KR102163522B1 - Precast floor plate having level correction unit and construction method of the same - Google Patents

Precast floor plate having level correction unit and construction method of the same Download PDF

Info

Publication number
KR102163522B1
KR102163522B1 KR1020190165741A KR20190165741A KR102163522B1 KR 102163522 B1 KR102163522 B1 KR 102163522B1 KR 1020190165741 A KR1020190165741 A KR 1020190165741A KR 20190165741 A KR20190165741 A KR 20190165741A KR 102163522 B1 KR102163522 B1 KR 102163522B1
Authority
KR
South Korea
Prior art keywords
correction
precast
bolt
floor plate
correction unit
Prior art date
Application number
KR1020190165741A
Other languages
Korean (ko)
Inventor
천진욱
서동영
이승후
Original Assignee
(주)아이오컨스텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)아이오컨스텍 filed Critical (주)아이오컨스텍
Priority to KR1020190165741A priority Critical patent/KR102163522B1/en
Application granted granted Critical
Publication of KR102163522B1 publication Critical patent/KR102163522B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

Provided are a precast bottom plate and a constructing method thereof, which are more precise than a conventional step correcting method of a precast bottom plate, prevent damage to a girder due to a height adjusting bolt, have a distribution plate integrated with the precast bottom plate to improve the convenience of a bottom plate installing operation, do not cause direct rotation of the distribution plate to reduce a rotational force of a bolt so as to improve workability in a step correcting stage, and conveniently remove a correcting bolt after an operation is completed. According to an embodiment of the present invention, the precast bottom plate comprises: a precast bottom plate body manufactured by installing a tendon or rebar, and then pouring and curing the same with concrete in a factory; a height adjustment unit buried in the precast bottom plate body to adjust an installation height; and a step correction unit including a lower end burying unit fastened to a lower end of the height adjustment unit.

Description

단차보정유닛이 구비된 프리캐스트 바닥판 및 그 시공방법{Precast floor plate having level correction unit and construction method of the same}Precast floor plate having level correction unit and construction method of the same}

본 발명은 높이 조절을 통해 거더위에 거치된 프리캐스트 바닥판의 단차를 보정할 수 있는 단차보정유닛이 구비된 프리캐스트 바닥판 및 이를 이용한 시공 방법에 관한 것으로, 특히 프리캐스트 바닥판 거치전 일체화 되었다가 연질가결제의 파괴로 높이조절부와 분리되는 하단매립부를 적용하여, 거더에 손상을 가하지 않고 적은 회전력으로 정밀하게 단차를 보정할 수 있으며, 단차보정을 완료한 후 필요에 따라 보정볼트를 제거할 수 있는 단차보정유닛이 구비된 프리캐스트 바닥판 및 시공방법에 관한 것이다.The present invention relates to a precast floor plate equipped with a step correction unit capable of correcting a level difference of a precast floor plate mounted on a girder through height adjustment, and a construction method using the same, and in particular, integration before mounting the precast floor plate Then, by applying the bottom buried part separated from the height adjustment part due to the destruction of the soft payment agent, it is possible to accurately correct the step with little rotational force without damaging the girder, and remove the correction bolt as necessary after completing the step correction. It relates to a precast floor plate and a construction method provided with a step correction unit capable of.

교량의 콘크리트 바닥판은 일반적으로 현장에서 거푸집을 제작하여 콘크리트를 타설하고, 장기간의 양생을 통해 완성한다. 그러나, 이와 같은 전통적인 방식의 바닥판 시공법은 거푸집의 설치 및 해체에 따른 공사기간의 증가 및 낙하물 등으로 인한 안전사고 발생 우려가 있으며, 현장 여건 및 기상 조건 등으로 인하여 균등한 품질의 콘크리트 바닥판을 시공하기 어렵고, 이로 인한 간접적인 손실이 발생하는 등 여러 문제점이 발생할 우려가 있다. 프리캐스트 바닥판을 이용한 시공방법은 이러한 전통적인 방식의 현장타설 바닥판 시공법을 개선하여 시공성과 안전성을 향상시킨 공법이다.The concrete deck of the bridge is generally completed through a long period of curing by pouring concrete by making a formwork on site. However, such a conventional method of constructing a floorboard may increase the construction period due to the installation and dismantling of the formwork, and may cause safety accidents due to falling objects, and the concrete floorboard of equal quality due to the site conditions and weather conditions. It is difficult to construct, and there is a fear of various problems such as indirect loss. The construction method using the precast floor plate is a construction method that improves the workability and safety by improving the conventional method of constructing the cast-in-place floor plate.

프리캐스트 바닥판은 교량의 제원에 맞추어 교폭 및 거더 사이의 간격 등을 고려하여 공장에서 분할 제작한 뒤 출하하여 현장에서 설치하는 공법으로, 전통적인 시공법과 비교하여 콘크리트 타설과 양생에 해당하는 시간을 감소시킬 수 있으며, 거더 상면에 프리캐스트 바닥판을 거치하는 방식으로 작업자에 대한 충분한 작업공간과 안전을 확보할 수 있다는 장점이 있다. Precast deck is a method that is divided and manufactured at the factory in consideration of the gap between the bridge width and the girder according to the specifications of the bridge, and then shipped and installed on site.Compared to traditional construction methods, the time required for concrete placement and curing is reduced. It has the advantage of securing a sufficient working space and safety for workers by mounting a precast floor plate on the upper surface of the girder.

그러나, 이러한 프리캐스트 바닥판은 분할제작 되어 현장에서 조립되는 방식이기 때문에 바닥판과 바닥판 사이의 이음부가 발생하게 되고, 교량의 종곡선 및 사각 등으로 인하여 단차가 발생하며, 특히, PSC 거더를 사용한 교량의 경우, 콘크리트의 재령 차이와 프리스트레스로 인해 전체 거더의 솟음이 일정하지 않게 되므로 바닥판 이음부의 단차가 더욱 심해지게 된다.However, since such a precast deck is divided and assembled in the field, a joint between the deck and the deck occurs, and a step occurs due to the vertical curve and square of the bridge, and in particular, the PSC girder In the case of the used bridge, the height difference of the entire girder is not uniform due to the difference in age of the concrete and the prestress, so the step of the joint of the deck becomes more severe.

프리캐스트 바닥판의 설치 작업시 발생하는 이음부의 단차는 캔틸레버부에서 특히 심해지기 때문에 완공 후 미관을 저해하고, 바닥판 위에 타설되는 포장층의 두께가 일정하지 않아 파손 등의 우려가 있어 반드시 단차 보정을 완료한 후 후속작업이 이루어져야 한다.Steps at the joints that occur during the installation work of the precast floor plate are particularly severe in the cantilever part, which hinders the aesthetic appearance after completion, and the thickness of the pavement layer placed on the floor plate is not constant, so there is a risk of damage. After completing the process, follow-up work should be done.

이러한 프리캐스트 바닥판의 단차를 보정하기 위하여 종래에 사용되는 방식으로는 고무패드를 이용하여 바닥판과 거더 사이에 설치하는 방식과, 높이 조절 볼트를 사용하는 방식 등이 있다. 이 중, 고무패드를 이용하는 방식은 바닥판과 거더 사이에 설치된 고무패드의 높이로 단차를 보정하는 방식으로 미세한 단차 보정은 어렵다는 단점이 있으며, 높이 조절 볼트를 이용하는 방식은 바닥판에 매립된 너트에 볼트를 삽입하여 볼트의 회전을 통해 거더와의 간격을 조절하는 방식으로, 미세한 단차까지 보정할 수 있지만, 중량물인 바닥판을 지지해야 하는 높이 조절 볼트로 인해 거더에 발생하는 응력집중으로 인하여 접촉면에 손상이 발생할 우려가 있다. Methods conventionally used to correct the step difference of the precast floor plate include a method of installing between the floor plate and the girder using a rubber pad, and a method of using a height adjustment bolt. Among them, the method using the rubber pad has the disadvantage that it is difficult to correct the minute level difference as the method corrects the step by the height of the rubber pad installed between the bottom plate and the girder, and the method using the height adjustment bolt is a method of using a nut embedded in the bottom plate. By inserting a bolt and adjusting the gap with the girder through rotation of the bolt, it is possible to correct even minute steps, but due to the concentration of stress generated in the girder due to the height adjustment bolt that must support the heavy base plate, There is a risk of damage.

이러한 손상을 방지하기 위하여 높이 조절 볼트의 단부에 지압판을 사용하는 경우, 높이 조절 볼트와 지압판이 일체화 되어 있지 않기 때문에, 지압판의 낙하로 인한 사고 발생 등의 위험이 있다. 또한, 바닥판의 설치 작업을 수행하기 전 볼트와 거더의 접촉면에 지압판을 미리 배치해야 하는 추가 작업이 이루어져야 하고, 정확한 배치가 이루어지지 않아 작업자가 배치작업을 반복하는 상황이 발생할 우려가 있다. 이러한 문제점을 해결하기 위하여 높이 조절 볼트 단부에 지압판을 용접하여 일체화시켜 사용하는 경우, 볼트의 회전시 지압판이 함께 회전하기 때문에 지압판과 거더의 접촉면적 만큼의 마찰력 증대로 인하여 회전력이 증가해 작업성이 저하된다. 또한, 단차 보정 작업 이후 높이 조절 볼트를 제거할 수 없기 때문에 볼트를 절단하는 등의 후속 작업이 동반되어야 한다.In order to prevent such damage, when the pressure plate is used at the end of the height adjustment bolt, since the height adjustment bolt and the pressure plate are not integrated, there is a risk of an accident due to the fall of the pressure plate. In addition, before performing the installation work of the floor plate, an additional work must be performed that requires pre-arrangement of the pressure plate on the contact surface between the bolt and the girder, and there is a fear that a situation in which the operator repeats the arrangement work due to not being accurately arranged. In order to solve this problem, when the pressure plate is welded to the end of the height adjustment bolt and integrated, the pressure plate rotates together when the bolt is rotated, so the rotational force increases due to the increase in friction as much as the contact area between the pressure plate and the girder. Is lowered. In addition, since the height adjustment bolt cannot be removed after the step correction operation, subsequent work such as cutting the bolt must be accompanied.

본 발명의 배경이 되는 기술로는 한국 공개특허 공개번호 제2002-0083994호로서, '프리캐스트 콘크리트 바닥재'가 제안되어 있다. 이는 규격화된 크기와 두께를 가지는 본체, 본체에 매립된 너트, 너트에 체결되어 본체의 구배를 조절하는 볼트를 포함하고 있다. 그러나 상기 배경기술은 프리캐스트 콘크리트 바닥재가 거더에 설치되어 볼트로 단차보정을 하는 경우, 볼트의 마찰력 증대로 인하여 회전력이 증가해 작업성이 저하된다. 또한 거더의 접촉면에 손상이 발생될 우려가 커지게 된다.As the background technology of the present invention, as Korean Patent Application Publication No. 2002-0083994,'precast concrete flooring' has been proposed. This includes a body having a standardized size and thickness, a nut embedded in the body, and a bolt fastened to the nut to adjust the gradient of the body. However, in the background art, when the precast concrete flooring is installed on the girder and the step is corrected with bolts, the rotational force increases due to the increase in the frictional force of the bolts, thereby reducing workability. In addition, there is a greater risk of damage to the contact surface of the girder.

한국 공개특허 공개번호 제2002-0083994호Korean Patent Application Publication No. 2002-0083994

본 발명은 기존의 프리캐스트 바닥판의 단차 보정 방식보다 정밀하고, 높이 조절 볼트로 인한 거더의 손상을 방지하며, 지압판을 프리캐스트 바닥판과 일체화시켜 바닥판 설치작업의 편의성을 향상시키고, 지압판의 직접 회전을 유발하지 않아 볼트의 회전력을 감소시켜 단차 보정 단계에서 작업성을 향상시키고, 작업을 완료한 후 보정볼트의 제거가 편리한 프리캐스트 바닥판과 이를 이용한 시공방법을 제공하는데 그 목적이 있다.The present invention is more precise than the conventional method of correcting the step difference of the precast floor plate, prevents damage to the girder due to the height adjustment bolt, improves the convenience of installation work of the floor plate by integrating the pressure plate with the precast floor plate, and Its purpose is to provide a precast deck and a construction method using the same, which improves workability in the step correction step by reducing the rotational force of the bolt because it does not induce direct rotation, and it is convenient to remove the correction bolt after the work is completed.

본 발명의 적절한 실시 형태에 따른 프리캐스트 바닥판은, 공장에서 긴장재 또는 철근 배근 후 콘크리트로 타설 양생되어 제작된 프리캐스트 바닥판 몸체와; 프리캐스트 바닥판 몸체에 매립되어 설치 높이를 조정할 수 있는 높이조절부와; 높이조절부의 하단에 체결되는 하단매립부를 포함한 단차보정유닛;이 구비된 것을 특징으로 한다.A precast floor plate according to a preferred embodiment of the present invention includes a precast floor plate body produced by pouring and curing concrete after reinforcement or reinforcement in a factory; A height adjustment unit embedded in the precast base plate body to adjust the installation height; It characterized in that it is provided with; a step correction unit including a bottom buried portion fastened to the bottom of the height adjustment unit.

또한, 단차보정유닛의 높이조절부는 프리캐스트 바닥판 몸체에 매립되어 있는 매립너트와; 매립너트에 나사 결합되어 설치되는 보정볼트;로 구성된 것을 특징으로 한다.In addition, the height adjustment unit of the step correction unit includes a buried nut embedded in the body of the precast base plate; It characterized in that it consists of; a correction bolt screwed to the buried nut is installed.

또한, 단차보정유닛의 하단매립부는 내부에 나사산이 형성되어 보정볼트에 체결할 수 있는 연질가결제와; 용접을 통해 연질가결제와 일체화되는 지압판;으로 구성된 것을 특징으로 한다.In addition, the bottom buried portion of the step correction unit includes a soft temporary payment agent that has a thread formed therein and can be fastened to the correction bolt; It characterized in that it consists of; acupressure plate integrated with the soft temporary payment through welding.

또한, 하단매립부의 연질가결제는 지압판과 용접될 수 있고, 동시에 보정볼트의 회전으로 인해 쉽게 파괴될 수 있도록 알루미늄, 구리 등과 같은 경도가 낮은 재질의 금속으로 제작된 것을 특징으로 한다.In addition, the soft finishing agent of the bottom buried part is characterized in that it is made of a low-hardness material such as aluminum and copper so that it can be welded to the pressure plate and can be easily destroyed due to rotation of the correction bolt.

또한, 연질가결제 내부의 나사산은 보정볼트에 형성된 나사산의 1피치 이하의 두께로 제작된 것을 특징으로 한다.In addition, it is characterized in that the internal thread of the soft payment agent is manufactured with a thickness of less than 1 pitch of the thread formed on the correction bolt.

또한, 상기 높이조절부와 하단매립부는 프리캐스트 바닥판 몸체의 제작단계에서 체결되어져 출하 및 바닥판 거치 시 일체화 거동하는 것을 특징으로 한다.In addition, the height adjustment part and the bottom buried part are fastened in the manufacturing stage of the precast base plate body, and thus, are integrated in the case of shipping and mounting the base plate.

한편, 본 발명의 일 실시 예에 따른 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법에 따르면, 프리캐스트 바닥판 몸체에 매립된 매립너트에 보정볼트를 나사 결합하여 높이조절부를 형성하는 제작단계와; 보정볼트의 하단에 지압판과 용접된 연질가결제를 체결하여 형성된 하단매립부를 결합하는 일체화 단계와; 현장으로 운송된 프리캐스트 바닥판을 거더에 거치하는 단계와; 거치된 프리캐스트 바닥판의 보정볼트를 회전하여 연질가결제의 파괴를 통해 보정볼트의 독립적인 회전을 유도하는 분리단계와; 하단매립부와 분리된 보정볼트의 회전을 통해 프리캐스트 바닥판 몸체의 높이를 조절하는 단차보정단계와; 거더와 프리캐스트 바닥판 몸체의 사이에 충진재를 충진하고, 충진재의 경화 후 보정볼트의 회전을 통해 매립너트로부터 보정볼트를 제거하는 제거단계;를 포함하여 이루어지는 것을 특징으로 한다.On the other hand, according to the construction method of a precast floor plate equipped with a step correction unit according to an embodiment of the present invention, a manufacturing step of forming a height adjustment unit by screwing a correction bolt to a buried nut embedded in the precast floor plate body Wow; An integration step of coupling a bottom buried part formed by fastening a soft prepayment welded with a pressure plate to a lower end of the correction bolt; Mounting the precast floor plate transported to the site on the girder; A separating step of rotating the correction bolt of the mounted precast floor plate to induce independent rotation of the correction bolt through destruction of the soft temporary payment agent; A step correction step of adjusting the height of the precast base plate body through rotation of the correction bolt separated from the bottom buried part; And a removal step of removing the correction bolt from the buried nut through rotation of the correction bolt after filling the filler material between the girder and the precast base plate body, and after curing the filler material.

또한, 본 발명의 다른 실시 예에 따른 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법에 따르면, 프리캐스트 바닥판 몸체에 매립된 매립너트에 보정볼트를 나사 결합하여 높이조절부를 형성하는 제작단계와; 보정볼트의 하단에 지압판과 용접된 연질가결제를 체결하여 형성된 하단매립부를 결합하는 일체화 단계와; 현장으로 운송된 프리캐스트 바닥판을 거더에 거치하는 단계와; 거치된 프리캐스트 바닥판의 보정볼트를 회전하여 연질가결제의 파괴를 통해 보정볼트의 독립적인 회전을 유도하는 분리단계와; 하단매립부와 분리된 보정볼트의 회전을 통해 프리캐스트 바닥판 몸체의 높이를 조절하는 단차보정단계와; 콘크리트를 현장 타설하여 공극과 단차보정유닛를 매립시키는 타설단계;를 포함하여 이루어지는 것을 특징으로 한다.In addition, according to the construction method of a precast floor plate equipped with a step correction unit according to another embodiment of the present invention, a manufacturing step of forming a height adjustment part by screwing a correction bolt to a buried nut embedded in the precast floor plate body Wow; An integration step of coupling a bottom buried part formed by fastening a soft prepayment welded with a pressure plate to a lower end of the correction bolt; Mounting the precast floor plate transported to the site on the girder; A separating step of rotating the correction bolt of the mounted precast floor plate to induce independent rotation of the correction bolt through destruction of the soft temporary payment agent; A step correction step of adjusting the height of the precast base plate body through rotation of the correction bolt separated from the bottom buried part; It characterized in that it comprises; a pouring step of placing concrete on-site to bury the gap and the step correction unit.

또한, 상기 단차보정단계시 최종 높이로 조정된 프리캐스트 바닥판 몸체는 양단에 보정볼트 삽입슬롯홀을 갖는 이음부재를 보정볼트에 끼움시킨 후 보정볼트에 체결된 고정너트의 조임으로 상호 이음되는 것을 특징으로 한다.In addition, the precast base plate body adjusted to the final height during the step correction step is connected to each other by tightening the fixing nuts fastened to the correction bolt after inserting the joint members having the correction bolt insertion slot holes at both ends into the correction bolt. It is characterized.

본 발명의 단차보정유닛이 구비된 프리캐스트 바닥판 및 그 시공방법에 따르면, 분할 제작된 프리캐스트 바닥판 이음부간의 단차를 미세하게 조절하여 균등한 두께의 포장을 통해 포장층의 부분적인 파손을 방지하고, 완공 후 바닥판 켄틸레버부의 단차로 인해 인접한 바닥판이 어긋나게 보이는 것을 방지하여 미관을 향상시킬 수 있다.According to the precast floor plate provided with the step difference correction unit of the present invention and the construction method thereof, partial damage of the pavement layer is prevented through pavement of an even thickness by finely adjusting the step difference between the joints of the precast floor plate manufactured separately. It is possible to prevent and improve the aesthetics by preventing the adjacent floor plate from appearing misaligned due to the step difference of the floor plate cantilever part after completion.

또한, 바닥판의 중량 및 작업하중을 보정볼트가 직접 거더에 전달하지 않고 하단매립부의 지압판을 통해 넓은 면적으로 분산하여 전달하기 때문에 응력 집중으로 인한 거더의 손상을 방지할 수 있다.In addition, since the correction bolt does not directly transmit the weight and working load of the floor plate to the girder, it is distributed and transmitted over a large area through the pressure plate of the bottom buried part, so it is possible to prevent damage to the girder due to stress concentration.

또한, 단차보정유닛의 높이조절부와 하단매립부가 서로 체결되어 일체화 거동을 하기 때문에, 바닥판 거치 전 지압판 배치 등의 준비 작업을 생략할 수 있고, 지압판 배치 오류로 인한 작업자의 수정 작업이 필요하지 않아 작업성을 향상시키며, 낙하물로 인한 안전사고를 방지할 수 있는 효과가 있다.In addition, since the height adjustment unit and the bottom buried part of the step correction unit are connected to each other to be integrated, it is possible to omit preparation work such as arranging the acupressure plate before mounting the floor plate, and the operator's correction work due to an error in the acupressure plate placement is not required. It improves workability and prevents safety accidents caused by falling objects.

또한, 단차보정단계에서 연질가결제의 파괴를 통해 높이조절부와 하단매립부가 서로 분리되기 때문에, 단차보정을 위한 보정볼트의 회전시 지압판은 거더 접촉면과의 마찰로 회전하지 않으며 이로인한 회전력의 감소로 작업성을 향상시키는 효과가 있다.In addition, since the height adjustment part and the bottom buried part are separated from each other through the destruction of the soft temporary settlement in the step correction step, the acupressure plate does not rotate due to friction with the contact surface of the girder when the correction bolt for step correction is rotated. There is an effect of improving workability.

또한, 단차 보정 작업을 완료한 후 보정볼트를 제거해야 하는 경우, 보정볼트가 하단매립부와 분리되어 있기 때문에, 보정볼트를 절단 하는 등의 후속 작업 없이 보정볼트의 회전만으로 제거할 수 있어 작업의 편리성을 향상시키는 효과가 있다.In addition, if the correction bolt needs to be removed after completing the step correction operation, since the correction bolt is separated from the bottom buried part, it can be removed only by rotating the correction bolt without subsequent work such as cutting the correction bolt. There is an effect of improving convenience.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명의 일 형태에 따른 프리캐스트 바닥판의 사시도이다.
도 2는 도 1의 A-A선 단면도이다.
도 3은 본 발명에 따른 프리캐스트 바닥판 단차보정유닛의 분해사시도이다.
도 4의 (가),(나),(다)는 본 발명에 적용되는 보정볼트의 단부 형상에 따른 다양한 예시도이다.
도 5의 (가),(나),(다)는 본 발명에 적용되는 연질가결제의 다양한 형태에 따른 사시도이다.
도 6의 (가),(나)는 본 발명의 단차보정유닛의 보정볼트 회전에 따른 연질가결제의 나선 파괴 및 용접부 파괴를 나타낸 단면도이다.
도 7은 본 발명의 단차보정유닛이 구비된 프리캐스트 바닥판의 거치 예시를 나타낸 사시도이다.
도 8a 및 도 8b는 본 발명의 단차보정유닛이 구비된 프리캐스트 바닥판의 시공순서를 나타낸 공정도이다.
도 9의 (가),(나)는 본 발명의 단차보정유닛이 구비된 프리캐스트 바닥판의 단차보정작업 완료 후, 이음부재를 통한 보정볼트간의 연결을 순차적으로 나타낸 단면도이다.
도 10은 본 발명에 적용되는 이음부재의 다양한 형태를 나타낸 사시도이다.
The following drawings attached to the present specification illustrate preferred embodiments of the present invention, and serve to further understand the technical idea of the present invention together with the detailed description of the present invention, so the present invention is limited to the matters described in the accompanying drawings. It is limited and should not be interpreted.
1 is a perspective view of a precast floor plate according to an embodiment of the present invention.
2 is a cross-sectional view taken along line AA of FIG. 1.
3 is an exploded perspective view of a precast floor plate step correction unit according to the present invention.
(A), (B), (C) of FIG. 4 are various exemplary diagrams according to the end shape of the correction bolt applied to the present invention.
Figure 5 (a), (b), (c) is a perspective view according to various forms of the soft temporary payment applied to the present invention.
6A and 6B are cross-sectional views showing the helical breakage and the breakage of the welded part of the soft temporary settlement agent according to the rotation of the correction bolt of the step correction unit of the present invention.
7 is a perspective view showing an example of mounting a precast floor plate provided with a step correction unit of the present invention.
8A and 8B are process diagrams showing the construction sequence of a precast floor plate equipped with a step correction unit of the present invention.
9A and 9B are cross-sectional views sequentially showing the connection between the correction bolts through the joint member after the step correction operation of the precast floor plate with the step correction unit of the present invention is completed.
10 is a perspective view showing various forms of a joint member applied to the present invention.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.In the following, the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the disclosed embodiments are illustrative for a clear understanding of the present invention, and the present invention is not limited thereto.

도 1은 본 발명의 일 형태에 따른 프리캐스트 바닥판의 사시도이고, 도 2는 도 1의 A-A선 단면도이고, 도 3은 본 발명에 따른 프리캐스트 바닥판 단차보정유닛의 분해사시도이다.1 is a perspective view of a precast floor plate according to an embodiment of the present invention, FIG. 2 is a cross-sectional view taken along line A-A of FIG. 1, and FIG. 3 is an exploded perspective view of a precast floor plate step correction unit according to the present invention.

도 1 내지 도 3과 같이 프리캐스트 바닥판(10)은 공장에서 긴장재 또는 철근 배근 후 콘크리트로 타설 양생되어 제작된 프리캐스트 바닥판 몸체(12)와, 프리캐스트 바닥판 몸체(12)에 매립되어 설치 높이를 조정할 수 있는 높이조절부(21)와, 높이조절부(21)의 하단에 체결되는 하단매립부(22)를 포함한 단차보정유닛(20)이 구비된 것을 특징으로 한다.1 to 3, the precast floor plate 10 is embedded in the precast floor plate body 12 and the precast floor plate body 12 produced by pouring and curing with concrete after reinforcement or reinforcement at the factory. It is characterized in that the step correction unit 20 including a height adjustment unit 21 that can adjust the installation height, and a bottom buried portion 22 fastened to the lower end of the height adjustment unit 21 is provided.

단차보정유닛(20)은 프리캐스트 바닥판 몸체(12)가 분할 제작되어 교량의 거더(100) 상면에 거치하는 단계에서 발생하는 프리캐스트 바닥판 몸체(12)간의 단차를 보정하기 위함이다.The step correction unit 20 is to correct the step difference between the precast deck body 12 that occurs in the step of the precast deck body 12 being divided and mounted on the upper surface of the girder 100 of the bridge.

단차보정유닛(20)은 본 실시 예에서 도 1과 같이 프리캐스트 바닥판 몸체(12)의 모서리부에 해당하는 4개소에 설치하였으나 이러한 설치 위치나 개소에 한정되는 것은 아니다. 프리캐스트 바닥판 몸체(12)는 공장에서 철근 배근된 거푸집에 콘크리트를 타설 양생한 후 탈형하여 일정 두께(t)를 갖는 사각형태로 제작된 것이다.The step correction unit 20 is installed at four locations corresponding to the corners of the precast bottom plate body 12 as shown in FIG. 1 in this embodiment, but is not limited to such installation locations or locations. The precast deck body 12 is manufactured in a square shape having a certain thickness (t) by pouring and curing concrete in a formwork reinforced in a factory and then demolding.

상기 높이조절부(21)는 프리캐스트 바닥판 몸체(12)에 매립되어 설치된 매립너트(211)와, 매립너트(211)에 나사 결합되어 있는 보정볼트(212)로 구성된다. 매립너트(211)는 중심축에 나사구멍(211a)을 갖는 것으로 프리캐스트 바닥판 몸체(12)의 두께(t)와 동일한 길이를 갖고 매립되어 설치될 수 있다. 보정볼트(212)는 프리캐스트 바닥판 몸체(12)의 두께(t)보다 더 긴 길이를 갖고 설치된다.The height adjustment unit 21 is composed of a buried nut 211 embedded in the precast bottom plate body 12 and installed, and a correction bolt 212 screwed to the buried nut 211. The buried nut 211 has a screw hole 211a on the central axis and may be buried and installed to have the same length as the thickness t of the precast bottom plate body 12. The correction bolt 212 is installed to have a length longer than the thickness t of the precast base plate body 12.

상기 보정볼트(212)의 단부는 도 5의 (가),(나),(다)에 도시한 바와 같이, 편평하거나 둥근 형태 또는 뾰족한 형태 등으로 나타날 수 있다.The ends of the correction bolts 212 may be flat, round, or pointed, as shown in (a), (b), and (c) of FIG. 5.

상기 하단매립부(22)는 내부에 나사산이 형성되어 보정볼트(212)에 체결할 수 있는 연질가결제(221)와, 용접을 통해 연질가결제(221)와 일체화되는 지압판(222)으로 구성된다.The bottom buried part 22 is composed of a soft temporary payment agent 221 that can be fastened to the correction bolt 212 by having a thread formed therein, and a pressure plate 222 integrated with the soft temporary payment agent 221 through welding.

하단매립부(22)의 연질가결제(221)는 지압판(222)과 용접될 수 있고, 동시에 보정볼트(212)의 회전으로 파괴될 수 있도록 알루미늄, 구리 등과 같은 경도가 낮은 재질의 연질금속을 사용함이 바람직하다. 연질가결제(221)는 도 5의 (가),(나),(다)와 같이 내부에 나사산이 형성된 링 또는 판 형태 및 보정볼트(212)에 형성된 나사산의 1피치 이하의 두께를 가진 소켓 형태 등으로 제작될 수 있다.The soft processing agent 221 of the bottom buried part 22 can be welded to the pressure plate 222, and at the same time, a soft metal of a low hardness material such as aluminum or copper is used so that it can be destroyed by rotation of the correction bolt 212 This is desirable. The soft payment agent 221 is in the form of a ring or plate with internal threads as shown in Fig. 5 (a), (b), and (c), and a socket shape having a thickness of less than 1 pitch of the thread formed on the correction bolt 212 It can be made of etc.

도 2에 도시한 바와 같이, 프리캐스트 바닥판 몸체(12)에 매립된 매립너트(211)에 보정볼트(212)를 나사 결합하여 프리캐스트 바닥판 몸체(12)의 하면으로 보정볼트(212)의 단부가 노출되도록 하되, 그 노출 길이는 프리캐스트 바닥판 몸체(12)의 구배 및 단차보정 높이를 고려하여 충분한 길이를 확보할 수 있도록 한다.As shown in Figure 2, by screwing the correction bolt 212 to the buried nut 211 embedded in the precast floor plate body 12, the correction bolt 212 to the lower surface of the precast floor plate body 12 The end of the plate is exposed, but the length of the exposure is to ensure a sufficient length in consideration of the height of the precast base plate body 12 and the height of the grade.

지압판(222)과 연질가결제(221)를 포함하는 하단매립부(22)는, 매립너트(211)에 나사결합된 보정볼트(212)의 하단이 연질가결제(221)의 나사산에 나사결합되어 높이조절부(21)와 체결된다. 이로서 본 발명에 적용되는 단차보정유닛(20)은 프리캐스트 바닥판(10)의 출하 및 거치 시 일체화 거동을 할 수 있다.The bottom buried part 22 including the acupressure plate 222 and the soft fastening agent 221 has a height of the lower end of the correction bolt 212 screwed to the buried nut 211 is screwed to the thread of the soft fastening agent 221 It is fastened with the adjustment part 21. Accordingly, the step correction unit 20 applied to the present invention can perform an integrated behavior when shipping and mounting the precast floor plate 10.

미설명부호 '10a'는 '전단포켓'이다.The non-explanatory symbol '10a' is a'shear pocket'.

이하, 본 발명의 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법을 전단면 프리캐스트 바닥판의 시공 방법과 반단면 프리캐스트 바닥판의 시공방법으로 구분하여 설명한다.Hereinafter, the construction method of the precast floor plate provided with the step correction unit of the present invention will be described by dividing the construction method of the front precast floor plate and the half sectional precast floor plate construction method.

<전단면 프리캐스트 바닥판의 시공방법><Construction method of precast floor plate for front end>

가. 제작단계end. Production stage

도 1 및 도 2와 같이 프리캐스트 바닥판 몸체(12)에 매립된 매립너트(211)에 보정볼트(212)를 삽입하여 높이조절부(21)를 형성한다.As shown in FIGS. 1 and 2, the height adjustment part 21 is formed by inserting the correction bolt 212 into the buried nut 211 embedded in the precast base plate body 12.

나. 일체화단계I. Integration stage

그 다음, 매립너트(211)에 삽입된 보정볼트(212)의 하단에 지압판(222)과 용접된 연질가결제(221)를 체결하여 단차보정유닛(20)의 높이조절부(21)와 하단매립부(22)를 일체화한다.Then, by fastening the acupressure plate 222 and the welded soft prepayment 221 at the bottom of the correction bolt 212 inserted into the buried nut 211, the height adjustment unit 21 and the bottom of the step correction unit 20 are embedded. Unit 22 is integrated.

다. 거치단계All. Deferred step

그 다음, 도 7 및 도 8a의 (가)와 같이 제작이 완료된 프리캐스트 바닥판(10)을 현장으로 운송하여 거더(100)에 거치한다.Then, as shown in (a) of FIGS. 7 and 8A, the precast floor plate 10, which has been manufactured, is transported to the site and mounted on the girder 100.

라. 분리단계la. Separation step

그 다음, 도 6 및 도 8a의 (나)와 같이 거치된 프리캐스트 바닥판의 보정볼트(212)를 회전하여 연질가결제(221)의 파괴를 통해 보정볼트(212)의 독립적인 회전을 유도한다.Then, by rotating the correction bolt 212 of the precast floor plate mounted as shown in (B) of FIGS. 6 and 8A, an independent rotation of the correction bolt 212 is induced through the destruction of the soft temporary payment agent 221. .

마. 단차보정단계hemp. Step correction step

그 다음, 하단매립부(22)와 분리된 보정볼트(212)의 독립적인 회전을 통해 프리캐스트 바닥판 몸체(12)의 높이를 조정하여 단차를 보정한다. 최종 높이로 조정된 프리캐스트 바닥판 몸체(12)는 도 9의 (가)와 같이 인접한 프리캐스트 바닥판 몸체(12)와 이음부재(30)를 사용해 연결할 수 있다. 이때 이음부재(30)는 도 10과 같이 평판 또는 L자형 단면의 앵글 형태로 제작될 수 있고 보정볼트(212)에 끼움하기 위해 양단에 보정볼트 삽입슬롯홀(301,301)을 갖는다. 따라서 도 9의 (나)와 같이 이음부재(30)는 인접한 프리캐스트 바닥판 몸체(12와 12)의 상면에 위치되어 보정볼트 삽입슬롯홀(301,301)을 보정볼트(212,212)에 끼워진 후 보정볼트(212,212)에 체결된 고정너트(32)의 조임으로 단차보정된 프리캐스트 바닥판 몸체(12와 12)를 서로 이음연결시킨다.Then, the height of the precast base plate body 12 is adjusted through independent rotation of the lower buried part 22 and the separate correction bolt 212 to correct the step difference. The precast base plate body 12 adjusted to the final height may be connected using the adjacent precast base plate body 12 and the joint member 30 as shown in (A) of FIG. 9. At this time, the joint member 30 may be manufactured in an angle shape of a flat plate or an L-shaped cross section as shown in FIG. 10, and has correction bolt insertion slot holes 301 and 301 at both ends to fit into the correction bolt 212. Therefore, as shown in (B) of FIG. 9, the joint member 30 is located on the upper surface of the adjacent precast base plate bodies 12 and 12, and after inserting the correction bolt insertion slot holes 301 and 301 into the correction bolts 212 and 212, the correction bolt The precast base plate bodies 12 and 12, which have been stepped corrected by tightening the fixing nuts 32 fastened to the (212, 212), are jointly connected to each other.

바. 제거단계bar. Removal step

그 다음, 도 8b의 (라)와 같이 거더(100)와 프리캐스트 바닥판 몸체(12)의 사이에 충진재(110)를 주입 경화시킨 후, 보정볼트(212)의 회전 풀림을 통해 매립너트(211)로부터 보정볼트(212)를 제거하여 회수한다. 이후 도 8b의 (마)와 같이 매립너트(211)의 나사구멍(211a)에 추가적으로 충진재(110)를 주입시킨다.Then, after injection-hardening the filler 110 between the girder 100 and the precast bottom plate body 12 as shown in (D) of FIG. 8B, the buried nut ( The correction bolt 212 is removed from 211) and recovered. Thereafter, as shown in (E) of FIG. 8B, the filler 110 is additionally injected into the screw hole 211a of the buried nut 211.

이와 같이 본 공법에서는 단차조정을 위해 보정볼트(212)의 회전 조작시 도 6과 같이 연질가결제(221)가 파괴되거나 용접부(223)가 파괴되어 지압판(222)의 상면에서 회전 조작이 용이하게 이루어진다. 또한 이 경우 보정볼트(212)의 하단은 지압판(222)에 지지되어져 회전 조작됨으로 거더(100) 표면의 손상은 발생되지 않게 된다.In this way, in this method, when rotating the correction bolt 212 for step adjustment, the soft temporary settlement agent 221 is destroyed or the welding part 223 is destroyed as shown in FIG. 6, so that the rotation operation is easily performed on the upper surface of the pressure plate 222. . In addition, in this case, the lower end of the correction bolt 212 is supported by the pressure plate 222 and is rotated so that damage to the surface of the girder 100 does not occur.

또한, 연질가결제(221)가 파괴전까지는 지압판(222)이 프리캐스트 바닥판(10)과 일체로 거동하기 때문에 지압판(222)의 낙하염려가 없다.In addition, there is no fear of falling of the pressure plate 222 because the pressure plate 222 behaves integrally with the precast bottom plate 10 until the soft temporary payment agent 221 is destroyed.

또한, 종래와 같이 바닥판의 설치 작업을 수행하기 전 볼트와 거더의 접촉면에 지압판(222)을 미리 정확히 배치해야 하는 추가 작업이 불필요해진다.In addition, as in the prior art, before performing the installation work of the bottom plate, the additional work of accurately disposing the pressure plate 222 on the contact surface between the bolt and the girder becomes unnecessary.

또한, 단차 보정 작업 이후 보정볼트(212)가 제거되기 때문에 종래와 같이 볼트를 절단해야 하는 후속 작업이 생략되는 이점을 갖게 된다.In addition, since the correction bolt 212 is removed after the step correction operation, a subsequent operation requiring cutting the bolt as in the prior art is omitted.

<반단면 프리캐스트 바닥판의 시공><Construction of half-section precast deck>

한편, 본 공법에서 위의 단차보정단계 후, 도 8b의 (라')와 같이 콘크리트(120)를 현장 타설하여 단차보정유닛(20)을 콘크리트에 매립시킬 수 있다. 이때 현장타설콘크리트(200)의 두께는 보정볼트(212)의 머리부 높이 이상이 된다.On the other hand, after the step correction step above in the present method, the step correction unit 20 may be embedded in the concrete by placing the concrete 120 on-site as shown in (D') of FIG. 8B. At this time, the thickness of the cast-in-place concrete 200 is equal to or greater than the height of the head of the correction bolt 212.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. Until now, the present invention has been described in detail with reference to the presented embodiments, but those of ordinary skill in the art can make various modifications and modifications without departing from the technical spirit of the present invention with reference to the presented embodiments. will be. The present invention is not limited by such modifications and variations of the invention, but is limited by the claims appended below.

10: 프리캐스트 바닥판
12: 프리캐스트 바닥판 몸체
20: 단차보정유닛
21: 높이조절부
22: 하단매립부
211: 매립너트
212: 보정볼트
221: 연질 가결제
222: 지압판
30: 이음부재
10: precast base plate
12: Precast base plate body
20: step correction unit
21: height adjustment unit
22: bottom reclaimed part
211: buried nut
212: correction bolt
221: soft temporary settlement
222: acupressure plate
30: joint member

Claims (9)

교량의 거더(100)에 시공되는 프리캐스트 바닥판(10)에 있어서,
공장에서 긴장재 또는 철근 배근 후 콘크리트로 타설 양생되어 제작된 프리캐스트 바닥판 몸체(12)와; 프리캐스트 바닥판 몸체(12)에 매립되어 설치 높이를 조정할 수 있는 높이조절부(21)와; 높이조절부(21)의 하단에 체결되는 하단매립부(22)를 포함한 단차보정유닛(20);이 구비되고,
단차보정유닛(20)의 하단매립부(22)는 내부에 나사산이 형성되어 보정볼트(212)에 체결할 수 있는 연질가결제(221)와; 용접을 통해 연질가결제(221)와 일체화되는 지압판(222);으로 구성된 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판.
In the precast deck 10 installed on the girder 100 of the bridge,
Precast deck body 12 produced by pouring and curing with concrete after reinforcement of a tension member or reinforcement in a factory; A height adjustment part 21 that is embedded in the precast base plate body 12 to adjust the installation height; A step correction unit 20 including a bottom buried part 22 fastened to the lower end of the height adjusting part 21; is provided,
The bottom buried part 22 of the step correction unit 20 includes a soft temporary payment agent 221 that has a thread formed therein and can be fastened to the correction bolt 212; A precast floor plate provided with a step correction unit, characterized in that consisting of; an acupressure plate 222 integrated with the soft temporary payment agent 221 through welding.
제 1항에 있어서,
단차보정유닛(20)의 높이조절부(21)는 프리캐스트 바닥판 몸체(12)에 매립되어 있는 매립너트(211)와; 매립너트(211)에 나사 결합되어 설치되는 보정볼트(212);로 구성된 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판.
The method of claim 1,
The height adjustment unit 21 of the step correction unit 20 includes a buried nut 211 embedded in the precast bottom plate body 12; A precast floor plate provided with a step correction unit, characterized in that consisting of; a correction bolt 212 which is screwed to the buried nut 211 and installed.
삭제delete 제 1항에 있어서,
하단매립부(22)의 연질가결제(221)는 지압판(222)과 용접될 수 있고, 동시에 보정볼트(212)의 회전으로 인해 쉽게 파괴될 수 있도록 알루미늄, 구리 등과 같은 경도가 낮은 재질의 금속으로 제작된 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판.
The method of claim 1,
The soft temporary payment agent 221 of the bottom buried part 22 can be welded to the pressure plate 222, and at the same time, it is made of a metal of a low hardness material such as aluminum or copper so that it can be easily destroyed due to rotation of the correction bolt 212. Precast floor plate provided with a step correction unit, characterized in that produced.
제 1항에 있어서,
연질가결제(221) 내부의 나사산은 보정볼트(212)에 형성된 나사산의 1피치 이하의 두께(t)로 제작된 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판.
The method of claim 1,
A precast floor plate provided with a step correction unit, characterized in that the thread inside the soft payment agent 221 is manufactured with a thickness (t) less than 1 pitch of the thread formed on the correction bolt 212.
제 1항에 있어서,
상기 높이조절부(21)와 하단매립부(22)는 프리캐스트 바닥판 몸체(12)의 제작단계에서 체결되어져 출하 및 바닥판 거치 시 일체화 거동하는 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판.
The method of claim 1,
The height adjustment part 21 and the bottom buried part 22 are fastened in the manufacturing stage of the precast base plate body 12 to be integrated when shipping and mounting the base plate. Precast equipped with a step correction unit, characterized in that Bottom plate.
프리캐스트 바닥판 몸체(12)에 매립된 매립너트(211)에 보정볼트(212)를 나사 결합하여 높이조절부(21)를 형성하는 제작단계와;
보정볼트(212)의 하단에 지압판(222)과 용접된 연질가결제(221)를 체결하여 형성된 하단매립부(22)를 결합하는 일체화 단계와;
현장으로 운송된 프리캐스트 바닥판(10)을 거더(100)에 거치하는 단계와;
거치된 프리캐스트 바닥판(10)의 보정볼트(212)를 회전하여 연질가결제(221)의 파괴를 통해 보정볼트(212)의 독립적인 회전을 유도하는 분리단계와;
하단매립부(22)와 분리된 보정볼트(212)의 회전을 통해 프리캐스트 바닥판 몸체(12)의 높이를 조절하는 단차보정단계와;
거더(100)와 프리캐스트 바닥판 몸체(12)의 사이에 충진재(110)를 충진하고, 충진재(110)의 경화 후 보정볼트(212)의 회전을 통해 매립너트(211)로부터 보정볼트(212)를 제거하는 제거단계;를 포함하여 이루어지는 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법.
A manufacturing step of forming a height adjustment part 21 by screwing the correction bolt 212 to the buried nut 211 embedded in the precast base plate body 12;
An integration step of coupling the bottom buried portion 22 formed by fastening the acupressure plate 222 and the welded soft temporary payment agent 221 to the lower end of the correction bolt 212;
Mounting the precast floor plate 10 transported to the site on the girder 100;
A separation step of inducing independent rotation of the correction bolt 212 through destruction of the soft temporary payment agent 221 by rotating the correction bolt 212 of the mounted precast floor plate 10;
A step correction step of adjusting the height of the precast base plate body 12 through rotation of the correction bolt 212 separated from the bottom buried part 22;
Filling the filler 110 between the girder 100 and the precast base plate body 12, and the correction bolt 212 from the buried nut 211 through the rotation of the correction bolt 212 after hardening of the filler 110 ) Removing step of removing; construction method of a precast floor plate provided with a step correction unit, characterized in that it comprises a.
프리캐스트 바닥판 몸체(12)에 매립된 매립너트(211)에 보정볼트(212)를 나사 결합하여 높이조절부(21)를 형성하는 제작단계와;
보정볼트(212)의 하단에 지압판(222)과 용접된 연질가결제(221)를 체결하여 형성된 하단매립부(22)를 결합하는 일체화 단계와;
현장으로 운송된 프리캐스트 바닥판(10)을 거더(100)에 거치하는 단계와;
거치된 프리캐스트 바닥판(10)의 보정볼트(212)를 회전하여 연질가결제(221)의 파괴를 통해 보정볼트(212)의 독립적인 회전을 유도하는 분리단계와;
하단매립부(22)와 분리된 보정볼트(212)의 회전을 통해 프리캐스트 바닥판 몸체(12)의 높이를 조절하는 단차보정단계와;
콘크리트를 현장 타설하여 공극과 단차보정유닛(20)를 매립시키는 타설단계;를 포함하여 이루어지는 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법.
A manufacturing step of forming a height adjustment part 21 by screwing the correction bolt 212 to the buried nut 211 embedded in the precast base plate body 12;
An integration step of coupling the bottom buried portion 22 formed by fastening the acupressure plate 222 and the welded soft temporary payment agent 221 to the lower end of the correction bolt 212;
Mounting the precast floor plate 10 transported to the site on the girder 100;
A separation step of inducing independent rotation of the correction bolt 212 through destruction of the soft temporary payment agent 221 by rotating the correction bolt 212 of the mounted precast floor plate 10;
A step correction step of adjusting the height of the precast base plate body 12 through rotation of the correction bolt 212 separated from the bottom buried part 22;
A method of constructing a precast floor plate having a step correction unit comprising; a pouring step of placing concrete on-site to fill the voids and the step correction unit 20.
제 7항 또는 제 8항에 있어서,
상기 단차보정단계시 최종 높이로 조정된 프리캐스트 바닥판 몸체(12와 12)는 양단에 보정볼트 삽입슬롯홀(301,301)을 갖는 이음부재(30)를 보정볼트(212와 212)에 끼움시킨 후 보정볼트(212,212)에 체결된 고정너트(32)의 조임으로 상호 이음되는 것을 특징으로 하는 단차보정유닛이 구비된 프리캐스트 바닥판의 시공방법.
The method according to claim 7 or 8,
After the precast base plate body 12 and 12 adjusted to the final height during the step correction step, the joint members 30 having the correction bolt insertion slot holes 301 and 301 at both ends are inserted into the correction bolts 212 and 212. Construction method of a precast floor plate provided with a step correction unit, characterized in that mutual connection by tightening the fixing nuts 32 fastened to the correction bolts (212, 212).
KR1020190165741A 2019-12-12 2019-12-12 Precast floor plate having level correction unit and construction method of the same KR102163522B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190165741A KR102163522B1 (en) 2019-12-12 2019-12-12 Precast floor plate having level correction unit and construction method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190165741A KR102163522B1 (en) 2019-12-12 2019-12-12 Precast floor plate having level correction unit and construction method of the same

Publications (1)

Publication Number Publication Date
KR102163522B1 true KR102163522B1 (en) 2020-10-07

Family

ID=72883643

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190165741A KR102163522B1 (en) 2019-12-12 2019-12-12 Precast floor plate having level correction unit and construction method of the same

Country Status (1)

Country Link
KR (1) KR102163522B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102663346B1 (en) * 2024-01-03 2024-05-03 (주)효명이씨에스 Embedded device of full-depth precast deck panel and construction method of transverse slope using the embedded device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06299706A (en) * 1993-04-13 1994-10-25 Jio Star Kk Level adjusting device of member
KR20020083994A (en) 2002-10-08 2002-11-04 전병구 Precast Concrete Floor Panel
KR20150057581A (en) * 2013-11-20 2015-05-28 한국건설기술연구원 Level adjusting apparatus for precast slab and precast slab construction method using therewith

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06299706A (en) * 1993-04-13 1994-10-25 Jio Star Kk Level adjusting device of member
KR20020083994A (en) 2002-10-08 2002-11-04 전병구 Precast Concrete Floor Panel
KR20150057581A (en) * 2013-11-20 2015-05-28 한국건설기술연구원 Level adjusting apparatus for precast slab and precast slab construction method using therewith

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102663346B1 (en) * 2024-01-03 2024-05-03 (주)효명이씨에스 Embedded device of full-depth precast deck panel and construction method of transverse slope using the embedded device
KR102663345B1 (en) * 2024-01-03 2024-05-03 (주)효명이씨에스 Full-depth precast deck panel using joint stiffeners and construction method of the precast deck panel

Similar Documents

Publication Publication Date Title
US6904636B2 (en) Deck-to-girder connections for precast or prefabricated bridge decks
JP6370729B2 (en) Road bridge protective fence installation method
KR200418585Y1 (en) Steel support plate and we use this bearing swap method
KR100770006B1 (en) Vertical connection steel-bar reinforcing structure of precast concreate column
KR100905728B1 (en) Manhole repairing apparutus and manhole repairing method using the same
RU2266370C2 (en) Method for manhole chimney and cover replacement
US6898910B2 (en) Precast composite header joint system and a method for forming and installing the same
KR102163522B1 (en) Precast floor plate having level correction unit and construction method of the same
KR102262951B1 (en) Precast floor plate having level correction unit and construction method of the same
JP4934779B2 (en) Boarding / exit structure and boarding / exiting method
KR100642762B1 (en) Material for temporary safety balustrade and method for constructing temporarily safety balustrade
KR100828003B1 (en) Reinforcing method of concrete structure
KR100966530B1 (en) Structure for linkage of expansion joint and construction method
KR102146577B1 (en) Fixed structure of high strength support material with easy to install at the construction site and construction method thereof
JP2013036269A (en) Sc pile
JPH0791858B2 (en) Concrete member with height adjustment mechanism and construction method of concrete member
KR101407990B1 (en) Replacement method for post-placing concrete of expansion joint, and post-placing structure of expansion joint
JP6345328B1 (en) Original position building method and original position structure
JP3171675U (en) Anti-sinking floor slab with maneuvering prevention function
KR20200129749A (en) Thin precast pavement structure, construction method of thin precast pavement, and manufacturing method of thin precast pavement
JP7463331B2 (en) Temporary jig and method for constructing artificial ground using said temporary jig
JP3513784B2 (en) How to reinforce pillars of viaduct
JP2002147027A (en) Fixing construction method for safety fence column
KR102570578B1 (en) A fast bridge bearing replacement method without safety accident dangerousness, civil complaints and structural damage
KR102441003B1 (en) Construction method and structure of pre-embedded anchor set for installation of bridge inspection facilities using form tie

Legal Events

Date Code Title Description
GRNT Written decision to grant