KR200268168Y1 - Hardening capsule for tunneling work - Google Patents

Hardening capsule for tunneling work Download PDF

Info

Publication number
KR200268168Y1
KR200268168Y1 KR2020010039062U KR20010039062U KR200268168Y1 KR 200268168 Y1 KR200268168 Y1 KR 200268168Y1 KR 2020010039062 U KR2020010039062 U KR 2020010039062U KR 20010039062 U KR20010039062 U KR 20010039062U KR 200268168 Y1 KR200268168 Y1 KR 200268168Y1
Authority
KR
South Korea
Prior art keywords
capsule
outer tube
filled
tunnel
construction
Prior art date
Application number
KR2020010039062U
Other languages
Korean (ko)
Inventor
정창영
Original Assignee
주식회사 한백산업
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 한백산업 filed Critical 주식회사 한백산업
Priority to KR2020010039062U priority Critical patent/KR200268168Y1/en
Application granted granted Critical
Publication of KR200268168Y1 publication Critical patent/KR200268168Y1/en

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

터널 공사시 암벽에 삽입 고정되는 락크 볼트를 경화시키기 위한 경화용 캡슐이 개시된다.Disclosed is a hardening capsule for hardening a lock bolt inserted into a rock wall during a tunnel construction.

종래의 경화 캡슐은 경화제 및 주제가 충전된 내부관과 외부관이 유리재로 형성됨에 따라 제조 공정을 자동화하기 어려워 코스트가 상승되고, 중량이 무거워 시공 및 취급이 어렵게 되는 문제점이 있는데, 이를 해결하기 위하여 내부에 주제가 충전된 외부관을 갖는 경화 캡슐에 있어서, 상기 외부관(50)의 내측에는 내부에 경화제(41)를 충전시킨 합성수지재의 내부 봉지체(40)가 위치되는 것을 특징으로 하는 터널 공사용 경화 캡슐이 제공된다.Conventional cured capsules are difficult to automate the manufacturing process as the inner tube and outer tube filled with the curing agent and the subject is made of glass, the cost is increased, and the weight is heavy, making construction and handling difficult. In the cured capsule having an outer tube filled with a main body therein, the inner envelope 40 of the synthetic resin material filled with a curing agent 41 therein is located inside the outer tube 50 is hardened for tunnel construction Capsules are provided.

따라서, 외부관의 내부에 합성수지재로 이루어지는 내부 봉지체가 충전됨에 따라 제조 공정을 자동화하는 것이 가능하여 제조 코스트가 절감됨과 아울러 중량이 가벼워 시공 및 취급이 편리하게 된다.Therefore, as the inner encapsulation material made of a synthetic resin is filled in the outer tube, it is possible to automate the manufacturing process, thereby reducing the manufacturing cost and making the construction light and easy to handle.

Description

터널 공사용 경화 캡슐{Hardening capsule for tunneling work}Hardening capsule for tunneling work

본 고안은 터널 공사용 경화 캡슐에 관한 것으로서, 보다 상세하게는 터널공사시 굴착작업이나 폭파작업으로 인하여 터널 내벽이 붕괴되지 않도록 터널 내면의 천정부, 아치부, 측벽부에 타설하여 이완된 지반을 지지하는데 사용되는 락크볼트(Rock Bolt)를 경화시키는 터널 공사용 경화 캡슐에 관한 것이다.The present invention relates to a hardened capsule for tunnel construction, and more particularly, in order to support the relaxed ground by placing in the ceiling, arch, and side walls of the tunnel inner surface so that the tunnel inner wall does not collapse due to excavation or blasting. It relates to a hardening capsule for tunnel construction to harden the rock bolt (Rock Bolt) used.

일반적으로 터널공사는 폭파작업과 굴착작업을 병행해가며 굴을 형성하게 되는데, 미리 형성된 터널의 내벽은 폭파작업과 굴착작업으로 인해 내벽의 지반이 이완된 상태이므로 이러한 상태에서 터널의 측벽 등의 공사를 하게될 경우에는 지반 침하로 인해 측벽이 붕괴되는 등의 위험성이 있다.In general, tunnel construction is performed by blasting and excavating in parallel to form an oyster. The inner wall of the preformed tunnel is loosened due to the blasting and excavation. If there is a risk that the side wall collapses due to ground subsidence.

이에 따라 터널의 내벽 전체에는 도 1 에 도시한 바와 같이 복수 개의 락크 볼트(10)를 타설하여 터널내벽(11)이 붕괴되는 것을 방지하게 된다.Accordingly, a plurality of lock bolts 10 are placed on the entire inner wall of the tunnel to prevent the tunnel inner wall 11 from collapsing.

이러한 락크 볼트(10)는 발파 등으로 이완된 지반을 원지반에 고정시켜주는 봉합(縫合)효과와, 층사이의 조임작용으로 층리면에서는 전단응력의 전달을 가능하게 하여 합성빔으로써 거동시키는 빔형성 효과와, 락크 볼트(10)의 인장력에 상당하는힘이 내압으로써 터널내벽(11)면에 작용하여 이에 의해 2축응력 상태의 터널 근반원 지반을 3측응력 상태로 유지시켜 주는 내압(內壓)효과와, 내압효과에 의해 지반이 일체화되어 내하능력이 높아진 터널주변의 원지반의 내공측은 균등하게 변위되도록 하는 아아치 형성 효과 등을 가짐으로써 터널붕괴를 방지하게 된다.The lock bolt 10 has a suture effect of fixing the ground loosened by blasting to the original ground, and a beam forming effect of acting as a synthetic beam by enabling the transfer of shear stress in the layered surface by the tightening action between the layers. And a pressure-resistant effect in which the force corresponding to the tensile force of the lock bolt 10 acts on the tunnel inner wall 11 surface as the internal pressure, thereby maintaining the tunnel root circle ground in the biaxial stress state in the trilateral stress state. And the inner hole side of the original ground around the tunnel where the ground is integrated due to the pressure resistance effect has increased the load capacity, thereby preventing the tunnel collapse by having an arch formation effect such that the ground is evenly displaced.

상기 락크 볼트(10)는 도 2 에 도시한 바와 같이 미리 타설공 내에 삽입된 경화 캡슐(20)에 의해 경화가 이루어지는데, 상기 경화 캡슐(20)은 폴리에틸렌계의 경화제(21)가 주입된 내부관(22)과, 상기 내부관(22)의 외측에 위치되며 폴리스틸렌계의 주제(23)가 충전된 외부관(24)으로 이루어진다.As shown in FIG. 2, the lock bolt 10 is hardened by a hardened capsule 20 inserted into a pour hole, and the hardened capsule 20 is filled with a polyethylene-based hardener 21. It consists of a tube 22 and an outer tube 24 located outside the inner tube 22 and filled with a polystyrene-based main body 23.

상기 내부관(22) 및 외부관(24)은 유리 재질로 제조된 후 내부에 경화제(21) 및 주제(23)가 충전된 상태에서 밀봉되는데, 터널 내의 타설공 내에 삽입된 상태에서 락크 볼트(10)를 오가 드릴 등의 공구를 이용하여 800RPM 이상으로 회전시키면 상기 외부관(24) 및 내부관(22)이 파괴되는데, 이때 상기 경화제(21) 및 주제(23)가 혼합되면서 경화되어 락크 볼트(10)를 고정시키게 되는 것이다.The inner tube 22 and the outer tube 24 are made of glass and then sealed in a state where the curing agent 21 and the main body 23 are filled therein, and the lock bolt ( Rotating 10) to 800 RPM or more using a tool such as an Oga drill, the outer tube 24 and the inner tube 22 are broken, and the hardener 21 and the main body 23 are mixed and cured to lock bolts. (10) will be fixed.

그러나, 이와 같은 경화 캡슐은 내부관이 유리로 형성됨에 따라 수작업으로 제조함으로써 제조 원가가 상승되고 중량이 무거워지는 등의 문제점들이 내재되어 있었다.However, such hardened capsules have problems in that the manufacturing cost is increased and the weight becomes heavy by manufacturing by hand as the inner tube is formed of glass.

본 고안은 상술한 종래의 문제점을 해결하기 위하여 안출된 것으로서, 본 고안의 목적은 제조가 용이하고 제조 원가를 절감할 수 있는 터널 공사용 경화 캡슐을 제공하는데 있다.The present invention has been made to solve the above-mentioned conventional problems, an object of the present invention is to provide a hardened capsule for tunnel construction that can be easily manufactured and reduced manufacturing costs.

본 고안의 다른 목적은 중량이 가볍고 취급이 용이한 터널 공사용 경화 캡슐을 제공하는데 있다.Another object of the present invention is to provide a hardened capsule for tunnel construction that is light in weight and easy to handle.

도 1 은 일반적인 터널 공사에서 락크 볼트의 시공상태를 도시한 개략도이다.1 is a schematic diagram showing the construction of lock bolts in a general tunnel construction.

도 2 는 종래의 터널 공사용 경화 캡슐을 도시한 절개 사시도이다.Figure 2 is a cutaway perspective view of a conventional hardened capsule for tunnel construction.

도 3 은 본 고안의 터널 공사용 경화 캡슐을 도시한 절개 사시도이다.3 is a perspective view showing a cut capsule for the tunnel construction of the present invention.

도 4 는 본 고안의 사용 상태를 도시한 단면도이다.4 is a cross-sectional view showing a state of use of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10: 락크 볼트 30: 경화 캡슐10: lock bolt 30: hardened capsule

40: 내부 봉지체 41: 경화제40: inner sealing body 41: hardener

42: 봉합부 50: 외부관42: seam 50: outer tube

51: 주제 60: 타설공51: Topic 60: Pour Ball

이와 같은 목적을 실현하기 위한 본 고안에 의한 터널 공사용 경화 캡슐은, 내부에 주제가 충전된 외부관을 갖는 경화 캡슐에 있어서, 상기 외부관의 내측에는 내부에 경화제를 충전시킨 합성수지재의 내부 봉지체가 위치되는 것을 특징으로 한다.In the cured capsule for tunnel construction according to the present invention for realizing such an object, in the cured capsule having an outer tube filled with a main body therein, an inner encapsulation material of a synthetic resin material filled with a curing agent therein is positioned inside the outer tube. It is characterized by.

따라서 본 고안에 의하면, 외부관의 내부에 합성수지재로 이루어지는 내부 봉지체가 충전됨에 따라 제조 공정을 자동화하는 것이 가능하여 제조 코스트가 절감됨과 아울러 중량이 가벼워 시공 및 취급이 편리하게 되는 등의 효과가 있다.Therefore, according to the present invention, as the inner encapsulation material made of a synthetic resin is filled in the outer tube, it is possible to automate the manufacturing process, thereby reducing the manufacturing cost and making the construction and handling easier due to the light weight. .

이하, 본 고안의 바람직한 실시예를 첨부 도면을 참조하여 상세하게 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 3은 본 고안에 의한 터널 공사용 경화 캡슐을 나타내는 절개 사시도로서, 부호 (30)은 터널 내의 타설공 내에 삽입되는 경화 캡슐을 나타내고 있다.Fig. 3 is a cutaway perspective view showing a cured capsule for tunnel construction according to the present invention, and the reference numeral 30 denotes a cured capsule inserted into a pour hole in the tunnel.

상기 경화 캡슐(30)은 내부 봉지체(40)와, 상기 내부 봉지체(40)의 외측에 형성되는 외부관(50)으로 이루어진다.The cured capsule 30 is composed of an inner encapsulation 40 and an outer tube 50 formed on the outer side of the inner encapsulation 40.

상기 내부 봉지체(40)는 합성수지재로 형성되며, 내부에는 폴리에틸렌계의 경화제(41)가 충전되고, 가장자리에는 열압착에 의해 봉합된 봉합부(42)가 형성되어 있다.The inner encapsulation 40 is formed of a synthetic resin material, the inside is filled with a polyethylene-based curing agent 41, the edge is formed with a sealed portion 42 sealed by thermocompression bonding.

그리고, 상기 외부관(50)은 내부에 상기 내부 봉지체(40)가 위치됨과 아울러 폴리스틸렌계의 주제(51)가 충전된 후 봉합되어 하나의 경화 캡슐(30)이 완성된다.In addition, the outer tube 50 is the inner encapsulation body 40 is located therein and the polystyrene-based main body 51 is filled and then sealed to complete one cured capsule 30.

상기 경화 캡슐(30)은 타설공 및 락크 볼트의 길에 따라 급결용, 선단용, 충진용 등으로 나뉘어진다.The cured capsule 30 is divided into fastening, tipping, filling, etc., depending on the length of the pour hole and the lock bolt.

이와 같이 구성된 본 고안에 의한 터널 공사용 경화 캡슐은 터널의 굴착 및 폭파작업으로 터널이 형성되면, 터널의 내벽면에 착암기 등으로 이용하여 32~38mm정도의 직경으로 복수 개의 타설공(60)을 형성하고, 상기 타설공(60) 내에 삽입될 락크 볼트(10)의 길이에 따라 경화 캡슐(30)의 레진을 조합한다.The hardened capsule for tunnel construction according to the present invention configured as described above forms a plurality of pouring holes 60 with a diameter of about 32 to 38 mm by using a rock drill or the like on the inner wall surface of the tunnel when the tunnel is formed by excavation and blasting of the tunnel. Then, the resin of the cured capsule 30 is combined according to the length of the lock bolt 10 to be inserted into the pouring hole 60.

예컨대, 길이가 2m인 타설공(60)의 경우에는 급결용 및 충전용으로 구성되는 2개의 경화 캡슐(30)이 사용되고, 길이가 3m인 타설공(60)의 경우에는 급결용, 선단용 및 충전용으로 이루어지는 경화 캡슐(30)이 사용되며, 길이가 4m인 경우에는급결용, 선단용 그리고 2개의 충전용으로 이루어지는 경화 캡슐(30)이 사용된다.For example, in the case of a pour ball 60 having a length of 2 m, two hardened capsules 30 configured for quenching and filling are used, and in the case of a pour ball 60 having a length of 3 m, for fastening, tipping and A cured capsule 30 is used for filling, and in the case of 4m in length, a cured capsule 30 is used for fastening, tipping and two fillings.

즉, 상기 타설공(60) 내에 길이에 해당되는 경화 캡슐(30)을 삽입한 후 오가 드릴을 이용하여 800RPM이상으로 20초 이상 회전하면서 락크 볼트(10)를 삽입하면 외부관(50)이 1차적으로 파괴된 후 내부 봉지체(40)가 파괴됨으로써 주제(51)와 경화 캡슐(30)이 혼합되는데, 이에 따라 락크 볼트(10)는 타설공(60) 내에서 고정 상태를 유지하게 되는 것이다.That is, after inserting the cured capsule 30 corresponding to the length in the pour hole (60) by inserting the lock bolt 10 while rotating for more than 20 seconds at 800 RPM or more using an Oga drill, the outer tube 50 is 1 After the main body is destroyed, the inner encapsulation 40 is destroyed, and the main body 51 and the hardened capsule 30 are mixed. As a result, the lock bolt 10 is fixed in the pour hole 60. .

상술한 바와 같이 본 고안에 의하면, 외부관의 내부에 합성수지재로 이루어지는 내부 봉지체가 충전됨에 따라 제조 공정을 자동화하는 것이 가능하여 제조 코스트가 절감됨과 아울러 중량이 가벼워 시공 및 취급이 편리하게 되는 등의 효과가 있다.As described above, according to the present invention, as the inner encapsulation material made of a synthetic resin is filled in the outer tube, it is possible to automate the manufacturing process, thereby reducing the manufacturing cost and making the construction and handling easier due to the light weight. It works.

본 고안은 상기한 실시예에 한정되지 않고, 이하의 실용신안등록청구범위에서 청구하는 바와 같이 본 고안의 요지를 벗어남이 없이 당해 고안이 속하는 분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변경 실시가 가능한 범위까지 본 고안의 기술적 정신이 있다고 할 것이다.The present invention is not limited to the above-described embodiment, and any person having ordinary knowledge in the field to which the present invention belongs without departing from the gist of the present invention as claimed in the utility model registration claims below. It will be said that the technical spirit of the present invention to the extent possible.

Claims (2)

내부에 주제가 충전된 외부관을 갖는 경화 캡슐에 있어서,A cured capsule having an outer tube filled with a main body therein, 상기 외부관(50)의 내측에는 내부에 경화제(41)를 충전시킨 합성수지재의 내부 봉지체(40)가 위치되는 것을 특징으로 하는 터널 공사용 경화 캡슐.Cured capsule for tunnel construction, characterized in that the inner tube 40 of the synthetic resin material filled with a curing agent 41 inside the outer tube 50 is located inside. 제 1 항에 있어서, 상기 내부 봉지체(40)는 가장자리에 봉합부(42)가 형성된 것을 특징으로 하는 터널 공사용 경화 캡슐.The hardened capsule for tunnel construction according to claim 1, wherein the inner encapsulation member (40) has a seal portion (42) formed at an edge thereof.
KR2020010039062U 2001-12-18 2001-12-18 Hardening capsule for tunneling work KR200268168Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010039062U KR200268168Y1 (en) 2001-12-18 2001-12-18 Hardening capsule for tunneling work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010039062U KR200268168Y1 (en) 2001-12-18 2001-12-18 Hardening capsule for tunneling work

Publications (1)

Publication Number Publication Date
KR200268168Y1 true KR200268168Y1 (en) 2002-03-15

Family

ID=73114349

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010039062U KR200268168Y1 (en) 2001-12-18 2001-12-18 Hardening capsule for tunneling work

Country Status (1)

Country Link
KR (1) KR200268168Y1 (en)

Similar Documents

Publication Publication Date Title
US6640893B1 (en) Wellbore packer
CA2949647C (en) Construction element for creating a tunnel, tunnel comprising such an element and methods for constructing such an element and such a tunnel
KR200268168Y1 (en) Hardening capsule for tunneling work
KR101029320B1 (en) Rock bolt and fixation method the rock bolt
JPH0125848B2 (en)
US3971227A (en) Installation of expanded base piles
JPH1077800A (en) Anchoring material filling method and seal unit
AU2016239986A1 (en) Building element for creating a tunnel, tunnel comprising such an element and methods of manufacturing such an element and such a tunnel
JP2001271347A (en) Drop method for ready-made pile
KR100552101B1 (en) Tunnel constructing method and anchor assembly for it
KR100869369B1 (en) The ground reinforcement apparatus and method grouting type using bundle steel pipe
CN110820724A (en) Device and method for connecting reinforcement cage of diaphragm wall and lining wall
JP3040682B2 (en) Concrete segment backfill injection method
JP2003096771A (en) Precast soil-cement pile having composite blades
JP2001271344A (en) Embedding method for ready-made pile
KR102359500B1 (en) Chemical capsule guard for anchors and anchor construction method using chemical capsule guard for anchor
JPH0522039B2 (en)
JPH10331567A (en) Excavating jig for sunk well
JP3886704B2 (en) Method for forming a space in a pile head into which a curable material flows and a space forming tool used therefor
KR200349154Y1 (en) anchor bolt
JPH0612036Y2 (en) Fixing material for earth anchor
JPH11172708A (en) Method for forming pile penetrating existing underground structure
JP3020087U (en) Lock bolt fixing material leakage prevention tool
JPH02304196A (en) Shaft excavation construction method
JP2015105463A (en) Precast pile and foundation pile structure

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20030305

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee