KR102614028B1 - Installed pipe structure installed in transfer layer of building and construction method thereof - Google Patents

Installed pipe structure installed in transfer layer of building and construction method thereof Download PDF

Info

Publication number
KR102614028B1
KR102614028B1 KR1020210047403A KR20210047403A KR102614028B1 KR 102614028 B1 KR102614028 B1 KR 102614028B1 KR 1020210047403 A KR1020210047403 A KR 1020210047403A KR 20210047403 A KR20210047403 A KR 20210047403A KR 102614028 B1 KR102614028 B1 KR 102614028B1
Authority
KR
South Korea
Prior art keywords
transition
pipe
facility
constructed
floor
Prior art date
Application number
KR1020210047403A
Other languages
Korean (ko)
Other versions
KR20220141175A (en
Inventor
손영훈
김준호
윤종원
지상현
나상철
Original Assignee
손영훈
김준호
윤종원
지상현
나상철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 손영훈, 김준호, 윤종원, 지상현, 나상철 filed Critical 손영훈
Priority to KR1020210047403A priority Critical patent/KR102614028B1/en
Publication of KR20220141175A publication Critical patent/KR20220141175A/en
Application granted granted Critical
Publication of KR102614028B1 publication Critical patent/KR102614028B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0023Building characterised by incorporated canalisations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L43/00Bends; Siphons

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Domestic Plumbing Installations (AREA)

Abstract

본 발명은 건축물의 전이층에 시공되는 설비 배관 구조 및 그 시공방법에 관한 것으로서, 보다 상세하게는, 건축물 전이층의 상층부 벽체의 외측면에 설치된 파이프 덕트 내에 수용되는 상태로 전이층의 전이슬래브를 상하로 관통하여 시공되는 설비 배관으로서, 전이슬래브를 관통하는 설비 배관이 전이층의 하층부 전이보에 비간섭 되도록 설비 배관에는 일정 각도로 구부러진 벤딩부가 형성되며, 벤딩부는 전이층의 상층부에서 형성되는 것을 특징으로 하는 건축물의 전이층에 시공되는 설비 배관 구조에 관한 것이다.
본 발명에 따르면, 건축물의 전이층을 시공하는데 있어서, 전이슬래브와 전이보를 기존과 동일한 시공방법으로 시공하되, 전이층에 시공되는 설비 배관이 전이슬래브의 상측에서 일정 각도로 구부러져 시공되기 때문에 전이슬래브를 관통하는 설비 배관이 전이보에 비간섭될 수 있다.
The present invention relates to a facility piping structure and construction method constructed on the transition floor of a building. More specifically, the present invention relates to a transition slab of a transition floor in a state accommodated in a pipe duct installed on the outer surface of the upper wall of the transition floor of a building. As a facility pipe that penetrates upward and downward, a bending portion bent at a certain angle is formed in the facility pipe so that the facility pipe penetrating the transition slab does not interfere with the transition beam in the lower layer of the transition layer, and the bending portion is formed in the upper layer of the transition layer. It relates to the facility piping structure constructed on the transition floor of a building with special features.
According to the present invention, when constructing the transition floor of a building, the transition slab and transition beam are constructed using the same construction method as the existing one, but since the facility pipe constructed on the transition layer is constructed by bending at a certain angle on the upper side of the transition slab, the transition slab is constructed. Equipment piping passing through may not interfere with the transition beam.

Description

건축물의 전이층에 시공되는 설비 배관 구조 및 그 시공방법{Installed pipe structure installed in transfer layer of building and construction method thereof}Equipment pipe structure installed in the transfer layer of a building and its construction method {Installed pipe structure installed in transfer layer of building and construction method thereof}

본 발명은 건축물의 전이층에 시공되는 설비 배관 구조에 관한 것으로, 특히 전이슬래브를 상하로 관통하는 설비 배관이 전이보에 비간섭 되도록 설비 배관을 일정 각도로 벤딩하여 시공할 수 있는 건축물의 전이층에 시공되는 설비 배관 구조 및 그 시공방법에 관한 것이다.The present invention relates to a facility piping structure constructed in the transition layer of a building. In particular, the transition layer of a building can be constructed by bending the facility piping at a certain angle so that the facility piping passing up and down through the transition slab does not interfere with the transition beam. It relates to the facility piping structure and construction method to be constructed.

일반적으로 건축물의 용도에 따라 또는 입면의 변화를 주는 목적에서도 상부와 하부의 기둥배치가 다를 수 있는데, 이러한 경우 구조적 안정성을 위해 상부층의 축력과 수평하중을 안전하게 하부에 전달시키는 전이(Transfer)층 시스템을 채택하게 된다.In general, the arrangement of columns at the top and bottom may be different depending on the purpose of the building or for the purpose of changing the elevation. In this case, a transfer layer system is used to safely transfer the axial force and horizontal load of the upper floor to the lower floor for structural stability. will be adopted.

