KR102004933B1 - The pre-loading device and method of pile using bearing plate and bolt fastened method - Google Patents
The pre-loading device and method of pile using bearing plate and bolt fastened method Download PDFInfo
- Publication number
- KR102004933B1 KR102004933B1 KR1020160091881A KR20160091881A KR102004933B1 KR 102004933 B1 KR102004933 B1 KR 102004933B1 KR 1020160091881 A KR1020160091881 A KR 1020160091881A KR 20160091881 A KR20160091881 A KR 20160091881A KR 102004933 B1 KR102004933 B1 KR 102004933B1
- Authority
- KR
- South Korea
- Prior art keywords
- nut
- bolt
- load
- additional
- file
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
- E02D35/005—Lowering or lifting of foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/48—Foundations inserted underneath existing buildings or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0229—Increasing or restoring the load-bearing capacity of building construction elements of foundations or foundation walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
본원발명은 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치에 관한 것으로 상세하게는 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 장치에 있어서, 내부의 구멍에 나사선이 형성된 관 형상의 너트와 외주면에 상기 너트의 나사선과 맞물리도록 형성되어 상기 너트의 내부 구멍에 설치되는 볼트와 상기 너트의 상면 외측에 결합되는 지압판으로 구성되는 것으로 상기 볼트의 하면이 기존 구조물의 기초 부분의 일부분을 제거한 후 시공되는 추가파일의 타단에 설치되는 하중재하부 및, 타설되는 콘크리트가 상기 볼트로 유입되지 못하도록 일단이 상기 지압판 또는 상기 너트의 상면에 설치되는 관 형상의 보호관으로 구성되되, 상기 추가파일이 시공된 공간에 콘크리트를 타설 및 양생하여 상기 지압판, 너트 및 보호관을 고정시킨 후 상기 볼트를 회전시키는 방법으로 시공된 상기 추가파일의 타단을 눌러 상기 추가파일에 하중을 가하는 것을 특징으로 한다.
본원발명은 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하방법에 관한 것으로 상세하게는 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 방법에 있어서, (a) 기존 구조물의 기초 일측에 추가파일이 시공될 위치의 일부분을 제거한 후 상기 추가파일을 시공하는 단계와, (b) 내부의 구멍에 나사선이 형성된 관 형상의 너트와 외주면에 상기 너트의 나사선과 맞물리도록 형성되어 상기 너트의 내부 구멍에 설치되는 볼트와 상기 너트의 상면 외측에 결합되는 지압판으로 구성된 하중재하부의 상기 볼트 하면이 상기 추가파일의 타단에 설치되는 단계와, (c) 타설되는 콘크리트가 상기 볼트로 유입되지 못하도록 관 형상의 보호관의 일단이 상기 지압판 또는 상기 너트의 상면에 설치되는 단계와, (d) 상기 (c)단계 후 상기 구조물의 기초 일부분이 제거된 공간에 콘크리트를 타설 및 양생하여 상기 지압판, 너트 및 보호관을 고정시키는 단계와, (e) 상기 (d)단계 후 상기 볼트를 회전시키는 방법으로 시공된 상기 추가파일의 타단을 눌러 상기 추가파일에 하중을 가하는 단계 및, (f) 상기 보호관 내부에 콘크리트 또는 그라우팅재를 타설하는 단계로 구성되는 것을 특징으로 한다.The present invention relates to a preloading device for a pile using a platen and a bolt fastening method, and more particularly, to a device for loading a load on an additional pile installed to support a load generated in addition to an existing structure, A bolt formed in an inner hole of the nut, and a pivot plate coupled to an outside of the upper surface of the nut, wherein the lower surface of the bolt is formed of a conventional structure And a tubular protective pipe having one end fixed to the upper surface of the pressure plate or the nut so that the concrete to be poured can not be introduced into the bolt The additional file is placed and cured in the space where the concrete is installed Jiappan group, then lock the nut and the protective tube by pressing the other end of the additional files installed by the method of rotating the bolt characterized in that applying a load to the additional file.
The present invention relates to a preloading method of a pile using a platen and a bolt fastening method, and more particularly, to a method of loading a load on an additional pile installed to support a load generated in addition to an existing structure, (B) inserting a tubular nut having a threaded hole in an inner hole thereof into the outer circumferential surface thereof so as to engage with the threaded nut of the nut, and removing the portion of the position where the additional file is to be installed, A bolt provided on the inner hole of the nut and a pivot plate joined to the outer side of the upper surface of the nut, the bolt bottom being provided at the other end of the additional pile; and (c) A step of installing one end of a tubular protective pipe on the upper surface of the pressure plate or the nut so as not to be introduced into the bolt, (c) a step of placing and curing the concrete in a space in which a part of the foundation of the structure is removed to fix the pressure plate, the nut and the protective pipe; and (e) Pressing the other end of the additional file to apply a load to the additional file; and (f) placing a concrete or a grouting material in the protective pipe.
Description
본 발명은 기존 구조물 증축 및 기존 기초의 지지력 부족 등으로 인해 추가로 발생되는 하중을 지지하기 위해 시공되는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치 및 재하방법에 관한 것이다.The present invention relates to a preloading apparatus and a loading method of a pile using a pivoting plate and a bolt fastening method, which are installed to support additional loads due to the expansion of existing structures and insufficient bearing capacity of existing foundations.
아파트 등의 구조물 리모델링과 같이 기존의 구조물의 규모를 확대(증축)할 필요가 있는 경우 확대되는 하중을 지탱하기 위한 기초구조물의 보강이 문제된다.If the existing structure needs to be enlarged (enlarged), such as remodeling a structure such as an apartment, there is a problem of reinforcing the foundation structure to support the enlarged load.
상기와 같은 문제를 해결하고자 종래에는 기존 구조물의 하부에 형성된 기존파일의 주위에 추가파일을 설치하는 방식을 시공하여 왔다. 그런데, 종래의 공법과 같이 단순히 기존파일 주위에 추가파일을 설치하는 경우 확대되는 하중이 기존파일과 추가파일에 분배되어 기존파일에는 기존 구조물 설계시 고려했던 하중보다 큰 하중이 재하되어 안전에 문제가 있다. 즉, 종래의 공법과 같이 확대되는 하중을 지탱하기 위하여 단순히 파일을 추가하는 경우 기존파일에는 기존 설계시 고려했던 하중보다 큰 하중이 재하되어 파일이 파괴되거나 지반이 파괴되어 지지력을 상실하고 지반침하가 발생될 염려가 있다.In order to solve the above-mentioned problem, conventionally, a method of installing additional files around existing files formed under the existing structure has been applied. However, when additional files are simply installed around the existing file as in the conventional method, the expanded load is distributed to the existing file and the additional file, so that a load greater than the load considered in designing the existing structure is loaded in the existing file, have. That is, when a file is simply added to support the enlarged load as in the conventional method, a load greater than the load considered in the existing design is loaded in the existing file, the file is destroyed or the ground is destroyed and the supporting force is lost, There is a risk of occurrence.
본 발명은 상기와 같은 문제점들을 해결하기 위하여 제안된 것으로서, 본 발명의 목적은 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가되는 파일 각각에 하중이 동일하게 재하되도록 추가되는 파일에 미리 하중을 재하시키는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치 및 재하방법을 제공함에 있다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems, and it is an object of the present invention to provide an apparatus and a method for preventing an excessive load from being concentrated on an existing file due to an enlarged load, And a preloading device and a loading method for a file using a platen and a bolt fastening method in which a load is previously loaded on a file added so that the load is equally loaded on the file.
상기와 같은 목적을 달성하기 위하여 본원발명은 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 장치에 있어서, 내부의 구멍에 나사선이 형성된 관 형상의 너트와 외주면에 상기 너트의 나사선과 맞물리도록 형성되어 상기 너트의 내부 구멍에 설치되는 볼트와 상기 너트의 상면 외측에 결합되는 지압판으로 구성되는 것으로 상기 볼트의 하면이 기존 구조물의 기초 부분의 일부분을 제거한 후 시공되는 추가파일의 타단에 설치되는 하중재하부 및, 타설되는 콘크리트가 상기 볼트로 유입되지 못하도록 일단이 상기 지압판 또는 상기 너트의 상면에 설치되는 관 형상의 보호관으로 구성되되, 상기 추가파일이 시공된 공간에 콘크리트를 타설 및 양생하여 상기 지압판, 너트 및 보호관을 고정시킨 후 상기 볼트를 회전시키는 방법으로 시공된 상기 추가파일의 타단을 눌러 상기 추가파일에 하중을 가하는 것을 특징으로 하는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치를 제공한다.In order to achieve the above object, the present invention provides an apparatus for loading a load on an additional pile installed to support a load generated in an existing structure, the apparatus comprising: a tubular nut having a screw thread formed in an inner hole; A bolt provided on an inner hole of the nut and formed to be engaged with a screw thread of the nut, and a pressure plate coupled to an outer side of the upper surface of the nut, wherein the lower surface of the bolt is formed by removing a portion of a base portion of the existing structure, A lower portion of the lower portion of the pile and a tubular protective pipe whose one end is installed on the upper surface of the pillar or the nut so that the concrete to be poured is prevented from flowing into the bolt, And the cushioning plate, the nut and the protective pipe are fixed, And a load is applied to the additional file by pressing the other end of the additional file constructed by rotating the additional file, thereby providing a file preloading device using the pliers and the bolt fastening method.
또한, 본원발명은 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 방법에 있어서, (a) 기존 구조물의 기초 일측에 추가파일이 시공될 위치의 일부분을 제거한 후 상기 추가파일을 시공하는 단계와, (b) 내부의 구멍에 나사선이 형성된 관 형상의 너트와 외주면에 상기 너트의 나사선과 맞물리도록 형성되어 상기 너트의 내부 구멍에 설치되는 볼트와 상기 너트의 상면 외측에 결합되는 지압판으로 구성된 하중재하부의 상기 볼트 하면이 상기 추가파일의 타단에 설치되는 단계와, (c) 타설되는 콘크리트가 상기 볼트로 유입되지 못하도록 관 형상의 보호관의 일단이 상기 지압판 또는 상기 너트의 상면에 설치되는 단계와, (d) 상기 (c)단계 후 상기 구조물의 기초 일부분이 제거된 공간에 콘크리트를 타설 및 양생하여 상기 지압판, 너트 및 보호관을 고정시키는 단계와, (e) 상기 (d)단계 후 상기 볼트를 회전시키는 방법으로 시공된 상기 추가파일의 타단을 눌러 상기 추가파일에 하중을 가하는 단계 및, (f) 상기 보호관 내부에 콘크리트 또는 그라우팅재를 타설하는 단계로 구성되는 것을 특징으로 하는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하방법을 제공한다.In addition, the present invention provides a method for loading a load on an additional file to be installed to support a load generated in addition to an existing structure, the method comprising the steps of: (a) removing a portion of a location, (B) a tubular nut having a screw thread formed in an inner hole thereof, a bolt formed on an outer circumferential surface of the nut so as to be engaged with a screw thread of the nut and provided in an inner hole of the nut, (C) one end of a tubular protective pipe is inserted into the bolt to prevent the inserted concrete from being introduced into the bolt, (D) placing the concrete in a space in which a part of the foundation of the structure is removed after the step (c) (E) applying a load to the additional file by pressing the other end of the additional file constructed by rotating the bolt after step (d), and (f) And placing a concrete or a grouting material in the inside of the protective pipe. The above and other objects of the present invention can also be accomplished by the provision of a preloading method for a pile using a pivoting plate and a bolt fastening method.
본원발명은 기존 구조물의 기초에 추가되는 파일에 하중을 미리 재하하는 방법으로 시공함으로써 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가되는 파일 각각에 하중이 동일하게 재하되어 기존 설계시 고려했던 하중보다 큰 하중이 기존파일에 재하되지 않아 파일이 파괴되거나 지반이 파괴되어 지지력을 상실하지 않고 지반침하가 발생될 염려가 없다. 즉, 본원발명은 기존 구조물에 단순히 선행하중이 재하된 파일을 시공함으로써 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가되는 파일 각각에 동일하게 재하되어 파일이 파괴되거나 지반침하가 발생될 없어 안정적으로 기초를 보강할 수 있는 장점이 있다. In the present invention, by applying a load to a file added to the foundation of an existing structure in advance, the load is not excessively concentrated on the existing file due to the expansion due to the enlargement of the existing structure or the like, The loads are equal to each other and the load greater than the load considered in the existing design is not transferred to the existing file, so that the file is destroyed or the ground is destroyed, so that the bearing capacity is not lost and the ground settlement is not caused. That is, according to the present invention, the load caused by the enlargement of the existing structure and the load of the existing structure are equally loaded on the existing file and the added file, respectively, so that the file is destroyed There is no ground subsidence and it is possible to reinforce the foundation with stability.
도1은 본원발명의 선행하중 재하장치가 추가파일에 시공된 것을 나타내는 도면이다.
도2는 하중재하부가 추가파일에 결합되는 것을 나타내는 도면이다.
도3은 볼트의 저면을 나타내는 도면이다.
도4 내지 도8은 파일의 선행하중 재하방법을 나타내는 도면이다.1 is a view showing that the preceding load-carrying device of the present invention is installed in an additional file.
Fig. 2 is a view showing that the load-bearing portion is coupled to an additional file. Fig.
3 is a view showing the bottom surface of the bolt.
Figs. 4 to 8 are views showing a method of loading a preceding load on a file. Fig.
이하 첨부된 도면들을 참조하여 본 발명에 따른 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치 및 재하방법의 구체적인 내용을 상세히 설명하기로 한다.Hereinafter, a detailed description will be given in detail of a preloading device and a loading method of a pile using a platen and bolt fastening method according to the present invention with reference to the accompanying drawings.
도1은 본원발명의 선행하중 재하장치가 추가파일에 시공된 것을 나타내는 도면이다.1 is a view showing that the preceding load-carrying device of the present invention is installed in an additional file.
도2는 하중재하부가 추가파일에 결합되는 것을 나타내는 도면이고, 도3은 볼트의 저면을 나타내는 도면이다.FIG. 2 is a view showing that the load-bearing portion is coupled to an additional file, and FIG. 3 is a view showing the bottom of the bolt. FIG.
본원발명은 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치에 관한 것으로 상세하게는 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 장치에 있어서, 내부의 구멍에 나사선이 형성된 관 형상의 너트(110)와 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되는 볼트(120)와 상기 너트(110)의 상면 외측에 결합되는 지압판(130)으로 구성되는 것으로 상기 볼트(120)의 하면이 기존 구조물의 기초 부분의 일부분을 제거한 후 시공되는 추가파일(10)의 타단에 설치되는 하중재하부(100) 및, 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 관 형상의 보호관(200)으로 구성되되, 상기 추가파일(10)이 시공된 공간에 콘크리트를 타설 및 양생하여 상기 지압판(130), 너트(110) 및 보호관(200)을 고정시킨 후 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 것을 특징으로 한다.The present invention relates to a preloading device for a pile using a platen and a bolt fastening method, and more particularly, to a device for loading a load on an additional pile installed to support a load generated in addition to an existing structure, A
본원발명은 하중재하부(100) 및 보호관(200)으로 구성되는 것으로 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가파일(10) 각각에 하중이 동일하게 재하되도록 추가파일(10)에 미리 하중을 재하시키는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치(20)에 관한 것이다.The present invention is composed of the
아파트 등의 구조물 리모델링과 같이 기존의 구조물의 규모를 확대(증축)할 필요가 있는 경우 확대되는 하중을 지탱하기 위한 기초구조물의 보강이 문제된다.If the existing structure needs to be enlarged (enlarged), such as remodeling a structure such as an apartment, there is a problem of reinforcing the foundation structure to support the enlarged load.
상기와 같은 문제를 해결하고자 종래에는 기존 구조물의 하부에 형성된 기존파일의 주위에 추가파일을 설치하는 방식을 시공하여 왔다. 그런데, 종래의 공법과 같이 단순히 기존파일 주위에 추가파일을 설치하는 경우 확대되는 하중이 기존파일과 추가파일에 분배되어 기존파일에는 기존 구조물 설계시 고려했던 하중보다 큰 하중이 재하되어 안전에 문제가 있다. 즉, 종래의 공법과 같이 확대되는 하중을 지탱하기 위하여 단순히 파일을 추가하는 경우 기존파일에는 기존 설계시 고려했던 하중보다 큰 하중이 재하되어 파일이 파괴되거나 지반이 파괴되어 지지력을 상실하고 지반침하가 발생될 염려가 있다.In order to solve the above-mentioned problem, conventionally, a method of installing additional files around existing files formed under the existing structure has been applied. However, when additional files are simply installed around the existing file as in the conventional method, the expanded load is distributed to the existing file and the additional file, so that a load greater than the load considered in designing the existing structure is loaded in the existing file, have. That is, when a file is simply added to support the enlarged load as in the conventional method, a load greater than the load considered in the existing design is loaded in the existing file, the file is destroyed or the ground is destroyed and the supporting force is lost, There is a risk of occurrence.
본 발명은 상기와 같은 문제점들을 해결하기 위하여 제안된 것으로서, 본 발명의 목적은 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가되는 파일 각각에 하중이 동일하게 재하되도록 추가되는 파일에 미리 하중을 재하시키는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치 및 재하방법을 제공함에 있다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems, and it is an object of the present invention to provide an apparatus and a method for preventing an excessive load from being concentrated on an existing file due to an enlarged load, And a preloading device and a loading method for a file using a platen and a bolt fastening method in which a load is previously loaded on a file added so that the load is equally loaded on the file.
본원발명은 기존 구조물의 기초에 추가되는 파일에 하중을 미리 재하하는 방법으로 시공함으로써 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가되는 파일 각각에 하중이 동일하게 재하되어 기존 설계시 고려했던 하중보다 큰 하중이 기존파일에 재하되지 않아 파일이 파괴되거나 지반이 파괴되어 지지력을 상실하지 않고 지반침하가 발생될 염려가 없다. 즉, 본원발명은 기존 구조물에 단순히 선행하중이 재하된 파일을 시공함으로써 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가되는 파일 각각에 동일하게 재하되어 파일이 파괴되거나 지반침하가 발생될 없어 안정적으로 기초를 보강할 수 있는 장점이 있다.In the present invention, by applying a load to a file added to the foundation of an existing structure in advance, the load is not excessively concentrated on the existing file due to the expansion due to the enlargement of the existing structure or the like, The loads are equal to each other and the load greater than the load considered in the existing design is not transferred to the existing file, so that the file is destroyed or the ground is destroyed, so that the bearing capacity is not lost and the ground settlement is not caused. That is, according to the present invention, the load caused by the enlargement of the existing structure and the load of the existing structure are equally loaded on the existing file and the added file, respectively, so that the file is destroyed There is no ground subsidence and it is possible to reinforce the foundation with stability.
하중재하부(100)는 기존 구조물의 기초를 보강하기 위하여 시공되는 추가파일(10)에 미리 선행하중을 가하여 추가되는 하중에 의해서 기존파일에 과도하게 하중이 재하되지 못하도록 하는 구성으로 다양하게 형성될 수 있는데 일례로 너트(110), 볼트(120) 및 지압판(130)으로 구성될 수 있다. 하중재하부(100)는 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가파일 각각에 동일하게 재하되도록 추가파일(10)에 하중을 먼저 재하시킬 수 있게 도와주는 구성이다.The lower part of the
너트(110)는 내부의 구멍에 나사선이 형성된 관 형상의 부재이다. 너트(110)는 타설되는 콘크리트에 의해서 고정되어 볼트(120)가 회전될 때 움직이지 않도록 하여 볼트(120)가 용이하게 회전되도록 도와주는 구성이다. 너트(110)는 내부의 관통홀에 볼트(120)의 나사선과 맞물리는 나사선이 형성되어 있으면 다양한 형상으로 제작될 수 있다. 볼트(120)는 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되되, 하면이 기존 구조물의 기초 부분의 일부분을 제거한 후 시공되는 추가파일(10)의 타단에 설치되는 부재이다. 볼트(120)는 볼트머리(121)와 몸체(122)로 나누어질 수 있다. 볼트머리(121)는 볼트(120)를 회전시키기 위하여 외부장비에 결합되는 구성으로 외주면이 다각형으로 형성된 통상의 볼트머리를 하고 있다. 몸체(122)는 외주면에 나사선이 형성되어 있고 하면에는 추가파일(10)의 타단이 삽입되도록 홈(123)이 형성되어 있다. 볼트(120)는 너트(110)에 서로의 나사선이 맞물리도록 되어 있어 일정한 방향으로 회전되면 일정한 방향(추가파일을 누르는 방향)으로 나아가 추가파일(10)의 타단을 눌러 추가파일(10)에 하중(압축력)을 가하는 부재이다. 볼트(120)는 다양한 장치를 이용하여 회전시킬 수 있는데 일례로 에어임팩렌치 또는 수동렌치로 회전시킬 수 있다. 지압판(130)은 상기 너트(110)의 상면 외측에 결합되는 부재이다. 지압판(130)은 너트에 설치되어 볼트(120)가 회전되어 추가파일(10)을 누를 때 너트(110)가 함께 움직이지 못하도록 지지하는 부재로 타설되는 콘크리트에 고정되는 구성이다. 지압판(130)은 다양한 방법으로 너트(110)에 결합될 수 있는데 일례로 판 형상으로 제작되어 일단이 상기 너트(110)의 상면 외측에 설치되고 타단이 타설되는 콘크리트에 묻히도록 제작될 수 있고, 또 다른 예로 너트(110)와 같이 내부에 관통공이 있는 원형 또는 사각형의 판으로 제작되어 내부의 관통공이 상기 너트(110)의 상면 외측에 설치되고 외측이 타설되는 콘크리트에 묻히도록 제작될 수 있다.The
하중재하부(100)는 소요되는 강도를 만족하면 다양한 재료가 사용될 수 있다.A variety of materials can be used as long as the load-carrying
보호관(200)은 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 관 형상의 부재이다. 보호관(200)은 너트에 설치된 볼트에 타설되는 콘크리트가 유입되지 않도록 설치되는 관 형상의 부재이다. 보호관(200)은 다양한 재료가 사용될 수 있는데 일례로 강관, PVC 관 등이 사용될 수 있다.The
본원발명은 추가파일(10)이 시공된 공간에 콘크리트를 타설 및 양생하여 상기 지압판(130), 너트(110) 및 보호관(200)을 고정시킨 후 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 발명이다. 너트(110)가 고정된 후에 볼트(120)를 회전시키는 경우 너트(110)가 더 이상 움직이지 않기 때문에 볼트(120)가 추가파일(10)의 타단을 누르는 방향으로 움직여 추가파일(10)에 선행하중을 가할 수 있다. 즉, 본원발명은 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가파일(10) 각각에 동일하게 재하되도록 추가파일(10)에 하중을 먼저 재하시키는 발명이다.The present invention can be applied to a concrete structure in which concrete is placed and cured in a space where the
도4 내지 도8은 파일의 선행하중 재하방법을 나타내는 도면이다.Figs. 4 to 8 are views showing a method of loading a preceding load on a file. Fig.
본원발명은 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하방법에 관한 것으로 상세하게는 기존 구조물에 추가로 발생되는 하중을 지지하기 위해 시공되는 추가파일에 하중을 재하하는 방법에 있어서, (a) 기존 구조물의 기초(1) 일측에 추가파일(10)이 시공될 위치의 일부분을 제거한 후 상기 추가파일(10)을 시공하는 단계와, (b) 내부의 구멍에 나사선이 형성된 관 형상의 너트(110)와 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되는 볼트(120)와 상기 너트(110)의 상면 외측에 결합되는 지압판(130)으로 구성된 하중재하부(100)의 상기 볼트(120) 하면이 상기 추가파일(10)의 타단에 설치되는 단계와, (c) 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 관 형상의 보호관(200)의 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 단계와, (d) 상기 (c)단계 후 상기 구조물의 기초(1) 일부분이 제거된 공간에 콘크리트를 타설 및 양생하여 상기 지압판(130), 너트(110) 및 보호관(200)을 고정시키는 단계와, (e) 상기 (d)단계 후 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 단계 및, (f) 상기 보호관(200) 내부에 콘크리트 또는 그라우팅재를 타설하는 단계로 구성되는 것을 특징으로 한다.The present invention relates to a preloading method of a pile using a platen and a bolt fastening method, and more particularly, to a method of loading a load on an additional pile installed to support a load generated in addition to an existing structure, (B) removing the portion of the location where the additional file (10) is to be installed on one side of the foundation (1) of the existing structure, and (b) A
본원발명은 (a)단계 내지 (f)단계로 구성되는 것으로 기존 구조물의 증축 등으로 인해 확대되는 하중에 의해서 기존파일에 과도하게 하중이 집중되지 않고, 기존파일과 추가파일(10) 각각에 하중이 동일하게 재하되도록 추가파일(10)에 미리 하중을 재하시키는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하방법에 관한 것이다.The present invention is composed of steps (a) through (f), wherein an excessive load is not concentrated on an existing file due to a load enlarged due to the enlargement of an existing structure or the like, To a preloading method of a file by using a platen and a bolt fastening method in which a load is preliminarily loaded on the additional file (10) so as to be equally loaded.
(a)단계는 기존 구조물의 기초(1) 일측에 추가파일(10)이 시공될 위치의 일부분을 제거한 후 상기 추가파일(10)을 시공하는 단계이다. (a)단계는 설계상 추가파일이 시공될 위치의 기초를 제거하고, 그 위에 추가파일을 시공하는 단계이다. 물론 시공된 추가파일의 길이가 맞지 않는 경우 설계에 맞게 커팅될 수 있다. 또한, 하중재하부(100)가 설치되는 곳인 추가파일(10)의 타단 부분까지 굴착공(11)에 콘크리트 또는 그라우팅재가 타설되어 있을 수 있다. In the step (a), a portion of the location where the
(b)단계는 시공된 추가파일(10)에 하중을 재하 하기 위한 하중재하부(100)가 설치되는 단계이다. 상세하게 (b)단계는 내부의 구멍에 나사선이 형성된 관 형상의 너트(110)와 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되는 볼트(120)와 상기 너트(110)의 상면 외측에 결합되는 지압판(130)으로 구성된 하중재하부(100)의 상기 볼트(120) 하면이 상기 추가파일(10)의 타단에 설치되는 단계이다. (b) is a stage in which a
하중재하부(100)는 기존 구조물의 기초를 보강하기 위하여 시공되는 추가파일(10)에 미리 선행하중을 가하여 추가되는 하중에 의해서 기존파일에 과도하게 하중이 재하되지 못하도록 하는 구성으로 다양하게 형성될 수 있는데 일례로 너트(110), 볼트(120) 및 지압판으로 구성될 수 있다. 하중재하부(100)는 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가파일 각각에 동일하게 재하되도록 추가파일(10)에 하중을 먼저 재하시킬 수 있게 도와주는 구성이다.The lower part of the
너트(110)는 내부의 구멍에 나사선이 형성된 관 형상의 부재이다. 너트(110)는 타설되는 콘크리트에 의해서 고정되어 볼트(120)가 회전될 때 움직이지 않도록 하여 볼트(120)가 용이하게 회전되도록 도와주는 구성이다. 너트(110)는 내부의 관통홀에 볼트(120)의 나사선과 맞물리는 나사선이 형성되어 있으면 다양한 형상으로 제작될 수 있다. 볼트(120)는 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되되, 하면이 기존 구조물의 기초 부분의 일부분을 제거한 후 시공되는 추가파일(10)의 타단에 설치되는 부재이다. 볼트(120)는 볼트머리(121)와 몸체(122)로 나누어질 수 있다. 볼트머리(121)는 볼트(120)를 회전시키기 위하여 외부장비에 결합되는 구성으로 외주면이 다각형으로 형성된 통상의 볼트머리를 하고 있다. 몸체(122)는 외주면에 나사선이 형성되어 있고 하면에는 추가파일(10)의 타단이 삽입되도록 홈(123)이 형성되어 있다. 지압판(130)은 상기 너트(110)의 상면 외측에 결합되는 부재이다. 지압판(130)은 너트에 설치되어 볼트(120)가 회전되어 추가파일(10)을 누를 때 너트(110)가 함께 움직이지 못하도록 지지하는 부재로 타설되는 콘크리트에 고정되는 구성이다. 지압판(130)은 다양한 방법으로 너트(110)에 결합될 수 있는데 일례로 판 형상으로 제작되어 일단이 상기 너트(110)의 상면 외측에 설치되고 타단이 타설되는 콘크리트에 묻히도록 제작될 수 있고, 또 다른 예로 너트(110)와 같이 내부에 관통공이 있는 원형 또는 사각형의 판으로 제작되어 내부의 관통공이 상기 너트(110)의 상면 외측에 설치되고 외측이 타설되는 콘크리트에 묻히도록 제작될 수 있다.The
하중재하부(100)는 소요되는 강도를 만족하면 다양한 재료가 사용될 수 있다.A variety of materials can be used as long as the load-carrying
(c)단계는 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 관 형상의 보호관(200)의 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 단계이다.(c) is a step in which one end of the pipe-shaped
보호관(200)은 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 관 형상의 부재이다. 보호관(200)은 너트에 설치된 볼트에 타설되는 콘크리트가 유입되지 않도록 설치되는 관 형상의 부재이다. 보호관(200)은 다양한 재료가 사용될 수 있는데 일례로 강관, PVC 관 등이 사용될 수 있다.The
또한, 상기 (c)단계는 보강철근(300)이 상기 (a)단계에서 제거된 기초의 일부분에 설치되되 상기 하중재하부(100) 위의 공간에 설치되는 것을 더 포함하여 구성될 수 있다. 보강철근(300)은 보호관(200)과 서로 간섭되지 않도록 설치되는 구성으로 설계에 맞는 직경을 선택하여 시공되는 일반적인 구조철근이다.The step (c) may further comprise the step of installing the reinforcing
(d)단계는 콘크리트를 타설 및 양생하는 단계로 상세하게 상기 (c)단계 후 상기 구조물의 기초(1) 일부분이 제거된 공간에 콘크리트를 타설 및 양생하여 상기 지압판(130), 너트(110) 및 보호관(200)을 고정시키는 단계이다.(d) is concrete pouring and curing step. Specifically, after the step (c), the concrete is placed and cured in a space where a part of the
(e)단계는 볼트(120)를 회전시켜 추가파일(10)에 하중을 가하는 단계이다. 즉, (e)단계는 상기 (d)단계 후 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 단계이다.(e) is a step of rotating the
볼트(120)는 너트(110)에 서로의 나사선이 맞물리도록 되어 있어 일정한 방향으로 회전되면 일정한 방향(추가파일을 누르는 방향)으로 나아가 추가파일(10)의 타단을 눌러 추가파일(10)에 하중(압축력)을 가하는 부재이다. 볼트(120)는 다양한 장치를 이용하여 회전시킬 수 있는데 일례로 에어임팩렌치 또는 수동렌치로 회전시킬 수 있다.When the
너트(110)가 고정된 후에 볼트(120)를 회전시키는 경우 너트(110)가 더 이상 움직이지 않기 때문에 볼트(120)가 추가파일(10)의 타단을 누르는 방향으로 움직여 추가파일(10)에 선행하중을 가할 수 있다. 즉, 본원발명은 기존 구조물의 증축 등으로 인해 발생되는 하중과 기존구조물의 하중이 기존파일과 추가파일(10) 각각에 동일하게 재하되도록 추가파일(10)에 하중을 먼저 재하시키는 발명이다.When the
(f)단계는 상기 보호관(200) 내부에 콘크리트 또는 그라우팅재를 타설하는 단계이다.(f) is a step of pouring concrete or a grouting material into the
이상으로 본 발명에 따른 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하장치 및 재하방법의 바람직한 실시 예를 설명하였으나 이는 적어도 하나의 실시예로서 설명되는 것이며, 이에 의하여 본 발명의 기술적 사상과 그 구성 및 작용이 제한되지는 아니하는 것으로, 본 발명의 기술적 사상의 범위가 도면 또는 도면을 참조한 설명에 의해 한정/제한되지는 아니하는 것이다. 또한 본 발명에서 제시된 발명의 개념과 실시예가 본 발명의 동일 목적을 수행하기 위하여 다른 구조로 수정하거나 설계하기 위한 기초로써 본 발명이 속하는 기술분야의 통상의 지식을 가진 자에 의해 사용되어질 수 있을 것인데, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자에 의한 수정 또는 변경된 등가 구조는 특허청구범위에서 기술되는 본 발명의 기술적 범위에 구속되는 것으로서, 특허청구범위에서 기술한 발명의 사상이나 범위를 벗어나지 않는 한도 내에서 다양한 변화, 치환 및 변경이 가능한 것이다.In the foregoing, preferred embodiments of the pile loading device and the pile loading method using the pliers and the bolt fastening method according to the present invention have been described. However, the present invention is described as at least one embodiment, And the scope of the technical idea of the present invention is not limited by the description with reference to the drawings or the drawings. It will also be appreciated by those skilled in the art that the concepts and embodiments of the invention set forth herein may be used as a basis for modifying or designing other structures for carrying out the same purposes of the present invention It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the present invention as defined by the appended claims and their equivalents. And various changes, substitutions, and alterations can be made without departing from the scope of the invention.
1 : 기초
10 : 추가파일 20 : 재하장치
100 : 하중재하부
110 : 너트 120 : 볼트
130 : 지압판
200 : 보호관
300 : 보강철근1: Foundation
10: Additional file 20: Loading device
100: lower part
110: Nuts 120: Bolts
130:
200: Protector
300: Rebar
Claims (7)
(a) 기존 구조물의 기초(1) 일측에 추가파일(10)이 시공될 위치의 일부분을 제거한 후 상기 추가파일(10)을 시공하는 단계;
(b) 내부의 구멍에 나사선이 형성된 관 형상의 너트(110)와 외주면에 상기 너트(110)의 나사선과 맞물리도록 형성되어 상기 너트(110)의 내부 구멍에 설치되는 볼트(120)와 상기 너트(110)의 상면 외측에 설치되는 지압판(130)으로 구성되는 하중재하부(100)의 상기 볼트(120) 하면이 상기 추가파일(10)의 타단에 설치되는 단계;
(c) 타설되는 콘크리트가 상기 볼트(120)로 유입되지 못하도록 관 형상의 보호관(200)의 일단이 상기 지압판(130) 또는 상기 너트(110)의 상면에 설치되는 단계;
(d) 상기 (c)단계 후 상기 구조물의 기초(1) 일부분이 제거된 공간에 콘크리트를 타설 및 양생하여 상기 지압판(130), 너트(110) 및 보호관(200)을 고정시키는 단계;
(e) 상기 (d)단계 후 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 단계; 및,
(f) 상기 보호관(200) 내부에 콘크리트 또는 그라우팅재를 타설하는 단계로 구성되되,
상기 (c)단계는 보강철근(300)이 상기 (a)단계에서 제거된 기초의 일부분에 설치되되 상기 하중재하부(100) 위의 공간에 설치되고, 상기 볼트(120)는 외주면이 다각형으로 형성된 볼트머리(121)와 외주면에 상기 너트(110)의 나사선과 맞물리도록 나사선이 형성되고, 타단에 홈이 형성된 원형 봉부재로 일단이 상기 볼트머리(121)의 하면에 결합되고 타단의 홈에 상기 추가파일(10)의 타단이 삽입되어 설치되는 몸체(122)로 구성되고,
상기 (e)단계는 에어임팩렌치 또는 수동렌치로 상기 볼트(120)를 회전시키는 방법으로 시공된 상기 추가파일(10)의 타단을 눌러 상기 추가파일(10)에 하중을 가하는 단계인 것을 특징으로 하는 것을 특징으로 하는 지압판과 볼트체결방식을 이용한 파일의 선행하중 재하방법.
CLAIMS What is claimed is: 1. A method of loading a load on an additional pile to support a load additionally generated on an existing structure,
(a) constructing the additional file (10) after removing a portion of the location where the additional file (10) is to be installed on the base (1) of the existing structure;
a bolt 120 formed on an outer circumferential surface of the nut 110 so as to engage with a thread of the nut 110 and installed in an inner hole of the nut 110, The lower surface of the bolt 120 of the lower part 100 constituted by the pressure plate 130 provided on the upper side of the upper surface of the additional pile 110 is installed at the other end of the additional pile 10;
(c) installing one end of a tubular protective pipe (200) on the upper surface of the pressure plate (130) or the nut (110) so that the concrete to be laid is prevented from flowing into the bolt (120);
(d) placing the concrete in the space where a part of the foundation (1) of the structure is removed after the step (c), and fixing the support plate (130), the nut (110) and the protective pipe (200);
(e) applying a load to the additional file (10) by pressing the other end of the additional file (10) constructed by rotating the bolt (120) after the step (d); And
(f) Placing concrete or grouting material in the protective pipe 200,
In the step (c), the reinforcing bar 300 is installed in a part of the foundation removed in the step (a), but is installed in the space above the lower part 100, and the bolt 120 has a polygonal outer circumferential surface A bolt head 121 formed on the outer circumferential surface of the bolt head 121, a screw thread formed on the outer circumferential surface of the bolt head 121 so as to engage with the thread of the nut 110, And a body 122 to which the other end of the additional file 10 is inserted,
(E) is a step of applying a load to the additional pile 10 by pressing the other end of the additional pile 10 constructed by rotating the bolt 120 with an air impact wrench or a manual wrench And a preloading method of the pile using a bolt fastening method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020160091881A KR102004933B1 (en) | 2016-07-20 | 2016-07-20 | The pre-loading device and method of pile using bearing plate and bolt fastened method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020160091881A KR102004933B1 (en) | 2016-07-20 | 2016-07-20 | The pre-loading device and method of pile using bearing plate and bolt fastened method |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20180009929A KR20180009929A (en) | 2018-01-30 |
KR102004933B1 true KR102004933B1 (en) | 2019-07-29 |
Family
ID=61070485
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020160091881A KR102004933B1 (en) | 2016-07-20 | 2016-07-20 | The pre-loading device and method of pile using bearing plate and bolt fastened method |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102004933B1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700618B (en) * | 2019-10-28 | 2021-10-01 | 上海悍马建筑科技有限公司 | Building prestress reinforcement construction method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100457406B1 (en) * | 2001-12-20 | 2004-11-18 | 주식회사 지오텍코리아 | Ground Anchor |
KR100816044B1 (en) * | 2007-12-18 | 2008-03-24 | 문형록 | Structure lifting and supporting method by using a micro pile |
KR101337570B1 (en) * | 2012-11-06 | 2013-12-06 | 한국건설기술연구원 | Construction method for addition pile |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101677448B1 (en) * | 2013-12-04 | 2016-11-29 | 한국건설기술연구원 | Construction method for addition pile |
-
2016
- 2016-07-20 KR KR1020160091881A patent/KR102004933B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100457406B1 (en) * | 2001-12-20 | 2004-11-18 | 주식회사 지오텍코리아 | Ground Anchor |
KR100816044B1 (en) * | 2007-12-18 | 2008-03-24 | 문형록 | Structure lifting and supporting method by using a micro pile |
KR101337570B1 (en) * | 2012-11-06 | 2013-12-06 | 한국건설기술연구원 | Construction method for addition pile |
Also Published As
Publication number | Publication date |
---|---|
KR20180009929A (en) | 2018-01-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4726891B2 (en) | How to set up a tower | |
KR101696916B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
EA027072B1 (en) | Lifting device | |
KR101863792B1 (en) | Pre-loading method of reinforcing pile | |
TWI771453B (en) | Offshore structure | |
KR101103530B1 (en) | Apparatus for restoration of disparity sinking construction or introducing pre-stress of pipe pile | |
KR102004933B1 (en) | The pre-loading device and method of pile using bearing plate and bolt fastened method | |
TW202117138A (en) | Corrugated shell bearing piles and installation methods | |
JP5498891B2 (en) | Hole forming mold and hole forming method | |
KR101731535B1 (en) | Pre-loading apparatus for pile and pre-loading method using the same | |
KR100714434B1 (en) | A bracing for reinforcing support | |
KR101945702B1 (en) | The pre-loading device and method of pile using bolt fastened method | |
US10030348B2 (en) | Apparatus for activating the lateral friction of pile-like load-bearing members | |
KR101561592B1 (en) | Apparatus and method for reinforcing PHC file head | |
JP5257123B2 (en) | Fixing structure of fixture to reinforced concrete and fixing method thereof | |
JP6006004B2 (en) | Pile head space formation auxiliary tool, hollow ready-made pile provided with the same, pile head processing method using the hollow ready-made pile, and pile head space forming method | |
KR102146577B1 (en) | Fixed structure of high strength support material with easy to install at the construction site and construction method thereof | |
KR20190123854A (en) | Micropile | |
JP7336406B2 (en) | One-touch fixed lock bolt | |
JP6322490B2 (en) | Pile head treatment method for severing material and site-built pile | |
KR101518034B1 (en) | manufacturing method for concrete column having self-restraint features | |
KR100667183B1 (en) | Method of high grouting and that of packer | |
KR101684480B1 (en) | Support pile with reinforcing structure of lower part | |
KR20200077468A (en) | Anchor of expandible type | |
JP2014031714A (en) | Wooden pole support device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |