KR200279711Y1 - Distributing board for having the construction of work and repair road - Google Patents

Distributing board for having the construction of work and repair road Download PDF

Info

Publication number
KR200279711Y1
KR200279711Y1 KR2020020008430U KR20020008430U KR200279711Y1 KR 200279711 Y1 KR200279711 Y1 KR 200279711Y1 KR 2020020008430 U KR2020020008430 U KR 2020020008430U KR 20020008430 U KR20020008430 U KR 20020008430U KR 200279711 Y1 KR200279711 Y1 KR 200279711Y1
Authority
KR
South Korea
Prior art keywords
work
switchgear
maintenance
low
vertical
Prior art date
Application number
KR2020020008430U
Other languages
Korean (ko)
Inventor
장세용
Original Assignee
주식회사 베스텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 베스텍 filed Critical 주식회사 베스텍
Priority to KR2020020008430U priority Critical patent/KR200279711Y1/en
Application granted granted Critical
Publication of KR200279711Y1 publication Critical patent/KR200279711Y1/en

Links

Abstract

본 고안은 저압배전반과 특고압 배전반을 전, 후로 복합되게 설치하는 축소형배전반의 구조를 개량한 것으로 저압배전반의 일측 하반부에 작업과 보수를 위한 보수로를 형성하고 이러한 보수로 내부에는 투명 수직절연안전판 구조를 형성하며, 그 상부와 후면부에도 역시 착탈식 구조의 안전커버를 형성하여 평상시에는 작업 및 보수자를 안전하게 보호하면서 또한 배전반의 설치 시공과 보수시에는 일정한 작업공간을 확보할 수 있는 축소형배전반에 관한 것으로 본 고안은 저압배전반의 함체 내부를 4개의 공간실로 각기 구획 형성하되 공간실(8a)에는 기중차단기로 인입되는 1차측 저압모선부(9)와 2차측 저압모선부(10)를 공지와 같이 구성하고, 공간실(8b)에는 기중차단기(11)를 구성하며, 공간실(8c)에는 저압수직모선부(12)와 브레커(13)를 설치하되 공간실(8d)의 입구측에는 보수문(16)에 의한 진입공간부 (17)을 형성하였고, 그 내부의 공간실(8d)은 작업 및 보수통로(18)가 되게 하며 작업 및 보수통로(18)와 저압수직모선부(12)의 사이에는 투명한 재질의 수직절연안전판(19)을 브라켓(20)(20')에 체결하고, 작업 및 보수통로(18)의 상부와 다른 내벽은 각각의 안전커버(23)(24)를 착탈식으로 체결하여 된 것이다.The present invention is an improvement of the structure of the miniature switchgear which installs the low-voltage switchgear and the special high-voltage switchgear in front and back, and forms a repair path for work and repair on one side of the low voltage switchgear and transparent vertical insulation inside the repair road. It forms a safety plate structure, and the upper and rear parts also have a removable safety cover to protect work and maintenance workers in normal times, and to reduce the size of the switchgear to secure a certain working space during installation and repair of the switchboard. The present invention is to form the compartment inside the compartment of the low-voltage switchgear into four space chambers, respectively, but the primary side low-pressure bus unit 9 and the secondary-side low-pressure bus unit 10 which is introduced into the air circuit breaker in the space chamber (8a) In the same manner, the air circuit breaker 11 is configured in the space chamber 8b, and the low pressure vertical busbar portion 12 and the breaker 13 are installed in the space chamber 8c. On the inlet side of the seal 8d, an entry space 17 is formed by the repair door 16. The space 8d therein becomes the work and maintenance passage 18 and the work and maintenance passage 18. And a vertical insulating safety plate 19 made of a transparent material are fastened to the brackets 20 and 20 'between the low pressure vertical busbar part 12 and the upper part of the work and maintenance passage 18 and the other inner wall of each of the safety cover. (23) (24) is made by detachably fastening.

Description

작업 및 보수로의 구조를 갖는 축소형배전반{Distributing board for having the construction of work and repair road}Distributing board for having the construction of work and repair road}

본 고안은 저압배전반과 특고압 배전반을 전, 후로 복합되게 설치하여 배전반의 설치면적을 최소화시키는 축소형배전반의 구조를 개량한 것으로 저압배전반의 일측 하반부에 작업과 보수를 위한 작업자의 인입로를 형성하고 이러한 보수로 내부의 전면부에는 투명 수직절연안전판 구조를 형성하며, 그 상부와 후면부에는 착탈식 구조의 안전커버를 형성하여 평상시에는 작업 및 보수자를 보호하면서 또한 배전반의 설치에 따른 배선작업 및 각종 전기 기기의 보수시에는 일정한 작업공간을 확보할 수 있도록 한 작업 및 보수로의 구조를 갖는 축소형배전반에 관한 것이다.The present invention improves the structure of the miniature switchgear by minimizing the installation area of the switchgear by installing the low-voltage switchgear and the special high-pressure switchgear in front and rear, and forming a worker's inlet for work and repair on the lower half of the low-voltage switchgear. In this repair, a transparent vertical insulating safety plate structure is formed on the inside of the front part, and a safety cover of a detachable structure is formed on the upper part and the rear part to protect work and maintenance workers in normal times, and also wiring work and various electricity according to the installation of switchboard. The maintenance of the equipment relates to a compact switchgear having a structure of work and maintenance paths to ensure a constant working space.

주지하는 바와 같이 전기의 사용량이 날로 증가함에 따라 전기의 설비가 대형화되고 첨단화되고 있으며 또한 배전반(수,배전장치)의 설비 역시 대형화되고 있는 현실이다.As is well known, as the use of electricity increases day by day, the facilities of electricity are becoming larger and more advanced, and the facilities of switchboards (water and distribution devices) are also becoming larger.

즉, 전기 수용가의 대형화에 부응하기 위하여 배전반은 수전부, 변압부, 배전부, 정류부 등이 열반되었을 때에는 각 단위 함체가 다수개로 하여 일렬로 열반하게 되는데 이러한 상태로 설치하기 위하여는 배전반의 전체적인 크기가 필요 이상으로 확대되며 또한 실내에 설치시에는 설치면적을 많이 차지하게 되는 관계로공간활용에 문제점이 있었다.That is, in order to meet the increase in the size of the electric consumer, when the power unit, the transformer unit, the power distribution unit, and the rectifier unit are enclosed, each unit enclosure is enclosed in a row, and in order to install in this state, the overall size of the switchboard Was enlarged more than necessary, and when installed indoors, there was a problem in space utilization because it occupies a lot of installation area.

따라서 이러한 열반식 배전반의 문제점에 의하여 요즈음에는 배전반 단위함체를 전, 후로 배치하되 전면부에는 다수개의 함체를 연결하여 저압배전반을 구성하고, 후면부에도 역시 다수의 함체로 특고압배전반을 구성하여 일체화한 소위 축소형배전반이 널리 공급되어 사용되고 있는 현실이다.Therefore, due to the problem of these nirvana type switchgear, the switchgear unit enclosures are arranged before and after these days, but a plurality of enclosures are connected to the front part to form a low voltage switchgear, and a plurality of enclosures also constitute a special high voltage switchgear to the rear part. So-called miniature switchgear is a widely supplied and used reality.

그러나 이와 같은 구조의 축소형배전반은 측면에서 보았을 때 2개의 단위 함체가 전, 후로 서로 밀착된 배치 구조이기 때문에 최초 배전반의 설치 작업을 할 때에는 각 단위 함체에 있는 전기 기기의 배선작업 및 기타의 설치작업을 위한 작업자의 진입 공간부를 확보할 수 없기 때문에 이러한 작업공간의 확보를 위하여 함체의 전면부에 형성된 개폐문을 열고 그 내부에 고정 설치된 전기 기기를 해체하여 밖으로 인출한 후 일정한 공간을 확보한 뒤 이 공간으로 작업자가 진입하여 설치 및 배선작업 등을 수행한 후 다시 전기 기기를 함체 내의 원위치로 인입하여 조립하여야 하는 등 설치작업의 불편성과 비능률성을 가지고 있었다.However, since the structure of the miniature switchgear has a structure in which two unit enclosures are in close contact with each other from the side, when the initial switchboard is installed, wiring work and other installations of electrical equipment in each unit enclosure are performed. Since it is impossible to secure the entry space of the worker for the work, to secure such a work space, the opening and closing door formed in the front part of the enclosure is opened, the electrical equipment fixed in the interior is dismantled and drawn out, and then a certain space is secured. It was inconvenient and inefficient for the installation work, such as an operator entering the space, performing installation and wiring work, and then bringing electrical equipment back into its original position in the enclosure and assembling it.

그리고 이와 같은 과정으로 배전반을 설치하고 난 이후에는 지속적인 점검 내지 보수작업이 요구되는데 이러한 일을 수행하기 위하여는 역시 일정한 진입공간이 요구되나 상기한 축소형 배전반의 경우에는 그 내부가 각종 기기들이 밀집된 상태로 설치된 데 따른 점검 내지 보수작업공간이 없는 관계로 정확한 육안 점검을 할 수 없었다.In addition, after the switchboard is installed in this process, continuous inspection or repair work is required. In order to perform such a work, a constant entry space is required, but in the case of the above-mentioned compact switchgear, various devices are concentrated inside. Due to the lack of inspection or maintenance work spaces, the visual inspection was not possible.

특히 각 배전반 함체의 전면부에 형성된 개폐도어를 열고 근거리에 있는 전기기기의 점검 내지 보수는 수행할 수 있으나 그 내부의 후면(함체의 내면 끝부분)에 위치한 기기의 점검 및 보수작업은 전혀 수행할 수 없었고, 또한 2개의 함체 뒷부분이 서로 밀접된 상태로 배치된 상기한 축소형배전반의 경우에는 이러한 후면부분(특고압부와 저압부의 근접된 부분)에서의 작업은 도저히 불가능하여 이에 위치한 내부 기기의 점검과 교체 및 보수작업을 위하여는 결국 모든 전원공급을 차단하고 각 함체의 전면부에 위치한 다른 기기를 해체하여 밖으로 인출하여 일정한 작업공간을 확보한 뒤 작업자가 이 부분으로 진입하여 점검을 하고 또한 필요한 부품의 교체 등을 포함한 보수작업을 수행하여야 하는 배전반 관리의 어려움과 불편성 및 비능률성의 문제점을 항시 내재하고 있었다.In particular, the opening and closing doors formed at the front of each switchgear enclosure can be opened to perform inspection or repair of electrical equipment at a short distance, but the inspection and maintenance of equipment located at the rear side (inner end of the enclosure) inside can be performed at all. In the case of the above-mentioned miniature switchgear in which two rear parts of the enclosure are arranged in close contact with each other, work on such a rear part (close to the high pressure part and the low pressure part) is impossible, and the internal equipment located therein is checked. In the event of overhaul and replacement and maintenance work, all power supply is cut off and other equipment located at the front of each enclosure is dismantled and drawn out to secure a certain working space. Difficulties, inconveniences, and inefficiencies in managing switchboards that require maintenance including replacement of cables The point was always inherent.

본 고안은 이러한 종래의 문제점에 착안하여 고안한 것으로, 본 고안은 배전반 함체가 전후로 밀접 배치된 통상의 축소형 배전반에서 전면부에 배치되는 저압배전반의 저압수직 모선부의 후면 즉, 저압배전반 함체의 후면 하반부에 일정한 공간부의 작업 및 보수를 위한 보수로를 서로 연통되게 형성하고, 보수로에는 투명절연안전구조와 안전커버구조를 각각 형성하여 작업자의 안전을 도모할 수 있음은 물론 전원이 "ON" 된 상태에서도 매우 안전하게 점검을 할 수 있어 축소형 배전반의 효율적인 관리 및 보수작업이 이루어지도록 한 것으로 이하 본 고안의 요지를 첨부도면에 연관시켜 보다 상세히 설명하면 다음과 같다.The present invention has been devised in view of these conventional problems, and the present invention is a rear panel of a low-voltage vertical busbar of a low-voltage switchgear, which is disposed at a front part, in a conventional reduced-type switchgear in which a switchgear enclosure is closely arranged back and forth, that is, the rear of a low-voltage switchgear enclosure. In the lower half, a maintenance path for work and maintenance of a certain space is formed in communication with each other, and a transparent insulation safety structure and a safety cover structure are formed in the maintenance road, respectively, to promote the safety of the worker and to turn the power on. It is possible to check very safely even in a state that the efficient management and repair work of the miniature switchgear is made to be described in more detail in connection with the subject matter of the present invention to the accompanying drawings.

도 1은 본 고안의 사시도.1 is a perspective view of the present invention.

도 2는 본 고안의 요부를 측단면으로 나타낸 측면도.Figure 2 is a side view showing the main portion of the present invention in a side cross-sectional view.

도 3은 본 고안의 평면설면도.Figure 3 is a plan view of the present invention.

도 4는 본 고안 수직절연안전판 구조의 사시도.Figure 4 is a perspective view of a vertical insulated safety plate structure of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1a,1b,1c : 저압배전반 함체 2a,2b,2c : 특고압배전반 함체1a, 1b, 1c: Low voltage switchgear enclosure 2a, 2b, 2c: Special high voltage switchgear enclosure

3 : 특고압 절연애자 4 : 전력용휴즈3: extra high voltage insulator 4: power fuse

5 : 변압기 6,6',6'' : 수직후레임5: Transformer 6,6 ', 6' ': Vertical Frame

7,7' : 수평후레임 8a,8b,8c,8d : 공간실7,7 ': Horizontal frame 8a, 8b, 8c, 8d: Space room

9 : 1차측 저압모선부 10 : 2차측 저압모선부9: Primary low voltage bus part 10: Secondary low voltage bus part

11 : 기중차단기(ACB) 12 : 저압수직모선부11: air breaker (ACB) 12: low pressure vertical bus

13 : 브레커 16 : 보수문13: breaker 16: repair statement

17 : 진입공간부 18 : 작업 및 보수통로17: entry space 18: work and maintenance passage

19 : 수직절연안전판 20,20' : 브라켓19: Vertical insulation safety plate 20,20 ': Bracket

21 : 수직안전커버 22,22',25,26 : 볼트21: Vertical safety cover 22,22 ', 25,26: Bolt

23,24 : 안전커버23,24: Safety cover

도 1은 본 고안 축소형 배전반의 사시도를 도시한 것이고, 도 2는 본 고안 의 요지되는 부분을 단면으로 나타낸 측면도, 도 3은 본 고안의 평면설명도를 도시한 것으로,1 is a perspective view of the present invention reduced-type switchgear, Figure 2 is a side view showing the main part of the present invention in cross-section, Figure 3 is a plan view of the present invention,

본 고안 축소형 배전반은 전면부에 다수의 저압배전반 함체(1a)(1b)(1c)를 설치하고 그 후면부에는 역시 다수의 특고압배전반 함체(2a)(2b)(2c)를 서로 밀접된 상태로 설치하며 그 일측에는 수전부(P)를 일체로 결합하여 구성된 것이다.The present invention miniature switchgear has a plurality of low voltage switchgear enclosures (1a) (1b) (1c) in the front part and a plurality of special high voltage switchgear enclosures (2a) (2b) (2c) in the rear part also close to each other. Installed on one side is configured to combine the power receiving unit (P) integrally.

도 2에 도시한 바와 같이 특고압배전반은 특고압 절연애자(3)가 상부에 설치되고 그 하부에는 전력용휴즈(4)와 변압기(5)가 순차적으로 형성됨은 공지된 구조와 같다.As shown in FIG. 2, the extra-high voltage switchgear is provided with the extra-high voltage insulator 3 and the power fuse 4 and the transformer 5 are sequentially formed in the lower part of the high voltage switch panel.

그리고 본 고안의 요지부분인 저압배전반 의 구조를 구체적으로 설명하면, 상기한 함체의 내부를 수직후레임(6)(6')(6'')으로 구획하고 중간 부분은 수평후레임(7)(7')을 설치하여 공간실(8a)(8b)(8c)(8d)을 각기 구획 형성하였다.And the structure of the low-voltage switchgear which is the main part of the present invention in detail, the interior of the enclosure is divided into a vertical frame (6) (6 ') (6' ') and the middle part is a horizontal frame (7) (7 ') Was installed to form compartments 8a, 8b, 8c and 8d, respectively.

공간실(8a)에는 기중차단기(ACB)로 인입되는 1차측 저압모선부(9)와 2차측 저압모선부(10)를 구성하였고, 공간실(8b)에는 기중차단기(11)를 구성하였으며, 다른 공간실(8c)에는 저압수직모선부(12)와 브레커(NFB)(13)를 설치하였다.In the space chamber 8a, a primary low voltage busbar 9 and a secondary low voltage busbar 10 drawn into the air circuit breaker (ACB) were configured, and an air circuit breaker 11 was constructed in the space chamber 8b. In the other space 8c, a low pressure vertical busbar portion 12 and a breaker (NFB) 13 were provided.

그리고 공간실(8d)의 입구측에는 다른 수직후레임(14)을 설치하여 이에 케이블트레이(15)를 구성하였고 외측의 보수문(16)에 의한 진입공간부(17)을 형성하였고, 그 내부의 공간실(8d)은 작업 및 보수통로(18)가 되는 것이다.In addition, another vertical frame 14 was installed at the entrance of the space chamber 8d to form a cable tray 15, and an entrance space 17 was formed by the exterior door 16, and the space therein. The seal 8d becomes the work and maintenance passage 18.

상기 작업 및 보수통로(18)의 폭은 길이(L)와 같다.The width of the work and maintenance passage 18 is equal to the length (L).

그리고 작업 및 보수통로(18)와 저압수직모선부(12)의 사이에는 투명한 재질의 수직절연안전판(19)을 상하의 브라켓(20)(20')에 볼트(22)로 체결하였고 나머지의 높이 부분은 수직안전커버(21)를 볼트(22')로 고정설치 하였으며, 작업 및 보수통로(18)의 상부와 다른 내벽은 각각의 안전커버(23)(24)를 역시 볼트(25)(26)에 의하여 착탈식으로 체결한 것이다.Between the work and maintenance passage 18 and the low-pressure vertical busbar portion 12, a vertical insulation safety plate 19 made of a transparent material was fastened to the upper and lower brackets 20 and 20 'with a bolt 22, and the rest of the height part thereof. The vertical safety cover 21 is fixedly installed with a bolt 22 ', and the upper part of the work and maintenance passage 18 and the other inner wall have respective safety covers 23, 24 and bolts 25 and 26 as well. By attaching detachably.

여기에서 본 고안은 필요한 사정에 따라 수직안전커버(21)의 구성이 없이 수직절연판(19)을 상부로 연장하여 구성할 수 있으며, 또한 다른 안전커버(23)(24)역시 2개 이상으로 각각 분할된 구조로 체결할 수도 있다.In this case, the present invention can be configured by extending the vertical insulating plate 19 to the top without the configuration of the vertical safety cover 21 according to the circumstances required, and also two or more safety covers 23, 24 respectively. It can also be fastened in a divided structure.

그리고 수직안전커버(21)는 측면부의 보호를 위하여 단면이 ""형으로 형성함이 바람직하며, 안전커버(23)(24)의 표면에는 고무층(미도시)을 피착시켜 보다 안전성을 기할 수도 있다.And vertical safety cover 21 has a cross-section " It is preferable to form a ", and a rubber layer (not shown) may be deposited on the surfaces of the safety covers 23 and 24 to provide more safety.

또한 작업 및 보수통로(18)의 내부 바닥면에는 미끄럼방지판(27)이 부착되었고 외측의 보수문(16)을 열면 별도의 리미트스위치에 의하여 점등되는 작업등(미 도시)이 설치된다.In addition, on the inner bottom surface of the work and maintenance passage 18, a non-slip plate 27 is attached and the work light (not shown) that is lit by a separate limit switch is installed when the repair door 16 is opened.

그리고 전면의 각 저압배전부함체(1a)(1b)(1c) 내의 작업 및 보수통로(18)는 도 3에 도시한 바와 같이 서로 연통되는 구조로 되었다.The work and maintenance passages 18 in each of the low-voltage distribution enclosures 1a, 1b, and 1c on the front face are constructed to communicate with each other as shown in FIG.

도면 중 미 설명부호 28, 29는 전,후면의 개폐문이고, 30은 각 함체를 운반시 사용되는 걸림 고리, 31은 절연애자를 도시한 것이다.In the drawings, reference numerals 28 and 29 are front and rear opening and closing doors, 30 is a hook ring used to transport each enclosure, and 31 shows an insulator.

이와 같이 구성된 본 고안의 작용을 설명한다.The operation of the present invention configured as described above will be described.

변압기(5)로 인입된 22900V의 특고압이 저압(600V 이하)으로 변압된 뒤 기중차단기(11)의 1차측 저압모선부(9)와 이를 거친 2차측 저압모선부(10) 및 수직모선부(12)를 거쳐 각 브레커(13)로 전압이 공급되어 여기에서 각 부하로 전원이 공급됨은 공지된 바와 같다.After the extra high voltage of 22900V introduced into the transformer (5) is transformed to low pressure (600V or less), the primary low side voltage bus section 9 of the air circuit breaker 11, the secondary side low side voltage bus section 10 and the vertical bus section It is known that voltage is supplied to each breaker 13 via 12, where power is supplied to each load.

본 고안은 축소형배전반을 실내의 적정위치에 설치할 시 각 단위배전반을 서로 연결하기 위한 전선의 인입이나 인출작업을 포함한 시공시에는 외측의 보수문 (16)을 열고 작업 및 보수통로(18)로 작업자가 들어가 적절한 작업을 수행할 수 있는 것이다.The present invention is to install the reduced type switchgear at a suitable position in the room, and open the outer door (16) to the work and maintenance passage (18) during the construction including the incoming or outgoing work of the wires to connect each unit switchgear to each other. Workers can go in and do the right thing.

이때에는 필요한 사정에 따라 절연수직안전판(19)이나 다른 안전커버(23) (24)의 볼트를 풀어 분리한 후 일정한 공간을 더 확보하여 시공의 설치작업을 할 수도 있다.At this time, depending on the circumstances required, after removing the bolts of the insulating vertical safety plate 19 or other safety cover 23, 24, and then secure a certain space may be installed work.

그리고 배전반을 사용하면서 그 내부의 점검 및 보수작업이나 각종 전기기기의 부품교체를 위하여는 역시 보수문(16)을 열고 작업 및 보수통로(18)로 진입하여 필요한 작업을 수행하게 되는데, 특히 본 고안의 작업 및 보수통로(18)는 그 내부가 투명 절연수직안전판(19)과 상부 안전커버(23)와 수직안전커버(24)에 의하여 그 내부를 안전하게 보호하여 주기 때문에 배전반에 전원이 인가된 상태에서도 그 내부로 작업자가 진입하여 필요한 점검 내지 보수작업을 수행할 수 있는 것이다.In addition, in order to inspect and repair the inside of the switchboard or to replace parts of various electric devices, the maintenance door 16 is also opened and the work and the maintenance passage 18 are entered to perform necessary work. The work and maintenance passage 18 of the state that the power is applied to the switchboard because the inside is protected by the transparent insulating vertical safety plate 19, the upper safety cover 23 and the vertical safety cover 24 to secure the interior thereof. Even in the interior of the worker can enter and perform the necessary inspection or maintenance work.

또한 본 고안 작업 및 보수통로(18)의 전면부에는 투명한 재질의 절연수직안전판(19)이 구성되어 작업자는 통로를 지나면서 저압 주모선부의 부스모선과 분기부스바 등에 체결된 각 부위의 연결볼트 조임 상태를 육안으로 확인하여 체결 상태가 불량한 부분은 상기 절연수직안전판(19)의 볼트를 분해한 뒤 즉시 관련부분을 시정할 수 있어 체결상태의 불량에서 생성되는 과열상태를 미연에 방지할 수 있는 것이고, 또한 기타의 다른 필요한 보수작업도 수행할 수 있는 것이다.In addition, the front part of the present work and the maintenance passage 18 is composed of an insulating vertical safety plate 19 made of a transparent material, so that the worker passes through the passage and connects bolts of each part fastened to the booth busbar and the branch busbar of the low pressure main busbar part. Visually check the tightening state, the poorly tightened state can be immediately corrected after disassembling the bolt of the insulating vertical safety plate 19 to prevent the overheating state generated from the poor tightening state in advance. And any other necessary maintenance work.

그리고 각기 다른 부분의 점검과 보수 및 부품교체를 위하여는 상부의 안전커버(23)나 다른 수직안전커버(24)가 체결된 부분의 볼트를 풀고 분해하여 관련된 부분의 점검 내지는 보수작업을 매우 간편, 용이하게 할 수 있는 것이다.And for the inspection and repair of different parts and replacement of parts, loosen and disassemble the bolt on the part where the upper safety cover 23 or the other vertical safety cover 24 is fastened, and very easy to check or repair the related parts. It can be done easily.

또한 본 고안의 작업 및 보수통로(18)는 배전반 내부에서 발생되는 열의 배출기능도 함께 기대할 수 있어 내부열에 의하여 각종 전기 기기가 손상됨을 방지할 수 있어 그 사용 년 한을 가일층 증대시킬 수 있다.In addition, the operation and maintenance passage 18 of the present invention can also be expected to discharge the heat generated inside the switchboard, it can prevent the damage to various electrical equipment by the internal heat can further increase the use year.

이상에서 설명한 바와 같이 본 고안은 단위배전반 함체가 전, 후의 위치로 서로 밀접되게 배치되는 통상의 축소형 배전반에서 전면부에 배치되는 저압배전반의 저압수직 모선부의 후면 즉, 저압배전반 함체의 후면 하반부에 일정한 공간부에 작업 및 보수통로를 서로 연통되게 형성하고, 보수로에는 투명절연구조와 안전커버구조를 각각 착탈식으로 형성하여 배전반의 설치시공의 작업능률화를 기할 수 있는 것이고, 또한 배전반의 사용에서 항시 간편 용이하게 점검과 보수 및 부품교체작업을 수행할 수 있음은 물론 작업자의 안전을 도모할 수 있으며 전원이 인가된 상태에서도 매우 안전하게 점검을 할 수 있어 축소형 배전반의 효율적인 사용이 이루어지도록 한 것이다.As described above, the present invention is a rear panel of the low-voltage vertical busbar of the low-voltage switchgear disposed at the front of the conventional switchgear panel in which the unit switchgear enclosures are arranged closely to each other at the front and rear positions, that is, at the lower half of the rear of the low-voltage switchgear enclosure. Work and maintenance passages are formed to communicate with each other in a certain space, and transparent insulation structure and safety cover structure can be detachably formed in the maintenance passage so that the work efficiency of installation and distribution of switchboards can be improved at all times. Not only can it easily and easily perform inspection, repair and parts replacement work, it can also improve the safety of the workers, and it is possible to check very safely even when the power is applied, so that the efficient use of the miniature switchgear is achieved.

Claims (4)

전면부에 저압배전반 함체(1a)(1b)(1c)를 설치하고 그 후면부에는 특고압배전반 함체(2a)(2b)(2c)를 서로 밀접된 상태로 하여 일체가 되게 결합하며 특고압배전반은 특고압 절연애자(3)가 상부에 설치되고 그 하부에는 전력용휴즈(4)와 변압기(5)가 순차적으로 설치하는 통상의 축소형 배전반에서, 저압배전반의 함체 내부를 수직후레임(6)(6')(6'')으로 구획하고 중간 부분은 수평후레임(7)(7')을 설치하여 공간실(8a)(8b)(8c)(8d)을 각기 구획 형성하며 공간실(8a)에는 기중차단기로 인입되는 1차측 저압모선부(9)와 2차측 저압모선부(10)를 공지된 구조와 같이 구성하고, 공간실(8b)에는 공지된 기중차단기(ACB)(11)를 구성하며, 공간실(8c)에는 저압수직모선부(12)와 브레커(13)를 설치함에 있어서,The low-voltage switchgear enclosures (1a) (1b) (1c) are installed in the front part, and the special high-voltage switchgear enclosures (2a) (2b) (2c) are in close contact with each other so as to be integrally connected. In a typical miniature switchgear in which an extra high voltage insulator (3) is installed on the upper part and a power fuse (4) and a transformer (5) are installed in the lower part, the vertical frame (6) ( 6 ') (6' ') and the middle part is provided with horizontal frames (7) and (7') to form space chambers (8a), (8b), (8c) and (8d), respectively. The primary low voltage busbar 9 and the secondary low voltage busbar 10 drawn into the air circuit breaker are configured in the same manner as the known structure, and the known air circuit breaker (ACB) 11 is configured in the space chamber 8b. In the space chamber (8c) in installing the low pressure vertical busbar 12 and the breaker 13, 공간실(8d)의 입구측에는 외측의 보수문(16)에 의한 진입공간부(17)을 형성하였고, 그 내부의 공간실(8d)은 작업 및 보수통로(18)가 되도록 하며 작업 및 보수통로(18)와 저압수직모선부(12)의 사이에는 투명한 재질의 수직절연안전판(19)을 상하의 브라켓(20)(20')에 볼트(22)로 체결하고 나머지의 높이 부분은 수직안전커버(21)를 볼트(22')로 체결하며, 작업 및 보수통로(18)의 상부와 다른 내벽은 각각의 안전커버(23)(24)를 볼트(25)(26)에 의하여 착탈식으로 체결되게 한 작업 및 보수로의 구조를 갖는 축소형배전반.On the entrance side of the space chamber 8d, an entry space 17 is formed by an outside repair door 16, and the space chamber 8d therein becomes a work and maintenance passage 18, and a work and maintenance passage. Between the 18 and the low-pressure vertical busbar portion 12, a vertical insulating safety plate 19 made of a transparent material is fastened to the upper and lower brackets 20 and 20 'with a bolt 22, and the remaining height portion is a vertical safety cover ( 21 is fastened to the bolt 22 ', and the upper part of the work and maintenance passage 18 and the other inner wall allow the respective safety covers 23 and 24 to be detachably fastened by the bolts 25 and 26. Miniature switchgear with a structure for work and maintenance. 제 1항에 있어서,The method of claim 1, 작업 및 보수통로(18) 내의 수직절연안전판(19)을 별도의 수직안전커버(21)의 구성이 없도록 그 길이만큼 연장되게 한 작업 및 보수로의 구조를 갖는 축소형배전반.Miniature switchgear having a structure of work and maintenance paths such that the vertical insulation safety plate 19 in the work and maintenance passages 18 is extended by its length so that there is no configuration of a separate vertical safety cover 21. 제 1항에 있어서,The method of claim 1, 작업 및 보수통로(18) 내의 상부와 다른 내벽의 안전커버(23)(24)를 서로 분할되는 구조로 체결되게 한 작업 및 보수로의 구조를 갖는 축소형배전반.A reduction type switchgear having a structure of a work and a maintenance path, which allows the upper part of the work and the maintenance path 18 and the safety cover 23 and 24 of the other inner wall to be divided into a structure that is divided into each other. 제 1항에 있어서,The method of claim 1, 수직절연안전판(19)을 단면이 ""형으로 하는 작업 및 보수로의 구조를 갖는 축소형배전반.The vertical insulation safety plate 19 has a cross section " Miniature switchgear with a structure of "work and repair".
KR2020020008430U 2002-03-21 2002-03-21 Distributing board for having the construction of work and repair road KR200279711Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020020008430U KR200279711Y1 (en) 2002-03-21 2002-03-21 Distributing board for having the construction of work and repair road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020020008430U KR200279711Y1 (en) 2002-03-21 2002-03-21 Distributing board for having the construction of work and repair road

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020020015326 Division 2002-03-21

Publications (1)

Publication Number Publication Date
KR200279711Y1 true KR200279711Y1 (en) 2002-06-26

Family

ID=73083721

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020020008430U KR200279711Y1 (en) 2002-03-21 2002-03-21 Distributing board for having the construction of work and repair road

Country Status (1)

Country Link
KR (1) KR200279711Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011156243A2 (en) * 2010-06-07 2011-12-15 Abd El & Larson Holdings LLC Multi-access switchgear assembly
KR101560472B1 (en) 2014-01-28 2015-10-14 에스티엑스조선해양 주식회사 Panel structure for maintenance of the in front of panel
US9620938B2 (en) 2014-12-03 2017-04-11 Lsis Co., Ltd. Switchboard applied with bushing-type current transformer

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011156243A2 (en) * 2010-06-07 2011-12-15 Abd El & Larson Holdings LLC Multi-access switchgear assembly
WO2011156243A3 (en) * 2010-06-07 2012-04-19 Abd El & Larson Holdings LLC Multi-access switchgear assembly
US8451589B2 (en) 2010-06-07 2013-05-28 Abd El & Larson Holdings LLC Multi-access switchgear assembly
KR101560472B1 (en) 2014-01-28 2015-10-14 에스티엑스조선해양 주식회사 Panel structure for maintenance of the in front of panel
US9620938B2 (en) 2014-12-03 2017-04-11 Lsis Co., Ltd. Switchboard applied with bushing-type current transformer

Similar Documents

Publication Publication Date Title
KR200485290Y1 (en) Distributing panel
US7450368B2 (en) Front access electrical enclosure and electrical bus assembly therefor
US7440260B2 (en) Electrical bus member mounting system and electrical enclosure employing the same
KR101196704B1 (en) Closed Compact Panel with Voltage Detector
KR100876586B1 (en) Metal-clad compartment and air-insulated compact panel
US20120013227A1 (en) Arc resistant switchgear modular compartment for instrumentation and circuit breakers
US8642885B2 (en) Electrical enclosures with removable end plate
EP1983625A1 (en) Removable compartment for use in a functional unit of an electrical switchgear
KR101145723B1 (en) Metal Clad Switch-Gear/Cubicle
KR200279711Y1 (en) Distributing board for having the construction of work and repair road
KR20200120455A (en) receiving electricity equipment with highvoltage
KR100880625B1 (en) The manufacturing method of distribution board box and a distribution board box thereof
KR100843457B1 (en) Cabinet Panel Busbar Insulation Equipment, Construction
CN117716590A (en) Substation transformer
JP2002199515A (en) Distribution board unit and distribution board constructed by same
JP3521678B2 (en) High-voltage power receiving equipment
KR200379736Y1 (en) Fire Retardant Insulator Cover of Underground Low Voltage Distribution Box
KR100570447B1 (en) A distributing board which has pipe road of an electric wire with operations and inspection room
KR100904457B1 (en) Distributing System forming The Service Space of Substation Room
CN217062865U (en) Generator neutral point cabinet
RU21254U1 (en) COMPLETE DISTRIBUTION DEVICE
JP2004120898A (en) Distribution panel
CN219304215U (en) Two-stage temporary electricity distribution box
RU208059U1 (en) EXTERNAL COMPLETE UNIT SINGLE-STANDING
JP7447231B1 (en) Power receiving and transforming equipment at electric stations and its construction method

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20110603

Year of fee payment: 10

EXPY Expiration of term