KR102281887B1 - Factory manufactured toilet module construction method using the ceiling slab opening of the building - Google Patents

Factory manufactured toilet module construction method using the ceiling slab opening of the building Download PDF

Info

Publication number
KR102281887B1
KR102281887B1 KR1020200151828A KR20200151828A KR102281887B1 KR 102281887 B1 KR102281887 B1 KR 102281887B1 KR 1020200151828 A KR1020200151828 A KR 1020200151828A KR 20200151828 A KR20200151828 A KR 20200151828A KR 102281887 B1 KR102281887 B1 KR 102281887B1
Authority
KR
South Korea
Prior art keywords
formwork
toilet module
installing
slab
factory
Prior art date
Application number
KR1020200151828A
Other languages
Korean (ko)
Inventor
이범호
Original Assignee
금강공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 금강공업 주식회사 filed Critical 금강공업 주식회사
Priority to KR1020200151828A priority Critical patent/KR102281887B1/en
Application granted granted Critical
Publication of KR102281887B1 publication Critical patent/KR102281887B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34807Elements integrated in a skeleton
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • E04G23/065Lifting of buildings

Abstract

The present invention relates to a construction method of lifting and installing a factory manufacturing toilet module through ceiling slab opening for simplifying site work of a toilet during construction of a building.

Description

건축물의 천장 슬래브 개방을 이용한 공장제작 화장실 모듈 시공방법{Factory manufactured toilet module construction method using the ceiling slab opening of the building}Factory manufactured toilet module construction method using the ceiling slab opening of the building

본 발명은 건축물 시공 시 화장실의 현장 작업의 간소화를 위하여 천장 슬래브(slab) 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법에 관한 것이다.The present invention relates to a construction method of lifting and installing a factory-made toilet module through opening a ceiling slab to simplify field work of a toilet during building construction.

일반적으로, 건축 구조물을 시공하기 위해서는, 다층의 콘크리트 건축물의 내, 외벽 거푸집과 슬래브(slab) 거푸집을 조립 설치하고 또 기둥 및 벽체의 철근과 슬래브의 철근을 배근 작업한 다음 시멘트 몰탈을 투입 충진하여 정해진 설계에 따라 콘크리트 건축물을 축조한다.In general, in order to construct a building structure, the inner and outer wall formwork and slab formwork of a multi-story concrete building are assembled and installed, and the reinforcing bars of columns and walls and the reinforcing bars of the slab are reinforced, and then cement mortar is put in and filled. Construct a concrete structure according to the specified design.

이와 같이 건축구조물의 골격이 완성되면 벽체로 구획된 공간별로 해당 공간의 기능이나 용도에 맞게 문, 창문, 수납공간, 조명, 장식물 등의 공간시설물과 상기 설비배관과 연결되는 설비들을 설치하여 주거공간을 형성한다.As such, when the skeleton of the building structure is completed, space facilities such as doors, windows, storage spaces, lighting, decorations, etc. and facilities connected to the facility and piping are installed according to the function or use of the space for each space partitioned by the wall to provide a residential space. to form

한편, 모듈러 공법(Modular Construction)은 공장에서 제작 및 조립된 3차원적인 상자형의 모듈 유닛을 현장으로 운반하여 조립하는 공법이다. 상기 모듈 유닛은 전기 및 기계설비, 창호를 포함한 내외장재, 바닥재, 천장재, 화장실이나 부엌의 기기 등을 포함한다. 이에 따라 모듈러 공법의 경우, 건축물의 70% 내지 90% 이상이 공장에서 완성된다.On the other hand, the modular construction method (Modular Construction) is a construction method that transports and assembles a three-dimensional box-shaped module unit manufactured and assembled in a factory to the site. The module unit includes electrical and mechanical equipment, interior and exterior materials including windows and doors, flooring materials, ceiling materials, and appliances for bathrooms and kitchens. Accordingly, in the case of the modular construction method, more than 70% to 90% of the building is completed in the factory.

이러한 모듈러 공법을 적용한 모듈러 건축물은 공장에서 제작된 각 모듈 유닛을 현장에서 상하, 전후, 좌우로 조립하여 완성된다. 이러한 모듈러 건축물은 공장 생산을 통한 품질의 향상과 인양 및 설치가 용이하여 현장시공 시 공기 단축을 통한 비용 절감의 효과가 있어 최근 다양한 유형의 건축물에 폭넓게 적용되고 있다.The modular building to which this modular construction method is applied is completed by assembling each module unit manufactured in the factory up and down, front and rear, left and right at the site. These modular buildings have been widely applied to various types of buildings in recent years because they have the effect of reducing costs through shortening of construction period during on-site construction by improving quality through factory production and easy lifting and installation.

종래의 콘크리트는 습식공정에 의해 타설되기 때문에 수분의 함량이 높아서 양생기간이 길다는 문제점과 겨울철에 재래식 시공 시 내부온도와 외부온도 차이로 인한 타일 들뜸 현상이나 콘크리트 시공에 따른 타일 깨짐 현상과 같은 습식 공사 문제점이 있다.Because conventional concrete is poured by a wet process, there is a problem that the curing period is long due to high moisture content. There is a construction problem.

예를들면, 물을 주로 사용하는 화장실의 경우, 현재 화장실은 습식 공법으로 현장 수작업에 의한 시공이 대부분으로 구성되어, 현장 기능공의 숙련도에 따라 품질이 결정되는데 현재 기능공 인력부족, 고령화로 인해 시공 품질이 문제가 되고 있다.For example, in the case of toilets that mainly use water, most of the current toilets are constructed using a wet construction method, and construction by on-site manual work is largely determined by the skill level of the on-site craftsmen. This is becoming a problem.

또한, 여러 공종(약 39개)이 투입되어 인력과 공종 투입 시기에 대한 소통이 어려워 시공 효율이 떨어지며, 여러 공종이 투입되므로 하자 발생 시 책임한계가 불명확하고 이에 따라 A/S가 늦어지게 되는 문제가 있으며, 제작이 어려워 시공비용이 많이 드는 단점이 있다.In addition, since several types of work (about 39) are put in, it is difficult to communicate with manpower and the timing of the input of the work type, so construction efficiency is lowered. Since multiple types of work are input, the limit of responsibility is unclear in case of a defect, and A/S is delayed accordingly. However, it is difficult to manufacture and has the disadvantage of high construction cost.

전술한 문제점을 해결하기 위한 본 발명이 이루고자 하는 기술적 과제는 세면대, 양변기, 샤워부스 등의 화장실 유닛을 공장에서 미리 제작되는 화장실 모듈을 이용하여 균일한 품질의 제품을 생산할 수 있으며, 재래식 습식공사에 대한 문제점을 해결할 수 있는, 빌딩 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법을 제공하기 위한 것이다.The technical problem to be achieved by the present invention for solving the above problems is that it is possible to produce products of uniform quality by using a toilet module that is pre-fabricated in a factory for a toilet unit such as a washbasin, a toilet, and a shower booth, and is suitable for conventional wet construction. It is to provide a construction method of lifting and installing a factory-made toilet module through opening of a ceiling slab during building construction, which can solve the problem of

또한, 본 발명이 이루고하 하는 다른 기술적 과제는, 화장실 모듈을 규격화 하여 하나의 모듈로 제작함으로써, 자동화된 공정에 따라 대량 생산을 통해 생산 단가를 절약할 수 있으며, 거의 모든 공정이 공사 현장이 아닌 공장에서 이루어짐으로써 불량률을 획기적으로 낮추어 품질의 향상시킬 수 있으며, 화장실 시공의 여러 공정을 화장실 모듈 제작하는 단일 업체에서 진행되므로 공사 관리가 수월해지고, 하자 발생시 책임한계가 명확하고 신속한 A/S 처리가 가능하며, 골조 공사와 함께 화장실 공사가 끝나므로 공기가 단축되는 건축물의 천장 슬래브 개방을 이용한 공장제작 화장실 모듈 시공방법을 제공하는데 있다.In addition, another technical problem to be achieved by the present invention is that by standardizing the toilet module and manufacturing it as one module, it is possible to save the production cost through mass production according to an automated process, and almost all processes are not at the construction site. As it is done in the factory, the defect rate can be dramatically lowered and the quality can be improved, and since the various processes of toilet construction are carried out by a single company that manufactures toilet modules, construction management becomes easier, and in case of defects, the limit of responsibility is clear and prompt A/S processing is possible. It is possible, and it is to provide a method of constructing a factory-made toilet module using the opening of the ceiling slab of a building that shortens the construction period because the toilet construction is completed together with the frame construction.

전술한 기술적 과제를 달성하기 위한 수단으로서, 본 발명에 따른 공장제작 화장실 모듈을 인양 및 설치하는 시공방법은, 화장실 모듈 유닛이 통과되기 위해 N층 천장부에 슬래브 개구가 형성되도록 콘크리트를 타설하는 제1 콘크리트 타설 단계;As a means for achieving the above-described technical problem, the construction method for lifting and installing the factory-made toilet module according to the present invention is a first method of pouring concrete so that a slab opening is formed in the ceiling of the N-floor for the toilet module unit to pass through. concrete pouring stage;

상기 N층 천장부의 슬래브 타설을 위해 기설치된 거푸집을 해제하는 거푸집 해제 단계; 상기 화장실 모듈을 인양하여 상기 슬래브 개구를 통과하여 N층에 화장실 모듈을 설치하는 인양 및 설치 단계; 상기 화장실 모듈과 접하는 부분에 거푸집을 설치하는 인접부 거푸집 설치 단계; 상기 N층 천장부 슬래브 개구에 철근을 배근하는 단계; 상기 N+1층의 벽체 철근과 천장부에 슬래브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계; 및 상기 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 포함하는 것을 특징으로 한다.a form release step of releasing the formwork previously installed for slab casting of the N-story ceiling part; a lifting and installation step of lifting the toilet module and installing the toilet module on the N-floor through the slab opening; Adjacent formwork installation step of installing a formwork in a portion in contact with the toilet module; Reinforcing reinforcing bars in the N-floor ceiling slab opening; Reinforcement reinforcement and formwork installation step of reinforcing slab reinforcement in the wall reinforcement and ceiling portion of the N+1 floor and installing a form; and a second concrete pouring step of pouring concrete at the location where the formwork is installed.

바람직하게는, 상기 철근 배근과 거푸집 설치 단계는, 화장실 모듈의 설치 여부에 따라, 슬래브 개구가 형성되도록 슬래브 철근 배근 및 거푸집을 설치하거나 슬래브 개구가 형성되지 않도록 선택하여 슬래브 철근 배근 및 거푸집을 설치할 수 있는 것을 특징으로 한다.Preferably, in the step of installing the reinforcement and formwork, depending on whether the toilet module is installed or not, the slab reinforcement and formwork may be installed so that the slab opening is formed, or the slab reinforcement and the formwork may be installed by selecting not to form the slab opening. characterized by having

더욱 바람직하게는, 상기 거푸집을 해제하는 단계 이후에, 상기 화장실 모듈이 설치되는 N층의 외벽 구간에 단열재를 설치하는 단열재 설치 단계를 더 포함하는 것을 특징으로 한다.More preferably, after the step of releasing the formwork, it characterized in that it further comprises a heat insulating material installation step of installing the heat insulating material in the outer wall section of the N-floor where the toilet module is installed.

또한 바람직하게는, 상기 제2 콘크리트 타설 단계 이후에, 상기 N층 천장부의 슬래브 타설을 위해 기설치된 거푸집을 해제하는 거푸집 해제 단계와 N층에 화장실 모듈을 설치하는 인양 및 설치 단계와 상기 화장실 모듈과 접하는 부분에 거푸집을 설치하는 거푸집 설치 단계와 상기 N층 천장부의 슬래브 개구에 철근을 배근하는 단계와 상기 N+1층의 벽체 철근과 슬라브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계 및 상기 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 반복적으로 실시하는 것을 특징으로 하는 한다.Also preferably, after the second concrete pouring step, a formwork release step of releasing the formwork previously installed for slab pouring of the N-floor ceiling portion, a lifting and installation step of installing a toilet module on the N-floor, and the toilet module; A formwork installation step of installing a formwork in a contact portion, a step of reinforcing reinforcing bars in the slab opening of the N-floor ceiling portion, a reinforcing bar and a formwork installation step of reinforcing the wall reinforcing bars and slab reinforcing bars of the N+1 floor and installing the formwork It is characterized in that the second concrete pouring step of pouring concrete at the location where the formwork is installed is repeatedly performed.

또한 바람직하게는, 상기 인접부 거푸집 설치 단계는, 공장제작 화장실 모듈에 데크 플레이트가 설치되기 용이하도록 공장제작 화장실 모듈 상부에 구비된 지지부와 상기 공장제작 화장실 모듈과 접하는 부분에 설치되는 인접부 거푸집이 맞닿아 배치되어 결합 핀에 의해 견고하게 결합되어 상호 지지되는 것을 특징으로 한다.Also preferably, in the step of installing the adjacent part formwork, the support part provided on the upper part of the factory-made toilet module and the adjacent part formwork installed at a part in contact with the factory-made toilet module are provided so that the deck plate can be easily installed on the factory-made toilet module. It is characterized in that it is abutted and is firmly coupled to each other by a coupling pin.

또한 바람직하게는, 상기 슬래브 개구는 상기 화장실 모듈이 용이하게 통과될 수 있도록 화장실 모듈 보다 더 크게 형성되는 것을 특징으로 한다.Also preferably, the slab opening is formed to be larger than the toilet module so that the toilet module can easily pass therethrough.

또한 바람직하게는, 상기 화장실 모듈 상부의 데크 플레이트는 상기 제2 콘크리트 타설 단계에서, 슬래브 개구 위치의 거푸집 역할을 하며, 데크 플레이트 상부에 콘크리트가 타설되는 것을 특징으로 한다.Also preferably, the deck plate above the toilet module serves as a formwork for the position of the slab opening in the second concrete pouring step, and the concrete is poured on the deck plate.

또한 바람직하게는, 상기 화장실 모듈 상부에 형성된 데크 플레이트는 데크 플레이트 철근을 구비하며; 상기 제2 콘크리트 타설 단계에서, 슬래브 개구 위치의 거푸집 역할을 하며; 상기 데크 플레이트 상부에 콘크리트가 타설되는 것을 특징으로 한다.Also preferably, the deck plate formed on the top of the toilet module is provided with a deck plate reinforcement; In the second concrete pouring step, it serves as a formwork for the slab opening position; It is characterized in that the concrete is poured on the upper deck plate.

본 발명에 따른 빌딩 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법은, 화장실 유닛을 공장에서 미리 제작되는 화장실 모듈을 이용하여 균일한 품질의 제품을 생산할 수 있으며, 재래식 습식공사에 대한 문제점을 해결할 수 있는 효과를 가진다.The construction method of lifting and installing the factory-made toilet module through the opening of the ceiling slab during building construction according to the present invention can produce a product of uniform quality using the toilet module pre-fabricated at the factory for the toilet unit, and the conventional wet It has the effect of solving problems on construction.

본 발명에 따르면, 화장실 시공의 여러 공정을 화장실 모듈 제작하는 단일 업체에서 진행되므로 공사 관리가 수월해지고, 하자 발생시 책임한계가 명확하고 신속한 A/S 처리가 가능한 효과를 가진다.According to the present invention, since the various processes of toilet construction are carried out by a single company that manufactures toilet modules, construction management becomes easy, and when defects occur, the limit of responsibility is clear and rapid A/S processing is possible.

본 발명에 따르면, 골조 공사와 함께 화장실 공사가 끝나므로 공기가 단축되며, 대량 생산이 가능하여 공사비가 절감되는 효과를 가진다.According to the present invention, since the toilet construction is completed together with the frame construction, the construction period is shortened, and mass production is possible, thereby reducing the construction cost.

도 1은 본 발명의 실시예에 따른 빌딩 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법을 나타내는 순서도이다.
도 2는 본 발명의 실시예에 따른 슬래브 개구가 형성되도록 콘크리트를 타설하는 제1 콘크리트 타설 단계를 나타내는 도면이다.
도 3은 본 발명의 실시예에 따른 기타설된 슬래브 개구가 있는 N층 천장부에 설치된 거푸집을 해제하는 단계를 나타내는 도면이다.
도 4는 본 발명의 실시예에 따른 외벽구간에 단열재를 시공하는 단열재 시공 단계를 나타내는 도면이다.
도 5 내지 도 7은 본 발명의 실시예에 따른 화장실 모듈 인양하여 슬래브 개구를 통과하여 화장실 모듈을 설치하는 인양 및 설치 단계를 나타내는 도면이다.
도 8은 본 발명의 실시예에 따른 화장실 모듈과 접하는 부분에 거푸집을 설치하는 거푸집 설치 단계를 나타내는 도면이다.
도 9는 본 발명의 실시예에 따른 공장제작 화장실 모듈과 인접부 거푸집 설치단계를 나타내는 도면이다.
도 10은 본 발명의 실시예에 따른 슬래브 개구에 철근을 배근하는 단계를 나타내는 도면이다.
도 11은 본 발명의 실시예에 따른 N+1층의 벽체 철근과 슬래브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계를 나타내는 도면이다.
도 12는 본 발명의 실시예에 따른 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 나타내는 도면이다.
1 is a flowchart illustrating a construction method of lifting and installing a factory-made toilet module through opening of a ceiling slab during building construction according to an embodiment of the present invention.
2 is a view showing a first concrete pouring step of pouring concrete so that a slab opening is formed according to an embodiment of the present invention.
Figure 3 is a view showing the step of releasing the formwork installed in the N-floor ceiling portion having a slab opening provided other according to an embodiment of the present invention.
4 is a view showing an insulating material construction step of constructing an insulating material in an outer wall section according to an embodiment of the present invention.
5 to 7 are views showing the lifting and installation steps of installing the toilet module through the slab opening by lifting the toilet module according to an embodiment of the present invention.
8 is a view showing a formwork installation step of installing a formwork in a portion in contact with the toilet module according to an embodiment of the present invention.
9 is a view showing a factory-made toilet module and adjacent formwork installation steps according to an embodiment of the present invention.
10 is a view showing the step of reinforcing reinforcing bars in the slab opening according to an embodiment of the present invention.
11 is a view showing the reinforcing bar and formwork installation step of reinforcing the wall reinforcing bars and slab reinforcing bars of the N+1 floor and installing the formwork according to an embodiment of the present invention.
12 is a view showing a second concrete pouring step of pouring concrete at the location where the formwork is installed according to an embodiment of the present invention.

본 발명의 동작상 이점 및 본 발명의 실시에 의하여 달성되는 목적을 충분히 이해하기 위해서는 본 발명의 바람직한 실시예를 예시하는 첨부도면 및 첨부도면에 기재된 내용을 참조하여야만 한다.In order to fully understand the operational advantages of the present invention and the objects achieved by the practice of the present invention, reference should be made to the accompanying drawings illustrating preferred embodiments of the present invention and the contents described in the accompanying drawings.

이하, 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대해 구성 및 작용을 상세히 설명하면 다음과 같다. 여기서, 각 도면의 구성요소들에 대해 참조부호를 부가함에 있어 동일한 구성요소들에 한해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 부호로 표기되었음에 유의하여야 한다.Hereinafter, the configuration and operation of the preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings. Here, in adding reference numerals to the components of each drawing, it should be noted that only the same components are marked with the same reference numerals as much as possible even though they are displayed on different drawings.

하기 실시예는 여러 가지 다른 형태로 변형될 수 있으며, 본 발명의 범위가 하기 실시예에 한정되는 것은 아니다.The following examples may be modified in various other forms, and the scope of the present invention is not limited to the following examples.

이하, 도 1 내지 도 12를 참조하여, 본 발명의 일 실시예들에 따른 빌딩 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법을 설명하기로 한다. Hereinafter, a construction method of lifting and installing a factory-made toilet module through opening of a ceiling slab during building construction according to embodiments of the present invention will be described with reference to FIGS. 1 to 12 .

먼저, 본 발명의 빌딩 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법 순서를 설명한다. First, the sequence of the construction method for lifting and installing the factory-made toilet module through the opening of the ceiling slab during the building construction of the present invention will be described.

본 발명의 실시예에 따른 공장제작 화장실 모듈을 인양 및 설치하는 시공방법은 먼저, 도 2 및 도 3에 도시된 바와 같이, 공장제작 화장실 모듈(100)이 설치되는 N층의 천장부(20)에 화장실 모듈(100)이 통과될 수 있도록 슬래브 개구(1)가 형성되도록 철근(10)을 배근하고 거푸집(30)을 설치한 상태에서 콘크리트가 타설되는 제1 콘크리트 타설 단계(S100)를 나타낸다.The construction method of lifting and installing the factory-made toilet module according to an embodiment of the present invention is first, as shown in FIGS. 2 and 3, on the ceiling portion 20 of the N-floor where the factory-made toilet module 100 is installed. It represents the first concrete pouring step (S100) in which the concrete is poured in a state in which the reinforcing bar 10 is reinforced and the formwork 30 is installed so that the slab opening 1 is formed so that the toilet module 100 can pass therethrough.

거푸집(30)은 콘크리트 타설 위치에 형성하는 것으로 거푸집(30) 또는 거푸집 돌출부(31)에 지지부(32)를 통해 지지하며, 조절부(34)를 통해 지지부의 지지 높이를 조절할 수 있으며, 지지판(33)을 통해 지지부(32)가 안정적으로 지지될 수 있도록 한다.The formwork 30 is formed at the concrete pouring position, and the formwork 30 or the formwork protrusion 31 is supported through the support part 32, and the support height of the support part can be adjusted through the adjustment part 34, and the support plate ( 33) so that the support part 32 can be stably supported.

거푸집 설치 방법에 대해서는 공지된 기술이므로 자세한 설명은 생략한다.Since the method for installing the formwork is a known technique, a detailed description thereof will be omitted.

다음으로, N층의 슬래브 천장부(20)의 슬래브 타설을 위해 기설치된 거푸집(30)을 해제한다(S110).Next, the formwork 30 previously installed for slab casting of the slab ceiling portion 20 of the N-layer is released (S110).

이어서, 도 5에 도시된 바와 같이, 화장실 모듈(100)을 타워 크레인(미도시)를 통해 화장실 모듈(100)의 상부 데크 플레이트(110)에 형성된 결합부(150)와 인양부(210)를 타워 크레인에 연결하여 인양하며, 도 6 및 도 7에 도시된 바와 같이, 슬래브 개구(1)를 상측에서 하측으로 통과하여 화장실 모듈(100)이 설치되는 N층의 설치 위치에 설치한다(S120).Then, as shown in Figure 5, the toilet module 100 through a tower crane (not shown) the coupling portion 150 and the lifting portion 210 formed on the upper deck plate 110 of the toilet module 100, It is connected to a tower crane and lifted, and as shown in FIGS. 6 and 7, it passes through the slab opening 1 from the top to the bottom and is installed at the installation location of the N floor where the toilet module 100 is installed (S120) .

화장실 모듈(100)은 바닥보와 천장보 바닥보와 천장보와 연결되는 기둥과 천장보 위에 데크 플레이트가 구비될 수 있다.The toilet module 100 may be provided with a deck plate on a column and a ceiling beam connected to the floor beam and the ceiling beam.

또한, 공장제작 화장실 모듈(100)의 천장보 상부에는 데크 플레이트(110)가 설치되기 용이하도록 후술될'ㄷ'자 형상의 골조인 지지부(105)가 일측과 타측에 구비될 수 있으며, 데크 플레이트(110)를 받쳐서 지지하는 형태로 구비되며, 'ㄷ'자 형상의 골조인 지지부(105) 상단에 데크 플레이트(110)가 설치되어 구비될 수 있다.In addition, on the upper part of the ceiling beam of the factory-made toilet module 100, a support part 105, which is a 'C'-shaped frame to be described later, may be provided on one side and the other side to facilitate installation of the deck plate 110, and the deck plate It is provided in a form to support and support (110), and the deck plate 110 may be installed on the upper end of the support part 105, which is a 'C'-shaped frame.

슬래브 개구(1)는 사각형 형태의 화장실 모듈(100)이 통과가 용이하도록 화장실 모듈(100)의 하단부 또는 상단부 둘레 보다 더 크게 형성되며, 화장실 모듈(100)의 하단부 또는 상단부의 둘레 보다 일정 간격의 여유가 형성될 수 있도록 개구(1)를 더 큰 크기로 형성하는 것이 바람직하나 그 크기와 모양은 제한되는 것은 아니다.The slab opening 1 is formed to be larger than the circumference of the lower or upper end of the toilet module 100 so that the rectangular toilet module 100 can pass easily, and is spaced apart from the circumference of the lower or upper end of the toilet module 100 at a predetermined interval. It is preferable to form the opening 1 in a larger size so that a margin can be formed, but the size and shape thereof are not limited.

즉, 화장실 모듈(100)의 크기에 따라서 슬래브 개구(1)의 크기는 조절할 수 있다.That is, the size of the slab opening 1 can be adjusted according to the size of the toilet module 100 .

다만, 슬래브 개구(1)가 너무 크게 형성되면 화장실 모듈(100)설치 후 화장실 모듈(100)과 슬래브 개구(1)의 사이 간격에 철근 배근과 거푸집 설치 및 콘크리트 타설 시공 작업 공간이 넓어 지므로 추가 시공을 위한 시간이 더 많이 소요되므로, 일정 간격을 두고 형성되도록 하는 것이 바람직하다.However, if the slab opening (1) is formed too large, the space between the toilet module (100) and the slab opening (1) after installation of the toilet module (100) becomes wider, so additional construction Since it takes more time for , it is preferable to form it at regular intervals.

이어서, 도 8에 도시된 바와 같이, 화장실 모듈(100)이 설치된 위치와 슬래브 개구(1)사이의 간격에 화장실 모듈(100)과 접하는 부분에 거푸집을 설치하는 인접부 거푸집 설치를 진행한다(S130).Next, as shown in FIG. 8, the adjacent part formwork installation of installing the formwork at the part in contact with the toilet module 100 at the interval between the location where the toilet module 100 is installed and the slab opening 1 is performed (S130) ).

인접부 거푸집은 기존의 거푸집과 동일한 형태로 접하는 부분에 설치되는 제1 인접부 거푸집(30-1)과 화장실 모듈(100)과의 단차(段差)에 따른 천장부 슬래브(20)와 화장실 모듈(100)의 높이에 맞게 콘크리트를 타설 할 수 있도록 거푸집을 설치하는 제2 인접부 거푸집(30-2)을 포함할 수 있다.The adjacent formwork has the same shape as the existing formwork, and the ceiling slab 20 and the toilet module 100 according to the step difference between the first adjacent formwork 30-1 and the toilet module 100, which are installed in the contacting part ) may include a second adjacent formwork (30-2) for installing the formwork so that the concrete can be poured according to the height.

도 9를 참조하면, 도 9(a)는 인접부 거푸집측에서 바라본 도면이고, 도 9(b)는 공장제작 화장실 모듈측에서 바라본 도면을 나타낸다.Referring to Figure 9, Figure 9 (a) is a view seen from the adjacent formwork side, Figure 9 (b) shows a view seen from the factory-made toilet module side.

공장제작 화장실 모듈(100)의 천장보 상부에는 데크 플레이트(110)가 설치되기 용이하도록 'ㄷ'자 형상의 지지부(105)가 일측과 타측에 구비될 수 있으며, 데크 플레이트(110)를 받쳐서 지지하는 형태로 구비되며, 'ㄷ'자 형상의 지지부(105) 상단에 데크 플레이트(110)가 설치되어 구비될 수 있다.A 'C'-shaped support 105 may be provided on one side and the other side to facilitate installation of the deck plate 110 on the upper part of the ceiling beam of the factory-made toilet module 100, and supports the deck plate 110 by supporting it. The deck plate 110 may be installed on the upper end of the 'C'-shaped support part 105 .

또한, 'ㄷ'자 형상의 지지부(105)에는 결합홀(미도시)이 구비될 수 있으며, 제2 인접부 거푸집(30-2)과 맞닿도록 배치되며, 제2 인접부 거푸집(30-2)에 형성된 결합홀(30a)에 결합핀(106)으로 체결되어 견고하게 결합되어 고정될 수 있다. In addition, a coupling hole (not shown) may be provided in the 'C'-shaped support part 105 , and disposed to contact the second adjacent part formwork 30-2, and the second adjacent part formwork 30-2. ) is fastened to the coupling hole 30a formed in the coupling pin 106 to be firmly coupled and fixed.

이것에 의해 공장제작 화장실 모듈(100)이 접하는 부분에 'ㄷ'자 형상의 지지부(105)와 제2 인접부 거푸집(30-2)가 맞닿아 견고하게 결합되어 상호 지지되도록 하여 콘크리트 타설 시 발생할 수 있는 측압을 견딜 수 있도록 견고하게 고정하는 것을 특징으로 한다.Thereby, the 'C'-shaped support part 105 and the second adjacent part form 30-2 are in contact with the part where the factory-made toilet module 100 is in contact and are firmly coupled to each other to support each other, which may occur during concrete pouring. It is characterized in that it is firmly fixed to withstand the possible lateral pressure.

거푸집(30) 또는 거푸집 돌출부(31)는 지지부(32)를 통해 지지되며, 지지부(32)는 조절부(34)에 의해 지지하는 높이를 조절할 수 있으며, 지지판(33)을 통해 지지부(32)가 안정되게 지지될 수 있다.The formwork 30 or the formwork protrusion 31 is supported through the support part 32 , and the support part 32 can adjust the height supported by the adjustment part 34 , and the support part 32 through the support plate 33 . can be stably supported.

다음으로, 도 10에 도시된 바와 같이, 슬래브 개구(1)에 콘크리트 타설을 위한 철근을 배근한다(S140).Next, as shown in Fig. 10, reinforcement for concrete pouring in the slab opening (1) (S140).

이때, 슬래브 개구(1)의 하부는 화장실 모듈(100)의 상부 데크 플레이트(110)이 거푸집 역할을 수행할 수 있으며, 데크 플레이트(110)에 구비된 데크 플레이트 철근(111)을 통해 슬래브 개구(1)에 철근을 배근하는 영역을 줄일 수 있어, 시공이 용이하도록 한다.At this time, in the lower portion of the slab opening 1, the upper deck plate 110 of the toilet module 100 may serve as a formwork, and through the deck plate reinforcement 111 provided in the deck plate 110, the slab opening ( 1) It is possible to reduce the area for reinforcing reinforcing bars, making construction easier.

따라서, 슬래브 개구(1)에 철근을 배근하고 거푸집은 추가로 설치하지 않을 수 있어, 시공이 용이하며 공기가 단축될 수 있다.Therefore, reinforcing bars are reinforced in the slab opening 1 and the formwork can not be additionally installed, so construction is easy and the construction period can be shortened.

이어서 화장실 모듈(100)이 설치된 N층 외에 추가로 설치되는지 여부를 확인한다(S150).Next, it is checked whether the toilet module 100 is installed in addition to the installed floor N (S150).

화장실 모듈(100)을 N+1 층에 추가로 설치하는 경우, 도 11 및 도 12에 도시된 바와 같이, N+1층의 천장부(200)에 슬래브 개구(1)가 형성(S155)되도록 N+1층의 벽체 철근과 천장부에 슬래브 철근을 배근하고 거푸집을 설치한다(S160).When the toilet module 100 is additionally installed on the N+1 floor, as shown in FIGS. 11 and 12, the slab opening 1 is formed (S155) in the ceiling 200 of the N+1 floor. Reinforce the slab reinforcement in the wall reinforcement and the ceiling of the +1 floor, and install the formwork (S160).

또한, N+1층에 화장실 모듈(100)이 추가 설치되는 경우, N층에 설치되는 화장실 모듈과 N+1층에 설치되는 화장실 모듈의 배관은 서로 연결될 수 있다.In addition, when the toilet module 100 is additionally installed on the N+1 floor, the pipes of the toilet module installed on the N floor and the toilet module installed on the N+1 floor may be connected to each other.

화장실 모듈(100)을 추가로 설치하지 않는 경우, 슬래브 개구(1)가 형성되지 않도록 벽체 철근과 슬래브 철근을 배근하고 거푸집을 설치한다(S160).If the toilet module 100 is not additionally installed, the wall reinforcement and the slab reinforcement are reinforced so that the slab opening 1 is not formed, and the formwork is installed (S160).

이어서, 데크플레이트(110)의 상부와 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 진행한다(S170).Next, a second concrete pouring step of pouring concrete on the upper portion of the deck plate 110 and the position where the formwork is installed (S170).

또한, 기설치된 거푸집을 해제하는 단계(S110) 이후에, 화장실 모듈(100)이 설치되는 N층의 외벽 구간에 단열재(15)를 설치하는 단열재 설치 단계를 더 포함할 수 있다.In addition, after the step of releasing the pre-installed formwork (S110), it may further include a heat insulating material installation step of installing the insulator 15 in the outer wall section of the N-floor where the toilet module 100 is installed.

또한, 화장실 모듈(100)의 벽타일(미도시)이 단열재를 포함하는 모듈로 구성된 경우에는 단열재 시공 단계를 생략할 수도 있다.In addition, when the wall tile (not shown) of the toilet module 100 is configured as a module including a heat insulating material, the insulating material construction step may be omitted.

또한, 제2 콘크리트 타설 단계(S170) 이후에, 추가로 화장실 모듈(100)을 설치시 천장부(20)의 슬래브 타설을 위해 기설치된 거푸집을 해제하는 거푸집 해제 단계(S110)와 화장실 모듈을 설치하는 인양 및 설치 단계(S120)와 화장실 모듈과 접하는 부분에 거푸집을 설치하는 인접부 거푸집 설치 단계(S130)와 N층 천장부의 슬래브 개구에 철근을 배근하는 단계(S140)와 화장실 모듈 추가 설치 여부를 확인하고(S150), N+1층의 벽체 철근과 슬라브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계(S160) 및 상기 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계(S170)를 반복적으로 실시할 수 있다.In addition, after the second concrete pouring step (S170), when the toilet module 100 is additionally installed, the formwork releasing step (S110) of releasing the pre-installed formwork for pouring the slab of the ceiling part 20 and installing the toilet module The lifting and installation step (S120) and the adjacent formwork installation step (S130) of installing the formwork in the portion in contact with the toilet module and the step of reinforcing reinforcing bars in the slab opening of the N-floor ceiling (S140) and additional installation of the toilet module and (S150), a second concrete pouring step (S170) of reinforcing reinforcement and formwork installation step (S160) of reinforcing wall reinforcing bars and slab reinforcing bars of the N+1 floor and installing a formwork (S160) and pouring concrete at the location where the formwork is installed (S170) can be repeatedly performed.

또한, 본 발명의 실시예에서는 화장실 모듈에 관하여, 설명하였으나 동일한 시공 방법을 통하여, 공장제작 모듈 내부에 다양한 공간 구성을 통해 대피공간, 발코니 등을 시공할 수 있도록 모듈을 구성할 수 있다.In addition, although the embodiment of the present invention has been described with respect to the toilet module, the module can be configured so that an evacuation space, a balcony, etc. can be constructed through various spatial configurations inside the factory-made module through the same construction method.

따라서, 본 발명에 따르면 건축물 시공 시 천장 슬래브 개방을 통해 공장제작 화장실 모듈을 인양 및 설치하는 시공방법은, 화장실 유닛을 공장에서 미리 제작되는 화장실 모듈을 이용하여 균일한 품질의 제품을 생산할 수 있으며, 재래식 습식공사에 대한 문제점을 해결할 수 있는 효과를 가진다.Therefore, according to the present invention, in the construction method of lifting and installing the factory-made toilet module through the opening of the ceiling slab during building construction, it is possible to produce a product of uniform quality using the toilet module manufactured in advance in the factory for the toilet unit, It has the effect of solving the problems of conventional wet construction.

또한, 화장실 시공의 여러 공정을 화장실 모듈 제작하는 단일 업체에서 진행되므로 공사 관리가 수월해지고, 하자 발생시 책임한계가 명확하고 신속한 A/S 처리가 가능하며, 골조 공사와 함께 화장실 공사가 끝나므로 공기가 단축되며, 대량 생산이 가능하여 공사비가 절감되는 효과를 가진다.In addition, since the various processes of toilet construction are carried out by a single company that manufactures toilet modules, construction management becomes easier, the limits of responsibility are clear and prompt A/S processing is possible in case of defects, and the construction of the toilet is completed together with the frame construction, so the construction period is reduced. It is shortened and has the effect of reducing the construction cost because mass production is possible.

본 발명은 상기 실시예에 한정되지 않고, 본 발명의 기술적 요지를 벗어나지 아니하는 범위 내에서 다양하게 수정 또는 변형되어 실시될 수 있음은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 있어서 자명한 것이다.The present invention is not limited to the above embodiments, and it is apparent to those skilled in the art that various modifications or variations can be implemented without departing from the technical gist of the present invention. did it

1: 슬래브 개구(slab open) 2: N 층 슬래브
10: 철근 15: 단열재
20: N 층 슬래브 천장부 30: 거푸집
31: 거푸집 돌출부 32: 지지부
33: 지지판 34: 조절부
100: 공장제작 화장실 모듈 110: 데크 플레이트(deck plate)
111: 데크 플레이트 철근 150: 결합부
200: N+1 층 슬래브 210: 인양부
1: slab open 2: N-layer slab
10: reinforcing bar 15: insulation material
20: N-floor slab ceiling 30: formwork
31: formwork protrusion 32: support part
33: support plate 34: control unit
100: factory-made toilet module 110: deck plate (deck plate)
111: deck plate reinforcement 150: coupling part
200: N+1 floor slab 210: lifting part

Claims (7)

화장실 모듈 유닛이 통과되기 위해 N층 천장부에 슬래브 개구가 형성되도록 콘크리트를 타설하는 제1 콘크리트 타설 단계;
상기 N층 천장부의 슬래브 타설을 위해 기설치된 거푸집을 해제하는 거푸집 해제 단계;
상기 화장실 모듈을 인양하여 상기 슬래브 개구를 통과하여 N층에 화장실 모듈을 설치하는 인양 및 설치 단계;
상기 화장실 모듈과 접하는 부분에 거푸집을 설치하는 인접부 거푸집 설치 단계;
상기 N층 천장부 슬래브 개구에 철근을 배근하는 단계;
상기 N+1층의 벽체 철근과 천장부에 슬래브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계; 및
상기 거푸집이 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 포함하며;
상기 화장실 모듈의 상부에는 데크 플레이트가 형성되며;
상기 데크 플레이트는 데크 플레이트 철근을 구비하고, 상기 제2 콘크리트 타설 단계에서, 슬래브 개구 위치의 거푸집 역할을 하며;
상기 데크 플레이트 상부에 콘크리트가 타설되는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
A first concrete pouring step of pouring concrete so that a slab opening is formed in the ceiling of the N-floor so that the toilet module unit passes;
a formwork release step of releasing the formwork previously installed for slab casting of the N-floor ceiling part;
a lifting and installation step of lifting the toilet module and installing the toilet module on the N-floor through the slab opening;
Adjacent formwork installation step of installing a formwork in a portion in contact with the toilet module;
Reinforcing reinforcing bars in the N-floor ceiling slab opening;
Reinforcement reinforcement and formwork installation step of reinforcing slab reinforcement in the wall reinforcement and ceiling portion of the N+1 floor and installing a form; and
a second concrete pouring step of pouring concrete at the location where the formwork is installed;
A deck plate is formed on the upper portion of the toilet module;
the deck plate is provided with deck plate reinforcement, and in the second concrete pouring step, serves as a formwork for the slab opening position;
A construction method for lifting and installing a factory-made toilet module, characterized in that concrete is poured on the deck plate.
청구항 1에 있어서,
상기 철근 배근과 거푸집 설치 단계는,
화장실 모듈의 설치 여부에 따라, 슬래브 개구가 형성되도록 슬래브 철근 배근 및 거푸집을 설치하거나 슬래브 개구가 형성되지 않도록 선택하여 슬래브 철근 배근 및 거푸집을 설치할 수 있는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
The method according to claim 1,
The reinforcing bar and formwork installation step,
Depending on whether the toilet module is installed or not, the slab reinforcement and formwork are installed so that the slab opening is formed, or the slab reinforcement and the formwork can be installed by selecting not to form the slab opening. Lifting and installing a factory-made toilet module, characterized in that construction method.
청구항 1에 있어서,
상기 거푸집을 해제하는 단계 이후에,
상기 화장실 모듈이 설치되는 N층의 외벽 구간에 단열재를 설치하는 단열재 설치 단계를 더 포함하는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
The method according to claim 1,
After releasing the formwork,
A construction method for lifting and installing a factory-made toilet module, characterized in that it further comprises the step of installing an insulator in the outer wall section of the N-floor where the toilet module is installed.
청구항 1 또는 청구항 2에 있어서,
상기 제2 콘크리트 타설 단계 이후에,
상기 N층 천장부의 슬래브 타설을 위해 기설치된 거푸집을 해제하는 거푸집 해제 단계와 N층에 화장실 모듈을 설치하는 인양 및 설치 단계와 상기 화장실 모듈과 접하는 부분에 거푸집을 설치하는 거푸집 설치 단계와 상기 N층 천장부의 슬래브 개구에 철근을 배근하는 단계와 상기 N+1층의 벽체 철근과 슬라브 철근을 배근하고 거푸집을 설치하는 철근 배근과 거푸집 설치 단계 및 상기 거푸집과 상기 화장실 모듈의 데크 플레이트가 설치된 위치에 콘크리트를 타설하는 제2 콘크리트 타설 단계를 반복적으로 실시하는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
The method according to claim 1 or 2,
After the second concrete pouring step,
A formwork release step of releasing the formwork previously installed for slab casting of the N-floor ceiling portion, a lifting and installation step of installing a toilet module on the N-floor, a formwork installation step of installing a formwork in a portion in contact with the toilet module, and the N-floor Reinforcement of reinforcement in the slab opening of the ceiling part and the reinforcement and formwork installation step of reinforcing the wall reinforcement and slab reinforcement of the N+1 floor and installing a formwork, and concrete at the position where the formwork and the deck plate of the toilet module are installed A construction method for lifting and installing a factory-made toilet module, characterized in that repeatedly performing the second concrete pouring step of pouring the
청구항 1에 있어서,
상기 인접부 거푸집 설치 단계는,
공장제작 화장실 모듈에 데크 플레이트가 설치되기 용이하도록 공장제작 화장실 모듈 상부에 구비된 지지부와 상기 공장제작 화장실 모듈과 접하는 부분에 설치되는 인접부 거푸집이 맞닿아 배치되어 결합 핀에 의해 견고하게 결합되어 상호 지지되는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
The method according to claim 1,
The adjacent formwork installation step,
In order to facilitate the installation of the deck plate on the factory-made toilet module, the support provided on the top of the factory-made toilet module and the adjacent mold installed on the part in contact with the factory-made toilet module are placed in contact and are firmly coupled by a coupling pin to each other. A construction method for lifting and installing a factory-made toilet module, characterized in that it is supported.
청구항 1에 있어서,
상기 슬래브 개구는 상기 화장실 모듈이 용이하게 통과될 수 있도록 화장실 모듈 보다 더 크게 형성되는 것을 특징으로 하는 공장제작 화장실 모듈을 인양 및 설치하는 시공방법.
The method according to claim 1,
The slab opening is a construction method for lifting and installing a factory-made toilet module, characterized in that it is formed larger than the toilet module so that the toilet module can pass easily.
삭제delete
KR1020200151828A 2020-11-13 2020-11-13 Factory manufactured toilet module construction method using the ceiling slab opening of the building KR102281887B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200151828A KR102281887B1 (en) 2020-11-13 2020-11-13 Factory manufactured toilet module construction method using the ceiling slab opening of the building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200151828A KR102281887B1 (en) 2020-11-13 2020-11-13 Factory manufactured toilet module construction method using the ceiling slab opening of the building

Publications (1)

Publication Number Publication Date
KR102281887B1 true KR102281887B1 (en) 2021-07-27

Family

ID=77125280

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200151828A KR102281887B1 (en) 2020-11-13 2020-11-13 Factory manufactured toilet module construction method using the ceiling slab opening of the building

Country Status (1)

Country Link
KR (1) KR102281887B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090107283A (en) * 2008-04-08 2009-10-13 김상준 Piece for deck plate
KR101116254B1 (en) * 2010-03-19 2012-03-09 깨뱉시스템주식회사 High-rise structure construction method by lifting up table-form
KR101389203B1 (en) * 2013-03-06 2014-04-24 도시구조안전(주) Method for constructing residential building using precast concrete and modular unit

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090107283A (en) * 2008-04-08 2009-10-13 김상준 Piece for deck plate
KR101116254B1 (en) * 2010-03-19 2012-03-09 깨뱉시스템주식회사 High-rise structure construction method by lifting up table-form
KR101389203B1 (en) * 2013-03-06 2014-04-24 도시구조안전(주) Method for constructing residential building using precast concrete and modular unit

Similar Documents

Publication Publication Date Title
EP1971727B1 (en) Construction of buildings
US11466445B2 (en) Integrated steel concrete building and construction method thereof
US20110113707A1 (en) Method and System of Building an ICF Residence
US20020005021A1 (en) Pre-cast concrete panels for construction of a building
JP2002004610A (en) Prefabricated bathroom
EP2149654A1 (en) Automatic system for construction of buildings
CA2801335C (en) Procedure for manufacturing of compact modules for construction
CN102230338A (en) Prefabricated toilet and construction method and installation method thereof
KR102281887B1 (en) Factory manufactured toilet module construction method using the ceiling slab opening of the building
CN102230339A (en) Prefabricated kitchen and construction and installation method thereof
KR102271151B1 (en) A Construction Method In Which A Factory Manufactured Toilet Module Is Lifted And The Installation Time Is Selected And Installed
KR102271152B1 (en) Manufacturing Method of Factory-made Integrated Toilet Module
KR102264712B1 (en) module type bathroom and building method using the same
CN107165332B (en) High-integration assembled enclosure wall board
US20100325992A1 (en) Access Floor and Installation Method Therefor
KR20060094068A (en) The finishing-insulation-board using construction for slab of ceiling and the slab structure of ceiling usig it and the construction method thereof
KR101854847B1 (en) the hybrid self-positioning connecting structure of column and beam for a horizontal extending a building
CN114108869B (en) Rammed-soil-imitated ancient wall and construction method thereof
JP3352043B2 (en) Floor structure
KR920004493B1 (en) Panel for heating system
KR102350985B1 (en) System for double insulation form and construction method thereof
JP3233938U (en) Precast board and the lowest floor structure using the precast board
CN219548070U (en) Assembled ceramic plate and gypsum pouring composite decoration integrated wall
JP2000080797A (en) Assembling method for water using unit in building to building frame by platform frame method
JP3062810B2 (en) Assembling method of plumbing unit in building and plumbing unit

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant