KR102638502B1 - Through hole fire prevention structure of wall and construction method - Google Patents

Through hole fire prevention structure of wall and construction method Download PDF

Info

Publication number
KR102638502B1
KR102638502B1 KR1020230143576A KR20230143576A KR102638502B1 KR 102638502 B1 KR102638502 B1 KR 102638502B1 KR 1020230143576 A KR1020230143576 A KR 1020230143576A KR 20230143576 A KR20230143576 A KR 20230143576A KR 102638502 B1 KR102638502 B1 KR 102638502B1
Authority
KR
South Korea
Prior art keywords
installation
fireproof
wall
foam
hole
Prior art date
Application number
KR1020230143576A
Other languages
Korean (ko)
Inventor
강병안
Original Assignee
강병안
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강병안 filed Critical 강병안
Priority to KR1020230143576A priority Critical patent/KR102638502B1/en
Application granted granted Critical
Publication of KR102638502B1 publication Critical patent/KR102638502B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/94Protection against other undesired influences or dangers against fire
    • E04B1/948Fire-proof sealings or joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • F16L5/04Sealing to form a firebreak device

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)

Abstract

본 발명은 벽체의 관통구 방화구조 및 시공방법에 관한 것으로서, 보다 상세하게는 건물의 벽체에 형성된 관통구를 통과하는 급수관, 배수관, 환기덕트, 전기 트레이 등을 포함하는 설치물과 관통구 간을 기밀하여 화재 발생시, 화염 등이 관통구를 통해 번지지 않도록 하기 위한 벽체의 관통구 방화구조 및 시공방법에 관한 것이다.The present invention relates to a fire protection structure and construction method for penetration holes in a wall. More specifically, the present invention relates to a fire protection structure and construction method for penetration holes formed in the wall of a building. This relates to fire prevention structures and construction methods for penetration holes in walls to prevent flames from spreading through penetration holes in the event of a fire.

Description

벽체의 관통구 방화구조 및 시공방법{THROUGH HOLE FIRE PREVENTION STRUCTURE OF WALL AND CONSTRUCTION METHOD}{THROUGH HOLE FIRE PREVENTION STRUCTURE OF WALL AND CONSTRUCTION METHOD}

본 발명은 벽체의 관통구 방화구조 및 시공방법에 관한 것으로서, 보다 상세하게는 건물의 벽체에 형성된 관통구를 통과하는 급수관, 배수관, 환기덕트, 전기 트레이 등을 포함하는 설치물과 관통구 간을 기밀하여 화재 발생시, 화염 등이 관통구를 통해 번지지 않도록 하기 위한 벽체의 관통구 방화구조 및 시공방법에 관한 것이다.The present invention relates to a fire protection structure and construction method for penetration holes in a wall. More specifically, the present invention relates to a fire protection structure and construction method for penetration holes formed in the wall of a building. This relates to fire prevention structures and construction methods for penetration holes in walls to prevent flames from spreading through penetration holes in the event of a fire.

일반적으로 아파트 등의 공동주택을 포함하는 건물에는 층간을 구획하는 슬라브 및 측면 공간을 구획하는 벽체가 마련되면서 슬라브나 벽체에 우수관, 급수관, 배수관, 환기관, 전기 트레이 등을 포함하는 설치물의 설치나 통과를 위해 관통구가 형성된다.In general, buildings containing multi-family houses such as apartments are equipped with slabs that divide between floors and walls that divide side spaces, and installation or passage of installations including rainwater pipes, water supply pipes, drain pipes, ventilation pipes, and electric trays on the slabs or walls. A through hole is formed for.

그러나, 이와 같은 관통구는 설치물과의 사이로 틈새가 형성되면서 건물 내에서의 화재 발생시, 화염이나 연기 등이 관통구를 통해 확산되면서 화재 및 인명피해를 키울 수 있는 문제점이 있다.However, such a penetration hole has a problem in that a gap is formed between the installation and when a fire occurs in the building, flame or smoke spreads through the penetration hole, increasing the risk of fire and casualties.

이러한 문제를 일부 개선한 종래기술로 대한민국 특허 공개번호 제10-2018-0137899호(2018.12.28.)에는 '관통구 방화구조'가 개시되어 있다.As a prior art that partially improves these problems, Korean Patent Publication No. 10-2018-0137899 (December 28, 2018) discloses a 'penetrating hole fire protection structure'.

그러나, 이와 같은 종래의 관통구 방화구조는 관통구로 주입되는 충전재와 통과 설치체 간의 사이나, 충전재와 관통구 간의 사이를 효과적으로 기밀하지 못하면서 틈새가 발생될 수 있는 문제점이 있다.However, such a conventional through-hole fire protection structure has a problem in that a gap may be created between the filler injected into the through-hole and the through-hole, or between the filler and the through-hole, as the space between the filler and the through-hole is not effectively airtight.

대한민국 특허공개번호 제10-2018-0137899호(2018.12.28.) '관통구 방화구조'Republic of Korea Patent Publication No. 10-2018-0137899 (2018.12.28.) ‘Fire prevention structure of penetration hole’

본 발명은 상술한 문제점을 해결하기 위하여 창안된 것으로서, 본 발명의 목적은 건물의 벽체에 형성된 관통구를 통과하는 급수관, 배수관, 환기덕트, 전기 트레이 등을 포함하는 설치물과 관통구 간을 기밀하여 화재 발생시, 화염 등이 관통구를 통해 번지지 않도록 하기 위한 벽체의 관통구 방화구조 및 시공방법을 제공하는 것이다.The present invention was created to solve the above-mentioned problems, and the purpose of the present invention is to provide airtightness between the penetration holes and installations including water supply pipes, drain pipes, ventilation ducts, electric trays, etc. that pass through penetration holes formed in the wall of a building. It provides a fire prevention structure and construction method for penetration holes in the wall to prevent flames from spreading through the penetration holes in the event of a fire.

본 발명의 해결하고자 하는 과제는 이상에서 언급된 것들에 한정되지 않으며, 언급되지 아니한 다른 해결과제들은 아래의 기재로부터 당업자에게 명확하게 이해되어 질 수 있을 것이다.The problems to be solved by the present invention are not limited to those mentioned above, and other problems not mentioned can be clearly understood by those skilled in the art from the description below.

