KR101999647B1 - construction method of under-ground Electric power pipe line using natural soil - Google Patents

construction method of under-ground Electric power pipe line using natural soil Download PDF

Info

Publication number
KR101999647B1
KR101999647B1 KR1020160109319A KR20160109319A KR101999647B1 KR 101999647 B1 KR101999647 B1 KR 101999647B1 KR 1020160109319 A KR1020160109319 A KR 1020160109319A KR 20160109319 A KR20160109319 A KR 20160109319A KR 101999647 B1 KR101999647 B1 KR 101999647B1
Authority
KR
South Korea
Prior art keywords
soil
longitudinal direction
pipeline
grooves
roller compaction
Prior art date
Application number
KR1020160109319A
Other languages
Korean (ko)
Other versions
KR20180024105A (en
Inventor
서영곤
Original Assignee
하나테크 주식회사
승리전력기술(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 하나테크 주식회사, 승리전력기술(주) filed Critical 하나테크 주식회사
Priority to KR1020160109319A priority Critical patent/KR101999647B1/en
Publication of KR20180024105A publication Critical patent/KR20180024105A/en
Application granted granted Critical
Publication of KR101999647B1 publication Critical patent/KR101999647B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Mechanical Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

본 발명은 원토를 재활용한 전력관로 되메우기 다지기 시공방법이 개시되는 것으로, 전력관로를 매설하기 위해 관로매설홈을 굴착한 후 관로매설홈을 굴착할 때 파내어진 원토를 선별토와 불량토로 선별하여 선별된 선별토를 다시 이용하여 되메우기 작업을 진행하기 때문에, 모래와 같은 골재가 필요치 않아 비용절감 효과를 기대할 수 있으며 모래와 같은 골재의 운반작업이 생략되기 때문에 즉시 되메우기 작업을 진행할 수 있고 작업자가 직접 스페이서를 설치하고 다시 철거하는 작업을 반복하는 것을 생략할 수 있고 전력관로들의 간격이 서로 일정하게 유지된 상태에서 즉시 선별토가 투입되고 선별토 투입과 동시에 표면 평탄화 고르기작업이 진행됨에 따라 전력관로를 매설할 때의 작업시간 및 작업자의 피로감을 최소화할 수 있으며 작업자의 안전사고를 미연에 방지할 수 있다.The present invention discloses a construction method for reclaiming a power pipeline by recycling a raw soil material. When excavating a pipeline buried groove to bury a power pipeline and digging a buried pipeline groove, the excavated raw soil is sorted into a selected soil and a defective soil, Since the re-use of the selected soil is carried out, the aggregate material such as sand is not needed and the cost reduction effect can be expected. Since the transportation work of the aggregate such as sand is omitted, it is possible to carry out immediate back- It is possible to omit the repetition of the installation and demolition of the electric power lines, and as the electric power lines are maintained at a constant interval, the screening soil is immediately injected, The work time and the fatigue of the worker can be minimized, It can prevent accidents from occurring.

Description

원토를 재활용한 전력관로 되메우기 다지기 시공방법{construction method of under-ground Electric power pipe line using natural soil}Construction method of under-ground electric power pipe line using natural soil

본 발명은 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 관한 것으로, 더욱 상세하게는 전력관로 설치를 위해 파내어진 원토를 이용하여 파내어진 구덩이를 메워줌은 물론 전력관로 사이사이를 되메우기 하여 자원재활용성을 높이고 되메우기와 전력관로의 균등 간격으로의 이격이 동시에 진행되도록 하여 작업시간의 단축은 물론 작업효율성을 향상시킬 수 있도록 한 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 관한 것이다.
The present invention relates to a method of reclaiming power from a recycled power plant, and more particularly, to a recycling method for recycled recycled power plants, And to improve the working efficiency as well as the working time by allowing the backwashing and the separation of the electric power lines to be equal to each other at the same time, thereby recycling the raw material for the electric power line backing.

일반적으로 전력관로공사에서의 지중선로 방식은 지면에 전력관로를 매설하고 매설된 전력관로를 이용하여 케이블을 설치하는 것으로, 근자들어서는 지면으로부터 세워지는 전봇대와 같은 지주 및 지주들간에 연결되는 케이블에 의해 도시의 미감을 해치게 되는 문제점에 의해 지중선로 방식으로 케이블을 지면에 매설하도록 하고 있다.Generally, the underground line system in electric power line construction is to install a cable by using a power line embedded in a ground and installing a cable using a built-in electric power line. By the cable connected between the landing pad and the landing pad, The cable is buried on the ground by an underground method due to the problem of damaging the beauty of the city.

이와 같은 지중선로 방식은, 먼저 케이블을 설치하고자 하는 지면에 일정깊이로 관로매설홈을 관로가 매설되는 거리만큼 파낸 후 파내어진 관로매설홈의 길이방향을 따라 복수개의 전력관로를 위치한 후 다시 파내어진 관로매설홈을 모래와 같은 골재로 되메우기 하고 있다.In such an underground railway system, first, a plurality of electric power lines are disposed along the longitudinal direction of the grooved grooved grooves, after digging the grooved grooves at a predetermined depth on the surface of the ground on which the cable is to be installed, The channel is rebuilt with sand-like aggregate.

즉, 도 1a 내지 도 1f에 도시된 바와 같이 전력관로가 설치되는 지면에 일정깊이의 관로매설홈(1)을 굴착하고 굴착된 관로매설홈(1)의 바닥면에 1차모래(2a)를 투입하여 고르기작업을 진행한 후 바닥면 1차모래(2a)를 다짐장치로 견고하고 평탄하게 다져준다.That is, as shown in FIGS. 1A to 1F, a groove 1 having a predetermined depth is drilled on a surface of a ground on which a power line is installed, and primary sand 2a is formed on the bottom surface of the channel- After finishing work, put the primary sand (2a) on the bottom surface firmly and firmly with the compaction device.

다음으로, 설치하고자 하는 복수개의 전력관로(3)를 다져진 모래위에 위치하도록 포설한 후, 포설된 복수개의 전력관로(3) 사이사이가 약 10cm 간격이 유지되도록 스페이서(4)를 작업자가 직접 수작업으로 설치하는 바, 이 때 관로매설홈(1)에 포설된 전력관로(3)의 길이방향으로 작업자가 일일이 이동하면서 복수개의 스페이서(4)를 복수개의 전력관로(3) 사이사이에 끼워 설치한다.Next, a plurality of electric power ducts 3 to be installed are installed on the sand, and then the spacers 4 are manually operated by the operator so that the space between the plurality of installed electric power ducts 3 is maintained at about 10 cm At this time, a plurality of spacers 4 are sandwiched between the plurality of electric power lines 3 while the worker moves one by one in the longitudinal direction of the electric power line 3 installed in the pipeline embedded grooves 1 .

다음으로, 2차모래(2b)를 관로매설홈(1)에 다시 채워 스페이서(4)가 끼워진 상태의 전력관로(3)가 덮어지도록 한 후 채워진 2차모래(2b)를 다시 고르기 작업을 한 다음 복수개의 전력관로(3) 사이사이에 끼워진 스페이서(4)를 작업자가 직접 전력관로(3)의 길이방향을 따라 이동하면서 하나하나 빼내고 2차모래(2b)의 표면을 역시 다짐장치를 이용하여 견고하고 평탄하게 다짐작업한다.Next, the secondary sand 2b is refilled in the channel-embedded grooves 1 so that the power line 3 in a state where the spacer 4 is sandwiched is covered, and then the filled secondary sand 2b is again grounded The worker directly removes the spacers 4 sandwiched between the plurality of electric power lines 3 while moving along the longitudinal direction of the electric power line 3 and removes the surface of the secondary sand 2b by using the compaction device Work hard and flat.

이와 같은 공정을 반복하면서 관로매설홈(1)에 복수개의 전력관로(3)를 복수개로 적층하여 전력관로(3)를 매설한 후 흙을 채워 다짐으로써 지중선로 방식에 의한 전력관로의 시공작업을 완료한다.By repeating the above steps, a plurality of electric power lines 3 are stacked in the channel-embedded grooves 1, and the power line 3 is buried. Complete.

이와 같이 종래 전력관로 시공방법은, 관로매설홈에 포설된 복수개의 전력관로 사이사이를 약 10cm 간격으로 이격시키기 위해 복수개의 스페이서를 작업자가 전력관로의 길이방향을 따라 이동하면서 끼워주고 다시 끼워진 복수개의 스페이서를 작업자가 전력관로의 길이방향을 따라 이동하면서 빼내어야 하기 때문에, 작업시간의 지연은 물론 작업자의 피로감을 극대화시켜 작업효율성이 현저하게 떨어지는 문제점을 갖고 있다.In the conventional power line construction method, a plurality of spacers are moved by a worker along the longitudinal direction of the power line so as to separate the plurality of power lines laid out in the grooves in the pipeline at intervals of about 10 cm, The spacers must be removed while moving along the longitudinal direction of the electric power line, thereby maximizing the fatigue of the worker as well as the delay of the work time, thereby significantly reducing the work efficiency.

또한, 전력관로를 매설하기 위해 덮어지는 모래를 작업자가 좁은 관로매설홈의 내부에서 역시 전력관로의 길이방향을 따라 이동하면서 일일이 수작업으로 평탄하게 고르는 작업을 진행해야 하는 문제점을 갖고 있다.Further, there is a problem in that the worker must smoothly sand the sand covered by the power pipeline by manually moving the sand along the longitudinal direction of the power pipeline inside the narrow pipeline buried groove.

뿐만 아니라, 전력관로를 매설하기 위해 관로매설홈에 모래를 덮어주는 작업을 진행하는 동안에는 작업자가 관로매설홈의 내부로 들어갈 수 없어 모래를 덮어주는 작업을 진행하는 동안에 작업자의 작업이 중지되는 문제점이 있다.In addition, during the operation of covering the sand to the groove of the pipeline to bury the electric power line, the operator can not enter the inside of the pipeline buried groove, and the work of the operator is stopped while the sand is being covered have.

또한, 관로매설홈에 작업자가 직접 들어가서 전력관로에 스페이서를 끼워 설치하는 작업을 진행함에 따라 작업 도중 토사의 붕괴가 발생될 경우 작업자의 안전사고가 발생됨은 물론 굴착기와 같은 대형장비와 작업자가 같은 공간에서 작업을 하기 때문에 작업자가 안전사고에 노출될 수 밖에 없는 실정이다.In addition, as the operator enters the pipeline buried grooves and installs the spacers on the electric power line, the collapse of the earth and sand causes a safety accident of the operator, and a large equipment such as an excavator and a worker The worker is exposed to safety accidents.

또한, 종래의 전력관로 시공방법의 경우 전력관로 사이사이로 충분하게 골재가 채워질 수 있도록 모래를 채워주기 때문에 모래의 사용에 따른 추가적인 시공비용이 발생되고 모래의 채취 및 처리에 대한 환경훼손을 유발하게 되며 모래를 운반하기 위한 운반비용이 가중됨은 물론, 운송과 매립과정에서의 다량의 온실가스나 오염물질이 발생하게 되는 문제점이 있다.In addition, in the case of the conventional power line construction method, since the sand is filled to fill the aggregate sufficiently between the power lines, the additional construction cost due to the use of the sand is generated and the environmental damage to the collection and treatment of the sand is caused There is a problem in that transportation cost for transporting sand is increased, and a large amount of greenhouse gases or pollutants are generated during transportation and landfilling.

종래 기술로, 등록특허 10-0748258호인 트로이관을 이용한 고압 케이블 지중선 관로 시공방법이 안출된 바 있으며, 이는 트로이관을 삽입할 수 있도록 좌우 일정한 경사각을 유지하여 경사면을 형성하면서 터파기작업을 하되, 바닥면의 너비는 트로이관 외측의 너비와 동일한 너비로 형성하는 굴착부 형성단계와 상기 굴착부의 바닥면에 트로이관을 안착시키되, 다수개의 트로이관을 결합홈을 이용하여 연속적으로 결합하는 트로이관 안착단계와 상기 트로이관의 공간부에 일정량의 모래를 형성시킨 후, 상기 모래의 상측으로 고압 케이블을 일정한 간격으로 형성하며, 재차 모래를 이용하여 상기 고압케이블 상측으로 모래를 편평하게 형상하는 것을 반복하면서 고압 케이블을 매설하는 관로 매설단계와 상기 트로이관 외측과 굴착부의 측면 사이에 형성되는 터파기공간에 모래와 자갈을 이용하여 매움 작업을 하되, 상기 트로이관의 높이와 동일한 높이까지 메움 작업을 하는 터파기 공간 메움단계와 상기 트로이관 상측으로 콘크리트를 이용하여 상측 보호부를 형성하는 상측 보호부 형성단계와 상기 상측 보호부의 상측으로 혼합기층, 프라임 코팅, 텍코팅으로 표면처리하는 표면처리단계로 이루어져 있으며, 가시설의 설치 없이도 시공이 가능하여 그에 따른 비용, 공정단축에 따른 작업능률이 향상되도록 하고 있다.In the prior art, a method of constructing a high-pressure cable underground pipe using a troi tube, which is disclosed in Patent Document 10-0748258, has been proposed. In order to insert a troi tube, a tilting surface is formed by maintaining a constant inclination angle, Wherein the bottom surface has a width equal to the width of the outer side of the trolley tube, and a plurality of troch tubes are seated on the bottom surface of the trench, Forming a predetermined amount of sand in the space portion of the trojan tube, forming a high-voltage cable at a predetermined interval on the upper side of the sand, and repeatedly forming the sand flat on the upper side of the high- A step of burying a pipe for embedding a high-voltage cable and a step formed between the outer side of the troy pipe and the side surface of the excavating portion The upper part of the trench pipe is filled with sand and gravel to fill the trench pipe to a height equal to the height of the trench pipe, And a surface treatment step of performing a surface treatment by a mixer layer, a primer coating, and a tec coating to the upper side of the protective part formation step and the upper side protective part, and it is possible to perform the construction without installing the provisional construction, .

그러나, 이러한 종래 기술 역시 트로이관의 내부에 케이블을 균등간격으로 이격시켜 시공하는 과정이 앞서 언급한 바와 같은 작업자의 수작업 및 스페이서의 설치 및 해체, 모래의 투입과 같은 공정을 그대로 진행되어야 하는 문제점이 있다.
However, such conventional techniques also require that the process of installing cables at even intervals in the interior of the troly tube requires manual work of the operator, installation and disassembly of the spacers, and input of sand, have.

대한민국등록특허 10-0748258호(2007.08.03. 등록)Korean Registered Patent No. 10-0748258 (Registered on Mar. 3, 2007) 대한민국등록특허 10-1309774호(2013.09.11. 등록)Korean Registered Patent No. 10-1309774 (Registered on September 11, 2013)

본 발명은 굴착된 관로매설홈 길이방향을 따라 복수개의 전력관로를 적층하여 시공함에 있어서, 관로매설홈을 굴착할 때 파내어진 원토를 이용하여 되메우기작업을 진행하도록 하고 스페이서의 설치 및 해체작업을 생략하며 원토투입과 다지기 및 전력관로의 간격유지작업이 동시에 이루어지도록 하여 자원재활용성을 높이고 작업시간의 단축은 물론 작업효율성을 향상시킬 수 있도록 한 원토를 재활용한 전력관로 되메우기 다지기 시공방법을 제공함에 그 목적이 있다.
In the present invention, when a plurality of electric power lines are stacked along the lengthwise direction of grooved grooved grooves, the grooved work is carried out using the excavated raw soil when excavating the grooved grooves, and the installation and dismantling work of the spacers are omitted And it is possible to increase the recyclability of resources and to improve work efficiency as well as work time by making the input of raw soil and chopping and maintenance of gap between power pipelines be performed at the same time. There is a purpose.

상기 목적을 달성하기 위한 수단으로 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법은, 굴착된 관로매설홈의 길이방향을 따라 바닥층을 시공하는 바닥층시공공정 후 시공된 바닥층 표면에 복수개의 전력관로를 관로매설홈의 길이방향을 따라 매설하는 전력관로매설공정 및 관로매설홈최상단층 시공공정을 포함하는 전력관로 시공방법에 있어서, 원토선별부와 간격유지부, 원토투입부 및 원토평탄부를 갖는 원토선별포설장치와, 1차롤러다짐부와 2차롤러다짐부 및 1차롤러다짐부와 2차롤러다짐부 사이에 구비되는 진동다짐부를 갖는 진동롤러다짐장치를 포함하고, 바닥층시공공정은, 관로매설홈을 굴착할 때 파내어진 원토를 상기 원토선별포설장치의 원토선별부로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치를 관로매설홈의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈의 길이방향을 따라 포설함과 동시에 원토선별장치의 원토평탄부에 의해 포설된 선별토의 표면 평탄화 고르기작업한 후, 상기 진동롤러다짐장치를 관로매설홈의 길이방향을 따라 이동시켜 상기 바닥층시공공정에서의 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부에 의한 1차롤러다짐과 진동다짐부에 의한 진동다짐 및 2차롤러다짐부에 의한 2차롤러다짐 작업이 관로매설홈의 길이방향을 따라 순차적으로 다져지도록 이루어지고, 전력관로매설공정은, 상기 복수개의 전력관로를 관로매설홈의 길이방향을 따라 포설하고 굴착된 관로매설홈의 길이방향을 따라 상기 원토선별포설장치가 이동되도록 위치한 후, 상기 간격유지부의 간격유지홈들을 상기 복수개의 전력관로 각각에 끼우는 간격유지부 위치공정; 간격유지부 위치공정 후 원토선별포설장치의 원토선별부를 통해 관로매설홈 굴착시 파내어진 원토를 선별토와 불량토를 선별하고 선별된 선별토를 원토투입부를 통해 관로매설홈에 투입하되 원토선별포설장치를 관로매설홈의 길이방향을 따라 이동시키면서 간격유지부에 의해 복수개의 전력관로의 간격이 동일하게 유지되는 상태로 원토투입부를 통해 선별된 선별토가 투입되도록 하고 투입된 선별토가 관로매설홈의 길이방향을 따라 이동되는 원토선별포설장치의 원토평탄부에 의해 즉시 표면 평탄화 고르기작업이 진행되도록 하는 전력관로 되메우기공정으로 구비되어 이루어지며, 상기 되메우기공정 후, 상기 진동롤러다짐장치를 관로매설홈의 길이방향을 따라 이동시켜 상기 되메우기공정에서의 상기 원토평탄부에 의해 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부에 의한 1차롤러다짐과 진동다짐부에 의한 진동다짐 및 2차롤러다짐부에 의한 2차롤러다짐이 관로매설홈의 길이방향을 따라 순차적으로 다져지도록 이루어지며, 관로매설홈최상단층 시공공정은, 관로매설홈을 굴착할 때 파내어진 원토를 상기 원토선별포설장치의 원토선별부로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치를 관로매설홈의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈의 길이방향을 따라 관로매설홈의 최상단층을 포설함과 동시에 원토선별장치의 원토평탄부에 의해 포설된 선별토의 표면 평탄화 고르기작업을 진행한 후, 상기 관로매설홈최상단층 시공공정 후, 상기 진동롤러다짐장치를 관로매설홈의 길이방향을 따라 이동시켜 상기 관로매설홈최상단층 시공공정에서의 상기 원토평탄부에 의해 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부에 의한 1차롤러다짐과 진동다짐부에 의한 진동다짐 및 2차롤러다짐부에 의한 2차롤러다짐이 관로매설홈의 길이방향을 따라 순차적으로 다져지도록 이루어진다.
In order to accomplish the above object, there is provided a method for reclaiming a power pipeline by recycling a raw material of the present invention, comprising the steps of: providing a plurality of electric power lines on a surface of a floor layer constructed after a floor layer construction process for constructing a floor layer along a longitudinal direction of an excavated channel- A method for constructing a power pipeline including a power pipeline burial process buried along a longitudinal direction of a pipeline buried groove and a topmost layer construction process of a buried grooved groove bottom, comprising the steps of: And a vibrating roller compaction device having a vibrating compaction part provided between the primary roller compaction part, the secondary roller compaction part, the primary roller compaction part, and the secondary roller compaction part, When the buried grooves are excavated, the extracted soil is sorted into the soil and defective soil by the earth sorting unit of the earth sorting and laying apparatus, and at the same time, The selected sorting soil is laid along the longitudinal direction of the excavated grove grooves while moving along the longitudinal direction of the buried grooves, and at the same time, after the surface flattening and sorting work of the selected soil laid by the original soil leveling portion of the earth sorting device, The roller compacting device is moved along the longitudinal direction of the grooved grooves so as to planarize the surface of the selected soil so that the surface of the selected soil is subjected to the primary roller compaction by the primary roller compaction portion and the vibration compaction by the vibration compaction portion, Wherein the second roller compaction operation by the roller compaction unit is performed so that the second roller compaction operation is sequentially performed along the longitudinal direction of the grooved groove, and the electric power line embedding step is a step of installing the plurality of electric power lines along the longitudinal direction of the grooved grooves, And the space holding grooves of the spacing retaining portions are disposed in the plurality of electric power pipes A gap holding portion positioning step of sandwiching the gap holding portions; Separation of the soil after the process of separating the retaining parts After selecting the soil extracted from the excavated soil through the earth selection part of the installation device, the selected soil is selected and the selected soil is put into the grouting groove through the soil input part, The apparatus is moved along the longitudinal direction of the pipeline buried grooves so that the selected soil is inputted through the raw soil input section in a state where the intervals of the plurality of power pipelines are kept the same by the interval maintaining section, And a power pipe backing process for allowing the surface flattening and leveling operation to proceed immediately by the original toe flattening portion of the earth soil sorting and laying apparatus moved along the longitudinal direction. After the backwashing process, the vibrating roller compaction device The flattening and grading operation is performed by the one-side flattening portion in the back- The surface of the screening soil is formed so that the primary roller compaction by the primary roller compaction portion and the vibration compaction by the vibration compaction portion and the secondary roller compaction by the secondary roller compaction portion are successively formed along the longitudinal direction of the groove embedded in the pipeline , The uppermost layer construction process for grouting grooves is performed by selecting the soil to be sorted and the soil to be sorted by the earth sorting unit of the earth sorting and laying apparatus when the excavated groove is excavated, The uppermost layer of the channel buried grooves is laid along the longitudinal direction of the groove buried in the channel excavated with the selected sorting soil while moving along the longitudinal direction, and at the same time, the surface flattening and leveling work of the screening soil laid by the one- The vibration roller compaction apparatus is moved along the longitudinal direction of the groove in the pipeline so as to form the uppermost layer of the groove embedded in the pipeline, The surface of the selected soil subjected to planarization and grading by the abovementioned original flat-bottomed sand portion is subjected to primary roller compaction by the primary roller compaction portion, vibration compaction by the vibration compaction portion, and secondary roller compaction by the secondary roller compaction portion, And is formed so as to be sequentially formed along the longitudinal direction of the groove.

본 발명은 전력관로를 매설하기 위해 관로매설홈을 굴착한 후 관로매설홈을 굴착할 때 파내어진 원토를 선별토와 불량토로 선별하여 선별된 선별토를 다시 이용하여 되메우기 작업을 진행하기 때문에, 모래와 같은 골재가 필요치 않아 비용절감 효과를 기대할 수 있으며 모래와 같은 골재의 운반작업이 생략되기 때문에 즉시 되메우기 작업을 진행할 수 있고 작업자가 직접 스페이서를 설치하고 다시 철거하는 작업을 반복하는 것을 생략할 수 있고 전력관로들의 간격이 서로 일정하게 유지된 상태에서 즉시 선별토가 투입되고 선별토 투입과 동시에 표면 평탄화 고르기작업이 진행됨에 따라 전력관로를 매설할 때의 작업시간 및 작업자의 피로감을 최소화할 수 있으며 작업자의 안전사고를 미연에 방지할 수 있다.
In the present invention, when excavating the grout grout to bury the electric power channel, the excavated groove is excavated, and the excavated soil is sorted into the selected soil and the defective soil, and the selected soil is again used to carry out the back- It is possible to expect a cost saving effect and omission of the transportation of aggregate such as sand can be carried out immediately and the operator can omit repeatedly installing and dismounting the spacer directly As the distance between the electric power lines is kept constant, the screening soil is immediately injected and the surface flattening and leveling operation is performed simultaneously with the selection of the soil. Therefore, the working time and the fatigue of the operator can be minimized when the power line is buried, Can be prevented in advance.

도 1a 내지 도 1f는 종래 전력관로를 매설 시공하는 과정을 나타낸 개념도이다.
도 2는 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법의 공정을 나타낸 공정도이다.
도 3은 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법의 바닥층시공공정을 나타낸 개념도이다.
도 4는 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법의 전력관로가 관로매설홈에 수평상으로 복수개 포설된 상태의 개념도이다.
도 5는 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 의해 되메우기 공정을 나타낸 정면도이다.
도 6은 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 의해 되메우기 공정을 나타낸 측면도이다.
도 7은 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법의 원토선별포설장치의 구성요부를 나타낸 사시도이다.
도 8 내지 도 10은 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 의한 다지기 공정을 각각 나타낸 개념도이다.
FIGS. 1A to 1F are conceptual diagrams showing a process of burial construction of a conventional power line.
Fig. 2 is a process drawing showing a process of a method for reclaiming power from a recycled power plant according to the present invention.
FIG. 3 is a conceptual view showing a bottom layer construction process of a power pipe back-up construction method in which a raw material of the present invention is recycled.
Fig. 4 is a conceptual diagram of a state in which a plurality of electric power lines of a power line construction method recycled using the present invention as a power line are installed on a plurality of water line grooves in a horizontal plane.
FIG. 5 is a front view showing the backwashing process by the backwashing method of recycling the power plant according to the present invention.
FIG. 6 is a side view showing a back-up process by a back-up method for recycling power plants according to the present invention.
Fig. 7 is a perspective view showing constituent parts of the earth soil sorting and laying apparatus of the power pipe backing construction method recycled as the present invention.
Figs. 8 to 10 are conceptual diagrams each showing a chopping process by a power piping construction method recycled using the earth of the present invention. Fig.

이하, 상기 목적 외에 본 발명의 다른 목적 및 특징들은 첨부 도면을 참조한 실시 예에 대한 설명을 통하여 명백히 드러나게 될 것이다.Hereinafter, other objects and features of the present invention will be apparent from the following description of embodiments with reference to the accompanying drawings.

다르게 정의되지 않는 한, 기술적이거나 과학적인 용어를 포함해서 여기서 사용되는 모든 용어들은 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미를 가지고 있다. 일반적으로 사용되는 사전에 정의되어 있는 것과 같은 용어들은 관련 기술의 문맥상 가지는 의미와 일치하는 의미를 가진 것으로 해석되어야 하며, 본 출원에서 명백하게 정의하지 않는 한, 이상적이거나 과도하게 형식적인 의미로 해석되지 않는다.
Unless defined otherwise, all terms used herein, including technical or scientific terms, have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. Terms such as those defined in commonly used dictionaries should be interpreted as having a meaning consistent with the meaning in the context of the relevant art and are to be interpreted in an ideal or overly formal sense unless explicitly defined in the present application Do not.

이하에서는, 본 발명의 실시예에 따른 원토를 재활용한 전력관로 되메우기 다지기 시공방법을 첨부된 도면을 참고하여 좀 더 구체적으로 설명한다.
Hereinafter, a construction method for reclaiming power from a raw material according to an embodiment of the present invention will be described in more detail with reference to the accompanying drawings.

도시된 바와 같이 본 발명인 원토를 재활용한 전력관로 되메우기 다지기 시공방법은, 굴착된 관로매설홈의 길이방향을 따라 바닥층을 시공하는 바닥층시공공정 후 시공된 바닥층 표면에 복수개의 전력관로를 관로매설홈의 길이방향을 따라 매설하는 전력관로매설공정 및 관로매설홈최상단층 시공공정을 포함하는 원토를 재활용한 전력관로 되메우기 다지기 시공방법에 관한 것이다.As shown in the drawings, the method for reclaiming a power pipe according to the present invention is a method for reclaiming a power pipeline by recycling a plurality of power pipelines into a bottom surface of a bottom layer constructed after a bottom layer construction process for constructing a bottom layer along a longitudinal direction of a buried channel, The present invention relates to a power pipe back-up method for recycling raw materials including a power pipe laying process along a longitudinal direction and a top-end floor construction process.

본 발명은 상기 관로매설홈의 굴착작업을 포크레인 즉 굴착기를 이용하여 길이가 긴 관로매설홈을 지면에 대해 굴착할 때 파내어진 흙 즉, 원토를 재활용 선별하여 파내어진 관로매설홈의 되메우기 작업에 사용한다.In the present invention, when excavating the pipeline buried grooves by using a forklag, that is, by using an excavator, the excavated grooves are used for back-up work of grouting grooves buried in pipelines do.

이에 따라, 본 발명은 모래와 같은 골재가 필요치 않기 때문에 골재구입에 따른 비용을 생략할 수 있으며 골재를 운반할 때 발생되는 시간이나 골재를 채취함에 따른 문제점을 해결할 수 있다.Accordingly, since the aggregate material such as sand is not required, the present invention can eliminate the cost of purchasing the aggregate material, and solve the problems caused by the time or aggregate material that is generated when the aggregate material is transported.

또한, 본 발명은 관로매설홈에 복수개의 전력관로를 시공할 때, 전력관로의 간격유지작업과 간격이 유지된 전력관로의 되메우기 작업은 물론 되메우기작업 후의 평탄화 작업을 동시에 진행할 수 있으며, 복수개의 스페이서를 설치하거나 설치된 스페이서를 빼내는 작업이 생략되기 때문에 작업효율성 및 작업성 향상과 작업시간의 단축은 물론 작업자의 안전사고를 방지한다.In addition, when constructing a plurality of electric power lines in the grooved grooves, the present invention can simultaneously carry out the interval maintaining operation of the electric power line, the backing operation of the electric power line with the interval maintained, and the flattening operation after the backing operation, It is possible to improve the work efficiency and workability, to shorten the working time, and to prevent worker safety accidents.

이를 위해 본 발명은, 원토선별부(10)와 간격유지부(20), 원토투입부(30) 및 원토평탄부(40)를 갖는 원토선별포설장치(100)를 포함하여 이루어진다.To this end, the present invention comprises a soil sorting and laying apparatus 100 having a soil sorting unit 10, a space holding unit 20, a soil input unit 30, and a circular arc sputtering unit 40.

또한, 1차롤러다짐부(210)와 2차롤러다짐부(220) 및 1차롤러다짐부(210)와 2차롤러다짐부(220) 사이에 구비되는 진동다짐부(230)를 갖는 진동롤러다짐장치(200)를 포함하여 이루어진다.The vibration of the primary roller 20 and the secondary roller compaction unit 220 is compensated by the vibration of the primary roller 20 and the secondary roller compaction unit 220 and between the primary roller compaction unit 210 and the secondary roller compaction unit 220, And a roller compaction apparatus 200.

상기 원토선별포설장치(100)는, 도시된 바와 같이 길이방향으로 길게 굴착된 관로매설홈(52)의 표면 일측에 위치된 상태로 관로매설홈(52)의 길이방향을 따라 이동한다.As shown in the figure, the soil sorting and laying apparatus 100 moves along the longitudinal direction of the pipeline buried grooves 52 while being positioned at one side of the surface of the pipeline buried grooves 52, which are excavated long in the longitudinal direction.

이와 같이 원토선별포설장치(100)가 관로매설홈(52)의 길이방향을 따라 이동할 때, 수평상으로 놓여진 복수개의 전력관로(51)에 대한 간격유지는 물론 간격이 유지된 복수개의 전력관로(51) 사이사이에 굴착할 때 파내어진 원토 중 선별된 선별토를 투입하여 되메우기 하고 되메워진 선별토의 표면을 평탄하게 고르는 평탄화작업이 동시에 진행된다.When the earth sorting and laying apparatus 100 moves along the longitudinal direction of the pipeline buried grooves 52, it is possible to maintain the spacing of the plurality of power pipelines 51 placed in the horizontal plane, 51), the selected sorting soil is squeezed out of the excavated soil, and the flattening operation for smoothly picking up the surface of the reclaimed soil is carried out at the same time.

이를 위해 원토선별포설장치(100)의 간격유지부(20)는, 상기 원토선별포설장치(100)가 관로매설홈(52)의 길이방향을 따라 이동되는 방향의 전방측에 위치되고, 상기 원토평탄부(40)는, 상기 간격유지부(20)의 후방측에 위치되며, 상기 원토투입부(30)는 상기 간격유지부(20)와 원토평탄부(40) 사이에 위치된다.The spacing maintaining unit 20 of the earth sorting and laying apparatus 100 is located on the front side in the direction in which the earth sorting and laying apparatus 100 is moved along the longitudinal direction of the pipeline buried grooves 52, The top end projecting portion 40 is located on the rear side of the gap holding portion 20 and the source putting portion 30 is positioned between the gap maintaining portion 20 and the original top end projecting portion 40.

또한, 상기 원토투입부(30)의 상부측에는 상기 원토선별부(10)에 의해 선별된 선별토를 상기 원토투입부(30)측으로 투입됨이 용이하도록 선별토가이드(31)가 구비된다.The selection soil guide 31 is provided on the upper side of the soil introduction part 30 so that the sorting soil selected by the soil sorting part 10 can be easily inputted to the soil introduction part 30 side.

상기 진동롤러다짐장치(200)는, 도시된 바와 같이 되메워진 선별토의 표면을 다져주는 것으로, 관로매설홈(52)의 내부에서 관로매설홈(52)의 길이방향을 따라 되메워진 선별토의 표면을 따라 이동하면서 상기 원토선별포설장치(100)의 원토평탄부(40)에 의해 평탄화 고르기 작업된 선별토 표면을 다져준다.The vibrating roller compaction apparatus 200 is constructed by grinding the surface of the reclaimed soil as shown in the figure so that the surface of the screening soil buried along the longitudinal direction of the pipeline embedding grooves 52 in the pipeline embedding grooves 52 So that the selected soil surface is planarized by the original soil leveling portion 40 of the soil sorting and laying apparatus 100.

이와 같이 이루어진 본 발명의 전력관로매설공정(S10)은, 간격유지부 위치공정(S11)과 전력관로 되메우기공정(S12)으로 이루어진다.The power pipeline sub-step S10 of the present invention thus constituted comprises a gap maintaining portion positioning step S11 and a power pipeline back-up step S12.

본 발명의 간격유지부 위치공정(S11)은, 상기 복수개의 전력관로(51)를 관로매설홈(52)의 길이방향을 따라 포설하고 굴착된 관로매설홈(52)의 길이방향을 따라 상기 원토선별포설장치(100)가 이동되도록 위치한 후, 상기 간격유지부(20)의 간격유지홈(21)들을 상기 복수개의 전력관로(51) 각각에 끼우는 공정이다.The spacing maintaining portion positioning step S11 of the present invention is characterized in that the plurality of power conduits 51 are laid along the longitudinal direction of the conduit burial grooves 52 and the grooves 52 are formed along the longitudinal direction of the excavated conduit buried grooves 52, And the gap holding grooves 21 of the gap holding portion 20 are inserted into the plurality of power conduits 51 after the selective laying apparatus 100 is moved.

즉, 굴착된 관로매설홈(52)의 길이방향을 따라 수평상으로 복수개의 전력관로(51)를 넣어 위치한 후, 관로매설홈(52)에 위치된 복수개의 전력관로(51) 각각을 원토선별포설장치(100)의 간격유지부(20)에 구비된 복수개의 간격유지홈(21) 각각에 끼워 위치한다.That is, a plurality of power conduits 51 are horizontally placed along the longitudinal direction of the excavated conduit buried grooves 52, and then each of the plurality of power conduits 51 located in the conduit buried grooves 52 is sorted And is sandwiched in each of the plurality of spacing grooves 21 provided in the gap holding portion 20 of the laying apparatus 100.

이와 같이 간격유지부(20)에 구비된 복수개의 간격유지홈(21) 각각에 수평상의 복수개 전력관로(51) 각각을 끼워 위치하는 이유는, 상기 원토선별포설장치(100)가 관로매설홈(52)의 길이방향을 따라 이동할 때 수평상의 복구개 전력관로(51) 각각의 간격이 일정하게 이격(離隔)되도록 하기 위함이다.The reason why the plurality of horizontal electric power lines 51 are sandwiched in each of the plurality of spacing grooves 21 provided in the interval holding portion 20 is that the earth sorting and laying apparatus 100 is installed in the channel- 52 are spaced apart from each other by a predetermined distance from each other.

본 발명의 전력관로 되메우기공정(S12)은, 간격유지부 위치공정(S11) 후 원토선별포설장치(100)의 원토선별부(10)를 통해 관로매설홈(52) 굴착시 파내어진 원토를 선별토와 불량토를 선별하고 선별된 선별토를 원토투입부(30)를 통해 관로매설홈(52)에 투입하되 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 간격유지부(20)에 의해 복수개의 전력관로(51)의 간격이 동일하게 유지되는 상태로 원토투입부(30)를 통해 선별된 선별토가 투입되도록 하고 투입된 선별토가 관로매설홈(52)의 길이방향을 따라 이동되는 원토선별포설장치(100)의 원토평탄부(40)에 의해 즉시 표면 평탄화 고르기작업이 진행되도록 하는 공정이다.The power pipe backing step S12 of the present invention is a method of sorting out the raw materials extracted at the time of excavation of the pipeline buried grooves 52 through the earth sorting unit 10 of the earth sorting and laying out apparatus 100 after the interval holding unit positioning step S11, Soil and poor soil are selected and the selected soil is put into the pipeline buried grooves 52 through the raw soil input part 30 so that the earth land sorting and laying apparatus 100 is moved along the longitudinal direction of the pipeline buried grooves 52 The selected soil is introduced into the channel embedded grooves 52 so that the selected soil can be introduced through the soil input section 30 in a state where the intervals of the plurality of electric power lines 51 remain the same by the interval maintaining section 20, So that the surface flattening and grading work is immediately carried out by the original to-be-flattened portion 40 of the earth-moving laying and laying apparatus 100 moving along the longitudinal direction of the ground.

이와 같은 본 발명의 전력관로 되메우기공정(S12)에 의해 수평상으로 놓여진 복수개의 전력관로(51)가 일정한 간격이 유지된 상태로 되메우기작업이 이루어진다.The power pipeline back-up step S12 of the present invention allows a plurality of power pipelines 51, which are placed on a horizontal plane, to be returned to a state in which a predetermined interval is maintained.

즉, 간격유지부 위치공정(S11) 후 원토선별포설장치(100)를 관로매설홈(52)의 길이방향으로 이동시키면, 수평상으로 복수개 놓여진 전력관로(51)들의 간격이 간격유지부(20)에 동일한 간격으로 유지된 상태에서 원토선별부(10)를 통해 선별된 선별토가 원토투입부(30)측으로 투입되어 간격유지부(20)에 의해 동일한 간격을 유지하는 복수개의 전력관로(51) 사이사이는 물론 복수개의 전력관로(51)의 상부측에 투입되어 채워진다.That is, when the separating and laying apparatus 100 is moved in the longitudinal direction of the pipeline embedding grooves 52 after the spacing maintaining portion positioning step S11, the spacing of the plurality of power piping 51, The plurality of electric power lines 51 (51), which are kept at the same interval by the interval holding unit (20), are inputted into the soil inputting unit (30) side through the soil sorting unit Of course, is filled into the upper side of the plurality of power conduits 51 and filled.

또한, 선별토가 투입되어 채워짐과 동시에 상기 원토평탄부(40)에 의해 채워진 선별토의 표면 평탄화작업이 동시에 이루어진다.In addition, the surface soil flattening operation of the screening soil filled with the original soil leveling portion 40 is carried out at the same time as the screening soil is filled and filled.

이와 같이 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키는 것에 의해 복수개의 전력관로(51)의 간격이 유지되고 간격이 유지된 복수개의 전력관로(51) 사이사이 및 상부측에 선별토가 투입되어 되메우기 작업이 진행되고 되메우기 된 선별토의 표면 평탄화작업이 동시에 이루어지기 때문에, 작업자가 일일이 복수개의 스페이서를 관로매설홈에 넣어진 복수개의 전력관로의 길이방향을 따라 끼워 설치한 후 모래와 같은 골재를 전력관로의 길이방향을 따라 채워 되메우기 한 다음, 되메워진 골재 표면의 길이방향을 따라 작업자가 일일이 이동하면서 골라 평탄화작업을 하고 또한 작업자가 전력관로의 길이방향을 따라 일일이 이동하면서 전력관로에 끼워진 복수개의 스페이서를 철거하는 작업이 생략된다.As described above, by moving the earth sorting and laying apparatus 100 along the longitudinal direction of the pipeline embedment grooves 52, the plurality of power pipelines 51 are spaced apart from each other, And a surface smoothing operation of the recovered soil is carried out simultaneously with the backwashing operation being carried out on the upper side, so that the worker can individually sandwich the plurality of spacers along the longitudinal direction of the plurality of electric power lines embedded in the channel- After the installation, aggregate such as sand is filled up along the longitudinal direction of the electric power line, and the operator performs planarization while moving along the longitudinal direction of the aggregate surface, and the worker conducts the planarization work along the longitudinal direction of the electric power line The operation of removing a plurality of spacers inserted in the electric power line while moving is omitted.

상기 되메우기공정(S12) 후, 상기 진동롤러다짐장치(200)를 관로매설홈(52)의 길이방향을 따라 이동시켜 상기 되메우기공정(S12)에서의 상기 원토평탄부(40)에 의해 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐이 관로매설홈(52)의 길이방향을 따라 순차적으로 다져지도록 이루어진다.After the backfilling step S12, the vibrating roller compaction apparatus 200 is moved along the longitudinal direction of the pipeline embedment groove 52, and the flattening and grading operation is performed by the original toff top portion 40 in the backfilling step S12 And the secondary roller compaction by the secondary roller compaction unit 220 is carried out by the grooved grooves ( 52 in the longitudinal direction.

이에 따라, 되메우기공정(S12)에서 되메워진 선별토 표면의 길이방향을 따라 진동롤러다짐장치(200)를 이동시키면서 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐 작업이 순차적으로 진행되기 때문에 롤러다짐장치를 이용한 롤러다짐작업과 진동다짐장치를 이용한 진동다짐작업을 따로따로 하지 않아도 된다. The primary roller compaction by the primary roller compaction unit 210 and the compaction of the primary vibration by the primary compaction unit 230 are performed while moving the vibration roller compaction apparatus 200 along the longitudinal direction of the surface of the screening soil, And the secondary roller compaction by the secondary roller compaction unit 220 proceeds sequentially. Therefore, the roller compaction operation using the roller compaction apparatus and the vibration compaction operation using the vibration compaction apparatus need not be separately performed.

본 발명은, 상기 전력관로매설공정(S10)을 반복적으로 진행하여 굴착된 관로매설홈(52)에 수평상태로 복수개 위치되는 전력관로(51)를 복수개 적층하여 매설하면 된다.In the present invention, a plurality of electric power lines 51 positioned in a horizontal state in a plurality of excavated pipeline buried grooves 52 may be stacked and buried by repeating the electric power line burial process S10.

이 때, 하단측에 위치되는 전력관로(51)를 포설하기 위해 되메워진 선별토를 원토평탄부(40)에 의해 평탄화작업한 후 평탄화작업된 선별토를 역시 진동롤러다짐장치(200)에 의한 1차롤러다짐과 진동다짐 및 2차롤러다짐을 순차적으로 진행하여 선별토를 견고하게 다진 다음, 상기 전력관로매설공정(S10)을 반복 진행하여 전력관로(51)의 상단측에 복수개의 전력관로(51)를 수평 매설한다.At this time, the selected soil which has been filled to lay the electric power line 51 located at the lower end side is planarized by the original soil leveling portion 40, and the soil subjected to the planarization is also ground by the vibrating roller compaction apparatus 200 The first and second roller compaction, the vibration compaction and the second roller compaction are sequentially performed to solidify the selected soil, and then the electric power pipeline submerging step (S10) is repeated so that a plurality of power pipes (51) is horizontally embedded.

본 발명의 바닥층시공공정(S20)은, 관로매설홈(52)을 굴착할 때 파내어진 원토를 상기 원토선별포설장치(100)의 원토선별부(10)로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈(52)의 길이방향을 따라 포설함과 동시에 원토선별장치(100)의 원토평탄부(40)에 의해 포설된 선별토의 표면 평탄화 고르기작업한 후, 상기 진동롤러다짐장치(200)를 관로매설홈(52)의 길이방향을 따라 이동시켜 상기 바닥층시공공정(S20)에서의 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐 작업이 관로매설홈(52)의 길이방향을 따라 순차적으로 다져지도록 이루어진다.In the bottom layer construction step (S20) of the present invention, the soil extracted when excavating the pipeline buried grooves (52) is sorted by the soil selection unit (10) of the soil sorting and laying out apparatus (100) At the same time, the soil sorting and laying apparatus 100 is moved along the longitudinal direction of the pipeline buried grooves 52, and the selected sorting soil is laid along the longitudinal direction of the excavated pipeline buried grooves 52, (S20) by moving the vibrating roller compaction apparatus 200 along the longitudinal direction of the pipeline embedment grooves 52 after the surface flattening and selecting operation of the screening soil disposed by the original top- The surface of the soil subjected to the sorting operation is subjected to the primary roller compaction by the primary roller compaction unit 210, the vibration compaction by the vibration compaction unit 230 and the secondary roller compaction by the secondary roller compaction unit 220 So that the work is sequentially formed along the longitudinal direction of the pipeline buried grooves 52.

즉, 굴착된 관로매설홈(52)에 전력관로(51)를 포설하기 전 관로매설홈(52)의 바닥층을 평탄하게 다지기 위한 공정인 바닥층시공공정(S20)을 진행할 때 모래와 같은 골재를 사용하지 않고 관로매설홈(52)을 굴착할 때 파내어진 원토를 선별한 후 선별토를 사용하여 바닥층을 시공함에 따라, 모래와 같은 골재를 사용할 때 발생되는 비용을 절감할 수 있다.That is, when performing the bottom layer construction process (S20), which is a process for flattening the bottom layer of the channel-embedded grooves 52 before installing the electric power channel 51 in the excavated channel-embedded grooves 52, It is possible to reduce the cost incurred in using the aggregate such as sand as the bottom layer is constructed by using the screening soil after selecting the excavated soil.

또한, 바닥층시공공정(S20)에서 되메워진 선별토 표면의 길이방향을 따라 진동롤러다짐장치(200)를 이동시키면서 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐 작업이 순차적으로 진행되기 때문에 롤러다짐장치를 이용한 롤러다짐작업과 진동다짐장치를 이용한 진동다짐작업을 따로따로 하지 않아도 된다. The primary roller compaction by the primary roller compaction unit 210 and the compaction of the primary vibration by the primary roller compaction unit 230 are performed while moving the vibration roller compaction apparatus 200 along the longitudinal direction of the surface of the screening soil, And the secondary roller compaction by the secondary roller compaction unit 220 proceeds sequentially. Therefore, the roller compaction operation using the roller compaction apparatus and the vibration compaction operation using the vibration compaction apparatus need not be separately performed.

또한, 본 발명은 상기 전력관로매설공정(S10)을 반복적으로 진행하여 수평상으로 복수개 위치되는 전력관로(51)를 수직선상으로 복수개 적층한 후 최상단측에 관로매설홈최상단층 시공공정(S30)을 진행하는 바, 상기 관로매설홈최상단층 시공공정(S30)은, 관로매설홈(52)을 굴착할 때 파내어진 원토를 상기 원토선별포설장치(100)의 원토선별부(10)로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈(52)의 길이방향을 따라 관로매설홈(52)의 최상단층을 포설함과 동시에 원토선별장치(100)의 원토평탄부(40)에 의해 포설된 선별토의 표면 평탄화 고르기작업이 진행되어 이루어질 수 있다.In the present invention, a plurality of electric power lines 51 are repeatedly laid on a vertical line, and a plurality of electric power lines 51 are horizontally laid out repeatedly. The uppermost layer construction step S30 of the grouting groove bottom is performed by selecting the soil extracted by the soil sorting unit 10 of the soil sorting and laying apparatus 100 when the pipeline buried grooves 52 are excavated, While the soil sorting and laying apparatus 100 is moved along the longitudinal direction of the pipeline buried grooves 52, the selected soil is buried in the pipeline along the longitudinal direction of the excavated pipeline buried grooves 52, The uppermost layer of the grooves 52 is laid out and the surface flattening and grading work of the screening soil laid by the original toe sloping portion 40 of the earth sorting apparatus 100 proceeds.

이에 따라, 역시 모래와 같은 골재를 사용하지 않고 관로매설홈(52)을 굴착할 때 파내어진 원토를 선별한 후 선별토를 사용하여 바닥층을 시공함에 따라, 모래와 같은 골재를 사용할 때 발생되는 비용을 절감할 수 있다.Accordingly, when excavating the grout-embedded grooves 52 without using aggregates such as sand, the ground floor is constructed by using the selected soil after selecting the excavated soil, and thus the cost incurred when using the aggregate such as sand Can be saved.

또한, 관로매설홈최상단층 시공공정(S30)에서 되메워진 선별토 표면의 길이방향을 따라 진동롤러다짐장치(200)를 이동시키면서 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐 작업이 순차적으로 진행되기 때문에 롤러다짐장치를 이용한 롤러다짐작업과 진동다짐장치를 이용한 진동다짐작업을 따로따로 하지 않아도 된다. The primary roller compaction and the compaction of the primary roller by the primary roller compaction unit 210 while moving the vibrating roller compaction apparatus 200 along the longitudinal direction of the surface of the screening soil restored in the uppermost layer construction step (S30) And the secondary roller compaction by the secondary roller compaction unit 220 proceeds sequentially. Therefore, the roller compaction operation using the roller compaction apparatus and the vibration compaction operation using the vibration compaction apparatus are separately performed You do not have to do.

또한, 바닥층시공공정(S20)과 관로매설홈최상단층 시공공정(S30)을 진행할 때 상기 원토선별포설장치(100)를 이용하여 선별토의 투입과 투입된 선별토의 평탄화작업이 동시에 진행될 수 있어 작업시간 단축은 물론 작업성 및 작업효율성을 크게 향상시킬 수 있다.
In addition, when proceeding with the bottom layer construction step S20 and the uppermost layer construction step S30 in which the grooves are buried, it is possible to simultaneously perform the planarization work of the input soil and the input soil by using the soil sorting and laying apparatus 100, And workability and work efficiency can be greatly improved.

이상과 같이 본 발명에서는 구체적인 구성 요소 등과 같은 특정 사항들과 한정된 실시예 및 도면에 의해 설명되었으나 이는 본 발명의 보다 전반적인 이해를 돕기 위해서 제공된 것일 뿐, 본 발명은 상기의 실시예에 한정되는 것은 아니며, 본 발명이 속하는 분야에서 통상적인 지식을 가진 자라면 이러한 기재로부터 다양한 수정 및 변형이 가능하다.As described above, the present invention has been described with reference to particular embodiments, such as specific elements, and specific embodiments and drawings. However, it should be understood that the present invention is not limited to the above- And various modifications and changes may be made thereto by those skilled in the art to which the present invention pertains.

따라서, 본 발명의 사상은 설명된 실시예에 국한되어 정해져서는 아니 되며, 후술하는 특허청구범위뿐 아니라 이 특허청구범위와 균등하거나 등가적 변형이 있는 모든 것들은 본 발명 사상의 범주에 속한다고 할 것이다.
Accordingly, the spirit of the present invention should not be construed as being limited to the embodiments described, and all of the equivalents or equivalents of the claims, as well as the following claims, belong to the scope of the present invention .

10 : 원토선별부 20 : 간격유지부
30 : 원토투입부 40 : 원토평탄부
51 : 전력관로 52 : 관로매설홈
100 : 원토선별포설장치 200 : 진동롤러다짐장치
210 : 1차롤러다짐부 220 : 2차롤러다짐부
230 : 진동다짐부
S10 : 전력관로매설공정 S11 : 간격유지부 위치공정
S12 : 되메우기공정 S20 : 바닥층시공공정
S30 : 관로매설홈최상단층 시공공정
10: earth sorting unit 20:
30: a raw material input unit 40: a one-
51: electric power line 52: duct laying groove
100: earth sorting installation apparatus 200: vibration roller compaction apparatus
210: primary roller compaction unit 220: secondary roller compaction unit
230:
S10: Power line laying process S11: Spacing maintaining portion positioning process
S12: backfilling process S20: bottom layer construction process
S30: Construction process of the uppermost floor

Claims (3)

굴착된 관로매설홈의 길이방향을 따라 바닥층을 시공하는 바닥층시공공정 후 시공된 바닥층 표면에 복수개의 전력관로를 관로매설홈의 길이방향을 따라 매설하는 전력관로매설공정 및 관로매설홈최상단층 시공공정을 포함하는 전력관로 시공방법에 있어서,
원토선별부(10)와 간격유지부(20), 원토투입부(30) 및 원토평탄부(40)를 갖는 원토선별포설장치(100)와,
1차롤러다짐부(210)와 2차롤러다짐부(220) 및 1차롤러다짐부(210)와 2차롤러다짐부(220) 사이에 구비되는 진동다짐부(230)를 갖는 진동롤러다짐장치(200)를 포함하고,
바닥층시공공정(S20)은,
관로매설홈(52)을 굴착할 때 파내어진 원토를 상기 원토선별포설장치(100)의 원토선별부(10)로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈(52)의 길이방향을 따라 포설함과 동시에 원토선별장치(100)의 원토평탄부(40)에 의해 포설된 선별토의 표면 평탄화 고르기작업한 후,
상기 진동롤러다짐장치(200)를 관로매설홈(52)의 길이방향을 따라 이동시켜 상기 바닥층시공공정(S20)에서의 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐 작업이 관로매설홈(52)의 길이방향을 따라 순차적으로 다져지도록 이루어지고,
전력관로매설공정(S10)은,
상기 복수개의 전력관로(51)를 관로매설홈(52)의 길이방향을 따라 포설하고 굴착된 관로매설홈(52)의 길이방향을 따라 상기 원토선별포설장치(100)가 이동되도록 위치한 후, 상기 간격유지부(20)의 간격유지홈(21)들을 상기 복수개의 전력관로(51) 각각에 끼우는 간격유지부 위치공정(S11);
간격유지부 위치공정(S11) 후 원토선별포설장치(100)의 원토선별부(10)를 통해 관로매설홈(52) 굴착시 파내어진 원토를 선별토와 불량토를 선별하고 선별된 선별토를 원토투입부(30)를 통해 관로매설홈(52)에 투입하되 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 간격유지부(20)에 의해 복수개의 전력관로(51)의 간격이 동일하게 유지되는 상태로 원토투입부(30)를 통해 선별된 선별토가 투입되도록 하고 투입된 선별토가 관로매설홈(52)의 길이방향을 따라 이동되는 원토선별포설장치(100)의 원토평탄부(40)에 의해 즉시 표면 평탄화 고르기작업이 진행되도록 하는 전력관로 되메우기공정(S12)으로 구비되어 이루어지며,
상기 되메우기공정(S12) 후,
상기 진동롤러다짐장치(200)를 관로매설홈(52)의 길이방향을 따라 이동시켜 상기 되메우기공정(S12)에서의 상기 원토평탄부(40)에 의해 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐이 관로매설홈(52)의 길이방향을 따라 순차적으로 다져지도록 이루어지고,
관로매설홈최상단층 시공공정(S30)은,
관로매설홈(52)을 굴착할 때 파내어진 원토를 상기 원토선별포설장치(100)의 원토선별부(10)로 선별토와 불량토를 선별함과 동시에 상기 원토선별포설장치(100)를 관로매설홈(52)의 길이방향을 따라 이동시키면서 선별된 선별토를 굴착된 관로매설홈(52)의 길이방향을 따라 관로매설홈(52)의 최상단층을 포설함과 동시에 원토선별장치(100)의 원토평탄부(40)에 의해 포설된 선별토의 표면 평탄화 고르기작업을 진행하고,
상기 관로매설홈최상단층 시공공정(S30) 후,
상기 진동롤러다짐장치(200)를 관로매설홈(52)의 길이방향을 따라 이동시켜 상기 관로매설홈최상단층 시공공정(S30)에서의 상기 원토평탄부(40)에 의해 평탄화 고르기작업된 선별토 표면을 1차롤러다짐부(210)에 의한 1차롤러다짐과 진동다짐부(230)에 의한 진동다짐 및 2차롤러다짐부(220)에 의한 2차롤러다짐이 관로매설홈(52)의 길이방향을 따라 순차적으로 다져지도록 이루어지고,
상기 전력관로매설공정(S10)을 반복적으로 진행하여 굴착된 관로매설홈(52)에 수평상태로 복수개 위치되는 전력관로(51)를 복수개 적층하여 매설하도록 이루어지는 것을 특징으로 하는 원토를 재활용한 전력관로 되메우기 다지기 시공방법.
A bottom layer that constructs the bottom layer along the longitudinal direction of the excavated pipeline buried grooves; a power pipeline buried along the longitudinal direction of the plurality of power pipelines on the surface of the bottom layer constructed after the construction process; The method comprising the steps of:
A soil sorting and laying apparatus 100 having a soil sorting unit 10, a space holding unit 20, a soil input unit 30,
A vibrating roller compaction having a vibrating compaction part 230 provided between the primary roller compaction part 210 and the secondary roller compaction part 220 and between the primary roller compaction part 210 and the secondary roller compaction part 220; Device 200,
In the bottom layer construction step S20,
When the excavation of the pipeline buried grooves 52 is performed, the extracted soil and defective soil are selected by the earth sorting unit 10 of the earth sorting and laying out apparatus 100, and at the same time, The selected sorting soil is laid along the longitudinal direction of the excavated channel embedding grooves 52 while moving along the longitudinal direction of the buried grooves 52 and at the same time, After surface planarization of the selected soil,
The vibratory roller compaction apparatus 200 is moved along the longitudinal direction of the pipeline embedment grooves 52 so that the surface of the selected soil surface subjected to the planarization in the bottom floor construction step S20 Vibration compaction of the vehicle by the roller compaction and vibration compaction unit 230 and secondary compaction of the secondary roller by the secondary roller compaction unit 220 are sequentially performed along the longitudinal direction of the pipeline embedment groove 52,
In the electric power line embedding step S10,
The plurality of power conduits 51 are installed along the longitudinal direction of the conduit burial grooves 52 and are positioned to move the pre-layout apparatus 100 along the longitudinal direction of the excavated conduit buried grooves 52, A gap holding portion positioning step (S11) of inserting the gap holding grooves (21) of the gap holding portion (20) into each of the plurality of power conduits (51);
After the interval maintaining portion positioning step S11, the soil sorting unit 100 separates the soil extracted at the time of excavation of the pipeline buried grooves 52 through the earth sorting unit 10 into a sorting soil and a defective soil, And the ground separating and installing apparatus 100 is moved along the longitudinal direction of the pipeline embedding grooves 52 while being inserted into the pipeline buried grooves 52 through the raw earth charging unit 30, (50), and the selected soil is moved along the longitudinal direction of the channel-inserted grooves (52) so that the sorted soil selected through the soil-feeding part (30) (S12) for allowing the surface flattening and leveling operation to proceed immediately by the original flat-topped portion (40)
After the back-up process (S12)
The vibrating roller compaction apparatus 200 is moved along the longitudinal direction of the pipeline embedment groove 52 and the cut soil surface subjected to the planarization and sorting operation by the original soil leveling section 40 in the back- The primary roller compaction by the compaction unit 210, the vibration compaction by the vibration compaction unit 230 and the secondary roller compaction by the secondary roller compaction unit 220 are sequentially performed along the longitudinal direction of the channel- As shown in FIG.
The uppermost layer construction step (S30)
When the excavation of the pipeline buried grooves 52 is performed, the extracted soil and defective soil are selected by the earth sorting unit 10 of the earth sorting and laying out apparatus 100, and at the same time, The uppermost layer of the pipeline buried grooves 52 is laid along the longitudinal direction of the pipeline buried grooves 52 excavated with the selected sorting soil while moving along the longitudinal direction of the buried grooves 52, The surface flattening and grading work of the screening soil laid by the original top-and-bottom flat portion 40 is performed,
After the uppermost layer construction step (S30) of the groove embedded in the pipe,
The vibrating roller compaction apparatus 200 is moved along the longitudinal direction of the pipeline embedment groove 52 and the planarization and grading work performed by the flattening and smoothing operation by the original toplevel portion 40 in the uppermost stage floor construction step S30 The surface of which is collapsed by the primary roller compaction unit 210 and the vibration compaction by the vibration compaction unit 230 and by the secondary roller compaction by the secondary roller compaction unit 220, Are sequentially arranged along the longitudinal direction,
Wherein a plurality of power pipelines (51) positioned horizontally in a plurality of excavated pipeline buried grooves (52) are repeatedly buried in the power pipeline burial process (S10) How to build back up.
삭제delete 삭제delete
KR1020160109319A 2016-08-26 2016-08-26 construction method of under-ground Electric power pipe line using natural soil KR101999647B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160109319A KR101999647B1 (en) 2016-08-26 2016-08-26 construction method of under-ground Electric power pipe line using natural soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160109319A KR101999647B1 (en) 2016-08-26 2016-08-26 construction method of under-ground Electric power pipe line using natural soil

Publications (2)

Publication Number Publication Date
KR20180024105A KR20180024105A (en) 2018-03-08
KR101999647B1 true KR101999647B1 (en) 2019-07-15

Family

ID=61726092

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160109319A KR101999647B1 (en) 2016-08-26 2016-08-26 construction method of under-ground Electric power pipe line using natural soil

Country Status (1)

Country Link
KR (1) KR101999647B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20240024655A (en) * 2022-08-17 2024-02-26 박재원 Method for replacing a superannuated pipes

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113718800A (en) * 2021-08-20 2021-11-30 广东省水利水电第三工程局有限公司 Method for backfilling and compacting pressure pipeline within limited time

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101049604B1 (en) * 2010-04-16 2011-07-14 서영곤 Sand filling and stomping equipment for cable construction line
KR101120958B1 (en) * 2011-10-25 2012-03-05 대원전기 주식회사 Self propelled apparatus for installing underground pipe line and method for installing underground pipe line using the same
KR101364519B1 (en) * 2012-06-29 2014-02-20 하나테크 주식회사 Frequently the earth and sand selector

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0540308U (en) * 1991-10-28 1993-06-01 株式会社小松エスト Roller type compactor
KR100748258B1 (en) 2007-04-16 2007-08-09 장영환 In the troy line tube in high tension cable underground power line use a conduit line spatial-temporal method
KR101309774B1 (en) 2013-03-22 2013-09-23 한붕전 A methode for constructing

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101049604B1 (en) * 2010-04-16 2011-07-14 서영곤 Sand filling and stomping equipment for cable construction line
KR101120958B1 (en) * 2011-10-25 2012-03-05 대원전기 주식회사 Self propelled apparatus for installing underground pipe line and method for installing underground pipe line using the same
KR101364519B1 (en) * 2012-06-29 2014-02-20 하나테크 주식회사 Frequently the earth and sand selector

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20240024655A (en) * 2022-08-17 2024-02-26 박재원 Method for replacing a superannuated pipes
KR102652353B1 (en) 2022-08-17 2024-03-27 박재원 Method for replacing a superannuated pipes

Also Published As

Publication number Publication date
KR20180024105A (en) 2018-03-08

Similar Documents

Publication Publication Date Title
RU2405109C1 (en) Method of developing thick ore deposits by underground mining with interchamber pillars support
KR100748258B1 (en) In the troy line tube in high tension cable underground power line use a conduit line spatial-temporal method
KR101999647B1 (en) construction method of under-ground Electric power pipe line using natural soil
JP2023113780A (en) Method and system for constructing underground tunnel
CN116113754A (en) Tunnel shield
CN111364482A (en) Multi-professional pipeline same-groove excavation construction method
JP6944882B2 (en) How to build an invert in an existing tunnel
JP6629825B2 (en) Road lining method in open shield method
CN101092878B (en) Main duct construction method laid down tunnel structure article
JP2011063958A (en) Open shield machine and method for constructing caisson foundation for open shield tunneling method
CN108487666B (en) Controlled demolition method for concrete retaining wall
JP4152935B2 (en) Reconstruction method and equipment for existing pipes
CN116066130A (en) Rectangular jacking pipe construction method for long-distance full-section rock stratum condition
JP3917146B2 (en) Laying method and removing method of lining plate in open shield method
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
JP5155236B2 (en) Installation method of lining board in open shield method
JP6266411B2 (en) Ground excavation method
JP2021181751A (en) Reaction force structure and method for launching concrete box or open shield machine
JP6947477B2 (en) How to advance the open shield machine
JP7248236B2 (en) Tunnel repair method and equipment for existing tunnels
KR20110057350A (en) Manhole repairing apparatus and manhole repairing method using the same
JP2021080798A (en) Pipeline construction method using propulsion method
JPWO2020193960A5 (en)
RU2481473C1 (en) Method for layered development of kimberlitic pipe with backfilling
JP6871344B1 (en) Tunnel repair method and repair equipment for existing tunnels

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E902 Notification of reason for refusal
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant