KR200370427Y1 KR20-2004-0026380U KR20040026380U KR200370427Y1 KR 200370427 Y1 KR200370427 Y1 KR 200370427Y1 KR 20040026380 U KR20040026380 U KR 20040026380U KR 200370427 Y1 KR200370427 Y1 KR 200370427Y1
Authority
KR
South Korea
Prior art keywords
pipe
coupled
support member
unit arm
ring body
Prior art date
Application number
KR20-2004-0026380U
Other languages
Korean (ko)
Inventor
심근섭
Original Assignee
주식회사 영화종합기술단건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 영화종합기술단건축사사무소 filed Critical 주식회사 영화종합기술단건축사사무소
Priority to KR20-2004-0026380U priority Critical patent/KR200370427Y1/en
Application granted granted Critical
Publication of KR200370427Y1 publication Critical patent/KR200370427Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G25/06Shores or struts; Chocks telescopic with parts held together by positive means
    • E04G25/061Shores or struts; Chocks telescopic with parts held together by positive means by pins
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/12Clamps or clips for crossing members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/22Stiff scaffolding clamps for connecting scaffold members of common shape for scaffold members in end-to-side relation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G2025/045Shores or struts; Chocks telescopic which telescoping action effected by a lever

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 고안은 건축용 서포트 파이프에 관한 것이다.The present invention relates to a building support pipe.

본 고안은 상부 서포트 부재가 끼워지도록 결합된 하부 서포트 부재의 상단에 높낮이 조절구가 나사 결합되어지도록 구성되고, 상기 높낮이 조절구가 결합된 하부 서포트 부재에 간격유지구가 결합되도록 구성된 건축용 서포트 파이프에 있어서, 상기 간격유지구는 다수의 고정공이 형성된 단위 아암이 절첩수단에 의하여 제 1파이프의 외경 보다 큰 내경을 갖는 링몸체의 바깥쪽에 결합 되어지도록 구성하되, 상기 단위 아암이 링몸체의 바깥쪽에 방사형태로 여러개가 결합 되어지도록 구성하고, 상기 고정공에 볼트와 너트를 결합시켜 다른 단위 아암이 연결되어지도록 구성됨을 특징으로 한다.The present invention is configured so that the height adjustment mechanism is screwed to the upper end of the lower support member coupled to the upper support member is fitted, the construction support pipe configured to be coupled to the interval support to the lower support member coupled to the height adjustment mechanism The spacing member is configured such that the unit arms having a plurality of fixing holes are coupled to the outside of the ring body having an inner diameter larger than the outer diameter of the first pipe by the folding means, wherein the unit arms are radially outside the ring body. It is configured to be coupled to each other, characterized in that configured to be connected to the other unit arm by coupling the bolt and nut to the fixing hole.

따라서, 본 고안은 바닥 슬라브와 천정 스라브 사이에 설치되는 각각의 서포트 파이프 간격을 일정하게 유지되도록 설치함으로써, 거푸집의 비틀림을 방지하여 정밀도가 높은 구조물을 얻을 수 있도록 하고, 아울러 그 시공성을 향상시켜 그에 따른 작업공기를 단축할 수 있도록 한 것이다.Therefore, the present invention is installed to maintain a constant spacing of each support pipe installed between the floor slab and the ceiling slab, to prevent the twisting of the formwork to obtain a high-precision structure, and also to improve the workability It is to shorten the working air.

Description

건축용 서포트 파이프{A SUPPROT PIPE FOR CONSTRUCTION}Construction support pipes {A SUPPROT PIPE FOR CONSTRUCTION}

본 고안은 건축용 서포트 파이프에 관한 것으로서, 특히 상하 서포트 부재및 하부 서포트 부재의 결합으로 구성되는 서포트 파이프에 전후, 좌우의 서포트 파이프의 간격이 유지되어지도록 하는 간격유지구를 결합시켜 사용함으로써, 거푸집의 비틀림을 방지하여 정밀도가 높은 구조물을 얻을 수 있도록 하고, 아울러 시공성을 향상시키고 그에 따른 작업공기를 단축할 수 있도록 한 것이다.The present invention relates to a support pipe for building, and in particular, by using a support pipe composed of a combination of upper and lower support members and a lower support member, a gap retaining zone for maintaining a space between the support pipes of the front and rear and left and right, It prevents torsion to obtain a structure with high precision, and improves workability and shortens working air accordingly.

토목이나 구조물을 건축하는 현장에서 콘크리트를 양생하기 위해서는 통상 콘크리트 구조물의 양생이 끝날 때까지 그 하부를 지지하는 서포트 파이프를 사용하게 된다.In order to cure concrete at the site of civil engineering or building structures, support pipes are usually used to support the lower part of the concrete structure until curing is completed.

상기 서포트 파이프는 콘크리트를 타설하기 전에 미리 시공되는 거푸집을 균일한 높이로 수평이 유지되도록 받침으로써, 상부로 타설되는 콘크리트의 국부적인 하중을 방지하여 붕괴되는 것을 방지하고, 아울러 타설된 콘크리트를 양생되기 전까지 받쳐 변형이 발생되는 것을 막는 주된 기능을 갖도록 되어 있다.The support pipe supports the formwork pre-installed before placing concrete to maintain a uniform height, thereby preventing local collapse of the concrete to be poured to the top to prevent collapse and curing the poured concrete. The main function is to prevent the deformation from occurring until now.

이러한 서포트 파이프는 통상 바닥 스라브의 상부에 거의 수직인 형태로 놓여지는 하부 서포트 부재와, 천정 스라브의 하부를 떠받치는 형태로 놓여지는 상부 서포트 부재 및 상기 하부 서포트 부재 및 상부 서포트 부재 사이에 상,하 수직방향으로 이동되어지도록 결합된 높낮이 조절부 그리고 상기 상부 서포트 부재가 하부로 이동되어지는 것을 방지하는 스톱핀으로 구성되어 있다.The support pipe is usually provided with a lower support member placed in a substantially vertical form on top of a bottom slab, an upper support member placed in a form supporting a lower portion of a ceiling slab, and an upper and a lower portion between the lower support member and the upper support member. It is composed of a height adjustment unit coupled to be moved in the vertical direction and a stop pin to prevent the upper support member is moved to the bottom.

이와 같은 구성을 갖는 서포트 파이프를 바닥 스라브 및 천정 스라브 사이에 설치하는 과정은 먼저, 하부 서포트 부재에 상부 서포트 부재를 삽입하여 세운 다음 높낮이 조절부를 회전시킴과 동시에 상부 서포트 부재에 끼워진스톱핀을 밀어 올리게 됨에 따라 이와 연결된 상부 서포트 부재가 상부로 이동하게 된다.The process of installing the support pipe having such a configuration between the floor slab and the ceiling slab is performed by first inserting the upper support member into the lower support member to raise it, then rotating the height adjusting part and simultaneously pushing up the stop pin fitted to the upper support member. As a result, the upper support member connected thereto moves upward.

따라서, 상부 서포트 부재 및 하부 서포트 부재가 천정 스라브의 하부를 밀어 받치는 형태를 유지하게 됨에 따라 콘크리트를 타설하는 과정에서 발생되는 콘크리트의 무게를 안정되게 받쳐 붕괴 등의 사고가 발생되는 것을 방지하고, 아울러 타설된 콘크리트를 양생시키는 과정에서 변형을 방지하게 된다.Therefore, as the upper support member and the lower support member maintain the shape of pushing down the lower part of the ceiling slab, the weight of the concrete generated in the process of placing the concrete stably supports and prevents accidents such as collapse. Deformation is prevented in the process of curing the poured concrete.

그러나 서포트 파이프는 타설되는 콘크리트의 하중을 안정적이게 받치도록 함과 동시에 붕괴의 위험을 방지하고 아울러 양생 과정에서 변형이 발생되는 것을 방지하기 위해서는 각각의 서포트 파이프가 일정한 간격을 갖도록 설치되어지는 것이 이상적이나 작업공간의 협소와 작업자의 인식부족으로 인하여 그 간격이 일정치 못함에 따라 거푸집(형틀)에 비틀림이 발생하게 되는 원인으로 인해 구조물의 정밀도와 시공성이 낮아짐으로써 작업공기가 길어지게 되는 문제점이 있었다.However, the support pipes should ideally be installed at regular intervals so that they can support the load of the concrete being poured while preventing the risk of collapse and preventing deformation from occurring during curing. Due to the narrowness of the work space and the lack of recognition of the workers, there is a problem that the work air is lengthened by lowering the precision and workability of the structure due to the torsion in the formwork (form).

본 고안은 이와 같은 문제점을 해소하기 위해 창출한 것으로서 상하 서포트 부재 및 하부 서포트 부재로 구성되는 서포트 파이프에 전후, 좌우의 서포트 파이프의 간격이 유지되어지도록 하는 간격유지구를 결합시켜 사용함으로써, 거푸집의 비틀림을 방지하여 정밀도가 높은 구조물을 얻을 수 있도록 하고, 아울러 시공성을 향상시키고 그에 따른 작업공기를 단축할 수 있도록 하는 건축용 서포트 파이프를 제공하는데 그 목적이 있다.The present invention was created in order to solve such a problem, and by using a support pipe composed of upper and lower support members and a lower support member in combination with a gap retaining hole for maintaining a gap between the support pipes of the front and rear and left and right sides, It is an object of the present invention to provide a support pipe for building to prevent twisting to obtain a structure with high precision, and to improve workability and shorten working air.

도 1은 본 고안에 따른 서포트 파이프의 분해 사시도.1 is an exploded perspective view of a support pipe according to the present invention.

도 2는 본 고안에 따른 서포트 파이프의 사시도.Figure 2 is a perspective view of the support pipe according to the present invention.

도 3은 본 고안에 따른 서포트 파이프의 종단면도.Figure 3 is a longitudinal sectional view of the support pipe according to the present invention.

도 4는 본 고안에 따른 서포트 파이프의 설치상태를 도시한 예시도.4 is an exemplary view showing an installation state of the support pipe according to the present invention.

도 5는 본 고안에 따른 서포트 파이프의 다른 실시예를 도시한 예시도.5 is an exemplary view showing another embodiment of the support pipe according to the present invention.

<도면의 주요 부분에 대한 부호의 간단한 설명><Brief description of symbols for the main parts of the drawings>

1:간격유지구 2:상부 서포트 부재1: Spacing zone 2: Upper support member

3:하부 서포트 부재 4:높낮이 조절구3: Lower support member 4: Height adjustment

11:단위 아암 12:절첩수단11: unit arm 12: folding means

13:링몸체 14:볼트13: Ring body 14: Bolt

15:너트 111:고정공It is a nut 15: Nut 111

32:제 1파이프32: The first pipe

이와 같은 목적을 달성하기 위한 본 고안은 상부 서포트 부재가 끼워지도록 결합된 하부 서포트 부재의 상단에 높낮이 조절구가 나사 결합되어지도록 구성되고, 상기 높낮이 조절구가 결합된 하부 서포트 부재에 간격유지구가 결합되도록 구성된 건축용 서포트 파이프에 있어서, 상기 간격유지구는 다수의 고정공이 형성된 단위 아암이 절첩수단에 의하여 제 1파이프의 외경 보다 큰 내경을 갖는 링몸체의 바깥쪽에 결합 되어지도록 구성하되, 상기 단위 아암이 링몸체의 바깥쪽에 방사형태로 여러개가 결합 되어지도록 구성하고, 상기 고정공에 볼트와 너트를 결합시켜 다른 단위 아암이 연결되어지도록 구성됨을 특징으로 하는 건축용 서포트 파이프를 제공함에 그 목적이 달성된다.The present invention for achieving the above object is configured to be screwed on the upper and lower adjustment member is coupled to the upper end of the lower support member coupled to the upper support member, the gap support is a lower support member coupled to the height adjustment opening In the building support pipe configured to be coupled, the spacing is configured so that the unit arm is formed with a plurality of fixing holes are coupled to the outside of the ring body having an inner diameter larger than the outer diameter of the first pipe by the folding means, the unit arm is The object is achieved by providing a support pipe for building, characterized in that it is configured to be coupled to the radially on the outer side of the ring body, and the other unit arm is connected by coupling the bolt and nut to the fixing hole.

이하, 본 고안의 실시예를 첨부 도면을 참조하여 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described with reference to the accompanying drawings.

먼저, 본 고안에 따른 건축용 서포트 파이프(A)는 도 1 내지 도 4에 도시된 바와 같이, 간격유지구(1), 상부 서포트 부재(2), 하부 서포트 부재(3) 및 높낮이 조절구(4)로 구성된다.First, the building support pipe (A) according to the present invention, as shown in Figures 1 to 4, the spacing holder (1), the upper support member (2), the lower support member (3) and the height adjustment opening (4) It is composed of

여기에서, 상기 간격유지구(1)는 천정 스라브(9)와 바닥 스라브(8) 사이에 세워질 다수개의 서포트 파이프의 간격을 일정하게 유지되도록 함으로써, 그에 따른 시공성을 향상시킴과 동시에 안정성 및 건축 구조물의 정밀도를 얻을 수 있도록 하는 주된 기능이 제공되어지도록 구성되어 있다.In this case, the spacer 1 is to maintain a constant spacing of the plurality of support pipes to be built between the ceiling slab 9 and the floor slab 8, thereby improving the construction and thereby stability and building structure It is configured to provide the main function to obtain the precision of.

이를 위하여 상기 간격유지구(1)는 도 1에 도시된 바와 같이, 단위 아암(11), 절첩수단(12), 링몸체(13) 및 볼트(14)와 너트(15)로 구성되어 있다.To this end, the spacer 1 is composed of a unit arm 11, a folding means 12, a ring body 13, a bolt 14 and a nut 15, as shown in FIG.

여기에서, 상기 단위 아암(11)은 직사각형의 단면이 길이 방향으로 연속되어지도록 형성된 것으로 그 상부에는 상하로 관통되는 다수개의 고정공(111)이 길이 방향을 따라 일정한 간격으로 형성되어 있다.Here, the unit arm 11 is formed so that the rectangular cross section is continuous in the longitudinal direction, and a plurality of fixing holes 111 penetrating upward and downward are formed at regular intervals along the longitudinal direction.

또한, 상기 단위 아암(11)은 일측 끝단은 만곡형태를 갖도록 형성되어 있고, 타측 끝단은 후술하는 제 2힌지공(123)이 일체로 형성되어 있다.In addition, the unit arm 11 is formed such that one end thereof has a curved shape, and the other end thereof is integrally formed with a second hinge hole 123 described later.

본 고안에서는 단위 아암(11)을 직사각형의 단면을 갖는 단순한 형태를 갖도록 형성하였으나, 이러한 형태 이외에 그 상부나 하부 및 양측면에 길이방향을 따라 연속되어지는 돌기를 형성하여 단위 아암(11)의 강도를 더 높혀 하측, 즉 바닥 스라브(8)의 방향으로 휘어지는 것을 방지하도록 사용하는 것이 더욱 바람직하다.In the present invention, the unit arm 11 is formed to have a simple shape having a rectangular cross section. However, in addition to the shape, the unit arm 11 has protrusions formed along the longitudinal direction on the top, the bottom, and both sides thereof, thereby increasing the strength of the unit arm 11. It is more preferable to use it higher to prevent it from bending in the direction of the lower side, namely the bottom slab 8.

또한, 상기 고정공(111)을 볼트(14)가 삽입되어질 수 있는 단순한 원형태를 갖도록 형성하였으나, 이러한 형태 이외에 단위 아암(11)과 다른 단위 아암(11')을 볼트(14)와 너트(15)로 결합 고정시키는 과정에서 보다 원활하게 결합시킬 수 있도록 하기 위하여 길이 방향으로 길게 형성된 장공형태를 갖도록 사용하는 것이 더욱 바람직하다.In addition, although the fixing hole 111 is formed to have a simple circular shape into which the bolt 14 can be inserted, the unit arm 11 and the other unit arm 11 'may be formed by the bolt 14 and the nut ( It is more preferable to use it to have a long hole shape formed in the longitudinal direction in order to be able to be coupled more smoothly in the process of bonding and fixing 15).

그리고 제 2힌지공(123)이 형성된 단위 아암(11)의 끝단은 반원형태를 갖도록 형성하여 힌지핀(124)을 중심으로 시계방향 또는 반시계방향으로 회동하는 과정에서 상호 간섭이 발생되는 것을 방지하여 보다 원활한 설치가 이루어질 수 있도록 구성되어 있다.The end of the unit arm 11 having the second hinge hole 123 is formed to have a semi-circle shape to prevent mutual interference from occurring in a process of rotating clockwise or counterclockwise around the hinge pin 124. It is configured to make more smooth installation.

한편, 상기 단위 아암(11)은 링몸체(13)의 바깥쪽으로 방사형태를 갖도록 적어도 2개 이상 바람직하기로는 4개가 구비되어 평면에서 볼때 상하, 좌우로 서포트 파이프의 간격이 일정하게 유지되어 질 수 있도록 구성되어 있다.On the other hand, the unit arm 11 is provided with at least two or more preferably four to have a radial shape to the outside of the ring body 13, so that the spacing of the support pipe vertically, horizontally and vertically can be maintained in a plan view. It is configured to.

상기 링몸체(13)는 평상시는 단위 아암(11)이 링몸체(13)로 부터 분리되는 것을 방지함과 동시에 설치할 경우, 동일한 중심에서 같은 거리를 갖도록 단위 아암(11)이 펼쳐질 수 있도록 하고, 아울러 하부 서포트 부재(3)로 부터 분리시켜 별도의 장소에 보관되어질 수 있도록 구성되어 있다.The ring body 13 usually prevents the unit arm 11 from being separated from the ring body 13 and at the same time, the unit arm 11 can be unfolded to have the same distance from the same center. In addition, it is configured to be stored in a separate place by separating from the lower support member (3).

이를 위해, 상기 링몸체(13)는 소정 두께를 갖는 중공형태로 그 내경이 제 1파이프(32)의 외경 보다 크게 형성되어 있고, 그 바깥쪽인 외주연부에는 절첩수단(12)에 의하여 단위 아암(11)이 접혔다 펼쳐질 수 있도록 구성되어 있다.To this end, the ring body 13 has a hollow shape having a predetermined thickness, the inner diameter of which is larger than the outer diameter of the first pipe 32, and the outer side of the outer peripheral portion of the unit arm by the folding means 12 (11) is configured to be folded and unfolded.

상기 절첩수단(12)은 길이가 비교적 길은 단위 아암(11)을 평상시는 하부 서포트 부재(3)를 구성하는 제 1파이프(32)와 같은 방향으로 접어 보관되어지도록 하고, 설치시 제 1파이프(32)에 직각이 되는 방향으로 펼쳐 이웃한 다른 하부 서포트 파이프에 결합된 또는 끼워진 형태로 있는 다른 단위 아암(11')에 볼트(14)와 너트(15)로 고정되어지도록 구성되어있다.The folding means 12 is such that the unit arm 11, which is relatively long in length, is folded and stored in the same direction as the first pipe 32 constituting the lower support member 3, and when installed, the first pipe ( It is configured to be secured with bolts 14 and nuts 15 to other unit arms 11 ′, which extend in a direction perpendicular to 32 and are joined or fitted to another adjacent lower support pipe.

이러한 절첩수단(12)은 제 1힌지공(121)을 갖는 힌지편(122)이 링몸체(13)의 외주면에 일정한 간격이 유지되어지도록 고정 결합되어 있고, 상기 제 1힌지공(121) 사이로 제공되는 공간에는 끝단에 제 2힌지공(123)이 형성된 단위 아암(11)이 삽입되어지도록 구성되어 있다.The folding means 12 has a hinge piece 122 having a first hinge hole 121 is fixedly coupled to the outer peripheral surface of the ring body 13 so as to maintain a predetermined interval, between the first hinge hole 121 In the space provided, the unit arm 11 in which the second hinge hole 123 is formed is inserted.

또한, 상기 제 1힌지공(121) 및 제 2힌지공(123)에는 소정 길이를 갖는 힌지핀(124)이 끼워지도록 구성되어지되, 상기 힌지핀(124)은 제 1힌지공(121) 및 제 2힌지공(123)에 결합되어지는 과정에서 제 1힌지공(121)의 바깥쪽이로 일정한 길이 만큼 노출되어지도록 결합시킨 상태에서 프레스를 이용하여 양측단을 압착시켜 한번 결합된 상태에서는 별도의 외력이 작용하지 않는 이상 결합된 상태가 계속 유지될 수 있도록 결합 되어있다.In addition, the first hinge hole 121 and the second hinge hole 123 is configured to be fitted with a hinge pin 124 having a predetermined length, the hinge pin 124 is the first hinge hole 121 and In the process of being coupled to the second hinge hole 123, the outer side of the first hinge hole 121 is coupled so as to be exposed to a certain length by a predetermined length, so that both ends are compressed by using a press and are separately Unless the external force of the action of the combined state is maintained so that it is combined.

한편, 상기 간격유지구(1)를 구성하는 링몸체(13)를 제 1파이프(32)에 끼운 상태에서 하부 서포트 부재(3)를 옮길 경우, 힌지핀(124)으로 결합된 단위 아암(11)들이 바깥쪽으로 벌어지는 것을 방지하기 위한 방안으로 단위 아암(11)의 끝단에 별도의 고정핀(127)을 끼우고, 끼워진 고정핀(127)의 일부가 제 1파이프(3)에 형성된 고정홈(321)에 결합되어지도록 함으로써, 이를 방지할 수 있게 된다.On the other hand, when the lower support member 3 is moved in a state where the ring body 13 constituting the spacing holder 1 is inserted into the first pipe 32, the unit arm 11 coupled with the hinge pin 124 is provided. In order to prevent them from spreading outwardly, a separate fixing pin 127 is inserted into the end of the unit arm 11, and a part of the fixing pin 127 fitted into the fixing groove is formed in the first pipe 3. By being coupled to 321, it is possible to prevent this.

상기 하부 서포트 부재(3)는 평판형태를 갖는 제 1받침 플레이트(31)의 상부에 소정의 길이를 가지며 중공형태인 제 1파이프(32)가 수직 또는 직각이 되도록 결합되어 있고, 상기 제 1파이프(32)의 상단에는 축방향의 길이를 갖는 슬라이드공(33)이 형성되어 있고, 상기 슬라이드공(33)을 포함하는 제 1파이프(32) 상단의 외주연부에는 소정 길이를 갖는 수나사(34)가 일체로 형성되어 있다.The lower support member 3 is coupled to the first pipe 32 having a predetermined length and a hollow shape perpendicular to or perpendicular to the upper portion of the first support plate 31 having a flat plate shape. A slide hole 33 having an axial length is formed at an upper end of the 32, and an external thread 34 having a predetermined length is formed at an outer periphery of the upper end of the first pipe 32 including the slide hole 33. Is integrally formed.

상기 상부 서포트 부재(2)는 제 2받침 플레이트(21)의 하부에 중공인 형태를 갖는 제 2파이프(22)가 수직되어지도록 결합되어있고, 상기 제 2파이프(22)에는 일정한 간격을 갖는 관통공(23)이 일체로 형성되어있으며, 상기 제 2파이프(22)의 외경은 제 1파이프(32)의 내경 보다 작게 형성하여 제 2파이프(22)가 제 1파이프(32)에 끼워지는 형태로 조립되어지도록 구성되어 있다.The upper support member 2 is coupled to the bottom of the second support plate 21 so that the second pipe 22 having a hollow shape is perpendicular to each other, and the second pipe 22 has a predetermined interval therethrough. Ball 23 is formed integrally, the outer diameter of the second pipe 22 is formed smaller than the inner diameter of the first pipe 32 so that the second pipe 22 is fitted to the first pipe (32). It is configured to be assembled.

상기 높낮이 조절부(4)는 소정 폭 또는 두께를 갖는 조절몸체(41)로 그 내면에는 상기 수나사(34)에 결합되는 암나사(42)가 형성되어 있고, 그 외주연부에는 힌지(43)로 핸들(44)이 결합되어지도록 구성되어 있다.The height adjusting portion 4 is a control body 41 having a predetermined width or thickness, the inner surface of which is formed with a female screw 42 coupled to the male screw 34, the outer peripheral portion is handled by a hinge 43 44 is configured to be coupled.

상기 스톱핀(5)은 소정의 직경, 즉 제 2파이프(22)에 형성된 관통공(23)에 끼워지도록 형성되어있으며, 분실을 방지하기 위한 방안으로 일측에 구멍을 형성하여 미도시한 와이어 등으로 높낮이 조절부(4)의 일측에 묶여지도록 구성되어 있다.The stop pin 5 is formed to fit into a predetermined diameter, that is, a through hole 23 formed in the second pipe 22, and forms a hole on one side to prevent loss, such as a wire not shown. It is configured to be tied to one side of the height adjustment unit (4).

이와 같은 구성을 갖는 서포트 파이프(A)를 바닥 스라브(8) 및 천정 스라브(9) 사이에 설치하는 과정은 먼저, 하부 서포트 부재(3)를 구성하는 제 1파이프(32)에 간격유지구(1)를 끼운 후 그 상부로 형성된 수나사(34)에 높낮이 조절구(4)를 결합시킨다.The process of installing the support pipe A having such a configuration between the bottom slab 8 and the ceiling slab 9 is first performed by a gap retaining hole in the first pipe 32 constituting the lower support member 3. 1) After fitting the height adjuster (4) is coupled to the male screw 34 formed in the upper portion.

다음, 하부 서포트 부재(3)의 제 1파이프(32)에 상부 서포트 부재(2)의 제 2파이프(22)를 삽입한 후 제 1파이프(32)의 하단에 결합된 제 1받침 플레이트(31)를 바닥 스라브(8)에 맞닿도록 세운 다음 제 1파이프(32)에 끼워진 제 2파이프(22)를 상부로 인출시켜 제 2파이프(22)의 상단에 결합된 제 2받침 플레이트(21)가 천정 스라브(9)의 하부에 거의 맞닿도록 위치시킨다.Next, after inserting the second pipe 22 of the upper support member 2 into the first pipe 32 of the lower support member 3, the first support plate 31 coupled to the lower end of the first pipe 32. ) And the second support plate 21 coupled to the upper end of the second pipe 22 is drawn out by pulling the second pipe 22 fitted in the first pipe 32 upward. It is positioned so that it is almost in contact with the lower part of the ceiling slab 9.

다음, 제 2파이프(22)에 형성된 관통공(23)이 제 1파이프(32)에 형성된 슬라이드공(33)으로 노출되도록 한 후 노출된 관통공(23)에 스톱핀(5)을 끼운 다음, 높낮이 조절부(4)의 조절몸체(41)에 힌지(43)로 결합된 핸들(44)을 펼친 상태로 회전시킴과 동시에 그 내부에 형성된 암나사(42)와 제 1파이프(32)의 외주연부에 형성된 수나사(34)에 의하여 조절몸체(41)가 상부로 이동하면서 스톱핀(5)의 양측단을 밀어 올리게 됨에 따라 이와 연결된 제 2파이프(22)가 상부로 이동하게 된다.Next, the through hole 23 formed in the second pipe 22 is exposed to the slide hole 33 formed in the first pipe 32, and then the stop pin 5 is inserted into the exposed through hole 23. The outer periphery of the female screw 42 and the first pipe 32 formed therein while rotating the handle 44 coupled with the hinge 43 to the adjusting body 41 of the height adjusting part 4 in an extended state. As the adjusting body 41 is moved upward by the male screw 34 formed at the edge, both ends of the stop pin 5 are pushed up so that the second pipe 22 connected thereto is moved upward.

따라서, 제 2파이프(22)의 상단에 일체로 형성된 제 2받침 플레이트(21)가 천정 스라브(9)의 하부를 밀어 떠받치는 형태를 유지하게 된다.Therefore, the second supporting plate 21 integrally formed at the upper end of the second pipe 22 maintains the shape of pushing the lower portion of the ceiling slab 9.

다음, 링몸체(13)에 힌지핀(124)으로 결합된 단위 아암(11)을 수평이 되도록 펼친 상태에서 다른 이웃한 단위 아암(11')을 펼쳐 고정공(111)의 중심이 일치하도록 한 후 볼트(14)를 고정공(111)에 삽입한 다음 너트(15)로 조이는 것으로 각각의 단위 아암(11)과 다른 단위 아암(11')이 결합 고정이 된다.Next, in the state in which the unit arm 11 coupled to the ring body 13 by the hinge pin 124 is extended to be horizontal, the other neighboring unit arms 11 'are extended so that the centers of the fixing holes 111 coincide with each other. After the bolt 14 is inserted into the fixing hole 111 and then tightened with the nut 15, each unit arm 11 and the other unit arms 11 ′ are fixed to each other.

이러한 과정을 통해 바닥 슬라브(8)와 천정 스라브(9) 사이에 세워진 모든 서포트 파이프를 연결할 경우, 평면에서 볼때 상하, 좌우의 간격이 모두 일정하게 유지될 수 있게 된다.Through this process, when connecting all the support pipes erected between the floor slab (8) and the ceiling slab (9), both the upper and lower, left and right spacing in the plane can be kept constant.

한편, 본 고안에서는 서포트 파이프 사이의 간격을 유지하기 위하여 하부 서포트 파이프를 구성하는 제 1파이프에 결합시켜 사용하였으나, 이와같은 방법 이외에 도 5에 도시된 바와 같이, 층간 사이 간격 즉, 바닥 스라브와 천정 스라브 사이의 간격이 클 경우에는 제 1파이프에 결합된 간격유지구와 동일한 형태를 갖는 다른 간격유지구(1')를 상부 서포트 부재를 구성하는 제 2파이프에 결합시켜 사용할 수 있다.Meanwhile, in the present invention, in order to maintain the gap between the support pipes, the first pipe constituting the lower support pipe is used. However, as shown in FIG. 5 in addition to the above method, the space between the floors, that is, the floor slab and the ceiling, is used. In the case where the spacing between the slabs is large, another spacer 1 'having the same shape as the spacer retained on the first pipe may be coupled to the second pipe constituting the upper support member.

이와 같이 본 고안은 상하 서포트 부재 및 하부 서포트 부재로 구성되는 서포트 파이프에 단위 아암이 펼쳐질 수 있는 간격유지구를 결합시켜 전후, 좌우의 서포트 파이프의 간격이 유지되어지도록 설치함으로써, 콘크리트를 타설하는 과정에서 발생되는 붕괴사고를 미연에 방지할 수 있도록 하고, 또한 거푸집의 비틀림을 방지하여 정밀도를 갖는 구조물을 얻을 수 있도록 하고, 아울러 시공성을 향상시켜 그에 따른 작업공기를 단축할 수 있도록 한 것이다.As such, the present invention combines the spacing support where the unit arm can be extended to the support pipe composed of the upper and lower support members and the lower support member, and installs the front and rear support pipes so that the space between the support pipes is maintained. To prevent the collapse accidents occurring in advance, and also to prevent the twisting of the formwork to obtain a structure with precision, and also to improve the workability to shorten the work air accordingly.

Claims (3)

상부 서포트 부재(2)가 끼워지도록 결합된 하부 서포트 부재(3)의 상단에 높낮이 조절구(4)가 나사 결합되어지도록 구성되고, 상기 높낮이 조절구(4)가 결합된 하부 서포트 부재(3)에 간격유지구(1)가 결합되도록 구성된 건축용 서포트 파이프(A)에 있어서,The lower support member 3 is configured such that the height adjustment mechanism 4 is screwed to the upper end of the lower support member 3 to which the upper support member 2 is fitted, and the height adjustment mechanism 4 is coupled thereto. In the building support pipe (A) configured to be coupled to the gap retaining zone (1), 상기 간격유지구(1)는 다수의 고정공(111)이 형성된 단위 아암(11)이 절첩수단(12)에 의하여 제 1파이프(32)의 외경 보다 큰 내경을 갖는 링몸체(13)의 바깥쪽에 결합 되어지도록 구성하되, 상기 단위 아암(11)이 링몸체(13)의 바깥쪽에 방사형태로 여러개가 결합 되어지도록 구성하고, 상기 고정공(111)에 볼트(14)와 너트(15)를 결합시켜 다른 단위 아암(11')이 연결되어지도록 구성됨을 특징으로 하는 건축용 서포트 파이프.The gap holder 1 has an outer portion of the ring body 13 in which the unit arm 11 having a plurality of fixing holes 111 has an inner diameter larger than that of the first pipe 32 by the folding means 12. It is configured to be coupled to the side, the unit arm 11 is configured to be coupled to a plurality of radially to the outside of the ring body 13, the bolt 14 and the nut 15 to the fixing hole 111 Construction support pipes, characterized in that configured to be coupled to the other unit arm (11 '). 제 1항에 있어서,The method of claim 1, 상기 절첩수단(12)은 제 1힌지공(121)이 형성된 힌지편(122)을 링몸체(13)의 외주면에 고정 결합시키고, 상기 제 1힌지공(121) 사이로 끝단에 제 2힌지공(123)이 형성된 단위 아암(11)을 삽입하고, 상기 제 1힌지공(121) 및 제 2힌지공(123)에 힌지핀(124)이 끼워져 힌지 가동되도록 결합됨을 특징으로 하는 건축용 서포트 파이프.The folding means 12 is fixedly coupled to the outer circumferential surface of the ring body 13, the hinge piece 122, the first hinge hole 121 is formed, the second hinge hole (end) between the first hinge hole (121) ( And a unit arm (11) having a 123 formed therein, and a hinge pin (124) is fitted into the first hinge hole (121) and the second hinge hole (123) so as to be hinged. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 단위 아암(11)은 하부 서포트 파이프(3)에 형성된 고정홈(321)에 고정핀(127)으로 그 끝단이 결합되어짐을 특징으로 하는 건축용 서포트 파이프.The unit arm (11) is a building support pipe, characterized in that the end of the fixing pin 127 is coupled to the fixing groove 321 formed in the lower support pipe (3).
KR20-2004-0026380U 2004-09-14 2004-09-14 A supprot pipe for construction KR200370427Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0026380U KR200370427Y1 (en) 2004-09-14 2004-09-14 A supprot pipe for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0026380U KR200370427Y1 (en) 2004-09-14 2004-09-14 A supprot pipe for construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020040072999A Division KR100482272B1 (en) 2004-09-13 2004-09-13 A supprot pipe for construction

Publications (1)

Publication Number Publication Date
KR200370427Y1 true KR200370427Y1 (en) 2004-12-14

Family

ID=49442803

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0026380U KR200370427Y1 (en) 2004-09-14 2004-09-14 A supprot pipe for construction

Country Status (1)

Country Link
KR (1) KR200370427Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100842061B1 (en) 2007-02-21 2008-06-30 강신덕 Jack support

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100842061B1 (en) 2007-02-21 2008-06-30 강신덕 Jack support

Similar Documents

Publication Publication Date Title
KR200384393Y1 (en) Jack support pipe for construction
JP2021529275A (en) Architectural system scaffolding
KR101618703B1 (en) Slab concrete mold for building
KR100482272B1 (en) A supprot pipe for construction
KR102079030B1 (en) Truss type assembly for form supporting member
KR200370427Y1 (en) A supprot pipe for construction
KR100818609B1 (en) The construction structure of slab form being dismantled easily
KR20060037137A (en) Space preservation device for construction support
KR102102214B1 (en) Safety handrail for beam table form
JP7250712B2 (en) balcony device
TWI751278B (en) Temporary support
JP4623570B2 (en) Construction method of jack base and formwork support
KR200384367Y1 (en) A support pipe for construction
KR102361789B1 (en) Supporter for installating horizontal member of supporting system
KR200344123Y1 (en) Strut Preloading Jack and Structure for Supporting Strut using thereof
KR20120049687A (en) Pipe support for construction
KR101796853B1 (en) Extender for extending length of support
RU2691249C1 (en) Unit for jointing pipe-concrete columns with tie beams
KR101806000B1 (en) Extender for extending length of support
KR101788650B1 (en) Double safety fixed support
KR100407115B1 (en) Formwork establishing method using sustaining support
JP2019116787A (en) Form structure for forming slab, and method for constructing floor slab
CN217480840U (en) Platform device
KR102249476B1 (en) Support frame connected to strut for mold
KR102075043B1 (en) Support structure of temporary members

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
EXTG Extinguishment