KR200398409Y1 - Construction structure of expanded polystyrene moulding - Google Patents

Construction structure of expanded polystyrene moulding Download PDF

Info

Publication number
KR200398409Y1
KR200398409Y1 KR20-2005-0019906U KR20050019906U KR200398409Y1 KR 200398409 Y1 KR200398409 Y1 KR 200398409Y1 KR 20050019906 U KR20050019906 U KR 20050019906U KR 200398409 Y1 KR200398409 Y1 KR 200398409Y1
Authority
KR
South Korea
Prior art keywords
expanded polystyrene
sculpture
building
wall
fixed
Prior art date
Application number
KR20-2005-0019906U
Other languages
Korean (ko)
Inventor
제 성 유
Original Assignee
주식회사 예인이엠
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 예인이엠 filed Critical 주식회사 예인이엠
Priority to KR20-2005-0019906U priority Critical patent/KR200398409Y1/en
Application granted granted Critical
Publication of KR200398409Y1 publication Critical patent/KR200398409Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0832Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
    • E04F13/0833Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable
    • E04F13/0835Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable the fastening elements extending into the back side of the covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

본 고안은 발포 폴리스티렌 조형물의 시공구조에 관한 것으로, 건축물의 인테리어 또는 외관장식에 사용되는 발포 폴리스티렌 조형물을 시공함에 있어서, 건물의 벽면에 고정철물의 일부분을 단단히 고정시킨 상태에서 건물의 벽면 바깥쪽으로 돌출된 고정철물의 다른 부분을 발포 폴리스티렌 조형물의 뒷부분 내측으로 형성된 장착홈에 끼워 결합하는 방식으로 시공함으로써 발포 폴리스티렌 조형물이 견고한 장착상태를 유지할 수 있도록 하고, 시공작업이 간단하면서도 정확하게 이루어질 수 있도록 하며, 시공후 오랜 시간이 경과되더라도 조형물이 설치상태로부터 분리되지 않도록 한 것이다.The present invention relates to a construction structure of expanded polystyrene sculpture, and in the construction of expanded polystyrene sculpture used for interior or exterior decoration of a building, protrudes to the outside of the wall of the building in a state where a part of the fixed hardware is firmly fixed to the wall of the building. The other part of the fixed steel is inserted into the mounting groove formed inside the rear part of the foamed polystyrene molding to be bonded so that the foamed polystyrene molding can be kept firmly mounted, and the construction work can be made simple and accurate. Even after a long time, the sculpture is not separated from the installation state.

본 고안의 시공구조는 소정의 형상으로 이루어지고, 수직을 이루는 뒷면에서 수평방향으로 소정 높이와 깊이를 갖는 장착홈이 형성된 다수의 발포 폴리스티티렌 조형물과; 소정 폭과 길이를 갖는 수직면과 수평면이 서로 직각되게 절곡된 형상으로 이루어지고, 상기 수직면이 시공대상 건물의 벽면에 앵커볼트에 의해 고정된 상태에서 수평면은 상기 발포 폴리스티렌 조형물의 됫면에 형성된 장착홈에 끼워져 발포 폴리스티렌 조형물을 지탱할 수 있도록 하는 고정 철물과; 상기 발포 폴리스티렌 조형물과 동일한 형상으로 이루어지며, 건물의 벽면에 미리 장착된 발포 폴리스티렌 조형물사이의 틈새를 메워주는 채워넣기 조형물로 이루어진다.The construction structure of the present invention is made of a predetermined shape, a plurality of foamed polystyrene molded article having a mounting groove having a predetermined height and depth in the horizontal direction from the vertical back; The vertical plane and the horizontal plane having a predetermined width and length are formed to be bent at right angles to each other, and the horizontal plane is mounted to the mounting groove formed on the rear surface of the expanded polystyrene sculpture while the vertical plane is fixed to the wall of the building to be constructed by anchor bolts. A fixing hardware fitted to support the expanded polystyrene sculpture; It is made of the same shape as the expanded polystyrene moldings, and is made of a fill molding to fill the gap between the expanded polystyrene moldings pre-mounted on the wall of the building.

Description

발포 폴리스티렌 조형물의 시공구조{CONSTRUCTION STRUCTURE OF EXPANDED POLYSTYRENE MOULDING}Construction structure of expanded polystyrene moldings {CONSTRUCTION STRUCTURE OF EXPANDED POLYSTYRENE MOULDING}

본 고안은 발포 폴리스티렌 조형물의 시공구조에 관한 것으로, 보다 상세하게는 건축물의 인테리어 또는 외관장식에 사용되는 발포 폴리스티렌 조형물을 시공함에 있어서, 건물의 벽면에 고정철물의 일부분을 단단히 고정시킨 상태에서 건물의 벽면 바깥쪽으로 돌출된 고정철물의 다른 부분을 발포 폴리스티렌 조형물의 뒷부분 내측으로 형성된 장착홈에 끼워 결합하는 방식으로 시공함으로써 발포 폴리스티렌 조형물이 견고한 장착상태를 유지할 수 있도록 하고, 시공작업이 간단하면서도 정확하게 이루어질 수 있도록 하며, 시공후 오랜 시간이 경과되더라도 조형물이 설치상태로부터 분리되지 않도록 한 발포 폴리스티렌 조형물의 시공구조에 관한 것이다.The present invention relates to a construction structure of expanded polystyrene moldings, and more particularly, in the construction of foamed polystyrene moldings used for interior or exterior decoration of buildings, a part of the fixed steel is firmly fixed to the wall of the building. By installing the other parts of the fixed steel protruding outward from the wall into the mounting grooves formed inside the rear part of the expanded polystyrene sculpture, the expanded polystyrene sculpture can be maintained firmly and the construction work can be made simple and accurate. The present invention relates to a construction structure of expanded polystyrene moldings in which a sculpture is not separated from an installed state even after a long time of construction.

일반적으로, 각종 건물에 대하여 인테리어를 하거나 외관장식을 하는 경우에 금속이나 대리석과 같은 석재를 원하는 형상으로 가공한 조형물이나 장식물을 만든 후 상기 금속재 또는 석재로 이루어진 조형물이나 장식물을 건물의 벽면에 고정시키는 방식으로 시공하였다.In general, in the case of interior decoration or exterior decoration for various buildings, making a sculpture or ornament processed into a desired shape of a stone, such as metal or marble, and then fixing the sculpture or ornament made of the metal or stone to the wall of the building It was constructed in the manner.

그러나, 이와 같이 건물의 외벽이나 내벽면에 금속이나 석재로 된 조형물이나 장식물을 설치·시공하는 경우 조형물이 무겁기 때문에 시공작업이 매우 어렵다는 문제가 있고, 비용이 과다하게 많이 소요된다는 문제가 있다.However, in the case of installing and constructing a metal or stone sculpture or decoration on the outer wall or the inner wall of the building as described above, there is a problem that the construction work is very difficult because the sculpture is heavy, and the cost is excessively high.

또한, 한번 시공된 후에는 변경이 거의 불가능하기 때문에 새로운 조형물을 설치할 수 없다는 문제가 있다.In addition, there is a problem that can not be installed a new sculpture because it is almost impossible to change once constructed.

이와 같은 문제점을 개선하기 위하여 최근에는 도 1에 도시된 바와 같이, 가볍고, 성형성이 우수한 발포 폴리스티렌재으로 가공된 조형물을 건물의 벽면(10)에 설치하고자 하는 시도가 제안되고 있다.In order to improve such a problem, as shown in FIG. 1, an attempt has recently been proposed to install a molded object made of a lightweight, excellent formability on a foamed polystyrene material on the wall surface 10 of a building.

그러나, 종래 발포 폴리스티렌재의 조형물(12)을 건물의 벽면(10)에 시공하고자 하는 경우에는 발포 폴리스테렌재 조형물(12)의 뒷면과 건물의 벽면사이에 몰타르 등의 접착제(14)를 채워 넣은 상태에서 건물의 벽면(10)에 부착시키기 때문에 일정 기간이 경과되어 접착제(14)의 접착력이 저하되거나 또는 외부로부터 충격력이 인가되는 경우에 부착·시공된 발포 폴리스티렌 조형물(12)이 떨어질 우려가 높다는 문제가 있다.However, when the molded article 12 of the expanded polystyrene material is to be applied to the wall surface 10 of the building, the adhesive 14 such as mortar is filled between the back surface of the expanded polystyrene material sculpture 12 and the wall surface of the building. Since it is attached to the wall surface 10 of the building, the problem is that there is a high possibility that the foamed polystyrene molded article 12 attached or constructed falls when a certain period of time is deteriorated or the impact force of the adhesive 14 is lowered or an impact force is applied from the outside. There is.

또한, 건물의 벽면(10)에 시공되는 발포 폴리스티렌 조형물(12)이 단품이 아니고 여러개로 이루어진 경우에 각각의 조형물에 도포되는 접착제(14)의 양이 동일하지 않거나 접착제의 접착강도가 동일하지 못한 경우에는 그 부착상태에 다소의 차이가 있기 때문에 시간이 경과되는 경우 각각의 발포 폴리스티렌 조형물(12)의 설치높이 등이 달라지게 되므로 여러번에 걸쳐 보수작업을 해야 되는 등의 문제가 있다.In addition, when the foamed polystyrene sculpture 12 to be constructed on the wall 10 of the building is not a single piece but a plurality of pieces, the amount of the adhesive 14 applied to each sculpture is not the same or the adhesive strength of the adhesive is not the same. In this case, since there is a slight difference in the state of attachment, since the installation height of each expanded polystyrene sculpture 12 is changed over time, there is a problem such as having to repair several times.

본 고안은 이와 같은 종래의 문제점을 해결하기 위한 것으로, 그 목적은 건축물의 인테리어 또는 외관장식에 사용되는 발포 폴리스티렌 조형물을 시공함에 있어서, 건물의 벽면에 고정철물 일부분을 단단히 고정시킨 상태에서 건물의 벽면 바깥쪽으로 돌출된 고정철물의 다른 부분을 발포 폴리스티렌 조형물의 뒷부분 내측으로 형성된 장착홈에 끼워 결합하는 방식으로 시공하므로써 발포 폴리스티렌 조형물이 견고한 장착상태를 유지할 수 있도록 하고, 시공작업이 간단하면서도 정확하게 이루어질 수 있도록 하며, 시공후 오랜 시간이 경과되더라도 발포 폴리스티렌 조형물이 설치상태로부터 분리되지 않도록 한 새로운 발포 폴리스티렌 조형물의 시공구조를 제공하는 것이다.The present invention is to solve such a conventional problem, the purpose is to construct a foamed polystyrene sculpture used in the interior or exterior decoration of the building, the wall surface of the building in a fixed state fixed to the wall surface of the building By installing the other parts of the fixed steel protruding outward into the mounting groove formed inside the rear part of the expanded polystyrene sculpture, the expanded polystyrene sculpture can be maintained firmly and the construction work can be made simple and accurate. The present invention provides a construction structure of a new expanded polystyrene molded article so that the expanded polystyrene molded article is not separated from the installed state even after a long time.

상기한 목적을 달성하기 위하여, 본 고안에 따른 발포 폴리스티렌 조형물의 시공구조는 소정의 형상으로 이루어지고, 수직을 이루는 뒷면에서 수평방향으로 소정 높이와 깊이를 갖는 장착홈이 형성된 다수의 발포 폴리스티티렌 조형물과; 소정폭과 길이를 갖는 수직면과 수평면이 서로 직각되게 절곡된 형상으로 이루어지고, 상기 수직면이 시공대상 건물의 벽면에 앵커볼트에 의해 고정된 상태에서 수평면은 상기 발포 폴리스티렌 조형물의 뒷면에 형성된 장착홈에 끼워져 발포 폴리스티렌 조형물을 지탱할 수 있도록 하는 고정 철물과; 상기 발포 폴리스티렌 조형물과 동일한 형상으로 이루어지며, 건물의 벽면에 미리 장착된 발포 폴리스티렌 조형물사이의 틈새를 메워주는 채워넣기 조형물로 이루어진 특징을 갖는다.In order to achieve the above object, the construction structure of the expanded polystyrene sculpture according to the present invention is made of a predetermined shape, a plurality of expanded polystyrene formed with a mounting groove having a predetermined height and depth in the horizontal direction from the vertical back Sculptures; The vertical plane and the horizontal plane having a predetermined width and length are formed to be bent at right angles to each other, and in the state where the vertical plane is fixed to the wall surface of the building to be constructed by the anchor bolt, the horizontal plane is formed in the mounting groove formed on the rear side of the expanded polystyrene sculpture. A fixing hardware fitted to support the expanded polystyrene sculpture; It is made of the same shape as the expanded polystyrene sculpture, and has a feature of the filling sculpture filling the gap between the expanded polystyrene sculpture pre-mounted on the wall of the building.

본 고안에서 상기 고정 철물상의 수직면의 세로방향 중심선상에는 위치조정을 위한 소정 크기의 장공이 형성되고, 상기 장공으로부터 좌우 양쪽으로 일정 거리 벗어난 위치에는 정공형태의 체결공이 형성되는 한편, 고정 철물상의 수평면 저면 양쪽 가장자리에는 쐐기형, 사각형, 원호형 중에서 선택된 어느 하나의 형상을 갖는 걸림편이 하나 또는 복수개로 하향·형성된 특징을 갖는다.In the present invention, a hole having a predetermined size for position adjustment is formed on a vertical center line of the vertical surface on the fixed hardware, and a hole in the form of a hole is formed at a position deviated by a predetermined distance from both the left and right sides of the fixed hole, Both edges have a feature in which one or more engaging pieces having a shape selected from a wedge shape, a square shape, and an arc shape are downwardly formed.

본 고안에서 상기 발포 폴리스티렌 조형물의 상부면과 접하는 앞부분 모서리부분에는 침탄강, 침탄질화강, 질화강, 알루미늄, 플라스틱중에서 선택된 어느 하나의 재질로 된 1∼2mm두께의 보강부재가 감싸여진 상태에서 우레탄 접착제에 의하여 접착된 특징을 갖는다.In the present invention, the front edge portion in contact with the upper surface of the expanded polystyrene molding is urethane adhesive in a state in which a reinforcing member having a thickness of 1 to 2 mm made of any one selected from carburized steel, carburized nitrile steel, nitride steel, aluminum, and plastic is wrapped. It has a feature bonded together.

본 고안에서 상기 건물의 벽면에 장착된 각각의 발포 폴리스티렌 조형물 사이에 형성되는 틈새에는 상기 조형물과 동일한 재질 및 형상을 갖는 채워넣기 조형물을 끼워 넣어 틈새를 메워주는 특징을 갖는다.In the present invention, the gap formed between each of the expanded polystyrene sculptures mounted on the wall of the building has a feature of filling a gap by inserting a filling sculpture having the same material and shape as the sculpture.

이하, 첨부된 도면에 의하여 본 고안의 바람직한 실시예를 보다 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail a preferred embodiment of the present invention.

도 2는 본 고안에 따른 발포 폴리스티렌 조형물의 시공구조를 나타내는 분리사시도이고, 도 3은 본 고안에 따른 발포 폴리스티렌 조형물 시공구조에서 고정철물을 나타내는 확대 사시도이다.2 is an exploded perspective view showing the construction structure of the expanded polystyrene sculpture according to the present invention, Figure 3 is an enlarged perspective view showing the fixed hardware in the expanded polystyrene sculpture construction structure according to the present invention.

또, 도 4는 본 고안에 따른 발포 폴리스티렌 조형물의 시공상태를 나타내는 측단면도이고, 도 5는 본 고안에 따른 발포 폴리스티렌 조형물의 시공순서를 나타내는 공정도이다.In addition, Figure 4 is a side cross-sectional view showing a construction state of the expanded polystyrene sculpture according to the present invention, Figure 5 is a process chart showing the construction procedure of the expanded polystyrene sculpture according to the present invention.

이를 참조하면, 본 고안에 따른 발포 폴리스티렌 조형물 시공구조(40)에서는 발포 폴리스티렌 조형물이 견고한 장착상태를 유지할 수 있도록 하고, 시공작업이 간단하면서도 정확하게 이루어질 수 있도록 구성된다.Referring to this, in the expanded polystyrene sculpture construction structure 40 according to the present invention is configured to maintain a solid mounting state of the expanded polystyrene sculpture, it is configured to be made simple and accurate construction work.

이를 위하여, 본 고안에 따른 발포 폴리스티렌 조형물 시공구조(40)는 소정의 형상으로 이루어지는 발포 폴리스티렌 조형물(42)의 뒷면 소정 높이에 소정의 높이와 깊이를 갖는 장착홈(44)이 형성된 구조로 이루어진다.To this end, the foamed polystyrene sculpture construction structure 40 according to the present invention has a structure in which a mounting groove 44 having a predetermined height and depth is formed at a predetermined height on the rear surface of the expanded polystyrene sculpture 42 having a predetermined shape.

상기 발포 폴리스티렌 조형물(42)은 그 외표면에 접착제의 역할을 하는 폴리우레탄층(46)이 소정의 두께로 도포되고, 상기 폴리우레탄층(46)에 대하여 베이스면의 강도를 보강하고, 특수한 질감을 나타내기 위하여 실리카 샌드(Silica sand)등의 마감재층(48)이 도포된다.The foamed polystyrene sculpture 42 has a polyurethane layer 46, which serves as an adhesive on its outer surface, with a predetermined thickness, reinforces the strength of the base surface with respect to the polyurethane layer 46, and has a special texture. In order to show the finish layer 48, such as silica sand (Silica sand) is applied.

또, 상기 발포 폴리스티렌 조형물(42)의 상부면과 접하는 앞부분 모서리부분에는 침탄강, 침탄질화강, 질화강, 알루미늄, 플라스틱중에서 선택된 어느 하나의 재질로 된 1∼2mm두께의 보강부재(50)가 감싸여진 상태에서 폴리우레탄 접착제에 의하여 접착되도록 구성된다.In addition, the front edge portion in contact with the upper surface of the expanded polystyrene sculpture 42 is wrapped with a reinforcing member (50) of 1 to 2 mm thickness of any one selected from carburized steel, carburized nitrile steel, nitride steel, aluminum and plastic. It is configured to be bonded by the polyurethane adhesive in the state.

본 고안에서 상기 발포 폴리스티렌 조형물(42)은 건물의 벽면(52)에 고정된 고정철물(54)에 의해 지탱되도록 구성된다.In the present invention, the expanded polystyrene sculpture 42 is configured to be supported by a fixed hardware 54 fixed to the wall surface 52 of the building.

상기 고정철물(54)은 금속으로 이루어지며, 소정 폭과 길이를 갖는 수직면(54a)과 수평면(54b)이 서로 직각되게 절곡된 형상으로 이루어진다.The fixing hardware 54 is made of metal, and the vertical surface 54a and the horizontal surface 54b having a predetermined width and length are bent at right angles to each other.

상기 고정철물(54)을 구성하는 상기 수직면(54a)은 시공대상 건물의 벽면(52)에 앵커볼트(56)에 의해 고정되고, 상기 수평면(54b)은 상기 발포 폴리스티렌 조형물(42)의 뒷면에 형성된 장착홈(44)에 끼워져 발포 폴리스티렌 조형물(42)을 지탱하는 역할을 한다.The vertical surface 54a constituting the fixed hardware 54 is fixed to the wall surface 52 of the building to be constructed by the anchor bolt 56, and the horizontal surface 54b is formed on the rear surface of the expanded polystyrene sculpture 42. It is inserted into the formed mounting groove 44 serves to support the foamed polystyrene sculpture (42).

본 고안에서 상기 고정철물(54)상의 수직면(54a)의 세로방향 중심선상에는 위치조정을 위한 소정 크기의 장공(58)이 형성되고, 상기 장공(58)으로부터 좌우 양쪽으로 일정 거리 벗어난 위치에는 정공형태의 체결공(60)이 형성되도록 구성된다.In the present invention, a long hole 58 having a predetermined size for position adjustment is formed on a vertical center line of the vertical surface 54a on the fixed hardware 54, and a hole shape is formed at a position away from the left and right sides by a predetermined distance from the long hole 58. The fastening hole 60 is configured to be formed.

또, 상기 고정철물(54)상의 수평면(54b) 저면 양쪽 가장자리에는 하나 또는 복수개의 걸림편(62)이 하향·형성된다.Further, one or a plurality of locking pieces 62 are downwardly formed on both edges of the bottom surface of the horizontal surface 54b on the fixing hardware 54.

상기 걸림편(62)은 쐐기형 또는 사각형, 또은 원호형중 어느 하나로 이루어진다.The locking piece 62 is made of any one of a wedge shape, a square shape, or an arc shape.

본 고안에서 건물의 벽면에 시공되는 발포 폴리스티렌 조형물(42)(42')이 다수개인 경우에 각 발포 폴리스티렌 조형물(42)(42') 사이에 틈새가 발생될 수 있는데, 이 경우 상기 각 조형물(42)(42') 사이의 틈새에는 발포 폴리스티렌 조형물과 동일한 재질 및 형상을 갖는 채워넣기 조형물(64)이 끼워져 설치된다.In the present invention, when there are a plurality of foamed polystyrene sculptures 42 and 42 'installed on the wall of a building, a gap may be generated between each foamed polystyrene sculptures 42 and 42', in which case each of the sculptures ( In the gap between 42) and 42 ', a filling sculpture 64 having the same material and shape as the expanded polystyrene sculpture is fitted.

한편, 본 고안에 따른 발포 폴리스티렌 조형물의 시공순서에 대하여 도 5를 참조하여 상세하게 설명한다.On the other hand, the construction sequence of the expanded polystyrene molded article according to the present invention will be described in detail with reference to FIG.

본 고안에 따른 발포 폴리스티렌 조형물의 시공순서는 벽면에 대한 기준선 표시단계(S1)와, 기준선에 대한 고정철물 가(假)고정단계(S2)와, 고정철물 고정단계(S3)와, 발포 폴리스티렌 조형물의 장착홈에 접착제를 채워 넣는 접착제 충전단계(S4), 발포 폴리스티렌 조형물상의 장착홈에 고정철물의 수평면을 끼워 결합하는 조형물 장착단계(S5)와, 실란트도포단계(S6)로 이루어진다.The construction order of the expanded polystyrene sculpture according to the present invention is the baseline display step (S1) for the wall surface, the fixed steel temporary fixing step (S2) for the reference line, the fixed steel fixing step (S3), and the expanded polystyrene sculpture Glue filling step (S4) of filling the adhesive into the mounting groove of the molded article is fitted into the mounting groove on the foamed polystyrene molded horizontal surface of the fitting fittings (S5) and the sealant coating step (S6).

이와 같은 본 고안의 발포 폴리스티렌 조형물의 시공순서에서는 상기 기준선 표시단계(S1)는 시공대상이 되는 건물의 벽면(52)에서 시공위치에 맞추어 수평방향 기준선(L)과 수직방향 기준선(V)을 먹메김방식으로 표시한다.In the construction sequence of the expanded polystyrene sculpture of the present invention, the reference line display step (S1) feeds the horizontal reference line (L) and the vertical reference line (V) in accordance with the construction position on the wall surface 52 of the building to be constructed. Display in paginated manner.

본 고안의 고정철물 가(假)고정단계(S2)에서는 건물의 벽면(52)에 표시된 수평방향 기준선(L)과 수직방향 기준선(V)에 맞추어 각 수직방향 기준선(V)상에 고정철물(54)의 수직면(54a)을 밀착시킨 상태에서 장공(58)에 앵커볼트(56)를 박아 가(假)고정시킨다.In the fixed steel provisional fixing step (S2) of the present invention in accordance with the horizontal reference line (L) and the vertical reference line (V) displayed on the wall surface 52 of the building fixed steel (on each vertical reference line (V) In the state in which the vertical surface 54a of 54) is in close contact, the anchor bolt 56 is driven and fixed in the long hole 58.

이 과정에서 상기 어느 하나의 고정철물(54)과 이웃하는 고정철물(54') 사이의 간격은 수평벽면의 경우 600mm로 한다.In this process, the distance between any one of the fixing hardware 54 and the adjacent fixing hardware 54 'is set to 600 mm in the case of the horizontal wall surface.

그런 다음, 고정철물 고정단계(S3)에서는 가(假)고정된 각각의 고정철물(54)을 서로 견주면서 각 고정철물(54)의 수평상태가 수평방향 기준선(L)과 일치되도록 맞춘 상태에서 고정철물(54)의 수직면(54a)상에 형성된 체결공(60)에 앵커볼트(56)를 박아 완전히 고정시킨다.Then, in the fixing steel fixing step (S3) while holding the respective fixed hardware 54 is temporarily fixed to each other while the horizontal state of each of the fixing hardware 54 is aligned to match the horizontal reference line (L) The anchor bolt 56 is driven to the fastening hole 60 formed on the vertical surface 54a of the fixing hardware 54 to be completely fixed.

이 때, 상기 고정철물(54)의 상하 수정범위는 장공(58)에 크기에 의하여 결정되는데, 대략 12mm 범위내에서 이루어진다.At this time, the upper and lower correction range of the fixing hardware 54 is determined by the size of the long hole 58, it is made within the range of approximately 12mm.

이와 같은 수치는 위에서 기재한 것으로 한정되지 않으며, 발포 폴리스티렌 조형물(42)의 크기에 따라 달라질 수 있음은 자명하다.This value is not limited to that described above, it is obvious that it may vary depending on the size of the expanded polystyrene sculpture (42).

한편, 이와 같이 건물의 벽면(52)에 대하여 고정철물(54)이 고정된 상태에서는 발포 폴리스틸렌 조형물(42)의 뒷면에 형성된 장착홈(44)내에 폴리우레탄 접착제(66)를 채워 넣는다(S4).On the other hand, in the state in which the fixed hardware 54 is fixed to the wall surface 52 of the building as described above, the polyurethane adhesive 66 is filled in the mounting groove 44 formed on the back of the foamed polystyrene sculpture 42 (S4). .

그런 다음, 폴리우레탄 접착제(68)로 충전된 발포 폴리스티렌 조형물(42)상의 장착홈(44) 내로 고정철물(54)의 수평면(54b)이 끼워지도록 하면, 상기 수평면(54b)의 좌우 양측면으로부터 하향 형성된 쐐기 형상의 걸림편(62)이 장착홈(44)의 바닥면을 약간 파고 들면서 끼워져 빠지지 않게 되어 발포 폴리스티렌 조형물(42)이 고정철물(54)에 장착되는 것이다(S5).Then, when the horizontal surface 54b of the fixing hardware 54 is fitted into the mounting groove 44 on the expanded polystyrene sculpture 42 filled with the polyurethane adhesive 68, it is downward from both left and right sides of the horizontal surface 54b. The formed wedge-shaped locking piece 62 is inserted into the bottom surface of the mounting groove 44 slightly so as not to be pulled out so that the foamed polystyrene sculpture 42 is mounted on the fixed hardware 54 (S5).

이와 같이 발포 폴리스티렌 조형물(42)이 고정철물(54)에 장착된 상태에서는 상기 발포 폴리스티렌 조형물(42)의 상부면 뒷부분과 건물의 벽면(52)사이에 간극이 형성되고, 이 간극을 통하여 이물질이 유입될 수 있으므로, 이를 방지하기 위하여 건물의 벽면(52)과 발포 폴리스티렌 조형물(42) 뒷면 사이에 이물질이 유입되지 않도록 조형물의 상·하부면과 벽면(52) 사이의 간극에 실란트(Sealant:68)를 도포하면(S6) 발포 폴리스티렌 조형물의 시공이 완료되는 것이다.As described above, in the state in which the expanded polystyrene sculpture 42 is mounted on the fixed hardware 54, a gap is formed between the rear surface of the upper surface of the expanded polystyrene sculpture 42 and the wall surface 52 of the building, and foreign matters are formed through the clearance. In order to prevent this, a sealant is formed in the gap between the upper and lower surfaces of the sculpture and the wall 52 so that foreign matter does not flow between the wall 52 of the building and the back side of the expanded polystyrene sculpture 42. ), The construction of the expanded polystyrene sculpture is completed.

이 때 실란트도포작업은 최소 24시간 이상이 경과된 후에 실시하는 것이 바람직하며, 시공부위의 습윤정도를 확인하고 먼지 등 이물질을 제거한다.At this time, the sealant application should be carried out after at least 24 hours has elapsed. Check the wetness of the construction site and remove foreign substances such as dust.

실란트를 도포한 후에는 전용 헤라를 이용하여 도포면이 고르게 유지되도록 압착한다.After applying the sealant, it is compressed using an exclusive hera to maintain the coated surface evenly.

한편, 본 고안에서 상기 실란트도포단계 직전이나 직후에 상기 건물의 벽면(52)에 장착된 각각의 발포 폴리스티렌 조형물(42)(42') 사이에 형성되는 틈새를 메워 주기 위하여 상기 조형물(42)(42')과 동일한 재질 및 형상을 갖는 채워넣기 조형물(64)을 끼워 넣는 공정이 더 포함될 수 있다.On the other hand, in the present invention, the sculpture 42 (to fill the gap formed between each foamed polystyrene sculptures 42, 42 'mounted on the wall 52 of the building immediately before or after the sealant coating step) 42 ') may further include the step of inserting the filling sculpture 64 having the same material and shape.

이와 같은 본 고안을 적용하면, 발포 폴리스티렌 조형물을 건물의 벽면에 설치함에 있어, 먼저 고정철물을 건물의 벽면의 시공기준선에 맞추어 고정·설치하고 한 다음, 상기 고정철물의 수평면을 폴리우레탄 접착제가 충전된 발포 폴리스티렌 조형물상의 장착홈내로 끼워 고정시키는 방식으로 시공하기 때문에 시공이 간단한 것은 물론, 시공상태가 견고하게 유지된다는 효과가 있다.According to the present invention, in installing the foamed polystyrene sculpture on the wall of the building, the fixed hardware is first fixed and installed in accordance with the construction baseline of the wall of the building, and then the polyurethane adhesive is filled in the horizontal surface of the fixed hardware. Since the construction is carried out in such a manner as to be fitted into the mounting groove on the expanded polystyrene molded article, the construction is simple and, of course, the construction state is firmly maintained.

또, 상기 발포 폴리스티렌 조형물의 상면 앞부분의 모서리에 보강부재가 감싸여지기 때문에 내충격성이 강해져 모서리부분의 파손이 방지된다는 효과가 있다.In addition, since the reinforcing member is wrapped around the upper edge of the upper surface of the expanded polystyrene molding, the impact resistance is enhanced, thereby preventing the breakage of the edge portion.

도 1은 종래 발포 폴리스티렌 조형물의 시공구조를 나타내는 측단면도,1 is a side cross-sectional view showing a construction structure of a conventional expanded polystyrene molded article,

도 2는 본 고안에 따른 발포 폴리스티렌 조형물의 시공구조를 나타내는 분리 사시도,Figure 2 is an exploded perspective view showing the construction structure of the expanded polystyrene molded article according to the present invention,

도 3은 본 고안에 따른 발포 폴리스티렌 조형물 시공구조에서 고정철물을 나타내는 확대 사시도,Figure 3 is an enlarged perspective view showing the fixed hardware in the expanded polystyrene sculpture construction structure according to the present invention,

도 4는 본 고안에 따른 발포 폴리스티렌 조형물의 시공상태를 나타내는 측단면도,Figure 4 is a side cross-sectional view showing a construction state of the expanded polystyrene molded article according to the present invention,

도 5는 본 고안에 따른 발포 폴리스티렌 조형물의 시공순서를 나타내는 공정도이다.5 is a process chart showing the construction procedure of the expanded polystyrene molded article according to the present invention.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings

42 : 발포 폴리스티렌 조형물, 44 : 장착홈42: expanded polystyrene sculpture, 44: mounting groove

50 : 보강부재 54 : 고정철물50: reinforcing member 54: fixed hardware

54a : 수직면 54b : 수평면54a: vertical plane 54b: horizontal plane

58 : 장공 60 : 체결공58: long hole 60: fastener

62 : 걸림편 64 : 채워넣기 조형물62: hanging piece 64: filling sculpture

66 : 폴리우레탄 접착제 68 : 실란트.66 polyurethane adhesive 68 sealant.

Claims (3)

소정의 형상으로 이루어지고, 수직을 이루는 뒷면에서 수평방향으로 소정 높이와 깊이를 갖는 장착홈이 형성된 다수의 발포 폴리스티티렌 조형물과;A plurality of expanded polystyrene moldings having a predetermined shape and having mounting grooves having a predetermined height and depth in a horizontal direction on a vertical rear surface thereof; 소정 폭과 길이를 갖는 수직면과 수평면이 서로 직각되게 절곡된 형상으로 이루어지고, 상기 수직면이 시공대상 건물의 벽면에 앵커볼트에 의해 고정된 상태에서 수평면은 상기 발포 폴리스티렌 조형물의 뒷면에 형성된 장착홈에 끼워져 발포 폴리스티렌 조형물을 지탱할 수 있도록 하는 고정 철물과;The vertical plane and the horizontal plane having a predetermined width and length are formed to be bent at right angles to each other, and the horizontal plane is mounted to the mounting groove formed on the rear side of the expanded polystyrene sculpture while the vertical plane is fixed to the wall of the building to be constructed by anchor bolts. A fixing hardware fitted to support the expanded polystyrene sculpture; 상기 발포 폴리스티렌 조형물과 동일한 형상으로 이루어지며, 건물의 벽면에 미리 장착된 발포 폴리스티렌 조형물사이의 틈새를 메워주는 채워넣기 조형물로 이루어진 것을 특징으로 하는 발포 폴리스티렌 조형물의 시공구조.Constructed of the same shape as the foamed polystyrene moldings, the construction structure of the foamed polystyrene moldings, characterized in that made of a filling molding to fill the gap between the foamed polystyrene moldings pre-mounted on the wall of the building. 제1항에 있어서,The method of claim 1, 상기 고정 철물상의 수직면의 세로방향 중심선상에는 위치조정을 위한 소정 크기의 장공이 형성되고, 상기 장공으로부터 좌우 양쪽으로 일정 거리 벗어난 위치에는 정공형태의 체결공이 형성되는 한편, 고정 철물상의 수평면 저면 양쪽 가장자리에는 쐐기형, 사각형, 원호형 중에서 선택된 어느 하나의 형상을 갖는 걸림편이 하나 또는 복수개로 하향·형성된 것을 특징으로 하는 발포 폴리스티렌 조형물의 시공구조.Long holes of a predetermined size are formed on the vertical center line of the vertical surface of the fixed hardware, and hole-shaped fastening holes are formed at positions deviated by a predetermined distance from the left and right sides of the long hole, and on both edges of the bottom surface of the horizontal surface of the fixed hardware. Construction structure of the expanded polystyrene moldings, characterized in that the engaging piece having any one shape selected from wedge shape, quadrangular shape and arc shape is downwardly formed. 제1항에 있어서,The method of claim 1, 상기 발포 폴리스티렌 조형물의 상부면과 접하는 앞부분 모서리부분에는 침탄강, 침탄질화강, 질화강, 알루미늄, 플라스틱중에서 선택된 어느 하나의 재질로 된 1∼2mm두께의 보강부재가 감싸여진 상태에서 우레탄 접착제에 의하여 접착된 것을 특징으로 하는 발포 폴리스티렌 조형물의 시공구조.The front edge portion contacting the upper surface of the expanded polystyrene molding is bonded by a urethane adhesive in a state in which a reinforcing member having a thickness of 1 to 2 mm made of any one selected from carburized steel, carburized nitride, nitride, aluminum, and plastic is wrapped. Construction structure of the expanded polystyrene moldings, characterized in that.
KR20-2005-0019906U 2005-07-08 2005-07-08 Construction structure of expanded polystyrene moulding KR200398409Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2005-0019906U KR200398409Y1 (en) 2005-07-08 2005-07-08 Construction structure of expanded polystyrene moulding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2005-0019906U KR200398409Y1 (en) 2005-07-08 2005-07-08 Construction structure of expanded polystyrene moulding

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020050052860A Division KR100669810B1 (en) 2005-06-20 2005-06-20 Construction structure of expanded polystyrene moulding and construction method of the same

Publications (1)

Publication Number Publication Date
KR200398409Y1 true KR200398409Y1 (en) 2005-10-12

Family

ID=43699475

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0019906U KR200398409Y1 (en) 2005-07-08 2005-07-08 Construction structure of expanded polystyrene moulding

Country Status (1)

Country Link
KR (1) KR200398409Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100738508B1 (en) 2006-09-06 2007-07-11 대건엔지니어링 주식회사 Reinforcement structure of modeling for building exterior adornment
KR100763242B1 (en) 2006-05-30 2007-10-04 박종우 Molding ornaments for interior and exterior of buildings and manufacturing method therefor
CN109750757A (en) * 2019-01-29 2019-05-14 无锡市政设计研究院有限公司 A kind of decoration for vertical face bar line for avoiding metope rainwater from impregnating

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100763242B1 (en) 2006-05-30 2007-10-04 박종우 Molding ornaments for interior and exterior of buildings and manufacturing method therefor
KR100738508B1 (en) 2006-09-06 2007-07-11 대건엔지니어링 주식회사 Reinforcement structure of modeling for building exterior adornment
CN109750757A (en) * 2019-01-29 2019-05-14 无锡市政设计研究院有限公司 A kind of decoration for vertical face bar line for avoiding metope rainwater from impregnating

Similar Documents

Publication Publication Date Title
US9637933B2 (en) Systems and methods for installing cladding panels
KR200410714Y1 (en) facing of constrution fixture
US8887460B1 (en) System and method for installation of decorative molding
KR100669810B1 (en) Construction structure of expanded polystyrene moulding and construction method of the same
MX2010011892A (en) Embedded clip attachment for cast architectural element.
WO2010065034A2 (en) Insulated exterior cladding system
JP3083722B2 (en) Outdoor structures such as gateposts, gate sleeves, and walls
KR200398409Y1 (en) Construction structure of expanded polystyrene moulding
KR102123459B1 (en) External panel for construction
KR20110004692U (en) Fixing Clip for Fabrication of Extruded Cement Panels
KR101808281B1 (en) The method for building exterior panels mounting bracket and bracket thereof
JPH0452367A (en) Construction method of tiling and sticking wall material
KR20060108481A (en) A mounting apparatus of decoration panel for building
KR20050104117A (en) Constructing structure for decoration panels of a building and constructing method
JP4213027B2 (en) Curtain
US20080092480A1 (en) Wall-mounted ornamental architectural members and mounting method
US20220053960A1 (en) Rod holder system
KR200435772Y1 (en) Gangform with urethane artform
KR20110116302A (en) A wall panel assembly
KR100388547B1 (en) The transformation-type door frame
KR200357108Y1 (en) Constructing structure for decoration panels of a building
JP2649882B2 (en) Tile installation method
US20120227341A1 (en) Devices for Anchoring Stone Facing Elements Comprising Retaining Members Pressing Against the Wall
JPH0835246A (en) Groove structure for drainage, water supply piping, and wiring
JP3078726B2 (en) Dry exterior structure

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20060828

Year of fee payment: 3

EXTG Extinguishment