KR20010007916A - delay-joint method of constructuction for underground structure - Google Patents

delay-joint method of constructuction for underground structure Download PDF

Info

Publication number
KR20010007916A
KR20010007916A KR1020000062303A KR20000062303A KR20010007916A KR 20010007916 A KR20010007916 A KR 20010007916A KR 1020000062303 A KR1020000062303 A KR 1020000062303A KR 20000062303 A KR20000062303 A KR 20000062303A KR 20010007916 A KR20010007916 A KR 20010007916A
Authority
KR
South Korea
Prior art keywords
concrete
joint
waterproofing
plate
underground
Prior art date
Application number
KR1020000062303A
Other languages
Korean (ko)
Other versions
KR100379187B1 (en
Inventor
진성문
Original Assignee
진성문
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 진성문 filed Critical 진성문
Priority to KR10-2000-0062303A priority Critical patent/KR100379187B1/en
Publication of KR20010007916A publication Critical patent/KR20010007916A/en
Application granted granted Critical
Publication of KR100379187B1 publication Critical patent/KR100379187B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: A method of delay joint construction of an underground structure is provided to reduce the structural crevice by preventing and reducing a stress caused by unequal sinking of a structure and the crevice due to the contraction caused by the drying of concrete. CONSTITUTION: A method of delay joint construction of an underground structure includes a bottom foundation process for mounting a protection plate on the bottom surface of underground, a pitching process of pitching a ferro-concrete structure by a predetermined distance from a top part of the protection plate, the first connecting process of connecting the interval space from the structure by a reinforcing rod, a cut-off process of covering both side parts and a top part of the connecting portion of the structure by a reinforcing plate, an external waterproofing process of waterproofing a gap between the protection plate and the structure, a refilling process of refilling the side and top parts of the waterproofed connection portion, an adapting process of adapting to a natural sinking caused by the load of structure and the refilled soil, the second connection process of inserting concrete into the reinforcing rod connection part after the sinking is proceeded within an allowable range, a grouting process of filling air gaps generated at the concrete insertion portion with concrete, and final waterproofing process of closing the concrete filling hole for the grouting.

Description

지하구조물의 늦체결이음공법 {delay-joint method of constructuction for underground structure}{Delay-joint method of constructuction for underground structure}

본 발명은 지하 구조물의 건설시에 철근 콘크리트 구조물과 구조물의 사이를 연결하는 이음공법에 관한 것으로, 더욱 상세하게는 구조물간에 이음(joint)을 두어 기초처짐 변위를 충분히 진행시킨 다음 지하수위가 회복되고 접지압이 거의 불변상태(또는 잔류침하량이 허용범위 이내)에서 구조물간 이음(joint)에 콘크리트를 타설, 체결시키는 구조물의 늦체결(delay joint) 공법에 관한 것이다.The present invention relates to a joint method for connecting between reinforced concrete structures and structures at the time of construction of underground structures, and more specifically, the groundwater level is restored after sufficiently advancing the foundation deflection displacement by placing joints between the structures. It relates to a delay joint method of a structure in which concrete is poured and fastened to joints between structures when the ground pressure is almost constant (or the residual settlement is within an allowable range).

지하 구조물은 지하철이나 차량 등이 지하에서도 운행할 수 있도록 터널형태로 축조되는 것이며, 이러한 지하구조물은 축조하고자 하는 부분의 지반을 일정깊이 파내고 그 바닥으로부터 철근 콘크리트 구조물을 축조하여 완성시킨 다음 그 구조물의 측부 및 상부에 됨메움작업을 실시하므로서, 지하에는 철근 콘크리트 구조물에 의해 일정한 형상을 갖는 구조물이 터널식으로 구성된다.Underground structures are constructed in the form of tunnels so that subways and vehicles can operate underground, such underground structures are dug out of the ground of the part to be constructed, and then the reinforced concrete structures are constructed from the floor and completed. By performing the filling operation on the sides and the upper part of the structure, the structure having a constant shape by the reinforced concrete structure in the basement is constructed in a tunnel type.

이러한 지하 구조물을 건설하기 위한 기술적인 공법은,Technical construction method for constructing such underground structures,

철근 콘크리트 연속구조물을 지지조건이 일양하지 않은 연약지반상에 건설할 경우,When constructing reinforced concrete continuous structures on soft ground without supporting conditions,

1) 기초보강공법으로서,1) As a basic reinforcement method,

① 연약지반을 잡석 등으로 치환, 지지력을 보강하는 방법① How to replace soft ground with rubble and reinforce bearing capacity

② JSP(또는 SIG)공법에 의한 복합적인 지반개량으로 지지력을 향상시키는 방법② How to improve bearing capacity by complex ground improvement by JSP (or SIG) method

③ 기초말뚝공법 등이 활용되어 왔고,③ Basic pile method has been used,

2) 구조물 내부 저항응력을 높히기 위하여는 구조물 유효 단면을 확대하고 종방향 철근을 보강하는 방법을 사용하고,2) In order to increase the internal stress of the structure, the effective cross section of the structure is expanded and the longitudinal reinforcement is used.

3) 구조물의 구조적 응력에 의하여 발생한 균열은 차후 보수(누수시는 방수 작업 병행)하는 소극적인 방법을 시행하여 왔던 것이다.3) The cracks caused by structural stress of the structure have been passively repaired at the same time.

그러나, 전기한 종래의 이음공법은 공사기간이 매우 많이 소요되어 시간적인 면은 물론 경제적인 측면에서도 공사기간의 장기화에 따른 인력 및 자재의 수급 등 그 건설비가 매우 많이 소요되는 문제점이 있는 것이다.However, the conventional joint method described above has a problem that the construction cost is very high, and the construction cost such as supply and demand of manpower and materials according to the prolongation of the construction period in terms of time and economics is very high.

또한, 일차 준공된 후에는 지반의 부등침하에 따른 구조물간의 이음부에 발생하는 균열 및 균열에 의한 누수가 발생하므로 이를 보수하는 작업을 지속적으로 실시해 주어야 하는 것이다.In addition, after the first construction is completed, the leakage caused by the cracks and cracks occurring in the joints between the structures due to the uneven settlement of the ground should be carried out to repair the work continuously.

즉, 강성이 큰 구조물은 비록 탄성변위라 할지라도 작은 변위에서도 큰 만곡응력이 발생하여 구조물에 큰 피해를 줄 수 있고,In other words, even if the structure is large rigidity, even if it is elastic displacement, a large bending stress can be generated even at a small displacement, which can cause great damage to the structure.

구조물의 접지면적이 큰 경우에는 상재하중에 의한 기초지반의 침하변위가 종료될 때까지 상당한 시일을 요하게 되므로 구조물이 준공된 후 상당한 기간이 경과된 후에 균열이 나타나게 되어 이에 대한 보수가 어렵게 되며, 이를 보수하고 유지하기 위해서는 상당한 시일과 공사비를 필요로 하는 것이다.If the ground area of the structure is large, it takes considerable time until the settlement settlement of the foundation ground due to the loading load is completed. Therefore, cracks appear after a considerable period of time after the construction of the structure. Repairing and maintaining requires considerable time and construction costs.

본 발명은 전기한 바와 같은 문제점을 제거코자 안출된 것으로서, 철근 콘크리트 구조물은 지지조건이 불규칙한 연약지반상에 축조되므로 구조물 축조 후 구조물 자중 및 되메움토 하중 영향에 의해 발생하는 부등침하로 인한 구조물의 구조적 응력발생을 방지 또는 최소화 시키기 위하여 구조물간에 이음을 두어 기초처짐 변위를 충분히 진행시킨 다음 지하수위가 회복되고 접지압이 거의 불변상태(또는 잔류 침하량이 허용범위 이내)에서 구조물간 이음에 콘크리트를 타설, 체결하므로서,The present invention has been made to eliminate the problems described above, the reinforced concrete structure is constructed on a soft ground with irregular support conditions, so after the construction of the structure due to uneven settlement caused by the weight of the structure and backfill soil load effect In order to prevent or minimize the occurrence of structural stresses, the joints are placed between the structures to sufficiently deflect the foundation deflection, and then the concrete is placed in the joints between the structures when the groundwater level is restored and the ground pressure is almost constant (or the residual settlement is within the allowable range). By tightening,

구조물의 부등침하로 인한 구조적 응력 발생이 방지 또는 저감됨에 따라 구조균열 및 콘크리트 건조수축에 따른 균열이 현저하게 감소하며,As the occurrence of structural stress due to uneven settlement of the structure is prevented or reduced, the cracks due to structural cracking and concrete drying shrinkage are significantly reduced.

기초보강, 구조물 단면보강, 균열 및 누수 보수등 타공법 대비 예산절감 효과와 공기단축에 크게 기여할 수 있는 지하구조물의 늦체결이음(delay joint)공법을 제공함에 본 발명의 목적이 있는 것이다.It is an object of the present invention to provide a delay joint method of underground structures, which can contribute significantly to the budget saving effect and air shortening compared to other methods such as basic reinforcement, structural section reinforcement, crack and leak repair.

도 1은 본 발명 이음방법을 공정별로 도시한 블럭도1 is a block diagram showing the joint method according to the present invention step by step

도 2a 내지 도 2e는 본 발명 이음방법의 개략적인 공정설명도2a to 2e is a schematic process explanatory diagram of the jointing method of the present invention

도 2a는 바닥 보호판을 설치한 상태도2a is a state in which the bottom protection plate

도 2b는 본체 구조물의 콘크리트 타설 상태도2b is a concrete pouring state diagram of the body structure

도 2c는 본 발명 이음방법에 의한 철근 체결상태도Figure 2c is a state of rebar fastening according to the present invention joint method

도 2d는 본 발명 이음방법에 의한 보호철판 설치 상태도Figure 2d is a protective steel plate installation state according to the present invention joint method

도 2e는 본 발명 이음방법에 의한 방수처리 상태도Figure 2e is a waterproof state diagram according to the joint method of the present invention

도 3은 본 발명에 의한 바닥 기초공정을 보인 상세도Figure 3 is a detailed view showing the floor foundation process according to the present invention

도 4는 본 발명에 의한 바닥철판방수공정을 보인 상세도Figure 4 is a detailed view showing a bottom plate waterproofing process according to the present invention

도 5는 본 발명 보강판을 결합한 지하구조물의 정면설명도5 is a front explanatory view of the underground structure combined with the reinforcing plate of the present invention

도 6은 본 발명 보강판을 결합한 지하구조물의 측면설명도Figure 6 is a side view of the underground structure combined with the reinforcing plate of the present invention

도 7a 및 도 7e는 본 발명에 의한 차수공정을 보인 요부상세도로서,7a and 7e is a detailed view of the main portion showing the degree of process according to the present invention,

도 7a는 구조물에 보강판을 결합한 측면설명도Figure 7a is a side view of the reinforcing plate coupled to the structure

도 7b는 구조물과 보강판을 결합한 일측 상세단면도Figure 7b is a one-sided detail cross-sectional view combining the structure and the reinforcement plate

도 7c는 구조물과 보강판을 결합한 타측 상세단면도Figure 7c is the other side cross-sectional view combining the structure and the reinforcement plate

도 7d는 앵글에 보강판을 삽입한 상태의 상부 상세단면도Figure 7d is a detailed cross-sectional view of the upper state with the reinforcement plate inserted in the angle

도 7e는 하부 앵글의 장착상태를 보인 상세단면도Figure 7e is a detailed cross-sectional view showing the mounting state of the lower angle

도 8은 본 발명에 의한 외부방수공정을 보인 상세도8 is a detailed view showing an external waterproofing process according to the present invention

도 9a 및 도 9c는 본 발명에 의한 되메움공정을 보인 요부상세도로서,9a and 9c is a detail of the main portion showing a backfilling process according to the present invention,

도 9a는 되메움공정이 완성된 상태의 측단면설명도Figure 9a is a side cross-sectional view of the backfill process is completed

도 9b는 되메움공정이 완성된 상태의 상부 상세단면도Figure 9b is a detailed top cross-sectional view of the backfill process is completed

도 9c는 되메움공정이 완성된 상태의 측부 상세단면도Figure 9c is a side cross-sectional detailed view of the backfill process is completed

도 10은 본 발명에 의한 그라우팅 공정을 보인 요부상세도로서,10 is a main detail view showing a grouting process according to the present invention,

도 10a는 그라우트케이블 및 수팽창지수재를 매설한 상부 상세도10A is a detailed view of the upper part of the grout cable and the water-expandable index member embedded therein;

도 10b는 그라우트케이블 및 수팽창지수재를 매설한 측부 상세도Fig. 10B is a side view in which the grout cable and the water-expandable resin are embedded;

도 10c는 그라우트케이블 및 수팽창지수재를 매설한 하부 상세도Figure 10c is a detailed view of the bottom of the grout cable and buried water expansion index

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1 : 보호판 2 : 버림콘크리트층1: protective plate 2: discarded concrete layer

3 : 방수재층 4 : 보호몰탈층3: waterproofing material layer 4: protective mortar layer

5,5' : 방수재고정앵글 6,6' : 수팽창성 방수재5,5 ': Waterproof fixing angle 6,6': Water-expandable waterproof material

7,7' : H-형 보강재 8,8' : 앵글7,7 ': H-shaped reinforcement 8,8': angle

9,9' : 러버패드 10 : 앵커볼트9,9 ': Rubber pad 10: Anchor bolt

11 : 클립핀 12 : 1차 도막방수층11 clip pin 12 primary coating waterproof layer

13 : 탄성실란트 14 : 2차 도막방수층13: elastic sealant 14: secondary coating film waterproofing layer

15 : 1차 성토층 16 : 2차 성토층15: first fill layer 16: second fill layer

17 : 되메움층 18,18' : 그라우트케이블17: backfill layer 18,18 ': grout cable

19 : 수팽창수지재19: water-expandable resin

100,100' : 구조물 101 : 보강판100,100 ': Structure 101: Reinforcement plate

이상과 같은 본 발명의 실시예를 첨부도면에 의해 설명한다.Embodiments of the present invention as described above will be described with reference to the accompanying drawings.

도 1은 본 발명 지하구조물의 늦체결이음(delay joint)공법의 공정별 블럭도이며, 도 2a 내지 도 2e는 전기한 블럭도에 의한 공정도를 개략도시한 것이다.1 is a block diagram for each process of the delay joint method of the underground structure of the present invention, Figures 2a to 2e is a schematic diagram showing the process by the above block diagram.

매설지의 바닥면에 보호판을 설치하는 바닥 기초공정과, 보호판의 상부에 일정거리 이격된 철근 콘크리트 구조물을 타설하는 타설공정과, 이격된 구조물의 사이공간을 철근으로 연결하는 1차 이음공정과, 1차 이어진 구조물 이음부의 양측부 및 상부에 보강판을 덮어 씌우는 차수공정과, 보호판과 구조물의 틈새를 방수처리하는 외부방수공정과, 방수처리된 이음부의 측,상부에 되메움작업을 하는 되메움공정과, 구조물 및 되메움토의 하중에 의한 자연침하에 적응케 하는 존치공정과,A ground foundation process for installing a protection plate on the bottom of the buried land, a casting process for placing reinforced concrete structures spaced a certain distance from the upper part of the protection plate, and a primary joint process for connecting the spaces between the spaced structures with reinforcing bars, 1 Water-repellent process that covers the reinforcement plate on both sides and top of the joint part of the structure, the external waterproof process to waterproof the gap between the protective plate and the structure, and the backfill process to backfill the sides and top of the waterproofed joint. And a process for adapting to natural settlement by the load of the structure and backfill soil,

침하가 허용범위 이내로 진행된 후 그 이음부의 철근이음부를 콘크리트 타설하여 일체화하는 2차 이음공정과, 양생된 이음부의 콘크리트 타설부에 발생하는 각 동공부를 콘크리트 충전하는 그라우팅공정과, 그라우팅에 필요한 콘크리트 충전공을 마감처리하는 최종방수공정으로 되는 것이다.After sinking to within the allowable range, the secondary joint process of concrete reinforcing the reinforcement joint of the joint, the grouting process of concrete filling each pupil generated in the concrete placing of the hardened joint, and the concrete necessary for grouting It will be the final waterproofing process to finish the filling hole.

또한, 전기한 바닥 기초공정에 있어서, 보호판(1)의 하부에는 최하부로부터 버림콘크리트층(2)과 방수재층(3), 보호몰탈층(4)을 순차적층하여 되는 것이며,In the bottom foundation step described above, the bottom of the protective plate 1 is to sequentially layer the discarded concrete layer 2, the waterproofing material layer 3, and the protective mortar layer 4 from the lowermost part.

타설공정은 전기한 보호판(1)의 양단부에 다수의 방수재고정앵글(5)(5')을 형성하여 이에 수팽창성 방수재(6)(6')를 삽입한 상태에서 그 상부에 철근 콘크리트 타설하여 구조물(100)(100')을 형성하여 되는 것이며,In the pouring process, a plurality of waterproofing fixing angles (5) (5 ') are formed at both ends of the protective plate (1), which is reinforced with concrete reinforced on top of the water-expandable waterproofing material (6) (6'). It is to form the structure (100, 100 '),

차수공정은 판상의 일측면에 다수의 H-형 보강재(7)(7')를 단축방향으로 일정거리 이격되게 다수 형성한 보호판(101)을 H-형 보강재(7)(7')가 구조물(100)(100')의 외측을 향하도록 위치시키고, 구조물(100)(100')의 각 모서리부에는 "ㄱ"자상의 앵글(8)(8')을 형성하여, 전기한 보강판(101)의 양단이 각 앵글(8)(8')의 홈에 안착되게 하며, 구조물(100)(100')과 보강판(101)의 사이에는 러버패드(9)(9')를 삽입하며,In the order of the process, the H-shaped reinforcement member (7) (7 ') has a structure in which a plurality of H-shaped reinforcement members (7) (7') are formed on one side of the plate, and a plurality of H-shaped reinforcement members (7 ', 7') Positioned so as to face the outside of the (100) (100 '), and formed a "b" shaped angles (8) (8') at each corner of the structure (100, 100 '), the reinforcement plate ( Both ends of the 101 are seated in the grooves of the angles 8 and 8 ', and rubber pads 9 and 9' are inserted between the structures 100 and 100 'and the reinforcement plate 101. ,

보강판(101)의 길이방향 일측은 다수의 앵커볼트(10)에 의해 구조물(100)(100')과 고정되게 하고, 타측은 별도의 클립핀(11)에 의해 압압되게 고정하여 되는 것이다.One side of the reinforcement plate 101 in the longitudinal direction is to be fixed to the structure (100, 100 ') by a plurality of anchor bolts 10, the other side is to be fixed by pressing by a separate clip pin (11).

또한, 외부방수공정은 보강판(101)과 구조물(100)(100')의 틈새를 방수처리하되, 하부로부터 상부에 이르기까지 1차 도막방수층(12)과 탄성실란트(13), 2차 도막방수층(14)을 순차 형성하여 되는 것이다.In addition, the external waterproof process is to waterproof the gap between the reinforcing plate 101 and the structure (100, 100 '), from the bottom to the top of the first coating layer waterproof layer 12 and the elastic sealant 13, the secondary coating film The waterproof layer 14 is formed sequentially.

되메움공정은 보강판(101)의 측,상부를 불투수성 되메움재에 의한 1차 성토층(15)으로 형성하되, 1차성토층(15)의 양측부는 상협하광상으로 형성하고, 1차성토층(15)의 상부에는 방수보호 성토재에 의한 2차성토층(16)을 형성하며, 그 이외의 부분에는 성토재에 의한 되메움층(17)으로 형성하여 되는 것이다.In the backfilling process, the side and top of the reinforcing plate 101 are formed of a primary fill layer 15 made of an impermeable backfill material, and both sides of the primary fill layer 15 are formed of an upper and lower subsurface deposits. The upper part of the (15) is formed with a secondary soil layer 16 made of waterproof protective soil material, and the other portion is formed of a backfill layer 17 of soil material.

2차 이음공정은 구조물(100)(100')의 각단부 표면에 다수의 그라우트케이블(18)(18')과 수팽창지수재(19)를 위치한 상태에서 콘크리트 타설하되, 구조물(100)(100')의 외측방으로는 그라우트케이블(18)(18')을 위치하고 내측방으로는 수팽창수지재(19)를 위치하여 되는 것이다.The secondary joint process is to cast concrete in a state in which a plurality of grout cables (18) (18 ') and the water-expandable index (19) is placed on the surface of each end of the structure (100) (100'), but the structure (100) ( The grout cable 18 (18 ') is located in the outer side of 100'), and the water-expandable resin material 19 is located in the inner side.

이상과 같은 공법에 의한 본 발명 지하구조물의 늦체결이음(delay joint)공법을 각 공정별 상세도면에 의해 보다 상세히 설명하면 다음과 같다.The delay joint method of the underground structure of the present invention by the above-described method will be described in more detail by detailed drawings for each process as follows.

도 3은 본 발명에 의한 이음공법중 기초공정 및 타설공정이 완성된 상태를 도시한 것으로서, 매설지의 최하부 바닥면에는 버림콘크리트층(2)을 형성하고, 그 상부에 방수재층(3)과 보호몰탈층(4)을 형성한 이후, 그 상부에 보호판(1)을 적층하여 형성하는 것이다.3 shows a state in which the basic process and the pouring process of the joint method according to the present invention are completed, and the discarded concrete layer 2 is formed on the bottom surface of the buried land, and the waterproofing layer 3 and the protection thereon are formed thereon. After the mortar layer 4 is formed, the protective plate 1 is laminated on the upper portion.

이러한 보호판(1)의 두께 및 보강재의 규격은 외부하중이 delay joint에 미치는 응력에 따라 적절하게 결정하여야 한다.The thickness of these protective plates (1) and the size of the stiffeners are to be determined appropriately according to the stress of the external load on the delay joint.

또한, 전기한 보호판(1)의 상부 양측에는 다수의 절곡형상 방수재고정앵글(5)(5')을 입설하되, 방수재고정앵글(5)(5')의 내측에는 수팽창성 방수재(6)(6')를 삽입한 상태에서 그 상부에 철근 콘크리트 구조물(100)(100')을 타설하여 시공하면 되는 것이며, 철근 콘크리트 구조물(100)(100')은 일시에 연속적인 시공이 불가능하므로 구간별 시공을 하게 되는데, 이때에는 철근 콘크리트 구조물(100)(100')이 양생되는 과정에서 수축이 발생하므로 블럭 형태의 구조물(100)(100')을 일정간격 이격된 상태로 시공하는 것이다.In addition, a plurality of bent shape waterproofing material fixing angles 5, 5 'are placed on both sides of the upper part of the protective plate 1, while the water-expandable waterproofing material 6, inside the waterproofing material fixing angles 5, 5'. 6 ') is inserted into the upper part of the reinforced concrete structure (100, 100') is to be installed, and the reinforced concrete structure (100, 100 ') is not possible to be continuous construction at a time by section In this case, since the contraction occurs in the process of curing the reinforced concrete structures 100 and 100 ', the construction of the blocks 100 and 100' in a predetermined interval is performed.

여기서, 전기한 이격거리는 연약지반에 축조된 구조물의 예상 침하량과 이에 따라 발생하는 구조물의 구조적 응력 및 주위의 여건에 따라 결정하여야 하는 것이며, 이음부에서 양쪽 구조물(100)(100')간의 예상단차에 따라 적절히 저정하여 결정하여야 한다.Here, the above separation distance is to be determined according to the expected settlement amount of the structure built on the soft ground, the structural stress and surrounding conditions of the resulting structure, and the expected step between the two structures (100, 100 ') at the joint It shall be determined appropriately by

또한, 블럭형태로 시공된 구조물(100)(100')의 양단부에 노출된 철근을 이용하여 두개의 마주한 구조물(100)(100')의 단부를 철근에 의해 연결형성하므로서 1차 이음공정이 완성되는 것이다.In addition, the first joint process is completed by connecting the ends of two opposed structures 100 and 100 'by reinforcing bars using reinforcing bars exposed at both ends of the structures 100 and 100' constructed in a block form. Will be.

여기서, 전기한 수팽창성 방수재(6)(6')는 도 4의 도시와 같이 지하수 또는 빗물이 보호판(1)과 철근 콘크리트 구조물(100)(100')과의 하부 틈새로 유입되는 경우 방수재고정앵글(5)(5') 및 수팽창성 방수재(6)(6')에 의해 지하수 및 빗물이 유입되지 않게 한 것이다.Here, the water-expandable waterproof member (6) (6 ') is fixed to the waterproof material when the groundwater or rainwater flows into the lower gap between the protective plate (1) and the reinforced concrete structure (100) (100'), as shown in FIG. The groundwater and rainwater are prevented from entering by the angles 5, 5 'and the water-expandable waterproof member 6, 6'.

또한, 수팽창성 방수재(6)(6')는 구조물의 전 둘레에 설치되는 것으로서, 단절됨이 없이 연속되도록 하고 방수재의 두께는 구조물의 변위에 따라 발생하는 공극이 충분히 충진될 수 있는 두께이어야 하며, 탄성이 있는 재료로 하여야 한다.In addition, the water-expandable waterproof member (6) (6 ') is installed around the periphery of the structure, so that it is continuous without disconnection and the thickness of the waterproof member should be a thickness sufficient to fill the voids generated by the displacement of the structure, It should be made of elastic material.

도 5는 본 발명에 의해 일정거리 이격된 상태의 철근 콘크리트 구조물(100)(100')의 이격공간부에 보강판(101)을 덧대어 부착형성한 상태를 정면도시한 것으로서, 보호판(1)이 설치된 하부를 제외한 양측부 및 상부에 각각의 보강판(101)을 덧대어 고정하므로서 차수공정이 완성됨을 알 수 있는 것이다.FIG. 5 is a front view illustrating a state in which a reinforcing plate 101 is attached to a spaced space of a reinforced concrete structure 100 and 100 ′ in a state spaced apart by a certain distance from the present invention, and a protective plate 1. It can be seen that the ordering process is completed by fixing each reinforcement plate 101 on both sides and the top except for the installed bottom.

이러한 보강판은 도 6의 도시와 같이 판상의 몸체 일측에 다수의 H-형 보강재(7)(7')를 부착형성하되, 그 부착방향을 보강판(101)의 단축방향으로 평행되게 연속부착한 것이다.Such a reinforcing plate is attached to form a plurality of H-shaped reinforcement (7) (7 ') on one side of the plate-shaped body, as shown in Figure 6, but the attachment direction is continuously attached in parallel to the short axis direction of the reinforcing plate 101 It is.

따라서, 전기한 H-형 보강재(7)(7')는 구조물(100)(100')간의 이격공간으로 상부의 되메움토에 의한 하중이 집중되어 보강판(101)이 휘는 문제점을 극복한 것이다.Therefore, the aforementioned H-shaped reinforcement member (7) (7 ') overcomes the problem that the reinforcement plate 101 is bent due to the concentration of the load due to the back-filling soil in the upper space into the space between the structure (100, 100') will be.

이러한 차수공정은 보강판(101)의 유동을 방지하기 위해 구조물(100)(100')의 일측에 보강판(101)을 고정하여 되는 것인데, 보강판(101)을 구조물(100)의 일측에 결합하되, 이때에는 도 7a의 도시와 같이 보강판(101)의 하부 양측에 러버패드(9)(9')를 삽입한 상태에서 도 7b의 도시와 같이 매설된 앵커볼트(10)에 의해 러버패드(9) 및 보강판(101), H-형 보강재(7)(7')가 동시에 결합고정되게 하는 것이다.This ordering process is to fix the reinforcement plate 101 to one side of the structure (100, 100 ') to prevent the flow of the reinforcement plate 101, the reinforcement plate 101 to one side of the structure 100 In this case, the rubber pads 9 and 9 'are inserted into the lower both sides of the reinforcing plate 101 as shown in FIG. 7A, and the rubber is buried by the anchor bolts 10 as shown in FIG. 7B. The pad 9, the reinforcement plate 101, and the H-shaped reinforcement 7 and 7 'are simultaneously bonded to each other.

또한, 타측 구조물(100')에는 보강판(101)을 전기한 바와 같이 고정하는 것이 아니라, 도 7c의 도시와 같이 보강판(101)과 러버패드(9)(9')를 동시에 클립핀(11)에 의해 클램핑되게 고정하는 것이다.In addition, instead of fixing the reinforcement plate 101 to the other structure 100 'as described above, as shown in FIG. 7C, the reinforcement plate 101 and the rubber pads 9 and 9' are simultaneously clipped ( 11) to be clamped by.

따라서, 클램핑부는 수축 및 팽창에 의해 구조물의 이격거리가 변화되는 것을 수용할 수 있는 탄력유동공간으로 작용하는 것이다.Therefore, the clamping portion acts as an elastic flow space that can accommodate the change of the separation distance of the structure by contraction and expansion.

또, 보강판(101)을 구조물(100)(100')의 이격공간에 부착형성하는 방법은 도 7d 및 도 7e의 도시와 같이 구조물의 상하부에 절곡판상의 앵글(8)(8')을 부착형성하되, 그 앵글이 구조물(100)(100')과 보강판(101)의 두께만큼 이격되게 부착형성한 다음, 그 이격홈에 보강판(101)의 단부를 삽입하여 고정하면 되는 것이다.In addition, the method of attaching the reinforcing plate 101 to the spaced spaces of the structures 100 and 100 ′ may include angles 8 and 8 ′ on the bent plate at the upper and lower portions of the structure, as shown in FIGS. 7D and 7E. Attachment is formed, but the angle is formed to be spaced apart by the thickness of the structure 100, 100 'and the reinforcing plate 101, and then insert the end of the reinforcing plate 101 in the separation groove to be fixed.

이러한 차수공정이 종료된 후에는 도 8의 도시와 같은 외부방수공정을 거치게 되는데, 이러한 외부방수공정은 구조물(100)(100')과 보강판(101)의 단부가 접하는 부분에 1차 도막방수층(12)을 형성한 다음 그 상부에 탄성실란트(13)를 적층하며, 그 상부에는 2차 도막방수층(14)을 형성하여 그 틈새의 완전한 방수가 되게 하는 것이다.After the ordering process is completed, an external waterproofing process as shown in FIG. 8 is performed. The external waterproofing process is the first coating layer in a portion where the ends of the structures 100, 100 ′ and the reinforcing plate 101 are in contact with each other. (12) is formed, and then the elastic sealant 13 is laminated on the upper portion thereof, and the secondary coating waterproof layer 14 is formed on the upper portion thereof so as to completely waterproof the gap.

이러한 차수공정 및 외부방수공정이 완성된 이후에는 그 측,상부에 되메움토를 투입하여 매설지를 메우게 되는데, 이때에도 도 9a의 도시와 같이 구조물의 측,상부에 불투수성 되메움재에 의한 1차 성토층(15)과, 방수보호 성토재에 의한 2차성토층(16) 및 성토재에 의한 되메움층(17)으로 순차 적층하여 완성하는 것이다.After completion of the water-repellent process and the external waterproof process, the backfill is added to the side and the upper part to fill the buried land. In this case, as shown in FIG. 9A, the impermeable backfill material is formed on the side and the upper part of the structure. It is completed by sequentially stacking the primary fill layer 15, the secondary fill layer 16 made of waterproof protective fill material, and the backfill layer 17 made of fill material.

즉, 도 9b의 상부 도시 및 도 9c의 측부 도시와 같이 구조물(100)(100')간의 이격공간에 위치한 보강판(101) 및 방수처리부가 완전히 덮히게 불투수성 되메움재에 의한 1차 성토층(15)을 형성하며, 이러한 1차 성토층(15)은 그 측부에 이르러서는 상협하광상의 경사부를 갖도록 형성하는 것이며, 그 1차 성토층(15)의 외측 상부에는 방수보호 성토재에 의해 일정두께의 2차 성토층(16)을 적층하므로서, 되메움재의 투입에 의해 방수처리된 부분이 손상되거나 파손되는 것을 방지하도록 하는 것이며, 그 상부에는 성토재에 의한 되메움층(17)을 형성하여 지표면을 형성하는 것이다.That is, as shown in the upper portion of FIG. 9B and the side portion of FIG. 9C, the first fill layer formed by an impermeable backfill material to completely cover the reinforcement plate 101 and the waterproofing portion disposed in the space between the structures 100 and 100 ′. (15) is formed, and the primary fill layer (15) is formed to have an inclined portion of the upper and lower deposits reaching its side portion, and the outer top of the primary fill layer (15) is fixed by a waterproof protective fill material. The secondary fill layer 16 having a thickness is laminated to prevent damage to or damage to the waterproofed portion by the input of the backfill material, and the backfill layer 17 formed by the fill material is formed on the upper surface thereof. To form.

또한, 되메움 작업은 되메움 토사 하중이 구조물에 집중적으로 작용하지 않도록 종방향 계단식으로 시행하여야 하며, 구조물이 주변 지하수위 이하에 축조될 경우 되메움 후 지하수위 회복에 따른 양압이 구조물에 미치는 영향을 고려하여 되메움 높이와 지하수위 회복속도를 연관 조정하면서 시행하여야 하는 것이다.In addition, backfilling should be carried out longitudinally so that the backfill soil load does not act intensively on the structure.If the structure is built below the surrounding groundwater level, the effect of positive pressure on the structure after the backfill is restored. This should be done by adjusting the backfill height and the groundwater recovery rate.

이렇게 되메움 공정이 종료된 후에는 그 구조물(100)(100')을 일정시간 동안 존치하는 존치공정을 갖게 되는것인데,After the backfilling process is finished, the structure 100 and 100 'will have a retaining process for a certain time.

이러한 존치공정은 시일이 경과함에 따라 구조물(100)(100') 및 되메움토의 하중에 의해 지반이 자연침하되는 구조물의 적응기로서, 수개월동안 방치(이때에는 다른 구간의 공사를 진행하는 상태이므로 연속적인 작업이 진행되고 있는 것임.)하게 되면 일정량 자연침하가 일어나게 되고 부등침하에 따른 구조물(100)(100')간의 단차 및 높이의 차를 보이게 되는 것이다.This process is an adaptor of the structure in which the ground naturally subsides due to the load of the structures 100 and 100 'and the backfill soil, which is left for several months (in this case, the construction of other sections is in progress. If the work is going on.) If a certain amount of natural settlement will occur and the difference between the step and height between the structures 100, 100 'according to the differential settlement.

따라서, 일정기간동안 침하량을 측정하여 그 측정치에 의해 더이상의 침하가 일어나지 않는 불변상태 또는 그 침하량이 허용기준 이내일때에는 도 10a 내지 도 10c의 도시와 같이 2차 이음공정을 실시하게 되는 것이다.Therefore, when the amount of settlement is measured for a certain period of time, and when the invariant state in which no further settlement occurs by the measured value or the amount of settlement is within the acceptance criteria, the secondary joint process is performed as shown in FIGS. 10A to 10C.

이러한 이음공정은 구조물(100)(100')의 각 단부면에 그라우트케이블(18)(18') 및 수팽창지수재(19)를 삽입한 상태에서 콘크리트 타설하는 것인데, 그라우트케이블(18)(18')은 구조물(100)(100')의 외측부에 위치하도록 배치하고, 수팽창지수재(19)는 그 내측부에 위치하도록 설치한 다음 콘크리트 타설하면 되는 것이다.This joint process is to cast concrete in the state in which the grout cables 18, 18 'and the water-expandable index member 19 are inserted into each end surface of the structure 100, 100', the grout cable 18 ( 18 ') is disposed so as to be located on the outer side of the structure (100, 100'), and the water-expandable index (19) is to be installed on the inner side is to be poured concrete.

이러한 그라우트케이블(18)(18')은 다수의 통공으로 이루어져 있으며, 콘크리트 양생과정에서 수축 및 하중에 의해 콘크리트 타설부에 동공이 형성되면 그 그라우트케이블(18)(18')을 통해 고압의 콘크리트 혼합물을 투입하여 동공을 메우므로 체결력을 향상시킴은 물론 틈새를 제거하므로서 방수효과 또한 향상시키는 것이다.The grout cable 18, 18 'is composed of a plurality of through-holes, and when the pupil is formed in the concrete pouring place by shrinkage and load in the concrete curing process, the grout cable (18, 18') through the high-pressure concrete Filling the pupil by adding a mixture to improve the fastening force as well as to remove the gap to improve the waterproof effect.

이러한 그라우팅 공정은 그 그라우트케이블(18)(18')을 통해 지하수 및 빗물이 흘러나오게 되면 그 부분은 누수 및 틈새가 발생한 것이므로 해당 그라우트케이블(18)(18')을 통해 동공으로 콘크리트 혼합물을 투입하면 되는 것이다.In this grouting process, when groundwater and rainwater flow out through the grout cables 18 and 18 ', leaks and gaps occur, and the concrete mixture is injected into the pupils through the grout cables 18 and 18'. You can do it.

이렇게 그라우팅공정이 종료된 후에는 그 내표면에 최종방수처리를 하므로서 완성되는 것이다.After the grouting process is completed, the inner surface is finished with the final waterproofing treatment.

따라서, 늦체결이음(delay joint)공법에 의해 지하 구조물을 설치하게 되면 구조균열 및 콘크리트 건조수축에 따른 균열이 현저하게 감소되는 것이며, 본 공법을 적용함으로써 기초보강, 구조물 단면보강, 균열 및 누수 보수등 타공법 대비 예산절감 효과와 공기단축에 크게 기여할 수 있는 것이다.Therefore, when the underground structure is installed by the delay joint method, the cracks due to structural cracking and concrete shrinkage are remarkably reduced. By applying this method, foundation reinforcement, structural section reinforcement, crack and leak repair It can contribute significantly to the budget saving effect and the air shortening compared to other methods.

하기의 표는 본 발명 출원인에 의해 비교된 종래공법 및 본 발명 공법의 각종 부분을 비교한 것이다.The following table compares various parts of the conventional method and the present method compared by the applicant of the present invention.

구분division delay joint 공법delay joint method 기초지반보강공법Basic Ground Reinforcement Method 구조물단면보강공법Structure section reinforcement method 공사 기간construction period 1One 22 1One 공사 비용Construction cost 1One 44 44

따라서, 본 발명에 의한 이음공법은 종래의 어떠한 공법보다도 월등한 공사기간의 단축은 물론 공사비용 또한 현저하게 감축할 수 있으므로 매우 경제적인 것이다.Therefore, the joint method according to the present invention is very economical because it can significantly reduce the construction cost as well as the construction period which is superior to any conventional method.

이상과 같은 본 발명 지하구조물의 늦체결이음(delay joint)공법은 구조물의 부등침하로 인한 구조적 응력 발생이 방지 또는 저감됨에 따라 구조균열 및 콘크리트 건조수축에 따른 균열이 현저하게 감소하며,As described above, the delay joint method of the underground structure of the present invention significantly reduces the cracks caused by structural cracking and concrete shrinkage as structural stresses are prevented or reduced due to uneven settlement of the structure.

기초보강, 구조물 단면보강, 균열 및 누수 보수등 타공법 대비 예산절감 효과와 공기단축에 크게 기여할 수 있는 효과가 있는 것이다.Compared to other methods such as foundation reinforcement, structural section reinforcement, crack and leak repair, there is an effect that can greatly contribute to the reduction of budget and air shortening.

Claims (3)

매설지의 바닥면에 보호판을 설치하는 바닥 기초공정과, 보호판의 상부에 일정거리 이격된 철근 콘크리트 구조물을 타설하는 타설공정과, 이격된 구조물의 사이공간을 철근으로 연결하는 1차 이음공정과, 1차 이어진 구조물 이음부의 양측부 및 상부에 보강판을 덮어 씌우는 차수공정과, 보호판과 구조물의 틈새를 방수처리하는 외부방수공정과, 방수처리된 이음부의 측,상부에 되메움작업을 하는 되메움공정과, 구조물 및 되메움토의 하중에 의한 자연침하에 적응케 하는 존치공정과,A ground foundation process for installing a protection plate on the bottom of the buried land, a casting process for placing reinforced concrete structures spaced a certain distance from the upper part of the protection plate, and a primary joint process for connecting the spaces between the spaced structures with reinforcing bars, 1 Water-repellent process that covers the reinforcement plate on both sides and top of the joint part of the structure, the external waterproof process to waterproof the gap between the protective plate and the structure, and the backfill process to backfill the sides and top of the waterproofed joint. And a process for adapting to natural settlement by the load of the structure and backfill soil, 침하가 허용범위 이내로 진행된 후 그 이음부의 철근이음부를 콘크리트 타설하여 일체화하는 2차 이음공정과, 양생된 이음부의 콘크리트 타설부에 발생하는 각 동공부를 콘크리트 충전하는 그라우팅공정과, 그라우팅에 필요한 콘크리트 충전공을 마감처리하는 최종방수공정으로 됨을 특징으로 하는 지하구조물의 늦체결이음공법.After sinking to within the allowable range, the secondary joint process of concrete reinforcing the reinforcement joint of the joint, the grouting process of concrete filling each pupil generated in the concrete placing of the hardened joint, and the concrete necessary for grouting Late tightening method of underground structure, characterized in that the final waterproofing process to finish the filling hole. 제 1항에 있어서, 타설공정은 전기한 보호판(1)의 양단부에 다수의 방수재고정앵글(5)(5')을 형성하여 이에 수팽창성 방수재(6)(6')를 삽입한 상태에서 그 상부에 철근 콘크리트 타설하여 구조물(100)(100')을 형성하여 됨을 특징으로 하는 지하구조물의 늦체결이음공법.2. The placing process according to claim 1, wherein a plurality of waterproofing fixing angles (5) (5 ') are formed at both ends of the protective plate (1), and the water-expandable waterproofing members (6) and (6') are inserted therein. Laying fastening method of the underground structure, characterized in that to form the structure (100, 100 ') by placing reinforced concrete on the top. 제 1항에 있어서, 2차 이음공정은 구조물(100)(100')의 각단부 표면에 다수의 그라우트케이블(18)(18')과 수팽창지수재(19)를 위치한 상태에서 콘크리트 타설하되, 구조물(100)(100')의 외측방으로는 그라우트케이블(18)(18')을 위치하고 내측방으로는 수팽창수지재(19)를 위치하여 됨을 특징으로 하는 지하구조물의 늦체결이음공법.The method of claim 1, wherein the secondary joint process is to cast concrete with a plurality of grout cables (18) (18 ') and the water-expandable index (19) on the surface of each end of the structure (100) (100') , Lateral fastening method of the underground structure, characterized in that the grout cable (18) (18 ') is located in the outer side of the structure 100, 100' and the water-expandable resin material (19) is located in the inner side. .
KR10-2000-0062303A 2000-10-23 2000-10-23 delay-joint method of constructuction for underground structure KR100379187B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0062303A KR100379187B1 (en) 2000-10-23 2000-10-23 delay-joint method of constructuction for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0062303A KR100379187B1 (en) 2000-10-23 2000-10-23 delay-joint method of constructuction for underground structure

Publications (2)

Publication Number Publication Date
KR20010007916A true KR20010007916A (en) 2001-02-05
KR100379187B1 KR100379187B1 (en) 2003-04-08

Family

ID=19694875

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0062303A KR100379187B1 (en) 2000-10-23 2000-10-23 delay-joint method of constructuction for underground structure

Country Status (1)

Country Link
KR (1) KR100379187B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778917A (en) * 2019-02-22 2019-05-21 中铁第六勘察设计院集团有限公司 A kind of cold seam waterproof construction of underground engineering construction and construction method
CN110761261A (en) * 2019-09-19 2020-02-07 中铁第四勘察设计院集团有限公司 Vehicle section storehouse overhead settlement prevention system suitable for weak stratum
CN115012452A (en) * 2022-06-15 2022-09-06 中建二局第二建筑工程有限公司 Post-cast strip construction process and basement drainage pressure relief structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778917A (en) * 2019-02-22 2019-05-21 中铁第六勘察设计院集团有限公司 A kind of cold seam waterproof construction of underground engineering construction and construction method
CN109778917B (en) * 2019-02-22 2024-02-09 中铁第六勘察设计院集团有限公司 Cold joint waterproof structure for underground engineering construction and construction method
CN110761261A (en) * 2019-09-19 2020-02-07 中铁第四勘察设计院集团有限公司 Vehicle section storehouse overhead settlement prevention system suitable for weak stratum
CN115012452A (en) * 2022-06-15 2022-09-06 中建二局第二建筑工程有限公司 Post-cast strip construction process and basement drainage pressure relief structure

Also Published As

Publication number Publication date
KR100379187B1 (en) 2003-04-08

Similar Documents

Publication Publication Date Title
KR100978314B1 (en) Reinforced Concrete Tunnels by Using Corrugated Steel Plate and the Construction Method thereof
CN105155551A (en) Pressure compensation type foundation pit supporting structure and construction method
WO2001084037A1 (en) Duct repairing material, repairing structure, and repairing method
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN108547645B (en) Assembled tunnel supporting device and method capable of realizing prestress
CN105888697B (en) A kind of Cross-fault leveling tunnel deformation cooperative type supporting construction and its construction method
CN106812131A (en) A kind of permanent sheet pile underground structure and its construction method
KR101863627B1 (en) Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system
CN110685234B (en) Construction method of corrugated steel pipe culvert
KR100379187B1 (en) delay-joint method of constructuction for underground structure
KR102103978B1 (en) Reinforcement and waterproof structure of vertical shafts for utility interface
KR100476839B1 (en) Construction method for installing concrete underground structures
CN214090006U (en) Basement lateral wall post-cast strip block structure
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
CN211421179U (en) Existing pipe gallery underground space and supporting construction thereof
CN112942148A (en) Method for reinforcing bridge by corrugated steel arch structure
KR102053112B1 (en) Method of structure aseismic reinforcement using reinforcing Fibers
JP7138281B2 (en) Embankment wall structure
CN113502847A (en) Assembly type rigid support protection foundation structure for buried pipeline
CN215632972U (en) On-spot prefabricated tube coupling of super large section rectangle push pipe
CN111101446B (en) Construction method of soil-covered corrugated steel plate bridge
CN108678002B (en) Prefabricated assembly pipe gallery structure
CN220377102U (en) Supporting type hidden bridge protection culvert structure
CN219195980U (en) Pile and wall integrated structure of yielding support structure
KR102554205B1 (en) Slurry wall joint connect method

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130326

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20140325

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20160325

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20170327

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20180322

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20190325

Year of fee payment: 17