즉, 주상복합 건물이나 지하주차장이 설계된 아파트에서 하부의 저층부는 기둥식 라멘조 구조의 사무실, 상가, 주민편의시설 또는 주차장으로 형성되고, 상부의 고층부는 벽식 구조의 아파트(주동)로 형성된다.That is, in a residential-commercial building or an apartment designed with an underground parking lot, the lower lower floor is formed as an office, shopping mall, resident convenience facility or parking lot with a column-shaped ramen structure, and the upper upper floor is formed as an apartment (main building) with a wall structure.

이때, 고층부의 아파트 벽체와 저층부의 기둥 주열이 대부분 맞지 않아 상부의 하중을 하부로 안정적으로 전달하기 위해 아파트가 시작되는 저층부의 상부 바닥에서 전이층을 형성하게 된다.At this time, most of the walls of the high-rise apartment and the column columns of the low-rise do not match, so a transition layer is formed at the upper floor of the low-rise where the apartment begins in order to stably transfer the load from the upper to the lower.

통상 전이층은 현장에서 철근을 배근하고, 합판이나 각목 등을 이용하여 배근된 철근을 둘러싸 거푸집을 형성한 후, 하부에 시스템 서포트 또는 동바리를 설치한 다음, 거푸집 내부에 콘크리트를 타설하는 것으로 시공된다.Typically, the transition layer is constructed by arranging reinforcing bars on site, forming a form surrounding the placed reinforcing bars using plywood or square lumber, installing system supports or braces at the bottom, and then pouring concrete inside the form. .

한편, 파이프 덕트(pipe duct)는, 기계설비에서 각종의 배관들이 입상관(수직으로 최상층까지 올라가는 주관)을 위한 공간이 형성되는 구조물로써, 파이프 덕트의 내부에는 급수배관, 배수배관, 오수배관 및 소화용배관 등이 수용된다.On the other hand, a pipe duct is a structure in which a space is formed for various pipes in mechanical equipment (main pipes that rise vertically to the top floor). The inside of the pipe duct contains water supply pipes, drainage pipes, sewage pipes, and Firefighting pipes, etc. are accommodated.

도 1 및 도 2는 종래의 건축물의 전이층에 시공된 설비 배관의 시공 상태를 나타낸 단면도이다.Figures 1 and 2 are cross-sectional views showing the construction state of facility piping constructed on the transition floor of a conventional building.

도 1을 참조하면, 종래에는 건축물의 전이층에 설비 배관을 시공함에 있어, 전이층(10)에서 벽식 구조인 상층부(10a)에 타설 시공된 벽체(11)의 외측면에 설치되는 파이프 덕트(pipe duct)(P.D)의 내측에 수용되는 설비 배관(100)이 전이층(10)의 전이슬래브(12)를 상하로 관통하여 전이층(10)에서 라멘조 구조인 하층부(10b)로 내려올 때, 하층부(10b)에 타설 시공된 전이보(13)에 설비 배관(100)이 간섭되는 문제가 있었다.Referring to FIG. 1, conventionally, when constructing facility piping on the transition floor of a building, a pipe duct ( When the equipment pipe 100 accommodated inside the pipe duct (P.D) penetrates the transition slab 12 of the transition layer 10 up and down and descends from the transition layer 10 to the lower layer 10b, which has a ramen structure, There was a problem with the facility pipe 100 interfering with the transition beam 13 poured in the lower layer 10b.

이처럼 하층부(10b)의 전이보(13)에 설비 배관(100)이 가로 막히기 때문에 이를 해소하기 위해서는 전이보(13)를 설비 배관(100)이 관통하거나 전이보(13)의 단면 폭(L)을 줄여 전이보(13)를 타설 시공해야 한다.In this way, since the equipment pipe 100 is blocked by the transition beam 13 of the lower layer 10b, in order to solve this, the equipment pipe 100 penetrates the transition beam 13 or the cross-sectional width (L) of the transition beam 13 is changed. It is necessary to reduce the transition beam (13) by pouring construction.

하지만, 설비 배관(100)이 전이보(13)를 관통하거나 전이보(13)의 단면 폭(L)을 줄여 전이보(13)를 타설 시공하는 것은 시공상 매우 어려운 문제가 있다.However, it is very difficult in construction to construct the transition beam 13 by allowing the facility pipe 100 to penetrate the transition beam 13 or reducing the cross-sectional width (L) of the transition beam 13.

이에 상술한 문제를 해소하기 위해 최근에는 도 2에서와 같이, 전이층(10)의 진이슬래브(12)를 관통하여 시공되는 설비 배관(100)이 전이보(13)를 관통하거나 전이보(13)에 간섭되지 않도록 전이슬래브(12)와 전이보(13) 사이가 약 200mm 내지 약 300mm 의 간격을 형성하도록 하여 타설 시공하는 방법이 제안되고 있다.Accordingly, in order to solve the above-mentioned problem, recently, as shown in FIG. 2, the facility pipe 100 constructed through the transition slab 12 of the transition layer 10 penetrates the transition beam 13 or the transition beam 13. ) A method of pouring construction by forming a gap of about 200 mm to about 300 mm between the transition slab (12) and the transition beam (13) has been proposed.