상술한 목적을 달성하기 위하여, 본 발명은 벽체에 형성된 관통구를 통과하는 설치물과 관통구 간을 기밀하는 방화구조에 있어서, 벽체의 전면에서 설치물과 관통구의 사이를 기밀하는 제1기밀부재; 후단부가 벽체의 전면에 접하도록 설치물의 외측을 감싸는 내화 충전패드; 및 상기 내화 충전패드와 벽체와의 사이를 기밀하는 제2기밀부재를 포함하는 것을 특징으로 하는 벽체의 관통구 방화구조를 제공한다.In order to achieve the above-described object, the present invention provides a fire protection structure that airtightens between an installation passing through a through hole formed in a wall and the penetration hole, comprising: a first airtight member airtight between the installation and the penetration hole at the front of the wall; A fireproof charging pad surrounding the outside of the installation so that the rear end is in contact with the front of the wall; and a second airtight member that airtightens between the fireproof charging pad and the wall.

또한, 설치물의 외측에 위치되도록 관통구로 삽입되는 내화폼을 더 포함하며, 상기 제1기밀부재는 방화 실란트로 이루어져 상기 내화폼과 관통구를 이루는 둘레 사이 및 상기 내화폼과 설치물의 사이를 덮도록 도포되고, 상기 제2기밀부재는 방화 실란트로 이루어져 상기 내화 충전패드의 외측에서 상기 내화 충전패드와 상기 내화폼의 사이를 덮도록 도포되거나, 상기 내화 충전패드와 벽체와의 사이를 덮도록 도포되는 것을 특징으로 한다.In addition, it further includes fire-resistant foam inserted into the through-hole so as to be located on the outside of the installation, and the first airtight member is made of fireproof sealant and is applied to cover between the fire-resistant foam and the perimeter of the through-hole and between the fire-resistant foam and the installation. The second airtight member is made of fireproof sealant and is applied on the outside of the fireproof charging pad to cover the space between the fireproof charging pad and the fireproof foam, or is applied to cover the space between the fireproof charging pad and the wall. Do it as

본 발명에 따른 상기 내화폼은 링 형태를 이루는 상태로부터 설치물을 중심으로 한 쌍의 폼유닛으로 분기되면서 설치물의 외측으로 결합되되, 전단부에 외측으로 돌출되는 플랜지가 형성되면서 관통구로의 삽입시, 상기 플랜지가 상기 관통구를 이루는 전단부 외측에 접하면서 삽입이 정지되는 것을 특징으로 한다.The fireproof foam according to the present invention is divided into a pair of foam units centered on the installation from a ring-shaped state and joined to the outside of the installation, and a flange protruding outward is formed at the front end, and when inserted into the through hole, Insertion is stopped when the flange contacts the outside of the front end forming the through hole.

본 발명에 따른 상기 플랜지는 상기 내화 충전패드보다 외측으로 돌출되고, 상기 플랜지를 벽체로 가압하는 가압수단을 더 포함하며, 상기 가압수단은 설치물의 양측에 배치되면서 상기 플랜지와 접하는 한 쌍의 가압판; 설치물의 외측으로 고정되는 클램프; 상기 클램프의 양측에 고정되며 전,후면을 관통하는 통공이 형성되는 한 쌍의 고정판; 후단부가 상기 가압판에 고정되고 전단부가 상기 통공을 통과하는 가압바; 상기 가압판과 상기 고정판의 사이에 위치되도록 상기 가압바의 외측으로 결합되어 상기 가압판을 상기 플랜지로 가압하는 탄성부재를 포함하는 것을 특징으로 한다.The flange according to the present invention protrudes outward from the fireproof charging pad and further includes a pressing means for pressing the flange to the wall, wherein the pressing means includes: a pair of pressure plates disposed on both sides of the installation and in contact with the flange; A clamp fixed to the outside of the installation; A pair of fixing plates fixed to both sides of the clamp and having through holes penetrating the front and rear surfaces; a pressure bar whose rear end is fixed to the pressure plate and whose front end passes through the hole; It is characterized in that it includes an elastic member coupled to the outside of the pressure bar so as to be located between the pressure plate and the fixing plate and pressing the pressure plate to the flange.

본 발명에 따른 상기 가압수단은 상기 탄성부재와 상기 고정판의 사이에 위치되도록 상기 가압바의 외측으로 전후 이동 가능하게 결합되는 이동링; 및 상기 통공으로 나사결합되는 한편, 내측으로 상기 가압바가 통과하면서 조임 회전에 따라 상기 탄성부재를 상기 가압판으로 가압하여 상기 플랜지가 벽체로 밀착되도록 하는 조절부재를 더 포함하는 것을 특징으로 한다.The pressing means according to the present invention includes a moving ring coupled to the outside of the pressing bar so as to be movable back and forth so as to be positioned between the elastic member and the fixing plate; And an adjustment member screwed into the through hole and pressurizing the elastic member to the pressure plate according to the tightening rotation while the pressure bar passes inside, so that the flange is in close contact with the wall.

본 발명에 따른 벽체의 관통구 방화구조의 시공방법으로서, 벽체의 전면에서 설치물과 관통구의 사이를 제1기밀부재로 기밀하는 1차 기밀단계; 후단부가 벽체의 전면에 접하도록 내화 충전패드를 설치물의 외측으로 감싸는 내화 충전패드 설치단계; 상기 내화 충전패드의 후단부와 벽체와의 사이를 제2기밀부재로 기밀하는 2차 기밀단계; 및 1차 기밀단계 전에 설치물의 외측에 위치되도록 관통구로 내화폼을 삽입하는 내화폼 삽입단계를 더 포함하며, 상기 1차 기밀단계에서는 상기 제1기밀부재가 상기 내화폼과 벽체 간 및 상기 내화폼과 설치물 간으로 도포되고, 상기 2차 기밀단계에서는 상기 제2기밀부재가 상기 내화 충전패드와 상기 내화폼 간이나, 상기 내화 충전패드와 벽체 간으로 도포되는 것을 특징으로 하는 벽체의 관통구 방화구조의 시공방법을 제공한다.A method of constructing a fire protection structure for a penetration hole in a wall according to the present invention, comprising: a first airtight step of airtightening the space between the installation and the penetration hole on the front side of the wall with a first airtight member; A fire-resistant charging pad installation step of wrapping the fire-resistant charging pad around the outside of the installation so that the rear end is in contact with the front of the wall; A second airtight step of airtightening the space between the rear end of the fireproof charging pad and the wall with a second airtight member; And it further includes a fire-resistant foam insertion step of inserting the fire-resistant foam into the through-hole so that it is located on the outside of the installation before the first air-tightening step, wherein the first air-tight member is inserted between the fire-resistant foam and the wall and the fire-resistant foam. and the installation, and in the second airtight step, the second airtight member is applied between the fireproof filling pad and the fireproof foam, or between the fireproof filling pad and the wall. A through-hole fire protection structure of the wall, characterized in that Provides a construction method.

본 발명에 따른 벽체의 관통구 방화구조의 시공방법으로서, 벽체의 전면에서 설치물과 관통구의 사이를 제1기밀부재로 기밀하는 1차 기밀단계; 후단부가 벽체의 전면에 접하도록 내화 충전패드를 설치물의 외측으로 감싸는 내화 충전패드 설치단계; 상기 내화 충전패드의 후단부와 벽체와의 사이를 제2기밀부재로 기밀하는 2차 기밀단계; 및 1차 기밀단계 전에 설치물의 외측에 위치되도록 관통구로 내화폼을 삽입하는 내화폼 삽입단계;를 포함하며, 상기 내화폼 삽입단계는 내,외주면이 관통구와 설치물의 형태에 맞게 상기 내화폼을 링 형태로 준비하는 내화폼 준비단계; 상기 내화폼을 설치물을 중심으로 상기 한 쌍의 폼유닛으로 분기하는 내화폼 분기단계; 및 상기 내화폼을 관통구로 삽입하는 내화폼 삽입단계를 포함하고, 상기 1차 기밀단계에서는 상기 제1기밀부재가 상기 내화폼과 벽체 간 및 상기 내화폼과 설치물 간으로 도포되고, 상기 2차 기밀단계에서는 상기 제2기밀부재가 상기 내화 충전패드와 상기 내화폼 간으로 도포되며, 상기 2차 기밀단계 후에 상기 가압수단을 설치물에 설치하여 상기 플랜지를 벽체로 가압하는 플랜지 가압단계를 더 포함하는 것을 특징으로 하는 벽체의 관통구 방화구조의 시공방법을 제공한다.A method of constructing a fire protection structure for a penetration hole in a wall according to the present invention, comprising: a first airtight step of airtightening the space between the installation and the penetration hole on the front side of the wall with a first airtight member; A fire-resistant charging pad installation step of wrapping the fire-resistant charging pad around the outside of the installation so that the rear end is in contact with the front of the wall; A second airtight step of airtightening the space between the rear end of the fireproof charging pad and the wall with a second airtight member; And a fire-resistant foam insertion step of inserting the fire-resistant foam into the through-hole so that it is located on the outside of the installation before the first airtightness step. The fire-resistant foam insertion step includes ringing the fire-resistant foam so that the inner and outer peripheral surfaces match the shape of the through-hole and the installation. Preparation step of fireproof foam prepared in a shape; A fireproof foam branching step of branching the fireproof foam into the pair of foam units centered on the installation; And a fire-resistant foam insertion step of inserting the fire-resistant foam into a through hole, wherein in the first airtight step, the first airtight member is applied between the fire-resistant foam and the wall and between the fire-resistant foam and the installation, and the secondary airtight In the step, the second airtight member is applied between the fireproof filling pad and the fireproof foam, and after the second airtightness step, the pressurizing means is installed on the installation to press the flange to the wall, further comprising a flange pressurizing step. Provides a construction method for a fire-proof structure with a penetration hole in a wall.

본 발명에 따르면, 건물의 벽체에 형성된 관통구를 통과하는 급수관, 배수관, 환기덕트, 전기 트레이 등을 포함하는 설치물과 관통구 간을 기밀함으로써 화재 발생시, 화염 등이 관통구를 통해 번지는 것을 방지할 수 있는 효과가 있다.According to the present invention, in the event of a fire, flames, etc., are prevented from spreading through the penetration hole by airtightening the gap between the penetration hole and installations including water supply pipes, drain pipes, ventilation ducts, electric trays, etc. that pass through the penetration hole formed in the wall of the building. There is an effect that can be done.

본 발명의 효과는 이상에서 언급된 것들에 한정되지 않으며, 언급되지 아니한 다른 해결과제들은 아래의 기재로부터 당업자에게 명확하게 이해되어 질 수 있을 것이다.The effects of the present invention are not limited to those mentioned above, and other problems not mentioned can be clearly understood by those skilled in the art from the description below.

도 1은 본 발명에 따른 벽체의 관통구 방화구조를 나타낸 측단면도이다.
도 2는 도 1에서 내화폼이 구비된 상태를 나타낸 측단면도이다.
도 3은 도 2에서 내화폼의 다른 예를 나타낸 측단면도이다.
도 4는 도 3에서 내화폼을 나타낸 사시도이다.
도 5는 본 발명에 따른 벽체의 관통구 방화구조에서 가압수단을 나타낸 사시도이다.
도 6은 도 5의 가압수단이 설치물에 설치된 상태를 나타낸 평면도이다.
도 7은 본 발명에 따른 벽체의 관통구 방화구조의 시공방법을 나타낸 순서도이다.
그리고
도 8은 본 발명에 따른 벽체의 관통구 방화구조의 시공방법의 다른 예를 나타낸 순서도이다.
Figure 1 is a side cross-sectional view showing a through-hole fire prevention structure of a wall according to the present invention.
Figure 2 is a side cross-sectional view showing a state in which the fireproof foam in Figure 1 is provided.
Figure 3 is a side cross-sectional view showing another example of the fireproof foam in Figure 2.
Figure 4 is a perspective view showing the fireproof foam in Figure 3.
Figure 5 is a perspective view showing the pressurizing means in the through-hole fire prevention structure of the wall according to the present invention.
Figure 6 is a plan view showing the pressurizing means of Figure 5 installed in an installation.
Figure 7 is a flow chart showing the construction method of the through-hole fire protection structure of the wall according to the present invention.
and
Figure 8 is a flowchart showing another example of a construction method of a fire-proof structure through a wall penetration hole according to the present invention.

이하, 첨부된 도면에 의하여 본 발명의 바람직한 실시예를 보다 상세하게 설명한다.Hereinafter, preferred embodiments of the present invention will be described in more detail with reference to the attached drawings.

도 1을 참조하여 보면, 본 발명에 따른 벽체의 관통구 방화구조(이하 "방화구조"라 한다)(100)는 아파트 등의 공동주택을 포함하는 건물의 실내 벽체(A)에 형성된 관통구(B)를 통과하는 설치물(C)과 관통구(B) 간을 기밀하는 방화구조로서, 벽체(A)의 전면에서 설치물(C)과 관통구(B)의 사이를 기밀하는 제1기밀부재(110), 벽체(A)에 접하도록 설치물(C)의 외측을 감싸는 내화 충전패드(120) 및 내화 충전패드(120)와 벽체(A)와의 사이를 기밀하는 제2기밀부재(130)를 포함할 수 있다.Referring to Figure 1, the through-hole fire prevention structure (hereinafter referred to as "fire prevention structure") of the wall according to the present invention (100) is a through-hole formed in the interior wall (A) of a building including an apartment complex, etc. It is a fire prevention structure that airtightens between the installation (C) and the penetration hole (B) passing through B), and the first airtight member ( 110), a fireproof charging pad 120 surrounding the outside of the installation (C) in contact with the wall (A), and a second airtight member 130 that airtightens the gap between the fireproof charging pad 120 and the wall (A). can do.

설치물(C)은 급수관, 배수관, 환기덕트, 전기 트레이 등으로 이루어질 수 있다.The installation (C) may be composed of a water supply pipe, a drain pipe, a ventilation duct, an electric tray, etc.

건물에는 각 세대 등으로의 전원 공급이나 급,배수 등을 위한 설치물(C)이 설치될 수 있으며, 벽체(A)에는 설치물(C)이 통과될 수 있도록 관통구(B)가 형성될 수 있다.Installations (C) may be installed in the building for power supply, water supply, and drainage to each household, etc., and a through hole (B) may be formed in the wall (A) to allow the installation (C) to pass through. .

본 발명에 따른 방화구조(100)는 설치물(C)과 관통구(B) 간을 기밀하여 화재 발생시, 화염 등이 관통구(B)를 통해 번지는 것을 방지한다.The fire protection structure 100 according to the present invention provides airtightness between the installation (C) and the penetration hole (B) to prevent flames, etc. from spreading through the penetration hole (B) when a fire occurs.

제1기밀부재(110)는 방화 실란트 등으로 이루어질 수 있으며 코킹작업 등을 통해 설치물(C)과 관통구(B)의 사이를 기밀할 수 있다.The first airtight member 110 may be made of fireproof sealant, etc., and can airtighten the space between the installation (C) and the through hole (B) through caulking, etc.

제1기밀부재(110)는 벽체(A)의 양면 중 어느 한 면에서 설치물(C)과 관통구(B)를 이루는 둘레 사이를 덮도록 코킹 다시 말하면, 도포되면서 설치물(C)과 관통구(B)의 사이를 기밀할 수 있다. 여기서, 벽체(A)의 양면 중 어느 한 면은 본 발명의 명확한 설명을 위해 전면으로 하기로 한다.The first airtight member 110 is caulked to cover the perimeter forming the installation (C) and the through hole (B) on either side of the wall (A). In other words, it is applied to cover the installation (C) and the through hole (B). B) can be confidential. Here, one of the two sides of the wall (A) is assumed to be the front for clear explanation of the present invention.

내화 충전패드(120)는 후단부가 벽체(A)의 전면에 접하도록 설치물(C)의 외측을 감싸되, 판상으로 이루어진 상태로부터 설치물(C)의 외측을 감싸면서 접착테이프 등에 의해 설치물(C)로 고정될 수 있다.The fireproof charging pad 120 wraps around the outside of the installation (C) so that the rear end is in contact with the front of the wall (A), and wraps around the outside of the installation (C) in a plate-shaped state and is attached to the installation (C) by adhesive tape, etc. It can be fixed as .

제2기밀부재(130)는 방화 실란트 등으로 이루어질 수 있으며 코킹작업 등을 통해 내화 충전패드(120)의 후단부와 벽체(A) 간을 덮도록 코킹 다시 말하면, 도포되면서 내화 충전패드(120)와 벽체(A)와의 사이를 기밀할 수 있다.The second airtight member 130 may be made of fireproof sealant, etc., and is caulked to cover the area between the rear end of the fireproof charging pad 120 and the wall A through caulking, etc. In other words, while being applied, the fireproof charging pad 120 The space between and the wall (A) can be airtight.

방화구조(100)는 도 2 내지 도 4에 도시된 바와 같이 관통구(B)와 설치물(C)의 사이로 삽입되는 내화폼(140)을 더 포함할 수 있다.The fire protection structure 100 may further include fire resistant foam 140 inserted between the through hole (B) and the installation (C) as shown in FIGS. 2 to 4.

내화폼(140)은 관통구(B)와 설치물(C)의 사이가 넓게 벌어진 경우에 사용될 수 있다.Fireproof foam 140 can be used when the gap between the through hole (B) and the installation (C) is wide.

제1기밀부재(110)는 내화폼(140)과 관통구(B)를 이루는 둘레 사이 및 내화폼(140)과 설치물(C)의 사이를 덮도록 도포되면서 내화폼(140)과 벽체(A) 간 및 내화폼(140)과 설치물(C) 간을 기밀할 수 있다.The first airtight member 110 is applied to cover the area between the fireproof foam 140 and the perimeter of the through hole (B) and between the fireproof foam 140 and the installation (C), thereby forming the fireproof foam 140 and the wall (A). ) It can be airtight between the fireproof foam (140) and the installation (C).

내화폼(140)은 도 4에 도시된 바와 같이 내,외주면이 관통구(B)와 설치물(C)의 형태에 맞게 링 형태를 이루는 상태로부터 설치물(C)을 중심으로 한 쌍의 폼유닛(141)으로 분기될 수 있다. 예를 들면, 내화폼(140)은 설치물(C)을 중심으로 상하 방향으로 한 쌍의 폼유닛(141)으로 절단되며 분기될 수 있다.As shown in FIG. 4, the fireproof foam 140 is a pair of foam units ( 141). For example, the fireproof foam 140 may be cut and branched into a pair of foam units 141 in the vertical direction around the installation C.

한 쌍의 폼유닛(141)은 설치물(C)의 외측 상,하부로 결합되면서 가압에 따라 관통구(B)와 설치물(C) 간으로 삽입될 수 있다.A pair of foam units 141 are coupled to the outer upper and lower parts of the installation (C) and can be inserted between the through hole (B) and the installation (C) according to pressure.

폼유닛(141)과 폼유닛(141)의 사이는 관통구(B)로 삽입된 상태에서 방화 실란트 등에 의해 기밀될 수 있다. 폼유닛(141)은 관통구(B)로의 삽입이 원활하게 이루어질 수 있도록 중앙부를 중심으로 좌우 한 쌍으로 분기될 수도 있다.The space between the foam units 141 and the foam units 141 can be airtightened with a fireproof sealant or the like when inserted into the through hole (B). The form unit 141 may be branched into a left and right pair centered on the central portion to ensure smooth insertion into the through hole (B).

내화폼(140)은 도 3 내지 도 4에 도시된 바와 같이 전단부에 외측으로 돌출되는 플랜지(142)가 형성될 수 있다.As shown in FIGS. 3 and 4, the fireproof foam 140 may be formed with a flange 142 protruding outward at the front end.

플랜지(142)는 내화폼(140)이 관통구(B)와 설치물(C)의 사이로 삽입될 때, 관통구(B)를 이루는 전단부 외측에 접하면서 내화폼(140)에 대한 삽입이 정지되도록 할 수 있다.When the fire-resistant foam 140 is inserted between the through-hole (B) and the installation (C), the flange 142 stops inserting the fire-resistant foam 140 while contacting the outside of the front end forming the through-hole (B). It can be done as much as possible.

플랜지(142)는 제1기밀부재(110)에 의해 벽체(A)와의 사이가 기밀될 수 있다. 다시 말하면, 플랜지(142)는 가장자리가 제1기밀부재(110)에 의해 벽체(A)에 고정되면서 벽체(A)와의 사이가 기밀될 수 있다.The flange 142 can be airtightened with the wall A by the first airtight member 110. In other words, the edge of the flange 142 is fixed to the wall A by the first airtight member 110, and the space between the flange 142 and the wall A can be airtight.

제2기밀부재(130)는 내화 충전패드(120)의 후단부가 내화폼(140)을 벗어나지 않는 경우, 내화 충전패드(120)의 외측에서 내화 충전패드(120)와 내화폼(140)의 사이를 덮도록 도포되면서 내화 충전패드(120)와 내화폼(140) 간을 기밀할 수 있다.When the rear end of the fireproof charging pad 120 does not go beyond the fireproof foam 140, the second airtight member 130 is installed between the fireproof charging pad 120 and the fireproof foam 140 on the outside of the fireproof charging pad 120. By being applied to cover, the space between the fireproof charging pad 120 and the fireproof foam 140 can be airtight.

제2기밀부재(130)는 내화 충전패드(120)의 후단부가 내화폼(140)을 벗어나는 경우, 내화 충전패드(120)의 외측에서 내화 충전패드(120)와 벽체(A)의 사이를 덮도록 도포되면서 내화 충전패드(120)와 벽체(A) 간을 기밀할 수 있다.When the rear end of the fireproof charging pad 120 leaves the fireproof foam 140, the second airtight member 130 covers the space between the fireproof charging pad 120 and the wall (A) on the outside of the fireproof charging pad 120. As it is applied, the space between the fireproof charging pad 120 and the wall (A) can be made airtight.

플랜지(142)는 내화 충전패드(120)보다 외측으로 돌출될 수 있다.The flange 142 may protrude outward from the refractory charging pad 120.

방화구조(100)는 도 5 내지 도 6에 도시된 바와 같이 플랜지(142)를 벽체(A)로 가압하는 가압수단(160)을 더 포함할 수 있다.The fire protection structure 100 may further include pressurizing means 160 for pressurizing the flange 142 to the wall A, as shown in FIGS. 5 and 6.

가압수단(160)은 도 5에 도시된 바와 같이 설치물(C)의 양측에 배치되면서 플랜지(142)와 접하는 한 쌍의 가압판(161), 설치물(C)의 외측으로 고정되는 클램프(162), 클램프(162)의 양측에 고정되며 전,후면을 관통하는 통공(163a)이 형성되는 한 쌍의 고정판(163), 후단부가 가압판(161)에 고정되고 전단부가 통공(163a)을 통과하는 가압바(164) 및 가압판(161)과 고정판(163)의 사이에 위치되도록 가압바(164)의 외측으로 결합되는 탄성부재(165)를 포함할 수 있다.As shown in FIG. 5, the pressing means 160 includes a pair of pressure plates 161 disposed on both sides of the installation C and in contact with the flange 142, a clamp 162 fixed to the outside of the installation C, A pair of fixing plates 163 that are fixed to both sides of the clamp 162 and have holes 163a penetrating the front and rear sides, and a pressure bar whose rear end is fixed to the pressure plate 161 and whose front end passes through the hole 163a (164) and an elastic member 165 coupled to the outside of the pressure bar 164 so as to be positioned between the pressure plate 161 and the fixing plate 163.

가압판(161)은 플랜지(142)의 전방 양측에 배치되면서 한 쌍의 폼유닛(141)이 접하는 부분으로 밀착될 수 있다.The pressure plate 161 may be disposed on both front sides of the flange 142 and come into close contact with the portion where the pair of foam units 141 come into contact.

클램프(162)는 설치물(C)의 외주면에 맞게 링 형태를 이루는 상태로부터 설치물(C)을 중심으로 한 쌍의 클램프유닛(162a)으로 분기되면서 볼트,너트를 포함하는 결합구(166)에 의해 설치물(C)의 외측으로 밀착되며 고정될 수 있다.The clamp 162 is branched from a ring-shaped state to fit the outer peripheral surface of the installation C into a pair of clamp units 162a centered on the installation C, and is connected by a coupler 166 including bolts and nuts. It can be closely adhered to and fixed to the outside of the installation (C).

고정판(163)은 일단부가 클램프(162)의 양측에 고정되고 타단부가 외측으로 연장 형성되면서 가압판(161)과 전후 대향될 수 있다.The fixing plate 163 may have one end fixed to both sides of the clamp 162 and the other end extending outward to face the pressure plate 161 back and forth.

가압바(164)는 후단부가 가압판(161)의 전면에 고정되고 전단부가 통공(163a)을 통과하면서 클램프(162)보다 전방으로 돌출될 수 있다.The pressure bar 164 may have its rear end fixed to the front of the pressure plate 161 and its front end protruding forward from the clamp 162 while passing through the through hole 163a.

탄성부재(165)는 스프링으로 이루어질 수 있으며 가압판(161)과 고정판(163)의 사이에 위치되도록 가압바(164)의 외측으로 결합되면서 고정판(163)으로부터 가압판(161)을 벽체(A) 방향으로 가압할 수 있다.The elastic member 165 may be made of a spring and is coupled to the outside of the pressure bar 164 so as to be located between the pressure plate 161 and the fixing plate 163 and moves the pressure plate 161 from the fixing plate 163 in the direction of the wall (A). It can be pressurized.

가압수단(160)은 도 6에 도시된 바와 같이 탄성부재(165)와 고정판(163)의 사이에 위치되도록 가압바(164)의 외측으로 전후 이동 가능하게 결합되는 이동링(167), 통공(163a)으로 나사결합되는 한편, 내측으로 가압바(164)가 통과하면서 조임 회전에 따라 이동링(167)과 함께 탄성부재(165)를 가압판(161)으로 가압하여 플랜지(142)가 벽체(A)로 밀착되도록 하는 조절부재(168)를 더 포함할 수 있다.As shown in FIG. 6, the pressing means 160 includes a moving ring 167 and a hole ( 163a), while the pressure bar 164 passes inside and presses the elastic member 165 with the moving ring 167 to the pressure plate 161 according to the tightening rotation, so that the flange 142 is pressed against the wall (A). ) may further include an adjustment member 168 that ensures close contact.

이동링(167)은 판상으로 이루어지는 중앙부에 구멍(167a)이 형성되면서 가압바(164)의 외측으로 전후 이동 가능하게 결합될 수 있다.The movable ring 167 can be coupled to the outside of the pressure bar 164 so as to be able to move back and forth while a hole 167a is formed in the plate-shaped central portion.

통공(163a)은 내주면에 나사산이 형성될 수 있다.The through hole 163a may have a thread formed on its inner peripheral surface.

조절부재(168)는 외주면에 나사산이 형성되면서 통공(163a)으로 나사결합될 수 있다.The adjustment member 168 may be screwed into the through hole 163a while threads are formed on the outer peripheral surface.

조절부재(168)은 전단부에 외측으로 돌출되는 손잡이부가 형성될 수 있다.The adjustment member 168 may have a handle portion protruding outwardly formed at the front end.

손잡이부(168a)는 외주면에 나사산이 형성되지 않으면서 손 등으로의 파지를 통한 조절부재(168)의 회전이 원활하게 이루어지도록 할 수 있다.The handle portion 168a can smoothly rotate the adjustment member 168 by gripping it with the hand or the like without forming a thread on the outer peripheral surface.

조절부재(168)는 조임 회전에 따라 벽체(A) 방향으로 이동되면서 이동링(167)을 가압하여 탄성부재(165)가 수축되도록 하면서 가압판(161)으로의 탄발력이 보다 강하게 작용되도록 할 수 있다.The adjusting member 168 moves in the direction of the wall (A) according to the tightening rotation and presses the moving ring 167 so that the elastic member 165 is contracted and the elastic force on the pressure plate 161 can be applied more strongly. there is.

플랜지(142)는 가압수단(160)에 의해 벽체(A)로 밀착되면서 제1기밀부재(110)가 떨어지거나 변형되더라도 벽체(A)와의 사이가 벌어지지 않을 수 있다.The flange 142 is in close contact with the wall A by the pressurizing means 160 and may not be separated from the wall A even if the first airtight member 110 falls or is deformed.

이로 인해, 방화구조는 관통구(B)와 설치물(C)의 사이로 유입될 수 있는 화염 등을 보다 효과적으로 방지할 수 있다.Because of this, the fire prevention structure can more effectively prevent flames that may enter between the through hole (B) and the installation (C).

도 7 내지 도 8을 참조하여 본 발명에 따른 방화구조의 시공방법을 살펴 보면, 벽체(A)의 전면에서 설치물(C)과 관통구(B)의 사이를 제1기밀부재(110)로 기밀하는 1차 기밀단계, 내화 충전패드(120)로 설치물(C)의 외측을 감싸는 내화 충전패드 설치단계 및 내화 충전패드(120)와 벽체(A)와의 사이를 제2기밀부재(130)로 기밀하는 2차 기밀단계를 포함할 수 있다.Looking at the construction method of the fire protection structure according to the present invention with reference to Figures 7 and 8, the space between the installation (C) and the through hole (B) on the front of the wall (A) is airtight with the first airtight member (110). The first airtightness step, the fireproof charging pad installation step of surrounding the outside of the installation (C) with the fireproof charging pad 120, and the second airtightness member 130 between the fireproof charging pad 120 and the wall (A). It may include a second confidentiality step.

방화구조의 시공방법은 1차 기밀단계 전에 설치물(C)의 외측에 위치되도록 관통구(B)로 내화폼(140)을 삽입하는 내화폼 삽입단계를 더 포함할 수 있다.The construction method of the fireproof structure may further include a fireproof foam insertion step of inserting the fireproof foam 140 into the through hole (B) so that it is located on the outside of the installation (C) before the first airtightness step.

내화폼 삽입단계에서는 내,외주면이 관통구(B)와 설치물(C)의 형태에 맞게 내화폼(140)을 링 형태로 준비하는 내화폼 준비단계, 내화폼(140)을 설치물(C)을 중심으로 한 쌍의 폼유닛(141)으로 분기하는 내화폼 분기단계 및 내화폼(140)을 관통구(B)로 삽입하는 내화폼 삽입단계를 포함할 수 있다.In the fireproof foam insertion step, the fireproof foam preparation step is to prepare the fireproof foam 140 in a ring shape so that the inner and outer peripheral surfaces match the shape of the through hole (B) and the installation (C). The fireproof foam (140) is then inserted into the installation (C). It may include a fire-resistant foam branching step of branching into a pair of foam units 141 at the center and a fire-resistant foam insertion step of inserting the fire-resistant foam 140 into the through hole (B).

내화폼 삽입단계에서는 내화폼(140)의 전단부에 형성된 플랜지(142)가 관통구(B)를 이루는 전단부 외측에 접하면서 내화폼(140)에 대한 삽입이 정지될 수 있다.In the fireproof foam insertion step, the flange 142 formed at the front end of the fireproof foam 140 comes into contact with the outside of the front end forming the through hole (B), and the insertion into the fireproof foam 140 may be stopped.

1차 기밀단계에서는 제1기밀부재(110)가 내화폼(140)과 벽체(A) 간 및 내화폼(140)과 설치물(C) 간으로 도포될 수 있다.In the first airtightness stage, the first airtight member 110 may be applied between the fireproof foam 140 and the wall (A) and between the fireproof foam 140 and the installation (C).

내화 충전패드 설치단계에서는 내화 충전패드(120)의 후단부가 벽체(A)의 전면에 접하도록 내화 충전패드(120)를 설치물(C)의 외측으로 감쌀 수 있다.In the fireproof charging pad installation step, the fireproof charging pad 120 may be wrapped around the outside of the installation (C) so that the rear end of the fireproof charging pad 120 is in contact with the front of the wall (A).

2차 기밀단계에서는 제2기밀부재(130)가 내화 충전패드(120)와 내화폼(140) 간이나, 내화 충전패드(120)와 벽체(A) 간으로 도포될 수 있다. In the second airtightness step, the second airtight member 130 may be applied between the fireproof filling pad 120 and the fireproof foam 140, or between the fireproof filling pad 120 and the wall (A).

방화구조의 시공방법은 2차 기밀단계 후에 가압수단(160)을 설치물(C)에 설치하여 플랜지(142)를 벽체(A)로 가압하는 플랜지 가압단계를 더 포함할 수 있다.The construction method of the fireproof structure may further include a flange pressurizing step in which the pressurizing means 160 is installed on the installation C after the second air tightness step to press the flange 142 to the wall A.

이때의 플랜지(142)는 내화 충전패드(120)보다 외측으로 돌출되고, 2차 기밀단계에서는 제2기밀부재(130)가 내화 충전패드(120)와 내화폼(140) 간으로 도포될 수 있다.At this time, the flange 142 protrudes outward from the fireproof filling pad 120, and in the second airtightness stage, the second airtight member 130 can be applied between the fireproof filling pad 120 and the fireproof foam 140. .

이로 인해, 방화구조의 시공방법은 건물의 벽체(A)에 형성된 관통구(B)를 통과하는 설치물(C)과 관통구(B) 간을 기밀하면서 화재 발생시, 화염 등이 관통구(B)를 통해 번지지 않도록 할 수 있다.For this reason, the construction method of the fireproof structure is to keep the gap between the installation (C) and the penetration hole (B) that passes through the penetration hole (B) formed in the wall (A) of the building airtight, so that in the event of a fire, flames, etc. are transmitted through the penetration hole (B). You can prevent it from spreading through .

이상에서 설명한 것은 본 발명에 따른 벽체의 관통구 방화구조 및 시공방법을 실시하기 위한 실시 예에 불과한 것으로서, 본 발명은 상기한 실시 예에 한정되지 않고, 이하의 특허청구범위에서 청구하는 바와 같이 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변경 실시가 가능한 범위까지 본 발명의 기술적 정신이 있다고 할 것이다.What has been described above is only an example for implementing the through-hole fire prevention structure and construction method of a wall according to the present invention, and the present invention is not limited to the above-described embodiment, and as claimed in the following patent claims. Anyone with ordinary knowledge in the field to which the invention pertains will say that the technical spirit of the present invention exists to the extent that various modifications can be made without departing from the gist of the invention.

100 : 방화구조 110 : 제1기밀부재
120 : 내화 충전패드 130 : 제2기밀부재
140 : 내화폼 141 : 폼유닛
142 : 플랜지 160 : 가압수단
161 : 가압판 162 : 클램프
163 : 고정판 164 : 가압바
165 : 탄성부재 166 : 결합구
100: Fire protection structure 110: First airtight member
120: Fireproof charging pad 130: Second airtight member
140: Fireproof foam 141: Foam unit
142: Flange 160: Pressurizing means
161: pressure plate 162: clamp
163: fixing plate 164: pressure bar
165: elastic member 166: coupler

Claims (7)

벽체에 형성된 관통구를 통과하는 설치물과 관통구 간을 기밀하는 방화구조에 있어서,
방화 실란트로 이루어져 벽체의 전면에서 설치물과 관통구의 사이를 기밀하는 제1기밀부재; 방화 실란트로 이루어져 후단부가 벽체의 전면에 접하도록 설치물의 외측을 감싸는 내화 충전패드; 상기 내화 충전패드와 벽체와의 사이를 기밀하는 제2기밀부재; 및 설치물의 외측에 위치되도록 관통구로 삽입되는 내화폼을 포함하며,
상기 내화폼은 링 형태를 이루는 상태로부터 설치물을 중심으로 한 쌍의 폼유닛으로 분기되면서 설치물의 외측으로 결합되되, 전단부에 외측으로 돌출되면서 상기 내화 충전패드보다 외측으로 돌출되는 플랜지가 형성되고,
상기 플랜지를 벽체로 가압하는 가압수단을 더 포함하며,
상기 가압수단은 설치물의 양측에 배치되면서 상기 플랜지와 접하는 한 쌍의 가압판; 설치물의 외측으로 고정되는 클램프; 상기 클램프의 양측에 고정되며 전,후면을 관통하는 통공이 형성되는 한 쌍의 고정판; 후단부가 상기 가압판에 고정되고 전단부가 상기 통공을 통과하는 가압바; 및 상기 가압판과 상기 고정판의 사이에 위치되도록 상기 가압바의 외측으로 결합되어 상기 가압판을 상기 플랜지로 가압하는 탄성부재를 포함하는 것을 특징으로 하는 벽체의 관통구 방화구조.
In a fire protection structure that airtightens between an installation passing through a penetration hole formed in a wall and the penetration hole,
A first airtight member made of fireproof sealant and airtight between the installation and the penetration hole at the front of the wall; A fireproof charging pad made of fireproof sealant and surrounding the outside of the installation so that the rear end is in contact with the front of the wall; a second airtight member that airtightens between the fireproof charging pad and the wall; And it includes fireproof foam inserted into the through hole to be located on the outside of the installation,
The fire-resistant foam is divided into a pair of foam units around the installation from a ring-shaped state and joined to the outside of the installation, and a flange is formed at the front end that protrudes outward and protrudes outward from the fire-resistant charging pad,
It further includes pressurizing means for pressurizing the flange to the wall,
The pressing means includes a pair of pressing plates disposed on both sides of the installation and in contact with the flange; A clamp fixed to the outside of the installation; A pair of fixing plates fixed to both sides of the clamp and having through holes penetrating the front and rear surfaces; a pressure bar whose rear end is fixed to the pressure plate and whose front end passes through the hole; And an elastic member coupled to the outside of the pressure bar to be positioned between the pressure plate and the fixing plate to press the pressure plate to the flange.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 제 1항의 벽체의 관통구 방화구조의 시공방법으로서,
벽체의 전면에서 설치물과 관통구의 사이를 제1기밀부재로 기밀하는 1차 기밀단계;
후단부가 벽체의 전면에 접하도록 내화 충전패드를 설치물의 외측으로 감싸는 내화 충전패드 설치단계;
상기 내화 충전패드의 후단부와 벽체와의 사이를 제2기밀부재로 기밀하는 2차 기밀단계; 및
1차 기밀단계 전에 설치물의 외측에 위치되도록 관통구로 내화폼을 삽입하는 내화폼 삽입단계;를 포함하며,
상기 내화폼 삽입단계는
내,외주면이 관통구와 설치물의 형태에 맞게 상기 내화폼을 링 형태로 준비하는 내화폼 준비단계;
상기 내화폼을 설치물을 중심으로 상기 한 쌍의 폼유닛으로 분기하는 내화폼 분기단계; 및
상기 내화폼을 관통구로 삽입하는 내화폼 삽입단계를 포함하고,
상기 1차 기밀단계에서는 상기 제1기밀부재가 상기 내화폼과 벽체 간 및 상기 내화폼과 설치물 간으로 도포되고,
상기 2차 기밀단계에서는 상기 제2기밀부재가 상기 내화 충전패드와 상기 내화폼 간으로 도포되며,
상기 2차 기밀단계 후에 상기 가압수단을 설치물에 설치하여 상기 플랜지를 벽체로 가압하는 플랜지 가압단계를 더 포함하는 것을 특징으로 하는 벽체의 관통구 방화구조의 시공방법.
As a construction method for the through-hole fire protection structure of the wall of paragraph 1,
A first airtight step of airtightening between the installation and the penetration hole at the front of the wall with a first airtight member;
A fire-resistant charging pad installation step of wrapping the fire-resistant charging pad around the outside of the installation so that the rear end is in contact with the front of the wall;
A second airtight step of airtightening the space between the rear end of the fireproof charging pad and the wall with a second airtight member; and
It includes a fireproof foam insertion step of inserting the fireproof foam into the through hole so that it is located on the outside of the installation before the first airtightness step,
The fireproof foam insertion step is
A fireproof foam preparation step in which the fireproof foam is prepared in a ring shape so that the inner and outer peripheral surfaces match the shape of the through hole and the installation;
A fireproof foam branching step of branching the fireproof foam into the pair of foam units centered on the installation; and
It includes a fireproof foam insertion step of inserting the fireproof foam into the through hole,
In the first airtightness step, the first airtight member is applied between the fireproof foam and the wall and between the fireproof foam and the installation,
In the second hermetic step, the second hermetic member is applied between the refractory filling pad and the refractory foam,
A method of constructing a through-hole fire protection structure of a wall, characterized in that it further comprises a flange pressurizing step of installing the pressurizing means on an installation after the second airtightening step to press the flange to the wall.
KR1020230143576A 2023-10-25 2023-10-25 Through hole fire prevention structure of wall and construction method KR102638502B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230143576A KR102638502B1 (en) 2023-10-25 2023-10-25 Through hole fire prevention structure of wall and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020230143576A KR102638502B1 (en) 2023-10-25 2023-10-25 Through hole fire prevention structure of wall and construction method

Publications (1)

Publication Number Publication Date
KR102638502B1 true KR102638502B1 (en) 2024-02-19

Family

ID=90055581

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020230143576A KR102638502B1 (en) 2023-10-25 2023-10-25 Through hole fire prevention structure of wall and construction method

Country Status (1)

Country Link
KR (1) KR102638502B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130039469A (en) * 2011-10-12 2013-04-22 (주)세이프코리아 A fireproof filling element which is applied in pipe penetration department of the building and construction method thereof
KR20180137899A (en) 2017-06-20 2018-12-28 박미순 a firestop system for penetration hole
KR20220032844A (en) * 2020-09-08 2022-03-15 최혁수 Fireproof foam unit and fireproof foam device having the same
KR20220078375A (en) * 2020-12-03 2022-06-10 사이언스세이프티 주식회사 One-touch fire protection cap for fireproof finishing of pipe penetration portion of wall
JP7320577B2 (en) * 2018-02-21 2023-08-03 未来工業株式会社 Refractories and closures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130039469A (en) * 2011-10-12 2013-04-22 (주)세이프코리아 A fireproof filling element which is applied in pipe penetration department of the building and construction method thereof
KR20180137899A (en) 2017-06-20 2018-12-28 박미순 a firestop system for penetration hole
JP7320577B2 (en) * 2018-02-21 2023-08-03 未来工業株式会社 Refractories and closures
KR20220032844A (en) * 2020-09-08 2022-03-15 최혁수 Fireproof foam unit and fireproof foam device having the same
KR20220078375A (en) * 2020-12-03 2022-06-10 사이언스세이프티 주식회사 One-touch fire protection cap for fireproof finishing of pipe penetration portion of wall

Similar Documents

Publication Publication Date Title
US9046194B2 (en) Protective conduit for a structural panel opening
CA1154004A (en) Fire barrier device
AU2012200767A1 (en) Line element lead-through
KR200474131Y1 (en) Assembling panel for fireproof wall
KR102638502B1 (en) Through hole fire prevention structure of wall and construction method
JP2004503697A (en) Connection elements for mechanical connection of components
JP2006254571A (en) Electric connection box and its box cover
KR102638503B1 (en) Through hole fire prevention structure of slab and construction method
KR101930909B1 (en) The damper with a foamable noncombustible material
US20180298605A1 (en) Fire barrier box for membrane penetrations
JP2010139056A (en) Disaster prevention piping method and fire resistant cover
US7348484B1 (en) Method of assisting a compromised barrier
JP5209253B2 (en) Fire spread prevention structure in hollow walls
CN212518215U (en) A fire resistive construction for cable shaft
KR101649544B1 (en) Hot water heating prefabricated panel structure
WO2008093056A1 (en) Fire resistant back box
KR102673365B1 (en) Fireproofing of pipe through hole in wall with improved construction efficiency
JP7304751B2 (en) Fireproof cladding structure for walls composed of thermal insulation panels
KR101802373B1 (en) Fireproof sleeve and its construction method
JP3644696B2 (en) Filler support for through holes
US20200101331A1 (en) Fire-protection collar
JP6916349B1 (en) Fireproof material, fireproof structure
KR200183493Y1 (en) Interior door
RU2785315C1 (en) Insulation and vapor resistance of the pipe assembly
RU2761812C1 (en) Flexible attachable fire-resistant cable penetration for thin-walled barriers

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant