KR102131957B1 - A horizontal beam manufacturing method of a Rahmen building structure - Google Patents

A horizontal beam manufacturing method of a Rahmen building structure Download PDF

Info

Publication number
KR102131957B1
KR102131957B1 KR1020180030885A KR20180030885A KR102131957B1 KR 102131957 B1 KR102131957 B1 KR 102131957B1 KR 1020180030885 A KR1020180030885 A KR 1020180030885A KR 20180030885 A KR20180030885 A KR 20180030885A KR 102131957 B1 KR102131957 B1 KR 102131957B1
Authority
KR
South Korea
Prior art keywords
horizontal member
horizontal
slab
weight
formwork
Prior art date
Application number
KR1020180030885A
Other languages
Korean (ko)
Other versions
KR20190109035A (en
Inventor
김택용
Original Assignee
(주)수하담
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)수하담 filed Critical (주)수하담
Priority to KR1020180030885A priority Critical patent/KR102131957B1/en
Publication of KR20190109035A publication Critical patent/KR20190109035A/en
Application granted granted Critical
Publication of KR102131957B1 publication Critical patent/KR102131957B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • E04C3/26Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members prestressed
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/43Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Panels For Use In Building Construction (AREA)

Abstract

본 발명은 라멘구조 건축물의 수평부재 제작방법에 관한 것으로서, 더욱 상세하게는 수평부재의 처짐요인을 고려한 수평보정치만큼 처지게 거푸집을 제작하고, 슬래브 자중 및 슬래브 자중에 의한 크리프만큼 솟음이 있도록 프리스트레싱을 가함으로써 슬래브 시공시 수평도를 높여 라멘구조의 건축물 외벽에 내력패널이 균일하게 시공될 수 있도록 한 라멘구조 건축물의 수평부재 제작방법에 관한 것이다.
이를 위해, 상,하방에 수평부재가 시공되고, 상,하방의 수평부재 사이에 내력패널이 끼움 시공되고, 상기 수평부재에는 슬래브가 안착 시공되는 라멘구조 건축물에 있어서, 상기 수평부재는, 프리스트레스트 빔으로 제작되며, 수평부재에 안착되는 슬래브 자중 및 슬래브 자중에 의한 크리프를 고려하여 슬래브가 수평부재에 시공되었을 때 수평부재는 지면에 대하여 수평되도록 상방으로 볼록하게 제작된 것을 특징으로 하는 라멘구조 건축물의 수평부재 제작방법을 제공한다.
The present invention relates to a method for manufacturing a horizontal member of a ramen structure building, and more specifically, to produce a formwork that sags as much as a horizontal correction value considering the deflection factor of the horizontal member, and prestressing so that it rises as much as creep by the slab weight and slab weight. The invention relates to a method of manufacturing a horizontal member of a ramen structured structure by allowing the strength panel to be uniformly installed on the outer wall of the structure of the ramen structure by increasing the horizontality during the construction of the slab.
To this end, in a ramen structure structure in which horizontal members are installed on the upper and lower sides, a load-bearing panel is sandwiched between the upper and lower horizontal members, and a slab is installed on the horizontal members, wherein the horizontal members are prestressed A ramen structure building characterized by being made of a beam and convex upward so that the horizontal member is horizontal with respect to the ground when the slab is constructed on the horizontal member in consideration of the slab self-weight and creep caused by the slab self-weight. Provides a method for manufacturing a horizontal member.

Description

라멘구조 건축물의 수평부재 제작방법{A horizontal beam manufacturing method of a Rahmen building structure} A horizontal beam manufacturing method of a Rahmen building structure}

본 발명은 라멘구조 건축물의 수평부재 제작방법에 관한 발명으로서, 더욱 상세하게는 슬래브 시공시 수평도의 정확도가 극대화될 수 있도록 한 라멘구조 건축물의 수평부재 제작방법에 관한 것이다.The present invention relates to a method of manufacturing a horizontal member of a ramen structure building, and more particularly, to a method of manufacturing a horizontal member of a ramen structure building so that the accuracy of horizontality can be maximized during slab construction.

일반적으로 외벽(outer wall)이란 건축물의 외부로 보여지는 바깥쪽 벽면을 지칭하는바, 과거에는 주로 페인트를 칠하거나 벽돌 등으로 치장하였지만, 최근 들어 건물의 벽면 바깥쪽으로 석재 또는 금속재의 판 구조물을 고정시켜 미려한 외관을 추구하는 방법이 많이 사용되고 있다. In general, an outer wall refers to an outer wall surface that is seen as the exterior of a building. In the past, it was mainly painted or decorated with bricks, but recently, a stone or metal plate structure has been fixed outside the building wall. There are many methods of pursuing beautiful appearance.

이때, 건물의 벽면 바깥쪽으로 고정되는 석재 또는 금속재의 판 구조물은 외장 패널이라 불리기도 한다.At this time, the stone or metal plate structure fixed to the outside of the wall of the building is also called an exterior panel.

한편, 건물의 완성된 벽면에 판 구조물을 고정하는 방법은 크게 습식방법과 건식방법이 있는데, 습식방법은 벽면의 바깥쪽에 판 구조물을 대면 배치한 후 그 사이로 시멘트 등을 타설해서 고정하는 방식으로서 양생을 포함한 시공기간이 길고 작업성과 시공성이 떨어져 현재에는 거의 사용되지 않는다. On the other hand, the method of fixing the plate structure to the finished wall surface of the building is largely wet and dry, and the wet method is a method of placing plate structures on the outside of the wall surface and placing cement, etc. to fix it. It is rarely used at present because of the long construction period including and the workability and workability are poor.

반면, 건식방법은 금속 등으로 이루어진 별도의 고정구를 동원하여 벽면의 바깥쪽에 판 구조물을 결합시키는 방식으로, 상대적으로 시공성과 작업성이 뛰어나다.On the other hand, the dry method is a method of joining a plate structure to the outside of the wall surface by using a separate fastener made of metal or the like, and is relatively excellent in workability and workability.

이하, 첨부된 도 1a 내지 도 2를 참조하여 건식방법을 통해 외장패널이 시공되는 것에 대하여 살펴보도록 한다.Hereinafter, with reference to the accompanying Figures 1a to 2 to look at with respect to the construction of the exterior panel through a dry method.

각 층 슬래브(2)의 측면에 고정되는 제 1 브래킷(10)과, 상기 제 1 브래킷(10)에 고정되어 해당 슬래브(2)의 측면으로부터 실질적으로 수직하게 돌출되는 복수의 고정빔(20)과, 상기 고정빔(20)에 고정되어 수평하게 배열되는 복수의 가로빔(30)과, 상기 가로빔(30)의 외측으로 고정되어 수직하게 배열되는 복수의 세로빔(40)을 기본적인 골격구조로 하는 한편, 상기 각 세로빔(40)의 외측을 따라서는 제 2 브래킷(50)에 의해 석재 또는 금속재의 외장패널(P)이 사방연속으로 지지되어 외벽을 이룬다.A first bracket 10 fixed to the side of each floor slab 2 and a plurality of fixed beams 20 fixed to the first bracket 10 and projecting substantially vertically from the side of the slab 2 And, a basic skeletal structure of a plurality of horizontal beams 30 fixed to the fixed beam 20 and horizontally arranged, and a plurality of vertical beams 40 fixed to the outside of the horizontal beam 30 and vertically arranged. On the other hand, along the outer side of each vertical beam 40, the exterior panel P of a stone or metal material is supported in all directions by a second bracket 50 to form an outer wall.

이 외에도 도 1b에 도시된 바와 같이, 슬래브(2)에 수평으로 연결빔(60)을 설치하고, 상기 연결빔(60)을 따라 연결빔(60)의 길이 방향으로 외장패널(P)을 고정하여 건축물의 외벽을 시공한다.In addition to this, as shown in FIG. 1B, the connecting beam 60 is horizontally installed on the slab 2, and the exterior panel P is fixed in the longitudinal direction of the connecting beam 60 along the connecting beam 60. To construct the outer wall of the building.

이때, 외장패널(P) 시공에 있어서, 외장패널(P)의 균일한 배치는 건축물의 심미감 및 외벽의 내구성 측면에서 영향을 끼치므로 매우 중요하다.At this time, in the construction of the exterior panel (P), uniform arrangement of the exterior panel (P) is very important because it affects the aesthetic sense of the building and the durability of the exterior wall.

상기한 외장패널(P) 시공구조는 시공상 오차 즉, 외장패널(P)이 일직선으로 균일하지 못한 시공이 발생하더라도, 가로빔(30)이나 세로빔(40) 또는 연결빔(60) 위치를 교정함으로써, 외장패널(P) 시공에 대한 오차를 해소할 수 있다.The construction structure of the exterior panel (P) is the constructional error, that is, even when the exterior panel (P) is not uniform in a straight line construction, the horizontal beam 30 or the vertical beam 40 or the connection beam 60 position By calibrating, it is possible to eliminate errors in the construction of the exterior panel P.

한편, 전술한 빔(30,40,60) 자체에 외장패널(P)이 설치되는 구조외에, 지진, 화재 등 외력으로부터 구조체를 보강하기 위하여 설계된 새로운 내력구조를 갖는 내력패널 구조가 『대한민국 등록특허 제10-1731493호』을 통해 본 출원인이 개시한 바 있다. On the other hand, in addition to the structure in which the exterior panels P are installed on the beams 30, 40 and 60 themselves, the proof panel structure having a new proof structure designed to reinforce the structure from external forces such as earthquakes and fires has been published in the Republic of Korea. No. 10-1731493' has been disclosed by the applicant.

이는 도 2를 통해 알 수 있듯이, 라멘 수평부재(100)와 라멘 수직부재(110)가 구성하는 공간에, 내력패널(200)의 배면을 구성하는 내부판(210)이 전단키(shear key)를 통해 고정되어, 수평, 수직, 외력에 저항하도록 설치된다.2, the inner plate 210 constituting the rear surface of the proof strength panel 200 has a shear key in a space constituted by the ramen horizontal member 100 and the ramen vertical member 110. It is fixed through and installed to resist horizontal, vertical and external forces.

상기와 같은 라멘 구조를 구축할 때, 라멘 수평부재(100)는 프리스트레스트 빔을 사용하는데, 상기 프리스트레스트 빔은 처짐 및 솟음에 예민하여 공정 단계별로 빔종곡선이 변화하여 존재하게 된다.When constructing the above-described ramen structure, the ramen horizontal member 100 uses a pre-stress beam, which is sensitive to sagging and rising so that the beam longitudinal curve changes in each step of the process.

상기 빔종곡선의 변화로 인해 내력패널(200) 설치시 상기 내력패널(200)이 일직선으로 균일하게 위치되지 못하므로, 건축물 외관의 심미감이 떨어지는 문제가 있었다.When the proof strength panel 200 is installed due to the change in the beam longitudinal curve, the proof strength panel 200 is not uniformly positioned in a straight line, so there is a problem in that the aesthetic sense of the building exterior is deteriorated.

즉, 라멘 수평부재(100)가 슬래브 하중 등 여러 가지 처짐요인이 고려되지 못한 상태로 설계되어 제작되기 때문에, 라멘 수평부재(100)에 슬래브(2) 시공시 상기 라멘 수평부재(100)가 하방으로 처짐이 일정치 않아 라멘 수평부재(100) 사이에 끼움 시공되는 내력패널(200)은, 하방으로 처짐이 일정치 않은 라멘 수평부재(100)를 따라 시공되어야 했으므로 건축물 외벽의 심미감이 떨어졌던 것이다.That is, since the ramen horizontal member 100 is designed and manufactured in such a way that various deflection factors such as slab load are not considered, when the slab 2 is installed on the ramen horizontal member 100, the ramen horizontal member 100 is downward. As the sag is not uniform, the proof strength panel 200, which is installed between the horizontal members 100 of the ramen, has to be constructed along the horizontal horizontal members 100 of which the sag is not constant downward. will be.

또한, 라멘 수평부재(100)의 빔종곡선 변화로 인해, 내력패널(200)의 내부판(210)과 라멘 수평부재(100) 사이에 설치되어 외력에 저항하는 중요 요소인 전단키가 균일하게 설치되지 못하여 지진 및 화재 등으로 인한 외력에 저항하는 힘을 극대화하기 어려운 문제가 있었다.In addition, due to the change in the beam longitudinal curve of the horizontal member 100 of the ramen, the shear key, which is an important element that resists external force, is not uniformly installed because it is installed between the inner plate 210 of the proof strength panel 200 and the horizontal member 100 of the ramen. There was a problem in that it was difficult to maximize the force resisting external forces caused by earthquakes and fires.

대한민국 등록특허공보 제 10-1731493호Republic of Korea Registered Patent Publication No. 10-1731493

본 발명은 상기한 문제점을 해결하기 위하여 안출된 것으로써, 본 발명의 목적은 라멘구조 건축물의 내력패널 시공에 있어서, 라멘구조 건축물의 수평부재 수평도를 극대화하여 내력패널의 균일한 시공을 통한 건축물 외벽의 심미감 향상과, 외력에 의한 저항력을 극대화할 수 있도록 한 라멘구조 건축물의 수평부재 제작방법을 제공하고자 한 것이다. The present invention has been devised to solve the above-mentioned problems, and the object of the present invention is to construct a load-bearing panel of a ramen structured building by maximizing the horizontal level of horizontal members of a ramen-structured building, thereby constructing a structure through uniform construction of the load-bearing panel The purpose of the present invention is to provide a method for manufacturing a horizontal member of a ramen structured structure that can enhance the aesthetics of the outer wall and maximize the resistance by external force.

본 발명은 상기한 목적을 달성하기 위하여, 상,하방에 수평부재가 시공되고, 상,하방의 수평부재 사이에 내력패널이 끼움 시공되고, 상기 수평부재에는 슬래브가 안착 시공되는 라멘구조 건축물에 있어서, 상기 수평부재는, 프리스트레스트 빔으로 제작되며, 수평부재에 안착되는 슬래브 자중 및 슬래브 자중에 의한 크리프가 슬래브에 작용했을 때 수평부재는 지면에 대하여 수평되도록 상방으로 볼록하게 제작된 것을 특징으로 하는 라멘구조 건축물의 수평부재 제작방법을 제공한다.In the present invention, in order to achieve the above object, horizontal members are installed on the upper and lower sides, a load-bearing panel is sandwiched between the upper and lower horizontal members, and a slab is installed on the horizontal members in a ramen structure building. , The horizontal member is made of a prestressed beam, characterized in that the horizontal member is convex upward so as to be horizontal with respect to the ground when the slab weight and the creep caused by the slab weight applied to the horizontal member act on the slab. Provides a method for manufacturing horizontal members of ramen structures.

이때, (a) 수평부재의 수평 보정치만큼 바닥 중앙부가 하방으로 처지도록 거푸집을 제작하는 단계;(b) 상기 거푸집에 철근 및 프리스트레싱을 위한 강선을 배치하는 단계;(c) 상기 거푸집에 콘크리트를 타설하고 양생시키는 단계;(d) 양생된 콘크리트의 강선을 양측으로 당겨 지면에 대하여 상방으로 볼록하게 프리스트레싱을 작용시키는 단계:를 포함하여 구성되며, 상기 (d)단계의 볼록하게 프리스트레싱된 높이는, 수평부재에 안착되는 슬래브 자중 및 슬래브 자중에 의한 크리프가 수평부재에 작용했을 때 수평부재는 지면에 대하여 수평되도록 한 것이 바람직하다.At this time, (a) producing a formwork so that the center of the floor sags downward by the horizontal correction value of the horizontal member; (b) placing reinforcing bars and steel wires for prestressing in the formwork; (c) pouring concrete into the formwork And curing; (d) pulling the steel wire of the cured concrete to both sides to convexly prestress against the ground: comprising, wherein the convexly prestressed height of step (d) is a horizontal member. When the slab self-weight and the creep due to the slab self-weight are applied to the horizontal member, it is preferable that the horizontal member is leveled with respect to the ground.

이때, 상기 수평 보정치는, 수평부재의 하부편심 스트레싱, 수평부재의 스트레싱 손실, 수평부재 스트레싱에 의한 크리프, 수평부재 자중, 수평부재 자중에 의한 크리프, 슬래브 자중, 슬래브 자중에 의한 크리프 합산값인 것이 바람직하다.At this time, the horizontal correction value, the lower eccentric stress of the horizontal member, the loss of stress of the horizontal member, the creep caused by the horizontal member stress, the horizontal member weight, the creep caused by the weight of the horizontal member, the weight of the slab, the weight of the creep by the weight of the slab It is preferably a value.

본 발명에 따른 라멘구조 건축물의 수평부재 제작방법은 다음과 같은 효과가 있다.The method of manufacturing a horizontal member of a ramen structure building according to the present invention has the following effects.

다양한 수평부재 처짐요인을 고려한 거푸집 제작 및 슬래브의 자중 및 슬래브 자중에 의한 크리프 합산값 등의 고려를 통해 수평부재 제작이 이루어짐으로써, 슬래브가 수평부재에 시공되었을 때 수평부재는 처지는 일 없이 수평도를 유지할 수 있다.By manufacturing the formwork considering various horizontal member deflection factors and considering the sum of the weight of the slab and the creep sum due to the weight of the slab, the horizontal member is produced, so that when the slab is constructed on the horizontal member, the horizontal member does not sag without leveling. Can be maintained.

이에 따라, 수평부재를 따라 내력패널이 균일하게 시공될 수 있으므로, 건축물의 외벽 심미감이 떨어지는 일은 발생하지 않으며, 지진 및 화재등의 요인에 의한 외력에 저항할 수 있는 내력패널의 체결력을 극대화할 수 있는 효과가 있다.Accordingly, since the proof panel can be uniformly constructed along the horizontal member, the aesthetic sense of the outer wall of the building does not decrease, and the fastening force of the proof panel that can resist external forces due to factors such as earthquake and fire is maximized. It has the effect.

도 1a는 종래 기술에 따른 외장패널 설치구조를 나타낸 요부 사시도
도 1b는 종래 기술에 따른 외장패얼 설치구조의 다른 예를 나타낸 요부 측면도
도 2는 일반적인 라멘구조 건축물의 내력패널 및 슬래브가 시공된 상태를 나타낸 요부 사시도
도 3은 본 발명의 바람직한 실시예에 따른 라멘구조 건축물의 수평부재 제작방법을 나타낸 순서도
도 4는 본 발명의 바람직한 실시예에 따른 라멘구조 건축물의 수평부재 제작공정순서를 개략적으로 나타낸 도면
도 5는 본 발명의 바람직한 실시예에 따른 라멘구조 건축물의 수평부재 제작시 수평보정 처짐 관계를 나타낸 표.
Figure 1a is a perspective view of a main portion showing an external panel mounting structure according to the prior art
Figure 1b is a side view of a main portion showing another example of the exterior panel installation structure according to the prior art
Figure 2 is a perspective view of a main portion showing a state in which the load-bearing panels and slabs of a general ramen structure building are constructed;
3 is a flow chart showing a method of manufacturing a horizontal member of a ramen structure building according to a preferred embodiment of the present invention
4 is a view schematically showing a process of manufacturing a horizontal member of a ramen structure building according to a preferred embodiment of the present invention
Figure 5 is a table showing the horizontal compensation sag relationship when manufacturing a horizontal member of a ramen structure building according to a preferred embodiment of the present invention.

본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정 해석되지 아니하며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The terms or words used in the specification and claims are not to be construed as being limited to ordinary or lexical meanings. It should be interpreted in a sense and concept consistent with the technical idea of the present invention.

이하, 첨부된 도 3 내지 도 5를 참조하여 본 발명의 바람직한 실시예에 따른 라멘구조 건축물의 수평부재 제작방법에 대하여 설명하도록 한다.Hereinafter, a method of manufacturing a horizontal member of a ramen structure building according to a preferred embodiment of the present invention will be described with reference to the attached FIGS. 3 to 5.

수평부재(100)를 제작하기 위해 거푸집(300)을 제작한다.(S100)In order to manufacture the horizontal member 100, the formwork 300 is manufactured. (S100)

수평부재(100)는 콘크리트로 제작되며 프리스트레싱을 통해 제작된다.The horizontal member 100 is made of concrete and is manufactured through prestressing.

이때, 상기 거푸집(300)은 도 4의 (a)에 도시된 바와 같이, 중앙부가 하방으로 처지도록 제작이 된다.At this time, the formwork 300 is manufactured so that the central portion sags downward, as shown in Fig. 4 (a).

이는, 추후 양생된 수평부재(100)에 프리스트레싱을 가하는 과정에서, 수평부재(100)의 프리스트레싱이 효과적으로 이루어지도록 하기 위함이다.This is to ensure that the prestressing of the horizontal member 100 is effectively performed in the process of applying prestressing to the horizontal member 100 that is cured later.

즉, 수평부재(100)를 수평으로 제작한 후에, 강선(500)을 당겨 프리스트레싱된 수평부재(100)가 슬래브 자중 및 슬래브 자중에 의한 크리프 변위로 수평상태가 되었을 때의 강성에 비해, 수평부재(100)의 중앙부를 하방으로 처지게 제작한 후, 강선(500)을 당겨 프리스트레싱된 수평부재(100)가 슬래브 자중 및 슬래브 자중에 의한 크리프 변위로 수평상태가 되었을 때의 강성이 높기 때문인 것이다.That is, after the horizontal member 100 is manufactured horizontally, compared to the stiffness when the prestressed horizontal member 100 is leveled due to the slab self-weight and creep displacement due to the slab self-weight by pulling the steel wire 500. This is because the stiffness is high when the center portion of the (100) is made to sag downward, and the prestressed horizontal member 100 is pulled by the steel wire 500 and leveled by creep displacement due to slab self-weight and slab self-weight.

이때, 거푸집(300) 제작은 우선 거푸집(300)의 저부(低部)만 이루어진다.At this time, the production of the formwork 300 is first made only the bottom (低部) of the formwork (300).

한편, 상기 거푸집(300)의 중앙이 하방으로 처진 수치는 수평부재(100)의 수평보정치(δ)에 해당이 된다.On the other hand, the numerical value of the center of the formwork drooping downward corresponds to the horizontal correction value δ of the horizontal member 100.

이때, 거푸집(300) 하방 처짐은 처짐 곡선에 따라 설치한다.At this time, the downward deflection of the formwork 300 is installed according to the deflection curve.

본 발명은 거푸집(300)을 제작하는 것에 있어, 거푸집(300) 중앙의 처짐을 임의로 설계하는 것은 아니다.In the present invention, in manufacturing the formwork 300, the sagging of the center of the formwork 300 is not arbitrarily designed.

즉, 슬래브(2) 시공시 수평부재(100)의 수평이 유지되도록 하여, 수평부재(100)에 응력이 균일하게 전달되도록 하고, 수평부재(100)에 시공되는 내력패널(200)의 균질한 미관 완성을 고려해야 하므로, 거푸집 제작시 하방 처짐 수치는 매우 중요한 것이다. That is, when the slab 2 is constructed, the horizontal member 100 is maintained horizontally, so that the stress is uniformly transmitted to the horizontal member 100, and the homogeneity of the proof strength panel 200 installed on the horizontal member 100 is uniform. Since the aesthetics must be considered, the downward deflection value is very important when manufacturing the formwork.

상기 수평보정치(δ)를 산출하기 위한 조건으로는 도 5에 도시된 바와 같이 표를 통해 설명될 수 있다.The condition for calculating the horizontal correction value δ may be described through a table as shown in FIG. 5.

수평보정치(δ)를 산출하기 위해서는 수평부재(100)의 처짐 요인을 파악하고, 그 처짐 요인값 보정을 통해 수평보정치(δ)를 산출할 수 있다.In order to calculate the horizontal correction value δ, the deflection factor of the horizontal member 100 is grasped, and the horizontal correction value δ can be calculated by correcting the deflection factor value.

이때, 수평부재(100)의 처짐요인으로는 수평부재(100)의 하부편심 스트레싱(δ1)과, 수평부재(100)의 스트레싱 손실(δ2)과, 수평부재(100) 스트레싱에 의한 크리프(δ3)와, 수평부재(100)의 자중(δ4)과, 수평부재(100) 자중에 의한 크리프(δ5)와, 슬래브(2)의 자중(δ6)과, 슬래브(2) 자중에 의한 크리프(δ7)가 있다.At this time, the deflection factors of the horizontal member 100 include the lower eccentric stress (δ1) of the horizontal member 100, the stress loss (δ2) of the horizontal member 100, and the horizontal member 100 stressing. The creep (δ3), the self-weight (δ4) of the horizontal member 100, the creep (δ5) due to the self-weight of the horizontal member 100, the self-weight (δ6) of the slab 2, and the weight of the slab 2 Creep (δ7).

이러한 수평부재(100)의 처짐요인을 각각 산출하여 합산함으로써 수평보정치 (δ)가 산출되며, 그 수평보정치(δ)만큼 거푸집(100)의 저부 중앙을 처지게 제작한다.By calculating and summing each deflection factor of the horizontal member 100, a horizontal correction value (δ) is calculated, and the center of the bottom of the formwork is sagged as much as the horizontal correction value (δ).

이때, 각 수평부재(100)의 처짐요인을 계산하는 수학식은 다음과 같다.At this time, the equation for calculating the deflection factor of each horizontal member 100 is as follows.

① 수평부재 하부편심 스트레싱 솟음 (δ1)① Horizontal member lower eccentric stress rise (δ1)

Figure 112018026608555-pat00001
Figure 112018026608555-pat00001

Figure 112018026608555-pat00002
: 초기솟음량
Figure 112018026608555-pat00002
: Initial rise

Figure 112018026608555-pat00003
: 초기긴장력
Figure 112018026608555-pat00003
: Initial tension

e : 강선(500) 편심 e: Steel wire 500 eccentric

Figure 112018026608555-pat00004
: 콘크리트 탄성계수
Figure 112018026608555-pat00004
: Concrete modulus

Figure 112018026608555-pat00005
: 콘크리트 단면 2차 모멘트
Figure 112018026608555-pat00005
: Second moment of concrete section

Figure 112018026608555-pat00006
: 수평보정 프리스트레스트빔 길이
Figure 112018026608555-pat00006
: Horizontal compensation prestress beam length

② 수평부재 스트레싱 손실 처짐 (δ2)② Deflection of horizontal member stress loss (δ2)

Figure 112018026608555-pat00007
α : 스트레싱 손실계수
Figure 112018026608555-pat00007
α: Stress loss factor

③ 수평부재 스트레싱에 의한 크리프 솟음 (δ3)③ Creep rise due to horizontal member stressing (δ3)

Figure 112018026608555-pat00008
Figure 112018026608555-pat00009
: 크리프계수
Figure 112018026608555-pat00008
Figure 112018026608555-pat00009
: Creep coefficient

④ 수평부재의 자중 처짐 (δ4)④ Self-deflection of the horizontal member (δ4)

Figure 112018026608555-pat00010
Figure 112018026608555-pat00011
= 수평보정 프리스트레스트빔 단위 자중
Figure 112018026608555-pat00010
Figure 112018026608555-pat00011
= Self-weighted horizontal compensation prestress beam

ℓ = 수평보정 프리스트레스트빔 길이 ℓ = horizontal compensation prestress beam length

⑤ 수평부재의 자중에 의한 크리프 (δ5)⑤ Creep by self-weight of horizontal member (δ5)

Figure 112018026608555-pat00012
Figure 112018026608555-pat00012

⑥ 상부 슬래브 자중처짐 (δ6) ⑥ Self-deflection of the upper slab (δ6)

Figure 112018026608555-pat00013
Figure 112018026608555-pat00014
= 상부슬라브자중
Figure 112018026608555-pat00013
Figure 112018026608555-pat00014
= Upper slab weight

⑦ 상부슬라브 자중에 의한 크리프 (δ7)⑦ Creep due to the weight of the upper slab (δ7)

Figure 112018026608555-pat00015
Figure 112018026608555-pat00015

이와 같은 수학식을 통해 산출된 각각의 산출값을 합산하여 수평보정치(δ)를 산출하고 그 수평보정치(δ)만큼 거푸집(100)의 저부 중앙을 처짐 곡선에 따라 하방으로 처지게 제작한다.The horizontal correction value δ is calculated by summing the respective calculated values calculated through the above equation, and the center of the bottom of the formwork 100 is sag downward along the deflection curve by the horizontal correction value δ.

다음으로, 수평보재(100) 강성을 높이기 위한 철근(400) 배근 및 프리스트레싱을 위한 강선(500)을 거푸집(300)에 배치한다.(S200)Next, the reinforcing bar 400 for increasing the stiffness of the horizontal complement 100 and the steel wire 500 for prestressing and prestressing are placed in the formwork 300. (S200)

철근(400)은 도 4의 (b)에 도시된 바와 같이 거푸집(300) 곡률을 따라 배근된다.The reinforcing bar 400 is reinforced along the curvature of the formwork 300, as shown in FIG. 4(b).

강선(500)은 단면 중립축으로부터 하방으로 e만큼 하부에 편심지게 배치된다.The steel wire 500 is eccentrically disposed below e from the neutral axis of the cross section.

다음으로, 강선(500) 및 철근(400) 배근이 완료된 후, 도 4의 (c)에 도시된 바와 같이 거푸집(300)의 측부를 제작하고 거푸집(300)에 콘크리트를 타설한다.(S300)Next, after the reinforcement of the steel wire 500 and the reinforcing bar 400 is completed, as shown in (c) of FIG. 4, the side of the formwork 300 is manufactured and concrete is poured into the formwork 300. (S300)

이때, 거푸집(300) 측부의 높이는 수평부재(100)의 높이에 대응된다.At this time, the height of the side of the formwork 300 corresponds to the height of the horizontal member 100.

이후, 일정 시간동안 콘크리트를 양생시킨다.Thereafter, the concrete is cured for a certain period of time.

다음으로, 콘트리트가 양생되면, 강선(500)을 당겨 양생된 콘크리트에 프리스트레싱을 가한다.(S400)Next, when the concrete is cured, prestressing is applied to the cured concrete by pulling the steel wire 500 (S400).

이때, 프리스트레싱은 도 4의 (d)에 도시된 바와 같이 콘크리트가 상방으로 볼록하게 솟아오르도록 이루어진다.At this time, the pre-stressing is made so that the concrete rises convex upward as shown in Fig. 4 (d).

이때, 프리스트레싱된 콘크리트의 솟은 높이는 슬래브(2) 자중과 슬래브(2) 자중에 의한 크리프를 합산한 수치(δ6 + δ7)로 이루어진다.At this time, the raised height of the prestressed concrete consists of a numerical value (δ6 + δ7) obtained by summing the creep by the weight of the slab (2) and the weight of the slab (2).

이와 같은 설계는, 프리스트레싱된 수평부재(100)에 상부 슬래브(2)가 시공되었을 때, 수평부재(100)의 수평이 유지되도록 한 것으로써, 이후, 추가 시공에 따른 수평부재(100)에 가해지는 하중은 고려되지 않아도 무방하다할 것이다.Such a design, when the upper slab 2 is constructed on the prestressed horizontal member 100, so that the horizontal member 100 is maintained horizontally, then applied to the horizontal member 100 according to the additional construction Losing load will be considered without consideration.

즉, 활하중이 아닌 사하중만을 고려한 설계로써, 수평부재(100)에 슬래브(2)가 시공되었을 때 상기 수평부재(100)의 수평이 유지되면 무방하다 할 것이다.That is, it is a design that considers only the dead load, not the live load. When the slab 2 is constructed on the horizontal member 100, it will be okay if the level of the horizontal member 100 is maintained.

다음으로, 상기와 같이 제작된 수평부재(100)를 기둥에 시공하고, 상기 수평부재(100)위에 도 4의 (e)에 도시된 바와 같이 슬래브(2)를 안착 시공한다.(S500)Next, the horizontal member 100 manufactured as described above is installed on a pillar, and the slab 2 is mounted on the horizontal member 100 as shown in FIG. 4(e). (S500)

이때, 수평부재(100)는 슬래브(2) 자중과 슬래브(2) 자중에 의한 크리프 변형 처짐량(δ6 + δ7)만큼이 처져 수평을 유지하게 된다.At this time, the horizontal member 100 maintains the level by deflecting the amount of creep deformation deflection (δ6 + δ7) due to the weight of the slab 2 and the weight of the slab 2.

이때, 수평부재(100)는 슬래브의 자중 및 여러 조건 들이 고려되어 설계되어 있기 때문에 수평부재(100) 수평도의 정확도는 극대화될 수 있다.At this time, since the horizontal member 100 is designed in consideration of the weight of the slab and various conditions, the accuracy of the horizontality of the horizontal member 100 can be maximized.

다음으로, 도시되지는 않았지만, 각 층마다 시공된 수평부재(100) 사이에 내력패널(200)을 끼워 시공한다.Next, although not shown, it is constructed by sandwiching the proof strength panel 200 between the horizontal members 100 installed for each layer.

이때, 내력패널(200)의 내부판(210)은 수평부재(100)를 지지하게 되므로, 수평부재(100)의 수평 유지력은 더욱 극대화될 수 있다.At this time, since the inner plate 210 of the proof strength panel 200 supports the horizontal member 100, the horizontal holding force of the horizontal member 100 can be further maximized.

또한, 수평부재(100)의 수평 유지를 통해, 내력패널(200)의 설치가 균일하게 이루어질 수 있으므로, 라멘구조 건축물의 심미감을 높일 수 있을 뿐만아니라, 외력 저항이 각 부위마다 균일하게 이루어질 수 있으므로 내력패널(200) 시공의 품질을 극대화시킬 수 있다. In addition, by horizontally maintaining the horizontal member 100, since the installation of the proof strength panel 200 can be made uniform, not only can the aesthetic sense of the ramen structure building be increased, but also the external force resistance can be made uniformly in each part. It is possible to maximize the quality of construction of the proof strength panel 200.

이상에서 본 발명은 기재된 구체예에 대하여 상세히 설명되었지만 본 발명의 기술사상 범위 내에서 다양한 변형 및 수정이 가능함은 당업자에게 있어서 명백한 것이며, 이러한 변형 및 수정은 첨부된 특허 청구범위에 속함은 당연한 것이다.In the above, the present invention has been described in detail with respect to the described embodiments, but it is obvious to those skilled in the art that various modifications and variations are possible within the technical scope of the present invention, and it is natural that such modifications and modifications belong to the appended claims.

100 : 수평부재 200 : 내력패널
210 : 내부판 300 : 거푸집
400 : 철근 500 : 강선
100: horizontal member 200: proof panel
210: inner plate 300: formwork
400: Rebar 500: Steel wire

Claims (3)

상,하방에 수평부재가 시공되고, 상,하방의 수평부재 사이에 내력패널이 끼움 시공되고, 상기 수평부재에는 슬래브가 안착 시공되는 라멘구조 건축물에 있어서,
상기 수평부재는,
프리스트레스트 빔으로 제작되며, 수평부재에 안착되는 슬래브 자중 및 슬래브 자중에 의한 크리프를 고려하여 슬래브가 수평부재에 시공되었을 때 수평부재는 지면에 대하여 수평되도록 상방으로 볼록하게 제작되되, 상기 수평부재 제작단계는,
(a) 수평부재의 수평 보정치만큼 바닥 중앙부가 하방으로 처지도록 거푸집을 제작하는 단계;
(b) 상기 거푸집에 철근 및 프리스트레싱을 위한 강선을 배치하는 단계;
(c) 상기 거푸집에 콘크리트를 타설하고 양생시키는 단계;
(d) 양생된 콘크리트의 강선을 양측으로 당겨 양생된 콘크리트를 지면에 대하여 상방으로 볼록하게 프리스트레싱을 작용시키는 단계;
상기 (d)단계의 볼록하게 프리스트레싱된 높이는, 수평부재에 안착되는 슬래브 자중 및 슬래브 자중에 의한 크리프가 수평부재에 작용했을 때 수평부재는 지면에 대하여 수평이 되도록 한 높이이며,
상기 수평 보정치는,
수평부재의 하부편심 스트레싱, 수평부재의 스트레싱 손실, 수평부재 스트레싱에 의한 크리프, 수평부재 자중, 수평부재 자중에 의한 크리프, 슬래브 자중, 슬래브 자중에 의한 크리프 합산값인 것을 특징으로 하며,
상기 (a)단계에서의 거푸집 제작은 거푸집의 저부(低部)만 이루어지고, 상기 거푸집의 측벽 제작은 (b)단계 후 이루어지며,
(e) 상기 수평부재 위에 슬래브가 안착 시공되는 단계;
(f) 건물의 각 층마다 상기 수평부재 사이에 내력패널을 시공하는 단계:를 포함하여 구성되어,
상기 수평부재의 수평유지를 통해 내력패널의 설치가 균일하게 이루어지도록 하여, 외력 저항이 내력패널의 각 부위마다 균일하게 이루어질 수 있도록 한 것을 특징으로 하는 라멘구조 건축물의 수평부재 제작방법.

In the ramen structure building, horizontal members are installed on the upper and lower sides, a load-bearing panel is sandwiched between the upper and lower horizontal members, and slabs are mounted on the horizontal members.
The horizontal member,
It is made of a prestressed beam, and when the slab is constructed on the horizontal member in consideration of the slab self-weight and creep caused by the slab weight, the horizontal member is made convex upward so as to be horizontal with respect to the ground. The steps are,
(a) producing a formwork such that the center of the floor sags downward by the horizontal correction value of the horizontal member;
(b) placing steel wires for rebar and prestressing in the formwork;
(c) pouring and curing concrete in the formwork;
(D) pulling the steel wire of the cured concrete to both sides to act to pre-stress the cured concrete convex upward with respect to the ground;
The height of the convex prestressing in the step (d) is a height such that the horizontal member is horizontal to the ground when the slab weight and the creep caused by the slab weight applied to the horizontal member act on the horizontal member,
The horizontal correction value,
Characterized in that the lower eccentric stress of the horizontal member, the loss of stress of the horizontal member, the creep caused by the horizontal member stress, the horizontal member weight, the creep caused by the horizontal member weight, the slab weight, the creep sum by the slab weight,
In the step (a), the formwork is made only at the bottom of the formwork, and the sidewalls of the formwork are made after the step (b),
(e) a step in which a slab is installed on the horizontal member;
(f) constructing a proof strength panel between the horizontal members for each floor of the building, including:
Method of manufacturing a horizontal member of a ramen structure building, characterized in that the installation of the proof strength panel is made uniform through the horizontal maintenance of the horizontal member, so that the external force resistance can be made uniformly in each part of the proof strength panel.

삭제delete 삭제delete
KR1020180030885A 2018-03-16 2018-03-16 A horizontal beam manufacturing method of a Rahmen building structure KR102131957B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180030885A KR102131957B1 (en) 2018-03-16 2018-03-16 A horizontal beam manufacturing method of a Rahmen building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180030885A KR102131957B1 (en) 2018-03-16 2018-03-16 A horizontal beam manufacturing method of a Rahmen building structure

Publications (2)

Publication Number Publication Date
KR20190109035A KR20190109035A (en) 2019-09-25
KR102131957B1 true KR102131957B1 (en) 2020-07-09

Family

ID=68068103

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180030885A KR102131957B1 (en) 2018-03-16 2018-03-16 A horizontal beam manufacturing method of a Rahmen building structure

Country Status (1)

Country Link
KR (1) KR102131957B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114150864B (en) * 2021-12-02 2023-01-31 浙江银晨建设有限公司 Large-span prestressed concrete roof beam formwork structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101157607B1 (en) * 2009-06-25 2012-06-18 주식회사 젬콘 Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
KR101731493B1 (en) * 2014-11-25 2017-05-02 (주)수하담 Insulation and bearing panel and its manufacturing and installation method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101157607B1 (en) * 2009-06-25 2012-06-18 주식회사 젬콘 Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof
KR101731493B1 (en) * 2014-11-25 2017-05-02 (주)수하담 Insulation and bearing panel and its manufacturing and installation method

Also Published As

Publication number Publication date
KR20190109035A (en) 2019-09-25

Similar Documents

Publication Publication Date Title
RU2525407C2 (en) Design of form to make stairs and stair platforms, method to manufacture such form and method of its usage
KR101240409B1 (en) Prestressed precast concrete Composite Beam and manufacture methode for there of and construction methode for there of
WO2011012974A2 (en) Method for manufacturing a precast composite steel and concrete beam and a precast composite steel and concrete beam made according to said method
KR100694587B1 (en) Wall Structure Using Precast Concrete Panel with Multi Rib Rows
KR100905806B1 (en) Precast concrete stair system
KR100909882B1 (en) Composite slab structure using deck plate for reducing floor level
KR102131957B1 (en) A horizontal beam manufacturing method of a Rahmen building structure
KR100646363B1 (en) A reinforcement deck structure for a long span and its construction method
US20090301011A1 (en) Reinforced concrete ceiling and process for the manufacture thereof
CN110409700B (en) Composite prefabricated inner wallboard for prefabricated building
KR100814732B1 (en) Manufacturing method of light weight precast concrete wall panel and the panel manufactured by the same method
KR101286112B1 (en) Composite girder with steel pipe and rahmen bridge construction method using the same
JP2001214563A (en) Gravity deflection correcting method in construction structure material
JP5532468B1 (en) Formwork support member in the slab
KR101109244B1 (en) Structural Wall having Fiber Concrete Reinforcing Part for Plastic Hinge
EP1416101A1 (en) Composite beam
KR100646103B1 (en) Hybrid beam using FRP form
US20060059835A1 (en) Precast composite floor panel with integrated joist and method of manufacturing same
KR101338890B1 (en) Wall system with frame pannel and method for fabricating and constructing the wall system
KR100992038B1 (en) Architectural beam by filled concrete
CN110863584A (en) A L type self preservation temperature shear force wall prefabricated plate for prefabricated construction corner
KR100837831B1 (en) Underground downward construction system
KR20210028869A (en) Installation structure of hollow core slab
KR102383548B1 (en) Pre-cast deck with inner void and construction method thereof
KR101340871B1 (en) Psc girder and psc girder making method using concrete saddle and psc girder thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right