하지만, 기존의 전이슬래브(12)와 일체형으로 전이보(13)를 타설 시공하는 방법에 비해 층고가 약 400mm 내지 약 500mm 높아짐으로써, 건축물의 높이에 영향을 끼치게 되는 문제가 발생한다.However, compared to the method of pouring and constructing the transition beam 13 integrally with the existing transition slab 12, the floor height increases by about 400 mm to about 500 mm, causing a problem that affects the height of the building.

즉, 이렇게 기존 시공방법 보다 층고가 높아지게 되면, 해당층의 계단 계획시 계단 시공이 어려워지는 문제가 발생할 뿐만 아니라, 전이슬래브(12)와 전이보(13)가 서로 분리되기 때문에 실제 시공 반영이 어려운 문제가 있다.In other words, if the floor height becomes higher than the existing construction method, not only does a problem arise in which stair construction becomes difficult when planning the stairs for the corresponding floor, but also it is difficult to reflect actual construction because the transition slab (12) and transition beam (13) are separated from each other. there is a problem.

한국 등록실용신안공보 제20-0139081호(1999년 04월 01일 공고)Korean Registered Utility Model Publication No. 20-0139081 (announced on April 1, 1999)

상술한 문제점을 해결하기 위해 안출된 본 발명의 과제는, 건축물의 전이층을 시공하는데 있어서, 전이슬래브와 전이보를 기존과 동일한 시공방법으로 시공하되, 전이층에 시공되는 설비 배관이 전이슬래브의 상측에서 일정 각도로 구부러져 시공되기 때문에 전이슬래브를 관통하는 설비 배관이 전이보에 비간섭될 수 있는 건축물의 전이층에 시공되는 설비 배관 구조 및 그 시공방법을 제공하는 데 있다.The problem of the present invention, which was devised to solve the above-mentioned problems, is to construct the transition floor of a building, where the transition slab and transition beam are constructed using the same construction method as the existing one, but the facility pipe constructed on the transition floor is installed on the upper side of the transition slab. The purpose is to provide a facility piping structure and construction method for construction on the transition floor of a building where the facility piping penetrating the transition slab may not interfere with the transition beam because it is constructed by bending at a certain angle.

또한, 본 발명의 과제는, 건축물의 전이층에 시공되는 설비 배관이 전이슬래브의 상측에서 일정 각도로 구부러져 시공되기 때문에 전이슬래브의 상면에 시공되는 기존 바닥 마감재를 더 두껍게 증가시킬 필요가 없게 되어 기존의 시공방법에 비해 층고를 줄일 수 있는 건축물의 전이층에 시공되는 설비 배관 구조 및 그 시공방법을 제공하는 데 있다.In addition, the problem of the present invention is that since the facility pipes constructed on the transition floor of a building are bent at a certain angle on the upper side of the transition slab, there is no need to thicken the existing floor finishing material constructed on the upper surface of the transition slab, thereby eliminating the need to thicken the existing floor finishing material. The purpose is to provide a facility piping structure and construction method to be constructed on the transition floor of a building that can reduce the floor height compared to the construction method of .

상기 과제를 달성하기 위해 안출된 본 발명은, 건축물의 전이층에 시공되는 설비 배관 구조로서, 건축물 전이층의 상층부 벽체의 외측면에 설치된 파이프 덕트(pipe duct) 내에 수용되는 상태로 상기 전이층의 전이슬래브를 상하로 관통하여 시공되는 설비 배관으로서, 상기 전이슬래브를 관통하는 상기 설비 배관이 상기 전이층의 하층부 전이보에 비간섭 되도록 설비 배관에는 일정 각도로 구부러진 벤딩부가 형성되며, 상기 벤딩부는 전이층의 상층부에서 형성되는 것을 특징으로 한다.The present invention, which was developed to achieve the above problem, is a facility piping structure constructed on the transition floor of a building, and is accommodated in a pipe duct installed on the outer surface of the upper wall of the transition floor of the building. As a facility pipe constructed to penetrate the transition slab up and down, a bending portion bent at a certain angle is formed in the facility pipe so that the facility pipe penetrating the transition slab does not interfere with the transition beam of the lower layer of the transition layer, and the bending portion is formed in the transition section. It is characterized by being formed in the upper layer of the layer.

상기 설비 배관의 벤딩부는 상기 파이프 덕트의 내측에서 형성되는 것을 특징으로 한다.The bending portion of the facility pipe is characterized in that it is formed inside the pipe duct.

상기 설비 배관에는, 상기 벽체의 외측을 향해 일정 각도로 구부러진 제1 벤딩부와, 상기 제1 벤딩부의 후단에 형성되며 상기 전이슬래브를 설비 배관이 관통되도록 전이슬래브를 향해 일정 각도로 구부러진 제2 벤딩부를 포함하는 것을 특징으로 한다.The facility pipe includes a first bending portion bent at a predetermined angle toward the outside of the wall, and a second bend formed at a rear end of the first bending portion and bent at a predetermined angle toward the transition slab so that the facility pipe penetrates the transition slab. It is characterized by including wealth.

상기 전이슬래브의 상면에는 바닥 마감재가 더 시공되며, 상기 제2 벤딩부는 상기 바닥 마감재와 전이슬래브 사이에서 형성되는 것을 특징으로 한다.A floor finishing material is further constructed on the upper surface of the transition slab, and the second bending portion is formed between the floor finishing material and the transition slab.

상기 벤딩부는, 각 단위 배관을 서로 연결하는 배관용 엘보인 것을 특징으로 한다.The bending part is characterized as a piping elbow that connects each unit pipe to each other.

또한, 본 발명은, 건축물의 전이층에 시공되는 설비 배관의 시공방법으로서, 상기 전이층의 전이슬래브를 관통하는 상기 설비 배관이 전이층의 하층부 전이보에 비간섭 되도록 전이슬래브의 상측에서 일정 각도로 구부러진 형태로 벤딩되어 시공되는 것을 특징으로 한다.In addition, the present invention is a method of constructing equipment piping constructed on the transition floor of a building, wherein the equipment piping penetrating the transition slab of the transition layer is installed at a certain angle on the upper side of the transition slab so that it does not interfere with the transition beam of the lower part of the transition layer. It is characterized by being bent and constructed in a curved shape.

본 발명은 건축물의 전이층을 시공하는데 있어서, 전이슬래브와 전이보를 기존과 동일한 시공방법으로 시공하되, 전이층에 시공되는 설비 배관이 전이슬래브의 상측에서 일정 각도로 구부러져 시공되기 때문에 전이슬래브를 관통하는 설비 배관이 전이보에 비간섭되는 효과가 있다.In the present invention, in constructing the transition floor of a building, the transition slab and transition beam are constructed using the same construction method as the existing one, but the facility pipe constructed on the transition layer is constructed by bending at a certain angle on the upper side of the transition slab, so it does not penetrate the transition slab. There is an effect that the equipment piping does not interfere with the transition beam.

또한, 본 발명은, 건축물의 전이층에 시공되는 설비 배관이 전이슬래브의 상측에서 일정 각도로 구부러져 시공되기 때문에 전이슬래브의 상면에 시공되는 기존 바닥 마감재를 더 두껍게 증가시킬 필요가 없게 되어 기존의 시공방법에 비해 층고를 줄일 수 있는 효과가 있다.In addition, in the present invention, since the facility pipes constructed on the transition floor of a building are constructed by bending at a certain angle on the upper side of the transition slab, there is no need to increase the thickness of the existing floor finishing material constructed on the upper surface of the transition slab, thereby eliminating the need for existing construction. Compared to other methods, it has the effect of reducing floor height.

도 1 및 도 2는 종래의 건축물의 전이층에 시공된 설비 배관의 시공 상태를 나타낸 단면도,
도 3은 본 발명의 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조를 나타낸 단면도,
도 4는 본 발명의 다른 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조를 나타낸 단면도,
도 5는 본 발명의 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조에서 벤딩부의 일실시예를 나타낸 확대도이다.
Figures 1 and 2 are cross-sectional views showing the construction state of equipment piping constructed on the transition floor of a conventional building;
Figure 3 is a cross-sectional view showing the facility piping structure constructed on the transition floor of a building according to an embodiment of the present invention;
Figure 4 is a cross-sectional view showing the facility piping structure constructed on the transition floor of a building according to another embodiment of the present invention;
Figure 5 is an enlarged view showing an example of a bending portion in a facility piping structure constructed on the transition floor of a building according to an embodiment of the present invention.

이하, 첨부한 도면을 참조하여 본 발명에 따른 건축물의 전이층에 시공되는 설비 배관 구조의 바람직한 실시예에 대해 상세하게 설명한다.Hereinafter, a preferred embodiment of the facility piping structure constructed on the transition floor of a building according to the present invention will be described in detail with reference to the attached drawings.

도 3은 본 발명의 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조를 나타낸 단면도이다.Figure 3 is a cross-sectional view showing the facility piping structure constructed on the transition floor of a building according to an embodiment of the present invention.

도 3을 참조하면, 본 발명의 바람직한 실시예에 따른 건축물의 전이층에 시공되는 설비 배관 구조는, 건축물의 전이층(10)에서 벽식 구조인 상층부(10a)에 타설 시공된 벽체(11)의 외측면에 설치되는 파이프 덕트(pipe duct)(P.D)의 내측에 수용되면서 전이층(10)의 전이슬래브(12)를 상하로 관통하여 시공되는 설비 배관(100)의 구조 및 이의 시공방법에 관한 발명이다.Referring to FIG. 3, the facility piping structure constructed on the transition floor of a building according to a preferred embodiment of the present invention is the structure of the wall 11 poured into the upper part 10a, which is a wall-type structure, on the transition floor 10 of the building. Regarding the structure and construction method of the facility pipe 100, which is accommodated inside the pipe duct (P.D) installed on the outer surface and constructed vertically through the transition slab 12 of the transition layer 10 It's an invention.

여기서, 설비 배관(100)이 전이층(10)의 전이슬래브(12)를 관통하여 시공될 때, 건축물의 전이층(10)에서 라멘조 구조인 하층부(10b)에 타설 시공된 전이보(13)에 설비 배관(100)이 간섭되는 문제가 있기 때문에 전이보(13)에 설비 배관(100)이 비간섭 되도록 설비 배관(100)에는 일정 각도(θ)로 구부러진 벤딩부(110)가 형성되는데, 이러한 벤딩부(110)는 전이슬래브(12)의 상측, 즉 전이층(10)의 상층부(10a)에서 형성된다.Here, when the facility pipe 100 is constructed by penetrating the transition slab 12 of the transition layer 10, the transition beam 13 poured into the lower layer 10b, which has a ramen structure, in the transition layer 10 of the building. Since there is a problem of interference with the equipment pipe 100, a bending portion 110 bent at a certain angle (θ) is formed in the equipment pipe 100 so that the equipment pipe 100 does not interfere with the transition beam 13. This bending portion 110 is formed on the upper side of the transition slab 12, that is, in the upper layer 10a of the transition layer 10.

그리고, 벤딩부(110)의 벤딩 각도(θ)는 약 30° 내지 약 45°로 이루어지는 것이 바람직하다. 벤딩 각도(θ)가 약 30°미만이며, 설비 배관(100)이 충분히 구부러지지 않은 상태로 전이슬래브(12)를 관통하게 되어 전이보(13)에 설비 배관(100)이 간섭되는 문제가 발생할 수 있다.And, the bending angle (θ) of the bending portion 110 is preferably set to about 30° to about 45°. When the bending angle (θ) is less than about 30°, the facility pipe 100 penetrates the transition slab 12 without being sufficiently bent, causing a problem of the facility pipe 100 interfering with the transition beam 13. You can.

또한, 벤딩 각도(θ)가 약 45°를 초과하게 되면, 설비 배관(100)이 지나치게 구부러지기 때문에 설비 배관(100)이 급배수용 배관인 경우, 배관 내부로 유동되는 유체의 흐름이 저하되는 문제가 발생할 수 있다.In addition, when the bending angle (θ) exceeds about 45°, the facility pipe 100 is excessively bent, so if the facility pipe 100 is a water supply/drain pipe, the flow of fluid flowing inside the pipe is reduced. may occur.

이때, 설비 배관(100)에 형성되는 벤딩부(110)는, 설비 배관(100)이 전이슬래브(12)를 관통하기 전인 파이프 덕트(P.D)의 내측에서 형성되는 것이 바람직하다.At this time, the bending portion 110 formed in the facility pipe 100 is preferably formed inside the pipe duct (P.D.) before the facility pipe 100 penetrates the transition slab 12.

한편, 설비 배관(100)에는, 벽체(11)의 외측을 향해 일정 각도(θ)로 구부러진 제1 벤딩부(110a)와, 제1 벤딩부(110a)의 후단에 형성되며 전이슬래브(12)를 설비 배관(100)이 관통되도록 전이슬래브(12)를 향해 일정 각도(θ)로 구부러진 제2 벤딩부(110b)를 포함하여 구성될 수 있다.Meanwhile, the facility pipe 100 includes a first bending portion 110a bent at a certain angle θ toward the outside of the wall 11, and a transition slab 12 formed at the rear end of the first bending portion 110a. It may be configured to include a second bending portion 110b bent at a certain angle θ toward the transition slab 12 so that the facility pipe 100 penetrates.

여기서, 설비 배관(100)에 형성되는 제1 벤딩부(110a)와 제2 벤딩부(110b)는, 설비 배관(100)이 전이슬래브(12)를 관통하기 전인 파이프 덕트(P.D)의 내측에서 형성되는 것이 바람직하다.Here, the first bending portion 110a and the second bending portion 110b formed in the facility pipe 100 are formed on the inside of the pipe duct (P.D.) before the facility pipe 100 penetrates the transition slab 12. It is desirable to form

부연하면, 전이보(13)의 단면 폭(L1)이 좁아 전이보(13)와 파이프 덕트(P.D) 간의 사이 간격이 충분히 확보되는 경우, 파이프 덕트(P.D)의 내측에서 제1 벤딩부(110a)와 제2 벤딩부(110b)가 형성되면서 전이슬래브(12)에 설비 배관(100)이 상하로 관통할 수 있게 되고, 전이슬래브(12)의 상면에 시공되는 바닥 마감재(12a)의 높이(두께)를 변화시킬 필요가 없게 되는 효과가 있다.To elaborate, when the cross-sectional width L1 of the transition beam 13 is narrow and the gap between the transition beam 13 and the pipe duct P.D is sufficiently secured, the first bending portion 110a is formed on the inside of the pipe duct P.D. ) and the second bending portion 110b are formed, allowing the equipment pipe 100 to penetrate up and down the transition slab 12, and the height of the floor finishing material 12a installed on the upper surface of the transition slab 12 ( This has the effect of eliminating the need to change the thickness.

도 4는 본 발명의 다른 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조를 나타낸 단면도이다.Figure 4 is a cross-sectional view showing the facility piping structure constructed on the transition floor of a building according to another embodiment of the present invention.

도 4를 참조하면, 파이프 덕트(P.D)의 단면 폭(L2)에 비해 전이보의 단면 폭(L1)이 넓어 전이보(13)와 파이프 덕트(P.D) 간의 사이 간격이 확보되지 않는 경우에는 파이프 덕트(P.D)의 외측인 전이슬래브(12)의 상면에 시공되는 바닥 마감재(12a)를 기 시공된 바닥 마감재(12a)의 두께 보다 약 100mm 더 두껍게 시공하는 것이 바람직하다.Referring to FIG. 4, when the cross-sectional width (L1) of the transition beam is wider than the cross-sectional width (L2) of the pipe duct (P.D.) and the gap between the transition beam (13) and the pipe duct (P.D.) is not secured, the pipe It is desirable to construct the floor finishing material 12a on the upper surface of the transition slab 12 outside the duct (P.D.) to be about 100 mm thicker than the thickness of the previously installed floor finishing material 12a.

이때, 설비 배관(100)에 형성되는 제2 벤딩부(110b)는 바닥 마감재(12a)와 전이슬래브(12) 사이에서 형성되게 된다.At this time, the second bending portion 110b formed in the facility pipe 100 is formed between the floor finishing material 12a and the transition slab 12.

부연하면, 설비 배관(100)의 제1 벤딩부(110a)가 파이프 덕트(P.D)의 내측에서 형성되고, 그 다음 설비 배관(100)이 파이프 덕트(P.D)의 외측으로 노출된 상태에서 바닥 마감재(12a)와 전이슬래브(12) 사이에서 제2 벤딩부(110b)가 형성되는 것이다.To elaborate, the first bending portion 110a of the facility pipe 100 is formed on the inside of the pipe duct (P.D), and then the facility pipe 100 is exposed to the outside of the pipe duct (P.D) and is applied to the floor finishing material. A second bending portion 110b is formed between (12a) and the transition slab 12.

이때, 두꺼운 바닥 마감재(12a)가 설비 배관(100)을 덮어 마감되기 때문에 전이층(10)의 상층부에서 설비 배관(100)이 노출되지 않게 되고, 기존의 시공방법에 비해 최소 약 300mm 이상 층고를 줄일 수 있는 효과를 얻을 수 있다.At this time, since the thick floor finishing material 12a covers the facility pipe 100, the facility pipe 100 is not exposed in the upper part of the transition layer 10, and the floor height is increased by at least about 300 mm compared to the existing construction method. You can achieve a reduction effect.

도 5는 본 발명의 실시예에 따른 건축물의 전이층에 시공된 설비 배관 구조에서 벤딩부의 일실시예를 나타낸 확대도이다.Figure 5 is an enlarged view showing an example of a bending portion in a facility piping structure constructed on the transition floor of a building according to an embodiment of the present invention.

도 5를 참조하면, 벤딩부(110)는, 각 단위 배관(100a, 100b, 100c)을 서로 연결하는 배관용 엘보(111)일 수 있다.Referring to FIG. 5, the bending portion 110 may be a piping elbow 111 that connects unit pipes 100a, 100b, and 100c to each other.

부연하면, 설비 배관(100)을 구성하는 단위 배관(100a, 100b, 100c)들은, 파이프 덕트(P.D) 내측에 수용되는 제1 배관(100a)과, 전이슬래브(12)를 관통하는 제2 배관(100b)과, 제1 배관(100a)과 제2 배관(100b) 사이를 연결하는 연결배관(100c)을 포함하여 구성될 수 있다.To elaborate, the unit pipes 100a, 100b, and 100c constituting the facility pipe 100 include a first pipe 100a accommodated inside the pipe duct P.D., and a second pipe penetrating the transition slab 12. It may be configured to include (100b) and a connection pipe (100c) connecting the first pipe (100a) and the second pipe (100b).

여기서, 제1 배관(100a)의 일측 단부와 연결배관(100c)의 일측 단부를 서로 연결하기 위해 약 30° 내지 약 45°의 각도로 벤딩 가공된 하나의 배관용 엘보(111)가 관이음될 수 있고, 제2 배관(100b)의 일측 단부와 연결배관(100c)의 타측 단부를 서로 연결하기 위해 약 30° 내지 약 45°의 각도로 벤딩 가공된 다른 하나의 배관용 엘보(111)가 관이음될 수 있다.Here, in order to connect one end of the first pipe (100a) and one end of the connecting pipe (100c), one pipe elbow 111 bent at an angle of about 30° to about 45° is used to connect the pipe. In order to connect one end of the second pipe 100b and the other end of the connection pipe 100c, another pipe elbow 111 is bent at an angle of about 30° to about 45°. It can be joined.

