KR102386500B1 - Plant pipe management system - Google Patents

Plant pipe management system Download PDF

Info

Publication number
KR102386500B1
KR102386500B1 KR1020200095159A KR20200095159A KR102386500B1 KR 102386500 B1 KR102386500 B1 KR 102386500B1 KR 1020200095159 A KR1020200095159 A KR 1020200095159A KR 20200095159 A KR20200095159 A KR 20200095159A KR 102386500 B1 KR102386500 B1 KR 102386500B1
Authority
KR
South Korea
Prior art keywords
information
module
construction
spool
management
Prior art date
Application number
KR1020200095159A
Other languages
Korean (ko)
Other versions
KR20220015094A (en
Inventor
최대진
Original Assignee
최대진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최대진 filed Critical 최대진
Priority to KR1020200095159A priority Critical patent/KR102386500B1/en
Publication of KR20220015094A publication Critical patent/KR20220015094A/en
Application granted granted Critical
Publication of KR102386500B1 publication Critical patent/KR102386500B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing

Abstract

본 발명은 관리의 효율화, 작업 능률의 극대화, 업무의 단순화를 실현할 수 있는 플랜트 배관 관리 시스템에 관한 것으로, 그 구성은, 해당 영역 내에 위치한 모든 배관에 대해서 관련 데이터베이스 정보를 저장하는 데이터베이스 시스템; 각 배관마다 설치되는 것으로, 각 스풀 또는 배관을 구성하는 부품의 위치정보를 생성하는 GPS 모듈과, 각 스풀의 조인트 위치 정보와 시공현황 정보 및 품질검사 상태 정보가 저장된 스풀정보저장모듈과, 상기 스풀정보저장모듈에 저장된 정보를 상기 데이터베이스 시스템으로 무선 전송하는 제어모듈로 구성된 스풀통신저장장치; 상기 스풀통신저장장치와 무선통신할 수 있는 무선 입/출력 모듈과, 마이크로 콘트롤러 유닛과, 무선통신모듈을 포함하고, 시스템접속권한통제모듈을 통하여 상기 데이터베이스 시스템 상에서 상기 스풀통신저장장치로 접근할 수 있는 권한이 부여된 경우, 모바일 웹(mobile web) 또는 안드로이드(android)/iOS 기반의 어플리케이션을 통해 배관 정보를 모니터링하거나 현장에서 최신 정보를 입력할 수 있도록 구비된 단말기; 및 상기 데이터베이스 시스템과 스풀통신저장장치 간에 무선통신이 가능하도록 구비된 신호중계기;를 포함하여 이루어진다.The present invention relates to a plant pipe management system capable of realizing management efficiency, maximization of work efficiency, and simplification of work, the configuration of which includes: a database system for storing related database information for all pipes located in a corresponding area; A GPS module that is installed for each pipe and generates position information of each spool or parts constituting the pipe, a spool information storage module that stores joint position information of each spool, construction status information, and quality inspection status information, and the spool a spool communication storage device comprising a control module for wirelessly transmitting information stored in the information storage module to the database system; It includes a wireless input/output module capable of wireless communication with the spool communication storage device, a microcontroller unit, and a wireless communication module, and can access the spool communication storage device on the database system through a system access permission control module a terminal equipped to monitor piping information through a mobile web or Android/iOS-based application or input the latest information in the field, if permission is granted; and a signal repeater provided to enable wireless communication between the database system and the spool communication storage device.

Description

플랜트 배관 관리 시스템{Plant pipe management system}Plant pipe management system

본 발명은 관리의 효율화, 작업 능률의 극대화, 업무의 단순화를 실현할 수 있는 플랜트 배관 관리 시스템에 관한 것으로, 보다 상세하게는 현장에서 발생하는 다수의 보고/검사/관리항목 등을 편리하게 관리할 수 있을 뿐만 아니라, 취득된 수많은 정보의 조합을 바탕으로 도출된 주요업무를 관리자가 직접 통제할 수 있고, 각 배관 스풀마다 장착된 스풀통신저장장치를 이용하여 실시간 위치 추적은 물론, 현장 내 적소의 위치에서 관련 자료를 취득하고, 또 작업 및 검사 진행현황을 직접 업데이트 할 수 있으며, 스풀통신저장장치와 단말기 간에 입출력 데이터를 모바일 웹 또는 안드로이드/iOS 운영체제 기반의 어플리케이션 형태로써 제공하는 플랜트 배관 관리 시스템에 관한 것이다.The present invention relates to a plant piping management system capable of realizing management efficiency, maximization of work efficiency, and simplification of work, and more particularly, it is possible to conveniently manage a number of reporting/inspection/management items occurring in the field. In addition, the manager can directly control the main tasks derived based on the combination of numerous acquired information, and real-time location tracking using the spool communication storage device mounted on each pipe spool, as well as the location of the right place in the field About the plant piping management system that can acquire related data from will be.

플랜트 공사는 한 국가의 기간산업을 건설하는 일로써, 산업 전반에 미치는 영향력이 지대하다. 이러한 플랜트 공사의 최근 트랜드 중에서 가장 중요한 것을 꼽자면 비약적인 기술발전으로 인한 프로젝트 규모의 대형화라고 할 수 있을 것이다.Plant construction is the construction of a country's key industry and has a great impact on the overall industry. Among these recent trends in plant construction, the most important thing can be said to be the enlargement of the project scale due to the rapid technological development.

프로젝트 규모의 대형화를 시공관리의 측면에서 보자면, 최근에는 어떤 하나의 프로젝트를 수행하기 위해서는 예전에 비해 수배 이상에 달하는 관리항목/정보를 통제하여야만 시공이 가능하다는 것이다. 그러나 예전에 비해 수배 이상에 달하는 관리항목/정보를 원활히 통제하기 위해서는 폭넓은 지식과 경험이 필히 요구되며, 단순히 인력만을 보충한다고해서 해결될 수 있는 사안이 아닐 뿐더러, 업무를 적합하게 처리할 수 있는 풍부한 경력을 보유한 인적자원조차 지극히 제한적이다는 문제점이 있다. 예컨대, 최근의 플랜트 프로젝트 시장에서는 예정된 공기와 원가를 충족시킨 사례를 찾아보기가 극히 어렵다. 이는 프로젝트 대형화 및 관리항목/정보의 대폭적인 증가와 결코 무관하지 않음을 시사한다.When looking at the enlargement of the project scale in terms of construction management, recently, in order to carry out any one project, it is necessary to control several times more management items/information than in the past before construction is possible. However, in order to smoothly control management items/information that is several times larger than in the past, extensive knowledge and experience are inevitably required. There is a problem that even human resources with abundant experience are extremely limited. For example, in the recent plant project market, it is extremely difficult to find examples of meeting scheduled time and cost. This suggests that it is not irrelevant to the large-scale project and a significant increase in management items/information.

이러한 상황에 대응하기 위하여 한국은 물론 세계유수의 EPC 건설사들은 ERP를 도입하고 있으며, 특히 배관공사에서는 프로그램화한 데이터베이스(이하, '배관 관리 시스템'이라 함)를 사용하는 등 폭증하는 관리항목/정보를 통제하고자 부단한 노력을 경주하여 왔다.In order to respond to this situation, not only Korea but also the world's leading EPC construction companies are introducing ERP, and in particular, in plumbing construction, programmatic databases (hereinafter referred to as 'pipe management system') are used, etc. It has been making strenuous efforts to control it.

그러나 배관 관리 시스템의 활용으로 배관공사의 효율성이 제고된 점은 분명하나, 현재까지 개발된 모든 배관 관리 시스템은 시공 및 품질관리의 현황관리 및 현황보고를 목적으로 개발된 한계가 있어, 배관 시공관리 및 품질관리 업무 자체에 대한 직접적인 기여는 매우 제한적이었다.However, although it is clear that the efficiency of plumbing construction has been improved by the use of the pipe management system, all pipe management systems developed so far have limitations in being developed for the purpose of managing the status of construction and quality control and reporting the current status. and direct contribution to the quality control work itself was very limited.

따라서, 종래의 배관 관리 시스템은 시공 및 검사 진행현황만을 제공할 뿐, 시공 및 품질관리자가 실질적으로 업무를 수행하기 위하여 필요한 정보를 제공하지 못하였던 관계로, 관리자는 시공/품질검사의 자원, 일정, 업무품질 및 원가를 통합적으로 관리할 수 없었고, 그 결과 아래와 같은 문제점이 발생하게 되었다.Therefore, the conventional pipe management system only provides the construction and inspection progress status, and since the construction and quality managers cannot provide the necessary information to actually perform their work, the manager can provide resources and schedules for construction/quality inspection However, it was not possible to manage work quality and cost in an integrated way, and as a result, the following problems occurred.

첫째, 제작된 스풀의 위치를 추적할 수 없어 분실이 잦았고, 정해진 위치에 제대로 설치되었는지 확인할 수 없었다.First, the location of the manufactured spool could not be tracked, so it was often lost, and it was impossible to check whether it was properly installed in the designated location.

둘째, 스풀 제작소에서 제작된 스풀이 비파괴시험공정 및 열처리공정이 시행되지 않은 상태에서 야적장이나 현장으로 이동되거나, 스풀 제작소에서 제작된 스풀이 최신도면에 의해 제작되었는지 확인되지 않은 상태에서 야적장이나 현장으로 이동되는 경우가 잦았다.Second, the spool manufactured at the spool manufacturing facility is moved to the yard or site without the non-destructive testing process and heat treatment process being performed, or the spool manufactured at the spool manufacturing facility is transferred to the yard or site without checking whether it is manufactured according to the latest drawings. moved frequently.

셋째, 스풀 제작소에서 제작된 스풀과 현장에 설치된 배관 라인이 최신도면에 의해 제작되거나 설치되지 않은 경우가 발생되기도 하였다.Third, there were cases in which the spool manufactured at the spool manufacturing plant and the piping line installed on the site were not manufactured or installed according to the latest drawings.

넷째, 스풀의 현장 설치 또는 검사시에 최신의 배관 관리 시스템상의 정보와 직접적으로 연계되지 않은 종이서류를 활용할 수 밖에 없어 매번 도면과 검사서류를 종이에 프린트하여 설치 현장까지 배포 내지는 휴대하여야 하였다. 따라서, 프린트된 도면과 검사서류가 최신 정보와 일치하지 않는 경우가 빈번하였고, 휴대가 불편함은 물론이고 분실의 위험성도 존재하였다.Fourth, when installing or inspecting the site of the spool, paper documents that are not directly linked to the latest information on the piping management system had to be used, so drawings and inspection documents had to be printed on paper every time and distributed or carried to the installation site. Therefore, the printed drawings and inspection documents frequently did not match the latest information, and there was a risk of loss as well as inconvenient to carry.

다섯째, 기존 배관 관리 시스템에서는 시공 및 품질검사의 현황정보만을 제공하므로, 시공 및 품질부서에서는 본연의 업무 추진을 위해선 수많은 별도의 정보를 추가로 수집하여 현황정보와 연계할 필요가 있는 바, 시공 및 품질관리부서에서는 배관 관리 시스템 외에 별도의 자체 배관공사/품질검사 정보를 보유해야만 하였으며, 이로 인해 각 부서간 배관 관리 시스템상의 정보가 불일치하여 유관부서간에 커뮤니케이션이 제대로 이루어지지 않거나, 프로젝트 진행에 있어서 혼란을 초래하는 경우가 많았다.Fifth, since the existing pipe management system provides only the status information of construction and quality inspection, the construction and quality department needs to collect a lot of additional information and link it with the current status information in order to carry out its original work. In addition to the pipe management system, the quality control department had to have its own plumbing work/quality inspection information. As a result, the information on the pipe management system between departments was inconsistent, so communication between related departments was not properly performed, or there was confusion in project progress. often resulted in

여섯째, 기존 배관 관리 시스템은 현재 시점에서의 시공 및 품질검사 현황정보만을 제공할 뿐, 시공 및 품질검사부서에서 실질적으로 필요한 정보인 작업가능물량과 작업불가물량에 대한 원인파악이 불가하였고, 작업가능물량 중 당일 작업지시를 내려야 하는 물량을 제대로 판별할 수 없었다.Sixth, the existing piping management system only provides information on the current status of construction and quality inspection, and it is impossible to determine the cause of the workable quantity and non-workable quantity, which are information practically needed by the construction and quality inspection department, and work is possible. It was not possible to properly determine the quantity that had to be given a work order on the same day.

한국 등록특허공보 제10-2001969호(상하수도 관로 매설 위치 확인 및 실시간 관리 시스템, 2019.07.15. 등록)Korean Patent Publication No. 10-2001969 (Fixing the location of water and sewage pipelines and real-time management system, registered on July 15, 2019) 일본 공개특허공보 제2012-180191호(플랜트 건설 지원방법 및 플랜트 건설 지원장치, 2012.09.02. 공개)Japanese Unexamined Patent Publication No. 2012-180191 (Plant Construction Support Method and Plant Construction Support Device, published on September 2, 2012) 한국 공개특허공보 제10-2013-0010067호(전자인식표시기를 이용한 지하시설물 관리시스템, 2013.01.25. 공개)Korean Unexamined Patent Publication No. 10-2013-0010067 (Underground facility management system using electronic recognition indicator, published on January 1, 2013)

본 발명은 상기한 바와 같은 기존 배관 관리 시스템의 문제점을 해결하기 위해 창작된 것으로, 본 발명의 목적은 각 시공/품질검사 단계별 작업가능물량정보(WORK-FRONT)와 작업가능물량정보를 토대로 한 작업/품질검사 지시서(WORK-ORDER)에 대한 정보 도출과, 이들 정보를 바탕으로 공사일정과 연계하며 분석할 수 있는 플랜트 배관 관리 시스템을 제공함에 있다.The present invention was created to solve the problems of the existing piping management system as described above, and an object of the present invention is to work based on workable quantity information (WORK-FRONT) and workable quantity information for each construction/quality inspection step. / It is to provide a plant piping management system that can be analyzed in connection with the construction schedule based on the derivation of information on the /Quality Inspection Order (WORK-ORDER) and based on this information.

본 발명의 다른 목적은, 시공현장에서 배관에 설치된 스풀통신저장장치와 단말기를 통하여 작업에 필요한 최신의 정보를 용이하게 취득하고, 또 종이서류를 구비하지 않고도 매 시공/품질검사 단계가 원활하게 진행될 수 있으며, 사무실에 설치된 배관 관리 시스템의 정보와 시공 현장에 설치된 스풀통신저장장치상의 정보가 상호 교류되도록 함으로써, 최신 정보가 실시간 업데이트되는 체계를 구축할 수 있는 플랜트 배관 관리 시스템을 제공함에 있다.Another object of the present invention is to easily obtain the latest information required for work through the spool communication storage device and terminal installed in the pipe at the construction site, and to smoothly perform each construction/quality inspection step without paper documents. It is to provide a plant piping management system that can build a system in which the latest information is updated in real time by allowing the information of the piping management system installed in the office to be exchanged with the information on the spool communication storage device installed at the construction site.

본 발명의 또 다른 목적은, 배관 관리 시스템의 정보와 스풀통신저장장치의 정보가 상호간 백업기능을 갖도록 시스템을 구현함으로써, 플랜트 배관 공사에서 시공 및 품질검사 업무에 대한 직접적인 업무효율 제고의 성과를 달성할 수 있고, 건설사로 하여금 주요공종인 배관 공사로 인해 야기되는 공기 및 원가에 대한 통제력 상실의 위험성을 최소화시킬 수 있는 플랜트 배관 관리 시스템을 제공함에 있다.Another object of the present invention is to achieve the performance of directly improving work efficiency for construction and quality inspection work in plant plumbing work by implementing a system so that the information of the pipe management system and the information of the spool communication storage device have a mutual backup function. It is to provide a plant piping management system that can minimize the risk of loss of control over air and cost caused by plumbing, which is a major type of construction, for construction companies.

상기한 목적을 달성하기 위한 본 발명의 플랜트 배관 관리 시스템은,Plant piping management system of the present invention for achieving the above object,

해당 영역 내에 위치한 모든 배관에 대해서 관련 데이터베이스 정보를 저장하는 데이터베이스 시스템(200);a database system 200 for storing related database information for all pipes located in the corresponding area;

각 배관마다 설치되는 것으로, 각 스풀 또는 배관을 구성하는 부품의 위치정보를 생성하는 GPS 모듈(420)과, 각 스풀의 조인트 위치 정보와 시공현황 정보 및 품질검사 상태 정보가 저장된 스풀정보저장모듈(430)과, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송하는 제어모듈(410)로 구성된 스풀통신저장장치(400);A GPS module 420 that is installed for each pipe and generates position information of each spool or parts constituting the pipe, and a spool information storage module that stores joint position information of each spool, construction status information, and quality inspection status information ( 430) and a spool communication storage device 400 comprising a control module 410 for wirelessly transmitting the information stored in the spool information storage module 430 to the database system 200;

상기 스풀통신저장장치(400)와 무선통신할 수 있는 무선 입/출력 모듈(513)과, 마이크로 콘트롤러 유닛(511)과, 무선통신모듈(512)을 포함하고, 시스템접속권한통제모듈(520)을 통하여 상기 데이터베이스 시스템(200) 상에서 상기 스풀통신저장장치(400)로 접근할 수 있는 권한이 부여된 경우, 모바일 웹(mobile web) 또는 안드로이드(android)/iOS 기반의 어플리케이션을 통해 배관 정보를 모니터링하거나 현장에서 최신 정보를 입력할 수 있도록 구비된 단말기(500); 및It includes a wireless input/output module 513 capable of wireless communication with the spool communication storage device 400 , a microcontroller unit 511 , and a wireless communication module 512 , and a system access right control module 520 . When access to the spool communication storage device 400 is granted on the database system 200 through the or a terminal 500 equipped to input the latest information in the field; and

상기 데이터베이스 시스템(200)과 스풀통신저장장치(400) 간에 무선통신이 가능하도록 구비된 신호중계기(300);를 포함하여 구성된다.and a signal repeater 300 provided to enable wireless communication between the database system 200 and the spool communication storage device 400 .

여기서, 상기 제어모듈(410)은 마이크로 콘트롤러 유닛(411)과, 무선통신모듈(412)과, 무선통신보안모듈(413)을 포함하여 구성되고, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송함과 아울러 갱신된 최신의 정보를 상기 제어모듈(410)에 의하여 실시간 및 자동으로 상기 데이터베이스 시스템(200)으로부터 무선으로 전송받는 구성으로 이루어질 수 있다.Here, the control module 410 is configured to include a microcontroller unit 411 , a wireless communication module 412 , and a wireless communication security module 413 , and stores information stored in the spool information storage module 430 . It may be configured to wirelessly transmit the latest information to the database system 200 in real time and automatically receive the updated information from the database system 200 wirelessly by the control module 410 .

본 발명에 따른 데이터베이스 시스템(200)은 메인서버와 보조서버로 구성된 서버부(210)와; 해당 배관공사를 포함한 전체 프로젝트와 관련된 정보를 저장 및 관리하는 프로젝트정보모듈(230)과; 상기 프로젝트정보모듈(230)에 저장된 정보를 바탕으로 실질적인 배관공사 시공 및 품질검사를 수행할 수 있도록 하는 배관관리메인모듈(240)과; 상기 배관관리메인모듈(240)을 시스템적으로 관리·운영하는 시스템운영 및 권한통제모듈(220)과; 상기 프로젝트정보모듈(230)과 배관관리메인모듈(240)을 상기 시스템운영 및 권한통제모듈(220)에 의해 해당 배관공사를 포함한 전체 프로젝트를 관리하는 시스템과 연계시키는 프로젝트통합관리모듈(250)과; 상기 데이터베이스 시스템(200)을 비롯하여 상기 신호중계기(300)와 스풀통신저장장치(400)와 전체 프로젝트를 관리하는 시스템에 구비된 신호통신장치와 무선으로 연결되는 무선통신모듈(260);을 포함하여 이루어진다.The database system 200 according to the present invention includes a server unit 210 comprising a main server and an auxiliary server; a project information module 230 for storing and managing information related to the entire project including the corresponding plumbing work; a plumbing management main module 240 capable of performing actual plumbing construction construction and quality inspection based on the information stored in the project information module 230; a system operation and authority control module 220 for systematically managing and operating the pipe management main module 240; The project information module 230 and the piping management main module 240 are linked with the system for managing the entire project including the corresponding piping construction by the system operation and authority control module 220 with a project integrated management module 250 and ; Including the database system 200, the signal repeater 300, the spool communication storage device 400, and a wireless communication module 260 wirelessly connected to the signal communication device provided in the system for managing the entire project. is done

여기서, 상기 배관관리메인모듈(240)은 설계상 자재(B/M)와 현장에서 실제 사용되어 소요된 자재정보를 자동링크, 자재비·간접비·기타경비정보를 활용하여 실행예산 및 원가를 도출함과 동시에 이를 모니터링하며, 타공사를 위한 견적정보를 제공하는 배관견적모듈(241)과; 배관 설계와 관련된 상세정보, 제원, B/M정보, 배관 코드를 생성하는 배관엔지니어링모듈(242)과; 배관 주자재의 발주와 조달을 시행 및 모니터링하는 배관조달모듈(243)과; 시공 현장에서의 배관 주자재입고관리 및 상기 배관조달모듈(243)의 업데이트, 시공 현장에서의 자재 불출관리, 현장구매자재에 대한 구매관리 및 상기 배관조달모듈(243)과의 시뮬레이션을 수행하는 배관현장자재관리모듈(244)과; 시공 현장에서 배관시공관리를 수행하기 위한 배관시공관리모듈(245)과; 시공 현장에서 배관품질검사를 수행하기 위한 배관품질관리모듈(246);을 포함한다.Here, the pipeline management main module 240 derives the execution budget and cost by using the automatic link between the design material (B/M) and the material information actually used and required in the field, and material cost, overhead cost, and other cost information. and a piping estimation module 241 that monitors it and provides estimation information for other construction projects; a piping engineering module 242 for generating detailed information, specifications, B/M information, and piping codes related to piping design; a pipe procurement module 243 for executing and monitoring the ordering and procurement of pipe main materials; A piping site that performs a simulation with the pipeline procurement module 243, management of stocking of main materials for piping at the construction site, update of the piping procurement module 243, management of material disbursement at the construction site, purchase management for on-site purchased materials, and the piping procurement module 243 a material management module 244 and; a pipe construction management module 245 for performing pipe construction management at the construction site; and a pipe quality control module 246 for performing a pipe quality inspection at the construction site.

상기 배관시공관리모듈(245)은 배관시공에 필요한 엔지니어링, 자재 및 품질요구조건에 대한 정보와 연계되어 기준시점에서의 시공현황 상세정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관시공현황정보모듈(245A)과; 배관시공에 필요한 인적자원 및 물적자원에 대한 상세내역, 인증/검사현황, 배치현황, 위치와 관련된 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관시공자원관리모듈(245B)과; 배관시공을 위한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/관리 인력 및 장비의 배정상 제한조건, 기타 작업 공도구 설치 및 배정현황, 입고 설치자재에 대한 배분현황, 선행공정 또는 유관공정에 의한 제한사항, 자재 및 도면/Engineering상 문제(Engineering Hold)로 인한 제한사항, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송, 및 출력할 수 있는 배관시공관리현장정보모듈(245C);을 포함할 수 있다.The pipe construction management module 245 can record, store, analyze, display, search, transmit and output detailed construction status information at a reference point in connection with information on engineering, materials, and quality requirements required for pipe construction. A pipe construction status information module (245A) and; Pipe construction resource management module (245B) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting information related to detailed details, certification/inspection status, arrangement status, and location of human and material resources required for pipe construction )class; Installation status of main scaffolding related to on-site conditions for plumbing construction, whether or not local scaffolding is needed and installation status, priority of work, restrictions on assignment of work/management personnel and equipment, etc. Work tool installation and allocation status, distribution status of incoming installation materials, restrictions due to preceding or related processes, restrictions due to material and drawings/Engineering Hold, restrictions due to comments from the original building/ordering company It may include; may include a;

이때, 상기 배관시공관리모듈(245)은 정보의 조합, 처리 및 분석을 통해 배관시공관리에 필요한 각종 현황자료/보고서와 각 시공단계별 preliminary work-front, 이후 시공부서의 확인을 거쳐 확정된 official work-front와 시공관리부서에서 설정한 조건에 따라 각 시공단계별, 즉 spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, reinstatement의 preliminary work order와 시공부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하는 기능을 수행한다.At this time, the pipe construction management module 245 receives various status data/reports necessary for pipe construction management through combination of information, processing and analysis, preliminary work-front for each construction stage, and official work confirmed after confirmation by the construction department. -According to the conditions set by the front and the construction management department, preliminary work orders for each construction stage, namely spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, and reinstatement, and the construction department confirm it It performs the functions of creating, displaying, retrieving, sending, printing and distributing an official work order.

상기 배관품질관리모듈(246)은 배관품질검사 수행을 위한 엔지니어링, 자재, 배관시공 및 품질요구조건의 정보와 연계되어 기준시점에서의 진척된 품질검사현황에 대한 상세한 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사현황모듈(246A)과; 품질검사 수행을 위해 필요한 인적자원 및 물적자원의 상세내역, 인증/검사현황, 배치현황, 위치정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사자원관리모듈(246B)과; 시공 현장에서 품질검사를 수행하기 위해 필요한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/검사 인력 및 배정상 제한조건, 작업 공도구 설치 및 배정현황, 타품질검사 또는 시공작업과의 간섭으로 인한 제한사항, 자재 및 도면/Engineering상 문제(Engineering Hold)로 인한 제한사항 판별, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사현장정보모듈(246C);을 포함할 수 있다.The pipe quality control module 246 records, stores, analyzes, and records detailed information on the progress of quality inspection at a reference point in connection with information of engineering, materials, pipe construction, and quality requirements for pipe quality inspection. a pipe quality inspection status module 246A capable of displaying, searching, transmitting and outputting; Pipe quality inspection resource management module (246B) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting detailed details of human and material resources necessary for quality inspection, certification/inspection status, arrangement status, and location information )class; Installation status of main scaffolding related to site conditions required to perform quality inspection at the construction site, whether or not local scaffolding is required and installation status, work priority, work/inspection manpower and assignment status Restriction conditions, work tool installation and assignment status, restrictions due to interference with other quality inspections or construction work, determination of restrictions due to material and drawings/Engineering Hold, restrictions due to comments from the original building/customer It may include; may include;

이때, 상기 배관품질관리모듈(246)은 정보의 조합, 처리 및 분석을 통해 배관품질검사관리에 필요한 각종 현황자료/보고서와 각 품질검사단계별 preliminary work-front, 이후 품질관리부서의 확인을 거쳐 확정된 official work-front와 품질관리부서에서 설정한 조건에 따라 승인한 품질검사계획(ITP: Inspection & Test Plan)에 따른 각 품질검사단계별, 즉 spool erection inspection, fit-up, inspection, welding inspection, heat treatment inspection, hydro-test(pneumatic) inspection, lay-up inspection, bolt tightening inspection, punch inspection, reinstatement의 preliminary work order와 품질관리부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하는 기능을 수행한다.At this time, the pipe quality control module 246 is confirmed through various status data/reports required for pipe quality inspection management through combination of information, processing and analysis, preliminary work-front for each quality inspection step, and then confirmed by the quality control department. According to the approved official work-front and the conditions set by the quality control department, each quality inspection step according to the ITP (Inspection & Test Plan), that is, spool erection inspection, fit-up, inspection, welding inspection, heat Create, display, search, transmit, print and perform preliminary work orders for treatment inspection, hydro-test (pneumatic) inspection, lay-up inspection, bolt tightening inspection, punch inspection, and reinstatement and official work orders confirmed by the quality control department It performs the distribution function.

한편, 상기 배관관리메인모듈(240)은 수집된 정보들을 기반으로 의사결정을 하기 위하여 요구되는 정보를 지능형 지식관리모델 및 알고리즘으로 구현할 수 있다.Meanwhile, the pipeline management main module 240 may implement information required to make a decision based on the collected information as an intelligent knowledge management model and algorithm.

본 발명에 따르면, 상기 스풀통신저장장치(400)에 구비된 GPS 모듈(420)은 스풀/배관부품 자체의 위치 정보를 추적하며 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로부터 요청된 신호를 수신받을 경우, 해당 정보를 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로 송출하고, 상기 스풀정보저장모듈(430)은 관련 도면, 시공작업과 관련된 정보 및 자료, 품질검사와 관련된 정보 및 자료를 저장하며, 상기 GPS 모듈(420)과 스풀정보저장모듈(430) 상의 정보와 자료는 상기 데이터베이스 시스템(200)과 교신하여 최신 정보들을 상호 교류하며 실시간으로 업데이트함은 물론, 현장 시공작업 및 품질검사를 위해서 상기 단말기(500)에 구비된 제어모듈(510)과 스풀통신저장장치(400)에 구비된 제어모듈(410)이 상호 교신하여 상기 스풀통신저장장치(400) 내에 저장된 정보를 열람, 검색 및 새롭게 진행되는 시공 진척상황과 품질검사 진척상황을 업데이트하는 구성으로 이루어질 수 있다.According to the present invention, the GPS module 420 provided in the spool communication storage device 400 tracks the location information of the spool/piping part itself and receives a signal requested from the database system 200 or the terminal 500 . When receiving, the corresponding information is transmitted to the database system 200 or the terminal 500, and the spool information storage module 430 includes related drawings, information and data related to construction work, and information and data related to quality inspection. information and data on the GPS module 420 and the spool information storage module 430 communicate with the database system 200 to exchange the latest information and update in real time, as well as on-site construction work and quality For inspection, the control module 510 provided in the terminal 500 and the control module 410 provided in the spool communication storage device 400 communicate with each other to read the information stored in the spool communication storage device 400, It may consist of a search and update of the construction progress and quality inspection progress that are newly carried out.

또한, 본 발명에 따른 상기 단말기(500)는 안드로이드 기반 자바(JAVA) 언어로 프로그래밍 된 모바일 웹 또는 스마트폰을 통해 실행되는 안드로이드/iOS 운영체제 기반의 어플리케이션 중에서 선택된 어느 하나의 프로그램으로 구성되고, 특정 스풀/배관부품에 장착된 스풀통신저장장치(400)에 접속하여 시공작업 및 품질검사를 수행하기 위한 모든 정보, 보고서, 도면 및 검사서류를 상기 단말기(500)의 화면을 통해 표출되도록 함과 동시에 시공작업과 품질검사의 결과를 상기 스풀통신저장장치(400)에 업데이트하는 구성으로 이루어질 수 있다.In addition, the terminal 500 according to the present invention is composed of any one program selected from among Android/iOS operating system-based applications executed through a mobile web or a smartphone programmed in Android-based Java language, and a specific spool / All information, reports, drawings, and inspection documents for performing construction work and quality inspection by accessing the spool communication storage device 400 mounted on the piping part are displayed through the screen of the terminal 500 and construction at the same time It may be configured to update the results of work and quality inspection in the spool communication storage device (400).

이와 같은 본 발명의 플랜트 배관 관리 시스템은, 플랜트 건설 프로젝트에서 배관공사와 관련된 견적/엔지니어링/자재/구매/조달관리의 실시간 검색, 파악, 보고서 작성/출력 등의 기능 제공과 함께 시공 및 품질검사 진척현황과 관련된 정보 제공은 물론 시공 및 품질검사에 대해서 매 진행단계별로 작업가능물량(work-front)과 작업지시서(work-order)까지 생성됨으로써, 배관시공 및 품질검사의 실질적인 영역에서의 업무효율이 극적으로 향상되고, 이 외에도 종이서류에 의존함에 따라 나타나는 최신정보와의 불일치로 인한 신뢰성 저하의 문제를 근본적으로 해결할 수 있으며, 배관 관리 시스템의 정보와 스풀통신저장장치상의 정보가 상호 교류되도록 함으로써, 최신 정보가 실시간 업데이트되는 체계를 구축할 수 있는 효과가 있다.As such, the plant piping management system of the present invention provides functions such as real-time search, identification, and report creation/printing of quotation/engineering/materials/purchase/procurement management related to piping work in a plant construction project, and construction and quality inspection progress In addition to providing information related to the current status, work-front and work-orders are generated for each stage of construction and quality inspection, thereby increasing work efficiency in the practical areas of piping construction and quality inspection. In addition to this, it is possible to fundamentally solve the problem of reliability degradation due to inconsistency with the latest information caused by reliance on paper documents. It has the effect of building a system in which the latest information is updated in real time.

도 1은 본 발명에 따른 플랜트 배관 관리 시스템을 나타낸 전체 구성도,
도 2는 본 발명에 따른 플랜트 배관 관리 시스템을 나타낸 개략도,
도 3은 본 발명이 적용되는 배관 공사의 플로우차트.
1 is an overall configuration diagram showing a plant pipe management system according to the present invention;
2 is a schematic diagram showing a plant pipe management system according to the present invention;
Figure 3 is a flowchart of plumbing work to which the present invention is applied.

이하에서는, 첨부도면을 참고하여 본 발명에 따른 바람직한 실시예를 보다 상세하게 설명하기로 한다.Hereinafter, a preferred embodiment according to the present invention will be described in more detail with reference to the accompanying drawings.

본 발명의 플랜트 배관 관리 시스템은, 도 1 및 도 2에 나타낸 바와 같이, 크게 데이터베이스 시스템(200), 스풀통신저장장치(400), 단말기(500) 및 신호중계기(300)로 구성된다.As shown in FIGS. 1 and 2 , the plant pipe management system of the present invention is largely composed of a database system 200 , a spool communication storage device 400 , a terminal 500 , and a signal repeater 300 .

상기 데이터베이스 시스템(200)은 해당 영역 내에 위치한 모든 배관에 대해서 관련 데이터베이스 정보를 저장하는 것으로, 서버부(210)와, 프로젝트정보모듈(230)과, 배관관리메인모듈(240)과, 시스템운영 및 권한통제모듈(220)과, 프로젝트통합관리모듈(250)과, 무선통신모듈(260)을 포함하여 이루어진다.The database system 200 stores related database information for all piping located in the corresponding area, and includes a server unit 210, a project information module 230, a piping management main module 240, and a system operation and The authority control module 220 , the project integrated management module 250 , and the wireless communication module 260 are included.

본 발명에 있어서, 상기 서버부(210)는 메인서버와 보조서버로 구성될 수 있으며, 상기 프로젝트정보모듈(230)은 해당 배관공사를 포함한 전체 프로젝트와 관련된 정보를 저장 및 관리한다. In the present invention, the server unit 210 may be composed of a main server and an auxiliary server, and the project information module 230 stores and manages information related to the entire project including the corresponding plumbing work.

또한, 상기 배관관리메인모듈(240)은 상기 프로젝트정보모듈(230)에 저장된 정보를 바탕으로 실질적인 배관공사시공 및 품질검사를 수행할 수 있도록 하고, 상기 시스템운영 및 권한통제모듈(220)은 상기 배관관리메인모듈(240)을 시스템적으로 관리 및 운영하는 모듈로써 구비되며, 상기 프로젝트통합관리모듈(250)운 상기 프로젝트정보모듈(230)과 배관관리메인모듈(240)을 상기 시스템운영 및 권한통제모듈(220)에 의해 해당 배관공사를 포함한 전체 프로젝트를 관리하는 시스템과 연계시키는 기능을 한다.In addition, the piping management main module 240 enables actual piping construction construction and quality inspection based on the information stored in the project information module 230, and the system operation and authority control module 220 is the It is provided as a module for systematically managing and operating the pipeline management main module 240, and the project integrated management module 250 operates the system operation and authority for the project information module 230 and the pipeline management main module 240. It functions to link with the system managing the entire project including the corresponding plumbing work by the control module 220 .

또, 상기 무선통신모듈(260)은 상기 데이터베이스 시스템(200)을 비롯하여 상기 신호중계기(300)와 스풀통신저장장치(400)와 전체 프로젝트를 관리하는 시스템에 구비된 신호통신장치와 무선으로 연결된다.In addition, the wireless communication module 260 is wirelessly connected to the signal communication device provided in the system for managing the entire project with the signal repeater 300 and the spool communication storage device 400 including the database system 200. .

상기 데이터베이스 시스템(200)을 구성하는 배관관리메인모듈(240)은 배관견적모듈(241)과, 배관엔지니어링모듈(242)과, 배관조달모듈(243)과, 배관현장자재관리모듈(244)과, 배관시공관리모듈(245)과, 배관품질관리모듈(246)을 포함한다.The piping management main module 240 constituting the database system 200 includes a piping estimation module 241, a piping engineering module 242, a piping procurement module 243, and a piping site material management module 244 and , a pipe construction management module 245 and a pipe quality control module 246 .

상기 배관관리메인모듈(240)은 수집된 정보들을 기반으로 의사결정을 하기 위하여 요구되는 정보를 지능형 지식관리모델(knowledge management model) 및 알고리즘으로 구현할 수 있다.The pipe management main module 240 may implement information required to make a decision based on the collected information as an intelligent knowledge management model and algorithm.

상기 지능형 지식관리모델은 수집 정보들에 대하여 정량적/정성적 효과를 자체평가하여 합리적인 의사결정 방안을 제시한다. 따라서, 상기한 지능형 지식관리모델에 의하여 필요한 정보에 대해 합리적이며 신속한 의사결정을 수행할 수 있는 토대를 마련할 수 있는 것이다.The intelligent knowledge management model suggests a rational decision-making method by self-evaluating the quantitative/qualitative effects of the collected information. Accordingly, it is possible to lay the foundation for rational and rapid decision-making on necessary information by the intelligent knowledge management model.

본 발명에 있어서, 상기 배관견적모듈(241)은 설계상 자재(B/M)와 현장에서 실제 사용되어 소요된 자재정보를 자동링크, 자재비·간접비·기타경비정보를 활용하여 실행예산 및 원가모니터링과 아울러 타공사를 위한 견적정보를 제공한다.In the present invention, the pipe estimation module 241 uses the automatic link between the design material (B/M) and the material information actually used in the field, and material cost, overhead cost, and other cost information to monitor the execution budget and cost. In addition, we provide quotation information for other construction projects.

상기 배관엔지니어링모듈(242)은 배관 설계와 관련된 상세정보, 제원, B/M정보, 배관 코드를 생성하며, 상기 배관조달모듈(243)은 배관 주자재의 발주와 조달을 시행 및 모니터링하는 기능을 한다.The piping engineering module 242 generates detailed information, specifications, B/M information, and piping codes related to piping design, and the piping procurement module 243 functions to execute and monitor ordering and procurement of piping main materials. .

그리고, 상기 배관현장자재관리모듈(244)은 시공 현장에서의 배관 주자재입고관리 및 상기 배관조달모듈(243)의 업데이트, 시공 현장에서의 자재 불출관리, 현장구매자재에 대한 구매관리 및 상기 배관조달모듈(243)과의 시뮬레이션을 수행한다.In addition, the piping site material management module 244 is a pipeline main material stock management at the construction site, update of the piping procurement module 243, material dispensing management at the construction site, purchase management for on-site purchased materials, and the piping procurement A simulation with module 243 is performed.

또한, 상기 배관시공관리모듈(245)과 배관품질관리모듈(246)은 각각 배관시공관리 및 배관품질검사를 수행하는 기능을 한다.In addition, the piping construction management module 245 and the piping quality management module 246 each function to perform piping construction management and piping quality inspection.

여기서, 상기 배관시공관리모듈(245)은 배관시공현황정보모듈(245A)과, 배관시공자원관리모듈(245B)과, 배관시공관리현장정보모듈(245C)을 포함할 수 있다.Here, the piping construction management module 245 may include a piping construction status information module 245A, a piping construction resource management module 245B, and a piping construction management site information module 245C.

상기 배관시공관리모듈(245)을 이루는 각 구성에 대해 구체적으로 설명하면, 상기 배관시공현황정보모듈(245A)은 배관시공에 필요한 엔지니어링, 자재 및 품질요구조건에 대한 정보와 연계되어 기준시점에서의 시공현황 상세정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 기능을 수행하고, 상기 배관시공자원관리모듈(245B)은 배관시공에 필요한 인적자원 및 물적자원에 대한 상세내역, 인증/검사현황, 배치현황, 위치와 관련된 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 기능을 수행한다. 이와 더불어 상기 배관시공관리현장정보모듈(245C)은 배관시공을 위한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/관리 인력 및 장비의 배정상 제한조건, 기타 작업 공도구 설치 및 배정현황, 입고 설치자재에 대한 배분현황, 선행공정 또는 유관공정에 의한 제한사항, 자재 및 도면/Engineering상 문제(Engineering Hold)로 인한 제한사항, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 기능을 수행한다.If each configuration constituting the pipe construction management module 245 will be described in detail, the pipe construction status information module 245A is linked with information on engineering, materials, and quality requirements required for pipe construction at a reference point in time. It performs a function of recording, storing, analyzing, displaying, searching, transmitting and outputting detailed construction status information, and the pipe construction resource management module 245B provides detailed information on human and material resources required for pipe construction, It performs functions to record, store, analyze, display, search, transmit, and output information related to authentication/inspection status, deployment status, and location. In addition, the pipe construction management site information module 245C is a main scaffolding installation state related to the site conditions for piping construction, whether or not local scaffolding is required and installation state, work priority (priority), Restrictions on assignment of work/management personnel and equipment, installation and assignment status of other work tools, distribution status of incoming installation materials, restrictions by preceding or related processes, material and drawings/engineering issues (Engineering Hold) It performs a function to record, store, analyze, display, search, transmit, and print information on restrictions due to restrictions, restrictions due to comments from the original building/customer, and general conditions and restrictions in safety/quality/construction management. .

즉, 배관시공현황정보모듈(245A), 배관시공자원관리모듈(245B) 및 배관시공관리현장정보모듈(245C)을 포함하는 배관시공관리모듈(245)은 정보의 조합, 처리 및 분석하여 배관시공관리에 필요한 각종 현황자료/보고서와 각 시공단계별 Preliminary work-front, 이후 시공부서의 확인을 거쳐 확정된 official work-front, offical work-front와 시공관리부서에서 설정한 조건에 따라 각 시공단계별, 즉 spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, reinstatement 등의 preliminary work order와 시공부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하는 기능을 하는 것이다.That is, the piping construction management module 245 including the piping construction status information module 245A, the piping construction resource management module 245B, and the piping construction management site information module 245C combines, processes and analyzes information to construct piping. Various status data/reports required for management, Preliminary work-front for each construction stage, and official work-front and offical work-front confirmed through confirmation by the construction department after each construction stage, namely, according to the conditions set by the construction management department Create, display, search, transmit, print and distribute preliminary work orders such as spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, reinstatement, and official work orders confirmed by the construction department to function.

한편, 배관관리메인모듈(240)을 구성하는 배관품질관리모듈(246)은 배관품질검사현황모듈(246A)과, 배관품질검사자원관리모듈(246B)과, 배관품질검사현장정보모듈(246C)을 포함할 수 있다.On the other hand, the pipe quality control module 246 constituting the pipe management main module 240 includes a pipe quality inspection status module 246A, a pipe quality inspection resource management module 246B, and a pipe quality inspection site information module 246C. may include

상기 배관품질검사현황모듈(246A)은 배관품질검사 수행을 위한 엔지니어링, 자재, 배관시공 및 품질요구조건의 정보와 연계되어 기준시점에서의 진척된 품질검사현황에 대한 상세한 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력하는 기능을 하며, 상기 배관품질검사자원관리모듈(246B)은 품질검사 수행을 위해 필요한 인적자원(검사원, 감리, 관리자 등) 및 물적자원(검사장비, 공도구 등)의 상세내역, 인증/검사현황, 배치현황, 위치정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력하는 기능을 수행한다.The pipe quality inspection status module 246A records, stores, and analyzes detailed information on the advanced quality inspection status at a reference point in connection with information on engineering, materials, pipe construction, and quality requirements for pipe quality inspection. , display, search, transmit and output, and the pipe quality inspection resource management module 246B includes human resources (inspectors, supervisors, managers, etc.) and material resources (inspection equipment, tools, etc.) necessary for quality inspection. ) records, stores, analyzes, displays, searches, transmits, and outputs detailed details, authentication/inspection status, placement status, and location information.

그리고, 상기 배관품질검사현장정보모듈(246C)은 시공 현장에서 품질검사를 수행하기 위해 필요한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/검사 인력 및 배정상 제한조건, 작업 공도구 설치 및 배정현황, 타품질검사 또는 시공작업과의 간섭으로 인한 제한사항, 자재 및 도면/engineering상 문제(Engineering Hold)로 인한 제한사항 판별, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력하는 기능을 수행한다.In addition, the pipe quality inspection site information module 246C is a main scaffolding installation state related to site conditions necessary to perform a quality inspection at a construction site, whether or not local scaffolding is required and installation state, work Priority, work/inspection personnel and assignment constraints, work tool installation and assignment status, other quality inspections or restrictions due to interference with construction work, material and drawing/engineering issues (Engineering Hold) It performs the functions of recording, storing, analyzing, displaying, searching, transmitting, and outputting information on restrictions caused by the identification of restrictions, restrictions due to comments from the original building/ordering company, and general conditions and restrictions in safety/quality/construction management.

즉, 배관품질검사현황모듈(246A), 배관품질검사자원관리모듈(246B) 및 배관품질검사현장정보모듈(246C)을 포함하는 배관품질관리모듈(246)은 정보의 조합, 처리 및 분석하여 배관품질검사관리에 필요한 각종 현황자료/보고서와 각 품질검사단계별 preliminary work-front, 이후 품질관리부서의 확인을 거쳐 확정된 official work-front, official work-front와 품질관리부서에서 설정한 조건에 따라 승인한 품질검사계획(ITP: Inspection & Test Plan)에 따른 각 품질검사단계별, 즉 spool erection inspection, fit-up inspection, welding inspection, heat treatment inspection, hydro-test(pneumatic) inspection, lay-up inspection, bolt tightening inspection, punch inspection, reinstatement의 preliminary work order와 품질관리부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하는 기능을 하는 것이다.That is, the piping quality control module 246 including the piping quality inspection status module 246A, the piping quality inspection resource management module 246B, and the piping quality inspection site information module 246C combines, processes, and analyzes information to Various status data/reports required for quality inspection and management, preliminary work-front for each quality inspection stage, and approval according to the conditions set by the official work-front and official work-front confirmed by the quality management department and the quality management department For each quality inspection step according to an Inspection & Test Plan (ITP), that is, spool erection inspection, fit-up inspection, welding inspection, heat treatment inspection, hydro-test(pneumatic) inspection, lay-up inspection, bolt It functions to create, display, search, transmit, print, and distribute preliminary work orders for tightening inspection, punch inspection, and reinstatement and official work orders confirmed by the quality control department.

본 발명에 있어서, 상기 스풀통신저장장치(400)는 각 배관마다 설치되는 것으로, 각 스풀 또는 배관을 구성하는 부품의 위치정보를 생성하는 GPS 모듈(420)과, 각 스풀의 조인트 위치 정보와 시공현황 정보 및 품질검사 상태 정보가 저장된 스풀정보저장모듈(430)과, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송하는 제어모듈(410)로 구성된다.In the present invention, the spool communication storage device 400 is installed for each pipe, and includes a GPS module 420 that generates position information of each spool or parts constituting the pipe, and joint position information and construction of each spool. It consists of a spool information storage module 430 in which status information and quality inspection status information are stored, and a control module 410 that wirelessly transmits the information stored in the spool information storage module 430 to the database system 200 .

여기서, 상기 제어모듈(410)은 마이크로 콘트롤러 유닛(411)과, 무선통신모듈(412)과, 무선통신보안모듈(413)을 포함하여 구성되고, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송함과 아울러 갱신된 최신의 정보를 상기 제어모듈(410)에 의하여 실시간 및 자동으로 상기 데이터베이스 시스템(200)으로부터 무선수신받도록 한다.Here, the control module 410 is configured to include a microcontroller unit 411 , a wireless communication module 412 , and a wireless communication security module 413 , and stores information stored in the spool information storage module 430 . In addition to wireless transmission to the database system 200 , the control module 410 enables the control module 410 to wirelessly receive the updated and updated information from the database system 200 in real time and automatically.

또한, 상기 스풀통신저장장치(400)에 구비된 GPS 모듈(420)은 스풀/배관부품 자체의 위치 정보를 추적하며 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로부터 요청된 신호를 수신받을 경우, 해당 정보를 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로 송출하도록 한다.In addition, the GPS module 420 provided in the spool communication storage device 400 tracks the location information of the spool/piping part itself, and when receiving a signal requested from the database system 200 or the terminal 500 , to transmit the corresponding information to the database system 200 or the terminal 500 .

아울러, 상기 스풀정보저장모듈(430)은 관련 도면, 시공작업과 관련된 정보 및 자료, 품질검사와 관련된 정보 및 자료를 저장하며, 상기 GPS 모듈(420)과 스풀정보저장모듈(430) 상의 정보와 자료는 상기 데이터베이스 시스템(200)과 교신하여 최신 정보들을 상호 교류하며 실시간으로 업데이트함은 물론, 현장 시공작업 및 품질검사를 위해서 상기 단말기(500)에 구비된 제어모듈(510)과 스풀통신저장장치(400)에 구비된 제어모듈(410)이 상호 교신하여 상기 스풀통신저장장치(400) 내에 저장된 정보를 열람, 검색 및 새롭게 진행되는 시공 진척상황과 품질검사 진척상황을 업데이트하는 기능을 수행한다.In addition, the spool information storage module 430 stores related drawings, information and data related to construction work, information and data related to quality inspection, and information on the GPS module 420 and the spool information storage module 430 and The data communicates with the database system 200 to exchange the latest information and update in real time, as well as the control module 510 and the spool communication storage device provided in the terminal 500 for on-site construction work and quality inspection. The control module 410 provided in the 400 communicates with each other and performs a function of reading and searching the information stored in the spool communication storage device 400 and updating the construction progress status and the quality inspection progress status newly progressed.

본 발명에 있어서, 상기 단말기는 상기 스풀통신저장장치(400)와 무선통신할 수 있는 무선 입/출력 모듈(513)과, 마이크로 콘트롤러 유닛(511)과, 무선통신모듈(512)을 포함하고, 시스템접속권한통제모듈(520)을 통하여 상기 데이터베이스 시스템(200) 상에서 상기 스풀통신저장장치(400)로 접근할 수 있는 권한이 부여된 경우, 모바일 웹(mobile web) 또는 안드로이드(android)/iOS 기반의 어플리케이션을 통해 배관 정보를 모니터링하거나 현장에서 최신 정보를 입력할 수 있도록 구비된다.In the present invention, the terminal includes a wireless input/output module 513 capable of wireless communication with the spool communication storage device 400, a microcontroller unit 511, and a wireless communication module 512, When access to the spool communication storage device 400 on the database system 200 is granted through the system access right control module 520, mobile web or Android/iOS based It is equipped to monitor piping information through the application of or to input the latest information in the field.

이때, 상기 단말기(500)는, 안드로이드 기반 자바(JAVA) 언어로 프로그래밍 된 모바일 웹 또는 스마트폰을 통해 실행되는 안드로이드/iOS 운영체제 기반의 어플리케이션 중에서 선택된 어느 하나의 프로그램으로 구성되고, 특정 스풀/배관부품에 장착된 스풀통신저장장치(400)에 접속하여 시공작업 및 품질검사를 수행하기 위한 모든 정보, 보고서, 도면 및 검사서류를 상기 단말기(500)의 화면을 통해 표출되도록 함과 동시에 시공작업과 품질검사의 결과를 상기 스풀통신저장장치(400)에 업데이트하도록 구성할 수 있다.At this time, the terminal 500 is composed of any one program selected from among Android/iOS operating system-based applications executed through a smartphone or a mobile web programmed in Android-based JAVA language, and a specific spool/piping part All information, reports, drawings and inspection documents for performing construction work and quality inspection by accessing the spool communication storage device 400 mounted on the It can be configured to update the test result to the spool communication storage device (400).

본 발명에 있어서, 상기 신호중계기(300)는 상기 데이터베이스 시스템(200)과 스풀통신저장장치(400) 간에 무선통신이 가능하도록 구비된다.In the present invention, the signal repeater 300 is provided to enable wireless communication between the database system 200 and the spool communication storage device 400 .

여기서, 데이터베이스 시스템(200)과 현장 내 스풀통신저장장치(400)를 무선으로 연결, 중계하는 상기 신호중계기(300)는 다량의 철제구성품과 구조물이 설치되는 일반적인 플랜트 건설현장의 특수성을 고려하여 본 발명에 포함시킨 것으로, 만일, 별도의 신호중계기(300) 없이 위성인터넷 등으로 데이터베이스시스템(200)과 스풀통신저장장치(400)를 직접 연결시킬 수 있는 수단이 확보될 수 있다면 신호중계기(300)는 생략이 가능하다.Here, the signal repeater 300, which wirelessly connects and relays the database system 200 and the spool communication storage device 400 in the field, considers the specificity of a general plant construction site where a large amount of iron components and structures are installed. As included in the invention, if a means for directly connecting the database system 200 and the spool communication storage device 400 to the satellite Internet without a separate signal repeater 300 can be secured, the signal repeater 300 can be omitted.

이상에서 설명한 바와 같이, 본 발명에 따른 플랜트 배관 관리 시스템은 플랜트 건설 프로젝트에서 배관공사와 관련된 견적/엔지니어링/자재/구매/조달관리의 실시간 검색, 파악, 보고서 작성/출력 등의 기능 제공과 함께 시공 및 품질검사 진척현황과 관련된 정보 제공은 물론 시공 및 품질검사에 대해서 매 진행단계별로 작업가능물량(work-front)과 작업지시서(work-order)까지 생성됨으로써, 배관시공 및 품질검사의 실질적인 영역에서의 업무효율이 극적으로 향상되고, 이 외에도 종이서류에 의존함에 따라 나타나는 최신정보와의 불일치로 인한 신뢰성 저하의 문제를 근본적으로 해결할 수 있으며, 배관 관리 시스템의 정보와 스풀통신저장장치상의 정보가 상호 교류되도록 함으로써, 최신 정보가 실시간 업데이트되는 체계를 구축할 수 있는 효과를 제공하는 매우 유용한 발명이다.As described above, the plant piping management system according to the present invention provides functions such as real-time search, identification, report creation/output, etc. of estimate/engineering/material/purchase/procurement management related to plumbing in a plant construction project and construction As well as providing information related to the progress of quality inspection and construction and quality inspection, work-front and work-orders are created for each stage of construction and quality inspection. work efficiency is dramatically improved, and in addition, it can fundamentally solve the problem of reliability degradation due to inconsistency with the latest information caused by reliance on paper documents. It is a very useful invention that provides the effect of building a system in which the latest information is updated in real time by allowing them to be exchanged.

200 : 데이터베이스 시스템 210 : 서버부
220 : 시스템운영 및 권한통제모듈 230 : 프로젝트정보모듈
240 : 배관관리메인모듈 241 : 배관견적모듈
242 : 배관엔지니어링모듈 243 : 배관조달모듈
244 : 배관현장자재관리모듈 245 : 배관시공관리모듈
245A : 배관시공현황정보모듈 245B : 배관시공자원관리모듈
245C : 배관시공관리현장정보모듈 246 : 배관품질관리모듈
246A : 배관품질검사현황모듈 246B : 배관품질검사자원관리모듈
246C : 배관품질검사현장정보모듈 250 : 프로젝트통합관리모듈
260 : 무선통신모듈 300 : 신호중계기
400 : 스풀통신저장장치 410 : 스풀통신저장장치 제어모듈
411 : 마이크로 콘트롤러 유닛 412 : 무선통신모듈
413 : 무선통신보안모듈 420 : GPS 모듈
430 : 스풀정보저장모듈 500 : 단말기
510 : 단말기 제어모듈 511 : 마이크로 콘트롤러 유닛
512 : 무선통신모듈 513 : 무선 입/출력 모듈
520 : 시스템접속권한통제모듈
200: database system 210: server unit
220: system operation and authority control module 230: project information module
240: piping management main module 241: piping estimation module
242: piping engineering module 243: piping procurement module
244: piping site material management module 245: piping construction management module
245A: Piping construction status information module 245B: Piping construction resource management module
245C: Piping construction management site information module 246: Piping quality management module
246A: Pipe quality inspection status module 246B: Pipe quality inspection resource management module
246C: Piping quality inspection site information module 250: Project integrated management module
260: wireless communication module 300: signal repeater
400: spool communication storage device 410: spool communication storage device control module
411: microcontroller unit 412: wireless communication module
413: wireless communication security module 420: GPS module
430: spool information storage module 500: terminal
510: terminal control module 511: microcontroller unit
512: wireless communication module 513: wireless input/output module
520: system access permission control module

Claims (11)

해당 영역 내에 위치한 모든 배관에 대해서 관련 데이터베이스 정보를 저장하는 데이터베이스 시스템(200);
각 배관마다 설치되는 것으로, 각 스풀 또는 배관을 구성하는 부품의 위치정보를 생성하는 GPS 모듈(420)과, 각 스풀의 조인트 위치 정보와 시공현황 정보 및 품질검사 상태 정보가 저장된 스풀정보저장모듈(430)과, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송하는 제어모듈(410)로 구성된 스풀통신저장장치(400);
상기 스풀통신저장장치(400)와 무선통신할 수 있는 무선 입/출력 모듈(513)과, 마이크로 콘트롤러 유닛(511)과, 무선통신모듈(512)을 포함하고, 시스템접속권한통제모듈(520)을 통하여 상기 데이터베이스 시스템(200) 상에서 상기 스풀통신저장장치(400)로 접근할 수 있는 권한이 부여된 경우, 모바일 웹(mobile web) 또는 안드로이드(android)/iOS 기반의 어플리케이션을 통해 배관 정보를 모니터링하거나 현장에서 최신 정보를 입력할 수 있도록 구비된 단말기(500); 및
상기 데이터베이스 시스템(200)과 스풀통신저장장치(400) 간에 무선통신이 가능하도록 구비된 신호중계기(300);를 포함하여 구성되고,
상기 데이터베이스 시스템(200)은, 메인서버와 보조서버로 구성된 서버부(210)와; 해당 배관공사를 포함한 전체 프로젝트와 관련된 정보를 저장 및 관리하는 프로젝트정보모듈(230)과; 상기 프로젝트정보모듈(230)에 저장된 정보를 바탕으로 실질적인 배관공사 시공 및 품질검사를 수행할 수 있도록 하는 배관관리메인모듈(240)과; 상기 배관관리메인모듈(240)을 시스템적으로 관리·운영하는 시스템운영 및 권한통제모듈(220)과; 상기 프로젝트정보모듈(230)과 배관관리메인모듈(240)을 상기 시스템운영 및 권한통제모듈(220)에 의해 해당 배관공사를 포함한 전체 프로젝트를 관리하는 시스템과 연계시키는 프로젝트통합관리모듈(250)과; 상기 데이터베이스 시스템(200)을 비롯하여 상기 신호중계기(300)와 스풀통신저장장치(400)와 전체 프로젝트를 관리하는 시스템에 구비된 신호통신장치와 무선으로 연결되는 무선통신모듈(260);을 포함하여 이루어지며,
상기 배관관리메인모듈(240)은, 설계상 자재(B/M)와 현장에서 실제 사용되어 소요된 자재정보를 자동링크, 자재비·간접비·기타경비정보를 활용하여 실행예산 및 원가를 도출함과 동시에 이를 모니터링하며, 타공사를 위한 견적정보를 제공하는 배관견적모듈(241)과; 배관 설계와 관련된 상세정보, 제원, B/M정보, 배관 코드를 생성하는 배관엔지니어링모듈(242)과; 배관 주자재의 발주와 조달을 시행 및 모니터링하는 배관조달모듈(243)과; 시공 현장에서의 배관 주자재입고관리 및 상기 배관조달모듈(243)의 업데이트, 시공 현장에서의 자재 불출관리, 현장구매자재에 대한 구매관리 및 상기 배관조달모듈(243)과의 시뮬레이션을 수행하는 배관현장자재관리모듈(244)과; 시공 현장에서 배관시공관리를 수행하기 위한 배관시공관리모듈(245)과; 시공 현장에서 배관품질검사를 수행하기 위한 배관품질관리모듈(246);을 포함하고,
상기 배관시공관리모듈(245)은, 배관시공에 필요한 엔지니어링, 자재 및 품질요구조건에 대한 정보와 연계되어 기준시점에서의 시공현황 상세정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관시공현황정보모듈(245A)과; 배관시공에 필요한 인적자원 및 물적자원에 대한 상세내역, 인증/검사현황, 배치현황, 위치와 관련된 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관시공자원관리모듈(245B)과; 배관시공을 위한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/관리 인력 및 장비의 배정상 제한조건, 기타 작업 공도구 설치 및 배정현황, 입고 설치자재에 대한 배분현황, 선행공정 또는 유관공정에 의한 제한사항, 자재 및 도면/Engineering상 문제(Engineering Hold)로 인한 제한사항, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관시공관리현장정보모듈(245C);을 포함하며,
상기 배관시공관리모듈(245)은, 정보의 조합, 처리 및 분석을 통해 배관시공관리에 필요한 각종 현황자료/보고서와 각 시공단계별 preliminary work-front, 이후 시공부서의 확인을 거쳐 확정된 official work-front와 시공관리부서에서 설정한 조건에 따라 각 시공단계별, 즉, spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, reinstatement의 preliminary work order와 시공부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하고,
상기 배관품질관리모듈(246)은, 배관품질검사 수행을 위한 엔지니어링, 자재, 배관시공 및 품질요구조건의 정보와 연계되어 기준시점에서의 진척된 품질검사현황에 대한 상세한 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사현황모듈(246A)과; 품질검사 수행을 위해 필요한 인적자원 및 물적자원의 상세내역, 인증/검사현황, 배치현황, 위치정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사자원관리모듈(246B)과; 시공 현장에서 품질검사를 수행하기 위해 필요한 현장조건과 관련된 주비계(main scaffolding) 설치상태, 특정구역비계(local scaffolding) 필요여부 및 설치상태, 작업우선순위(priority), 작업/검사 인력 및 배정상 제한조건, 작업 공도구 설치 및 배정현황, 타품질검사 또는 시공작업과의 간섭으로 인한 제한사항, 자재 및 도면/Engineering상 문제(Engineering Hold)로 인한 제한사항 판별, 원청사/발주처의 코멘트로 인한 제한사항, 안전/품질/시공 관리상 일반적 조건 및 제한사항의 정보를 기록, 저장, 분석, 표시, 검색, 전송 및 출력할 수 있는 배관품질검사현장정보모듈(246C);을 포함하며,
상기 배관품질관리모듈(246)은, 정보의 조합, 처리 및 분석을 통해 배관품질검사관리에 필요한 각종 현황자료/보고서와 각 품질검사단계별 preliminary work-front, 이후 품질관리부서의 확인을 거쳐 확정된 official work-front와 품질관리부서에서 설정한 조건에 따라 승인한 품질검사계획(ITP: Inspection & Test Plan)에 따른 각 품질검사단계별, 즉, spool erection inspection, fit-up, inspection, welding inspection, heat treatment inspection, hydro-test(pneumatic) inspection, lay-up inspection, bolt tightening inspection, punch inspection, reinstatement의 preliminary work order와 품질관리부서에서 이를 확정한 official work order를 생성, 표시, 검색, 전송, 출력 및 배포하고,
상기 배관관리메인모듈(240)은, 수집된 정보들을 기반으로 의사결정을 하기 위하여 요구되는 정보를 지능형 지식관리모델 및 알고리즘으로 구현하는 것을 특징으로 하는 플랜트 배관 관리 시스템.
a database system 200 for storing related database information for all pipes located in the corresponding area;
A GPS module 420 that is installed for each pipe and generates position information of each spool or parts constituting the pipe, and a spool information storage module that stores joint position information of each spool, construction status information, and quality inspection status information ( 430) and a spool communication storage device 400 comprising a control module 410 for wirelessly transmitting the information stored in the spool information storage module 430 to the database system 200;
It includes a wireless input/output module 513 capable of wireless communication with the spool communication storage device 400 , a microcontroller unit 511 , and a wireless communication module 512 , and a system access right control module 520 . When access to the spool communication storage device 400 is granted on the database system 200 through the or a terminal 500 equipped to input the latest information in the field; and
and a signal repeater 300 provided to enable wireless communication between the database system 200 and the spool communication storage device 400;
The database system 200 includes a server unit 210 comprising a main server and an auxiliary server; a project information module 230 for storing and managing information related to the entire project including the corresponding plumbing work; a plumbing management main module 240 capable of performing actual plumbing construction construction and quality inspection based on the information stored in the project information module 230; a system operation and authority control module 220 for systematically managing and operating the pipe management main module 240; The project information module 230 and the piping management main module 240 are linked with the system for managing the entire project including the corresponding piping construction by the system operation and authority control module 220 with a project integrated management module 250 and ; Including the database system 200, the signal repeater 300, the spool communication storage device 400, and a wireless communication module 260 wirelessly connected to the signal communication device provided in the system for managing the entire project. is made,
The pipeline management main module 240 derives the execution budget and cost by using the automatic link between the design material (B/M) and the material information actually used in the field, and material cost, overhead cost, and other cost information. a piping estimation module 241 that monitors this at the same time and provides estimation information for other construction projects; a piping engineering module 242 for generating detailed information, specifications, B/M information, and piping codes related to piping design; a pipe procurement module 243 for executing and monitoring the ordering and procurement of pipe main materials; A piping site that performs a simulation with the piping procurement module 243, management of stocking of main materials for piping at the construction site, updating of the piping procurement module 243, management of material dispensing at the construction site, purchase management for on-site purchased materials, and the piping procurement module 243 a material management module 244 and; a pipe construction management module 245 for performing pipe construction management at the construction site; Including; a pipe quality control module 246 for performing a pipe quality inspection at the construction site;
The pipe construction management module 245 records, stores, analyzes, displays, searches, transmits and outputs detailed construction status information at a reference point in connection with information on engineering, materials, and quality requirements required for pipe construction. A possible piping construction status information module (245A) and; Pipe construction resource management module (245B) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting information related to detailed details, certification/inspection status, arrangement status, and location of human and material resources required for pipe construction )class; Installation status of main scaffolding related to on-site conditions for plumbing construction, whether or not local scaffolding is needed and installation status, priority of work, restrictions on assignment of work/management personnel and equipment, etc. Work tool installation and assignment status, distribution status of incoming installation materials, restrictions due to preceding or related processes, restrictions due to material and drawings/Engineering Hold, restrictions due to comments from the original building/ordering company It includes; a piping construction management site information module (245C) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting information of general conditions and restrictions in terms of safety / quality / construction management;
The pipe construction management module 245 includes various status data/reports necessary for pipe construction management through combination of information, processing and analysis, preliminary work-front for each construction stage, and official work-front confirmed after confirmation by the construction department. According to the conditions set by the front and the construction management department, the preliminary work order for each construction stage, that is, spool erection, fit-up, welding, heat treatment, hydro-test, lay-up, punch, and reinstatement, and the construction department confirm it create, display, retrieve, transmit, print and distribute an official work order;
The pipe quality control module 246 records, stores, and analyzes detailed information on the progress of quality inspection status at a reference point in connection with information of engineering, materials, pipe construction, and quality requirements for pipe quality inspection. , a pipe quality inspection status module 246A capable of displaying, searching, transmitting and outputting; Pipe quality inspection resource management module (246B) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting detailed details of human and material resources necessary for quality inspection, certification/inspection status, arrangement status, and location information )class; Installation status of main scaffolding related to site conditions required to perform quality inspection at the construction site, whether or not local scaffolding is required and installation status, work priority, work/inspection manpower and assignment status Restriction conditions, work tool installation and assignment status, restrictions due to interference with other quality inspections or construction work, determination of restrictions due to material and drawings/Engineering Hold, restrictions due to comments from the original building/customer and a pipe quality inspection site information module (246C) capable of recording, storing, analyzing, displaying, searching, transmitting and outputting information of general conditions and restrictions in terms of safety / quality / construction management;
The pipe quality management module 246, through the combination of information, processing and analysis, various status data/reports necessary for pipe quality inspection management, preliminary work-front for each quality inspection stage, and confirmation of the quality management department after that. According to the conditions set by the official work-front and the quality control department, each quality inspection step according to the approved ITP (Inspection & Test Plan), namely, spool erection inspection, fit-up, inspection, welding inspection, heat Create, display, search, transmit, print and perform preliminary work orders for treatment inspection, hydro-test (pneumatic) inspection, lay-up inspection, bolt tightening inspection, punch inspection, and reinstatement and official work orders confirmed by the quality control department distribute,
The piping management main module 240 is a plant piping management system, characterized in that the information required to make a decision based on the collected information is implemented as an intelligent knowledge management model and algorithm.
제1 항에 있어서,
상기 제어모듈(410)은, 마이크로 콘트롤러 유닛(411)과, 무선통신모듈(412)과, 무선통신보안모듈(413)을 포함하여 구성되고, 상기 스풀정보저장모듈(430)에 저장된 정보를 상기 데이터베이스 시스템(200)으로 무선 전송함과 아울러 갱신된 최신의 정보를 상기 제어모듈(410)에 의하여 실시간 및 자동으로 상기 데이터베이스 시스템(200)으로부터 무선으로 전송받는 것을 특징으로 하는 플랜트 배관 관리 시스템.
According to claim 1,
The control module 410 is configured to include a microcontroller unit 411, a wireless communication module 412, and a wireless communication security module 413, and stores the information stored in the spool information storage module 430. Plant piping management system, characterized in that while wirelessly transmitting to the database system (200), the updated latest information is wirelessly transmitted from the database system (200) in real time and automatically by the control module (410).
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 제1 항에 있어서,
상기 스풀통신저장장치(400)에 구비된 GPS 모듈(420)은, 스풀/배관부품 자체의 위치 정보를 추적하며 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로부터 요청된 신호를 수신받을 경우, 해당 정보를 상기 데이터베이스 시스템(200) 또는 상기 단말기(500)로 송출하고,
상기 스풀정보저장모듈(430)은, 관련 도면, 시공작업과 관련된 정보 및 자료, 품질검사와 관련된 정보 및 자료를 저장하며, 상기 GPS 모듈(420)과 스풀정보저장모듈(430) 상의 정보와 자료는 상기 데이터베이스 시스템(200)과 교신하여 최신 정보들을 상호 교류하며 실시간으로 업데이트함은 물론, 현장 시공작업 및 품질검사를 위해서 상기 단말기(500)에 구비된 제어모듈(510)과 스풀통신저장장치(400)에 구비된 제어모듈(410)이 상호 교신하여 상기 스풀통신저장장치(400) 내에 저장된 정보를 열람, 검색 및 새롭게 진행되는 시공 진척상황과 품질검사 진척상황을 업데이트하는 것을 특징으로 하는 플랜트 배관 관리 시스템.
According to claim 1,
The GPS module 420 provided in the spool communication storage device 400 tracks the location information of the spool/piping part itself, and when receiving a signal requested from the database system 200 or the terminal 500, Transmitting the corresponding information to the database system 200 or the terminal 500,
The spool information storage module 430 stores related drawings, information and data related to construction work, information and data related to quality inspection, and information and data on the GPS module 420 and the spool information storage module 430 . communicates with the database system 200 to exchange the latest information and update in real time, as well as a control module 510 and a spool communication storage device provided in the terminal 500 for on-site construction work and quality inspection ( Plant piping, characterized in that the control module 410 provided in 400) communicates with each other to view and search the information stored in the spool communication storage device 400, and to update the construction progress and quality inspection progress newly progressed. management system.
제1 항에 있어서,
상기 단말기(500)는, 안드로이드 기반 자바(JAVA) 언어로 프로그래밍 된 모바일 웹 또는 스마트폰을 통해 실행되는 안드로이드/iOS 운영체제 기반의 어플리케이션 중에서 선택된 어느 하나의 프로그램으로 구성되고, 특정 스풀/배관부품에 장착된 스풀통신저장장치(400)에 접속하여 시공작업 및 품질검사를 수행하기 위한 모든 정보, 보고서, 도면 및 검사서류를 상기 단말기(500)의 화면을 통해 표출되도록 함과 동시에 시공작업과 품질검사의 결과를 상기 스풀통신저장장치(400)에 업데이트하는 것을 특징으로 하는 플랜트 배관 관리 시스템.
According to claim 1,
The terminal 500 is composed of any one program selected from among Android/iOS operating system-based applications executed through a mobile web or a smartphone programmed in Android-based JAVA language, and is mounted on a specific spool/piping part. All information, reports, drawings, and inspection documents for performing construction work and quality inspection by accessing the spool communication storage device 400 that has been A plant piping management system, characterized in that the result is updated in the spool communication storage device (400).
KR1020200095159A 2020-07-30 2020-07-30 Plant pipe management system KR102386500B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200095159A KR102386500B1 (en) 2020-07-30 2020-07-30 Plant pipe management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200095159A KR102386500B1 (en) 2020-07-30 2020-07-30 Plant pipe management system

Publications (2)

Publication Number Publication Date
KR20220015094A KR20220015094A (en) 2022-02-08
KR102386500B1 true KR102386500B1 (en) 2022-04-13

Family

ID=80251601

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200095159A KR102386500B1 (en) 2020-07-30 2020-07-30 Plant pipe management system

Country Status (1)

Country Link
KR (1) KR102386500B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102488376B1 (en) 2022-09-05 2023-01-13 주식회사 도원엔지니어링 Plant piping structure with improved insulation properties

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102001969B1 (en) * 2019-04-30 2019-07-19 부경엔지니어링주식회사 Confirmation of water pipe location And real-time management system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010000969A (en) 2000-10-26 2001-01-05 김병기 Making method of multicolored beancurd containing various kinds of vegetable juice and particles
JP5452524B2 (en) 2011-03-02 2014-03-26 日立Geニュークリア・エナジー株式会社 Plant construction support method and plant construction support device
KR101337722B1 (en) 2012-12-24 2013-12-06 중앙항업(주) Underground Management System
KR20150138958A (en) * 2014-05-30 2015-12-11 성균관대학교산학협력단 N f c based plant management system
KR101754243B1 (en) * 2015-07-27 2017-07-06 삼성중공업 주식회사 System and method for plumbing work management

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102001969B1 (en) * 2019-04-30 2019-07-19 부경엔지니어링주식회사 Confirmation of water pipe location And real-time management system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102488376B1 (en) 2022-09-05 2023-01-13 주식회사 도원엔지니어링 Plant piping structure with improved insulation properties

Also Published As

Publication number Publication date
KR20220015094A (en) 2022-02-08

Similar Documents

Publication Publication Date Title
Ma et al. Data-driven decision-making for equipment maintenance
US8606548B2 (en) Energy facility control system
Liu et al. Automatically updating maintenance information from a BIM database
Duffuaa et al. Turnaround maintenance in petrochemical industry: practices and suggested improvements
Young et al. Improving construction supply network visibility by using automated materials locating and tracking technology
US20160300195A1 (en) System and Method for Managing a Product Life Cycle
US20130253968A1 (en) Facility control system (fcs, c1) to manage assets planning, design, construction, fabrication, operating, maintence and products
US8527550B1 (en) Bridge inspection diagnostic system
US20050065839A1 (en) Methods, systems and computer program products for generating an aggregate report to provide a certification of controls associated with a data set
KR20100035481A (en) Real time construction management system and method using personal digital assistant(pda) being linked with geographic information system(gis)
CA2708694A1 (en) Compliance management system
KR102386500B1 (en) Plant pipe management system
Weeks et al. Facility defect and cost reduction by incorporating maintainability knowledge transfer using maintenance management system data
US20220244720A1 (en) Maintenance management method, maintenance management device and maintenance management program
Love et al. Object oriented modeling: Retrospective systems information model for constructability assessment
US20160140499A1 (en) Engineering document mobile collaboration tool
RU2726832C1 (en) Engineering data management system
CN112215510A (en) Method, device, equipment and storage medium for generating work priority of nuclear power plant
Board Tank waste remediation system characterization project quality policies
Gado et al. Work order management: a challenging tool towards successful hotel management
US20220405672A1 (en) System for management of facility construction and maintenance
Ali et al. Understanding the business process of reactive maintenance projects
Guven et al. Value of RFID technology in construction supply chains
Becotte et al. Significant change
Govan et al. Benchmarking natural gas pipeline projects