KR102214787B1 - Multi guide block and construction method of underground continuous wall using the same - Google Patents
Multi guide block and construction method of underground continuous wall using the same Download PDFInfo
- Publication number
- KR102214787B1 KR102214787B1 KR1020200105142A KR20200105142A KR102214787B1 KR 102214787 B1 KR102214787 B1 KR 102214787B1 KR 1020200105142 A KR1020200105142 A KR 1020200105142A KR 20200105142 A KR20200105142 A KR 20200105142A KR 102214787 B1 KR102214787 B1 KR 102214787B1
- Authority
- KR
- South Korea
- Prior art keywords
- plate
- guide block
- block
- block body
- guide
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Abstract
Description
본 발명은 지하연속벽을 구축할 때 연속되는 판넬과 판넬 사이의 연결부를 보강시킴으로써 지하연속벽의 차수성능과 내력을 향상시킬 수 있도록 상기 연결부에 설치되는 블록부재 및 이를 이용한 지하연속벽의 시공방법에 관한 것이다.The present invention is a block member installed in the connection portion to improve the ordering performance and strength of the underground continuous wall by reinforcing the connection between the panel and the panel when constructing the underground continuous wall, and a construction method of the underground continuous wall using the same It is about.
지중에 지하건축물을 구축하고자 하여 지반을 굴착하게 되는 경우 굴착면이 붕괴되는 것을 방지하고 지하수가 작업공간 내부로 흘러 들어오는 것을 방지하기 위하여 흙막이 벽체를 설치한다.If the ground is to be excavated to build an underground building in the ground, an earthen wall is installed to prevent the collapse of the excavation surface and to prevent groundwater from flowing into the working space.
이러한 흙막이 벽체의 시공은 지반의 조건과 지하건축물의 규모 등의 작업 환경 내지 조건에 따라 다양한 공법이 적용될 수 있는데, 그 중 슬러리월(slurry wall) 공법 또는 D-wall 공법으로도 불리는 지하연속벽 공법에 의해 구축된 벽체는 차수성과 강성이 매우 높아 본 구조물의 영구벽체로 사용될 수 있기 때문에 특히 도심지의 대규모 공사 또는 지하수가 많이 용출되는 대심도 공사에서 많이 이용되고 있다.Various construction methods can be applied according to the working environment or conditions, such as ground conditions and the scale of the underground building, for the construction of such earthing walls. Among them, the underground continuous wall construction method, also called the slurry wall construction method or the D-wall construction method. The wall constructed by the structure has very high water-repellency and rigidity and can be used as a permanent wall of this structure, so it is particularly widely used in large-scale construction in urban areas or large depth constructions where a lot of groundwater flows out.
지하연속벽 공법은 지중 굴착을 통해 트렌치를 형성하고, 트렌치 내부에 철근망을 설치한 후, 콘크리트를 타설하여 선행 패널을 구축하고, 다시 구축된 패널에 연장하여 트렌치를 형성한 후 철근망을 설치하고 여기에 콘크리트를 타설하여 후행 패널을 구축하는 방식으로 이루어진다.In the underground continuous wall construction method, a trench is formed through underground excavation, a reinforcing bar network is installed inside the trench, concrete is poured to build a preceding panel, and a trench is formed by extending the rebuilt panel, and then a rebar network is installed. And it is done by pouring concrete here to build a trailing panel.
따라서 선행 패널과 후행 패널 사이의 이음부는 취약부가 되어 지하수의 누출 통로가 되기도 하는 바, 이러한 문제점을 해결하기 위하여 선행 패널과 후행 패널의 이음부에 차수판을 설치하여 지하연속벽의 차수능력을 향상시키고자 하는 노력이 지속되고 있다.Therefore, the joint between the preceding panel and the following panel becomes a weak part and becomes a passage for groundwater leakage.In order to solve this problem, a water shield plate is installed at the joint of the preceding panel and the succeeding panel to improve the ordering capacity of the underground continuous wall. Efforts to make it continue.
예컨대 등록특허공보 등록번호 10-1051965호는 도 1에 도시된 패널조인트(100)를 이용하여 선행 콘크리트 단위패널(200)과 후행 콘크리트 단위패널(300)의 이음부 사이에 차수판(110)이 설치되도록 한다.For example, Patent Publication No. 10-1051965 uses the
이에 관한 구체적인 시공은 도 2에 도시된 바와 같이, a) 차수판(110)이 삽입된 패널조인트(100)를 굴착공간의 일측면에 설치하고, 상기 굴착공간에 콘크리트를 타설하여 철근콘크리트 구조의 선행 콘크리트 단위패널(200)을 구축한 후, b) 인접지반을 굴착하여 후행 콘크리트 단위패널(300)의 구축을 위한 후행의 굴착공간을 확보하고, 이에 의해 노출된 패널조인트(100)를 차수판(110)과 분리시켜 제거하며, c) 상기 후행의 굴착공간에 다시 철근망을 설치하고 콘크리트를 타설하여 선행 콘크리트 단위패널(200)에 일측이 매립된 차수판(110)이 후행콘크리트 단위패널(300)에 매립되도록 함으로써 선행 콘크리트 단위패널(200)과 후행콘크리트 단위패널(300) 사이의 이음부에 차수판(110)이 설치되도록 한다.As shown in Fig. 2, a) the
그런데 등록번호 10-1051965호에 의한 상기한 이음부는, 선행 콘크리트 패널(200)과 후행 콘크리트 패널(300) 사이를 양 단면이 접하도록 단순이음하면서 그 사이에 차수판(110)만이 설치된 것이어서, 구조적으로 매우 취약할 뿐 아니라, 그 이음부의 이음상태를 확인하는 것도 쉽지 아니하여 하다.However, the above-described joint according to Registration No. 10-1051965 is a simple connection between the preceding
예컨대 선행 콘크리트 패널(200)과 후행 콘크리트 패널(300)은 콘크리트 타설 시점이 다르기 때문에 양생과정 중의 건조수축의 정도에 차이가 있고, 이로 인하여 이음부에 공극이 발생할 여지가 있다.For example, the preceding
또한 선행 콘크리트 패널(200)과 후행 콘크리트 패널(300) 사이의 이음부는 무근콘크리트 구조로 이루어져 있어 지하연속벽의 배면토압이나 지진 등의 진동이 발생할 경우 응력집중이 이루어져 파손되면서 차수성능을 잃을 수 있게 되는 문제점이 있다.In addition, the joint between the preceding
본 발명은 종래기술의 상기한 문제점을 해결하기 위하여 안출된 것으로서, 지하연속벽을 구성하는 패널과 패널사이를 구조적으로 일체화시킴과 더불어, 이들 패널사이의 이음부를 파일화하여 강성을 증대시킴으로써, 지하연속벽의 차수구조가 파괴되지 않는 멀티가이드블록 및 이를 이용한 지하연속벽의 시공방법을 제공하고자 한다.The present invention was conceived to solve the above-described problems of the prior art. In addition to structurally unifying the panels constituting the underground continuous wall and the panels, the joints between these panels are piled to increase rigidity, It is intended to provide a multi-guide block in which the order structure of the continuous wall is not destroyed, and a construction method of the underground continuous wall using the same.
또한 본 발명은 지하연속벽의 깊이가 매우 깊어 차수구조의 길이가 길어지더라도 차수구조의 연속성을 유지시킬 수 있어 신뢰성 있는 고품질 차수구조를 가지게 하는 멀티가이드블록 및 이를 이용한 지하연속벽의 시공방법을 제공하고자 한다.In addition, the present invention provides a multi-guide block for maintaining the continuity of the order structure even if the length of the order structure becomes longer due to the very deep depth of the underground continuous wall, and a method of constructing the underground continuous wall using the same. I want to provide.
상기한 과제를 해결하기 위한 본 발명의 가장 바람직한 실시예에 의하면, 가이드블록과, 상기 가이드블록에 분리 가능하도록 결합되며 지하연속벽을 형성하는 패널과 패널 사이의 이음부에 매립되는 멀티플레이트로 이루어지며, 상기 멀티플레이트에는 전후 양방향으로 차수판과 이음봉이 각각 설치되어 있는 것을 특징으로는 멀티가이드블록이 제공된다.According to the most preferred embodiment of the present invention for solving the above problems, it consists of a guide block and a multi-plate that is detachably coupled to the guide block and is buried in the joint between the panel and the panel forming an underground continuous wall. The multi-plate is provided with a multi-guide block, characterized in that the shield plate and the connecting rod are respectively installed in both front and rear directions.
여기에서 상기 가이드블록은, 상하 양 단부에 위치한 한 쌍의 단부판과 좌우 양 측부에 위치한 한 쌍의 측판이 결합되어 구성되는 블록몸체와, 상기 블록몸체의 후방에 위치하면서 블록몸체의 양 측으로 돌출편이 형성되도록 한 지지외판으로 이루어지지게 하고, 상기 돌출편에는 파지대가 설치되어 측판과 파지대 사이에 끼움슬릿이 형성되게 하며, 상기 멀티플레이트는, 끼움고정판과 이에 수평절곡된 지지내판으로 이루어지는 하프플레이트의 한 쌍이 결합되어 구성되어, 상기 끼움슬릿에 끼움고정판이 삽입됨으로써 멀티플레이트가 가이드블록에 분리가능하도록 결합되게 할 수 있다.Here, the guide block includes a block body formed by combining a pair of end plates located at both ends of the upper and lower ends and a pair of side plates located at both left and right sides, and protruding to both sides of the block body while being located at the rear of the block body. It is made of a supporting outer plate so that a piece is formed, and a gripper is installed on the protruding piece to form a fitting slit between the side plate and the gripper, and the multi-plate is a half consisting of a fitting fixing plate and a horizontally bent support inner plate. A pair of plates are combined and configured, and a fitting fixing plate is inserted into the fitting slit so that the multi-plate may be detachably coupled to the guide block.
또한, 상기 파지대는, 지지외판에 고정되는 지지편과, 상기 지지편에서 연장 절곡되어 단부가 자유단인 가압편으로 이루어지는, 탄성부재로 구성시켜 끼움고정판을 가압 고정되게 할 수 있다.In addition, the gripper may be constituted of an elastic member comprising a support piece fixed to the support shell plate and a pressing piece extending from the support piece and having a free end portion thereof, so that the fitting fixing plate is pressed and fixed.
또한, 상기 블록몸체의 일측 단부판에는 연결봉이 설치되고, 상기 블록몸체의 타측 단부판에는 연결봉이 삽입되는 연결홀이 구비되게 하여, 복수 개의 멀티가이드블록을 이음 연결하거나 멀티가이드블록에 조립용 헤드의 설치를 용이하게 할 수 있다.In addition, a connecting rod is installed on one end plate of the block body, and a connection hole into which the connecting rod is inserted is provided in the other end plate of the block body, so that a plurality of multi-guide blocks are jointly connected or a head for assembly to the multi-guide block. Can be easily installed.
또한, 상기 블록몸체의 측판과 하프플레이트의 끼움고정판에는 상호 일치하는 내외측 작업개구를 각 설치하여 상기한 멀티가이드블록의 이음 연결 및 조립용 헤드의 설치작업을 용이하게 할 수 있다.In addition, the side plate of the block body and the fitting fixing plate of the half plate are provided with internal and external working openings that match each other to facilitate the joint connection of the multi-guide block and the installation of the assembly head.
또한, 상기 블록몸체의 측판과 하프플레이트의 끼움고정판에 상호 일치하는 내외측 핀고정공을 각 구비시키고, 잠금핀으로 하여금 상기 내외측 핀고정공을 함께 통과하여 고정되게 함으로써, 가이드블록에 설치된 멀티플레이트가 분리되지 않게 할 수 있다.In addition, by providing each of the inner and outer pin fixing holes coincident with the side plate of the block body and the fitting fixing plate of the half plate, and allowing the locking pin to pass through the inner and outer pin fixing holes together, You can prevent the plate from separating.
또한, 상기 하프플레이트의 끼움고정판에 봉삽입공이 구비되게 하여, 상기 봉삽입공에 삽입된 압착봉과 이에 체결되는 가압너트에 의해 상호 대향한 하프플레이트들 사이간극이 좁아지면서 차수판이 고정 설치되게 할 수 있다.In addition, a sealing plate may be provided with a sealing hole in the fixing plate of the half plate, so that the gap between the half plates opposite to each other is narrowed by the pressing rod inserted into the sealing hole and the pressing nut fastened thereto, so that the water shield plate can be fixedly installed. have.
본 발명의 또 다른 실시예에 의하면, 상기한 멀티가이드블록을 이용한 것으로서, a) 지반을 굴착하여 선행 패널 구축을 위한 선행 트렌치를 형성시키는 단계; b) 선행 트렌치 내부의 전후방 양 측 내면 중 적어도 어느 한 내면에 멀티가이드블록을 설치하는 단계; c) 상기 선행 트렌치 내부에 철근망을 삽입하고, 콘크리트를 타설하는 단계; d) 상기 멀티가이드블록의 블록몸체가 노출되도록 후행 패널 구축을 위한 후행 트렌치를 형성시키는 단계; e) 상기 멀티가이드블록의 블록몸체와 멀티플레이트를 분리시켜, 블록몸체를 제거하는 단계; f) 후행 트렌치 내부에 철근망을 삽입하고, 콘크리트를 타설하는 단계;가 포함되어 이루어지는 것을 특징으로 지하연속벽의 시공방법이 제공된다.According to another embodiment of the present invention, the multi-guide block is used, comprising: a) excavating the ground to form a preceding trench for building a preceding panel; b) installing a multi-guide block on at least one of the front and rear inner surfaces of the preceding trench; c) inserting a reinforcing bar net into the preceding trench and pouring concrete; d) forming a trailing trench for building a trailing panel so that the block body of the multi-guide block is exposed; e) removing the block body by separating the block body and the multi-plate of the multi-guide block; f) inserting a reinforcing bar net into the trailing trench and pouring concrete; a method of constructing an underground continuous wall is provided.
본 발명은 패널과 패널 사이의 이음부에 멀티플레이트 및 이음봉이 설치되어 독립된 강성을 가지는 파일 형상의 구조체가 형성되면서 양측 패널에 대하여 높은 전단연결체 기능을 함으로써, 각 패널들이 일체적 거동을 하게 됨과 더불어 상기 이음부에서 균열이 발생할 여지가 없게 되므로, 이에 의해 구축된 지하연속벽은 매우 높은 차수성능과 함께 높은 내력을 가진 외벽체의 기능을 할 수 있게 한다.In the present invention, a multi-plate and a joint bar are installed at the joint between the panel and the panel to form a pile-shaped structure having independent rigidity, and function as a high shear connector for both panels, so that each panel has an integral behavior. In addition, since there is no room for cracks to occur at the joints, the underground continuous wall constructed thereby can function as an outer wall having a very high order performance and high strength.
또한 본 발명은 멀티가이드블록을 복수 개 이음 연결하는 것이 용이할 뿐 아니라, 이음 연결된 각 멀티가이드블록 사이가 연결봉 및 체결수단에 의해 높은 일체성을 가지게 되고, 요홈 및 돌기 또는 연결공에 의해 차수판의 연속성을 유지시킬 수 있어, 지하연속벽이 구축되는 모든 깊이에 대하여 쉽게 적용할 수 있는 범용성 및 신뢰성을 가지게 한다. 아울러 이러한 이음 연결작업이 트렌치의 외부에서 이루어지기 때문에 안전성 및 작업성이 향상되어 정밀 작업을 도모할 수 있게 한다.In addition, in the present invention, it is not only easy to connect a plurality of joints of the multi-guide blocks, but also have high integrity between the multi-guide blocks connected by the joints by means of a connecting rod and a fastening means, and As it can maintain the continuity of the underground continuous wall, it has versatility and reliability that can be easily applied to all depths at which the underground continuous wall is constructed. In addition, since this joint connection operation is performed outside the trench, safety and workability are improved, thereby enabling precision work.
또한 본 발명의 가이드블록은 패널의 콘크리트에 접하게 되는 부분이 최소화된 상태로 설치 및 제거되므로, 회수후 재사용을 위한 청소 등의 노력을 최소화시켜 경제적인 반복 사용을 가능하게 한다.In addition, since the guide block of the present invention is installed and removed in a state in which the part that comes into contact with the concrete of the panel is minimized, the effort such as cleaning for reuse after recovery is minimized, thereby enabling economical repeated use.
도 1은 종래기술에 의해 패널과 패널 사이의 이음부에 차수판을 설치하기 위한 패널조인트의 단며도이다.
도 2는 상기 패널조인트를 이용한 지하연소벽의 시공방법에 관한 설명도이다.
도 3은 본 발명의 일 실시예에 의한 멀티가이드블록의 사시도이다.
도 4는 상기 멀티가이드블록의 분해사시도이다.
도 5은 4의 A와 B부분에 대한 확대사시도이다.
도 6은 본 발명의 조립용 헤드의 사시도이다.
도 7은 본 발명의 멀티플레이트를 상하부에서 각 바라본 사시도이다.
도 8은 본 발명의 일 실시예에 의한 파지대의 작동관계에 관한 설명도이다.
도 9는 본 발명의 일 실시예에 의한 잠금수단의 작동관계에 관한 설명도이다.
도 10은 본 발명의 차수판 설치구조에 관한 설명도이다.
도 11, 12는 본 발명의 차수판 구조에 관한 또 다른 실시예의 사시도이다.
도 13 내지 21은 본 발명의 멀티가이드블록을 이용한 지하연속벽의 시공방법에 관한 각 단계의 수직 및 수평단면도이다.1 is a cross-sectional view of a panel joint for installing a water shield plate at a joint between a panel and a panel according to the prior art.
2 is an explanatory view of a method of constructing an underground combustion wall using the panel joint.
3 is a perspective view of a multi-guide block according to an embodiment of the present invention.
4 is an exploded perspective view of the multi-guide block.
5 is an enlarged perspective view of portions A and B of 4;
6 is a perspective view of the assembly head of the present invention.
7 is a perspective view of the multiplate of the present invention as viewed from above and below.
8 is an explanatory diagram of an operation relationship of a gripper according to an embodiment of the present invention.
9 is an explanatory view of the operation relationship of the locking means according to an embodiment of the present invention.
Fig. 10 is an explanatory diagram of a water shield plate installation structure according to the present invention.
11 and 12 are perspective views of still another embodiment of the structure of the shield plate of the present invention.
13 to 21 are vertical and horizontal cross-sectional views of each step of the method for constructing an underground continuous wall using a multi-guide block of the present invention.
이하에서는 본 발명의 실시 예를 첨부된 도면을 참조하여 상세히 설명한다. 그러나 본 발명을 설명함에 있어 공지의 구성을 구체적으로 설명함으로 인하여 본 발명의 기술적 사상을 흐리게 하거나 불명료하게 하는 경우에는 위 공지의 구성에 관한 설명을 생략하기로 한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. However, in the case of obscuring or obscuring the technical idea of the present invention due to a detailed description of a known configuration in the description of the present invention, a description of the known configuration will be omitted.
도 3은 본 발명의 일 실시예에 의한 멀티가이드블록(MB)의 외관을 전체적으로 도시한 것이고, 도 4는 상기 멀티가이드블록(MB)을 분해하여 도시한 것이다.3 is an overall view of the multi-guide block MB according to an embodiment of the present invention, and FIG. 4 is an exploded view of the multi-guide block MB.
본 발명의 멀티가이드블록(MB)은 지하연속벽을 구축하기 위하여 연속된 패널(P1,P2)을 구축할 때, 굴착된 트렌치(T1,T2)의 전방 내지 후방에 설치되어 패널(P1)과 패널(P2) 사이의 이음부(J)에서 지하수가 침투하는 것을 방지하는 차수기능과 더불어, 각 패널(P1,P2)간에 강결합된 구조적 연속성을 가질 수 있도록 하는 것으로서, 도 3, 4에서 보여지는 바와 같이, 가이드블록(10)과 멀티플레이트(30)로 이루어진다.The multi-guide block (MB) of the present invention is installed in front or rear of the excavated trenches (T1, T2) when constructing the continuous panels (P1, P2) to build the underground continuous wall, and the panel (P1) and In addition to the order function to prevent the penetration of groundwater in the joint (J) between the panels (P2), and to have a structural continuity strongly coupled between the panels (P1, P2), as shown in Figs. As it is lost, it consists of a
가이드블록(10)은, 멀티플레이트(30)가 패널(P1,P2)간의 이음부(J)에 매립 설치되도록 이를 안내하는 한편 패널(P1,P2)의 구축이 완료될 때까지 멀티플레이트(30)를 지지하는 것으로서, 어느 한 패널의 구축이 완료되면 회수된 후 다른 패널의 구축을 위하여 반복 재사용된다.The
이러한 가이드블록(10)은, 도 3에 도시된 바와 같이, 멀티플레이트(30)의 탈착을 안내하는 블록몸체(10A)와 상기 블록몸체(10A)를 지지하는 지지외판(10B)으로 이루어진다. 그 중 블록몸체(10A)는 상하 양 단부에 위치한 한 쌍의 단부판(11)과 좌우 양 측부에 위치한 한 쌍의 측판(12)이 결합되어 전후방이 모두 개방되는 장방향의 사각 띠판 형상을 가진다. 이에 지지외판(10B)은 블록몸체(10A) 후방의 개방된 부분을 폐쇄시키는 판상구조의 형상을 가지면서, 상기 블록몸체(10A)의 양 측으로 돌출편(19)을 형성하여 후술하는 파지대(20)의 설치면을 제공한다. 단부판(11)가 측판(12)에 의해 형성된 블록몸체(10A)의 내부공간에는 보강벽(18)이 더 설치될 수 있다.As shown in FIG. 3, the
도 5은 상기한 블록몸체(10A)에 관한 구체적인 실시예를 설명하기 위하여 도 4의 A와 B부분을 확대한 것이다.5 is an enlarged view of portions A and B of FIG. 4 in order to explain a specific embodiment of the
블록몸체(10A)의 양측 단부판(11)에는 체결공(15a,15b)이 각 구비된다. 상기 체결공(15a,15b)은 상부에 위치한 멀티가이드블록(MB)의 하단과 하부에 위치한 멀티가이드블록(MB)의 상단을 체결수단으로 체결하게 함으로써, 이들 상하부의 멀티가이드블록(MB)이 구조적으로 일체가 되게 하는 결합수단이 된다.Fastening
아울러, 블록몸체(10A)의 일측 단부판(11)에는 도 5의 (a)에서와 같이 외측으로 돌출된 연결봉(13)이 설치된다. 또한 상기 연결봉(13)에 대응하여 블록몸체(10A)의 타측 단부판(11)에도 도 5의 (b)에서와 같이 상기 연결봉(13)이 삽입되는 연결홀(14)이 구비된다.In addition, a connecting
이러한 연결봉(13)과 연결홀(14)은 멀티가이드블록(MB)의 복수 개가 이음 연결되어 사용될 때, 멀티가이드블록(MB) 상호간의 연결작업이 보다 정확하고 간단하게 이루어질 수 있도록 이들의 결합과정을 안내한다.When a plurality of the connecting
즉 상하부 멀티가이드블록(MB) 사이의 체결공(15a,15b) 체결은 어느 일측 멀티가이드블록(MB)의 연결봉(13)이 타측 멀티가이드블록(MB)의 연결홀(14)에 삽입된 상태에서 이루어지게 되는데, 연결봉(13)이 연결홀(14)에 삽입되면 상기의 각 대응 체결공(15a,15b)들이 자연스럽게 상호 일치하게 되고 그에 따라 체결작업은 쉽게 진행될 수 있게 된다.That is, the
또한 멀티가이드블록(MB)을 트렌치(T1,T2) 내부에 삽입하여 설치하거나 가이드블록(10)을 제거할 때 이들을 현수할 수 있도록 상기 멀티가이드블록(MB)의 상단, 구체적으로 가이드블록(10)의 상단에 후술하는 조립용 헤드(60)가 설치된다. 이때에도 상기의 연결봉(13)은 조립용 헤드(60)의 삽입홀(61)에 삽입되면서 블록몸체(10A)의 단부판(11)에 구비된 체결공(15a)과 조립용 헤드(60)에 구비된 체결공(62)을 상호 일치시킴으로써 이들 사이의 결합작업을 용이하게 한다.In addition, the upper end of the multi-guide block (MB), specifically the guide block (10), so that the multi-guide block (MB) is inserted into the trench (T1, T2) to be installed or the guide block (10) is removed. The
지지외판(10B)의 돌출편(19)에는 거치공(19a)가 더 구비될 수 있다. 상기 거치공(19a)는 상기 돌출편(19)의 상하부 중 적어도 어느 한쪽에 구비되어, 복수 개의 멀티가이드블록(MB)이 이음 연결되어야 할 경우, 트렌치(T1,T2)에 먼저 삽입되는 하부의 멀티가이드블록(MB) 상부가 트렌치(T1,T2)의 외부로 돌출된 상태에서 이음 연결작업을 할 수 있게 함으로써, 멀티가이드블록(MB)들 사이의 이음 연결작업이 안전하고 효율적으로 이루어질 수 있게 한다. 이에 관한 구체적인 사항은 후술하는 지하연속벽의 시공방법과 관련하여 설명한다.A mounting
도 6은 상술한 조립용 헤드(60)에 관한 일 실시예를 도시한 것이다.6 shows an embodiment of the above-described
조립용 헤드(60)는 상술한 바와 같이 멀티가이드블록(MB)을 트렌치(T1,T2)에 설치하거나 그 중 가이드블록(10)을 제거할 때 이들을 양중하거나, 복수 개의 멀티가이드블록(MB)을 상호 이음 연결시킬 때 상부의 멀티가이드블록(MB)을 현수시킬 수 있도록 하는 것으로서, 삽입홀(61) 및 체결공(62)이 각 구비된 접합편(60A)과, 상기 접합편(60A)에 수직으로 설치되며 현수홀(63)이 구비된 현수편(60B)으로 이루어진다.As described above, the
상기 삽입홀(61)에는 연결봉(13)이 삽입된다. 또한 상기 접합편(60A)에 구비된 체결공(62)은, 접합편(60A)과 블록몸체(10A)의 단부판(11)이 정위치에서 맞접하게 되면, 상기 단부판(11)에 구비된 각 대응 체결공(15a)과 그 위치가 일치하게 된다. 따라서 작업자는, 복수 개의 멀티가이드블록(MB)을 연결하는 작업과 마찬가지로, 블록몸체(10A)의 단부판(11)에 설치된 연결봉(13)을 조립용 헤드(60)의 삽입홀(61)에 삽입시킨 후, 단부판(11)과 접합편(60A)에 각 구비된 체결공(15a,62))에 대한 별도의 맞춤작업을 하지 않고서도 즉시 체결작업을 할 수 있게 된다.The connecting
접합편(60A)과 현수편(60B) 사이에는 보강편(60C)이 더 설치될 수 있다.A reinforcing piece (60C) may be further installed between the joining piece (60A) and the suspension piece (60B).
한편 상기한 체결공(15a,15b,62))에 대한 체결작업을 위해서는 블록몸체(10A) 내부로 작업자의 손 내지 공구가 진입될 필요가 있게 되는바, 이를 위하여 블록몸체(10A)의 측판(12)에는 내측작업개구(16)가 구비된다. 따라서 작업자는 상기 내측작업개구(16)를 통해 작업공구를 블록몸체(10A) 내부에 삽입함으로써 상부 멀티가이드블록(MB)과 하부 멀티가이드블록(MB) 사이의 일체화 작업을 쉽게 할 수 있게 된다. 물론 후술하는 멀티플레이트(30)의 끼움고정판(31)에도 상기한 내측작업개구(16)와 일치하는 외측작업개구(35)가 구비되어야 한다.On the other hand, for the fastening work for the
도 7은 멀티플레이트(30)를 상하부에서 각 바라본 것이다. 상기 멀티플레이트(30)는 가이드블록(10)에 분리 가능하도록 결합되는 것으로서, 패널(P1)과 패널(P2) 사이의 이음부(J)에 매립되어 파일 형상의 구조체를 형성하여 이음부(J)의 강성을 증대시키면서 각 패널(P1,P2)들이 일체적으로 거동할 수 있도록 전단연결체의 기능을 한다. 아울러 멀티플레이트(30)는 차수판(50)이 상기 이음부(J) 내부의 정위치에 설치될 수 있게 하는 가이드의 역할도 한다.7 is a view of the multi-plate 30 from the top and bottom. The multi-plate 30 is detachably coupled to the
이러한 멀티플레이트(30)는, 끼움고정판(31)과 이에 수평절곡된 지지내판(32)으로 이루어지는 하프플레이트(30A)의 한 쌍이 결합됨으로써 구성된다.This multi-plate 30 is configured by coupling a pair of
멀티플레이트(30)는 블록몸체(10A) 전방의 개방된 부분과 양 측판(12)을 감싸는 형태로 가이드블록(10)와 결합되는 바, 상기 끼움고정판(31)은 블록몸체(10A)의 상기 측판(12)에 접한 상태에서 분리 가능하도록 고정된다.The multi-plate 30 is coupled to the
이를 위하여 지지외판(10B)에 의해 형성된 돌출편(19)에 파지대(20)를 설치하여 측판(12)과 파지대(20) 사이에 끼움슬릿(s)이 형성되게 한다. 이에 따라 끼움고정판(31)은 상기 끼움슬릿(s)에 삽입되면서 멀티플레이트(30)가 가이드블록(10)에 결합되게 할 뿐 아니라, 끼움슬릿(s)으로부터 쉽께 빠질 수 있어 멀티플레이트(30)와 가이드블록(10) 사이의 분리작업을 용이하게 한다.To this end, a
이때 상기 파지대(20)를 탄성부재로 구성시키고, 지지편(21)과 상기 지지편(21)에서 연장 절곡된 가압편(22)으로 구성시켜 ∧형상의 단면을 가지게 하면서, 상기 지지편(21)은 돌출편(19)에 고정되게 하고, 상기 가압편(22)의 단부는 자유단으로 구성시킴으로써, 파지대(20)의 탄성력으로 끼움슬릿(s)에 삽입된 끼움고정판(31)을 가압하여 멀티플레이트(30)가 가이드블록(10)으로부터 의도하지 않게 쉽게 이탈하는 것을 방지하는 한편, 멀티플레이트(30)로부터 가이드블록(10)을 제거할 때에도 이들이 탄성력에 의해 쉽게 분리되게 할 수 있다. 도 8은 이와 같이 파지대(20)를 탄성부재로 구성시킨 경우의 상기한 작동관계를 설명한 것이다.At this time, the
그러나 파지대(20)의 탄성력으로만 끼움슬릿(s)에 삽입된 끼움고정판(31)의 고정이 완벽하지 않은 경우에는 끼움고정판(31)과 파지대(20) 사이에 쐐기부재(44)를 삽입시킴으로써 이들의 결합된 상태를 보다 견고하게 할 수도 있다.However, if the fixing
또한 멀티가이드블록(MB)에는 잠금수단이 더 구비될 수 있다. 상기 잠금수단은 가이드블록(10)과 멀티플레이트(30) 사이가 작업 과정 중에 의도하지 않게 분리되는 것을 방지하는 것으로서, 도 9는 이러한 잠금수단에 관한 일 실시예를 도시한 것이다.In addition, a locking means may be further provided in the multi-guide block MB. The locking means prevents unintentional separation between the
잠금수단은 가이드블록(10)과 멀티플레이트(30)의 결합구조에 대한 잠금과 해지작업을 쉽게 할 수 있도록 구성되어 있으면 족하는 것으로서, 상기한 도 9에 도시된 실시예에 의하면 블록몸체(10A)의 측판(12)에 내측 핀고정공(17)이 구비되고, 결합시 블록몸체(10A)의 측판(12)에 접하게 되는 하프플레이트(30A)의 끼움고정판(31)에는 상기 내측 핀고정공(17)과 일치하는 외측 핀고정공(36)이 구비되어, 잠금핀(41)으로 하여금 상기 내외측 핀고정공(17,36)을 함께 통과하여 고정되게 한다. 이때 잠금핀(41)에 수나사산을 구비시켜 잠금핀(41)으로 하여금 내외측 핀고정공(17,36) 중 어느 하나에 나사체결방식으로 체결 고정되게 할 수도 있다.The locking means is sufficient as long as it is configured to facilitate locking and unlocking of the coupling structure of the
따라서 블록몸체(10A)의 측판(12)과 하프플레이트(30A)의 끼움고정판(31)이 잠금핀(41)에 의해 잠금되면 가이드블록(10)에 설치된 멀티플레이트(30)는 전후방향으로 분리될 수 없게 된다. Therefore, when the
이러한 잠금핀(41)의 잠금 작업은 통상적으로 멀티플레이트(30)의 외부에서 이루어지고 트렌치(T1,T2) 내부에 대한 설치작업이 완료되면 곧바로 제거되나, 작업의 여건상 콘크리트타설이 완료될 때까지 잠금핀(41)이 존치되어야 하는 등으로 인하여 그의 잠금 및 해지작업이 블록몸체(10A)의 내부에서 이루어져야 할 경우도 있다. 따라서 상기 내외측 핀고정공(17,36)은 내외측 작업개구(16,35)의 부근에 위치시키는 것이 바람직하다.The locking operation of the locking
한편 본 발명의 멀티플레이트(30)는 상술한 바와 같이 패널(P1)과 패널(P2) 사이의 이음부(J) 강성을 증대시키면서 각 패널(P1,P2)들이 일체적으로 거동할 수 있게 하는 것인바, 이를 위하여 상기 멀티플레이트(30)에는 전후 양방향으로 이음봉(38)이 설치된다.Meanwhile, the multi-plate 30 of the present invention increases the rigidity of the joint J between the panel P1 and the panel P2, as described above, while allowing the panels P1 and P2 to behave integrally. For this purpose, the multi-plate 30 is provided with a
멀티플레이트(30) 전방에 위치한 이음봉(38)은 선행 패널(P1)에 매립되면서 선행 패널(P1)과 멀티플레이트(30)와의 사이가 전단연결되게 하고, 멀티플레이트(30)의 후방에 위치한 이음봉(38)은 후행 패널(P2)에 매립되면서 멀티플레이트(30)와 후행 패널(P2) 사이가 전단연결되도록 함으로써, 선행 패널(P1)과 후행 패널(P2)이 멀티플레이트(30)를 매개로 하여 구조적으로 일체성을 가지게 한다. 이때 이음봉(38)의 단부에 후크(미도시)를 형성시킴으로써 이음봉(38)이 보다 강력한 전단연결기능을 하게 할 수 있다. 이러한 이음봉(38)은 구체적으로 하프플레이트(30A)의 지지내판(32)에 전후방으로 수직 설치된다.The
도 10은 차수판(50)의 설치구조에 관하여 도시한 것이다.10 shows the installation structure of the
패널(P1)과 패널(P2)의 이음부(J)에서 지하수의 침입을 방지하는 차수판(50) 역시 멀티플레이트(30)에 전후 방향으로 수직 설치된다. 이를 위하여 하프플레이트(30A)에는, 도 10의 (a)에 도시된 바와 같이, 지지내판(32)에서 경사절곡된 설치판(33)이 구비되고, 상기 설치판(33)에는 단부면에 차수판(50) 설치를 위한 고정홈(34a)이 구비된 고정편(34)이 형성된다.A
상기 차수판(50)은 중앙의 고정돌기(51)와 상기 고정돌기(51)의 양측으로 형성된 차수날개(52)로 이루어지는 바, 상기 고정돌기(51)가 멀티플레이트(30) 형성을 위한 한 쌍의 하프플레이트(30A)에 각 구비된 고정홈(34a) 사이에 삽입되는 형상으로 설치된다.The
이와 같이 차수판(50)은 가이드블록(10)에 멀티플레이트(30)를 결합시키는 과정 중에 설치되는 것, 보다 구체적으로 도 10의 (a)에서 나타내고 있는 바와 같이, 블록몸체(10A)에 상호 분리된 한 쌍의 하프플레이트(30A)를 설치하는 과정 중에 설치되는 것인 바, 상호 분리된 한 쌍의 하프플레이트(30A)를 가압하여 차수판(50)이 고정홈(34a)으로부터 이탈되지 않게 할 필요가 있다.In this way, the
이를 위한 수단으로 도 10의 (b)에 도시된 바와 같이 하프플레이트(30A)의 끼움고정판(31) 상부쪽에는 봉삽입공(37)이 구비된다. 이에 따라 한 쌍의 하프플레이트(30A)에 각 구비된 봉삽입공(37)에 압착봉(42)을 삽입하고 이를 가압너트(43)로 조임하게 되면 양측의 고정편(34)은 그 사이에 위치한 차수판(50)을 가압하게 된다.As a means for this, as shown in (b) of FIG. 10, a sealing
보다 구체적으로 멀티플레이트(30)를 가이드블록(10)에 결합시키고자 할 때, 먼저 각 하프플레이트(30A)의 끼움고정판(31)을 끼움슬릿(s)에 삽입 고정시켜 하프플레이트(30A)의 하부를 고정시키고, 하프플레이트(30A)의 상부쪽은 봉삽입공(37)에 압착봉(42)을 삽입한 후 가압너트(43)로 이들 양측의 하프플레이트(30A)를 가압하게 되면, 서로 대향한 하프플레이트(30A)들의 사이간극, 보다 구체적으로 차수판(50)을 사이에 둔 고정편(34)들의 사이간극이 좁혀지면서 차수판(50)이 양측 고정편(34)들에 의해 가압되어 멀티플레이트(30)로부터 쉽게 이탈되지 않게 된다.More specifically, when the multi-plate 30 is to be coupled to the
상기한 방법으로 멀티플레이트(30)에 고정 설치된 차수판(50)은, 멀티가이드블록(MB)이 복수 개 이음 연결되어 사용될 때 인접한 또 다른 차수판(50)과의 일체성을 필요로 할 수도 있다.The
도 11, 12는 이를 위한 차수판(50)의 구조에 관한 각 실시예를 도시한 것이다.11 and 12 show examples of the structure of the
도 11의 실시예에 의한 차수판(50)은, 상하의 일측단부에 요홈(53)이 구비되고 타측단부에는 상기 요홈(53)에 삽입되는 돌기(54)가 형성된다. 이러한 요홈(53)과 돌기(54)는 멀티가이드블록(MB)의 복수 개가 길게 이음 연장되어 설치되는 경우, 상하부에 위치한 차수판(50)들이 상호 일체화되면서 차수판(50)들 사이에 간극이 생길 여지가 없게 한다.In the
도 12의 실시예에 의한 차수판(50)은 고정돌기(51)에 연결공(55)이 더 구비된다. 상기 연결공(55)은, 복수 개의 멀티가이드블록(MB)을 길게 이음 연장하여 설치할 경우, 인접한 차수판(50)의 연결공(55)과 연통하도록 접하게 된다. 따라서 결합봉(56)의 양쪽을 상하 차수판의 각 연결공(55)에 삽입시킴으로써 이들 차수판(50)이 일체성을 가지게 할 수 있다. 이때 차수판(50)의 각 차수날개(52) 사이에 접착제를 도포하여 이들 차수날개(52)들도 일체화시키는 것이 바람직하다.The
그외 도시하지는 아니하였으나, 차수판(50)의 양측 단부에 요홈(53)만을 구비시키고, 상하 차수판(50)의 상단부와 하단부가 접하게 될 경우 상기 요홈(53)에 접착성 액체를 삽입시켜 일체성을 가지게 할 수도 있다.Other than that, although not shown, only the
도 13 내지 21은 지금까지 설명한 본 발명의 멀티가이드블록(MB)을 이용하여 차수성 및 이음부(J) 강성이 증대된 지하연속벽을 구축하는 시공방법에 관하여 각 단계별로 도시한 것으로서, 이는 a) 선행 트렌치(T1) 형성 단계; b) 멀티가이드블록(MB) 설치 단계; c) 선행 패널(P1) 구축 단계; d) 후행 트렌치(T2) 형성 단계; e) 블록몸체(10A) 제거 단계; f) 후행 패널(P2) 구축 단계;가 포함되어 이루어지며, 이들 각 단계를 보다 구체적으로 설명하면 다음과 같다.13 to 21 show each step with respect to a construction method for constructing an underground continuous wall with increased water-repellency and joint (J) stiffness using the multi-guide block (MB) of the present invention described so far, which a) forming a preceding trench (T1); b) installing a multi-guide block (MB); c) building the preceding panel (P1); d) forming a trailing trench (T2); e) removing the
a) 선행 트렌치(T1) 형성 단계(도 13);a) forming the preceding trench T1 (Fig. 13);
지하연속벽을 구축하기 위한 트렌치(T1,T2)의 형성에 앞서 그의 양측 주변에 가이드월(1)을 설치한다.Prior to the formation of trenches (T1, T2) for constructing the underground continuous wall, guide walls (1) are installed around both sides thereof.
상기 가이드월(1)은 굴착과정 중에 굴착기의 충격에 의해 트렌치(T1,T2)가 붕괴되지 않도록 그 주변의 지반을 보호하고 향후 설치되는 철근망(2) 및 트레미관(3)의 받침대 역할을 하는 것으로서, 철근콘크리트조 또는 철골조로 구축한다.The guide wall (1) protects the ground around the trenches (T1, T2) from collapsing due to the impact of the excavator during the excavation process, and serves as a support for the rebar net (2) and the tremi pipe (3) to be installed in the future. It is constructed with reinforced concrete or steel frame.
가이드월(1)의 설치가 완료되면, 굴착장비에 트렌치 커터 등을 장착하여 지반에 굴착을 실시함으로써 지중에 선행 패널(P1) 구축을 위한 선행 트렌치(T1)가 형성되게 한다.When the installation of the
상기 굴착은 공벽이 붕괴되지 않도록 그 내부에 벤토나이트 등의 안정액을 주입하면서 진행하며, 이러한 안정액은 작업과정 중 항상 지하수위보다 높은 상태를 유지해야 한다.The excavation proceeds by injecting a stabilizer such as bentonite into the interior so that the empty wall does not collapse, and such a stabilizer must always be kept higher than the groundwater level during the working process.
또한 굴착이 완료되면, 디샌딩(desanding) 작업을 통해 안정액에 섞여 있는 슬라임을 제거하여 구축된 지하연속벽의 콘크리트에 품질이 저하되지 않도록 해야 한다.In addition, when excavation is completed, the slime mixed in the stabilizer should be removed through desanding to prevent the quality of the concrete of the constructed underground continuous wall from deteriorating.
b) 멀티가이드블록(MB) 설치 단계(도 14, 15);b) Multi-guide block (MB) installation step (Fig. 14, 15);
굴착 및 슬라임처리가 완료된 선행 트렌치(T1) 내부의 전후방 양 측 내면 중 적어도 어느 한 내면에 멀티가이드블록(MB)을 설치한다.A multi-guide block (MB) is installed on at least one of the inner surfaces of both front and rear sides of the preceding trench (T1) where excavation and slime treatment have been completed.
이때 멀티가이드블록(MB)에 형성된 작업개구(16,35)는 향후 제거 가능한 필러를 이용하여 폐쇄구조가 되게 함으로써 콘크리트 타설시 멀티가이드블록(MB) 내부로 콘크리트가 유입되지 않도록 해야 한다. 물론 트렌치(T1)의 바닥부분에 위치하는 등 향후 사용이 불필요한 작업개구(16,35)는 완전 폐쇄시켜도 무방하다.At this time, the working
상기 멀티가이드블록(MB)의 설치작업은 상단에 조립용 헤드(60)가 설치된 상태에서 이루어지고, 멀티가이드블록(MB)의 설치작업이 완료되면 상기 조립용 헤드(60)는 분리 제거된다.The installation work of the multi-guide block (MB) is performed in a state where the
이러한 본 단계의 멀티가이드블록(MB) 설치는 다음 단계의 철근망(2) 설치작업과 동시에 이루어질 수도 있다. 그러나 여기에서는 멀티가이드블록(MB)이 먼저 설치된 후 철근망(2)이 설치되는 것을 예로 하여 설명한다.The multi-guide block (MB) installation in this step may be performed simultaneously with the rebar network (2) installation work in the next step. However, here, the multi-guide block (MB) is first installed, and then the reinforcing bar network (2) is installed as an example.
잠금핀(41)에 의해 블록본체와 멀티플레이트(30)의 결합이 잠금된 경우에는 멀티가이드블록(MB)의 설치가 완료된 후 곧바로 이를 해지하여 잠금핀(41)을 제거할 수도 있다.When the combination of the block main body and the multi-plate 30 is locked by the locking
또한 멀티가이드블록(MB)의 복수 개가 이음 연결되어야 하는 경우에는, 일측 블록몸체(10A)의 단부판(11)에 설치된 연결봉(13)을 타측 블록몸체(10A)의 단부판(11)에 구비된 연결홀(14)에 삽입시키고, 이에 의해 상호 접하게 된 양측 단부판(11)의 각 체결공(15a,15b)에 체결볼트 등의 체결수단을 삽입하여 체결함으로써, 상하부의 멀티가이드블록(MB)을 일체화시킨다.In addition, when a plurality of multi-guide blocks (MB) are to be jointly connected, a connecting
도 15는 상기한 멀티가이드블록(MB)들 사이의 이음 연결방법에 관한 구체적인 예를 도시한 것이다.15 shows a specific example of a joint connection method between the multi-guide blocks (MB).
멀티가이드블록(MB)들 사이의 이음 연결은, 트렌치(T1)의 외부에서 이루어지게 하는 것이 안전할 뿐 아니라, 정밀한 작업을 가능하게 한다. 그러나 이들을 먼저 이음 연결한 후 트렌치(T1)에 삽입하게 되면, 이음 연결된 멀티가이드블록(MB)의 길이가 너무 길어져 트렌치(T1) 내부로의 삽입 자체가 쉽지 않을 수도 있다.The joint connection between the multi-guide blocks MB is not only safe to be made outside of the trench T1, but also enables precise work. However, if these are first jointed and then inserted into the trench T1, the length of the jointly connected multi-guide block MB may be too long, so that insertion into the trench T1 itself may not be easy.
따라서 도 15에 도시된 바와 같이, 하부의 멀티가이드블록(MB)을 트렌치(T1) 내부에 삽입시키되, 상부가 트렌치(T1)의 외부로 돌출된 상태가 되게 하여, 이음 연결작업이 트렌치(T1,T2)의 직상부에서 이루어지게 함으로써 상기한 길이의 문제점을 해결함과 더불어 작업의 용이성과 안전성 및 정밀성을 도모할 수 있도록 하는 것이 바람직하다.Therefore, as shown in FIG. 15, the lower multi-guide block MB is inserted into the trench T1, but the upper part protrudes to the outside of the trench T1, so that the joint connection operation is performed in the trench T1. It is desirable to solve the problem of the above length by making it directly above the T2), and to promote ease of operation, safety, and precision.
이에 관하여 보다 구체적으로 설명하면 다음과 같다.This will be described in more detail as follows.
먼저, 도 15의 (a)에 도시된 바와 같이, 하부에 위치하게 될 멀티가이드블록(MB)를 트렌치(T1)의 내부에 삽입하되, 돌출편(19)에 형성된 거치공(19a)에 거치봉(23)을 삽입한 후, 상기 거치봉(23)이 가이드블록(10)에 의해 지지되도록 함으로써, 잠금핀(41)과 작업개구(16,35)가 외부로 노출되게 한다. 이를 위하여 거치봉(23)과 가이드블록(10) 사이에 거치대(70)가 더 설치된다.First, as shown in Figure 15 (a), insert the multi-guide block (MB) to be located at the bottom into the inside of the trench (T1), but mount it in the mounting hole (19a) formed in the protruding piece (19) After the
하부의 멀티가이드블록(MB)이 상부가 노출된 상태로 거치봉(23)에 의해 안전하게 지지되면, 도 15의 (b)에 도시된 바와 같이, 잠금핀(41)을 제거하고, 작업개구(16,35)를 통해 조립용 헤드(60)를 제거한다.When the lower multi-guide block (MB) is securely supported by the mounting
다음으로, 도 15의 (c)에 도시된 바와 같이 상부의 멀티가이드블록(MB)을 조립용 헤드(60)를 이용하여 현수시킨 상태에서 그 하단을, 상기 거치봉(23)에 의해 거치되어 상부만 노출된 하부의 멀티가이드블록(MB)에 밀착시킨 후, 상술한 바와 같이 연결봉(13)과 연결홀(14) 및 각 체결공(15a,15b)을 이용하여 상하 멀티가이드블록(MB)을 이음 연결한다.Next, as shown in (c) of FIG. 15, in a state in which the upper multi-guide block (MB) is suspended using the
이때 상하의 차수판(50)들 사이도 상술한 요홈(53) 및 돌기(54)의 수단, 또는 연결공(55)과 결합봉(56)의 수단 등을 이용하여 일체화시키는 것이 바람직하다.At this time, it is preferable to integrate the upper and
c) 선행 패널(P1) 구축 단계(도 16, 17);c) the step of constructing the preceding panel P1 (Figs. 16 and 17);
멀티가이드블록(MB)의 설치가 완료되면, 철근망(2)을 선행 트렌치(T1) 내부에 설치하여 고정시키고, 트레미관(3)을 삽입한 후 이를 인발시키면서 선행 트렌치(T1) 내부에 콘크리트를 타설한다.When the installation of the multi-guide block (MB) is completed, the reinforcing bar network (2) is installed and fixed inside the preceding trench (T1), and after inserting the tremi pipe (3), the concrete inside the preceding trench (T1) is pulled out. Pour.
이때 트렌치(T1) 외부에 진동봉(4a)이 구비된 진동장치(4)를 설치하고, 철근망(2)의 상단에 설치된 후크근(2a)을 상기 진동봉(4a)에 거치시켜, 상기 진동봉(4a)에 의해 철근망(2)이 정위치를 유지함과 더불어 콘크리트 타설시 후크근(2a)에 진동이 전달되게 함으로써 타설된 콘크리트에 다짐이 이루어지게 할 수도 있다.At this time, a
d) 후행 트렌치(T2) 형성 단계(도 18);d) forming a trailing trench (T2) (Fig. 18);
타설된 콘크리트가 소요 강도를 발현하도록 양생되면, 이에 인접하여 구축될 후행 패널(P2)의 구축을 위한 후행 트렌치(T2)를 형성시킨다. 후행 트렌치(T2)의 형성과정은 선행 트렌치(T1)의 것과 다르지 않다.When the poured concrete is cured to express the required strength, a trailing trench (T2) for constructing a trailing panel (P2) to be built adjacent thereto is formed. The process of forming the trailing trench T2 is not different from that of the preceding trench T1.
후행 트렌치(T2)의 형성을 위한 굴착으로 인하여 선행 패널(P1)에 부착 설치된 멀티가이드블록(MB)의 블록몸체(10A)는 외부로 노출된다.Due to excavation for formation of the trailing trench T2, the
e) 블록몸체(10A) 제거 단계(도 19);e) removing the
후행 트렌치(T2)의 형성으로 선행 패널(P1)에 부착 설치된 상태로 노출된 멀티가이드블록(MB)의 블록몸체(10A)를 멀티플레이트(30)로부터 분리시켜 제거한다.The
이를 위하여 먼저 트렌치 커터 등을 이용하여 트렌치(T1)와 멀티가이드블록(MB)사이의 틈을 통해 누출되어 경화된 콘크리트를 제거하여 블록몸체(10A)의 분리작업을 용이하게 한다.To this end, first, a trench cutter or the like is used to remove the hardened concrete leaking through the gap between the trench T1 and the multi-guide block MB, thereby facilitating the separation of the
아울러 멀티가이드블록(MB)의 상부에 위치한 작업개구(16,35)에서 필러를 제거한 후, 상기 작업개구(16,35)를 이용하여 블록몸체(10A)의 상단에 조립용 헤드(60)를 설치한다. 물론 잠금핀(41)이 존치되어 있는 경우에는 이 역시 작업개구(16,35)를 통해 제거될 수 있다.In addition, after removing the filler from the working
다음으로 블록몸체(10A)와 일체화된 조립용 헤드(60)의 현수공에 크레인 등의 장비에 설치된 현수고리를 끼워 넣고, 이를 후방으로 당기게 되면 블록몸체(10A)는 멀티플레이트(30)로부터 쉽게 분리된다.Next, insert the suspension hook installed on equipment such as a crane into the suspension hole of the
선행 패널(P1)에서 블록몸체(10A)를 제거하게 되면, 멀티플레이트(30)의 후방쪽으로 차수판(50)의 일측 차수날개(52)와 함께 일측 이음봉(38)이 돌출한 상태로 후행 트렌치(T2) 내부로 노출된다. 이와 같이 노출된 차수날개(52)와 이음봉(38)은, 다음 단계에서 구축되는 후행 패널(P2)에 매립됨으로써 높은 차수성능과 더불어 강성이 향상된 이음부(J)가 형성될 수 있게 한다.When the
f) 후행 패널(P2) 구축 단계(도 20, 21);f) Construction of the trailing panel P2 (Figs. 20 and 21);
상술한 c)단계와 동일한 방법으로 후행 트렌치(T2) 내부에 철근망(2)을 삽입시키고, 콘크리트를 타설함으로써 선행 패널(P1)과 구조적으로 일체성을 가지는 후행 패널(P2)을 구축한다.In the same manner as in step c) described above, the reinforcing
상기한 각 단계를 반복함으로써 지하연속벽의 구축을 완료시킨다.The construction of the underground continuous wall is completed by repeating each of the above steps.
이상에서 본 발명은 구체적인 실시 예를 참조하여 상세히 설명하였으나, 상기 실시 예는 본 발명을 이해하기 쉽도록 하기 위한 예시에 불과한 것이므로, 이 분야에서 통상의 지식을 가진 자라면 본 발명의 기술적 사상의 범위 내에서 이를 다양하게 변형하여 실시할 수 있을 것임은 자명한 것이다. 따라서 그러한 변형 예들은 청구범위에 기재된 바에 의해 본 발명의 권리범위에 속한다고 할 것이다.In the above, the present invention has been described in detail with reference to specific embodiments, but the embodiments are only examples for making the present invention easier to understand, so those of ordinary skill in the art will have the scope of the technical idea of the present invention. It is obvious that it will be possible to implement this in various ways. Therefore, such modified examples will be said to belong to the scope of the present invention as described in the claims.
1; 가이드월 2; 철근망
2a; 후크근 3; 트레미관
4; 진동장치 4a; 진동봉
10; 가이드블록 10A; 블록몸체
11; 단부판 12; 측판
13; 연결봉 14; 연결홀
15a,15b,62; 체결공 16,35; 작업개구
17,36; 핀고정공 18; 보강벽
19; 돌출편 20; 파지대
21; 지지편 22; 가압편
30; 멀티플레이트 30A; 하프플레이트
31; 끼움고정판 32; 지지내판
33; 설치판 34; 고정편
34a; 고정홈 37; 봉삽입공
38; 이음봉 41; 잠금핀
42; 압착봉 43; 가압너트
44; 쐐기부재 50; 차수판
51; 고정돌기 52; 차수날개
53; 요홈 54; 돌기
60; 조립용 헤드 60A; 접합편
60B; 현수편 60C; 보강편
61; 삽입홀 63; 현수홀
P1,P2; 패널 T1,T2; 트렌치
s; 끼움슬릿 MB; 멀티가이드블록One;
2a;
4;
10;
11;
13; Connecting
15a, 15b, 62; Fastening holes 16,35; Work opening
17,36;
19; Protruding
21;
30;
31; Fitting
33; Mounting
34a; Fixing
38;
42; Crimping
44;
51; Fixed
53;
60;
60B;
61;
P1,P2; Panels T1,T2; Trench
s; Fitting slit MB; Multi Guide Block
Claims (15)
가이드블록(10)과,
상기 가이드블록(10)에 분리 가능하도록 결합되며 지하연속벽을 형성하는 패널(P1)과 패널(P2) 사이의 이음부(J)에 매립되는 멀티플레이트(30)로 이루어지며,
상기 멀티플레이트(30)에는 전후 양방향으로 차수판(50)과 이음봉(38)이 각각 설치되어 있되,
상기 가이드블록(10)은, 상하 양 단부에 위치한 한 쌍의 단부판(11)과 좌우 양 측부에 위치한 한 쌍의 측판(12)이 결합되어 구성되는 블록몸체(10A)와, 상기 블록몸체(10A)의 후방에 위치하면서 블록몸체(10A)의 양 측으로 돌출편(19)이 형성되도록 한 지지외판(10B)으로 이루어지고,
상기 돌출편(19)에는 파지대(20)가 설치되어 측판(12)과 파지대(20) 사이에 끼움슬릿(s)이 형성되며,
상기 멀티플레이트(30)는, 끼움고정판(31)과 이에 수평절곡된 지지내판(32)으로 이루어지는 하프플레이트(30A)의 한 쌍이 결합되어 구성되고,
상기 끼움슬릿(s)에 끼움고정판(31)이 삽입됨으로써 멀티플레이트(30)가 가이드블록(10)에 분리가능하도록 결합되는 것을 특징으로 하는 멀티가이드블록.It is installed in the front or rear of the excavated trenches (T1, T2) to build the underground continuous wall,
Guide block 10,
It consists of a multi-plate 30 that is detachably coupled to the guide block 10 and is buried in the joint J between the panel P1 and the panel P2 forming an underground continuous wall,
The multi-plate 30 is provided with a shield plate 50 and a connecting rod 38 in both front and rear directions, respectively,
The guide block 10 includes a block body 10A formed by combining a pair of end plates 11 located at both ends of the upper and lower ends and a pair of side plates 12 located at both left and right sides, and the block body ( It is made of a supporting shell plate 10B that is positioned at the rear of 10A) and has protruding pieces 19 formed on both sides of the block body 10A,
The protruding piece 19 is provided with a gripper 20 to form a fitting slit (s) between the side plate 12 and the gripper 20,
The multi-plate 30 is configured by combining a pair of half plates 30A comprising a fitting fixing plate 31 and a support inner plate 32 bent horizontally thereto,
A multi-guide block, characterized in that the multi-plate 30 is detachably coupled to the guide block 10 by inserting the fixing plate 31 into the fitting slit (s).
상기 이음봉(38)은 지지내판(32)의 전후방으로 수직 설치되고,
상기 차수판(50)은 지지내판(32)에서 경사절곡된 설치판(33)에 구비된 고정편(34)에 의해 고정 설치되는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
The joint rod 38 is vertically installed in the front and rear of the support inner plate 32,
The water shield plate (50) is a multi-guide block, characterized in that it is fixedly installed by a fixing piece (34) provided on the installation plate (33) bent in the support inner plate (32).
상기 파지대(20)는, 지지외판(10B)에 고정되는 지지편(21)과, 상기 지지편(21)에서 연장 절곡되어 단부가 자유단인 가압편(22)으로 이루어지는, 탄성부재인 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
The gripper 20 is an elastic member consisting of a support piece 21 fixed to the support shell plate 10B, and a pressing piece 22 that is extended and bent from the support piece 21 and has a free end. Multi-guide block characterized by.
상기 블록몸체(10A)의 일측 단부판(11)에는 연결봉(13)이 설치되고,
상기 블록몸체(10A)의 타측 단부판(11)에는 연결봉(13)이 삽입되는 연결홀(14)이 구비되어 있는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
A connecting rod 13 is installed on one end plate 11 of the block body 10A,
A multi-guide block, characterized in that the other end plate (11) of the block body (10A) is provided with a connection hole (14) into which the connecting rod (13) is inserted.
상기 블록몸체(10A)의 단부판(11)에는 체결공(15a,15b)이 구비되고,
상기 블록몸체(10A)의 측판(12)에는 상기 체결공(15a,15b)에 대한 체결작업을 위한 내측작업개구(16)가 구비되며,
상기 하프플레이트(30A)의 끼움고정판(31)에는 상기 내측작업개구(16)와 일치하는 외측작업개구(35)가 구비되어 있는 것을 특징으로 하는 멀티가이드블록. The method of claim 1,
Fastening holes 15a and 15b are provided in the end plate 11 of the block body 10A,
The side plate 12 of the block body 10A is provided with an inner working opening 16 for fastening work for the fastening holes 15a, 15b,
A multi-guide block, characterized in that the fitting fixing plate (31) of the half plate (30A) is provided with an outer working opening (35) that matches the inner working opening (16).
상기 블록몸체(10A)의 측판(12)에는 내측 핀고정공(17)이 구비되고,
상기 하프플레이트(30A)의 끼움고정판(31)에는 상기 내측 핀고정공(17)과 일치하는 외측 핀고정공(36)이 구비되어,
상기 내외측 핀고정공(17,36)을 함께 통과하여 설치되는 잠금핀(41)에 의해 잠금됨으로써 가이드블록(10)에 설치된 멀티플레이트(30)가 분리되는 것이 방지되는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
The side plate 12 of the block body 10A is provided with an inner pin fixing hole 17,
The fitting fixing plate 31 of the half plate 30A is provided with an outer pin fixing hole 36 that matches the inner pin fixing hole 17,
A multi-guide, characterized in that the multi-plate 30 installed in the guide block 10 is prevented from being separated by being locked by the locking pin 41 installed through the inner and outer pin fixing holes 17 and 36 together. block.
상기 하프플레이트(30A)의 끼움고정판(31)에는 봉삽입공(37)이 구비되고, 상기 봉삽입공(37)에 삽입된 압착봉(42)과 이에 체결되는 가압너트(43)에 의해 상호 대향한 하프플레이트(30A)들 사이간극이 좁아지면서 차수판(50)이 고정 설치되는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
A rod insertion hole 37 is provided in the fitting fixing plate 31 of the half plate 30A, and mutually by a pressing rod 42 inserted into the rod insertion hole 37 and a pressing nut 43 fastened thereto. A multi-guide block, characterized in that the shield plate 50 is fixedly installed while the gap between the opposite half plates 30A is narrowed.
상기 돌출편(19)에는 거치공(19a)이 형성되어 있는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
Multi-guide block, characterized in that the mounting hole (19a) is formed in the protruding piece (19).
상기 차수판(50)은 상하의 일측단부에 요홈(53)이 구비되고 타측단부에 상기 요홈(53)에 삽입되는 돌기(54)가 형성되어 있는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
The water shield plate (50) is a multi-guide block, characterized in that the groove (53) is provided at one end of the top and bottom, and a protrusion (54) inserted into the groove (53) is formed at the other end.
상기 차수판(50)의 고정돌기(51)에는 연결공(55)이 형성되어 있는 것을 특징으로 하는 멀티가이드블록.The method of claim 1,
A multi-guide block, characterized in that a connection hole (55) is formed in the fixing protrusion (51) of the shield plate (50).
a) 지반을 굴착하여 선행 패널(P1) 구축을 위한 선행 트렌치(T1)를 형성시키는 단계;
b) 선행 트렌치(T1) 내부의 전후방 양 측 내면 중 적어도 어느 한 내면에 멀티가이드블록(MB)을 설치하는 단계;
c) 상기 선행 트렌치(T1) 내부에 철근망(2)을 삽입하고, 콘크리트를 타설하는 단계;
d) 상기 멀티가이드블록(MB)의 블록몸체(10A)가 노출되도록 후행 패널(P2) 구축을 위한 후행 트렌치(T2)를 형성시키는 단계;
e) 상기 멀티가이드블록(MB)의 블록몸체(10A)와 멀티플레이트(30)를 분리시켜, 블록몸체(10A)를 제거하는 단계;
f) 후행 트렌치(T2) 내부에 철근망(2)을 삽입하고, 콘크리트를 타설하는 단계;가 포함되어 이루어지는 것을 특징으로 지하연속벽의 시공방법.As using the multi-guide block (MB) according to any one of claims 1, 3 to 11,
a) excavating the ground to form a preceding trench (T1) for building the preceding panel (P1);
b) installing a multi-guide block (MB) on at least one of the inner surfaces of both front and rear sides of the preceding trench (T1);
c) inserting a reinforcing bar net (2) into the preceding trench (T1) and pouring concrete;
d) forming a trailing trench (T2) for constructing a trailing panel (P2) such that the block body (10A) of the multi-guide block (MB) is exposed;
e) removing the block body (10A) by separating the block body (10A) and the multi-plate (30) of the multi-guide block (MB);
f) inserting the reinforcing bar net (2) into the trailing trench (T2) and pouring concrete; the method of constructing an underground continuous wall comprising:
상기 b)단계는 멀티가이드블록(MB)의 상단에 조립용 헤드(60)가 설치된 상태에서 이루어지고,
상기 조립용 헤드(60)는, 삽입홀(61) 및 체결공(62)이 구비된 접합편(60A)과, 상기 접합편(60A)에 수직으로 설치되며 현수홀(63)이 구비된 현수편(60B)으로 이루어져,
블록몸체(10A)의 단부판(11)에 설치된 연결봉(13)이 조립용 헤드(60)의 삽입홀(61)에 삽입되고, 단부판(11)과 접합편(60A)에 각 구비된 체결공(15a,62))을 통해 단부판(11)과 접합편(60A)이 체결 결합됨으로써, 멀티가이드블록(MB)에 조립용 헤드(60)가 일체화되는 것을 특징으로 하는 지하연속벽의 시공방법.The method of claim 12,
The step b) is performed in a state where the assembly head 60 is installed on the top of the multi-guide block (MB),
The assembly head 60 is a junction piece (60A) provided with an insertion hole (61) and a fastening hole (62), and is vertically installed in the bonding piece (60A) and a suspension hole (63) It consists of a piece (60B),
The connecting rod 13 installed on the end plate 11 of the block body 10A is inserted into the insertion hole 61 of the assembly head 60, and is provided on the end plate 11 and the joining piece 60A. Construction of an underground continuous wall, characterized in that the assembly head 60 is integrated with the multi-guide block (MB) by fastening the end plate 11 and the joining piece (60A) through the holes (15a, 62). Way.
상기 b)단계는 멀티가이드블록(MB)은 복수 개가 이음 연결되어 설치되며,
상하부의 멀티가이드블록(MB) 연결은, 일측 블록몸체(10A)의 단부판(11)에 설치된 연결봉(13)이 타측 블록몸체(10A)의 단부판(11)에 구비된 연결홀(14)에 삽입되고, 상호 접한 양측 단부판(11)이 이에 각 구비된 체결공(15a,15b)을 통해 체결 결합됨으로써 이루어지는 것을 특징으로 하는 지하연속벽의 시공방법.The method of claim 12,
In step b), a plurality of multi-guide blocks (MB) are jointly connected and installed,
The connection of the upper and lower multi-guide blocks (MB) is a connection hole (14) provided in the end plate (11) of the other block body (10A) with a connecting rod (13) installed on the end plate (11) of one block body (10A) A method of constructing an underground continuous wall, characterized in that the end plates 11 are inserted into and contacted with each other through fastening holes 15a and 15b provided thereto.
상기 (b)단계에서의 복수 개 멀티가이드블록(MB)의 이음 연결은, 하부의 멀티가이드블록(MB)의 작업개구(16,35)가 트렌치(T1)의 외부로 노출되도록 하부의 멀티가이드블록(MB)를 상기 트렌치(T1)에 삽입시킨 상태에서 이루어지는 것을 특징으로 하는 지하연속벽의 시공방법.
The method of claim 14,
The joint connection of the plurality of multi-guide blocks MB in the step (b) is performed so that the operation openings 16 and 35 of the multi-guide block MB are exposed to the outside of the trench T1. A method of constructing an underground continuous wall, characterized in that the block MB is inserted into the trench T1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020200105142A KR102214787B1 (en) | 2020-08-21 | 2020-08-21 | Multi guide block and construction method of underground continuous wall using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020200105142A KR102214787B1 (en) | 2020-08-21 | 2020-08-21 | Multi guide block and construction method of underground continuous wall using the same |
Publications (1)
Publication Number | Publication Date |
---|---|
KR102214787B1 true KR102214787B1 (en) | 2021-02-10 |
Family
ID=74561324
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020200105142A KR102214787B1 (en) | 2020-08-21 | 2020-08-21 | Multi guide block and construction method of underground continuous wall using the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102214787B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102351891B1 (en) | 2021-10-26 | 2022-01-18 | 엠씨씨건설 주식회사 | Connecting block for earthquake resistant underground continuous wall |
KR102554205B1 (en) * | 2022-09-23 | 2023-07-11 | 문제모 | Slurry wall joint connect method |
KR20230126940A (en) | 2022-02-24 | 2023-08-31 | 주식회사 유탑엔지니어링 | Joint for connecting parts of slurry wallslurry wall and construction method of slurry wall using the joint |
KR20230126941A (en) | 2022-02-24 | 2023-08-31 | 주식회사 유탑엔지니어링 | Joint for connecting parts of slurry wallslurry wall and construction method of slurry wall using the joint |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009019371A (en) * | 2007-07-10 | 2009-01-29 | Ohbayashi Corp | Forming implement and constructing method of construction joint part of underground wall and underground wall |
KR20100031815A (en) * | 2008-09-16 | 2010-03-25 | 박길석 | Joint structure for diaphragm wall and method of constructing diaphragm wall using the same |
KR20100115019A (en) * | 2009-04-17 | 2010-10-27 | 박길석 | Panel joint for construction for underground diaphragm well and underground diaphragm well constructing method using the same |
-
2020
- 2020-08-21 KR KR1020200105142A patent/KR102214787B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009019371A (en) * | 2007-07-10 | 2009-01-29 | Ohbayashi Corp | Forming implement and constructing method of construction joint part of underground wall and underground wall |
KR20100031815A (en) * | 2008-09-16 | 2010-03-25 | 박길석 | Joint structure for diaphragm wall and method of constructing diaphragm wall using the same |
KR20100115019A (en) * | 2009-04-17 | 2010-10-27 | 박길석 | Panel joint for construction for underground diaphragm well and underground diaphragm well constructing method using the same |
KR101051965B1 (en) | 2009-04-17 | 2011-07-26 | 박길석 | Panel joint for underground continuous wall construction and underground continuous wall construction method |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102351891B1 (en) | 2021-10-26 | 2022-01-18 | 엠씨씨건설 주식회사 | Connecting block for earthquake resistant underground continuous wall |
KR20230126940A (en) | 2022-02-24 | 2023-08-31 | 주식회사 유탑엔지니어링 | Joint for connecting parts of slurry wallslurry wall and construction method of slurry wall using the joint |
KR20230126941A (en) | 2022-02-24 | 2023-08-31 | 주식회사 유탑엔지니어링 | Joint for connecting parts of slurry wallslurry wall and construction method of slurry wall using the joint |
KR102601492B1 (en) | 2022-02-24 | 2023-11-13 | 주식회사 유탑엔지니어링 | Joint for connecting parts of slurry wallslurry wall and construction method of slurry wall using the joint |
KR102554205B1 (en) * | 2022-09-23 | 2023-07-11 | 문제모 | Slurry wall joint connect method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102214787B1 (en) | Multi guide block and construction method of underground continuous wall using the same | |
CN108612111B (en) | Steel pipe pile, foundation pit support structure and construction method of foundation pit support structure | |
KR20140055639A (en) | A execution method of architecture beam | |
KR20210090101A (en) | Integrated slurry wall construction structure and method using pouring blocking device and extension rebar, and construction device thereof | |
KR102217329B1 (en) | Guide device for continuous excavation of casing | |
KR20070081633A (en) | Construction method for underground watertight wall and subsidiary casing used in the same | |
KR101524303B1 (en) | The wall members and underground wall, underground wall construction method using the same | |
KR101840226B1 (en) | The guide holes of the form for soil auger dredges | |
JP2019199705A (en) | Box culvert insertion assisting device | |
KR102134366B1 (en) | Ground soil retaining method using h-beam and steel sheet | |
KR20220065461A (en) | WIRE STRUCTURE FOR STAGGERED LAPPING IN SLURRY WALL, SLURRY WALL and CONSTRUCTION METHOD FOR THE SAME | |
KR101219451B1 (en) | Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same | |
KR101407632B1 (en) | Underground auxiliary tunnel structure and construction method for underground auxiliary tunnel structure using presssed pipe | |
KR100588185B1 (en) | A construction method of concrete retaining wall | |
KR102540577B1 (en) | Structure For Connecting Horizontal Rebars In Integrated Underground Wall Construction | |
JPS6198817A (en) | Method of forming concrete wall of underground structure employing composite sheet pile and composite sheet pile as weir panel | |
WO2010093080A1 (en) | Ground excavator and underground polygonal shoring method | |
KR100374062B1 (en) | Soil improvement technique for foundation applied to reinforced earth theory re-using front board | |
EP1964981A1 (en) | Reinforcement elements for in-situ cast walls and method to excavate in situ cast walls | |
KR100556976B1 (en) | New Messer Shield engineering method | |
CN216194666U (en) | Assembled skeleton texture and continuous wall | |
KR102439239B1 (en) | Connecting box for underground continuous wall and construction method using them same | |
KR102268882B1 (en) | Three-way thumb pile reinforcement type self-supporting soil barrier construction method | |
KR102078794B1 (en) | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same | |
KR102139743B1 (en) | Soil retaining method using steel pipe for retaining ground soil and steel plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |