KR102477113B1 - Temporary scaffolding assembly for construction site - Google Patents
Temporary scaffolding assembly for construction site Download PDFInfo
- Publication number
- KR102477113B1 KR102477113B1 KR1020210188396A KR20210188396A KR102477113B1 KR 102477113 B1 KR102477113 B1 KR 102477113B1 KR 1020210188396 A KR1020210188396 A KR 1020210188396A KR 20210188396 A KR20210188396 A KR 20210188396A KR 102477113 B1 KR102477113 B1 KR 102477113B1
- Authority
- KR
- South Korea
- Prior art keywords
- frame
- temporary
- vertical
- fixing means
- frames
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 22
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 19
- 239000010959 steel Substances 0.000 claims abstract description 19
- 238000003825 pressing Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 description 6
- 238000004132 cross linking Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000000295 complement effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/24—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/045—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on profiles, e.g. I or H profiles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/08—Scaffold boards or planks
Abstract
Description
본 발명은 철골구조물에 직접적인 체결 없이 손쉽게 설치 및 해체가 가능한 현장 시공 가설발판 조립체에 관한 것으로, 보다 상세하게는 발판부를 설치하기 앞서 가설되는 가설프레임을 1인(人) 현장 시공이 가능하도록 고정수단의 조임 없이 철골구조물 매달린 상태로 임시 걸쳐지도록 한 후, 고정수단을 통해 가설프레임을 설치할 수 있도록 한 현장 시공 가설발판 조립체에 관한 것이다.The present invention relates to a temporary scaffolding assembly for on-site construction that can be easily installed and dismantled without direct fastening to a steel structure, and more particularly, a fixing means for enabling one-person on-site construction of a temporary frame to be constructed prior to installing a scaffolding unit. It relates to an on-site construction temporary scaffolding assembly that allows a temporary frame to be installed through a fixing means after temporarily hanging a steel structure in a suspended state without tightening.
일반적으로 철골구조물의 외벽 공사에서는 수직빔(H빔)에 근접되게 가설 발판을 설치한다. In general, in the exterior wall construction of a steel structure, a temporary scaffold is installed in close proximity to a vertical beam (H beam).
특히 이러한 임시 가설 발판은 수직빔의 손상을 피하기 위해 원형의 파이프를 격자형태로 설치하게 되며, 이러한 파이프에 발판플레이트를 결합시켜 임시 가설 발판을 설치하였다.In particular, these temporary temporary scaffolds are installed in a grid form of circular pipes to avoid damage to vertical beams, and temporary temporary scaffolds are installed by combining scaffolding plates with these pipes.
이와 같은 가설 발판으로, 통상 건축용 비계 조립구조(대한민국 등록실용 제20-0323788호)가 있는데, 이러한 종래 기술은 현장에서 작업자에 의해 용접과 클램프와 같은 방법으로 제작됨에 따라 많은 자재가 필요하고, 인건비와 시공이 길어지는 문제점이 발생된다.As such a temporary scaffolding, there is usually a scaffolding assembly structure for construction (Republic of Korea Registration Office No. 20-0323788). This prior art requires a lot of materials and labor costs as it is produced by methods such as welding and clamping by workers in the field. and the problem of prolonged construction occurs.
또한 종래의 기술은 설치 뿐만 아니라 분해가 어렵고, 공사구간의 높이를 조절할 경우, 일일이 파이프 자재를 덧대어 재조립해야 해야 하는 문제점이 있었다.In addition, the conventional technology has a problem in that it is difficult to disassemble as well as installation, and when adjusting the height of the construction section, it is necessary to reassemble by attaching pipe materials one by one.
본 발명은 상기와 같은 문제점을 감안하여 안출된 것으로, 본 발명의 제1목적은, 걸림프레임을 통해 가설프레임을 철골구조물 중 수직빔을 가로질러 연결되는 수평빔에 임시 걸쳐지도록 1인 현장 시공이 가능한 현장 시공이 용이한 가설 발판 조립체를 제공하는데 있다.The present invention has been devised in view of the above problems, and the first object of the present invention is a one-person on-site construction so that the temporary frame through the hanging frame is temporarily hung over the horizontal beam connected across the vertical beam of the steel structure. It is to provide a temporary scaffolding assembly that is easy to construct on-site as possible.
본 발명의 제2목적은, 지지프레임을 수직빔에 고정하는 고정수단의 결속을 느슨하게 된다 하더라도, 걸림프레임을 통해 가설프레임이 낙하되지 않아 안전사고를 방지할 수 있도록 한 현장 시공이 용이한 가설 발판 조립체를 제공하는데 있다.A second object of the present invention is a temporary scaffold that is easy to construct on site so that even if the binding of the fixing means for fixing the support frame to the vertical beam is loosened, the temporary frame does not fall through the hanging frame to prevent safety accidents. to provide an assembly.
본 발명의 제3목적은, 가설프레임과, 가교부와, 발판부로만 이루어져 있어 구조가 매우 간단하고 시공이 용이한 현장 시공이 용이한 가설 발판 조립체를 제공하는데 있다.A third object of the present invention is to provide a temporary scaffold assembly having a very simple structure and easy on-site construction because it consists of only a temporary frame, a bridge part, and a scaffolding part.
상기한 바와 같은 목적을 달성하기 위한 특징에 따르면, 제1발명은, 현장 시공 가설 발판조립체에 관한 것으로, 이를 위해 철골구조물 중 지면에 일정간격을 두고 설치된 다수의 수직빔에 가설되는 가설프레임;과, 상기 각 수직빔에 가설된 가설프레임을 수직빔에 고정하는 다수의 고정수단;과, 상기 각 가설프레임을 상호 간 연결하기 위해 상기 가설프레임을 가로질러 설치되는 가교부; 및 상기 가교부의 상부에 거치되는 발판부;를 포함하여 이루어지되, 상기 가설프레임은 1인 현장 시공이 용이하도록 고정수단의 조임 없이 철골구조물 중 수직빔을 가로질러 연결되는 수평빔에 임시 걸쳐지도록 걸림프레임을 갖는 것을 특징으로 한다.According to the characteristics for achieving the above object, the first invention relates to a field construction temporary scaffolding assembly, for which a temporary frame is constructed on a plurality of vertical beams installed at regular intervals on the ground among steel structures; and A plurality of fixing means for fixing the temporary frame hypothesized to each vertical beam to the vertical beam; and a bridging unit installed across the temporary frame to connect each of the temporary frames to each other; And a scaffolding portion mounted on the upper portion of the bridge portion, wherein the temporary frame is temporarily caught on a horizontal beam connected across a vertical beam of a steel structure without tightening a fixing means so that one-person on-site construction is easy. It is characterized by having a frame.
제2발명은, 제1발명에서, 상기 가설프레임은 난간 핸드레일이 연결되는 수직프레임과, 상기 수직프레임의 하부에 수평 연결되고 수직빔의 전면에 2점 가설되는 한쌍의 지지프레임으로 이루어지되, 상기 걸림프레임은 상기 수직프레임의 상부에 연결되는 수평프레임을 매개로 분기되어 상기 철골구조물 중 상기 각 수직빔을 가로질러 연결되는 수평빔에 타면에 2점 가설되는 것을 특징으로 한다.In the second invention, in the first invention, the temporary frame is composed of a vertical frame to which a handrail is connected, and a pair of support frames connected horizontally to the lower part of the vertical frame and constructed at two points in front of the vertical beam, The hanging frame is branched via a horizontal frame connected to the upper portion of the vertical frame, characterized in that two points are hypothesized on the other side of the horizontal beam connected across each vertical beam of the steel frame structure.
제3발명은, 제1발명에서, 상기 각 지지프레임은 고정수단을 연결하기 위해 수직방향으로 연결되는 제1프레임플랜지를 더 포함하고, 상기 각 걸림프레임은 고정수단을 연결하기 위해 수직방향으로 연결되는 제2프레임플랜지를 더 포함하는 것을 특징으로 한다.In the third invention, in the first invention, each support frame further comprises a first frame flange connected in the vertical direction to connect the fixing means, and each locking frame is connected in the vertical direction to connect the fixing means. It is characterized in that it further comprises a second frame flange.
제4발명은, 제1발명에서, 상기 고정수단은 연결된 손잡이의 회전방향에 따라 진퇴될 수 있도록 상기 제1,2프레임플랜지에 나선 결합되는 조임볼트(21)와, 상기 조임볼트의 단부에 고정되어 수직빔 또는 수평빔에 가압 고정되는 조임접시로 구성되는 것을 특징으로 한다. In the fourth invention, in the first invention, the fixing means is fixed to the tightening
본 발명의 현장 시공이 용이한 가설 발판 조립체에 따르면, 가설프레임과, 가교부와, 발판부로만 이루어져 있어 구조가 매우 간단하고 시공이 용이한 효과가 있다.According to the temporary scaffolding assembly, which is easy to construct on site, of the present invention, the structure is very simple and the construction is easy because it consists of only the temporary frame, the bridge part, and the scaffolding part.
또한 지지프레임을 수직빔에 고정하는 고정수단의 결속을 느슨하게 된다 하더라도, 걸림프레임을 통해 가설프레임이 낙하되지 않아 안전사고를 방지할 수 있는 효과가 있다.In addition, even if the binding of the fixing means for fixing the support frame to the vertical beam is loosened, the temporary frame does not fall through the hanging frame, thereby preventing safety accidents.
또한 걸림프레임을 통해 가설프레임을 철골구조물 중 수직빔을 가로질러 연결되는 수평빔에 임시 걸쳐지도록 1인 현장 시공이 가능한 효과가 있다.In addition, there is an effect that one-person on-site construction is possible so that the temporary frame is temporarily strung on the horizontal beam connected across the vertical beam of the steel frame through the hanging frame.
도 1은 본 발명에 따른 현장 시공이 용이한 가설 발판 조립체의 사시도,
도 2는 도 1에서 발췌된 가설프레임을 나타내는 사시도,
도 3은 수직빔에 가설된 가설프레임의 나타내는 사시도,
도 4는 도 3의 측면도,
도 5는 도 4에서 수평프레임에 걸쳐진 가설프레임을 나타내는 개념도,
도 6은 가설프레임에 가교부의 설치 상태를 나타내는 사시도,
도 7은 도 1에서 발췌된 발판부를 나타내는 사시도,1 is a perspective view of a temporary scaffolding assembly that is easy to construct on-site according to the present invention;
Figure 2 is a perspective view showing a hypothetical frame extracted from Figure 1;
3 is a perspective view showing a temporary frame hypothesized to a vertical beam;
Figure 4 is a side view of Figure 3;
5 is a conceptual diagram showing a hypothetical frame spanning a horizontal frame in FIG. 4;
6 is a perspective view showing the installation state of the bridge unit on the temporary frame;
Figure 7 is a perspective view showing the scaffolding extracted from Figure 1;
이하의 본 발명의 목적들, 다른 목적들, 특징들 및 이점들은 첨부된 도면과 관련된 이하의 바람직한 실시예들을 통해서 쉽게 이해될 것이다. 그러나 본 발명은 여기서 설명되는 실시예들에 한정되지 않고 다른 형태로 구체화될 수도 있다.Objects, other objects, features and advantages of the present invention below will be easily understood through the following preferred embodiments in conjunction with the accompanying drawings. However, the present invention is not limited to the embodiments described herein and may be embodied in other forms.
오히려, 여기서 소개되는 실시예들은 개시된 내용이 철저하고 완전해질 수 있도록 그리고 당업자에게 본 발명의 사상이 충분히 전달될 수 있도록 하기 위해 제공되는 것이다.Rather, the embodiments introduced herein are provided so that the disclosed content will be thorough and complete and the spirit of the present invention will be sufficiently conveyed to those skilled in the art.
여기에 설명되고 예시되는 실시예들은 그것의 상보적인 실시예들도 포함한다.Embodiments described and illustrated herein also include complementary embodiments thereof.
본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 '포함한다(comprise)' 및/또는 '포함하는(comprising)'은 언급된 구성요소는 하나 이상의 다른 구성요소의 존재 또는 추가를 배제하지 않는다.In this specification, singular forms also include plural forms unless specifically stated otherwise in a phrase. The terms 'comprise' and/or 'comprising' used in the specification do not exclude the presence or addition of one or more other elements.
이하, 도면을 참조하여 본 발명을 상세히 설명하도록 한다. 아래의 특정 실시예들을 기술하는데 있어서, 여러가지의 특정적인 내용들은 발명을 더 구체적으로 설명하고 이해를 돕기 위해 작성되었다. 하지만 본 발명을 이해할 수 있을 정도로 이 분야의 지식을 갖고 있는 독자는 이러한 여러 가지의 특정적인 내용들이 없어도 사용될수 있다는 것을 인지할 수 있다. 어떤 경우에는, 발명을 기술하는 데 있어서 흔히 알려졌으면서 발명과 크게 관련 없는 부분들은 본 발명을 설명하는 데 있어 혼돈을 막기 위해 기술하지 않음을 미리 언급해 둔다.Hereinafter, the present invention will be described in detail with reference to the drawings. In describing the specific embodiments below, various specific details have been prepared to more specifically describe the invention and aid understanding. However, readers who have knowledge in this field to the extent that they can understand the present invention can recognize that it can be used without these various specific details. In some cases, it is mentioned in advance that parts that are commonly known in describing the invention and are not greatly related to the invention are not described in order to prevent confusion in describing the present invention.
이하에서는 본 발명에 따른 현장 시공이 용이한 가설 발판 조립체에 관하여 첨부되어진 도면과 함께 더불어 상세히 설명하기로 한다.Hereinafter, it will be described in detail in conjunction with the accompanying drawings with respect to the temporary scaffolding assembly, which is easy to construct on-site according to the present invention.
도 1은 본 발명에 따른 현장 시공이 용이한 가설 발판 조립체의 사시도이고, 도 2는 도 1에서 발췌된 가설프레임을 나타내는 사시도이고, 도 3은 수직빔에 가설된 가설프레임의 나타내는 사시도이고, 도 4는 도 3의 측면도이고, 도 5는 도 4에서 수평프레임에 걸쳐진 가설프레임을 나타내는 개념도이고, 도 6은 가설프레임에 가교부의 설치 상태를 나타내는 사시도이고, 도 7은 도 1에서 발췌된 발판부를 나타내는 사시도이다.1 is a perspective view of a temporary scaffolding assembly that is easy to construct on site according to the present invention, FIG. 2 is a perspective view showing a temporary frame extracted from FIG. 1, and FIG. 3 is a perspective view showing a temporary frame constructed on a vertical beam. 4 is a side view of FIG. 3, FIG. 5 is a conceptual diagram showing a temporary frame spanning a horizontal frame in FIG. 4, FIG. 6 is a perspective view showing the installation state of a bridge unit on a temporary frame, and FIG. 7 is a scaffolding portion extracted from FIG. It is a perspective view that represents
도 1 내지 도 7에 도시된 바와 같이, 본 발명은 발판부를 설치하기 앞서 가설되는 가설프레임을 1인(人) 현장 시공이 가능하도록 고정수단의 조임 없이 철골구조물 매달린 상태로 임시 걸쳐지도록 한 후, 고정수단을 통해 가설프레임을 손쉽게 설치할 수 있도록 한 현장 시공 가설발판 조립체(100)에 관한 것이다.As shown in FIGS. 1 to 7, the present invention temporarily hangs the temporary frame in a hanging state without tightening the fixing means so that the temporary frame to be constructed prior to installing the scaffolding portion can be constructed by one person, It relates to a field construction
이러한 본 발명의 현장 시공이 용이한 가설 발판 조립체(100)는 크게 3부분으로 구성되는데, 이는 가설프레임(10)과, 가교부(30) 및 발판부(40)로 구성된다. The
상기 가설프레임(10)은 철골구조물 중 지면에 일정간격을 두고 설치된 다수의 수직빔(210)에 가설되는 구조이다.The
이러한 상기 가설프레임(10)은 1인 현장 시공이 용이하도록 고정수단(20)의 조임 없이 철골구조물 중 수직빔(210)을 가로질러 연결되는 수평빔(220)에 임시 걸쳐지도록 걸림프레임(14)을 갖는 구조이다.The
보다 상세하게는 상기 가설프레임(10)은 난간 핸드레일(11a)이 연결되는 수직프레임과, 상기 수직프레임(11)의 하부에 수평 연결되고 수직빔(210)의 전면에 2점 지지되는 한쌍의 지지프레임(12)으로 이루어진다.More specifically, the
여기서 지지프레임(12)은 상하로 이격되게 한쌍이 설치되는 것으로, 상부에 배치되는 지지프레임(12)은 수직프레임(11)의 하부에 연결되어 발판부(40)의 설치 공간을 확보하고, 더불어 수직빔(210)에 1점 지지된다.Here, a pair of
그리고 하부에 배치된 지지프레임(12)은 보강프레임(13)을 매개로 상부에 배치된 지지프레임(12)과 연결되고, 수직빔(210)에 2점 지지되어 보다 안정적으로 가설프레임(10)을 가설할 수 있는 구조를 마련한다.In addition, the
그리고 상기 걸림프레임(14)은 상기 수직프레임(11)의 상부에 연결되는 수평프레임(11b)을 매개로 분기되는 구조이다.In addition, the hanging
이러한 상기 걸림프레임(14)은 수직빔(210)의 간섭을 피할 수 있도록 상기 수직빔(210)을 사이에 두고 분기된 구조로, 상기 철골구조물 중 상기 각 수직빔(210)을 가로질러 연결되는 수평빔(220)에 타면에 2점 지지될 수 있도록 기능한다.The hanging
이 때 상기 각 지지프레임(12)은 수직빔(210)에 지지될 수 있도록 고정수단(20)을 연결하기 위해 수직방향으로 연결되는 제1프레임플랜지(121)를 더 포함한다.At this time, each
또한 상기 각 걸림프레임(14) 역시 수평빔(220)에 지지될 수 있도록 고정수단(20)을 연결하기 위해 수직방향으로 연결되는 제2프레임플랜지(141)를 더 포함하는 구성이다.In addition, each of the
아울러 상기 고정수단(20)은 연결된 손잡이(211)의 회전방향에 따라 진퇴될 수 있도록 상기 제1,2프레임플랜지(121,141)에 나선결합되는 조임볼트(21)와, 상기 조임볼트(21)의 단부에 고정되어 수직빔(210) 또는 수평빔(220)에 가압 고정되는 조임접시(22)로 구성된다.In addition, the fixing means 20 includes a tightening
상술된 가설프레임(10)은 고정수단(20)을 통해 수직빔(210)과 수평빔(220)에 가설하기 앞서, 도 5와 같이, 상기 걸림프레임(14)의 제2프레임플랜지(141)에 나선 결합된 고정수단(20)이 수평빔(220)의 플랜지에 걸쳐지도록 하여 철골구조물에서 낙하됨이 없이 매달아 임시 설치할 수 있는 구조이다.The above-described
이 후 1인 설치자는 가설프레임(10)의 위치를 정위치 시킨 후, 제2프레임플랜지(141)에 결합된 조임볼트(21)를 수평빔(220)의 타면에 가압하여 고정하고, 연속적으로 제1프레임플랜지(121)의 조임볼트(21)를 수평빔(220)의 전면에 가압하여 설치할 수 있다.Thereafter, the one-person installer positions the
상기 가설프레임(10)의 지지프레임(12)에는 발판부(40)를 설치하기 위해 가교부(30)가 설치된다.A bridge part 30 is installed in the
이러한 상기 가교부(30)는 도 6과 같이, 지지프레임(12) 상부에 고정되는 제1가교파이프(31)와, 상기 각 제1가교파이프(31)을 가로질러 상기 각 제1가교파이프(31)의 양측 상부에 연결되는 제2가교파이프(32)로 구성된다.As shown in FIG. 6, the cross-linking portion 30 crosses the
이러한 상기 가교부(30)는 지지력을 확보할 수 있도록 원형의 파이프로 이루어질 수 있으며, 이외에 각형 파이프로도 구성할 수 있다.The bridging part 30 may be made of a circular pipe to secure bearing capacity, or may also be made of a prismatic pipe.
상기 발판부(40)는 도 7과 같이, 가교부(30)의 상부에 거치되는 것으로, 발판플레이트(41)와, 상기 발판플레이트(41)의 양측에 결합되는 걸림후크(H)로 구성된다.As shown in FIG. 7, the
이러한 상기 발판부(40)는 별도의 결속 없이 양단에 결합된 걸림후크(H)를 통해 가교부(30)인 제2가교파이프(32)에 거치시켜 손쉽게 분해 조립할 수 있는 구조이다.The
한편 상기 가설프레임(10)의 수직프레임(11)은 도 4에 도시된 바와 같이, 수직빔(210)에 가설된 상태에서 발판부(40)의 높이를 조절할 수 있도록 구성될 수 있다.Meanwhile, as shown in FIG. 4, the
이를 위해 상기 가설프레임(10)의 수직프레임(11)은 2개로 분리되고, 분리된 2개의 수직프레임(11)은 상호 간 삽입된 상태에서 고정핀(P)을 통해 고정된 상태로 구성될 수 있다.To this end, the
이하에서는 본 발명에 따른 현장 시공이 용이한 가설 발판 조립체의 시공방법에 관하여 간단히 설명하기로 한다.Hereinafter, a simple description will be given of the construction method of the temporary scaffolding assembly, which is easy to construct on site according to the present invention.
먼저 가설프레임(10) 중 걸림프레임(14)을 철골구조물인 수평빔(220)의 플랜지()에 걸쳐지도록 하여 낙하됨이 없이 매달아 임시 설치한다.First, the hanging
이 후 가설프레임(10)의 위치를 수직빔(210)의 전면에 정위치 시킨 후, 제2프레임플랜지(141)에 결합된 조임볼트(21)를 수평빔(220)의 타면에 가압하여 고정한다.After that, after setting the position of the
그리고 제1프레임플랜지(121)의 조임볼트(21)를 수평빔(220)의 전면에 가압하여 가설프레임(10)의 설치를 완료한다.Then, the installation of the
그리고 가설프레임(10)의 지지프레임(12) 상부에 가교부(30)를 고정한다.In addition, the bridge part 30 is fixed to the upper part of the
마지막으로 걸림후크(H)를 통해 가교부(30)에 발판부(40)을 거치시켜 시공을 완성한다.Finally, the construction is completed by placing the
본 발명의 현장 시공이 용이한 가설 발판 조립체는 하기와 같은 차별적인 특징을 갖는다.The temporary scaffolding assembly, which is easy to construct on site, of the present invention has the following distinctive features.
첫째: 걸림프레임을 통해 가설프레임을 철골구조물 중 수직빔을 가로질러 연결되는 수평빔에 임시 걸쳐지도록 1인 현장 시공이 가능한 특징이 있다.First: There is a feature that one-person on-site construction is possible so that the temporary frame is temporarily hung on the horizontal beam connected across the vertical beam of the steel structure through the hanging frame.
둘째; 지지프레임을 수직빔에 고정하는 고정수단의 결속을 느슨하게 된다 하더라도, 걸림프레임을 통해 가설프레임이 낙하되지 않아 안전사고를 방지할 수 있는 특징이 있다.second; Even if the binding of the fixing means for fixing the support frame to the vertical beam is loosened, the temporary frame does not fall through the locking frame, so there is a feature that can prevent safety accidents.
셋째: 가설프레임과, 가교부와, 발판부로만 이루어져 있어 구조가 매우 간단한 특징이 있다.Third: It consists of only temporary frames, bridges, and scaffoldings, so it has a very simple structure.
본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형 예들이 있을 수 있음을 이해하여야 한다.Since the embodiments described in this specification and the configurations shown in the drawings are only one of the most preferred embodiments of the present invention and do not represent all of the technical spirit of the present invention, various equivalents that can replace them at the time of this application It should be understood that there may be variations and examples.
10: 가설프레임 11: 수직프레임 11a: 핸드레일
11b: 수평프레임 12: 지지프레임
121: 제1프레임플랜지 13: 보강프레임
14: 걸림프레임 141: 제2프레임플랜지
20: 고정수단 21: 조임볼트 211: 손잡이
22: 조임접시
30: 가교부 31: 제1가교파이프 32: 제2가교파이프
40: 발판부 41: 발판플레이트 42: 걸림후크
100: 현장 시공이 용이한 가설 발판 조립체
210: 수직빔 220: 수평빔 P: 핀10: temporary frame 11:
11b: horizontal frame 12: support frame
121: first frame flange 13: reinforcing frame
14: hanging frame 141: second frame flange
20: fixing means 21: tightening bolt 211: handle
22: fastening plate
30: bridge part 31: first bridge pipe 32: second bridge pipe
40: scaffolding part 41: scaffolding plate 42: hanging hook
100: Temporary scaffolding assembly that is easy to construct on site
210: vertical beam 220: horizontal beam P: pin
Claims (4)
상기 각 수직빔(210)에 가설된 가설프레임(10)을 수직빔(210)에 고정하는 다수의 고정수단(20);
상기 각 가설프레임(10)을 상호 간 연결하기 위해 상기 가설프레임(10)을 가로질러 설치되는 가교부(30); 및
상기 가교부(30)의 상부에 거치되는 발판부(40);를 포함하여 이루어지되,
상기 가설프레임(10)은 1인 현장 시공이 용이하도록 고정수단(20)의 조임 없이 철골구조물 중 수직빔(210)을 가로질러 연결되는 수평빔(220)에 임시 걸쳐지도록 걸림프레임(14)으로 이루어지고,
상기 가설프레임(10)은 난간 핸드레일(11a)이 연결되는 수직프레임(11)과, 상기 수직프레임(11)의 하부에 수평 연결되고 수직빔(210)의 전면에 2점 가설되는 한쌍의 지지프레임(12)으로 이루어지되,
상기 걸림프레임(14)은 상기 수직프레임(11)의 상부에 연결되는 수평프레임(11b)을 매개로 분기되어 상기 철골구조물 중 상기 각 수직빔(210)을 가로질러 연결되는 수평빔(220)에 타면에 2점 가설되고,
상기 각 걸림프레임(14)은 고정수단(20)을 연결하기 위해 수직방향으로 연결되는 제2프레임플랜지(141)를 더 포함하는 것을 특징으로 하는 현장 시공이 용이한 가설 발판조립체.
A temporary frame 10 that is hypothesized to a plurality of vertical beams 210 installed at regular intervals on the ground among steel structures;
A plurality of fixing means 20 for fixing the temporary frame 10 hypothesized to each vertical beam 210 to the vertical beam 210;
A bridging part 30 installed across the temporary frames 10 to connect each of the temporary frames 10 to each other; and
It is made to include; scaffolding portion 40 mounted on the upper portion of the bridge portion 30,
The temporary frame 10 is a hanging frame 14 so that it is temporarily hung on the horizontal beam 220 connected across the vertical beam 210 of the steel structure without tightening the fixing means 20 so that one-person on-site construction is easy. done,
The temporary frame 10 is a vertical frame 11 to which the handrail handrail 11a is connected, and a pair of supports horizontally connected to the lower part of the vertical frame 11 and two points hypothesized to the front of the vertical beam 210. It consists of a frame 12,
The hanging frame 14 is branched through the horizontal frame 11b connected to the upper part of the vertical frame 11 to the horizontal beam 220 connected across each vertical beam 210 of the steel structure. Two points are installed on the batting surface,
Each of the hanging frames 14 further comprises a second frame flange 141 connected in the vertical direction to connect the fixing means 20.
상기 각 지지프레임(12)은 고정수단(20)을 연결하기 위해 수직방향으로 연결되는 제1프레임플랜지(121)를 더 포함하는 것을 특징으로 하는 현장 시공이 용이한 가설 발판조립체.
According to claim 1,
Each of the support frames 12 further comprises a first frame flange 121 connected in the vertical direction to connect the fixing means 20.
상기 고정수단(20)은 연결된 손잡이(211)의 회전방향에 따라 진퇴될 수 있도록 상기 제1,2프레임플랜지(121,141)에 나선 결합되는 조임볼트(21)와, 상기 조임볼트(21)의 단부에 고정되어 수직빔(210) 또는 수평빔(220)에 가압 고정되는 조임접시(22)로 구성되는 것을 특징으로 하는 현장 시공이 용이한 가설 발판조립체. According to claim 1 or 3,
The fixing means 20 includes a tightening bolt 21 spirally coupled to the first and second frame flanges 121 and 141 so that the handle 211 can move forward and backward according to the rotation direction of the handle 211, and an end of the tightening bolt 21 A temporary scaffolding assembly that is easy to construct on site, characterized in that it consists of a tightening plate 22 fixed to the vertical beam 210 or the horizontal beam 220 by pressing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210188396A KR102477113B1 (en) | 2021-12-27 | 2021-12-27 | Temporary scaffolding assembly for construction site |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210188396A KR102477113B1 (en) | 2021-12-27 | 2021-12-27 | Temporary scaffolding assembly for construction site |
Publications (1)
Publication Number | Publication Date |
---|---|
KR102477113B1 true KR102477113B1 (en) | 2022-12-13 |
Family
ID=84439137
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020210188396A KR102477113B1 (en) | 2021-12-27 | 2021-12-27 | Temporary scaffolding assembly for construction site |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102477113B1 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20000012050U (en) * | 1998-12-14 | 2000-07-05 | 최규두 | Builder's workbench |
KR200323788Y1 (en) | 2003-01-11 | 2003-08-19 | 주식회사 신영 | Assembly structures of scaffold for construction |
KR102180857B1 (en) * | 2020-08-07 | 2020-11-19 | 이규운 | A TEMPORARY GUARDRAIL ASSEMBLY FOR THE POSt |
-
2021
- 2021-12-27 KR KR1020210188396A patent/KR102477113B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20000012050U (en) * | 1998-12-14 | 2000-07-05 | 최규두 | Builder's workbench |
KR200323788Y1 (en) | 2003-01-11 | 2003-08-19 | 주식회사 신영 | Assembly structures of scaffold for construction |
KR102180857B1 (en) * | 2020-08-07 | 2020-11-19 | 이규운 | A TEMPORARY GUARDRAIL ASSEMBLY FOR THE POSt |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102180857B1 (en) | A TEMPORARY GUARDRAIL ASSEMBLY FOR THE POSt | |
JP2603178B2 (en) | Formwork equipment | |
GB2243863A (en) | Formwork | |
KR102477113B1 (en) | Temporary scaffolding assembly for construction site | |
US4462573A (en) | Support post for temporary guard-rail chains | |
US2916245A (en) | Adjustable scaffold bracket | |
KR200467252Y1 (en) | cage for exterior works of building | |
CN111593898A (en) | Adjustable turnover discharging platform and installation method | |
KR20020036198A (en) | A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same | |
KR200392341Y1 (en) | Fixing Device for Aerial Scaffolding | |
KR101707037B1 (en) | A structure for assembled system scaffold and erecting method thereof | |
KR20020049414A (en) | Inspection plate for a pier | |
KR200213539Y1 (en) | Frame of safety workbench | |
KR101880854B1 (en) | Construction method of the mold available again | |
JP2021075967A (en) | Suspended scaffolding | |
CN212773547U (en) | Adjustable turnover platform of unloading | |
CN214462700U (en) | Horizontal steel bar binding platform | |
JPH0754480A (en) | Prefabricated scaffolding and assembling and disassembling method thereof | |
CN218028577U (en) | Prefabricated staircase that adaptation degree is high | |
KR200495306Y1 (en) | Scaffold tread plate tightening device | |
CN113931354B (en) | Cantilever scaffold and curtain wall integrated structure and construction method | |
KR100260674B1 (en) | A net of safety styled for cable stayed bridge | |
KR102289940B1 (en) | A Study on the Hypothesis Tread Plates for Framed Construction | |
JP3075475U (en) | Scaffold for laying bridge pipelines | |
KR100760332B1 (en) | Temporary cantilever resources, construction method of structure using the same and dismantling method for the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |