KR20020005249A - Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method - Google Patents

Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method Download PDF

Info

Publication number
KR20020005249A
KR20020005249A KR1020000038622A KR20000038622A KR20020005249A KR 20020005249 A KR20020005249 A KR 20020005249A KR 1020000038622 A KR1020000038622 A KR 1020000038622A KR 20000038622 A KR20000038622 A KR 20000038622A KR 20020005249 A KR20020005249 A KR 20020005249A
Authority
KR
South Korea
Prior art keywords
formwork
cross beam
dismantling
main body
forms
Prior art date
Application number
KR1020000038622A
Other languages
Korean (ko)
Inventor
김준규
Original Assignee
김준규
한국스틸폼주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김준규, 한국스틸폼주식회사 filed Critical 김준규
Priority to KR1020000038622A priority Critical patent/KR20020005249A/en
Publication of KR20020005249A publication Critical patent/KR20020005249A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Abstract

PURPOSE: An installing and dismantling method of a cross beam mold is provided to continuously install and dismantle a cross beam reinforced steel and the cross beam mold without regarding to a bridge. CONSTITUTION: An installing and dismantling device contains a rail fixed on a reinforced steel of a PC(Pre-Concrete) beam; a trolley(10) moved on the rail; a main body(20) located on the trolley; a supporting arm(30) located in both ends of the main body vertically; a rotation portion(50) extended downward from the lower end of the supporting arm; and a workplace(60) supported and rotated by the rotation portion(10). Thereby, the installing and the dismantling processes are continuously performed and the workability is improved. Moreover, the safety is advanced.

Description

교량용 PC빔 또는 스틸 박스 공법에 적용되는 철근 작업 및 크로스빔 거푸집 설치, 해체 장치 {Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method}Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method}

본 발명은 P.C.빔(Pre-Concrete Beam) 또는 스틸 박스(Steel Box) 공법에 적용되는 크로스빔 철근 작업과 크로스빔 거푸집 설치 및 해체 작업용 장치에 관한 것으로, 보다 상세하게는 상기 공법을 사용한 교량 공사시 크로스빔 철근을 용접하고 배근하거나, 크로스빔 거푸집을 설치하며, 콘크리트 타설 및 양생후 해체할 때 작업자가 안전하고 유효하게 작업에 임할 수 있는 작업 공간을 확보하기 위한 장치에 관한 것이다.The present invention relates to a device for cross beam reinforcement work and cross beam formwork installation and dismantling work applied to PC beam (Pre-Concrete Beam) or Steel Box (Steel Box) method, more specifically, in the construction of bridges using the method The present invention relates to a device for securing a work space where a worker can safely and effectively work when welding and reinforcing cross beam reinforcement, installing a crossbeam formwork, and dismantling after concrete placing and curing.

P.C.빔 또는 스틸 박스 공법에 의한 교량 공사시에는 지상으로부터 상당한 높이에서 이루어져야하는 작업, 예를 들어 크로스빔 철근 작업 또는 거푸집 설치 및 해체 작업 등이 필수적이다. 따라서 종래의 경우 상기 크로스빔용 철근 작업 또는 거푸집 작업시, PC빔 사이에 행어(Hanger)와 와이어, 목재 평판 등으로 구성된 하부비계 또는 상기 목재 평판 등을 철근 구조물로 대체한 달비계 등을 설치하여 작업자의 작업 공간을 확보하여야 하므로, 비계 비용도 많이 소요되고 비계의 설치 및 해체에 많은 시간이 소요되는 문제점이 있었다.In the construction of bridges by P.C.beam or steel box construction, work that must be done at a substantial height from the ground, such as crossbeam rebar or formwork and dismantling, is essential. Therefore, in the conventional case when the cross beam reinforcement work or formwork, the worker by installing a lower scaffold consisting of a hanger (Hanger), a wire, a wooden plate, etc. between the PC beam or a moon scaffold that replaced the wooden plate with a reinforcing structure Since the work space of the must be secured, the scaffolding cost is also high, and the installation and dismantling of the scaffolding takes a long time.

상기 비계에 대한 대안으로 교량 아래에서 사다리차와 같은 방식인 하이랜더를 이용하여 거푸집을 설치하고 해체하는 방식도 있으나, 이 방식은 교량 아래가 하천일 경우 등 험한 지형에서는 사용하기 힘든 문제점이 있고 하이랜더가 제공할 수 있는 높이에도 제한이 있다.As an alternative to the scaffolding, there is also a method of installing and dismantling formwork using a highlander, which is the same as a ladder car, under the bridge, but this method has a problem that is difficult to use in rough terrain such as a river under the bridge and provided by the highlander. There is a limit to the height that can be done.

최근 비계문제를 해결하기 위하여, 실용신안등록 제 181651호와 같은 이동식비계가 제안되고 있고, 이 방식은 대체로 양생된 교량 위를 이동하는 대차와, 상기 대차의 상부 양 끝단에 각각 위치한 윈치와, 상기 각 윈치와 연결된 와이어로프와, 상기 와이어로프가 양 끝단에 연결된 장방형 작업대로 구성되어 있다.Recently, in order to solve the scaffolding problem, a mobile scaffold such as Utility Model Registration No. 181651 has been proposed, and this method generally includes a bogie moving on a cured bridge, a winch respectively located at both ends of the upper portion of the bogie, and A wire rope connected to each winch and a rectangular workbench connected to both ends of the wire rope.

그런데 상기 이동식 비계는 한 경간(교각 사이)에서 사용한 후 타 경간으로 이동시 작업대를 분리하여 이동후 다시 체결하여야 하기 때문에 작업 공정이 연속적이지 못할 뿐 아니라, 작업대의 분리 및 해체 작업이 어렵고 위험하다는 문제점이 있다. 또한, 통상의 자동차와 같이 4개의 바퀴에 의해 이동하기 때문에 크로스빔 철근 작업이나 크로스빔 거푸집 설치 및 해체 작업 등의 슬라브 양생 전 작업에는 사용하기 어려운 단점이 있다.However, since the mobile scaffold is used in one span (between piers) and then moved to another span, the worktable must be separated and re-joined after moving, and the work process is not continuous, and the work of separating and disassembling the worktable is difficult and dangerous. . In addition, since it is moved by four wheels as in a typical car, it is difficult to use for pre-slave curing work such as crossbeam rebar work, crossbeam formwork installation and dismantling work.

본 발명은 상기와 같은 종래의 거푸집 해체장치의 문제점을 해결하기 위하여 안출된 것으로, 본 발명의 목적은 교각에 구애받지 않고 연속적인 크로스빔 철근 작업과 크로스빔 거푸집의 설치 및 해체 작업이 가능한 크로스빔 거푸집 설치 및 해체 장치를 제공하는 것이다.The present invention has been made to solve the problems of the conventional formwork dismantling device as described above, the object of the present invention is a crossbeam capable of continuous crossbeam reinforcement work and installation and dismantling work of crossbeam formwork regardless of the piers It is to provide a formwork installation and dismantling device.

기타 본 발명의 목적은 여러 가지가 있으나, 이는 이하 설명하는 상세한 설명과 도면을 통해 이해될 수 있을 것이다.Other purposes of the present invention may be various, but will be understood through the detailed description and drawings described below.

도 1은 본 발명에 따른 설치 및 해체 장치가 PC빔 콘크리트위에 설치된 모양을 도시한 정면도1 is a front view showing the installation and dismantling device according to the present invention installed on the PC beam concrete

도 2는 도 1의 설치 및 해체 장치의 평면도2 is a plan view of the installation and dismantling device of FIG.

도 3은 도 1의 설치 및 해체 장치의 작업대가 회전한 상태를 도시한 평면도3 is a plan view showing a state in which the worktable of the installation and dismantling device of FIG.

도 4는 본 발명에 따른 동력전달과정을 도시한 블록도4 is a block diagram showing a power transmission process according to the present invention.

* 도면의 주요 부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10: 대차 20: 본체10: balance 20: main body

30: 지지대 50: 로테이션부30: support 50: rotation part

60: 작업대60: working table

상기 목적을 달성하기 위하여, 본 발명은 PC 빔 상에 설치된 레일과; 상기 레일을 따라 움직이는 적어도 하나 이상의 대차와; 상기 대차에 의해 지지되고 전원 장치를 포함하는 본체와; 상기 본체의 양끝단에서 각각 수직으로 연장된 지지암과; 상기 지지암 각각의 일끝단에 하방으로 연장되고 회전 가능한 로테이션부와; 상기 로테이션부 각각의 끝단에 장착된 작업대를 포함하는 거푸집 설치 및 해체 장치를 제공한다.In order to achieve the above object, the present invention is a rail mounted on the PC beam; At least one bogie moving along the rail; A main body supported by the bogie and including a power supply device; Support arms vertically extending at both ends of the main body; A rotation part extending downward and rotatable at one end of each of the support arms; It provides a formwork installation and dismantling device comprising a worktable mounted on each end of the rotation unit.

