KR200189590Y1 - A cover for a steel tube - Google Patents

A cover for a steel tube Download PDF

Info

Publication number
KR200189590Y1
KR200189590Y1 KR2020000005350U KR20000005350U KR200189590Y1 KR 200189590 Y1 KR200189590 Y1 KR 200189590Y1 KR 2020000005350 U KR2020000005350 U KR 2020000005350U KR 20000005350 U KR20000005350 U KR 20000005350U KR 200189590 Y1 KR200189590 Y1 KR 200189590Y1
Authority
KR
South Korea
Prior art keywords
steel pipe
cover plate
present
construction
reinforcement
Prior art date
Application number
KR2020000005350U
Other languages
Korean (ko)
Inventor
고환택
Original Assignee
코리아테크엔지니어링주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 코리아테크엔지니어링주식회사 filed Critical 코리아테크엔지니어링주식회사
Priority to KR2020000005350U priority Critical patent/KR200189590Y1/en
Application granted granted Critical
Publication of KR200189590Y1 publication Critical patent/KR200189590Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/226Protecting piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/223Details of top sections of foundation piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 고안은 교량등 건출물의 시공 시 지반을 다지기 위한 지정작업에 사용되는 강관 말뚝용 덮개판에 관한 것으로, 좀 더 상세하게는 강관에 의한 지정작업시 강관의 상부로 기초콘크리트를 치기 위한 배근에 있어서 강관과 덮개판을 체결하여 강도를 증대시킨 강관 말뚝용 덮개판에 관한 것이다. 본 고안은 원판의 외주면에 적어도 하나 이상의 홈이 형성되고, 다수의 체결공이 형성되는 원판과; 상기 원판의 하부에 고정되고, 내측에 암나사부가 형성되는 원형보강판으로 이루어져 상기 강관과 체결되고, 상기 홈은 사각형 또는 다각형으로 이루어진다.The present invention relates to a cover plate for steel pipe piles used for designating works for compacting the ground during the construction of buildings such as bridges, and more specifically, in the reinforcement for striking the foundation concrete to the top of steel pipes during designation work by steel pipes. It relates to a cover plate for steel pipe piles to increase the strength by fastening the steel pipe and the cover plate. The present invention is at least one groove is formed on the outer circumferential surface of the disk, and a plurality of fastening holes are formed; It is fixed to the lower portion of the disk, and consists of a circular reinforcement plate is formed inside the female screw portion is fastened to the steel pipe, the groove is made of a square or polygon.

상기와 같은 본 고안은 덮개판을 공장에서 제작하여 시공하므로 품질의 고급화를 이룰 수 있고, 별도의 유압 타공기를 사용하지 않아도 됨과 동시에 일정한 규격을 갖출 수 있게 되므로서 시공시간이 단축되는 효과가 있다.The present invention as described above can be achieved by the manufacturing of the cover plate in the factory to achieve high quality, it is possible to shorten the construction time by not having to use a separate hydraulic perforator and at the same time having a certain standard. .

또한 종래의 볼트식 머리 보강방법보다 적은 인원으로도 쉽고 빠르게 조립할 수 있으므로 공사비가 절감되는 우수한 효과가 있는 것이다.In addition, since it can be easily and quickly assembled with fewer personnel than the conventional bolt head reinforcement method, there is an excellent effect of reducing the construction cost.

Description

강관 말뚝용 덮개판{A cover for a steel tube}Cover plate for steel pipe piles {A cover for a steel tube}

본 고안은 교량등 건출물의 시공 시 지반을 다지기 위한 지정작업에 사용되는 강관 말뚝용 덮개판에 관한 것으로, 좀 더 상세하게는 강관에 의한 지정작업시 강관의 상부로 기초콘크리트를 치기 위한 배근에 있어서 강관과 덮개판을 체결하여 강도를 증대시킨 강관 말뚝용 덮개판에 관한 것이다.The present invention relates to a cover plate for steel pipe piles used for designating works for compacting the ground during the construction of buildings such as bridges, and more specifically, in the reinforcement for striking the foundation concrete to the top of steel pipes during designation work by steel pipes. It relates to a cover plate for steel pipe piles to increase the strength by fastening the steel pipe and the cover plate.

일반적으로 교량 및 건축물의 시공시 지반이 무른 경우에 지반의 강도 증대를 위해 지반 다지기를 한다.In general, when the ground is soft when constructing bridges and buildings, ground compaction is performed to increase the strength of the ground.

지반 다지기에는 보통지정과 말뚝지정 및 깊은 기초지정으로 분류할 수 있는데 상기 말뚝지정은 다시 나무말뚝지정, 기성 콘크리트지정, 푸리 스트레스 콘크리트말뚝, 강제말뚝 등으로 나뉘어지게 된다.The ground compactor can be classified into ordinary designation, pile designation, and deep foundation designation. The pile designation is divided into wood pile designation, ready-made concrete designation, four-stress concrete pile, and forced pile.

본 고안은 상기 말뚝지정 중 강제말뚝 지정에 사용되는 덮개판을 고안한 것으로, 종래의 강관 말뚝용 덮개판을 설명하면 다음과 같다.The present invention devised a cover plate to be used for the designation of the forced pile of the pile designation, a description of the conventional steel pipe pile cover plate as follows.

도 1은 종래의 강관 말뚝용 덮개판의 구조를 보여주는 사시도이고, 도 2는 도 1의 단면도이다.1 is a perspective view showing the structure of a conventional steel pipe pile cover plate, Figure 2 is a cross-sectional view of FIG.

우선, 강관(100)의 상단부 외주면에 90도 간격으로 네 방향에 다수의 체결공(114)이 형성된다.First, a plurality of fastening holes 114 are formed in four directions at 90 degree intervals on the outer circumferential surface of the upper end of the steel pipe 100.

그리고, 덮개판(110)은 원판(114)의 하부에 십자 보강판(112)을 고정시키고, 상기 원판(114)에는 하단부에 수나사부(121)가 형성된 철근(120)이 체결될 수 있도록 다수의 나사공(111)이 원둘레를 따라 형성되어 있으며, 일부 나사공(111)은 90도 간격으로 네 방향에 서로 마주보도록 관통되어 있다.In addition, the cover plate 110 is fixed to the cross reinforcement plate 112 in the lower portion of the disc 114, a plurality of reinforcing bars 120, the male screw portion 121 is formed on the lower end portion 114 is fastened to the disc 114. The screw holes 111 are formed along the circumference, and some screw holes 111 are penetrated to face each other in four directions at 90 degree intervals.

이때, 상기 십자 보강판(120) 각각의 상부 면에는 나사공(111)이 형성되어 있고, 그 측면에도 다수의 나사공(111)이 각각 형성되어져 상기 덮개판(110)과 상기 강관(100)의 결합시 고정볼트(B)에 의해 체결되어 진다.At this time, the screw hole 111 is formed on the upper surface of each of the cross reinforcement plate 120, a plurality of screw holes 111 are formed on the side surface of the cover plate 110 and the steel pipe 100, respectively It is fastened by fixing bolts (B) at the time of coupling.

그리고, 상기 원판(114)에 형성된 다수의 나사공(111)에는 다수의 철근(120)이 원둘레를 따라 체결되어 무른 지반의 강도를 증대시킨다.In addition, a plurality of reinforcing bars 120 are fastened along the circumference of the plurality of screw holes 111 formed in the disc 114 to increase the strength of the soft ground.

상기와 같은 다수의 볼트를 이용한 볼트식 두부 보강방법의 시공을 살펴보면, 우선 확대기초 저면에서 20Cm를 남겨두고, 자동절단기를 이용하여 강관(100) 말뚝을 절단하고, 타공위치를 표시할 수 있는 유도기를 강관말뚝에 씌우고, 정을 이용하여 강관(100) 말뚝 머리 측면부분에 8개의 타공위치를 표시한 후, 표시된 타공위치에 유압 타공기를 이용하여 8개의 볼트 구멍을 형성한다.Looking at the construction of the bolt-type head reinforcement method using a plurality of bolts as described above, first leave the 20Cm at the bottom of the enlarged base, using the automatic cutting machine to cut the steel pipe 100 piles, and can mark the punching position Put on the steel pipe pile, and using the chisel to mark the eight punching positions on the side of the steel pipe 100 pile head, and forms the eight bolt holes using the hydraulic perforator at the marked punching position.

그 후, 공장제품인 덮개판(110)을 강관(100) 말뚝 내부에 삽입하고, 십자보강판(112)에 형선된 나사구멍과 강관(100)에 형성된 나사구멍을 일치시켜 16개의 볼트로 체결한다. 이때, 확대 기초 저면에서 10Cm 정도의 버림 콘크리트를 타설하고, 확대기초 하부철근을 조립하면서 부풀림 보강철근을 원형 덮개판 나사구멍에 볼트 8개를 체결하고, 확대기초 잔여 철근조립과 콘크리트를 타설하여 시공을 끝낸다.Thereafter, the cover plate 110, which is a factory product, is inserted into the steel pipe 100 pile, and the screw holes formed in the cross reinforcing plate 112 and the screw holes formed in the steel pipe 100 are matched and fastened with 16 bolts. . At this time, cast the discarded concrete of about 10cm from the bottom of the expanded foundation, assemble the expanded reinforcement reinforcement, fasten the eight reinforcement reinforcing bars into the circular cover plate screw hole, and install the expanded foundation reinforcement assembly and concrete. Ends.

그러나, 상기와 같은 덮개판의 경우에 유압 타공기를 이용하여 강관에 다수의 나사공을 형성하고, 덮개판에도 다수의 나사공을 형성하여야 했으므로 장치의 비용이 증가하였고, 작업이 번거로왔으며 작업시간도 오래 걸리는 단점이 있었다.However, in the case of the cover plate as described above, a number of screw holes must be formed in the steel pipe by using a hydraulic perforator and a plurality of screw holes must also be formed in the cover plate, thereby increasing the cost of the apparatus, and the work has been cumbersome. It also took a long time.

또한, 나사공 형성작업을 끝낸 후 강관과 덮개판을 고정볼트에 의해 결합하여야 했으므로 많은 인력을 필요로 하였고, 적은 인원으로 작업을 할 경우에는 작업시간이 오래 걸려 공사기간이 길어지는 문제점이 있었다.In addition, since the steel pipe and the cover plate had to be combined by fixing bolts after finishing the formation of the screw holes, a large number of manpower was required.

본 고안은 상기와 같은 문제점을 해결하기 위해 안출된 것으로서, 별도의 유압 타공기를 이용한 나사공 형성작업을 하지 않으므로 비용을 절감하고 적은 인원으로도 작업을 할 수 있으며, 시공이 간단하고 빠르게 이루어지는 강관 말뚝용 덮개판을 제공하는 것을 그 목적으로 한다.The present invention has been devised to solve the above problems, it is possible to reduce the cost and work with a small number of people, because it does not form a screw hole using a separate hydraulic perforator, the construction is simple and fast construction It is an object to provide a cover plate for a pile.

도 1은 종래의 강관 말뚝용 덮개판의 구조를 보여주는 사시도1 is a perspective view showing the structure of a cover plate for a conventional steel pipe pile

도 2는 도 1의 단면도2 is a cross-sectional view of FIG.

도 3은 본 고안의 강관 말뚝용 덮개판의 구조를 보여주는 사시도Figure 3 is a perspective view showing the structure of the cover plate for steel pipe piles of the present invention

도 4는 본 고안의 분해 사시도4 is an exploded perspective view of the present invention

도 5는 본 고안의 덮개판을 보여주는 단면도5 is a cross-sectional view showing a cover plate of the present invention

도 6은 본 고안의 덮개판에 결합되는 강관을 보여주는 정면도6 is a front view showing a steel pipe coupled to the cover plate of the present invention

* 도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings

10 : 원판 12 : 홈10: negative 12: groove

14 : 원통 보강판 16 : 암나사부14: cylindrical reinforcement plate 16: female thread portion

18 : 철근 20 : 체결부18: rebar 20: fastening portion

22 : 체결공 24 : 강관22: fastener 24: steel pipe

26 : 수나사부26: male thread

상기한 바와 같은 목적을 달성하기 위한 본 고안은 원판의 외주면에 적어도 하나 이상의 홈이 형성되고, 다수의 체결공이 형성되는 원판과; 상기 원판의 하부에 고정되고, 내측에 암나사부가 형성되는 원형보강판으로 이루어져 상기 강관과 체결되고, 상기 홈은 사각형 또는 다각형으로 이루어지는 것을 특징으로 한다.The present invention for achieving the object as described above is at least one groove is formed on the outer peripheral surface of the disc, the disc is formed with a plurality of fastening holes; It is fixed to the lower portion of the disc, consisting of a circular reinforcing plate is formed inside the female screw portion is fastened with the steel pipe, the groove is characterized in that consisting of a square or polygon.

이상에서와 같은 본 고안의 바람직한 실시예를 첨부된 도면을 참고하여 상세히 설명하기로 한다.Preferred embodiments of the present invention as described above will be described in detail with reference to the accompanying drawings.

도 3은 본 고안의 강관 말뚝용 덮개판의 구조를 보여주는 사시도이고, 도 4는 본 고안의 분해 사시도이고, 도 5는 본 고안의 덮개판을 보여주는 단면도이며, 도 6은 본 고안의 덮개판에 결합되는 강관을 보여주는 정면도이다.Figure 3 is a perspective view showing the structure of the steel plate pile cover plate of the present invention, Figure 4 is an exploded perspective view of the present invention, Figure 5 is a cross-sectional view showing a cover plate of the present invention, Figure 6 is a cover plate of the present invention Front view showing the steel pipe being joined.

도 1 내지 도 6을 참조하여 본 고안을 설명하여 보면, 먼저 도 6에 도시된 바와 같이, 강관(24)의 상단부에 일정한 길이의 수나사부(26)가 형성되어 있다.Referring to the present invention with reference to Figures 1 to 6, first, as shown in Figure 6, the male screw portion 26 of a predetermined length is formed at the upper end of the steel pipe (24).

그리고, 도 5에 도시되어 있는 바와 같이, 덮개판(28)은 상부면에 다수의 체결공(22)이 형성된 원판(10)과, 내측에 암나사부(16)가 형성된 원통 보강판(14)으로 이루어진다. 이때 상기 원판(10)의 외주면에는 대칭으로 사각형상의 홈(12)을 형성시키고, 이 홈(12)에 바아(Bar)(도시안함)를 끼워서 작업자들이 손쉽게 회전시킬 수 있도록 한다. 상기 홈(12)은 본 고안에서는 바람직하게 사각형상으로 이루어졌지만 다양하게는 원형의 관통공을 형성하여도 좋고, 다각형을 갖는 형상이어도 가능하다. 이는 당업자라면 용이하게 실시할 수 있다고 생각되므로 더욱 구체적으로 언급하지 않기로 한다.As shown in FIG. 5, the cover plate 28 includes a disc 10 having a plurality of fastening holes 22 formed thereon, and a cylindrical reinforcing plate 14 having female threads 16 formed therein. Is done. At this time, the outer circumferential surface of the disc 10 to form a symmetrical rectangular groove 12, and put a bar (not shown) in the groove 12 so that workers can easily rotate. In the present invention, the groove 12 is preferably formed in a rectangular shape, but may be formed in a variety of circular through holes, or may have a polygonal shape. This will be described by those skilled in the art, and thus will not be described in more detail.

상기 원판(10)의 체결공(22)에는 철근(18)이 끼워지게 되는데, 철근(18)의 하단부에는 나사산이 형성된 체결부(20)가 형성되어져 상기 체결공(22)과 서로 체결된다.Reinforcing bar 18 is inserted into the fastening hole 22 of the disc 10, the lower end of the reinforcing bar 18 is formed with a fastening portion 20 is formed with a screw thread is fastened with the fastening hole 22.

상기 원통 보강판(14)은 상기 원판(10)의 하부에 용접시킴으로써 지지 강도를 증대시킨다.The cylindrical reinforcing plate 14 is welded to the lower portion of the disk 10 to increase the support strength.

상기한 바와 같이 본 고안에서는 원통 보강판(14)을 원판(10)의 하부에 용접시키도록 이루어지지만 상기 원판(10)과 원통 보강판(14)을 일체로 형성하는 것은 당업자라면 누구나 용이하게 실시할 수 있는 자명한 것이라 하겠다.As described above, in the present invention, the cylindrical reinforcing plate 14 is made to be welded to the lower part of the disc 10, but it is easy for anyone skilled in the art to form the disc 10 and the cylindrical reinforcing plate 14 integrally. It is obvious that you can do it.

계속해서, 본 고안의 나사식 강관 말뚝 머리 보강공법에 대해 설명하여 보면, 우선 확대기초 저면에서 20Cm를 남겨두고, 자동 절단기로 강관(24) 말뚝을 절단한다.Subsequently, the screw-type steel pipe pile head reinforcement method of the present invention will be described. First, the steel pipe 24 is cut with an automatic cutter, leaving 20 cm at the bottom of the expanded base.

그리고, 상기 절단된 강관(24) 말뚝을 나사산 가공기로 강과 외면에 수나사부(26)를 가공한다.Then, the male pipe portion 26 is processed on the steel and the outer surface of the cut steel pipe 24 pile by a thread processing machine.

이때, 공장에서 제작된 덮개판(28)을 상기 강관(24)의 수나사부(26)에 체결한다.At this time, the cover plate 28 manufactured at the factory is fastened to the male threaded portion 26 of the steel pipe 24.

이어서, 확대기초 저면에서 버림콘크리트를 10Cm 타설하고, 확대기초 하부철근을 조립하면서 다수의 부풀림 보강 철근(18)을 상기 덮개판(18)의 체결공(22)에 체결한 후, 확대기초 잔여 철근조립 및 콘크리트를 타설하여 공사를 마무리 한다.Subsequently, cast concrete 10 cm from the bottom of the expanded foundation, and fasten the plurality of inflated reinforcing bars 18 to the fastening holes 22 of the cover plate 18 while assembling the expanded foundation lower reinforcing bars, and then expand the residual foundation reinforced bars. Finish the construction by assembling and pouring concrete.

상기와 같은 본 고안을 기존의 볼트식 두부 보강방법과 비교하여 보면 다음표와 같다.Compared with the present invention as compared to the conventional bolt type head reinforcement method is as follows.

1) 강관의 지름이 406.4mm 인 경우1) When the diameter of the steel pipe is 406.4mm

구분division 볼트식(85kg)Bolt type (85 kg) 본 고안(55kg)This design (55 kg) 공장제품 가공비Factory product processing cost 112,450원1,320원/kg당KRW 1,320 per kg 72,770원1,320원/kg당KRW 72,770 per 1,320 KRW / kg 현장가공비 및 시공비(철근조립포함)On-site processing and construction costs (including rebar assembly) 34,340원KRW 34,340 38,820원38,820 won 직접 공사비Direct construction cost 146,820원/개당1,730원/kg당146,820 won / each 1,730 won / kg 111,590원/개당2,030원/kg당111,590 won / each 2,030 won / kg 총 공사비(직접공사비*1.5배)Total construction cost (direct construction cost * 1.5 times) 220,240원/개당220,240 won / each 167,380원/개당167,380 won / each

상기 표에서는 강관의 지름이 406.4mm 인 경우를 예로 들어 표시하였으나, 강관의 지름이 더욱 커질 경우 그에 따른 인원 및 경비의 절감 효과는 더욱 더 커지게 된다.In the above table, the case where the diameter of the steel pipe is 406.4 mm is shown as an example, but when the diameter of the steel pipe is larger, the effect of reducing the number of personnel and expenses is further increased.

상기와 같은 본 고안은 덮개판을 공장에서 제작하여 시공하므로 품질의 고급화를 이룰 수 있고, 별도의 유압 타공기를 사용하지 않아도 됨과 동시에 일정한 규격을 갖출 수 있게 되므로서 시공시간이 단축되는 효과가 있다.The present invention as described above can be achieved by the manufacturing of the cover plate in the factory to achieve high quality, it is possible to shorten the construction time by not having to use a separate hydraulic perforator and at the same time having a certain standard. .

또한 종래의 볼트식 머리 보강방법보다 적은 인원으로도 쉽고 빠르게 조립할 수 있으므로 공사비가 절감되는 우수한 효과가 있는 것이다.In addition, since it can be easily and quickly assembled with fewer personnel than the conventional bolt head reinforcement method, there is an excellent effect of reducing the construction cost.

Claims (2)

강관 말뚝의 상부에 씌워지는 덮개판에 있어서,In the cover plate which is covered on the upper part of the steel pipe pile, 원판의 외주면에 적어도 하나 이상의 홈이 형성되고, 다수의 체결공이 형성되는 원판과;At least one groove is formed on the outer circumferential surface of the disc, the disc is formed with a plurality of fastening holes; 상기 원판의 하부에 고정되고, 내측에 암나사부가 형성되는 원형보강판으로 이루어져 상기 강관과 체결되는 것을 특징으로 하는 강관 말뚝용 덮개판.Steel plate pile cover plate is fixed to the lower portion of the disk, the inner thread consisting of a circular reinforcing plate formed with a female screw portion is fastened to the steel pipe. 제 1항에 있어서, 상기 홈은 사각형 또는 다각형으로 이루어지는 것을 특징으로 하는 강관 말뚝용 덮개판.The cover plate for a steel pipe pile according to claim 1, wherein the groove is formed in a square or a polygon.
KR2020000005350U 2000-02-26 2000-02-26 A cover for a steel tube KR200189590Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020000005350U KR200189590Y1 (en) 2000-02-26 2000-02-26 A cover for a steel tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020000005350U KR200189590Y1 (en) 2000-02-26 2000-02-26 A cover for a steel tube

Publications (1)

Publication Number Publication Date
KR200189590Y1 true KR200189590Y1 (en) 2000-07-15

Family

ID=19644076

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020000005350U KR200189590Y1 (en) 2000-02-26 2000-02-26 A cover for a steel tube

Country Status (1)

Country Link
KR (1) KR200189590Y1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020079082A (en) * 2001-04-13 2002-10-19 구일건설(주) Structure method of head cover for steel tube file and its structure
KR100791263B1 (en) 2006-10-13 2008-01-04 김정빈 Bolt type pile cap and the manufacture method of this
KR100837263B1 (en) * 2007-02-16 2008-06-11 (주)석탑엔지니어링 Composite pile making method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020079082A (en) * 2001-04-13 2002-10-19 구일건설(주) Structure method of head cover for steel tube file and its structure
KR100791263B1 (en) 2006-10-13 2008-01-04 김정빈 Bolt type pile cap and the manufacture method of this
KR100837263B1 (en) * 2007-02-16 2008-06-11 (주)석탑엔지니어링 Composite pile making method

Similar Documents

Publication Publication Date Title
JP2001311169A (en) Block for earth retaining wall
WO2002068776A3 (en) Concrete form system
KR200189590Y1 (en) A cover for a steel tube
US20040226236A1 (en) Foundation structure
CN211899268U (en) Precast concrete post and pre-buried anchor slab connection structure
US6178651B1 (en) Reusable batter board support
US3292329A (en) Building construction
JP2006194062A (en) Connection for connecting floor post footing and floor post
CN213115520U (en) Concrete turn-ups reinforcement tool
KR100867976B1 (en) A pile head reinforcement device of precast concrete pile
CN111042440A (en) Precast concrete post and pre-buried anchor slab connection structure
KR200342284Y1 (en) Connecting structure for construction mold
JP2006193985A (en) Concrete construction joint method
WO1982000170A1 (en) Fence construction
KR100522746B1 (en) A Dismounting Structure Form And Manufacturing Method Thereof
AU2018100695A4 (en) A retaining wall arrangement
CN209760790U (en) novel combined template
KR200291542Y1 (en) Construction form tie bolt assembly for underground breast wall
CN215858607U (en) Combined column capable of reducing anchoring depth
US11988013B2 (en) Wall assemblies, systems, and methods thereof
KR20120133871A (en) Support for a upper reinforcing bar of footings
CN219138053U (en) Mutual-bearing brick without cement mortise and tenon structure
JP3744922B2 (en) PC foundation beam member and its connection structure
KR200149657Y1 (en) A stopper for steel reinforcing connection
KR20030056008A (en) Panel Assembly for Ground Protection of Earths Wall and Destruction Method of it

Legal Events

Date Code Title Description
REGI Registration of establishment
LAPS Lapse due to unpaid annual fee
T701 Written decision to grant on technology evaluation