KR20040049354A - Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam - Google Patents

Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam Download PDF

Info

Publication number
KR20040049354A
KR20040049354A KR1020020076379A KR20020076379A KR20040049354A KR 20040049354 A KR20040049354 A KR 20040049354A KR 1020020076379 A KR1020020076379 A KR 1020020076379A KR 20020076379 A KR20020076379 A KR 20020076379A KR 20040049354 A KR20040049354 A KR 20040049354A
Authority
KR
South Korea
Prior art keywords
pier
installing
foundation
piers
reflection
Prior art date
Application number
KR1020020076379A
Other languages
Korean (ko)
Other versions
KR100511464B1 (en
Inventor
노윤근
박근화
Original Assignee
노윤근
박근화
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 노윤근, 박근화 filed Critical 노윤근
Priority to KR10-2002-0076379A priority Critical patent/KR100511464B1/en
Publication of KR20040049354A publication Critical patent/KR20040049354A/en
Application granted granted Critical
Publication of KR100511464B1 publication Critical patent/KR100511464B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Abstract

PURPOSE: A construction method for a T-shaped pier using a prestressed preflextion H-beam is provided to shorten a period of construction and to cut down the construction expenses by a simple construction method and a scale-down of pier section. CONSTITUTION: The construction method for a T-shaped pier using a prestressed preflextion H-beam comprises the steps of: installing an H-beam(13) which forms a column of a pier on the footing ground, then placing concrete to the pier foundation(14); installing an upper T-shaped pier by forming a pier head(11) by connecting a preflextion H-beam(20) to the other end of the H-beam(13) which forms a column of a pier and installing many haunches(15) to a joint between the H-beam(13) and the preflextion H-beam(20); installing a lower T-shaped pier by forming a pier head(11) by connecting the preflextion H-beam(20) on the B-beam(13) which forms a column of a bridge and installing many haunches(15); and installing a double-storied T-shaped pier by placing concrete to the H-beam(13) which forms the pier head(11) and the pier column of the upper, lower T-shaped piers.

Description

프리스트레스를 도입한 플리플렉션 H빔 및 이를 이용한 T형 교각 시공방법{Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam }Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam}

본 발명은 H빔에 강연선을 이용하여 프리스트레스를 도입한 플리플렉션 H빔을 이용하여 T형 교각을 시공하는 방법에 관한 것으로서, H빔의 상부 플랜지에 인장 브라켓을 양측단에 설치하고 강연선을 인장 브라켓에 관통시킨 후에 강연선을 인장하고 정착구를 이용하여 인장 브라켓에 정착하여 하향 솟음을 갖도록 제작한 플리플렉션 H빔과, 이를 이용하여 교각을 설치하고자하는 곳의 교각기초의 지반까지 H빔을 설치하고 타단의 H빔의 끝단에는 상기 플리플렉션 H빔의 하향으로 솟음이 주어진 중앙 부분을 연결설치한 후에 H빔과 상기 플리플렉션 H빔이 연결설치되는 부분에 복수의 헌치를 설치한 후에 콘크리트를 타설양생하여 T형 교각을 설치하는 것이다.The present invention relates to a method for constructing a T-type pier using a H-beam, which employs a pre-stressed H-beam, using a stranded wire. A tension bracket is installed at both ends of the H-beam and a stranded bracket is provided. After penetrating the steel wire, the H-beam is made to be stretched down and anchored to the tensioning bracket using the anchorage to rise upward, and the H-beam is installed to the ground of the bridge foundation where the pier is to be installed. At the end of the H-beam, the center portion is given to the bottom of the reflection H-beam is connected and installed, and after installing a plurality of haunches on the portion where the H-beam and the H-beam connected to the installation, the concrete is poured It is to install a T-pier.

본 발명의 목적은 교각을 시공할 때 교각 두부에 압축력이 도입된 플리플렉션 H빔을 설치하여 교각 두부의 양쪽날개에 하향으로 작용하는 인장력이 플리플렉션 H빔에 도입된 압축력에 의하여 상쇄되게 하여 교각 설계시 교각 두부의 단면을적게할 수 있도록 하면서 교각을 설치할 때 강재인 H빔을 사용하므로서 설치기간의 단축과 이를 통하여 공사비의 절감을 하기 위함이다.An object of the present invention is to install a flexion H beam in which the compression force is introduced to the pier head when constructing the pier so that the tensile force acting downward on both wings of the pier head is offset by the compressive force introduced in the reflection H beam. This is to reduce the installation period and reduce construction cost by using H beam which is steel when installing the piers while reducing the cross section of the head of the piers during the design.

일반적으로 교각을 설치하기 위하여 소정의 깊이까지 교각의 기초를 굴착한 후에 기초를 설치하고 그 위에 교각을 설치하면서 교각두부를 설치하는 것이다. 그러나 이러한 방법으로 교각의 두부를 설치하는 경우에는 교각두부의 양측날개부분에 작용하는 인장력을 지지하기 위하여 과도한 철근과 이를 위한 콘크리트의 사용으로 단면이 과다설계되고 있으며, 또한, 교각을 설치할 경우에도 교각을 설치하기 위하여 철근을 배근하고 이의 주위에 거푸집을 일일이 단계적으로 설치한 후에 콘크리트를 타설양생하는 작업을 여러번 반복적으로 하고나서 비로소 교각을 설치하게 되는 것이다. 이러한 방법은 설치기간의 장기화와 이로인한 설치비용의 증가로 인하여 공사비의 증가를 가져오는 문제점이 지적되어 왔다.Generally, in order to install a pier, the foundation of the pier is excavated to a predetermined depth, and then the foundation is installed and the pier head is installed while the pier is installed thereon. However, in the case of installing the head of the piers in this way, the cross section is over-designed due to the use of excessive reinforcement and concrete for supporting the tensile force acting on both wing parts of the piers. After installing reinforcement bars and installing formwork around them step by step to install the concrete, the concrete will be installed several times before the piers are installed. This method has been pointed out that the construction cost is increased due to the prolonged installation period and the increased installation cost.

본 발명은 이상과 같은 사항을 감안하여 제안된 것으로서, H빔의 상부 플랜지에 인장 브라켓을 양측단에 설치하고 강연선을 인장 브라켓에 관통시킨 후에 강연선을 인장하고 정착구를 이용하여 인장 브라켓에 정착하여 하향 솟음을 갖도록 제작한 플리플렉션 H빔을 교각기초에 설치된 H빔의 일측단에는 상기 플리플렉션 H빔의 하향으로 솟음이 주어진 부분을 연결설치한 후에 콘크리트를 타설양생하여 교각을 완성하는 것이다. 이때 교각 두부의 양쪽날개에 작용하는 인장력이 상기 교각두부에 하향 솟음을 갖도록 설치된 상기 플리플렉션 H빔에 도입된 압축력에 의하여 상쇄되므로서 교각의 단면을 줄일 수 있도록 하는 것이다.The present invention has been proposed in view of the above matters, and the tension bracket is installed at both ends of the upper flange of the H-beam, the strand is passed through the tension bracket, and then the tension line is tensioned and fixed to the tension bracket using the anchorage. One side of the H-beam installed at the foundation of the piercing H-beam manufactured to have the rise is connected to the bottom of the fold-up H-beam to install the given part, and then the concrete is poured to finish the pier. At this time, the tensile force acting on both blades of the pier head is canceled by the compressive force introduced to the flip-hole H beam installed so as to rise downward on the pier head, thereby reducing the cross section of the pier.

도 1은 본 발명의 플리플렉션 H빔을 나타낸 도면.1 is a diagram illustrating a reflection H beam of the present invention.

도 2는 본 발명의 플리플렉션 H빔을 이용하여 T형 교각을 형성한 것을 보여주는 도면.2 is a view showing the formation of a T-type pier using the H-beam of the present invention.

도 3은 본 발명의 또다른 실시예로서 플리플렉션 H빔을 이용하여 T형 복층 교각을 형성한 것을 보여주는 도면.3 is a view showing the formation of a T-type multilayer pier using a reflection H beam as another embodiment of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10... T형 교각 11... 교각 두부10 ... T pier 11 ... Pier head

12... 콘크리트 13... H빔12 ... concrete 13 ... H beam

14... 교각 기초 15... 헌치14 ... Pier Foundation 15 ... Haunting

20... 플리플렉션 H빔 21... 상부 플랜지20 ... Flation H-beam 21 ... Upper flange

22... 하부 플랜지 23... 강연선22 ... lower flange 23 ... strand

24... 정착구 25... 인장 브라켓24 ... anchorage 25 ... tension bracket

30... T형 복층 교각 40... 상부 T형 교각30 ... T-type pier 40 ... Upper T-pier

50... 하부 T형 교각50 ... lower tee pier

본 발명은 H빔(13)의 상부 플랜지(21)에 인장 브라켓(25)을 양측단에 설치하고 강연선(23)을 인장 브라켓(25)에 관통시킨 후에 강연선(23)을 인장하고 정착구(24)를 이용하여 인장 브라켓(25)에 정착하여 하향 솟음을 갖도록 제작한 플리플렉션 H빔(20)과, 이를 이용하여 교각을 설치하고자하는 곳의 교각 기초(14)의 지반까지 H빔(13)을 설치하고 타단의 H빔(13)의 끝단에는 상기 플리플렉션 H빔(20)의 하향으로 솟음이 주어진 부분의 중앙을 연결설치한 후에 H빔(13)과 상기 플리플렉션 H빔(20)이 연결설치되는 부분에 복수의 헌치(15)를 설치하여 교각 두부(11)를 형성하고 콘크리트(12)를 타설양생하여 T형 교각(10)을 설치하는 것에 특징이 있다.In the present invention, the tension brackets 25 are installed at both ends of the upper flange 21 of the H beam 13, and the strands 23 are penetrated through the tension brackets 25 to tension the strands 23 and the anchorage 24 H-beam (20) to be fixed to the tension bracket (25) by using a) H-beam (20) produced to have a downward rise, and to the ground of the pier foundation (14) where the pier is to be installed using this After installing and connecting the center of the given portion to the bottom of the H-beam (20) to the other end of the H-beam 13 at the other end of the H-beam 13 and the H-beam (20) It is characterized by installing a plurality of haunch (15) in the portion to be connected to form the pier head (11) and pouring the concrete 12 to install the T-type pier (10).

상기의 강연선은 1개 또는 그 이상을 설치하여 인장력을 도입할 수 있는데 강연선의 개수는 교량의 설계하중의 크기에 따라 다양하게 설치한다.The stranded wire may be provided with one or more of the strands to introduce a tensile force, the number of the stranded wire is installed in various ways depending on the design load of the bridge.

또 다른 실시예로서, 교각 기초(14)의 기초지반까지 H빔(13)을 설치한 후에 타측의 H빔(13)의 끝단에 상기 플리플렉션 H빔(20)을 연결설치하여 교각 두부(11)를 형성하여 상부 T형 교각(40)을 설치하고, 일정간격을 두고 상기 플리플렉션 H빔(20)을 H빔(13)에 연결설치하여 교각 두부(11)를 형성하여 하부 T형 교각(50)을 설치하되 상기 플리프렉션 H빔(20)의 하향 솟음의 중앙부를 H빔(13)에 연결설치한후에 콘크리트(12)를 타설양생하여 T형 복층 교각(30)을 설치하는 것에 특징이 있다.In another embodiment, after installing the H-beam 13 to the foundation ground of the pier foundation 14, the piercing head 11 by connecting the reflection H-beam 20 to the end of the H-beam 13 on the other side ) To form the upper T-type pier 40, and to install the piercing H-beam 20 to the H-beam 13 at a predetermined interval to form a pier head (11) to form a lower T-pier ( 50) is installed, but after installing the center portion of the downward rise of the projection H beam 20 is connected to the H beam 13, the concrete 12 is poured and cured to install the T-type double piers 30. have.

상기의 강연선은 1개 또는 그 이상을 설치하여 인장력을 도입할 수 있는데 강연선의 개수는 교량의 설계하중의 크기에 따라 다양하게 설치한다.The stranded wire may be provided with one or more of the strands to introduce a tensile force, the number of the stranded wire is installed in various ways depending on the design load of the bridge.

상기와 같은 T형 교각시공 방법을 단계적으로 살펴보면 다음과 같다.Looking at the T-type bridge construction method as described above step by step.

교각 기초(14)를 이루는 기초의 기초지반에 교각의 기둥을 이루는 H빔(13)을 설치하고 교각 기초(14) 콘크리트(12)를 타설양생하는 단계와Installing the H beam 13 forming the pillar of the pier on the foundation ground of the foundation constituting the pier foundation 14 and pouring and curing the pier foundation 14 and the concrete 12;

교각의 기둥을 이루는 H빔(13)의 타측단에 상기 플리플렉션 H빔(20)을 연결설치하고 H빔(13)과 상기 플리플렉션 H빔(20)이 만나는 부분에 복수개의 헌치(15)를 설치하여 교각 두부(11)를 형성하는 단계와A plurality of haunches 15 are installed at the other end of the H beam 13 forming the pillar of the pier by connecting the Flection H beam 20 to the portion where the H beam 13 and the F H beam 20 meet. Step to form a pier tofu 11 by installing the

상기 교각 두부(11)와 교각의 기둥을 이루는 H빔(13)에 콘크리트(12)를 타설양생하여 T형 교각(10)을 설치하는 단계로 이루어진다.Placing the concrete 12 on the H beam 13 forming the pillar of the pier head 11 and the pier to install a T-type pier (10).

또한, 본 시공방법의 다른 실시예에 의한 T형 복층 교각시공방법은In addition, the T-type pier construction method according to another embodiment of the present construction method

교각 기초(14)를 이루는 기초의 기초지반에 교각의 기둥을 이루는 H빔(13)을 설치하고 교각 기초(14) 콘크리트(12)를 타설양생하는 단계와Installing the H beam 13 forming the pillar of the pier on the foundation ground of the foundation constituting the pier foundation 14 and pouring and curing the pier foundation 14 and the concrete 12;

교각의 기둥을 이루는 H빔(13)의 타측단에 상기 플리플렉션 H빔(20)을 연결설치하고 H빔(13)과 상기 플리플렉션 H빔(20)이 만나는 부분에 복수개의 헌치(15)를 설치하여 교각 두부(11)를 형성하여 상부 T형 교각(40)을 설치하는 단계와A plurality of haunches 15 are installed at the other end of the H beam 13 forming the pillar of the pier by connecting the Flection H beam 20 to the portion where the H beam 13 and the F H beam 20 meet. Installing the upper pier pier 40 by forming a pier head 11 by

상기 상부 T형 교각(40)을 설치하고 난 후에 하부로 일정한 거리를 두고 교량의 기둥을 형성하는 H빔(13) 상에 상기 플리플렉션 H빔(20)을 연결설치하고 복수개의 헌치(15)를 설치하여 교각 두부(11)를 형성하여 하부 T형 교각(50)을 설치하는 단계와After the installation of the upper T-pier 40, the bottom of the H-beam (20) connected to the H beam 13 to form a pillar of the bridge at a certain distance to the bottom and a plurality of haunch (15) Step to install the lower T-shaped pier (50) by installing a bridge head (11) to install the

상기 상, 하부 T형 교각(40, 50)의 교각 두부(11)와 교각의 기둥을 이루는 H빔(13)에 콘크리트(12)를 타설양생하여 T형 복층 교각(30)을 설치하는 단계로 설치되는 것에 특징이 있다.Placing concrete 12 on the H-beam 13 forming the pier head 11 and the pier pillar of the upper and lower T-pier pier (40, 50) to install the T-type double piers (30) It is characterized by being installed.

이하, 첨부된 도면에 의하여 본 발명의 기술적 구성 및 작용을 상세히 설명하면 다음과 같다.Hereinafter, the technical configuration and operation of the present invention by the accompanying drawings in detail.

도 1은 본 발명의 플리플렉션 H빔을 나타낸 도면으로서 H빔(13)의 상부 플랜지(21)에 인장 브라켓(25)을 양측단에 설치하고 강연선(23)을 인장 브라켓(25)에 관통시킨 후에 강연선(23)을 인장하고 정착구(24)를 이용하여 인장 브라켓(25)에 정착하여 하향 솟음을 갖도록 제작한 플리플렉션 H빔(20)이다.FIG. 1 is a view showing a reflection H-beam of the present invention, in which tension brackets 25 are installed at both ends of the upper flange 21 of the H-beam 13, and the strand 23 is penetrated through the tension brackets 25. As shown in FIG. Later, the stranded wire 23 is pulled and is fixed to the tension bracket 25 using the anchoring hole 24 to produce a reflection H beam 20 to have a downward rise.

이와 같이 상기 플레플렉션 H빔(20)에 하향의 솟음을 갖게하면 상기 플리플렉션 H빔(20)의 상부 플랜지(21)에 압축력이 도입되고 하부 플랜지(22)에 인장력이 도입되어 이러한 플리프렉션 H빔(20)이 교각 두부(11)에 설치되면 추후에 교각이 완성되어 교각 두부(11)에 하중이 작용하게되면 교각 두부(11)의 양쪽의 날개에는 하향의 인장력이 작용하게되는데 이러한 인장력을 교각 두부(11)에 설치된 상기 플리플렉션 H빔(20)에 도입된 압축력에 의하여 상쇄되게하는 것이다.In this way, when the projection H beam 20 has a downward rise, a compressive force is introduced to the upper flange 21 of the reflection H beam 20, and a tensile force is introduced to the lower flange 22, such a flip. When the traction H beam 20 is installed on the pier head 11, the pier is completed later, and when a load is applied to the pier head 11, downward tension is applied to both wings of the pier head 11. The tensile force is to be canceled by the compressive force introduced into the reflection H-beam 20 provided in the pier head (11).

도 2는 본 발명의 플리플렉션 H빔을 이용하여 T형 교각을 형성한 것을 보여주는 도면으로서 교각 기초(14)의 기초지반까지 H빔(13)을 설치하고 타단의 H빔(13)에 상기 플리플렉션 H빔(20)을 연결설치하고 H빔(13)과 상기 플리플렉션 H빔(20)이 서로 연결되는 부분에 복수개의 헌치(15)를 설치하여 교각 두부(11)를 형성한 후에 교각 두부(11)와 기둥을 형성하는 H빔(13) 및 교각 기초(14)에 콘크리트(12)를 타설양생하여 T형 교각(10)을 설치하게 되는 것을 보여주는 도면이다.FIG. 2 is a view showing the formation of a T-type pier using the reflection H beam of the present invention, in which the H beam 13 is installed up to the foundation ground of the pier foundation 14, and the H beam 13 at the other end is provided. After connecting the reflection H-beam 20 and installing the plurality of haunches 15 in the portion where the H-beam 13 and the reflection H-beam 20 are connected to each other to form a pier head (11), the pier head (11) and the H beam 13 and the bridge foundation 14 to form a pillar 12 to pour the concrete 12 is a view showing that the T-shaped pier 10 is installed.

상기 교각은 하천에 설치되는 수중교각 또는 지상에 설치되는 교각에 모두 동일하게 적용할 수 있다.The pier is equally applicable to both underwater piers installed in rivers or piers installed on the ground.

도 3은 본 발명의 또다른 실시예로서 플리플렉션 H빔을 이용하여 복층의 T형 교각을 형성한 것을 보여주는 도면으로서 상기 도 2의 T형 교각(10)을 상하로 설치한 것이다.3 is a view showing the formation of a T-type pier in multiple layers using a reflection H-beam as another embodiment of the present invention, in which the T-type pier 10 of FIG. 2 is installed up and down.

교각 기초(14)의 기초 지반까지 H빔(13)을 설치하여 교각 기둥을 설치한 후에 타측의 H빔(13)의 끝단에 상기 플리플렉션 H빔(20)을 연결설치하고 H빔(13)과 상기 플리플렉션 H빔(20)이 서로 만나는 부분에 복수개의 헌치(15)를 설치한 교각 두부(11)를 형성하여 상부 T형 교각(40)을 설치하고, 하부로 일정간격을 두고 상기 플리플렉션 H빔(20)을 H빔(13)에 연결설치하고 H빔(13)과 상기 플리플렉션 H빔(20)이 서로 만나는 부분에 복수의 헌치(15)를 설치한 교각 두부(11)를 형성하여 하부 T형 교각(50)을 설치한 후에 상기 상부 및 하부 T형 교각(40, 50)과 기둥을 이루고 있는 H빔(13)과 교각 기초(14)에 콘크리트(12)를 타설양생하여 T형 복층 교각(30)을 설치하는 것이다.After installing the H beam 13 to the foundation ground of the pier foundation 14, the pier pillar is installed, and then connecting the reflection H beam 20 to the end of the H beam 13 on the other side, and then installing the H beam 13 And piercing head 11 having a plurality of haunches 15 installed at a portion where the reflection H beam 20 meets each other to install an upper T-pier pier 40, and to the lower portion at a predetermined interval. Pier head 11 having a plurality of haunches 15 provided at a portion where the reflection H beam 20 is connected to the H beam 13 and the H beam 13 and the reflection H beam 20 meet each other. After forming and installing the lower T-pier pier (50) by pouring concrete (12) to the H beam 13 and the pier foundation (14) forming a column with the upper and lower T-pier pier (40, 50) The T-type multilayer pier 30 is provided.

상기와 같은 교각을 다수개 설치하여 교각 두부의 상부에 교량상판을 설치하고 상판위에 아스팔트 콘크리트를 포설하면 교량이 설치되는 것이다.By installing a plurality of bridges as described above, if the bridge top plate is installed on the upper part of the bridge head and asphalt concrete is laid on the top plate, the bridge is installed.

이상의 설명에서와 같이, 본 발명은 압축력이 도입된 플리플렉션 H빔을 교각 두부에 설치하고 교각 기둥을 형성하고 있는 H빔에 연결설치하고 콘크리트를 타설양생하여 교각을 설치하는 것이다. 이러한 방법은 교각 두부에 작용하는 하향의 인장력을 상기 플리플렉션 H빔에 도입된 압축력에 의하여 상쇄되어 기존 교량의 설계 단면에 비하여 단면이 작아지게 할 수 있는 시공방법이다. 이러한 방법은 시공방법이 간단하면서 교량의 단면이 작아지는 장점이 있으며 이렇게 설치하게 되므로서 건설기간의 단축 및 이로 인한 공사비의 절감을 할 수 있는 매우 유용한 경제적인 공법인 것이다.As described above, the present invention is to install the fold reflection H-beam in the pier head and connect to the H-beam forming the pier pillars and to pour concrete to install the pier. This method is a construction method in which the downward tension acting on the head of the bridge is canceled by the compressive force introduced into the Flection H beam, so that the cross section becomes smaller than the design cross section of the existing bridge. This method has the advantage that the construction method is simple and the cross section of the bridge is small, and this is a very useful economic method that can shorten the construction period and thereby reduce the construction cost due to the installation.

Claims (7)

H빔의 상부 플랜지에 인장 브라켓을 양측단에 설치하고 강연선을 인장 브라켓에 관통시킨 후에 강연선을 인장하고 정착구를 이용하여 인장 브라켓에 정착하여 상부 플랜지가 압축력을 하부 플랜지가 인장력을 갖도록 하향 솟음을 갖는 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔.Tension brackets are installed at both ends of the upper flange of the H-beam, and the strands are penetrated through the tension brackets, and the strands are tensioned and fixed to the tension brackets using the anchorages so that the upper flanges have a compressive force and the lower flanges have a tensile force. A reflection H-beam incorporating prestressing characterized by the above-mentioned. 제 1항에 있어서,The method of claim 1, 상기 플리플렉션 H빔의 하향 솟음의 중앙부를 교각기초에 설치된 H빔의 타측단에 연결설치하고 다수개의 헌치를 설치한 후에 콘크리트를 타설양생하여 설치된 T형 교각인 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔.The pre-stressed pier is characterized in that it is a T-type bridge piers installed by pouring concrete after installing the central part of the downward rise of the reflection H beam at the other end of the H beam installed at the foundation of the bridge and installing a plurality of haunches. Reflection H beam. 제 1항에 있어서,The method of claim 1, 상기 플리플렉션 H빔의 하향 솟음의 중앙부를 교각기초에 설치된 H빔에 상하로 연결설치하고 각각 다수개의 헌치를 설치한 후에 콘크리트를 타설양생하여 설치된 복층 T형 교각인 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔.The pre-stress is introduced by connecting the center portion of the downward H-beam of the reflection H-beam up and down to the H-beam installed at the foundation of the bridge and installing a plurality of haunts, respectively, and then pouring concrete to pour the concrete. Flection H-beam. 교량의 교각을 설치하는 방법에 있어서,In the method of installing the bridge piers, a) 교각 기초를 이루는 기초의 기초지반에 교각의 기둥을 이루는 H빔을 설치하고 교각 기초 콘크리트를 타설양생하는 단계;a) installing an H beam forming a column of piers on the foundation ground of the foundation forming the piers foundation and pouring the piers foundation concrete; b) 교각의 기둥을 이루는 H빔의 타측단에 상기 플리플렉션 H빔을 연결설치하고 H빔과 상기 플리플렉션 H빔이 만나는 부분에 복수개의 헌치를 설치하여 교각 두부를 형성하는 단계; 및b) forming a pier head by connecting the pletion H beam to the other end of the H beam forming the pillar of the pier and installing a plurality of haunts at a portion where the H beam and the fold H beam meet; And c) 상기 교각 두부와 교각의 기둥을 이루는 H빔에 콘크리트를 타설양생하여 T형 교각을 설치하는 단계로 이루어지는 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔을 이용한 T형 교각 시공방법.c) T-type pier construction method using the pre-stressed H-beams, characterized in that the step of installing concrete T-beams in the H beam constituting the pier head and pier pillars. 제 4항에 있어서,The method of claim 4, wherein 상기 b)단계에서 교각 두부를 형성하기 위하여 설치되는 상기 플리플렉션 H빔은 하향의 솟음을 갖는 것으로서 상기 교각 기둥을 이루는 H빔의 타측단 위에 설치할 때 하향 솟음의 중앙부분이 상기 H빔과 만나도록 하는 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔을 이용한 T형 교각 시공방법.The reflection H beam installed to form the pier head in step b) has a downward rise so that the center portion of the downward rise meets the H beam when installed on the other end of the H beam forming the pier pillar. T-type pier construction method using a reflection H-beam incorporating prestressing characterized in that. 교량의 교각을 설치하는 방법에 있어서,In the method of installing the bridge piers, a) 교각 기초를 이루는 기초의 기초 지반에 교각의 기둥을 이루는 H빔을 설치하고 교각 기초의 콘크리트를 타설양생하는 단계;a) installing an H beam forming a pillar of the piers on the foundation ground of the foundation forming the piers foundation and pouring concrete of the piers foundation; b) 교각의 기둥을 이루는 H빔의 타측단에 상기 플리플렉션 H빔을 연결설치하고 H빔과 상기 플리플렉션 H빔이 만나는 부분에 복수개의 헌치를 설치하여 교각 두부를 형성하여 상부 T형 교각을 설치하는 단계;b) The pleated H beam is connected to the other end of the H beam forming the pillar of the pier, and a plurality of haunts are formed at the portion where the H beam and the pleated H beam meet to form a pier head, thereby forming an upper T pier. Installing; c) 상기 상부 T형 교각을 설치하고 난 후에 하부로 일정한 거리를 두고 교량의 기둥을 형성하는 H빔 상에 상기 플리플렉션 H빔을 연결설치하고 복수개의 헌치를 설치하여 교각 두부를 형성하여 하부 T형 교각을 설치하는 단계; 및c) After installing the upper T-shaped bridge pier connecting the reflection H-beams on the H beam to form a pillar of the bridge at a constant distance to the bottom and a plurality of haunch to form a bridge head to form a lower head T Installing a mold piers; And d) 상기 상, 하부 T형 교각의 교각 두부와 교각의 기둥을 이루는 H빔에 콘크리트를 타설양생하여 T형 복층 교각을 설치하는 단계로 이루어지는 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔을 이용한 T형 교각 시공방법.d) using a pre-stressed H-beam using pre-stressing, characterized in that the step of pour concrete into the H beam constituting the pier head and pier columns of the upper, lower T-type bridge piers T-type pier construction method. 제 6항에 있어서,The method of claim 6, 상기 b), c)단계에서 교각 두부를 형성하기 위하여 설치되는 상기 플리플렉션 H빔은 하향의 솟음을 갖는 것으로서 상기 교각 기둥을 이루는 H빔상에 설치할 때 하향 솟음의 중앙부분이 상기 H빔과 만나도록 하는 것을 특징으로 하는 프리스트레스를 도입한 플리플렉션 H빔을 이용한 T형 교각 시공방법.The reflection H beam installed to form the pier head in steps b) and c has a downward rise so that the center portion of the downward rise meets the H beam when installed on the H beam forming the pier pillar. T-type pier construction method using a reflection H-beam incorporating prestressing characterized in that.
KR10-2002-0076379A 2002-12-03 2002-12-03 Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam KR100511464B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0076379A KR100511464B1 (en) 2002-12-03 2002-12-03 Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0076379A KR100511464B1 (en) 2002-12-03 2002-12-03 Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0036265U Division KR200307713Y1 (en) 2002-12-04 2002-12-04 Prestressed preflextion H-beam

Publications (2)

Publication Number Publication Date
KR20040049354A true KR20040049354A (en) 2004-06-12
KR100511464B1 KR100511464B1 (en) 2005-08-31

Family

ID=37343766

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0076379A KR100511464B1 (en) 2002-12-03 2002-12-03 Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam

Country Status (1)

Country Link
KR (1) KR100511464B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103774550A (en) * 2014-01-08 2014-05-07 华侨大学 Box-shaped steel pier with embedded energy consumption shell plates
CN104213504A (en) * 2014-09-25 2014-12-17 中铁第一勘察设计院集团有限公司 Rotation V-type T-structure bridge pier and construction thereof
CN105019350A (en) * 2014-04-30 2015-11-04 郑州大学 Prefabricated T-shaped beam and method of building continuous beam bridge by adopting prefabricated T-shaped beams
CN110725220A (en) * 2019-10-26 2020-01-24 中铁六局集团有限公司 Construction method for dismantling pier
CN113235459A (en) * 2021-06-17 2021-08-10 安徽省路港工程有限责任公司 Assembled main bridge pier roof beam concreties device temporarily

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS509931A (en) * 1973-06-01 1975-01-31
JPH0520817Y2 (en) * 1985-04-05 1993-05-28
JPH0673709A (en) * 1991-05-27 1994-03-15 Yuuji Sorayama Anchorage device for anchoring prestressing steel to tension flange of steel girder
JPH07317208A (en) * 1994-05-23 1995-12-05 Maeda Corp Reinforcing structure of h beam
KR100202270B1 (en) * 1996-03-13 1999-06-15 조세훈 Deck plate for reforced concrete slab
KR100188465B1 (en) * 1996-12-04 1999-06-01 황문삼 Apparatus for stiffening the side of foundation pits and sheathing board
KR20020007818A (en) * 2000-07-19 2002-01-29 신흥우 Steel bridge reinforcement equipment
KR200235027Y1 (en) * 2000-10-06 2001-09-26 주식회사 만영엔지니어링 A pier
KR100396715B1 (en) * 2001-05-28 2003-09-02 (주)스틸엔콘크리트 The method of prestressed composite beam made by using incrementally prestressing
KR200297321Y1 (en) * 2002-05-28 2002-12-12 박대열 Prestressed steel beam
KR100509452B1 (en) * 2002-12-03 2005-08-24 노윤근 Prestressed preflextion H-beam and method for building a Π-shaped bridge pier using the H-beam

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103774550A (en) * 2014-01-08 2014-05-07 华侨大学 Box-shaped steel pier with embedded energy consumption shell plates
CN103774550B (en) * 2014-01-08 2016-01-20 华侨大学 The box steel pier of embedded power consumption coverboard
CN105019350A (en) * 2014-04-30 2015-11-04 郑州大学 Prefabricated T-shaped beam and method of building continuous beam bridge by adopting prefabricated T-shaped beams
CN105019350B (en) * 2014-04-30 2017-02-15 郑州大学 Prefabricated T-shaped beam and method of building continuous beam bridge by adopting prefabricated T-shaped beams
CN104213504A (en) * 2014-09-25 2014-12-17 中铁第一勘察设计院集团有限公司 Rotation V-type T-structure bridge pier and construction thereof
CN104213504B (en) * 2014-09-25 2016-06-01 中铁第一勘察设计院集团有限公司 Turn V-type T structure bridge pier and constructional method thereof
CN110725220A (en) * 2019-10-26 2020-01-24 中铁六局集团有限公司 Construction method for dismantling pier
CN113235459A (en) * 2021-06-17 2021-08-10 安徽省路港工程有限责任公司 Assembled main bridge pier roof beam concreties device temporarily

Also Published As

Publication number Publication date
KR100511464B1 (en) 2005-08-31

Similar Documents

Publication Publication Date Title
KR100935096B1 (en) Prestressed-precast-segmental stone arch bridge and its constructing method
KR100991869B1 (en) Single and continuous prestressed concrete girder bridge and the construction method
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
JP2004092078A (en) Structure and construction method for bridge
JP2007002557A (en) Overhang road
KR100901803B1 (en) Method for composite girder and bridge construction method composite girder
KR100511464B1 (en) Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam
CN209114299U (en) A kind of Single-box multi-chamber box beam bridge
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
CN117051700A (en) Construction method of prestress system of pier stud reserved post-pouring capping beam
CN217268348U (en) Hybrid prestressed composite beam
KR100547485B1 (en) Continuous multi-span bridge using bridge girder units and construction method thereof
KR200307713Y1 (en) Prestressed preflextion H-beam
KR100509452B1 (en) Prestressed preflextion H-beam and method for building a Π-shaped bridge pier using the H-beam
KR100393132B1 (en) Construction method of composite steel-box bridge using prestress
KR20020010175A (en) The continuous method in p.s.c beam with steel plate girder splice and there of apparatus
KR200307712Y1 (en) Prestressed preflextion H-beam
KR100565359B1 (en) Continuous Bridge Construction Method
KR100466017B1 (en) The Method of Reinforce Steel Box Girder type Bridge and The Structure thereof
KR100555251B1 (en) The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this
KR100556719B1 (en) H shaped steel beam having a graded prestress introduction apparatus and method for installing temporary steel bridge using the H shaped steel beam
KR20030006681A (en) Apparatus and method for reinforcing a construction by enlarging its&#39; size
KR100530025B1 (en) Section enlargement repairing and reinforcing apparatus for reinforcing earing power of reinforced concrete structures by introducing prestress to entended section and repairing and reinforcing construction method using the apparatus
CN216474457U (en) Short T roof beam flood bridge flood fighting anchorage structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee