KR102194744B1 - Safety installing structure of main column for inspection passage - Google Patents

Safety installing structure of main column for inspection passage Download PDF

Info

Publication number
KR102194744B1
KR102194744B1 KR1020200024241A KR20200024241A KR102194744B1 KR 102194744 B1 KR102194744 B1 KR 102194744B1 KR 1020200024241 A KR1020200024241 A KR 1020200024241A KR 20200024241 A KR20200024241 A KR 20200024241A KR 102194744 B1 KR102194744 B1 KR 102194744B1
Authority
KR
South Korea
Prior art keywords
inspection
main column
main
pier
inspection passage
Prior art date
Application number
KR1020200024241A
Other languages
Korean (ko)
Inventor
박현철
Original Assignee
박현철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박현철 filed Critical 박현철
Priority to KR1020200024241A priority Critical patent/KR102194744B1/en
Application granted granted Critical
Publication of KR102194744B1 publication Critical patent/KR102194744B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Provided is a safe installation structure of a main column for an inspection passage for a bridge inspection passage, which is able to install a detachable main column anchor unit in a construction method without punching an iron formwork on a pier or an abutment, to firmly attach the inspection passage main column anchor unit in the iron formwork also in the placement of concrete, to be constructed at a preset position of the pier, to hold the inspection passage main column through the inspection passage main column anchor unit after the iron formwork is removed, and to firmly engage the inspection passage main column with the inspection passage main column anchor unit buried in the pier by using bolts. According to a proper embodiment of the present invention, in the structure for safely installing the inspection passage main column supporting a foothold for an inspection passage on a pier, at every position of installation of the inspection passage main column, the inspection passage main column anchor unit is buried in the concrete structure of the pier. The inspection passage main column anchor unit is attached to the iron formwork when constructing the pier, and has its position fixed by the iron formwork and its own strength even when concrete is placed. The inspection passage main column comprises: a horizontal foothold supporter for supporting the foothold; a pier-connecting attachment unit buried in one end of the horizontal foothold supporter to be connected to the inspection passage main column anchor unit side; and a handrail supporter buried in the other end of the horizontal foothold supporter. On the pier-connecting attachment unit, an upper latch and a lower latch held on the inspection passage main column anchor unit side are installed. After inspection passage main column fixing bolts are respectively inserted into the upper latch and the lower latch, the inspection passage main column is fixed to the concrete structure of the pier by being fastened with the inspection passage main column anchor unit side by screws.

Description

교량점검로를 위한 점검로 주기둥의 안전 설치구조{Safety installing structure of main column for inspection passage}Safety installing structure of main column for inspection passage {Safety installing structure of main column for inspection passage}

본 발명은 교량점검로를 위한 점검로 주기둥의 안전 설치구조에 관한 것으로, 특히 교각(교대)측에 철제거푸집 천공없는 시공방식에 탈부착되는 점검로 주기둥 앵커유닛이 설치되도록 함으로써 콘크리트의 타설에도 철제거푸집에서 점검로 주기둥 앵커유닛이 확고하게 부착되어 있어 교각의 설정된 위치에 시공이 가능하고, 철제거푸집의 철거 후에는 점검로 주기둥의 거치가 점검로 주기둥 앵커유닛을 통해 이루어지며, 볼트 결합을 통해 점검로 주기둥이 교각에 매설된 점검로 주기둥 앵커유닛에 확고하게 결합 지지되도록 한 교량점검로를 위한 점검로 주기둥의 안전 설치구조에 관한 것이다.The present invention relates to a safety installation structure of a main post for an inspection road for a bridge inspection route, and in particular, an anchor unit is installed on the pier (alternate) side by an inspection that is detachable in a construction method without iron removal or perforation. Since the main post anchor unit is firmly attached to the bridge by inspection from the iron removal work, construction is possible at the set location of the pier, and after the removal of the iron removal work, the installation of the main post is performed through the main post anchor unit as an inspection. It is related to the safety installation structure of the main post for the inspection route for the bridge inspection route in which the main post is buried in the main pier by coupling and is firmly coupled to the main post anchor unit.

일반적으로 교각에는 교량의 건설을 마치고 차후 교량 받침 점검 및 유지보수 등의 관계로 교각의 하부에 점검로를 설치한다. 교각에서 상부 슬래브에는 차도 또는 인도가 부설되고, 교각의 유지보수 및 관리의 차원에서 교각점검을 위한 통로인 점검로가 설치된다.In general, an inspection path is installed in the lower part of the bridge after completion of the construction of the bridge in the bridge pier for future inspection and maintenance of the bridge support. A roadway or sidewalk is installed on the upper slab of the pier, and an inspection path, which is a passage for inspection of the pier, is installed in terms of maintenance and management of the pier.

점검로는 점검자가 보행시 부주의로 인한 추락사고 등을 방지하기 위하여 교각의 바깥쪽으로 난간 설치를 위해 주기둥이 우선적으로 설치된다. 물론 작업자의 통행 가능한 발판이 주기둥에 설치된다. 이러한 점검로는 단순히 철재의 길이재를 절단하여 용접방식에 의해 설치함에 따라 교각에서 점검대가 차지하는 하중이 과다하여, 교량의 설계 하중에 영향을 주고 있으며, 특히 부식 등의 이유로 용융 아연 도금을 하는 등 피복의 후공정이 필요하며, 설치후 유지관리의 어려움이 있다. 즉, 주된 교각점검 외에 이를 위한 난간대의 점검사항에 따른 관리업무의 불편함이 있는 것이다. 따라서 근래에는 알루미늄재질로써 사형주물 주조형식으로 찍어서 만든 난간 포스트에 발판을 쉽게 조립할 수 있게 하고, 경량화와 내부식성을 좋게 한 제품이 사용되고 있다.In order to prevent accidents such as falls due to carelessness when the inspector walks, the main post is installed preferentially to install railings outside the pier. Of course, a footrest that can be passed by workers is installed in the main post. As such inspection paths are simply cut and installed by a welding method by simply cutting the length of steel, the load occupied by the inspection table in the pier is excessive, affecting the design load of the bridge. A post-coating process is required, and there is difficulty in maintenance after installation. In other words, in addition to the main pier inspection, there is an inconvenience in the management work according to the inspection items of the railing for this purpose. Therefore, in recent years, a product that makes it easy to assemble a scaffolding on a railing post made by stamping it in a sand casting type of aluminum material, and has a light weight and good corrosion resistance, has been used.

한편, 점검로 시설을 위해 주기둥은 교각에 확고하고 안전하게 설치되어야 한다. 예로, 비계 설치를 하는 경우 고소작업으로 인해 안전성이 떨어지고 공사기간이 길어지는 문제가 있다.On the other hand, the main pillar must be firmly and safely installed on the pier for the inspection route facility. For example, when scaffolding is installed, there is a problem that safety is deteriorated and the construction period is prolonged due to high place work.

본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-0353882호로서 '교각에 점검대를 설치하기 위한 고정장치'가 제안되어 있다. 이는 교각의 슬래브 일정위치에 상하 일정 간격으로 매입 설치되는 길이방향의 전,후면에 각각 안내홈을 갖는 레일과, 상기 각각의 레일의 안내홈에 머리가 삽입안내되는 볼트와, 상기 볼트를 상하 일정 간격으로 유지하기 위해 상,하부에 볼트의 로드가 관통되는 구멍을 일정간격으로 갖는 간격편과, 상기 볼트의 로드에는 너트를 체결하여 상기 간격편을 고정하고, 상기 안내홈에 가이드되어 교각 슬래브에 배근된 수직 철근에 접촉되어 용접 또는 결속끈으로 고정되고 전면의 안내홈에는 교각 슬래브 거푸집에 콘크리트 붓기시 메움 방지용으로 삽입되는 실링과, 교각 슬래브의 타설후 상기 실링을 제거한 안내홈에는 대상물 고정수단으로써, 머리가 삽입되어 가이드되는 볼트에 대상물을 관통하여 고정하는 너트로 구성된 것을 특징으로 한다. As a background technology of the present invention, as Korean Patent Registration No. 10-0353882, a'fixing device for installing an inspection table on a pier' has been proposed. This includes rails having guide grooves on the front and rear sides of the longitudinal direction that are buried and installed at regular intervals up and down at a fixed position of the slab of the pier, a bolt through which a head is inserted into the guide groove of each rail, and the bolt is vertically fixed. In order to maintain the gap, a spacer piece having a hole through which the rod of a bolt passes through the upper and lower parts at regular intervals, and a nut is fastened to the rod of the bolt to fix the spacer piece, and guided to the guide groove to It is in contact with the reinforced vertical reinforcing bars and is fixed with welding or binding strings, and a sealing inserted in the front guide groove to prevent filling when concrete is poured into the pier slab formwork, and the guide groove in which the sealing has been removed after the pier slab is placed is a means of fixing objects. , It characterized in that it consists of a nut that penetrates and fixes the object to the bolt that the head is inserted and guided.

그러나 상기 배경기술은 교각에 매입 설치될 때 즉, 콘크리트 타설 전 레일의 위치를 확고하게 고정시키기 위한 기술적 수단이 없어 설정된 위치에 정확히 고정장치를 시공하기 어렵다.However, in the above background technology, it is difficult to accurately install a fixing device at a set position because there is no technical means for firmly fixing the position of the rail before concrete pouring when it is embedded in the pier.

본 발명의 배경이 되는 다른 기술로는 한국 등록특허 등록번호 제10-1453065호로서, '조립형 교량점검난간'이 제안되어 있다. 이는 난간대가 앵커를 통해 교각에 설치되어 있는 구조를 갖기 때문에 앵커 시공을 위한 교각의 천공 작업으로 인해 교각에 진동 균열이 발생될 소지가 있을 뿐만 아니라 이로 인해 앵커 고정력을 신뢰하기 어렵다.As another technology that serves as the background of the present invention, as Korean Patent Registration No. 10-1453065, a'assembled bridge inspection railing' has been proposed. This is because the railing has a structure in which the railing is installed on the pier through an anchor, so not only may vibration cracks occur in the pier due to the drilling work of the pier for anchor construction, but also it is difficult to trust the anchor fixing force.

한국 등록특허 등록번호 제10-0353882호Korean Patent Registration No. 10-0353882 한국 등록특허 등록번호 제10-1453065호Korean Patent Registration No. 10-1453065

본 발명은 교각측에 철제거푸집에 탈부착되는 점검로 주기둥 앵커유닛이 설치되도록 함으로써 콘크리트의 타설에도 철제거푸집에서 점검로 주기둥 앵커유닛이 확고하게 부착되어 있어 교각의 설정된 위치에 시공이 가능하고, 철제거푸집의 철거 후에는 점검로 주기둥의 거치가 점검로 주기둥 앵커유닛을 통해 이루어지며, 볼트 결합을 통해 점검로 주기둥이 교각에 매설된 점검로 주기둥 앵커유닛에 확고하게 결합 지지되도록 한 교량점검로를 위한 점검로 주기둥의 안전 설치구조를 제공함에 그 목적이 있다.In the present invention, the main pillar anchor unit is installed on the pier side by inspection that is detachable from the iron removal piece, so that the main pillar anchor unit is firmly attached to the inspection from the iron removal piece even when concrete is poured, so that construction can be performed at a set position of the pier, After the demolition of the iron removal work, the installation of the main post is carried out through the main post anchor unit as the inspection, and the main post is firmly bonded and supported by the main post anchor unit through the inspection buried in the main post through the inspection through bolts. Its purpose is to provide a safety installation structure of the main post as an inspection route for the inspection route.

본 발명의 적절한 실시 형태에 따르면, 교각에 점검통로용 발판을 지지하는 점검로 주기둥을 안전하게 설치하기 위한 구조에 있어서, 상기 점검로 주기둥이 설치되는 위치마다 교각의 콘크리트구조물내에는 교각 시공시 철제거푸집에 부착되어 콘크리트 타설시에도 철판거푸집과 자력으로 위치가 고정되는 점검로 주기둥 앵커유닛이 매립되어 있고; 상기 점검로 주기둥은 점검통로용 발판을 지지하는 수평발판받침대, 수평발판받침대의 일단에 입설되어 점검로 주기둥 앵커유닛측에 연결되는 교각연결용 부착대, 수평발판받침대의 타단에 입설된 난간지지대로 구성되되, 상기 교각연결용 부착대에는 점검로 주기둥 앵커유닛측에 거치되는 상,하부 걸쇠가 설치되고; 상,하부 걸쇠에 각기 점검로 주기둥 고정볼트가 삽입된 후 점검로 주기둥 앵커유닛측에 나사체결되어 점검로 주기둥이 교각의 콘크리트구조물에 고정되어 있는 것을 특징으로 한다.According to a preferred embodiment of the present invention, in a structure for safely installing a main post for an inspection path supporting a scaffolding for an inspection passage on a pier, the concrete structure of the pier at each position where the main post is installed is made of iron when constructing the pier. It is attached to the formwork and the main column anchor unit is buried as a check in which the position of the steel plate formwork is fixed by magnetic force even when concrete is poured; The inspection path main post is a horizontal scaffold support supporting the scaffolding for the inspection passage, an attachment for pier connection that is installed at one end of the horizontal scaffolding stand and connected to the anchor unit side of the main post for inspection, and a handrail installed at the other end of the horizontal scaffolding stand. Consisting of a support, the attachment for connecting the pier is provided with upper and lower clasps mounted on the anchor unit side of the main pillar as an inspection; It is characterized in that the main post fixing bolts are inserted into the upper and lower clasps for inspection, and then screwed to the main post anchor unit side by inspection, and the main post is fixed to the concrete structure of the pier by inspection.

또한, 상기 점검로 주기둥 앵커유닛은 교각의 콘크리트구조물내에 상,하로 일정 간격를 두고 설치되는 상,하부 점검로 주기둥 거치블럭과; 상기 점검로 주기둥 거치블럭에 각기 복수개씩 삽입되어 있는 상,하부 주기둥 연결너트와; 상기 점검로 주기둥 거치블럭을 각기 통해 주기둥 연결너트의 일단에 체결되어 콘크리트구조물내에 매립된 상,하부 앵커볼트와; 일단이 상부 앵커볼트에 삽입 고정되고 타단이 하부 앵커볼트에 삽입 고정된 간격유지용 플레이트와; 상기 상,하부 점검로 주기둥 거치블럭에 각기 고정 결합되어 있는 복수개의 거푸집 부착용 자석;을 포함한 것을 특징으로 한다.In addition, the inspection path main post anchor unit includes an upper and lower inspection route main post mounting block installed at a predetermined interval up and down in the concrete structure of the pier; A plurality of upper and lower main post connecting nuts inserted into the main post mounting block through the inspection; The upper and lower anchor bolts are fastened to one end of the main post connection nut through each of the main post mounting blocks through the inspection and are embedded in the concrete structure; A plate having one end inserted into and fixed to the upper anchor bolt and the other end inserted into the lower anchor bolt; It characterized in that it comprises a; a plurality of magnets for attaching the formwork, each fixedly coupled to the main column mounting block by the upper and lower inspection.

또한, 상,하부 점검로 주기둥 거치블럭은 반원형 단면구조를 갖는 거치블럭 본체와; 상기 거치블럭 본체의 상부 일측면에 상향 돌출되어 상,하부 걸쇠를 거치시키는 걸쇠 거치턱과; 상기 거치블럭 본체의 중앙에 상,하부 주기둥 연결너트가 위치되도록 사각단면으로 관통된 주기둥 연결너트 결합홈과; 상기 거치블럭 본체의 하부 일측면에 형성된 거푸집 부착용 자석 결합홈이 구비되어 있는 것을 특징으로 한다.In addition, the main column mounting block as the upper and lower inspection includes a mounting block body having a semicircular cross-sectional structure; A clasp mounting jaw protruding upward from an upper side of the mounting block body to mount the upper and lower clasps; A main column connection nut coupling groove through a rectangular cross-section so that the upper and lower main column connection nuts are located in the center of the mounting block body; A magnet coupling groove for attaching a formwork formed on a lower side of the mounting block body is provided.

또한, 상기 거푸집 부착용 자석은 철제거푸집에 부착 후 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭의 밀림이 방지되도록 표면에 널링 가공된 요철이 형성되어 있는 것을 특징으로 한다.In addition, the magnet for attaching the formwork is characterized in that knurling-processed irregularities are formed on the surface of the magnet for attaching the formwork to prevent pushing of the main column mounting block by checking the upper and lower parts when placing concrete after being attached to the iron removal work.

또한, 상기 거치블럭 본체에는 상부* 수평계 설치용 홈이 형성되어 있고, 수평계 설치용 홈에는 점검로 주기둥 앵커유닛의 수평적 설치위치를 맞추기 위해 수평계가 더 설치되어 있는 것을 특징으로 한다.In addition, the mounting block body is characterized in that the upper * horizontal system installation groove is formed, and the level system installation groove is further provided with a level system to adjust the horizontal installation position of the main post anchor unit by inspection.

또한, 상,하부 점검로 주기둥 거치블럭의 각기 거푸집 부착용 자석 결합홈에는 거푸집 부착용 자석을 수용함과 동시에 교각의 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭의 밀림이 방지되도록 상단과 하단에 톱니형 치형을 갖는 밀림방지용 자석하우징이 더 설치되어 있는 것을 특징으로 한다.In addition, by checking the upper and lower parts, the magnet for attaching the formwork is accommodated in the magnet coupling grooves for attaching the formwork of the main column mounting block, and at the same time, the upper and lower parts of the main column mounting block are prevented from being pushed by checking the upper and lower parts when placing concrete in the pier. It is characterized in that a magnetic housing for preventing slipping having a toothed tooth shape is further installed.

또한, 주기둥 연결너트와 주기둥 연결너트 결합홈과의 사이에는 교각에 콘크리트를 타설시 주기둥 연결너트의 나사구멍으로 타설콘크리트의 유입을 차단할 수 있도록 내,외측 콘크리트 유입방지용 실이 설치된 것을 특징으로 한다.In addition, between the main column connection nut and the main column connection nut coupling groove, a seal for preventing the inflow of concrete inside and outside is installed to block the inflow of the poured concrete through the screw hole of the main column connection nut when concrete is poured into the pier. To do.

또한, 상,하부 걸쇠에는 상부에 하향으로 절곡 형성된 걸고리와, 교각연결용 부착대의 걸쇠 결합홀에 삽입 고정되는 걸쇠 원통부와, 걸쇠 원통부의 일단에 상기 걸쇠 결합홀에 삽입 후 삽입 역방향으로 이탈을 억제하는 이탈억지용 경사원판이 구비되어 있는 것을 특징으로 한다.In addition, the upper and lower clasps have a clasp bent downward on the upper side, a clasp cylinder portion inserted and fixed in the clasp fitting hole of the attachment for pier connection, and the clasp fitting hole at one end of the clasp cylindrical portion, and then inserted into the clasp fitting hole, and then removed in the reverse direction. It characterized in that it is provided with an inclined disc for suppressing separation.

본 발명의 교량점검로를 위한 점검로 주기둥의 안전 설치구조에 따르면, 교각측에 철제거푸집에 탈부착되는 점검로 주기둥 앵커유닛이 설치되도록 함으로써 콘크리트의 타설에도 철제거푸집에서 점검로 주기둥 앵커유닛측 점검로 주기둥 거치블럭이 확고하게 부착되어 있어 점검로 주기둥 앵커유닛을 설정된 위치에 정확히 시공될 수 있다.According to the safety installation structure of the main post of the inspection road for the bridge inspection route of the present invention, the main post anchor unit is installed as an inspection route that is attached to and attached to the iron-removing piece on the pier side. As the main post mounting block is firmly attached to the side inspection, the main post anchor unit can be accurately installed at the set position through the inspection.

또한, 철제거푸집의 철거 후에는 점검로 주기둥의 거치가 점검로 주기둥 앵커유닛의 점검로 주기둥 거치블럭을 통해 이루어지며, 볼트 결합을 통해 점검로 주기둥이 안전하고 확고하게 교각에 매설된 점검로 주기둥 앵커유닛에 결합 지지되어 점검로 주기둥의 안전한 설치가 완료된다.In addition, after the demolition of the iron removal work, the installation of the main post is carried out through the main post mounting block as the inspection of the main post anchor unit, and the main post is safely and firmly buried in the pier by checking through bolts. It is connected and supported to the main post anchor unit, and the safe installation of the main post is completed by inspection.

또한, 교각에 천공 작업을 하고 앵커 볼트를 설치하는 과정이 없어져 교각에 진동 균열이 발생될 소지가 없어져 안전한 교각 시공이 가능하다.In addition, since the process of drilling a pier and installing an anchor bolt is eliminated, there is no possibility of vibrating cracks in the pier, thereby enabling safe pier construction.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명에 따른 교량점검로를 위한 점검로 주기둥의 설치 상태도.
도 2는 도 1에 적용된 점검로 주기둥 및 알루미늄 보호용 고무판의 분리사시도.
도 3a는 본 발명에 적용되는 점검로 주기둥에 상부 걸쇠가 설치된 상태도.
도 3b는 도 3a에 도시된 상부 걸쇠의 입체도.
도 4는 도 1의 'K'부 확대도.
도 5는 본 발명에 적용되는 점검로 주기둥 앵커유닛의 사시도.
도 6은 본 발명에 포함된 점검로 주기둥 앵커유닛에 적용된 검검로 주기둥 거치블럭과 거푸집 부착용 자석간의 다양한 설치상태도.
도 7a는 본 발명에 적용되는 점검로 주기둥 앵커유닛의 일측면도로서 철제거푸집에 부착된 상태도.
도 7b는 도 7a에 도시된 점검로 주기둥 앵커유닛의 정면도.
도 8a의 (a),(b),(c)는 본 발명에 적용되는 거푸집 부착용 자석의 정면도, 일측단면도 및 분해사시도.
도 8b는 본 발명에 적용되는 거푸집 부착용 자석에 미끄럼방지용 입자가 도포된 상태도.
도 9는 본 발명에 적용되는 밀림방지용 자석하우징의 사시도.
도 10은 도 9에 도시된 밀림방지용 자석하우징의 설치상태도.
The following drawings attached to the present specification illustrate preferred embodiments of the present invention, and serve to further understand the technical idea of the present invention together with the detailed description of the present invention, so the present invention is limited to the matters described in the accompanying drawings. It is limited and should not be interpreted.
1 is an installation state diagram of the main post of the inspection path for the bridge inspection path according to the present invention.
Figure 2 is an exploded perspective view of the main post and the rubber plate for aluminum protection by the inspection applied to Figure 1;
Figure 3a is a state diagram in which the upper clasp is installed in the main post for inspection applied to the present invention.
Figure 3b is a three-dimensional view of the upper clasp shown in Figure 3a.
Figure 4 is an enlarged view of the'K' portion of Figure 1;
Figure 5 is a perspective view of the anchor unit of the main post for inspection applied to the present invention.
6 is a view of various installation states between the main post mounting block and the magnet for attaching the formwork applied to the main post anchor unit as an inspection furnace included in the present invention.
Figure 7a is a side view of the anchor unit of the main post for inspection applied to the present invention, a state diagram attached to the iron removal work.
Figure 7b is a front view of the anchor unit of the main post of the inspection road shown in Figure 7a.
Figure 8a (a), (b), (c) is a front view, a side cross-sectional view and an exploded perspective view of a magnet for attaching a formwork applied to the present invention.
Figure 8b is a state diagram for anti-slip particles are applied to the magnet for attaching a formwork applied to the present invention.
9 is a perspective view of a magnet housing for preventing slipping applied to the present invention.
10 is an installation state diagram of the magnet housing for preventing slipping shown in FIG. 9;

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.In the following, the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the disclosed embodiments are illustrative for a clear understanding of the present invention, and the present invention is not limited thereto.

본 발명은 도 1과 같이 교각(또는 교대)(10)에 점검통로용 발판(20)을 지지하는 점검로 주기둥(30)을 안전하게 설치하기 위한 구조를 제공한다.The present invention provides a structure for safely installing the main post 30 as an inspection path supporting the scaffolding 20 for an inspection passage on the pier (or alternation) 10 as shown in FIG. 1.

점검로 주기둥(30)이 설치되는 위치마다 교각(10)의 콘크리트구조물(12)내에 도 1 및 도 5에 도시된 바와 같이 점검로 주기둥 앵커유닛(40)이 매립되어 설치된다. 점검로 주기둥 앵커유닛(40)은 교각(10) 시공시 도 7a와 같이 철제거푸집(500)에 부착되어 콘크리트 타설시에도 철판거푸집(500)과 자력으로 위치가 고정되어 움직임없이 설정된 위치에 매설된다. 점검로 주기둥 앵커유닛(40)은 교각(10)의 둘레를 따라 소정 간격을 가지고 설치된다.As shown in Figs. 1 and 5, in the concrete structure 12 of the pier 10 at each location where the inspection path main column 30 is installed, the inspection path main column anchor unit 40 is embedded and installed. The main post anchor unit 40 of the inspection path is attached to the iron removal work 500 as shown in Fig. 7A when the pier 10 is constructed, and the position is fixed by the steel plate formwork 500 and magnetic force even when concrete is poured, and is buried at the set position without movement. do. The anchor unit 40 is installed along the circumference of the pier 10 at predetermined intervals.

여기서, 점검로 주기둥(30)은 점검로를 포함한 작업자들의 하중을 지지하는 부분이다. 점검로 주기둥(30)은 점검통로용 발판(20)을 지지하는 수평발판받침대(31), 수평발판받침대(31)의 일단에 입설되어 점검로 주기둥 앵커유닛(40)측에 확고하게 연결되는 교각연결용 부착대(32), 수평발판받침대(31)의 타단에 입설되고 난간대(35)가 설치되는 난간지지대(33)로 구성된다. 이때 교각연결용 부착대(32)에는 도 3 및 도 4와 같이 점검로 주기둥 앵커유닛(40)측에 거치되기 위한 상,하부 걸쇠(50,50a)가 설치되어 있다. 상,하부 걸쇠(50,50a)는 동일 구조를 갖는 것으로 상부에 하향으로 절곡된 걸고리(501)가 형성되어 있다. 또한 상,하부 걸쇠(50,50a)는 교각연결용 부착대(32)의 걸쇠 결합홀(32a)에 삽입 고정되는 걸쇠 원통부(502)가 구비되어 있고, 걸쇠 원통부(502)에는 상,하부 걸쇠(50,50a)가 걸쇠 결합홀(32a)에 삽입 후 삽입 역방향으로 이탈을 억제하는 이탈억지용 경사원판(503)이 구비될 수 있다. 이탈억지용 경사원판(503)은 도 3과 같이 걸쇠 결합홀(32a)에 삽입 후 외력의 힘(타격) 또는 점검로 주기둥 고정볼트(59)의 체결력에 의해 강제적으로 벌어지고, 이에 의해 이탈억지용 경사원판(503)은 걸쇠 결합홀(32a)에서 빠져나올 수 없어 상,하부 걸쇠(50,50a)를 고정시킨다.Here, the inspection path main column 30 is a part that supports the load of workers including the inspection path. The inspection path main post (30) is installed at one end of the horizontal scaffold support (31) and horizontal scaffold support (31) that supports the inspection passage scaffold (20), and is firmly connected to the inspection route main post anchor unit (40) side. It is composed of a railing support 33, which is installed on the other end of the pier connection attachment 32, the horizontal footrest support 31, and the handrail 35 is installed. At this time, the pier connection attachment 32 is provided with upper and lower clasps 50 and 50a to be mounted on the main post anchor unit 40 side as shown in FIGS. 3 and 4. The upper and lower clasps 50 and 50a have the same structure, and the clasps 501 bent downwardly are formed at the top. In addition, the upper and lower clasps (50, 50a) are provided with a clasp cylindrical portion 502 that is inserted and fixed to the clasp coupling hole (32a) of the pier connection attachment 32, and the clasp cylindrical portion 502 has an upper, After the lower clasps 50 and 50a are inserted into the clasp coupling hole 32a, an inclined disc 503 for preventing separation may be provided to suppress separation in the reverse direction of insertion. As shown in Fig. 3, the inclined disc 503 is forcibly opened by the force of external force (strike) or the fastening force of the main column fixing bolt 59 by inspection after being inserted into the clasp coupling hole 32a, as shown in FIG. The inclined disc 503 for deterrence cannot come out from the clasp coupling hole 32a and thus fixes the upper and lower clasps 50 and 50a.

점검로 주기둥(30)은 상,하부 걸쇠(50,50a)가 점검로 주기둥 앵커유닛(40)측에 거치된 후 상,하부 걸쇠(50,50a)에 각기 점검로 주기둥 고정볼트(59)가 삽입된 후 점검로 주기둥 앵커유닛(40)측에 나사체결되어 교각(10)의 콘크리트구조물(12)에 고정되어 설치된다.In the inspection path main post 30, the upper and lower clasps (50, 50a) are mounted on the side of the main column anchor unit 40 as the inspection path, and then the upper and lower clasps (50, 50a) are respectively inspected by fixing bolts ( After 59) is inserted, it is screwed to the main column anchor unit 40 side by inspection and fixed to the concrete structure 12 of the pier 10 and installed.

도 5 및 도 7과 같이 점검로 주기둥 앵커유닛(40)은 교각(10)의 콘크리트구조물(12)내에 상,하로 일정 간격(S)를 두고 설치되는 상,하부 점검로 주기둥 거치블럭(41,41a)과, 점검로 주기둥 거치블럭(41,41a)에 각기 복수개씩 삽입되어 있는 상,하부 주기둥 연결너트(42,42a)와, 점검로 주기둥 거치블럭(41,41a)을 각기 통해 상,하부 주기둥 연결너트(42,42a)의 일단에 체결되어 콘크리트구조물(12)내에 매립된 상,하부 앵커볼트(43,43a)와, 일단이 상부 앵커볼트(43)에 삽입 고정되고 타단이 하부 앵커볼트(43a)에 삽입 고정된 간격유지용 플레이트(44)와, 상,하부 점검로 주기둥 거치블럭(41,41a)에 각기 고정 결합되어 있는 복수개의 거푸집 부착용 자석(45,45a)을 포함한다.As shown in FIGS. 5 and 7, the main post anchor unit 40 of the pier 10 is installed at a certain distance S up and down in the concrete structure 12 of the pier 10. 41,41a), the upper and lower main post connecting nuts 42 and 42a, which are inserted in plural pieces respectively, into the main post mounting blocks 41 and 41a as an inspection, and the main post-mounting blocks 41 and 41a as an inspection. The upper and lower anchor bolts 43 and 43a, which are fastened to one end of the upper and lower main column connecting nuts 42 and 42a and embedded in the concrete structure 12, and one end are inserted and fixed to the upper anchor bolt 43 And the other end is inserted into the lower anchor bolt (43a) and a fixed gap maintenance plate (44), and a plurality of formwork attachment magnets (45, respectively) fixedly coupled to the main column mounting blocks (41, 41a) by upper and lower inspection. 45a).

여기서, 도 6과 같이 상,하부 점검로 주기둥 거치블럭(41,41a)은 반원형 단면구조를 갖는 거치블럭 본체(411)와, 거치블럭 본체(411)의 상부 일측면에 상향 돌출되어 상,하부 걸쇠(50,50a)를 거치시키는 걸쇠 거치턱(412)과, 거치블럭 본체(411)의 중앙에 상,하부 주기둥 연결너트(42)가 위치되도록 사각단면으로 관통된 주기둥 연결너트 결합홈(413)과, 거치블럭 본체(411)의 하부 일측면에 형성된 거푸집 부착용 자석 결합홈(414)이 구비되어 있다.Here, as shown in FIG. 6, the main column mounting blocks 41 and 41a are protruding upward from the upper one side of the mounting block body 411 and the mounting block body 411 having a semicircular cross-sectional structure. The clasp mounting jaws 412 for mounting the lower clasps (50, 50a) and the main column connecting nut penetrated in a rectangular cross section so that the upper and lower main column connecting nuts 42 are located in the center of the mounting block body 411 are combined. A groove 413 and a magnet coupling groove 414 for attaching a formwork formed on a lower side of the mounting block body 411 are provided.

거푸집 부착용 자석(45,45a)은 거푸집 부착용 자석 결합홈(414)의 깊이에 따라 도 6과 같이 하나 이상으로 적층되어 설치될 수 있다. 이때 거푸집 부착용 자석(45,45a)은 거치블럭 본체(411)에 체결되는 나사(47)에 의해 거푸집 부착용 자석 결합홈(414)에 확고하게 고정 설치된다. 또한 거푸집 부착용 자석(45,45a)은 도 4와 같이 상,하부 걸쇠(50,50a)에 각기 자력으로 흡착되어져 점검로 주기둥 앵커유닛(40)의 설치 위치가 고정된다.One or more magnets 45 and 45a for attaching the formwork may be stacked and installed as shown in FIG. 6 according to the depth of the magnet coupling groove 414 for attaching the formwork. At this time, the magnets 45 and 45a for attaching the formwork are firmly fixed to the magnet coupling groove 414 for attaching the formwork by screws 47 that are fastened to the mounting block body 411. In addition, as shown in Fig. 4, the magnets 45 and 45a for attaching the formwork are respectively magnetically adsorbed to the upper and lower clasps 50 and 50a, so that the installation position of the main column anchor unit 40 is fixed by inspection.

이같이 상,하부 점검로 주기둥 거치블럭(41,41a)은 알루미늄으로 제작되더라도 거푸집 부착용 자석(45,45a)이 부착되어 있어 도 7a의 철제거푸집(500)에 점검로 주기둥 앵커유닛(40)이 확고하게 부착될 수 있도록 한다. As such, even if the main pole mounting blocks 41 and 41a are made of aluminum, the magnets 45 and 45a for attaching the formwork are attached to the iron removal work 500 of FIG. So that it can be firmly attached.

따라서 점검로 주기둥 앵커유닛(40)을 철제거푸집(500)에 거푸집 부착용 자석(45,45a)을 이용하여 부착시킨 후 콘크리트를 타설하게 되더라도 상,하부 점검로 주기둥 거치블럭(41,41a)의 고정이 이루어져 점검로 주기둥 앵커유닛(40)은 정위치에서 콘크리트에 매립되게 된다. 이때 고무 또는 실리콘으로 제작된 마개(90)가 상,하부 점검로 주기둥 거치블럭(41,41a)에 강제적으로 삽입되어 상,하부 주기둥 연결너트(42,42a)의 나사구멍의 입구를 밀폐시키게 되어 타설콘크리트가 상,하부 주기둥 연결너트(42,42a)의 나사구멍으로 침입되지 못한다.Therefore, even if concrete is poured after attaching the main column anchor unit 40 to the iron removal piece 500 using the magnets 45 and 45a for attaching the formwork, the main column mounting blocks 41 and 41a are used for upper and lower inspection. The main column anchor unit 40 is embedded in the concrete at the correct position as the main column anchor unit 40 is fixed by inspection. At this time, a stopper 90 made of rubber or silicone is forcibly inserted into the main column mounting blocks 41 and 41a by checking the upper and lower parts to seal the entrance of the screw hole of the upper and lower main column connection nuts 42 and 42a. As a result, the poured concrete cannot penetrate into the screw holes of the upper and lower main column connecting nuts 42 and 42a.

이같이 점검로 주기둥 앵커유닛(40)이 콘크리트에 매립되면, 앵커볼트(43)와 간격유지용 플레이트(44)가 콘크리트에 합성되어 상,하부 점검로 주기둥 거치블럭(41,41a)은 콘크리트층에 확고히 고정된다. 따라서 점검로 주기둥(30)이 점검로 주기둥 고정볼트(59)를 통해 점검로 주기둥 앵커유닛(40)에 결합되면 설치 안전성이 증가된다.In this way, when the main column anchor unit 40 is embedded in concrete by inspection, the anchor bolts 43 and the plate 44 for maintaining the gap are combined with the concrete, and the main column mounting blocks 41 and 41a are It is firmly fixed to the floor. Therefore, when the inspection path main column 30 is coupled to the inspection path main column anchor unit 40 through the inspection path main column fixing bolt 59, the installation safety is increased.

한편, 도 8a와 같이 거푸집 부착용 자석(45,45a)에는 철제거푸집에 부착 후 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 널링 가공된 널링 마찰판(451)이 설치될 수 있다. 이같이 널링 마찰판(451)은 표면의 널링 무늬에 의해 마찰작용이 극대화된다. 또한 도 8b와 같이 거푸집 부착용 자석(45,45a)에는 철제거푸집에 부착 후 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 표면에 마찰의 극대화를 위해 미끄럼방지용 입자(452)가 도포되어 구성될 수도 있다. 미끄럼방지용 입자(452)는 마찰계수가 높은 입자로서 예로 규사, 세라믹, 탄화규소, 산화알루미늄 등등의 알려진 거친 입자가 될 수 있다.On the other hand, as shown in Fig. 8a, the knurled friction plate 451 is knurled to prevent the sliding of the main column mounting blocks 41 and 41a by checking the upper and lower parts when placing concrete after attaching to the iron removal work after attaching to the iron removal work as shown in FIG. Can be installed. In this way, the knurling friction plate 451 maximizes the frictional action by the knurling pattern on the surface. In addition, as shown in Figure 8b, the magnet for attaching the formwork (45, 45a) is attached to the iron removal piece and then inspected at the top and bottom when placing concrete to prevent slipping of the main column mounting blocks (41, 41a). Particles 452 may be applied and configured. The anti-slip particles 452 are particles having a high coefficient of friction and may be known coarse particles such as silica sand, ceramics, silicon carbide, aluminum oxide, and the like.

또한, 도 4 및 도 6과 같이 상부 점검로 주기둥 거치블럭(41)의 거치블럭 본체(411)에는 상부에 수평계 설치용 홈(411a)이 형성되어 있고, 수평계 설치용 홈(411a)에는 점검로 주기둥 앵커유닛(40)의 수평적 설치위치를 맞추기 위해 상부 수평계(420)가 더 설치될 수 있다. 물론 하부 점검로 주기둥 거치블럭(41,41a)에도 동일한 구조에 의해 하부 수평계(420a)가 더 설치될 수 있다.In addition, as shown in Figs. 4 and 6, a mounting block main body 411 of the main column mounting block 41 has a leveler installation groove 411a formed at the top, and the leveler installation groove 411a is an inspection path. An upper leveling system 420 may be further installed to adjust the horizontal installation position of the column anchor unit 40. Of course, the lower leveling system 420a may be further installed in the main column mounting blocks 41 and 41a by the same structure as the lower inspection.

또한, 도 9 및 도 10과 같이 상,하부 점검로 주기둥 거치블럭(41,41a)의 각기 거푸집 부착용 자석 결합홈(414)에는 거푸집 부착용 자석(45)을 수용함과 동시에 교각의 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 상단과 하단에 톱니형 치형(491)을 갖는 밀림방지용 자석하우징(49)이 더 설치될 수 있다.In addition, as shown in Figs. 9 and 10, the magnet 45 for attaching the formwork is accommodated in the magnetic coupling groove 414 for attaching the formwork of the main column mounting blocks 41 and 41a by checking the upper and lower parts, A magnet housing 49 for preventing slipping having a toothed tooth 491 at the top and bottom may be further installed to prevent the main column mounting blocks 41 and 41a from being pushed through the upper and lower inspection.

한편, 도 4와 같이 주기둥 연결너트(42)와 주기둥 연결너트 결합홈(413)과의 사이에는 교각(교대)에 콘크리트를 타설시 주기둥 연결너트(42)의 나사구멍으로 타설콘크리트의 유입을 차단할 수 있도록 내,외측 콘크리트 유입방지용 실(60,61)이 설치됨이 바람직하다.On the other hand, as shown in Fig. 4, between the main column connection nut 42 and the main column connection nut coupling groove 413, when concrete is poured into the pier (alternating), a screw hole of the main column connection nut 42 It is preferable that the inner and outer concrete inflow prevention chambers 60 and 61 are installed to block the inflow.

또한, 점검로 주기둥(30)을 알루미늄을 제작하는 경우 교각연결용 부착대(32)와 교각(10)의 사이에는 알루미늄 보호용 고무판(15)이 설치될 수 있다. 이때 알루미늄 보호용 고무판(15)은 상,하부 점검로 주기둥 거치블럭(41,41a)이 교각연결용 부착대(32)에 밀착 설치되도록 개구부(15a)를 갖는다.In addition, when the main column 30 is made of aluminum for inspection, an aluminum protective rubber plate 15 may be installed between the pier connection attachment 32 and the pier 10. At this time, the aluminum protective rubber plate 15 has an opening 15a so that the main column mounting blocks 41 and 41a are installed in close contact with the pier connection attachment 32 for upper and lower inspection.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. Until now, the present invention has been described in detail with reference to the presented embodiments, but those of ordinary skill in the art can make various modifications and modifications without departing from the technical spirit of the present invention with reference to the presented embodiments. will be. The present invention is not limited by such modifications and modifications, but is limited by the claims appended below.

30: 점검로 주기둥
40: 점검로 주기둥 앵커유닛
41,41a: 상,하부 점검로 주기둥 거치블럭
42,42a: 상,하부 주기둥 연결너트
43,43a: 상,하부 앵커볼트(매립볼트)
44: 간격유지용 플레이트
45,45a: 거푸집 부착용 자석
50,50a: 상,하부 걸쇠
30: check furnace main post
40: inspection furnace main post anchor unit
41,41a: Main post mounting block by upper and lower inspection
42,42a: upper and lower main column connecting nut
43,43a: upper and lower anchor bolts (embedded bolts)
44: gap maintenance plate
45,45a: Magnet for attaching formwork
50,50a: upper and lower clasps

Claims (9)

교각(10)에 점검통로용 발판(20)을 지지하는 점검로 주기둥(30)을 안전하게 설치하기 위한 구조에 있어서,
상기 점검로 주기둥(30)이 설치되는 위치마다 교각(교대)(10)의 콘크리트구조물(12)내에는 교각(10) 시공시 철제거푸집(500)에 부착되어 콘크리트 타설시에도 철판거푸집과 자력으로 위치가 고정되는 점검로 주기둥 앵커유닛(40)이 매립되어 있고;
상기 점검로 주기둥(30)은 점검통로용 발판(20)을 지지하는 수평발판받침대(31), 수평발판받침대(31)의 일단에 입설되어 점검로 주기둥 앵커유닛(40)측에 연결되는 교각연결용 부착대(32), 수평발판받침대(31)의 타단에 입설된 난간지지대(33)로 구성되되, 상기 교각연결용 부착대(32)에는 점검로 주기둥 앵커유닛(40)측에 거치되는 상,하부 걸쇠(50,50a)가 설치되고;
상,하부 걸쇠(50,50a)에 각기 점검로 주기둥 고정볼트(59)가 삽입된 후 점검로 주기둥 앵커유닛(40)측에 나사체결되어 점검로 주기둥(30)이 교각(10)의 콘크리트구조물(12)에 고정되고;
상기 점검로 주기둥 앵커유닛(40)은 교각(10)의 콘크리트구조물(12)내에 상,하로 일정 간격(S)를 두고 설치되는 상,하부 점검로 주기둥 거치블럭(41,41a)과; 상기 점검로 주기둥 거치블럭(41,41a)에 각기 복수개씩 삽입되어 있는 상,하부 주기둥 연결너트(42,42a)와; 상기 점검로 주기둥 거치블럭(41,41a)을 각기 통해 주기둥 연결너트(42,42a)의 일단에 체결되어 콘크리트구조물(12)내에 매립된 상,하부 앵커볼트(43,43a)와; 일단이 상부 앵커볼트(43)에 삽입 고정되고 타단이 하부 앵커볼트(43a)에 삽입 고정된 간격유지용 플레이트(44)와; 상기 상,하부 점검로 주기둥 거치블럭(41,41a)에 각기 고정 결합되어 있는 복수개의 거푸집 부착용 자석(45,45a);을 포함한 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
In the structure for safely installing the main post 30 through the inspection path for supporting the scaffolding 20 for the inspection passage on the pier 10,
In the concrete structure 12 of the pier (alternate) 10 at each location where the main pillar 30 is installed as the inspection, it is attached to the iron removal work 500 during the construction of the pier 10, and the steel plate form and magnetic force The main column anchor unit 40 is buried by the inspection in which the position is fixed;
The inspection path main pillar 30 is installed at one end of the horizontal footrest support 31 and the horizontal footrest support 31 to support the inspection passage footrest 20, and is connected to the main anchor unit 40 side of the inspection passage. It is composed of a bridge pier connection attachment (32), a railing support (33) installed on the other end of the horizontal footrest support (31), and the pier connection attachment (32) has an inspection path on the main column anchor unit (40) side. The upper and lower clasps 50 and 50a to be mounted are installed;
After the main post fixing bolts 59 are inserted into the upper and lower clasps (50, 50a) for inspection, the main post 30 is screwed to the main post anchor unit 40 side by inspection. Is fixed to the concrete structure 12;
The inspection path main post anchor unit 40 includes upper and lower inspection road main post mounting blocks 41 and 41a installed at a predetermined distance S up and down in the concrete structure 12 of the pier 10; A plurality of upper and lower main post connecting nuts 42 and 42a inserted into the main post mounting blocks 41 and 41a through the inspection; The upper and lower anchor bolts 43 and 43a are fastened to one end of the main post connection nuts 42 and 42a through the main post mounting blocks 41 and 41a as the inspection and are embedded in the concrete structure 12; A plate 44 having one end inserted and fixed to the upper anchor bolt 43 and the other end inserted and fixed into the lower anchor bolt 43a; Safety installation of the main post as an inspection route for a bridge inspection route, comprising: a plurality of magnets for attaching a formwork (45, 45a) fixedly coupled to the main post mounting blocks 41 and 41a by the upper and lower inspection routes. rescue.
삭제delete 제 1항에 있어서,
상,하부 점검로 주기둥 거치블럭(41,41a)은
반원형 단면구조를 갖는 거치블럭 본체(411)와;
상기 거치블럭 본체(411)의 상부 일측면에 상향 돌출되어 상,하부 걸쇠(50,50a)를 거치시키는 걸쇠 거치턱(412)과;
상기 거치블럭 본체(411)의 중앙에 상,하부 주기둥 연결너트(42)가 위치되도록 사각단면으로 관통된 주기둥 연결너트 결합홈(413)과;
상기 거치블럭 본체(411)의 하부 일측면에 형성된 거푸집 부착용 자석 결합홈(414)이 구비되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 1,
By checking the upper and lower parts, the main column mounting blocks (41, 41a)
A mounting block main body 411 having a semicircular cross-sectional structure;
A clasp mounting jaw 412 protruding upward from an upper side of the mounting block body 411 to mount the upper and lower clasps 50 and 50a;
A main column connection nut coupling groove 413 penetrating in a rectangular cross-section so that the upper and lower main column connection nuts 42 are located in the center of the mounting block body 411;
A safety installation structure of a main post for an inspection path for a bridge inspection path, characterized in that a magnetic coupling groove 414 for attaching a formwork formed on a lower side of the mounting block body 411 is provided.
제 3항에 있어서,
상기 거푸집 부착용 자석(45,45a)에는 철제거푸집에 부착 후 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 표면에 마찰작용이 극대화되도록 널링 가공된 널링 마찰판(451)이 더 설치되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 3,
The knurling friction plate ( 451) is further installed, the safety installation structure of the main post for the inspection route for the bridge inspection route.
제 3항에 있어서,
상기 거푸집 부착용 자석(45,45a)에는 철제거푸집에 부착 후 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 표면에 마찰의 극대화를 위해 미끄럼방지용 입자(452)가 도포되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 3,
The magnet for attaching the formwork (45,45a) has anti-slip particles (452) for maximizing friction on the surface so as to prevent the sliding of the main column mounting blocks (41,41a) by checking the upper and lower parts when placing concrete after attaching to the iron removal piece. Safety installation structure of the main post as an inspection route for a bridge inspection route, characterized in that is applied.
제 3항에 있어서,
상기 거치블럭 본체(411)에는 상부에 수평계 설치용 홈(411a)이 형성되어 있고, 수평계 설치용 홈(411a)에는 점검로 주기둥 앵커유닛(40)의 수평적 설치위치를 맞추기 위해 수평계(420)가 더 설치되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 3,
The mounting block main body 411 has a leveler installation groove 411a formed at the top, and the leveler installation groove 411a includes a leveler 420 to adjust the horizontal installation position of the main column anchor unit 40 as an inspection. Safety installation structure of the main post as an inspection path for a bridge inspection path, characterized in that it is further installed.
제 3항에 있어서,
상,하부 점검로 주기둥 거치블럭(41,41a)의 각기 거푸집 부착용 자석 결합홈(414)에는 거푸집 부착용 자석(45)을 수용함과 동시에 교각의 콘크리트 타설시 상,하부 점검로 주기둥 거치블럭(41,41a)의 밀림이 방지되도록 상단과 하단에 톱니형 치형(491)을 갖는 밀림방지용 자석하우징(49)이 더 설치되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 3,
By checking the upper and lower parts, the magnet for attaching the formwork is accommodated in the magnet coupling groove 414 for attaching the formwork in each of the main column mounting blocks (41, 41a). Safety installation of the main post as an inspection for a bridge inspection route, characterized in that a magnet housing 49 for preventing slipping having a toothed tooth 491 at the top and bottom is further installed to prevent the pushing of (41, 41a) rescue.
제 3항에 있어서,
주기둥 연결너트(42)와 주기둥 연결너트 결합홈(413)과의 사이에는 교각에 콘크리트를 타설시 주기둥 연결너트(42)의 나사구멍으로 타설콘크리트의 유입을 차단할 수 있도록 내,외측 콘크리트 유입방지용 실(60,61)이 설치된 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 3,
Between the main column connection nut 42 and the main column connection nut coupling groove 413, when concrete is poured into the pier, the inner and outer concrete can be blocked through the screw hole of the main column connection nut 42. Safety installation structure of the main post for inspection routes for bridge inspection routes, characterized in that the inflow prevention chamber (60, 61) is installed.
제 1항에 있어서,
상,하부 걸쇠(50,50a)에는 상부에 하향으로 절곡 형성된 걸고리(501)와, 교각연결용 부착대(32)의 걸쇠 결합홀(32a)에 삽입 고정되는 걸쇠 원통부(502)와, 걸쇠 원통부(502)의 일단에 상기 걸쇠 결합홀(32a)에 삽입 후 삽입 역방향으로 이탈을 억제하는 이탈억지용 경사원판(503)이 구비되어 있는 것을 특징으로 하는 교량점검로를 위한 점검로 주기둥의 안전 설치구조.
The method of claim 1,
The upper and lower clasps (50, 50a) include a clasp 501 bent downwardly at the top, a clasp cylindrical portion 502 inserted and fixed into the clasp coupling hole 32a of the pier connection attachment 32, and the clasp An inspection path for a bridge inspection path, characterized in that an inclined disc 503 is provided at one end of the cylindrical part 502 for suppressing separation in the reverse direction of insertion after being inserted into the clasp coupling hole 32a. Safety installation structure.
KR1020200024241A 2020-02-27 2020-02-27 Safety installing structure of main column for inspection passage KR102194744B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200024241A KR102194744B1 (en) 2020-02-27 2020-02-27 Safety installing structure of main column for inspection passage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200024241A KR102194744B1 (en) 2020-02-27 2020-02-27 Safety installing structure of main column for inspection passage

Publications (1)

Publication Number Publication Date
KR102194744B1 true KR102194744B1 (en) 2020-12-23

Family

ID=74089198

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200024241A KR102194744B1 (en) 2020-02-27 2020-02-27 Safety installing structure of main column for inspection passage

Country Status (1)

Country Link
KR (1) KR102194744B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102277193B1 (en) 2021-01-12 2021-07-14 (주)이알코리아 Formwork perforation type pre-embedded anchor device for installation of bridge inspection facilities
KR102338605B1 (en) 2021-08-09 2021-12-14 주식회사 에스티 All-in-one inspection facility and construction method with reinforced durability
KR102404663B1 (en) 2021-08-10 2022-06-02 두한종합건설 주식회사 Inspection facility equipped with rail type safety hook and its construction method
KR102413916B1 (en) 2021-01-12 2022-06-28 (주)이알코리아 Construction method of pre-buried anchor in formwork perforation type for installation of bridge inspection facility

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0561343U (en) * 1992-01-28 1993-08-13 松下電工株式会社 Mounting jig for hanging metal fittings for hanging cabinets
KR19980032036U (en) * 1998-05-19 1998-08-17 김남영 Fastening Reinforcement Member
KR20010104585A (en) * 2000-05-15 2001-11-26 박현철 Fixation Device and Apparatus for Mounting Checking Plate in a Bent
KR101293853B1 (en) * 2012-02-08 2013-08-07 주식회사 로드맥스 엔지니어링 Bridge inspection passage
KR101453065B1 (en) 2013-02-04 2014-10-23 주식회사 무한건설 A built-up type a bridge inspection rail
KR102078267B1 (en) * 2019-02-28 2020-02-18 현빈개발 주식회사 Rebar fixed type Pre-embedded Prefabricated Anchor for Bridge Inspection Facility and Method for constructing this same

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0561343U (en) * 1992-01-28 1993-08-13 松下電工株式会社 Mounting jig for hanging metal fittings for hanging cabinets
KR19980032036U (en) * 1998-05-19 1998-08-17 김남영 Fastening Reinforcement Member
KR20010104585A (en) * 2000-05-15 2001-11-26 박현철 Fixation Device and Apparatus for Mounting Checking Plate in a Bent
KR100353882B1 (en) 2000-05-15 2002-09-27 주식회사 로드맥스 엔지니어링 Fixation Device and Apparatus for Mounting Checking Plate in a Bent
KR101293853B1 (en) * 2012-02-08 2013-08-07 주식회사 로드맥스 엔지니어링 Bridge inspection passage
KR101453065B1 (en) 2013-02-04 2014-10-23 주식회사 무한건설 A built-up type a bridge inspection rail
KR102078267B1 (en) * 2019-02-28 2020-02-18 현빈개발 주식회사 Rebar fixed type Pre-embedded Prefabricated Anchor for Bridge Inspection Facility and Method for constructing this same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102277193B1 (en) 2021-01-12 2021-07-14 (주)이알코리아 Formwork perforation type pre-embedded anchor device for installation of bridge inspection facilities
KR102413916B1 (en) 2021-01-12 2022-06-28 (주)이알코리아 Construction method of pre-buried anchor in formwork perforation type for installation of bridge inspection facility
KR102338605B1 (en) 2021-08-09 2021-12-14 주식회사 에스티 All-in-one inspection facility and construction method with reinforced durability
KR102404663B1 (en) 2021-08-10 2022-06-02 두한종합건설 주식회사 Inspection facility equipped with rail type safety hook and its construction method

Similar Documents

Publication Publication Date Title
KR102194744B1 (en) Safety installing structure of main column for inspection passage
KR100998631B1 (en) Sidewalk for bridge
KR102119202B1 (en) Magnetic type embeded anchor
KR102168358B1 (en) Landfill facility for bridge inspection structure and construction method
KR101353491B1 (en) Method for constructing the balcony using a precast concrete balcony and the precast concrete balcony for a building
KR100782667B1 (en) Embedded device for fixing inspection facilites of bridge
KR102033453B1 (en) Method for Construction Threshold of Gate for Elevator Cabin
KR100989111B1 (en) Tilting access stairway structure for approaching bridge inspection passage
KR100675571B1 (en) Safety anchor for concrete structure and the constructing method thereof
KR20200098233A (en) Safe apparatus for preventing fall
KR102470452B1 (en) Temporary Structure for Bridge Inspection
KR200426056Y1 (en) Concrete slab railing prop for joining it to bare reinforcing rod directly
KR100353882B1 (en) Fixation Device and Apparatus for Mounting Checking Plate in a Bent
KR101576542B1 (en) The safety handrail to easy installation
KR200303255Y1 (en) Rail for checking pier and fixing apparatus thereof
JP3862707B2 (en) Construction method of overpass slab and precast concrete plate for overhang slab
KR100554473B1 (en) Check road structure of cutting the ground part of road
KR101839600B1 (en) a Bridge check road using wire
KR100557880B1 (en) Apparatus for fixing bridge checking device to bridge
KR200206699Y1 (en) Fixation Device for Mounting Checking Plate in a Bent
BE1017137A3 (en) Anchor for securing safety railing supports in wall, includes connectors at both ends for securing inside wall and to railing support stand
KR100586487B1 (en) The foundation instrument for a railing's pole
NL1024287C1 (en) Hanging strip for securing safety rail to sand lime brick wall, contains tongue with slot for rail post bracket
KR200497116Y1 (en) Safety guard fixing device
NZ336959A (en) Scaffolding

Legal Events

Date Code Title Description
GRNT Written decision to grant