KR200352963Y1 - a clamp for a cast iron gabion - Google Patents

a clamp for a cast iron gabion Download PDF

Info

Publication number
KR200352963Y1
KR200352963Y1 KR20-2004-0007995U KR20040007995U KR200352963Y1 KR 200352963 Y1 KR200352963 Y1 KR 200352963Y1 KR 20040007995 U KR20040007995 U KR 20040007995U KR 200352963 Y1 KR200352963 Y1 KR 200352963Y1
Authority
KR
South Korea
Prior art keywords
clamp
gabion
fixing member
cast iron
panel
Prior art date
Application number
KR20-2004-0007995U
Other languages
Korean (ko)
Inventor
이재덕
Original Assignee
이재덕
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이재덕 filed Critical 이재덕
Priority to KR20-2004-0007995U priority Critical patent/KR200352963Y1/en
Application granted granted Critical
Publication of KR200352963Y1 publication Critical patent/KR200352963Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0208Gabions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 고안은 주철 가비언 구조물을 제조하기 위해 단위 판넬을 연결하는 수단으로서 보울트 너트의 체결이라는 손쉬운 방법에 의하여 단위 판넬을 용이하게 체결하게 하는 수단을 제공한다. 구체적으로는 판넬과 판넬을 연결함에 있어 다양한 방식과 각도로 판넬들이 상호 체결될 수 있도록 하는 클램프에 관한 것이다.The present invention provides a means for easily fastening the unit panel by an easy method of fastening the bolt nut as a means of connecting the unit panel to produce a cast iron gabion structure. More particularly, the present invention relates to a clamp that allows the panels to be fastened to each other in various ways and angles in connecting the panels.

Description

주철 가비언 클램프{a clamp for a cast iron gabion}Cast iron gabion clamp {a clamp for a cast iron gabion}

본 고안은 주철 가비언(cast iron gabion) 제조용 클램프에 관한 것이다.The present invention relates to a clamp for manufacturing cast iron gabion.

주철 가비언은 하천 저면이나 하천 범면 또는 도로 옆 경사면 등에 사용되는 토목 구조물을 일컫는 용어이다. 즉, 도 1과 같은 구조물을 하천 바닥이나 하천 범면 또는 도로 측면에 설치하는 것이다.Cast iron gabion is a term that refers to civil structures used on river basins, river slopes, or roadside slopes. That is, the structure as shown in Figure 1 is to be installed on the river bed or river surface or road side.

본 고안은 주철 가비언을 제조하기 위해 단위 판넬을 연결하는 손쉬운 도구를 제공하고자 한다. 구체적으로는 판넬과 판넬을 연결함에 있어 다양한 방식과 각도로 판넬들이 상호 체결될 수 있도록 하기 위한 클램프를 제공하여 판넬과 판넬의 체결이 용이하게 이루어질 수 있게 하는 것을 그 목적으로 한다.The present invention seeks to provide an easy tool for connecting unit panels to fabricate cast iron guards. Specifically, the purpose of the panel and the panel is to provide a clamp for allowing the panels to be fastened to each other in various ways and angles in connecting the panel and the panel.

도 1은 종래의 가비언 구조에 대한 예시도이다.1 is an exemplary view of a conventional Gabion structure.

도 2 내지 도 14는 본고안의 실시예를 설명하기 위한 도면이다.2 to 14 are diagrams for explaining an embodiment of the present invention.

본 고안은, 중앙에 일부 잘린 절단부(803)가 존재하는형상의 한 쌍의 고정부재 -상기 고정부재의 좌측과 우측에 한 쌍의 개구(802)가 형성되어 있고 좌우 양측에 두께가 증가한 부분(805)이 존재함- 를 포함하되, 상기 한 쌍의 개구를 관통하여 보울트부재 및 너트부재가 결합함으로써 클램핑 작용이 이루어지는 것을 그 특징으로 하는 전면 상하 클램프에 관한 것이다.The present invention, there is a cut portion 803 is partially cut in the center A pair of fixing members having a shape, wherein a pair of openings 802 are formed on the left and right sides of the fixing member, and a portion 805 having an increased thickness exists on both left and right sides thereof. It relates to a front upper and lower clamps characterized in that the clamping action is made by the bolt member and the nut member are coupled through.

이하 첨부도면을 참조하여 본 고안의 실시예에 대하여 자세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2는 평행클램프에 대한 개략도이다. 일자 형의 제 1 고정부재(200)와 중앙부에 ㄷ자 모양으로 절곡된 부위를 포함하여 좌우 양측에 비하여 중앙부가 움푹 들어간 형태를 갖는 제 2 고정부재(201)를 서로 마주 보게 대향시킨 후 제 1 고정부재와 제 2 고정부재에 대향하여 형성된 각각 2개의 체결공(202,203)을 관통하여 보울트부재(204) 및 너트부재(205)가 체결됨으로써 클램핑 작용이 이루어진다.2 is a schematic diagram of a parallel clamp. The first fixing member 200 and the second fixing member 201 having a shape in which the central portion is recessed from the left and right sides are opposed to each other, including a portion having a straight first bent member 200 and a portion bent in a central portion, and then fixed to the first. The bolt member 204 and the nut member 205 are fastened through two fastening holes 202 and 203 formed to face the member and the second fixing member, respectively, to achieve a clamping action.

도 12의 도면에 의하면, 도 2의 평행클램프를 사용하여 주철 가비언 판넬을 결합한 구조(20)이 도시되어 있다. 도 12와 같이 제 2 고정부재의 절곡된 부위에 체결대상인 좌우 양측의 판넬의 세로대를 끼운 후 보울트 및 너트를 통해 체결함으로써 판넬의 결합이 이루어진다.12, there is shown a structure 20 in which a cast iron gabion panel is coupled using the parallel clamp of FIG. 12 is coupled to the bent portion of the second fixing member by inserting the longitudinal poles of the panel on both the left and right sides to be fastened by fastening through the bolt and the nut is coupled to the panel.

도 3은 교차클램프에 대한 개략도이다. 교차 클램프는 일자형의 제 1 고정부재(300)와,자 형상으로 절곡되어 형성된 제 2 고정부재(301)가 체결공(302,303)을 관통하는 보울트부재(304) 및 너트부재(306)의 체결에 의하여 체결됨으로써 클램핑 작용을 수행한다. 교차 클램프는 가비언 판넬이 교차하는 경우 즉 T자 형태로 교차하는 경우 고정하기 위한 장치이다.3 is a schematic diagram of a cross clamp. Cross clamp is a first fixing member 300 of the straight type, The second fixing member 301 bent in a shape of a child is fastened by fastening the bolt member 304 and the nut member 306 passing through the fastening holes 302 and 303 to perform a clamping action. The cross clamp is a device for fixing when the Gabion panels intersect, that is, when they cross in a T-shape.

도 12에 의하면, 도 3의 교차클램프를 사용하여 주철 가비언 판넬을 결합한 구조(30)이 도시되어 있다. 도면에는 비록 제 1 고정부재만 보이나 이와 제 2 고정부재(301)이 결합되어 있는 것이다. 제 2 고정부재의 절곡에 의하여 이루어지는 공간에 좌우 양측의 가비언 판넬의 세로대와 이에 직각으로 결합되는 제 3의 판넬의 세로대를 삽입한 후 보울트부재 및 너트부재를 사용하여 체결한다.Referring to FIG. 12, there is shown a structure 30 in which a cast iron gabion panel is coupled using the cross clamp of FIG. Although only the first fixing member is shown in the figure, the second fixing member 301 is coupled thereto. After inserting the longitudinal bars of the left and right sides of the Gabion panel and the third panels joined at right angles to the space formed by the bending of the second fixing member, the bolts and nut members are fastened.

도 4는 또다른 교차 클램프에 대한 개략도이다. 도 3과 달리 2개의자 형상으로 절곡되어 형성된 고정부재(400)가 서로를 향해 마주보는 형태로 배치된 후 각각의 고정부재(400)에 형성되어 있는 체결공(402)을 관통하는 보울트부재(404) 및 너트부재(406)의 체결에 의하여 체결됨으로써 클램핑 작용을 수행한다. 이러한 형태의 교차 클램프는 십자 형태로 가비언 판넬이 교차하는 경우에 이들 판넬을 고정하기 위하여 사용하는 것이다.4 is a schematic of another cross clamp. Unlike FIG. 3 The bolt member 404 and the nut member penetrating through the fastening hole 402 formed in each of the fixing member 400 after the fixing member 400 is formed in a shape that is bent in a shape facing each other 406 is fastened by the fastening to perform the clamping action. This type of cross clamp is used to fix these panels when the Gabion panels intersect in a cross shape.

도 4의 교차 클램프는 +자 처럼 직각을 이루며 결합하는 4개의 가비언 판넬의 4개의 세로대를 결합할 때 사용된다.The cross clamp of FIG. 4 is used when joining four longitudinal bars of four Gabion panels that are joined at right angles like a +.

도 5는 상하 클램프에 대한 개략도이다. 상하 클램프는 ㄷ자 모양의 고정부재(500)의 마주보는 면에 대향하는 체결공(502)이 형성되어 있어서 이들 체결공을 관통하여 보울트부재(504) 및 너트부재(506)가 체결됨으로써 고정부재의 대향하는 양면을 서로 당겨줌으로써 클램핑 작용이 이루어진다.5 is a schematic view of a vertical clamp. The upper and lower clamps have fastening holes 502 formed to face opposite sides of the U-shaped fixing member 500 so that the bolt member 504 and the nut member 506 are fastened to penetrate the fastening holes. The clamping action is achieved by pulling opposite sides against each other.

도 12에 의하면, 도 5의 상하클램프를 사용하여 주철 가비언 판넬을 결합한 구조(50)이 도시되어 있다. 도시되어 있는 바와 같이 결합되는 가비언 판넬의 가로대를 ㄷ자 형상의 고정부재의 내측에 삽입한 후 보울트부재 및 너트부재를 사용하여 체결한다.12, there is shown a structure 50 in which a cast iron gabion panel is coupled using the upper and lower clamps of FIG. Insert the crosspiece of the Gabion panel to be coupled as shown in the inner side of the U-shaped fixing member and then fastened using a bolt member and a nut member.

도 6은 코너 클램프에 대한 개략도이다. ㄱ자형의 제 1 고정부재(600)와 ㄴ자가 3회 연속된형상의 제 2 고정부재(601)를 대향하게 배치한 후, 제 1 고정부재 및 제 2 고정부재 사이에 가비언 판넬의 봉(bar)을 넣은 후 제 1 및 제 2 고정부재 각각에 형성된 체결공(602, 603)을 관통하여 보울트부재(604) 및 너트부재(606)를 체결함으로써 클램핑 작용이 이루어진다. 도 15에 의하면, 도 6의교차클램프를 사용하여 주철 가비언 판넬을 결합한 구조(60)이 도시되어 있다.6 is a schematic view of a corner clamp. A-shaped first fixing member 600 and b-shaped three consecutive After arranging the second fixing member 601 having a shape opposite thereto, a bar of the Gabion panel is inserted between the first fixing member and the second fixing member, and then a fastening hole formed in each of the first and second fixing members. The clamping action is achieved by fastening the bolt member 604 and the nut member 606 through the 602 and 603. Referring to FIG. 15, there is shown a structure 60 in which a cast iron gabion panel is coupled using the cross clamp of FIG.

도 7은 전면 상하 클램프에 대한 개략도이다. 제 1 개구(702)와 외주의 일부가 잘린 형태의 제 2 개구(703)가 형성된 고정부재 2개를 대향하게 배치한 후 대향하는 두 고정부재의 제 1 개구를 각각 관통하여 보울트부재 및 너트부재가 결합함으로써 클램핑 작용이 이루어진다. 바람직하게는 제 1 개구와 제 2 개구 사이에 두께가 증가한 부분(705)가 존재한다.7 is a schematic diagram of a front top and bottom clamp. Two fixing members each having a first opening 702 and a second opening 703 having a portion cut out of the outer circumference thereof are disposed to face each other, and then penetrate through the first openings of the two opposite fixing members, respectively. The clamping action is achieved by combining. Preferably there is an increased portion 705 between the first opening and the second opening.

도 8은 또다른 전면 상하 클램프에 대한 개략도이다. 중앙에 일부 잘린 절단부(803)가 존재하는형상의 고정부재의 좌측과 우측에 한 쌍의 개구(802)가 형성되어 있고 좌우 양측에 두께가 증가한 부분(805)이 존재한다. 도 8에 도시된 바와 같이 한 쌍의 고정부재를 대향하게 한 후 개구를 관통하여 보울트부재 및 너트부재가 결합함으로써 클램핑 작용이 이루어진다.8 is a schematic diagram of another front upper and lower clamps. There is a part cut 803 cut in the center A pair of openings 802 are formed on the left and right sides of the fixing member having a shape, and there are portions 805 having increased thicknesses on both left and right sides thereof. As shown in FIG. 8, after the pair of fixing members face each other, a clamping action is performed by coupling the bolt member and the nut member through the opening.

도 13에 의하면, 도 7 및 도 8의 전면 상하 클램프를 사용하여 주철 가비언 판넬을 결합한 구조(70, 80)이 각각 도시되어 있다. 전면 상하 클램프는 가비언 판넬의 가로대와 가로대를 직각 방향으로 체결하기 위한 장치로서 하나의 가로대는 제 2 개구 또는 절단부(703, 803)에 끼우고 나머지 하나의 가로대는 양 고정부재 사이의 공간에 끼운후 보울트부재 및 너트 부재를 통해 체결한다. 도 14에 도시되어 있듯이 가비언 판넬에는 리브(81, 82, 83)가 형성되어 있어서 제 2 개구 또는 절단부(703, 803)에 삽입된 가비언 판넬의 리브가 대향하는 고정부재와 맞물려 체결됨으로써 양 가비언 판넬의 가로대가 서로 결합하게 된다.Referring to FIG. 13, there are shown structures 70 and 80 in which cast iron gabion panels are coupled using the front and bottom clamps of FIGS. 7 and 8, respectively. The front upper and lower clamps are devices for fastening the crossbars and crossbars of the guardian panel at right angles. One crossbar is inserted into the second opening or the cutouts 703 and 803, and the other crossbar is inserted into the space between the two fixing members. After tightening through bolt member and nut member. As shown in FIG. 14, ribs 81, 82, and 83 are formed in the Gabion panel so that the ribs of the Gabion panel inserted into the second opening or the cutouts 703 and 803 are engaged with and engaged with the opposing fixing member. The crosspieces of the unpaneled panels are joined together.

도 9는 보호망 클램프에 대한 개략도이다. 한 쌍의 대향하는 결합부재(901)와, 한 쌍의 대향하는 환봉고정부재(902)를 포함하는 대칭형 구조로 고정부재(900)가 형성된다. 결합부재에는 체결공(903)이 형성되어 있고 환봉고정부재는 환봉을 걸어서 고정할 수 있도록 고리모양으로 형성되어 있다. 보호망 클램프의 한 쌍의 결합부재 사이에 판넬의 봉을 끼우고 환봉고정부재에는 환봉을 끼운 상태에서 상기 체결공을 관통하는 보울트부재와 너트부재가 결합함으로써 결합부재를 서로를 향해 당겨줌으로써 클램핑 작용이 이루어진다.9 is a schematic diagram of a guard clamp. The fixing member 900 is formed in a symmetrical structure including a pair of opposing coupling members 901 and a pair of opposing round bar fixing members 902. The coupling member has a fastening hole (903) is formed and the round bar fixing member is formed in a ring shape to be fixed by walking the round bar. The clamping action is achieved by inserting the rod of the panel between the pair of coupling members of the protection net clamp and the bolt member penetrating the fastening hole and the nut member while the round rod is fitted to the round rod fixing member. Is done.

도 10은 보호망 클램프의 또다른 실시예에 대한 개략도이다. 결합부재(1001)와, 환봉고정부재(1002)를 포함하는 고정부재(1000)가 형성된다. 결합부재에는 체결공(1004)이 형성되어 있고 환봉고정부재는 환봉을 걸어서 고정할 수 있도록 고리모양으로 형성되어 있다. 고정부재의 일부에는 두께가 두꺼워진 부분(1005)가 존재한다. 한 쌍의 대향하는 보호망 클램프의 각각의 결합부재 사이에 판넬의 봉을 끼우고 환봉고정부재에는 환봉을 끼운 상태에서 상기 체결공을 관통하는 보울트부재(1006)와 너트부재(1007)가 결합함으로써 클램핑 작용이 이루어진다.10 is a schematic diagram of another embodiment of a guard clamp. A fixing member 1000 including a coupling member 1001 and a round bar fixing member 1002 is formed. The coupling member has a fastening hole (1004) is formed and the round bar fixing member is formed in a ring shape to be fixed by walking the round bar. A portion 1005 of which the thickness is thick is present in part of the fixing member. Clamping is performed by sandwiching a rod of a panel between each coupling member of a pair of opposing protection net clamps, and a bolt member 1006 and a nut member 1007 penetrating the fastening hole while a round rod is fitted to the round rod fixing member. Work is done.

보호망 클램프는 가비언 구조 상부에 다수의 봉(95)로 이루어진 구조물을 결합시키는 작용을 한다. 가비언 구조를 하천 바닥에 시공하면서 하천 바닥에 돌을 깔아주는 경우가 많은데 가비언 구조물 상측에 도 12와 같이 다수의 봉으로 이루어진 보호망 구조를 형성하면 하천 바닥의 돌이 유실되는 것이 방진된다.The guard clamp serves to couple the structure consisting of a plurality of rods 95 on top of the guardian structure. The construction of the Gabion structure on the river floor while laying a stone on the bottom of the river in many cases, as shown in FIG.

도 11은 브라켓 클램프에 대한 개략도이다. 브라켓 클램프는 2개의 봉이 소정의 각도를 이루면서 형성된다. 2개의 봉이 만나는 쪽의 제 1 봉(111)의 일 끝단에는 집게 발 구조(112)가 형성되어 있고 제 1 봉의 타 끝단에는 한 쌍의 집게발 구조(114)가 형성되어 있다. 2개의 봉이 만나는 쪽의 끝단에 형성된 집게발 구조에는 한 쌍의 대향하는 체결공(116)이 형성되어 있어서 상기 체결공을 관통하여 보울트부재와 너트부재가 체결되고 제 2 봉의 양 단부 중 제 1 봉과 맞닿는 단부의 반대편 단부에는 ㄷ자 형상의 구조(115)가 형성되어 있다. 바람직하게는 세로대(117, 118)를 구비하여 견고한 구조를 형성한다.11 is a schematic diagram of a bracket clamp. The bracket clamp is formed with two rods at an angle. One end of the first rod 111 on the side where two rods meet is formed with a claw structure 112, and the other end of the first rod is a pair of claw structure 114 is formed. A pair of fastening holes 116 are formed in the tongs structure formed at the end of the two rods where the two rods meet, so that the bolt member and the nut member are fastened through the fastening holes and abut the first rod of both ends of the second rod. At the opposite end of the end, a U-shaped structure 115 is formed. Preferably, longitudinal bars 117 and 118 are provided to form a rigid structure.

브라켓 클램프는 단차를 형성하여 복수의 가비언 판넬을 연결하는데 사용된다. 도 13에 도시되어 있듯이 서로 단차를 가지고 결합하는 가비언 판넬을 견고하게 결합하기 위하여 브라켓 클램프를 사용한다.Bracket clamps are used to form a step to connect a plurality of Gabion panels. As shown in FIG. 13, a bracket clamp is used to firmly connect the Gabion panels that are stepped together.

본 고안은 주철 가비언을 제조하기 위해 단위 판넬을 연결하는 보울트 너트의 체결이라는 손쉬운 방법에 의하여 용이하게 체결할 수 있도록 하는 수단을 제공한다. 구체적으로는 판넬과 판넬을 연결함에 있어 다양한 방식과 각도로 판넬들이 상호 체결될 수 있도록 하는 다양한 형태의 클램프를 제공하여 판넬과 판넬의 연결이 손쉽게 이루어질 수 있게 한다.The present invention provides a means for easily fastening by an easy method of fastening a bolt nut connecting a unit panel to produce a cast iron gabion. Specifically, the panel and the panel can be easily connected by providing various types of clamps that allow the panels to be fastened to each other in various ways and angles.

Claims (1)

중앙에 일부 잘린 절단부(803)가 존재하는형상의 한 쌍의 고정부재 -상기 고정부재의 좌측과 우측에 한 쌍의 개구(802)가 형성되어 있고 좌우 양측에 두께가 증가한 부분(805)이 존재함- 를 포함하되,There is a part cut 803 cut in the center A pair of fixing members having a shape, wherein a pair of openings 802 are formed on the left and right sides of the fixing member, and a portion 805 having increased thickness exists on both left and right sides thereof, 상기 한 쌍의 개구를 관통하여 보울트부재 및 너트부재가 결합함으로써 클램핑 작용이 이루어지는 것을 그 특징으로 하는Clamping action is achieved by the bolt member and the nut member is coupled through the pair of openings 전면 상하 클램프.Front upper and lower clamps.
KR20-2004-0007995U 2004-03-23 2004-03-23 a clamp for a cast iron gabion KR200352963Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0007995U KR200352963Y1 (en) 2004-03-23 2004-03-23 a clamp for a cast iron gabion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0007995U KR200352963Y1 (en) 2004-03-23 2004-03-23 a clamp for a cast iron gabion

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020030088458A Division KR20050055290A (en) 2003-12-08 2003-12-08 A clamp for a cast iron gabion and a gabion structure

Publications (1)

Publication Number Publication Date
KR200352963Y1 true KR200352963Y1 (en) 2004-06-09

Family

ID=49431757

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0007995U KR200352963Y1 (en) 2004-03-23 2004-03-23 a clamp for a cast iron gabion

Country Status (1)

Country Link
KR (1) KR200352963Y1 (en)

Similar Documents

Publication Publication Date Title
KR101075156B1 (en) Cable tray
KR101329635B1 (en) High strength steel grating
JP2005520960A5 (en)
KR101599672B1 (en) Coupling device for supporting beam of earth retaining wall
GB2387394A (en) Connector
KR200352963Y1 (en) a clamp for a cast iron gabion
KR200348373Y1 (en) a clamp for a cast iron gabion
KR200352964Y1 (en) a clamp for a cast iron gabion
KR101895448B1 (en) Anchor bolt fixing device for wall form supporter
KR200366437Y1 (en) a clamp for a cast iron gabion and a gabion structure
JP2012526220A (en) Assembled fence
KR200392025Y1 (en) Safety plate for construction
WO2010098254A1 (en) Building unit structural member and floor structure utilizing said unit structural member
KR101144666B1 (en) Cable tray
KR20050055290A (en) A clamp for a cast iron gabion and a gabion structure
KR102308089B1 (en) Clamp for scaffold pipes
KR200468562Y1 (en) construction truss a vinyl house
KR101472942B1 (en) Fence assembling clamp
KR100450733B1 (en) a gabion pannel and a method for constructing the pannel structure
KR101880343B1 (en) Shear Reinforcing Bar Assembly for Wall and Bar Assembly Module using such Assembly
KR101381660B1 (en) Space keep goods for mold
JP2641831B2 (en) Construction site fence assembly
JP2012202037A (en) Wire rod grating fence panel
JP5662216B2 (en) Construction method of wire lattice fence
KR101170543B1 (en) Device for clamping horizontal rod and vertical column

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
LAPS Lapse due to unpaid annual fee
R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20130530

Year of fee payment: 10

EXPY Expiration of term