KR200342365Y1 - shore protection structure of using cramp - Google Patents

shore protection structure of using cramp Download PDF

Info

Publication number
KR200342365Y1
KR200342365Y1 KR20-2003-0036457U KR20030036457U KR200342365Y1 KR 200342365 Y1 KR200342365 Y1 KR 200342365Y1 KR 20030036457 U KR20030036457 U KR 20030036457U KR 200342365 Y1 KR200342365 Y1 KR 200342365Y1
Authority
KR
South Korea
Prior art keywords
rock
flow rate
soil surface
layer
prevent
Prior art date
Application number
KR20-2003-0036457U
Other languages
Korean (ko)
Inventor
최종선
Original Assignee
최종선
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최종선 filed Critical 최종선
Priority to KR20-2003-0036457U priority Critical patent/KR200342365Y1/en
Application granted granted Critical
Publication of KR200342365Y1 publication Critical patent/KR200342365Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

경사진 토사면에 놓여지는 암석과 암석을 연결부재로서 일체형으로 연결함에 따라 토사면으로 부터 암석의 흘러내림을 방지하고, 유속 및 토압에 대해 대항력을 갖게되며, 암석사이의 공극에 어류 등의 서식처를 제공하며, 공극에 유입되는 물의 유속 감쇠로 인해 세굴되는 것을 방지할 수 있도록 한 것으로,By connecting the rock and the rock placed on the inclined soil surface as a connecting member, it prevents the rock from flowing down from the soil surface and has a counter force against the flow velocity and soil pressure, and it is a habitat for fish in the air gap between the rocks. It provides a, to prevent the scour due to the decay of the flow rate of water entering the void,

본 고안은, 정지작업된 토사면에 적층형성되고, 암석과 암석사이에 출입되는 유체의 유속을 감쇠시키는 공극을 형성하는 암석층과, 유속에 대해 저항력을 갖도록 암석에 천공된 고정공에 삽입되어 암석과 암석을 일체형으로 연결하며, 적층위치로 부터 암석 이탈되는 것을 방지하도록 스토퍼가 단부에 형성되는 연결부재와, 토사면으로 부터 암석의 이탈되는 것을 방지하도록 암석층과 토사면사이에 채워지는 잡석층을 구비한다.The present invention is a rock layer formed on the sedimentation surface of the sedimentation work, the rock layer to form a void to attenuate the flow rate of the fluid flowing between the rock and the rock, and inserted into the fixed hole drilled in the rock to have a resistance to the flow rate And a rocking body integrally connected to each other, and a connecting member having a stopper formed at an end portion to prevent rock separation from the stacked position, and a rubble layer filled between the rock layer and the soil surface to prevent the rock from being separated from the soil surface. Equipped.

Description

꺽쇠를 이용한 유속 감쇠형 호안 구조물{shore protection structure of using cramp}Shore protection structure of using cramps

본 고안은 하천 등의 경사면을 축조하는 시공시 어류 등의 서식처를 제공하고, 유속으로 인해 세굴되는 것을 방지하여 수해로 인한 피해를 최소화할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물에 관한 것이다.The present invention provides a habitat for fish, etc., when constructing slopes such as rivers, and relates to a flow-rate damping revetment structure using a cramp to prevent damage from flooding by minimizing scouring due to the flow rate.

더욱 상세하게는, 경사진 토사면에 놓여지는 암석과 암석을 연결부재로서 일체형으로 연결함에 따라, 토사면으로 부터 암석의 흘러내림을 방지하고, 유속 및 토압에 대해 대항력을 갖게되며, 암석사이의 공극에 어류 등의 서식처를 제공하며, 공극에 유입되는 물의 유속 감쇠로 인해 세굴되는 것을 방지할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물에 관한 것이다.More specifically, by integrally connecting the rock and the rock placed on the inclined soil surface as a connecting member, it prevents the rock from flowing down from the soil surface, has a force against the flow rate and earth pressure, and between the rocks The present invention relates to a flow decay-type revetment structure using a bracket that provides a habitat for fish and the like and prevents scouring due to the decay of the flow rate of water flowing into the pore.

일반적으로, 도심 주변의 하천, 저수지 공사 등에 있어서, 자연 형태의 산또는 하천의 사면을 인위적으로 훼손 및 변형시킴에 따라 제방을 보호하기 위하여 사면에는 주로 콘크리트로 구성한 구조물에 각종 호안부재를 피복하며, 호안부재의 하단 기초부에는 다각형 형태의 콘크리트 기초물 또는 철사로 구성된 망체형태의 돌을 채운 돌망태를 설치하여 기초부를 보호하고 있다.In general, in the construction of rivers, reservoirs, etc. around the city center, the slopes cover various shore protection members mainly on concrete structures to protect the levees by artificially damaging and deforming the slopes of natural forms of mountains or rivers. The lower base of the revetment member protects the foundation by installing a gabion filled with a mesh-shaped stone composed of a polygonal concrete foundation or wire.

각종 유수천변은 동하절기, 유수의 흐름형태, 주변환경 등에 따라 천연적인 여러가지 생태환경과 자연환경을 구성하고 있다. 이러한 유수천변 주변을 인공적인 콘크리트 또는 석재 등으로 축조하는 경우 일시적인 미관과 치수의 효과를 발휘하게 된다.The various riversides are composed of various natural ecological and natural environments according to the winter season, the flow of the river, and the surrounding environment. When the circumference of the river flow is constructed with artificial concrete or stone, temporary beauty and dimension are exerted.

그러나, 이러한 제방은 시간이 경과할수록 유속으로 인해 침식과 세굴현상이 심화되고, 식생대의 파괴로 인해 자연 생태계에 엄청난 피해를 초래하여 이들 구조물의 재시공으로 인해 막대한 비용 및 시간이 소요되는 문제점을 갖는다.However, such levees have erosion and scour phenomena due to the flow rate over time, causing tremendous damage to the natural ecosystem due to the destruction of the vegetation zone, resulting in a huge cost and time due to the reconstruction of these structures.

또한, 각종 어류, 조류는 물론 여러종류의 식물체들이 인공구조물에 의하여 그들의 서식처를 잃게되므로 자연적으로 멸종되고 있다. 이로 인해 자연적인 정화기능, 신선한 공기의 제공과 도시민의 휴식처 제공 등의 기본적인 기능이 상실된 죽은 하천, 호수 등으로 전락하여 궁극적으로 인류의 생활환경을 저해시키는 요인으로 지적되고 있다.In addition, various fish, algae, as well as various kinds of plants are naturally extinct because they lose their habitat by the artificial structure. As a result, it has been pointed out as a factor that ultimately impairs the living environment of human beings by falling into dead rivers and lakes that have lost their basic functions such as natural purification, providing fresh air, and providing urban retreats.

최근에는 사면보호 공사시 시공성을 향상시키거나 또는 미관을 향상시키기 위하여 작업장에 돌 종류를 미리 다수 늘어놓은 후, 패널 또는 매트형으로 돌을 고정한 것을 기중기 등을 이용하여 시공하는 방식의 스톤넷 공법(stone net)[랩스톤 공법(wrap stone)] 등이 활용되고 있다.Recently, in order to improve the workability or improve the aesthetics of slope protection construction, the Stonenet method is a method in which a large number of stone types are arranged in advance in a workshop, and then the stones are fixed by using a crane or the like. stone net) (wrap stone method) is used.

도 1에 도시된 바와 같이, 종래 기술에 의한 암석을 이용한 호안은, 중장비를 이용하여 토사면을 고르게 정지작업한 후, 부피가 큰 암석을 적층식으로 쌓아 올리되, 큰 암석과 암석사이의 공극에는 중간크기의 자갈 또는 작은 크기의 돌을 채워넣어 암석의 결속력을 증대시킴에 따라, 홍수시 풍랑 등으로 인해 사면으로 부터 암석의 흘러내림을 방지할 수 있다.As shown in Figure 1, the prior art rock using the prior art, even after stopping the soil surface using the heavy equipment, and stacked a large volume of rock stacked, but the gap between the large rock and rock In order to increase the cohesion of the rock by filling a medium-sized gravel or small size stone, it is possible to prevent the flow of rock from the slope due to storms and floods.

전술한 호안 구조는, 암석의 공극에 채워지는 자갈로 인해 어류, 조류 등의 서식처를 잃게되므로 이들에 의한 자연적인 정화기능 등이 상실되어 수질 또는 환경오염을 가속시키는 문제점을 갖는다.The above-described revetment structure loses habitats of fish, algae, etc. due to the gravel filled in the pores of the rock, and thus has a problem of accelerating water quality or environmental pollution due to the loss of its natural purification function.

또한, 유체가 암석 또는 하천 구조물에 접촉시 유체의 유속을 감쇠시키는 기능이 상실되어 유체의 유속에 의한 세굴현상을 초래하고, 일부 암석이 토사면으로 부터 이탈되는 경우 인접한 암석이 연쇄적으로 이탈되어 홍수시 제방이 무너져 발생되는 수해로 인해 귀중한 재산 및 인명피해를 초래하는 문제점을 갖는다.In addition, the fluid loses its ability to attenuate the flow velocity of the fluid when it is in contact with the rock or river structure, causing scour caused by the flow velocity of the fluid, and when some rocks are separated from the soil surface, adjacent rocks are separated in series. The flooding caused by the collapse of the embankment has the problem of causing valuable property and casualties.

도 2에 도시된 바와 같이, 종래 기술에 의해 암석을 이용하여 축조되는 호안구조물은, 중장비 등을 이용하여 토사면(1)을 고르게 정지작업한 후, 토사면(1)을 보호할 수 있도록 자연석(2)(일반적으로, 직경 300㎜임)에 앵커식 철심(3)(일반적으로, 직경 8㎜임)을 연결하여 적층형성 한다.As shown in FIG. 2, the revetment structure constructed by the rock according to the prior art is a natural stone so as to protect the soil surface 1 evenly after stopping the soil surface 1 using heavy equipment or the like. (2) Laminate is formed by connecting the anchor core 3 (generally, 8 mm in diameter) to (usually, 300 mm in diameter).

전술한 철심(3) 일단부에 지압판(4)을 연결하고, 드릴머시인에 의해서 자연석(2)에 천공된 고정공(5)과 고정공(5)에 결합되는 철심(3)에 접착제를 각각 도포한 후, 자연석(2)에 철심(3)을 고정한다.The pressure plate 4 is connected to one end of the iron core 3 described above, and the adhesive is attached to the iron core 3 coupled to the fixing hole 5 and the fixing hole 5 drilled in the natural stone 2 by a drill machine. After each application, the iron core 3 is fixed to the natural stone 2.

전술한 자연석(2)이 적층위치로 부터 이탈되는 것을 방지할 수 있도록 자연석(2)과 지압판(3)사이에 상대적으로 작은 크기의 잡석(5)을 채워넣는다.The natural stone 2 is filled with rubble 5 having a relatively small size between the natural stone 2 and the pressure plate 3 so as to prevent the natural stone 2 from being separated from the stacked position.

이로 인해, 전술한 토사면(1)으로 부터 자연석(2) 흘러내리는 것을 방지하여 토사면(1)을 풍수해(風水害)로 부터 보호할 수 있게 된다.Therefore, the natural stone 2 can be prevented from flowing down from the above-mentioned earth and sand surface 1, so that the earth and sand surface 1 can be protected from feng shui.

도면중 6은 필터매트이다.6 in the figure is a filter mat.

전술한 호안 구조물은, 앵커식 철심(3)에 자연석(2)을 고정시키는 접착제가 경화되어야만 다음 단계의 작업을 시작할 수 있어, 작업시간이 많이 소요되어 인건비 상승을 초래하며, 철심(3)이 고정공(5)으로 부터 쉽게 이완되어 재고정시키는 작업을 하게되므로 전체적인 공사비용이 증가되는 문제점을 갖는다.In the above-described shoreline structure, the adhesive for fixing the natural stone (2) to the anchor iron core (3) must be cured to start the next step of work, it takes a lot of work time, leading to a rise in labor costs, the iron core (3) Easily relaxed from the fixing hole (5) to work because of the re-establishment has a problem that the overall construction cost is increased.

또한, 자연석(2) 상호간의 결속력이 없게되므로 유속에 대한 저항력이 약하고, 유속에 대해 자연석(2)이 저항력을 갖도록 자연석(2)의 공극에 잡석 또는 콘크리트 등을 채워넣게 되므로, 하천수 유입시 유속을 감쇠시키지 못하여 유속의 반사작용으로 인한 수해피해를 초래하는 문제점을 갖는다.In addition, since there is no binding force between the natural stones (2), the resistance to the flow rate is weak, and the natural stone (2) is filled with rubble or concrete to fill the voids of the natural stone (2) to have a resistance to the flow rate, so the flow rate at the inflow of river water There is a problem that can not attenuate the damage caused by the reflection action of the flow rate.

이와 같이, 유속을 감쇠시키지 못하여 세굴을 초래하므로 홍수시 유속 및 토압에 의해 자연석(2)이 쉽게 무너지고, 골재가 유실되어 제방이 무너져 대형 수해사고를 초래하는 문제점을 갖는다.As such, because the flow rate does not attenuate and causes scour, the natural stone 2 easily collapses due to the flow rate and earth pressure during flooding, and the aggregates are lost to collapse the dike, resulting in a large flood accident.

또한, 자연석(2)사이의 공극에 채워진 잡석 등에 의해 동,식물이 서식하지 못해 수질오염을 초래하고, 하천제방 주변의 온도를 상승시키며, 대기중의 환경오염원을 증가시키는 문제점을 갖는다.In addition, due to the rubble filled in the pores between the natural stone (2), such as plants and plants do not inhabit, causing water pollution, raising the temperature around the river bank, and has a problem of increasing the environmental pollution source in the atmosphere.

본 고안의 목적은, 암석과 암석을 연결부재로서 일체형으로 연결하여 유속에 대한 저항력을 갖게되어 내구성을 증대시킬 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공함에 있다.It is an object of the present invention to provide a flow rate damping type relief structure using a cramp that has a resistance to the flow rate to increase the durability by integrally connecting the rock and the rock as a connecting member.

본 고안의 다른 목적은, 하천수와 접하는 위치에 설치되는 암석과 암석사이의 공극에 물의 유입공간을 확보함에 따라, 유체의 유속을 감쇠시켜 골재의 유실, 하천 쇄골 및 침식되는 것을 방지할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공하는 것이다.Another object of the present invention is to prevent the loss of aggregate, stream clavicle and erosion by attenuating the flow rate of the fluid by securing the water inflow space in the gap between the rock and the rock installed in the position in contact with the river water It is to provide a flow rate damping type relief structure using a clamp.

본 고안의 또 다른 목적은, 암석사이의 공극에 동물, 수목 또는 수초 등의 서식처를 제공할 수 있어 대기오염 또는 수질오염원을 줄여 쾌적한 도시환경을 제공할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공하는 것이다.Another object of the present invention is to provide a habitat, such as animals, trees or plants in the air gap between the rocks to reduce the air pollution or water pollution source to provide a comfortable urban environment to reduce the flow rate decay-type revetment To provide.

본 고안의 또 다른 목적은, 호안 구조물의 축조시 자연석은 물론 콘크리트 호안블럭에도 적용할 수 있어 범용적으로 사용할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공하는 것이다.Still another object of the present invention is to provide a flow rate damping type relief structure using a clamp that can be applied to natural stone as well as concrete relief block when constructing a relief structure.

본 고안의 또 다른 목적은, 암석과 암석을 일체형으로 연결하는 연결부재가 암석의 고정공으로 이탈되는 것을 방지할 수 있도록 한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공하는 것이다.Still another object of the present invention is to provide a flow rate damping type relief structure using a bracket so as to prevent the connecting member for integrally connecting the rock and the rock to escape from the fixed hole of the rock.

도 1은 종래 기술에 의한 호안을 나타내는 도면대용 사진,1 is a drawing substitute photograph showing a revetment according to the prior art,

도 2는 종래 기술에 의해 호안을 축조하는 제방공사시 암석을 고정하는 요부발췌확대도,Figure 2 is an enlarged view of the excerpts fixing the rock during embankment construction to build a revetment by the prior art,

도 3은 본 고안의 일 실시예에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물의 요부발췌확대도,3 is an enlarged excerpt of the excerpt of the flow rate damping type revetment structure using a clamp according to an embodiment of the present invention,

도 4는 본 고안에 의한 다른 실시예에 의한 꺽쇠를 이용한 유속 감쇠형 호안구조물의 요부발췌확대도,Figure 4 is an enlarged view of the excerpt excavation of the flow rate damping type relief eye relief using the clamp according to another embodiment of the present invention,

도 5는 본 고안에 의해 암석을 일체형으로 연결하는 꺽쇠의 변형예시도,Figure 5 is a modified example of the clamp to connect the rock integrally by the present invention,

도 6은 본 고안에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 시공하는 작업방법을 나타내는 흐름도이다.Figure 6 is a flow chart illustrating a work method for constructing a flow-rate damping type relief structure using a clamp according to the present invention.

*도면중 주요 부분에 사용된 부호의 설명* Explanation of symbols used in the main part of the drawing

10; 토사면10; Soil slope

11,12; 암석11,12; rock

13; 공극13; air gap

14,15; 고정공14,15; Fastener

16; 스토퍼16; stopper

A; 암석층A; Rock formation

B; 연결부재B; Connecting member

C; 잡석층C; Rubble

D; 세굴 방지부재D; Scour prevention member

전술한 본 고안의 목적은, 정지작업된 토사면에 적층형성되고, 암석과 암석사이에 출입되는 유체의 유속을 감쇠시키는 공극을 형성하는 암석층과,An object of the present invention described above, the rock layer is laminated on the suspended soil surface, and the rock layer to form a void to attenuate the flow rate of the fluid entering and going between the rock and the rock,

유속에 대해 저항력을 갖도록 암석에 천공된 고정공에 삽입되어 암석과 암석을 일체형으로 연결하며, 적층위치로 부터 암석의 이탈되는 것을 방지하도록 스토퍼가 단부에 형성되는 연결부재와,A connection member inserted into a fixed hole drilled in the rock so as to be resistant to the flow rate and integrally connecting the rock and the rock, and having a stopper formed at the end to prevent the rock from being separated from the stacked position;

토사면으로 부터 암석의 이탈되는 것을 방지하도록 암석층과 토사면사이에 채워지는 잡석층을 구비하는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 제공함에 의해 달성된다.It is achieved by providing a flow rate damping type relief structure using a cramp, characterized by having a rubble layer filled between the rock layer and the soil surface to prevent the rock from escaping from the soil surface.

바람직한 실시예에 의하면, 전술한 암석층과 잡석층사이에 설치되며, 유속으로 인해 골재 및 토사의 세굴을 방지하는 세굴 방지부재를 구비한다.According to a preferred embodiment, it is provided between the rock layer and the rubble layer described above, and has a scour prevention member that prevents scour of aggregate and soil due to the flow rate.

전술한 세굴 방지부재와 연결부재는 소정강도 및 내부식성을 갖도록 외주연이 아연도금 코팅처리된 금속재로 형성된다.The above-described scour prevention member and the connecting member are formed of a metal material whose outer periphery is galvanized to have a predetermined strength and corrosion resistance.

전술한 암석에 형성되는 고정공은 원뿔형 또는 원통형으로 형성된다.The fixing hole formed in the aforementioned rock is formed in a conical or cylindrical shape.

전술한 암석의 고정공에 결합되는 연결부재는 접착제, 앙카볼트 또는 쐐기형 연결구의 어느 하나에 의해 고정공에 고정된다.The connecting member coupled to the fixing hole of the rock is fixed to the fixing hole by any one of an adhesive, an anchor bolt or a wedge-shaped connector.

이하, 본 고안의 바람직한 실시예를 첨부도면을 참조하여 더욱 설명하되, 이는 본 고안이 속하는 기술 분야에서 통상의 지식을 가진 자가 고안을 용이하게 실시할 수 있을 정도로 상세하게 설명하기 위한 것이지, 이로 인해 본 고안의 기술적이 사상 및 범주가 한정되는 것을 의미하지는 않는 것이다.Hereinafter, a preferred embodiment of the present invention will be described in more detail with reference to the accompanying drawings, which is intended to describe in detail enough to be able to easily carry out the invention by those skilled in the art to which the present invention belongs, The technical spirit and scope of the present invention are not meant to be limited.

도 3 내지 도 5에 도시된 바와 같이, 본 고안에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물은, 소정각도로 정지작업된 토사면(10)에 적층형성되고, 암석(11)과 암석(12)사이에 출입되는 유체의 유속을 감쇠시키는 공극(13)을 형성하는 암석층(A)을 구비한다.As shown in Figures 3 to 5, the flow-rate damping type revetment structure using the bracket according to the present invention, is laminated on the soil surface 10 stopped at a predetermined angle, the rock 11 and the rock 12 The rock layer A which forms the space | gap 13 which attenuates the flow velocity of the fluid which flows in and out between is provided.

유속에 대해 저항력을 갖도록 암석(11,12)에 원뿔형 또는 원통형으로 천공된 고정공(14,15)에 삽입되어 암석(11)과 암석(12)을 일체형으로 연결하며, 적층위치로 부터 암석(11,12) 이탈되는 것을 방지하도록 스토퍼(16)가 단부에 형성되는 연결부재(B)를 구비한다.It is inserted into the fixed holes (14, 15) perforated in a conical or cylindrical shape in the rock (11, 12) to have a resistance against the flow rate to connect the rock (11) and the rock (12) integrally, and from the stacked position 11 and 12, the stopper 16 is provided with a connecting member (B) formed at the end to prevent the separation.

이때, 전술한 연결부재(B)는 "ㄷ"형, "U"형, "E"형, "W"형, "V"형 등으로 다양하게 변형실시할 수 있음은 물론이다.At this time, the above-described connection member (B) can be variously modified to "C" type, "U" type, "E" type, "W" type, "V" type and the like.

토사면(10)으로 부터 암석(11,12)의 이탈되는 것을 방지하도록 암석층(A)과 토사면(10)사이에 채워지는 잡석층(C)과, 전술한 암석층(A)과 잡석층(C)사이에 설치되며 유속으로 인해 골재 및 토사의 세굴을 방지하는 세굴 방지부재(D)를 구비한다.Rubble layer (C) which is filled between the rock layer (A) and the soil surface 10 to prevent the separation of the rocks (11, 12) from the soil surface (10), the above-described rock layer (A) and rubble layer ( C) is installed between and provided with a scour prevention member (D) to prevent scour of the aggregate and soil due to the flow rate.

이때, 전술한 세굴 방지부재(D)와 연결부재(B)는 소정강도 및 내부식성을 갖도록 외주연이 아연도금 코팅처리된 금속재로 형성된다.At this time, the above-described scour prevention member (D) and the connection member (B) is formed of a metal material whose outer periphery is galvanized coating so as to have a predetermined strength and corrosion resistance.

전술한 암석(11,12)의 고정공(14,15)에 결합되는 연결부재(B)는 접착제, 앙카볼트 또는 쐐기형 연결구의 어느 하나에 의해 고정공(14,15)에 고정된다.The connecting member B coupled to the fixing holes 14 and 15 of the rock 11 and 12 is fixed to the fixing holes 14 and 15 by any one of an adhesive, an anchor bolt or a wedge-shaped connector.

본 고안에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물을 축조하는 과정을 첨부도면을 참조하여 상세하게 설명한다.With reference to the accompanying drawings will be described in detail the process of constructing a flow-rate damping type revetment structure using a clamp according to the present invention.

도 6에 도시된 바와 같이, 하천 제방의 토사면(10)을 소정의 중장비를 이용하여 다진후 표면을 고르게 정지(整地)작업한다(S100 참조).As shown in FIG. 6, the soil surface 10 of the river bank is chopped using a predetermined heavy equipment, and then the surface is stopped evenly (see S100).

정지작업된 토사면(10)위에 집게 기능을 갖는 전용 중장비에 의해 운반되어고르게 놓여지는 크고 작은 암석(11,12)에 소정의 드릴 머시인을 이용하여 고정공(14,15)을 원뿔형(또는, 원통형으로 형성됨)으로 각각 천공한다(S200 참조).The fixed holes 14, 15 are conical (or fixed) using predetermined drill machines on the large and small rocks 11 and 12, which are carried evenly by the dedicated heavy machinery having a tongs function on the suspended soil surface 10. Perforated into a cylindrical shape) (see S200).

이때, 암석(11,12)을 토사면(10)위에 올려놓은 후 유동하지않도록 서로 연결하게되어 시공성이 향상됨은 물론이다.At this time, the rock (11, 12) is placed on the soil surface 10 and connected to each other so as not to flow, of course, the workability is improved.

전술한 원뿔형 고정공(14,15)에 연결부재(B)의 소켓부(b)를 강제적으로 삽입시킴에 따라, 복원력에 의해 소켓부(b)가 고정공(14,15) 내부에서 외측으로 확장되어 벌어진다.As the socket portion b of the connecting member B is forcibly inserted into the conical fixing holes 14 and 15 described above, the socket portion b is moved from the inside of the fixing holes 14 and 15 to the outside by the restoring force. Expands and opens

이로 인해, 소켓부(b)는 고정공(14,15)에 결합된 후 이탈되는 것이 방지되므로 연결부재(B)에 의해 암석(11)과 암석(12)을 일체형으로 연결한다(S300 참조).For this reason, since the socket part b is prevented from being separated after being coupled to the fixing holes 14 and 15, the rock part 11 and the rock 12 are integrally connected by the connecting member B (see S300). .

암석(11)과 암석(12)를 연결부재(B)를 일체형으로 연결함에 따라 유속에 대해 저항력을 갖게 되므로 호안구조물의 내구성을 갖는다.Since the rock 11 and the rock 12 are integrally connected to the connecting member B, the rock 11 and the rock 12 have resistance to the flow rate, thereby having durability of the revetment structure.

전술한 암석(11,12)에 고정공(14,15)을 천공한 후 연결부재(B)를 고정하여다음 단계의 작업을 할 수 있어 공사 기간을 단축할 수 있음은 물론이다.After drilling the fixing holes (14, 15) in the above-described rock (11, 12) can be fixed to the connecting member (B) to perform the next step of course can shorten the construction period.

전술한 연결부재(B)에 의해 일체형으로 연결되는 암석(11)과 암석(12)을 토사면(10)에 적층형성하되, 암석(11)과 암석(12)사이에 형성되는 공극(13)에 의해 암석 또는 하천구조물에 접촉되는 유체의 유속을 감쇠시킴에 따라, 유속으로 인한 세굴을 방지할 수 있다(S400 참조).The rock 11 and the rock 12 which are integrally connected by the aforementioned connection member B are laminated on the soil surface 10, and the void 13 is formed between the rock 11 and the rock 12. By attenuating the flow rate of the fluid in contact with the rock or river structure by, it is possible to prevent scour due to the flow rate (see S400).

풍랑 등으로 인해 적층위치로 부터 암석(11,12) 이탈되는 것을 방지할 수 있도록 전술한 토사면(10)과 암석(11,12)사이에 상대적으로 작은 크기의 잡석층(C)을 채워넣는다(S500 참조). 즉 연결부재(B)와 연결부재(B)의 단부에 형성되는 스토퍼(16)를 잡석층(C)에 의해 압착 및 짓눌림하게 되므로 암석(11,12)의 이탈되는 것을 방지할 수 있다.Fill the rubble layer C having a relatively small size between the above-described soil surface 10 and the rocks 11 and 12 so as to prevent the rocks 11 and 12 from being separated from the stacking position due to the storm. (See S500). That is, since the stopper 16 formed at the end of the connecting member B and the connecting member B is squeezed and crushed by the rubble layer C, separation of the rocks 11 and 12 can be prevented.

한편, 전술한 암석(11,12)과 잡석층(C)사이에 설치되는 세굴 방지부재(D)에 의해 유체의 유속으로 인해 골재 및 토사면(10)의 세굴되는 것을 방지할 수 있다(S450 참조).On the other hand, by the scour prevention member (D) provided between the rock (11, 12) and the rubble layer (C) described above can be prevented from scouring the aggregate and the soil surface 10 due to the flow rate of the fluid (S450). Reference).

한편, 본 고안에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물은 전술한 암석은 물론, 콘크리트 호안블럭에 적용될 수 있고, 이에 대한 상세한 설명은 암석에 이용되는 기술내용과 실질적으로 동일하게 적용되므로 생략함을 밝혀둔다.On the other hand, the flow rate damping type relief structure using the clamp according to the present invention can be applied to the concrete relief block as well as the above-described rock, the detailed description thereof will be omitted because it is applied substantially the same as the technical content used in the rock. Reveal.

이상에서와 같이, 본 고안에 의한 꺽쇠를 이용한 유속 감쇠형 호안 구조물은 아래와 같은 이점을 갖는다.As described above, the flow rate damping type relief structure using the clamp according to the present invention has the following advantages.

암석과 암석을 꺽쇠로서 일체형으로 연결하여 유속에 대한 저항력을 갖게되어 내구성을 증대시키므로 유지관리비용을 절감할 수 있다.It is possible to reduce the maintenance cost by increasing the durability by having the resistance to the flow rate by connecting the rock and the rock as an integral type.

하천수와 접하는 위치에 설치되는 암석과 암석사이의 공극에 물의 유입공간을 확보함에 따라, 유체의 유속을 감쇠시켜 골재의 유실, 하천 쇄골 및 침식되는 것을 방지할 수 있다.As the water inflow space is secured in the gap between the rock and the rock installed at the position contacting the river water, it is possible to prevent the loss of the aggregate, stream clavicle and erosion by attenuating the flow rate of the fluid.

암석사이의 공극에 동물, 수목 또는 수초 등의 서식처를 제공할 수 있어 대기오염 또는 수질오염원을 줄여 쾌적한 도시환경을 제공할 수 있다.It can provide habitats such as animals, trees or plants to the air gap between the rocks, thereby providing a pleasant urban environment by reducing air pollution or water pollution sources.

호안 구조물의 축조시 자연석은 물론 콘크리트 호안블럭에도 적용하여 범용적으로 사용할 수 있다.When constructing a revetment structure, it can be used universally by applying to natural stone as well as concrete revetment block.

암석과 암석을 일체형으로 연결하는 연결부재가 암석의 고정공으로 이탈되는 것을 방지함에 따라 이를 재고정시 발생되는 비용을 절감할 수 있다.As the connection member connecting the rock and the rock in one piece is prevented from being separated by the fixing hole of the rock, it is possible to reduce the cost incurred when resetting it.

Claims (6)

정지작업된 토사면에 적층형성되고, 암석과 암석사이에 출입되는 유체의 유속을 감쇠시키는 공극을 형성하는 암석층;A rock layer laminated on the stationary soil surface, the rock layer forming voids to attenuate the flow velocity of the fluid entering and leaving the rock; 유속에 대해 저항력을 갖도록 상기 암석에 천공된 고정공에 삽입되어 상기 암석과 암석을 일체형으로 연결하며, 적층위치로 부터 상기 암석의 이탈되는 것을 방지하도록 스토퍼가 단부에 형성되는 연결부재; 및A connection member inserted into a fixed hole drilled in the rock to have a resistance against a flow rate and integrally connecting the rock and the rock, and having a stopper formed at an end portion thereof to prevent the rock from being separated from the stacked position; And 상기 토사면으로 부터 상기 암석의 이탈되는 것을 방지하도록 상기 암석층과 토사면사이에 채워지는 잡석층을 구비하는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.And a rubble layer filled between the rock layer and the soil surface to prevent the rock from being separated from the soil surface. 청구항 1에 있어서, 상기 암석층과 잡석층사이에 설치되며, 유속으로 인해 골재 및 토사의 세굴을 방지하는 세굴 방지부재를 구비하는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.The flow rate damping type relief structure using a clamp according to claim 1, wherein the rock layer is provided between the rock layer and the rubble layer, and has a scour prevention member that prevents scour of aggregate and soil due to the flow rate. 청구항 2에 있어서, 상기 세굴 방지부재는 소정강도 및 내부식성을 갖도록 외주연이 아연도금 코팅처리된 금속재로 형성되는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.The method of claim 2, wherein the scour prevention member is a flow rate damping type relief structure using a clamp, characterized in that the outer periphery is formed of a galvanized coating metal material to have a predetermined strength and corrosion resistance. 청구항 1 또는 청구항 2에 있어서, 상기 연결부재는 소정 강도 및 내부식성을 갖도록 외주연이 아연도금 코팅처리된 금속재로 형성되는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.The method of claim 1 or claim 2, wherein the connecting member is a flow rate damping type relief structure using a clamp, characterized in that the outer periphery is formed of a galvanized metal material to have a predetermined strength and corrosion resistance. 청구항 1 또는 청구항 2에 있어서, 상기 암석에 형성되는 고정공은 원뿔형 또는 원통형으로 형성되는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.The method of claim 1 or claim 2, wherein the fixing hole formed in the rock is a flow rate damping type relief structure using a cramp, characterized in that formed in a conical or cylindrical. 청구항 1 또는 청구항 2에 있어서, 상기 암석의 고정공에 결합되는 상기 연결부재는 접착제, 앙카볼트 또는 쐐기형 연결구의 어느 하나에 의해 상기 고정공에 고정되는 것을 특징으로 하는 꺽쇠를 이용한 유속 감쇠형 호안 구조물.The method according to claim 1 or 2, wherein the connecting member coupled to the fixing hole of the rock is fixed to the fixing hole by any one of an adhesive, an anchor bolt or a wedge-shaped connector, the flow rate damping type relief using a cramp structure.
KR20-2003-0036457U 2003-11-21 2003-11-21 shore protection structure of using cramp KR200342365Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2003-0036457U KR200342365Y1 (en) 2003-11-21 2003-11-21 shore protection structure of using cramp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2003-0036457U KR200342365Y1 (en) 2003-11-21 2003-11-21 shore protection structure of using cramp

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020030083103A Division KR101147143B1 (en) 2003-11-21 2003-11-21 shore protection structure and construction method of using cramp

Publications (1)

Publication Number Publication Date
KR200342365Y1 true KR200342365Y1 (en) 2004-02-18

Family

ID=49425036

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2003-0036457U KR200342365Y1 (en) 2003-11-21 2003-11-21 shore protection structure of using cramp

Country Status (1)

Country Link
KR (1) KR200342365Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210021212A (en) * 2019-08-16 2021-02-25 주식회사 동해종합기술공사 Green sloping ground eco-friendly Gavion structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210021212A (en) * 2019-08-16 2021-02-25 주식회사 동해종합기술공사 Green sloping ground eco-friendly Gavion structure
KR102259673B1 (en) * 2019-08-16 2021-06-03 주식회사 동해종합기술공사 Green sloping ground eco-friendly Gavion structure

Similar Documents

Publication Publication Date Title
KR100817471B1 (en) Stone net for river bulkhead and this construction technique
KR100993335B1 (en) Revetment protection works using gabion and construction method thereof
CN103233444B (en) Underwater dumped rockfill bedding and side slope Anti-scouring structure and construction method thereof
KR100554867B1 (en) Method for soil erosion control works or shore protection works and structure for soil protection or shore protection
WO2003089720A1 (en) Method for constructing check dam or fire prevention dam using gear-type block
JP2002105928A (en) Revetment block and slope face construction method using the same
KR101059140B1 (en) Gabion Leg with Gabion
KR200342365Y1 (en) shore protection structure of using cramp
KR101147143B1 (en) shore protection structure and construction method of using cramp
JP3728725B2 (en) River bed structure and river bed protection method
KR100737109B1 (en) Interlinkage erosion shield system of block which has space and the mobile passage of fish
KR100743550B1 (en) Scour prevention block
KR100631385B1 (en) construction method of nature embankment
JP2005214006A (en) River bed structure
KR101684340B1 (en) Scour protection system for shore and its installation methods
RU2317369C1 (en) Method for river bank consolidation
KR100461664B1 (en) Structures and system of construction based on the use of plants growing block that protect a shore
KR100691502B1 (en) The scour part repair method of a underwater structure of having used scour prevention member for underwater structures, and this
KR200369898Y1 (en) Scour prevention member for underwater structures
KR200429763Y1 (en) Scour prevention block
KR200327410Y1 (en) Fastener for protect the banks block
KR100434196B1 (en) Guard structure for using in the slope of the bank
KR200410822Y1 (en) Eco block executive construction
KR102548639B1 (en) Construction method of upper net binding type stone protection structure
KR200311996Y1 (en) Fiber stone unit

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20111205

Year of fee payment: 9

EXTG Extinguishment