KR200441371Y1 - Sleeve for protecting pipe in building - Google Patents

Sleeve for protecting pipe in building Download PDF

Info

Publication number
KR200441371Y1
KR200441371Y1 KR2020070003094U KR20070003094U KR200441371Y1 KR 200441371 Y1 KR200441371 Y1 KR 200441371Y1 KR 2020070003094 U KR2020070003094 U KR 2020070003094U KR 20070003094 U KR20070003094 U KR 20070003094U KR 200441371 Y1 KR200441371 Y1 KR 200441371Y1
Authority
KR
South Korea
Prior art keywords
sleeve
pipe
clamp member
wedge
building
Prior art date
Application number
KR2020070003094U
Other languages
Korean (ko)
Inventor
김성환
Original Assignee
김성환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김성환 filed Critical 김성환
Priority to KR2020070003094U priority Critical patent/KR200441371Y1/en
Application granted granted Critical
Publication of KR200441371Y1 publication Critical patent/KR200441371Y1/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • F16L5/06Sealing by means of a swivel nut compressing a ring or sleeve

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

본 고안은 건축물의 배관을 보호하기 위한 슬리브에 관한 것으로, 더욱 상세하게는 슬리브 내부를 통해 삽입되는 배관을 슬리브의 중심부에 정확히 위치되게 잡아줄 수 있도록 한 건축물의 배관 보호용 슬리브 구조체가 제공하는데 있다.The present invention relates to a sleeve for protecting a pipe of a building, and more particularly, to provide a pipe protection sleeve structure of a building to hold the pipe inserted through the inside of the sleeve to be accurately positioned in the center of the sleeve.

이를 위해, 본 고안은 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와; 상기 슬리브를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와; 상기 슬리브 내측과 상기 클램프부재 외측면 사이에 분할된 상태로 위치되는 웨이지와; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재의 상단부를 배관에 밀착되게 조여 줌과 더불어 상기 웨이지가 상기 클램프부재를 배관에 밀착되게 가압하도록 하는 조임너트;를 포함하여 구성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체가 제공된다.To this end, the present invention and the sleeve of the hollow structure is installed through the building floor; A clamp member which is divided into two or more in a pair so as to hold the pipe installed through the sleeve to be positioned at the center of the sleeve; A wedge positioned in a divided state between the sleeve inner side and the clamp member outer side surface; And a tightening nut coupled to the upper end of the clamp member to tighten the upper end of the clamp member to be in close contact with the pipe, and the wedge to press the clamp member to be in close contact with the pipe. A sleeve protective structure is provided.

건축물, 배관, 슬리브 Architecture, plumbing, sleeve

Description

건축물의 배관 보호용 슬리브 구조체{Sleeve for protecting pipe in building}Sleeve for protecting pipe in building

도 1은 본 고안의 슬리브 구조체를 나타낸 분해사시도1 is an exploded perspective view showing a sleeve structure of the present invention

도 2는 도 1의 슬리브 구조체의 결합 종단면도2 is a longitudinal cross sectional view of the sleeve structure of FIG. 1;

도 3a 및 도 3b는 도 2의 Ⅰ-Ⅰ선 횡단면도로서, 본 고안의 슬리브 구조체에 의한 배관 고정을 설명하기 위한 작용도3A and 3B are cross-sectional views taken along the line I-I of FIG. 2, and are functional diagrams for explaining the pipe fixing by the sleeve structure of the present invention.

도 3a는 배관에 클램프부재가 밀착되기 전의 상태도Figure 3a is a state diagram before the clamp member is in close contact with the pipe

도 3b는 배관에 클램프부재가 밀착된 후의 상태도Figure 3b is a state diagram after the clamp member is in close contact with the pipe

도 4a 내지 도 4e는 본 고안에 따른 배관 고정 과정을 나타낸 단면도로서,4a to 4e are cross-sectional views showing a pipe fixing process according to the present invention,

도 4a는 콘크리트에 슬리브만이 남아 고정되어 있는 모습을 나타낸 단면도Figure 4a is a cross-sectional view showing that only the sleeve is fixed to the concrete

도 4b는 슬리브 내측에 배관이 위치된 모습을 나타낸 단면도Figure 4b is a cross-sectional view showing a state in which the pipe is located inside the sleeve

도 4c는 슬리브 내측 상부에 제1, 2클램프부재가 결합된 모습을 나타낸 단면도Figure 4c is a cross-sectional view showing a state in which the first and second clamp members are coupled to the upper inner sleeve

도 4d는 슬리브 상부에 패킹이 결합됨과 더불어 슬리브 내측과 제1, 2클램프부재 외측 사이에 웨이지가 결합된 모습을 나타낸 단면도Figure 4d is a cross-sectional view showing the coupling of the wedge between the inside of the sleeve and the first and second clamp members while the packing is coupled to the upper sleeve

도 4e는 배관이 슬리브 중심에 고정되게 조임너트가 제1, 2클램프부재 상부 에 결합된 모습을 나타낸 단면도Figure 4e is a cross-sectional view showing a coupling nut is coupled to the upper portion of the first and second clamp member to secure the pipe to the center of the sleeve

도 5는 도 1의 웨이지의 다른 형상을 나타낸 사시도5 is a perspective view showing another shape of the wedge of FIG.

도 6은 도 5의 웨이지의 저면 사시도6 is a bottom perspective view of the wedge of FIG.

도 7a 및 도 7b는 도 5의 웨이지 적용에 따른 작용도로서,7a and 7b is an operation diagram according to the application of the wedge of Figure 5,

도 7a는 웨이지가 적용되기 전의 상태로서, 배관에 클램프부재가 밀착되기 전의 횡단면도7A is a cross-sectional view before the clamping member is brought into close contact with the pipe as it is before the wedge is applied.

도 7b는 웨이지가 적용된 후의 상태로서, 배관에 클램프부재가 밀착된 후의 횡단면도Figure 7b is a state after the wedge is applied, cross-sectional view after the clamp member is in close contact with the pipe

도 8은 본 고안의 슬리브 구조체의 다른 실시 예를 나타낸 분해 사시도8 is an exploded perspective view showing another embodiment of the sleeve structure of the present invention

도 9a 내지 도 9g는 도 8에 따른 배관 고정을 설명하기 위한 작용도로서,9A to 9G are functional diagrams for describing the pipe fixing according to FIG. 8.

도 9a는 슬리브 상단부 내측과 배관 사이에 지지부재가 일부 결합된 상태로 위치된 모습을 나타낸 종단면도 Figure 9a is a longitudinal cross-sectional view showing a state in which the support member is partially coupled between the inner sleeve upper end and the pipe.

도 9b는 지지부재를 벗어난 위치에 연장된 배관 외주면에 대향되게 클램프부재가 위치된 모습을 나타낸 종단면도Figure 9b is a longitudinal cross-sectional view showing a state in which the clamp member is positioned to face the outer peripheral surface of the pipe extending in the position out of the support member

도 9c는 클램프부재의 상단부를 조임너트로 일부 체결하여 배관에 고정된 상태의 모습을 나타낸 종단면도Figure 9c is a longitudinal cross-sectional view showing a state in which the upper part of the clamp member is fastened to the pipe by tightening a part of the tightening nut.

도 9d는 지지부재 내측에 클램프부재가 위치되게 결합시킨 모습을 나타낸 종단면도Figure 9d is a longitudinal cross-sectional view showing a state in which the clamp member is positioned inside the support member

도 9e는 슬리브 상단부에 지지부재를 고정하는 웨이지를 안내홈을 통해 지지부재 내측으로 밀어 넣은 상태의 모습을 나타낸 종단면도 Figure 9e is a longitudinal sectional view showing a state in which the way to secure the support member to the upper end of the sleeve pushed into the support member through the guide groove

도 9f는 슬리브 내측에 지지부재를 완전히 결합시킨 상태의 모습을 나타낸 종단면도 Figure 9f is a longitudinal cross-sectional view showing a state in which the support member is fully engaged inside the sleeve

도 9g는 클램프부재의 상단부에 일부 체결된 조임너트를 완전 체결하여 슬리브 중심에 배관을 고정시킨 상태의 모습을 나타낸 종단면도Figure 9g is a longitudinal cross-sectional view showing a state in which the pipe is fixed to the center of the sleeve by fully tightening the tightening nut partially fastened to the upper end of the clamp member

도 10은 도 9g의 Ⅱ - Ⅱ선을 나타낸 횡단면도 FIG. 10 is a cross-sectional view of the II-II line of FIG. 9G. FIG.

도 11은 본 고안의 슬리브 구조체의 또 다른 실시 예를 나타낸 분해 사시도11 is an exploded perspective view showing another embodiment of the sleeve structure of the present invention

도 12a 내지 도 12c는 도 11의 슬리브 구조체의 결합 종단면도로서, 본 고안의 슬리브 구조체에 의한 배관 고정을 설명하기 위한 작용도12a to 12c is a longitudinal cross-sectional view of the sleeve structure of Figure 11, the action diagram for explaining the pipe fixing by the sleeve structure of the present invention

도 12a는 배관이 관통된 슬리브 상단부에 클램프부재가 대향된 상태로 슬리브에 결합되기 전의 모습을 나타낸 종단면도 Figure 12a is a longitudinal sectional view showing a state before the coupling is coupled to the sleeve in the state in which the clamp member is opposed to the upper end of the sleeve through the pipe

도 12b는 슬리브 상단부에 클램프부재가 결합된 후의 모습을 나타낸 종단면도12B is a longitudinal sectional view showing the state after the clamp member is coupled to the upper end of the sleeve;

도 12c는 클램프부재의 상단부에 조임너트를 완전 체결하여 슬리브 중심에 배관을 고정시킨 상태의 모습을 나타낸 종단면도Figure 12c is a longitudinal cross-sectional view showing a state in which the fastening nut is completely fastened to the upper end of the clamp member to secure the pipe in the center of the sleeve

* 도면의 주요부분에 대한 부호의 설명 * Explanation of symbols for main parts of the drawings

100:슬리브 110:요철100: Sleeve 110: Unevenness

120:돌기 200,300:제 1, 2 클램프부재120: projection 200,300: first, second clamp member

210,310,600,800:웨이지 230,330:삽입부210,310,600,800: Wedge 230,330: Insertion part

250,350:체결부 240,340:탄성가압편250, 350: Fastening part 240, 340: Elastic pressing piece

260,360:걸림부 270,370:걸림편260,360: jam 270,370: jam

280,380:수용부 400:조임너트280,380: Receiving part 400: Tightening nut

410:누름부 500:폐킹410: pressing part 500: closing

610:웨이지부 630:연결부610: the way part 630: connection part

700:지지부재 710:안내홈700: support member 710: guide groove

730:걸림부 P:배관730: catching part P: piping

M:슬리브 구조체 M: Sleeve structure

본 고안은 건축물의 배관을 보호하기 위한 슬리브에 관한 것으로, 더욱 상세하게는 슬리브 내부를 통해 삽입되는 배관을 슬리브의 중심부에 정확히 위치되게 잡아줄 수 있도록 한 건축물의 배관 보호용 슬리브 구조체 및 그 시공방법을 제공하는데 있다.The present invention relates to a sleeve for protecting a pipe of a building, and more particularly, to a pipe protection sleeve structure and a construction method of the building to hold the pipe inserted through the sleeve to be accurately positioned in the center of the sleeve. To provide.

일반적으로, 슬리브(Sleeve)는 "긴 축 등을 끼우는 쇠붙이"라는 사전적 의미를 가지고 있으며, 통상 건축분야에서 상기 슬리브는 건물에 설치되는 오수관, 공기관, 배수관 및 급수관 등의 배관을 고정하는데 사용된다.In general, the sleeve (Sleeve) has a preliminary meaning of "metal fittings such as long shafts," and in the construction field, the sleeve is used to fix the pipes such as sewage pipes, air pipes, drain pipes and water supply pipes installed in the building. .

즉, 통상적인 슬리브의 시공방법을 보면 건물 각각의 층에 건물 바닥면 형성을 위한 거푸집이 설치된다. 이때 상기 거푸집의 바닥면에는 상기 슬리브가 정확한 위치에 설치되도록 하기 위해 중심선(원형을 중심으로 십자선이 그어진 상태)을 만 들게 된다. 한편 상기 거푸집의 바닥면에 만들어진 중심선에 상기 슬리브를 정렬하여 고정한 다음, 고정 못으로 상기 슬리브를 고정하게 된다. 이때, 상기 슬리브의 상부에는 이물질 유입 방지를 위한 캡을 씌우게 되고, 상기 캡이 슬리브에 씌어진 상태에서는 상기 거푸집 상부에 콘크리트를 타설하여 일정 양생기간을 경과한 후, 거푸집을 콘크리트로부터 탈거함과 동시에 콘크리트에 매설된 슬리브 내부로 배관을 삽입한 다음 별도의 고정수단인 지지체를 슬리브의 상부에 설치되어 배관을 고정, 마무리하게 된다. 그러나 종래의 슬리브는 배관을 고정하는데 다음과 같은 문제점을 안고 있다.That is, in the construction method of the conventional sleeve formwork for forming the building floor surface is installed on each floor of the building. At this time, the bottom surface of the formwork is to create a centerline (the state in which the crosshairs are drawn around the circle) so that the sleeve is installed in the correct position. Meanwhile, the sleeve is aligned and fixed to a centerline formed on the bottom surface of the formwork, and then the sleeve is fixed with a fixing nail. At this time, the upper part of the sleeve is covered with a cap for preventing foreign matter inflow, and in the state where the cap is covered on the sleeve after pouring concrete to the upper part of the form after a certain curing period, while removing the formwork from the concrete The pipe is inserted into the sleeve embedded in concrete, and then a separate fixing means is installed on top of the sleeve to fix and finish the pipe. However, the conventional sleeve has the following problems in fixing the pipe.

예컨대, 상기 슬리브 내측을 통해 설치되는 배관이 슬리브의 중심에 정확히 위치되지 않은 상태로 설치됨으로써, 슬리브 내측을 통해 설치되는 배관과 배관간의 연결시, 연결위치가 어긋나 이를 연결하는데 어려움을 겪게 되는 문제점이 있다.For example, the pipes installed through the inside of the sleeve are installed in a state not exactly positioned at the center of the sleeve, so that when connecting the pipes and the pipes installed through the inside of the sleeve, there is a problem that the connection position is difficult to connect. have.

즉, 단층 건물이 아니 고층건물에 배관을 설치할 경우 정확한 위치에 배관의 설치작업이 요구된다. 이는 층과 층 사이에 연속적으로 설치되는 배관이 정확한 위치로부터 벗어나거나, 기울어지게 설치되면 상기 배관과 배관의 연결하는데 어려우며, 상기 배관을 통해 배출되는 내용물에 상기 배관이 막히게 되는 문제점이 생기게 된다.In other words, if the pipe is installed in a high-rise building, not a single-story building, the installation work is required at the correct location. It is difficult to connect the pipe and the pipe when the pipes continuously installed between the floors and the floor are deviated or inclined, and the pipes are blocked in the contents discharged through the pipes.

본 고안은 상기한 제반 문제점을 해결하기 위한 것으로서, 본 고안의 목적은 슬리브 상부에 설치되어 슬리브 내부를 통해 삽입되는 배관을 슬리브의 중심부에 신속하면서도 정확히 위치되게 잡아주도록 한 건축물의 배관 보호용 슬리브 구조체를 제공하는데 그 목적이 있다.The present invention is to solve the above-mentioned problems, an object of the present invention is to provide a sleeve structure for protecting the pipe structure of the structure which is installed on the upper sleeve to hold the pipe inserted through the inside of the sleeve quickly and accurately to the center of the sleeve The purpose is to provide.

상기한 목적을 달성하기 위해, 본 고안은 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와; 상기 슬리브를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와; 상기 슬리브 내측과 상기 클램프부재 외측면 사이에 분할된 상태로 위치되는 웨이지와; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재의 상단부를 배관에 밀착되게 조여 줌과 더불어 상기 웨이지가 상기 클램프부재를 배관에 밀착되게 가압하도록 하는 조임너트;를 포함하여 구성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체가 제공된다.In order to achieve the above object, the present invention is a sleeve having a hollow structure installed through the building floor; A clamp member which is divided into two or more in a pair so as to hold the pipe installed through the sleeve to be positioned at the center of the sleeve; A wedge positioned in a divided state between the sleeve inner side and the clamp member outer side surface; And a tightening nut coupled to the upper end of the clamp member to tighten the upper end of the clamp member to be in close contact with the pipe, and the wedge to press the clamp member to be in close contact with the pipe. A sleeve protective structure is provided.

이하, 본 고안의 실시 예를 도 1 내지 도 3을 참조하여 상세히 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail with reference to FIGS. 1 to 3.

도 1은 본 고안의 슬리브 구조체를 나타낸 분해사시도이고, 도 2는 도 1의 슬리브 구조체의 결합 종단면도이며, 도 3a 및 도 3b는 도 2의 Ⅰ-Ⅰ선 횡단면도로서, 본 고안의 슬리브 구조체에 의한 배관 고정과정을 설명하기 위한 작용도이다.1 is an exploded perspective view showing a sleeve structure of the present invention, Figure 2 is a longitudinal cross-sectional view of the sleeve structure of Figure 1, Figures 3a and 3b is a cross-sectional view of the line I-I of FIG. This is an operation diagram for explaining the process of fixing the pipe.

이들 도면을 참조하면, 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브(100)와; 상기 슬리브(100)를 관통하여 설치되는 배관(P)이 슬리브(100) 중심에 위치되게 잡아 줄 수 있도록 2개가 한조를 이루며 각각 분할 형성되는 제 1, 2 클램프부재(200)(300)와; 상기 슬리브(100) 내측과 상기 제 1, 2 클램프부재(200)(300) 외측면 사이에 분할된 상태로 위치되는 웨이지(210)(310)와; 상기 제 1, 2 클램프부재(200)(300)의 상단부에 결합되어 상기 제 1, 2 클램프부재(200)(300)의 상단부를 배관(P)에 밀착되게 조여 줌과 더불어 상기 웨이지(210)(310)가 상기 제 1, 2 클램프부재(200)(300)를 배관(P)에 밀착되게 가압하도록 하는 조임너트(400);를 포함하여 구성된다.Referring to these drawings, the sleeve 100 of the hollow structure is installed through the building floor; First and second clamp members (200) (300) formed in two sets and divided into two groups so that the pipe (P) installed through the sleeve (100) can be held at the center of the sleeve (100); Wedges 210 and 310 positioned in a divided state between the sleeve 100 and the outer surfaces of the first and second clamp members 200 and 300; Wedge 210 is coupled to the upper end of the first and second clamp members 200 and 300 to tighten the upper ends of the first and second clamp members 200 and 300 to be in close contact with the pipe P. And a tightening nut 400 to press the first and second clamp members 200 and 300 to be in close contact with the pipe P.

상기 슬리브(100)는 플라스틱 또는 PVC 재질로 내부가 관통된 중공 구조로서, 상기 슬리브(100)의 축방향에 있어서의 중간 부위의 외경은 콘크리트와의 결합력을 높이기 위해 상기 슬리브(100) 양단부의 외경 보다 작은 외경을 이루도록 형성된다.The sleeve 100 is a hollow structure through which the inside is made of plastic or PVC material, the outer diameter of the intermediate portion in the axial direction of the sleeve 100 is the outer diameter of both ends of the sleeve 100 in order to increase the bonding force with the concrete It is formed to achieve a smaller outer diameter.

이와 더불어 상기와 같이 형성된 상기 슬리브(100)의 중간 부위는 건물 바닥면 형성을 위해 타설되는 콘크리트(CON)와의 결합력을 한층 높이기 위한 미세 요철(110)이 표면에 형성된다.In addition, the middle portion of the sleeve 100 formed as described above is formed with fine concavo-convex 110 on the surface to further increase the bonding force with the concrete (CON) that is poured to form the building floor surface.

또한 상기 슬리브(100)의 중간 부위 외주면 상에는 돌기(120)가 원주방향을 따라 환형 혹은 호형으로 형성됨이 바람직하다.In addition, the protrusion 120 is preferably formed in an annular or arc shape along the circumferential direction on the outer circumferential surface of the middle portion of the sleeve 100.

한편 상기 제 1, 2 클램프부재(200)(300)는 상기 슬리브(100) 내측 상부에 삽입되며 상기 슬리브(100) 내측과 배관(P) 외주면 사이에 위치된다. 또한 상기 제 1, 2 클램프부재(200)(300)는 상기 슬리브(100) 내측 상부에 결합되게 삽입부(230)(330)가 하부측에 형성되고, 상기 삽입부(230)(330)의 직경 보다 작은 직경 으로서 상기 조임너트(400)와 결합되도록 외주면에 나사산이 형성된 체결부(250)(350)가 상기 삽입부(230)(330) 상부에 일체로 형성된다.Meanwhile, the first and second clamp members 200 and 300 are inserted into the upper portion of the sleeve 100 and are positioned between the inner side of the sleeve 100 and the outer peripheral surface of the pipe P. In addition, the first and second clamp members 200 and 300 have insertion portions 230 and 330 formed on the lower side of the first and second clamp members 200 and 300 so as to be coupled to the upper portion of the sleeve 100. Fastening parts 250 and 350 having a thread formed on an outer circumferential surface thereof are integrally formed on the insertion parts 230 and 330 to be combined with the tightening nut 400 as a diameter smaller than the diameter.

또한 상기 삽입부(230)(330)와 체결부(250)(350)의 경계지점 외주면에는 상기 슬리브(100)의 상단부에 걸쳐지게 하여 상기 삽입부(230)(330)만 상기 슬리브(100) 내측으로 삽입되도록 걸림편(270)(370)이 형성된다.In addition, the upper end portion of the sleeve 100 is disposed on the outer circumferential surface of the insertion portion 230, 330 and the fastening portion 250, 350 so that only the insertion portion 230, 330 is the sleeve 100. The engaging pieces 270 and 370 are formed to be inserted inward.

한편 상기 제 1, 2 클램프부재(200)(300)의 외주면에는 상기 웨이지(210)(310)가 형합되는 수용부(280)(380)가 각각 형성되고, 그 수용부(280)(380)는 상기 웨이지(210)(310)의 내주면에 대응되게 테이퍼지게 형성된다.Meanwhile, the outer peripheral surfaces of the first and second clamp members 200 and 300 are provided with accommodating parts 280 and 380 for joining the wedges 210 and 310, respectively, and the accommodating parts 280 and 380. Is tapered to correspond to the inner circumferential surface of the wedges 210 and 310.

또한 상기 수용부(280)(380)에 형합되는 상기 웨이지(210)(310)의 내주면은 상기 수용부(280)(380)에 대응되게 테이퍼지고, 그 상단부에는 상기 슬리브(100) 상단부에 걸려지는 걸림부(210a)(310a)가 형성된다.In addition, the inner circumferential surfaces of the wedges 210 and 310 that are joined to the receiving portions 280 and 380 are tapered to correspond to the receiving portions 280 and 380, and the upper end portion thereof is hung on an upper end portion of the sleeve 100. The stopping portions 210a and 310a are formed.

한편 상기 슬리브(100) 상단부에는 상기 제 1, 2 클램프부재(200)(300)의 걸림편(270)(370)과의 상호 마찰에 따른 소음방지 및 웨이지(210)(310)와 슬리브(100) 사이의 밀폐를 위해 패킹(500)이 더 구비된다.On the other hand, the upper end of the sleeve 100, the noise prevention and the wedge 210, 310 and the sleeve 100 due to mutual friction with the engaging pieces 270, 370 of the first and second clamp members (200, 300) Packing 500 is further provided for sealing between the).

또한 상기 조임너트(400)의 외주면은 조임너트(400)를 풀거나 조을 때 미끌리지 않도록 거친 표면체를 이루고 있으며, 그 하단부 외측으로 가압면적을 증가시키기 위해 직경이 큰 누름부(410)가 형성된다. In addition, the outer circumferential surface of the tightening nut 400 forms a rough surface so as not to slip when loosening or tightening the tightening nut 400, and a pressing part 410 having a large diameter is formed to increase the pressing area outside the lower end thereof. do.

한편 상기 조임너트(400)의 전체 프로파일 단면형상을 다각형 형태로 해도 무방하다.On the other hand, the overall profile cross-sectional shape of the tightening nut 400 may be polygonal.

따라서 본 고안의 슬리브 구조체(M)를 이용한 배관(P)의 고정과정 중 콘크리 트(CON) 양생과정을 거쳐 건물 바닥면에 상기 슬리브(100)만이 남아 고정된 상태에서 상기 제 1, 2 클램프부재(200)(300)와 상기 웨이지(210)(310)와 상기 조임너트(400)의 상호결합에 따른 작용효과를 도 4a 내지 도 4e를 참조하되, 필요에 따라 도 3a 및 도 3b를 참조하여 설명하면 다음과 같다.Therefore, the first and second clamp members in a state in which only the sleeve 100 remains on the building bottom surface through a concrete curing process during the fixing process of the pipe P using the sleeve structure M of the present invention. (200) 300 and the effect of the coupling between the wedge 210, 310 and the tightening nut 400 with reference to Figures 4a to 4e, with reference to Figures 3a and 3b as necessary The explanation is as follows.

먼저, 도 4a를 참조하여 보면, 콘크리트에 슬리브만이 매설되어 고정되어 있게 된다.First, referring to FIG. 4A, only a sleeve is embedded and fixed in concrete.

다음으로, 도 4b 및 도 4c를 참조하여 보면, 슬리브 내측에 배관이 위치되고, 그 슬리브 내측 상부에 제 1, 2 클램프부재가 결합된다.Next, referring to FIGS. 4B and 4C, the pipe is positioned inside the sleeve, and the first and second clamp members are coupled to the inside of the sleeve.

즉, 상기 슬리브(100) 내측에 배관(P)이 설치되고, 그 배관(P) 외측과 상기 슬리브(100) 내측 사이에 삽입되어 상기 배관(P)이 상기 슬리브(100) 중심에 위치되게 잡아주도록 분할된 제 1, 2 클램프부재(200)(300)가 상기 슬리브(100) 상부 내측에 삽입된다.That is, the pipe P is installed inside the sleeve 100 and is inserted between the outside of the pipe P and the inside of the sleeve 100 so that the pipe P is positioned at the center of the sleeve 100. First and second clamp members 200 and 300, which are divided to give, are inserted into the upper part of the sleeve 100.

이때 상기 슬리브(100) 중심으로 분할되게 위치된 상기 제 1, 2 클램프부재(200)(300)는 상기 제 1, 2 클램프부재(200)(300)가 상기 배관(P)에 밀착되지 않은 소정거리(ℓ) 이격된 상태이고, 이는 도 3a에 도시된 바와 같다.In this case, the first and second clamp members 200 and 300 positioned to be divided into the sleeve 100 have a predetermined shape in which the first and second clamp members 200 and 300 are not in close contact with the pipe P. The distance l is spaced apart, as shown in FIG. 3A.

다음으로, 도 4d를 참고하면, 슬리브 상부에 패킹이 위치됨과 더불어 슬리브 내측과 제 1, 2 클램프부재 외측 사이에 웨이지가 삽입된다.Next, referring to FIG. 4D, the packing is positioned on the upper portion of the sleeve, and a wedge is inserted between the inner side of the sleeve and the outer side of the first and second clamp members.

즉, 상기 배관(P)을 중심으로 소정거리(ℓ) 이격된 상기 제 1, 2 클램프부재(200)(300)의 외측과 상기 슬리브(100) 내측 사이 중 수용부(280)(380)에 상기 웨이지(210)(310)가 각각 삽입된다. 이때, 상기 제 1, 2 클램프부재(200)(300)의 수용홈(280)(380)에 삽입되는 상기 웨이지(210)(310)는 상기 제 1, 2 클램프부재(200)(300)를 가압하여 상기 배관(P)에 상기 제 1, 2 클램프부재(200)(300)가 밀착됨으로서 상기 슬리브(100) 중심에 상기 배관(P)이 고정된 상태이고, 이는 도 3b에 도시된 바와 같다.That is, in the receiving portion 280 and 380 between the outside of the first and second clamp members 200 and 300 spaced apart from the pipe P by a predetermined distance ℓ and the inside of the sleeve 100. Wedges 210 and 310 are respectively inserted. In this case, the wedges 210 and 310 inserted into the receiving grooves 280 and 380 of the first and second clamp members 200 and 300 may serve as the first and second clamp members 200 and 300. As the first and second clamp members 200 and 300 are in close contact with the pipe P by being pressurized, the pipe P is fixed to the center of the sleeve 100, as shown in FIG. 3B. .

다음으로, 도 4e를 참고하면, 제 1, 2 클램프부재 상부를 배관(P)에 밀착되게 조임너트가 제 1, 2 클램프부재 상부에 결합된다.Next, referring to FIG. 4E, the tightening nut is coupled to the upper portion of the first and second clamp members to closely contact the upper portion of the first and second clamp members to the pipe P.

즉, 상기 제 1, 2 클램프부재(200)(300)의 체결부에 결합되는 조임너트(400)가 상기 제 1, 2 클램프부재(200)(300)의 상단부를 상기 배관(P)에 밀착되게 조여 주게 되고, 또한 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)에 상기 조임너트(400)가 결합되는 과정에서 상기 웨이지(210)(310) 상단부를 가압하게 되고, 상기 조임너트(400)에 가압되는 상기 웨이지(210)(310)는 상기 제 1, 2 클램프부재(200)(300)를 가압하여 상기 슬리브(100) 중심에 고정되도록 상기 배관(P)에 더욱 강하게 밀착된다.That is, the tightening nut 400 coupled to the fastening portion of the first and second clamp members 200 and 300 closely adheres to the upper end of the first and second clamp members 200 and 300 to the pipe P. The upper and lower portions of the wedge 210 and 310 are coupled to the fastening nut 400 to the fastening parts 250 and 350 of the first and second clamp members 200 and 300. The wedge 210 and 310 pressurized by the tightening nut 400 pressurizes the first and second clamp members 200 and 300 to fix the pipe 100 to the center of the sleeve 100. It adheres more strongly to P).

한편 상기 슬리브(100) 중심에 고정된 상기 배관(P)을 탈거하고자 할 경우, 상기 조임너트(400)를 체결력이 해제되는 방향으로 풀어주면 상기 조임너트(200)는 상기 제1, 2클램프부재(200)(300)의 체결부(250)(350)로부터 탈거된다.On the other hand, when removing the pipe (P) fixed to the center of the sleeve 100, when the fastening nut 400 is released in the direction in which the tightening force is released, the tightening nut 200 is the first and second clamp members It is detached from the fastening parts 250 and 350 of the 200 and 300.

이로 인해 상기 배관(P)에 밀착된 상기 제1, 2클램프부재(200)(300)의 밀착력이 해제되어 상기 배관(P)은 상기 슬리브(100) 내측으로부터 탈거할 수 있게 된다.As a result, the adhesion of the first and second clamp members 200 and 300 in close contact with the pipe P is released, so that the pipe P can be removed from the inside of the sleeve 100.

또한 상기 조임너트(400)의 전체 프로파일 단면형상을 다각형으로 할 경우 전용의 공구(예:몽키 스패너, 파이프 렌치 등)를 이용 더욱 쉽게 풀어줄 수 있다. In addition, when the overall profile cross-sectional shape of the tightening nut 400 is a polygon, a dedicated tool (for example, a monkey spanner, a pipe wrench, etc.) may be more easily released.

한편 도 5 및 도 6에 도시된 웨이지(600)는 상기 슬리브(100) 내측과 상기 제 1, 2 클램프부재(200)(300) 외측면 사이에 이격된 상태로 삽입되는 웨이지부(610)와, 상기 웨이지부(610) 상부를 연결하는 연결부(630)로 구성되는 것으로, 이에 따른 효과는 상기 웨이지부(610)가 연결부(630)로 연결되어 있기 때문에 한 쌍으로 이루어진 상기 웨이지부(610)를 관리하는데 효과적 이다.Meanwhile, the wedge 600 illustrated in FIGS. 5 and 6 has a wedge 610 inserted into the sleeve 100 and spaced apart from the outer surface of the first and second clamp members 200 and 300. And the connection part 630 connecting the upper part of the wedge part 610. The effect thereof is that the wedge part 610 is connected to the connection part 630. Effective in managing

여기서 도 4a 내지 도 4e를 포함하여 도 3a 및 도 3b에 적용된 웨이지(210)(310) 대신 상기 웨이지(600)를 적용할 경우 상기에서 설명된 작용과 동일하므로 이에 따른 내용 설명은 생략한다.Herein, when the wedge 600 is applied instead of the wedge 210 and 310 applied to FIGS. 3A and 3B including FIGS. 4A to 4E, the description thereof will be omitted.

도 7a 및 도 7b는 도 5 및 도 6의 웨이지(600) 적용시의 도 2의 Ⅰ-Ⅰ선에 대응하는 횡단면도로서, 도 7a는 웨이지가 적용되기 전의 상태로서, 배관에 클램프부재가 밀착되기 전의 횡단면도이고, 도 7b는 웨이지가 적용된 후의 상태로서, 배관에 클램프부재가 밀착된 후의 횡단면도이다.7A and 7B are cross-sectional views corresponding to line I-I of FIG. 2 when the wedge 600 is applied to FIGS. 5 and 6, and FIG. 7A is a state before the wedge is applied, and the clamp member is in close contact with the pipe. 7B is a cross-sectional view after the clamp member is in close contact with the pipe as a state after the wedge is applied.

한편 본 고안의 다른 실시 예를 도 8 내지 도 10을 참조하여 상세히 설명하면 다음과 같다.Meanwhile, another embodiment of the present invention will be described in detail with reference to FIGS. 8 to 10.

도 8은 본 고안의 슬리브 구조체의 다른 실시 예를 나타낸 분해 사시도이고, 도 9a 내지 도 9g는 도 8에 따른 배관 고정을 설명하기 위한 작용도이며, 도 10은 도 9g의 Ⅱ - Ⅱ선을 나타낸 횡단면도이다. 8 is an exploded perspective view showing another embodiment of the sleeve structure of the present invention, Figures 9a to 9g is a functional diagram for explaining the pipe fixing according to Figure 8, Figure 10 is a line II-II of Figure 9g Cross section view.

본 고안의 또 다른 실시 예를 설명하기에 앞서, 도 1에 도시된 슬리브(100), 제 1, 2 클램프부재(200)(300), 조임너트(400)의 구성과 동일하게 이루어지는 부분 에 대해서는 동일한 부호를 적용하여 설명한다.Prior to describing another embodiment of the present invention, for the parts made in the same manner as the configuration of the sleeve 100, the first and second clamp members 200 and 300, and the tightening nut 400 shown in FIG. The same code | symbol is applied and demonstrated.

도 8을 참조하면, 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브(100)와; 상기 슬리브(100) 내측에 위치되며 외주면상에 안내홈(710)이 다수개 형성되는 지지부재(700)와; 상기 지지부재(700)를 관통하여 설치되는 배관(P)이 슬리브(100) 중심에 위치되게 잡아 줄 수 있도록 2개가 한조를 이루며 각각 분할 형성되는 제 1, 2 클램프부재(200)(300)와; 상기 지지부재(700)의 안내홈(710)에 삽입되는 웨이지(800)와; 상기 제 1, 2 클램프부재(200)(300)의 상단부에 결합되어 상기 제 1, 2 클램프부재(200)(300)의 상단부를 배관(P)에 밀착되게 조여 줌과 더불어 상기 웨이지(800)가 상기 제 1, 2 클램프부재(200)(300)를 배관(P)에 밀착되게 가압하도록 하는 조임너트(400);를 포함하여 구성된다.Referring to Figure 8, the sleeve 100 of the hollow structure is installed through the building bottom surface; A support member 700 located inside the sleeve 100 and having a plurality of guide grooves 710 formed on an outer circumferential surface thereof; The first and second clamp members 200 and 300 which are divided into two sets are formed so that the pipe P installed through the support member 700 can be positioned at the center of the sleeve 100. ; Wedge 800 is inserted into the guide groove 710 of the support member 700; The wedge 800 is coupled to the upper end of the first and second clamp members 200 and 300 to tighten the upper end of the first and second clamp members 200 and 300 to be in close contact with the pipe P. It comprises a; fastening nut 400 to press the first and second clamp members 200, 300 in close contact with the pipe (P).

이때 상기 지지부재(700)의 상단부에는 상기 슬리브(100)의 상단부에 걸리는 걸림부(730)가 외측으로 절곡되게 형성된다.At this time, the upper end of the support member 700 is formed so that the engaging portion 730 is caught to the upper end of the sleeve 100 is bent to the outside.

또한 상기 웨이지(800)는 상기 제 1, 2 클램프부재(200)(300) 내측에 삽입된 배관(P)의 축방향 이동을 방지하도록 상기 제 1, 2 클램프부재(200)(300) 외측에 대응되게 테이퍼진다. In addition, the wedge 800 is outside the first and second clamp members 200 and 300 to prevent axial movement of the pipe P inserted into the first and second clamp members 200 and 300. Correspondingly tapered.

한편 상기 제 1, 2 클램프부재(200)(300)는 상기 슬리브(100) 내측 상부에 결합되게 삽입부(230)(330)가 하부측에 형성되고, 상기 삽입부(230)(330) 상부에는 상기 삽입부(230)(330)의 직경 보다 작은 직경으로 조임너트(400)와 결합되도록 외주면에 나사산이 형성된 체결부(250)(350)가 일체로 형성된다.Meanwhile, the first and second clamp members 200 and 300 have insertion portions 230 and 330 formed on the lower side of the first and second clamp members 200 and 300 so as to be coupled to the upper portion of the sleeve 100 and the upper portions of the insertion portions 230 and 330. The fastening parts 250 and 350 having a screw thread formed on the outer circumferential surface thereof are integrally formed to be coupled to the tightening nut 400 to a diameter smaller than the diameter of the insertion parts 230 and 330.

이때 상기 제 1, 2 클램프부재(200)(300)의 삽입부(230)(330)는 아래에서 위 로 테이퍼진다.At this time, the insertion portions 230 and 330 of the first and second clamp members 200 and 300 are tapered from the bottom up.

따라서 본 고안의 일실시예에 따른 슬리브 조립체 시공 과정 및 그 과정에서의 작용효과는 다음과 같다.Therefore, the sleeve assembly construction process according to an embodiment of the present invention and the effects in the process are as follows.

먼저, 도 9a를 참조하여 보면, 슬리브(100) 상단부 내측과 배관(P) 사이에 지지부재(700)가 일부 결합된 상태로 위치된다.First, referring to FIG. 9A, the support member 700 is positioned between the inside of the upper end of the sleeve 100 and the pipe P in a partially coupled state.

즉, 가상선 상태에 위치해 있던 상기 지지부재(700)가 화살표 방향으로 이동시 상기 지지부재(700)의 안내홈(710)에 결합되며 외측으로 일부 돌출된 상기 웨이지(210)(310)들이 상기 슬리브(100) 상단부에 얹혀지게 된다. 이로 인해, 상기 지지부재(700)의 일부분만 상기 슬리브(100) 상단부 내측에 삽입된다.That is, when the support member 700 positioned in the imaginary line state moves in the direction of the arrow, the wedges 210 and 310 which are coupled to the guide groove 710 of the support member 700 and protrude outwardly are sleeves. 100 will be placed on the upper end. For this reason, only a part of the support member 700 is inserted inside the upper end of the sleeve 100.

다음으로, 도 9b와 같이 지지부재(700)를 벗어난 위치에 연장된 배관(P) 외주면에 대향된 2개의 제 1, 2 클램프부재(200)(300)가 위치하게 된후, 도 9C와 같이 상기 제 1, 2 클램프부재(200)(300)의 상단부를 조임너트(400)로 일부 체결한다.Next, as shown in FIG. 9C, two first and second clamp members 200 and 300 opposed to the outer circumferential surface of the pipe P extended to a position outside the support member 700 are positioned as shown in FIG. 9B. The upper ends of the first and second clamp members 200 and 300 are partially fastened to the tightening nut 400.

즉, 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)에 조임너트(400)를 체결하되, 상기 배관(P)에 상기 제 1, 2 클램프부재(200)(300)가 고정된 상태만 유지되게 상기 체결부(250)(350)에 상기 조임너트(400)를 일부만 체결하게 된다.That is, the fastening nut 400 is fastened to the fastening parts 250 and 350 of the first and second clamp members 200 and 300, but the first and second clamp members 200 are connected to the pipe P. Only a part of the tightening nut 400 is fastened to the fastening parts 250 and 350 so that the 300 remains fixed.

다음으로, 도 9d를 참조하여 보면, 지지부재(700) 내측에 상기 제 1, 2 클램프부재(200)(300)가 위치되게 한다.Next, referring to FIG. 9D, the first and second clamp members 200 and 300 are positioned inside the support member 700.

즉, 상기 슬리브(100) 상단부 내측에 일부분만 결합된 상태인 상기 지지부 재(700) 상부에 상기 제 1, 2 클램프부재(200)(300)를 상기 배관(P)에 고정시키는 상기 조임너트(400)의 누름부(410) 부분이 얹혀진 상태가 되고, 상기 지지부재(700) 내측에는 상기 제 1, 2 클램프부재(200)(300)가 위치된다.That is, the tightening nut for fixing the first and second clamp members 200 and 300 to the pipe P on the upper portion of the support member 700 in which only a part of the sleeve 100 is coupled inside the upper end of the sleeve 100. The pressing portion 410 of the 400 is placed on the state, and the first and second clamp members 200 and 300 are positioned inside the support member 700.

다음으로, 도 9e를 참조하여 보면, 슬리브(100) 상단부에 지지부재(700)를 고정하는 웨이지(800)를 안내홈(710)을 통해 지지부재(700) 내측으로 밀어 넣게 된다.Next, referring to FIG. 9E, the wedge 800 fixing the support member 700 to the upper end of the sleeve 100 is pushed into the support member 700 through the guide groove 710.

즉, 상기 슬리브(100) 상단부에 걸쳐진 상기 웨이지(800)들을 상기 지지부재(700)의 안내홈(710) 내측으로 밀어 주면, 상기 지지부재(700)는 상기 슬리브(100) 내측으로 삽입시 상기 슬리브(100)에 간섭을 받지 않게 된다.That is, when the wedges 800 spanning the upper end of the sleeve 100 are pushed into the guide groove 710 of the support member 700, the support member 700 is inserted into the sleeve 100. There is no interference with the sleeve 100.

다음으로, 도 9f를 참조하여 보면, 슬리브(100) 내측에 지지부재(700)를 완전히 삽입한 상태가 된다.Next, referring to FIG. 9F, the support member 700 is completely inserted into the sleeve 100.

즉, 상기 슬리브(100) 상단부에 상기 지지부재(700)의 걸림부(730)가 얹혀진 상태가 된다. That is, the engaging portion 730 of the support member 700 is placed on the upper end of the sleeve 100.

다음으로, 도 9g를 참조하여 보면, 클램프부재의 상단부에 일부 체결된 조임너트를 완전 체결하여 슬리브 중심에 배관을 고정시킨 상태가 된다.Next, referring to FIG. 9G, the fastening nut partially fastened to the upper end of the clamp member is completely fastened to fix the pipe at the center of the sleeve.

즉, 상기 배관(P)에 고정되게 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)를 고정하고 있는 상기 조임너트(400)를 조임력이 이루어지는 방향으로 더 돌려주면 상기 제 1, 2 클램프부재(200)(300)는 상승된다.That is, further turning the tightening nut 400 holding the fastening portions 250 and 350 of the first and second clamp members 200 and 300 to be fixed to the pipe P in the direction of tightening force. The main surface of the first and second clamp members 200 and 300 is raised.

또한 상기 제 1, 2 클램프부재(200)(300)의 테이퍼진 부분과 상기 웨이지(210)(310)의 테이퍼진 부분은 도 10에 도시된 바와 같이 밀착되면서 상기 제 1, 2 클램프부재(200)(300)를 가압하여 상기 배관(P)에 상기 제 1, 2 클램프부재(200)(300)를 밀착시킨다.In addition, the tapered portions of the first and second clamp members 200 and 300 and the tapered portions of the wedge 210 and 310 are in close contact with each other as shown in FIG. Press the 300 to closely contact the first and second clamp members 200 and 300 to the pipe P.

부언컨대, 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)를 조여 주는 상기 조임너트(400)의 조임력은 상기 제 1, 2 클램프부재(200)(300)를 상기 배관에 밀착되게 조여 주게 됨으로서, 상기 슬리브(100) 중앙에 안정된 상태로 상기 배관(P)이 고정된다.In other words, the tightening force of the tightening nut 400 which tightens the fastening parts 250 and 350 of the first and second clamp members 200 and 300 is the first and second clamp members 200 and 300. By tightening close to the pipe, the pipe (P) is fixed in a stable state in the center of the sleeve (100).

한편 상기 슬리브(100) 중심에 고정된 상기 배관(P)을 탈거하고자 할 경우, 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)로부터 상기 조임너트(400)를 조임력이 해제되는 방향으로 풀어주면 상기 배관(P)을 밀착하고 있는 상기 제 1, 2 클램프부재(200)(300)의 밀착력이 해제되고, 이에 따라 상기 슬리브(100)로부터 상기 배관(P)을 탈거할 수 있게 된다.Meanwhile, when the pipe P fixed to the center of the sleeve 100 is to be removed, the fastening nut 400 is fastened from the fastening portions 250 and 350 of the first and second clamp members 200 and 300. When release in the direction in which the tightening force is released, the adhesive force of the first and second clamp members (200, 300) in close contact with the pipe (P) is released, thereby the pipe (P) from the sleeve 100 You can remove the.

한편 본 고안의 또 다른 실시 예를 도 11 및 도 12를 참조하여 상세히 설명하면 다음과 같다.Meanwhile, another embodiment of the present invention will be described in detail with reference to FIGS. 11 and 12.

도 11은 본 고안의 슬리브 구조체의 또 다른 실시 예를 나타낸 분해 사시도이고, 도 12a 및 도 12b는 도 11의 슬리브 구조체의 결합 종단면도로서, 본 고안의 슬리브 구조체에 의한 배관 고정을 설명하기 위한 작용도이이다.11 is an exploded perspective view showing still another embodiment of the sleeve structure of the present invention, Figures 12a and 12b is a coupling longitudinal cross-sectional view of the sleeve structure of Figure 11, the operation for explaining the pipe fixing by the sleeve structure of the present invention Doi is.

본 고안의 또 다른 실시 예를 설명하기에 앞서, 도 1에 도시된 슬리브(100), 제 1, 2 클램프부재(200)(300), 조임너트(400)의 구성과 동일하게 이루어지는 부분에 대해서는 동일한 부호를 적용하여 설명한다.Before describing another embodiment of the present invention, for the parts made in the same manner as the configuration of the sleeve 100, the first and second clamp members 200, 300, and the tightening nut 400 shown in FIG. The same code | symbol is applied and demonstrated.

도 11을 참조하면, 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리 브(100)와; 상기 슬리브(100)를 관통하여 설치되는 배관(P)이 슬리브(100) 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 제 1, 2 클램프부재(200)(300)와; 상기 제 1, 2 클램프부재(200)(300)의 상단부에 결합되어 상기 제 1, 2 클램프부재(200)(300)가 배관(P)에 밀착되게 조여지게 하는 조임너트(400);를 포함하여 구성되되, 상기 분할 형성된 각 제 1, 2 클램프부재(200)(300)의 외주면상에는 슬리브(100) 내측으로 삽입시 상기 제 1, 2 클램프부재(200)(300)의 내주면이 배관(P) 외주면에 밀착되도록 하는 복수개의 탄성가압편(240)(340)이 돌출 형성된다.Referring to Figure 11, and the sleeve 100 of the hollow structure is installed through the building floor; The first and second clamp members 200 and 300 are divided into two or more in a set so that the pipe P installed through the sleeve 100 can be positioned at the center of the sleeve 100. Wow; A fastening nut 400 coupled to the upper ends of the first and second clamp members 200 and 300 to tighten the first and second clamp members 200 and 300 to be in close contact with the pipe P. The inner circumferential surface of the first and second clamp members 200 and 300 is inserted into the sleeve 100 on the outer circumferential surface of each of the divided first and second clamp members 200 and 300. A plurality of elastic pressing pieces 240 and 340 to be in close contact with the outer circumferential surface is protruded.

또한 상기 탄성가압편(240)(340)들은 상기 제 1, 2 클램프부재(200)(300)의 외주면상에서 수평방향으로 돌출된 상태에서 다시 하방으로 절곡되고, 그 절곡된 끝단부 외측면은 슬리브(100) 내부로의 삽입이 용이하도록 경사지게 형성된다.In addition, the elastic pressing pieces 240 and 340 are bent downward again in a state of protruding in the horizontal direction on the outer circumferential surface of the first and second clamp members 200 and 300, the bent end outer surface is a sleeve 100 is formed to be inclined to facilitate insertion into the interior.

한편 상기 탄성가압편(240)(340)들의 수평방향 돌출된 부분에는 수평방향으로 더 연장된 걸림부(260)(360)가 구비된다.Meanwhile, the horizontally protruding portions of the elastic pressing pieces 240 and 340 are provided with locking portions 260 and 360 extending further in the horizontal direction.

따라서 본 고안의 또 다른 실시예에 따른 슬리브 조립체 시공 과정 및 그 과정에서의 작용효과는 다음과 같다.Therefore, the sleeve assembly construction process according to another embodiment of the present invention and the effects in the process are as follows.

도 12a를 참조하면, 배관(P)이 관통된 슬리브(100) 상단부에 제 1, 2 클램프부재(200)(300)가 상기 배관(P)을 중심으로 대향되게 위치된다.Referring to FIG. 12A, first and second clamp members 200 and 300 are positioned to face the pipe P at an upper end portion of the sleeve 100 through which the pipe P passes.

다음으로, 도 12b를 참조하면, 상기 슬리브(100) 내측에 위치된 배관(P) 외주면과 상기 슬리브(100) 내측 사이에 상기 제 1, 2 클램프부재(200)(300)가 대향되게 결합된다.Next, referring to FIG. 12B, the first and second clamp members 200 and 300 are opposed to each other between the outer peripheral surface of the pipe P located inside the sleeve 100 and the inside of the sleeve 100. .

즉, 상기 슬리브(100) 상부를 통해 삽입되는 상기 제 1, 2 클램프부재(200)(300)는 상기 배관(P) 외주면에 상기 제 1, 2 클램프부재(200)(300)의 내주면이 밀착된 상태에서 상기 제 1, 2 클램프부재(200)(300)의 외주면에 돌출 형성된 상기 탄성가압편(240)(340)들이 상기 슬리브(100) 내측으로 삽입된다.That is, the first and second clamp members 200 and 300 inserted through the sleeve 100 are in close contact with the inner circumferential surface of the first and second clamp members 200 and 300 to the outer circumferential surface of the pipe P. The elastic pressing pieces 240 and 340 protruding from the outer circumferential surfaces of the first and second clamp members 200 and 300 in the state of being inserted are inserted into the sleeve 100.

이때 슬리브(100) 내부로 삽입되는 상기 탄성가압편(240)(340)들의 끝단부는 경사진 부분이 최하점(a)과 최상점(b)으로 구분되는데, 도 12a에 도시된 바와 같이 상기 최하점(a)이 이루는 직경은 상기 슬리브(100)의 직경 보다 작은 직경을 이루게 되고, 상기 최상점(b)이 이루는 직경은 상기 슬리브(100)의 직경 보다 큰 직경을 이루게 된다.In this case, the end portions of the elastic pressing pieces 240 and 340 inserted into the sleeve 100 are divided into a lowermost point (a) and a highest point (b), as shown in FIG. 12A. The diameter formed by a) is smaller than the diameter of the sleeve 100, and the diameter formed by the uppermost point b is larger than the diameter of the sleeve 100.

상기에서와 같이, 상기 슬리브(100) 내부로 상기 제 1, 2 클램프부재(200)(300)를 삽입하게 되면 상기 제 1, 2 클램프부재(200)(300)의 탄성가압편(240)(340)들 끝단부 최상점(b)의 직경이 상기 슬리브(100)의 직경 보다 크기 때문에 상기 탄성가압편(240)(340)들이 상기 슬리브(100) 내면에 의해 내측으로 가압되고, 양측 상기 제 1, 2 클램프(200)(300)는 서로 맞닿는 방향으로 이동된다.As described above, when the first and second clamp members 200 and 300 are inserted into the sleeve 100, the elastic pressing pieces 240 of the first and second clamp members 200 and 300 ( Since the diameter of the uppermost point b of the ends 340 is larger than the diameter of the sleeve 100, the elastic pressing pieces 240 and 340 are pressed inward by the inner surface of the sleeve 100, and both sides of the first The first and second clamps 200 and 300 are moved in contact with each other.

따라서 상기 배관(P) 외주면에 상기 제 1, 2 클램프부재(200)(300)의 내주면이 밀착된다.Therefore, the inner circumferential surfaces of the first and second clamp members 200 and 300 are in close contact with the outer circumferential surface of the pipe P.

한편 상기 제 1, 2 클램프부재(200)(300)가 상기 슬리브(100) 내측에 완전히 결합되지 않도록 상기 탄성가압편(240)(340)들의 일측에 형성된 걸림부(260)(360)가 상기 슬리브(100) 상부에 걸쳐지게 된다.Meanwhile, the locking parts 260 and 360 formed on one side of the elastic pressing pieces 240 and 340 are not coupled to the first and second clamp members 200 and 300 inside the sleeve 100. It will be over the sleeve 100.

다음으로, 도 12c를 참조하여 보면, 상기 제 1, 2 클램프부재(200)(300)의 상단부에 조임너트(400)를 완전 체결하여 상기 슬리브(100) 중심에 배관(P)을 고정시키게 된다. Next, referring to FIG. 12C, the fastening nut 400 is completely fastened to the upper ends of the first and second clamp members 200 and 300 to fix the pipe P at the center of the sleeve 100. .

즉, 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)에 상기 조임너트(400)가 조임력이 이루어지는 방향으로 돌려주면 상기 제 1, 2 클램프부재(200)(300)의 상단부를 조여주게 됨은 물론, 상기 제 1, 2 클램프부재(200)(300)의 외주면에 형성된 상기 탄성가압편(240)(340)들을 추가적으로 가압하여 상기 슬리브(100) 중앙에 더욱 안정된 상태로 상기 배관(P)이 고정된다.That is, when the tightening nut 400 is turned in the direction in which the tightening force is applied to the fastening parts 250 and 350 of the first and second clamp members 200 and 300, the first and second clamp members 200 ( Tightening the upper end of the 300, as well as by further pressing the elastic pressing pieces 240, 340 formed on the outer circumferential surface of the first, second clamp member 200, 300 is more stable in the center of the sleeve 100 The pipe P is fixed in the state.

이때 상기 탄성가압편(240)(340)들의 상부를 상기 조임너트(400)의 누름부(410)가 눌러 주게되어 상기 슬리브(100) 내측면에 상기 탄성가압편(240)(340)들의 밀착력은 더 증가 된다.At this time, the pressing portion 410 of the tightening nut 400 presses the upper portions of the elastic pressing pieces 240 and 340 so that the adhesion force of the elastic pressing pieces 240 and 340 to the inner surface of the sleeve 100 is increased. Is further increased.

한편 상기 슬리브(100) 중심에 고정된 상기 배관(P)을 탈거하고자 할 경우, 상기 제 1, 2 클램프부재(200)(300)의 체결부(250)(350)로부터 상기 조임너트(400)를 조임력이 해제되는 방향으로 풀어주면 상기 배관(P)을 밀착하고 있는 상기 제 1, 2 클램프부재(200)(300)의 밀착력이 해제되고, 또한 상기 슬리브(100) 내측면에 밀착되어 있던 상기 탄성가압편(240)(340)들의 밀착력이 해제됨으로서, 상기 슬리브(100)로부터 상기 배관(P)을 탈거할 수 있게 된다.Meanwhile, when the pipe P fixed to the center of the sleeve 100 is to be removed, the fastening nut 400 is fastened from the fastening portions 250 and 350 of the first and second clamp members 200 and 300. When released in the direction in which the tightening force is released, the adhesive force of the first and second clamp members (200, 300) in close contact with the pipe (P) is released, and the close contact with the inner surface of the sleeve (100) As the adhesive force of the elastic pressing pieces 240 and 340 is released, the pipe P may be removed from the sleeve 100.

여기서, 미설명 부호 230,330은 슬리브(100)에 삽입되는 삽입부, 500은 제 1, 2 클램프부재(200)(300)와 슬리브(100) 상부 사이에 놓이는 패킹이다.Here, reference numerals 230 and 330 denote insertion parts inserted into the sleeve 100, and 500 is a packing placed between the first and second clamp members 200 and 300 and the upper portion of the sleeve 100.

이상과 같이 된 본 고안은 다음과 같은 효과가 있다.The present invention as described above has the following effects.

즉, 슬리브 상부에 설치되어 슬리브 내부를 통해 삽입되는 배관을 슬리브의 중심부에 신속하면서도 정확히 위치되게 잡아주게 되어 배관과 배관간의 연결시, 서로 어긋나지 않게 연결할 수 있으므로 작업시간을 단축시킬 수 있는 효과가 있다.That is, the pipe is installed on the top of the sleeve to be inserted through the inside of the sleeve to hold the center of the sleeve quickly and precisely, when the connection between the pipe and the pipe can be connected to each other, there is an effect that can reduce the working time. .

Claims (11)

건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와;A sleeve having a hollow structure installed through the building bottom surface; 상기 슬리브를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와;A clamp member which is divided into two or more in a pair so as to hold the pipe installed through the sleeve to be positioned at the center of the sleeve; 상기 슬리브 내측과 상기 클램프부재 외측면 사이에 분할된 상태로 위치되는 웨이지와;A wedge positioned in a divided state between the sleeve inner side and the clamp member outer side surface; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재의 상단부를 배관에 밀착되게 조여 줌과 더불어 상기 웨이지가 상기 클램프부재를 배관에 밀착되게 가압하도록 하는 조임너트;를 포함하여 구성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.And a tightening nut coupled to the upper end of the clamp member to tighten the upper end of the clamp member to be in close contact with the pipe, and the wedge to press the clamp member to be in close contact with the pipe. Sleeve protection structure for piping. 제 1 항에 있어서,The method of claim 1, 상기 웨이지의 내주면이 테이퍼지게 형성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.Sleeve structure for protecting the piping of the building, characterized in that the inner peripheral surface of the wedge is tapered. 제 1 항에 있어서,The method of claim 1, 상기 클램프부재는 외주면에 상기 웨이지가 형합되는 수용부가 형성되고, 그 수용부는 상기 웨이지의 내주면에 대응되게 테이퍼진 형상을 갖는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.The clamp member is formed on the outer circumferential surface of the receiving portion is formed, the receiving portion, the receiving portion has a tapered protection structure of the building, characterized in that the tapered shape corresponding to the inner circumferential surface of the wedge. 제 1 항에 있어서,The method of claim 1, 상기 웨이지의 상단부에는 상기 슬리브 상단부에 걸려지는 걸림편이 더 구비되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.The upper end of the wedge is a sleeve structure for protecting the piping structure, characterized in that the hook piece is further provided on the upper end of the sleeve. 제 1 항에 있어서,The method of claim 1, 상기 조임너트의 외주면은 거친 표면체가 더 구비되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.The outer circumferential surface of the tightening nut is a sleeve structure for protecting the piping of the building, characterized in that the surface is further provided. 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와;A sleeve having a hollow structure installed through the building bottom surface; 상기 슬리브를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와;A clamp member which is divided into two or more in a pair so as to hold the pipe installed through the sleeve to be positioned at the center of the sleeve; 상기 슬리브 내측과 상기 클램프부재 외측면 사이에 이격된 상태로 삽입되는 웨이지부와, 상기 웨이지부 상부를 연결하는 연결부로 구성되는 웨이지와;A wedge including a wedge portion inserted between the inner side of the sleeve and an outer surface of the clamp member, and a connecting portion connecting the upper portion of the wedge portion; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재의 상단부를 배관에 밀착되게 조여 줌과 더불어 상기 웨이지의 웨이지부가 상기 클램프부재를 배관에 밀착되게 가압하도록 하는 조임너트;를 포함하여 구성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.And a tightening nut coupled to the upper end of the clamp member to tighten the upper end of the clamp member to be in close contact with the pipe, and a wedge part of the wedge pressurizing the clamp member to be in close contact with the pipe. Sleeve structure for protection of plumbing. 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와;A sleeve having a hollow structure installed through the building bottom surface; 상기 슬리브 내측에 위치되며 외주면상에 안내홈이 다수개 형성되는 지지부재와;A support member positioned inside the sleeve and having a plurality of guide grooves formed on an outer circumferential surface thereof; 상기 지지부재를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와;A clamp member which is divided into two or more in a pair so as to hold a pipe installed through the support member at a center of the sleeve; 상기 지지부재의 안내홈에 삽입되는 웨이지와;A wedge inserted into the guide groove of the support member; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재의 상단부를 배관에 밀착되게 조여 줌과 더불어 상기 웨이지가 상기 클램프부재를 배관에 밀착되게 가압하도록 하는 조임너트;를 포함하여 구성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.And a tightening nut coupled to the upper end of the clamp member to tighten the upper end of the clamp member to be in close contact with the pipe, and the wedge to press the clamp member to be in close contact with the pipe. Sleeve protection structure for piping. 제 7 항에 있어서,The method of claim 7, wherein 상기 웨이지의 내측면이 상기 클램프부재의 외주면에 대응되게 테이퍼지게 형성 되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.Sleeve structure for protecting the piping of the building, characterized in that the inner surface of the wedge is formed to be tapered to correspond to the outer peripheral surface of the clamp member. 건물 바닥면을 관통하여 설치되는 중공 구조의 슬리브와;A sleeve having a hollow structure installed through the building bottom surface; 상기 슬리브를 관통하여 설치되는 배관이 슬리브 중심에 위치되게 잡아 줄 수 있도록 2개 이상이 한조를 이루며 각각 분할 형성되는 클램프부재와;A clamp member which is divided into two or more in a pair so as to hold the pipe installed through the sleeve to be positioned at the center of the sleeve; 상기 클램프부재의 상단부에 결합되어 상기 클램프부재가 배관에 밀착되게 조여지게 하는 조임너트;를 포함하여 구성되되, It is configured to include; a tightening nut coupled to the upper end of the clamp member to tighten the clamp member in close contact with the pipe, 상기 분할 형성된 각 클램프부재의 외주면상에는 슬리브 내측으로 삽입시 상기 클램프부재의 내주면이 배관 외주면에 밀착되도록 하는 탄성가압편이 돌출 형성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.On the outer circumferential surface of each of the divided clamp members formed sleeves for protection of the pipe structure, characterized in that the elastic pressing piece is formed so that the inner circumferential surface of the clamp member is in close contact with the outer circumferential surface when inserted into the sleeve. 제 9 항에 있어서,The method of claim 9, 상기 탄성가압편은The elastic pressing piece 상기 클램프부재의 외주면상에서 수평방향으로 돌출된 상태에서 다시 하방으로 절곡되고, 그 절곡된 끝단부 외측면은 슬리브 내부로의 삽입이 용이하도록 경사지게 형성되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.It is bent downward again in a state protruding in the horizontal direction on the outer peripheral surface of the clamp member, the bent end outer surface is formed to be inclined to facilitate the insertion into the sleeve sleeve structure of a building. 제 9 항에 있어서,The method of claim 9, 상기 탄성가압편의 수평방향으로 돌출된 부분에는 수평방향으로 더 연장된 걸림부가 구비되는 것을 특징으로 하는 건축물의 배관 보호용 슬리브 구조체.The projecting portion of the elastic pressing piece in the horizontal direction, the sleeve structure for protecting the pipe of the building, characterized in that the locking portion further extended in the horizontal direction is provided.
KR2020070003094U 2007-02-22 2007-02-22 Sleeve for protecting pipe in building KR200441371Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020070003094U KR200441371Y1 (en) 2007-02-22 2007-02-22 Sleeve for protecting pipe in building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020070003094U KR200441371Y1 (en) 2007-02-22 2007-02-22 Sleeve for protecting pipe in building

Publications (1)

Publication Number Publication Date
KR200441371Y1 true KR200441371Y1 (en) 2008-08-12

Family

ID=41640062

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020070003094U KR200441371Y1 (en) 2007-02-22 2007-02-22 Sleeve for protecting pipe in building

Country Status (1)

Country Link
KR (1) KR200441371Y1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144056B1 (en) 2010-06-17 2012-05-23 안병득 Quick clamp for supporting wall pipes
KR101241278B1 (en) 2011-10-18 2013-03-15 비에이치아이 주식회사 Tube support for harp module of the heat recovery steam generator
KR200474408Y1 (en) 2014-05-02 2014-09-18 이종식 Jig for hydraulic test
KR20210004878A (en) * 2019-07-03 2021-01-13 강석재 Piping airtight device
KR20220132315A (en) * 2021-03-23 2022-09-30 나윤성 Wall finishing device for piping

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144056B1 (en) 2010-06-17 2012-05-23 안병득 Quick clamp for supporting wall pipes
KR101241278B1 (en) 2011-10-18 2013-03-15 비에이치아이 주식회사 Tube support for harp module of the heat recovery steam generator
KR200474408Y1 (en) 2014-05-02 2014-09-18 이종식 Jig for hydraulic test
KR20210004878A (en) * 2019-07-03 2021-01-13 강석재 Piping airtight device
KR102259022B1 (en) * 2019-07-03 2021-06-01 강석재 Piping airtight device
KR20220132315A (en) * 2021-03-23 2022-09-30 나윤성 Wall finishing device for piping
KR102497744B1 (en) * 2021-03-23 2023-02-07 나윤성 Wall finishing device for piping

Similar Documents

Publication Publication Date Title
KR200441371Y1 (en) Sleeve for protecting pipe in building
KR102505320B1 (en) Standpipe fixed clamp
KR101988611B1 (en) non-slip steel bar reinforcement coupler
KR101076084B1 (en) Pipe fixation for clamp
US20060033003A1 (en) Pocket former
KR100627140B1 (en) pipe supporter
KR102227527B1 (en) Branch pipe binding device that can guarantee a solid state of connection with the main pipe
KR200487780Y1 (en) Pipe fixing band
KR200437763Y1 (en) A sleeve fixture on panal
KR101598339B1 (en) Fastener for deck plate combine
KR200471167Y1 (en) clamp apparatus for sleeve
KR200453521Y1 (en) Watertight pipe connection
KR100979817B1 (en) Surporter for construction
KR200438800Y1 (en) A fixing device for pipe arrangement
KR100739657B1 (en) Sleeve for protecting pipe in building
CN212984207U (en) Prefabricated component assembly body and prefabricated building
KR100748678B1 (en) Sleeve for protecting pipe in building and method for constructing the sam
KR100553529B1 (en) Saparated prevention device for Joining Pipe of mechanical joining or KP mechanical joining
KR200452023Y1 (en) Clamp assembly for scaffolding
KR20170002262A (en) Fixture set with connecting surface for increasing fixation stability
KR101985494B1 (en) Simple pipe joint
KR100915629B1 (en) Pipe fixing device for building construction
KR101785632B1 (en) water and sewage pipe set integrated with protective socket for improved water tightness by prevent breakage of connection end and prevent separation of the pipes
JP2008115911A (en) Packing fastening device in pipe coupling
KR101825740B1 (en) Press wheel for preventing departure of pipes

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
REGI Registration of establishment
LAPS Lapse due to unpaid annual fee