이하, 본 발명에 따른 건축물의 전이층에 시공되는 설비 배관의 시공방법에 대해 설명하면, 건축물 전이층(10)의 상층부(10a) 벽체(11)의 외측면에 설치된 파이프 덕트(P.D) 내에 수용되는 상태로 전이층(10)의 전이슬래브(12)를 상하로 관통하여 시공되는 설비 배관(100)이 전이층(10)의 하층부 전이보(13)에 비간섭 되도록 전이슬래브(12)의 상측에서 설비 배관(100)이 일정 각도로 구부러진 형태로 벤딩되어 시공된다.Hereinafter, the construction method of the equipment piping constructed in the transition layer of the building according to the present invention will be described. The upper layer 10a of the building transition layer 10 is accommodated in the pipe duct (P.D.) installed on the outer surface of the wall 11. The upper side of the transition slab (12) so that the equipment pipe (100), which is constructed by penetrating the transition slab (12) of the transition layer (10) upward and downward, does not interfere with the transition beam (13) of the lower layer of the transition layer (10). The facility pipe 100 is constructed by bending it in a shape bent at a certain angle.

이상에서는 본 발명을 바람직한 실시예에 의거하여 설명하였으나, 본 발명의 기술적 사상은 이에 한정되지 아니하고 청구항에 기재된 범위 내에서 변형이나 변경 실시가 가능함은 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에게 명백한 것이며, 그러한 변형이나 변경은 첨부된 특허청구범위에 속한다 할 것이다.In the above, the present invention has been described based on preferred embodiments, but the technical idea of the present invention is not limited thereto, and modifications or modifications may be made within the scope set forth in the claims by those skilled in the art. It is clear to everyone that such modifications or changes fall within the scope of the appended patent claims.

10: 전이층 10a: 상층부
10b: 하층부 11: 벽체
12: 전이슬래브 12a: 바닥 마감재
13: 전이보 100: 설비 배관
100a, 100b, 100c: 단위 배관
110: 벤딩부 110a: 제1 벤딩부
110b: 제2 벤딩부 111: 배관용 엘보
P.D: 파이프 덕트
10: transition layer 10a: upper layer
10b: lower layer 11: wall
12: Transition slab 12a: Floor finishing material
13: Transition beam 100: Facility piping
100a, 100b, 100c: unit piping
110: bending part 110a: first bending part
110b: second bending portion 111: plumbing elbow
PD: pipe duct

Claims (6)

건축물 전이층의 상층부 벽체의 외측면에 설치된 파이프 덕트(pipe duct) 내에 수용되는 상태로 상기 전이층의 전이슬래브를 상하로 관통하여 시공되는 설비 배관으로서,
상기 전이슬래브를 관통하는 상기 설비 배관이 상기 전이층의 하층부 전이보에 비간섭 되도록 설비 배관에는 일정 각도로 구부러진 벤딩부가 형성되며, 상기 벤딩부는 전이층의 상층부에서 형성되고,
상기 설비 배관에는, 상기 벽체의 외측을 향해 일정 각도로 구부러진 제1 벤딩부와, 상기 제1 벤딩부의 후단에 형성되며 상기 전이슬래브를 설비 배관이 관통되도록 전이슬래브를 향해 일정 각도로 구부러진 제2 벤딩부를 포함하며, 상기 전이슬래브의 상면에는 바닥 마감재가 더 시공되며, 상기 제2 벤딩부는 상기 바닥 마감재와 전이슬래브 사이에서 형성되는 것을 특징으로 하는 건축물의 전이층에 시공되는 설비 배관 구조.
As a facility pipe constructed to penetrate vertically through the transition slab of the transition layer while being accommodated in a pipe duct installed on the outer surface of the upper wall of the transition layer of a building,
A bending portion bent at a certain angle is formed in the facility pipe so that the facility pipe passing through the transition slab does not interfere with the transition beam of the lower layer of the transition layer, and the bending portion is formed in the upper layer of the transition layer,
The facility pipe includes a first bending portion bent at a predetermined angle toward the outside of the wall, and a second bend formed at a rear end of the first bending portion and bent at a predetermined angle toward the transition slab so that the facility pipe penetrates the transition slab. A facility piping structure constructed in the transition layer of a building, wherein a floor finishing material is further constructed on the upper surface of the transition slab, and the second bending portion is formed between the floor finishing material and the transition slab.
제1항에 있어서,
상기 설비 배관의 벤딩부는 상기 파이프 덕트의 내측에서 형성되는 것을 특징으로 하는 건축물의 전이층에 시공되는 설비 배관 구조.
According to paragraph 1,
A facility piping structure constructed in the transition layer of a building, wherein the bending portion of the facility piping is formed inside the pipe duct.
삭제delete 삭제delete 제1항에 있어서,
상기 벤딩부는, 각 단위 배관을 서로 연결하는 배관용 엘보인 것을 특징으로 하는 건축물의 전이층에 시공되는 설비 배관 구조.
According to paragraph 1,
The bending part is a facility piping structure constructed on the transition floor of a building, characterized in that the bending part is a piping elbow that connects each unit pipe to each other.
제1항의 건축물의 전이층에 시공되는 설비 배관의 시공방법으로서,
상기 전이층의 전이슬래브를 관통하는 상기 설비 배관이 전이층의 하층부 전이보에 비간섭 되도록 전이슬래브의 상측에서 일정 각도로 구부러진 형태로 벤딩되어 시공되는 것을 특징으로 하는 건축물의 전이층에 시공되는 설비 배관의 시공방법.
As a construction method for equipment piping constructed on the transition floor of the building of paragraph 1,
Equipment constructed on the transition floor of a building, characterized in that the equipment pipe penetrating the transition slab of the transition floor is constructed by bending at a certain angle on the upper side of the transition slab so that it does not interfere with the transition beam of the lower layer of the transition floor. Piping construction method.
KR1020210047403A 2021-04-12 2021-04-12 Installed pipe structure installed in transfer layer of building and construction method thereof KR102614028B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210047403A KR102614028B1 (en) 2021-04-12 2021-04-12 Installed pipe structure installed in transfer layer of building and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210047403A KR102614028B1 (en) 2021-04-12 2021-04-12 Installed pipe structure installed in transfer layer of building and construction method thereof

Publications (2)

Publication Number Publication Date
KR20220141175A KR20220141175A (en) 2022-10-19
KR102614028B1 true KR102614028B1 (en) 2023-12-13

Family

ID=83804650

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210047403A KR102614028B1 (en) 2021-04-12 2021-04-12 Installed pipe structure installed in transfer layer of building and construction method thereof

Country Status (1)

Country Link
KR (1) KR102614028B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001012651A (en) * 1999-06-30 2001-01-16 Sumitomo Forestry Co Ltd Piping structure and piping method
KR100730239B1 (en) 2005-06-22 2007-06-25 현대산업개발 주식회사 Wall structure for airduct and pipeduct of bathroom and balcony
KR101011402B1 (en) 2009-02-16 2011-01-28 (주)대우건설 Multi-direction transfer girder system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0139081Y1 (en) 1996-06-12 1999-04-01 한상열 A device for supporting pipes
JP3943212B2 (en) * 1997-11-05 2007-07-11 永大産業株式会社 Side wall structure of building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001012651A (en) * 1999-06-30 2001-01-16 Sumitomo Forestry Co Ltd Piping structure and piping method
KR100730239B1 (en) 2005-06-22 2007-06-25 현대산업개발 주식회사 Wall structure for airduct and pipeduct of bathroom and balcony
KR101011402B1 (en) 2009-02-16 2011-01-28 (주)대우건설 Multi-direction transfer girder system

Also Published As

Publication number Publication date
KR20220141175A (en) 2022-10-19

Similar Documents

Publication Publication Date Title
SG187296A1 (en) A multi-storey building with prefabricated members and a semi-prefabricating construction method thereof
CN101215856B (en) Steel tube concrete column-plate hinged joint node
CN105178354B (en) One farming word beam column cap and flatslab construction system
KR101081970B1 (en) Construction method for On-floor drainage piping system of bathroom in multistory building
CN201144462Y (en) Steel pipe concrete column-floor hinged node
KR102614028B1 (en) Installed pipe structure installed in transfer layer of building and construction method thereof
KR100784191B1 (en) Composite floor structure using steel beam with web openings and the construction method
CN206539026U (en) A kind of one side formwork formwork system
KR101011402B1 (en) Multi-direction transfer girder system
KR20230122817A (en) Modular housing with foundation support structure
KR101616483B1 (en) Construction Method Of Underground Parking Lot Using Precast Concrete Beam With Changing Cross Section
AU2018101022B4 (en) Incorporation of pods in multi-storey constuctions
FI122569B (en) A method of raising a building
KR20170118349A (en) deck for wall form
KR20220055619A (en) Transfer girder system for reducing the height of underground parking lots using reverse beam
JP2016216910A (en) Building structure
CN105350784B (en) Utilize skirt location technology one-shot forming service sleeve installation method
JP2015190120A (en) Aseismatic repair method of building
JP4302616B2 (en) Construction method for multi-story buildings
CN215802022U (en) Same-floor drainage structure of toilet in building
CN220318862U (en) Assembled roofing superimposed sheet antiseep structure
CN217027529U (en) Assembled steel construction building column base waterproof construction
JP6662816B2 (en) Two-story building or more
KR102209700B1 (en) Precast type hollow concrete slab construction method for wall-type apartment and precast type hollow concrete slab using the same
US10202750B2 (en) Structure and method for installing bathroom plumbing

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant