KR20010008545A - Spacer for separation construction of concrete framework - Google Patents

Spacer for separation construction of concrete framework Download PDF

Info

Publication number
KR20010008545A
KR20010008545A KR1019990026435A KR19990026435A KR20010008545A KR 20010008545 A KR20010008545 A KR 20010008545A KR 1019990026435 A KR1019990026435 A KR 1019990026435A KR 19990026435 A KR19990026435 A KR 19990026435A KR 20010008545 A KR20010008545 A KR 20010008545A
Authority
KR
South Korea
Prior art keywords
spacer
concrete
concrete structure
construction
vinyl film
Prior art date
Application number
KR1019990026435A
Other languages
Korean (ko)
Other versions
KR100335175B1 (en
Inventor
전홍건
Original Assignee
전홍건
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 전홍건 filed Critical 전홍건
Priority to KR1019990026435A priority Critical patent/KR100335175B1/en
Publication of KR20010008545A publication Critical patent/KR20010008545A/en
Application granted granted Critical
Publication of KR100335175B1 publication Critical patent/KR100335175B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE: A spacer for a separate construction of a concrete structure is provided to easily and rapidly remove the space interposed a gap for separate construction of concrete structure. CONSTITUTION: spacer for a separate construction of a concrete structure includes at least two vinyl films(10) piled one over another, air layers(11) densely formed keeping a proper thickness at the center of the vinyl films, a wire(20) of fine diameter providing a shear force to the vinyl film on a joining surface between the air layers, and a coated sheet(30) bonded at both sides of the vinyl films and forming flat surface when pouring concrete. The vinyl films having the air layers and the coated sheet attached to both sides of the vinyl films are wound in a scroll.

Description

콘크리트 구조물의 분리시공을 위한 스페이서{SPACER FOR SEPARATION CONSTRUCTION OF CONCRETE FRAMEWORK}Spacer for separation and construction of concrete structures {SPACER FOR SEPARATION CONSTRUCTION OF CONCRETE FRAMEWORK}

본 발명은 콘크리트 구조물의 분리시공을 위한 스페이서, 보다 상세하게는 교량의 중앙분리대와 난간 및 방호벽 등 길이가 긴 콘크리트 구조물의 일정구간 또는 특정 부위를 틈새 형태로 분리시켜 시공할 때 콘크리트가 양생될 때까지 틈새를 유지하게 일시적으로 개입설치하는 스페이서를 간편하게 제거함과 아울러 시공에 따른 취급을 용이하게 할 수 있게 한 콘크리트 구조물의 분리시공을 위한 스페이서에 관한 것이다.The present invention is a spacer for separating construction of concrete structures, more specifically, when concrete is cured when separating a certain section or a specific portion of a long concrete structure such as a bridge and a barrier and a protective wall in the form of a gap The present invention relates to a spacer for separation and construction of a concrete structure that allows easy removal of a spacer temporarily intervening to maintain a gap and facilitates handling according to construction.

일반적으로, 도 1a 내지 1c에서와 같이 콘크리트로 된 교량의 중앙분리대(1)와 옹벽(2) 및 난간 등 비교적 길이가 긴 각종 구조물은 기후변화에 따른 온도차이에 의해 미세한 길이 만큼 늘고 줄어드는 신축현상이 불가피 하였다.Generally, as shown in FIGS. 1A to 1C, various structures having a relatively long length such as a median divider 1, a retaining wall 2, and a railing of a concrete bridge are expanded and shrunk by a minute length due to a temperature difference due to climate change. This was inevitable.

이러한 신축현상은 콘크리트 구조물의 내구수명을 단축시키는 요인이 됨으로써 신축현상을 흡수할 수 있는 설계가 필수적이었고, 이에 구조물의 크기에 비례하여 일정구간 및 특정부위에 약간의 틈새(G)를 유지하게 분리 시공하는 방법이 보편화 되었다.This expansion phenomenon is a factor to shorten the durability life of the concrete structure, so it was necessary to design a design that can absorb the expansion phenomenon, and to maintain a small gap (G) in a certain section and specific areas in proportion to the size of the structure Construction methods have become commonplace.

종래에 콘크리트 구조물을 분리시공 하기 위해 사용되는 스페이서(S)는 그 두께가 약 10~20mm 내외인 스치로폼판 또는 합판이 주종을 이루었으나, 합판의 경우에는 표면이 거칠고 시공에 따른 취급이 번거로웠으므로, 비교적 취급이 용이하고 경제적인 스치로폼판을 선호하고 있는 추세이다.Conventionally, the spacer (S) used for separating and constructing a concrete structure is mainly composed of a styrofoam plate or plywood having a thickness of about 10-20 mm, but in the case of plywood, the surface is rough and cumbersome to handle according to construction. However, the trend is to prefer styrofoam plates that are relatively easy to handle and economical.

그러나, 상기 스치로폼판은 외압이나 충격 및 인장력에 취약한 재질로 되어 있으므로, 콘크리트 구조물의 스페이서로 사용하기 위해 정해진 위치에 설치하여 콘크리트를 타설하고 타설된 콘크리트가 양생된 후 제거할 때 스치로폼판의 양측에 접촉된 콘크리트벽으로부터 큰 압력을 받게 되는 협착현상에 의해 스티로폼판을 원활히 제거할 수 없었다.However, since the styrofoam plate is made of a material that is vulnerable to external pressure, impact and tensile force, it is installed at a predetermined position for use as a spacer of the concrete structure, and the concrete is poured on both sides of the styrofoam plate when the concrete is cured and then removed. The styrofoam plate could not be removed smoothly due to the stenosis which is under great pressure from the contacted concrete wall.

그러므로, 간격이 매우 협소한 틈새(G)로부터 제거되지 않고 잔류된 스티로폼을 제거하기 위한 수단으로 구조물의 틈새에 비해 두께 및 직경이 작은 도구를 이용하여 강제로 밀어내거나 파내는 수작업을 하였으므로, 이 과정에서 많은 작업시간과 일손을 필요로 하였음은 물론 제거된 스치로폼을 수거하기 위해 별도의 공정이 소요되는 문제점이 있었다.Therefore, as a means for removing the remaining styrofoam without being removed from the gap (G) where the gap is very narrow, the manual operation is forcibly pushed out or dug by using a tool having a smaller thickness and diameter than the gap of the structure. It required a lot of work time and work as well as a problem that takes a separate process to collect the removed styrofoam.

콘크리트 구조물의 틈새에 잔류된 스티로폼판을 제거하기 위한 다른 예로서 화학약품을 사용하여 녹이거나 가연성 연료를 사용하여 태우는 등 화학적 방법으로 제거하게 된 기술도 이용되었으나, 이 경우에는 콘크리트 구조물에 흔적을 남기게 되어 구조물의 표면을 보수해야되는 번거로움과 공해를 유발하는 등의 문제점이 있었다.As another example of removing styrofoam plates remaining in the gaps of concrete structures, chemical techniques such as melting with chemicals or burning with flammable fuels have been used. There has been a problem such as causing trouble and pollution to repair the surface of the structure.

본 발명은 위와 같은 종래의 스페이서로 사용되던 스치로폼의 문제점을 감안하여 안출한 것으로, 그 목적은 콘크리트 구조물을 분리시공하기 위해 틈새에 임시로 개재시킨 스페이서를 간편하고 신속하게 제거할 수 있는 콘크리트 구조물의 분리시공을 위한 스페이서를 제공하는 것이다.The present invention has been made in view of the problems of the styrofoam that was used as a conventional spacer as described above, the purpose of the concrete structure that can be easily and quickly remove the spacer temporarily interposed in the gap to separate construction of the concrete structure It is to provide a spacer for separation.

본 발명의 다른 목적은 스페이서의 제작을 간편하게 함과 아울러 보관 및 취급을 용이하게 할 수 있는 콘크리트 구조물의 분리시공을 위한 스페이서를 제공함에 있다.Another object of the present invention is to provide a spacer for the separation construction of a concrete structure that can simplify the manufacture of the spacer and facilitate the storage and handling.

이러한 목적을 달성하기 위한 본 발명은, 적어도 두장의 비닐필름을 중첩되게 접합하되 그 중앙부에 적정 두께를 유지되도록 하는 공기층이 조밀한 상태로 형성되고, 상기 공기층의 사이에 위치하는 접합면에는 비닐필름에 인장력을 제공하는 미세한 직경의 와이어가 일체로 부착되며, 상기 비닐필름의 양측면에는 그 공기층의 돌출된 부위를 덮여지도록 하여 콘크리트를 타설할 때 평편한 표면을 형성하여 주는 합성수지재의 피복시트가 접합되어 있고, 상기 공기층을 가진 비닐필름과 그 양측에 부착되는 피복시트를 길이 방향으로 길게 형성하여 두루말이 형태로 감겨지도록 한것을 특징으로 한다.In order to achieve the above object, the present invention provides a dense state in which an air layer is formed in a dense state in which at least two sheets of vinyl film are superimposed to maintain an appropriate thickness at a central portion thereof, and a vinyl film is disposed on the bonding surface between the air layers. Wires of fine diameter providing tensile force to the body are integrally attached to each other, and both sides of the vinyl film are covered to cover the protruding portions of the air layer so that a coated sheet of synthetic resin material is formed to form a flat surface when concrete is poured. And, the vinyl film having the air layer and the coating sheet attached to both sides of the length is formed in the longitudinal direction is characterized in that the roll is wound in the form.

도 1a 내지 1c는 일반적인 길이가 긴 콘크리트 구조물의 분리시공 상태를 각각 나타낸 구성도,Figure 1a to 1c is a schematic view showing a separate construction state of a general long concrete structure,

도 2a 및 2b는 본 발명의 실시예의 콘크리트 구조물의 분리시공을 위한 스페이서와 그 일부확대 단면도,Figure 2a and 2b is an enlarged cross-sectional view of the spacer and a part for the separation construction of the concrete structure of the embodiment of the present invention,

도 3a 내지 3c는 본 발명의 스페이서를 이용한 시공상태 단면도,3a to 3c is a cross-sectional view of the construction state using the spacer of the present invention,

도 4는 본 발명의 스페이서의 취급상태를 나타낸 사시도이다.4 is a perspective view showing a handling state of the spacer of the present invention.

〈 도면의 주요부분에 대한 부호의 설명 〉<Description of the reference numerals for the main parts of the drawings>

1 : 중앙분리대 2 : 난간1: center separator 2: handrail

10 : 비닐필름 11 : 공기층10 vinyl film 11: air layer

20 : 와이어 30 : 피복시트20: wire 30: covering sheet

G : 틈새G: clearance

S : 스페이서S: spacer

이하, 본 발명의 콘크리트 구조물의 분리시공을 위한 스페이서를 첨부도면을 참조하여 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings, the spacer for the separation construction of the concrete structure of the present invention will be described.

도 2a 및 2b는 본 발명의 실시예의 콘크리트 구조물의 분리시공을 위한 스페이서와 그 일부확대 단면도이고, 도 3a 내지 3c는 상기 스페이서를 이용한 시공상태 단면도로서, 스페이서(S)는 적어도 두장의 비닐필름(10)을 중첩되게 접합하되 그 중앙부에 적정 두께를 유지되도록 하는 공기층(11)이 조밀한 상태로 형성되고, 이 공기층(11)의 사이에 위치하는 접합면에는 비닐필름(10)에 인장력을 제공하는 미세한 직경의 와이어(20)가 일체로 부착되어 있다.2A and 2B are enlarged cross-sectional views of a spacer and a partially enlarged cross-sectional view of a spacer for concrete construction according to an embodiment of the present invention, and FIGS. 3A to 3C are cross-sectional views of a construction state using the spacer, wherein the spacers S are at least two vinyl films ( 10) is superimposed, but the air layer 11 is formed in a dense state to maintain a proper thickness in the center portion, and provide a tensile force to the vinyl film 10 to the bonding surface located between the air layer (11) The fine diameter wire 20 is integrally attached.

상기 와이어(20)는 격자상으로 형성되고, 그 재질은 금속재 또는 합성수지사로 된 것이 바람직하다.The wire 20 is formed in a lattice shape, the material is preferably made of metal or synthetic resin.

비닐필름(10)의 양측면에는 그 공기층(11)의 돌출된 부위를 덮여지도록 하여 콘크리트를 타설할 때 평편한 표면을 형성하여 주는 합성수지재의 피복시트(30)가 접합되어 있다.Both sides of the vinyl film 10 are bonded to the covering sheet 30 of synthetic resin material to cover the protruding portion of the air layer 11 to form a flat surface when placing concrete.

상기 비닐필름(10)과 그 외측의 피복시트(30)를 포함한 스페이서(S)의 두께는 약 10mm 정도로 형성하고, 그 길이와 폭은 시공현장에 맞게 절단하여 원하는 크기로 형성하게 된다.The thickness of the spacer S including the vinyl film 10 and the outer cover sheet 30 is about 10 mm, and the length and width thereof are cut to fit the construction site to form a desired size.

이러한 본 발명의 비닐필름으로 된 스페이서(S)를 사용함에 있어서, 도 3a에서와 같이 좌우로 대칭인 콘크리트 구조물의 중앙부에 틈새(G)가 형성되는 중앙분리대(1)를 일예로 설명하면, 먼저 일측 구조물(1')의 형태에 부합되게 통상적인 방법으로 콘크리트를 타설하여 응고 및 양생시킨 후 거푸집을 제거한다.When using the spacer (S) made of a vinyl film of the present invention, as shown in the example, the center separator (1) is formed in the center of the concrete structure symmetrical from side to side as shown in Figure 3a as an example, first In accordance with the shape of the one-sided structure (1 '), the concrete is poured in the usual way to solidify and cure, and then remove the formwork.

이어서 도 3b에서와 같이 상기 일측 구조물(1')의 배면에 본 발명의 스페이서(S)를 밀착되게 하여 도 3c와 같이 콘크리트를 타설 및 양생시켜 나머지 타측의 구조물(1")을 형성하게 되는데, 상기 스페이서(S)를 일측 구조물(1')의 배면에 밀착되게 할 때 스페이서의 상단부를 상향으로 팽팽하게 당겨지도록 거푸집을 이용하여 가시설을 함에 따라 직진도와 평편도를 향상 및 유지하게 된다.Subsequently, as shown in FIG. 3B, the spacer S of the present invention is brought into close contact with the rear surface of the one-side structure 1 ′ to form and cure concrete as shown in FIG. 3C, thereby forming the other structure 1 ″. When the spacer (S) is in close contact with the rear surface of the one-side structure (1 ') to improve the straightness and flatness as the temporary installation using the formwork to pull the upper end of the spacer tightly upward.

상기 공정에 의해 중앙분리대의 시공이 완료된 후에는 양측 구조물(1')(1")의 사이에 개재된 스페이서(S)의 상단부를 당김에 따라 일체로 이탈되며, 이때 비닐필름(10)의 접합부에 형성된 와이어(20)가 인장력을 향상되게 함으로써 스페이서를 이탈시키는 도중 임의로 찢어지는 현상이 방지된다.After the construction of the central separator is completed by the above process is pulled out integrally by pulling the upper end of the spacer (S) interposed between the two structures (1 ') (1 "), wherein the bonding portion of the vinyl film 10 By causing the wire 20 formed thereon to improve the tensile force, the phenomenon of random tearing during detachment of the spacer is prevented.

한편, 본 발명의 스페이서를 형성하는 외측의 피복시트(30)가 합성수지 재질로 됨으로써 콘크리트를 타설할 때 자체적으로 방수가 됨은 물론 콘크리트와 접착되지 않게 되어 스페이서의 이탈이 매우 용이함은 물론 콘크리트의 양생면에 대한 강도를 향상시키는 작용을 한다.On the other hand, since the outer covering sheet 30 forming the spacer of the present invention is made of synthetic resin material, when the concrete is poured, it becomes waterproof itself and is not adhered to the concrete, so that the spacer is easily removed and the curing surface of the concrete. It acts to improve the strength against.

도 4는 본 발명의 스페이서의 취급상태를 나타낸 사시도로서, 공기층(11)을 가진 비닐필름(10)과 그 양측에 부착되는 피복시트(30)를 길이 방향으로 길게 형성하여 두루말이 형태로 감기도록 하여 부피를 최소화 시킴에 따라 시공현장으로 운반과 취급이 용이하고, 시공부의 길이에 맞도록 필요한 길이 만큼 절단하여 사용하여 작업을 효율적으로 할 수 있는 것이다.Figure 4 is a perspective view showing a handling state of the spacer of the present invention, the vinyl film 10 having the air layer 11 and the covering sheet 30 attached to both sides are formed long in the longitudinal direction so that the roll is wound in the form By minimizing the volume, it is easy to transport and handle to the construction site, and it is possible to efficiently work by cutting the required length to fit the length of the construction site.

이와 같은 본 고안의 콘크리트 구조물의 분리시공을 위한 스페이서와 그 시공방법은 콘크리트의 양생후 필수적으로 제거시키는 스페이서를 간단하고 효율적으로 제거함에 따라 작업성을 향상시킴은 물론 스페이서의 미제거로 인한 구조물의 취약성을 방지할 수 있는 효과가 있다.Such a spacer and the construction method for the separate construction of the concrete structure of the present invention improves workability by simply and efficiently removing the spacer that is essentially removed after curing of the concrete, as well as the structure of the structure due to the removal of the spacer It has the effect of preventing vulnerabilities.

또한 스페이서를 사용하지 않은 상태에서는 두루말이 형태로 감기도록 하여 보관 및 취급함에 따라 부피를 최소화 시켜 시공현장으로 운반이 용이하고, 시공현장의 상황에 따라 필요한 길이 만큼 절단하여 사용하여 시공 효율을 향상시킬 수 있는 장점도 있다.In addition, it can be easily transported to the construction site by minimizing the volume as it is stored and handled so that the scroll is wound in the form without spacers, and the construction efficiency can be improved by cutting to the required length according to the situation of the construction site. There is also an advantage.

Claims (2)

적어도 두장의 비닐필름(10)을 중첩되게 접합하되 그 중앙부에 적정 두께를 유지되도록 하는 공기층(11)이 조밀한 상태로 형성되고, 상기 공기층(11)의 사이에 위치하는 접합면에는 비닐필름(10)에 인장력을 제공하는 미세한 직경의 와이어(20)가 일체로 부착되며, 상기 비닐필름(10)의 양측면에는 그 공기층(11)의 돌출된 부위를 덮여지도록 하여 콘크리트를 타설할 때 평편한 표면을 형성하여 주는 합성수지재의 피복시트(30)가 접합되어 있고, 상기 공기층(11)을 가진 비닐필름(10)과 그 양측에 부착되는 피복시트(30)를 길이 방향으로 길게 형성하여 두루말이 형태로 감기도록 한것을 특징으로 하는 콘크리트 구조물의 분리시공을 위한 스페이서.At least two sheets of vinyl film 10 are superposedly bonded to each other, but an air layer 11 is formed in a dense state so as to maintain an appropriate thickness in the center thereof. The wire 20 having a fine diameter providing tension to the 10 is integrally attached to both sides of the vinyl film 10 so as to cover the protruding portion of the air layer 11 so that the flat surface when the concrete is poured. Coated sheet 30 of a synthetic resin material is formed to bond to, and the vinyl film 10 having the air layer 11 and the coated sheet 30 attached to both sides are formed long in the longitudinal direction to wind the roll in the form of Spacer for separation construction of the concrete structure, characterized in that. 제 1항에 있어서, 상기 와이어(20)는 격자상으로 형성되고, 그 재질은 금속재 또는 비닐필름과 동일한 재질의 합성수지사의 어느 하나로 됨을 특징으로 하는 콘크리트 구조물의 분리시공을 위한 스페이서.The spacer for separating and constructing a concrete structure according to claim 1, wherein the wire (20) is formed in a lattice shape, and the material is made of metal or synthetic resin of the same material as the vinyl film.
KR1019990026435A 1999-07-02 1999-07-02 Spacer for separation construction of concrete framework KR100335175B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019990026435A KR100335175B1 (en) 1999-07-02 1999-07-02 Spacer for separation construction of concrete framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019990026435A KR100335175B1 (en) 1999-07-02 1999-07-02 Spacer for separation construction of concrete framework

Publications (2)

Publication Number Publication Date
KR20010008545A true KR20010008545A (en) 2001-02-05
KR100335175B1 KR100335175B1 (en) 2002-05-04

Family

ID=19598734

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019990026435A KR100335175B1 (en) 1999-07-02 1999-07-02 Spacer for separation construction of concrete framework

Country Status (1)

Country Link
KR (1) KR100335175B1 (en)

Also Published As

Publication number Publication date
KR100335175B1 (en) 2002-05-04

Similar Documents

Publication Publication Date Title
US7874540B2 (en) Concrete form for pouring non-round columns, and method of making same
JP2007327210A (en) Reinforcement method and reinforcement structure of steel structure
KR20210120751A (en) Waterproof sheet for exterior of concrete or structure with ease of on-site construction
KR100335175B1 (en) Spacer for separation construction of concrete framework
JP4072908B2 (en) Repair method of steel structure
KR102005470B1 (en) Barrier structure for the opening of the gangform
JP3839446B2 (en) Method for reinforcing concrete structures
JP2016118090A (en) Buckling-restrained brace and method of manufacturing the same
JP4067682B2 (en) Reinforcement structure of structure and its reinforcement method
JP3541065B2 (en) Fireproof coating method and structure of steel
JP2000054645A (en) Concrete structure reinforcing method
JP3550437B2 (en) How to join buried formwork
CN216865735U (en) Pre-paved self-adhesive waterproof roll with good connectivity
JPH08270217A (en) Honeycomb core panel for placing stop of concrete and placing stop work of concrete
JP2004143847A (en) Repair and reinforcement method of wooden long member
JP2007247139A (en) Water cut-off structure of inner wall surface of structure and method of constructing it
JP4713992B2 (en) Thermal insulation board with adhesive and thermal insulation method using the same
KR20230152419A (en) Concrete form releasing film
JPH0761448A (en) Corrugated cardboard tube and pallet using the same
JP4431976B2 (en) Crack control structure of concrete body
JPH08144540A (en) Exfoliation preventive construction method for structure surface, exfoliation preventive finishing construction method for structure surface and exfoliation preventive layered product used therefor
JP5453152B2 (en) Roofing structure
JP2592235Y2 (en) Air cap sheet for concrete curing
JPH0762807A (en) Waterproofing asphalt roofing
JP2005144988A (en) Manufacturing method for concrete member with surface roughening material

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20050328

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee