KR102584444B1 - Installation method of bridge superstructure using temporary through truss - Google Patents

Installation method of bridge superstructure using temporary through truss Download PDF

Info

Publication number
KR102584444B1
KR102584444B1 KR1020230017508A KR20230017508A KR102584444B1 KR 102584444 B1 KR102584444 B1 KR 102584444B1 KR 1020230017508 A KR1020230017508 A KR 1020230017508A KR 20230017508 A KR20230017508 A KR 20230017508A KR 102584444 B1 KR102584444 B1 KR 102584444B1
Authority
KR
South Korea
Prior art keywords
truss
support frame
bridge
floor support
temporary
Prior art date
Application number
KR1020230017508A
Other languages
Korean (ko)
Inventor
김정현
신재우
박정천
Original Assignee
코벡 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 코벡 주식회사 filed Critical 코벡 주식회사
Priority to KR1020230017508A priority Critical patent/KR102584444B1/en
Application granted granted Critical
Publication of KR102584444B1 publication Critical patent/KR102584444B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D6/00Truss-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 교량 하부구조 외측에 설치된 가벤트 상부에 바닥지지틀과 한 쌍의 트러스 주구로 구성된 가설 하로 트러스를 거치한 후 바닥지지틀 상부에서 교량 상부구조를 시공할 수 있으므로, 신설되는 교량 하부의 교하공간을 그대로 운영하면서 형하공간을 최대한 확보하여 도로 종단 구배를 최소화할 수 있는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법에 대한 것이다.
본 발명은 교축 방향으로 서로 이격되도록 설치된 한 쌍의 교량 하부구조 상부에 상부구조를 설치하기 위한 것으로, (a) 상기 각 교량 하부구조의 일측에 가벤트를 설치하는 단계; (b) 바닥지지틀과 상현재, 하현재 및 상기 상현재와 하현재를 연결하는 사재로 구성되어 각각 하단이 상기 바닥지지틀의 양측에 결합되는 한 쌍의 트러스 주구로 구성되는 가설 하로 트러스를 상기 가벤트의 상부에 거치하는 단계; (c) 상기 가설 하로 트러스의 바닥지지틀 상부에서 교량 상부구조를 시공하는 단계; (d) 상기 트러스 주구를 바닥지지틀에서 해체하여 제거하는 단계; (e) 상기 바닥지지틀을 제거하는 단계; 및 (f) 상기 가벤트를 제거하는 단계; 로 구성되는 것을 특징으로 한다.
The present invention allows the construction of a bridge superstructure on the upper part of the floor support frame after mounting a temporary truss consisting of a floor support frame and a pair of truss main shafts on the upper part of the vent installed on the outside of the bridge substructure, so that the lower part of the newly constructed bridge can be installed. This is about a method of installing a bridge superstructure using a temporary lower truss that can minimize the longitudinal gradient of the road by maximizing the lower profile space while operating the bridge space as is.
The present invention is to install a superstructure on top of a pair of bridge substructures installed to be spaced apart from each other in the direction of the bridge, including the steps of (a) installing a vent on one side of each bridge substructure; (b) A temporary lower truss consisting of a floor support frame, an upper chord, a lower chord, and a pair of truss main members whose lower ends are connected to both sides of the floor support frame, and of a stay member connecting the upper chord and the lower chord. Mounting on top of the vent; (c) constructing a bridge superstructure on the upper part of the bottom support frame of the temporary truss; (d) dismantling and removing the truss main structure from the floor support frame; (e) removing the floor support frame; and (f) removing the vent; It is characterized by being composed of.

Description

가설 하로 트러스를 이용한 교량 상부구조 설치 방법{Installation method of bridge superstructure using temporary through truss}Installation method of bridge superstructure using temporary through truss}

본 발명은 교량 하부구조 외측에 설치된 가벤트 상부에 바닥지지틀과 한 쌍의 트러스 주구로 구성된 가설 하로 트러스를 거치한 후 바닥지지틀 상부에서 교량 상부구조를 시공할 수 있으므로, 신설되는 교량 하부의 교하공간을 그대로 운영하면서 형하공간을 최대한 확보하여 도로 종단 구배를 최소화할 수 있는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법에 대한 것이다.The present invention allows the construction of a bridge superstructure on the upper part of the floor support frame after mounting a temporary truss consisting of a floor support frame and a pair of truss main shafts on the upper part of the vent installed on the outside of the bridge substructure, so that the lower part of the newly constructed bridge can be installed. This is about a method of installing a bridge superstructure using a temporary lower truss that can minimize the longitudinal gradient of the road by maximizing the lower profile space while operating the bridge space as is.

도로나 인도가 철도선로와 평면상 서로 교차하여 철도선로를 횡단해야 하는 경우, 통행량이 적은 곳에는 주로 건널목이 설치된다. 그러나 통행량이 많은 곳에서는 건널목 설치 시 교통 정체 및 충돌 사고의 위험이 있어 지하차도나 과선교가 주로 설치된다.When a road or sidewalk intersects a railroad track in plan and must cross the railroad track, a railroad crossing is usually installed in a place with low traffic volume. However, in areas with high traffic, there is a risk of traffic congestion and collisions when installing a crossing, so underpasses or overpasses are mainly installed.

그러나 지하차도는 시공이 복잡하고 건설비가 높으며 별도의 배수설비가 필요하다. 이와 달리 과선교는 비교적 시공이 용이하고 비용면에서도 경제적이여서 많이 적용된다(도 1, 도 2).However, underground driveways are complicated to construct, have high construction costs, and require separate drainage facilities. In contrast, overpass bridges are relatively easy to construct and cost-effective, so they are widely applied (Figures 1 and 2).

과선교 시공 시에는 교량 상부구조 설치를 위해 FSM, ILM, FCM, PSM 등 다양한 공법을 채택할 수 있다.When constructing an overbridge, various construction methods such as FSM, ILM, FCM, and PSM can be adopted to install the bridge superstructure.

FSM(Full Staging Method)은 교량 경간 전체에 동바리(벤트)를 가설하고, 동바리 상부에서 교량 상부구조를 시공하는 공법이다. FSM 공법은 사용 장비 비용이 저렴하고 시공이 간편하다.FSM (Full Staging Method) is a method of constructing a brace (vent) across the entire bridge span and constructing the bridge superstructure on top of the span. The FSM method requires low equipment costs and is easy to construct.

그러나 동바리의 조립 및 해체 작업이 필수여서 공기가 길고, 종래 과선 구간에 적용 시 선로의 레일 사용 및 열차 운행 중단이 불가피하다. 뿐만 아니라 과선 구간에 상부구조 설치 시 열차 레일에서 상부구조 하부까지 최소 7.2m 이상 높이를 확보해야 하는데, FSM 공법은 형하고가 높으면 동바리 비용이 많이 소요되어 경제성이 떨어진다.However, as assembly and disassembly work is required, the construction period is long, and when applied to existing over-track sections, use of track rails and interruption of train operations are inevitable. In addition, when installing the superstructure in the overpass section, a height of at least 7.2 m must be secured from the train rail to the bottom of the superstructure, but the FSM method requires a lot of support costs when the height of the superstructure is high, making it less economical.

그리고 교량 상부구조를 교대 후방에 설치된 작업장에서 세그먼트로 제작한 후 교축 방향으로 밀어 점차적으로 교량을 시공하는 ILM(Incremental Launching Method), 특수 가설장비를 이용하여 각 교각으로부터 좌우로 평형을 맞추면서 포스트텐션에 의해 세그먼트를 순차적으로 접합해 나가면서 경간을 구성하는 FCM(Free Cantilever Method), 한 경간의 PC 박스 거더를 특수 이동 및 가설장비로 한 스팬씩 가설하는 PSM(Precast Span Method) 등은 가설 동바리 없이 과선교를 시공할 수 있다. In addition, ILM (Incremental Launching Method) involves manufacturing the bridge superstructure into segments at a workshop installed at the rear of the abutment and then gradually constructing the bridge by pushing it in the direction of the bridge axis. Using special temporary equipment, post-tensioning is achieved by balancing left and right from each pier. The Free Cantilever Method (FCM), which constructs a span by sequentially connecting segments, and the Precast Span Method (PSM), which constructs a PC box girder of one span one span at a time using special moving and temporary equipment, are used to create overbridge bridges without temporary braces. can be constructed.

그러나 이들 공법을 과선 구간에 적용할 경우, 레일, 전철주, 고압전선 등 철도 시설의 안전성을 위해 안전시설을 필수적으로 설치하여야 한다. 이때, 열차의 계속적인 운행을 위해 가설교 형태로 안전시설을 설치할 수 있는데, 이 경우 과선 구간의 높이 7.2m를 확보하기 위해 상부구조의 설치 위치가 가설교 형고만큼 높아져야 한다. 이에 따라 도로 종단 구배가 높아져 공사비가 증가하는 단점이 있다.However, when these methods are applied to over-track sections, safety facilities such as rails, poles, and high-voltage wires must be installed to ensure the safety of railroad facilities. At this time, safety facilities can be installed in the form of a temporary bridge to ensure the continuous operation of the train. In this case, the installation location of the superstructure must be as high as the temporary bridge height to secure the height of 7.2m for the overtrack section. As a result, the longitudinal gradient of the road increases, which has the disadvantage of increasing construction costs.

KRKR 10-0924277 10-0924277 B1B1

상기와 같은 문제점을 해결하기 위하여 본 발명은 교량 상부구조 설치 시, 신설되는 교량 하부에 철도나 전철이 통과하는 등 교하공간 운영을 그대로 유지할 수 있는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공하고자 한다.In order to solve the above problems, the present invention aims to provide a method of installing a bridge superstructure using a temporary truss that can maintain the operation of the bridge space as is, such as allowing railroads or subways to pass through the lower part of a newly constructed bridge when installing the bridge superstructure. do.

아울러 본 발명은 형하공간을 최대한 확보하여 도로 종단 구배를 최소화할 수 있는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공하고자 한다.In addition, the present invention seeks to provide a method of installing a bridge superstructure using a temporary lower truss that can minimize the longitudinal gradient of the road by securing maximum geometry space.

바람직한 실시예에 따른 본 발명은 교축 방향으로 서로 이격되도록 설치된 한 쌍의 교량 하부구조 상부에 상부구조를 설치하기 위한 것으로, (a) 상기 각 교량 하부구조의 일측에 가벤트를 설치하는 한편, 상기 교량 하부구조의 내측에 교폭 방향으로 가로지르는 한 쌍의 가이드레일부를 교축 방향으로 서로 이격되도록 설치하고, 각 가이드레일부의 상부에 이송대차를 설치하는 단계; (b) 바닥지지틀과 상현재, 하현재 및 상기 상현재와 하현재를 연결하는 사재로 구성되어 각각 하단이 상기 바닥지지틀의 양측에 결합되는 한 쌍의 트러스 주구로 구성되는 가설 하로 트러스를 상기 가벤트의 상부에 거치하는 단계; (c) 상기 가설 하로 트러스의 바닥지지틀 상부에서 교량 상부구조를 시공하는 단계; (d) 상기 트러스 주구를 바닥지지틀에서 해체하여 제거하는 단계; (e) 상기 바닥지지틀이 이송대차의 상부에 거치된 상태에서 이송대차를 교량 상부구조 외측으로 이동시킨 후 바닥지지틀을 제거하는 단계; 및 (f) 상기 가벤트를 제거하는 단계; 로 구성되되, 상기 (b) 단계에서, 상기 각 가이드레일부의 상부에 설치되는 이송대차는 각각 한 쌍으로 구비되어, 상기 한 쌍의 이송대차의 상단을 링크빔으로 연결하며, 상기 바닥지지틀은 링크빔의 상면에 거치되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공한다.The present invention according to a preferred embodiment is to install a superstructure on top of a pair of bridge substructures installed to be spaced apart from each other in the bridge direction. (a) A temporary vent is installed on one side of each bridge substructure, while the Installing a pair of guide rail parts crossing in the bridge width direction on the inside of the bridge substructure to be spaced apart from each other in the bridge axis direction, and installing a transfer truck on top of each guide rail part; (b) A temporary lower truss consisting of a floor support frame, an upper chord, a lower chord, and a pair of truss main members whose lower ends are connected to both sides of the floor support frame, and of a stay member connecting the upper chord and the lower chord. Mounting on top of the vent; (c) constructing a bridge superstructure on the upper part of the bottom support frame of the temporary truss; (d) dismantling and removing the truss main structure from the floor support frame; (e) moving the transfer trolley to the outside of the bridge superstructure while the floor support frame is mounted on the top of the transfer trolley, and then removing the floor support frame; and (f) removing the vent; In step (b), the transfer trolleys installed on the upper part of each guide rail are provided in pairs, the upper ends of the pair of transfer trolleys are connected by a link beam, and the floor support frame Provides a method of installing a bridge superstructure using a temporary truss, which is mounted on the upper surface of the link beam.

삭제delete

다른 바람직한 실시예에 따른 본 발명은 상기 (b) 단계에서, 상기 바닥지지틀을 이송대차의 상부에 거치시킨 후 상기 트러스 주구를 가벤트의 상부에 거치시킨 상태에서 바닥지지틀의 양측에 결합하여 가설 하로 트러스가 조립되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공한다.In the present invention according to another preferred embodiment, in step (b), the floor support frame is mounted on the upper part of the transfer trolley, and then the truss main body is mounted on the upper part of the gargantu and coupled to both sides of the floor support frame. A method of installing a bridge superstructure using a temporary truss is provided, wherein the truss is assembled under a temporary structure.

다른 바람직한 실시예에 따른 본 발명은 상기 이송대차는 높이 조절 가능하게 구성되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공한다.The present invention according to another preferred embodiment provides a method of installing a bridge superstructure using a temporary lower truss, wherein the transport bogie is configured to be height-adjustable.

다른 바람직한 실시예에 따른 본 발명은 상기 트러스 주구의 하현재 내측에는 바닥지지틀의 단부에 결합되는 복수의 브래킷이 구비되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공한다.The present invention according to another preferred embodiment provides a method of installing a bridge superstructure using a temporary lower truss, characterized in that a plurality of brackets coupled to the ends of the floor support frame are provided on the inside of the lower chord of the main groove of the truss.

삭제delete

본 발명에 따르면 교량 하부구조의 외측에 가벤트를 설치한 다음, 가벤트 상부에 바닥지지틀과 한 쌍의 트러스 주구로 이루어져 U자 형상으로 구성된 가설 하로 트러스를 거치한 후, 가설 하로 트러스의 바닥지지틀 상부에서 교량 상부구조를 시공 가능한 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공할 수 있다. According to the present invention, a temporary vent is installed on the outside of the bridge substructure, and then the truss is installed on the upper part of the temporary vent in a U-shaped temporary structure consisting of a floor support frame and a pair of truss main shafts, and then the bottom of the truss is installed under the temporary structure. A method of installing a bridge superstructure using a truss can be provided as a temporary structure that allows the bridge superstructure to be constructed from the upper part of the support frame.

특히, 트러스 주구의 하단이 바닥지지틀의 측면에 결합되어 교량 상부구조의 하부로 돌출되는 높이가 낮으므로, 신설되는 교량 하부의 교하공간 운영을 유지할 수 있고, 형하공간을 최대한 확보하여 도로 종단 구배를 최소화할 수 있다. In particular, the lower end of the truss main body is connected to the side of the floor support frame, so the height that protrudes from the lower part of the bridge superstructure is low, so it is possible to maintain the operation of the bridge space at the bottom of the newly built bridge and secure the profile space as much as possible to maintain the longitudinal gradient of the road. can be minimized.

또한, 트러스 주구를 트러스 부재로 구성함으로써 중량이 가볍고 강성이 커 설치가 용이하고, 교량 상부구조의 하중을 안정적으로 지지할 수 있다. In addition, since the truss main body is made of truss members, it is light in weight and has high rigidity, making installation easy and stably supporting the load of the bridge superstructure.

도 1은 과선교의 설치 위치를 도시하는 평면도.
도 2는 도 1의 정면도.
도 3은 가벤트의 설치 상태를 도시하는 평면도.
도 4는 도 3의 정면도.
도 5는 트러스 주구를 도시하는 정면도 및 단면도.
도 6은 가설 하로 트러스를 도시하는 단면도.
도 7은 가설 하로 트러스의 설치 상태를 도시하는 평면도.
도 8은 도 7의 정면도.
도 9는 도 7의 단면도.
도 10은 상부구조의 설치 상태를 도시하는 평면도.
도 11은 도 10의 정면도.
도 12는 도 10의 단면도.
도 13은 트러스 주구의 제거 상태를 도시하는 단면도.
도 14는 바닥지지틀의 제거 상태를 도시하는 단면도.
도 15는 가벤트의 제거 상태를 도시하는 단면도.
도 16은 가이드레일부 및 이송대차의 설치 상태를 도시하는 평면도.
도 17은 이송대차 및 가벤트의 상부에 가설 하로 트러스가 설치된 상태를 도시하는 단면도.
도 18은 이송대차에 의한 바닥지지틀의 제거 상태를 도시하는 단면도.
도 19는 이송대차에 의한 바닥지지틀의 설치 상태를 도시하는 단면도.
도 20은 바닥지지틀 설치 후 트러스 주구의 설치 상태를 도시하는 단면도.
Figure 1 is a plan view showing the installation position of the overbridge.
Figure 2 is a front view of Figure 1.
Figure 3 is a plan view showing the installation state of the vent.
Figure 4 is a front view of Figure 3.
Figure 5 is a front view and a cross-sectional view showing the main truss structure.
Figure 6 is a cross-sectional view showing a temporary truss.
Figure 7 is a plan view showing the installation state of the temporary truss.
Figure 8 is a front view of Figure 7.
Figure 9 is a cross-sectional view of Figure 7.
Fig. 10 is a plan view showing the installation state of the superstructure.
Figure 11 is a front view of Figure 10.
Figure 12 is a cross-sectional view of Figure 10.
Fig. 13 is a cross-sectional view showing the removed state of the truss main sphere.
Figure 14 is a cross-sectional view showing the removed state of the floor support frame.
Fig. 15 is a cross-sectional view showing a state in which a gar vent is removed.
Figure 16 is a plan view showing the installation state of the guide rail portion and the transfer cart.
Figure 17 is a cross-sectional view showing a state in which a temporary truss is installed on the upper part of the transfer cart and the vent.
Figure 18 is a cross-sectional view showing the state of removal of the floor support frame by the transfer truck.
Figure 19 is a cross-sectional view showing the installation state of the floor support frame by the transfer cart.
Figure 20 is a cross-sectional view showing the installation state of the main truss structure after installation of the floor support frame.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다. Hereinafter, the present invention will be described in detail according to the accompanying drawings and preferred embodiments.

도 3은 가벤트의 설치 상태를 도시하는 평면도이고, 도 4는 도 3의 정면도이다. 도 5는 트러스 주구를 도시하는 정면도 및 단면도이고, 도 6은 가설 하로 트러스를 도시하는 단면도이다. 그리고 도 7은 가설 하로 트러스의 설치 상태를 도시하는 평면도이고, 도 8은 도 7의 정면도이며, 도 9는 도 7의 단면도이다. Figure 3 is a plan view showing the installation state of the vent, and Figure 4 is a front view of Figure 3. FIG. 5 is a front view and a cross-sectional view showing the main sphere of the truss, and FIG. 6 is a cross-sectional view showing the truss under construction. And Figure 7 is a plan view showing the installation state of the truss under temporary construction, Figure 8 is a front view of Figure 7, and Figure 9 is a cross-sectional view of Figure 7.

아울러 도 10은 상부구조의 설치 상태를 도시하는 평면도이고, 도 11은 도 10의 정면도이며, 도 12는 도 10의 단면도이다. 또한, 도 13은 트러스 주구의 제거 상태를 도시하는 단면도이고, 도 14는 바닥지지틀의 제거 상태를 도시하는 단면도이며, 도 15는 가벤트의 제거 상태를 도시하는 단면도이다.In addition, Figure 10 is a plan view showing the installation state of the superstructure, Figure 11 is a front view of Figure 10, and Figure 12 is a cross-sectional view of Figure 10. Additionally, FIG. 13 is a cross-sectional view showing the truss main groove removed, FIG. 14 is a cross-sectional view showing the floor support frame removed, and FIG. 15 is a cross-sectional view showing the vent removed.

본 발명 가설 하로 트러스를 이용한 교량 상부구조 설치 방법은 교축 방향으로 서로 이격되도록 설치된 한 쌍의 교량 하부구조(11) 상부에 상부구조(12)를 설치하기 위한 것으로, (a) 상기 각 교량 하부구조(11)의 일측에 가벤트(3)를 설치하는 단계; (b) 바닥지지틀(5a)과 상현재(53), 하현재(54) 및 상기 상현재(53)와 하현재(54)를 연결하는 사재(55)로 구성되어 각각 하단이 상기 바닥지지틀(5a)의 양측에 결합되는 한 쌍의 트러스 주구(5b)로 구성되는 가설 하로 트러스(5)를 상기 가벤트(3)의 상부에 거치하는 단계; (c) 상기 가설 하로 트러스(5)의 바닥지지틀(5a) 상부에서 교량 상부구조(12)를 시공하는 단계; (d) 상기 트러스 주구(5b)를 바닥지지틀(5a)에서 해체하여 제거하는 단계; (e) 상기 바닥지지틀(5a)을 제거하는 단계; 및 (f) 상기 가벤트(3)를 제거하는 단계; 로 구성되는 것을 특징으로 한다.The method of installing a bridge superstructure using a temporary truss according to the present invention is to install a superstructure 12 on top of a pair of bridge substructures 11 installed to be spaced apart from each other in the bridge axis direction, (a) each bridge substructure Installing a vent (3) on one side of (11); (b) It consists of a floor support frame (5a), an upper chord (53), a lower chord (54), and a stay member (55) connecting the upper chord (53) and the lower chord (54), the lower ends of each of which support the floor. Mounting a temporary truss (5) consisting of a pair of truss main holes (5b) coupled to both sides of the frame (5a) on the upper part of the gable (3); (c) constructing a bridge superstructure (12) on the upper part of the floor support frame (5a) of the temporary lower truss (5); (d) dismantling and removing the truss main hole (5b) from the floor support frame (5a); (e) removing the floor support frame (5a); and (f) removing the vent (3); It is characterized by being composed of.

본 발명은 교량 상부구조(12)의 설치 시, 신설되는 교량(1)의 하부에 철도나 전철이 통과하는 등 교하공간 운영을 그대로 유지할 수 있고, 형하공간을 최대한 확보하여 도로 종단 구배를 최소화할 수 있는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법을 제공하가 위한 것이다.In the present invention, when installing the bridge superstructure (12), the operation of the bridge space can be maintained as is, such as allowing a railroad or subway to pass through the lower part of the newly constructed bridge (1), and the longitudinal space of the road can be minimized by securing the profile space as much as possible. It is intended to provide a method of installing a bridge superstructure using trusses as a possible temporary construction.

본 발명은 교각 또는 교대인 하부구조(11)의 상부에 거더와 교량 상판인 상부구조(12)가 구비되는 교량(1)에서, 상기 상부구조(12)를 설치하기 위한 것이다.The present invention is intended to install the superstructure 12 in a bridge (1) in which a superstructure (12), which is a girder and a bridge deck, is provided on the upper part of the substructure (11), which is a pier or abutment.

특히, 본 발명은 하부에 철도나 전철이 통과하는 과선교로서 해체 대상 교량(1) 하부를 통과하는 철주 등 철도 시설물(100)로 인해 교하공간에 여유가 없는 경우 더욱 효과적으로 적용할 수 있다.In particular, the present invention can be applied more effectively when there is insufficient space under the bridge due to railroad facilities (100) such as iron poles passing under the bridge (1) to be dismantled as an overpass bridge through which a railroad or subway passes.

본 발명에서는 먼저 (a) 각 교량 하부구조(11)의 일측에 가벤트(3)를 설치한다(도 3, 도 4).In the present invention, (a) first, a temporary vent (3) is installed on one side of each bridge substructure (11) (FIGS. 3 and 4).

상기 (a) 단계에서는 바닥 정지 작업 후 가벤트(3, temporary bent)를 설치한다. In step (a), a temporary bent (3) is installed after floor preparation.

상기 가벤트(3)의 설치 전에 가벤트(3)의 하중을 지반으로 전달하기 위한 기초(F)를 시공할 수 있다.Before installing the temporary vent (3), a foundation (F) can be constructed to transmit the load of the temporary vent (3) to the ground.

상기 기초(F)는 터파기와 잡석 다짐 후 기초콘크리트를 타설하여 형성할 수 있다. 도면에는 도시되지 않았으나 지반 상태에 따라 기초(F) 하부에 기초파일을 시공할 수 있다.The foundation (F) can be formed by pouring foundation concrete after digging and compacting rubble. Although not shown in the drawing, foundation piles may be constructed at the bottom of the foundation (F) depending on the ground condition.

상기 가벤트(3)는 교량 하부구조(11)의 양측에 각각 적어도 2게 이상 설치될 수 있다. 이를 위해 상기 가벤트(3)가 설치될 기초(F)는 상부구조(12)의 좌우에 각각 한 쌍씩 구비되는 독립기초로 시공될 수 있다.At least two of the vents 3 may be installed on both sides of the bridge substructure 11. For this purpose, the foundation (F) on which the temporary vent (3) will be installed can be constructed as an independent foundation provided in pairs on each side of the superstructure (12).

상기 기초(F)를 시공한 다음, 각 기초(F)의 상부에 가벤트(3)를 설치한다.After constructing the foundation (F), a temporary vent (3) is installed on the top of each foundation (F).

상기 가벤트(3)는 후술할 가설 하로 트러스(5)의 양단부 4지점을 지지하기 위한 가설 구조물로, 과선 구간 외측에 설치하므로 과선 구간 사용에 지장이 없다.The temporary vent 3 is a temporary structure to support four points at both ends of the temporary truss 5, which will be described later, and is installed outside the overwire section, so there is no problem in using the overwire section.

상기 가벤트(3)를 설치 완료한 후에는 (b) 가설 하로 트러스(5)를 양중하여 상기 가벤트(3)의 상부에 거치한다(도 7 내지 도 9). After completing the installation of the garland (3), (b) the truss (5) is lifted under the temporary suspension and placed on the upper part of the garland (3) (FIGS. 7 to 9).

상기 가설 하로 트러스(5)는 바닥지지틀(5a)과 한 쌍의 트러스 주구(5b)로 구성된다(도 6).The hypothesized truss 5 is composed of a floor support frame 5a and a pair of truss main grooves 5b (FIG. 6).

상기 바닥지지틀(5a)은 공장에서 제작되거나 현장에 마련된 별도의 조립장에서 현장 조립할 수 있다. 상기 바닥지지틀(5a)은 철골 부재인 복수의 가로보(51)와 가로보(51)들을 연결하는 세로보(52)로 구성될 수 있다(도 6, 도 7).The floor support frame 5a can be manufactured at a factory or assembled on-site at a separate assembly facility provided on site. The floor support frame 5a may be composed of a plurality of crossbeams 51, which are steel members, and vertical beams 52 connecting the crossbeams 51 (FIGS. 6 and 7).

상기 트러스 주구(5b, 主構)는 상하로 서로 이격되어 배치되는 상현재(53)와 하현재(54) 및 상기 상현재(53)와 하현재(54)를 연결하는 사재(55)로 구성된 트러스 부재이다(도 5).The truss main body (5b, main member) is composed of upper and lower chords (53) and lower chords (54) arranged vertically and spaced apart from each other, and a stay member (55) connecting the upper chord (53) and the lower chord (54). It is a truss member (Figure 5).

상기 트러스 주구(5b)는 트러스 부재로 이루어져 중량이 가벼우면서도 강성이 크다. 따라서 설치가 용이하고, 교량 상부구조(12)의 하중을 안정적으로 지지할 수 있다. 또한 상기 트러스 주구(5b)의 사재(55) 사이 개방 공간을 활용하여 작업자가 이동할 수 있으므로, 트러스 주구(5b)와 바닥지지틀(5a)의 조립 및 해체 작업이 용이하다.The truss main port 5b is made of a truss member, so it is light in weight and has high rigidity. Therefore, installation is easy and the load of the bridge superstructure 12 can be stably supported. In addition, since workers can move by utilizing the open space between the yarns 55 of the truss main body 5b, assembly and disassembly of the truss main body 5b and the floor support frame 5a are easy.

상기 트러스 주구(5b)의 하부가 바닥지지틀(5a)의 단부와 결합되어 좌우 한 쌍의 트러스 주구(5b)와 한 쌍의 트러스 주구(5b) 사이에 구비된 바닥지지틀(5a)로 이루어진 가설 하로 트러스(5)가 형성된다.The lower part of the truss main hole (5b) is coupled to the end of the floor support frame (5a) and consists of a pair of left and right truss main holes (5b) and a floor support frame (5a) provided between the pair of truss main holes (5b). A truss (5) is formed under the hypothesis.

상기 바닥지지틀(5a)은 양측 트러스 주구(5b)를 서로 연결하여 트러스 주구(5b)의 뒤틀림을 방지한다.The floor support frame 5a connects the two truss main grooves 5b to each other to prevent the truss main sphere 5b from being distorted.

상기 가설 하로 트러스(5)는 교량 상부구조(12)의 하중을 지지하여 가벤트(3)로 전달하는 것으로, 전체적으로 U형 단면으로 형성된다.The temporary truss 5 supports the load of the bridge superstructure 12 and transmits it to the vent 3, and is formed as a whole with a U-shaped cross section.

상기 바닥지지틀(5a)은 교량 상부구조(12)의 시공하중을 좌우의 트러스 주구(5b)로 전달하고, 트러스 주구(5b)는 시공하중을 휨강성에 의해 지지한다.The floor support frame 5a transfers the construction load of the bridge superstructure 12 to the left and right truss main openings 5b, and the truss main openings 5b support the construction load by bending rigidity.

시공하중을 지지하는 부재인 트러스 주구(5b)는 교량 상부구조(12)의 하부가 아닌 측면에 위치하므로, 교량 상부구조(12)의 하부로는 바닥지지틀(5a)의 두께만큼만 돌출된다.Since the truss main hole 5b, which is a member supporting the construction load, is located on the side rather than the bottom of the bridge superstructure 12, it protrudes into the lower part of the bridge superstructure 12 only by the thickness of the floor support frame 5a.

그러므로 교량 상부구조(12)의 하부로 돌출되는 높이가 낮아, 철도, 철주 등 철도 시설물(100)로 인해 교하공간에 여유가 없는 경우에도 형하공간(통과 높이)을 최대한 확보하여 교량 하부 지장물의 간섭 없이 설치 높이를 최소화하여 상부구조(12)를 시공할 수 있다. 아울러 종단 급경사, 직선, 곡선교 등 다양한 교량(1)에 적용 가능하다.Therefore, the height protruding from the lower part of the bridge superstructure 12 is low, and even when there is no space under the bridge due to railroad facilities 100 such as railroads and pontoons, the profile space (passing height) is secured as much as possible to prevent interference from obstacles under the bridge. The superstructure 12 can be constructed by minimizing the installation height. In addition, it can be applied to various bridges (1) such as steep longitudinal, straight, and curved bridges.

다음으로, (c) 상기 가설 하로 트러스(5)가 가벤트(3) 상부에 설치된 상태에서, 가설 하로 트러스(5)의 바닥지지틀(5a) 상부에서 교량 상부구조(12)를 시공한다(도 10 내지 도 12).Next, (c) in a state where the temporary lower truss 5 is installed on the upper part of the temporary lower truss 5, the bridge superstructure 12 is constructed on the upper part of the bottom support frame 5a of the temporary lower truss 5 ( 10 to 12).

상기 교량 상부구조(12)는 바닥지지틀(5a)의 상부에 거푸집을 설치한 후 현장에서 콘크리트를 타설하여 형성될 수 있다. 이 경우 상기 바닥지지틀(5a)은 거푸집을 지지한다.The bridge superstructure 12 can be formed by installing formwork on the upper part of the floor support frame 5a and then pouring concrete on site. In this case, the floor support frame (5a) supports the formwork.

또는, 상기 교량 상부구조(12)는 PSC 박스 거더, 스틸박스 거더, 플레이트 거더, PSC빔 등으로 형성될 수 있다. 이 경우 거더의 양단이 하부구조(11)의 상단에 직접 거치되므로, 가설 하로 트러스(5)가 교량 상부구조(12)의 하중을 직접 지지하지는 않는다. 다만, 상기 바닥지지틀(5a)의 상부에 낙하물 방지망 등을 설치하여 낙하물 방지 시설 역할을 할 수 있다. 물론 이 경우에도 경간이 크거나 고중량인 경우에는 가설 하로 트러스(5)가 상부구조(12)의 가설 지보재 역할을 할 수 있다.Alternatively, the bridge superstructure 12 may be formed of PSC box girder, steel box girder, plate girder, PSC beam, etc. In this case, since both ends of the girder are directly mounted on the top of the substructure 11, the truss 5 does not directly support the load of the bridge superstructure 12 under temporary conditions. However, a falling object prevention net, etc. may be installed on the upper part of the floor support frame 5a to serve as a falling object prevention facility. Of course, even in this case, if the span is large or heavy, the temporary truss 5 can serve as a temporary support for the superstructure 12.

이후, (d) 상기 트러스 주구(5b)를 바닥지지틀(5a)에서 해체하여 제거한다(도 13).Thereafter, (d) the truss main hole (5b) is dismantled and removed from the floor support frame (5a) (FIG. 13).

상기 교량 상부구조(12)를 시공한 후에는 가설 하로 트러스(5)를 제거해야 한다. 그런데 상기 가설 하로 트러스(5)의 트러스 주구(5b)가 시공 완료된 상부구조(12)의 양측에 위치하므로, 가설 하로 트러스(5)를 바로 제거할 수 없다.After constructing the bridge superstructure 12, the truss 5 must be removed for temporary installation. However, since the truss main grooves 5b of the temporary truss 5 are located on both sides of the superstructure 12 on which construction has been completed, the temporary truss 5 cannot be immediately removed.

따라서 상기 트러스 주구(5b)를 바닥지지틀(5a)로부터 해체한 후 양중하여 제거한다.Therefore, the truss main port 5b is dismantled from the floor support frame 5a and then lifted and removed.

그리고 (e) 상기 바닥지지틀(5a)을 제거한다(도 14).And (e) remove the floor support frame (5a) (FIG. 14).

상기 트러스 주구(5b)가 제거되면 바닥지지틀(5a)의 양측에 간섭 요인이 없으므로, 바닥지지틀(5a)을 측방으로 이동하여 쉽게 제거할 수 있다.When the truss main hole 5b is removed, there is no interference factor on both sides of the floor support frame 5a, so the floor support frame 5a can be easily removed by moving to the side.

마지막으로 (f) 상기 가벤트(3)를 제거한다(도 15).Finally, (f) remove the vent (3) (FIG. 15).

도 16은 가이드레일부 및 이송대차의 설치 상태를 도시하는 평면도이고, 도 17은 이송대차 및 가벤트의 상부에 가설 하로 트러스가 설치된 상태를 도시하는 단면도이며, 도 18은 이송대차에 의한 바닥지지틀의 제거 상태를 도시하는 단면도이다.Figure 16 is a plan view showing the installation state of the guide rail portion and the transfer trolley, Figure 17 is a cross-sectional view showing a state in which a temporary truss is installed on the upper part of the transfer trolley and the gable vent, and Figure 18 is a floor support by the transfer trolley. This is a cross-sectional view showing the frame being removed.

상기 (a) 단계에서, 상기 교량 하부구조(11)의 내측에 교폭 방향으로 가로지르는 한 쌍의 가이드레일부(2)를 교축 방향으로 서로 이격되도록 설치하고, 각 가이드레일부(2)의 상부에 이송대차(4)를 설치하며, 상기 (e) 단계에서, 상기 바닥지지틀(5a)이 이송대차(4)의 상부에 거치된 상태에서 이송대차(4)를 교량 상부구조(12) 외측으로 이동시킨 후 바닥지지틀(5a)을 제거할 수 있다. In step (a), a pair of guide rail parts 2 crossing in the bridge width direction are installed on the inside of the bridge substructure 11 to be spaced apart from each other in the bridge axis direction, and the upper part of each guide rail part 2 A transfer cart (4) is installed on the transfer cart (4), and in step (e), the transfer cart (4) is placed on the outside of the bridge superstructure (12) with the floor support frame (5a) mounted on the top of the transfer cart (4). After moving to , the floor support frame (5a) can be removed.

상기 가설 하로 트러스(5)는 상부구조(12)의 설치 전에는 간섭요인이 없어 가벤트(3)의 상부에 용이하게 거치할 수 있다. With the above-mentioned construction, the truss 5 can be easily mounted on the upper part of the vent 3 since there is no interference factor before the installation of the superstructure 12.

그러나 상기 교량 상부구조(12)의 설치가 완료된 후에는 U형 단면인 가설 하로 트러스(5)가 교량 상부구조(12)의 하부와 측면을 감싸고 있으므로, 가설 하로 트러스(3)를 해체하기가 쉽지 않다. 특히 상기 가설 하로 트러스(3)의 해체 시, 트러스 주구(5b)를 바닥지지틀(5a)에서 분리하여 먼저 제거하더라도 교량 상부구조(12)의 하부에 위치하는 바닥지지틀(5a)을 측방으로 이동하기 쉽지 않다.However, after the installation of the bridge superstructure 12 is completed, the temporary truss 5, which has a U-shaped cross section, surrounds the lower part and the side of the bridge superstructure 12, so it is not easy to dismantle the temporary truss 3. not. In particular, when dismantling the truss (3) under the above-mentioned construction, even if the truss main hole (5b) is separated from the floor support frame (5a) and removed first, the floor support frame (5a) located at the lower part of the bridge superstructure (12) is moved laterally. Not easy to move.

따라서 상기 가벤트(3)를 설치하는 (a) 단계에서, 상기 바닥지지틀(5a)을 측방으로 슬라이딩 이동시키기 위한 가이드레일부(2)를 교량 하부구조(11)의 내측에 교폭 방향으로 가로지르도록 설치하고, 상기 가이드레일부(2)의 상부에 가이드레일부(2)의 길이 방향을 따라 주행 가능한 이송대차(4)를 설치할 수 있다(도 16).Therefore, in step (a) of installing the temporary vent (3), the guide rail part (2) for sliding the floor support frame (5a) laterally is installed horizontally in the bridge width direction on the inside of the bridge substructure (11). It is installed so as to support the guide rail part 2, and a transfer truck 4 capable of traveling along the longitudinal direction of the guide rail part 2 can be installed on the upper part of the guide rail part 2 (FIG. 16).

상기 가이드레일부(2)의 설치 전에 가이드레일부(2)의 하중을 지반으로 전달하기 위한 기초가 시공될 수 있다. 상기 가이드레일부(2)가 설치될 기초는 교량 상부구조(12)를 가로지르도록 연속된 줄기초로 시공할 수 있다(도 17, 도 18).Before installing the guide rail portion 2, a foundation may be constructed to transmit the load of the guide rail portion 2 to the ground. The foundation on which the guide rail portion 2 will be installed can be constructed as a continuous stem foundation to cross the bridge superstructure 12 (FIGS. 17 and 18).

상기 기초 시공 후 기초 상부에 가이드레일부(2)를 설치한다.After the foundation construction, the guide rail portion (2) is installed on the upper part of the foundation.

상기 가이드레일부(2)는 설치될 상부구조(12)의 하부에 상부구조(12)를 교폭 방향으로 가로지르도록 설치되며, 한 쌍이 교축 방향으로 서로 이격되도록 배치된다.The guide rail portion 2 is installed at the lower part of the superstructure 12 to be installed so as to cross the superstructure 12 in the bridge direction, and a pair is arranged to be spaced apart from each other in the bridge direction.

상기 가이드레일부(2)는 교폭보다 다소 길이를 길게 형성하여 교량 상부구조(12)의 외측으로 일정 길이 돌출되게 구성할 수 있다.The guide rail portion 2 may be formed to be slightly longer than the bridge width and protrude for a certain length to the outside of the bridge superstructure 12.

상기 가이드레일부(2)는 상단이 교량 상부구조(12)의 하면보다 낮게 설치되어, 교량 상부구조(12)의 하면과의 사이에 소정의 이격 공간이 형성될 수 있다.The upper end of the guide rail portion 2 is installed lower than the lower surface of the bridge superstructure 12, so that a predetermined space can be formed between the lower surface of the bridge superstructure 12.

상기 가이드레일부(2)의 상면에는 이송대차(4)의 거치 및 이동을 위한 레일빔(21)이 구비될 수 있다.A rail beam 21 may be provided on the upper surface of the guide rail portion 2 for mounting and moving the transfer cart 4.

철도 등 과선 구간에 교량 상부구조(12)가 설치되는 경우, 상기 가이드레일부(2)는 철도 선로 외측에 설치하여 선로 사용에 간섭되지 않게 함이 바람직하다.When the bridge superstructure 12 is installed in a section of a railway line, etc., it is desirable to install the guide rail part 2 outside the railway track so as not to interfere with the use of the track.

상기 가이드레일부(2)는 교축 방향과 직교하는 방향으로 배치될 수 있으나, 하부 선로가 비스듬하게 통과하는 경우 철도 선로와 평행하게 배치하는 것이 바람직하다.The guide rail portion 2 may be arranged in a direction perpendicular to the direction of the throttling axis, but if the lower track passes obliquely, it is preferable to be placed parallel to the railway track.

상기 가이드레일부(2)의 설치 후에는 각 가이드레일부(2)의 레일빔(21) 상부에 이송대차(4)를 거치하여 설치한다.After installation of the guide rail part (2), the transfer truck (4) is mounted and installed on the upper part of the rail beam (21) of each guide rail part (2).

상기 이송대차(4)는 가이드레일부(2)의 레일빔(21)에 의해 가이드되어 교폭 방향으로 자유롭게 이동 가능하다.The transfer truck (4) is guided by the rail beam (21) of the guide rail portion (2) and can freely move in the bridge width direction.

상기 가이드레일부(2)와 이송대차(4)를 설치한 다음, 이송대차(4) 및 가벤트(3)의 상부에 가설 하로 트러스(5)를 설치한다(도 17).After installing the guide rail portion (2) and the transfer cart (4), a temporary truss (5) is installed on the upper part of the transfer cart (4) and the gargantuan (3) (FIG. 17).

그리고 상기 (e) 단계에서는 이송대차(4)가 바닥지지틀(5a)의 하부를 지지한 상태에서 이송대차(4)를 외측으로 슬라이딩 이동하여 바닥지지틀(5a)을 교량 상부구조(12)의 외측으로 이동시킬 수 있다. 이후 바닥지지틀(5a)을 양중하여 제거한다(도 18).And in step (e), while the transfer truck 4 supports the lower part of the floor support frame 5a, the transfer truck 4 is slid outward to move the floor support frame 5a to the bridge superstructure 12. It can be moved to the outside of . Afterwards, the floor support frame (5a) is lifted and removed (FIG. 18).

상기 이송대차(4)는 이송되는 바닥지지틀(5a)의 안정적인 지지를 위해 각 가이드레일부(2)마다 일측에 2개씩 상호 이격되게 설치될 수 있다.The transfer carts 4 may be installed two on one side of each guide rail part 2 to be spaced apart from each other in order to stably support the transported floor support frame 5a.

상기 이송대차(4) 및 가이드레일부(2)는 (f) 단계에서 가벤트(3) 제거 시 같이 제거할 수 있다. The transfer cart (4) and the guide rail portion (2) can be removed together when removing the vent (3) in step (f).

도 19는 이송대차에 의한 바닥지지틀의 설치 상태를 도시하는 단면도이고, 도 20은 바닥지지틀 설치 후 트러스 주구의 설치 상태를 도시하는 단면도이다.Figure 19 is a cross-sectional view showing the installation state of the floor support frame by the transfer cart, and Figure 20 is a cross-sectional view showing the installation state of the main truss structure after installation of the floor support frame.

상기 (b) 단계에서, 상기 바닥지지틀(5a)을 이송대차(4)의 상부에 거치시킨 후 상기 트러스 주구(5b)를 가벤트(3)의 상부에 거치시킨 상태에서 바닥지지틀(5a)의 양측에 결합하여 가설 하로 트러스(5)가 조립될 수 있다. In step (b), the floor support frame (5a) is mounted on the upper part of the transfer cart (4), and then the truss main hole (5b) is mounted on the upper part of the gar vent (3), and then the floor support frame (5a) ) The truss (5) can be assembled under construction by joining both sides of the truss.

경간이 큰 경우에는 상기 가설 하로 트러스(5)가 대형화되어 중량이 증가된다. 그러므로 상기 가설 하로 트러스(5) 전체를 일체로 양중하여 가벤트(3) 상부에 거치하기 곤란하다.When the span is large, the truss 5 is enlarged and its weight increases. Therefore, it is difficult to lift the entire truss (5) as a whole and place it on the upper part of the gar vent (3) under the above-mentioned temporary structure.

따라서 상기 바닥지지틀(5a)과 트러스 주구(5b)를 분리된 상태로 개별적으로 양중하여 설치할 수 있다.Therefore, the floor support frame 5a and the truss main shaft 5b can be lifted and installed separately.

이를 위해 상기 이송대차(4)를 설치될 교량 상부구조(12)의 하부에 위치시킨 상태에서 이송대차(4)의 상부에 바닥지지틀(5a)을 거치할 수 있다(도 19).For this purpose, the floor support frame 5a can be mounted on the upper part of the transfer truck 4 while the transfer truck 4 is located at the lower part of the bridge superstructure 12 to be installed (FIG. 19).

이후, 상기 트러스 주구(5b)를 양중하여 바닥지지틀(5a)의 양측에서 가벤트(3) 상부에 거치시킨 후, 상기 트러스 주구(5b)의 하부 내측을 바닥지지틀(5a)의 측단과 결합하여 가설 하로 트러스(5)를 조립할 수 있다.Thereafter, the truss main port 5b is lifted and placed on the upper part of the vent 3 on both sides of the floor support frame 5a, and then the lower inner side of the truss main port 5b is connected to the side end of the floor support frame 5a. By combining them, the truss (5) can be assembled under temporary construction.

이때, 상기 트러스 주구(5b)는 공장 등에서 모듈형으로 분할 제작하고, 바닥지지틀(5a)의 상부에서 각 트러스 주구(5b) 모듈들을 조립한 후 양중하여 바닥지지틀(5a)의 측방으로 이동시켜 결합할 수 있다. 이 경우 트러스 주구(5b)의 운반 및 양중 부담을 줄이고, 바닥지지틀(5a)을 작업장으로 활용할 수 있어 공간 활용 면에서 유리하다.At this time, the truss main body 5b is manufactured in modular form in a factory, etc., and each truss main body 5b module is assembled at the upper part of the floor support frame 5a, then lifted and moved to the side of the floor support frame 5a. It can be combined. In this case, the burden of transporting and lifting the truss main body (5b) is reduced, and the floor support frame (5a) can be used as a workplace, which is advantageous in terms of space utilization.

이와 같이 상기 트러스 주구(5b)는 가벤트(3)의 상부에 거치되고, 바닥지지틀(5a)은 한 쌍의 트러스 주구(5b) 사이에서 이송대차(4)의 상부에 거치되므로, 바닥지지틀(5a)은 교폭 방향 가벤트(3) 사이 간격보다 폭을 좁게 형성할 수 있다.In this way, the truss main port 5b is mounted on the upper part of the vent 3, and the floor support frame 5a is mounted on the upper part of the transfer cart 4 between the pair of truss main ports 5b, so the floor support The frame (5a) may be formed to have a width narrower than the gap between the bridge vents (3) in the crossing direction.

상기 바닥지지틀(5a)은 이송대차(4)를 먼저 교량 상부구조(12)의 하부 위치로 이동시킨 상태에서 이송대차(4)의 상부에 거치할 수 있다. The floor support frame 5a can be mounted on the upper part of the transfer truck 4 after first moving the transfer truck 4 to the lower position of the bridge superstructure 12.

또는 상기 가벤트(3) 및 교량 하부구조(11)의 간섭으로 인해 바닥지지틀(5a)을 양중하기 곤란한 경우, 이송대차(4)를 교량 상부구조(12)의 외측에 위치시킨 상태에서 바닥지지틀(5a)을 이송대차(4)의 상부에 거치한 다음, 바닥지지틀(5a)이 거치된 이송대차(4)를 교량 상부구조(12)가 설치될 위치로 슬라이딩 이동시킬 수도 있다(도 19).Alternatively, if it is difficult to lift the floor support frame (5a) due to interference between the vent (3) and the bridge substructure (11), the transfer truck (4) is positioned outside the bridge superstructure (12) and the floor is lifted. After mounting the support frame (5a) on the top of the transfer truck (4), the transfer truck (4) on which the bottom support frame (5a) is mounted can be slidably moved to the position where the bridge superstructure 12 is to be installed ( Figure 19).

아울러 상기 바닥지지틀(5a)의 설치 또는 해체를 위해 수평 이동 시, 교량 하부구조(11) 또는 가벤트(3)가 간섭될 수 있다. 그러므로 상기 바닥지지틀(5a)은 교축 방향 가벤트(3) 사이 및 교량 하부구조(11) 사이 순간격보다 길이를 짧게 형성할 수 있다(도 7). 이 경우 바닥지지틀(5a)을 설치한 후 바닥지지틀(5a)의 길이 방향 양단에 연장바닥틀(50a)을 조립하여 바닥지지틀(5a)을 확대 형성할 수 있다. In addition, when moving horizontally to install or dismantle the floor support frame 5a, the bridge substructure 11 or the vent 3 may interfere. Therefore, the floor support frame 5a can be formed to have a length shorter than the instantaneous gap between the bridge direction vents 3 and the bridge substructure 11 (FIG. 7). In this case, after installing the floor support frame 5a, the floor support frame 5a can be enlarged by assembling extended floor frames 50a at both ends in the longitudinal direction of the floor support frame 5a.

상기 연장바닥틀(50a)은 바닥지지틀(5a) 단부의 트러스 주구(5b)보다 짧은 일부 부분에 대해 가로보(51) 개별 부재를 고소작업대나 호이스트 등으로 양중한 후 현장에서 조립하여 양측 트러스 주구(5b)에 연결할 수 있다.The extended floor frame (50a) is assembled on site by lifting individual members of the crossbeam (51) at a portion shorter than the truss main hole (5b) at the end of the floor support frame (5a) with an aerial work platform or hoist, and then assembling the truss main hole on both sides. It can be connected to (5b).

도 18, 도 19에 도시된 바와 같이, 상기 이송대차(4)는 높이 조절 가능하게 구성될 수 있다. As shown in FIGS. 18 and 19, the transfer cart 4 may be configured to have an adjustable height.

상기 트러스 주구(5b)와 바닥지지틀(5a)의 접합이 용이하도록 이송대차(4)는 상부를 상하로 승하강 가능하게 높이 조절 가능하도록 구성할 수 있다.To facilitate the joining of the truss main port 5b and the floor support frame 5a, the transfer cart 4 may be configured to have its upper part raised and lowered and height-adjustable.

이에 따라 상기 이송대차(4)의 상부에 바닥지지틀(5a)이 거치된 상태에서 이송대차(4)를 승하강하여, 바닥지지틀(5a)의 가로보(51) 위치와 가벤트(3) 상단에 거치된 트러스 주구(5b)의 위치를 일치시킨 후 접합할 수 있다(도 19, 도 20).Accordingly, the transfer truck (4) is raised and lowered with the floor support frame (5a) mounted on the upper part of the transfer truck (4), so that the position of the cross beam (51) of the floor support frame (5a) and the top of the gable vent (3) are raised and lowered. It can be joined after matching the positions of the truss main ports (5b) mounted on (FIGS. 19 and 20).

상기 가설 하로 트러스(5)의 해체 및 제거 시에는 트러스 주구(5b)를 바닥지지틀(5a)에서 분리하여 제거한 다음, 이송대차(4)를 하강시켜 바닥지지틀(5a)이 교량 상부구조(12)의 하면과 이격되게 한 후 수평 방향으로 슬라이딩시켜 바닥지지틀(5a)을 교량 상부구조(12) 외측으로 이동시킬 수 있다(도 18).When dismantling and removing the truss 5 under the above-mentioned construction, the truss main hole 5b is separated and removed from the floor support frame 5a, and then the transfer truck 4 is lowered so that the floor support frame 5a is attached to the bridge superstructure ( The floor support frame 5a can be moved to the outside of the bridge superstructure 12 by separating it from the lower surface of the bridge 12) and then sliding it in the horizontal direction (FIG. 18).

도 5, 도 6 등에 도시된 바와 같이, 상기 트러스 주구(5b)의 하현재(54) 내측에는 바닥지지틀(5a)의 단부에 결합되는 복수의 브래킷(56)이 구비될 수 있다.As shown in FIGS. 5 and 6, a plurality of brackets 56 coupled to the ends of the floor support frame 5a may be provided inside the lower chord 54 of the truss main port 5b.

상기 가설 하로 트러스(5)가 바닥지지틀(5a)과 트러스 주구(5b)로 분리 구성되는 것으로, 바닥지지틀(5a)은 이송대차(4)의 상부에 거치되고, 트러스 주구(5b)는 가벤트(3)의 상부에 거치되는 경우, 바닥지지틀(5a)의 폭이 양측 가벤트(3)의 간격 이상이면 바닥지지틀(5a)을 설치하기 곤란하다.Under the above hypothesis, the truss 5 is composed of a floor support frame 5a and a truss main body 5b, and the floor support frame 5a is mounted on the upper part of the transfer cart 4, and the truss main sphere 5b is When mounted on the upper part of the garland 3, it is difficult to install the floor support frame 5a if the width of the floor support frame 5a is greater than the gap between the garland vents 3 on both sides.

특히 상기 이송대차(4)의 승하강 시 바닥지지틀(5a)과 가벤트(3)가 서로 간섭된다.In particular, when the transfer truck 4 is raised and lowered, the floor support frame 5a and the vent 3 interfere with each other.

따라서 상기 바닥지지틀(5a)의 폭을 양측 가벤트(3) 사이 순간격보다 좁게 형성하되, 트러스 주구(5b)의 하단 내측에 브래킷(56)을 구비하여 바닥지지틀(5a)과 접합할 수 있다. Therefore, the width of the floor support frame (5a) is formed to be narrower than the instantaneous gap between the two side vents (3), and a bracket 56 is provided on the inside of the lower end of the truss main hole (5b) to connect to the floor support frame (5a). You can.

상기 브래킷(56)은 바닥지지틀(5a)의 가로보(51) 단부와 볼트 접합 등에 의해 접합 가능하다.The bracket 56 can be joined to the end of the crossbeam 51 of the floor support frame 5a by bolting or the like.

도 5에 도시된 바와 같이, 상기 트러스 주구(5b)의 부재 단면을 최소화하여 경량화하고 강재량을 절감하기 위해 트러스 주구(5b)의 하현재(54)에 길이 방향으로 긴장재(57)가 구비될 수 있다.As shown in FIG. 5, in order to minimize the member cross-section of the truss main port 5b to reduce weight and reduce the amount of steel, a tension member 57 will be provided in the longitudinal direction on the lower chord 54 of the truss main port 5b. You can.

도 16, 도 17 등에 도시된 바와 같이, 상기 (b) 단계에서, 상기 각 가이드레일부(2)의 상부에 설치되는 이송대차(4)는 각각 한 쌍으로 구비되어, 상기 한 쌍의 이송대차(4)의 상단을 링크빔(40)으로 연결하며, 상기 바닥지지틀(5a)은 링크빔(40)의 상면에 거치될 수 있다. As shown in FIGS. 16, 17, etc., in step (b), the transfer trolleys 4 installed on the upper part of each guide rail part 2 are provided in pairs, and the pair of transfer trolleys The upper end of (4) is connected to the link beam 40, and the floor support frame 5a can be mounted on the upper surface of the link beam 40.

상기 바닥지지틀(5a)의 거치 및 횡이동 시 안전성을 확보하기 위해 가이드레일부(2)의 상부에 구비되는 이송대차(4)는 서로 이격된 한 쌍이 구비될 수 있다.In order to ensure safety when mounting and lateral movement of the floor support frame 5a, a pair of transport carts 4 provided on the upper part of the guide rail portion 2 may be provided as a pair spaced apart from each other.

이 경우 상기 바닥지지틀(5a)을 이송대차(4)의 상부에 안정적으로 거치하고, 한 쌍의 이송대차(4)의 횡방향 이동 시 이송대차(4)가 일체로 이동하도록 한 쌍의 이송대차(4) 상부를 링크빔(40)으로 연결할 수 있다.In this case, the floor support frame (5a) is stably mounted on the upper part of the transfer cart (4), and a pair of transfer carts (4) are moved so that the transfer carts (4) move as one when the pair of transport carts (4) move in the lateral direction. The upper part of the bogie (4) can be connected to the link beam (40).

상기 링크빔(40)은 바닥지지틀(5a)의 안정적인 지지를 위해 바닥지지틀(5a)의 폭보다 길게 형성하는 것이 바람직하다.The link beam 40 is preferably formed to be longer than the width of the floor support frame 5a in order to stably support the floor support frame 5a.

1: 교량 100: 철도 시설물
11: 하부구조 12: 상부구조
2: 가이드레일부 21: 레일빔
3: 가벤트 4: 이송대차
40: 링크빔 5: 가설 하로 트러스
5a: 바닥지지틀 50a: 연장바닥틀
5b: 트러스 주구 51: 가로보
52: 세로보 53: 상현재
54: 하현재 55: 사재
56: 브래킷 57: 긴장재
F: 기초
1: Bridge 100: Railway facility
11: Substructure 12: Superstructure
2: Guide rail part 21: Rail beam
3: Gavent 4: Transfer truck
40: Link beam 5: Temporary halo truss
5a: floor support frame 50a: extended floor frame
5b: Truss main body 51: Crossbeam
52: stringer 53: upper current
54: Ha Hyeon-jae 55: Sajae
56: bracket 57: tension material
F: Basic

Claims (6)

교축 방향으로 서로 이격되도록 설치된 한 쌍의 교량 하부구조(11) 상부에 상부구조(12)를 설치하기 위한 것으로,
(a) 상기 각 교량 하부구조(11)의 일측에 가벤트(3)를 설치하는 한편, 상기 교량 하부구조(11)의 내측에 교폭 방향으로 가로지르는 한 쌍의 가이드레일부(2)를 교축 방향으로 서로 이격되도록 설치하고, 각 가이드레일부(2)의 상부에 이송대차(4)를 설치하는 단계;
(b) 바닥지지틀(5a)과 상현재(53), 하현재(54) 및 상기 상현재(53)와 하현재(54)를 연결하는 사재(55)로 구성되어 각각 하단이 상기 바닥지지틀(5a)의 양측에 결합되는 한 쌍의 트러스 주구(5b)로 구성되는 가설 하로 트러스(5)를 상기 가벤트(3)의 상부에 거치하는 단계;
(c) 상기 가설 하로 트러스(5)의 바닥지지틀(5a) 상부에서 교량 상부구조(12)를 시공하는 단계;
(d) 상기 트러스 주구(5b)를 바닥지지틀(5a)에서 해체하여 제거하는 단계;
(e) 상기 바닥지지틀(5a)이 이송대차(4)의 상부에 거치된 상태에서 이송대차(4)를 교량 상부구조(12) 외측으로 이동시킨 후 바닥지지틀(5a)을 제거하는 단계; 및
(f) 상기 가벤트(3)를 제거하는 단계; 로 구성되되,
상기 (b) 단계에서, 상기 각 가이드레일부(2)의 상부에 설치되는 이송대차(4)는 각각 한 쌍으로 구비되어, 상기 한 쌍의 이송대차(4)의 상단을 링크빔(40)으로 연결하며, 상기 바닥지지틀(5a)은 링크빔(40)의 상면에 거치되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법.
It is intended to install the superstructure (12) on top of a pair of bridge substructures (11) installed to be spaced apart from each other in the bridge direction.
(a) A temporary vent (3) is installed on one side of each bridge substructure (11), and a pair of guide rail parts (2) crossing in the bridge width direction are installed on the inside of the bridge substructure (11). Installing them to be spaced apart from each other in each direction and installing a transfer cart (4) on the upper part of each guide rail part (2);
(b) It consists of a floor support frame (5a), an upper chord (53), a lower chord (54), and a stay member (55) connecting the upper chord (53) and the lower chord (54), the lower ends of each of which support the floor. Mounting a temporary truss (5) consisting of a pair of truss main holes (5b) coupled to both sides of the frame (5a) on the upper part of the gable (3);
(c) constructing a bridge superstructure (12) on the upper part of the floor support frame (5a) of the temporary lower truss (5);
(d) dismantling and removing the truss main hole (5b) from the floor support frame (5a);
(e) moving the transfer truck (4) to the outside of the bridge superstructure (12) with the floor support frame (5a) mounted on the upper part of the transfer truck (4) and then removing the floor support frame (5a) ; and
(f) removing the vent (3); It consists of,
In step (b), the transfer trolleys 4 installed on the upper part of each guide rail part 2 are provided in pairs, and the upper end of the pair of transfer trolleys 4 is connected to the link beam 40. A bridge superstructure installation method using a temporary lower truss, characterized in that the floor support frame (5a) is mounted on the upper surface of the link beam (40).
삭제delete 제1항에서,
상기 (b) 단계에서, 상기 바닥지지틀(5a)을 이송대차(4)의 상부에 거치시킨 후 상기 트러스 주구(5b)를 가벤트(3)의 상부에 거치시킨 상태에서 바닥지지틀(5a)의 양측에 결합하여 가설 하로 트러스(5)가 조립되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법.
In paragraph 1:
In step (b), the floor support frame (5a) is mounted on the upper part of the transfer cart (4), and then the truss main hole (5b) is mounted on the upper part of the gar vent (3), and then the floor support frame (5a) ) A method of installing a bridge superstructure using a temporary lower truss, characterized in that the temporary lower truss (5) is assembled by joining both sides of the temporary lower truss.
제3항에서,
상기 이송대차(4)는 높이 조절 가능하게 구성되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법.
In paragraph 3,
A method of installing a bridge superstructure using a temporary truss, characterized in that the transfer cart (4) is configured to be height adjustable.
제3항에서,
상기 트러스 주구(5b)의 하현재(54) 내측에는 바닥지지틀(5a)의 단부에 결합되는 복수의 브래킷(56)이 구비되는 것을 특징으로 하는 가설 하로 트러스를 이용한 교량 상부구조 설치 방법.
In paragraph 3,
A method of installing a bridge superstructure using a temporary lower truss, characterized in that a plurality of brackets (56) coupled to the end of the floor support frame (5a) are provided inside the lower chord (54) of the truss main port (5b).
삭제delete
KR1020230017508A 2023-02-09 2023-02-09 Installation method of bridge superstructure using temporary through truss KR102584444B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230017508A KR102584444B1 (en) 2023-02-09 2023-02-09 Installation method of bridge superstructure using temporary through truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020230017508A KR102584444B1 (en) 2023-02-09 2023-02-09 Installation method of bridge superstructure using temporary through truss

Publications (1)

Publication Number Publication Date
KR102584444B1 true KR102584444B1 (en) 2023-10-04

Family

ID=88290103

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020230017508A KR102584444B1 (en) 2023-02-09 2023-02-09 Installation method of bridge superstructure using temporary through truss

Country Status (1)

Country Link
KR (1) KR102584444B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100634848B1 (en) * 2005-04-27 2006-10-19 주식회사 벤트코리아 Bridge construction method using main girder launching system with temporary scaffolding
KR100924277B1 (en) 2007-11-15 2009-10-30 주식회사 대용이엔씨 Temporary bridge construction method using slab penetrating columns
KR101077092B1 (en) * 2010-10-29 2011-10-26 주식회사 장헌산업 Girder installation method using trolly without closing nor detouring existing road

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100634848B1 (en) * 2005-04-27 2006-10-19 주식회사 벤트코리아 Bridge construction method using main girder launching system with temporary scaffolding
KR100924277B1 (en) 2007-11-15 2009-10-30 주식회사 대용이엔씨 Temporary bridge construction method using slab penetrating columns
KR101077092B1 (en) * 2010-10-29 2011-10-26 주식회사 장헌산업 Girder installation method using trolly without closing nor detouring existing road

Similar Documents

Publication Publication Date Title
US20220333320A1 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
US4301565A (en) Method and system for the removal and replacement of a bridge
CN111424570A (en) Assembly type trolley for box culvert construction and construction method thereof
CN112609912B (en) Construction method for newly building canopy in overhead operation subway station
CN112727132B (en) Method for dismantling existing canopy of overhead operation subway station
KR100692952B1 (en) Railroad crane and method for carrying out replacement of an upper structure of a railway bridge utilizing the same
CN114808747A (en) Multifunctional bridge girder erection machine and bridge girder erection construction method
CN110158486B (en) Bridge girder erection machine for erecting spliced wide beams and construction method
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
WO2022142193A1 (en) Construction method for large-span thin-wall concrete sound barrier pouring trolley
CN111021415A (en) Construction structure and method for transition beam of railway underpass type frame bridge
CN214005379U (en) Prefabricated part for expanding existing elevated operation subway station platform
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
KR102584444B1 (en) Installation method of bridge superstructure using temporary through truss
JP3991067B1 (en) Temporary bridge between railway platforms
CN116427283A (en) Construction method for erecting small-radius bridge precast beam in mountain area
CN112610244B (en) Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof
CN212316712U (en) Box culvert construction is with assembled platform truck
KR100907141B1 (en) Mobile crane installation structure and method for replacing an upper structure of a railway bridge using the same
KR102557944B1 (en) Demolition method of bridge superstructure using temporary through truss
JP6630260B2 (en) Temporary assembly bridge and floor slab replacement method
CN212714587U (en) Equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN203411914U (en) Segment supporting and locating system structure
CN217499962U (en) Multifunctional bridge girder erection machine

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant