KR20030097029A - 자동배관 설비방법 - Google Patents
자동배관 설비방법 Download PDFInfo
- Publication number
- KR20030097029A KR20030097029A KR1020020034156A KR20020034156A KR20030097029A KR 20030097029 A KR20030097029 A KR 20030097029A KR 1020020034156 A KR1020020034156 A KR 1020020034156A KR 20020034156 A KR20020034156 A KR 20020034156A KR 20030097029 A KR20030097029 A KR 20030097029A
- Authority
- KR
- South Korea
- Prior art keywords
- pipe
- unit
- welding
- spool
- pipes
- Prior art date
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/17—Mechanical parametric or variational design
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L37/00—Couplings of the quick-acting type
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2113/00—Details relating to the application field
- G06F2113/14—Pipes
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- General Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Pure & Applied Mathematics (AREA)
- Mathematical Optimization (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Mathematical Analysis (AREA)
- Computational Mathematics (AREA)
- Mechanical Engineering (AREA)
- General Factory Administration (AREA)
Abstract
Description
Claims (10)
- 산업용 배관을 설비하는 방법에 있어서,배관에 필요한 도면을 분석하여 필요한 단위관체를 분석하고, 분석한 단위관체가 보관하고 있는 자재용 단위관체가 해당 스풀(조립 가능한 단위 배관)로 조립 가능한지를 확인하는 예비 단계(P1);예비 단계(P1)에서 도면에 필요한 단위관체가 보관중인 단위관체보다 작은 스풀 중에서 해당 스풀별 배관에 필요한 단위관체를 배관설계 데이터(도면)를 기초로 제조하도록 파이프 원자재 길이와 잔재를 설정하는 제 1 단계(S1);저장한 단위관체 데이터를 기초로 작업에 필요한 양만큼 재료 손실이 없도록 소팅하는 제 2 단계(S2);소팅한 데이터를 기초로 엔시데이터를 로딩하여 파이프 원자재를 단위관체로 커팅 후 다음 단계로 이송하는 제 3 단계(S3);절단한 단위 관체를 이송 받아 위치, 개수 및 사양을 인식하여 용접 가능토록 내외주면 모서리 및 양 단면을 가공하여 다음 단계로 이송하는 제 4 단계(S4);가공한 단위 관체를 구분 인식하여 일차 스포트 용접하여 배관 형태를 완성하는 제 5 단계(S5);예비 완성한 배관 형태의 용접 부위의 모재에 맞는 용접 조건으로 용접하는 제 6 단계(S6)를 순차 수행하는 것을 특징으로 하는 자동배관 설비방법.
- 제 1 항에 있어서, 예비 단계(P1)는 도면의 단위관체와 파이프 원자재로 수득 예상되는 단위관체의 수량을 확인하는 제 01단계(P01)와,제 01단계(P01)에서 확인한 수량을 기초로 실 수득 자재용 단위관체가 부족한지 비교하는 제 02단계(P02)와,부족하지 않고 남을 경우 오케이 표시(T)를 해당 스풀에 기록하고 다음 스풀을 다시 확인하는 과정을 마지막 스풀 까지 반복하는 제 03단계(P03)와,스풀별로 오케이 표시(T)가 있는 스풀만 필터링 하는 제 04단계(P04)를 순차 수행하는 것을 특징으로 하는 자동 배관 설비방법.
- 제 2 항에 있어서, 제 01 단계(P01)는 도면에 근거한 단위관체의 수량을 확인하는 제 0100 단계(P0100)와, 파이프 원자재를 기초로 수득 예상하는 단위관체의 수량을 확인하는 제 0120단계(P0120)로 구분하여 동시에 병행 수행함을 특징으로 하는 자동배관 설비방법.
- 제 3 항에 있어서, 제 0100 단계(P0100)는 사용할 자재관체 데이터를 도면에서 분석 하는 자동입력 또는, 수동으로 입력받는 단계(P0110)와,스풀 제작용 우선순위 번호를 지정하는 단계(P0111)와,지정한 우선 순위별로 소팅하는 단계(P0112)와,순차적으로 하나의 스풀에 해당하는 자재관체의 리스트를 선택하는단계(P0113)와,선택한 리스트를 기초로 해당하는 자재관체의 수량을 지정하는 단계(P0114)를 순차 수행함을 특징으로 하는 자동배관 설비방법.
- 제 3 항에 있어서, 제 0120 단계(P0120)는 사용할 자재관체의 재고량을 자재데이터에서 자동으로 또는 수동으로 입력받는 단계(P0121)와,입력받은 자재관체의 사이즈 및 종류별 수량을 합산하여 중복입력된 아이템의 수량을 자재별로 구분 합산하는 단계(P0122)합산한 자재관체의 자재별로 재고량을 지정하는 단계(P0123)을 순차 수행함을 특징으로 하는 자동배관 설비방법.
- 제 2 항에 있어서, 상기 단계(P02)는 도면상의 자재를 지정하는 단계(P0100)로부터 지정받은 자재(A_S_QTY)와, 소요자재의 재고량(A_I_QTY)을 파악하여 비교값이 마이너스가 되었을 때 실행을 취소토록 하는 기준 시점을 정하는 단계(P021)와,기준 시점에 따라 재고량에서 도면에 필요항 소요량의 차가 제로 미만일 때 스풀별로 해당하는 스풀의 진행을 취소시켜 상기 단계(P0113)에서 다른 스풀의 자재관체를 선택토록 하며, 제로 이상일 때 다음 단계(P03)를 수행하는 것을 특징으로 하는 자동배관 설비방법.
- 제 1 항에 있어서, 제 3 단계(S3)는 절단할 데이터를 제공받아(S31), 파이프 원자재를 크립하는 척을 가지고 절단할 단위관체의 길이만큼 이송을 하고(S32), 캐리지 이송이 완료된 후에 커팅을 수행하도록 커팅기를 구동한 후 커팅한 자재를 콘베이어로 이송하는 단계(S33)을 순차 수행함을 특징으로 하는 자동배관 설비방법.
- 제 1 항에 있어서, 제 4 단계(S4)는 단위관체를 인식하여 일단을 1차 크램프하여 나머지 단부의 내주면과 외주면 및 단면부를 동시에 1차 용접개선(facing)가공을 하고(S41), 이어 가공한 단면을 2차 크램프하고, 1차크램프한 부분을 2차 용접개선 하는 한 후 콘베이어로 이송하는 단계(S42)를 수행함을 특징으로 하는 자동배관 설비방법.
- 제 1 항에 있어서, 제 5 단계(S5)는 용접개선한 단위관체를 배관 설계에 맞게 정렬하여 확인한 다음 용접 지그에 안치시키고(S51,S52),안치시킨 상태에서 크램프하여 스포트 웰딩하여 태그웰딩을 수행한 후,2차 웰딩부로 이송토록 하는 단계(S53,S54)를 수행함을 특징으로 하는 자동배관 설비방법.
- 제 1 항에 있어서, 제 6 단계(S6)는 1차 웰딩한 배관 1차 용접 부위의 대응 단위관체를 크램프 하고(S61), 단위관체의 사양을 인식하여 해당하는 사양으로 웰딩을 용접부위마다 하고(S62), 단위 구간마다 용접이 완료되면 콘베이어로 순차 이송하는 단계(S63)를 수행함을 특징으로 하는 자동배관 설비방법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2002-0034156A KR100444548B1 (ko) | 2002-06-18 | 2002-06-18 | 자동 배관 설비방법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2002-0034156A KR100444548B1 (ko) | 2002-06-18 | 2002-06-18 | 자동 배관 설비방법 |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20030097029A true KR20030097029A (ko) | 2003-12-31 |
KR100444548B1 KR100444548B1 (ko) | 2004-08-16 |
Family
ID=32387602
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2002-0034156A KR100444548B1 (ko) | 2002-06-18 | 2002-06-18 | 자동 배관 설비방법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100444548B1 (ko) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102043278B1 (ko) * | 2019-05-02 | 2019-11-11 | (주)디노 | 플랜트 시공 지원 방법 및 시스템 |
CN112131637A (zh) * | 2020-09-09 | 2020-12-25 | 武汉市汉阳市政建设集团有限公司 | 一种基于bim技术的变曲率弧形管道预制加工安装方法 |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101169038B1 (ko) * | 2004-08-02 | 2012-07-26 | 글로벌파운드리즈 인크. | 예외 상황들을 해소하기 위해 재료에 우선순위를 정하기위한 방법 및 시스템 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06325134A (ja) * | 1993-05-14 | 1994-11-25 | Toda Constr Co Ltd | 鉄骨建方計画図の自動作成方法 |
KR0134283B1 (ko) * | 1994-10-06 | 1998-05-15 | 김공 | 데이터 방식에 기초한 배관 요소의 설계 방법 |
KR0173892B1 (ko) * | 1995-10-24 | 1999-04-01 | 정순착 | 용접철망 단위 모듈의 자동설계 방법 |
JPH1040282A (ja) * | 1996-07-26 | 1998-02-13 | Mitsubishi Electric Corp | アイソメトリック図作成編集装置およびその方法 |
JP3846945B2 (ja) * | 1996-10-07 | 2006-11-15 | 千代田化工建設株式会社 | 配管生産計画管理装置 |
KR100368004B1 (ko) * | 1999-06-07 | 2003-01-14 | 주식회사 제이.이.씨 | 배관 설계에 사용되는 아이소메트릭 및 스풀 도면, 및 자재 명세서 자동 작성 장치 및 방법 |
-
2002
- 2002-06-18 KR KR10-2002-0034156A patent/KR100444548B1/ko active IP Right Grant
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102043278B1 (ko) * | 2019-05-02 | 2019-11-11 | (주)디노 | 플랜트 시공 지원 방법 및 시스템 |
CN112131637A (zh) * | 2020-09-09 | 2020-12-25 | 武汉市汉阳市政建设集团有限公司 | 一种基于bim技术的变曲率弧形管道预制加工安装方法 |
CN112131637B (zh) * | 2020-09-09 | 2024-04-02 | 武汉市汉阳市政建设集团有限公司 | 一种基于bim技术的变曲率弧形管道预制加工安装方法 |
Also Published As
Publication number | Publication date |
---|---|
KR100444548B1 (ko) | 2004-08-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1727008B1 (en) | Device and method for correcting taught points in a robot program | |
US4998206A (en) | Automated method and apparatus for fabricating sheet metal parts and the like using multiple manufacturing stations | |
CN106334944B (zh) | H型钢工件智能生产线 | |
CN103476543A (zh) | 管子相互定位的方法 | |
Zhang et al. | Operational dimensioning and tolerancing in process planning: setup planning | |
CN210172874U (zh) | 一种转向架构架自动化焊接系统 | |
KR100444548B1 (ko) | 자동 배관 설비방법 | |
CN111438534A (zh) | 管道焊接成套自动化系统 | |
CN110549188B (zh) | 基于叠合量检测的阀芯同步磨削去毛刺一体化方法及系统 | |
CN111872704A (zh) | 一种具有高柔性高效率的管子生产线 | |
Zhang et al. | Operational dimensioning and tolerancing in CAPP | |
KR20150072896A (ko) | Cnc 머신을 포함한 it 융합형 자동화 라인 모니터링 시스템 | |
US5471394A (en) | Method for defining machining areas of a workpiece | |
KR20190093732A (ko) | Cnc 머신을 결합한 it융합형 자동화라인 모니터링 방법 | |
KR20200000782A (ko) | 공작기계 가공 깊이 자동제어 방법 | |
KR20200093471A (ko) | Cnc 장치를 이용한 공정 자동화 시스템 | |
CN220679710U (zh) | 一种bim钢结构管件预制装置 | |
KR102594493B1 (ko) | 배관스풀 자동제조 시스템 | |
KR102643024B1 (ko) | 레이저 가공방법 | |
US20230405743A1 (en) | Piping spool auto manufacturing system | |
CN108747363A (zh) | 一种水泵座全自动化加工装置及工艺 | |
KR102580394B1 (ko) | 로봇팔용 터닝 그립퍼모듈 및 이를 이용한 허브 가공방법 | |
CN113798140B (zh) | 一种自动生产线 | |
JPS6128470B2 (ko) | ||
CN110449789B (zh) | 一种自适应焊接装置及方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20120806 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20130805 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20140805 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20150805 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20160608 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20170801 Year of fee payment: 14 |
|
FPAY | Annual fee payment |
Payment date: 20180802 Year of fee payment: 15 |