched support body (1),
Fixed end portions (2) are fixed to the pile (P) at each corner, which is an end of the support body (1), and the pile lifting tool (4) formed with a fixing ring groove (3) in the center,
Removably fixed to the fixing ring groove (3) of the pile lifting tool (4) and the upper end is formed with a hook portion (5) caught on the hook (H) of the lifting equipment and at the bottom of the fixing of the pile lifting tool (4) It includes a connector (7) attached to the insertion piston (6) is inserted into the ring groove (3),
The support body (1) is formed in a triangular branch form a reinforcing bar (11) for reinforcing the support body (1) at the upper portion is formed in a triangular branch form a reinforcement wall opened outward at the edge of the fixed end (2) ( 12 is formed, the fixing ring groove (3) formed in the longitudinal direction in the middle of the reinforcing bar 11 'protruding upwards is formed in the middle of the reinforcing bar 11 formed on the upper portion of the support body (1),
The fixed end portion 2 is a screw hole 21 is formed in each corner, which is an end of the support body 1, the bolt 8 is fixed to the assembly portion (P1) of the upper end of the pile (P) is assembled ,
The connector 7 detachably fixed to the fixing ring groove 3 of the support body 1 is provided with a protruding fixing portion 71a in which the ring portion 5 is rotatably fixed, and a lower portion thereof. A connecting body 71 having a branching portion 71c having a fixing groove 71b formed therebetween so that the insertion piston 6 is fixed, and a hook of a lifting device being rotatably fixed to an upper end of the connecting body 71. Ring portion (5) is formed to be caught, and the insertion piston (6) inserted into the fixing ring groove (3) of the pile lifting tool (4) in one side branch portion (71c) of the lower end of the connecting body (71) Is attached, the rear lifting of the insertion piston (6) pile lifting structure, characterized in that the operating wire (61) is installed to retract the insertion piston (6) to the rear.
파일 인양구조체(A)에 있어서,
상기 파일 인양구조체(A)는, 한일자(一)형의 지지본체(1)와,
상기 지지본체(1)의 단부에 파일(P)에 고정되는 고정단부(2)가 형성되고 중앙에는 고정고리홈(3)이 형성된 파일인양구(4)와,
상기 파일인양구(4)의 고정고리홈(3)에 착탈가능하게 고정되며 상단에는 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고 하단에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착된 연결구(7)를 포함하고,
상기 지지본체(1)는 한일자(一)형으로 형성되어 상부에는 지지본체(1)를 보강시키는 보강대(11)가 한일자(一)형으로 형성되고 상기 고정단부(2)의 가장자리에는 외향으로 개방된 보강벽(12)이 형성되고, 상기 지지본체(1)의 상부에 형성된 보강대(11)의 중간에는 상방으로 돌출된 돌출보강대(11')의 중앙에 종방향으로 형성된 고정고리홈(3)이 형성되고,
상기 고정단부(2)는 지지본체(1)의 단부에 나사공(21)이 형성되어 파일(P)의 상단의 조립부(P1)에 고정되는 볼트(8)가 나사조립되고,
상기 지지본체(1)의 고정고리홈(3)에 착탈가능하게 고정되는 연결구(7)는 상부에는 상기 고리부(5)가 회동가능하게 고정되는 돌출고정부(71a)가 형성되고 하부에는 상기 삽입피스톤(6)의 고정되게 중간에 고정홈(71b)이 형성된 분기부(71c)가 형성된 연결본체(71)와, 상기 연결본체(71)의 상단에 회동가능하게 고정되며 인양장비의 훅(H)에 걸리는 고리부(5)가 형성되고, 연결본체(71)의 하단의 일측 분기부(71c)에는 상기 파일인양구(4)의 고정고리홈(3)에 삽입되는 삽입피스톤(6)이 부착되고, 상기 삽입피스톤(6)의 후방에는 상기 삽입피스톤(6)을 후방으로 후퇴시키는 작동와이어(61)가 설치된 것을 특징으로 하는 파일 인양구조체.
In the pile lifting structure (A),
The pile lifting structure (A), the support body (1) of the Japanese-Japanese type, and
Fixed end portion (2) is formed at the end of the support body (1) to be fixed to the pile (P) and in the center is a pile lifting tool (4) formed with a fixing ring groove (3),
Removably fixed to the fixing ring groove (3) of the pile lifting tool (4) and the upper end is formed with a hook portion (5) caught on the hook (H) of the lifting equipment and at the bottom of the fixing of the pile lifting tool (4) It includes a connector (7) attached to the insertion piston (6) is inserted into the ring groove (3),
The support body (1) is formed in the shape of a one-day (I), reinforcing bar 11 for reinforcing the support body (1) is formed in the shape of the one-day (I) and open outwardly at the edge of the fixed end (2) Fixed reinforcing wall 12 is formed, the fixing ring groove (3) formed in the middle of the reinforcing bar 11 formed in the upper portion of the support body 1 in the longitudinal direction in the center of the protruding reinforcing bar 11 ' Is formed,
The fixed end portion 2 is a screw hole 21 is formed at the end of the support body 1, the bolt 8 is fixed to the assembly portion (P1) of the upper end of the pile (P) is screw-assembled,
The connector 7 detachably fixed to the fixing ring groove 3 of the support body 1 is provided with a protruding fixing portion 71a in which the ring portion 5 is rotatably fixed, and a lower portion thereof. A connecting body 71 having a branching portion 71c having a fixing groove 71b formed in the middle of the insertion piston 6, and a hook of a lifting device being rotatably fixed to an upper end of the connecting body 71. Ring portion (5) is formed to be caught, and the insertion piston (6) inserted into the fixing ring groove (3) of the pile lifting tool (4) in one side branch portion (71c) of the lower end of the connecting body (71) Is attached, the rear lifting of the insertion piston (6) pile lifting structure, characterized in that the operating wire (61) is installed to retract the insertion piston (6) to the rear.
KR2020120008232U 2012-09-14 2012-09-14 A pile lifting structrue KR200467345Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020120008232U KR200467345Y1 (en) 2012-09-14 2012-09-14 A pile lifting structrue

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020120008232U KR200467345Y1 (en) 2012-09-14 2012-09-14 A pile lifting structrue

Publications (1)

Publication Number Publication Date
KR200467345Y1 true KR200467345Y1 (en) 2013-06-07

Family

ID=51386506

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020120008232U KR200467345Y1 (en) 2012-09-14 2012-09-14 A pile lifting structrue

Country Status (1)

Country Link
KR (1) KR200467345Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190109748A (en) * 2017-01-30 2019-09-26 아이에이취시 홀랜드 아이이 비.브이. System used in crane of ship
KR20220051658A (en) 2020-10-19 2022-04-26 김형민 Pile connecting device
US11945694B1 (en) * 2020-07-23 2024-04-02 The Crosby Group LLC Master link test fixture assembly

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08158359A (en) * 1994-12-02 1996-06-18 Kubota Corp Connecting method for steel pipe pile
JP2745322B2 (en) 1989-04-26 1998-04-28 三和テッキ株式会社 Hanging fittings for steel pipes for steel towers
KR101038453B1 (en) 2010-11-02 2011-06-01 이규철 Device for sling pile
KR20120046667A (en) * 2011-03-28 2012-05-10 녹우건설(주) Device for sling pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2745322B2 (en) 1989-04-26 1998-04-28 三和テッキ株式会社 Hanging fittings for steel pipes for steel towers
JPH08158359A (en) * 1994-12-02 1996-06-18 Kubota Corp Connecting method for steel pipe pile
KR101038453B1 (en) 2010-11-02 2011-06-01 이규철 Device for sling pile
KR20120046667A (en) * 2011-03-28 2012-05-10 녹우건설(주) Device for sling pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190109748A (en) * 2017-01-30 2019-09-26 아이에이취시 홀랜드 아이이 비.브이. System used in crane of ship
KR102497762B1 (en) 2017-01-30 2023-02-10 아이큐아이피 홀딩 비.브이. System used in ship's crane
US11945694B1 (en) * 2020-07-23 2024-04-02 The Crosby Group LLC Master link test fixture assembly
KR20220051658A (en) 2020-10-19 2022-04-26 김형민 Pile connecting device

Similar Documents

Publication Publication Date Title
KR101215356B1 (en) Device for sling pile
KR101038453B1 (en) Device for sling pile
KR101800327B1 (en) Device for fling pile
KR200467345Y1 (en) A pile lifting structrue
KR101272430B1 (en) A pile lifting structrue
US20120061112A1 (en) Method and apparatus for installing a shank within a ripper assembly of a tractor/crawler involving a rotating shank installer
KR200476243Y1 (en) Anchor frame for tower crain
JP6223701B2 (en) Heavy lifting tool
US6405460B1 (en) Excavator bucket attachment
JP6068774B1 (en) Earth retaining prior construction method using adjustable erection
JP2012002030A (en) Temporary scaffold for slope face and installation method of the same
KR101645013B1 (en) Attachment of Excavator
AU2013216670A1 (en) Automatic safety device for quick coupler
KR20200009604A (en) Pile lifting device and construction method using the same
KR101217189B1 (en) The soil excavation device for pipe type tunnel
US20060108568A1 (en) Power driven tree stand
US7090199B2 (en) Base for use with a pole puller
JP2005096984A (en) Lever rod for heavy object
US6863262B2 (en) Pole bridle
US9497906B2 (en) Method of assembling a platform to support a tree and rootball for tree relocation
CN204431473U (en) Beam slab stretching construction support
KR102270545B1 (en) Device for insertion and sling pile, and construction method thereof
JP5729670B1 (en) Temporary fence fixing method and anchor in soil
JP5618201B2 (en) Lifting method of prefabricated manhole using lifting jig for prefabricated manhole
CN211974066U (en) Concrete precast beam

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20180530

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee