KR102497744B1 - Wall finishing device for piping - Google Patents

Wall finishing device for piping Download PDF

Info

Publication number
KR102497744B1
KR102497744B1 KR1020210037468A KR20210037468A KR102497744B1 KR 102497744 B1 KR102497744 B1 KR 102497744B1 KR 1020210037468 A KR1020210037468 A KR 1020210037468A KR 20210037468 A KR20210037468 A KR 20210037468A KR 102497744 B1 KR102497744 B1 KR 102497744B1
Authority
KR
South Korea
Prior art keywords
pipe
finishing
hole
corrosion
outer circumferential
Prior art date
Application number
KR1020210037468A
Other languages
Korean (ko)
Other versions
KR20220132315A (en
Inventor
나윤성
Original Assignee
나윤성
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 나윤성 filed Critical 나윤성
Priority to KR1020210037468A priority Critical patent/KR102497744B1/en
Publication of KR20220132315A publication Critical patent/KR20220132315A/en
Application granted granted Critical
Publication of KR102497744B1 publication Critical patent/KR102497744B1/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • F16L5/10Sealing by using sealing rings or sleeves only
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L58/00Protection of pipes or pipe fittings against corrosion or incrustation
    • F16L58/18Protection of pipes or pipe fittings against corrosion or incrustation specially adapted for pipe fittings

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
  • Sink And Installation For Waste Water (AREA)
  • Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)

Abstract

본 발명은 배관용 벽체 마감부재에 관한 것으로, 배관을 관통시키기 위해 벽체에 형성된 배관용 관통홀을 마감하기 위해 구비되는 마감부재의 마감용 캡을 상기 배관을 감싸면서 결합된 후, 상기 배관용 관통홀에 삽입하는 것에 의해 걸림돌기를 통하여 배관용 관통홀 내주면에 걸림 고정되면서 마감이 이루질 수 있도록 구성함으로써, 실리콘 작업을 배제할 수 있어 작업비용 절감 및 작업 시간을 단축시킬 수 있고, 배관이 유동하더라도 마감용 캡은 배관용 관통홀로부터 이격되지 않아 마감용 캡의 기능을 유지할 수 있을 뿐만 아니라, 벽체에 형성된 배관용 관통홀과 배관 사이에 마감용 부식방지관을 구성하여, 배관용 관통홀에 위치된 배관의 부식을 지연시킬 수 있도록 구성된다.The present invention relates to a wall finishing member for piping, after a cap for closing a closing member provided to close a through-hole for piping formed in a wall to penetrate the piping is coupled while surrounding the piping, By inserting into the hole, it is configured so that the finish can be achieved while being caught and fixed to the inner circumferential surface of the through-hole for piping through a protrusion, so that silicon work can be eliminated to reduce work cost and work time, and even if the pipe is flowing The cap for finishing not only maintains the function of the cap for finishing as it is not separated from the through-hole for piping, but also forms a corrosion-resistant pipe for finishing between the through-hole for piping formed in the wall and the pipe and is located in the through-hole for piping. It is configured to delay the corrosion of the piping.

Description

배관용 벽체 마감장치{Wall finishing device for piping}Wall finishing device for piping {Wall finishing device for piping}

본 발명은 배관용 벽체 마감장치에 관한 것으로서, 보다 상세하게는 실리콘 작업을 배제할 수 있어 작업비용 절감 및 작업 시간을 단축시킬 수 있고, 배관이 유동하더라도 마감용 캡은 배관용 관통홀로부터 이격되지 않아 마감용 캡의 기능을 유지할 수 있을 뿐만 아니라 마감용 부식방지관으로 인해 벽체의 배관용 관통홀에 위치되는 배관의 부식을 지연시킬 수 있도록 한 배관용 벽체 마감장치에 관한 것이다.The present invention relates to a wall finishing device for piping, and more specifically, it is possible to eliminate silicone work, thereby reducing work costs and shortening working time, and even if the pipe is flowing, the cap for finishing is not separated from the through hole for the pipe. It relates to a wall finishing device for piping, which not only maintains the function of the cap for finishing but also can delay the corrosion of the pipe located in the through hole for piping of the wall due to the anti-corrosion pipe for finishing.

일반적인 건축물에는 가스와, 상,하수도의 공급 그리고 실내에 설치하는 가전제품의 사용을 위해 다양한 위치에 배관을 설치하게 되며, 상기 배관은 벽체를 관통하여 설치하게 되지만 마감상태가 깨끗하게 마감되지 않는 결점이 있다.In a typical building, pipes are installed in various locations for the supply of gas, water, and sewage, and for the use of home appliances installed indoors. there is.

따라서, 벽체를 관통하는 배관을 마감하기 위해서는 외벽과 배관의 주위에 코킹처리를 한 후 외측으로 마감캡을 설치하여 마감상태가 깨끗하게 유지되도록 한다.Therefore, in order to finish the pipe penetrating the wall, caulking is performed around the outer wall and the pipe, and then a closing cap is installed to the outside so that the finished state is kept clean.

그러나 배관이 설치되는 부분의 높이가 다양하게 있으며, 마감을 위한 캡의 설치를 위해서는 양손에 각각 분할된 캡을 잡고 배관의 양쪽에서 결합한 후 캡의 양쪽으로 설치한 후크가 상대편의 구멍을 관통하여 결합되도록 함으로써, 마감이 이루어지게 되므로 양손을 모두 사용하는 불편함이 있고, 작업시 안전사고의 위험성이 있는 결점이 발생하게 된다.However, there are various heights of the part where the pipe is installed, and in order to install the cap for finishing, hold the divided cap in both hands and combine them on both sides of the pipe, and then hooks installed on both sides of the cap penetrate the hole on the other side to combine them. By doing so, since the finish is made, there is inconvenience in using both hands, and a defect that poses a risk of safety accident during work occurs.

그리고 배관을 설치한 후에는 배관에 문제가 발생하게 되어 분리 후 수리를 해야하는 경우가 발생하지만, 종래의 마감캡은 후크 형태로 결합한 것이어서 분리하는 것이 불가능한 결점이 발생하며, 작업을 위해서는 플라스틱으로 이루어진 마감캡을 공구로 파손시켜 제거해야 하는 결점이 발생하여 새로운 마감캡을 필요로 하는 등 많은 결점과 어려움이 발생하게 되었다.In addition, after installing the pipe, problems occur in the pipe and repair after separation occurs. However, the conventional closing cap is hook-shaped, so there is a defect that cannot be separated. Many defects and difficulties occurred, such as the need for a new finishing cap due to the defect that the cap had to be damaged with a tool and removed.

이러한 점을 감안하여 실용신안등록출원번호 20-2015-0000561호에 배관용 벽체 마감캡이 제안된 바 있다.In view of this, a wall cap for piping has been proposed in Utility Model Registration Application No. 20-2015-0000561.

살펴보면 종래의 일반적인 배관용 벽체 마감캡은, 벽체를 관통하는 배관에 양쪽으로 대칭되게 결합하며 분할면과 내경면을 형성하고, 한쪽으로 공간을 형성하여 코킹부와 함께 마감되도록 측면캡이 일정한 두께로 이루어지며 결합돌기가 마주하는 돌기홈에 결합하는 마감캡에 있어서, 상기 내경면의 양쪽 선단에 형성한 분할면에서 한쪽 선단으로 내경면과 같은 호상을 갖도록 결합돌기가 돌출되고, 상기 결합돌기가 형성되지 않은 분할면에서 내경면 방향으로 돌기홈을 형성하여 결합돌기가 위치하도록 위치하도록 형성하되, 상기 결합돌기는 내경면의 연장선에서 돌출되는 내경으로 선단돌기를 더 돌출시켜 배관을 결합하는 것으로 구성된다.Looking at the conventional wall finishing cap for pipe, the side cap has a certain thickness so that it is symmetrically coupled to the pipe penetrating the wall on both sides, forms a dividing surface and an inner diameter surface, and forms a space on one side to be finished with the caulking part. In the closing cap formed and coupled to the protrusion groove facing the engaging protrusion, the engaging protrusion protrudes from the dividing surface formed at both ends of the inner diameter surface to one end to have the same arc shape as the inner diameter surface, and the engaging protrusion is formed. A protruding groove is formed in the direction of the inner diameter surface on the undivided surface so that the coupling protrusion is positioned so that the coupling protrusion is formed by further protruding the tip protrusion to the inner diameter protruding from the extension line of the inner diameter surface to couple the pipe. .

그러나, 이와 같이 구성된 종래의 일반적인 배관용 벽체 마감캡은 상기한 바와 같이 마감캡의 결합돌기가 돌기홈에 삽입되는 것에 의해 결합되도록 구성되는 바, 이는 마감캡의 측면캡들간의 결합으로 상기 마감캡이 벽체에 고정되지 않아 배관의 유동에 의해 마감캡도 벽체에 형성된 배관용 관통홀로 멀어져 마감캡의 기능을 상실하게 되는 단점이 있다. However, as described above, the conventional general pipe wall finishing cap configured as described above is configured to be coupled by inserting the coupling protrusion of the closing cap into the protruding groove, which is coupled between the side caps of the closing cap. Since it is not fixed to the wall, the closing cap also moves away from the through-hole for piping formed in the wall due to the flow of the pipe, thereby losing the function of the closing cap.

실용신안등록출원번호 20-2015-0000561호, 출원일; 2015년01월23일Utility model registration application number 20-2015-0000561, filing date; January 23, 2015

이에, 본 발명은 상술한 문제점을 해소하기 위해 안출된 것으로서, 배관을 관통시키기 위해 벽체에 형성된 배관용 관통홀을 마감하기 위해 구비되는 마감부재의 마감용 캡을 상기 배관을 감싸면서 결합된 후, 상기 배관용 관통홀에 삽입하는 것에 의해 걸림돌기를 통하여 배관용 관통홀 내주면에 걸림 고정되면서 마감이 이루질 수 있도록 구성함으로써, 실리콘 작업을 배제할 수 있어 작업비용 절감 및 작업 시간을 단축시킬 수 있을 뿐만 아니라, 배관이 유동하더라도 마감용 캡은 배관용 관통홀로부터 이격되지 않아 마감용 캡의 기능을 유지할 수 있도록 한 배관용 벽체 마감장치를 제공하는 것에 그 목적이 있다.Therefore, the present invention has been made to solve the above-described problems, and after the cap for closing the closing member provided to close the pipe through-hole formed in the wall to penetrate the pipe is coupled while surrounding the pipe, By inserting into the pipe through-hole, it is configured so that the finish can be achieved while being caught and fixed to the inner circumferential surface of the pipe through-hole through the protrusion, so that silicon work can be eliminated, thereby reducing work costs and shortening work time. Rather, it is an object of the present invention to provide a pipe wall closing device capable of maintaining the function of the cap for finishing without being separated from the pipe through-hole even if the pipe flows.

또한, 본 발명의 또 다른 목적은, 벽체에 형성된 배관용 관통홀과 배관 사이에 마감용 부식방지관을 구성하여, 배관용 관통홀에 위치된 배관의 부식을 지연시킬 수 있도록 한 배관용 벽체 마감장치를 제공하는 것에 있다.In addition, another object of the present invention is to construct a corrosion-resistant pipe for finishing between the pipe through-hole formed in the wall and the pipe, so that the corrosion of the pipe located in the through-hole for pipe can be delayed. It is to provide the device.

본 발명의 다른 목적들은 기술이 진행되면서 명확해질 것이다.Other objects of the present invention will become apparent as the technology progresses.

상술한 목적을 달성하기 위한 본 발명 배관용 벽체 마감장치는, 길이방향으로 절개된 중공의 관으로 형성되어 배관(A) 상에 설치되는 것에 의해 벽체(B)에 형성된 배관용 관통홀(C)에 위치되어 배관(A)의 부식을 지연가능하게 구비되는 마감용 부식방지관(110)과, 제1,1'분할면(131a,131b)을 갖는 제1마감처리부재(131)와, 제2,2'분할면(133a,133b)을 갖는 제2마감처리부재(133)로 이분할되어 결합수단(150)을 통하여 서로 결합되는 것에 의해 상기 마감용 부식방지관(110)을 관통하는 배관(A) 상에 설치되면서 상기 배관용 관통홀(C)의 내측면에 일단이 걸림 고정되어 배관용 관통홀(C)을 마감처리 가능하도록 구비되는 마감용 캡(130)을 포함하는 것을 특징으로 한다.The pipe wall closing device of the present invention for achieving the above object is formed of a hollow pipe cut in the longitudinal direction and installed on the pipe (A) to form a pipe through hole (C) in the wall (B) A corrosion-resistant pipe 110 for finishing provided to delay corrosion of the pipe A and a first finishing member 131 having 1, 1' split surfaces 131a and 131b, The pipe passing through the anti-corrosion pipe 110 for finishing is divided into two into a second finishing member 133 having 2,2' split surfaces 133a and 133b and coupled to each other through a coupling means 150. It is installed on (A) and includes a finishing cap 130 provided so that one end is engaged and fixed to the inner surface of the pipe through hole (C) so that the pipe through hole (C) can be finished. do.

또한, 상기한 마감용 부식방지관(110)은, 벽체(B)에 형성된 배관용 관통홀(C)에 내설되면서 배관(A) 상에 설치할 수 있도록 외주면에는 길이방향으로 절개부(111)가 형성되고, 내주면에는 배관(A)의 외주면과 이격되도록 방사방향으로 일정 간격 복수 개의 마감용 부식 방지돌기(113)가 돌출 형성되어 구비된 것을 특징으로 한다.In addition, the above-described corrosion-resistant pipe 110 for finishing has a cutout 111 in the longitudinal direction on the outer circumferential surface so that it can be installed on the pipe (A) while being installed in the pipe through-hole (C) formed in the wall (B). It is formed, and a plurality of anti-corrosion protrusions 113 for finishing are protruded and provided at regular intervals in the radial direction so as to be spaced apart from the outer circumferential surface of the pipe (A) on the inner circumferential surface.

그리고, 상기한 마감용 캡(130)의 제1마감처리부재(131)는, "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 외주면 반을 감쌀 수 있도록 제1접촉면(131c)이 형성되고, 상기 제1접촉면(131c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제1걸림돌기(131d')가 형성된 제1걸림편(131d)이 형성되며, 상기 제2마감처리부재(133)는, "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 나머지 외주면 반을 감쌀 수 있도록 제2접촉면(133c)이 형성되고, 상기 제2접촉면(133c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제2걸림돌기(133d')가 형성된 제2걸림편(133d)이 형성되어 구비된 것을 특징으로 한다.In addition, the first finishing member 131 of the cap 130 for finishing is formed in a "C" shape so that the inner surface can cover half the outer circumferential surface of the pipe A. A first protrusion ( 131d') is formed, and the second finishing member 133 is formed in a "C" shape, and the remaining outer circumference half of the pipe A is formed as an inner surface. A second contact surface 133c is formed so as to be wrapped, and one end of each end is integrally connected to both sides of the second contact surface 133c and protrudes in one direction apart from each other, and the other end is inserted into the pipe through hole (C) side It is characterized in that a second locking piece 133d having a second locking protrusion 133d' formed to be hooked is formed and provided.

상기한 바와 같이 본 발명에 따른 배관용 벽체 마감장치에 따르면, 실리콘 작업을 배제할 수 있어 작업비용 절감 및 작업 시간을 단축시킬 수 있는 효과와 함께 배관이 유동하더라도 마감용 캡은 배관용 관통홀로부터 이격되지 않아 마감용 캡의 기능을 유지할 수 있을 뿐만 아니라, 또한, 본 발명의 또 다른 목적은, 벽체에 형성된 배관용 관통홀과 배관 사이에 마감용 부식방지관을 구성하고 있어서, 배관용 관통홀에 위치된 배관의 부식을 지연시킬 수 있는 효과가 있다.As described above, according to the wall finishing device for piping according to the present invention, silicone work can be eliminated, thereby reducing work costs and working time, and even if the pipe flows, the cap for finishing is removed from the through hole for piping. In addition to being able to maintain the function of the cap for finishing because it is not spaced apart, another object of the present invention is to construct a corrosion-resistant pipe for finishing between the pipe through hole and the pipe formed in the wall, There is an effect that can delay the corrosion of the pipe located in the.

도 1은 본 발명에 따른 배관용 벽체 마감장치가 가스배관에 설치된 일부 분해 사시도이다.
도 2는 본 발명에 따른 배관용 벽체 마감장치의 마감용 부식방지관을 도시한 사시도이다.
도 3은 본 발명에 따른 배관용 벽체 마감장치의 마감용 캡을 도시한 분해 사시도이다.
도 4는 본 발명에 따른 배관용 벽체 마감장치의 마감용 부식방지관이 가스배관 상에 설치된 상태를 도시한 단면도이다.
도 5는 본 발명에 따른 배관용 벽체 마감장치가 가스배관 상에 설치된 상태를 도시한 단면도이다.
1 is a partially exploded perspective view of a pipe wall finishing device according to the present invention installed in a gas pipe.
Figure 2 is a perspective view showing a corrosion-resistant pipe for finishing of the pipe wall finishing device according to the present invention.
Figure 3 is an exploded perspective view showing a cap for closing the pipe wall closing device according to the present invention.
Figure 4 is a cross-sectional view showing a state in which the corrosion-resistant pipe for finishing of the pipe wall finishing device according to the present invention is installed on the gas pipe.
5 is a cross-sectional view showing a state in which the pipe wall closing device according to the present invention is installed on a gas pipe.

이하에서는, 본 발명에 따른 배관용 벽체 마감장치의 일실시 예를 들어 상세하게 설명한다.Hereinafter, an embodiment of the pipe wall closing device according to the present invention will be described in detail.

우선, 도면들 중, 동일한 구성요소 또는 부품들은 가능한 한 동일한 참조부호를 나타내고 있음에 유의하여야 한다. 본 발명을 설명함에 있어, 관련된 공지기능 혹은 구성에 대한 구체적인 설명은 발명의 요지를 모호하지 않게 하기 위하여 생략한다. First of all, it should be noted that in the drawings, the same components or parts are denoted by the same reference numerals as much as possible. In describing the present invention, detailed descriptions of related known functions or configurations are omitted in order not to obscure the subject matter of the present invention.

도시된 바와 같이 본 발명에 따른 배관용 벽체 마감장치는, 실리콘 작업을 배제할 수 있어 작업비용 절감 및 작업 시간을 단축시킬 수 있고, 배관이 유동하더라도 마감용 캡은 배관용 관통홀로부터 이격되지 않아 마감용 캡의 기능을 유지할 수 있을 뿐만 아니라 마감용 부식방지관으로 인해 벽체의 배관용 관통홀에 위치되는 배관의 부식을 지연시킬 수 있도록 구성된다.As shown, the pipe wall finishing device according to the present invention can eliminate silicone work, thereby reducing work costs and shortening work time, and even if the pipe is flowing, the cap for finishing is not separated from the through hole for pipe. It is configured to not only maintain the function of the cap for finishing, but also to delay corrosion of the pipe located in the through-hole for piping of the wall due to the corrosion-resistant pipe for finishing.

즉, 상기한 본 발명에 따른 배관용 벽체 마감장치(100)는, 길이방향으로 절개된 중공의 관으로 형성되어 배관(A) 상에 설치되는 것에 의해 벽체(B)에 형성된 배관용 관통홀(C)에 위치되어 배관(A)의 부식을 지연가능하게 구비되는 마감용 부식방지관(110)과, 제1,1'분할면(131a,131b)을 갖는 제1마감처리부재(131)와, 제2,2'분할면(133a,133b)을 갖는 제2마감처리부재(133)로 이분할되어 결합수단(150)을 통하여 서로 결합되는 것에 의해 상기 마감용 부식방지관(110)을 관통하는 배관(A) 상에 설치되면서 상기 배관용 관통홀(C)의 내측면에 일단이 걸림 고정되어 배관용 관통홀(C)을 마감처리 가능하도록 구비되는 마감용 캡(130)을 포함하여 구성된다.That is, the pipe wall closing device 100 according to the present invention described above is formed of a hollow pipe cut in the longitudinal direction and installed on the pipe A, thereby forming a pipe through hole formed in the wall (B) ( C) a corrosion-resistant pipe 110 for finishing, which is provided to delay corrosion of the pipe A, and a first finishing member 131 having 1,1' split surfaces 131a and 131b, , Penetrates the anti-corrosion pipe 110 for finishing by being divided in two into the second finishing member 133 having the 2nd and 2' dividing surfaces 133a and 133b and coupled to each other through the coupling means 150 It is installed on the pipe (A) to be installed and one end is hooked and fixed to the inner surface of the through-hole (C) for pipe, including a cap 130 for finishing provided to finish the through-hole (C) for pipe. do.

이하에서, 상기한 본 발명에 따른 배관용 벽체 마감장치를 첨부된 도면 도 1 내지 도 3을 참조하여 보다 상세하게 설명하면 다음과 같다.Hereinafter, the above-described pipe wall closing device according to the present invention will be described in more detail with reference to the accompanying drawings 1 to 3.

먼저, 상기한 본 발명에 따른 배관용 벽체 마감장치의 마감용 부식방지관(110)은, 길이방향으로 절개된 중공의 관으로 형성되어 배관(A) 상에 설치되는 것에 의해 벽체(B)에 형성된 배관용 관통(C)홀에 위치되어 배관(A)의 부식을 방지가하게 구비된다.First, the corrosion-resistant pipe 110 for finishing of the wall finishing device for piping according to the present invention is formed as a hollow pipe cut in the longitudinal direction and installed on the pipe (A) to the wall (B). It is located in the through hole (C) for the formed pipe and is provided to prevent corrosion of the pipe (A).

즉, 상기한 마감용 부식방지관(110)은 중공의 관으로 형성되어 벽체(B)에 형성된 배관용 관통홀(C)에 내설되면서 배관(A) 상에 설치할 수 있도록 외주면에는 길이방향으로 절개부(111)가 형성되고, 내주면에는 배관(A)의 외주면과 이격되도록 방사방향으로 일정 간격 복수 개의 마감용 부식 방지돌기(113)가 돌출 형성되어 구비된다.That is, the above-mentioned corrosion-resistant pipe 110 for finishing is formed as a hollow pipe and is installed in the pipe through-hole (C) formed in the wall (B) and cut in the longitudinal direction on the outer circumferential surface so that it can be installed on the pipe (A). A portion 111 is formed, and a plurality of anti-corrosion protrusions 113 for finishing are protrudingly provided on the inner circumferential surface at regular intervals in the radial direction to be spaced apart from the outer circumferential surface of the pipe A.

상기한 마감용 캡(130)은, 제1,1'분할면(131a,131b)을 갖는 제1마감처리부재(131)와, 제2,2'분할면(133a,133b)을 갖는 제2마감처리부재(133)로 이분할되어 결합수단(150)을 통하여 서로 결합되는 것에 의해 상기 마감용 부식방지관(110)을 관통하는 배관(A) 상에 설치되면서 상기 배관용 관통홀(C)의 내측면에 일단이 걸림 고정되어 배관용 관통홀(C)을 마감처리 가능하도록 구비된다.The cap 130 for finishing described above includes a first finishing member 131 having first and first split surfaces 131a and 131b, and a second end having second and second split surfaces 133a and 133b. The through-hole for the pipe (C) is installed on the pipe (A) passing through the corrosion-resistant pipe 110 for finishing by being divided into two parts by the finishing member 133 and coupled to each other through the coupling means 150 One end is hooked and fixed to the inner surface of the through-hole (C) for piping is provided so as to be able to finish treatment.

즉, 상기한 마감용 캡(130)의 제1마감처리부재(131)는 "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 외주면 반을 감쌀 수 있도록 제1접촉면(131c)이 형성되고, 상기 제1접촉면(131c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제1걸림돌기(131d')가 형성된 제1걸림편(131d)이 형성되어 구비된다.That is, the first finishing member 131 of the cap 130 for finishing described above is formed in a "C" shape so that the inner surface can cover half of the outer circumferential surface of the pipe A. The first contact surface 131c ) is formed, and each end is integrally connected to both sides of the first contact surface 131c and protrudes in one direction while being spaced apart from each other, and the other end is inserted into the through hole for pipe (C) and caught so that the first locking protrusion 131d ') is formed and provided with a first locking piece (131d) formed.

또한, 상기한 제1마감처리부재(131)의 제1접촉면(131c)에는 상기 배관(A)의 외주면 반을 감쌀 때, 상기 배관(A)의 외주면과 이격되어 부식방지를 위해 일정 간격 복수 개의 제1부식방지용 돌기(131e)가 더 형성되어 구비된다.In addition, the first contact surface 131c of the first finishing member 131 is spaced apart from the outer circumferential surface of the pipe A when wrapping the outer circumferential half of the pipe A to prevent corrosion. A first anti-corrosion protrusion 131e is further formed and provided.

그리고, 상기한 제1접촉면(131c) 타단은 실리콘으로 마감처리시 실리콘이 돌출됨 없이 마감처리 가능하도록 제1마감처리용 단턱부(131f)가 더 형성되어 구비된다.In addition, when the other end of the first contact surface 131c is finished with silicon, a stepped portion 131f for the first finishing treatment is further formed and provided so that the silicon can be finished without protruding.

상기한 제2마감처리부재(133)는 상기 제1마감처리부재(131)와 동일한 형상 즉, "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 나머지 외주면 반을 감쌀 수 있도록 제2접촉면(133c)이 형성되고, 상기 제2접촉면(133c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제2걸림돌기(133d')가 형성된 제2걸림편(133d)이 형성되어 구비된다.The second finishing member 133 is formed in the same shape as the first finishing member 131, that is, in a "C" shape, and can wrap the remaining outer circumference half of the pipe A with the inner surface. A second contact surface 133c is formed so that one end of the second contact surface 133c is integrally connected to both sides and spaced apart from each other to protrude in one direction, and the other end is inserted into the pipe through-hole (C) and caught A second locking piece 133d having a second locking protrusion 133d' is formed and provided.

또한, 상기한 제2마감처리부재(133)의 제2접촉면(133c)에는 상기 제1마감처리부재(131)가 배관(A)의 외주면 반을 감싼 나머지 반의 외주면을 감쌀 때, 상기 배관(A)의 외주면과 이격되어 부식방지를 위해 일정 간격 복수 개의 제2부식방지용 돌기(133e)가 더 형성되어 구비된다.In addition, when the first finishing member 131 wraps half of the outer circumferential surface of the pipe (A) on the second contact surface 133c of the second finishing member 133, the pipe (A) ) A plurality of second anti-corrosion protrusions 133e are further formed and provided at regular intervals to prevent corrosion by being spaced apart from the outer circumferential surface of the.

그리고, 상기한 제2접촉면(133c)의 타단은 실리콘으로 마감처리시 실리콘이 돌출됨 없이 마감처리 가능하도록 제2마감처리용 단턱부(133f)가 더 형성되어 구비된다.In addition, when the other end of the second contact surface 133c is finished with silicon, a stepped portion 133f for second finishing treatment is further formed and provided so that the silicon can be finished without protruding.

상기한 결합수단(150)은 상기 배관(A)을 반씩 감싸는 제1,2마감처리부재(131,133)를 서로 결합시킬 수 있도록 구성된다.The coupling means 150 is configured to couple the first and second finishing members 131 and 133 that surround the pipe A in half.

즉, 상기한 결합수단(150)은 상기 제1마감처리부재(131)의 제1분할면(131a)에 일측이 개구되어 형성된 제1수용홀(151)과, 상기 제1수용홀(151)의 각 후단에 위치되는 것에 의해 일단은 상기 제1마감처리부재(131)에 연결되고, 타단은 일방향으로 돌출된 원형의 단면을 갖는 제1고정돌기(152)와, 상기 제1'분할면(131b)으로부터 서로에 대하여 이격되어 한 쌍으로 돌출되되, 각 내측면은 제1'경사면(153a)이 형성되고, 상기 제1'경사면(153a) 일측에는 제1결함요홈(153b)이 각각 형성되어 구비되는 제1'결합편(153)과, 상기 제2마감처리부재(133)의 제2분할면(133a)으로부터 서로에 대하여 이격되어 한 쌍으로 돌출되되, 각 내측면은 제2경사면(154a)이 형성되고, 상기 제2경사면(154a) 일측에는 제2결함요홈(154b)이 각각 형성되어 상기 제1수용홀(151)측으로 삽입되면서 제1고정돌기(152)와 결합가능하도록 구비되는 제2결합편(154)과, 상기 제2'분할면(133b) 일측이 개구되어 형성된 제2'수용홀(155)과, 상기 제'2수용홀(155)의 각 후단에 위치되는 것에 의해 일단은 상기 제2마감처리부재(133)에 연결되고, 타단은 일방향으로 돌출되어 상기 제1'결합편(153)과 결합될 수 있도록 원형의 단면으로 형성된 제2'고정돌기(156)로 구성된다.That is, the coupling means 150 includes a first accommodating hole 151 formed by opening one side of the first divided surface 131a of the first finishing member 131, and the first accommodating hole 151 By being located at each rear end of, one end is connected to the first finishing member 131, and the other end has a first fixing protrusion 152 having a circular cross section protruding in one direction, and the first 'divided surface ( 131b) are spaced apart from each other and protrude as a pair, each inner surface is formed with a first 'inclined surface (153a), and a first defective groove (153b) is formed on one side of the first 'inclined surface (153a), respectively. The provided first 'coupling piece 153 and the second split surface 133a of the second finishing member 133 are spaced apart from each other and protrude as a pair, and each inner surface has a second inclined surface 154a. ) is formed, and second defective grooves 154b are formed on one side of the second inclined surface 154a and inserted into the first receiving hole 151 so as to be coupled with the first fixing protrusion 152. The two coupling pieces 154, the 2nd' accommodating hole 155 formed by opening one side of the 2nd' split surface 133b, and the 'second accommodating hole 155 are located at each rear end, so that once is connected to the second finishing member 133, and the other end protrudes in one direction and is composed of a 2nd 'fixing protrusion 156 formed in a circular cross section so as to be combined with the 1st' coupling piece 153. .

또한, 상기한 제1'결합편(153)과 제2결합편(154)의 외주면에는 제1수용홀(151)과 제2수용홀(155)측으로 삽입된 후, 각각 걸림되도록 제1'걸림돌기(도면부호 생략)와 제2'걸림돌기(도면부호 생략)가 더 돌출 형성되어 구비된다. In addition, after being inserted into the first accommodating hole 151 and the second accommodating hole 155 on the outer circumferential surfaces of the first' coupling piece 153 and the second coupling piece 154, the first' stumbling stones are respectively engaged. A group (reference numeral omitted) and a 2nd 'locking protrusion (reference numeral omitted) are further formed to protrude and are provided.

이와 같이 이루어진 본 발명에 따른 배관용 벽체 마감장치를 이용하여 가스배관(A)을 벽체(B)에 형성된 배관용 관통홀(C)을 관통시켜 배관시킨 후 마감처리시키고자 할 경우, 첨부된 도면 도 1 내지 도 5에 도시된 바와 같이 먼저, 절개부(111)를 확경시키면서 마감용 부식방지관(110)을 가스배관(A) 상에 설치한다.When using the wall finishing device for piping according to the present invention made as described above to pass through the piping through-hole (C) formed in the wall (B) for gas piping (A) and then finish the pipe, the accompanying drawings As shown in FIGS. 1 to 5, first, the corrosion-resistant pipe 110 for finishing is installed on the gas pipe A while expanding the incision 111.

상기와 같이 마감용 부식방지관(110)이 설치된 가스배관(A)을 벽체(B)에 형성된 배관용 관통홀(C)측으로 배관시키되, 상기 가스배관(A) 상에 설치된 마감용 부식방지관(110)은 벽체(B)에 형성된 배관용 관통홀(C)에 위치되게 배관시킨다.As described above, the gas pipe (A) in which the corrosion-resistant pipe 110 for finishing is installed is piped to the through-hole (C) for pipe formed in the wall (B), and the corrosion-resistant pipe for finishing is installed on the gas pipe (A). (110) is piped to be located in the pipe through hole (C) formed in the wall (B).

이때, 상기 가스배관(A)의 외주면과 마감용 부식방지관(110)의 내주면은, 도 4에 도시된 바와 같이 복수 개의 마감용 부식 방지돌기(113)에 의해 이격된다.At this time, the outer circumferential surface of the gas pipe (A) and the inner circumferential surface of the corrosion-resistant pipe 110 for finishing are spaced apart by a plurality of anti-corrosion protrusions 113 for finishing, as shown in FIG.

상기와 같이 마감용 부식방지관(110)을 설치하여 배관용 관통홀(C)에 상기 가스배관(A)이 배관되면, 마감을 위해 마감용 캡(130)의 제1마감처리부재(131)와 제2마감처리부재(133)로 가스배관(A)을 감싼 후, 결합수단(150)으로 결합시켜, 결합된 마감용 캡(130)을 배관용 관통홀(C)측으로 가압시키는 것에 의해 제1걸림편(131d)와 제2걸림편(133d)이 배관용 관통홀(C)과 마감용 부식방지관(110) 사이로 삽입된다.When the gas pipe (A) is piped to the through-hole (C) for piping by installing the corrosion-resistant pipe 110 for finishing as described above, the first finishing member 131 of the cap 130 for finishing After wrapping the gas pipe (A) with the second finishing member 133 and then combining it with the coupling means 150, the combined cap 130 for piping is pressed toward the pipe through-hole (C) side. The first catching piece 131d and the second catching piece 133d are inserted between the pipe through hole C and the corrosion-resistant pipe 110 for finishing.

상기와 같이 제1걸림편(131d)와 제2걸림편(133d)이 배관용 관통홀(C)측으로 삽입되므로 인해, 도 5에 도시된 바와 같이, 제1걸림돌기(131d')와 제2걸림돌기(133d')가 배관용 관통홀(C) 내측면에 각각 걸림되면서 마감처리가 완료된다.As described above, since the first locking piece 131d and the second locking piece 133d are inserted into the pipe through-hole C, as shown in FIG. The finishing process is completed as the locking protrusions 133d' are each caught on the inner surface of the pipe through-hole C.

이때 상기 제1마감처리부재(131)와 제2마감처리부재(133)의 제1접촉면(131c)과 제2접촉면(133c)은 제1부식방지용 돌기(131e)와 제2부식방지용 돌기(133e)에 의해 가스배관의 외주면과 이격되면서 마감처리 된다.At this time, the first contact surface 131c and the second contact surface 133c of the first finishing member 131 and the second finishing member 133 have a first anti-corrosion protrusion 131e and a second anti-corrosion protrusion 133e. ), it is finished while being separated from the outer circumferential surface of the gas pipe.

이상과 같이, 본 발명에 따른 배관용 벽체 마감장치를 통하여 가스배관의 배관에 따른 마감처리할 경우, 가스배관의 외주면은 마감용 부식방지관(110)의 마감용 부식 방지돌기(113)와, 마감용 캡(130)의 제1부식방지용 돌기(131e)와 제2부식방지용 돌기(133e)에 상기 마감용 부식방지관(110)의 내주면과 제1접촉면(131c) 그리고 제2접촉면(133c)이 이격되어 배관되므로 습기가 가스배관 외주면에 차지 않아 상기 가스배관이 부식되는 것을 지연시킬 수 있다.As described above, when the gas pipe is finished according to the pipe of the gas pipe through the wall finishing device for pipe according to the present invention, the outer circumferential surface of the gas pipe is formed with the anti-corrosion protrusion 113 for finishing of the anti-corrosion pipe 110 for finishing, The inner circumferential surface, first contact surface 131c, and second contact surface 133c of the corrosion-resistant pipe 110 for finishing on the first anti-corrosion protrusion 131e and the second anti-corrosion protrusion 133e of the cap 130 for finishing Since the pipes are spaced apart from each other, moisture does not fill the outer circumferential surface of the gas pipe, thereby delaying corrosion of the gas pipe.

이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형이 가능할 것이다. 따라서, 본 발명에 개시된 실시예들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다. 본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.The above description is merely an example of the technical idea of the present invention, and various modifications and variations can be made to those skilled in the art without departing from the essential characteristics of the present invention. Therefore, the embodiments disclosed in the present invention are not intended to limit the technical idea of the present invention, but to explain, and the scope of the technical idea of the present invention is not limited by these embodiments. The protection scope of the present invention should be construed according to the claims below, and all technical ideas within the equivalent range should be construed as being included in the scope of the present invention.

A ; 배관 B ; 벽체
C ; 배관용 관통홀 100 ; 배관용 벽체 마감장치
110 ; 마감용 부식방지관 130 ; 마감용 캡
150 ; 결합수단
A; pipe B ; wall
C; Through-hole for piping 100; Wall finishing device for plumbing
110; Corrosion-resistant pipe for finishing 130; cap for finishing
150; connecting means

Claims (5)

배관용 벽체 마감장치는,
길이방향으로 절개된 중공의 관으로 형성되어 배관(A) 상에 설치되는 것에 의해 벽체(B)에 형성된 배관용 관통홀(C)에 위치되어 배관(A)의 부식을 지연가능하게 구비되는 마감용 부식방지관(110)과;
제1,1'분할면(131a,131b)을 갖는 제1마감처리부재(131)와, 제2,2'분할면(133a,133b)을 갖는 제2마감처리부재(133)로 이분할되어 결합수단(150)을 통하여 서로 결합되는 것에 의해 상기 마감용 부식방지관(110)을 관통하는 배관(A) 상에 설치되면서 상기 배관용 관통홀(C)의 내측면에 일단이 걸림 고정되어 배관용 관통홀(C)을 마감처리 가능하도록 구비되는 마감용 캡(130);을 포함하고,
상기 마감용 캡(130)의 제1마감처리부재(131)는, "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 외주면 반을 감쌀 수 있도록 제1접촉면(131c)이 형성되고, 상기 제1접촉면(131c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제1걸림돌기(131d')가 형성된 제1걸림편(131d)이 형성되며,
상기 제2마감처리부재(133)는, "C"자 형상으로 형성으로 형성되어 내측면으로 상기 배관(A)의 나머지 외주면 반을 감쌀 수 있도록 제2접촉면(133c)이 형성되고, 상기 제2접촉면(133c) 일단 양측에는 각 일단이 일체로 연결되면서 서로 이격되어 일방향으로 돌출되되, 타단은 배관용 관통홀(C)측으로 삽입되어 걸림되도록 제2걸림돌기(133d')가 형성된 제2걸림편(133d)이 형성되어 구비되고,
상기 제1마감처리부재(131)의 제1접촉면(131c)에는, 상기 배관(A)의 외주면 반을 감쌀 때, 상기 배관(A)의 외주면과 이격되어 부식방지를 위해 일정 간격 복수 개의 제1부식방지용 돌기(131e)가 형성되고, 상기 제2마감처리부재(133)의 제2접촉면(133c)에는 상기 제1마감처리부재(131)가 배관(A)의 외주면 반을 감싼 나머지 반의 외주면을 감쌀 때, 상기 배관(A)의 외주면과 이격되어 부식방지를 위해 일정 간격 복수 개의 제2부식방지용 돌기(133e)가 더 형성되어 구비된 것을 특징으로 하는 배관용 벽체 마감장치.
Wall finishing device for piping,
It is formed of a hollow pipe cut in the longitudinal direction and is installed on the pipe (A) so as to be positioned in the pipe through-hole (C) formed in the wall (B) to delay corrosion of the pipe (A). For corrosion protection pipe 110 and;
It is divided into a first finishing member 131 having first and first splitting surfaces 131a and 131b and a second finishing member 133 having second and second splitting surfaces 133a and 133b. By being coupled to each other through the coupling means 150, one end is caught and fixed to the inner surface of the through-hole (C) for the pipe while being installed on the pipe (A) penetrating the corrosion-resistant pipe (110) for finishing Including; cap 130 for finishing provided to enable finishing of the through-hole (C);
The first finishing member 131 of the cap 130 for finishing is formed in a “C” shape and has a first contact surface 131c so as to cover half of the outer circumferential surface of the pipe A with the inner surface. Formed, on both sides of the first contact surface 131c, each end is integrally connected and spaced apart from each other to protrude in one direction, and the other end is inserted into the pipe through hole (C) side to be caught. A first holding piece 131d is formed,
The second finishing member 133 is formed in a "C" shape, and a second contact surface 133c is formed to cover the remaining half of the outer circumferential surface of the pipe A on the inner side, and the second contact surface 133c is formed. On both sides of the contact surface 133c, each end is integrally connected and spaced apart from each other to protrude in one direction, while the other end is inserted into the through-hole for pipe (C) and has a second holding protrusion 133d' formed thereon. (133d) is formed and provided,
On the first contact surface 131c of the first finishing member 131, when half of the outer circumferential surface of the pipe A is wrapped, a plurality of first surfaces are spaced apart from the outer circumferential surface of the pipe A to prevent corrosion. Corrosion-preventing protrusions 131e are formed, and the first finishing member 131 wraps half of the outer circumferential surface of the pipe A on the second contact surface 133c of the second finishing member 133 and covers the other half of the outer circumferential surface. When wrapped, a plurality of second anti-corrosion protrusions 133e are further formed at regular intervals to prevent corrosion by being spaced apart from the outer circumferential surface of the pipe (A).
제1항에 있어서,
상기 마감용 부식방지관(110)은, 벽체(B)에 형성된 배관용 관통홀(C)에 내설되면서 배관(A) 상에 설치할 수 있도록 외주면에는 길이방향으로 절개부(111)가 형성되고, 내주면에는 배관(A)의 외주면과 이격되도록 방사방향으로 일정 간격 복수 개의 마감용 부식 방지돌기(113)가 돌출 형성되어 구비된 것을 특징으로 하는 배관용 벽체 마감장치.
According to claim 1,
The corrosion-resistant pipe 110 for finishing has a cutout 111 formed in the longitudinal direction on the outer circumferential surface so that it can be installed on the pipe (A) while being installed in the pipe through-hole (C) formed in the wall (B), Wall finishing device for pipes, characterized in that a plurality of anti-corrosion protrusions 113 for finishing are protrudingly formed on the inner circumferential surface at regular intervals in the radial direction so as to be spaced apart from the outer circumferential surface of the pipe (A).
삭제delete 제1항에 있어서,
상기 결합수단(150)은, 상기 제1마감처리부재(131)의 제1분할면(131a)에 일측이 개구되어 형성된 제1수용홀(151)과, 상기 제1수용홀(151)의 각 후단에 위치되는 것에 의해 일단은 상기 제1마감처리부재(131)에 연결되고, 타단은 일방향으로 돌출된 원형의 단면을 갖는 제1고정돌기(152)와, 상기 제1'분할면(131b)으로부터 서로에 대하여 이격되어 한 쌍으로 돌출되되, 각 내측면은 제1'경사면(153a)이 형성되고, 상기 제1'경사면(153a) 일측에는 제1결함요홈(153b)이 각각 형성되어 구비되는 제1'결합편(153)과, 상기 제2마감처리부재(133)의 제2분할면(133a)으로부터 서로에 대하여 이격되어 한 쌍으로 돌출되되, 각 내측면은 제2경사면(154a)이 형성되고, 상기 제2경사면(154a) 일측에는 제2결함요홈(154b)이 각각 형성되어 상기 제1수용홀(151)측으로 삽입되면서 제1고정돌기(152)와 결합가능하도록 구비되는 제2결합편(154)과, 상기 제2'분할면(133b) 일측이 개구되어 형성된 제2'수용홀(155)과, 상기 제'2수용홀(155)의 각 후단에 위치되는 것에 의해 일단은 상기 제2마감처리부재(133)에 연결되고, 타단은 일방향으로 돌출되어 상기 제1'결합편(153)과 결합될 수 있도록 원형의 단면으로 형성된 제2'고정돌기(156)로 구성된 것을 특징으로 하는 배관용 벽체 마감장치.
According to claim 1,
The coupling means 150 includes a first accommodating hole 151 formed by opening one side of the first divided surface 131a of the first finishing member 131, and each of the first accommodating hole 151. By being located at the rear end, one end is connected to the first finishing member 131, and the other end has a first fixing protrusion 152 having a circular cross section protruding in one direction, and the first 'divided surface 131b Doedoe protrudes as a pair spaced apart from each other, each inner surface is formed with a first 'inclined surface (153a), and a first defective groove (153b) is formed on one side of the first 'inclined surface (153a), respectively. The first 'coupling piece 153 and the second split surface 133a of the second finishing member 133 are spaced apart from each other and protrude as a pair, and each inner surface has a second inclined surface 154a. The second coupling groove 154b is formed on one side of the second inclined surface 154a and is inserted into the first receiving hole 151 so as to be coupled with the first fixing protrusion 152. One end of the piece 154 and the 2nd' accommodating hole 155 formed by opening one side of the 2nd' dividing surface 133b, and located at each rear end of the 'second accommodating hole 155, It is connected to the second finishing member 133, and the other end protrudes in one direction and is composed of a second 'fixing protrusion 156 formed in a circular cross section so that it can be combined with the first' coupling piece 153. Wall finishing device for piping.
삭제delete
KR1020210037468A 2021-03-23 2021-03-23 Wall finishing device for piping KR102497744B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210037468A KR102497744B1 (en) 2021-03-23 2021-03-23 Wall finishing device for piping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210037468A KR102497744B1 (en) 2021-03-23 2021-03-23 Wall finishing device for piping

Publications (2)

Publication Number Publication Date
KR20220132315A KR20220132315A (en) 2022-09-30
KR102497744B1 true KR102497744B1 (en) 2023-02-07

Family

ID=83451442

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210037468A KR102497744B1 (en) 2021-03-23 2021-03-23 Wall finishing device for piping

Country Status (1)

Country Link
KR (1) KR102497744B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200336658Y1 (en) * 2003-09-30 2003-12-24 최종력 Supporter having tension supporting part combined to gas pipe.
KR200441371Y1 (en) * 2007-02-22 2008-08-12 김성환 Sleeve for protecting pipe in building

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110082351A (en) * 2010-01-11 2011-07-19 엘지전자 주식회사 Dissimilar material manufactured heat tube
KR20150000561U (en) 2013-07-26 2015-02-04 현대중공업 주식회사 Scaffold

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200336658Y1 (en) * 2003-09-30 2003-12-24 최종력 Supporter having tension supporting part combined to gas pipe.
KR200441371Y1 (en) * 2007-02-22 2008-08-12 김성환 Sleeve for protecting pipe in building

Also Published As

Publication number Publication date
KR20220132315A (en) 2022-09-30

Similar Documents

Publication Publication Date Title
US9599266B2 (en) Externally sealing connector
US9568130B2 (en) Profiled clamp with sealing element
US20040041353A1 (en) Metal packing
US11215302B2 (en) Positioning device for a spring clamp
KR101330452B1 (en) Flange for coupling plumbing
CN110552633B (en) Threaded connection
KR102497744B1 (en) Wall finishing device for piping
EP3633213A1 (en) Connecting pipe fitting, pipe assembly and pipe connecting method
KR200496835Y1 (en) Plug for tap water piping
KR102053283B1 (en) Pipe coupler
CA2835162A1 (en) Hose connection arrangement
KR100881351B1 (en) Expanding pipe with separation prevention structure
JPH08338577A (en) Pipe joint for connection of pipe with ring
RU2621429C2 (en) Pipe fitting
KR102476994B1 (en) Pipe corrosion prevention device
KR20170129573A (en) Coupling Structure for Pipes
KR200386857Y1 (en) Improvement structure of building wall piping protection sleeve
KR101047503B1 (en) Branch pipe socket
JP7340851B2 (en) insulation fittings
JP5536169B2 (en) Adhesive core for water faucet and mounting method
KR101035553B1 (en) A Joint for water supply pipes
KR100895040B1 (en) Clamping pipe joint
KR101040681B1 (en) Coupling pipe of round bar
KR200390240Y1 (en) Improvement structure of building wall piping protection sleeve
AU2010100709A4 (en) Plumbing fitting

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right