KR102008965B1 - Construction method for wall structure - Google Patents
Construction method for wall structure Download PDFInfo
- Publication number
- KR102008965B1 KR102008965B1 KR1020170102538A KR20170102538A KR102008965B1 KR 102008965 B1 KR102008965 B1 KR 102008965B1 KR 1020170102538 A KR1020170102538 A KR 1020170102538A KR 20170102538 A KR20170102538 A KR 20170102538A KR 102008965 B1 KR102008965 B1 KR 102008965B1
- Authority
- KR
- South Korea
- Prior art keywords
- foundation
- partition wall
- wall
- sheath
- central
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H7/00—Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
- E04H7/22—Containers for fluent solids, e.g. silos, bunkers; Supports therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H7/00—Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
- E04H7/22—Containers for fluent solids, e.g. silos, bunkers; Supports therefor
- E04H2007/225—Silos with retaining wall type wall elements, e.g. trench silos
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법에 관한 것으로서, 상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계; 폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계; 상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계; 상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법을 제시함으로써, 시공이 안전하고, 공사기간을 단축할 수 있도록 한다.The present invention relates to a construction method of a wall structure having a central partition 10 installed along the front and rear direction, and a side partition wall 20 installed along the lateral direction on both sides of the central partition 10. A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed; The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare; The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101; And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked. By presenting the construction method of the wall structure, characterized in that the construction is safe and can shorten the construction period.
Description
본 발명은 건설 분야에 관한 것으로서, 상세하게는 벽체 구조물의 시공방법에 관한 것이다.The present invention relates to the field of construction, and more particularly, to a construction method of a wall structure.
석탄 저장고(Coal Shed)란 석탄 화력발전소에서 대규모의 석탄을 저장하기 위해 사용되는 것으로서, 높이 및 폭이 수십m에 이르는 대규모의 벽체 구조물을 말한다.Coal Sheds are used to store large amounts of coal in coal-fired power plants. They are large-scale wall structures up to several tens of meters in height and width.
이는 중앙격벽과, 그 양측에 측방향을 따라 설치되는 복수의 측방격벽에 의해 다수의 구획된 석탄저장실을 구비한 구조를 취한다.It has a structure having a central partition and a plurality of partitioned coal storage chambers by a plurality of side partitions provided laterally on both sides thereof.
종래에는 거푸집을 설치하고 콘크리트를 현장타설하는 방식을 취하였는데, 이는 대규모의 구조물이므로, 시공이 어려워 안전성이 좋지 못하고, 공사기간이 길며, 공사비용이 많이 소요된다는 문제가 있었다.Conventionally, formwork was installed and concrete was cast in place, which is a large-scale structure, which is difficult to construct due to difficult construction, long construction period, and high cost of construction.
본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 하는 벽체 구조물의 시공방법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, the object of the present invention is to propose a construction method of the wall structure to be safe construction, shorten the construction period, and to reduce the construction cost.
상기 과제의 해결을 위하여, 본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서, 상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계; 폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계; 상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계; 상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법을 제시한다.In order to solve the above problems, the present invention provides a wall structure having a
상기 단위부재(100)는, 양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103); 상기 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하고, 상기 가이드공(101)은 상기 보강벽부(104)에 형성되고, 상기 쉬스(1)는 상기 보강벽부(104) 또는 상기 측벽(103a)에 설치된 것이 바람직하다.The
상기 기초구조물(30)은 상기 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성되는 것이 바람직하다.The
상기 격벽 형성단계는, 상기 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 상기 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계; 상기 최하단 단위부재(100a)의 가이드공(101)을 통해 상기 가이드봉(301)을 삽입하여, 상기 가이드봉(301)의 하단이 상기 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계; 상기 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 상기 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계;를 포함하는 것이 바람직하다.The partition forming step may include: a lowermost unit member mounting step of mounting a
상기 격벽 형성단계는, 상기 기초콘크리트 타설단계 이전, 상기 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 상기 기초콘크리트 타설영역(302)에 "U"자형 구조의 상기 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를 더 포함하는 것이 바람직하다.The barrier rib forming step may include, before the foundation concrete placing step, the
상기 기초콘크리트 타설단계는, 상기 기초콘크리트 타설영역(302) 및 상기 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 것이 바람직하다.In the basic concrete placing step, it is preferable to pour the base concrete in the
상기 기초부재(300)는, 상기 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 상기 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하고, 상기 중앙격벽 기초부재(310)는, 폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311); 상기 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312); 상기 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하고, 상기 측방격벽 기초부재(320)는, 길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321); 상기 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322); 상기 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하는 것이 바람직하다.The
상기 단위부재(100)는, 상기 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110); 상기 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하고, 상기 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치되고, 상기 격벽 형성단계는, 복수의 상기 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계; 상기 결합작업공간(410)의 측방에 상기 측방격벽 단위부재(120)를 설치하는 단계; 상기 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 상기 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계; 상기 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를 포함하는 것이 바람직하다.The
상기 중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의한 긴장재(2c)가 설치된 것이 바람직하다.The
상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 상기 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성되고, 복수의 상기 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 상기 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 상기 결합부 콘크리트 타설영역(302c)의 양측에 설치된 상기 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 상기 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 하는 단계; 상기 결합부 콘크리트 타설영역(302c)의 일측에 상기 측방격벽 기초부재(320)를 설치하는 단계;를 포함하는 것이 바람직하다.One central partition longitudinal foundation of one of the pair of central partition
상기 격벽 형성단계는, 상기 복수의 단위부재(100) 중 일부를 적층하여 상기 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 상기 가이드공(101)에 충전재를 타설하되, 상기 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계; 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 상기 가이드봉(301)의 상단에 연장가이드봉(301a)을 연결하는 단계; 상기 연장가이드봉(301a)에 상기 가이드공(101)이 관통하도록, 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하는 단계;를 포함하는 것이 바람직하다.In the forming of the partition wall, a part of the plurality of
상기 격벽 일부 설치단계는, 상기 격벽 일부의 측면과 상기 기초구조물(30)의 상면 사이에 전도방지부재(4)를 설치하는 단계;를 더 포함하는 것이 바람직하다.The partial installation of the partition wall may further include installing a
복수의 상기 전도방지부재(4)의 상단이 상기 결합부(400)의 네 귀퉁이에 각각 결합하는 것이 바람직하다.Upper ends of the plurality of
상기 단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비하는 주두부 준비단계; 적층된 상기 복수의 단위부재(100)의 상단에 상기 주두부(500)를 설치하는 주두부 설치단계;를 더 포함하고, 상기 긴장정착단계는, 상기 기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 상기 복수의 단위부재(100)의 쉬스(1) 및 상기 주두부(500)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 상기 주두부(500)의 상면에 정착하는 것이 바람직하다.A head head preparation step of preparing a
상기 격벽 형성단계 이후, 상기 측방격벽(20)의 측방에 대하여 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 단계;를 더 포함하는 것이 바람직하다.After the partition forming step, the step of installing the formwork for the side of the
본 발명은 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 하는 벽체 구조물의 시공방법을 제시한다.The present invention proposes a construction method of a wall structure that is safe to construction, can shorten the construction period, and can reduce the construction cost.
도 1 이하는 본 발명에 의한 벽체 구조물의 시공방법의 실시예를 도시한 것으로서,
도 1은 석탄 저장고의 정면도.
도 2는 석탄 저장고의 평면도.
도 3은 중앙격벽 단위부재의 평면도.
도 4는 중앙격벽 단위부재의 제1 종단면도.
도 5는 도 4의 A-A 단면도.
도 6은 도 4의 B-B 단면도.
도 7은 중앙격벽 단위부재의 제2 종단면도.
도 8은 도 7의 A-A 단면도.
도 9는 도 7의 B-B 단면도.
도 10은 측방격벽 단위부재의 횡단면도.
도 11은 측방격벽 단위부재의 제1 종단면도.
도 12는 도 11의 A-A 단면도.
도 13은 도 11의 B-B 단면도.
도 14는 측방격벽 단위부재의 제2 종단면도.
도 15는 측방격벽 단위부재의 정면도.
도 16은 도 14의 B-B 단면도.
도 17은 중앙격벽 기초부재의 제1 실시예의 사시도.
도 18은 중앙격벽 기초부재의 제1 실시예의 평면도.
도 19는 중앙격벽 기초부재의 제2 실시예의 사시도.
도 20은 중앙격벽 기초부재의 제2 실시예의 평면도.
도 21은 측방격벽 기초부재의 평면도.
도 22 내지 25는 제1 실시예의 공정도.
도 26 내지 38은 제2 실시예의 공정도.
도 39,40은 제3 실시예의 공정도.Figure 1 below shows an embodiment of the construction method of the wall structure according to the present invention,
1 is a front view of a coal reservoir.
2 is a plan view of a coal reservoir.
3 is a plan view of the central bulkhead unit member.
Figure 4 is a first longitudinal cross-sectional view of the central partition unit member.
5 is a cross-sectional view taken along AA of FIG. 4.
6 is a cross-sectional view taken along line BB of FIG. 4.
7 is a second longitudinal cross-sectional view of the central bulkhead unit member.
8 is a cross-sectional view taken along AA of FIG. 7.
9 is a cross-sectional view taken along line BB of FIG. 7.
10 is a cross-sectional view of the side bulkhead unit member.
11 is a first longitudinal cross-sectional view of the side partition wall unit member.
12 is a cross-sectional view taken along AA of FIG. 11.
13 is a cross-sectional view taken along line BB of FIG.
14 is a second longitudinal sectional view of the side bulkhead unit member.
15 is a front view of the side partition wall unit member.
FIG. 16 is a cross-sectional view taken along line BB of FIG. 14.
17 is a perspective view of a first embodiment of a central partition base member.
18 is a plan view of a first embodiment of a central partition base member;
19 is a perspective view of a second embodiment of a central partition base member;
20 is a plan view of a second embodiment of a central partition foundation member;
21 is a plan view of the side partition foundation member.
22-25 are process diagrams of the first embodiment.
26 to 38 are process diagrams of a second embodiment.
39 and 40 are process diagrams of the third embodiment.
이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 1 이하에 도시된 바와 같이, 본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서, 기본적으로 다음과 같은 공정에 의해 이루어진다.As shown in Figure 1 below, the present invention is a wall structure having a
이하에서는 본 발명이 대규모의 석탄 저장고(Coal Shed)에 적용된 실시예에 대하여 설명한다.Hereinafter, an embodiment in which the present invention is applied to a large-scale coal shed will be described.
중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치한다(기초구조물 설치단계, 도 17 내지 21,22,26,27).The
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비한다(단위부재 준비단계, 도 3 내지 16).The length is formed longer than the width and height, the
기초구조물(30)에 하단이 매설된 가이드봉(301)에 가이드공(101)이 관통하도록, 기초구조물(30)의 상부에 복수의 단위부재(100)를 적층하여 설치하여 중앙격벽(10) 및 측방격벽(20)을 형성하고, 가이드공(101)에 충전재(M)를 타설한다(격벽 형성단계, 도 23 내지 25, 도 28 내지 37).The
기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착한다(긴장정착단계, 도 38).
석탄 저장고는 도 1,2에 도시된 바와 같이, 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)에 의해 구성되므로, 그 자체로 자립이 가능하다.As shown in Figures 1 and 2, the coal reservoir is composed of a
본 발명은 이에 착안한 것으로서, 기초구조물(30)에 매설된 가이드봉(301)에 의해 가이드되도록, 복수의 단위부재(100)를 적층하여 설치하여 중앙격벽(10) 및 측방격벽(20)을 형성하고, 가이드공(101)의 충전 및 텐던(2)의 정착에 의해 석탄 저장고를 시공하는 방식을 취한 것이다.The present invention was conceived in this regard, the
이는 대규모의 구조물의 시공방법임에 불구하고, 시공 중 구조물의 자립이 가능하도록 하므로, 종래의 거푸집 설치 및 현장타설 방식에 비해, 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 한다는 장점이 있다.Although this is a method of constructing a large-scale structure, it enables the structure to stand on its own during construction. Therefore, construction is safer, construction time can be shorter, and construction cost can be reduced compared to the conventional formwork and site casting method. The advantage is that it can be done.
이하, 본 발명에 의한 벽체 구조물의 시공방법의 구체적 실시예에 대하여 설명한다.Hereinafter, specific examples of the construction method of the wall structure according to the present invention will be described.
단위부재(100)는, 양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103); 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하여 구성된다(도 3 내지 16).The
즉, 보강벽부(104)는 몸통부(103)의 양단부에만 형성될 수도 있고, 추가로 중앙부에 형성될 수도 있다.That is, the reinforcing
가이드공(101)은 보강벽부(104)에 형성되고, 쉬스(1)는 보강벽부(104) 또는 측벽(103a)에 설치된다.The
기초구조물(30)은 전체적으로 콘크리트 현장타설 방식에 의해 형성될 수도 있으나, 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성된 구조를 취하는 것이 시공성 측면에서 바람직하다(도 17 내지 21).Although the
기초부재(300)는 위 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 하는 구조로 형성된다(도 22).The
상기 격벽 형성단계는, 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계(도 23,28,29); 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)을 삽입하여, 가이드봉(301)의 하단이 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계(도 30,31); 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계(도 32,33);를 포함하여 구성될 수 있다.The partition wall forming step may include a lowermost unit member mounting step of mounting the
즉, 기초구조물(30)에 가이드봉(301)의 하단을 먼저 매설하고, 이후 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)이 삽입되는 방식을 취할 수도 있으나, 상술한 바와 같이 먼저 최하단 단위부재(100a)를 기초부재(300)의 상부에 거치한 후, 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)을 삽입하여, 가이드봉(301)의 하단이 기초구조물(30)에 매설되도록 하는 경우, 가이드봉(301)의 설치위치가 자연스럽게 결정되므로 시공이 더욱 편리하다는 장점이 있다.That is, the lower end of the
상기 격벽 형성단계는, 기초콘크리트 타설단계 이전, 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 기초콘크리트 타설영역(302)에 "U"자형 구조의 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를 더 포함하여 구성될 수 있다(도 30,31).In the partition forming step, the
이러한 기초 쉬스(1a)는 추후 긴장정착단계(도 38)에서 격벽 및 기초구조물 전체에 대하여 텐던(2)을 "U"자형으로 배치하여 긴장하고 정착할 수 있도록 한다.The
기초구조물(30)의 형성을 위하여 기초부재(300)의 기초콘크리트 타설영역(302)에만 기초콘크리트를 타설할 수도 있으나, 기초콘크리트 타설영역(302) 및 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 경우, 취약한 격벽의 하단을 보강할 수 있다는 장점이 추가된다(도 32,33).In order to form the
필요한 경우, 최하단 단위부재(100a) 뿐만 아니라, 그 상부에 배치되는 단위부재(100)의 공간에 대하여도 콘크리트를 타설하여 보강할 수 있다.If necessary, concrete may be poured into and reinforce not only the
기초부재(300)는 기본적으로, 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하여 구성된다(도 2,22 내지 25).The
중앙격벽 기초부재(310)는 구체적으로, 폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311); 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312); 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하여 구성된다(도 17 내지 20).The center
측방격벽 기초부재(320)는 구체적으로, 길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321); 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322); 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하여 구성된다(도 21).The side partition wall base member 320 may include, in particular, a pair of side partition wall width
단위부재(100)는 기본적으로, 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110); 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하여 구성되는데(도 1,2), 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치된다(도 10,14,15).The
이 경우 상기 격벽 형성단계는, 복수의 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계; 결합작업공간(410)의 측방에 측방격벽 단위부재(120)를 설치하는 단계; 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계; 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를 포함하여 구성될 수 있다(도 23 내지 25).In this case, the forming of the partition wall may include installing a plurality of central
즉, 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 사이에 결합작업공간(410)이 형성되도록 한 후, 이에 별도로 콘크리트를 타설하여 결합부(400)를 형성하고, 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 설치된 측방향 텐던(2a)의 긴장 및 정착에 의해 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 일체화 구조가 형성되도록 한 것이다.That is, after the
중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의해 긴장재(2c)를 설치하는 것이 시공성 및 구조적 안정성을 위하여 바람직하다(도 7 내지 9).It is preferable to install the tension member 2c on the
또한, 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 적층구조는 전체적으로 동일한 높이를 유지하도록 시공함으로써, 그 자체로 자립구조를 취하도록 하는 것이 안전한 시공을 위하여 바람직하다.In addition, the laminated structure of the central
상술한 바와 같이 기초부재(300)는, 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하여 구성되는데, 상술한 중앙격벽 단위부재(110) 및 측방격벽 단위부재(120)의 편리한 시공을 위하여, 위 기초부재(300)는 다음과 같은 구성 및 공정을 취하는 것이 바람직하다(도 22 내지 25).As described above, the
즉, 상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성된다(도 17 내지 20).That is, the center partition longitudinal direction of one of the pair of central bulkhead longitudinal
이러한 구조를 취하는 경우, 복수의 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 결합부 콘크리트 타설영역(302c)의 양측에 설치된 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 할 수 있다.In this structure, a plurality of central
결합부 콘크리트 타설영역(302c)의 일측에는 측방격벽 기초부재(320)를 설치하여 폐쇄할 수 있다.One side of the coupling portion
격벽의 높이가 높으므로, 일부씩 나누어 시공하는 것이 바람직하다.Since the height of a partition is high, it is preferable to divide and install by one part.
즉, 복수의 단위부재(100) 중 일부를 적층하여 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 가이드공(101)에 충전재를 타설하되, 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계; 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 가이드봉(301)의 상단에 커플러 등을 이용하여 연장가이드봉(301a)을 연결하는 단계; 연장가이드봉(301a)에 가이드공(101)이 관통하도록, 상중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 복수의 단위부재(100)를 적층하여 설치하는 단계;를 포함하는 것이 바람직하다(도 34 내지 36).That is, a part of the plurality of
본 발명에 의한 시공방법에 의한 석탄 저장고는 시공 중 상술한 바와 같은 자립 구조를 취하지만, 일정 높이마다 전도방지부재(4)를 설치하는 경우, 더욱 안전한 시공이 가능하다(도 39,40).The coal storage by the construction method according to the present invention takes the self-supporting structure as described above during construction, but when the
즉, 격벽 일부의 측면과 기초구조물(30)의 상면 사이에 전도방지부재(4)를 순차적으로 설치하는 것이 바람직하다.That is, it is preferable to sequentially install the
구체적으로, 복수의 전도방지부재(4)의 상단이 결합부(400)의 네 귀퉁이에 각각 결합하도록 하는 것이 구조적 안정성을 위하여 바람직하다(도 40).Specifically, it is preferable for structural stability that the upper ends of the plurality of
격벽의 상단에는 프리캐스트 주두부(500)를 다음과 같은 공정에 의해 설치한다.On the upper end of the partition wall, the
단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비한 후, 적층된 복수의 단위부재(100)의 상단에 주두부(500)를 설치한다(도 36).After forming the
기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 복수의 단위부재(100)의 쉬스(1) 및 주두부(500)의 쉬스(1)에 텐던(2)을 "U"자형 구조로 설치하고 긴장하여 주두부(500)의 상면에 정착한다(도 37).The "U" shaped structure of the tendon sheath (1a) embedded in the foundation structure (30), the sheath (1) of the plurality of unit members (100) stacked, and the tendon (2) on the sheath (1) of the head head (500). It is installed and tensioned to settle on the upper surface of the head (500) (Fig. 37).
석탄 저장고의 중앙 격벽(10) 및 측방격벽(20)의 전부를 상술한 복수의 단위부재(100)의 적층 방식에 의해 시공할 수도 있으나, 이는 기본적으로 시공 중 구조물의 자립을 위한 것이므로, 반드시 측방격벽(20)의 전부를 이러한 방식에 의해 시공할 필요는 없다.Although all of the
따라서 구조물의 자립이 가능한 정도로만 측방격벽(20)의 일부를 복수의 단위부재(100)의 적층 방식에 의해 시공하고, 측방격벽(20)의 측방 나머지 영역에 대하여는 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 것이 경제성 측면에서 바람직하다(도 1).Therefore, only a part of the
이상에서는 본 발명에 의한 벽체 구조물이 석탄 저장고(Coal Shed)에 적용되는 경우의 실시예에 관하여 설명하였으나, 그 밖의 벽체 구조물에 대하여도 효과적으로 적용될 수 있다.In the above described an embodiment in the case where the wall structure according to the present invention is applied to the coal shed (Coal Shed), it can be effectively applied to other wall structures.
이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.
1 : 쉬스 1a : 기초 쉬스
2 : 텐던 2a : 측방향 텐던
2c : 프리텐션 긴장재 4 : 전도방지부재
10 : 중앙격벽 20 : 측방격벽
21 : 연장측방격벽 30 : 기초구조물
100 : 단위부재 100a : 최하단 단위부재
101 : 가이드공 103 : 몸통부
103a : 측벽 103b : 공간
104 : 보강벽부 110 : 중앙격벽 단위부재
120 : 측방격벽 단위부재 300 : 기초부재
301 : 가이드봉 301a : 연장가이드봉
302 : 기초콘크리트 타설영역
302a : 중앙격벽 기초콘크리트 타설영역
302b : 측방격벽 기초콘크리트 타설영역
302c : 결합부 기초콘크리트 타설영역
310 : 중앙격벽 기초부재 311 : 중앙격벽 길이방향 기초벽
311c : 폐쇄용 연장부 312 : 폭방향 기초벽
313 : 삽입홈 320 : 측방격벽 기초부재
321 : 측방격벽 폭방향 기초벽 322 : 측방격벽 길이방향 기초벽
323 : 삽입홈 400 : 결합부
410 : 결합작업공간 500 : 프리캐스트 주두부1:
2:
2c: pretension tension member 4: fall prevention member
10: center bulkhead 20: side bulkhead
21: extension side partition wall 30: foundation structure
100:
101: guide ball 103: the body
103a:
104: reinforcing wall portion 110: central bulkhead unit member
120: side bulkhead unit member 300: base member
301: guide
302: Foundation concrete pouring area
302a: Central concrete foundation concrete casting area
302b: Lateral bulkhead foundation concrete casting area
302c: Foundation concrete casting area
310: center partition foundation member 311: center partition longitudinal foundation wall
311c: closing extension 312: widthwise base wall
313: insertion groove 320: side partition wall foundation member
321: side bulkhead width direction foundation wall 322: side bulkhead longitudinal direction wall
323: insertion groove 400: coupling portion
410: combined working space 500: precast head tofu
Claims (15)
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 단위부재(100)는,
양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103);
상기 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하고,
상기 가이드공(101)은 상기 보강벽부(104)에 형성되고,
상기 쉬스(1)는 상기 보강벽부(104) 또는 상기 측벽(103a)에 설치된 것을 특징으로 하는 벽체 구조물의 시공방법.As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
The unit member 100,
A body portion 103 having an H-shaped cross-sectional structure having side walls 103a formed on both sides and a space 103b formed above and below;
And a reinforcing wall portion 104 having a wall-shaped cross-sectional structure formed at an end portion or a central portion of the body portion 103.
The guide hole 101 is formed in the reinforcing wall portion 104,
The sheath (1) is a method of constructing a wall structure, characterized in that installed on the reinforcing wall portion (104) or the side wall (103a).
상기 기초구조물(30)은 상기 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성되는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 1,
The foundation structure 30 is formed by assembling a plurality of foundation members 300 manufactured by a precast method to support the unit member 100 and to form the foundation concrete casting region 302 in the core portion. Construction method of the wall structure, characterized in that the.
상기 격벽 형성단계는,
상기 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 상기 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계;
상기 최하단 단위부재(100a)의 가이드공(101)을 통해 상기 가이드봉(301)을 삽입하여, 상기 가이드봉(301)의 하단이 상기 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계;
상기 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 상기 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 3,
The partition wall forming step,
A lowermost unit member mounting step of mounting the lowermost unit member 100a installed at the lowermost end of the plurality of unit members 100 on the upper portion of the base member 300;
Inserting the guide rod 301 through the guide hole 101 of the lowest unit member (100a), the guide rod installation step so that the lower end of the guide rod 301 is located in the basic concrete placing area 302 ;
A foundation concrete placing step of placing concrete at the foundation concrete placing area 302 to bury the lower end of the guide rod 301;
Construction method of a wall structure comprising a.
상기 격벽 형성단계는,
상기 기초콘크리트 타설단계 이전,
상기 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 상기 기초콘크리트 타설영역(302)에 "U"자형 구조의 상기 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를
더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 4, wherein
The partition wall forming step,
Before the foundation concrete pouring step,
A foundation sheath installation step of installing the foundation sheath 1a having a “U” shaped structure in the foundation concrete placing region 302 so as to communicate with the sheath 1 of the lowermost unit member 100a;
Construction method of the wall structure, characterized in that it further comprises.
상기 기초콘크리트 타설단계는,
상기 기초콘크리트 타설영역(302) 및 상기 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 4, wherein
The foundation concrete pouring step,
Construction method of the wall structure, characterized in that the foundation concrete is cast in the lower space (103b) of the base concrete placing area (302) and the lower body unit 103 of the lowermost unit member (100a).
상기 기초부재(300)는,
상기 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310);
상기 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하고,
상기 중앙격벽 기초부재(310)는,
폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311);
상기 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312);
상기 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하고,
상기 측방격벽 기초부재(320)는,
길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321);
상기 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322);
상기 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 3,
The base member 300,
A central partition base member 310 installed along a lower region in which the central partition 10 is to be installed;
And a side partition foundation member 320 installed along a lower region in which the side partition walls 20 are to be installed.
The central partition base member 310,
A pair of central bulkhead longitudinal foundation walls 311 provided along the longitudinal direction at intervals along the width direction;
A plurality of centers are provided at intervals along the longitudinal direction between the pair of central bulkhead longitudinal direction walls 311, and an insertion groove 313 is formed in which a lower portion of the unit member 100 is inserted. Partition wall width direction base wall 312;
And a central bulkhead foundation concrete pouring area 302a formed between the pair of central bulkhead longitudinal foundation walls 311 and the plurality of central bulkhead widthwise foundation walls 312.
The side partition wall member 320,
A pair of side partition wall width direction base walls 321 provided along the width direction at intervals along the length direction;
A plurality of side surfaces of the pair of side partition walls in the width direction of the base wall 321 are installed at intervals along the width direction, and an insertion groove 323 in which a lower portion of the unit member 100 is inserted is formed thereon. Partition longitudinal foundation walls 322;
A method of constructing a wall structure comprising a; side partition wall foundation concrete placing area 302b formed between the pair of side partition wall width direction base walls 321 and the plurality of side partition wall longitudinal base walls 322. .
상기 단위부재(100)는,
상기 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110);
상기 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하고,
상기 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치되고,
상기 격벽 형성단계는,
복수의 상기 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계;
상기 결합작업공간(410)의 측방에 상기 측방격벽 단위부재(120)를 설치하는 단계;
상기 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 상기 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계;
상기 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 7, wherein
The unit member 100,
A central partition unit member 110 forming the central partition 10;
And a side partition unit member 120 forming the side partition walls 20.
A sheath 1 is installed along the longitudinal direction of the side wall 103a of the side partition wall unit member 120.
The partition wall forming step,
Installing a plurality of the central partition unit member 110 at intervals along the longitudinal direction to form a coupling working space (410);
Installing the side partition wall unit member 120 on the side of the coupling working space (410);
Placing a sheath (1) in the coupling work space (410) and placing concrete so as to communicate with the sheath (1) of the side partition wall unit member (120) to form a coupling part (400);
Installing and tensioning the lateral tendons 2a on the sheath 1 of the side partition wall unit member 120 and the sheath 1 of the coupling part 400;
Construction method of a wall structure comprising a.
상기 중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의한 긴장재(2c)가 설치된 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 8,
Method of constructing a wall structure, characterized in that the tension member (2c) by the pretension method is installed in the side wall (103a) of the central partition unit member (110) in the longitudinal direction.
상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 상기 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성되고,
복수의 상기 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 상기 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 상기 결합부 콘크리트 타설영역(302c)의 양측에 설치된 상기 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 상기 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 하는 단계;
상기 결합부 콘크리트 타설영역(302c)의 일측에 상기 측방격벽 기초부재(320)를 설치하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 8,
One central partition longitudinal foundation of one of the pair of central partition longitudinal foundation walls 311 of the central partition foundation member 310 so that the coupling portion concrete placing region 302c is formed below the coupling portion 400. At the end of the wall 311 a closing extension 311c is formed,
A plurality of central bulkhead foundation members 310 are installed at intervals along the lengthwise direction such that the coupling part concrete placing area 302c is formed therebetween, and is installed at both sides of the coupling part concrete placing area 302c. Closing the other side of the coupling part concrete placing area (302c) by the closing extension part (311c) of the central partition base member (310);
Installing the side partition wall base member 320 on one side of the coupling portion concrete placing area (302c);
Construction method of a wall structure comprising a.
상기 격벽 형성단계는,
상기 복수의 단위부재(100) 중 일부를 적층하여 상기 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 상기 가이드공(101)에 충전재를 타설하되, 상기 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계;
상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 상기 가이드봉(301)의 상단에 연장가이드봉(301a)을 연결하는 단계;
상기 연장가이드봉(301a)에 상기 가이드공(101)이 관통하도록, 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 8,
The partition wall forming step,
Some of the plurality of unit members 100 are stacked to form part of the central partition wall 10 and the side partition wall 20, and the filler is poured into the guide hole 101, but the guide rod 301 of the Partial installation of the partition wall to expose the top;
Connecting an extension guide rod (301a) to an upper end of the guide rod (301) exposed at an upper end of a portion of the central partition (10) and the side partition wall (20);
Stacking the plurality of unit members (100) on top of a portion of the central partition wall (10) and the side partition wall (20) to allow the guide hole (101) to pass through the extension guide rod (301a); To
Construction method of a wall structure comprising a.
상기 격벽 일부 설치단계는,
상기 격벽 일부의 측면과 상기 기초구조물(30)의 상면 사이에 전도방지부재(4)를 설치하는 단계;를 더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 11,
Part of the partition wall installation step,
Installing a fall prevention member (4) between the side of the partition portion and the upper surface of the foundation structure (30); Construction method of the wall structure further comprises a.
복수의 상기 전도방지부재(4)의 상단이 상기 결합부(400)의 네 귀퉁이에 각각 결합하는 것을 특징으로 하는 벽체 구조물의 시공방법.The method of claim 12,
Method of constructing a wall structure, characterized in that the upper end of the plurality of anti-conduction member (4) is respectively coupled to the four corners of the coupling portion (400).
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비하는 주두부 준비단계;
적층된 상기 복수의 단위부재(100)의 상단에 상기 주두부(500)를 설치하는 주두부 설치단계;를 더 포함하고,
상기 긴장정착단계는, 상기 기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 상기 복수의 단위부재(100)의 쉬스(1) 및 상기 주두부(500)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 상기 주두부(500)의 상면에 정착하는 것을 특징으로 하는 벽체 구조물의 시공방법.As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
A head head preparation step of preparing a precast head head 500 having a wider width than that of the unit member 100 and having the sheath 1 installed along the vertical direction;
Further comprising: a head head installation step of installing the head head 500 on the top of the plurality of stacked unit members 100,
The tension fixing step may include a foundation sheath 1a embedded in the foundation structure 30, a sheath 1 of the plurality of unit members 100 stacked on the sheath 1 and a sheath 1 of the head head 500. (2) the installation method of the wall structure, characterized in that the tension is settled on the upper surface of the head (500).
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 격벽 형성단계 이후,
상기 측방격벽(20)의 측방에 대하여 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 단계;를
더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
After the partition wall forming step,
Installing the formwork with respect to the side of the side partition wall 20 and pouring concrete to form an extended side partition wall 21;
Construction method of the wall structure, characterized in that it further comprises.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020170102538A KR102008965B1 (en) | 2017-08-11 | 2017-08-11 | Construction method for wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020170102538A KR102008965B1 (en) | 2017-08-11 | 2017-08-11 | Construction method for wall structure |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20190017541A KR20190017541A (en) | 2019-02-20 |
KR102008965B1 true KR102008965B1 (en) | 2019-08-12 |
Family
ID=65562089
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020170102538A KR102008965B1 (en) | 2017-08-11 | 2017-08-11 | Construction method for wall structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102008965B1 (en) |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100779772B1 (en) * | 2006-04-17 | 2007-11-27 | 삼성물산 주식회사 | Guide block and construction method for pre-cast member using it |
-
2017
- 2017-08-11 KR KR1020170102538A patent/KR102008965B1/en active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
KR20190017541A (en) | 2019-02-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100549649B1 (en) | Precast Tall Pier for Bridge | |
KR101545649B1 (en) | Construction method for coping using permanent form preventing interference of reinforcing bar | |
KR101229263B1 (en) | Slab-type box girder with a vertical connecting structure made by precast concrete and method constructing the bridge thereof | |
KR100758504B1 (en) | Method of construction for underground diaphragm wall and underground diaphragm wall structure | |
KR102008965B1 (en) | Construction method for wall structure | |
KR102059459B1 (en) | Construction method for coal shed using foundation member | |
KR101023179B1 (en) | Tee type ribbed slab, manufacturing method and construction method thereof | |
CN110984691B (en) | Construction method of enclosure upright post | |
KR200440047Y1 (en) | Block for reinforcing wall | |
KR20120131034A (en) | Container Assembled with Precast Members Using Loop Connection | |
CN216194664U (en) | Prestressing force assembled underground continuous wall | |
CN108571092A (en) | A kind of module shear wall system with perps | |
PT94407A (en) | FRAMEWORK STRUCTURE FOR STRUCTURAL BEAM MOLDING | |
NL2027756B1 (en) | FOUNDATION ELEMENT FOR A MAST FOUNDATION, A MAST FOUNDATION AND A METHOD TO PLACE A MAST FOUNDATION | |
JP2014206025A (en) | Culvert | |
JP2007126936A (en) | Semisubterranean road and its construction method | |
KR101219459B1 (en) | The water-storage tank of assembly type and method for constructing thereof | |
CN207109611U (en) | A kind of prefabricated just beam buttress | |
KR20130038089A (en) | Precast concrete frame for buildings using precast concrete beam continued by post tensioning | |
CN112095638A (en) | Prefabricated anchor rope frame | |
CN107338734A (en) | A kind of prefabricated just beam buttress and prefabricated jacking construction method | |
CN219753696U (en) | Skeleton texture and prefabricated wall | |
KR100568904B1 (en) | Structure, Method and Apparatus for Fiberglass Reinforced Plastics Deck-to-Girder Connections | |
CN210288772U (en) | Wall combined brick | |
CN216007325U (en) | Connecting joint of steel beam and steel column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||