KR102058423B1 - Direct vision type brick wall and construction method thereof - Google Patents

Direct vision type brick wall and construction method thereof Download PDF

Info

Publication number
KR102058423B1
KR102058423B1 KR1020160093210A KR20160093210A KR102058423B1 KR 102058423 B1 KR102058423 B1 KR 102058423B1 KR 1020160093210 A KR1020160093210 A KR 1020160093210A KR 20160093210 A KR20160093210 A KR 20160093210A KR 102058423 B1 KR102058423 B1 KR 102058423B1
Authority
KR
South Korea
Prior art keywords
rail
bricks
bolt
fitted
computer
Prior art date
Application number
KR1020160093210A
Other languages
Korean (ko)
Other versions
KR20180010685A (en
Inventor
최연수
Original Assignee
주식회사 대도벽돌시스템
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 대도벽돌시스템 filed Critical 주식회사 대도벽돌시스템
Priority to KR1020160093210A priority Critical patent/KR102058423B1/en
Publication of KR20180010685A publication Critical patent/KR20180010685A/en
Application granted granted Critical
Publication of KR102058423B1 publication Critical patent/KR102058423B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/14Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element
    • E04B2/16Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element using elements having specially-designed means for stabilising the position
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B1/40
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0243Separate connectors or inserts, e.g. pegs, pins or keys
    • E04B2002/0247Strips or bars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0243Separate connectors or inserts, e.g. pegs, pins or keys
    • E04B2002/0254Tie rods

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Finishing Walls (AREA)

Abstract

본 발명은 투시형 벽돌벽 및 그 시공방법에 관한 것으로, 전산볼트를 연결하는 레일걸림볼트가 상부레일과 하부레일에서 이동 가능하도록 구성됨으로써 원하는 위치에 위치시킬 수 있도록 하고, 상,하로 조적되는 벽돌들의 사이에 고정클립을 설치하여 벽돌들의 유동을 방지하면서 안정적인 시공이 이루어지도록 하는 투시형 벽돌벽 및 그 시공방법을 제공함에 있다.
상기 목적 달성을 위한 본 발명은, 건축물의 상부슬래브 및 하부슬래브에 설치되는 상부레일 및 하부레일; 상기 상,하부레일에 끼워지고 레일의 길이방향을 따라 이동 가능하도록 구성되는 다수의 레일걸림볼트; 상기 레일걸림볼트에 일측단이 체결되어 레일걸림볼트를 상,하부레일에 고정시켜주는 연결너트; 상기 연결너트의 타측단에 체결되어 상,하부레일 사이에 수직하게 설치되는 전산볼트; 상기 전산볼트에 끼워져 높이 방향을 따라 다수단으로 조적되되, 전산볼트에 끼워짐으로써 폭방향으로 이웃하는 벽돌과 이격되도록 시공이 가능한 다수의 벽돌; 상기 전산볼트에 끼워지져 상,하에 위치하는 벽돌들 사이에 개재되도록 설치되되, 벽돌벽의 폭방향으로 연장되도록 설치됨으로써 폭방향으로 이격되는 2개 이상의 벽돌들을 연결해주는 연속형 고정클립; 상기 전산볼트에 끼워지도록 설치되고 상,하에 위치하는 벽돌들 사이에 개재되어 전산볼트에 체결되는 너트에 의해 가압됨으로서 벽돌들을 상하 고정해주는 단독형 고정클립;을 포함하여 구성된 투시형 벽돌벽 및 그 시공방법에 관한 것을 기술적 요지로 한다.
The present invention relates to a see-through brick wall and a construction method thereof, and the rail catching bolts connecting the computer bolts are configured to be movable on the upper rail and the lower rail, so that they can be positioned at a desired position, and the bricks are stacked up and down. By providing a fixed clip between the two to prevent the flow of the bricks to provide a see-through brick wall and a construction method for a stable construction is made.
The present invention for achieving the above object, the upper rail and the lower rail is installed on the upper slab and lower slab of the building; A plurality of rail locking bolts fitted to the upper and lower rails and configured to be movable along a longitudinal direction of the rail; One end is fastened to the rail locking bolts to secure the rail locking bolts to the upper and lower rails; Computed bolt is fastened to the other end of the connection nut is installed vertically between the upper, lower rail; A plurality of bricks which are fitted to the computer bolts and are assembled in a plurality of stages along a height direction, and are constructed to be spaced apart from neighboring bricks in the width direction by being fitted to the computer bolts; A continuous fixing clip fitted to the computer bolt and installed to be interposed between bricks positioned above and below, connecting two or more bricks spaced in the width direction by being installed to extend in the width direction of the brick wall; Perspective-type brick wall and its construction, including; a single fixed clip that is installed to be fitted to the computer bolt and is interposed between the bricks positioned up and down, and is pressed by a nut fastened to the computer bolt to fix the bricks up and down The technical point is about a method.

Description

투시형 벽돌벽 및 그 시공방법{Direct vision type brick wall and construction method thereof}Perspective type brick wall and construction method

본 발명은 투시형 벽돌벽 및 그 시공방법에 관한 것으로, 벽돌을 띄어 쌓기 하여 투시가 가능한 벽돌벽을 형성하되, 상기 벽돌들은 상부레일과 하부레일을 연결하도록 설치되는 전산볼트에 끼워지면서 조적됨으로써 안정적인 벽돌의 지지가 이루어지도록 하는 투시형 벽돌벽 및 그 시공방법에 관한 것이다.The present invention relates to a see-through brick wall and a construction method thereof, while stacking bricks to form a viewable brick wall, the bricks are stable by being fitted while being fitted to a computer bolt installed to connect the upper rail and the lower rail. It relates to a see-through brick wall and a construction method for the support of the brick.

일반적으로 조적식 외부벽돌벽은 벽돌을 모르타르로 점착하여 쌓는 구조로서, 주택이나 창고 및 빌라 등과 같은 건물의 내력벽에서 일정한 간격으로 이격되어 시공되고 내습 및 내구성이 좋으며 내화구조이고 경제적이어서 가장보편적인 방식으로 평가된다.In general, the masonry external brick wall is a structure in which bricks are bonded by mortar, and are spaced at regular intervals from the bearing walls of buildings such as houses, warehouses, and villas, and are constructed with good moisture resistance and durability. Is evaluated.

최근에는 이러한 벽돌을 띄어 쌓기 하여 투시가 이루어지도록 하는 투시형 벽돌벽의 시공이 많이 이루어지고 있다.Recently, many constructions of see-through brick walls are made by stacking such bricks to achieve perspective.

종래의 투시형 벽돌벽은 상부슬래브와 하부슬래브를 연결하는 전산볼트에 벽돌을 끼워 넣어 다수단으로 조적하도록 구성된다.The conventional see-through brick wall is configured to assemble in multiple stages by inserting bricks into a threaded bolt connecting the upper slab and the lower slab.

이러한 종래의 투시형 벽돌벽은 벽돌들을 조적하는 과정에서 전산볼트의 위치가 고정되어 있기 때문에 오차 발생시 이에 대응하지 못해 전산볼트를 다시 설치해야하는 문제점이 있다.Such a conventional see-through brick wall has a problem in that the computer bolts need to be reinstalled because the position of the computer bolts is fixed in the process of stacking the bricks.

또한 상,하로 조적되는 벽돌이 단순히 전산볼트에 끼워진 상태에서 모르타르에 의해 부착되어 고정되기 때문에 구조적으로 상당히 취약한 문제점이 있다.In addition, there is a problem that the structure is vulnerable structurally because it is attached to and fixed by the mortar in the state that the brick is simply assembled in the upper and lower bolts.

등록실용신안공보 제20-0265957호Utility Model Registration No. 20-0265957 공개실용신안공보 제20-2009-0009004호Published Utility Model Publication No. 20-2009-0009004

상기와 같은 문제점을 해결하기 위한 본 발명의 목적은 전산볼트를 연결하는 레일걸림볼트가 상부레일과 하부레일에서 이동 가능하도록 구성됨으로써 원하는 위치에 위치시킬 수 있도록 하고, 상,하로 조적되는 벽돌들의 사이에 고정클립을 설치하여 벽돌들의 유동을 방지하면서 안정적인 시공이 이루어지도록 하는 투시형 벽돌벽 및 그 시공방법을 제공함에 있다.An object of the present invention for solving the above problems is that the rail locking bolt connecting the computer bolt is configured to be movable in the upper rail and the lower rail, so that it can be positioned in a desired position, between the bricks are assembled up and down It is to provide a see-through brick wall and a construction method to ensure a stable construction while preventing the flow of bricks by installing a fixed clip on the.

상기한 바와 같은 목적을 달성하고 종래의 결점을 제거하기 위한 과제를 수행하는 본 발명은, 건축물의 상부슬래브 및 하부슬래브에 설치되는 상부레일 및 하부레일; 상기 상,하부레일에 끼워지고 레일의 길이방향을 따라 이동 가능하도록 구성되는 다수의 레일걸림볼트; 상기 레일걸림볼트에 일측단이 체결되어 레일걸림볼트를 상,하부레일에 고정시켜주는 연결너트; 상기 연결너트의 타측단에 체결되어 상,하부레일 사이에 수직하게 설치되는 전산볼트; 상기 전산볼트에 끼워져 높이 방향을 따라 다수단으로 조적되되, 전산볼트에 끼워짐으로써 폭방향으로 이웃하는 벽돌과 이격되도록 시공이 가능한 다수의 벽돌; 상기 전산볼트에 끼워져 상,하에 위치하는 벽돌들 사이에 개재되도록 설치되되, 벽돌벽의 폭방향으로 연장되도록 설치됨으로써 폭방향으로 이격되는 2개 이상의 벽돌들을 연결해주는 연속형 고정클립; 상기 전산볼트에 끼워지도록 설치되고 상,하에 위치하는 벽돌들 사이에 개재되어 전산볼트에 체결되는 너트에 의해 가압됨으로서 벽돌들을 상하 고정해주는 단독형 고정클립;을 포함하여 구성된 것을 특징으로 한다.The present invention to achieve the object as described above and to perform the problem for eliminating the conventional defects, the upper rail and the lower rail is installed on the upper slab and lower slab of the building; A plurality of rail locking bolts fitted to the upper and lower rails and configured to be movable along a longitudinal direction of the rail; One end is fastened to the rail locking bolts to secure the rail locking bolts to the upper and lower rails; Computed bolts are fastened to the other end of the connection nut is installed vertically between the upper, lower rail; A plurality of bricks which are fitted to the computer bolts and are assembled in a plurality of stages along a height direction, and are constructed to be spaced apart from neighboring bricks in a width direction by being fitted to the computer bolts; A continuous fixing clip inserted into the computer bolt and interposed between bricks positioned above and below, and connected to two or more bricks spaced in the width direction by being installed to extend in the width direction of the brick wall; It is installed so as to be fitted to the computer bolt and is interposed between the bricks located in the upper and lower, by a nut fastened to the computer bolt is fixed by a single fixed clip for fixing the up and down bricks.

또한 상기 상부레일 및 하부레일은, 바닥판과, 상기 바닥판의 양 끝단에서 동일방향을 각각 연장되도록 형성되는 한 쌍의 측면판과, 상기 측면판의 끝단에서 바닥판 방향으로 수평하게 연장되어 상기 레일걸림볼트의 이탈을 방지하는 걸림판으로 이루어진 레일몸체; 상기 레일몸체의 길이방향으로 연속되게 설치되고 상부가 개방되도록 구성되어 상기 레일걸림볼트가 상부레일과 하부레일로 삽입될 수 있는 공간을 제공해주는 소켓;으로 구성된 것을 특징으로 한다.In addition, the upper rail and the lower rail, the bottom plate, a pair of side plates formed to extend in the same direction at each end of the bottom plate, respectively, and extends horizontally in the direction of the bottom plate from the end of the side plate A rail body made of a stopping plate to prevent separation of the rail locking bolts; And a socket that is continuously installed in the longitudinal direction of the rail body and configured to open at an upper portion thereof to provide a space into which the rail locking bolt can be inserted into the upper rail and the lower rail.

또한 상기 레일몸체의 측면판을 관통하도록 설치되어 상부슬래브 및 하부슬래브의 내부에 안정적으로 매설되도록 하는 보강철근;을 더 포함하여 구성된 것을 특징으로 한다.In addition, the reinforcing bars are installed to penetrate the side plate of the rail body to be embedded in the interior of the upper slab and the lower slab; characterized in that it further comprises.

또한 상기 연속형 고정클립은, 상기 전산볼트에 끼워질 수 있도록 폭방향으로 연장되는 슬롯홀이 일정간격으로 형성되고 벽돌벽의 폭방향으로 이격되는 2개 이상의 벽돌들을 연결하여 벽돌들의 유동을 방지해주는 클립몸체; 상기 클립몸체의 가장자리에서 돌출되도록 형성되어 모르타르와의 접착력이 향상될 수 있도록 하는 다수의 돌기부;를 포함하여 구성된 것을 특징으로 한다.In addition, the continuous fixing clip, the slot hole extending in the width direction to be fitted to the computer bolt is formed at a predetermined interval and connects two or more bricks spaced in the width direction of the brick wall to prevent the flow of bricks Clip body; And a plurality of protrusions formed to protrude from the edge of the clip body so that adhesion to the mortar can be improved.

또한 상기 단독형 고정클립은, 일측 가장자리에서 내측방향을 향해 오목한 형태로 형성되는 끼움홈을 통해 전산볼트에 끼워지도록 설치된 후 너트에 의해 고정되는 것을 특징으로 한다.In addition, the single fixed clip is characterized in that it is fixed by a nut after being installed to be fitted to the computer bolt through the fitting groove formed in a concave shape toward the inner side at one edge.

또한 상기 벽돌들 중 상부슬래브와 인접하는 적어도 2단 이상의 벽돌은, 내측에 형성되는 중공과 연결되는 개구부(520)가 측면에 형성되어 개구부(520)를 통해 전산볼트에 측방향으로 끼움 설치되는 것을 특징으로 한다.In addition, at least two or more steps of bricks adjacent to the upper slab among the bricks, the opening 520 is connected to the hollow formed in the side is formed in the side through the opening 520 is inserted into the threaded thread through the opening 520 It features.

한편 본 발명은 상부슬래브 및 하부슬래브의 시공시 상부레일과 하부레일이 매설되도록 시공하는 레일설치단계; 상기 하부레일에 다수의 레일걸림볼트를 끼워 넣고 설계된 위치로 이동시킨 후 연결너트의 일측단을 레일걸림볼트에 체결하여 하부레일에 고정해주는 하측 레일걸림볼트 설치단계; 상기 연결너트의 타측단에 전산볼트를 체결하여 벽돌벽의 높이 방향으로 수직하게 설치하는 전산볼트 설치단계; 상기 전산볼트에 벽돌이 끼워지도록 다수단으로 조적하되 상,하로 조적된 벽돌들 사이에 모르타르를 도포하여 줄눈을 형성하면서 벽돌을 조적하는 벽돌 조적단계; 상기 벽돌을 조적하는 과정에서 일정 간격마다 상, 하로 조적되는 벽돌들 사이에 개재되도록 고정클립을 설치하는 고정클립 설치단계; 상기 상부레일에 레일걸림볼트를 끼워 넣고 연결너트를 이용하여 레일걸림볼트와 상기 벽돌이 끼워지는 전산볼트를 연결해주는 상측 레일걸림볼트 설치단계; 상기 벽돌들을 조적하는 과정에서 상부슬래브와 인접하는 적어도 2단 이상의 벽돌들은 내측에 형성되는 중공과 연결되는 개구부가 형성되도록 구성되며 상기 개구부를 통해 전산볼트에 측방향으로 끼워지도록 설치하는 상부마감단계;를 포함하여 구성된 것을 특징으로 한다.Meanwhile, the present invention provides a rail installation step of constructing the upper rail and the lower rail when the upper slab and the lower slab are constructed; Inserting a plurality of rail locking bolts into the lower rails and moving them to a designed position, and then installing a lower rail locking bolt fixing one end of the connection nut to the rail locking bolts to fix the lower rails to the lower rails; Computing bolt installation step of fastening the bolt to the other end of the connection nut to install vertically in the height direction of the brick wall; Brick masonry step of masonry bricks to form a joint by applying a mortar between the masonry is arranged in a plurality of stages so that the brick is fitted to the computer bolt; Fixing clip installation step of installing a fixing clip so as to be interposed between the bricks are arranged up and down at a predetermined interval in the process of masonry bricks; Installing the upper rail locking bolt to insert the rail locking bolt to the upper rail and connects the rail locking bolt and the computer bolt that the brick is fitted using a connecting nut; At least two steps of the brick adjacent to the upper slab in the process of masonry is configured to form an opening connected to the hollow formed inside the upper finishing step of installing so as to be laterally fitted to the computer bolt through the opening; Characterized in that configured to include.

또한 상기 레일설치단계는, 상기 레일걸림볼트가 끼워지는 레일몸체를 설치하고, 상기 레일걸림볼트가 레일몸체로 삽입될 수 있는 공간을 제공하는 소켓부를 레일몸체의 길이방향에 연속되도록 설치하며, 상기 레일몸체의 폭방향으로 관통되도록 보강철근을 설치하고 상부슬래브와 하부슬래브의 내부에 매설된 철근에 연결하도록 이루어진 것을 특징으로 한다.In addition, the rail installation step, install the rail body is inserted into the rail locking bolt, the socket portion for providing a space for the rail locking bolt can be inserted into the rail body is installed so as to be continuous in the longitudinal direction of the rail body, Reinforcing bars are installed so as to penetrate in the width direction of the rail body, characterized in that made to connect to the reinforcement embedded in the upper slab and the lower slab.

또한 상기 고정클립 설치단계는, 상기 전산볼트에 끼워지도록 설치되어 상,하에 위치하는 벽돌들 사이에 개재되되, 벽돌벽의 폭방향으로 이격되는 2개 이상의 벽돌들을 연결해주는 연속형 고정클립 설치단계와, 상기 전산볼트에 끼워지도록 설치되고 상,하에 위치하는 벽돌들 사이에 개재되되, 전산볼트에 체결되는 너트에 의해 가압됨으로서 벽돌들 고정해주는 단독형 고정클립 설치단계;를 포함하여 구성된 것을 특징으로 한다.In addition, the fixing clip installation step is installed so as to be fitted to the computer bolt is interposed between the bricks located above, below, continuous fixing clip installation step of connecting two or more bricks spaced in the width direction of the brick wall and It is installed so as to be fitted to the computer bolt is interposed between the bricks located in the upper, lower, by the nut is fastened by a nut fastened to the computer bolt fixed fixing installation step for fixing the bricks; .

이상에서 설명한 바와 같이 본 발명에 의하면, 이와 같이 구성되는 본 발명의 투시형 벽돌벽은, 상부슬래브와 하부슬래브에 상부레일과 하부레일을 형성하여 레일걸림볼트를 원하는 위치로 이동시켜 고정이 가능하게 됨으로써 시공성이 매우 뛰어나고 오차에 대해서도 적절하게 대응할 수 있는 효과가 있다.As described above, according to the present invention, the see-through brick wall of the present invention constituted as described above forms an upper rail and a lower rail on the upper slab and the lower slab to move the rail locking bolts to a desired position so that they can be fixed. By doing so, it is very excellent in workability and there exists an effect which can respond suitably also to an error.

또한 레일몸체와 연속되도록 소켓부를 설치하여 레일걸림볼트의 설치가 용이하게 이루어지게 함으로써 시공성이 향상되는 효과가 있다.In addition, by installing the socket portion so as to be continuous with the rail body to facilitate the installation of the rail locking bolt has the effect of improving the workability.

또한 상부레일과 하부레일의 설치시 보강철근을 이용하여 상부슬래브와 하부슬래브에 배근된 철근과 연결되도록 시공함으로써 상부레일과 하부레일의 안정적인 고정이 이루어지는 효과가 있다.In addition, when the upper rail and the lower rail is installed to be connected to the reinforcing bars on the upper slab and the lower slab by using reinforcing bars, the upper rail and the lower rail have a stable fixing effect.

또한 상,하로 위치하는 벽돌들 사이에 연속형 고정클립과 단독형 고정클립을 설치하여 벽돌벽의 폭방향으로 위치하는 벽돌을 잡아줌과 동시에 높이 방향으로 위치하는 벽돌들 까지 가압 고정하여 견고하고 안정적인 벽돌벽의 형성이 가능한 효과가 있는 매우 유용한 발명이다.In addition, a continuous fixed clip and a single fixed clip are installed between the bricks positioned up and down to grab the bricks located in the width direction of the brick wall and at the same time press and fix the bricks located in the height direction to be firm and stable. It is a very useful invention with the effect that the formation of a brick wall is possible.

도 1 은 본 발명에 의한 투시형 벽돌벽을 나타낸 사시도,
도 2 는 본 발명에 의한 투시형 벽돌벽을 나타낸 정면도,
도 3 은 본 발명에 의한 투시형 벽돌벽을 나타낸 측면도,
도 4 는 본 발명에 의한 연속형 고정클립을 나타낸 사시도,
도 5 는 본 발명에 의한 레일에 레일걸림볼트를 결합한 상태를 상세히 나타낸 사시도,
1 is a perspective view showing a perspective brick wall according to the present invention,
Figure 2 is a front view showing a perspective brick wall according to the present invention,
Figure 3 is a side view showing a perspective brick wall according to the present invention,
4 is a perspective view showing a continuous fixing clip according to the present invention,
5 is a perspective view showing in detail the state in which the rail locking bolt is coupled to the rail according to the present invention;

이하 본 발명의 실시 예인 구성과 그 작용을 첨부도면에 연계시켜 상세히 설명하면 다음과 같다. 또한 본 발명을 설명함에 있어서, 관련된 공지기능 혹은 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명은 생략한다.Hereinafter, the configuration and the operation of the embodiments of the present invention will be described in detail with reference to the accompanying drawings. In describing the present invention, when it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description thereof will be omitted.

도 1 은 본 발명에 의한 투시형 벽돌벽을 나타낸 사시도, 도 2 는 본 발명에 의한 투시형 벽돌벽을 나타낸 정면도, 도 3 은 본 발명에 의한 투시형 벽돌벽을 나타낸 측면도, 도 4 는 본 발명에 의한 연속형 고정클립을 나타낸 사시도, 도 5 는 본 발명에 의한 레일에 레일걸림볼트를 결합한 상태를 상세히 나타낸 사시도로서,1 is a perspective view showing a perspective brick wall according to the present invention, FIG. 2 is a front view showing a perspective brick wall according to the present invention, FIG. 3 is a side view showing a perspective brick wall according to the present invention, and FIG. 5 is a perspective view illustrating a state in which a rail locking bolt is coupled to a rail according to the present invention in detail.

도면에서와 같이 본 발명의 투시형 벽돌벽(10)은, 상부슬래브(30)와 하부슬래브(20)에 설치되는 상부레일(100b) 및 하부레일(100a)과, 상기 상,하부레일(100b)(100a)에 끼워지고 레일의 길이방향을 따라 이동 가능하도록 구성되는 다수의 레일걸림볼트(200)와, 상기 레일걸림볼트(200)에 일측단이 체결되어 레일걸림볼트(200)를 상, 하부레일(100b)(100a)에 고정시켜주는 연결너트(300)와, 상기 연결너트(300)의 타측단에 체결되어 상, 하부레일(100b)(100a) 사이에 수직하게 설치되는 전산볼트(400)와, 상기 전산볼트(400)에 끼워져 높이 방향을 따라 다수단으로 조적되되, 전산볼트(400)에 끼워짐으로써 폭 방향으로 이웃하는 다른 벽돌(500)들과 이격되도록 시공이 가능한 다수의 벽돌(500)과, 상기 전산볼트(400)에 끼워지도록 설치되어 상, 하에 위치하는 벽돌(500) 사이에 개재되도록 위치하되, 벽돌벽(10)의 폭방향으로 연장되도록 설치됨으로써 폭방향으로 이격되도록 조적되는 2개 이상의 벽돌(500)을 연결하여 일체로 형성되는 연속형 고정클립(600)과, 상기 전산볼트(400)에 끼워지도록 설치되고 상,하에 위치하는 벽돌(500)들 사이에 개재되어 전산볼트(400)에 체결되는 너트(310)에 의해 가압됨으로서 벽돌(500)들을 상하방향으로 고정해주는 단독형 고정클립(700)을 포함하여 구성된다.As shown in the drawing, the perspective brick wall 10 of the present invention includes an upper rail 100b and a lower rail 100a installed on the upper slab 30 and the lower slab 20, and the upper and lower rails 100b. One side end is fastened to the rail locking bolt 200 and the rail locking bolt 200 is configured to be movable in the longitudinal direction of the rail (100a) and the rail locking bolt 200, The connection nut 300 fixed to the lower rails 100b and 100a and a computer bolt which are fastened to the other end of the connection nut 300 and vertically installed between the upper and lower rails 100b and 100a. 400 and a plurality of steps that are fitted to the threaded bolt 400 and assembled in multiple stages along the height direction, and are fitted to the threaded bolt 400 so that a plurality of constructions can be spaced apart from neighboring bricks 500 in the width direction. Installed to be fitted to the brick 500 and the computer bolt 400, so as to be interposed between the brick 500 located above, below Positioned, but is installed so as to extend in the width direction of the brick wall 10 by connecting two or more bricks 500 to be assembled to be spaced apart in the width direction continuous fixed clip 600 and integrally formed with the computer bolt ( It is installed to be fitted to 400 and is interposed between the bricks 500 located in the upper and lower, and is fixed by a single type fixed by fixing the bricks 500 in the vertical direction by being pressed by a nut 310 fastened to the computer bolt 400 And a clip 700.

상기 상부레일(100b)과 하부레일(100a)은 상부슬래브(30)와 하부슬래브(20)의 시공시 미리 매립되도록 설치되는 것으로, 내부 공간을 끼워지는 레일걸림볼트(200)의 이동이 가능하도록 구성되는 것으로, 레일걸림볼트(200)가 걸려져 이동가능하도록 구성되는 레일몸체(110)와, 상기 레일몸체(110)의 길이방향에서 연속되도록 설치되어 상기 레일걸림볼트(200)가 레일몸체(110)의 내측으로 삽입될 수 있는 공간을 제공하는 소켓(120)을 포함하여 구성된다.The upper rail 100b and the lower rail 100a are installed to be buried in advance when the upper slab 30 and the lower slab 20 are constructed, so that the rail catching bolt 200 fitted with the inner space can be moved. The rail locking bolt 200 is configured to be caught and movable by the rail locking bolt 200, and the rail locking bolt 200 is installed to be continuous in the longitudinal direction of the rail body 110. It is configured to include a socket 120 that provides a space that can be inserted into the inside of 110.

상기 레일몸체(110)는, 바닥판(111)과, 상기 바닥판(111)의 양 끝단에서 동일방향으로 각각 연장되도록 형성되는 한 쌍의 측면판(112)과, 상기 측면판(112)의 끝단에서 바닥판(111) 방항으로 수평하게 연장되어 상기 레일걸림볼트(200)의 두부(210)가 걸려지게 되는 걸림판(113)을 포함하여 구성된다.The rail body 110, the bottom plate 111, a pair of side plates 112 formed to extend in the same direction at each end of the bottom plate 111, and the side plate 112 of It is configured to include a locking plate 113 that extends horizontally from the end to the bottom plate 111 in the direction that the head 210 of the rail locking bolt 200 is caught.

한편 상기 소켓(120)은 바닥판(121)과 상기 바닥판(121)의 양측면에서 동일방향으로 각각 연장되도록 형성되는 한 쌍의 측면판(112)으로 이루어져 레일걸림볼트(200)가 레일몸체(110)의 내측으로 끼워질 수 있는 공간을 제공하는 것이다.Meanwhile, the socket 120 includes a pair of side plates 112 formed to extend in the same direction on both bottom surfaces of the bottom plate 121 and the bottom plate 121, respectively. It is to provide a space that can be fitted into the inside of (110).

즉 상기 레일걸림볼트(200)는 두부(210)가 걸림판(113) 보다 크게 형성되기 때문에 레일몸체(110)의 내측 공간으로 직접적으로 삽입될 수가 없어 상기 소켓(120)을 통해 레일걸림볼트(200)의 두부(210)를 삽입한 후 레일몸체(110)의 내측 공간으로 끼워넣음으로써 설치가 가능하게 되는 것이다.That is, the rail locking bolts 200 are larger than the locking plate 113, so that the head locking bolts 200 may not be directly inserted into the inner space of the rail body 110, and thus the rail locking bolts may be inserted through the sockets 120. After inserting the head 210 of the 200 is inserted into the inner space of the rail body 110 it is possible to install.

한편 상기 레일몸체(110)에는 레일몸체(110)의 측면판(112)을 관통하도록 설치되어 상부슬래브(30)와 하부슬래브(20)의 내부에 매설된 철근(40)과 연결될 수 있도록 하여 상부레일(100b)과 하부레일(100a)의 안정적인 고정이 가능하도록 하는 보강철근(130)이 더 설치된다.Meanwhile, the rail body 110 is installed to penetrate the side plate 112 of the rail body 110 so as to be connected to the reinforcing bar 40 embedded in the upper slab 30 and the lower slab 20. Reinforcing bars 130 are further installed to enable stable fixing of the rail 100b and the lower rail 100a.

상기 보강철근(130)은 절곡부(131)를 형성하여 절곡부(131)를 기준으로 일측단은 상부슬래브(30) 및 하부슬래브(20)의 내부에 배근된 철근(40)의 상부로 배근되고 타측은 하부로 배근되어 연결됨으로써 보다 견고한 이음 시공이 이루질 수 있도록 한다.The reinforcing bar 130 forms the bent portion 131 so that one side end of the bent portion 131 is placed on the upper side of the reinforcing bar 40 arranged in the upper slab 30 and the lower slab 20. And the other side is connected to the lower side to make a more firm joint construction.

한편 상기 연결너트(300)는 통상의 너트보다 길게 형성되고 내부에 나사산이 형성되어 양측으로 볼트의 체결이 가능하도록 구성되며 내부 중심에는 공간을 구획하는 걸림턱(도시없음)이 형성되어 양측으로 체결되는 볼트들이 일정한 깊이까지만 삽입되어 체결될 수 있도록 구성된다.On the other hand, the connection nut 300 is formed longer than the usual nut, and the thread is formed therein so that the bolts can be fastened to both sides, and a locking jaw (not shown) is formed at the inner center to fasten to both sides. The bolts are configured to be inserted and fastened only to a certain depth.

또한 상기 연결너트(300)를 이용하여 레일걸림볼트(200)를 고정할 경우 와셔(220)를 매개로 하여 레일걸림볼트(200)의 결합력을 보다 증가시킬 수 있도록 한다.In addition, when fixing the rail locking bolt 200 by using the connection nut 300 to increase the coupling force of the rail locking bolt 200 via the washer 220.

상기 벽돌(500)은 내부에 다수의 중공(510)이 형성되도록 구성되는 통상의 벽돌로 구성할 수 있다.The brick 500 may be formed of a conventional brick configured to form a plurality of hollows 510 therein.

또한 상기 벽돌(500)은, 상부슬래브(30)와 인접하는 적어도 2단 이상의 벽돌은 내측에 형성되는 중공(510)과 연결되는 개구부(520)가 형성되어 상기 개구부(520)를 통해 전산볼트(400)에 측방향으로 끼움 결합될 수 있도록 구성된다.In addition, the brick 500, the at least two or more stages adjacent to the upper slab 30 is formed with an opening 520 connected to the hollow 510 is formed inside the computer bolt through the opening 520 ( 400 is configured to be coupled to the sideways.

즉 벽돌벽(10)의 최상단을 시공할 경우 전산볼트(400)가 연결너트(300)에 의해 상부레일(100b)에 설치되는 레일걸림볼트(200)에 체결되기 때문에 벽돌을 수직하게 끼워 넣을 수가 없어 벽돌(500)의 측면에 개구부(520)를 형성하여 벽돌(500)을 측면으로 끼움 결합할 수 있도록 구성하는 것이다.That is, when constructing the top end of the brick wall 10, the threaded bolt 400 is fastened to the rail catching bolt 200 installed on the upper rail 100b by the connecting nut 300, so that the brick can be inserted vertically. Without forming the opening 520 on the side of the brick 500 is to configure the brick 500 to be fitted to the side.

한편 상기 개구부(520)는 중공의(510) 중심을 기준으로 일측에 위치하도록 형성하여 벽돌(500)을 전산볼트(400)에 끼워 넣은 상태에서 벽돌(500)을 이동시키면 벽돌(500)의 중공(510) 내면에 전산볼트(400)가 걸려짐으로써 벽돌(500)이 이탈되지 않고 안정적인 시공이 가능하게 된다.On the other hand, the opening 520 is formed so as to be located on one side with respect to the center of the hollow 510 to move the brick 500 in a state in which the brick 500 is inserted into the computational bolt 400 to hollow the brick 500. Since the computational bolt 400 is hung on the inner surface of the wall 510, the stable construction can be performed without leaving the brick 500.

한편 상기 연속형 고정클립(600)은 상기 전산볼트(400)에 끼워지도록 설치되고 벽돌벽(10)의 폭방향으로 이격되는 2개 이상의 벽돌(500)들을 연결하여 벽돌(500)들을 일체화시켜 유동을 방지하는 클립몸체(610)와, 상기 클립몸체(610)의 가장자리에서 돌출되도록 형성되어 벽돌(500)을 조적하는 과정에서 도포되는 모르타르(530)와의 부착력이 증가되도록 하는 다수의 돌기부(620)를 포함하여 구성된다.Meanwhile, the continuous fixing clip 600 is installed to be fitted to the computer bolt 400 and connects two or more bricks 500 spaced apart in the width direction of the brick wall 10 to integrate the bricks 500 to flow. A plurality of protrusions 620 formed to protrude from the edge of the clip body 610 to prevent the plurality of protrusions 620 is formed so as to increase the adhesion force with the mortar 530 applied in the process of masonry 500 It is configured to include.

상기 클립몸체(610)는 상기 전산볼트(400)가 끼워질 수 있도록 형성되되, 클립몸체(610)의 설치위치 조절 및 오차에 대응할 수 있도록 클립몸체(610)의 폭방향으로 연장되는 슬롯홀(611)이 형성되어 있다.The clip body 610 is formed so that the computer bolt 400 can be fitted, the slot hole extending in the width direction of the clip body 610 to cope with the installation position adjustment and error of the clip body 610 ( 611 is formed.

한편 상기 단독형 고정클립(700)은 일측 가장자리에서 내측방향을 향해 오목한 형태로 형성되는 끼움홈(710)을 통해 전산볼트(400)에 끼워지도록 설치되고 너트(310)에 의해 가압되어 높이 방향으로 조적되는 벽돌(500)들이 견고하게 고정될 수 있도록 하는 것이다.Meanwhile, the single fixed clip 700 is installed to be fitted to the computer bolt 400 through a fitting groove 710 formed in a concave shape from one side edge toward the inner side, and is pressed by the nut 310 in the height direction. The bricks 500 to be stacked are to be firmly fixed.

한편 상기 너트(310)는 통상의 너트를 이용하여 단독형 고정클립(700)을 가압할 수 도 있고, 상기 연결너트(300)를 통해서도 단독형 고정클립(700)을 가압 고정할 수 있게 된다.On the other hand, the nut 310 may pressurize the single fixed clip 700 by using a conventional nut, it is also possible to pressure-fix the single fixed clip 700 through the connection nut 300.

이와 같이 구성되는 단독형 고정클립(700)은 상기 끼움홈(710)을 통해 전산볼트(400)의 측면에서 끼움 시공이 가능하게 되어 간편하고 빠른 시공이 이루어질 수 있도록 한다.The single fixed clip 700 configured as described above can be fitted at the side of the computational bolt 400 through the fitting groove 710 to enable simple and quick construction.

이와 같이 구성되는 본 발명의 투시형 벽돌벽의 시공과정을 설명하면, 먼저 상부슬래브(30) 및 하부슬래브(20)의 시공시 상기 상부레일(100b)과 하부레일(100a)을 미리 매설되도록 한 상태에서 상부슬래브(30)와 하부슬래브(20)를 시공하는 레일설치단계와, 상기 하부레일(100a)에 다수의 레일걸림볼트(200)를 끼워 넣고 설계된 위치로 이동시킨 후 연결너트(300)의 일측단을 레일걸림볼트(200)에 체결하여 하부레일(100a)에 고정해주는 하측 레일걸림볼트 설치단계와, 상기 연결너트(300)의 타측단에 전산볼트(400)를 체결하여 벽돌벽(10)의 높이 방향으로 수직하게 설치하는 전산볼트 설치단계와, 상기 전산볼트(400)에 벽돌이 끼워지도록 다수단으로 조적하되 상, 하로 조적된 벽돌(500)들 사이에 모르타르(530)를 도포하여 줄눈을 형성하면서 벽돌(500)을 조적하는 벽돌 조적단계와, 상기 벽돌(500)을 조적하는 과정에서 일정 간격마다 상, 하로 조적되는 벽돌(500)들 사이에 개재되도록 고정클립을 설치하는 고정클립 설치단계와, 상기 상부레일(100b)에 레일걸림볼트(200)를 끼워 넣고 연결너트(300)를 이용하여 레일걸림볼트(200)와 상기 벽돌(500)이 끼워지는 전산볼트(400)를 연결해주는 상측 레일걸림볼트 설치단계와, 상기 벽돌(500)들의 조적하는 과정에서 상부슬래브(30)와 인접하는 적어도 2단 이상의 벽돌(500)들은 내측에 형성되는 중공(510)과 연결되는 개구부(520)가 형성되도록 구성되며 상기 개구부(520)를 통해 전산볼트(400)에 측방향으로 끼워지도록 설치하는 상부마감단계를 포함하여 구성된다.Referring to the construction process of the see-through brick wall of the present invention configured as described above, when the upper slab 30 and the lower slab 20 is constructed, the upper rail 100b and the lower rail 100a are buried in advance. Rail installation step of constructing the upper slab 30 and the lower slab 20 in the state, and inserting a plurality of rail locking bolts 200 to the lower rail (100a) to move to the designed position connecting nut 300 Fastening one side end of the rail fastening bolt 200 to the lower rail locking bolt installation step of fixing to the lower rail (100a), and fastening the computer bolt 400 to the other end of the connecting nut 300 brick wall ( 10) and the computer bolt installation step to install vertically in the height direction, and the mortar 530 is applied between the bricks 500, the upper and lower masonry is installed in a plurality of stages so that the brick is fitted to the computer bolt 400. Brick masonry to masonry 500 while forming a joint Steps, and a fixed clip installation step of installing a fixed clip so as to be interposed between the bricks 500 to be assembled up and down at a predetermined interval in the process of masonry 500, and rail fastening to the upper rail (100b) Inserting the bolt 200 and using the connection nut 300, the rail mounting bolt 200 and the upper rail locking bolt installation step for connecting the computer bolt 400 is fitted into the brick 500, and the brick 500 ), At least two or more steps of bricks 500 adjacent to the upper slab 30 are configured to form an opening 520 connected to the hollow 510 formed therein, and through the opening 520. It is configured to include a top closing step to be installed to be laterally inserted into the computational bolt (400).

상기 레일설치단계는, 상부슬래브(30)와 하부슬래브(20)의 콘크리트 타설시 설계된 위치에 레일몸체(110)와 소켓(120)을 미리 설치한 후 콘크리트를 타설하는 과정이다.The rail installation step is a process of placing concrete after installing the rail body 110 and the socket 120 in advance at the position of the concrete slab of the upper slab 30 and the lower slab 20.

즉 상부레일(100b)과 하부레일(100a)은 상부슬래브(30)와 하부슬래브(20)의 시공시 미리 설치해 놓는 것이다.That is, the upper rail (100b) and the lower rail (100a) is installed in advance when the construction of the upper slab 30 and the lower slab 20.

또한 상기 상부레일(100b)과 하부레일(100a)의 레일몸체(110)를 관통하도록 설치되고 상부슬래브(30)와 하부슬래브(20)의 내부에 배근되는 철근(40)에 연결되도록 보강철근(130)을 더 설치하여 시공할 수 있다.In addition, the reinforcing bar is installed to penetrate the rail body 110 of the upper rail (100b) and the lower rail (100a) and connected to the reinforcing bar (40) that is reinforced inside the upper slab (30) and the lower slab (20). 130) can be installed by installing more.

한편 상기 하측 레일걸림볼트 설치단계는, 소켓(120)을 통해 레일걸림볼트(200)의 두부(210)를 끼워 넣은 상태에서 소켓(120)에 연속되도록 설치된 레일몸체(110)의 내부 공간으로 레일걸림볼트(200)를 이동시키고 설계된 위치에서 연결너트(300)를 이용하여 고정시켜주는 과정이다.On the other hand, the lower rail locking bolt installation step, the rail into the inner space of the rail body 110 installed to be continuous to the socket 120 in the state in which the head 210 of the rail locking bolt 200 is inserted through the socket 120 The locking bolt 200 is moved and fixed using the connection nut 300 at the designed position.

이때 상기 레일걸림볼트(200)와 연결너트(300) 사이에는 와셔(220)를 개재하여 결합력을 향상시켜준다.At this time, between the rail locking bolt 200 and the connection nut 300 to improve the coupling force through the washer 220.

상기 전산볼트 설치단계는 상기 연결너트(300)에 전산볼트(400)를 체결하여 벽돌(500)의 끼움 시공이 이루어질 수 있도록 준비하는 과정이다.The computer bolt installation step is a process of preparing the fitting construction of the brick 500 by fastening the computer bolt 400 to the connection nut 300.

이때 투시형 벽돌벽(10)의 높이에 따라 상기 전산볼트(400)는 다수의 연결너트(300)를 통해 이음 시공하여 벽돌벽(10)의 높이 방향으로 설치될 수 있도록 한다.At this time, according to the height of the see-through brick wall 10, the computer bolt 400 is to be installed in the height direction of the brick wall 10 by the joint construction through a plurality of connection nuts (300).

한편 상기 벽돌 조적단계는 벽돌(500)에 형성되어 있는 중공(510)을 통해 상기 전산볼트(400)에 끼워지도록 하면서 벽돌(500)을 조적하는 과정이다.The brick masonry step is a process of masonry brick 500 while being fitted to the computer bolt 400 through the hollow 510 formed in the brick 500.

이때 상기 벽돌(500)들은 영롱쌓기(띄어쌓기) 형태로 벽돌벽(10)의 폭방향으로 이웃하는 벽돌(500)과 이격되도록 하여 시공할 수 있다.In this case, the bricks 500 may be constructed to be spaced apart from neighboring bricks 500 in the width direction of the brick wall 10 in the form of a zero stack.

한편 상기 고정클립 설치단계는, 상기 전산볼트(400)에 끼워지도록 설치되어 상,하에 위치하는 벽돌(500)들 사이에 상기 연속형 고정클립(600)을 개재되도록 설치하여 벽돌벽(10)의 폭방향으로 이격되는 2개 이상의 벽돌(500)들을 연결해주는 연속형 고정클립(600)을 설치하는 연속형 고정클립 설치단계와, 상기 전산볼트(400)에 끼워지도록 설치되고 상,하에 위치하는 벽돌(500)들 사이에 개재되는 단독형 고정클립(700) 설치하여 전산볼트(400)에 체결되는 너트(310)에 의해 가압됨으로서 벽돌(500)들 고정해주는 단독형 고정클립 설치단계를 포함하여 구성된다.On the other hand, the fixing clip installation step is installed so as to be fitted to the computer bolt 400 is installed so as to interpose the continuous fixed clip 600 between the bricks 500 located above and below the brick wall 10 of the Continuous fixed clip installation step of installing a continuous fixed clip 600 connecting the two or more bricks 500 spaced apart in the width direction, and the brick is installed to be fitted to the threaded bolt 400, located above and below It comprises a single fixed clip installation step for fixing the bricks 500 by being pressed by a nut 310 fastened to the computer bolt 400 by installing a single fixed clip 700 interposed between the 500 (500). do.

한편 상측 레일걸림볼트 설치단계는, 상부레일(100b)에 레일걸림볼트(200)를 설치하고 연결너트(300)를 이용하여 상기 전산볼트(400)를 연결해줌으로써 전산볼트(400)의 양단이 상, 하부레일(100a)에 연결되어 고정되도록 하는 과정이다.Meanwhile, in the step of installing the upper rail locking bolts, the rail locking bolts 200 are installed on the upper rails 100b and the connecting bolts 300 are connected to each other to connect the threaded bolts 400 to each other. It is a process of being connected and fixed to the lower rail 100a.

이때 설치되는 레일걸림볼트(200) 또한 소켓(120)을 통해 레일몸체(110)의 내부공간으로 진입하여 레일몸체(110)에 걸려지게 되고 연결너트(300)에 의해 고정되는 것이다.At this time, the rail locking bolt 200 is also installed to enter the inner space of the rail body 110 through the socket 120 is caught by the rail body 110 and is fixed by the connection nut 300.

한편 상기 상부마감단계는 최상단에 끼워지는 벽돌은 상기 전산볼트(400)가 상부레일(100b)에 연결되도록 설치되기 때문에 전산볼트(400)에 수직하게 끼워질 수가 없어서, 벽돌(500)의 중공(510)에 연결되는 개구부(520)를 형성하여 전산볼트(400)에 측방향으로 끼워지도록 설치하는 과정이다.On the other hand, the upper closing step is because the brick is fitted to the top end is installed so that the computer bolt 400 is connected to the upper rail (100b) can not be fitted vertically to the computer bolt 400, the hollow of the brick (500) Forming the opening 520 connected to the 510 is a process of installing so as to be laterally fitted to the computer bolt (400).

한편 본 발명은 상기 상부레일(100b)과 하부레일(100a)의 내부에 모르타르(530)를 주입하여 레일걸림볼트(200)가 완전히 고정되도록 하는 모르타르 주입단계를 더 포함하여 구성할 수 있다.Meanwhile, the present invention may further include a mortar injection step of injecting a mortar 530 into the upper rail 100b and the lower rail 100a to completely fix the rail catching bolt 200.

즉 상부레일(100b)과 하부레일(100a)의 내부에 모르타르(530)를 주입함으로서 레일걸림볼트(200)가 레일상에서 유동되는 것을 완전히 차단하여 설계된 위치에 보다 견고하게 고정될 수 있도록 하는 것이다.That is, by injecting mortar 530 into the upper rail 100b and the lower rail 100a, the rail locking bolt 200 is completely blocked from flowing on the rail so as to be more firmly fixed at the designed position.

또한 상기 전산볼트(400)가 끼워지는 벽돌(500)의 중공(510)에는 모르타르(530)를 주입하여 벽돌이 전산볼트(400)와 벽돌(500)이 일체가 되도록 함으로써 벽돌(500)의 비들림이나 유동을 방지한다.In addition, the mortar 530 is injected into the hollow 510 of the brick 500 to which the threaded bolt 400 is inserted, thereby allowing the brick to be integral with the threaded bolt 400 and the brick 500. Prevent lift or flow.

이와 같이 구성되는 본 발명의 투시형 벽돌벽(10)은, 상부슬래브(30)와 하부슬래브(20)에 상부레일(100b)과 하부레일(100a)을 형성하여 레일걸림볼트(200)를 원하는 위치로 이동시켜 고정이 가능하게 됨으로써 시공성이 매우 뛰어나고 오차에 대해서도 적절하게 대응할 수 있게 된다.Perspective brick wall 10 of the present invention configured as described above, the upper rail (30) and the lower slab 20 to form the upper rail (100b) and the lower rail (100a) desired rail locking bolt 200 By being able to move to a position and fixing it, the workability is very excellent and the error can be properly responded to.

또한 레일몸체(110)와 연속되도록 소켓(120)을 설치하여 레일걸림볼트(200)의 설치가 용이하게 이루어지게 함으로써 시공성이 향상된다.In addition, by installing the socket 120 so as to be continuous with the rail body 110 to facilitate the installation of the rail locking bolts 200, the construction is improved.

또한 상부레일(100b)과 하부레일(100a)의 설치시 보강철근을 이용하여 상부슬래브(30)와 하부슬래브(20)에 배근된 철근과 연결되도록 시공함으로써 상부레일(100b)과 하부레일(100a)의 안정적인 고정이 이루어지게 된다.In addition, when installing the upper rail (100b) and the lower rail (100a) by using a reinforcing steel bar to be connected to the reinforcing bar reinforcement on the upper slab 30 and the lower slab 20 by the upper rail (100b) and lower rail (100a) ) Stable fixing is achieved.

또한 상,하로 위치하는 벽돌들 사이에 연속형 고정클립(600)과 단독형 고정클립(700)을 설치하여 벽돌벽(10)의 폭방향으로 위치하는 벽돌을 잡아줌과 동시에 높이 방향으로 위치하는 벽돌들 까지 가압 고정하여 견고하고 안정적인 벽돌벽의 형성이 가능하게 된다.In addition, by installing a continuous fixed clip 600 and a single fixed clip 700 between the bricks positioned up and down, while holding the bricks located in the width direction of the brick wall 10 while being positioned in the height direction By pressing and fixing the bricks, it is possible to form a solid and stable brick wall.

본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. Of course, such changes will fall within the scope of the claims.

(10) : 벽돌벽 (20) : 하부슬래브
(30) : 상부슬래브 (100a) : 하부레일
(40) : 철근 (100b) : 상부레일
(110) : 레일몸체 (111) : 바닥판
(112) : 측면판 (113) : 걸림판
(120) : 소켓 (121) : 바닥판
(122) : 측면판 (130) : 보강철근
(131) : 절곡부 (200) : 레일걸림볼트
(210) : 두부 (220) : 와셔
(300) : 연결너트 (310) : 너트
(400) : 전산볼트 (500) : 벽돌
(510) : 중공 (520) : 개구부
(530) : 모르타르 (600) : 연속형 고정클립
(610) : 클립몸체 (611) : 슬롯홀
(620) : 돌기부 (700) : 단독형 고정클립
(710) : 끼움홈 (800) : 모르타르
(10): brick wall (20): lower slab
(30): upper slab (100a): lower rail
40: rebar 100b: upper rail
110: rail body 111: bottom plate
(112): side plate 113: locking plate
120: socket 121: bottom plate
(122): side plate 130: rebar
(131): bend portion (200): rail locking bolt
(210): tofu 220: washers
(300): Connection nut (310): Nut
(400): Computer bolt (500): Brick
510: hollow 520: opening
(530): Mortar (600): Continuous fixed clip
(610): Clip body (611): Slotted hole
(620): protrusion (700): single fixed clip
(710): Fit Home (800): Mortar

Claims (9)

건축물의 상부슬래브 및 하부슬래브에 설치되는 상부레일 및 하부레일;
상기 상,하부레일에 끼워지고 레일의 길이방향을 따라 이동 가능하도록 구성되는 다수의 레일걸림볼트;
상기 레일걸림볼트에 일측단이 체결되어 레일걸림볼트를 상,하부레일에 고정시켜주는 연결너트;
상기 연결너트의 타측단에 체결되어 상,하부레일 사이에 수직하게 설치되는 전산볼트;
상기 전산볼트에 끼워져 높이 방향을 따라 다수단으로 조적되되, 전산볼트에 끼워짐으로써 폭방향으로 이웃하는 벽돌과 이격되도록 시공이 가능한 다수의 벽돌;
상기 전산볼트에 끼워져 상,하에 위치하는 벽돌들 사이에 개재되도록 설치되되, 벽돌벽의 폭방향으로 연장되도록 설치됨으로써 폭방향으로 이격되는 2개 이상의 벽돌들을 연결해주는 연속형 고정클립;
상기 전산볼트에 끼워지도록 설치되고 상,하에 위치하는 벽돌들 사이에 개재되어 전산볼트에 체결되는 너트에 의해 가압됨으로서 벽돌들을 상하 고정해주는 단독형 고정클립;을 포함하여 구성되고,
상기 상부레일 및 하부레일은, 바닥판과, 상기 바닥판의 양 끝단에서 동일방향을 각각 연장되도록 형성되는 한 쌍의 측면판과, 상기 측면판의 끝단에서 바닥판 방향으로 수평하게 연장되어 상기 레일걸림볼트의 이탈을 방지하는 걸림판으로 이루어진 레일몸체와, 상기 레일몸체의 길이방향으로 연속되게 설치되고 바닥판과 상기 바닥판의 양측면에서 동일방향으로 각각 연장되도록 형성되는 한 쌍의 측면판으로 이루어져 상부가 개방되도록 구성되어 상기 레일걸림볼트가 상부레일과 하부레일로 삽입될 수 있는 공간을 제공해주는 소켓으로 구성되고,
상기 연속형 고정클립은, 상기 전산볼트에 끼워질 수 있도록 폭방향으로 연장되는 슬롯홀이 일정간격으로 형성되고 벽돌벽의 폭방향으로 이격되는 2개 이상의 벽돌들을 연결하여 벽돌들의 유동을 방지해주는 클립몸체와, 상기 클립몸체의 가장자리에서 돌출되도록 형성되어 모르타르와의 접착력이 향상될 수 있도록 하는 다수의 돌기부;를 포함하여 구성된 것을 특징으로 하는 투시형 벽돌벽.
An upper rail and a lower rail installed on the upper slab and the lower slab of the building;
A plurality of rail locking bolts fitted to the upper and lower rails and configured to be movable along a longitudinal direction of the rail;
One end is fastened to the rail locking bolts to secure the rail locking bolts to the upper and lower rails;
Computed bolts are fastened to the other end of the connection nut is installed vertically between the upper, lower rail;
A plurality of bricks which are fitted to the computer bolts and are assembled in a plurality of stages along a height direction, and are constructed to be spaced apart from neighboring bricks in a width direction by being fitted to the computer bolts;
A continuous fixing clip fitted to the computer bolt and interposed between bricks positioned above and below, and connected to two or more bricks spaced in the width direction by being installed to extend in the width direction of the brick wall;
It is installed to be fitted to the threaded bolt and is interposed between the bricks located in the upper, lower, and is fixed by a nut fixed to the threaded bolt by a single fixed clip for fixing the top and bottom;
The upper rail and the lower rail, a bottom plate, a pair of side plates formed to extend in the same direction at both ends of the bottom plate, respectively, and extends horizontally in the direction of the bottom plate from the end of the side plate the rail Rail body consisting of a locking plate to prevent the separation of the locking bolt and a pair of side plates that are continuously installed in the longitudinal direction of the rail body and extending in the same direction on both sides of the bottom plate and the bottom plate, respectively The upper part is configured to open is configured as a socket for providing a space for the rail locking bolt can be inserted into the upper rail and the lower rail,
The continuous fixing clip, the slot hole extending in the width direction so as to be fitted to the computer bolt is formed at a predetermined interval and connects two or more bricks spaced in the width direction of the brick wall to prevent the flow of bricks And a plurality of protrusions formed to protrude from the edge of the body and the clip body to improve adhesion to the mortar.
삭제delete 제 1 항에 있어서,
상기 레일몸체의 측면판을 관통하도록 설치되어 상부슬래브 및 하부슬래브의 내부에 안정적으로 매설되도록 하는 보강철근;을 더 포함하여 구성된 것을 특징으로 하는 투시형 벽돌벽.
The method of claim 1,
Perspective-type brick wall, characterized in that it further comprises; is installed so as to penetrate the side plate of the rail body to be stably embedded in the interior of the upper slab and the lower slab.
삭제delete 제 1 항에 있어서,
상기 단독형 고정클립은, 일측 가장자리에서 내측방향을 향해 오목한 형태로 형성되는 끼움홈을 통해 전산볼트에 끼워지도록 설치된 후 너트에 의해 고정되는 것을 특징으로 하는 투시형 벽돌벽.
The method of claim 1,
The stand-alone fixing clip is a perspective type brick wall, characterized in that it is fixed by a nut after being installed to be fitted to the computer bolt through the fitting groove formed in a concave shape toward the inner side at one edge.
제 1 항에 있어서
상기 벽돌들 중 상부슬래브와 인접하는 적어도 2단 이상의 벽돌은, 내측에 형성되는 중공과 연결되는 개구부가 측면에 형성되어 개구부를 통해 전산볼트에 측방향으로 끼움 설치되는 것을 특징으로 하는 투시형 벽돌벽.
The method of claim 1
Perspective brick wall, characterized in that at least two or more stages of the brick adjacent to the upper slab, the opening is connected to the hollow formed inside the side is fitted laterally to the computer bolt through the opening. .
상부슬래브 및 하부슬래브의 시공시 상부레일과 하부레일이 매설되도록 시공하는 레일설치단계;
상기 하부레일에 다수의 레일걸림볼트를 끼워 넣고 설계된 위치로 이동시킨 후 연결너트의 일측단을 레일걸림볼트에 체결하여 하부레일에 고정해주는 하측 레일걸림볼트 설치단계;
상기 연결너트의 타측단에 전산볼트를 체결하여 벽돌벽의 높이 방향으로 수직하게 설치하는 전산볼트 설치단계;
상기 전산볼트에 벽돌이 끼워지도록 다수단으로 조적하되 상,하로 조적된 벽돌들 사이에 모르타르를 도포하여 줄눈을 형성하면서 벽돌을 조적하는 벽돌 조적단계;
상기 벽돌을 조적하는 과정에서 일정 간격마다 상, 하로 조적되는 벽돌들 사이에 개재되도록 고정클립을 설치하는 고정클립 설치단계;
상기 상부레일에 레일걸림볼트를 끼워 넣고 연결너트를 이용하여 레일걸림볼트와 상기 벽돌이 끼워지는 전산볼트를 연결해주는 상측 레일걸림볼트 설치단계;
상기 벽돌들을 조적하는 과정에서 상부슬래브와 인접하는 적어도 2단 이상의 벽돌들은 내측에 형성되는 중공과 연결되는 개구부가 형성되도록 구성되며 상기 개구부를 통해 전산볼트에 측방향으로 끼워지도록 설치하는 상부마감단계;를 포함하여 구성되고,
상기 레일설치단계는, 상기 레일걸림볼트가 끼워지고 바닥판과, 상기 바닥판의 양 끝단에서 동일방향을 각각 연장되도록 형성되는 한 쌍의 측면판과, 상기 측면판의 끝단에서 바닥판 방향으로 수평하게 연장되어 상기 레일걸림볼트의 이탈을 방지하는 걸림판으로 이루어진 레일몸체를 설치하고, 바닥판과 상기 바닥판의 양측면에서 동일방향으로 각각 연장되도록 형성되는 한 쌍의 측면판으로 이루어져 상부가 개방되도록 구성되어 레일걸림볼트가 레일몸체로 삽입될 수 있는 공간을 제공하는 소켓을 레일몸체의 길이방향에 연속되도록 설치하며 상기 레일몸체의 폭방향으로 관통되도록 보강철근을 설치하고 상부슬래브와 하부슬래브의 내부에 매설된 철근에 연결하도록 구성하며,
상기 고정클립 설치단계는, 상기 전산볼트에 끼워질 수 있도록 폭방향으로 연장되는 슬롯홀이 일정간격으로 형성되고 벽돌벽의 폭방향으로 이격되는 2개 이상의 벽돌들을 연결하여 벽돌들의 유동을 방지해주는 클립몸체와, 상기 클립몸체의 가장자리에서 돌출되도록 형성되어 모르타르와의 접착력이 향상될 수 있도록 하는 다수의 돌기부로 이루어진 연속형 고정클립을 상기 전산볼트에 끼워지도록 설치하여 상,하에 위치하는 벽돌들 사이에 개재되도록 하고 벽돌의 폭방향으로 이격되는 2개 이상의 벽돌들을 연결해주는 연속형 고정클립 설치단계와, 상기 전산볼트에 끼워지도록 설치되고 상,하에 위치하는 벽돌들 사이에 개재되고, 전산볼트에 체결되는 너트에 의해 가압됨으로서 벽돌들 고정해주는 단독형 고정클립을 설치하는 단독형 고정클립 설치단계;를 포함하여 구성된 것을 특징으로 하는 투시형 벽돌벽의 시공방법.










A rail installation step of constructing the upper rail and the lower rail when the upper slab and the lower slab are constructed;
Inserting a plurality of rail locking bolts into the lower rails and moving them to a designed position, and then installing a lower rail locking bolt fixing one end of the connection nut to the rail locking bolts to fix the lower rails to the lower rails;
Computing bolt installation step of fastening the bolt to the other end of the connection nut to install vertically in the height direction of the brick wall;
Brick masonry step of masonry bricks to form a joint by applying a mortar between the masonry is arranged in multiple stages so that the brick is fitted to the computer bolt;
Fixing clip installation step of installing a fixing clip so as to be interposed between the bricks are arranged up and down at a predetermined interval in the process of masonry bricks;
Installing the upper rail locking bolt to insert the rail locking bolt to the upper rail and connects the rail locking bolt and the computer bolt that the brick is fitted using a connecting nut;
An upper finishing step of installing at least two levels of bricks adjacent to the upper slab in the process of stacking the bricks such that an opening connected to a hollow formed inside is formed and fitted to the computer bolt laterally through the opening; It is configured to include,
The rail installation step may include a pair of side plates to which the rail locking bolts are fitted and extend in the same direction at both ends of the bottom plate and the bottom plate, and horizontally in the direction of the bottom plate at the end of the side plate. It is extended so as to install a rail body consisting of a locking plate to prevent the separation of the rail locking bolt, and consists of a pair of side plates formed to extend in the same direction on both sides of the bottom plate and the bottom plate to open the top The socket is provided so that the rail locking bolt can be inserted into the rail body so that the socket is continuously installed in the longitudinal direction of the rail body, and the reinforcing bars are installed to penetrate in the width direction of the rail body. To connect to rebar embedded in
The fixing clip installation step, the slot hole extending in the width direction so as to be fitted to the computer bolt is formed at a predetermined interval and connects two or more bricks spaced in the width direction of the brick wall to prevent the flow of bricks A continuous fixing clip consisting of a body and a plurality of protrusions formed to protrude from the edge of the clip body to improve the adhesive force with the mortar is installed to be fitted to the computer bolts between the bricks positioned above and below A continuous fixing clip installation step of connecting the two or more bricks spaced in the width direction of the brick to be interposed, and is installed to be fitted to the computer bolt and interposed between the bricks located above and below, and fastened to the computer bolt Single fixed clip for installing a single fixed clip for fixing bricks by being pressed by a nut Construction method of a perspective type brick wall, characterized in that configured including; Chi phase.










삭제delete 삭제delete
KR1020160093210A 2016-07-22 2016-07-22 Direct vision type brick wall and construction method thereof KR102058423B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160093210A KR102058423B1 (en) 2016-07-22 2016-07-22 Direct vision type brick wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160093210A KR102058423B1 (en) 2016-07-22 2016-07-22 Direct vision type brick wall and construction method thereof

Publications (2)

Publication Number Publication Date
KR20180010685A KR20180010685A (en) 2018-01-31
KR102058423B1 true KR102058423B1 (en) 2019-12-23

Family

ID=61083035

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160093210A KR102058423B1 (en) 2016-07-22 2016-07-22 Direct vision type brick wall and construction method thereof

Country Status (1)

Country Link
KR (1) KR102058423B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102000400B1 (en) 2018-08-07 2019-07-15 키움건설 주식회사 Direct vision type brick wall using and construction method thereof
KR102212286B1 (en) 2019-08-22 2021-02-04 타이아(주) Unmanned smart mart system with module unit type based on Internet of Things, and method providing method thereof
EP4155473A1 (en) * 2021-09-23 2023-03-29 Leviat GmbH Wall arrangement
CN115126116B (en) * 2022-06-23 2023-07-14 南通固盛建材有限公司 Crack-resistant building rubbish recycled concrete wallboard

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081152A (en) * 2000-09-06 2002-03-22 Japan Science & Technology Corp Brick masonry structure, brick masonry method and brick manufacturing method
JP2007107282A (en) * 2005-10-13 2007-04-26 Harigae Komuten:Kk Steel framed reinforcement type dry block masonry method
JP2014129682A (en) * 2012-12-28 2014-07-10 Takenaka Komuten Co Ltd Wall surface structure of brick wall, and construction method of brick wall
KR101422445B1 (en) * 2014-04-24 2014-07-22 심장보 Brick dry wall structure and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20140005726U (en) * 2013-04-30 2014-11-07 윤기원 Fabricated insulation barrier

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081152A (en) * 2000-09-06 2002-03-22 Japan Science & Technology Corp Brick masonry structure, brick masonry method and brick manufacturing method
JP2007107282A (en) * 2005-10-13 2007-04-26 Harigae Komuten:Kk Steel framed reinforcement type dry block masonry method
JP2014129682A (en) * 2012-12-28 2014-07-10 Takenaka Komuten Co Ltd Wall surface structure of brick wall, and construction method of brick wall
KR101422445B1 (en) * 2014-04-24 2014-07-22 심장보 Brick dry wall structure and construction method thereof

Also Published As

Publication number Publication date
KR20180010685A (en) 2018-01-31

Similar Documents

Publication Publication Date Title
KR102058423B1 (en) Direct vision type brick wall and construction method thereof
EP1217141B1 (en) Constructional elements
US8365481B2 (en) Anchorage system of ventilated facades
KR101664359B1 (en) Terra-cotta tile fixing device for buildings
KR101075156B1 (en) Cable tray
KR101323638B1 (en) Brick wall type masonry
KR200438912Y1 (en) Reinforcement bracket for constructing earthquake-proof wall
KR102099933B1 (en) Precast Concrete Modualr Structure And Method for Constructing the Same
KR100991046B1 (en) H beam and constructing method using the H beam
KR101463222B1 (en) Structural panel assembly
KR101500313B1 (en) Dry brick wall structure and construction method thereof
KR101234673B1 (en) Ceiling panel clip bar and mounting structure using the same
WO2016161478A1 (en) Stay-in-place beam formwork for concrete structures
KR101640797B1 (en) The panel for wall of a set building and thereof construction method
KR200441333Y1 (en) Structure of ceiling with lightweight steel frame
KR102183697B1 (en) Window bracket including fabricable condensation-proof pad assembly
KR101329098B1 (en) Prefabricated structures for the roof bracket
KR101275932B1 (en) Method for installing ALC panel to concrete slab
KR102065623B1 (en) the improved yoke truss and the wall form structure using the same
KR101901240B1 (en) A mold panel of assembly for building
KR102224796B1 (en) Precast Concrete Modualr Structure
KR200443097Y1 (en) steel rest including insert
JP5687919B2 (en) Assembly building and construction method of assembly building
KR100581028B1 (en) Prefabricated wall using panel
JP4083052B2 (en) Fence

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant