KR100565359B1 - Continuous Bridge Construction Method - Google Patents

Continuous Bridge Construction Method Download PDF

Info

Publication number
KR100565359B1
KR100565359B1 KR1020030073929A KR20030073929A KR100565359B1 KR 100565359 B1 KR100565359 B1 KR 100565359B1 KR 1020030073929 A KR1020030073929 A KR 1020030073929A KR 20030073929 A KR20030073929 A KR 20030073929A KR 100565359 B1 KR100565359 B1 KR 100565359B1
Authority
KR
South Korea
Prior art keywords
bridge
upper inner
inner steel
horizontal member
girder
Prior art date
Application number
KR1020030073929A
Other languages
Korean (ko)
Other versions
KR20050038713A (en
Inventor
방명석
고한승
Original Assignee
휘선건설(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 휘선건설(주) filed Critical 휘선건설(주)
Priority to KR1020030073929A priority Critical patent/KR100565359B1/en
Publication of KR20050038713A publication Critical patent/KR20050038713A/en
Application granted granted Critical
Publication of KR100565359B1 publication Critical patent/KR100565359B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 교량용거더를 이용한 교량연속화공법에 관한 것으로, I형, T형, U형, 박스 거더 등과 같은 교량용거더 상부플랜지 단부를 본 발명의 연속화수단인 연결틀 설치에 충분한 길이의 홈을 파고, 고강도 나사철근 및 나사강봉을 포함하는 상부내부강재가 상기 상부플랜지를 돌출하도록 제작하고, 상부내부강재가 형성된 교량용거더를 단순보 방식으로 설치하여, 상기 상부내부강재를 슬래브콘크리트 타설 전에 상기 연속화수단에 너트부재로 고정시켜 슬래브콘크리트 타설 하중을 부담할 수 있도록 함으로서, 기존의 2차사하중 및 활하중에 부담에 관한 교량의 연속화 시공을 더욱 효율적으로 개선한 교량연속화공법에 관한 것이다.The present invention relates to a bridge sequencing method using a bridge girder, the bridge girder upper flange end, such as I type, T type, U type, box girder, etc. The upper inner steel including digging, high-strength screw reinforcing and screw steel rods are made to protrude the upper flange, and the bridge girder formed with the upper inner steel is installed in a simple beam method, and the upper inner steel is placed before slab concrete pouring. The present invention relates to a bridge sequencing method in which a sequential load of a slab concrete is fixed by a nut member to a sequential means, thereby more efficiently improving the sequential construction of bridges with a burden on existing secondary dead and live loads.

연속화, 고강도 나사철근, 고강도 나사강봉, 연결틀Continuous, high strength threaded rod, high strength threaded rod, connecting frame

Description

교량연속화공법{Continuous Bridge Construction Method}Continuous Bridge Construction Method

도1a 및 도1b는 본 발명에 따른 연속화공법을 이용하여 RC 및 PSC 거더를 연결한 상태의 종단면도 및 평면도이다. 1A and 1B are a longitudinal sectional view and a plan view of a state in which RC and PSC girder are connected by using a sequencing method according to the present invention.

도2a,도2b,도2c,도2d 및 도2e는 본 발명에 따른 연속화 방법을 이용하여 RC 및 PSC거더를 연결시키는 순서에 따른 시공도를 도시한 것이다.Figures 2a, 2b, 2c, 2d and 2e show the construction according to the sequence of connecting the RC and PSC girder using the sequencing method according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of Symbols for Main Parts of Drawings>

10:교각 20:교량받침10: pier 20: bridge bearing

100:RC 및 PSC 거더 200:연속화수단100: RC and PSC girder 200: serialization means

210:연속화수단의 가로부재 220:연속화수단의 세로부재210: horizontal member of serializing means 220: vertical member of serializing means

230:너트부재230: nut member

300:슬래브콘크리트 310:슬래브강재300: slab concrete 310: slab steel

본 발명은 기존의 RC 및 PSC 거더와 같은 교량용거더의 연속화가 2차사하중 및 활하중에 더하여 슬래브콘크리트 하중까지 연속화 되게 함으로서, 종래의 단순 보 설치방식에서 전체하중의 1/3정도를 차지하는 슬래브콘크리트 사하중을 연속화된 교량용거더가 지지하도록 함으로서 보다 경제적이고 효율적인 교량 연속화 시공방법에 관한 것이다. 교량용 거더를 연속화하는 종래의 방법은 슬래브콘크리트에 연속철근을 배근하거나 연결부 주변에 강선을 배근하여 긴장을 도입하는 공법 및 지점부의 상승·하강을 이용하여 연속하는 공법 등이 있었으나 이는 연속화된 거더가 2차사하중이나 활하중을 지지하도록 한 것이지 슬래브콘크리트 사하중이나 보의 사하중은 단순보 구조로 지지하는 방식이었다. 즉 종래의 교량 연속화 공법은 전체하중 중 1/3을 차지하는 2차사하중 및 활하중만을 연속보로 지지하는 방식으로 교량용거더를 연속화하고 있었다. The present invention allows the continuity of bridge girders such as RC and PSC girders to be continued to slab concrete loads in addition to secondary dead loads and live loads, so that the slab concrete occupies about one third of the total load in the conventional simple beam installation method. The present invention relates to a more economical and efficient bridge continuity construction method by supporting the dead weight of the bridge girder. Conventional methods of sequencing bridge girders include a method of introducing a continuous reinforcement to a slab concrete or a steel wire around a connecting part to introduce tension, and a continuous method using a rising / falling point of a branch. Secondary or live loads were to be supported, but slab concrete and beams were supported by a simple beam structure. That is, the conventional bridge sequencing method has continued the girder for bridges in such a way that only the secondary dead and live loads, which occupy one third of the total load, are supported by continuous beams.

또한 최근에 개발된 슬래브콘크리트 사하중을 연속화하기 위해서 PSC 거더에 PC강봉을 이용한 연속화 공법이 제안되었으나 이는 활하중에 차륜 축하중이 정착구에 끊임없는 반복하중으로 작용함으로서 피로에 의해 도입된 프리스트레스가 손실되고 정착구가 파손될 가능성이 있으며, 시공상 PC강봉의 삽입 및 긴장이 어렵고 제작 시 삽입구의 오차에 의해서 현장 설치가 불가능할 가능성 등 시공성이 매우 낮고 경제적인 면에서도 제작 및 시공단가의 상승 등 문제점이 많았으며, 매우 큰 응력단차가 발생하여, 그 부근의 콘크리트부에 균열이 발생하는 문제점이 지적되어 최근에는 널리 사용되지 않는 실정이다. In addition, in order to continually develop the slab concrete dead weight, the sequential construction method using PC steel bar was proposed for the PSC girder, but the pre-stress introduced by fatigue is lost due to the continuous cyclic load on the anchorage during live load and the anchorage is lost. There is a possibility of breakage, and it is difficult to insert and tension PC steel rod during construction, and it is impossible to install on site due to the error of insertion hole during manufacturing. It is pointed out that a problem arises in that a large stress step is generated and a crack occurs in a concrete part nearby, and it is not widely used recently.

상기와 같은 종래 기술의 문제점으로 인해 시공성 및 경제성을 고려한 대체공법 개발의 필요성이 제기되었다.Due to the problems of the prior art as described above, the necessity of developing alternative construction methods in consideration of workability and economics has been raised.

본 발명의 목적은 기존 RC 및 PSC 거더 등을 포함한 교량용거더의 연속화수단의 단점을 극복하고자 창출한 것으로, 보다 안전하고 내구성이 있으며 시공이 간편하여 특정업체만이 시공이 가능하지 않은 교량용거더 및 연속화수단을 이용한 교량 연속화공법을 제공하기 위한 것이다. An object of the present invention was created to overcome the shortcomings of the continuity means of the bridge girder, including the existing RC and PSC girder, more secure, durable and easy to use construction only bridge construction girder And to provide a bridge sequencing method using the sequencing means.

본 발명은 특히 RC 거더(Reinforced Concrete Girder) 및 PSC 거더(Prestressed Concrete Girder) 제작 시 단부에 연결틀과 같은 연속화수단을 설치할 수 있을 정도의 충분한 길이의 홈을 파서 고강도 나사 강봉을 포함하는 상부내부강재를 돌출하도록 제작하여 교각, 교대와 같은 교량하부구조물에 단순보 방식으로 설치하고, 슬라브콘크리트 타설 전에 상기 상부내부강재를 연속화수단을 통하여 너트부재In particular, the present invention provides an upper inner steel including a high-strength threaded steel rod by digging a groove of sufficient length to install a continuity means such as a connecting frame at the end when manufacturing RC girder and reinforced concrete girder. It is manufactured to protrude and installed in a simple beam method on the bridge substructures, such as bridge piers, shifts, and the nut member through the sequencing means to the upper inner steel prior to slab concrete

로 고정함으로서 거더를 연속화시켜 슬라브콘크리트 하중을 연속보 구조로 지지하도록 하여 RC 및 PSC 거더와 같은 교량용거더의 형고 또는 단면크기를 줄이거나 지지길이를 늘일 수 있는 효율적이고 경제적인 교량시공이 가능한 것을 기술적 특징으로 하며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 최선의 실시예를 첨부도면을 참조로 하여 상세히 설명하며, 도 1 및 도 2를 을 참조하여 RC 및 PSC 거더인 교량용거더 및 이를 이용한 교량 연속화공법을 기준으로 그 각각을 살펴본다.It is possible to efficiently and economically construct bridges to reduce the profile height or cross-sectional size of bridge girder such as RC and PSC girder or to increase the support length by continually girder to support slab concrete load by continuous beam structure. Technical features, the best embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art to which the present invention pertains can be easily carried out, with reference to Figures 1 and 2 Then, each of them will be examined on the basis of the bridge girder which is RC and PSC girder and the bridge continuous method using the same.

<RC 및 PSC 거더(교량용거더)><RC and PSC girder (bridge girder)>

본 발명의 RC 및 PSC 거더(100)는 통상의 RC 및 PSC 거더 제작방법에 의해 제작되며, 제작된 RC 및 PSC 거더는 다경간에 걸쳐 교각위에 교량받침을 이용하여 설치되고 서로 단부가 연결되어 연속보로서 기능하게 된다.RC and PSC girder 100 of the present invention is manufactured by a conventional RC and PSC girder manufacturing method, the manufactured RC and PSC girder is installed by using the bridge support on the bridge over the multi-span and the end is connected to each other continuous beam Function as.

도1a 및 도1b는 본 발명의 RC 및 PSC 거더(100)의 연결부인 각 단부가 연속화수단(200)에 의하여 서로 연결된 상태를 종단면도 및 평면도로 도시한 것이다.Figures 1a and 1b is a longitudinal cross-sectional view and a plan view showing a state in which each end of the connection portion of the RC and PSC girder 100 of the present invention is connected to each other by the sequencing means 200.

각 RC 및 PSC 거더(100)에는 다수의 상부내부강재(110)가 RC 및 PSC 거더의 상부플랜지 단부에 형성된 블록 아웃된 홈(120)을 돌출 연장하도록 형성되며, 서로 대응되는 상부내부강재(110)는 연속화수단(200)에 의하여 연결된다. 이러한 연결에 의하여 RC 및 PSC 거더가 서로 연속보로서 기능 하게된다. 상기 홈(120)은 최종적으로 슬래브콘크리트(300) 타설 등에 의하여 메워지게 되고, 후술되는 연속화수단(200)을 수용하는 공간이 된다. Each RC and PSC girder 100 has a plurality of upper inner steel 110 is formed to protrude to extend the blocked groove 120 formed at the upper flange end of the RC and PSC girder, the upper inner steel 110 corresponding to each other ) Is connected by the serialization means (200). This connection causes the RC and PSC girders to function as continuous beams to each other. The groove 120 is finally filled by placing the slab concrete 300, etc., and becomes a space for accommodating the sequencing means 200 to be described later.

이에 홈(120)의 길이(L),두께(H) 및 폭(D)은 최소한으로 형성되도록 함이 바람직한데, 길이(L)의 경우 적어도 연속화수단(200)이 수용될 수 있으며, 그 설치작업이 용이할 수 있도록 지점부와 같이 부모멘트 발생구간에 설치하고, 그 두께(H)는 적어도 후술되는 연속화수단(200)의 가로부재(210)가 홈의 내부에 수용될 수 있도록 연속화수단의 가로보 두께보다 약간 크게 형성되도록 결정하되 RC 및 PSC 거더의 상부플랜지 두께보다는 작도록 형성시키며, 그 폭(D)은 설치되는 상부내부강재의 폭 방향 설치개수에 따라 최소한으로 형성되도록 함이 바람직하다.The length (L), thickness (H) and width (D) of the groove 120 is preferably to be formed to a minimum, in the case of the length (L) at least the continuation means 200 can be accommodated, the installation It is installed in the parent section generating section, such as the point portion to facilitate the operation, the thickness (H) is at least of the continuum means so that the horizontal member 210 of the sequencing means 200 to be described later can be accommodated in the groove The thickness of the cross beam is determined to be slightly larger than the thickness of the upper flange of the RC and PSC girders, and the width D is preferably formed to be at least according to the widthwise installation number of the upper inner steel to be installed.

이때, 상기 돌출된 상부내부강재(100)의 길이는 도2에서 a로 표시된 라인에 미치지 못할 정도의 길이를 가지도록 형성되도록 한다. 즉 RC 및 PSC 거더의 단부에 수직으로 설치되는 단부거푸집을 넘어서 돌출되지 않도록 함으로서, 상부내부강 재(110)를 너트부재(230)로 연속화수단(200)의 가로부재(210)에 체결할 때 용이하게 인장력이 도입되도록 한다.At this time, the length of the protruding upper inner steel 100 is formed to have a length that does not reach the line indicated by a in FIG. That is, when the upper inner steel 110 is fastened to the horizontal member 210 of the sequencing means 200 by the nut member 230 by preventing it from protruding beyond the end formwork vertically installed at the ends of the RC and PSC girder. Make it easy to introduce tension.

상기 연속화수단(200)은 서로 연결될 상부내부강재(110)의 각 단부가 고정되며, 상부내부강재와 직각방향으로 설치되는 가로부재(210); 및 상기 가로부재를 서로 연결시키는 세로부재(220);를 포함한다.The continuation means 200 is a horizontal member 210 is fixed to each end of the upper inner steel 110 to be connected to each other, installed in a direction perpendicular to the upper inner steel material; And a vertical member 220 connecting the horizontal members to each other.

연속화수단(200)은 상기 가로부재(210) 및 세로부재(220)에 의하여 RC 및 PSC 거더의 상부내부강재(110)를 서로 연결시키는 기능을 하는 것으로서, 상부내부강재(110)가 너트부재(230)에 의하여 조여질 때 인장력이 도입되도록 지지대역할을 하게 된다. The sequencing means 200 has a function of connecting the upper inner steel 110 of the RC and PSC girder to each other by the horizontal member 210 and the vertical member 220, the upper inner steel 110 is a nut member ( When tightened by 230, the support band is to be introduced so that the tensile force is introduced.

가로부재(210)는 도1b와 같이 서로 연결되는 RC 및 PSC 거더(100)의 상부내부강재(110)의 단부가 관통될 수 있도록 구멍이 형성되며, RC 및 PSC 거더의 홈(120)에 수용되는 두께를 가지며 그 폭은 연결시킬 상부내부강재의 설치 개수에 따라 결정된다. 도1b에서는 각각 4개의 상부내부강재가 일정한 간격을 두고 설치될 수 있는 폭을 가지도록 형성된 경우가 도시되어 있다.Horizontal member 210 has a hole is formed so that the end of the upper inner steel 110 of the RC and PSC girder 100 connected to each other as shown in Figure 1b is accommodated in the groove 120 of the RC and PSC girder The width is determined by the number of installations of the upper inner steel to be connected. In FIG. 1B, four upper inner steels are formed to have widths that can be installed at regular intervals.

연결될 상부내부강재 각 4개가 관통되는 가로부재 2개가 서로 마주보면서 설치되어 결국 가로부재는 상부내부강재와 수직을 이룰 수 있도록 한다.Two horizontal members, each of which passes through each of the upper inner steels to be connected, are installed facing each other so that the horizontal members can be perpendicular to the upper inner steels.

상기 2개의 가로부재를 서로 연결시키는 부재가 세로부재(220)이다. 상기 세로부재와 가로부재의 연결방식은 구조적으로 세로부재가 지점부재로서 기능하며 이러한 지점부재에 가로부재가 연속부재로 기능하도록 한다. 말하자면 가로부재는 세로부재에 의하여 연속성이 단절되지 않도록 해야 한다. 또한 세로부재(220)는 도1b와 같이 서로 인접한 상부내부강재(110)의 항복인장력과 동일한 인장력이 확보될 수 있는 강도를 가지도록 해야 하며 소정의 두께를 가지는 강판(Steel Plate) 등을 이용할 수 있다. 나아가 가로부재(210)의 경우도 상부내부강재의 항복인장력에 의한 전단력과 모멘트에 저항할 수 있는 강도 및 강성을 가지도록 해야 하며 역시 소정의 두께를 가지는 강판 등을 이용할 수 있다.The member connecting the two horizontal members to each other is the vertical member 220. The vertical member and the horizontal member are connected to each other structurally so that the vertical member functions as a point member and the horizontal member functions as a continuous member. In other words, the horizontal member should not be interrupted by the longitudinal member. In addition, the vertical member 220 should have the same strength as the yield strength of the upper inner steel 110 adjacent to each other as shown in Figure 1b to ensure the strength and can use a steel plate (Steel Plate) having a predetermined thickness, etc. have. Furthermore, the horizontal member 210 should also have strength and rigidity capable of resisting shear force and moment due to the yield tensile strength of the upper internal steel, and steel sheets having a predetermined thickness may also be used.

이로서 상기 연속화수단(200)은 가로부재(210) 및 세로부재(220)가 서로 결합된 연결틀의 형상으로 제작되며, 이러한 연속화수단은 RC 및 PSC 거더의 상부플랜지 내부에 형성되며, 교량 전체로 보아서는 RC 및 PSC 거더가 서로 연결되는 교각 상부 지점부를 포함하는 부모멘트 구간에 형성된다. 말하자면 지점부에 발생하는 부모멘트에 저항하는 인장철근으로서 기능한다.As a result, the continuation means 200 is manufactured in the shape of a connecting frame in which the horizontal member 210 and the vertical member 220 are coupled to each other, and the continuation means is formed inside the upper flange of the RC and PSC girder, and as a whole bridge In the bore, the RC and PSC girders are formed in the parent section, which includes the pier top points connected to each other. In other words, it acts as a tensile reinforcing bar resisting the parent moment occurring at the point.

연속화수단(200)에 체결되는 상부내부강재(110)는 돌출된 단부에 나사산을 형성시키게 되며, 상기 연속화수단의 가로부재에 형성된 구멍을 관통하여 역시 가로부재로부터 약간 더 돌출되는 위치가 되도록 그 길이가 조절된다. 상기 나사산에는 너트부재(230)가 체결되고, 체결된 나사를 각각 회전시키면 너트부재는 각 RC 및 PSC 거더 쪽으로 가로부재(210)에 지지되면서 이동하게 되는데 상기 가로부재는 세로부재(220)에 의하여 구속되어 있으므로 결국 너트부재를 체결하여 조임으로서 상부내부강재와 연속화시킨다. 이러한 연속화는 결국 슬래브콘크리트 자중에 의해 지점부에 발생하는 부모멘트에 저항하는 역할을 함으로서 결국 RC 및 PSC 거더 상부에 발생하는 콘크리트 자중을 상부내부철근이 저항하게 됨으로서 RC 및 PSC 거더에 발생하는 정모멘트를 줄일 수 있게 되고, 이로서 그 자체의 자중에 저항할 수 있을 정도의 단면 크기로 제작될 수 있게 된다. 이로서 동일경간이라면 보다 장지간의 RC 및 PSC 교량을 시공할 수 있으며, 동일지간이라면 보다 단면크기가 작은 RC 및 PSC 교량을 시공할 수 있게 된다.The upper inner steel 110 is fastened to the sequencing means 200 to form a screw thread on the protruding end, the length of the upper inner steel 110 through the hole formed in the horizontal member of the sequential means to be a position further protruded further from the horizontal member. Is adjusted. The nut member 230 is fastened to the screw thread, and when the screw is rotated, the nut member is moved while being supported by the horizontal member 210 toward each RC and PSC girder, and the horizontal member is moved by the vertical member 220. Since it is constrained, the nut member is finally tightened to be continuous with the upper inner steel. This continuity eventually plays a role of resisting the parent moments generated at the point due to the slab concrete weight, so that the upper internal reinforcement resists the concrete self-weights generated in the upper part of RC and PSC girder. It can be reduced, thereby making it possible to produce a cross-sectional size that can resist its own weight. As a result, it is possible to construct longer and longer RC and PSC bridges in the same span, and it is possible to construct RC and PSC bridges with smaller cross-sectional sizes.

도 3 내지 도 6은 상기 연속화수단(200)의 다른 실시예들을 도시한 것인데, 상기 4개의 연속화수단은 상기 상부내부강재를 연속화수단에 너트부재를 이용하여 긴장 후 가로부재(210)에 설치될 수 있도록 하기 위한 것으로서 제작 및 시공 상의 편리함을 위한 것으로서 반드시 이러한 실시예들에 의하여 본 발명의 연속화수단이 한정되는 것은 아니다.3 to 6 show other embodiments of the continuation means 200, wherein the four continuation means are to be installed on the horizontal member 210 after the upper inner steel is tensioned using a nut member to the continuation means. As it is intended to be as convenient for manufacturing and construction is not necessarily limited to the sequencing means of the present invention by these embodiments.

도 3은 도 1a 및 도 1b와 같이 가로부재(210) 및 세로부재(220)가 격자형상의 구조로 제작된 것으로 서 중간에 가로부재(210)가 더 형성될 수 있음을 도시한 것이다. 상부내부강재(110)는 상기 가로부재에 기 형성된 구멍을 관통하여 설치되어 너트부재(230)에 의하여 가로부재에 조여져 정착됨으로서 상부내부강재에 긴장력(인장력)이 도입된다.3 illustrates that the horizontal member 210 and the vertical member 220 have a lattice-like structure as shown in FIGS. 1A and 1B, and the horizontal member 210 may be further formed in the middle. The upper inner steel 110 is installed through a hole previously formed in the horizontal member and is tightened and fixed to the horizontal member by the nut member 230 so that tension force (tensile force) is introduced into the upper inner steel.

도 4는 도 3과 동일한 구조로 제작되기는 하나, 상부내부강재를 보다 용이하게 가로부재에 설치하기 위한 것으로서, 도 3과 같이 가로부재에 상부내부강재를 관통하여 설치될 수 있도록 구멍을 형성시키되, 상기 구멍에 상부내부강재의 단부를 직접 삽입하는 방식으로 설치하는 것이 아니라 상기 구멍에 상부내부강재용 유도홈(240)을 이용하여 가로부재(210)에 상부내부강재(110)를 유도홈에 끼우면서 최종적으로 상부내부강재가 가로부재에 단부가 관통되도록 설치하는 방식이다. 도 3에 의한 연속화수단(200)과 비교하여 상부내부강재 설치를 위한 시공성이 매우 뛰 어나다는 장점이 있다.4 is manufactured in the same structure as in FIG. 3, but for easily installing the upper internal steel material in the horizontal member, as shown in FIG. 3, a hole is formed so as to penetrate the upper internal steel material in the horizontal member. Rather than installing the end of the upper inner steel directly into the hole in such a way as to insert the upper inner steel 110 in the horizontal member 210 using the upper inner steel guide groove 240 in the hole in the guide groove. Finally, the upper inner steel is installed in such a manner that the end penetrates the horizontal member. Compared with the sequential means 200 according to FIG. 3, the workability for installing the upper internal steel material is very excellent.

도 5는 도 3 및 도 4와는 달리, 가로부재(210)에 미리 원형 등의 구멍을 형성시키는 것이 아니라, 도 3의 완성된 상태의 연속화수단을 수평으로 개략 중간부위를 잘라 낸 형상으로 연속화수단을 상하로 나뉘도록 제작하고 상부 및 하부 연속화수단(200a. 200b)의 가로부재에 반원형 구멍을 각각 형성시킨 후 상부 및 하부 연속화수단을 서로 결합시킬 때 상기 각각의 반원형 구멍이 서로 겹쳐져 하나의 구멍을 형성하도록 한다. 이 때, 상부내부강재(110)를 미리 하부 연속화수단(200b)의 반원형구멍에 위치 시킨 후, 상부 연속화수단(200a)을 그 위에 설치하고, 앵커부재로서 상기 상부 및 하부 연속화수단을 조여 결합시키면 최종적으로 상부내부강재를 연속화수단에 용이하게 설치할 수 있다.3 and 4, the horizontal member 210 does not form a hole, such as a circular in advance, the continuous means in the shape of the sequential means of the completed state of Fig. And the semi-circular holes are formed in the horizontal members of the upper and lower serialization means (200a. 200b), respectively. To form. At this time, after placing the upper inner steel 110 in the semi-circular hole of the lower continuation means 200b, the upper continuation means 200a is installed thereon, and the upper and lower continuation means are fastened and combined as anchor members. Finally, the upper inner steel can be easily installed in the sequencing means.

도 6은 연속화수단(200)의 세로부재(220)를 강판과 같은 플레이트부재로 제작하는 하는 것이 아니라, 가로부재만을 상부내부강재가 관통되도록 설치하고, 세로부재로서 단부에 나사산이 형성된 봉 형상의 연결부재를 이용하여 가로부재를 서로 연결시켜 주는 방식으로서 현장에서 쉽게 구할 수 있는 부재를 이용할 수 있다는 장점이 있으며, 세로부재의 길이 조정에 의한 가로부재의 설치간격을 용이하게 조정할 수 있다는 장점이 있다. FIG. 6 shows that the vertical member 220 of the sequential means 200 is not manufactured with a plate member such as a steel plate, but only the horizontal member is installed so that the upper inner steel material penetrates, and the rod-shaped rod is formed at the end as the vertical member. As a method of connecting the horizontal members to each other by using a connecting member, there is an advantage that a member that can be easily obtained in the field can be used, and an installation interval of the horizontal member can be easily adjusted by adjusting the length of the vertical member. .

<RC 및 PSC 거더의 연속화공법><Continuous Chemical Processing of RC and PSC Girder>

본 발명의 RC 및 PSC 거더 연속화공법은 상기와 같이 제작된 RC 및 PSC 거더(100)의 단부를 지점부에서 서로 연속화수단(200)을 이용하여 서로 연결하여 연속보로서 기능하도록 하고 슬래브콘크리트(300)를 형성시키는 것을 특징으로 하 며, 이하 도2를 기준으로 설명한다.RC and PSC girder sequencing method of the present invention by connecting the ends of the RC and PSC girder 100 produced as described above to each other using the continuity means 200 at the point portion to function as a continuous beam and slab concrete (300) ), And will be described with reference to FIG.

도2a 내지 도2e는 본 발명의 RC 및 PSC 거더를 설치순서에 따라서 개략적으로 도시한 순서도이다.2A to 2E are flowcharts schematically showing the RC and PSC girders of the present invention according to the installation procedure.

먼저, 도2a와 같이 먼저 다수의 교각(10)위에 교량받침(20)을 설치한다. 이때 상기 교량받침(20)은 순수한 단순보 또는 종래의 연속보 방식으로 RC 및 PSC 거더를 설치할 때와는 달리, 본 발명에서는 PSC 거더가 실질적으로 연속보로서 기능하도록 미리 연결되므로, 각각의 RC 및 PSC 거더를 지지할 수 있는 교량받침은 1개의 교량받침을 설치할 수도 있으나 2개의 교량받침(20)이 설치될 수 있도록 하는 것이 바람직하다.First, as shown in FIG. 2A, first, bridge support 20 is installed on a plurality of bridges 10. In this case, unlike the case of installing the RC and PSC girder in a pure simple beam or a conventional continuous beam method, the bridge support 20 is connected in advance in the present invention so that the PSC girder functions substantially as a continuous beam, each RC and The bridge support capable of supporting the PSC girder may be provided with one bridge support, but it is preferable to allow two bridge supports 20 to be installed.

상기 RC 및 PSC 거더(100)는 I형이나 U형 단면으로 제작될 수 있으며, RC 및 PSC 거더(100)에는 연속화를 위한 상부내부강재(110)가 설치된다. RC 및 PSC 거더(100)의 상부플랜지 단부에는 소정의 형상을 가지는 홈(120)이 형성되어 있어 상부내부강재가 돌출 형성되어 대응하는 맞은편 RC 및 PSC 거더(100)의 상부내부강재와 중심선이 일치되도록 설치된 상태에서 연속화수단(200)에 의해 서로 연결된다.The RC and PSC girder 100 may be manufactured in an I-type or U-shaped cross section, and the upper internal steel 110 for continuity is installed in the RC and PSC girder 100. The upper flange end of the RC and PSC girder 100 is formed with a groove 120 having a predetermined shape so that the upper inner steel protrudes to form the upper inner steel and the center line of the corresponding opposite RC and PSC girder 100. It is connected to each other by the sequencing means 200 in the installed state to match.

상기 홈(120)은, RC 및 PSC 거더(100)가 I형보인 경우 홈(120)의 두께는 상부플랜지의 두께보다 작고, RC 및 PSC 거더(100)의 복부(web)가 노출되지 않도록 하며, U형거더에서는 상부내부강재(110)가 상하로 2열로 배근될 수 있도록 충분한 두께를 확보할 수 있도록 한다. The groove 120, when the RC and PSC girder 100 is the I-beam, the thickness of the groove 120 is smaller than the thickness of the upper flange, so that the abdominal (web) of the RC and PSC girder 100 is not exposed , U-shaped girder to ensure a sufficient thickness so that the upper inner steel 110 is arranged in two rows up and down.

본 발명의 실시예에서는 각각의 상부내부강재(110)의 단부에 나사산이 형성 되어 연속화강재의 가로부재에 형성된 구멍에 삽입되어 너트부재(230)에 의해 조여짐으로서 각 상부내부강재가 연속화수단의 가로부재(210)에 의하여 지지되면서 인장력이 도입되도록 한다. 상기 가로부재(210)는 세로부재(220)에 의하여 서로 연결되어 연속화수단은 전체적으로 연결틀의 형상을 가지게 되며, 강재로 제작하는 것이 바람직하나 이에 한정되는 것은 아니다.In the embodiment of the present invention, a thread is formed at the end of each upper inner steel 110 and is inserted into a hole formed in the horizontal member of the continuous steel, and is tightened by the nut member 230 so that each upper inner steel of the continuous means The tensile force is introduced while being supported by the horizontal member 210. The horizontal member 210 is connected to each other by the vertical member 220 so that the continuity means has the shape of the connecting frame as a whole, preferably made of steel, but is not limited thereto.

상부내부강재(110)는 연속보에서 부모멘트 구간(연속보의 지점부)에 배근되도록 함으로서 상기 구간에서의 부모멘트에 의한 RC 및 PSC 거더(100)의 상부플랜지에 작용하는 부모멘트에 의한 인장력에 대하여 구조적으로 인장철근으로서 기능하게 된다. 이러한 인장철근의 기능을 가지는 상부내부강재는 지점부에서 도 1, 도 3 내지 도 6과 같은 연속화수단(200)에 의하여 연결됨으로서 RC 및 PSC 거더(100)가 연속화되어 상부슬래브콘크리트(300) 타설에 있어 그 자중에 의한 RC 및 PSC 거더(100)의 정모멘트를 지지하게 되어 결국 보다 작은 단면크기의 RC 및 PSC 거더(100) 제작이 가능해진다.The upper inner steel 110 is to be reinforced to the parent section in the continuous beam (point portion of the continuous beam) by the tension force due to the parent acting on the upper flange of the RC and PSC girder 100 by the parent in the section. It is structurally functioning as a reinforcing bar. The upper inner steel having the function of the tensile reinforcing bar is connected by the continuation means 200 as shown in Figs. 1, 3 to 6 at the point portion, RC and PSC girder 100 is continuous to pour the upper slab concrete 300 In order to support the static moment of the RC and PSC girder 100 due to its own weight, it is possible to manufacture the RC and PSC girder 100 having a smaller cross-sectional size.

또한 상부내부강재(110)는 RC 및 PSC 거더(100)로부터 돌출되어 RC 및 PSC 거더(100)의 단부면을 초과하지 않도록 하여 너트부재로 조여질 때 보다 용이하게 인장력이 도입되며, 상부내부강재는 나사산이 형성될 수 있도록 강봉을 이용할 수 있으며, 나사산이 형성된 커플러를 이용하면 철근 또는 PC 강연선이 이용될 수도 있다.In addition, the upper internal steel 110 is protruded from the RC and PSC girder 100 so as not to exceed the end surface of the RC and PSC girder 100, the tensile force is introduced more easily when tightened by a nut member, the upper internal steel The steel bar may be used to form a thread, and when the coupler is formed with a thread, rebar or PC strand may be used.

또한, 상부내부강재(110)의 배근간격을 최소화하는 것이 바람직하고, 가능하면 RC 및 PSC 거더(100)의 홈(120)의 하부에 형성되는 복부에 가깝도록 집중 배근 되도록 하는 것이 바람직하다. 이와 같이, RC 및 PSC 거더(100)에 상부내부강재가 배근된 경우에는 인장력에 의한 RC 및 PSC 거더(100)의 상부플렌지 외측의 얇은 부분의 인발파괴를 방지할 수 있고, 충분한 피복두께를 확보할 수 있게 된다. 또한, 상부내부강재(200)를 연결하여 연속화 하는 연속화수단(200)의 가로부재(210)의 두께를 줄일 수 있게 한다. 상부내부강재는 RC 및 PSC 거더(100)의 상부플랜지 폭 등을 고려하여 다수가 설치된다.In addition, it is desirable to minimize the spacing of the upper inner steel material 110, and preferably to be concentrated close to the abdomen formed in the lower portion of the groove 120 of the RC and PSC girder 100. As such, when the upper inner steel is placed in the RC and PSC girder 100, it is possible to prevent the breakage of the thin portion outside the upper flange of the RC and PSC girder 100 due to the tensile force, and to secure sufficient coating thickness. You can do it. In addition, it is possible to reduce the thickness of the horizontal member 210 of the sequencing means 200 to be continuous by connecting the upper inner steel (200). A plurality of upper inner steels are installed in consideration of the width of the upper flange of the RC and PSC girder 100 and the like.

이 후, 도2c와 같이 슬래브콘크리트(300) 타설 시 슬래브콘크리트 자중에 의해서 압축력을 받을 수 있도록 슬래브콘크리트 타설 전에 RC 및 PSC 거더(100)의 홈(120)의 하부 단부면을 서로 연결시킬 수 있도록 연결벽(400, 다이아프램 또는 격벽)을 설치한다. 상기 격벽은 통상 콘크리트 또는 무수축 모르타르를 이용할 수 있으나, 이에 한정되지는 않는다.Thereafter, as shown in Figure 2c so that the lower end surface of the groove 120 of the RC and PSC girder 100 can be connected to each other before the slab concrete to be compressed by the slab concrete weight when placing the slab concrete 300 Install the connecting wall 400, diaphragm or partition wall. The barrier rib may generally use concrete or non-contraction mortar, but is not limited thereto.

연결벽(400)이 형성된 후에, 도2d와 같이 나사산이 형성된 상부내부강재(110)를 너트부재(230)를 사용하여 연속화수단(200)의 가로부재에 인장력이 도입되도록 체결하여 상부내부강재를 연속화시키고, 이 때 와셔를 사용하는 것이 바람직하다.After the connection wall 400 is formed, as shown in FIG. 2D, the upper internal steel material 110 having the thread formed therein is fastened so that the tensile force is introduced into the horizontal member of the sequencing means 200 by using the nut member 230. It is preferable to use a washer at this time.

상기와 같이 연속화수단(200)을 사용하여 상부내부강재(110)의 연속화가 끝나면, 도2e와 같이 슬래브 강재(310, 이형철근 등)을 배근하고 슬래브콘크리트(300)를 타설하여 RC 및 PSC 거더(100)를 슬래브콘크리트와 일체화시킨다. 이로서 본 발명에서는 슬래브 위에 형성되는 교량난간, 포장층과 같은 2차 사하중 및 교통하중과 같은 활하중에 대하여 일체화된 슬래브 및 RC 및 PSC 거더(100)가 저항할 수 있게 된다.When the sequencing of the upper inner steel 110 is completed using the sequencing means 200 as described above, the slab concrete (310, deformed rebar, etc.) is laid as shown in FIG. 100 is integrated with slab concrete. As a result, in the present invention, the integrated slab and the RC and PSC girder 100 can resist the bridge rails formed on the slab, the secondary dead loads such as the paving layer, and the live loads such as the traffic loads.

이 때, 상기 슬래브강재(310)는 슬래브콘크리트 자중은 지지하지 못하나, 2차 사하중과 활하중에 대하여 상부내부강재(200)와 함께 지점부의 부모멘트에 대한 인장철근으로 작용하게 된다.At this time, the slab steel 310 does not support the slab concrete weight, but acts as a tensile reinforcement for the parent portion of the point with the upper inner steel 200 for the secondary dead and live loads.

슬래브콘크리트는 RC 및 PSC 거더(100)에 형성된 홈(120)에 충진되면서, RC 및 PSC 거더(100) 및 연결벽과 일체화되어 상기 2차 사하중 및 활하중에 대하여 일체로 저항하게 되므로 시공 및 품질관리에 유의해야 한다.The slab concrete is filled in the groove 120 formed in the RC and PSC girder 100, integrated with the RC and PSC girder 100 and the connecting wall to integrally resist the secondary dead and live loads, so construction and quality control It should be noted that

본 발명은 RC 및 PSC 거더와 같은 교량용거더를 다경간에 걸쳐 연속화 시공함에 있어, 슬래브콘크리트를 타설하기 전에 설치된 RC 및 PSC 거더를 연속화시킴으로서, 보다 효율적인 RC 및 PSC 거더의 단면설계가 가능한 RC 및 PSC 거더의 제작을 통한 공사비 절감 및 공기단축이 가능하며, RC 및 PSC 거더의 연속화를 위하여 별도의 프리스트레스 도입용 정착구를 필요치 않으므로 경제적이며 시공성이 뛰어나고, 최적화된 단면의 RC 및 PSC 거더의 사용에 의해 동일형고에서 거더다 장지간의 교량건설이 가능하며, 동일지간에서는 보다 낮은 형고의 교량 시공이 가능하게 된다.According to the present invention, in the continuous construction of bridge girders such as RC and PSC girders over multiple spans, RC and PSC girders are designed to continuously cross RC and PSC girders before placing slab concrete, thereby enabling more efficient cross-sectional design of RC and PSC girders. It is possible to reduce construction cost and shorten the air through the manufacture of girder, and it is economical and constructable because it does not need a separate prestressing anchorage for continuity of RC and PSC girder, and it is the same by using optimized RC and PSC girder. It is possible to build bridges between long and long, and even lower bridges can be constructed between the same sites.

Claims (12)

삭제delete 삭제delete 교량용거더를 다경간에 걸쳐 연속보방식으로 시공함에 있어서,In constructing the bridge girders in a continuous beam method over a multi span, 단부 상부가 블록 아웃되어 형성된 홈 및 상부를 관통하며 상기 홈쪽으로 돌출 형성되거나 또는 단부에 나사산이 형성된 고강도 강재로서 단부 상부가 블록 아웃되어 형성된 홈 및 상부를 관통하며 상기 홈쪽으로 거더의 단부보다 작은 길이로 돌출된 상부내부강재를 포함하는 교량용거더를 교량상부구조물에 설치하고, A high-strength steel that penetrates the groove and the upper portion formed through the end of the block and protrudes toward the groove, or has a thread formed at the end. Bridge girder including the upper inner steel protruding into the bridge upper structure, 교량용거더의 상부내부강재를 연속화수단을 이용하여 인장력이 상부내부강재에 도입되도록 서로 연결시켜 각각의 교량용거더를 연속화시킨 이후 슬래브콘크리트를 상기 연속화된 교량용거더 상부에 형성시키는 것을 특징으로 하는 교량 연속화공법.The upper inner steel of the bridge girder is connected to each other so that the tensile force is introduced into the upper inner steel by using the sequencing means to sequentially bridge each girder and then to form the slab concrete on the continuous bridge girder Bridge sequencing method. 제 3항에 있어서, 상기 연속화수단은 교량용거더의 복부에 가깝도록 집중 배치되는 것을 특징으로 하는 교량 연속화공법.4. The bridge sequencing method according to claim 3, wherein the continuity means is arranged to be close to the abdomen of the bridge girder. 제 3항에 있어서, 상기 슬래브콘크리트를 형성시키기 이전에 각 교량용거더의 단부에 형성된 홈 이외의 부분을 서로 연결시키는 연결벽이 교량용 거더 사이에 더 형성되는 것을 특징으로 하는 교량 연속화공법.4. The bridge sequencing method according to claim 3, wherein a connecting wall for connecting portions other than grooves formed at the ends of each bridge girder to each other before the slab concrete is formed is further formed between the bridge girders. 제 3항에 있어서, 상기 교량용거더의 상부내부강재 및 연속화수단이 형성되는 위치는 연속보에 있어 부모멘트 발생부위인 것을 특징으로 하는 교량 연속화공법.4. The method according to claim 3, wherein the position where the upper inner steel material and the continuity means of the bridge girder are formed is a portion of generating a parent moment in the continuous beam. 제 3항에 있어서, 상기 상부내부강재의 단부에는 나사산이 형성되며 가로부재를 관통한 단부가 너트부재에 의하여 연속화수단의 가로부재에 지지되어 체결됨으로서 상부내부강재에 인장력이 도입되는 것을 특징으로 하는 교량 연속화공법.According to claim 3, wherein the end portion of the upper inner steel is formed with a thread and the end penetrating the horizontal member is supported by the horizontal member of the continuous means by the nut member is fastened by the tensile force is introduced into the upper inner steel Bridge sequencing method. 제 3항에 있어서, 상기 연속화수단은,The method of claim 3, wherein the serialization means, 서로 연결될 상부내부강재의 각 단부가 고정되며, 상부내부강재와 직각방향으로 설치되는 가로부재; 및 Each end of the upper inner steel to be connected to each other is fixed, the horizontal member is installed in a direction perpendicular to the upper inner steel; And 상기 가로부재를 서로 연결시키는 세로부재;A vertical member connecting the horizontal members to each other; 를 포함하며, 상기 가로부재 및 세로부재는 일체로 형성되거나 서로 조립되어 제작된 것을 특징으로 하는 교량 연속화공법.It includes, The horizontal member and the vertical member is a continuous bridge method, characterized in that formed integrally or assembled with each other. 제 8항에 있어서, 상기 가로부재 및 세로부재의 연결은 플레이트로 형성된 가로부재 및 세로부재가 서로 격자형태로 서로 겹쳐지게 하여 서로 연결시키거나, 플레이트인 가로부재에 단부에 나사산이 형성된 봉 형상의 부재인 세로부재를 너트 부재로 연결시켜 가로부재와 세로부재를 서로 연결시키는 것을 특징으로 교량 연속화공법.The method of claim 8, wherein the horizontal member and the vertical member is connected to each other by overlapping each other in a lattice form of the horizontal member and the vertical member formed of a plate, or the rod-shaped rod-shaped end portion in the horizontal member which is a plate Bridge member continuous method characterized in that the vertical member is connected to each other by a nut member to connect the horizontal member and the vertical member. 제 8항에 있어서, 상기 상부내부강재의 고정은, 상부내부강재의 단부에 나사산을 형성시키고 상기 나사산이 형성된 상부내부강재를 가로부재에 형성된 구멍에 관통시켜 고정시키는 것을 특징으로 하는 교량 연속화 공법.9. The method of claim 8, wherein the fixing of the upper inner steel material forms a screw thread at an end of the upper inner steel material and fixes the upper inner steel material having the screw thread through a hole formed in the horizontal member. 제 10항에 있어서, 상기 가로부재의 구멍은 가로부재에 직접 형성된 구멍 또는 일체로 형성된 가로부재와 세로부재를 하부 및 상부로 구분하여 제작하고 상기 하부 및 상부 각각에 형성된 홈의 결합에 의해 형성된 구멍인 것을 특징으로 하는 교량 연속화 공법.11. The method of claim 10, wherein the hole of the horizontal member is a hole formed directly in the horizontal member or formed by integrally forming the horizontal member and the vertical member divided into the lower and the upper and formed by the combination of the groove formed in each of the lower and upper Bridge sequencing method, characterized in that. 제 8항에 있어서, 상기 상부내부강재의 고정은, 상부내부강재의 단부에 나사산을 형성시키고 상기 나사산이 형성된 상부내부강재를 가로부재에 형성된 구멍에 연결된 유도홈에 끼워 넣은 후 상부내부강재가 구멍에 위치되도록 하여 고정시키는 것을 특징으로 하는 교량 연속화 공법.The method of claim 8, wherein the fixing of the upper inner steel, the upper inner steel is formed by forming a thread at the end of the upper inner steel and the upper inner steel is inserted into the guide groove connected to the hole formed in the horizontal member Bridge continuation method, characterized in that fixed to be located.
KR1020030073929A 2003-10-22 2003-10-22 Continuous Bridge Construction Method KR100565359B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030073929A KR100565359B1 (en) 2003-10-22 2003-10-22 Continuous Bridge Construction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030073929A KR100565359B1 (en) 2003-10-22 2003-10-22 Continuous Bridge Construction Method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2003-0033201U Division KR200341097Y1 (en) 2003-10-23 2003-10-23 A girder and continuous bridge construction structure using the same

Publications (2)

Publication Number Publication Date
KR20050038713A KR20050038713A (en) 2005-04-29
KR100565359B1 true KR100565359B1 (en) 2006-04-03

Family

ID=37241046

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030073929A KR100565359B1 (en) 2003-10-22 2003-10-22 Continuous Bridge Construction Method

Country Status (1)

Country Link
KR (1) KR100565359B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101013009B1 (en) * 2008-08-27 2011-02-10 한국건설기술연구원 Apparatus having a girder connection anchor plate and the continuous construction method for a psc girder bridge by using the same apparatus
KR101077090B1 (en) * 2009-01-21 2011-10-26 주식회사 장헌산업 Bridge structure of continuous PSC girder
KR101086643B1 (en) 2009-04-01 2011-11-24 주식회사 젬콘 Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR101268002B1 (en) 2011-08-08 2013-05-27 주식회사 장헌산업 Manufacturing Method of Prestressed Concrete Member having Prestressing Bar

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101230920B1 (en) * 2010-11-03 2013-02-07 주식회사 장헌산업 Prestressed Concrete Member having Prestressing Bar and Connecting Structure thereof and Manufacturing Method thereof
KR101533354B1 (en) * 2014-08-08 2015-07-24 (주)연우피씨엔지니어링 A eco-friendly multi-slab structure for construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101013009B1 (en) * 2008-08-27 2011-02-10 한국건설기술연구원 Apparatus having a girder connection anchor plate and the continuous construction method for a psc girder bridge by using the same apparatus
KR101077090B1 (en) * 2009-01-21 2011-10-26 주식회사 장헌산업 Bridge structure of continuous PSC girder
KR101086643B1 (en) 2009-04-01 2011-11-24 주식회사 젬콘 Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
KR101268002B1 (en) 2011-08-08 2013-05-27 주식회사 장헌산업 Manufacturing Method of Prestressed Concrete Member having Prestressing Bar

Also Published As

Publication number Publication date
KR20050038713A (en) 2005-04-29

Similar Documents

Publication Publication Date Title
KR102212482B1 (en) Half deck with supporting bracket and construction method thereof
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
KR101112195B1 (en) Steel-concrete composite crossbeam having wire mesh and construction method using the same
KR20090001261A (en) Prestressed concrete girder bridge having connecting structure using steel bar, and constructing method thereof
KR100664698B1 (en) Complementing apparatus of tensile strength in a prestress concrete gurder bridge
KR101043239B1 (en) Prestressed segment concrete girder for bridge and manufacturing method thereof
KR100988074B1 (en) Girder bridge connected to abutment and the construction method thereof
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR100911148B1 (en) Lightened Coping for bridge
KR100565359B1 (en) Continuous Bridge Construction Method
JP2005090115A (en) Reinforcing construction method for existing floor slab by beam
KR20100007300A (en) A steel composite bridge having steel plates connected by using concrete cross beams and its constructing method
KR20130040652A (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR200341097Y1 (en) A girder and continuous bridge construction structure using the same
KR100530025B1 (en) Section enlargement repairing and reinforcing apparatus for reinforcing earing power of reinforced concrete structures by introducing prestress to entended section and repairing and reinforcing construction method using the apparatus
KR200375153Y1 (en) Prestressed concrete beam
KR100734172B1 (en) PC Beam
JP4909445B1 (en) Ground tank construction method and ground tank
KR100511464B1 (en) Prestressed preflextion H-beam and method for building a T-shaped bridge pier using the H-beam
KR20010068055A (en) PSC Girder having Anchoring Sleeves and Strengthening Method
KR101004221B1 (en) One Way Waffle Slab System Continued by Post-tensioning and Post-tensioning method of the same
KR200240385Y1 (en) PSC Girder having Anchoring Sleeves
KR100565422B1 (en) Construction method for making into continuous prestressed concrete beam using Prestressing apparatus

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee