CN112942148A - Method for reinforcing bridge by corrugated steel arch structure - Google Patents

Method for reinforcing bridge by corrugated steel arch structure Download PDF

Info

Publication number
CN112942148A
CN112942148A CN202110177225.4A CN202110177225A CN112942148A CN 112942148 A CN112942148 A CN 112942148A CN 202110177225 A CN202110177225 A CN 202110177225A CN 112942148 A CN112942148 A CN 112942148A
Authority
CN
China
Prior art keywords
arch
corrugated steel
bridge
corrugated
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110177225.4A
Other languages
Chinese (zh)
Inventor
宋振旺
周威
鞠鹏飞
宋振辉
陈俊
熊志刚
宋振浩
余鹏
黄葛胤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Chujianke Technology Co ltd
Hubei Chutian Lianfa Road And Bridge Maintenance Co ltd
Original Assignee
Hubei Chujianke Technology Co ltd
Hubei Ctlf Engineering Test And Detection Co ltd
Hubei Chutian Lianfa Road And Bridge Maintenance Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Chujianke Technology Co ltd, Hubei Ctlf Engineering Test And Detection Co ltd, Hubei Chutian Lianfa Road And Bridge Maintenance Co ltd filed Critical Hubei Chujianke Technology Co ltd
Priority to CN202110177225.4A priority Critical patent/CN112942148A/en
Publication of CN112942148A publication Critical patent/CN112942148A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种波纹钢拱形结构加固桥梁的方法,包括:利用片石混凝土或者沙袋筑墙设置成围堰;(如有需要围堰导流)基坑开挖;拱脚部位施工处理;检查波纹钢板拱底部平整度、水平、标高;核对土建基准,确定钢板拱的位置、中心轴线、中点;由下向上顺次拼装波纹钢板;用专用密封胶或环氧树脂砂浆封填波纹钢板拱外圈搭接处;在主拱圈另一侧通过卷扬机或手拉葫芦对拼装完成的钢板拱往拱底拉拽就位;采用泵送混凝土形式对拱上空隙进行填充,有效实现了修复危旧桥梁的目的,解决了目前波纹钢板修复拱形桥梁施工过程中空间不足,难于安装、难于定位、施工效率低的问题,实现了现场不断交通,能快速施工,减少投入,降低造价,缩短工期,且可保障施工过程中道路的正常运营基本不受影响;具备良好的结构强度和防水性能且占用桥拱净空高度小。

Figure 202110177225

A method for reinforcing a bridge with a corrugated steel arch structure, comprising: using rubble concrete or sandbags to build walls and setting up a cofferdam; (if necessary, cofferdam diversion) foundation pit excavation; arch foot part construction treatment; checking corrugated steel plate arch Bottom flatness, level, elevation; check the civil engineering datum to determine the position, center axis, and midpoint of the steel plate arch; assemble the corrugated steel plate in sequence from bottom to top; seal the outer ring of the corrugated steel plate arch with special sealant or epoxy resin mortar. On the other side of the main arch ring, the assembled steel plate arch is pulled to the bottom of the arch by a hoist or a chain hoist. The purpose is to solve the problems of insufficient space, difficult installation, difficult positioning, and low construction efficiency in the current construction process of corrugated steel plate repairing arch bridges, realizing continuous traffic on site, enabling rapid construction, reducing investment, reducing construction costs, and shortening the construction period. To ensure that the normal operation of the road during the construction process is basically unaffected; it has good structural strength and waterproof performance and occupies a small headroom of the bridge arch.

Figure 202110177225

Description

Method for reinforcing bridge by corrugated steel arch structure
Technical Field
The invention relates to a bridge reinforcing method, in particular to a method for reinforcing a bridge by a corrugated steel arch structure.
Background
The existing culvert is classified into a round pipe culvert, an arch culvert, a cover plate culvert and a box culvert according to different structural forms; brick culverts, stone culverts, concrete culverts and reinforced concrete culverts are classified according to the materials according to the open culverts and the dark culverts; the culvert is divided into a non-pressure type culvert, a semi-pressure type culvert and a pressure type culvert according to different hydraulic performances. The bridge is classified into a beam bridge, an arch bridge, a rigid bridge, a cable-stayed bridge and a suspension bridge according to the stress component. The beam type bridge comprises a continuous beam, a simply supported beam, a cantilever beam and a continuous beam, but the simply supported beam is mostly used within 20 meters of span. The arch bridge can be divided into masonry arch and reinforced concrete. With the rapid development of the transportation industry in China, the damage of the culvert of the existing bridge is accelerated, at present, the repair of the small-span bridge and the culvert mainly adopts construction methods of steel plate pasting, carbon fiber cloth adhering, section increasing reinforcement and crack repair, and the reinforcement methods are limited for increasing the bearing capacity and the service life of the bridge. In addition, the requirements of structural stability cannot be met by adopting bar planting reinforcement and crack repair for small bridges and culverts with serious damage on parts, the small bridges and culverts mostly only can be rebuilt or are internally lined with corrugated steel plates under the condition that structural stress cannot meet the use requirements, the small bridge culverts are built in 60 ages in the last century, and the small bridge culverts around 70 years, are half a century old today, have historical memorial significance, the rebuilding and is dismantled and loses historical memorial value, and the small bridge culverts are reinforced by concrete filling, thereby forming a complete whole with the original structure, thereby providing good supporting force, not only ensuring the safety of the original bridge structure, but also prolonging the service life, achieving the purpose of repairing and transforming, and having high memorial significance for the history of old bridges.
Compared with the traditional concrete material, the corrugated steel plate has the advantages of light weight, high strength, good stress performance, strong adaptability, short construction period, long service life and the like, and is increasingly widely applied to the construction of domestic and foreign roads, particularly mountainous roads and unfavorable geological conditions.
For part of severely damaged road and bridge culverts, if the road and bridge culverts are rebuilt, the time consumption is long, the cost is high, the normal operation of traffic is affected, and in addition, some historical original appearances cannot be reserved;
disclosure of Invention
The invention aims to solve the problems that if a seriously damaged road and bridge culvert in the prior art is rebuilt, the time consumption is long, the manufacturing cost is high, the protection significance on the history of the bridge is lost, and the normal operation of traffic is influenced.
The technical scheme adopted by the invention is as follows: a method for reinforcing a bridge by a corrugated steel arch structure comprises the following steps:
the method comprises the following steps: and (5) coffering. The cofferdam and the diversion wall are formed by using stone slab concrete or sand bag for building the wall, so that the problem that construction cannot be carried out due to over-emergency water or water flow is solved. Determining a cofferdam foundation according to the water level and the depth of water, building a weir after tamping the cofferdam foundation, wherein the built weir needs to ensure the difference of water pressure inside and outside a weir wall and ensure the firmness of the cofferdam;
step two: excavating a foundation pit, wherein the joint of the steel corrugated plate and the arch springing needs to be excavated according to the section of a foundation trench specified by design; reserving a soil layer with a certain thickness according to the soil layer condition, so that the soil layer reaches the designed elevation of the substrate after being tamped; the foundation pit should avoid the overexcavation, such as the overexcavation, should remove the loose part, when the foundation soil is a bad soil layer such as silt, should adopt the good gravel of gradation, natural sand, gravel soil, but need to remove the hard thing such as more than 100mm of stone, the bedding course compacts according to the compactness that the design requires;
step three: treating the arch springing part; because the main stress point of newly-increased shaped steel rack and wave form steel sheet is the hunch foot position, strengthen the processing to the hunch foot position: concrete arch foot foundations are poured over the original arch bottom concrete slab along the bridge width direction in full length, and meanwhile, steel bars are implanted between the new foundation and the old foundation, so that the new foundation and the old foundation become a finished stress, and the stress condition of the foundations is increased. In order to facilitate the installation of a steel corrugated plate and the improvement of the connection firmness of the corrugated steel plate and a foundation and the stress point of an arch, a rectangular groove with the width of 0.3 m and the height of 0.2 m is reserved at the arch angle part and the original structure surface, and a steel member is embedded at the bottom of the groove to connect the steel corrugated arch;
step four: checking the flatness, the level and the elevation of the bottom of the corrugated steel plate arch; checking a civil engineering standard, and determining the position, the central axis and the midpoint of the steel plate arch;
step five: sequentially assembling corrugated steel plates from bottom to top; axial lapping is adopted between the steel plates, the upper plate of the lapping part covers the lower plate, the circumferential connection adopts a step shape, namely, the connection lap joint of the upper two plates is staggered with the lap joint of the lower two plates, after the connecting holes are aligned, a bolt coated with a lubricant is used, a washer is sleeved on the bolt, a hole site is inserted from inside to outside, a nut is pre-tightened by a socket wrench, and corrugated plates at two sides are symmetrically installed;
step six: when a plurality of corrugated plates are assembled in the circumferential direction, the section shape is measured once, the corrugated plates are assembled continuously after reaching the standard, and the corrugated plates are adjusted in time when not reaching the standard; when the annular ring is assembled in the circumferential direction and closed, the section shape is measured, a positioning pull rod is adopted for fixing, a pre-tightening bolt is adjusted, and a first corrugated plate at the top is assembled;
step seven: after the corrugated steel plates are completely assembled, fastening all bolts according to the pretightening force torque by using a fixed-torque electric wrench, and marking the fastened bottom bolts by using red paint in sequence without omission; all bolts should be tightened before backfilling to ensure that the overlapping portions of the corrugations are tightly nested together;
step eight: after the lap joint of the outer ring of the corrugated steel plate arch meets the requirement of pre-tightening force torque, the lap joint of the outer ring of the corrugated steel plate arch is sealed and filled with special sealant to prevent water seepage at the joint of the corrugated steel plates;
step nine: after the steel corrugated main arch ring is assembled at the lower part of the bridge, an arch ring is assembled outside the steel corrugated main arch ring, the assembled steel plate arch is pulled to the arch bottom to be in place at the other side of the main arch ring through a winch or a chain block, and the assembly of the whole steel corrugated plate is sequentially completed; if one bridge has several spans, the bridge is assembled synchronously or sequentially from front to back, but the pouring concrete must be poured synchronously for several spans;
step ten: and (6) pouring concrete. Filling gaps between the steel corrugated plates and the original plates in a pump concrete mode or a bridge deck opening mode, adopting a segmented and vault two-side synchronous pouring mode in the pouring process, and performing segmented pouring on gaps on the vaults by adopting C20 fine aggregate concrete or micro-expansive concrete; the method of symmetrical pouring must be adopted when pouring, adopt the mode of knocking to trail in time the filling effect at the in-process of pouring, mend the not closely knit district section of filling effect, utilize the mode of electromagnetic shaker vibrations steel sheet to fill concrete vibrations, guarantee the closely knit degree of pouring of concrete, carry out the maintenance after pouring.
Furthermore, the soil foundation pit dug to the elevation in the second step cannot be exposed, disturbed or soaked for a long time, and the size, the elevation and the bearing capacity of the foundation pit should be checked in time. And after the requirements are met, performing foundation construction immediately.
Further, in the sixth step, in order to ensure that the required value of the bolt torque is reached, 2% of bolts on the longitudinal joint of the structure are randomly extracted before backfilling, a fixed-torque wrench is used for carrying out a sampling test, and if any test value exceeds a given torque range, 5% of all bolts on the longitudinal joint and the circumferential joint are sampled. If more than 90% of the above tests meet the requirements, the installation is considered to be qualified. Otherwise, the design should be re-checked to determine if the resulting torque value meets the requirements.
Furthermore, the soil foundation pit dug to the elevation cannot be exposed, disturbed or soaked for a long time, and the size, the elevation and the bearing capacity of the foundation pit should be checked in time; and after the requirements are met, performing foundation construction immediately.
Furthermore, a section steel reinforcing structure can be arranged between the corrugated steel plate arch and the inner side of the bridge according to engineering requirements, and the structure mainly plays a supporting role and reinforces supporting force.
Furthermore, the section steel reinforcing structure is I-shaped steel arch rings which are arranged at intervals of 20-40 cm along the width direction of the bridge, connecting steel bars are fixedly arranged between every two arch rings, and the connecting steel bars transversely connect every two I-shaped steel arch rings to form a whole.
Furthermore, the arch springing foundation is of a groove-shaped concrete structure, an embedded steel plate is arranged inside the groove shape, and the embedded steel plate can be provided with guide steel bars.
Furthermore, in the step ten, before the concrete is poured on the arch, temporary supporting treatment needs to be carried out on the corrugated steel plate arch to prevent the corrugated steel plate arch from being damaged in the concrete pumping process.
Furthermore, a waterproof layer can be arranged between the corrugated steel plate arch and the inner side of the bridge.
The invention has the advantages and characteristics that:
(1) the method effectively realizes the repair of the arched bridge to be repaired, solves the problems of complicated working procedures and low construction efficiency in the construction process of repairing the arched bridge by the corrugated steel plate at present, realizes the on-site rapid construction, reduces the labor and equipment investment, reduces the manufacturing cost, and can ensure the normal operation of roads in the construction process;
(2) possesses good structural strength and waterproof performance and occupies that the bridge arch headroom height is little.
Drawings
FIG. 1 is a schematic view of the overall mounting structure of the preferred embodiment of the present invention;
FIG. 2 is a schematic structural view of a column of a sectional view of a cofferdam construction according to a preferred embodiment of the present invention;
FIG. 3 is a circumferential connection view of the inner and outer surfaces of the segmented steel corrugated pipe according to the preferred embodiment of the present invention;
FIG. 4 is a structural view of a steel reinforcing structure according to a preferred embodiment of the present invention;
FIG. 5 is a schematic view of the layout of the anti-friction guiding bars according to the preferred embodiment of the present invention;
FIG. 6 is a schematic view of the anti-friction guide bars according to the preferred embodiment of the present invention;
FIG. 7 is a schematic view of an overall installation structure (cylindrical corrugated steel plate arch) according to another preferred embodiment of the present invention;
FIG. 8 is a schematic view of an overall installation structure (arc door type corrugated steel plate arch) according to another preferred embodiment of the present invention;
FIG. 9 is a schematic structural view of a deck arch for simple bridge reinforcement according to a preferred embodiment of the present invention;
the reference numbers in the figures denote: 1-corrugated steel plate arch, 2-arch springing foundation, 21-embedded steel plate, 22-guide steel bar and 3-section steel reinforcing structure.
Detailed Description
The invention is further illustrated with reference to the accompanying drawings:
example 1:
referring to fig. 1 and 2, a method for reinforcing a bridge with a corrugated steel arch structure includes the following steps:
the method comprises the following steps: and (5) coffering. The cofferdam and the diversion wall are formed by using stone slab concrete or sand bag for building the wall, so that the problem that construction cannot be carried out due to over-emergency water or water flow is solved. Determining a cofferdam foundation according to the water level and the depth of water, building a weir after tamping the cofferdam foundation, wherein the built weir needs to ensure the difference of water pressure inside and outside a weir wall and ensure the firmness of the cofferdam;
step two: excavating a foundation pit, wherein the joint of the steel corrugated plate and the arch springing needs to be excavated according to the section of a foundation trench specified by design; reserving a soil layer with a certain thickness according to the soil layer condition to ensure that the soil layer reaches the designed elevation of the substrate after being tamped; the foundation pit should avoid the overexcavation, such as the overexcavation, should remove the loose part, when the foundation soil is a bad soil layer such as silt, should adopt the good gravel of gradation, natural sand, gravel soil, but need to remove the hard thing such as more than 100 mm's stone, the compactness of the bedding cushion should not be less than 95%; the soil foundation pit dug to the elevation cannot be exposed, disturbed or soaked for a long time, and the size, the elevation and the bearing capacity of the foundation pit should be checked in time. And after the requirements are met, performing foundation construction immediately.
Step three: treating the arch springing part; because the main stress point of newly-increased shaped steel rack and wave form steel sheet is the hunch foot position, strengthen the processing to the hunch foot position: the method comprises the following steps of pouring a wide C30 reinforced concrete arch foot foundation over an original arch bottom concrete slab along the full length of the bridge width direction, improving the stress form of a corrugated steel slab arch by implanting short steel bars between a new foundation and an old foundation, reserving a rectangular groove with the width of 0.3 m and the height of 0.2 m at the position of an arch corner rubber, and embedding a steel member at the bottom of the groove to connect the steel corrugated arch;
step four: checking the flatness, the level and the elevation of the bottom of the corrugated steel plate arch; checking a civil engineering standard, and determining the position, the central axis and the midpoint of the steel plate arch;
step five: sequentially assembling corrugated steel plates from bottom to top; the axial lapping width is 120mm, the lapping part is covered with the lower plate by the upper plate, the circumferential connection adopts a step shape, namely, the connecting lap joint of the upper two plates is staggered with the lap joint of the lower two plates, after the connecting holes are aligned, a bolt coated with a lubricant is used, a washer (a convex pad used when meeting valley and a concave pad used when meeting peak but not reversed) is sleeved on the bolt, a hole site is inserted from inside to outside, a nut is pre-tightened by a socket wrench, and the corrugated plates at two sides are symmetrically installed;
step six: when a plurality of corrugated plates are circumferentially assembled, the section shape is measured once, the corrugated plates are assembled continuously after reaching the standard, and the corrugated plates are adjusted in time when not reaching the standard; when the annular ring is assembled in the circumferential direction and closed, the section shape is measured, a positioning pull rod is adopted for fixing, a pre-tightening bolt is adjusted, and a first corrugated plate at the top is assembled; in order to ensure that the required value of bolt torque is achieved, 2% of bolts on a longitudinal joint on a structure are randomly extracted before backfilling, a fixed-torque wrench is used for carrying out a sampling test, and if any test value exceeds a given torque range, 5% of all the bolts on the longitudinal joint and the circumferential joint are sampled. If more than 90% of the above tests meet the requirements, the installation is considered to be qualified. Otherwise, the design should be re-checked to determine if the resulting torque value meets the requirements.
Step seven: after the corrugated steel plates are completely assembled, fastening all bolts according to the pretightening force torque of 340 N.m +/-70 N.m by using a fixed-torque electric wrench, and marking the fastened bottom bolts by using red paint in sequence without omission; all bolts (including longitudinal and circumferential seams) should be tightened prior to backfilling to ensure that the overlapping portions of the corrugations nest closely together;
step eight: after the lap joint of the outer ring of the corrugated steel plate arch meets the requirement of pretightening force torque, special sealant or epoxy resin mortar can be used for sealing and filling to prevent water seepage at the joint of the corrugated steel plate arch;
step nine: after an arch ring assembly is completed outside a main arch ring of the arch bridge, pulling the assembled steel plate arch to the arch bottom to be in place through a winch or a chain block on the other side of the main arch ring; sequentially completing the assembly of the whole steel corrugated plate; if one bridge has several spans, the bridge is assembled synchronously or sequentially from front to back, but the pouring concrete must be poured synchronously for several spans;
step ten: pouring concrete; filling gaps on the arch in a pump concrete mode, adopting a sectional pouring treatment mode in the pouring process, and performing sectional pouring on the gaps on the arch by adopting C20 fine aggregate concrete, wherein each section is 5-8 meters; meanwhile, a symmetrical pouring method is adopted during pouring, the filling effect is tracked in time in a knocking mode in the pouring process, and the section with an uncompacted filling effect is filled; and (5) ensuring the pouring compactness of the concrete, and curing after pouring. The corrugated steel plate arch needs to be subjected to temporary supporting treatment before concrete is poured on the arch, so that the corrugated steel plate arch is prevented from being damaged in the concrete pumping process.
The soil foundation pit dug to the elevation cannot be exposed, disturbed or soaked for a long time, and the size, the elevation and the bearing capacity of the foundation pit should be checked in time. And after the requirements are met, performing foundation construction immediately.
Referring to fig. 3 and 4, a section steel reinforcing structure is further disposed between the corrugated steel plate arch and the inner side of the bridge. The structural steel reinforcing structure is I-shaped steel arch rings which are arranged at intervals of 20-40 cm along the width direction of the bridge, short reinforcing steel bars are fixedly arranged between every two arch rings, and the short reinforcing steel bars transversely link the I-shaped steel arch rings.
Referring to fig. 5 and 6, the arch foot foundation is a groove-type concrete structure, and an embedded steel plate is arranged in the groove-type concrete structure and provided with a guide steel bar.
And a waterproof rubber layer is arranged between the arch and the inner side of the bridge in consideration of the possibility of water seepage of the inner side of the bridge in the rainy period.
Example 2:
referring to fig. 7-9, the technical solution of the present invention can be implemented in other forms, such as a cylindrical corrugated steel in fig. 7 for reinforcing a bridge, and an arc-shaped door corrugated steel in fig. 8 for reinforcing a bridge; it can also be used for reinforcing a simple bridge as in fig. 9.
The foregoing shows and describes the general principles and features of the present invention, together with the advantages thereof. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only for the purpose of illustrating the structural relationship and principles of the present invention, but that various changes and modifications may be made without departing from the spirit and scope of the invention as defined in the appended claims. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (9)

1.一种波纹钢拱形结构加固桥梁的方法,其特征在于:包括如下步骤:1. a method for corrugated steel arch structure reinforcement bridge, is characterized in that: comprise the steps: 步骤一:围堰;利用片石混凝土或者沙袋筑墙设置成围堰及导流墙,解决有水或水流过急而无法施工的问题。根据水位水深确定围堰基础,夯实围堰基础后开始筑堰,筑堰应保证堰墙内外水压差,保证围堰的牢固;Step 1: Cofferdam; use rubble concrete or sandbags to build walls and set up cofferdams and diversion walls to solve the problem of water or too fast water flow and cannot be constructed. The cofferdam foundation is determined according to the water level and water depth. After the cofferdam foundation is compacted, the cofferdam foundation is built. The weir construction should ensure the water pressure difference between the inside and outside of the weir wall to ensure the firmness of the cofferdam; 步骤二:基坑开挖;钢波纹板与拱脚连接处应按设计规定的基槽断面进行开挖;应根据土层情况预留一定厚度的土层,使其夯实后达到基底设计标高;基坑应避免超挖,如超挖,应将松动部分清除,当基底土为淤泥等不良土层时,应采用级配良好的砂砾、天然砂、砾石土、碎石土,但需清除100mm以上的石块等硬物,垫层按照设计要求的压实度压实;Step 2: Excavation of the foundation pit; the connection between the steel corrugated plate and the arch foot should be excavated according to the section of the foundation groove specified by the design; a certain thickness of soil layer should be reserved according to the soil layer, so that it can reach the base design elevation after compaction; The foundation pit should avoid over-excavation. If over-excavation, the loose part should be removed. When the base soil is poor soil layer such as silt, well-graded gravel, natural sand, gravel soil and gravel soil should be used, but 100mm of soil should be removed. For the above stones and other hard objects, the cushion should be compacted according to the compaction degree required by the design; 步骤三:拱脚部位处理;由于新增型钢棚架及波形钢板的主要受力点为拱脚位置,对拱脚位置进行加强处理:在原拱底混凝土板其上方沿着桥宽方向全长浇筑混凝土拱脚基础,同时采用在新旧基础间植入钢筋,使新旧基础成为一个整理受力,增加基础的受力情况。为了便于安装钢波纹板及改善波纹钢板与基础的连接牢固性和拱的受力点,拱角部位与原结构面预留0.3米宽、高0.2米的矩形槽,在槽底预埋钢构件以连接钢波纹拱;Step 3: Treatment of the arch foot position; since the main stress point of the newly added profiled steel scaffold and corrugated steel plate is the arch foot position, strengthen the position of the arch foot position: pour the top of the original arch bottom concrete slab along the full length of the bridge width direction For the concrete arch foot foundation, steel bars are implanted between the old and new foundations, so that the old and new foundations become a finishing force and increase the force of the foundation. In order to facilitate the installation of corrugated steel plates and improve the connection firmness of corrugated steel plates and the foundation and the stress point of the arch, a rectangular groove with a width of 0.3 meters and a height of 0.2 meters is reserved between the corners of the arch and the original structural surface, and steel components are embedded at the bottom of the groove. to connect steel corrugated arches; 步骤四:检查波纹钢板拱底部平整度、水平、标高;核对土建基准,确定钢板拱的位置、中心轴线、中点;Step 4: Check the flatness, level and elevation of the bottom of the corrugated steel plate arch; 步骤五:由下向上顺次拼装波纹钢板;钢板与钢板之间采用轴向搭接,搭接部分上板复盖下板,圆周向连接采用阶梯形,即上面二块板的连接叠缝与下面二块板的叠缝错位,连接孔对正后,用涂上润滑剂的螺栓,套上垫圈由内向外插入孔位,用套筒扳手预紧螺母,两侧波纹板对称安装;Step 5: Assemble corrugated steel plates in sequence from bottom to top; axial lap joint is adopted between the steel plates and the steel plates, the upper plate of the overlapping part covers the lower plate, and the circumferential connection adopts a stepped shape, that is, the connection overlapping seam of the upper two plates is The overlapping seams of the lower two plates are misaligned. After the connecting holes are aligned, use the bolts coated with lubricant, put on the washers and insert them into the holes from the inside to the outside, use a socket wrench to pre-tighten the nuts, and install the corrugated plates on both sides symmetrically; 步骤六:圆周向拼装多块波纹板时,测定一次截面形状,达到标准再继续拼装,达不到标准应及时调整;圆周向拼装到环形圈合拢时,测定截面形状,采用定位拉杆固定,调整预紧螺栓,拼装顶部第一块波纹板;Step 6: When assembling multiple corrugated boards in the circumferential direction, measure the cross-sectional shape once, and then continue to assemble if the standard is reached. If the standard is not met, it should be adjusted in time; when the annular ring is assembled in the circumferential direction, measure the cross-sectional shape, fix it with a positioning rod, and adjust it. Pre-tighten the bolts to assemble the first corrugated plate at the top; 步骤七:波纹钢板拼装全部完成后,用定扭电动扳手,按预紧力扭矩紧固所有螺栓,依次序,不得遗漏,紧固后底螺栓用红漆标示;所有螺栓应在回填之前拧紧,保证波纹的重叠部分紧密地嵌套在一起;Step 7: After the corrugated steel plate is assembled, use a fixed-torque electric wrench to fasten all the bolts according to the pre-tightening torque, in order, without omission. After tightening, the bottom bolts are marked with red paint; all bolts should be tightened before backfilling. Ensure that the overlapping parts of the corrugations are closely nested; 步骤八:波纹钢板拱外圈搭接处用预紧力扭矩符合要求后,用专用密封胶封填波纹钢板拱外圈搭接处,以防钢波纹板连接处渗水;Step 8: After the pre-tightening torque at the lap joint of the outer ring of the corrugated steel plate arch meets the requirements, seal the lap joint of the outer ring of the corrugated steel plate arch with special sealant to prevent water seepage at the joint of the corrugated steel plate; 步骤九:在桥梁下部拼装钢波纹主拱圈外拼装完成一拱拱圈后,在主拱圈另一侧通过卷扬机或手拉葫芦对拼装完成的钢板拱往拱底拉拽就位,依次顺序完成整个钢波纹板的拼装;如果一座桥有几跨的情况下,应同步拼装或前后顺序拼装,但是,浇筑混凝土必须几跨同步浇筑;Step 9: Assemble the steel corrugated main arch ring at the lower part of the bridge after assembling an arch arch ring, on the other side of the main arch ring, pull the assembled steel plate arch to the bottom of the arch by means of a hoist or a chain hoist. Complete the assembly of the entire corrugated steel plate; if a bridge has several spans, it should be assembled synchronously or sequentially, but the concrete must be poured simultaneously across several spans; 步骤十:混凝土浇筑。采用泵送混凝土形式或在桥面开孔形式对钢波纹板与原体之间的空隙进行填充,在浇筑过程中采用分段及拱顶两侧同步浇筑的方式,必须做到同步浇筑,对拱上空隙采用C20细石混凝土或微膨胀混凝土进行分段浇筑;在浇筑时必须采用对称浇筑的办法,在浇筑的过程中采用敲击的方式对填充效果进行及时跟踪,对填充效果不密实的区段进行补填,利用震动器震动钢板的方式对填充混凝土震动,保证混凝土的浇筑密实度,浇筑完成后进行养护。Step 10: Concrete pouring. The gap between the corrugated steel plate and the original body is filled in the form of pumped concrete or in the form of opening on the bridge deck. During the pouring process, the method of simultaneous pouring on both sides of the vault and the two sides of the dome must be done synchronously. C20 fine stone concrete or micro-expanded concrete shall be used for sectional pouring of the gap on the arch; the method of symmetrical pouring must be adopted during pouring, and the filling effect shall be tracked in time by tapping during the pouring process. The section is filled, and the filled concrete is vibrated by vibrating the steel plate to ensure the compactness of the concrete pouring. After the pouring is completed, the maintenance is carried out. 2.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述步骤二中挖至标高的土质基坑不得长期暴露,扰动或浸泡,并应及时检查基坑尺寸、高程、基底承载力。符合要求后,应立即进行基础施工。2. The method for reinforcing bridges with corrugated steel arch structure according to claim 1, characterized in that: the soil foundation pit dug to the elevation in the step 2 must not be exposed, disturbed or soaked for a long time, and the size of the foundation pit should be checked in time , elevation, and base bearing capacity. After meeting the requirements, foundation construction should be carried out immediately. 3.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:3. the method for corrugated steel arch structure reinforcement bridge according to claim 1, is characterized in that: 所述步骤六中为了保证达到螺栓扭矩的要求值,在回填之前随机抽取结构上纵向接缝上2%的螺栓,用定扭扳手,进行抽检试验,如果有任一试验值超出了给定的扭矩范围,则应抽检纵向和环向接缝所有螺栓的5%。如果上述试验90%以上满足要求,则认为安装是合格的。否则应重新复核设计,以确定得到的扭矩值是否满足要求。In the sixth step, in order to ensure that the required value of the bolt torque is reached, 2% of the bolts on the longitudinal joints of the structure are randomly selected before backfilling, and a fixed torque wrench is used to conduct a random inspection test. If any test value exceeds the given value. torque range, 5% of all bolts should be sampled for longitudinal and circumferential joints. If more than 90% of the above tests meet the requirements, the installation is considered qualified. Otherwise, the design should be re-checked to determine whether the obtained torque value meets the requirements. 4.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述挖至标高的土质基坑不得长期暴露,扰动或浸泡,并应及时检查基坑尺寸、高程、基底承载力;符合要求后,应立即进行基础施工。4. The method for reinforcing bridges with corrugated steel arch structure according to claim 1, characterized in that: the soil foundation pit dug to the elevation shall not be exposed for a long time, disturbed or soaked, and the size, elevation, The bearing capacity of the base; after meeting the requirements, the foundation construction should be carried out immediately. 5.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述波纹钢板拱与桥梁内侧之间如工程需要还可设置有型钢加强结构,该结构主要起支撑作用,加强支撑力。5 . The method for reinforcing a bridge with a corrugated steel arch structure according to claim 1 , wherein the corrugated steel arch and the inner side of the bridge can also be provided with a profiled steel reinforcing structure as required by the project, and the structure mainly plays a supporting role. 6 . , strengthen the support. 6.根据权利要求5所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述型钢加强结构为沿桥梁宽度方向每隔20-40厘米布置的工字钢拱圈,每道拱圈之间固定设置有连接钢筋,连接钢筋将每道工字钢拱圈横向联系起来,形成一个整体。6. The method for reinforcing a bridge with a corrugated steel arch structure according to claim 5, wherein the profiled steel reinforcing structure is an I-beam arch ring arranged every 20-40 cm along the width direction of the bridge, and each arch Connecting steel bars are fixed between the rings, and the connecting steel bars connect each I-beam arch ring horizontally to form a whole. 7.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述拱脚基础为槽型混凝土结构,槽型内部设置有预埋钢板,预埋钢板可设置有导向钢筋。7 . The method for reinforcing a bridge with a corrugated steel arch structure according to claim 1 , wherein the base of the arch foot is a trough-shaped concrete structure, and a pre-embedded steel plate is arranged inside the trough, and the pre-embedded steel plate can be provided with a guide. 8 . rebar. 8.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述步骤十中在拱上混凝土浇筑前需要对波纹钢板拱进行临时支撑处理,以防止在泵送混凝土过程中,波纹钢板拱出现损伤。8. The method for reinforcing a bridge with a corrugated steel arch structure according to claim 1, wherein in the step 10, the corrugated steel plate arch needs to be temporarily supported before the concrete is poured on the arch to prevent the concrete from being pumped. During the process, the corrugated steel plate arch was damaged. 9.根据权利要求1所述的波纹钢拱形结构加固桥梁的方法,其特征在于:所述波纹钢板拱与桥梁内侧之间还可设置有防水层。9 . The method for reinforcing a bridge with a corrugated steel arch structure according to claim 1 , wherein a waterproof layer can be further provided between the corrugated steel arch and the inner side of the bridge. 10 .
CN202110177225.4A 2021-02-07 2021-02-07 Method for reinforcing bridge by corrugated steel arch structure Pending CN112942148A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110177225.4A CN112942148A (en) 2021-02-07 2021-02-07 Method for reinforcing bridge by corrugated steel arch structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110177225.4A CN112942148A (en) 2021-02-07 2021-02-07 Method for reinforcing bridge by corrugated steel arch structure

Publications (1)

Publication Number Publication Date
CN112942148A true CN112942148A (en) 2021-06-11

Family

ID=76244626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110177225.4A Pending CN112942148A (en) 2021-02-07 2021-02-07 Method for reinforcing bridge by corrugated steel arch structure

Country Status (1)

Country Link
CN (1) CN112942148A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293485A (en) * 2022-01-20 2022-04-08 四川省公路规划勘察设计研究院有限公司 An arch bridge reinforcement structure without interrupting traffic and its construction method
CN114483098A (en) * 2022-01-05 2022-05-13 中国电建集团贵阳勘测设计研究院有限公司 A concrete lining grouting support arch for tunnels
CN115522486A (en) * 2022-10-14 2022-12-27 山东高速工程建设集团有限公司 Arch corrugated steel plate installation and positioning fine-tuning device
CN116676889A (en) * 2023-04-24 2023-09-01 四川省公路规划勘察设计研究院有限公司 Corrugated steel reinforcement system and method for existing bridges

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104213514A (en) * 2014-08-25 2014-12-17 浙江大学 Reinforcement method of earthed corrugated steel plate-concrete combined arch bridge
CN105672144A (en) * 2016-02-19 2016-06-15 湖南省交通规划勘察设计院 Medium-small span old bridge reinforcement and jointing-widening structure and construction method thereof
CN106049516A (en) * 2016-06-16 2016-10-26 苏交科集团股份有限公司 Corrugated steel cofferdam hollow digging pile and manufacturing technique thereof
CN207646626U (en) * 2017-11-03 2018-07-24 中交第一公路勘察设计研究院有限公司 A kind of corrugated steel construction snow defence channel
KR102006981B1 (en) * 2018-08-10 2019-10-08 청암이앤씨 주식회사 Steel-concrete composite rahmen bridge and construction method thereof
CN210509228U (en) * 2019-08-28 2020-05-12 中铁三局集团有限公司 Corrugated plate hoisting device for tunnel renovation
CN211006302U (en) * 2019-10-22 2020-07-14 湖北盛达泰水利水电工程有限公司 Stone arch bridge
CN111676836A (en) * 2020-04-22 2020-09-18 青海路拓工程设施制造集团有限公司 Reinforcing construction method for corrugated steel of existing old small bridges and culverts
CN211815488U (en) * 2019-10-31 2020-10-30 衡水益通管业股份有限公司 Arch foot connecting piece of corrugated steel arch structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104213514A (en) * 2014-08-25 2014-12-17 浙江大学 Reinforcement method of earthed corrugated steel plate-concrete combined arch bridge
CN105672144A (en) * 2016-02-19 2016-06-15 湖南省交通规划勘察设计院 Medium-small span old bridge reinforcement and jointing-widening structure and construction method thereof
CN106049516A (en) * 2016-06-16 2016-10-26 苏交科集团股份有限公司 Corrugated steel cofferdam hollow digging pile and manufacturing technique thereof
CN207646626U (en) * 2017-11-03 2018-07-24 中交第一公路勘察设计研究院有限公司 A kind of corrugated steel construction snow defence channel
KR102006981B1 (en) * 2018-08-10 2019-10-08 청암이앤씨 주식회사 Steel-concrete composite rahmen bridge and construction method thereof
CN210509228U (en) * 2019-08-28 2020-05-12 中铁三局集团有限公司 Corrugated plate hoisting device for tunnel renovation
CN211006302U (en) * 2019-10-22 2020-07-14 湖北盛达泰水利水电工程有限公司 Stone arch bridge
CN211815488U (en) * 2019-10-31 2020-10-30 衡水益通管业股份有限公司 Arch foot connecting piece of corrugated steel arch structure
CN111676836A (en) * 2020-04-22 2020-09-18 青海路拓工程设施制造集团有限公司 Reinforcing construction method for corrugated steel of existing old small bridges and culverts

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
上海市路政局等: "《公路工程施工质量验收标准》", 28 February 2019, 同济大学出版社, pages: 50 *
张俊波等: "波纹钢板拱在石拱桥加固中的应用", 《城市建设理论研究(电子版)》, no. 14, 15 May 2018 (2018-05-15), pages 117 - 118 *
李百建等: "波纹钢板-混凝土钢合梁在旧桥加固中的应用技术", 《公路》, no. 10, 25 October 2016 (2016-10-25), pages 77 - 78 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114483098A (en) * 2022-01-05 2022-05-13 中国电建集团贵阳勘测设计研究院有限公司 A concrete lining grouting support arch for tunnels
CN114293485A (en) * 2022-01-20 2022-04-08 四川省公路规划勘察设计研究院有限公司 An arch bridge reinforcement structure without interrupting traffic and its construction method
CN114293485B (en) * 2022-01-20 2022-11-08 四川省公路规划勘察设计研究院有限公司 An arch bridge reinforcement structure without interrupting traffic and its construction method
CN115522486A (en) * 2022-10-14 2022-12-27 山东高速工程建设集团有限公司 Arch corrugated steel plate installation and positioning fine-tuning device
CN116676889A (en) * 2023-04-24 2023-09-01 四川省公路规划勘察设计研究院有限公司 Corrugated steel reinforcement system and method for existing bridges

Similar Documents

Publication Publication Date Title
CN108914931B (en) An assembled vertical shield ring foundation pile and construction method
CN112942148A (en) Method for reinforcing bridge by corrugated steel arch structure
CN110004991B (en) Anti-floating system and construction method of underground structure based on convex wing foot plate
CN108547645B (en) Assembled tunnel supporting device and method capable of realizing prestress
CN109252874B (en) A tunnel base and its construction method
CN105735157B (en) Highland and severe cold area cut-fill subgrades Large-diameter Steel corrugated culvert structure and construction method
CN110863520A (en) Construction structure and method for reinforcing pile foundation by using pushing steel sleeve
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
KR100819624B1 (en) Waterproof open caisson assembly and concrete foundation construction method using the same
CN219410378U (en) Rock slope overhanging type road structure
CN111287217B (en) A construction system and method for a pipe gallery with integrally prefabricated pipe sections and inner partitions
CN113028139B (en) Combined type connector of rain and sewage pipe and construction method
CN119289168A (en) A linear engineering assembled combined pipe construction method
CN111379273A (en) Construction method of corrugated steel comprehensive pipe gallery
CN217399730U (en) Manhole with reinforced well wall and integral well cover
CN208121929U (en) Heavy caliber combined type smears band interface rain pipe system
CN117845995A (en) A pipe segment type caisson and construction method thereof
CN116876518A (en) Construction method suitable for foundation pit supporting of assembled subway entrance and exit in soft soil area
CN115045338A (en) Prestressed reinforcement assembly type multi-loop straight-through cable inspection well and construction method thereof
KR100379187B1 (en) delay-joint method of constructuction for underground structure
CN115262433A (en) Construction method of large-diameter U-shaped steel corrugated pipe channel culvert
CN210263110U (en) Prefabricated template device of basement cushion cap and grade beam
CN116145642A (en) A sheet pile wall structure and method of use thereof
CN114232491A (en) Construction method of multi-span simply supported prestressed bridge span in tunnel
CN219508628U (en) Permanent open caisson for preventing pavement from subsidence

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20211111

Address after: 430034 floor 20, building 6, Lianfa Jiudu mansion, No. 235, Jiefang Avenue, Qiaokou District, Wuhan City, Hubei Province

Applicant after: HUBEI CHUTIAN LIANFA ROAD AND BRIDGE MAINTENANCE CO.,LTD.

Applicant after: Hubei chujianke Technology Co.,Ltd.

Address before: 430034 No. 13, floor 20, building 6, Lianfa jiudufu, Gutian 4th Road, Qiaokou District, Wuhan City, Hubei Province

Applicant before: HUBEI CHUTIAN LIANFA ROAD AND BRIDGE MAINTENANCE CO.,LTD.

Applicant before: Hubei chujianke Technology Co.,Ltd.

Applicant before: HUBEI CTLF ENGINEERING TEST AND DETECTION Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20210611

RJ01 Rejection of invention patent application after publication