본 발명에서 상기 대차는 통상의 기차 선로와 같은 레일 위에서 이동할 수 있는 구조의 바퀴와 동력 장치를 포함한다.In the present invention, the bogie includes a wheel and a power unit having a structure that can move on a rail such as a conventional train track.

본 발명에서 상기 로테이션부와 상기 작업대는 바람직하게 360도 회전가능하며, 상기 작업대 중 적어도 하나는 서로 다른 작업대와 연결할 수 있는 체결 장치를 포함한다.In the present invention, the rotation unit and the worktable is preferably rotatable 360 degrees, at least one of the workbench includes a fastening device that can be connected to different workbench.

본 발명에서 상기 로테이션부는 모터와 기어박스를 포함하고 있어, 상기 모터에 의해 상기 작업대는 회전한다.In the present invention, the rotation part includes a motor and a gearbox, and the work table rotates by the motor.

이하, 본 발명에 따른 바람직한 실시예를 첨부된 도면을 참조하여 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 설치 및 해체 장치의 정면도로서, 본 발명의 장치를 사용하여 PC빔 사이에 설치된 크로스빔 거푸집을 해체하고 있는 것을 도시한 정면도이다.1 is a front view of the installation and dismantling device according to the present invention, showing the dismantling of crossbeam formwork provided between PC beams using the device of the present invention.

도시한 바와 같이, 본 발명은 상기 PC빔(P)의 철근(C) 위에 용접 또는 클램프 체결 등의 방법으로 고정 설치된 선로(R)와, 상기 선로(R)위를 이동하는 대차(10)와, 상기 대차의 상부에 위치한 본체(20)와, 상기 본체의 양끝단에 수직으로 위치한 지지암(30)과, 상기 지지암의 하측 끝단에서 하방으로 연장된 로테이션부(50)와, 상기 로테이션부(10)에 의해 지지되고 회전하는 작업대(60)를 구비하고 있다.As shown in the drawing, the present invention provides a track (R) fixedly installed on the reinforcing bar (C) of the PC beam (P) by welding or clamping, and the bogie (10) moving on the track (R); And a main body 20 positioned at an upper portion of the bogie, a support arm 30 vertically positioned at both ends of the main body, a rotation portion 50 extending downward from a lower end of the support arm, and the rotation portion. A work bench 60 supported and rotated by 10 is provided.

상기 대차(10)는 원격조정에 의한 동력으로 또는 수동으로 작동될 수 있으며, 통상의 기차 선로와 같은 레일 상에서 유효하게 움직일 수 있는 구조의 바퀴와 동력 장치를 적어도 하나 이상 포함하고 있다.The trolley 10 may be operated by remote control or manually, and includes at least one wheel and a power unit of a structure that can effectively move on a rail such as a conventional train track.

상기 본체(20)는 빔 구조물로서 상기 대차(10)에 의해 지지되며 양끝단 사이 소정의 위치에 대차와 로테이션부의 구동용 모터의 전원으로 쓰이는 배터리(25)를 포함하고 있다.The main body 20 is a beam structure and is supported by the cart 10 and includes a battery 25 used as a power source for the motor for driving the cart and the rotation unit at a predetermined position between both ends.

상기 지지암(30)은 하측 끝단에 위치한 고정 기어부(34)와 양끝단 사이 소정의 위치에 장착된 슬루잉 베어링(SLEWING BEARING, 36)을 포함하고 있으며, 상기 슬루잉 베어링(36)의 구동부(미표기)는 상기 로테이션부(50)의 상측 일끝단과 결합된다.The support arm 30 includes a slewing bearing 36 mounted at a predetermined position between a fixed gear part 34 positioned at a lower end and both ends, and a driving part of the slewing bearing 36. (Not shown) is coupled to the upper end of the rotation unit 50.

상기 로테이션부(50)는 모터(54)와 기어박스(56)를 포함하며 상측 일끝단은 상기 슬루잉 베어링(36)의 구동부와 결합되고 하측 타끝단은 상기 작업대(60)와 결합되어 상기 지지암(30)의 고정 기어부(34)와 상기 모터(54) 및 상기 기어박스(56)의 작용에 의해 작업대와 함께 상기 슬루잉 베어링(35)의 중심축과 동축으로 360°회전이 가능하다. 물론 상기 고정 기어부(34)와 상기 기어박스(56) 및 모터(54)의 동력 전달 구조는 필요에 따라 원형 기어 간의 결합 등의 다양한 형태를 가질 수 있다.The rotation part 50 includes a motor 54 and a gear box 56, one upper end of which is coupled to the driving unit of the slewing bearing 36 and the other lower end of which is coupled to the work table 60 to support the support. By the action of the fixed gear part 34 of the arm 30, the motor 54 and the gearbox 56, it is possible to rotate 360 ° coaxially with the central axis of the slewing bearing 35 together with the worktable. . Of course, the power transmission structure of the fixed gear unit 34, the gearbox 56 and the motor 54 may have various forms such as coupling between the circular gear, if necessary.

상기 작업대(60)는 작업자의 작업공간 및 자재 적재 공간 등으로 쓰이는 수평면부(60a)와 작업자의 안전을 위한 수직면부(60b)를 갖는 장방형 구조물로서, 일끝단에 체결장치(65)를 포함하고 타끝단 소정의 위치에서 상기 로테이션부(50)와 결합된다. 또한 상기 한 쌍의 작업대(60)는 필요에 따라 상기 체결장치(65)에 의해 서로 결합 또는 분리된다.The worktable 60 is a rectangular structure having a horizontal surface portion 60a used as a work space and a material loading space of the worker and a vertical surface portion 60b for the safety of the worker, and includes a fastening device 65 at one end thereof. The other end is coupled to the rotation unit 50 at a predetermined position. In addition, the pair of working table 60 is coupled or separated from each other by the fastening device 65 as necessary.

도 2에 도시된 평면도를 참조하면, 본 발명에 따른 설치 및 해체 장치(1)는 PC빔(P) 상에 임시 설치된 레일(R)을 따라 PC빔의 연장 방향 어느 쪽으로도 이동할 수 있다.Referring to the plan view shown in FIG. 2, the installation and dismantling device 1 according to the present invention may move in any direction in which the PC beam extends along the rail R temporarily installed on the PC beam P.

도 3은 상기 도 1, 2에 도시된 해체장치가 교각을 만났을 때 작업대(60)를 회전하여 교각을 지나는 것을 도시한 평면도로서, 작업대를 90도 회전시켜 교량의 외곽에 작업대가 위치하도록 하여 이동한다.FIG. 3 is a plan view showing the dismantling device shown in FIGS. 1 and 2 passing the bridge by rotating the work bench 60 when the dismantling device shown in FIGS. 1 and 2 rotates by 90 degrees to move the work table to the outside of the bridge. do.

도 4는 본 발명에 따라 작업대를 회전시키기 위한 동력전달과정을 도시한 블록도로서, 배터리(25)의 전원으로 모터(54)를 구동시키면, 모터는 기어박스(56)를 구동시키고 기어박스의 피니언은 고정 기어부(34)에 동력을 전달한다. 상기 고정 기어부(34)는 움직이지 않도록 고정되어 있으므로 결국 상기 기어박스(56)와 상기 모터(54)가 위치한 로테이션부(50)가 회전하게 되고 로테이션부에 고정된 작업대(60)가 회전하게 된다. 이때 모터는 원격조정될 수 있음은 물론이고, 고정 기어부와 기어 박스 및 모터는 다양한 형태의 동력 전달 구조를 가질 수 있다.4 is a block diagram illustrating a power transmission process for rotating a work table according to the present invention. When the motor 54 is driven by the power of the battery 25, the motor drives the gear box 56 and the gear box 56. The pinion transmits power to the fixed gear portion 34. Since the fixed gear part 34 is fixed so as not to move, the rotation part 50 in which the gearbox 56 and the motor 54 are located rotates and the worktable 60 fixed to the rotation part rotates. do. In this case, the motor may be remotely controlled, and the fixed gear unit, the gear box, and the motor may have various types of power transmission structures.

이상에서 본 발명을 설명한 바와 같이, 종래에는 교각을 지날 때 마다 작업대를 분리해체하여야 하는 불편함이 있었으나, 본 발명에 따른 거푸집 설치 및 해체장치로 인하여 연속적인 설치 및 해체 공정이 가능하게 되어 작업성이 높아지고, 안전성이 제고되는 이점이 있다. 또한, 슬라브가 타설 및 양생되기 전 PC빔 상에서 이동할 수 있는 구조이므로 크로스빔 철근 작업과 크로스빔 거푸집의 설치 및 해체 작업용으로 유효하게 쓰일 수 있다.As described above, the present invention has been inconveniently required to dismantle and separate the workbench each time past the pier, but due to the formwork installation and dismantling device according to the present invention, the continuous installation and dismantling process is enabled. This has the advantage of increasing the safety. In addition, since the slab can move on the PC beam before placing and curing, it can be effectively used for crossbeam reinforcement work and installation and dismantling work of crossbeam formwork.

이상에서 본 발명에 따른 바람직한 실시예를 설명하고 있으나, 이는 예시이며, 본 발명의 정신은 여기에 한정되는 것이 아니며, 본 발명의 정신을 벗어나지 않고 다양한 변화와 변형이 가능하고, 이 다양한 변화와 변형은 모두 본 발명의 권리범위에 속하게 됨은 첨부된 청구범위를 통해 알 수 있을 것이다.Although preferred embodiments according to the present invention have been described above, this is merely an example, and the spirit of the present invention is not limited thereto, and various changes and modifications may be made without departing from the spirit of the present invention, and the various changes and modifications may be made. All belong to the scope of the present invention will be seen through the appended claims.

Claims (4)

P.C.빔 또는 스틸 박스 공법으로 크로스빔을 타설하고 양생할 때, 크로스빔 철근을 배근하고 용접하거나, 크로스빔 거푸집을 설치 및 해체하는 장치로서,When placing and curing cross beam by P.C. beam or steel box method, it is a device to reinforce and weld cross beam rebar, or to install and dismantle cross beam formwork, 상기 PC빔 위에서 구동할 수 있는 하나 이상의 대차와;At least one bogie capable of driving on said PC beam; 상기 대차에 의해 지지되는 본체와;A main body supported by the bogie; 상기 본체의 양끝단에서 각각 하방으로 수직 연장된 지지암과;Support arms vertically extending downward from both ends of the main body; 상기 각각의 지지암의 하측 일단에 위치한 로테이션부와;A rotation part located at one lower end of each support arm; 상기 각각의 로테이션부에 의해 회전가능하고 작업자가 상기 철근 및 거푸집 작업을 위한 작업 공간으로 활용하는 작업대Worktable that is rotatable by the respective rotation part and used by the worker as a work space for the rebar and formwork 를 포함하는 거푸집 설치 및 해체장치Formwork installation and dismantling device including 청구항 1에 있어서,The method according to claim 1, 상기 대차는 모터 등의 동력 장치와 이동로인 레일을 포함하고 있으며,The bogie includes a power device such as a motor and a rail that is a moving path. 상기 레일은 용접 또는 클램프 체결 등의 방법에 의해 PC빔 상부 철근 위에 고정되는 거푸집 설치 및 해체장치The rail is installed and dismantled in the formwork fixed to the upper beam of the PC beam by welding or clamp fastening method 청구항 1에 있어서,The method according to claim 1, 상기 본체는 배터리 또는 제너레이터 등의 전원 장치를 포함하고,The main body includes a power supply such as a battery or a generator, 상기 지지암은 슬루잉 베어링과 고정 기어부를 포함하며,The support arm includes a slewing bearing and a fixed gear portion, 상기 로테이션부는 모터와 기어 박스를 포함하는 거푸집 설치 및 해체 장치The rotation unit is a formwork installation and dismantling device comprising a motor and a gear box 청구항 1에 있어서,The method according to claim 1, 상기 작업대는 적어도 하나 이상의 작업대 체결 장치를 포함하는The workbench includes at least one workbench fastening device. 거푸집 설치 및 해체 장치Formwork installation and dismantling device
KR1020000038622A 2000-07-06 2000-07-06 Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method KR20020005249A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020000038622A KR20020005249A (en) 2000-07-06 2000-07-06 Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000038622A KR20020005249A (en) 2000-07-06 2000-07-06 Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020000019364U Division KR200213384Y1 (en) 2000-07-06 2000-07-06 Apparatus for setting and removing forms

Publications (1)

Publication Number Publication Date
KR20020005249A true KR20020005249A (en) 2002-01-17

Family

ID=19676610

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020000038622A KR20020005249A (en) 2000-07-06 2000-07-06 Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method

Country Status (1)

Country Link
KR (1) KR20020005249A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100504426B1 (en) * 2002-05-13 2005-07-28 최성문 Movable Bridge Inspection Device
CN102660925A (en) * 2012-06-06 2012-09-12 长安大学 Moveable formwork for variable-width curved bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57174506A (en) * 1981-04-20 1982-10-27 Kayaba Industry Co Ltd Bridge inspection car for long and large bridge
JPH03110208A (en) * 1989-09-25 1991-05-10 Miyaji Tekkosho:Kk Mobile scaffold device for bridge and assembling method for same
KR0160244B1 (en) * 1996-01-25 1999-01-15 전장열 Working stand for both bridge construction and management
KR20000049885A (en) * 2000-05-04 2000-08-05 이석원 Working automobile for check and maintenance of bridges
KR20000050166A (en) * 2000-05-19 2000-08-05 김태환 Working platform for bridge construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57174506A (en) * 1981-04-20 1982-10-27 Kayaba Industry Co Ltd Bridge inspection car for long and large bridge
JPH03110208A (en) * 1989-09-25 1991-05-10 Miyaji Tekkosho:Kk Mobile scaffold device for bridge and assembling method for same
KR0160244B1 (en) * 1996-01-25 1999-01-15 전장열 Working stand for both bridge construction and management
KR20000049885A (en) * 2000-05-04 2000-08-05 이석원 Working automobile for check and maintenance of bridges
KR20000050166A (en) * 2000-05-19 2000-08-05 김태환 Working platform for bridge construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100504426B1 (en) * 2002-05-13 2005-07-28 최성문 Movable Bridge Inspection Device
CN102660925A (en) * 2012-06-06 2012-09-12 长安大学 Moveable formwork for variable-width curved bridge
CN102660925B (en) * 2012-06-06 2014-01-15 长安大学 Moveable formwork for variable-width curved bridge

Similar Documents

Publication Publication Date Title
CN107338727B (en) Integrally-disassembled and assembled anti-collision wall template and walking type rail hanging and moving system thereof
JP4504910B2 (en) Dolly and method of erection of temporary pier using it
JP2007138514A (en) Erection method of girder
JP2010121284A (en) Construction method of steel structure
KR100991190B1 (en) The bridge inspection and the repair method for which a circular travelling rail mobile bridge inspection car and this were used
CN105569385B (en) Building industrialization PC component production line mounting and testing techniques
WO1996007795A1 (en) Bridge construction machinery and method for constructing bridges
JP2017020290A (en) Disassembling method of bridge
JP6876573B2 (en) Suspended scaffolding device
CN110745574A (en) Installation method of gate type scraper reclaimer
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
JPH111910A (en) Bridge construction method by erection and replacement
KR100432811B1 (en) The method for checking bridge
JP2008050811A (en) Movable suspended scaffolding apparatus
KR200213384Y1 (en) Apparatus for setting and removing forms
KR20020005249A (en) Apparatus for setting reinforcing steels or forms for cross beam and removing forms applicable to a P.C. beam or steel box method
CN212532065U (en) Gantry crane capable of being used in different height difference places
CN110904853B (en) Construction method for automatic lifting operation platform for mounting high-speed railway pier body lifting rail
KR102149417B1 (en) Moving Lift Scaffold System
CN111139742B (en) Method for mounting and dismounting highway bridge girder erection machine
JP2005307684A (en) Laying apparatus of precast concrete floor board
KR200213385Y1 (en) Appparatus for removing slab forms
KR100367028B1 (en) A self propelled working platform for construction and maintenance of bridge
JP4425611B2 (en) Installation method of scaffolding for bridge girder repair painting work and scaffold equipment for bridge girder repair painting work
CN217629425U (en) Sliding form device for construction of ultra-wide pier

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application