KR102088917B1 - Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same - Google Patents

Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same Download PDF

Info

Publication number
KR102088917B1
KR102088917B1 KR1020170090945A KR20170090945A KR102088917B1 KR 102088917 B1 KR102088917 B1 KR 102088917B1 KR 1020170090945 A KR1020170090945 A KR 1020170090945A KR 20170090945 A KR20170090945 A KR 20170090945A KR 102088917 B1 KR102088917 B1 KR 102088917B1
Authority
KR
South Korea
Prior art keywords
steel pipe
unit steel
structures
unit
pipe structure
Prior art date
Application number
KR1020170090945A
Other languages
Korean (ko)
Other versions
KR20190009452A (en
Inventor
엄태성
임종진
Original Assignee
단국대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 단국대학교 산학협력단 filed Critical 단국대학교 산학협력단
Priority to KR1020170090945A priority Critical patent/KR102088917B1/en
Publication of KR20190009452A publication Critical patent/KR20190009452A/en
Application granted granted Critical
Publication of KR102088917B1 publication Critical patent/KR102088917B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/36Columns; Pillars; Struts of materials not covered by groups E04C3/32 or E04C3/34; of a combination of two or more materials
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

본 발명은, 단위 강관 구조체들이 조립되어 연장되며, 그 내부에 콘크리트가 채워지는 콘크리트 충전형(CFT(Concrete Filled Tube)) 구조물에 사용되는 조립형 강관으로서, 상기 단위 강관 구조체는, 내면에 보강 부재가 결합되고, 상기 보강 부재는, 상기 조립형 강관의 연장 방향 또는 그 반대 방향으로 연장되어 상기 단위 강관 구조체에 돌출되도록 형성되며, 상기 단위 강관 구조체는, 제 1 또는 제 2 단위 강관 구조체(100, 200)를 포함하고, 상기 조립형 강관(500)은, 제 1 및 제 2 단위 강관 구조체(100, 200)를 포함하며, 상기 제 1 단위 강관 구조체(100)의 보강 부재(120)는, 상기 제 2 단위 강관 구조체(200) 내측으로 삽입되고, 상기 제 2 단위 강관 구조체(200)의 보강 부재(220)는 상기 제 1 단위 강관 구조체(100) 내측으로 삽입되도록 형성되며, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 보강 부재(120, 220)들은, 콘크리트에 정착되어, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 이음부의 결합력을 강화하도록 형성되는, 조립형 강관을 제공한다. The present invention is a prefabricated steel pipe used for a concrete filled type (CFT) structure in which unit steel pipe structures are assembled and extended, and concrete is filled therein, wherein the unit steel pipe structure is a reinforcement member on an inner surface. Is coupled, the reinforcing member is formed to extend in the extending direction or the opposite direction of the prefabricated steel pipe to protrude from the unit steel pipe structure, the unit steel pipe structure, the first or second unit steel pipe structure (100, 200), the assembled steel pipe 500 includes first and second unit steel pipe structures 100 and 200, and the reinforcing member 120 of the first unit steel pipe structure 100 includes: The second unit steel pipe structure 200 is inserted inside, and the reinforcing member 220 of the second unit steel pipe structure 200 is formed to be inserted into the first unit steel pipe structure 100, and the first and first 2 unit steel pipe Reinforcing members (120, 220) of the structures (100, 200) are fixed to concrete, and are formed to strengthen the bonding force of the joints of the first and second unit steel pipe structures (100, 200), providing a prefabricated steel pipe do.

Description

보강 부재가 내부에 구비된 조립형 강관 및 이를 이용한 콘크리트 충전형 구조물의 시공 방법 {Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same}Assembly type steel tube having a reinforcing member therein and construction method of concrete filled tube structures using the same}

본 발명은 보강 부재가 내부에 구비된 조립형 강관 및 이를 이용한 콘크리트 충전형 구조물의 시공 방법에 관한 것이다. The present invention relates to a construction method of a prefabricated steel pipe provided with a reinforcing member therein and a concrete-filled structure using the same.

철근 콘크리트 구조(RC조), 철골 구조(S조), 철골철근 콘크리트 구조(SRC조)에 이어 제4의 구조시스템으로 일컬어지고 있는 콘크리트 충전형 강관(Concrete Filled Tube, CFT로 약칭) 구조는, 최근 미국, 일본 등 선진국에서 이에 대한 연구가 활발히 이루어지고 있으며, 실제로 초고층 건물을 중심으로 성공적으로 적용되고 있다. Reinforced concrete structure (RC group), steel structure (S group), steel reinforced concrete structure (SRC group), and concrete filled steel pipe (abbreviated as CFT) structure, which is referred to as a fourth structural system, Recently, research on this has been actively conducted in developed countries such as the United States and Japan, and has been successfully applied to skyscrapers.

CFT 구조는 연성이 높고, 시공이 비교적 단순하며, 강재와 콘크리트의 합성을 통하여 단면의 휨저항 및 압축저항 효율을 높일 수 있는 바, 큰 압축하중과 휨모멘트가 작용하는 초고층 구조시스템의 기둥 및 벽체에 적합하다.CFT structure has high ductility, relatively simple construction, and can increase the bending resistance and compression resistance efficiency of the cross section through the synthesis of steel and concrete, and the pillars and walls of the ultra-high-rise structure system with large compressive load and bending moment Is suitable for

또한, 강관을 거푸집으로 활용함으로써, 거푸집 공사를 생략할 수 있게 됨은 물론, 콘크리트는 강관의 국부 좌굴을 방지하고, 강관은 내부 콘크리트를 구속시킴으로써, 콘크리트가 가지고 있는 최대 약점인 연성을 증대시킬 수 있다. In addition, by using the steel pipe as a formwork, it is possible to omit the formwork construction, and concrete prevents local buckling of the steel pipe, and the steel pipe can constrain the internal concrete, thereby increasing ductility, the greatest weakness of concrete. .

구체적으로, 콘크리트는 압축력에는 매우 강하지만, 인장력에는 취약한 특성이 있으며, 철은 인장 및 압축력에 모두 강하지만, 국부 좌굴에 취약한 특성을 지니고 있는 바, CFT 구조물은 이 두가지 재료의 장단점이 잘 보완된 구조이다. Concretely, concrete is very strong in compressive force, but is vulnerable to tensile force, iron is strong in both tensile and compressive force, but it is vulnerable to local buckling. Structure.

한편, CTF 구조는 기둥에 적용될 수 있으며, 기둥의 특성상 길이를 길게 적용할 경우, 여타 강구조 공법과 마찬가지로 상하로 배치된 기둥들을 용접이나 볼트를 사용하여 이음 시공을 해야하는 경우가 대부분이다.On the other hand, the CTF structure can be applied to the column, and when the length is long due to the characteristics of the column, as in other steel structure methods, most of the columns placed up and down need to be welded or bolted to joint construction.

도 1은 종래의 CFT 기둥을 나타낸 사시도이고, 도 2는 도 1에 도시된 CFT 기둥에 덧판을 댄 구조를 나타낸 사시도이다.1 is a perspective view showing a conventional CFT pillar, and FIG. 2 is a perspective view showing a structure in which a CFT pillar shown in FIG. 1 is covered with a leaf plate.

도 1 및 2를 함께 참조하면, 종래의 CFT 기둥(10)은 상하로 배치된 한 쌍의 단위 기둥(11, 12)을 도 1에 도시된 것처럼 용접(W)에 의한 이음 시공을 통해 결합한다.Referring to FIGS. 1 and 2 together, the conventional CFT pillar 10 combines a pair of unit pillars 11 and 12 arranged up and down through a joint construction by welding W as shown in FIG. 1. .

이러한 경우, 용접된 이음부의 내력 확보를 위해 도 2에 도시된 것처럼 덧판(13)을 이음부 부분에 덧댄 후 보강판 외곽 라인 전체를 용접하여 보강한다.In this case, to secure the strength of the welded joint, as shown in FIG. 2, the top plate 13 is overlaid on the joint portion and then welded to reinforce the entire outer line of the reinforcement plate.

이렇게 종래의 CFT 기둥(10)은 과도한 용접으로 인해 인건비가 상승하고, 이는 원가 상승의 요인이 되며, 이음부의 내력확보를 위해 구비되는 덧판(13)은 단위 기둥(11, 12)을 구성하는 강재보다 두꺼운 철판을 적용해야 하기 때문에, 자재 수가 증가하고, 원가를 상승시키는 문제가 있다. In this way, the conventional CFT column 10 increases the labor cost due to excessive welding, which is a factor of cost increase, and the leaf plate 13 provided for securing the joint strength of the joint is a steel material constituting the unit columns 11 and 12 Since a thicker iron plate has to be applied, there is a problem in that the number of materials increases and the cost increases.

또한, CFT에 사용되는 단위 기둥(11, 12)은, 일반적으로 두께가 얇게 형성되어 있는 바, 결합시 용접열에 의해 얇은 강관이 변형될 수 있는 문제가 있다. In addition, since the unit pillars 11 and 12 used in the CFT are generally formed to have a thin thickness, there is a problem that the thin steel pipe may be deformed by welding heat during bonding.

이에 따라, 최근에는 CFT 구조물을 시공할 때, 현장 용접이 필요없이 단위 기둥들을 결합시킴과 동시에, 외력에 취약한 단위 기둥들의 이음부의 구조적 강성을 증대시킬 수 있는 기술에 대한 필요성이 높은 실정이다. Accordingly, in recent years, when constructing a CFT structure, there is a high need for a technology capable of combining unit pillars without the need for on-site welding and increasing structural rigidity of the joints of unit pillars vulnerable to external forces.

(특허문헌 1) KR 10-2012-0056117 A(Patent Document 1) KR 10-2012-0056117 A

(특허문헌 2) KR 10-2006-0042561 A(Patent Document 2) KR 10-2006-0042561 A

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것이며, 구체적으로, 단위 강관 구조체의 결합을 수행할 때, 용접 작업이 필요없는 조립형 강관을 제공함과 동시에, 외력에 취약한 단위 강관 구조체들의 이음부의 구조적 강성을 증대시킨 조립형 강관을 제공하고자 한다. The present invention has been devised to solve the above problems, and specifically, when performing the joining of the unit steel pipe structure, while providing a prefabricated steel pipe that does not require welding work, the joint portion of the unit steel pipe structures vulnerable to external forces It is intended to provide a prefabricated steel pipe with increased structural rigidity.

상기와 같은 과제를 해결하기 위한 본 발명의 일 실시예는, 단위 강관 구조체들이 조립되어 연장되며, 그 내부에 콘크리트가 채워지는 콘크리트 충전형(CFT(Concrete Filled Tube)) 구조물에 사용되는 조립형 강관으로서, 상기 단위 강관 구조체는, 내면에 보강 부재가 결합되고, 상기 보강 부재는, 상기 조립형 강관의 연장 방향 또는 그 반대 방향으로 연장되어 상기 단위 강관 구조체에 돌출되도록 형성되며, 상기 단위 강관 구조체는, 제 1 또는 제 2 단위 강관 구조체(100, 200)를 포함하고, 상기 조립형 강관(500)은, 제 1 및 제 2 단위 강관 구조체(100, 200)를 포함하며, 상기 제 1 단위 강관 구조체(100)의 보강 부재(120)는, 상기 제 2 단위 강관 구조체(200) 내측으로 삽입되고, 상기 제 2 단위 강관 구조체(200)의 보강 부재(220)는 상기 제 1 단위 강관 구조체(100) 내측으로 삽입되도록 형성되며, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 보강 부재(120, 220)들은, 콘크리트에 정착되어, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 이음부의 결합력을 강화하도록 형성되는 조립형 강관을 제공하고자 한다. One embodiment of the present invention for solving the above problems, the unit steel pipe structures are assembled and extended, the prefabricated steel pipe used in a concrete filled type (CFT (Concrete Filled Tube)) structure filled with concrete therein As, the unit steel pipe structure, a reinforcing member is coupled to the inner surface, the reinforcing member is formed to extend in the extending direction or the opposite direction of the prefabricated steel pipe and protrude from the unit steel pipe structure, wherein the unit steel pipe structure is , A first or second unit steel pipe structure (100, 200), the prefabricated steel pipe 500, the first and second unit steel pipe structure (100, 200), the first unit steel pipe structure The reinforcing member 120 of (100) is inserted into the second unit steel pipe structure 200, and the reinforcing member 220 of the second unit steel pipe structure 200 is the first unit steel pipe structure 100 Shovel inward It is formed so as to, the reinforcing members (120, 220) of the first and second unit steel pipe structures (100, 200) is fixed to the concrete, the first and second unit steel pipe structures (100, 200) of the joint It is intended to provide a prefabricated steel pipe formed to strengthen the bonding force.

또한, 상기 단위 강관 구조체(100, 200)는, 4 면이 형성되어 있는 사각 기둥 형상이며, 상기 보강 부재(120, 220)는, 결합 수단(140, 240)에 의해 상기 4 면에 각각 결합되도록 형성되고, 상기 결합 수단(140, 240)은, 상기 콘크리트의 양생이 종료된 후, 상기 조립형 강관(500)의 외측에서 제거 가능하도록 형성되는 것이 바람직하다. In addition, the unit steel pipe structures 100 and 200 have a quadrangular pillar shape in which four surfaces are formed, and the reinforcing members 120 and 220 are coupled to the four surfaces by coupling means 140 and 240, respectively. It is formed, it is preferable that the coupling means (140, 240) is formed to be removable from the outside of the assembled steel pipe 500 after curing of the concrete is finished.

또한, 상기 조립형 강관(500)은, 제 3 단위 강관 구조체(300); 를 더 포함하며, 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)가 순서대로 적층되고, 상기 제 2 단위 강관 구조체(200)의 보강 부재(220)는, 상기 제 1 및 제 3 단위 강관 구조체(100, 300) 내부로 삽입되도록 형성되고, 상기 제 3 단위 강관 구조체(300)의 보강 부재(320)는, 상기 제 2 단위 강관 구조체(200) 내부로 삽입되도록 형성되는 것이 바람직하다. In addition, the assembled steel pipe 500, the third unit steel pipe structure 300; Further comprising, the first to third unit steel pipe structure (100, 200, 300) are sequentially stacked, the reinforcing member 220 of the second unit steel pipe structure 200, the first and third It is formed to be inserted into the unit steel pipe structures 100 and 300, and the reinforcing member 320 of the third unit steel pipe structure 300 is preferably formed to be inserted into the second unit steel pipe structure 200. .

또한, 상기 보강 부재(120, 220) 중 단위 강관 구조체(100, 200)에 돌출 형성된 부분(120a, 220a)은, 상기 단위 강관 구조체(100, 200) 단면의 중심 방향으로 절곡된 갈고리 형상인 것이 바람직하다. In addition, among the reinforcing members 120 and 220, the portions 120a and 220a protruding from the unit steel pipe structures 100 and 200 are hook-shaped bent in the center direction of the cross section of the unit steel pipe structures 100 and 200. desirable.

또한, 상기 보강 부재(120, 220)의 단부는, 90도 또는 180도로 절곡되는 갈고리 형상인 것이 바람직하다. In addition, it is preferable that the ends of the reinforcing members 120 and 220 have a hook shape bent at 90 degrees or 180 degrees.

한편, 상기와 같은 과제를 해결하기 위한 본 발명의 일 실시예는, 전술한 조립형 강관을 이용하여, 콘크리트 충전형 구조물을 시공 방법으로서, (a) 상기 제 1 및 제 2 단위 강관 구조체(100, 200)를 상기 제 1 방향으로 적층시키는 단계; (b) 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 외면에 형성되어 있는 고정 부재(160, 260)를 이용하여, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)를 고정시키는 단계; (c) 상기 제 1 및 제 2 단위 강관 구조체(100, 200)로 이루어진 조립형 강관(500) 내부에 콘크리트를 타설하는 단계; (d) 상기 콘크리트를 양생하는 단계; 및 (e) 상기 콘크리트의 양생이 종료된 후, 상기 보강 부재(120, 220) 및 상기 단위 강관 구조체(100, 200) 사이를 고정시키고 있는 결합 수단(140, 240)을, 상기 단위 강관 구조체(100, 200)의 외측에서 제거시키는 단계; 를 포함하는 콘크리트 충전형 구조물의 시공 방법을 제공하고자 한다. On the other hand, an embodiment of the present invention for solving the above problems, using the above-described assembled steel pipe, as a construction method for a concrete-filled structure, (a) the first and second unit steel pipe structure 100 , 200) in the first direction; (b) fixing the first and second unit steel pipe structures 100 and 200 using fixing members 160 and 260 formed on outer surfaces of the first and second unit steel pipe structures 100 and 200 Letting; (c) pouring concrete into the prefabricated steel pipe 500 made of the first and second unit steel pipe structures 100 and 200; (d) curing the concrete; And (e) after curing of the concrete is finished, the reinforcing member (120, 220) and the coupling means (140, 240) for fixing between the unit steel pipe structure (100, 200), the unit steel pipe structure ( 100, 200); It is intended to provide a construction method of a concrete-filled structure comprising a.

본 발명에 따른 조립형 강관을 구성하는 단위 강관 구조체는 보강 부재를 포함함으로써, 콘크리트 충전형 구조물 중 단위 강관 구조체들의 이음부에서 구조적 강성과 강도를 증대시킬 수 있다. The unit steel pipe structure constituting the prefabricated steel pipe according to the present invention includes a reinforcing member, so that structural rigidity and strength can be increased at a joint of the unit steel pipe structures among concrete filled structures.

또한, 단위 강관 구조체들의 외면에는 고정 부재가 형성되어 있는 바, 단위 강관 구조체들을 결합하여 조립형 강관을 형성하는 과정에서, 용접 과정이 불필요하므로 시공이 편리하며, 고정 부재들 사이를 결합하여 조립형 강관을 형성함으로써, 용접에 따른 단위 강관 구조체의 변형을 방지할 수 있다. In addition, since the fixing member is formed on the outer surface of the unit steel pipe structures, in the process of combining the unit steel pipe structures to form the assembled steel pipe, the welding process is unnecessary, so the construction is convenient, and the fixing members are assembled by combining the fixing members. By forming the steel pipe, it is possible to prevent deformation of the unit steel pipe structure due to welding.

도 1은, 종래의 CFT 기둥을 개략적으로 나타낸 사시도이다.
도 2는, 도 1에 도시된 CFT 기둥에 덧판을 댄 구조를 개략적으로 나타낸 사시도이다.
도 3은, 본 발명에 따른 조립형 강관을 형성하는 제 1 및 제 2 단위 강관 구조체를 결합하기 전의 상태를 개략적으로 나타낸 사시도이다.
도 4는, 본 발명에 따른 제 1 및 제 2 단위 강관 구조체가 결합되어 조립형 강관을 형성한 상태의 단면도이다.
도 5는, 본 발명에 따른 보강 부재의 사시도이다.
도 6은, 본 발명에 따른 조립형 강관을 형성하는 제 1 내지 제 3 단위 강관 구조체를 결합하기 전의 상태를 개략적으로 나타낸 사시도이다.
도 7은, 본 발명에 따른 조립형 강관을 이용하여, 콘크리트 충전형 구조물을시공하는 방법의 순서도이다.
1 is a perspective view schematically showing a conventional CFT pillar.
FIG. 2 is a perspective view schematically showing the structure of the CFT pillar shown in FIG. 1 with a leaf plate.
3 is a perspective view schematically showing a state before combining the first and second unit steel pipe structures forming the assembled steel pipe according to the present invention.
4 is a cross-sectional view of a state in which the first and second unit steel pipe structures according to the present invention are combined to form an assembled steel pipe.
5 is a perspective view of a reinforcing member according to the present invention.
6 is a perspective view schematically showing a state before combining the first to third unit steel pipe structures forming the assembled steel pipe according to the present invention.
7 is a flow chart of a method for constructing a concrete-filled structure using an assembled steel pipe according to the present invention.

이하, 도면을 참조하여 본 발명에 따른 조립형 강관을 상세히 설명한다. 여기에서, 본 발명을 이루는 구성요소들은 필요에 따라 일체형으로 사용되거나 각각 분리되어 사용될 수 있다. 또한, 사용 형태에 따라 일부 구성요소를 생략하여 사용 가능하다. 본 발명의 형태 및 구성요소의 개수에 있어서도 다양한 변형이 가능하다.Hereinafter, the assembled steel pipe according to the present invention will be described in detail with reference to the drawings. Here, the components constituting the present invention may be used integrally or separately used as required. Also, some components may be omitted depending on the type of use. Various modifications are possible in the form of the present invention and the number of components.

본 발명에 따른 조립형 강관의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 이 과정에서 도면에 도시된 선들의 두께나 구성요소의 크기 등은 설명의 명료성과 편의상 과장되게 도시되어 있을 수 있다. 또한, 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례에 따라 달라질 수 있다. 그러므로 이러한 용어들에 대한 정의는 본 명세서 전반에 걸친 내용을 토대로 기술되어야 할 것이다. Preferred embodiments of the assembled steel pipe according to the present invention will be described with reference to the accompanying drawings. In this process, the thickness of the lines or the size of components shown in the drawings may be exaggerated for clarity and convenience. In addition, terms to be described later are terms defined in consideration of functions in the present invention, which may vary according to a user's or operator's intention or practice. Therefore, the definition of these terms should be described based on the contents throughout this specification.

본 명세서에서 일 실시예에 해당되는 구성요소들을 모두 포함하거나, 이외의 특징들을 구비하는 다른 형태의 조립형 강관도 용이하게 도출 가능할 것임이 이해되어야 한다.It should be understood that other types of prefabricated steel pipes including all of the components corresponding to one embodiment or other features in this specification may be easily derived.

도 3은, 본 발명에 따른 조립형 강관을 형성하기 위해, 제 1 및 제 2 단위 강관 구조체를 결합하기 전의 상태를 개략적으로 나타낸 사시도이다. 3 is a perspective view schematically showing a state before combining the first and second unit steel pipe structures to form an assembled steel pipe according to the present invention.

도 3을 참조하면, 조립형 강관(500)은, 단위 강관 구조체들이 조립되어 연장되는 구조이며, 구체적으로, 단위 강관 구조체는 제 1 또는 제 2 단위 강관 구조체(100, 200)로 이루어져 있으며, 제 1 단위 강관 구조체(100)는 하방에 위치한 단위 강관 구조체를 의미하며, 제 2 단위 강관 구조체(200)는 상방에 위치한 단위 강관 구조체를 의미한다. Referring to FIG. 3, the assembled steel pipe 500 is a structure in which unit steel pipe structures are assembled and extended. Specifically, the unit steel pipe structure is composed of first or second unit steel pipe structures 100 and 200. 1 unit steel pipe structure 100 refers to a unit steel pipe structure located at the bottom, and the second unit steel pipe structure 200 refers to a unit steel pipe structure located at the upper side.

이 때, 제 1 및 제 2 단위 강관 구조체(100, 200)의 내면에는 각각 보강 부재(120, 220)가 결합되며, 제 1 단위 강관 구조체(100)의 보강 부재(120)는 조립형 강관(500)의 연장 방향인 상방을 향해 돌출 형성되고, 제 2 단위 강관 구조체(200)의 보강 부재(220)는 상기 연장 방향의 반대 방향인 하방을 향해 돌출 형성된다. At this time, reinforcement members 120 and 220 are coupled to the inner surfaces of the first and second unit steel pipe structures 100 and 200, respectively, and the reinforcement members 120 of the first unit steel pipe structure 100 are assembled steel pipes ( 500) is formed to protrude upward in the extending direction, and the reinforcing member 220 of the second unit steel pipe structure 200 is protruded downward in the direction opposite to the extending direction.

또한, 보강 부재(120, 220)들은 모두 제 1 및 제 2 단위 강관 구조체(100, 200)의 내면에 각각 결합되어 있는 바, 제 1 및 제 2 단위 강관 구조체(100, 200)가 조립된 상태에서는, 보강 부재(120, 220)들이 외부로 노출되지 않고, 이에 따라, 콘크리트 타설 및 양생 후, 콘크리트의 내부에 정착되도록 형성된다. In addition, the reinforcing members 120 and 220 are all coupled to the inner surfaces of the first and second unit steel pipe structures 100 and 200, respectively, and the first and second unit steel pipe structures 100 and 200 are assembled. In, the reinforcing members 120 and 220 are not exposed to the outside, and thus, are formed to settle inside the concrete after pouring and curing the concrete.

구체적으로, 제 1 단위 강관 구조체(100)의 보강 부재(120)는, 제 2 단위 강관 구조체(200) 내측으로 삽입되고, 제 2 단위 강관 구조체(200)의 보강 부재(220)는 상기 제 1 단위 강관 구조체(100) 내측으로 삽입되도록 형성된다. Specifically, the reinforcing member 120 of the first unit steel pipe structure 100 is inserted into the second unit steel pipe structure 200, and the reinforcing member 220 of the second unit steel pipe structure 200 is the first The unit steel pipe structure 100 is formed to be inserted inside.

한편, 제 1 및 제 2 단위 강관 구조체(100, 200)는, 4 면이 형성되어 있는 사각 기둥 형상이며, 보강 부재(120, 220)는, 결합 수단(140, 240)에 의해 4 면에 각각 결합되도록 형성되고, 추후에 결합 수단(140, 240)이 다시 제거 가능할 수 있으며, 볼트 체결을 통해 결합될 수 있다. On the other hand, the first and second unit steel pipe structures 100 and 200 have a quadrangular pillar shape in which four surfaces are formed, and the reinforcing members 120 and 220 are respectively attached to four surfaces by means of couplings 140 and 240. It is formed to be coupled, and later the coupling means 140 and 240 may be removable again, and may be coupled through bolting.

또한, 각 면에는 한 쌍의 보강 부재(120, 220)가 형성되어 있으며, 4 면에 결합되어 있는 총 4 쌍의 보강 부재(120, 220)들은, 단위 강관 구조체의 동일한 높이에 결합되는 것이 바람직하다. In addition, a pair of reinforcing members 120 and 220 are formed on each side, and a total of four pairs of reinforcing members 120 and 220 coupled to the four sides are preferably coupled to the same height of the unit steel pipe structure. Do.

한편, 각 면에 결합되어 있는 보강 부재(120, 220)의 개수는 설계자의 선택 내지 필요에 따라, 자유롭게 조절할 수 있으며, 보강 부재(120, 220)가 결합되어 있는 높이 역시 변경 가능함을 명시한다. On the other hand, the number of reinforcing members (120, 220) coupled to each surface can be freely adjusted according to the designer's choice or need, and specifies that the heights of the reinforcing members (120, 220) are also changeable.

도 4는, 본 발명에 따른 제 1 및 제 2 단위 강관 구조체가 결합되어 조립형 강관을 형성한 상태의 단면도이다. 4 is a cross-sectional view of a state in which the first and second unit steel pipe structures according to the present invention are combined to form an assembled steel pipe.

도 4를 참조하면, 보강 부재(120, 220) 중 단위 강관 구조체(100, 200)의 이음단으로부터 돌출된 부분(120a, 220a)은, 단위 강관 구조체(100, 200) 단면의 중심 방향으로 절곡된 갈고리 형상이며, 보강 부재(120, 220)의 단부는, 180도로 절곡되는 갈고리 형상이다. Referring to FIG. 4, among the reinforcement members 120 and 220, portions 120a and 220a protruding from the joint ends of the unit steel pipe structures 100 and 200 are bent in the center direction of the cross section of the unit steel pipe structures 100 and 200 It is a hook shape, and the ends of the reinforcing members 120 and 220 are hook shapes bent at 180 degrees.

이와 같이, 보강 부재(120, 220)의 단부는, 갈고리 형상으로 형성함에 따라, 보강 부재(120, 220)의 단부가 절곡되지 않은 플레이트 구조에 비해, 더욱 강한 콘크리트와의 결합력을 발휘할 수 있다. As described above, as the end portions of the reinforcing members 120 and 220 are formed in a hook shape, the end portions of the reinforcing members 120 and 220 can exhibit stronger bonding strength with concrete compared to a plate structure in which the ends are not bent.

이에 따라, 제 1 및 제 2 단위 강관 구조체(100, 200)의 이음부에 횡방향의 외력이 인가될 때, 상기 외력을 제 1 단위 강관 구조체(100)에 충전되어 있는 콘크리트 및 제 2 단위 강관 구조체(200)에 충전되어 있는 콘크리트에 균등하게 분해할 수 있는 바, 궁극적으로, 이음부의 구조적 강성과 강도를 보강시킬 수 있다. Accordingly, when the external force in the transverse direction is applied to the joints of the first and second unit steel pipe structures 100 and 200, the concrete and the second unit steel pipe filled with the external force in the first unit steel pipe structure 100 It can be evenly decomposed in the concrete filled in the structure 200, ultimately, it can reinforce the structural rigidity and strength of the joint.

한편, 제 1 및 제 2 단위 강관 구조체(100, 200)의 외면에는 각각 고정 부재(160, 260)가 형성되며, 고정 부재(160, 260)는, 제 1 및 제 2 단위 강관 구조체(100, 200)가 접하는 부위에 형성되되, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)가 고정되도록 상호 대응되는 위치에 형성된다. 또한, 고정부재가 1 내지 제 3 단위 강관 구조체(100, 200, 300)가 서로 접하는 상기 이음부의 외측으로 형성되고, 상기 고정부재는 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)의 상기 이음부의 결합력을 강화하도록 형성된다.Meanwhile, fixing members 160 and 260 are formed on outer surfaces of the first and second unit steel pipe structures 100 and 200, respectively, and the fixing members 160 and 260 include first and second unit steel pipe structures 100, 200) are formed at the contacting portions, and are formed at positions corresponding to each other so that the first and second unit steel pipe structures 100 and 200 are fixed. In addition, a fixing member is formed on the outside of the joint where the first to third unit steel pipe structures 100, 200 and 300 contact each other, and the fixing member is the first to third unit steel pipe structures 100, 200 and 300. It is formed to enhance the coupling force of the joint.

이와 같이, 제 1 및 제 2 단위 강관 구조체(100, 200)는, 고정 부재(160, 260)를 통해 상호 가결합됨으로써, 조립형 강관(500)을 연장 형성하는 과정에서, 상호 정렬이 비틀어지는 현상을 방지할 수 있으며, 이에 따라, 작업자의 시공상 편의를 제공할 수 있다. As described above, the first and second unit steel pipe structures 100 and 200 are mutually coupled through the fixing members 160 and 260, so that in the process of extending and forming the prefabricated steel pipe 500, the mutual alignment is twisted. The phenomenon can be prevented, and accordingly, it is possible to provide convenience in construction for the operator.

한편, 고정 부재(160, 260)는, 제 1 및 제 2 단위 강관 구조체(100, 200)에 용접되어 결합될 수도 있으며, 제 1 및 제 2 단위 강관 구조체(100, 200)의 크기에 비해 상대적으로 작게 형성함으로써, 용접 면적을 최소화할 수 있다. Meanwhile, the fixing members 160 and 260 may be welded to and coupled to the first and second unit steel pipe structures 100 and 200, relative to the sizes of the first and second unit steel pipe structures 100 and 200. By making it small, it is possible to minimize the welding area.

또한, 고정 부재(160, 260)는, 볼트 체결 방식으로 결합되며, "ㄴ"자 단면을 갖는 브라켓으로 형성될 수도 있으며, 다른 공지의 부재로 형성될 수 있는 바, 이에 제한되지 않는다. In addition, the fixing members 160 and 260 are coupled by a bolt fastening method, and may be formed of a bracket having a “b” cross-section, and may be formed of other known members, but are not limited thereto.

도 5는, 본 발명에 따른 보강 부재의 사시도이며, 제 1 단위 강관 구조체(100)에 결합되어 보강 부재(120)를 전제로 설명을 한다. 5 is a perspective view of a reinforcing member according to the present invention, which is coupled to the first unit steel pipe structure 100 and will be described on the premise of the reinforcing member 120.

도 5를 참조하면, 보강 부재(120)는, 제 1 단위 강관 구조체(100) 내측에 삽입되는 부분(120b) 및 제 2 단위 강관 구조체(200) 내측에 삽입되는 부분(120a)으로 구성되며, 제 2 단위 강관 구조체(200) 내측에 삽입되는 부분(120a)은, 제 1 단위 강관 구조체(100)에 돌출 형성된 부분과 동일하다. 또한, 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)에 각각 구비된 보강 부재(120, 220, 320)는, 단위 강관 구조체의 내면에 결합되는 결합부(120b, 220b, 320b)와 단위 강관 구조체의 내면에 결합된 결합부(120b, 220b, 320b)와 연결되며 결합부(120b, 220b, 320b)로부터 각각 일방향으로 연장되되, 결합부(120b, 220b, 320b)와 연결된 일측부는 단위 강관 구조체 내에 삽입되며, 결합부(120b, 220b, 320b)로부터 이격된 말단부는 단위 강관 구조체 외측으로 돌출 형성되는 삽입부(120a, 220a, 320a), 일방향 또는 일방향의 반대방향을 기준으로 삽입부(120a, 220a, 320a)의 말단에 형성되되, 소정의 곡률을 갖는 곡선 형상으로 형성되어 상기 단위 강관 구조체 수평 단면의 중심 방향으로 절곡된 갈고리 형상인 단부(120c, 220c, 320c)로 구성된다.Referring to FIG. 5, the reinforcing member 120 is composed of a portion 120b inserted inside the first unit steel pipe structure 100 and a portion 120a inserted inside the second unit steel pipe structure 200, The portion 120a inserted into the second unit steel pipe structure 200 is the same as the portion protruding from the first unit steel pipe structure 100. In addition, the reinforcing members 120, 220, and 320 respectively provided in the first to third unit steel pipe structures 100, 200, and 300 are coupled with the inner surfaces of the unit steel pipe structures 120b, 220b, 320b. It is connected to the coupling parts 120b, 220b, 320b coupled to the inner surface of the unit steel pipe structure, and extends in one direction from the coupling parts 120b, 220b, 320b, and one side part connected to the coupling parts 120b, 220b, 320b. Inserted into the steel pipe structure, the distal end spaced apart from the coupling portions 120b, 220b, 320b is the insertion portion 120a, 220a, 320a protruding outward from the unit steel pipe structure, the insertion portion based on one direction or the opposite direction of one direction ( It is formed at the ends of 120a, 220a, 320a), and is formed in a curved shape having a predetermined curvature, and is composed of ends 120c, 220c, 320c, which are hook-shaped curved in the center direction of the horizontal cross section of the unit steel pipe structure.

이 때, 제 2 단위 구조체(200) 내측에 삽입되는 부분의 단부(120c)는 90도로 절곡되는 갈고리 형상이며, 제 1 단위 구조체(100) 내측에 삽입되는 부분에는 제 1 단위 강관 구조체(100)에 결합되는 부분이 형성되고, 제 1 단위 강관 구조체(100)에 결합되는 부분은, 결합을 위해, 다른 부위보다 넓은 면적으로 형성된다.At this time, the end portion 120c of the portion inserted into the second unit structure 200 has a hook shape that is bent at 90 degrees, and the first unit steel pipe structure 100 is inserted into the portion inserted inside the first unit structure 100. The portion to be coupled to is formed, and the portion to be coupled to the first unit steel pipe structure 100 is formed to have a larger area than other parts for bonding.

도 6은, 본 발명에 따른 조립형 강관을 형성하기 위해, 제 1 내지 제 3 단위 강관 구조체를 결합하기 전의 상태를 개략적으로 나타낸 사시도이다. 6 is a perspective view schematically showing a state before combining the first to third unit steel pipe structures in order to form the assembled steel pipe according to the present invention.

도 6을 참조하면, 조립형 강관(500)은, 제 3 단위 강관 구조체(300)를 더 포함하며, 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)가 순서대로 적층된다.Referring to FIG. 6, the prefabricated steel pipe 500 further includes a third unit steel pipe structure 300, and the first to third unit steel pipe structures 100, 200, and 300 are sequentially stacked.

이 때, 제 2 단위 강관 구조체(200)의 보강 부재(220)는, 제 1 및 제 3 단위 강관 구조체(100, 300) 내부로 삽입되도록 형성되며, 제 3 단위 강관 구조체(300)의 보강 부재(320)는, 제 2 단위 강관 구조체(200) 내부로 삽입되도록 형성된다. At this time, the reinforcing member 220 of the second unit steel pipe structure 200 is formed to be inserted into the first and third unit steel pipe structures 100 and 300, and the reinforcing member of the third unit steel pipe structure 300 320 is formed to be inserted into the second unit steel pipe structure 200.

구체적으로, 제 1 내지 제 3 단위 강관 구조체(100, 200, 300) 중 가운데 위치되어 있는 제 2 단위 강관 구조체(200)는 제 1 단위 강관 구조체(100)를 향하여 연장된 보강 부재(220) 및 제 3 단위 강관 구조체(300)를 향하여 연장된 보강 부재(220)를 모두 구비하고 있다. Specifically, the second unit steel pipe structure 200 located in the center among the first to third unit steel pipe structures 100, 200, and 300 includes a reinforcing member 220 extending toward the first unit steel pipe structure 100 and All of the reinforcing members 220 extending toward the third unit steel pipe structure 300 are provided.

도 7은, 본 발명에 따른 조립형 강관을 이용하는 콘크리트 충전형 구조물의시공하는 방법의 순서도이다. 7 is a flowchart of a method for constructing a concrete filled type structure using a prefabricated steel pipe according to the present invention.

도 7을 참조하면, 콘크리트 충전형 구조물의 시공 방법은, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)를 상기 조립형 강관의 연장 방향으로 적층시키는 단계(S10), 상기 제 1 및 제 2 단위 강관 구조체(100, 200)의 외면에 형성되어 있는 고정 부재(160, 260)를 이용하여, 상기 제 1 및 제 2 단위 강관 구조체(100, 200)를 고정시키는 단계(S20), 상기 제 1 및 제 2 단위 강관 구조체(100, 200)로 이루어진 조립형 강관(500) 내부에 콘크리트를 타설하는 단계(S30), 상기 콘크리트를 양생하는 단계(S40) 및 상기 콘크리트의 양생이 종료된 후, 상기 보강 부재(120, 220) 및 상기 단위 강관 구조체(100, 200) 사이를 고정시키고 있는 결합 수단(140, 240)을, 상기 단위 강관 구조체(100, 200)의 외측에서 제거시키는 단계(S50)을 포함한다. Referring to FIG. 7, a method of constructing a concrete-filled structure includes stacking the first and second unit steel pipe structures 100 and 200 in the extending direction of the prefabricated steel pipe (S10), and the first and the first Fixing the first and second unit steel pipe structures 100 and 200 by using fixing members 160 and 260 formed on the outer surfaces of the two unit steel pipe structures 100 and 200 (S20), After pouring concrete into the prefabricated steel pipe 500 made of the first and second unit steel pipe structures 100 and 200 (S30), curing the concrete (S40) and curing of the concrete is completed, Step of removing the coupling means (140, 240) fixing between the reinforcement member (120, 220) and the unit steel pipe structure (100, 200) from the outside of the unit steel pipe structure (100, 200) (S50). It includes.

이 때, 단계(S50)에서, 결합 수단(140, 240)을 제거한 부분에는 별도의 마감 처리를 통해, 결합 수단(140, 240)이 제거된 부분을 보완할 수 있다. At this time, in step (S50), the part from which the coupling means 140 and 240 have been removed may be supplemented by a separate finishing process to remove the coupling means 140 and 240.

이상, 본 명세서에는 본 발명을 당업자가 용이하게 이해하고 재현할 수 있도록 도면에 도시한 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 당업자라면 본 발명의 실시예로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다. 따라서 본 발명의 보호범위는 특허청구범위에 의해서 정해져야 할 것이다. As described above, the present specification has been described with reference to the embodiments shown in the drawings so that those skilled in the art can easily understand and reproduce the present invention, but these are merely exemplary, and those skilled in the art can make various modifications and equivalents from the embodiments of the present invention. It will be understood that embodiments are possible. Therefore, the protection scope of the present invention should be defined by the claims.

10: 주근 100: 제 1 단위 강관 구조체
200: 제 2 단위 강관 구조체 300: 제 3 단위 강관 구조체
120, 220, 320: 보강 부재 140, 240: 결합 수단
160, 260: 고정 부재
10: main root 100: first unit steel pipe structure
200: second unit steel pipe structure 300: third unit steel pipe structure
120, 220, 320: reinforcement member 140, 240: coupling means
160, 260: fixing member

Claims (6)

단위 강관 구조체들이 조립되어 연장되며, 그 내부에 콘크리트가 채워지는 콘크리트 충전형(CFT(Concrete Filled Tube)) 구조물에 사용되는 조립형 강관으로서,
상기 단위 강관 구조체는, 4 면이 형성되어 있는 사각 기둥 형상이며, 내면에 보강 부재가 결합되되, 상기 4 면에 각각 상기 보강 부재가 결합되고,
상기 보강 부재는, 상기 조립형 강관의 연장 방향 또는 그 반대 방향으로 연장되어 상기 단위 강관 구조체에 돌출되도록 형성되며,
상기 단위 강관 구조체는, 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)를 포함하고,
상기 조립형 강관(500)은, 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)를 포함하되, 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)가 순서대로 수직 방향으로 적층되며,
상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)에 각각 구비된 보강 부재(120, 220, 320)는,
상기 단위 강관 구조체의 내면에 결합되는 결합부(120b, 220b, 320b);
상기 단위 강관 구조체의 내면에 결합된 결합부(120b, 220b, 320b)와 연결되며 상기 결합부(120b, 220b, 320b)로부터 각각 일방향으로 연장되되, 상기 결합부(120b, 220b, 320b)와 연결된 일측부는 상기 단위 강관 구조체 내에 삽입되며, 상기 결합부(120b, 220b, 320b)로부터 이격된 말단부는 상기 단위 강관 구조체 외측으로 돌출 형성되는 삽입부(120a, 220a, 320a); 및
상기 일방향 또는 상기 일방향의 반대방향을 기준으로 상기 삽입부(120a, 220a, 320a)의 말단에 형성되되, 소정의 곡률을 갖는 곡선 형상으로 형성되어 상기 단위 강관 구조체 수평 단면의 중심 방향으로 절곡된 갈고리 형상인 단부(120c, 220c, 320c); 로 구성되며,
상기 제 1 단위 강관 구조체(100)의 보강 부재(120)의 일부는, 상기 제 2 단위 강관 구조체(200)에 수직방향으로 내측에 삽입되며,
상기 제 2 단위 강관 구조체(200)의 보강 부재(220)는, 상호 대향하는 방향으로 형성된 한 쌍으로 구비되며,
하방을 향하는 상기 보강 부재(220)의 일부는, 상기 제 1 단위 강관 구조체(100) 내측에 삽입되고, 상방을 향하는 상기 보강 부재(220)의 일부는, 상기 제 3 단위 강관 구조체(300) 내측에 삽입되며,
상기 제 3 단위 강관 구조체(300)의 보강 부재(320)의 일부는, 상기 제 2 단위 강관 구조체(200)와 수직방향으로 내측에 삽입되고,
상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)의 상기 보강 부재(120, 220, 320)들은, 콘크리트에 정착되어, 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)의 이음부의 결합력을 강화하도록 형성되며,
상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)가 서로 접하는 상기 이음부의 외측으로 고정부재가 형성되고,
상기 고정부재는 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)의 상기 이음부의 결합력을 강화하도록 형성되는,
조립형 강관.
The unit steel pipe structures are assembled and extended, and as a prefabricated steel pipe used in a concrete filled tube (CFT) structure filled with concrete therein,
The unit steel pipe structure is a quadrangular pillar shape having four surfaces , and a reinforcement member is coupled to the inner surface, and the reinforcement members are coupled to the four surfaces,
The reinforcing member is formed to extend in the extending direction or the opposite direction of the assembled steel pipe and protrude from the unit steel pipe structure,
The unit steel pipe structure includes first to third unit steel pipe structures 100, 200, and 300,
The assembled steel pipe 500 includes the first to third unit steel pipe structures 100, 200, and 300, in which the first to third unit steel pipe structures 100, 200, and 300 are vertically ordered. Stacked with
Reinforcing members (120, 220, 320) provided on the first to third unit steel pipe structures (100, 200, 300), respectively,
Coupling units (120b, 220b, 320b) coupled to the inner surface of the unit steel pipe structure;
It is connected to the coupling parts 120b, 220b, 320b coupled to the inner surface of the unit steel pipe structure, and extends in one direction from the coupling parts 120b, 220b, 320b, respectively, and is connected to the coupling parts 120b, 220b, 320b. One side portion is inserted into the unit steel pipe structure, the end portion spaced apart from the coupling portion (120b, 220b, 320b) is an insertion portion (120a, 220a, 320a) protruding out of the unit steel pipe structure; And
It is formed at the end of the insertion portion (120a, 220a, 320a) based on the one direction or the opposite direction of the one direction, is formed in a curved shape having a predetermined curvature hook hook in the center direction of the horizontal cross-section of the unit steel pipe structure Shaped ends 120c, 220c, 320c; It consists of,
A part of the reinforcing member 120 of the first unit steel pipe structure 100 is inserted into the second unit steel pipe structure 200 in the vertical direction,
The reinforcing member 220 of the second unit steel pipe structure 200 is provided in a pair formed in opposite directions,
A portion of the reinforcing member 220 facing downward is inserted into the first unit steel pipe structure 100, and a portion of the reinforcing member 220 facing upwards is inside the third unit steel pipe structure 300. Is inserted into,
A part of the reinforcing member 320 of the third unit steel pipe structure 300 is inserted inside the second unit steel pipe structure 200 in the vertical direction,
The reinforcing members 120, 220, and 320 of the first to third unit steel pipe structures 100, 200, 300 are fixed to concrete, and the first to third unit steel pipe structures 100, 200, 300 It is formed to strengthen the bonding force of the joint,
A fixing member is formed outside the joint where the first to third unit steel pipe structures 100, 200 and 300 contact each other,
The fixing member is formed to strengthen the coupling force of the joint of the first to third unit steel pipe structures (100, 200, 300),
Prefabricated steel pipe.
제 1 항에 있어서,
상기 보강 부재(120, 220, 320)는, 결합 수단에 의해 상기 4 면에 각각 결합되도록 형성되고,
상기 결합 수단은, 상기 콘크리트의 양생이 종료된 후, 상기 조립형 강관(500)의 외측에서 제거 가능하도록 형성되는,
조립형 강관.
According to claim 1,
The reinforcing member (120, 220, 320) is formed to be respectively coupled to the four sides by a coupling means,
The coupling means, after curing of the concrete is finished, is formed to be removable from the outside of the assembled steel pipe 500,
Prefabricated steel pipe.
삭제delete 삭제delete 제 1 항에 있어서,
상기 보강 부재(120, 220, 320)의 단부는, 90도 또는 180도로 절곡되는 갈고리 형상인,
조립형 강관.
According to claim 1,
The end of the reinforcing member (120, 220, 320) is a hook shape bent 90 degrees or 180 degrees,
Prefabricated steel pipe.
제 1 항, 제 2 항 및 제 5 항 중 어느 한 항에 따른 조립형 강관을 이용하여, 콘크리트 충전형 구조물의 시공 방법으로서,
(a) 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)를 제 1방향으로 적층시키는 단계;
(b) 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)의 외면에 각각 형성되어 있는 고정 부재를 이용하여, 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)를 고정시키는 단계;
(c) 상기 제 1 내지 제 3 단위 강관 구조체(100, 200, 300)로 이루어진 조립형 강관(500) 내부에 콘크리트를 타설하는 단계;
(d) 상기 콘크리트를 양생하는 단계; 및
(e) 상기 콘크리트의 양생이 종료된 후, 상기 보강 부재(120, 220, 320) 및 상기 단위 강관 구조체(100, 200, 300) 사이를 고정시키고 있는 상기 결합 수단을 상기 단위 강관 구조체(100, 200, 300)의 외측에서 제거시키는 단계; 를 포함하는,
콘크리트 충전형 구조물의 시공 방법.
As a construction method of a concrete-filled structure, using the prefabricated steel pipe according to any one of claims 1, 2, and 5,
(a) stacking the first to third unit steel pipe structures 100, 200 and 300 in a first direction;
(b) fixing the first to third unit steel pipe structures 100, 200 and 300 using fixing members formed on outer surfaces of the first to third unit steel pipe structures 100, 200 and 300, respectively. Letting;
(c) pouring concrete into the assembled steel pipe 500 made of the first to third unit steel pipe structures 100, 200, and 300;
(d) curing the concrete; And
(e) after curing of the concrete is finished, the unit steel pipe structure 100, the coupling means for fixing between the reinforcing members 120, 220, 320 and the unit steel pipe structures 100, 200, 300 200, 300); Containing,
Construction method of concrete-filled structures.
KR1020170090945A 2017-07-18 2017-07-18 Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same KR102088917B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170090945A KR102088917B1 (en) 2017-07-18 2017-07-18 Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170090945A KR102088917B1 (en) 2017-07-18 2017-07-18 Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same

Publications (2)

Publication Number Publication Date
KR20190009452A KR20190009452A (en) 2019-01-29
KR102088917B1 true KR102088917B1 (en) 2020-03-16

Family

ID=65323103

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170090945A KR102088917B1 (en) 2017-07-18 2017-07-18 Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same

Country Status (1)

Country Link
KR (1) KR102088917B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000240156A (en) * 1999-02-23 2000-09-05 Shimizu Corp Joint part structure for building of hybrid structure
JP7116759B2 (en) * 2013-11-04 2022-08-10 アマゾン・テクノロジーズ・インコーポレーテッド Centralized network configuration in distributed system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09291598A (en) * 1996-04-26 1997-11-11 Shimizu Corp Joint structure of filled steel pipe concrete structural body

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000240156A (en) * 1999-02-23 2000-09-05 Shimizu Corp Joint part structure for building of hybrid structure
JP7116759B2 (en) * 2013-11-04 2022-08-10 アマゾン・テクノロジーズ・インコーポレーテッド Centralized network configuration in distributed system

Also Published As

Publication number Publication date
KR20190009452A (en) 2019-01-29

Similar Documents

Publication Publication Date Title
KR101523532B1 (en) Closed steel assembly for column
KR102056406B1 (en) Half pc slab and producing method thereof
CN106759865B (en) A kind of U-shaped steel plate combination beam frame of steel core concrete column-
JP6802646B2 (en) Wall body, wall body construction method and formwork combined wall member
KR101458435B1 (en) Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same
KR102195990B1 (en) Non removing form with double structure and non removing form assembly with insulation inside the same
KR102088917B1 (en) Assembly Type Steel Tube Having a Reinforcing Member Therein and Construction Method of Concrete Filled Tube Structures Using the Same
JP5268470B2 (en) How to lift a rebar basket
JP6428027B2 (en) Column rebar connection panel and rebar structure
CN107859208B (en) Self-resetting high-strength concrete shear wall and manufacturing method thereof
KR101736594B1 (en) Connecting sturcture between column and beam
KR102278450B1 (en) Truss hybrid beam with wide Precast concrete lower flange
KR102085624B1 (en) Connecting structure of Composite column and concrete beam and manufacturing method thereof
KR101297110B1 (en) Concrete filled tube
KR101281320B1 (en) Connectable multi-layer tube and method for connecting the same
CN207829168U (en) The prefabricated overlapping side wall of additional corner diagonal bar and overlapping top plate connecting node
KR101978748B1 (en) Deck Plate With Compression Parts Reinforcement Structure
TWI644006B (en) Seismic reinforcing structure of composite spiral reinforcement and method for producing thereof
JP4044835B2 (en) Junction structure
CN111593846A (en) High-strength thin-wall steel pipe concrete combined column
JP6748914B2 (en) Method of designing joint structure between columns and joint structure between columns
JP6836853B2 (en) Brace joint structure
KR102539498B1 (en) Deck structure and floor structure
KR100660524B1 (en) Reinforcement structure of CFT column and beam setting flat bar in steel pipe
KR102524252B1 (en) High-strength assembly type cft column structure with easy concrete filled

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant