KR20040011787A - Method for constructing vegetation reinforcement soil retainint wall and that of structure - Google Patents

Method for constructing vegetation reinforcement soil retainint wall and that of structure Download PDF

Info

Publication number
KR20040011787A
KR20040011787A KR1020020044906A KR20020044906A KR20040011787A KR 20040011787 A KR20040011787 A KR 20040011787A KR 1020020044906 A KR1020020044906 A KR 1020020044906A KR 20020044906 A KR20020044906 A KR 20020044906A KR 20040011787 A KR20040011787 A KR 20040011787A
Authority
KR
South Korea
Prior art keywords
soil
layer
mat
reinforcement
fill
Prior art date
Application number
KR1020020044906A
Other languages
Korean (ko)
Inventor
김동민
Original Assignee
김동민
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김동민 filed Critical 김동민
Priority to KR1020020044906A priority Critical patent/KR20040011787A/en
Publication of KR20040011787A publication Critical patent/KR20040011787A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B11/00Drainage of soil, e.g. for agricultural purposes
    • E02B11/005Drainage conduits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0085Geotextiles
    • E02D2300/0089Geotextiles non-woven
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

PURPOSE: A construction method for a vegetation reinforced retaining wall is provided to have excellent tensile stress and dewatering/dampproofing efficiency, to keep the construction state firmly and safely without breakdown against internal and external pressure, and to heighten work efficiency and economical efficiency on maintenance works. CONSTITUTION: The construction method for a vegetation reinforced retaining wall comprises the steps of: spreading a geotextile mat(20) for reinforcement on each banking layer(10a-10n) and each ridging layer(12a-12n); spreading a woven fabric mat(30) on the front of the geotextile mat(20) for reinforcement, then banking up with soils(40), lifting up a woven fabric mat(30) and constructing secondary or nth banking layers(10b-10n) and ridging layers(12b-12n) in order, and covering up banking soils(40) to form each ridging layer(12a-12n); fixing a polyester net having strong tensile stress on the front of an incline formed by a woven fabric mat(30) to the height of each banking layer(10a-10n) and the ridging layer(12a-12n), then compressing organic vegetation reinforced soils on the surface of the polyester net in a driving-injecting method.

Description

식생 보강토 옹벽의 시공법 및 그 구조물{METHOD FOR CONSTRUCTING VEGETATION REINFORCEMENT SOIL RETAININT WALL AND THAT OF STRUCTURE}METHODS FOR CONSTRUCTING VEGETATION REINFORCEMENT SOIL RETAININT WALL AND THAT OF STRUCTURE}

본 발명은 지반의 활동파괴 등으로 인하여 지반이 약한 지역이나 천재지변으로 인한 축대 붕괴지역 및 토목공사등으로 인하여 발생되는 경사이완부의 축조공사 및 보수공사를 더욱 견고하고 안전하게 시공설치 할 수 있도록 하기 위하여 제안된 식생보강토옹벽의 시공법 및 그 구조물에 관한 것으로, 탈수성 및 내습성이 양호하고 인장응력이 강력한 보강용 토목섬유매트와, 흙의 흘러내림을 방지하고 물빠짐이 원활한 부직포매트 및 성토흙을 순차적으로 적층시키고, 그 전면부에 폴리에스터망을 부착하여 다수의 앵커핀으로 고정시킨 다음, 폴리에스터망의 전면부에는 관상수의 씨앗과 유기질 비료를 혼합시킨 식생보강토를 드라이브타입으로 주사압착하면서 시공 설치하여 줌으로써 보강용 토목섬유매트와 부직포, 폴리에스터망, 앵커핀 및 유기질 식생보강토의 결합구조에 의하여 성토흙(40)의 인장응력과 탈수 및 내습기능을 발휘하면서 폴리에스터망의 전면부에 압착하는 유기질 식생보강토가 폴리에스터망을 매체로하여 전면부의 성토흙과 토착 효과를 증대시킬 수 있으며, 내,외부토압에도 무너지는 일이 없이 축조상태를 더욱 견고하고 안전하게 유지할 수 있도록 하며, 경사이완부에 성토된 평면부의 활용면적을 넓힐 수 있으며 또한 초목이나 관상수목등의 씨앗발아 및 그 생장을 촉진시킬 수 있도록 함으로써 시공지역의 환경미화는 물론 보수공사의 효율성 및 경제성을 높일 수 있도록 한 것이다.The present invention in order to be able to install more firmly and safely the construction and repair work of the slope loosening section caused by the collapsed area and civil engineering work due to the weak ground or natural disasters due to the destruction of the ground, etc. The present invention relates to a method for constructing a vegetation-reinforced soil retaining wall and its structure, and includes a reinforcing geotextile mat having good dehydration and moisture resistance and strong tensile stress, a non-woven fabric mat and a soil soil which prevents the flow of soil and smooths water drainage. Lay out sequentially, attach the polyester net to the front side and fix it with a number of anchor pins, and then install the vegetation reinforcement soil mixed with seeds of organic water and organic fertilizer on the front part of the polyester net while driving and compressing it with a drive type. Reinforcement geotextile mat and nonwoven fabric, polyester net, anchor pin and organic The organic vegetation reinforced soil, which is pressed onto the front surface of the polyester network while exerting the tensile stress, dehydration and moisture resistance of the sandy soil 40 by the combined structure of the vegetation reinforced soil, is made up of polyester soil and the indigenous effect on the front surface. It is possible to increase the size, to maintain the construction state more firmly and safely without collapsing to internal and external earth pressure, and to increase the utilization area of the flat part that is inclined to the loosening part, and also to seeds of plants and ornamental trees. By promoting germination and its growth, it is possible to enhance the efficiency and economic efficiency of the renovation work as well as the environmental beautification of the construction area.

종래에 통수성시이트나 폴리에스터매트를 경사구간의 공사면에 평면상태로깔고 성토흙을 덮어 쌓아 올리는 시공 설치 작업으로 행하여지고 있는 구조에 있어서는 통수성시이트나 폴리에스터매트가 공사면에 평면상태로만 깔아지게 되므로 성토흙을 쌓아올리는 전단부로 성토흙이 흘러내리게 되어 전단부로 흘러내리는 흙을 다시 퍼올리면서 성토작업을 하여야 되는 번거러운 결점이 있었다.Conventionally, in a structure in which a water-permeable sheet or polyester mat is laid in a flat state on a construction surface of an inclined section and covered with soil, the water-permeable sheet or polyester mat is in a flat state only on the construction surface. Since it is laid, the soil flows down to the front end portion of the piled up soil, which causes cumbersome defects to be carried out while spreading the soil flowing down to the front end portion.

이와 같은 결점을 해결하기 위하여 공사면에 평면상태로 깔아지는 폴리에스터매트의 전후방부를 연장하여 형성되어지는 연장매트로서 전후방의 성토를 덮어씌워 줌으로써 공사면의 전후방으로 형성되어지게 되는 힘받이 두둑층의 성토층과 함께 한단(段)의 쟁반형 성토층이 형성되어 지도록 시공 설치한 다음 전면부로 형성되어 지게되는 호형굴곡 형상의 전면주벽으로 텍솔을 가압 착접하여 시공 설치 작업을 완료하였으나, 이는 폴리에스터매트에 의하여 쟁반형 성토층의 인장응력의 효과는 있으나 탈수 및 내습성이 미약하여 비가 많이 오게되면 배수가 원활하지 못하여 호형굴곡형상의 전면주벽에 착접된 텍솔이 쉽게 탈이되었으며, 공사면의 상면부에 다소간의 압력이 가하여지게 되더라도 성토층의 축조상태가 변형되어 쉽게 붕괴되는 결점이 있었다.In order to solve this drawback, it is an extension mat formed by extending the front and rear parts of the polyester mat laid in a flat state on the construction surface. The installation was completed so that a single tray-type fill layer was formed along with the fill layer, and then the texol was press-welded to the arc of the front circumferential wall which is formed as a front part. The effect of tensile stress on the tray-type fill layer is due to the weakness of dehydration and moisture resistance. However, when the rain is heavy, the drainage is not smooth and the texol contacted to the circumferential wall of the arc-shaped curve is easily detached. Even if a little pressure is applied to the defect, the buildup state of the fill layer is deformed and collapses easily. there was.

본 발명은 종래의 제반 결점을 해소하기 위하여 성토흙이 보강용 토목섬유매트와 부직포, 폴리에스터망, 앵커핀 및 유기질 식생보강토의 결합구조에 의하여 인장응력과 탈수 및 내습효과는 물론 폴리에스터망의 전면부에 압착하는 유기질 식생보강토가 폴리에스터망을 매체로하여 전면부의 성토흙과 토착 효과를 증대시킬 수있도록 하며, 내외부토압에도 무너지는 일이 없이 축조상태를 더욱 견고하고 안전하게 유지할 수 있도록 하며, 성토된 평면부의 활용 면적을 높일 수 있으며, 또한 화초나 관상수목등의 씨앗발아 및 그 생장을 촉진시킬 수 있도록 함으로써 시공지역의 환경미화는 물론 보수공사의 효율성 및 경제성을 높일 수 있도록 한 식생보강토 옹벽 시공법 및 그 구조물을 제공함에 목적이 있다.In order to solve the conventional drawbacks, the present invention provides a tensile stress, dehydration and moisture resistance effect as well as the effect of tensile stress, dehydration and moisture resistance by the combination structure of earth soil reinforcement geotextile mat and nonwoven fabric, polyester network, anchor pin and organic vegetation reinforcement soil. Organic vegetation-reinforced soil compressed on the front side can increase the indigenous effect with the soil and soil on the front side by using polyester net, and it can maintain the construction state more firmly and securely without collapsing to internal and external earth pressure. Reinforcing wall of vegetation reinforced soil, which can increase the utilization area of the flattened section, and also promote seed germination and growth of plants and ornamental trees. The purpose is to provide a construction method and its structure.

도 1은 본 발명의 단면도.1 is a cross-sectional view of the present invention.

도 2는 본 발명의 요부인 그라우팅파이프를 분리하여 보인 사시도.Figure 2 is a perspective view showing the separation of the grouting pipe that is the main part of the present invention.

도 3a 내지 도 3f는 본 발명의 시공과정을 나타낸 단면도.3a to 3f are cross-sectional views showing the construction process of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1 원지반 3 잡석 10a...10n 성토층1 Ground 3 Rubble 10a ... 10n Fill layer

12a...12n 두둑층 14 층접부 16 배수관12a ... 12n Thick layer 14 Floor contact 16 Drain pipe

20 보강용 토목섬유매트 22 전단부 30 부직포매트20 Geosynthetic mat for reinforcement 22 Shear 30 Nonwoven mat

32 일측단부 34 타측단부 40 성토흙32 One end 34 Other end 40 Filled soil

50 폴리에스터망 52 앵커핀 60 유기질 식생보강토50 Polyester Net 52 Anchor Pins 60 Organic Vegetative Reinforced Soil

본 발명은 종래의 결점을 해소하기 위하여 제안된 것으로 이를 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.The present invention has been proposed to solve the conventional drawbacks and will be described in detail with reference to the accompanying drawings.

도 1은 본 발명을 축조한 상태의 단면도, 도 2는 본 발명의 요부 확대도를 나타낸 것으로,1 is a cross-sectional view of the present invention, Figure 2 is an enlarged view of the main part of the present invention,

원지반(1) 상부에 탈수성 및 내습성이 양호하고 인장응력이 강력한 보강용 토목섬유매트(20)를 펼쳐 깔아 놓은 상단 전방으로는 흙의 흘러내림을 방지하고 물빠짐이 원활한 부직포매트(30)의 일측단부(32)를 상기 보강용 토목섬유매트(20)의 전단부(22)에 층접하여 층접부(14)가 형성되도록 깔아 설치하며, 층접부(14)로부터 보강용 토목섬유매트(20)의 상부로는 성토흙(40)을 적정두께가 되도록 성토하여 1차성토층(10a)을 형성하며, 층접부(14)의 상부로 층접된 부직포매트(30)의 상부로는 성토흙(40)을 제차 성토하여 두둑을 형성하여 성토되지 아니한 부직포매트(30)를 들어 올려 층접부(14)의 상부에 두둑으로 성토된 성토흙(40)을 덮어 씌워 부직포매트(30)의 타측단부(34)를 1차성토층(10a)의 상면으로 덮어 설치하여 1차 힘받이 두둑층(12a)을 형성한다.Non-woven fabric mat (30) to prevent dirt from flowing down and smooth out the water toward the top of the base plate (1), the dehydration and moisture resistance is good and the resilient geotextile mat (20), which is strong in tensile stress One side end 32 of the reinforcing geotextile mat 20 to the front end 22 of the reinforcement geothermal mat mat is installed so as to form a layer contact portion 14, the geosynthetic fiber mat 20 for reinforcement from the layer contact portion 14 ) The upper part of the fill soil (40) to the appropriate thickness to form a primary fill layer (10a), the upper part of the nonwoven fabric mat layered to the top of the layer contact portion 14 the fill soil (40) ) To form the embankment to raise the non-concrete mat (30) to cover the top of the layer contact portion (14), the soil filled with the embankment (14), the other end of the nonwoven mat (30) ) Is installed to cover the upper surface of the primary soil layer (10a) to form a primary force receiving layer (12a).

이와 같이 형성되는 1차 성토층(10a)과 1차 힘받이 두둑층(12a)의 상면부에 보강용 토목섬유매트(20)와 부직포매트(30) 및 성토흙(40)을 상기와 같은 순서로 실시하면서 2차 내지 n차 성토층(10b,10c..10n) 및 힘받이 두둑층(12b,12c,...12n)이 형성되도록 순차적으로 시공 설치한 다음, 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n)의 전면부의 높이로 부직포매트(30)에 의하여 형성되어지는 경사진 전면주벽으로는 인장응력이 강력한 폴리에스터망(50)이 부착 고정 설치되도록 앵커핀(52)을 박아 설치한다.The geotextile mat 20 for reinforcement, the nonwoven fabric mat 30 and the clay soil 40 in the upper surface of the primary fill layer 10a and the first force receiving toad layer 12a formed as above are in the same order as described above. While the second to nth fill layer (10b, 10c..10n) and force receiving layer (12b, 12c, ... 12n) are installed in order to form sequentially, each fill layer (10a, 10b) 10 n) and the inclined front circumferential wall formed by the nonwoven fabric mat 30 at the height of the front part of the force supporting layer 12a, 12b, ... 12n, a polyester network having strong tensile stress (50). ) So that the anchor pins 52 are installed and fixed.

이와 같이 시공 설치한 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n)의 전면주벽을 형성하는 폴리에스터망(50)의 전면부에서 유기질 식생보강토(60)를 드라이브타입주사공법으로 압착하여 줌으로써 본 발명의 시공작업이 완료된다.Organic vegetation is formed in the front part of the polyester network 50 forming the front circumferential wall of each of the fill layer (10a, 10b ... 10n) and the eminent layer (12a, 12b, ... 12n) installed in this way The construction work of the present invention is completed by compressing the reinforcement soil 60 by the drive type scanning method.

한편, 상기의 2차 성토층(10b)에는 배수를 원활하게 하기 위한 배수관(16)을 매설한다.On the other hand, the secondary fill layer 10b is buried in the drain pipe 16 for smooth drainage.

이와 같은 본 발명은 상기의 보강용 토목섬유매트(20)와 각 부직포매트(30)를 층접하여 상기 부직포매트(30)에 의하여 각 힘받이 두둑층(12a,12b,...12n)을 시공 설치함으로써, 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n) 내부의 배수를 원활하게 함과 동시에 각 힘받이 두둑층(12a,12b,...12n)의 흙이 흘러내리지 못하도록 시공 설치하는 구조물이며, 각 힘받이 두둑층(12a,12b,...12n)에 의하여 형성되는 경사진 전면주벽에 앵커핀(52)으로 고정 부착 설치시킨 폴리에스터망(50)은 유기질 식생보강토(60)를 더욱 견고하고 안전하게 착접하는 기능을 발휘하면서 각 성토층(10a,10b...10n)이 힘받이 두둑층(12a,12b,...12n)과 일체화되도록 하는 구조물이다.In the present invention as described above, the geotextile mat 20 for reinforcement and each nonwoven fabric mat 30 are contacted with each other to construct each force receiving layer 12a, 12b, ... 12n by the nonwoven mat 30. By providing, smooth drainage of each fill layer (10a, 10b ... 10n) and force receiving layer (12a, 12b, ... 12n) and at the same time each of the force receiving layer (12a, 12b). ..12n) is a structure to be installed so that the soil does not flow down, and fixedly attached to the inclined front circumference wall formed by each force layer (12a, 12b, ... 12n) with anchor pins 52 The polyester network 50 has a function of more firmly and safely contacting the organic vegetation reinforcement soil 60, while each soil layer (10a, 10b ... 10n) is embossed layer 12a, 12b, ... 12n ) Is to be integrated with the structure.

도면중 미설명부호 100는 옹벽축조상부의 덮개흙, 101은 초목을 표시한 것이다.In the drawings, reference numeral 100 denotes cover soil of the retaining wall ancestors, and 101 denotes vegetation.

이와 같은 본 발명을 시공설치하는 시공법을 도 3a 내지 도 3f에 의하여 상세히 설명하면 다음과 같다.The construction method for constructing and installing the present invention will be described in detail with reference to FIGS. 3A to 3F.

먼저 도 3a에 나타낸 바와 같이, 지반이 활동파괴 등으로 지반이 연약한 지역이나 천재지변으로 인한 축대 붕괴지역 및 토목공사 등으로 인하여 발생되는 경사이완부 지역의 원지반(1) 상부에 탈수성 및 내습성이 양호하고 인장응력이 강력한 보강용 토목섬유매트(20)를 펼쳐 깔아 놓은 상단 전방으로는 흙의 흘러내림을 방지하고 물빠짐이 원활한 부직포매트(30)의 일측단부(32)를 보강용 토목섬유매트(20)의 전단부(22)에 층접하여 층접부(14)가 형성되도록 깔아 설치하며, 층접부(14)로부터 보강용 토목섬유매트(20)의 상부로는 성토흙(40)을 적정두께가 되도록 성토하여 1차 성토층(10a)을 형성하며, 층접부(14)의 상부로 층접된 부직포매트(30)의 상부로는 성토흙(40)을 제차 성토하여 두둑을 형성하여 성토되지 아니한 부직포매트(30)를 들어 올려 층접부(14)의 상부에 두둑으로 성토된 성토흙(40)을 덮어 씌워 부직포매트(30)의 타측단부(34)를 1차 성토층(10a)의 상면으로 덮어 설치하여 1차 힘받이 두둑층(12a)을 형성한다.First, as shown in Fig. 3a, dehydration and moisture resistance in the upper ground (1) of the slope loosening region caused by the collapse of the ground due to the destruction of the activity, the collapsed area due to natural disasters, civil engineering work, etc. This good and tensile stress reinforced geotextile mat 20 is laid in front of the top to prevent the soil from flowing down and smooth water draining one end 32 of the non-woven fabric mat 30 is reinforced geotextile The floor contact part 22 is formed by layer contact with the front end part 22 of the mat 20 so as to form a layer contact part 14, and the soil soil 40 is titrated from the layer contact part 14 to the upper part of the reinforcing geotextile mat 20. Fill to the thickness to form a primary fill layer (10a), the top of the non-woven fabric mat 30 layered to the top of the layer contact portion 14 to fill the fillet soil 40 to fill the embankment is not filled Lifting the nonwoven fabric mat 30 to raise the image of the layer contact portion 14. Covers the soil soil (40) filled in the embankment to cover the other end portion 34 of the nonwoven fabric mat (30) to cover the upper surface of the primary fill layer (10a) to form a primary force toad layer (12a). .

도 3b에 나타낸 바와 같이 1차 힘받이 두둑층(12a)이 형성된 일측으로 상기1차 힘받이 두둑층(12a)과 동일한 높이가 되도록 성토흙(40)을 채운 후 상기 1차 성토층(10a)의 상부로 보강용 토목섬유매트(20)를 펼쳐 깔고, 상기 보강용 토목섬유매트(20) 전단부(22)로는 흙의 흘러내림을 방지하고 물빠짐이 원활한 부직포매트(30)의 일측단부(32)를 보강용 토목섬유매트(20)의 전단부(22)에 층접하여 층접부(14)가 형성되도록 깔아 설치하며, 층접부(14)로부터 보강용 토목섬유매트(20)의 상부로는 성토흙(40)을 적정두께가 되도록 성토함과 동시에 배수관(16)을 매설하여 부직포매트(30)의 상부로 제차 성토하여 두둑을 형성하여 성토되지 아니한 부직포매트(30)를 들어 올려 층접부(14)의 상부에 두둑으로 성토된 성토흙(40)을 덮어 씌워 부직포매트(30)의 타측단부(34)를 2차 성토층(10b)의 상면으로 덮어 설치하여 2차 힘받이 두둑층(12b)을 형성한다.As shown in FIG. 3B, after filling the soil soil 40 to the same height as the primary force receiving layer 12a to one side where the primary force receiving layer 12a is formed, the primary fill layer 10a is formed. Spread the reinforcing geotextile mat 20 to the upper portion of the reinforcement geotextile mat 20, the front end portion 22 of the one end of the nonwoven fabric mat 30 to prevent the flow of dirt and smooth water drainage ( 32 is laid in contact with the front end 22 of the reinforcing geotextile mat 20 so as to form a layer contact portion 14, and from the layer contact portion 14 to the top of the reinforcement geotextile mat 20. While filling the soil soil 40 to an appropriate thickness, the drain pipe 16 is embedded, and the soil is piled up to the upper portion of the nonwoven fabric mat 30 to form a ridge to lift the non-woven fabric mat 30 which is not filled. 14) covering the fill soil (40) filled with the embankment on the upper portion of the non-woven mat (30) to fill the second end 34 By installing a top surface of the cover (10b) forms the second force receiving patter layer (12b).

도 3c는 2차 힘받이 두둑층(12b)이 형성된 일측으로 상기 2차 힘받이 두둑층(12b)과 동일한 높이가 되도록 성토흙(40)을 채움과 동시에 상기의 2차 성토층(10b)의 후방부와 원지반(1) 사이로 물빠짐이 용이하도록 하기 위한 잡석(3)을 채운다.FIG. 3C shows the filling of the soil soil 40 to the same height as the secondary force receiving layer 12b to one side where the secondary force receiving layer 12b is formed, and at the same time, the secondary fill layer 10b of the secondary filling layer 10b. The rubble 3 is filled between the rear portion and the base 1 to facilitate drainage.

도 3d는 상기 2차 성토층(10b)의 상부로 보강용 토목섬유매트(20)를 펼쳐 깔고, 상기 보강용 토목섬유매트(20) 전방으로는 흙의 흘러내림을 방지하고 물빠짐이 원활한 부직포매트(30)의 일측단부(32)를 보강용 토목섬유매트(20)의 전단부(22)에 층접하여 층접부(14)가 형성되도록 깔아 설치하며, 층접부(14)로부터 보강용 토목섬유매트(20)의 상부로는 성토흙(40)을 적정두께가 되도록 성토함과 동시에 부직포매트(30)의 상부로 제차 성토하여 두둑을 형성한다.Figure 3d is spreading the reinforcement geotextile mat 20 to the upper portion of the secondary fill layer (10b), the front of the reinforcement geotextile mat 20 to prevent the flow of dirt and non-woven smooth water drainage One side end 32 of the mat 30 is laid in contact with the front end 22 of the geosynthetic fiber mat 20 for reinforcement so that the layer contact portion 14 is formed, and the geotextile for reinforcement from the layer contact portion 14 is formed. The top of the mat 20 to fill the fill soil 40 to the appropriate thickness and at the same time to fill the top of the non-woven fabric mat 30 to form a ridge.

도 3e는 상기 성토흙(40)에 의하여 두둑이 형성되며, 성토되지 아니한 부직포매트(30)를 들어 올려 층접부(14)의 상부에 두둑으로 성토된 성토흙(40)을 덮어 씌워 부직포매트(30)의 타측단부(34)를 3차 성토층(10c)의 상면으로 덮어 설치하여 3차 힘받이 두둑층(12c)을 형성한 다음, 상기와 같은 보강용 토목섬유매트(20)와 부직포매트(30) 및 성토흙(40)을 상기와 같은 순서로 실시하면서 4차 내지 n차 성토층(10d...10n) 및 힘받이 두둑층(12d...12n)을 순차적으로 시공 설치한다.3e is formed by the soil soil 40, the non-woven mat (30) is not raised to cover the soil soil (40) embanked on the upper part of the layer contact portion 14 by lifting the non-woven mat ( 30 is formed by covering the other end 34 of the tertiary fill layer 10c with the upper surface of the tertiary fill layer 10c to form a tertiary force receiving ridge layer 12c, and then the geotextile mat 20 for reinforcement and the nonwoven fabric mat as described above. (30) and the fill soil 40 in the same order as described above to install the fourth to n-th fill layer (10d ... 10n) and force receiving layer (12d ... 12n) in sequence.

도 3f는 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n)의 전면부와 상부로 인장응력이 강력한 폴리에스터망(50)을 덮어 설치한 후 각 성토층(10a,10b...10n)에 앵커핀(52)을 박아 고정 설치한다.FIG. 3F shows a polyester network 50 having a strong tensile stress on the front and upper portions of each fill layer 10a, 10b ... 10n and force receiving layer 12a, 12b, 12n. After fixing the anchor pin 52 in each fill layer (10a, 10b ... 10n).

상기와 같은 구조로 시공 설치한 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n)과 힘받이 두둑층(12a,12b,...12n))의 전면주벽으로 모래와 관상수 및 화초씨앗, 유기질 비료및 장섬유를 혼합하여 얻어지는 유기질 식생보강토(60)를 드라이브주사공법에 의하여 압착하여 줌으로서, 유기질 식생보강토(60)가 폴리에스터망(50)에 걸어물려 빈틈없이 메꿔 결합되면서 강력하게 착접 고정되어 본 발명의 시공 설치작업이 완료되는 것이다.Each soil layer (10a, 10b ... 10n) and force support layer (12a, 12b, ... 12n) and force support layer (12a, 12b, ... 12n) installed in the above structure By compressing the organic vegetation reinforcement soil (60) obtained by mixing sand, tubular water, flower seeds, organic fertilizer and long fibers to the front circumferential wall by a drive injection method, the organic vegetation reinforcement soil (60) is polyester network (50). ) And is tightly coupled to the gap tightly fixed, and the installation of the installation of the present invention is completed.

이와 같이 된 본 발명은 보강용 토목섬유매트(20)와 부직포매트(30)를 순차적으로 층접하여 적층 형성함으로서 각 성토층(10a,10b...10n)의 성토흙(40)이 인장응력이 강력한 부직포매트(30)에 의하여 안전하게 응착되는 것이며, 또한 탈수성 및 내습성이 양호한 부직포매트(30)에 의하여 물빠짐이 원활함과 동시에 항상 적당한 습기를 함유하게 되므로 항상 견고하고 안전한 축조상태를 유지할 수 있는 것이며, 아울러 보강용 토목섬유매트(20)의 전단부(22)와 부직포매트(30)를 중접시켜 형성되는 층접부(14) 상부의 성토흙(40)을 덮어 씌워 각 힘받이 두둑층(12a,12b,...12n)을 형성하는 부직포매트(30)에 의하여 각 힘받이 두둑층(12a,12b,...12n)에 성토된 성토흙(40)의 흘러 내림을 방지할 수 있으며, 축조상태의 각 성토층(10a,10b...10n)의 물빠짐을 원활하게 할 수 있는 것이다.According to the present invention as described above, the geosynthetic mat 20 for the reinforcement geosynthetic mat 20 and the nonwoven fabric mat 30 are sequentially laminated to form the laminated soil 40 of each soil layer 10a, 10b ... 10n. It is securely adhered by the strong nonwoven mat 30, and the non-woven mat 30 having good dehydration and moisture resistance smoothly drains and always contains adequate moisture, so that it always maintains a firm and safe construction state. In addition, it covers the soil soil 40 on the layer contact portion 14 formed by overlapping the front end portion 22 and the nonwoven fabric mat 30 of the reinforcement geotextile mat 20, each layer of force receiving Non-woven mat 30 forming (12a, 12b, ... 12n) can prevent the flow of fill soil (40) deposited in each force layer (12a, 12b, ... 12n). In addition, it is possible to smooth the drainage of each fill layer (10a, 10b ... 10n) in the built state.

또한, 각 힘받이 두둑층(12a,12b,...12n)의 전면부에 형성되는 전면주벽에 앵커핀(52)으로 걸어 박아 고정 부착시킨 인장응력이 강력한 폴리에스터망(50)은 표면부가 되는 탈수성 및 내습성이 양호한 부직포매트(30)와 유기질 식생보강토(60)간에 강력한 인장응력을 발휘하면서 본 발명의 축조상태를 일체화로서 결합시키게 되는 것이다.In addition, the polyester mesh 50 having a strong tensile stress attached to the front circumferential wall formed on the front surface of each force receiving layer 12a, 12b, ... 12n by fixing with anchor pins 52 is attached to the surface thereof. While exhibiting a strong tensile stress between the non-woven fabric mat 30 and the organic vegetation reinforcement soil 60 is good dehydration and moisture resistance is to combine the construction state of the present invention as an integral.

이와 같은 본 발명은 홍수시에 물빠짐이 원활함과 아울러 내습성이 양호하여 붕괴될 염려가 없으며, 내.외부의 토압이나 또한 외부충격에도 축조상태가 변형되거나 붕괴될 염려가 없는 것이다.In the present invention, there is no fear of collapse due to smooth water drainage and good moisture resistance during flooding, and there is no fear of deforming or collapse of the built-up state even inside and outside earth pressure or external impact.

이와 같이된 본 발명은 보강토 토목섬유매트와 부직포매트, 폴리에스터망, 앵커핀 및 유기질 식생보강토의 결합구조에 의하여 인장응력과 탈수 및 내습기능을 발휘함은 물론 폴리에스터망의 전면부에 압착하는 모래와 씨앗 및 장섬유를 혼합한 유기질 식생토가 폴리에스터망을 매체로하여 전면부의 성토흙과 토착 효과를 증대시킬 수 있으며, 홍수시에 물빠짐이 원활함과 아울러 내습성이 양호하여 붕괴될 염려가 없으며, 내.외부토압이나 외부충격에도 무너지는 일이 없이 축조상태를 더욱 견고하고 안전하게 유지할 수 있도록 하며, 성토된 평면부의 활용면적을 넓일수 있으며 또한 화초나 관상수목등의 씨앗발아 및 그 생장을 촉진시킬 수 있도록 함으로써 시공지역의 환경미화는 물론 보수공사의 효율성 및 경제성을 높일 수 있도록 한 것이다.As described above, the present invention exhibits tensile stress, dehydration and moisture resistance as well as crimping on the front surface of the polyester network by a combined structure of reinforcing earth fiber mat and nonwoven fabric mat, polyester network, anchor pin and organic vegetation reinforcement soil. Organic vegetation soil mixed with sand, seeds, and long fiber can increase the indigenous effect with the soil soil at the front surface by using polyester net, and it can be collapsed due to smooth water drainage and good moisture resistance during flooding. There is no concern, and it is possible to maintain the construction state more firmly and safely without collapsing to internal and external earth pressure or external impact, and it can widen the utilization area of the filled flat part, and also to germinate seeds and ornamental trees, etc. By promoting the growth, the construction area would not only beautify the environment but also improve the efficiency and economic efficiency of the renovation work.

Claims (2)

지반의 활동파괴 또는 산사태 등으로 인하여 지반이 연약하거나 붕괴된 지역의 사전 보강 및 축조를 보강하기 위하여 원지반(1)의 상부에 폴리에스터와 부직포매트(30), 폴리에스터망(50), 앵커핀(52) 및 성토흙(40)을 순차적으로 시공 설치하여 형성되는 층접부(14)에 의하여 1차성토층(10a) 및 각 성토층(10n)과 1차 힘받이 두둑층(12a) 및 각 힘받이 두둑층(12n)이 되도록 시공 설치하는 통상의 시공법에 있어서,Polyester and nonwoven mats (30), polyester net (50), anchor pins on top of the original ground (1) to reinforce the pre-reinforcement and construction of areas where the ground is soft or collapsed due to the destruction of the ground or landslides. 52 and the first soil layer 10a and each soil layer 10n and the primary force receiving layer 12a and each force by the layer contact portion 14 formed by sequentially installing and installing the soil soil 40. In the normal construction method of constructing and installing so that it may become the bottom wall 12n, 상기의 각 성토층(10a,10b,...10n)과 각 힘받이 두둑층(12a,12b,...12n)의 상면부에 보강용 토목섬유매트(20)를 펼쳐 깔아 설치함과;Spreading and installing the reinforcing geotextile mat 20 on the upper surface of each of the fill layers (10a, 10b, ... 10n) and each of the force receiving layer (12a, 12b, ... 12n); 보강용 토목섬유매트(20)의 전단부에 부직포매트(30)를 깔고 성토흙(40)을 성토한 다음, 성토되지 않은 부직포매트(30)를 들어 올려서 2차 내지 n차 성토층(10b,10c..10n) 및 힘받이 두둑층(12b,12c,...12n)을 순차적으로 시공하며, 상기에서 성토된 성토흙(40)을 덮어 씌워 각 힘받이 두둑층(12a,12b,...12n)이 되도록 시공 설치하며,Lay the nonwoven fabric mat 30 on the front end of the reinforcement geotextile mat 20 and then fill the soil soil 40, and then lift the unfilled nonwoven fabric mat 30 to the secondary to nth fill layer 10b, 10c..10n) and the force receiving layer (12b, 12c, ... 12n) are sequentially installed, covering the fill soil (40) that has been filled in the above, each force receiving layer (12a, 12b, .. Installation to be .12n) 상기 각 성토층(10a,10b...10n)과 힘받이 두둑층(12a,12b,...12n)의 전면부의 높이로 부직포매트(30)에 의하여 형성되어지는 경사면의 전면주벽으로 인장응력이 강력한 폴리에스터망(50)을 앵커핀(52)으로 고정 부착시킨 다음, 상기 폴리에스터망(50)의 표면부에서 통상의 유기질 식생보강토(60)를 드라이브타입 주사공법으로 압착하여 시공 설치작업을 완료하도록 함을 특징으로 한 식생 보강토 옹벽 시공법.Tensile stress to the front circumferential wall of the inclined surface formed by the nonwoven mat 30 at the height of the front portion of each of the fill layer (10a, 10b ... 10n) and the force receiving layer (12a, 12b, ... 12n) The strong polyester mesh 50 is fixedly attached to the anchor pin 52, and then the conventional organic vegetation reinforcement soil 60 is pressed on the surface of the polyester mesh 50 by a drive type scanning method for installation work. Vegetation reinforcement retaining wall construction method characterized in that to complete the. 지반의 활동파괴 또는 산사태 등으로 인하여 지반이 연약하거나 붕괴된 지역의 사전 보강 및 축조를 보강하기 위하여 원지반(1)의 상부에 폴리에스터와 부직포매트(30), 폴리에스터망(50), 앵커핀(52) 및 성토흙(40)을 순차적으로 시공 설치하여 형성되는 층접부(14)에 의하여 1차성토층(10a) 및 각 성토층(10n)과 1차 힘받이 두둑층(12a) 및 각 힘받이 두둑층(12n)이 되도록 시공 설치하는 통상의 시공법에 있어서,Polyester and nonwoven mats (30), polyester net (50), anchor pins on top of the original ground (1) to reinforce the pre-reinforcement and construction of areas where the ground is soft or collapsed due to the destruction of the ground or landslides. 52 and the first soil layer 10a and each soil layer 10n and the primary force receiving layer 12a and each force by the layer contact portion 14 formed by sequentially installing and installing the soil soil 40. In the normal construction method of constructing and installing so that it may become the bottom wall 12n, 층접부(14)의 상부로 층접된 보강토 토목섬유매트(20)와 부직포매트(30) 및 성토흙(40)에 의하여 형성되는 각 성토층(10a,10b,...10n)의 전단부에 부직포매트(30)로서 둘러 감겨지는 각 힘받이 두둑층(12a,12b,...12n)을 형성함을 특징으로 한 식생 보강토 옹벽을 축조하는 구조물.At the front end of each soil layer (10a, 10b, ... 10n) formed by the reinforcement geosynthetic mat 20 and the nonwoven mat 30 and the fill soil (40) layered to the top of the layer contact portion 14 A structure for building a vegetation-reinforced soil retaining wall, characterized in that each of the force receiving layer (12a, 12b, ... 12n) is wound around the non-woven mat (30).
KR1020020044906A 2002-07-30 2002-07-30 Method for constructing vegetation reinforcement soil retainint wall and that of structure KR20040011787A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020020044906A KR20040011787A (en) 2002-07-30 2002-07-30 Method for constructing vegetation reinforcement soil retainint wall and that of structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020020044906A KR20040011787A (en) 2002-07-30 2002-07-30 Method for constructing vegetation reinforcement soil retainint wall and that of structure

Publications (1)

Publication Number Publication Date
KR20040011787A true KR20040011787A (en) 2004-02-11

Family

ID=37319836

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020020044906A KR20040011787A (en) 2002-07-30 2002-07-30 Method for constructing vegetation reinforcement soil retainint wall and that of structure

Country Status (1)

Country Link
KR (1) KR20040011787A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100520285B1 (en) * 2002-12-04 2005-10-11 최춘식 Method for reinforcing a dam by layer compaction using high intensity public works texture
KR100746730B1 (en) * 2006-08-16 2007-08-06 주식회사 에이치에스지 Constructing method of reinforced soil wall and slope
KR100930115B1 (en) * 2008-03-04 2009-12-07 최성호 Environment-friendly slope type fill section structure and its construction method
KR100980818B1 (en) * 2010-07-05 2010-09-10 주식회사 경호엔지니어링 종합건축사사무소 Improved post type reinforced earth retaining wall for workability and ecology space
CN101713182B (en) * 2009-11-18 2011-06-08 河海大学 Method for forming ecological embankment of vertical revetment live branch bundles
KR101138192B1 (en) * 2009-08-13 2012-05-11 그린인프라 주식회사 Afforestation method of vertical wall and shelf assembly thereof
CN103774616A (en) * 2014-01-22 2014-05-07 安徽水安建设集团股份有限公司 Construction method for ecological retaining wall built by self-embedded blocks
CN109098060A (en) * 2018-08-31 2018-12-28 青岛天力多维生态有限公司 Grid device and its application based on stereoscopic-state
CN109371989A (en) * 2018-10-26 2019-02-22 华中科技大学 A kind of combined type retaining structure and its construction method suitable for stability of slope supporting

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61207723A (en) * 1985-03-12 1986-09-16 Mitsui Petrochem Ind Ltd Method of stabilizing face of slope of banking
KR0180099B1 (en) * 1996-04-30 1999-04-01 임철웅 Construction of retaining wall
JP2000080654A (en) * 1998-09-04 2000-03-21 Nisshoku Corp Reinforced earth work method
KR20000075687A (en) * 1997-02-25 2000-12-26 오피신 마카페리 에스. 피. 에이. An element for forming ground covering, restraining and reinforcing structures, particularly for forming retaining walls
KR100327465B1 (en) * 1999-07-02 2002-03-13 이은수 KORESWall system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61207723A (en) * 1985-03-12 1986-09-16 Mitsui Petrochem Ind Ltd Method of stabilizing face of slope of banking
KR0180099B1 (en) * 1996-04-30 1999-04-01 임철웅 Construction of retaining wall
KR20000075687A (en) * 1997-02-25 2000-12-26 오피신 마카페리 에스. 피. 에이. An element for forming ground covering, restraining and reinforcing structures, particularly for forming retaining walls
JP2000080654A (en) * 1998-09-04 2000-03-21 Nisshoku Corp Reinforced earth work method
KR100327465B1 (en) * 1999-07-02 2002-03-13 이은수 KORESWall system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100520285B1 (en) * 2002-12-04 2005-10-11 최춘식 Method for reinforcing a dam by layer compaction using high intensity public works texture
KR100746730B1 (en) * 2006-08-16 2007-08-06 주식회사 에이치에스지 Constructing method of reinforced soil wall and slope
KR100930115B1 (en) * 2008-03-04 2009-12-07 최성호 Environment-friendly slope type fill section structure and its construction method
KR101138192B1 (en) * 2009-08-13 2012-05-11 그린인프라 주식회사 Afforestation method of vertical wall and shelf assembly thereof
CN101713182B (en) * 2009-11-18 2011-06-08 河海大学 Method for forming ecological embankment of vertical revetment live branch bundles
KR100980818B1 (en) * 2010-07-05 2010-09-10 주식회사 경호엔지니어링 종합건축사사무소 Improved post type reinforced earth retaining wall for workability and ecology space
CN103774616A (en) * 2014-01-22 2014-05-07 安徽水安建设集团股份有限公司 Construction method for ecological retaining wall built by self-embedded blocks
CN103774616B (en) * 2014-01-22 2015-09-30 安徽水安建设集团股份有限公司 From the Ecological Retaining Wall construction method that embedded block is built by laying bricks or stones
CN109098060A (en) * 2018-08-31 2018-12-28 青岛天力多维生态有限公司 Grid device and its application based on stereoscopic-state
CN109371989A (en) * 2018-10-26 2019-02-22 华中科技大学 A kind of combined type retaining structure and its construction method suitable for stability of slope supporting

Similar Documents

Publication Publication Date Title
KR100981258B1 (en) The retaining wall block and the construction method of retaining wall with retaining wall block and geogrid
KR100737768B1 (en) Environmental vegetation mat pannels
CN106368238A (en) Honeycomb geocell earth retaining wall with ecological restoration function and construction method thereof
US20100104779A1 (en) Shock absorbing athletic field and method of constructing same
JP2003193543A (en) Construction method for draining ground and member used therefor
KR20040011787A (en) Method for constructing vegetation reinforcement soil retainint wall and that of structure
CN106522244B (en) A kind of embankment combination binding structure and its construction method
KR100641815B1 (en) Reinforced geotextile mat and reinforcement of earth slopes and embankments using the same
CN206157760U (en) Honeycomb geotechnique check room retaining wall with ecological recovery function
KR20090065039A (en) A vegetation slope structure
CN101182708B (en) Covering type composite vacuum electroosmosis, method for forced ramming reinforcing foundation and device thereof
KR101963362B1 (en) Reinforced gabion retaining wall capable of completely drainage and construction method thereof
JP2597116B2 (en) Embankment foundation and its construction method
KR100992076B1 (en) Structure of raising the ground level and excecution method thereof
KR101525942B1 (en) Method for slope reinforcement construction using the ground improvement product
CN213061572U (en) Landscape road bed course
KR100930115B1 (en) Environment-friendly slope type fill section structure and its construction method
KR100317701B1 (en) a reinforcement land method of construction to using tires
CN112281806A (en) Spring soil roadbed unsaturated horizontal drainage device and construction method thereof
KR20030052871A (en) Retaining wall and its construction method of steel panel
KR20050050732A (en) Anchor for ground and retaining wall structure using anchor
KR20060063827A (en) Prefabricated drainage pipe and rapid drainage method using the same
KR19990046526A (en) A structure for establing a slope and execution method using it
JPS63284321A (en) Sheathing for inclined surface of filling
KR100995094B1 (en) Method for constructing retaining wall block

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application