KR102008965B1 - Construction method for wall structure - Google Patents

Construction method for wall structure Download PDF

Info

Publication number
KR102008965B1
KR102008965B1 KR1020170102538A KR20170102538A KR102008965B1 KR 102008965 B1 KR102008965 B1 KR 102008965B1 KR 1020170102538 A KR1020170102538 A KR 1020170102538A KR 20170102538 A KR20170102538 A KR 20170102538A KR 102008965 B1 KR102008965 B1 KR 102008965B1
Authority
KR
South Korea
Prior art keywords
foundation
partition wall
wall
sheath
central
Prior art date
Application number
KR1020170102538A
Other languages
Korean (ko)
Other versions
KR20190017541A (en
Inventor
정태원
Original Assignee
한라산업개발 주식회사
주식회사 장헌산업
(주)한맥기술
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한라산업개발 주식회사, 주식회사 장헌산업, (주)한맥기술 filed Critical 한라산업개발 주식회사
Priority to KR1020170102538A priority Critical patent/KR102008965B1/en
Publication of KR20190017541A publication Critical patent/KR20190017541A/en
Application granted granted Critical
Publication of KR102008965B1 publication Critical patent/KR102008965B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/22Containers for fluent solids, e.g. silos, bunkers; Supports therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/22Containers for fluent solids, e.g. silos, bunkers; Supports therefor
    • E04H2007/225Silos with retaining wall type wall elements, e.g. trench silos

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법에 관한 것으로서, 상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계; 폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계; 상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계; 상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법을 제시함으로써, 시공이 안전하고, 공사기간을 단축할 수 있도록 한다.The present invention relates to a construction method of a wall structure having a central partition 10 installed along the front and rear direction, and a side partition wall 20 installed along the lateral direction on both sides of the central partition 10. A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed; The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare; The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101; And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked. By presenting the construction method of the wall structure, characterized in that the construction is safe and can shorten the construction period.

Description

벽체 구조물의 시공방법{CONSTRUCTION METHOD FOR WALL STRUCTURE}Construction method of wall structure {CONSTRUCTION METHOD FOR WALL STRUCTURE}

본 발명은 건설 분야에 관한 것으로서, 상세하게는 벽체 구조물의 시공방법에 관한 것이다.The present invention relates to the field of construction, and more particularly, to a construction method of a wall structure.

석탄 저장고(Coal Shed)란 석탄 화력발전소에서 대규모의 석탄을 저장하기 위해 사용되는 것으로서, 높이 및 폭이 수십m에 이르는 대규모의 벽체 구조물을 말한다.Coal Sheds are used to store large amounts of coal in coal-fired power plants. They are large-scale wall structures up to several tens of meters in height and width.

이는 중앙격벽과, 그 양측에 측방향을 따라 설치되는 복수의 측방격벽에 의해 다수의 구획된 석탄저장실을 구비한 구조를 취한다.It has a structure having a central partition and a plurality of partitioned coal storage chambers by a plurality of side partitions provided laterally on both sides thereof.

종래에는 거푸집을 설치하고 콘크리트를 현장타설하는 방식을 취하였는데, 이는 대규모의 구조물이므로, 시공이 어려워 안전성이 좋지 못하고, 공사기간이 길며, 공사비용이 많이 소요된다는 문제가 있었다.Conventionally, formwork was installed and concrete was cast in place, which is a large-scale structure, which is difficult to construct due to difficult construction, long construction period, and high cost of construction.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 하는 벽체 구조물의 시공방법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, the object of the present invention is to propose a construction method of the wall structure to be safe construction, shorten the construction period, and to reduce the construction cost.

상기 과제의 해결을 위하여, 본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서, 상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계; 폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계; 상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계; 상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법을 제시한다.In order to solve the above problems, the present invention provides a wall structure having a central partition 10 installed along the front and rear directions, and a side partition wall 20 provided on both sides of the central partition 10 in a lateral direction. As a construction method, the foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 will be installed; The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare; The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101; And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked. The construction method of the wall structure is characterized.

상기 단위부재(100)는, 양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103); 상기 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하고, 상기 가이드공(101)은 상기 보강벽부(104)에 형성되고, 상기 쉬스(1)는 상기 보강벽부(104) 또는 상기 측벽(103a)에 설치된 것이 바람직하다.The unit member 100 may include a body portion 103 having an H-shaped cross-section having sidewalls 103a formed on both sides thereof and a space 103b formed above and below; And a reinforcing wall portion 104 having a wall-shaped cross-sectional structure formed at an end or a central portion of the body portion 103, wherein the guide hole 101 is formed in the reinforcing wall portion 104, and the sheath 1 is It is preferable that the reinforcing wall portion 104 or the side wall 103a is provided.

상기 기초구조물(30)은 상기 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성되는 것이 바람직하다.The foundation structure 30 is formed by assembling a plurality of foundation members 300 manufactured by a precast method to support the unit member 100 and to form the foundation concrete casting region 302 in the core portion. It is preferable to be.

상기 격벽 형성단계는, 상기 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 상기 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계; 상기 최하단 단위부재(100a)의 가이드공(101)을 통해 상기 가이드봉(301)을 삽입하여, 상기 가이드봉(301)의 하단이 상기 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계; 상기 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 상기 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계;를 포함하는 것이 바람직하다.The partition forming step may include: a lowermost unit member mounting step of mounting a lowermost unit member 100a installed at a lowermost end of the plurality of unit members 100 on an upper portion of the base member 300; Inserting the guide rod 301 through the guide hole 101 of the lowest unit member (100a), the guide rod installation step so that the lower end of the guide rod 301 is located in the basic concrete placing area 302 ; It is preferable to include; foundation concrete placing step of embedding the lower end of the guide rod 301 by placing concrete in the foundation concrete placing area (302).

상기 격벽 형성단계는, 상기 기초콘크리트 타설단계 이전, 상기 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 상기 기초콘크리트 타설영역(302)에 "U"자형 구조의 상기 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를 더 포함하는 것이 바람직하다.The barrier rib forming step may include, before the foundation concrete placing step, the foundation sheath 1a having a “U” shape in the foundation concrete placing area 302 so as to communicate with the sheath 1 of the lowermost unit member 100a. It is preferable to further include; basic sheath installation step of installing).

상기 기초콘크리트 타설단계는, 상기 기초콘크리트 타설영역(302) 및 상기 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 것이 바람직하다.In the basic concrete placing step, it is preferable to pour the base concrete in the lower space 103b of the body portion 103 of the base concrete placing region 302 and the lowermost unit member 100a.

상기 기초부재(300)는, 상기 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 상기 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하고, 상기 중앙격벽 기초부재(310)는, 폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311); 상기 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312); 상기 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하고, 상기 측방격벽 기초부재(320)는, 길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321); 상기 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322); 상기 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하는 것이 바람직하다.The base member 300, the central partition base member 310 is installed along the lower region where the central partition 10 is to be installed; And a side partition foundation member 320 installed along a lower region in which the side partition walls 20 are to be installed, wherein the center partition foundation members 310 are provided along the longitudinal direction at intervals along the width direction. A pair of central bulkhead longitudinal foundation walls 311; A plurality of centers are provided at intervals along the longitudinal direction between the pair of central bulkhead longitudinal direction walls 311, and an insertion groove 313 is formed in which a lower portion of the unit member 100 is inserted. Partition wall width direction base wall 312; And a central bulkhead foundation concrete pouring area 302a formed between the pair of central bulkhead longitudinal base walls 311 and the plurality of central bulkhead widthwise foundation walls 312. Is a pair of side partition wall width direction base wall 321 provided along the width direction at intervals along the longitudinal direction; A plurality of side surfaces of the pair of side partition walls in the width direction of the base wall 321 are installed at intervals along the width direction, and an insertion groove 323 in which a lower portion of the unit member 100 is inserted is formed thereon. Partition longitudinal foundation walls 322; And a side partition wall concrete placing region 302b formed between the pair of side partition wall width direction base walls 321 and the plurality of side partition wall longitudinal base walls 322.

상기 단위부재(100)는, 상기 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110); 상기 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하고, 상기 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치되고, 상기 격벽 형성단계는, 복수의 상기 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계; 상기 결합작업공간(410)의 측방에 상기 측방격벽 단위부재(120)를 설치하는 단계; 상기 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 상기 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계; 상기 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를 포함하는 것이 바람직하다.The unit member 100 may include a central partition unit member 110 forming the central partition 10; And a side partition wall unit member 120 forming the side partition walls 20. The side wall 103a of the side partition wall unit member 120 is provided with a sheath 1 along a longitudinal direction, and the partition wall is formed. The step may include installing a plurality of the central partition unit members 110 at intervals along the longitudinal direction to form a coupling work space 410; Installing the side partition wall unit member 120 on the side of the coupling working space (410); Placing a sheath (1) in the coupling work space (410) and placing concrete so as to communicate with the sheath (1) of the side partition wall unit member (120) to form a coupling part (400); It is preferable to include; and to install the lateral tendon (2a) on the sheath (1) of the side partition wall unit member 120 and the sheath (1) of the coupling portion 400 and to fix the tension.

상기 중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의한 긴장재(2c)가 설치된 것이 바람직하다.The side wall 103a of the central partition wall unit member 110 is preferably provided with a tension member 2c by a pretension method along the longitudinal direction.

상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 상기 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성되고, 복수의 상기 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 상기 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 상기 결합부 콘크리트 타설영역(302c)의 양측에 설치된 상기 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 상기 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 하는 단계; 상기 결합부 콘크리트 타설영역(302c)의 일측에 상기 측방격벽 기초부재(320)를 설치하는 단계;를 포함하는 것이 바람직하다.One central partition longitudinal foundation of one of the pair of central partition longitudinal foundation walls 311 of the central partition foundation member 310 so that the coupling portion concrete placing region 302c is formed below the coupling portion 400. A closing extension portion 311c is formed at an end of the wall 311, and a plurality of the central partition foundation members 310 are provided at intervals along the longitudinal direction, and the coupling portion concrete placing region 302c is disposed therebetween. To be formed, but to close the other side of the coupling portion concrete placing area (302c) by the closing extension portion (311c) of the central partition base member 310 installed on both sides of the coupling portion concrete placing area (302c). Making; It is preferable to include; installing the side partition wall base member 320 on one side of the coupling portion concrete placing area (302c).

상기 격벽 형성단계는, 상기 복수의 단위부재(100) 중 일부를 적층하여 상기 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 상기 가이드공(101)에 충전재를 타설하되, 상기 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계; 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 상기 가이드봉(301)의 상단에 연장가이드봉(301a)을 연결하는 단계; 상기 연장가이드봉(301a)에 상기 가이드공(101)이 관통하도록, 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하는 단계;를 포함하는 것이 바람직하다.In the forming of the partition wall, a part of the plurality of unit members 100 may be stacked to form a part of the central partition wall 10 and the side partition wall 20, and the filler may be poured into the guide hole 101. Partial installation of a partition wall to expose the top of the guide rod 301; Connecting an extension guide rod (301a) to an upper end of the guide rod (301) exposed at an upper end of a portion of the central partition (10) and the side partition wall (20); Stacking the plurality of unit members (100) on top of a portion of the central partition wall (10) and the side partition wall (20) to allow the guide hole (101) to pass through the extension guide rod (301a); It is preferable to include.

상기 격벽 일부 설치단계는, 상기 격벽 일부의 측면과 상기 기초구조물(30)의 상면 사이에 전도방지부재(4)를 설치하는 단계;를 더 포함하는 것이 바람직하다.The partial installation of the partition wall may further include installing a fall prevention member 4 between a side surface of the partition wall and an upper surface of the foundation structure 30.

복수의 상기 전도방지부재(4)의 상단이 상기 결합부(400)의 네 귀퉁이에 각각 결합하는 것이 바람직하다.Upper ends of the plurality of anti-falling members 4 are preferably coupled to four corners of the coupling part 400, respectively.

상기 단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비하는 주두부 준비단계; 적층된 상기 복수의 단위부재(100)의 상단에 상기 주두부(500)를 설치하는 주두부 설치단계;를 더 포함하고, 상기 긴장정착단계는, 상기 기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 상기 복수의 단위부재(100)의 쉬스(1) 및 상기 주두부(500)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 상기 주두부(500)의 상면에 정착하는 것이 바람직하다.A head head preparation step of preparing a precast head head 500 having a wider width than that of the unit member 100 and having the sheath 1 installed along the vertical direction; A head head mounting step of installing the head head 500 to the upper end of the plurality of the unit member 100 is stacked; The tension fixing step, the base sheath buried in the foundation structure (30) 1a), a tendon 2 is installed on the sheath 1 of the plurality of unit members 100 and the sheath 1 of the head head 500, and are tensioned to fix the upper surface of the head head 500. It is desirable to.

상기 격벽 형성단계 이후, 상기 측방격벽(20)의 측방에 대하여 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 단계;를 더 포함하는 것이 바람직하다.After the partition forming step, the step of installing the formwork for the side of the side partition wall 20 and the concrete is poured to form an extended side partition wall (21); preferably.

본 발명은 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 하는 벽체 구조물의 시공방법을 제시한다.The present invention proposes a construction method of a wall structure that is safe to construction, can shorten the construction period, and can reduce the construction cost.

도 1 이하는 본 발명에 의한 벽체 구조물의 시공방법의 실시예를 도시한 것으로서,
도 1은 석탄 저장고의 정면도.
도 2는 석탄 저장고의 평면도.
도 3은 중앙격벽 단위부재의 평면도.
도 4는 중앙격벽 단위부재의 제1 종단면도.
도 5는 도 4의 A-A 단면도.
도 6은 도 4의 B-B 단면도.
도 7은 중앙격벽 단위부재의 제2 종단면도.
도 8은 도 7의 A-A 단면도.
도 9는 도 7의 B-B 단면도.
도 10은 측방격벽 단위부재의 횡단면도.
도 11은 측방격벽 단위부재의 제1 종단면도.
도 12는 도 11의 A-A 단면도.
도 13은 도 11의 B-B 단면도.
도 14는 측방격벽 단위부재의 제2 종단면도.
도 15는 측방격벽 단위부재의 정면도.
도 16은 도 14의 B-B 단면도.
도 17은 중앙격벽 기초부재의 제1 실시예의 사시도.
도 18은 중앙격벽 기초부재의 제1 실시예의 평면도.
도 19는 중앙격벽 기초부재의 제2 실시예의 사시도.
도 20은 중앙격벽 기초부재의 제2 실시예의 평면도.
도 21은 측방격벽 기초부재의 평면도.
도 22 내지 25는 제1 실시예의 공정도.
도 26 내지 38은 제2 실시예의 공정도.
도 39,40은 제3 실시예의 공정도.
Figure 1 below shows an embodiment of the construction method of the wall structure according to the present invention,
1 is a front view of a coal reservoir.
2 is a plan view of a coal reservoir.
3 is a plan view of the central bulkhead unit member.
Figure 4 is a first longitudinal cross-sectional view of the central partition unit member.
5 is a cross-sectional view taken along AA of FIG. 4.
6 is a cross-sectional view taken along line BB of FIG. 4.
7 is a second longitudinal cross-sectional view of the central bulkhead unit member.
8 is a cross-sectional view taken along AA of FIG. 7.
9 is a cross-sectional view taken along line BB of FIG. 7.
10 is a cross-sectional view of the side bulkhead unit member.
11 is a first longitudinal cross-sectional view of the side partition wall unit member.
12 is a cross-sectional view taken along AA of FIG. 11.
13 is a cross-sectional view taken along line BB of FIG.
14 is a second longitudinal sectional view of the side bulkhead unit member.
15 is a front view of the side partition wall unit member.
FIG. 16 is a cross-sectional view taken along line BB of FIG. 14.
17 is a perspective view of a first embodiment of a central partition base member.
18 is a plan view of a first embodiment of a central partition base member;
19 is a perspective view of a second embodiment of a central partition base member;
20 is a plan view of a second embodiment of a central partition foundation member;
21 is a plan view of the side partition foundation member.
22-25 are process diagrams of the first embodiment.
26 to 38 are process diagrams of a second embodiment.
39 and 40 are process diagrams of the third embodiment.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 이하에 도시된 바와 같이, 본 발명은 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서, 기본적으로 다음과 같은 공정에 의해 이루어진다.As shown in Figure 1 below, the present invention is a wall structure having a central partition 10 is installed in the longitudinal direction along the longitudinal direction, and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction As a construction method of, it is basically made by the following process.

이하에서는 본 발명이 대규모의 석탄 저장고(Coal Shed)에 적용된 실시예에 대하여 설명한다.Hereinafter, an embodiment in which the present invention is applied to a large-scale coal shed will be described.

중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치한다(기초구조물 설치단계, 도 17 내지 21,22,26,27).The foundation 30 is installed along the lower region where the central partition 10 and the side partition 20 are to be installed (base structure installation step, FIGS. 17 to 21, 22, 26, and 27).

폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비한다(단위부재 준비단계, 도 3 내지 16).The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Prepare (unit member preparation step, Figures 3 to 16).

기초구조물(30)에 하단이 매설된 가이드봉(301)에 가이드공(101)이 관통하도록, 기초구조물(30)의 상부에 복수의 단위부재(100)를 적층하여 설치하여 중앙격벽(10) 및 측방격벽(20)을 형성하고, 가이드공(101)에 충전재(M)를 타설한다(격벽 형성단계, 도 23 내지 25, 도 28 내지 37).The central partition 10 is installed by stacking a plurality of unit members 100 on the upper portion of the basic structure 30 so that the guide hole 101 penetrates the guide rod 301 having the lower end embedded in the basic structure 30. And a side partition wall 20, and the filler M is poured into the guide hole 101 (the partition wall forming step, FIGS. 23 to 25, and FIGS. 28 to 37).

기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착한다(긴장정착단계, 도 38).Tendon 2 is installed and tensioned in the sheath 1 of the foundation sheath 1a embedded in the foundation structure 30 and the stacked unit members 100 (tension fixing step, FIG. 38).

석탄 저장고는 도 1,2에 도시된 바와 같이, 전후방향을 따라 길게 설치되는 중앙격벽(10)과, 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)에 의해 구성되므로, 그 자체로 자립이 가능하다.As shown in Figures 1 and 2, the coal reservoir is composed of a central partition 10 is installed in the longitudinal direction in the longitudinal direction, and the side partition wall 20 is installed in both sides of the central partition 10 in the lateral direction. Indeed, self-reliance is possible.

본 발명은 이에 착안한 것으로서, 기초구조물(30)에 매설된 가이드봉(301)에 의해 가이드되도록, 복수의 단위부재(100)를 적층하여 설치하여 중앙격벽(10) 및 측방격벽(20)을 형성하고, 가이드공(101)의 충전 및 텐던(2)의 정착에 의해 석탄 저장고를 시공하는 방식을 취한 것이다.The present invention was conceived in this regard, the central partition wall 10 and the side partition wall 20 by installing a plurality of unit members 100 are laminated so as to be guided by the guide rod 301 embedded in the foundation structure 30 And a method of constructing a coal reservoir by filling the guide hole 101 and fixing the tendon 2.

이는 대규모의 구조물의 시공방법임에 불구하고, 시공 중 구조물의 자립이 가능하도록 하므로, 종래의 거푸집 설치 및 현장타설 방식에 비해, 시공이 안전하고, 공사기간을 단축할 수 있으며, 공사비용을 절감할 수 있도록 한다는 장점이 있다.Although this is a method of constructing a large-scale structure, it enables the structure to stand on its own during construction. Therefore, construction is safer, construction time can be shorter, and construction cost can be reduced compared to the conventional formwork and site casting method. The advantage is that it can be done.

이하, 본 발명에 의한 벽체 구조물의 시공방법의 구체적 실시예에 대하여 설명한다.Hereinafter, specific examples of the construction method of the wall structure according to the present invention will be described.

단위부재(100)는, 양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103); 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하여 구성된다(도 3 내지 16).The unit member 100 may include a body portion 103 having an H-shaped cross-section having sidewalls 103a formed on both sides thereof, and a space 103b formed above and below; And a reinforcing wall portion 104 having a wall-shaped cross-sectional structure formed at an end portion or a central portion of the trunk portion 103 (FIGS. 3 to 16).

즉, 보강벽부(104)는 몸통부(103)의 양단부에만 형성될 수도 있고, 추가로 중앙부에 형성될 수도 있다.That is, the reinforcing wall portion 104 may be formed only at both ends of the body portion 103, or may be further formed in the central portion.

가이드공(101)은 보강벽부(104)에 형성되고, 쉬스(1)는 보강벽부(104) 또는 측벽(103a)에 설치된다.The guide hole 101 is formed in the reinforcement wall part 104, and the sheath 1 is provided in the reinforcement wall part 104 or the side wall 103a.

기초구조물(30)은 전체적으로 콘크리트 현장타설 방식에 의해 형성될 수도 있으나, 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성된 구조를 취하는 것이 시공성 측면에서 바람직하다(도 17 내지 21).Although the basic structure 30 may be formed by a concrete cast-in-place method as a whole, it is preferable to take a structure formed by assembling a plurality of base members 300 manufactured by a precast method (from FIG. 17 to FIG. 17). 21).

기초부재(300)는 위 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 하는 구조로 형성된다(도 22).The base member 300 supports the unit member 100 and is formed in a structure such that the foundation concrete pouring area 302 is formed in the core portion (FIG. 22).

상기 격벽 형성단계는, 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계(도 23,28,29); 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)을 삽입하여, 가이드봉(301)의 하단이 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계(도 30,31); 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계(도 32,33);를 포함하여 구성될 수 있다.The partition wall forming step may include a lowermost unit member mounting step of mounting the lowermost unit member 100a installed at the lowermost of the plurality of unit members 100 on the upper portion of the base member 300 (FIGS. 23, 28, 29); Inserting the guide rod 301 through the guide hole 101 of the lowermost unit member (100a), the guide rod installation step so that the lower end of the guide rod 301 is located in the basic concrete placing area (302) (Fig. 30, 31); It can be configured to include; foundation concrete placing step (Fig. 32, 33) to pour the bottom of the guide rod 301 by placing concrete in the foundation concrete placing area (302).

즉, 기초구조물(30)에 가이드봉(301)의 하단을 먼저 매설하고, 이후 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)이 삽입되는 방식을 취할 수도 있으나, 상술한 바와 같이 먼저 최하단 단위부재(100a)를 기초부재(300)의 상부에 거치한 후, 최하단 단위부재(100a)의 가이드공(101)을 통해 가이드봉(301)을 삽입하여, 가이드봉(301)의 하단이 기초구조물(30)에 매설되도록 하는 경우, 가이드봉(301)의 설치위치가 자연스럽게 결정되므로 시공이 더욱 편리하다는 장점이 있다.That is, the lower end of the guide rod 301 is first embedded in the basic structure 30, and then the guide rod 301 may be inserted through the guide hole 101 of the lowermost unit member 100a, but the above-described method may be used. As described above, the lowermost unit member 100a is first mounted on the upper portion of the base member 300, and then the guide rod 301 is inserted through the guide hole 101 of the lowermost unit member 100a to guide the guide rod 301. When the lower end of the) to be embedded in the foundation structure 30, there is an advantage that the installation is more convenient because the installation position of the guide rod 301 is naturally determined.

상기 격벽 형성단계는, 기초콘크리트 타설단계 이전, 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 기초콘크리트 타설영역(302)에 "U"자형 구조의 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를 더 포함하여 구성될 수 있다(도 30,31).In the partition forming step, the base sheath 1a having a “U” -shaped structure is installed in the foundation concrete placing area 302 so as to communicate with the sheath 1 of the lowermost unit member 100a before the foundation concrete placing step. Foundation sheath installation step; may be configured to include more (FIGS. 30, 31).

이러한 기초 쉬스(1a)는 추후 긴장정착단계(도 38)에서 격벽 및 기초구조물 전체에 대하여 텐던(2)을 "U"자형으로 배치하여 긴장하고 정착할 수 있도록 한다.The foundation sheath 1a is arranged to tension and settle the tendon 2 in a "U" shape in relation to the bulkhead and the foundation structure in a later tension fixing step (FIG. 38).

기초구조물(30)의 형성을 위하여 기초부재(300)의 기초콘크리트 타설영역(302)에만 기초콘크리트를 타설할 수도 있으나, 기초콘크리트 타설영역(302) 및 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 경우, 취약한 격벽의 하단을 보강할 수 있다는 장점이 추가된다(도 32,33).In order to form the foundation 30, the foundation concrete may be poured only in the foundation concrete placing region 302 of the foundation member 300, but the body portion 103 of the foundation concrete placing region 302 and the lowermost unit member 100a When placing the foundation concrete in the lower space (103b) of the), the advantage that can be reinforced the bottom of the vulnerable partition wall is added (FIGS. 32, 33).

필요한 경우, 최하단 단위부재(100a) 뿐만 아니라, 그 상부에 배치되는 단위부재(100)의 공간에 대하여도 콘크리트를 타설하여 보강할 수 있다.If necessary, concrete may be poured into and reinforce not only the lowermost unit member 100a but also the space of the unit member 100 disposed thereon.

기초부재(300)는 기본적으로, 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하여 구성된다(도 2,22 내지 25).The base member 300 basically includes a central partition base member 310 installed along a lower region in which the central partition 10 is to be installed; It is configured to include; the side partition wall base member 320 is installed along the lower region where the side partition wall 20 is to be installed (Figs. 2, 22 to 25).

중앙격벽 기초부재(310)는 구체적으로, 폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311); 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312); 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하여 구성된다(도 17 내지 20).The center partition base member 310 may include, in particular, a pair of center partition longitudinal base walls 311 installed along the longitudinal direction at intervals along the width direction; A plurality of central bulkhead widths are provided at intervals along the longitudinal direction between the pair of central bulkhead longitudinal direction walls 311 and an insertion groove 313 is formed in which a lower portion of the unit member 100 is inserted. Directional foundation walls 312; And a central bulkhead foundation concrete pouring area 302a formed between the pair of central bulkhead longitudinal foundation walls 311 and the plurality of central bulkhead widthwise foundation walls 312 (FIGS. 17 to 20).

측방격벽 기초부재(320)는 구체적으로, 길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321); 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322); 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하여 구성된다(도 21).The side partition wall base member 320 may include, in particular, a pair of side partition wall width direction base walls 321 provided along the width direction with a distance along the length direction; A plurality of side partition walls having a gap between the pair of side barrier ribs in the width direction of the base wall 321 are installed along the width direction and having an insertion groove 323 into which the lower portion of the unit member 100 is inserted. Directional base wall 322; And a side partition wall concrete placing region 302b formed between the pair of side partition wall width direction foundation walls 321 and the plurality of side partition wall longitudinal foundation walls 322 (FIG. 21).

단위부재(100)는 기본적으로, 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110); 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하여 구성되는데(도 1,2), 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치된다(도 10,14,15).The unit member 100 basically includes a central partition unit member 110 forming a central partition 10; The side partition wall unit member 120 forming the side partition wall 20; is configured to include (Fig. 1, 2), the side wall 103a of the side partition wall unit member 120, the sheath 1 along the longitudinal direction It is installed (FIGS. 10, 14, 15).

이 경우 상기 격벽 형성단계는, 복수의 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계; 결합작업공간(410)의 측방에 측방격벽 단위부재(120)를 설치하는 단계; 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계; 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를 포함하여 구성될 수 있다(도 23 내지 25).In this case, the forming of the partition wall may include installing a plurality of central partition unit members 110 at intervals along the length direction to form a coupling work space 410; Installing a side partition wall unit member 120 on the side of the coupling working space 410; Placing the sheath 1 in the coupling work space 410 and placing concrete so as to communicate with the sheath 1 of the side partition wall unit member 120 to form the coupling part 400; And installing the lateral tendons 2a on the sheath 1 of the lateral bulkhead unit member 120 and the sheath 1 of the coupling part 400 and tensioning and fixing them (FIGS. 23 to 23). 25).

즉, 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 사이에 결합작업공간(410)이 형성되도록 한 후, 이에 별도로 콘크리트를 타설하여 결합부(400)를 형성하고, 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 설치된 측방향 텐던(2a)의 긴장 및 정착에 의해 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 일체화 구조가 형성되도록 한 것이다.That is, after the coupling work space 410 is formed between the central bulkhead unit member 110 and the side partition wall unit member 120, concrete is poured separately to form the coupling portion 400, the side bulkhead unit Tension and fixation of the lateral tendons 2a provided in the sheath 1 of the member 120 and the sheath 1 of the coupling part 400 of the central bulkhead unit member 110 and the side bulkhead unit member 120. It is intended to form an integrated structure.

중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의해 긴장재(2c)를 설치하는 것이 시공성 및 구조적 안정성을 위하여 바람직하다(도 7 내지 9).It is preferable to install the tension member 2c on the side wall 103a of the central partition unit member 110 by a pretensioning method along the longitudinal direction (for FIGS. 7 to 9).

또한, 중앙격벽 단위부재(110)와 측방격벽 단위부재(120)의 적층구조는 전체적으로 동일한 높이를 유지하도록 시공함으로써, 그 자체로 자립구조를 취하도록 하는 것이 안전한 시공을 위하여 바람직하다.In addition, the laminated structure of the central partition unit member 110 and the side partition wall unit member 120 is preferably constructed to maintain the same height as a whole, so that the self-supporting structure itself is preferable for safe construction.

상술한 바와 같이 기초부재(300)는, 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310); 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하여 구성되는데, 상술한 중앙격벽 단위부재(110) 및 측방격벽 단위부재(120)의 편리한 시공을 위하여, 위 기초부재(300)는 다음과 같은 구성 및 공정을 취하는 것이 바람직하다(도 22 내지 25).As described above, the base member 300 includes: a central partition base member 310 installed along a lower region in which the central partition 10 is to be installed; The side partition wall base member 320 is installed along the lower region in which the side partition wall 20 is to be installed, which is configured to include, for convenient construction of the above-described central partition unit member 110 and the side partition unit 120. , The base member 300 is preferably to take the following configuration and process (FIGS. 22 to 25).

즉, 상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성된다(도 17 내지 20).That is, the center partition longitudinal direction of one of the pair of central bulkhead longitudinal direction base walls 311 of the central partition foundation member 310 so that the coupling portion concrete placing region 302c is formed below the coupling portion 400. A closing extension part 311c is formed at the end of the base wall 311 (FIGS. 17 to 20).

이러한 구조를 취하는 경우, 복수의 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 결합부 콘크리트 타설영역(302c)의 양측에 설치된 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 할 수 있다.In this structure, a plurality of central bulkhead foundation members 310 are installed at intervals along the lengthwise direction such that the joint concrete placing region 302c is formed therebetween, The other end of the coupling portion concrete placing area 302c may be closed by the closing extension part 311c of the central partition base member 310 installed at both sides.

결합부 콘크리트 타설영역(302c)의 일측에는 측방격벽 기초부재(320)를 설치하여 폐쇄할 수 있다.One side of the coupling portion concrete placing area 302c may be installed by closing the side partition base member 320.

격벽의 높이가 높으므로, 일부씩 나누어 시공하는 것이 바람직하다.Since the height of a partition is high, it is preferable to divide and install by one part.

즉, 복수의 단위부재(100) 중 일부를 적층하여 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 가이드공(101)에 충전재를 타설하되, 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계; 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 가이드봉(301)의 상단에 커플러 등을 이용하여 연장가이드봉(301a)을 연결하는 단계; 연장가이드봉(301a)에 가이드공(101)이 관통하도록, 상중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 복수의 단위부재(100)를 적층하여 설치하는 단계;를 포함하는 것이 바람직하다(도 34 내지 36).That is, a part of the plurality of unit members 100 are stacked to form part of the central partition wall 10 and the side partition wall 20, and the filler is poured into the guide hole 101, but the upper end of the guide rod 301 is Partial installation of the partition wall to be exposed; Connecting the extension guide rods 301a to the upper ends of the guide rods 301 exposed at the upper ends of the central bulkhead 10 and the side partition walls 20 using a coupler or the like; And stacking a plurality of unit members 100 on top of a portion of the upper middle partition wall 10 and the side partition wall 20 so that the guide hole 101 passes through the extension guide rod 301a. It is preferable (FIGS. 34-36).

본 발명에 의한 시공방법에 의한 석탄 저장고는 시공 중 상술한 바와 같은 자립 구조를 취하지만, 일정 높이마다 전도방지부재(4)를 설치하는 경우, 더욱 안전한 시공이 가능하다(도 39,40).The coal storage by the construction method according to the present invention takes the self-supporting structure as described above during construction, but when the fall prevention member 4 is installed at a predetermined height, more safe construction is possible (Figs. 39 and 40).

즉, 격벽 일부의 측면과 기초구조물(30)의 상면 사이에 전도방지부재(4)를 순차적으로 설치하는 것이 바람직하다.That is, it is preferable to sequentially install the fall prevention member 4 between the side surface of the partition and the upper surface of the foundation structure 30.

구체적으로, 복수의 전도방지부재(4)의 상단이 결합부(400)의 네 귀퉁이에 각각 결합하도록 하는 것이 구조적 안정성을 위하여 바람직하다(도 40).Specifically, it is preferable for structural stability that the upper ends of the plurality of anti-conduction members 4 are respectively coupled to four corners of the coupling part 400 (FIG. 40).

격벽의 상단에는 프리캐스트 주두부(500)를 다음과 같은 공정에 의해 설치한다.On the upper end of the partition wall, the precast head 500 is installed by the following process.

단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비한 후, 적층된 복수의 단위부재(100)의 상단에 주두부(500)를 설치한다(도 36).After forming the precast head 500 having a wider width than the unit member 100 and having the sheath 1 installed along the vertical direction, the head head 500 is disposed on the upper ends of the plurality of stacked unit members 100. ) Is installed (FIG. 36).

기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 복수의 단위부재(100)의 쉬스(1) 및 주두부(500)의 쉬스(1)에 텐던(2)을 "U"자형 구조로 설치하고 긴장하여 주두부(500)의 상면에 정착한다(도 37).The "U" shaped structure of the tendon sheath (1a) embedded in the foundation structure (30), the sheath (1) of the plurality of unit members (100) stacked, and the tendon (2) on the sheath (1) of the head head (500). It is installed and tensioned to settle on the upper surface of the head (500) (Fig. 37).

석탄 저장고의 중앙 격벽(10) 및 측방격벽(20)의 전부를 상술한 복수의 단위부재(100)의 적층 방식에 의해 시공할 수도 있으나, 이는 기본적으로 시공 중 구조물의 자립을 위한 것이므로, 반드시 측방격벽(20)의 전부를 이러한 방식에 의해 시공할 필요는 없다.Although all of the central bulkhead 10 and the side bulkhead 20 of the coal storage may be constructed by the stacking method of the plurality of unit members 100 described above, since this is basically intended for self-reliance of the structure during construction, It is not necessary to construct all of the partition walls 20 in this manner.

따라서 구조물의 자립이 가능한 정도로만 측방격벽(20)의 일부를 복수의 단위부재(100)의 적층 방식에 의해 시공하고, 측방격벽(20)의 측방 나머지 영역에 대하여는 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 것이 경제성 측면에서 바람직하다(도 1).Therefore, only a part of the side partition wall 20 is constructed by the stacking method of the plurality of unit members 100 to the extent that the structure can be self-supporting, and form a formwork for the remaining side areas of the side partition wall 20 and extend it by pouring concrete. It is preferable from the viewpoint of economics to form the side partition wall 21 (FIG. 1).

이상에서는 본 발명에 의한 벽체 구조물이 석탄 저장고(Coal Shed)에 적용되는 경우의 실시예에 관하여 설명하였으나, 그 밖의 벽체 구조물에 대하여도 효과적으로 적용될 수 있다.In the above described an embodiment in the case where the wall structure according to the present invention is applied to the coal shed (Coal Shed), it can be effectively applied to other wall structures.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.

1 : 쉬스 1a : 기초 쉬스
2 : 텐던 2a : 측방향 텐던
2c : 프리텐션 긴장재 4 : 전도방지부재
10 : 중앙격벽 20 : 측방격벽
21 : 연장측방격벽 30 : 기초구조물
100 : 단위부재 100a : 최하단 단위부재
101 : 가이드공 103 : 몸통부
103a : 측벽 103b : 공간
104 : 보강벽부 110 : 중앙격벽 단위부재
120 : 측방격벽 단위부재 300 : 기초부재
301 : 가이드봉 301a : 연장가이드봉
302 : 기초콘크리트 타설영역
302a : 중앙격벽 기초콘크리트 타설영역
302b : 측방격벽 기초콘크리트 타설영역
302c : 결합부 기초콘크리트 타설영역
310 : 중앙격벽 기초부재 311 : 중앙격벽 길이방향 기초벽
311c : 폐쇄용 연장부 312 : 폭방향 기초벽
313 : 삽입홈 320 : 측방격벽 기초부재
321 : 측방격벽 폭방향 기초벽 322 : 측방격벽 길이방향 기초벽
323 : 삽입홈 400 : 결합부
410 : 결합작업공간 500 : 프리캐스트 주두부
1: Sheath 1a: Foundation Sheath
2: tendon 2a: lateral tendon
2c: pretension tension member 4: fall prevention member
10: center bulkhead 20: side bulkhead
21: extension side partition wall 30: foundation structure
100: unit member 100a: lowest unit member
101: guide ball 103: the body
103a: side wall 103b: space
104: reinforcing wall portion 110: central bulkhead unit member
120: side bulkhead unit member 300: base member
301: guide rod 301a: extension guide rod
302: Foundation concrete pouring area
302a: Central concrete foundation concrete casting area
302b: Lateral bulkhead foundation concrete casting area
302c: Foundation concrete casting area
310: center partition foundation member 311: center partition longitudinal foundation wall
311c: closing extension 312: widthwise base wall
313: insertion groove 320: side partition wall foundation member
321: side bulkhead width direction foundation wall 322: side bulkhead longitudinal direction wall
323: insertion groove 400: coupling portion
410: combined working space 500: precast head tofu

Claims (15)

전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서,
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 단위부재(100)는,
양측에 측벽(103a)이 형성되고, 상하에 공간(103b)이 형성된 H형 단면구조의 몸통부(103);
상기 몸통부(103)의 단부 또는 중앙부에 형성된 벽체형 단면구조의 보강벽부(104);를 포함하고,
상기 가이드공(101)은 상기 보강벽부(104)에 형성되고,
상기 쉬스(1)는 상기 보강벽부(104) 또는 상기 측벽(103a)에 설치된 것을 특징으로 하는 벽체 구조물의 시공방법.
As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
The unit member 100,
A body portion 103 having an H-shaped cross-sectional structure having side walls 103a formed on both sides and a space 103b formed above and below;
And a reinforcing wall portion 104 having a wall-shaped cross-sectional structure formed at an end portion or a central portion of the body portion 103.
The guide hole 101 is formed in the reinforcing wall portion 104,
The sheath (1) is a method of constructing a wall structure, characterized in that installed on the reinforcing wall portion (104) or the side wall (103a).
삭제delete 제1항에 있어서,
상기 기초구조물(30)은 상기 단위부재(100)를 지지함과 아울러, 심부에 기초콘크리트 타설영역(302)이 형성되도록 프리캐스트 방식에 의해 제조된 복수의 기초부재(300)의 조립에 의해 형성되는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 1,
The foundation structure 30 is formed by assembling a plurality of foundation members 300 manufactured by a precast method to support the unit member 100 and to form the foundation concrete casting region 302 in the core portion. Construction method of the wall structure, characterized in that the.
제3항에 있어서,
상기 격벽 형성단계는,
상기 복수의 단위부재(100) 중 최하단에 설치되는 최하단 단위부재(100a)를 상기 기초부재(300)의 상부에 거치하는 최하단 단위부재 거치단계;
상기 최하단 단위부재(100a)의 가이드공(101)을 통해 상기 가이드봉(301)을 삽입하여, 상기 가이드봉(301)의 하단이 상기 기초콘크리트 타설영역(302)에 위치하도록 하는 가이드봉 설치단계;
상기 기초콘크리트 타설영역(302)에 콘크리트를 타설하여 상기 가이드봉(301)의 하단을 매설하는 기초콘크리트 타설단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 3,
The partition wall forming step,
A lowermost unit member mounting step of mounting the lowermost unit member 100a installed at the lowermost end of the plurality of unit members 100 on the upper portion of the base member 300;
Inserting the guide rod 301 through the guide hole 101 of the lowest unit member (100a), the guide rod installation step so that the lower end of the guide rod 301 is located in the basic concrete placing area 302 ;
A foundation concrete placing step of placing concrete at the foundation concrete placing area 302 to bury the lower end of the guide rod 301;
Construction method of a wall structure comprising a.
제4항에 있어서,
상기 격벽 형성단계는,
상기 기초콘크리트 타설단계 이전,
상기 최하단 단위부재(100a)의 쉬스(1)와 상호 연통하도록, 상기 기초콘크리트 타설영역(302)에 "U"자형 구조의 상기 기초 쉬스(1a)를 설치하는 기초 쉬스 설치단계;를
더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 4, wherein
The partition wall forming step,
Before the foundation concrete pouring step,
A foundation sheath installation step of installing the foundation sheath 1a having a “U” shaped structure in the foundation concrete placing region 302 so as to communicate with the sheath 1 of the lowermost unit member 100a;
Construction method of the wall structure, characterized in that it further comprises.
제4항에 있어서,
상기 기초콘크리트 타설단계는,
상기 기초콘크리트 타설영역(302) 및 상기 최하단 단위부재(100a)의 몸통부(103)의 하부 공간(103b)에 기초콘크리트를 타설하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 4, wherein
The foundation concrete pouring step,
Construction method of the wall structure, characterized in that the foundation concrete is cast in the lower space (103b) of the base concrete placing area (302) and the lower body unit 103 of the lowermost unit member (100a).
제3항에 있어서,
상기 기초부재(300)는,
상기 중앙격벽(10)이 설치될 하부 영역을 따라 설치되는 중앙격벽 기초부재(310);
상기 측방격벽(20)이 설치될 하부 영역을 따라 설치되는 측방격벽 기초부재(320);를 포함하고,
상기 중앙격벽 기초부재(310)는,
폭방향을 따라 간격을 두고 길이방향을 따라 설치된 한 쌍의 중앙격벽 길이방향 기초벽(311);
상기 한 쌍의 중앙격벽 길이방향 기초벽(311)의 사이에 길이방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(313)이 형성된 복수의 중앙격벽 폭방향 기초벽(312);
상기 한 쌍의 중앙격벽 길이방향 기초벽(311) 및 복수의 중앙격벽 폭방향 기초벽(312) 사이에 형성된 중앙격벽 기초콘크리트 타설영역(302a);을 포함하고,
상기 측방격벽 기초부재(320)는,
길이방향을 따라 간격을 두고 폭방향을 따라 설치된 한 쌍의 측방격벽 폭방향 기초벽(321);
상기 한 쌍의 측방격벽 폭방향 기초벽(321)의 사이에 폭방향을 따라 간격을 두고 설치됨과 아울러, 상부에 상기 단위부재(100)의 하부가 삽입되는 삽입홈(323)이 형성된 복수의 측방격벽 길이방향 기초벽(322);
상기 한 쌍의 측방격벽 폭방향 기초벽(321) 및 복수의 측방격벽 길이방향 기초벽(322) 사이에 형성된 측방격벽 기초콘크리트 타설영역(302b);을 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 3,
The base member 300,
A central partition base member 310 installed along a lower region in which the central partition 10 is to be installed;
And a side partition foundation member 320 installed along a lower region in which the side partition walls 20 are to be installed.
The central partition base member 310,
A pair of central bulkhead longitudinal foundation walls 311 provided along the longitudinal direction at intervals along the width direction;
A plurality of centers are provided at intervals along the longitudinal direction between the pair of central bulkhead longitudinal direction walls 311, and an insertion groove 313 is formed in which a lower portion of the unit member 100 is inserted. Partition wall width direction base wall 312;
And a central bulkhead foundation concrete pouring area 302a formed between the pair of central bulkhead longitudinal foundation walls 311 and the plurality of central bulkhead widthwise foundation walls 312.
The side partition wall member 320,
A pair of side partition wall width direction base walls 321 provided along the width direction at intervals along the length direction;
A plurality of side surfaces of the pair of side partition walls in the width direction of the base wall 321 are installed at intervals along the width direction, and an insertion groove 323 in which a lower portion of the unit member 100 is inserted is formed thereon. Partition longitudinal foundation walls 322;
A method of constructing a wall structure comprising a; side partition wall foundation concrete placing area 302b formed between the pair of side partition wall width direction base walls 321 and the plurality of side partition wall longitudinal base walls 322. .
제7항에 있어서,
상기 단위부재(100)는,
상기 중앙격벽(10)을 형성하는 중앙격벽 단위부재(110);
상기 측방격벽(20)을 형성하는 측방격벽 단위부재(120);를 포함하고,
상기 측방격벽 단위부재(120)의 측벽(103a)에는 길이방향을 따라 쉬스(1)가 설치되고,
상기 격벽 형성단계는,
복수의 상기 중앙격벽 단위부재(110)를 길이방향을 따라 간격을 두고 설치하여 결합작업공간(410)이 형성되도록 하는 단계;
상기 결합작업공간(410)의 측방에 상기 측방격벽 단위부재(120)를 설치하는 단계;
상기 측방격벽 단위부재(120)의 쉬스(1)와 상호 연통하도록, 상기 결합작업공간(410)에 쉬스(1)를 배치하고 콘크리트를 타설하여 결합부(400)를 형성하는 단계;
상기 측방격벽 단위부재(120)의 쉬스(1) 및 결합부(400)의 쉬스(1)에 측방향 텐던(2a)을 설치하고 긴장하여 정착하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 7, wherein
The unit member 100,
A central partition unit member 110 forming the central partition 10;
And a side partition unit member 120 forming the side partition walls 20.
A sheath 1 is installed along the longitudinal direction of the side wall 103a of the side partition wall unit member 120.
The partition wall forming step,
Installing a plurality of the central partition unit member 110 at intervals along the longitudinal direction to form a coupling working space (410);
Installing the side partition wall unit member 120 on the side of the coupling working space (410);
Placing a sheath (1) in the coupling work space (410) and placing concrete so as to communicate with the sheath (1) of the side partition wall unit member (120) to form a coupling part (400);
Installing and tensioning the lateral tendons 2a on the sheath 1 of the side partition wall unit member 120 and the sheath 1 of the coupling part 400;
Construction method of a wall structure comprising a.
제8항에 있어서,
상기 중앙격벽 단위부재(110)의 측벽(103a)에는 길이방향을 따라 프리텐션 방식에 의한 긴장재(2c)가 설치된 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 8,
Method of constructing a wall structure, characterized in that the tension member (2c) by the pretension method is installed in the side wall (103a) of the central partition unit member (110) in the longitudinal direction.
제8항에 있어서,
상기 결합부(400)의 하부에 결합부 콘크리트 타설영역(302c)이 형성되도록, 상기 중앙격벽 기초부재(310)의 한 쌍의 중앙격벽 길이방향 기초벽(311) 중 하나의 중앙격벽 길이방향 기초벽(311)의 단부에는 폐쇄용 연장부(311c)가 형성되고,
복수의 상기 중앙격벽 기초부재(310)를 길이방향을 따라 간격을 두고 설치하여 그 사이에 상기 결합부 콘크리트 타설영역(302c)이 형성되도록 하되, 상기 결합부 콘크리트 타설영역(302c)의 양측에 설치된 상기 중앙격벽 기초부재(310)의 폐쇄용 연장부(311c)에 의해 상기 결합부 콘크리트 타설영역(302c)의 타측을 폐쇄하도록 하는 단계;
상기 결합부 콘크리트 타설영역(302c)의 일측에 상기 측방격벽 기초부재(320)를 설치하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 8,
One central partition longitudinal foundation of one of the pair of central partition longitudinal foundation walls 311 of the central partition foundation member 310 so that the coupling portion concrete placing region 302c is formed below the coupling portion 400. At the end of the wall 311 a closing extension 311c is formed,
A plurality of central bulkhead foundation members 310 are installed at intervals along the lengthwise direction such that the coupling part concrete placing area 302c is formed therebetween, and is installed at both sides of the coupling part concrete placing area 302c. Closing the other side of the coupling part concrete placing area (302c) by the closing extension part (311c) of the central partition base member (310);
Installing the side partition wall base member 320 on one side of the coupling portion concrete placing area (302c);
Construction method of a wall structure comprising a.
제8항에 있어서,
상기 격벽 형성단계는,
상기 복수의 단위부재(100) 중 일부를 적층하여 상기 중앙격벽(10) 및 측방격벽(20)의 일부를 형성하고, 상기 가이드공(101)에 충전재를 타설하되, 상기 가이드봉(301)의 상단이 노출되도록 하는 격벽 일부 설치단계;
상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상단에 노출된 상기 가이드봉(301)의 상단에 연장가이드봉(301a)을 연결하는 단계;
상기 연장가이드봉(301a)에 상기 가이드공(101)이 관통하도록, 상기 중앙격벽(10) 및 측방격벽(20)의 일부의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하는 단계;를
포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 8,
The partition wall forming step,
Some of the plurality of unit members 100 are stacked to form part of the central partition wall 10 and the side partition wall 20, and the filler is poured into the guide hole 101, but the guide rod 301 of the Partial installation of the partition wall to expose the top;
Connecting an extension guide rod (301a) to an upper end of the guide rod (301) exposed at an upper end of a portion of the central partition (10) and the side partition wall (20);
Stacking the plurality of unit members (100) on top of a portion of the central partition wall (10) and the side partition wall (20) to allow the guide hole (101) to pass through the extension guide rod (301a); To
Construction method of a wall structure comprising a.
제11항에 있어서,
상기 격벽 일부 설치단계는,
상기 격벽 일부의 측면과 상기 기초구조물(30)의 상면 사이에 전도방지부재(4)를 설치하는 단계;를 더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 11,
Part of the partition wall installation step,
Installing a fall prevention member (4) between the side of the partition portion and the upper surface of the foundation structure (30); Construction method of the wall structure further comprises a.
제12항에 있어서,
복수의 상기 전도방지부재(4)의 상단이 상기 결합부(400)의 네 귀퉁이에 각각 결합하는 것을 특징으로 하는 벽체 구조물의 시공방법.
The method of claim 12,
Method of constructing a wall structure, characterized in that the upper end of the plurality of anti-conduction member (4) is respectively coupled to the four corners of the coupling portion (400).
전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서,
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 단위부재(100)에 비해 폭이 넓게 형성되고, 상하방향을 따라 쉬스(1)가 설치된 프리캐스트 주두부(500)를 준비하는 주두부 준비단계;
적층된 상기 복수의 단위부재(100)의 상단에 상기 주두부(500)를 설치하는 주두부 설치단계;를 더 포함하고,
상기 긴장정착단계는, 상기 기초구조물(30)에 매설된 기초 쉬스(1a), 적층된 상기 복수의 단위부재(100)의 쉬스(1) 및 상기 주두부(500)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 상기 주두부(500)의 상면에 정착하는 것을 특징으로 하는 벽체 구조물의 시공방법.
As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
A head head preparation step of preparing a precast head head 500 having a wider width than that of the unit member 100 and having the sheath 1 installed along the vertical direction;
Further comprising: a head head installation step of installing the head head 500 on the top of the plurality of stacked unit members 100,
The tension fixing step may include a foundation sheath 1a embedded in the foundation structure 30, a sheath 1 of the plurality of unit members 100 stacked on the sheath 1 and a sheath 1 of the head head 500. (2) the installation method of the wall structure, characterized in that the tension is settled on the upper surface of the head (500).
전후방향을 따라 길게 설치되는 중앙격벽(10)과, 상기 중앙격벽(10)의 양측에 측방향을 따라 설치되는 측방격벽(20)을 구비한 벽체 구조물의 시공방법으로서,
상기 중앙격벽(10) 및 측방격벽(20)이 설치될 하부 영역을 따라 기초구조물(30)을 설치하는 기초구조물 설치단계;
폭과 높이에 비해 길이가 길게 형성되고, 상하방향을 따라 가이드공(101)이 형성되고, 상하방향을 따라 쉬스(1)가 설치되고, 프리캐스트 방식에 의해 제조된 복수의 단위부재(100)를 준비하는 단위부재 준비단계;
상기 기초구조물(30)에 하단이 매설된 가이드봉(301)에 상기 가이드공(101)이 관통하도록, 상기 기초구조물(30)의 상부에 상기 복수의 단위부재(100)를 적층하여 설치하여 상기 중앙격벽(10) 및 측방격벽(20)을 형성하고, 상기 가이드공(101)에 충전재를 타설하는 격벽 형성단계;
상기 기초구조물(30)에 매설된 기초 쉬스(1a) 및 적층된 상기 복수의 단위부재(100)의 쉬스(1)에 텐던(2)을 설치하고 긴장하여 정착하는 긴장정착단계;를 포함하고,
상기 격벽 형성단계 이후,
상기 측방격벽(20)의 측방에 대하여 거푸집을 설치하고 콘크리트를 타설하여 연장측방격벽(21)을 형성하는 단계;를
더 포함하는 것을 특징으로 하는 벽체 구조물의 시공방법.
As a construction method of a wall structure having a central partition 10 is installed in the longitudinal direction and the side partition wall 20 is installed on both sides of the central partition 10 in the lateral direction,
A foundation structure installation step of installing the foundation structure 30 along the lower region where the central partition wall 10 and the side partition wall 20 are to be installed;
The length is formed longer than the width and height, the guide hole 101 is formed along the up and down direction, the sheath 1 is installed along the up and down direction, and the plurality of unit members 100 manufactured by the precast method. Unit member preparation step to prepare;
The plurality of unit members 100 are stacked and installed on the upper portion of the foundation structure 30 so that the guide hole 101 penetrates through the guide rod 301 embedded at the bottom of the foundation structure 30. A partition wall forming step of forming a center partition wall 10 and a side partition wall 20 and pouring filler into the guide hole 101;
And a tension fixing step of installing and tensioning a tendon 2 on the sheath 1 of the plurality of unit members 100 and the foundation sheath embedded in the foundation structure 30 and stacked.
After the partition wall forming step,
Installing the formwork with respect to the side of the side partition wall 20 and pouring concrete to form an extended side partition wall 21;
Construction method of the wall structure, characterized in that it further comprises.
KR1020170102538A 2017-08-11 2017-08-11 Construction method for wall structure KR102008965B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170102538A KR102008965B1 (en) 2017-08-11 2017-08-11 Construction method for wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170102538A KR102008965B1 (en) 2017-08-11 2017-08-11 Construction method for wall structure

Publications (2)

Publication Number Publication Date
KR20190017541A KR20190017541A (en) 2019-02-20
KR102008965B1 true KR102008965B1 (en) 2019-08-12

Family

ID=65562089

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170102538A KR102008965B1 (en) 2017-08-11 2017-08-11 Construction method for wall structure

Country Status (1)

Country Link
KR (1) KR102008965B1 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100779772B1 (en) * 2006-04-17 2007-11-27 삼성물산 주식회사 Guide block and construction method for pre-cast member using it

Also Published As

Publication number Publication date
KR20190017541A (en) 2019-02-20

Similar Documents

Publication Publication Date Title
KR100549649B1 (en) Precast Tall Pier for Bridge
KR101545649B1 (en) Construction method for coping using permanent form preventing interference of reinforcing bar
KR101229263B1 (en) Slab-type box girder with a vertical connecting structure made by precast concrete and method constructing the bridge thereof
KR100758504B1 (en) Method of construction for underground diaphragm wall and underground diaphragm wall structure
KR102008965B1 (en) Construction method for wall structure
KR102059459B1 (en) Construction method for coal shed using foundation member
KR101023179B1 (en) Tee type ribbed slab, manufacturing method and construction method thereof
CN110984691B (en) Construction method of enclosure upright post
KR200440047Y1 (en) Block for reinforcing wall
KR20120131034A (en) Container Assembled with Precast Members Using Loop Connection
CN216194664U (en) Prestressing force assembled underground continuous wall
CN108571092A (en) A kind of module shear wall system with perps
PT94407A (en) FRAMEWORK STRUCTURE FOR STRUCTURAL BEAM MOLDING
NL2027756B1 (en) FOUNDATION ELEMENT FOR A MAST FOUNDATION, A MAST FOUNDATION AND A METHOD TO PLACE A MAST FOUNDATION
JP2014206025A (en) Culvert
JP2007126936A (en) Semisubterranean road and its construction method
KR101219459B1 (en) The water-storage tank of assembly type and method for constructing thereof
CN207109611U (en) A kind of prefabricated just beam buttress
KR20130038089A (en) Precast concrete frame for buildings using precast concrete beam continued by post tensioning
CN112095638A (en) Prefabricated anchor rope frame
CN107338734A (en) A kind of prefabricated just beam buttress and prefabricated jacking construction method
CN219753696U (en) Skeleton texture and prefabricated wall
KR100568904B1 (en) Structure, Method and Apparatus for Fiberglass Reinforced Plastics Deck-to-Girder Connections
CN210288772U (en) Wall combined brick
CN216007325U (en) Connecting joint of steel beam and steel column

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant