KR101936762B1 - Steel concrete composite rahmen bridge and construction method thereof - Google Patents

Steel concrete composite rahmen bridge and construction method thereof Download PDF

Info

Publication number
KR101936762B1
KR101936762B1 KR1020180050221A KR20180050221A KR101936762B1 KR 101936762 B1 KR101936762 B1 KR 101936762B1 KR 1020180050221 A KR1020180050221 A KR 1020180050221A KR 20180050221 A KR20180050221 A KR 20180050221A KR 101936762 B1 KR101936762 B1 KR 101936762B1
Authority
KR
South Korea
Prior art keywords
girder member
weight
alternation
parts
bridge
Prior art date
Application number
KR1020180050221A
Other languages
Korean (ko)
Inventor
오종훈
김종열
유경아
Original Assignee
(주)씨앤씨엔지니어링
오종훈
김종열
유경아
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)씨앤씨엔지니어링, 오종훈, 김종열, 유경아 filed Critical (주)씨앤씨엔지니어링
Priority to KR1020180050221A priority Critical patent/KR101936762B1/en
Application granted granted Critical
Publication of KR101936762B1 publication Critical patent/KR101936762B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a steel composite rigid-frame bridge and a construction method thereof, and more specifically, to a rigid-frame bridge, including: a steel rod in which one side is buried in a bridge frame and the other side penetrates the end of a girder member to be installed so as to be tensed upwards; a support block fixed to the girder member, mounted on an upper surface of the bridge frame, and inserting a wedge member into a gap portion with the upper surface of the bridge frame generated by jack-up; and a slab made of placing reinforcing bar concrete to the outside of the support block and the girder member.

Description

단부 잭업(Jack-Up)에 의해 향상된 인장저항성능을 가지는 강합성 라멘교 및 그 시공방법{STEEL CONCRETE COMPOSITE RAHMEN BRIDGE AND CONSTRUCTION METHOD THEREOF}TECHNICAL FIELD [0001] The present invention relates to a steel composite raymen bridge having improved tensile resistance performance by an end jack-up (jack-up)

본 발명은 강합성 라멘교 및 그 시공방법에 관한 것으로서, 보다 상세하게는, 거더부재에 고정되어 교대 벽체부에 받침블럭을 거치하고, 거치된 받침블럭의 외측에 일 측이 교대(또는 교각)에 매립되고 타 측이 거더부재의 단부를 관통하여 상방으로 긴장되도록 설치된 강봉을 구비하고, 설치된 강봉에 의한 거더부재의 받침블럭부의 상향 연직력과 설치된 받침블럭의 내측에 잭업에 의한 상향력 도입으로 받침블럭의 하면과 교대의 상면에 갭을 형성하고, 형성된 갭에 쐐기부재를 게재하여 영구 작용력으로 변환시킨 상향 연직력에 의한 발생모멘트를 통해 거더 중앙부 인장저항성능을 향상시킨 구조를 특징으로 하는 라멘교 및 그 시공방법에 관한 것이다.More particularly, the present invention relates to a steel composite rail bridge and a method of constructing the same. More particularly, the present invention relates to a steel composite rail bridge and a method of constructing the bridge, And an upper side vertical force of the supporting block portion of the girder member by the installed steel bar and an upward force by the jack-up on the inside of the supporting block installed, The gap between the lower surface of the support block and the upper surface of the support block is formed and the wedge member is placed in the formed gap to improve the tensile resistance performance at the center portion of the girder through the generation moment generated by the upward vertical force, And a method of constructing the same.

일반적으로, 라멘교(Rahmen bridge)란 교량의 상부구조와 교량의 하부구조를 일체화시킨 구조를 가지는 교량으로서, 상부구조를 하부구조로 지지하는 대신 상부 및 하부구조를 강결하여 시공되는 교량이다.In general, the Rahmen bridge is a bridge having a structure in which the upper structure of the bridge and the lower structure of the bridge are integrated, and the upper structure and the lower structure are strengthened instead of supporting the upper structure as the lower structure.

도 1 은 일반적인 라멘교를 도시한 것으로서, 지면에 시공되는 기초판(1)과, 기초판(1)에서 상방으로 돌출되어 교량을 지지하는 교대(2)와, 교대(2)의 양단부 상부면에서 교대(2)와 일체로 형성되는 슬래브(3)로 이루어져 있다.Fig. 1 shows a general ramen bridging system. Fig. 1 shows a basic ramen bridge, which comprises a base plate 1 to be installed on the ground, an alternation 2 which projects upward from the foundation plate 1 to support the bridge, And a slab 3 integrally formed with the alternating portion 2 in the second direction.

상기 기초판(1)은 지반을 터파기하고 거푸집을 이용하여 직육면체 형태로 시공되는 철근콘크리트 구조물이고, 상기 교대(2)는 거푸집을 이용하여 기초판(1) 상면에서 상방으로 소정 높이를 가지는 벽체 형상의 철근콘크리트 구조물이다.The base plate 1 is a reinforced concrete structure which is constructed in a rectangular parallelepiped shape by using a mold to form a ground, and the alternation 2 is a wall structure having a predetermined height from the upper surface of the foundation plate 1, Shaped reinforced concrete structure.

상기 슬래브(3)는 상기 양 교대(2) 사이에 동바리를 지반에 설치하고 동바리 위에 거푸집을 설치하여 이루어지는 철근콘크리트 구조물이다.The slab (3) is a reinforced concrete structure made up of two alternating alternations (2) in which a tortoise is installed on a ground and a formwork is installed on a tortoise.

이때, 상기 슬래브(3)의 양 측방 단부 근처에서 하방으로 경사지게 형성되어 상기 교대(2)의 상단 부위에 연결되는 헌치부(4)가 형성되는데, 상기 헌치부(4)는 라멘교의 강결 부위에서 발생되는 휨 모멘트(moment)에 충분히 저항할 수 있도록 시공된다.At this time, a tilting portion 4 formed to be inclined downward from both sides of the slab 3 at both lateral ends and connected to the upper portion of the alternation 2 is formed, So that it can sufficiently resist the bending moment generated.

이러한 라멘교는 비교적 시공 방법이 간단하고, 공사기간이 적게 소요되어 경간장이 짧은 소형 교량에서 이용되고 있다.These ramen bridges are used in small bridges that have a relatively short construction time, a short construction time, and a short span.

그러나, 교량의 경간장이 긴 구간(대략 18m 초과 구간)에 라멘교를 설치하는 경우, 라멘교의 구조적 특성상 라멘교의 강결 부위에서 발생되는 휨 모멘트에 충분히 저항을 할 수 없게 되므로, 이러한 단점을 보완하기 위하여 강합성 라멘교(steel concrete composite rahmen bridge)의 시공방법이 공지되어 있다.However, in case of installing a ramen bridge over a long section of the bridge span (a section exceeding about 18 m), the structural characteristics of the ramen bridge can not sufficiently resist the bending moment generated at the bridge portion of the ramen bridge. A construction method of a steel concrete composite rahmen bridge is known.

즉, 도 2 의 강합성 라멘교의 구성도에 도시된 바와 같이, 양측 기초판(1)에 교대부(2)를 각각 시공하고, 양 교대부(2) 상면에 ㄱ자형의 철골부재(5)를 각각 설치하고, 상기 철골부재(5)들 사이에 거더(girder)부재(6)를 강결부(7) 지점에서 연결고정킨 후, 철골부재(5) 및 거더부재(6)의 외측을 철근콘크리트로 타설하여 교량 상단의 슬래브(3)를 시공하는 라멘교 구조이다. 상기 거더부재(6)는 강철로 이루어진 H 빔 또는 I 빔을 사용한다.That is, as shown in the structural diagram of the composite synthetic ramen bridge of FIG. 2, the alternate portions 2 are respectively installed on the two side foundation plates 1, and the five-folded steel frame members 5 are formed on the upper surfaces of the alternate portions 2, And the girder member 6 is connected and fixed between the steel members 5 at the point of the steel member 7 so that the outer side of the steel member 5 and the girder member 6 is connected to the steel member 5, And a slab (3) at the upper end of the bridge is laid in concrete. The girder member 6 uses an H beam or I beam made of steel.

그러나, 상술한 바와 같이 이루어지는 강합성 라멘교도 교량 구간이 장경간일 경우, 거더부재(6)의 중앙부분으로 갈수록 휨 모멘트에 대한 저항력이 충분하지 않은 단점이 있으며, 따라서, 이러한 단점을 해소하기 위한 보다 향상된 강합성 라멘교의 시공방법 및 이러한 시공방법이 적용된 라멘교 구조를 도입하여야 하는 실정이다.However, when the steel composite ramp bridge section as described above has a long span, there is a disadvantage in that the resistance against the bending moment is not sufficient as it goes to the central portion of the girder member 6. Therefore, It is necessary to introduce a method of construction of a more improved steel composite bridges bridge and a bridges bridge structure to which such a construction method is applied.

한편, 라멘교 시공방법에 관한 선행기술로서, 대한민국특허 제 1178876 호의 라멘교 시공방법의 기술이 소개되어 있으나, 상술한 바와 같은 종래 문제점을 해소할 필요성이 여전히 상존하고 있다. On the other hand, as a prior art relating to a method of constructing a ramen bridge, there has been disclosed a technique of a ramen bridge construction method of Korean Patent No. 1178876, but there is still a need to solve the conventional problems as described above.

본 발명은 상술한 바와 같은 종래의 제반 문제점을 해소하기 위한 것으로서, 교량 구간이 장경간일 경우에도 거더부재의 중앙부분으로 갈수록 휨 모멘트에 대한 저항력을 충분하게 확보할 수 있는 보다 향상된 강합성 라멘교 및 그 시공방법의 구성을 제공한다.It is an object of the present invention to solve the above-mentioned problems of the prior art, and it is an object of the present invention to provide an improved steel composite ramen bridge capable of sufficiently securing a resistance against a bending moment toward a center portion of a girder member even when a bridge section is a long span. And a structure of the construction method.

상술한 바와 같은 기술적 과제를 달성하기 위한 본 발명의 강합성 라멘교 및 그 시공방법은, 거더부재에 고정되어 교대 벽체부에 받침블럭을 거치하고, 거치된 받침블럭의 외측에 일 측이 교대(또는 교각)에 매립되고 타 측이 거더부재의 단부를 관통하여 상방으로 긴장되도록 설치된 강봉을 구비하고, 설치된 강봉에 의한 거더부재의 받침블럭부의 상향 연직력과 설치된 받침블럭의 내측에 잭업에 의한 상향력 도입으로 받침블럭의 하면과 교대의 상면에 갭을 형성하고, 형성된 갭에 쐐기부재를 게재하여 영구 작용력으로 변환시킨 상향 연직력에 의한 발생모멘트를 통해 거더 중앙부 인장저항성능을 향상시킨 구조를 특징으로 한다.According to another aspect of the present invention, there is provided a steel composite rail bridge and a method of constructing the same, comprising the steps of fixing a girder member to a support block and mounting the support block on an alternating wall member, And an upper vertical force of the supporting block portion of the girder member caused by the installed steel bar and an upper side raised by the jack-up on the inner side of the supporting block installed in the girder member. The gap is formed on the upper surface alternately with the lower surface of the support block by the introduction of the force, and the wedge member is placed on the formed gap, and the tensile resistance performance of the girder center portion is improved through the generation moment generated by the upward vertical force .

상술한 바와 같이 구성되는 본 발명의 강합성 라멘교 및 그 시공방법은 거더부재와 교대(또는 교각) 사이에 거더부재와 일체로 고정된 받침블럭을 구비하고, 교대 또는 교각에 설치되는 받침블럭의 외측에 거더부재의 단부를 관통하는 강봉을 설치하고 강봉을 긴장시켜 거더부재의 받침블럭부에 상향 연직력을 부여함으로써 거더부재의 중앙부에 부여되는 휨모멘트에 대한 저항력을 충분하게 확보할 수 있는 효과가 있다.The steel composite rail bridge and the construction method of the present invention constructed as described above have a supporting block integrally fixed to a girder member between alternating (or pierced) bridges and a girder member, It is possible to sufficiently secure the resistance against the bending moment applied to the center portion of the girder member by providing a steel bar that penetrates the end portion of the girder member on the outside and tilting the steel bar to give an upward vertical force to the support block portion of the girder member .

그리고 거더부재와 교대(또는 교각)사이에 거치된 받침블럭의 내측으로 유압잭을 설치하고, 유압잭을 상승(잭업, Jack-up)시켜 받침블럭과 교대(또는 교각) 사이에 발생하는 갭 부분에 쐐기부재를 삽입한 후 유압잭을 제거하고 받침블럭과 거더부재를 철근콘크리트에 매입시켜 형성되는 본 발명의 라멘교는 잭업에 의한 상향 연직력을 쐐기부재에 의한 상향 연직력의 영구 작용효과로 변환하여 보다 향상된 인장저항성능을 가지게 되는 효과를 발현하는 매우 진보한 발명인 것이다.A hydraulic jack is installed inside the bearing block between the girder member and the alternating (or piercing) member. The hydraulic jack is jacked up to form a wedge portion in the gap formed between the bearing block and the alternating The raymen bridge of the present invention formed by removing the hydraulic jack and inserting the support block and the girder member into the reinforced concrete, converts the upright vertical force by the jack-up into the permanent effect of the upright vertical force by the wedge member And is an extremely advanced invention that exhibits the effect of having improved tensile resistance performance.

도 1 은 일반적인 라멘교의 구조를 나타내는 도면,
도 2 는 일반적인 강합성 라멘교의 구조를 나타내는 도면,
도 3 및 도 4 는 본 발명의 강합성 라멘교의 구조를 나타내는 도면으로서, 도 3 은 받침블럭을 설치한 상태의 구성도, 도 4 는 유압잭에 의한 쐐기부재를 삽입하는 상태의 구성도,
도 5 는 본 발명의 쐐기부재의 일례의 사시도,
도 6 은 본 발명의 잭업보강재의 설치 상태를 나타내는 도면이다.
BRIEF DESCRIPTION OF THE DRAWINGS Fig. 1 is a view showing a general structure of a ramen bridge,
2 is a view showing a structure of a general steel composite ramen bridge,
3 and 4 are views showing the structure of a steel composite ramp bridge of the present invention. Fig. 3 is a diagram showing a state in which a bearing block is installed. Fig. 4 is a diagram showing a state in which a wedge member is inserted by a hydraulic jack.
5 is a perspective view of an example of a wedge member of the present invention,
6 is a view showing an installation state of a jack up stiffener according to the present invention.

이하, 첨부 도면에 의거하여 본 발명의 강합성 라멘교 및 그 시공방법의 구성을 상세하게 설명하기로 한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a steel composite rail bridge according to the present invention and a construction method thereof will be described in detail with reference to the accompanying drawings.

단, 개시된 도면들은 당업자에게 본 발명의 사상이 충분하게 전달될 수 있도록 하기 위한 예로서 제공되는 것이다. 따라서, 본 발명은 이하 제시되는 도면들에 한정되지 않고 다른 태양으로 구체화될 수도 있다.It is to be noted, however, that the disclosed drawings are provided as examples for allowing a person skilled in the art to sufficiently convey the spirit of the present invention. Accordingly, the present invention is not limited to the following drawings, but may be embodied in other forms.

또한, 본 발명 명세서에서 사용되는 용어에 있어서 다른 정의가 없다면, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 통상적으로 이해하고 있는 의미를 가지며, 하기의 설명 및 첨부 도면에서 본 발명의 요지를 불필요하게 흐릴 수 있는 공지 기능 및 구성에 대한 상세한 설명은 생략한다.In addition, unless otherwise defined, the terms used in the description of the present invention have the same meaning as commonly understood by one of ordinary skill in the art to which the present invention belongs. In the following description and the accompanying drawings, A detailed description of known functions and configurations that may be unnecessarily blurred is omitted.

도 3 및 도 4 는 본 발명의 강합성 라멘교의 구조를 나타내는 도면으로서, 도 3 은 받침블럭을 설치한 상태의 구성도, 도 4 는 유압잭에 의한 쐐기부재를 삽입하는 상태의 구성도이며, 전술한 도 1 및 도 2 에 도시된 부분과 동일한 부분은 동일한 참조부호를 사용하여 설명한다.3 and 4 are views showing the structure of the steel composite rammen bridge of the present invention. Fig. 3 is a diagram showing a state in which a bearing block is installed. Fig. 4 is a diagram showing a state in which a wedge member is inserted by a hydraulic jack. The same parts as those shown in Figs. 1 and 2 are denoted by the same reference numerals.

본 발명의 강합성 라멘교 및 그 시공방법은, 거더부재(6)와 교대(2)(또는 교각) 사이에 거더부재(6)와 일체로 고정된 받침블럭(20)을 구비하고, 교대(2) 또는 교각(미도시)에 거치된 받침블럭(20)의 내측에 거더부재(6)의 단부를 관통하는 강봉(10)을 설치하고, 설치된 강봉(10)을 상방으로 긴장시켜 거더부재(6)의 받침블럭부(거더부재 중 받침블럭(20)이 받치고 있는 부분)에 상향 연직력을 부여함으로써, 거더부재(6)의 중앙부에 가해지는 휨모멘트에 대하여 충분한 저항력을 확보할 수 있도록 한 구성이다.The steel composite ramen bridge of the present invention and its construction method are provided with a support block 20 integrally fixed to the girder member 6 between the girder member 6 and the alternation 2 A steel bar 10 passing through an end portion of the girder member 6 is provided on the inner side of the support block 20 which is fixed to the girder member 2 or the bridge block (not shown), and the girder member 10 6) of the girder member 6 (a portion of the girder member supported by the support block 20) is provided with an upward vertical force to secure sufficient resistance against the bending moment applied to the center portion of the girder member 6 .

또한, 본 발명의 라멘교 및 그 시공방법은, 거더부재(6)와 교대(2) 또는 교각 사이에 거더부재(6)에 거치된 받침블럭(20)의 내측으로 유압잭(30)을 설치하고, 거더부재(6) 및 받침블럭(20)에 철근콘크리트를 타설하기 전에 유압잭(30)을 상승(잭업)시켜 받침블럭(20)과 교대(2)(또는 교각) 사이에 발생하는 갭(g) 부분에 쐐기부재(40)를 삽입한 후 유압잭(30)을 제거하고 받침블럭(20)과 거더부재(6)를 철근콘크리트에 매입시킨 라멘교로서, 받침블럭(20)과 교대(2) 사이의 갭(g) 부분에 삽입되어 게재되는 쐐기부재(40)에 의하여 잭업에 의한 상향 연직력을 영구적으로 작용시켜 거더부재(6)의 인장저항성능이 보강됨으로써 종래 라멘교와 대비하여 보다 향상된 인장저항성능을 가지게 되는 구성이다.The ramen bridge and its construction method according to the present invention are characterized in that the hydraulic jack 30 is installed inside the support block 20 which is fixed to the girder member 6 between the girder member 6 and the alternation 2 (Jacked up) the hydraulic jack 30 before placing the reinforcing concrete on the girder member 6 and the support block 20 to form a gap g (g) between the support block 20 and the alternating 2 (2) as a ramen bridge in which the hydraulic jacks 30 are removed and the support block 20 and the girder member 6 are embedded in the reinforced concrete after inserting the wedge members 40 into the reinforcing concrete blocks, The upright vertical force by the jack-up is permanently applied by the wedge member 40 inserted in the gap g between the upper and lower portions of the girder member 6 to reinforce the tensile resistance performance of the girder member 6, And has a tensile resistance performance.

이하에서, 이러한 본 발명의 라멘교 및 그 시공방법을 보다 구체적으로 설명한다.Hereinafter, such a ramen bridge and its construction method of the present invention will be described in more detail.

먼저, 도 3 은 본 발명의 라멘교에 있어서 받침블럭을 설치한 상태의 구성도로서, 기본적으로, 본 발명의 라멘교는 도 1 에 도시된 바와 같이 지면에 시공되는 기초판(1) 상에서 상방으로 돌출되어 교량을 지지하는 양측의 교대(2)와, 각 교대(2)의 단부 상부면에서 교대(2)와 일체로 형성되는 슬래브(3)를 포함한다.First, FIG. 3 is a view showing a state in which a bearing block is installed in a ramen bridges of the present invention. Basically, the bridges of the present invention are basically the same as those shown in FIG. 1, And a slab 3 integrally formed with the alternation 2 at the upper end surface of each alternation 2.

이때, 본 발명의 라멘교는 내부에 철근(2a)을 매립시킨 철근콘크리트 구조로 이루어진 양측 교대(2)의 상면(2b) 상에 받침블럭(20)에 의하여 거치되는 거더부재(6)를 포함한다.The ramen bridge of the present invention includes a girder member 6 which is fixed by a support block 20 on an upper surface 2b of a bilateral alternation 2 having a reinforced concrete structure in which reinforcing bars 2a are embedded. do.

여기서, 본 발명의 라멘교의 구성요소들은 교대(2) 뿐만 아니라 교각(미도시)에도 동일한 형태로 적용될 수 있으나, 설명의 편의상 이하에는 교대(2)에 적용되는 것으로 설명하기로 하며, 본 발명의 라멘교 및 그 시공방법의 구성은 교대(2) 뿐만 아니라 교각에도 동일하게 구성될 수 있음을 유의하여야 한다. Here, the components of the ramen bridge of the present invention may be applied to the bridge (not shown) as well as the bridge (not shown). However, for convenience of explanation, the following description is applied to the alternation (2) It should be noted that the construction of the ramen bridge and its construction method can be configured in the same way as the bridge (2) as well as the bridge.

본 발명의 라멘교는 상기 받침블럭(20)으로 거더부재(6)가 교대(2)의 상면(2b)상에 거치된 상태에서 거더부재(6)의 양측 단부를 각각 관통하여 결합되는 강봉(10)을 포함한다.The ramen bridge of the present invention is characterized in that the girder member 6 is fixed to the upper surface 2b of the alternating frame 2 by the support block 20, 10).

상기 강봉(10)은 강철 소재의 봉형상 부재로서, 상부 말단은 거더부재(6)의 단부를 관통하여 상단 체결너트(12)에 의하여 거더부재(6)에 결합되고, 하부 말단은 교대(2)의 내부에 매립된 상부체결판(14)을 관통하여 하방으로 진입하여 하부체결판(13)을 관통하여 하부체결판(13)의 바닥면에 연결되는 하단 체결너트(11)에 의하여 교대(2) 내부에 콘크리트 타설 매립 고정된다.The upper end of the steel rod 10 is connected to the girder member 6 by an upper end coupling nut 12 through the end of the girder member 6 and the lower end of the rod member 10 And the lower end of the lower fastening plate 13 is connected to the bottom of the lower fastening plate 13 through the upper fastening plate 14 embedded in the lower fastening plate 13, 2) The concrete is embedded and fixed in the inside.

상기 하부체결판(13)과 상부체결판(14)은 지지대(15)에 의하여 지지된 상태로 매립되므로 강봉(10)의 매립 상태를 공고하게 유지할 수 있게 된다.Since the lower fastening plate 13 and the upper fastening plate 14 are buried in a state of being supported by the support rods 15, the state of filling of the steel rods 10 can be maintained.

그리고 이렇게 거더(6)의 양측 단부에 결합된 강봉(10)을 상방으로 긴장시키게 되면, 받침블럭부에 상향 연직력이 부여되면서 거더부재(6)의 중앙부에 가해지는 휨모멘트에 대하여 충분한 저항력을 가질 수 있게 된다.When the steel bar 10 coupled to both ends of the girder 6 is tilted upwardly, an upright vertical force is applied to the supporting block so that sufficient resistance against the bending moment applied to the center of the girder member 6 .

상기 받침블럭(20)은 도 2 를 참조하여 설명한 종래의 강합성 라멘교 구조의 철골부재(5)에 상응하는 구성요소으로서, 몸체(21) 상하부로 양측 교대(2)의 상면(2b)에 접촉되는 하판(22)과 거더부재(6)의 하면에 접촉되는 상판(23)으로 이루어져 있으며, 상판(23)이 거더부재(6)의 하면에 부착되어 결합된 상태이며, 하판(22)은 교대(2)와 결합되지 않은 블럭으로서, 받침블럭(20)과 거더부재(6)는 상호 결합되어 일체화된 구조이다. 본 발명 실시예는 상기 받침블럭(20)으로서 강철 재질의 H 빔을 이용한다.The supporting block 20 is a component corresponding to the steel member 5 of the conventional steel composite framing structure described with reference to Fig. 2 and is formed on the upper surface 2b of the alternation 2 on the upper and lower sides of the body 21 The upper plate 23 is attached to the lower surface of the girder member 6 and is engaged with the lower plate 22. The lower plate 22 is in contact with the upper surface of the girder member 6, As a block which is not coupled with the shift 2, the support block 20 and the girder member 6 are integrally combined with each other. The embodiment of the present invention uses an H beam of a steel material as the support block 20.

또한, 본 발명의 라멘교는, 거더부재(6)의 인장저항성능을 보강하기 위하여, 잭업에 의하여 발생된 연직 상향력에 의해 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이에 발생된 갭(b)을 영구적으로 유지시키기 위하여 상기 갭(b)에 내삽되는 쐐기부재(40)의 구성을 가지고 있다.The racetrack bridge of the present invention is characterized in that in order to reinforce the tensile resistance performance of the girder member 6, a vertical upward force generated by the jack-up causes the lower plate 22 of the support block 20, (B) so as to permanently hold the gap (b) generated between the wedge member (2b).

즉, 쐐기부재(40)가 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이로 게재되면서 갭(g)을 유지한 상태로 받침블럭(20) 및 거더부재(6)가 철근콘크리트에 매립됨으로써 거더부재(6)의 인장저항성능을 보강시킨 구조를 가지고 있다. That is, the wedge member 40 is placed between the lower plate 22 of the support block 20 and the upper surface 2b of the alternate 2, and the support block 20 and the girder member 6 ) Is embedded in the reinforced concrete to reinforce the tensile resistance of the girder member (6).

구체적으로는, 도 4 에 도시된 바와 같이, 쐐기부재(40)를 받침블럭(20)의 하판(22)의 하측으로 삽입시키기 위하여, 받침블럭(20)을 결합시킨 상태의 거더부재(6)를 상방으로 거상시켜야 하므로, 거더부재(6)의 하면과 교대(2)의 상면(2b) 사이에 유압잭(30)을 이용하여 거더부재(6)을 상방으로 거상시킨 다음, 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이로 쐐기부재(40)를 게재시킨다.4, in order to insert the wedge member 40 to the lower side of the lower plate 22 of the receiving block 20, the girder member 6 in a state in which the receiving block 20 is engaged, The girder member 6 is lifted upwards by the use of the hydraulic jack 30 between the lower surface of the girder member 6 and the upper surface 2b of the alternation 2 and then the support block 20 is raised, The wedge member 40 is placed between the lower plate 22 of the first alternating portion 2 and the upper surface 2b of the alternate portion 2.

이를 위하여, 받침블럭(20)의 내측(즉, 강봉(10)설치지점과 반대 방향인 거더부재(6)의 중앙부분 방향) 지점의 교대(2)의 상면(2b) 상에 유압에 의하여 상방으로 상승되는 자키(32)를 가지는 유압잭(30)을 임시로 가설치한다.For this purpose, on the upper surface 2b of the alternation 2 at the point of the inner side of the support block 20 (that is, in the direction of the central portion of the girder member 6 opposite to the installation point of the steel rods 10) The hydraulic jack 30 having the jockeys 32 raised to a predetermined position is temporarily installed.

그리고, 유압잭(30)의 베이스(31)를 교대(2)의 상면(2b)에 임시로 가설치한 상태에서, 유압잭(30)을 작동시키면 유압잭(30)의 상부에 설치된 자키(32)가 상방향으로 상승하면서 거더부재(6)의 하면에 접촉되고, 이후 유압잭(30)의 계속적인 작동이 이루어지면 자키(32)가 거더부재(6)를 상방으로 들어올리게 된다.When the hydraulic jack 30 is operated while the base 31 of the hydraulic jack 30 is temporarily installed on the upper surface 2b of the shift 2, And then the jaws 32 lift the girder member 6 upward when the hydraulic jack 30 is continuously operated.

이러한 상태에서, 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이로 형성된 갭(g)에 쐐기부재(40)를 내삽시킨다.In this state, the wedge member 40 is inserted into the gap g formed between the lower plate 22 of the support block 20 and the upper surface 2b of the alternating 2.

상기 쇄기부재(40)는 도 5 의 상부 (a)에 도시된 바와 같이, 일측이 쐐기 형상의 첨단부(41)가 형성되며, 하부 (b)에 도시된 바와 같이, A-A' 선 단면이 삼각형을 이루는 부재로서, 첨단부(41)가 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이로 형성된 갭(g)에 내삽됨으로써 거더부재(6)의 인장저항성능을 보강시키는 기능을 수행하게 된다.As shown in the upper part (a) of FIG. 5, the wedge member 40 is formed with a wedge-shaped tip portion 41 on one side, and the AA ' The leading end portion 41 is inserted into the gap g formed between the lower plate 22 of the receiving block 20 and the upper surface 2b of the alternating portion 2 to thereby improve the tensile resistance performance of the girder member 6 Thereby performing the function of reinforcing.

이어서, 상기와 같이 받침블럭(20)의 하판(22)과 교대(2)의 상면(2b) 사이로 형성된 갭(g)에 쐐기부재(40)가 게재되면, 유압잭(30)의 작동을 중지시키고 자키(32)를 하강시켜 유압잭(30)을 교대(2)의 상면(2b) 상에서 제거한다.Then, when the wedge member 40 is placed in the gap g formed between the lower plate 22 of the support block 20 and the upper surface 2b of the shift 2, the operation of the hydraulic jack 30 is stopped The jaws 32 are lowered to remove the hydraulic jack 30 on the upper surface 2b of the shift 2.

이후, 유압잭(30)이 제거되고 쐐기부재(40)가 갭(g)에 내삽된 상태에서 받침블럭(20)의 외부에 거푸집을 이용하여 철근콘크리트를 타설하여 받침블럭(20)을 철근콘크리트를 매립하고, 이어서, 거더부재(6)의 상측으로 거푸집을 이용하여 철근콘크리트를 타설하여 양측 교대(2)사이로 슬래브(3) 구조물을 형성함으로써 본 발명의 라멘교의 시공을 완료하게 된다.Thereafter, when the hydraulic jack 30 is removed and the wedge member 40 is inserted in the gap g, the reinforcing concrete is laid outside the supporting block 20 by using a form so that the supporting block 20 is inserted into the reinforcing concrete And then the reinforced concrete is laid on the upper side of the girder member 6 to form a slab 3 structure between the two alternate turns 2 to complete the construction of the ramen bridge of the present invention.

한편, 도 6은 본 발명의 잭업보강재의 설치 상태를 나타내는 도면으로서, 본 발명의 라멘교 시공시 유압잭(30)을 가설치하는 과정에서 유압잭(30)의 상방 압력에 대한 거더부재(6)의 내구력을 보강하기 위하여, 거더부재(6)의 하부 날개면(6a)과 상부날개면(6b) 사이에 평판 형상의 잭업보강재(50)를 설치한다.6 is a view showing the installation state of the jack-up reinforcement according to the present invention. In the process of installing the hydraulic jack 30 during the ramming work according to the present invention, Up jacket stiffener 50 is provided between the lower blade surface 6a and the upper blade surface 6b of the girder member 6 to reinforce the durability.

상기 잭업보강재(50)는 하면(51)과 상면(52)이 각각 거더부재(6)의 하부날개면(6a)과 상부날개면(6b) 사이에 밀접하게 접촉되도록 설치됨으로써, 유압잭(30)의 상방 압력에 대하여 내구력을 부여함으로써 거더부재(6)가 안정적으로 상방으로 거상될 수 있도록 도와주는 기능을 수행한다.The lower surface 51 and the upper surface 52 of the jack-up stiffener 50 are provided so as to be in close contact with each other between the lower blade surface 6a and the upper blade surface 6b of the girder member 6, So that the girder member 6 can be stably lifted upwards.

또한, 상술한 바와 같이 구성되는 본 발명의 라멘교의 시공방법은, 상기 교대(2)에, 상기 거더부재(6)와 교대(2) 사이에 거더부재(6)에 고정된 받침블럭(20)을 거치시키는 단계, 그리고 일 측이 상기 교대(2)에 매립되고 타 측이 상기 거더부재(6)의 단부를 관통하도록 강봉(10)을 설치하고, 설치된 상기 강봉(10)을 상방으로 긴장시켜 거더부재(6)의 받침블럭부에 상향 연직력을 부여하는 단계, 그리고 상기 받침블럭(20)의 내측 지점의 교대(2)의 상면(2b) 상에 유압에 의하여 상방으로 상승되는 자키(32)를 가지는 유압잭(30)을 임시로 가설치하는 단계; 상기 유압잭(30)을 상승시켜 받침블럭(20)과 교대(2) 사이의 갭(g)에 쐐기부재(40)를 삽입하는 단계, 그리고 상기 유압잭(30)을 제거하고 받침블럭(20)과 거더부재(6)의 외측에 철근콘크리트를 타설하여 양측 교대(2)사이로 슬래브(3)를 형성하는 단계를 포함하여 구성된다.The method of constructing a ramen bridge according to the present invention as described above is characterized in that the support block 20 fixed to the girder member 6 between the girder member 6 and the alternation 2 is provided in the alternation 2, The steel bar 10 is installed so that one side is embedded in the alternation 2 and the other side passes through the end of the girder member 6 and the steel bar 10 installed is tensed upward A step of applying an upright vertical force to the supporting block portion of the girder member 6 and a step of raising the upper surface 2b of the alternation 2 of the inner point of the supporting block 20 by hydraulic pressure Temporarily installing the hydraulic jack (30) having the hydraulic jack (30); A step of raising the hydraulic jack 30 to insert the wedge member 40 into the gap g between the support block 20 and the shift 2 and the step of removing the hydraulic jack 30, And placing the reinforcing concrete on the outside of the girder member (6) to form the slab (3) between the two alternate turns (2).

그러므로 상술한 바와 같이 구성되는 본 발명의 강합성 라멘교 및 그 시공방법은 거더부재(6)와 교대 또는 교각 사이에 거더부재(6)와 일체로 결합된 받침블럭(20)을 구비하고, 교대 또는 교각에 거치된 받침블럭(20)의 외측에 거더부재(6)의 단부를 관통하는 강봉(10)을 설치하고, 설치된 강봉(10)을 긴장시켜 설치된 받침블럭부에 상향 연직력을 부여함으로써 거더부재(6)의 중앙부에 부여되는 휨모멘트에 대한 저항력을 충분하게 확보할 수 있게 된다.Therefore, the steel composite rail bridge and the construction method of the present invention constructed as described above have the support block 20 integrally coupled with the girder member 6 between the girder member 6 and the alternating or piercing angle, A steel bar 10 passing through the end of the girder member 6 is provided on the outside of the support block 20 mounted on the bridge pier and an upright vertical force is given to the support block portion provided by tightening the installed steel bar 10 The resistance against the bending moment applied to the center portion of the girder member 6 can be sufficiently secured.

또한, 받침블럭(20)의 내측으로 유압잭(30)을 설치하고, 유압잭(30)을 상승시켜 받침블럭(20)과 교대 또는 교각 사이의 갭 부분에 쐐기부재(40)를 삽입한 후 유압잭(30)을 제거하고 받침블럭(20)과 거더부재(6)를 철근콘크리트를 타설하여 매립시키는 구조로서, 받침블럭(20)에 게재된 쐐기부재(40)에 의하여 인장저항성능이 보강됨으로써 종래기술 대비 보다 향상된 인장저항성능을 가지게 되는 효과를 수득하게 되었다.The hydraulic jack 30 is installed inside the support block 20 and the hydraulic jack 30 is raised to insert the wedge member 40 into the gap portion between the support block 20 and the bridge pier 20, And the reinforcing concrete is laid on the supporting block 20 and the girder member 6 so that the tensile resistance is reinforced by the wedge member 40 placed on the supporting block 20. Thus, An effect that the tensile resistance performance is improved as compared with the contrast is obtained.

한편, 본 발명에서, 받침블럭(20)은 시공 기간 동안 콘크리트 타설 전까지 외부에 노출되어야 한다는 점 때문에 부식 등의 우려가 있다. 이를 해결하기 위한 방안으로. 본 발명은 받침블럭(20)의 외면에 코팅제의 도포 및 경화에 의해 형성되는 코팅층을 더 포함할 수 있음을 특징으로 한다.Meanwhile, in the present invention, since the support block 20 must be exposed to the outside until the concrete is poured during the construction period, corrosion of the support block 20 may occur. To solve this problem. The present invention is further characterized in that it may further comprise a coating layer formed on the outer surface of the support block (20) by applying and curing a coating agent.

이러한 코팅층은 충격에 의한 파손, 첨예체에 의한 자상 등을 방지함은 물론 향상된 난연성, 신속한 경화로 인한 향상된 제조성, 발수 처리를 통한 향상된 방수성을 제공한다.Such a coating layer prevents damage due to impact, splashes caused by the pointed body, etc., as well as improved flame retardancy, improved composition due to rapid curing, and improved water resistance through water repellent treatment.

상기 효과를 제공하는 본 발명의 코팅제 조성물은, 바인더 수지 100 중량부, 이소시아네이트 프리폴리머(Isocyanate prepolymer) 1 내지 10 중량부, 폴리에스테르 아크릴레이트(Polyester acrylate) 1 내지 30 중량부, 메틸 아세테이트(Methyl acetate) 30 내지 60 중량부, 아조비스 이소부틸니트릴(Azobis isobutyronitrile) 0.5 내지 5 중량부, 수산화 알루미늄(Aluminum hydroxide) 5 내지 15 중량부, 디메틸아닐린(Dimethylaniline) 1 내지 5 중량부 및, 테트라에톡시실란(Tetraethoxysilane) 0.5 내지 2.5 중량부를 포함한다.The coating composition of the present invention which provides the above-mentioned effect comprises 100 parts by weight of a binder resin, 1 to 10 parts by weight of an isocyanate prepolymer, 1 to 30 parts by weight of a polyester acrylate, 30 to 60 parts by weight of azobisisobutyronitrile, 0.5 to 5 parts by weight of azobis isobutyronitrile, 5 to 15 parts by weight of aluminum hydroxide, 1 to 5 parts by weight of dimethylaniline, 0.5 to 2.5 parts by weight of tetraethoxysilane.

각 구성 별로, 먼저 바인더 수지는 UV 경화형으로 이루어지는 것이 바람직하며, 그 종류가 특별히 한정되지 않는다.For each constitution, it is preferable that the binder resin is first made of UV curing type, and the kind thereof is not particularly limited.

다음으로, 이소시아네이트 프리폴리머(Isocyanate prepolymer)는 2개의 이소시아네이트기를 가지는 화합물을 이소시아누레이트 변성, 트리메티롤프로판(TMP) 변성, 비우렛(biuret) 변성 등의 방법으로 변성하여 얻을 수 있으며, 바인더 수지 100 중량부에 대해 1 내지 10 중량부가 사용되는 것이 바람직한데, 1 중량부 미만으로 사용되는 경우 가교성이 저하되며, 10 중량부를 초과하여 사용되는 경우 가교성이 과도하게 증가하여 코팅층의 표면이 거칠어지고, 크랙에 의한 파손 가능성이 높아지는 문제가 있다.Next, the isocyanate prepolymer can be obtained by modifying a compound having two isocyanate groups by a method such as isocyanurate denaturation, trimethylol propane (TMP) denaturation, biuret denaturation, etc., and the binder resin If it is used in an amount of less than 1 part by weight, the crosslinking property decreases. When the amount of the crosslinking agent is more than 10 parts by weight, the crosslinking property is excessively increased, There is a problem that the possibility of breakage due to cracking increases.

다음으로, 폴리에스테르 아크릴레이트(Polyester acrylate)는 상기한 이소시아네이트 프리폴리머와 함께 가교제로 사용되며, 바인더 수지 100 중량부에 대해 1 내지 30 중량부가 사용되는 것이 바람직한데, 1 중량부 미만으로 사용되는 경우 코팅층의 표면이 깨끗하게 형성되지 않으며, 30 중량부를 초과하여 사용되는 경우 역시 가교성이 과도하게 증가하여 코팅층의 표면이 거칠어지게 된다.Next, polyester acrylate is used as a crosslinking agent together with the above-mentioned isocyanate prepolymer. It is preferable that 1 to 30 parts by weight of the polyester acrylate is used relative to 100 parts by weight of the binder resin. When the amount is less than 1 part by weight, The surface of the coating layer is not cleanly formed, and when it is used in an amount exceeding 30 parts by weight, the crosslinking property is excessively increased and the surface of the coating layer becomes rough.

다음으로, 메틸 아세테이트(Methyl acetate)는 코팅제의 안정적인 상용성을 확보하고 용액 중합을 제공하는 유기용제로서 첨가되며, 바인더 수지 100 중량부에 대해 30 내지 60 중량부가 사용되는 것이 바람직한데, 30 중량부 미만으로 사용되는 경우 코팅제의 점도가 과도하게 높아지게 되어 흐름성이 나빠지고, 60 중량부를 초과하여 사용되는 경우 환경성이 저하되거나 심한 경우 환경 규제에 저촉되는 문제가 있다.Next, methyl acetate is added as an organic solvent which ensures stable compatibility of the coating agent and provides solution polymerization. It is preferable that 30 to 60 parts by weight of the methyl acetate is used relative to 100 parts by weight of the binder resin, and 30 parts by weight , The viscosity of the coating agent becomes excessively high to deteriorate the flowability. When the coating agent is used in an amount exceeding 60 parts by weight, there is a problem that the environmental property is deteriorated or the environment regulation is seriously deteriorated.

다음으로, 아조비스 이소부틸니트릴(Azobis isobutyronitrile)은 라디칼을 생성하는 개시제로서 사용되며, 바인더 수지 100 중량부에 대해 0.5 내지 5 중량부가 사용되는 것이 바람직한데, 0.5 중량부 미만으로 사용되는 경우 충분한 라디칼 이온을 발생시킬 수 없고, 5 중량부를 초과하여 사용되는 경우 과 생성된 라디칼 이온이 전체 중합도를 낮춰 물성이 저하되는 문제가 발생한다.Next, azobis isobutyronitrile is used as an initiator for radical generation. It is preferable that 0.5 to 5 parts by weight of the azobis isobutyronitrile is used relative to 100 parts by weight of the binder resin. When the amount is less than 0.5 parts by weight, sufficient radicals Ions can not be generated. When the amount is more than 5 parts by weight, there is a problem that the resulting radical ion lowers the total degree of polymerization and deteriorates the physical properties.

다음으로, 수산화 알루미늄(Aluminum hydroxide)은 코팅층이 연소되는 과정에서 특정 연소단계를 방해하기 위해 첨가되고, 바인더 수지 100 중량부에 대해 5 내지 15 중량부가 사용되는 것이 바람직한데, 5 중량부 미만으로 사용되는 경우 난연 효과가 미미하고, 15 중량부를 초과하여 사용되는 경우 난연 효과에 비해 경제성이 저하된다.Next, aluminum hydroxide is added in order to prevent a specific combustion step in the process of burning the coating layer, and it is preferable that 5 to 15 parts by weight is used for 100 parts by weight of the binder resin. , The flame retardant effect is insignificant, and when used in excess of 15 parts by weight, the economical efficiency is lowered compared with the flame retardant effect.

다음으로, 디메틸아닐린(Dimethylaniline)은 상기한 아조비스 이소부틸니트릴의 라디칼 생성을 돕기 위해 첨가되며, 바인더 수지 100 중량부에 1 내지 5 중량부가 사용되는 것이 바람직한데, 1 중량부 미만으로 사용되는 경우 완전 경화가 되지 않고, 5 중량부를 초과하여 사용되는 경우 코팅층의 표면에 흑점이나 부식이 발생할 수 있다.Next, dimethylaniline is added to assist radical generation of the azobisisobutylnitrile. It is preferable that 1 to 5 parts by weight of the dimethylaniline is used in 100 parts by weight of the binder resin. If less than 1 part by weight of the dimethylaniline is used If it is used in excess of 5 parts by weight, black spots or corrosion may occur on the surface of the coating layer.

다음으로, 테트라에톡시실란(Tetraethoxysilane)은 가수분해 축합되어 코팅층의 방수성 및 발수성을 부여하고 방부성을 향상시키기 위해 첨가되며, 바인더 수지 100 중량부에 대해 0.5 내지 2.5 중량부가 사용되는 것이 바람직한데, 0.5 중량부 미만으로 사용되는 경우 방수성, 발수성 및 방부성 향상 효과가 미미하며, 2.5 중량부를 초과하여 사용되는 경우 시공성이 저하되는 문제가 있다.Next, tetraethoxysilane is added to enhance the water repellency and water repellency of the coating layer by hydrolysis and condensation, and to improve the anticorrosive property. It is preferable that 0.5 to 2.5 parts by weight of the tetraethoxysilane is used in the range of 0.5 to 2.5 parts by weight based on 100 parts by weight of the binder resin. When used in an amount of less than 1 part by weight, the effect of improving waterproofness, water repellency and anticorrosion is insignificant, and when used in an amount exceeding 2.5 parts by weight, workability is lowered.

이하에서는 상기한 코팅제 조성물을 이용한 코팅층의 실시예를 소개하기로 한다.Hereinafter, embodiments of the coating layer using the coating composition will be described.

[실시예][Example]

바인더 수지로, 에폭시 아크릴레이트 올리고머 1kg에, 이소시아네이트 프리폴리머 50g, 폴리에스테르 아크릴레이트 200g, 메틸 아세테이트 500g, 아조비스 이소부틸니트릴 30g, 수산화 알루미늄 100g, 디메틸아닐린 30g, 테트라에톡시실란(Tetraethoxysilane) 20g을 혼합하여 1시간 정도 교반하여 코팅제 조성물을 제조하였다.As binder resin, 50 g of isocyanate prepolymer, 200 g of polyester acrylate, 500 g of methyl acetate, 30 g of azobisisobutylnitrile, 100 g of aluminum hydroxide, 30 g of dimethylaniline and 20 g of tetraethoxysilane were mixed with 1 kg of epoxy acrylate oligomer And the mixture was stirred for about 1 hour to prepare a coating composition.

제조된 코팅제 조성물을 시험용 블록(시멘트로 제조)에 도포한 후, 완전 경화하는 단계를 거쳐 시험용 블록에 코팅층을 형성하였다.The coating composition thus prepared was applied to a test block (made of cement) and completely cured to form a coating layer on the test block.

[실시예1][Example 1]

이 후 코팅층을 불규칙한 돌출부위를 갖는 스크래처를 통해 긁는 실험과 스크래처를 코팅층에 10회 반복하여 내려치는 실험을 수행한 결과, 스크래치 및 코팅층의 함몰이 발생하지 않았다.Thereafter, the coating layer was scratched through a scratcher having irregular protruding portions and the scratches were repeatedly applied to the coating layer ten times. As a result, scratches and depression of the coating layer did not occur.

[실시예2][Example 2]

또한 코팅층에 토치를 통해 10분간 화염을 직접 분사하는 실험을 수행한 결과, 약간의 그을음은 발생하였으나 코팅층이 전혀 연소되지 않았다.Also, as a result of direct spraying of the flame on the coating layer through the torch for 10 minutes, a little soot was generated but the coating layer was not burned at all.

[실시예3][Example 3]

또한 코팅층에 6시간 동안 물을 분사한 후, 코팅층을 제거하고 시험용 블록의 내부 침습도를 검사한 결과 습기가 전혀 검출되지 않았다.In addition, water was sprayed on the coating layer for 6 hours, the coating layer was removed, and the degree of internal infiltration of the test block was examined. As a result, no moisture was detected.

상기 실시예들을 통해 본 발명에 따른 코팅층은 보호성, 난연성 및 방수성이 탁월하다는 것을 확인할 수 있다.It can be seen from the above examples that the coating layer according to the present invention is excellent in protection property, flame retardancy and waterproofness.

* 도면의 주요 부분에 대한 부호의 설명 *
1; 기초판
2; 교대
2a; 교대 매립 철근 2b; 교대 상면
3; 슬래브
4; 헌치부
5; 철골부재
6; 거더부재
6a; 하부날개면 6b; 상부날개면
7; 강결부
10; 강봉
11; 하단 체결너트 12; 상단 체결너트
13; 하부 체결판 14; 상부 체결판
15; 지지대
20; 받침블럭
21; 몸체 22; 받침블럭 하판
23; 받침블럭 상판
30; 유압잭
31; 유압잭 베이스 32; 유압잭 자키
40; 쐐기부재 41; 첨단부
50; 잭업 보강재
51; 상면 52; 바닥면
Description of the Related Art [0002]
One; Base plate
2; rotation
2a; Alternating buried reinforcing bars 2b; Alternating top surface
3; Slab
4; An old part
5; Steel member
6; Girder member
6a; Lower wing surface 6b; Upper wing face
7; Steel joint
10; Bar
11; Bottom fastening nut 12; Top fastening nut
13; Lower fastening plate 14; The upper fastening plate
15; support fixture
20; Bearing block
21; A body 22; Bottom block bottom plate
23; Base block top plate
30; Hydraulic jack
31; A hydraulic jack base 32; Hydraulic jacks
40; A wedge member 41; Leading edge
50; Jack up stiffener
51; Top surface 52; Bottom surface

Claims (4)

교대(2)에 거더부재(6)를 설치하여 이루어지는 강합성 라멘교에 있어서,
일측이 상기 교대(2)에 매립되고, 타측이 상기 거더부재(6)의 단부를 관통하여 상방으로 긴장되도록 설치된 강봉(10);
상기 거더부재(6)에 고정되어 교대(2)의 상면(2b)에 거치되어 잭업에 의해 발생되는 상기 교대(2)의 상면(2b)과의 갭(g) 부분에 쐐기부재(40)를 게재시키는 받침블럭(20);
상기 받침블럭(20)과 거더부재(6)의 외측으로 철근콘크리트를 타설하여 이루어지는 슬래브(3);
를 포함하고,
상기 받침블럭(20)의 외면에 코팅제의 도포 및 경화에 의해 형성되는 코팅층을 더 포함하고,
상기 코팅제는, 바인더 수지 100 중량부, 이소시아네이트 프리폴리머(Isocyanate prepolymer) 1 내지 10 중량부, 폴리에스테르 아크릴레이트(Polyester acrylate) 1 내지 30 중량부, 메틸 아세테이트(Methyl acetate) 30 내지 60 중량부, 아조비스 이소부틸니트릴(Azobis isobutyronitrile) 0.5 내지 5 중량부, 수산화 알루미늄(Aluminum hydroxide) 5 내지 15 중량부, 디메틸아닐린(Dimethylaniline) 1 내지 5 중량부 및, 테트라에톡시실란(Tetraethoxysilane) 0.5 내지 2.5 중량부를 포함하는 것을 특징으로 하는 라멘교.
In a composite steel framing system in which a girder member (6) is provided on an alternation (2)
A steel bar 10 having one side embedded in the alternation 2 and the other side passing through an end of the girder member 6 so as to be tensed upward;
The wedge member 40 is fixed to the upper surface 2b of the alternation 2 and fixed to the girder member 6 at a gap g between the upper surface 2b of the alternation 2 and the upper surface 2b of the alternation 2, A supporting block 20 to be placed;
A slab 3 formed by placing reinforcing concrete on the outside of the support block 20 and the girder member 6;
Lt; / RTI >
Further comprising a coating layer formed on the outer surface of the support block (20) by application and curing of a coating agent,
The coating agent may contain 100 parts by weight of a binder resin, 1 to 10 parts by weight of an isocyanate prepolymer, 1 to 30 parts by weight of a polyester acrylate, 30 to 60 parts by weight of methyl acetate, 0.5 to 5 parts by weight of azobisisobutyronitrile, 5 to 15 parts by weight of aluminum hydroxide, 1 to 5 parts by weight of dimethylaniline and 0.5 to 2.5 parts by weight of tetraethoxysilane The ramen bridge which is characterized by doing.
제 1 항에 있어서,
상기 강봉(10)의 상부 말단은 거더부재(6)의 단부를 관통하여 상단 체결너트(12)에 의하여 거더부재(6)에 결합되고,
상기 강봉(10)의 하부 말단은 교대(2)의 내부에 매립된 상부체결판(14)을 관통하여 진입하여 하부체결판(13)을 관통하고 하부체결판(13)의 바닥면에 연결되는 하단 체결너트(11)에 의하여 교대(2) 내부에 고정되고,
상기 받침블럭(20)은,
몸체(21)와, 교대(2)의 상면(2b)에 접촉되는 하판(22)과, 상기 거더부재(6)의 하면에 접촉되는 상판(23)으로 이루어져 있으며, 상기 상판(23)이 거더부재(6)에 고정되어 거더부재(6)와 일체로 결합되는 구성을 특징으로 하는 라멘교.
The method according to claim 1,
The upper end of the steel bar 10 passes through the end of the girder member 6 and is coupled to the girder member 6 by the upper end fixing nut 12,
The lower end of the steel bar 10 penetrates through the upper fastening plate 14 embedded in the inside of the shift 2 and passes through the lower fastening plate 13 and is connected to the bottom surface of the lower fastening plate 13 Is fixed inside the alternating (2) by a lower end fastening nut (11)
The support block (20)
A lower plate 22 contacting the upper surface 2b of the alternation 2 and an upper plate 23 contacting the lower surface of the girder member 6, Is fixed to the member (6) and is integrated with the girder member (6).
청구항 1에 기재된 라멘교의 시공방법에 있어서,
상기 거더부재(6)와 상기 교대(2) 사이에 상기 거더부재(6)에 고정된 받침블럭(20)을 설치하는 단계;
상기 교대(2)에, 일 측이 상기 교대(2)에 매립되고 타 측이 상기 거더부재(6)의 단부를 관통하도록 강봉(10)을 설치하고, 설치된 상기 강봉(10)을 상방으로 긴장시켜 상기 거더부재(6)의 받침블럭부(받침블럭(20)이 구비된 부분)에 상향 연직력을 부여하는 단계;
상기 받침블럭(20)의 내측 지점의 교대(2)의 상면(2b) 상에 유압에 의하여 상방으로 상승되는 자키(32)를 가지는 유압잭(30)을 임시로 가설치하는 단계;
상기 유압잭(30)을 상승시켜 받침블럭(20)과 교대(2) 사이의 갭(g)에 쐐기부재(40)를 삽입하는 단계;
상기 유압잭(30)을 제거하고 받침블럭(20)과 거더부재(6)의 외측에 철근콘크리트를 타설하여 양측 교대(2)사이로 슬래브(3)를 형성하는 단계; 를 포함하여 구성되는 것을 특징으로 하는 라멘교의 시공방법.
A method of constructing a ramen bridge according to claim 1,
Installing a support block (20) fixed to the girder member (6) between the girder member (6) and the alternation (2);
The steel rods 10 are installed in the alternation 2 so that one side is embedded in the alternation 2 and the other side is passed through the end of the girder member 6, (A portion provided with the supporting block 20) of the girder member (6) to an upright vertical force;
Temporarily mounting a hydraulic jack (30) having a jockey (32) upwardly raised by hydraulic pressure on an upper surface (2b) of an alternate (2) of an inner point of the support block (20);
Raising the hydraulic jack 30 to insert the wedge member 40 into the gap g between the support block 20 and the shift 2;
Removing the hydraulic jack 30 and placing reinforcing concrete on the outer sides of the supporting block 20 and the girder member 6 to form the slab 3 between the two alternating portions 2; And a plurality of bridges connected to each other.
제 3 항에 있어서, 상기 유압잭(30)을 가설치하는 단계는,
유압잭(30)의 상방 압력에 대한 거더부재(6)의 내구력을 보강하기 위하여, 거더부재(6)의 하부 날개면(6a)과 상부날개면(6b) 사이에 평판 형상의 잭업보강재(50)를 설치하는 구성을 특징으로 하는 라멘교의 시공방법.
4. The method according to claim 3, wherein the step of mounting the hydraulic jack (30)
Shaped jack-up stiffener 50 is provided between the lower blade surface 6a and the upper blade surface 6b of the girder member 6 in order to reinforce the durability of the girder member 6 against the upward pressure of the hydraulic jack 30. [ Is installed on the side of the ramming bridge.
KR1020180050221A 2018-04-30 2018-04-30 Steel concrete composite rahmen bridge and construction method thereof KR101936762B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180050221A KR101936762B1 (en) 2018-04-30 2018-04-30 Steel concrete composite rahmen bridge and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180050221A KR101936762B1 (en) 2018-04-30 2018-04-30 Steel concrete composite rahmen bridge and construction method thereof

Publications (1)

Publication Number Publication Date
KR101936762B1 true KR101936762B1 (en) 2019-04-03

Family

ID=66165380

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180050221A KR101936762B1 (en) 2018-04-30 2018-04-30 Steel concrete composite rahmen bridge and construction method thereof

Country Status (1)

Country Link
KR (1) KR101936762B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102197011B1 (en) 2020-02-21 2020-12-30 (주)리튼브릿지 Steel-concrete composite rahman bridge
KR102241347B1 (en) * 2020-07-23 2021-04-16 (주)네오브릿지 Double post rahman-bridge and construction method thereof
KR102559951B1 (en) 2023-03-13 2023-07-25 정영수 Steel composite rahmen structure and construction method thereof
KR102704345B1 (en) 2023-07-27 2024-09-06 (주)지아이건설 Prestessed rahman bridge and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005015307A (en) * 2003-06-27 2005-01-20 Kansai Paint Co Ltd Coating method of concrete
KR101267433B1 (en) * 2012-10-19 2013-05-30 (주) 인택산업 Water proofing and floor construction method on concrete using eco-friendly materials
KR101337346B1 (en) * 2013-07-03 2013-12-06 김영기 Flooring coating composition for concreate structure, method of manufacturing theirof and flooring coating method
KR101655330B1 (en) * 2015-08-11 2016-09-08 주식회사 하이드로코리아 Rahmem structure using composite steel beam and the construction method therefor
KR101740500B1 (en) * 2016-11-18 2017-06-07 주식회사 드림인테크 Repair filler for concrete structures having excellent chemical resistance and its repair method
KR101783326B1 (en) * 2016-06-17 2017-09-29 주식회사 씨알디 Ultra high strength concrete rahmen bridge and construction method thereof
KR101786758B1 (en) * 2017-04-28 2017-10-17 김성 Construction method of prstressed steel composite bridge using temporary hydraulic jack

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005015307A (en) * 2003-06-27 2005-01-20 Kansai Paint Co Ltd Coating method of concrete
KR101267433B1 (en) * 2012-10-19 2013-05-30 (주) 인택산업 Water proofing and floor construction method on concrete using eco-friendly materials
KR101337346B1 (en) * 2013-07-03 2013-12-06 김영기 Flooring coating composition for concreate structure, method of manufacturing theirof and flooring coating method
KR101655330B1 (en) * 2015-08-11 2016-09-08 주식회사 하이드로코리아 Rahmem structure using composite steel beam and the construction method therefor
KR101783326B1 (en) * 2016-06-17 2017-09-29 주식회사 씨알디 Ultra high strength concrete rahmen bridge and construction method thereof
KR101740500B1 (en) * 2016-11-18 2017-06-07 주식회사 드림인테크 Repair filler for concrete structures having excellent chemical resistance and its repair method
KR101786758B1 (en) * 2017-04-28 2017-10-17 김성 Construction method of prstressed steel composite bridge using temporary hydraulic jack

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102197011B1 (en) 2020-02-21 2020-12-30 (주)리튼브릿지 Steel-concrete composite rahman bridge
KR102241347B1 (en) * 2020-07-23 2021-04-16 (주)네오브릿지 Double post rahman-bridge and construction method thereof
KR102559951B1 (en) 2023-03-13 2023-07-25 정영수 Steel composite rahmen structure and construction method thereof
KR102704345B1 (en) 2023-07-27 2024-09-06 (주)지아이건설 Prestessed rahman bridge and construction method thereof

Similar Documents

Publication Publication Date Title
KR101936762B1 (en) Steel concrete composite rahmen bridge and construction method thereof
US20120279000A1 (en) Construction method of steel composition girder bridge
US20050036835A1 (en) Disk plate concrete dowel system
KR101701089B1 (en) Method of repairing and reinforcing damaged part of concrete structure using assemblable anchor and panel
KR101127561B1 (en) Method of connecting bridge without pouring concrete
CN104563524A (en) Anti-water-seepage prefabricated slab construction method
KR101914004B1 (en) Temporary facility
CN111893878A (en) Steel box girder bridge deck pavement structure and construction method
RU2371560C1 (en) Method for recovery of bearing capacity of reinforced concrete centrifuged support of power transmission line
JP2010047962A (en) Construction method for pc bridge
KR20000071932A (en) Latex modified concrete composition and method for placing the same with bridge surface
KR100741439B1 (en) Stud-fixing sheet for concrete repair/enforcement and its method thereof
KR200331557Y1 (en) Connecting Structure for Head of Pile
KR101889683B1 (en) Constructing method for steel frame structure
KR100474640B1 (en) Method for protecting the loss of prestress in prestressed beam by temporary load
KR101959959B1 (en) Construction method for rahmen bridge using counterweight
KR101889684B1 (en) Constructing method for steel frame structure
KR20090095204A (en) Method of repairing and reinforcing submarine concrete constructions
JP2013155481A (en) Restoration method of inclined building foundation and building foundation structure
KR101952600B1 (en) Soundproof wall basis
CN215106157U (en) Temporarily confined post-cast strip structure
KR20030036396A (en) Construction method of expansion joint for bridge
CN204311757U (en) For the plate face force application mechanism of precast plate percolation-proof construction
KR200311685Y1 (en) A seal-board for installing a seal of a construction
KR19990073455A (en) 2nd Prestressing Method of Simple Composite Beam Using PSC Steel Bar