KR101422094B1 - a soil nailing device using packer - Google Patents

a soil nailing device using packer Download PDF

Info

Publication number
KR101422094B1
KR101422094B1 KR1020130028550A KR20130028550A KR101422094B1 KR 101422094 B1 KR101422094 B1 KR 101422094B1 KR 1020130028550 A KR1020130028550 A KR 1020130028550A KR 20130028550 A KR20130028550 A KR 20130028550A KR 101422094 B1 KR101422094 B1 KR 101422094B1
Authority
KR
South Korea
Prior art keywords
nail
packer
perforation hole
hole
filler
Prior art date
Application number
KR1020130028550A
Other languages
Korean (ko)
Inventor
송기방
박성훈
이처근
Original Assignee
(유)초당지질
(주)나노지오이엔씨
박성훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (유)초당지질, (주)나노지오이엔씨, 박성훈 filed Critical (유)초당지질
Priority to KR1020130028550A priority Critical patent/KR101422094B1/en
Application granted granted Critical
Publication of KR101422094B1 publication Critical patent/KR101422094B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/14Geometrical or physical properties resilient or elastic
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0001Rubbers

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a pressurizing type soil nailing device using a non-shrinkage double-layer packer and a construction method thereof. According to the present invention, a soil nailing device for stabilizing a slope comprises a nail (100) which is inserted into a perforated hole on the slope ground; a packer (200) which is combined with the nail, inserted into an inner wall on the inlet side of the perforated hole, and expands outward when being filled with non-shrinkage chemical to be pressurized and supported by the inner wall; a filler injecting pipe (300) which passes through the packer to be arranged in the perforated hole and guides an outer side grout filler; an air discharging pipe (400) which passes through the packer to be arranged in the perforated hole, and discharges internal air to the outside; and a nail fixing plate (500) which has a through hole through which the nail passes, has one side attached around the inlet of the perforated hole to elastically change the shape in case of nut locking and fix the nail. The soil nailing device of the present invention maintains the stably fixed state of the packer on the inlet side of the perforated hole after the nail is installed in the perforated hole formed on the slope ground and before a filler is injected into the perforated hole, and then the filler is injected into the perforated hole. Therefore, since the packer stably supports the inlet of the perforated hole and then the filler is inserted into the perforated hole, the filling is stably performed and the inlet of the perforated hole is prevented from being damaged by filling pressure.

Description

무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치 및 시공 방법{a soil nailing device using packer}Technical Field [0001] The present invention relates to a pressurized soil nailing apparatus and a method of constructing a two-

본 발명은 쏘일 네일링 장치에 관한 것으로서, 더욱 상세하게는 사면지의 천공홀에 삽입되는 네일에 무수축 패커가 결합되어 천공홀의 입구에 정착되도록 한 상태에서 패커가 팽창되도록 한 후 패커 고정상태에서 천공홀에 그라우트 충진제가 채워지도록 하여 네일의 안정된 정착이 가능하도록 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치 및 시공 방법에 관한 것이다.
The present invention relates to a soot nailing apparatus, and more particularly, to a soot nailing apparatus in which a nail inserted into a perforation hole of a slope paper is coupled to a non-shrinkable packer so as to be fixed to an inlet of the perforation hole, The present invention relates to a pressurized soil nailing apparatus and a construction method using a non-shrinkage two-stage packer for allowing a hole to be filled with a grouting agent so as to enable stable fixing of the nail.

통상, 쏘일 네일링(Soil Nailing)은, 토류 벽체의 설치 또는 사면 안정화 공법에 가장 널리 적용되고 있는 공법을 말하며, 자연 사면이나 굴착에 의한 인공 사면의 안정성을 향상시키고자 하는 공법이다.In general, Soil Nailing refers to a method that is most widely applied to the installation of slope walls or stabilization of slopes, and is a method of improving the stability of artificial slopes by natural slopes or excavation.

이는, 인장응력, 전단응력 및 휨 모멘트 등에 저항할 수 있는 보강재 즉, 사면의 지반 내에 비교적 조밀한 간격으로 네일을 설치하게 되며, 설치시 지반의 전체적인 전단 저항력과 활동 저항력을 증가시켜 사면을 안정화시키고 동시에 지반의 변위를 억제시키는 공법이다.This makes it possible to stabilize the slope by increasing the overall shear resistance and the action resistance of the ground during installation, and to provide a reinforcing material capable of resisting tensile stress, shear stress and bending moment, that is, nails arranged at relatively close intervals in the ground of the slope At the same time, it is a method to suppress the displacement of the ground.

종래에 공지된 쏘일 네일링 공법은 무압식(중력식) 공법과 가압식 공법이 널리 알려진 바 있다.BACKGROUND ART Conventionally known soil nailing methods are widely known as non-pressing (gravity type) and pressure type.

상기 무압식 쏘일 네일링 공법은, 중력식으로 그라우팅을 하는 것이며, 지반보강 효과가 명확하지 않아 지반 보강체에 구조적으로 결함이 유발될 우려가 있고, 또한 충전 물질의 지반 침투 및 수축 현상을 보완하기 위하여, 다수회 그라우팅 작업을 반복 실시하여야 함에 따라 지반 보강공사가 번거롭고 공정이 길어져 시공성이 저하되는 문제점이 있다.The non-pressurized soil nailing method is a gravity grouting method. Since the ground reinforcement effect is not clear, there is a concern that structural defects may be induced in the ground reinforcement. In addition, in order to compensate for the infiltration and shrinkage of the filling material , It is necessary to repeatedly perform the grouting operation a plurality of times, so that the ground reinforcement is troublesome and the process is prolonged, thereby deteriorating the workability.

상기 가압식 쏘일 네일링공법은, 천공홀의 입구부에 가압 그라우팅을 시공하기 위한 목적으로 별도의 패킹부재를 설치하고, 이 패킹부재의 통과하여 소정의 압력에 의해 그라우팅 재료를 천공홀내에 채움시키게 되는 공법으로, 패킹부재에 과도한 압력이 작용되는 경우 천공홀 입구 주변이 훼손되는 문제점이 있다. 이를 해결하고자 천공홀 입구 주변에 별도의 고정판을 결합시킨 후 작업하게 되지만 이는 작업이 번거럽게 되는 문제점이 있다.In the pressurized soil nailing method, a separate packing member is provided for the purpose of applying pressure grouting to the inlet of the perforation hole, and the grouting material is filled in the perforation hole by a predetermined pressure through the packing member There is a problem that the periphery of the perforation hole is damaged when an excessive pressure is applied to the packing member. In order to solve this problem, a separate fixing plate is connected to the periphery of the perforation hole entrance, and then the work is performed.

일 례로 상기 가압식 쏘일 네일링 공법은 특허등록 제10-1175521호로 제시된 바 있다.For example, the pressurized soil nailing method is disclosed in Patent Registration No. 10-1175521.

이는, 가압식 쏘일 네일링장치를 사용하여 토류벽체 또는 사면안정화 시공을 위한 가압식 쏘일 네일링공법으로서, 지반을 천공하여 천공홀을 형성하는 단계; 패커부재에 형성된 중공으로 쏘일 네일을 삽입하고, 체결부재를 쏘일 네일에 설치하며, 그 패커부재에 그라우팅 호스 및 공기배출호스를 관통시 후, 상기 쏘일 네일을 천공홀로 삽입하는 단계; 상기 패커부재의 상부에 충전물질을 그라우팅하여 천공홀의 입구를 밀폐하는 단계; 상기 그라우팅호스를 통해 충전물질을 천공홀의 내부로 주입하여 충전물질에 의해 압력이 가해지도록 가압 그라우팅을 실시하는 단계; 및 상기 공기배출호스를 통해 천공홀 내부로 공급되는 충전물질이 오버플로우되면 상기 그라우팅호스를 통한 충전물질의 공급을 중단하는 가압 그라우팅 중단 단계를 수행하여서 된다.This is a pressurized soil nailing method for a soil wall or a slope stabilization construction using a pressurized soil nailing apparatus, comprising the steps of: drilling a ground to form a perforation hole; Inserting a hollow soil nail formed in a packer member, installing a fastening member on a nail to be sacked, inserting the soil nail into a perforation hole after passing the grouting hose and the air discharge hose through the packer member; Sealing the inlet of the perforation hole by grouting filler material on top of the packer member; Injecting a filling material into the perforation hole through the grouting hose and performing pressurized grouting so that pressure is applied by the filling material; And stopping the supply of the filling material through the grouting hose when the filling material supplied to the inside of the hole is overflowed through the air discharge hose.

하지만, 상기한 공법은, 천공홀 입구에 설치된 패커부재가 천공홀 내벽에 안정되게 고정상태를 유지하지 못해 천공홀 내부에 그라우팅이 채워지게 되면 압력을 이기지 못하고 외부로 이탈되는 문제가 있고, 또한 그라우팅이 천천히 채워지도록 하게 되면 상대적으로 작업시간이 지연되는 문제가 있다.
However, in the above-mentioned method, when the grout is filled in the perforation hole because the packer member installed at the perforation hole entrance can not be stably fixed to the inner wall of the perforation hole, there is a problem that the grouting is released, There is a problem that the work time is relatively delayed.

특허등록 제10-1175521호 가압식 쏘일 네일링장치 및 공법 공고일 2012년 8월 21일Patent Registration No. 10-1175521 Pressurized Soil Nailing Device and Method Notification Date Aug. 21, 2012 특허등록 제10-0697333호 도로 및 단지 사면 안정용 압력 네일링 패커 공고일 2007년 3월 21일Patent Registration No. 10-0697333 Pressure Nailing Packer for Stability of Roads and Complexes Notification Notification Date March 21, 2007

이에, 본 발명은 상기한 문제점을 해결하기 위해 창안된 것으로,SUMMARY OF THE INVENTION Accordingly, the present invention has been made keeping in mind the above problems occurring in the prior art,

본 발명의 목적은,SUMMARY OF THE INVENTION [0006]

첫째; 사면의 천공홀에 네일 설치시 네일과 함께 천공홀에 설치된 패커가 천공홀의 입구 부분에서 무수축 약액의 주입시 팽창력을 통해 안정된 고정력을 확보하게 되고 동시에 경화된 상태에서는 무수축에 의한 정착상태를 유지하도록 하는데 있다.first; When the nail is installed in the perforated hole of the slope, the packer installed in the perforated hole together with the nail secures a stable fixing force through the inflating force at the inlet of the perforated hole at the inlet of the perforated hole. At the same time, .

둘째; 그라우트 충진제가 채워진 패커의 후방에 코킹부재가 더 결합되어 네일이 천공홀에 2단의 고정력에 의해 안정된 고정상태를 유지 및 천공홀 입구 주변의 훼손이 방지되도록 하도록 하는데 있다.
second; The caulking member is further coupled to the back of the packer filled with the grout filler so that the nail is stably fixed to the perforated hole by the two-step fixing force and the peripheries are prevented from being damaged.

상기 목적을 달성하기 위하여, 본 발명은 사면 안정을 위한 가압식 쏘일 네일링 장치에 관한 것으로, 사면지의 천공홀에 삽입되는 네일, 상기 네일에 결합된 상태에서 천공홀의 입구측 내벽에 끼워져 무수축 약액 충진시 외측으로 팽창되어 내벽에 가압 지지되는 패커, 상기 패커를 통과하여 상기 천공홀의 내측에 위치되며 외부측 그라우트 충진제를 안내하게 되는 충진제 주입관, 상기 패커를 통과하여 상기 천공홀의 내측에 위치되어 내부 에어를 외부로 배출시키는 에어 배출관, 상기 네일이 통과되는 통과홀을 가지며 일면이 상기 천공홀의 입구 주변에 밀착되어 너트 잠금시 탄성 변형되면서 상기 네일을 고정하는 네일 고정판으로 구현된다.In order to achieve the above object, the present invention provides a pressurized soil nailing apparatus for slope stabilization, comprising: a nail inserted into a perforation hole of a slope; a nail inserted into an inner wall of an inlet side of the perforation hole in a state of being coupled to the nail, A filler injection tube which is located on the inner side of the perforation hole and guides the outer side grout filler; a filler injection pipe which is located inside the perforation hole and passes through the inner hole, And a nail fixing plate for fixing the nail while being elastically deformed when the nut is locked when one side of the nail is in close contact with the periphery of the opening of the perforation hole.

상기 패커는, 탄성소재로 이루어지며 전후 한 쌍을 가져서 된 제1 및 제2 패킹부재와, 수분 침투가 가능한 소재로 이루어지며 상기 제1 및 제2 패킹부재를 감싸며 연결하는 팽창시트 및 상기 제1 및 제2 패킹부재 사이의 공간으로 무수축 약액이 주입되도록 상기 제1 패킹부재에 결합되는 무수축 약액 주입관 그리고 상기 제1 패킹부재에 결합되어 내부 에어를 배출시키는 에어 배출관으로 구성될 수 있다.Wherein the packer comprises first and second packing members made of an elastic material and having a pair of front and rear parts, an inflated sheet made of a material capable of permeating moisture and enclosing the first and second packing members, And an air discharge pipe connected to the first packing member and discharging the inner air. The non-shrinkage liquid injecting pipe is connected to the first packing member to inject the non-shrinkage liquid into the space between the first and second packing members.

상기 제1 및 제2 패킹부재는, 탄성력을 갖는 고무소재를 말하는 것이며, 상기 천공홀의 내벽에 결합시 탄성 변형력을 통해 천공홀로부터 이탈됨이 없이 고정 상태를 유지하도록 함이 가능할 것이다.
The first and second packing members refer to a rubber material having an elastic force and can be maintained in a fixed state without being separated from the perforation hole through an elastic deformation force when engaged with the inner wall of the perforation hole.

본 발명은, 사면지에 형성되는 천공홀에 네일 설치후 충진제 주입전 패커가 천공홀 입구측에 안정된 고정상태를 유지하도록 한 상태에서 천공홀 내부에 충진제가 주입될 수 있도록 한 것으로 패커가 천공홀 입구를 안정되게 지지한 상태에서 천공홀 내부에 충진제가 주입되어져 안정된 충전 및 충진 압력에 의해 천공홀 입구구 훼손이 방지되는 효과가 있다.The present invention is characterized in that a packing agent is injected into a perforation hole in a state in which a packer is nipped in a perforation hole formed in a slope paper and then the packer is kept in a fixed state on the inlet side of the perforation hole, The filler is injected into the perforation hole and the perforation hole is prevented from being damaged due to a stable filling and filling pressure.

또한, 패커의 내부에 주입되는 무수축 약액이 패커를 이루는 팽창시트를 밀어 천공홀의 내벽에 밀착되도록 한 상태에서 더이상 팽창되지 않고 경화되어져 안정된 고정상태를 유지하는 효과가 있다.In addition, the non-shrinkage liquid injected into the interior of the packer is not inflated and hardened in a state in which the inflated sheet constituting the packer is pressed against the inner wall of the perforation hole to maintain a stable fixed state.

또한, 패커 후방의 천공홀에 코킹부재가 더 결합되어 천공홀 입구 주변의 훼손 방지 및 네일을 안정되게 고정시키는 효과가 있다.
Further, the caulking member is further coupled to the perforation hole in the back of the packer, thereby preventing damage to the peripheries of the perforation hole and fixing the nail stably.

도 1은 본 발명에 따른 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치가 설치된 사용상태도,
도 2는 도 1에서 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치를 도시한 단면도,
도 3은 도 2에서 무수축 패커를 확대 도시한 단면도,
도 4는 도 3의 요부 사시도,
도 5는 도 4의 "E-E"선 단면도,
도 6은 도 2에서 간격유지부재를 도시한 확대도.
FIG. 1 is an exploded view showing a state where a pressurized soil nailing apparatus using a non-shrinkable two-stage packer according to the present invention is installed,
FIG. 2 is a sectional view showing a pressurized soil nailing apparatus using a non-shrinkable two-stage packer in FIG.
FIG. 3 is an enlarged sectional view of the non-shrinkable packing in FIG. 2,
Fig. 4 is a principal perspective view of Fig. 3,
5 is a sectional view taken along the line "EE" in Fig. 4,
Fig. 6 is an enlarged view showing the gap holding member in Fig. 2; Fig.

이하, 본 발명에 따른 바람직한 실시예를 첨부된 도면을 참조로 하여 상세히 설명하며, 본 발명을 설명함에 있어 관련된 공지 기술 등은 본 발명의 요지를 흐리게 할 수 있다고 판단되는 경우 그 자세한 설명은 생략하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the following description of the present invention, .

본 발명은, 도 1 내지 도 6의 도시에 의하여 사면지의 천공홀(H)에 삽입되는 네일(100)과, 상기 천공홀(H)의 입구에 위치되어 네일(100)을 고정함과 동시에 팽창 상태로 고정되는 패커(200)와, 상기 천공홀(H) 내로 그라우트 충진제를 주입하게 되는 충진제 주입관(300), 및 상기 충진제 주입관(300)을 통한 그라우트 충진제 주입시 발생되는 에어를 외부로 배출시키는 에어 배출관(400), 그리고 네일(100)이 사면지에 안정되고 고정상태를 유지하도록 하는 네일 고정판(500)으로 구성된다.The present invention relates to a nail 100 which is inserted into a perforation hole H of a slope according to the view of Figures 1 to 6 and a nail 100 which is located at the entrance of the perforation hole H and fixes the nail 100, A filler injection pipe 300 for injecting the grout filler into the perforation hole H and air generated during the injection of the grout filler through the filler injection pipe 300 to the outside An air discharge pipe 400 for discharging the nail 100, and a nail fixing plate 500 for keeping the nail 100 in a stable and fixed state on the oblique surface.

그리고, 상기 천공홀의 입구로부터 상기 천공홀에 결합된 패커 사이에 코킹부재(800)가 더 결합된다.A caulking member 800 is further coupled between the perforation hole and the packer coupled to the perforation hole.

상기 네일(100)은, 공지에 적용되고 있는 것이며, 사면지에 형성된 천공홀(H)에 중심라인을 따라 삽입되게 된다.The nail 100 is applied to the known art and is inserted along the center line into the perforation hole H formed in the slope paper.

상기 패커(200)는, 상기 천공홀(H)의 입구측 내부에 위치되어 팽창력을 통해 고정상태를 유지하게 되며, 중심에 상기 네일(100)이 통과하여 고정되게 된다.The packer 200 is located inside the inlet of the perforation hole H and is maintained in a fixed state through an expansion force. The nail 100 is fixed to the center of the packer 200.

상기 패커(200)는, 탄성소재로 이루어지며 전후 한 쌍을 가져서 된 제1 및 제2 패킹부재(210)(220)와, 수분 침투가 가능한 소재로 이루어지며 상기 제1 및 제2 패킹부재(210)(220)를 감싸며 연결하는 팽창시트(230) 및 상기 제1 및 제2 패킹부재(210)(220) 사이의 공간으로 무수축 약액이 주입되도록 상기 제1 패킹부재(210)에 결합되는 무수축 약액 주입관(212) 그리고 상기 제1 패킹부재(210)에 결합되어 내부 에어를 배출시키는 에어 배출관(214)으로 이루어진다.The packer 200 includes first and second packing members 210 and 220 formed of an elastic material and having a pair of front and rear parts, a material capable of permeating water, and the first and second packing members The first packing member 210 and the second packing member 210 are connected to each other so that a non-shrinkage solution is injected into the space between the first and second packing members 210 and 220. [ A non-shrinkage liquid injection pipe 212, and an air discharge pipe 214 coupled to the first packing member 210 to discharge the internal air.

상기 제1 및 제2 패킹부재(210)(220)는, 탄성력을 갖는 고무소재를 말하는 것이며, 상기 천공홀(H)의 내벽에 결합시 탄성력을 발생시키며 고정되게 된다. The first and second packing members 210 and 220 refer to a rubber material having an elastic force and generate an elastic force when fixed to the inner wall of the perforation hole H and are fixed.

즉, 상기 천공홀(H)에 끼워진 상태에서 탄성변형력을 통해 이탈됨이 없이 고정 상태를 유지하게 된다.That is, in a state of being fitted in the perforation hole H, it is maintained in a fixed state without being separated through an elastic deformation force.

상기 팽창시트(230)는, 부직포 등의 소재를 말하는 것이며, 양단이 양쪽으로 위치된 제1 및 제2 패킹부재(210)(220)를 동시에 감싸는 형태를 취하는 것이고, 바람직하게는 상기 팽창시트(230)가 상기 제1 및 제2 패킹부재(210)(220)를 권취상태로 감은 상태에서 고정되도록 하여서 된다.The inflatable sheet 230 refers to a material such as a nonwoven fabric and is configured to simultaneously enclose first and second packing members 210 and 220 having both ends positioned on both sides, 230 may be fixed while the first and second packing members 210, 220 are wound in a wound state.

상기 팽창시트(230)는 상기 제1 및 제2 패킹부재(210)(220)에 각각 잠금수단(232)을 통해 잠금 고정된다.The expansion sheet 230 is locked to the first and second packing members 210 and 220 through a locking means 232, respectively.

상기 잠금수단(232)은, 금속띠의 밴딩에 의한 잠금, 또는 끈 등에 의해 잠금될 수 있다. The locking means 232 can be locked by a banding of the metal strip or by a string or the like.

상기 제1 및 제2 패킹부재(210)(220)에는 충진제 주입관(300) 및 에어 배출관(400)이 순차적으로 통과되도록 각각 그라우트 안내홀과 에어 안내홀이 형성된다.Grout guide holes and air guide holes are formed in the first and second packing members 210 and 220 so that the filler injection pipe 300 and the air discharge pipe 400 are sequentially passed through.

상기 무수축 약액은, 무수축 그라우트가 바람직하며 이는 상기 팽창시트(230)를 부풀린 상태로 경화됨에 따라 상기 팽창시트(230)가 천공홀(H)의 내벽에 밀착시 안정된 고정상태를 유지하게 된다.The non-shrinkable fluid is preferably a shrink-proof grout, which is kept in a stable state when the inflated sheet 230 is in close contact with the inner wall of the perforation hole H as the inflated sheet 230 is cured in an inflated state .

상기 충진제 주입관(300)은, 상기 패커(200)를 통과하여 상기 천공홀(H)의 내측에 위치되며 외부측 그라우트 충진제를 안내하게 된다.The filler injection tube 300 passes through the packer 200 and is positioned inside the perforation hole H to guide the outer side grout filler.

즉, 상기 제1 및 제2 패킹부재(210)(220)에 형성된 안내홀을 순차적으로 통과하여 고정되게 되며, 상기 제1 및 제2 패킹부재(210)(220)의 자체 탄성력을 통해 고정상태를 유지할 수 있게 된다. 바람직하게는 상기 네일(100)의 이탈을 방지하도록 실링 처리가 가능하다. 상기 충진제는 공지의 그라우트가 가능하다.The first and second packing members 210 and 220 sequentially pass through the guide holes formed in the first and second packing members 210 and 220 and are fixed through the self- . Preferably, the sealing treatment is performed to prevent the nail 100 from escaping. The filler may be a known grout.

또한, 상기 충진제 주입관(300)의 일단이 상기 천공홀(H)의 내벽 끝 부분에 위치되도록 함이 바람직하며, 이는 그라우트 주입시 상기 천공홀(H)의 내벽인 안쪽에서부터 입구측인 바깥쪽으로 채워지는 형태로 채움되도록 하기 위함이다.It is preferable that one end of the filler injection tube 300 is located at the end of the inner wall of the perforation hole H. When the grout is injected into the perforation hole H, So that it is filled in a filled form.

상기 에어 배출관(400)은, 상기 패커(200)를 통과하여 상기 천공홀(H)의 내측에 위치되어 내부 에어를 외부로 배출시키게 된다.The air discharge pipe 400 passes through the packer 200 and is positioned inside the perforation hole H to discharge the internal air to the outside.

즉, 상기 제1 및 제2 패킹부재(210)(220)에 형성된 안내홀을 순차적으로 통과하여 고정되게 되며, 상기 제1 및 제2 패킹부재(210)(220)의 자체 탄성력을 통해 고정상태를 유지할 수 있게 된다. 바람직하게는 상기 네일(100)의 이탈을 방지하도록 실링 처리가 가능하고 또한 일단부가 상기 패커(200)에 근접하여 위치된다.The first and second packing members 210 and 220 sequentially pass through the guide holes formed in the first and second packing members 210 and 220 and are fixed through the self- . Preferably, the nail 100 is sealed so as to prevent the release of the nail 100, and one end thereof is located close to the packer 200.

이는, 상기 천공홀(H) 내에 그라우트 충진제가 채워지면서 상기 패커(200) 쪽 방향으로 이동시 천공홀(H) 내에 채워진 에어를 빠르게 배출시키도록 하기 위함이다.This is to rapidly discharge the air filled in the perforation hole H when the grout filler is filled in the perforation hole H and is moved toward the packer 200.

한편, 제1 패킹부재(210)의 외경이 제2 패킹부재(220)의 외경보다 크게 형성함이 바람직하며, 상기 제2 패킹부재(220)는 천공홀(H)의 내부에서 이동이 용이하도록 상기 천공홀(H)의 내경보다 작아도 무방하다. 이는 상기 팽창시트(230)의 무수축 약액 주입에 따른 팽창시 상기 팽창시트(230)가 상기 천공홀(H)의 내벽에 지지되기 때문이다.The outer diameter of the first packing member 210 is preferably larger than the outer diameter of the second packing member 220 so that the second packing member 220 can be easily moved inside the perforation hole H. May be smaller than the inner diameter of the perforation hole (H). This is because the inflated sheet 230 is supported on the inner wall of the perforation hole H when the inflated sheet 230 expands due to the infusion of the non-shrinkage solution.

상기 네일 고정판(500)은, 상기 네일(100)이 통과되는 통과홀을 가지며 일면이 상기 천공홀(H)의 입구 주변에 밀착되어 너트(520) 잠금시 탄성 변형되면서 상기 네일(100)을 고정하게 되는 것으로, 중심에 네일 안내홀(510)이 형성되고, 외측 테두리를 따라 상기 천공홀(H) 입구 주변에 밀착되도록 밀착면(530)이 형성되며, 중간부에는 외향으로 볼록한 융기부(540)가 형성되어 상기 너트(520)의 밀착에 따른 가압시 탄성력을 발생시켜 상기 밀착면(530)이 상기 천공홀(H) 입구 주변에 안정되게 고정상태를 유지하도록 하게 된다.The nail fixing plate 500 has a through hole through which the nail 100 is passed and one surface of the nail fixing plate 500 is closely attached to the periphery of the inlet of the perforation hole H to elastically deform the nail 100 when the nut 520 is locked, A nail guide hole 510 is formed at the center and an adhered surface 530 is formed so as to closely contact the periphery of the entrance of the perforation hole H along the outer rim and an outwardly convex protruding portion 540 So that an elastic force is generated when the nuts 520 are pressed against each other to maintain a stable state of the contact surface 530 around the perforation hole H.

한편, 상기 천공홀(H)에 삽입된 상기 네일(100)에는 상기 네일(100)이 상기 천공홀(H)의 중심에 위치할 수 있도록 간격유지부재(600)가 제공된다.Meanwhile, the nail 100 inserted in the perforation hole H may be provided with a spacing member 600 so that the nail 100 may be positioned at the center of the perforation hole H.

상기 간격유지부재(600)는, 양쪽에 상기 네일(100)이 축방향을 따라 통과하면서 안내될 수 있도록 걸림단(610)이 형성되고, 중간에 상기 걸림단(610)이 걸림에 의한 압축력 발생시 상기 천공홀(H)의 내벽에 지지되도록 볼록 중심부(620)가 형성된 것이다.The gap holding member 600 is formed with a locking step 610 on both sides thereof so that the nail 100 can be guided while passing along the axial direction and a pressing force And a convex center portion 620 is formed to be supported on the inner wall of the perforation hole H.

상기 코킹부재(800)는, 상기 천공홀(H)의 입구에 결합되어 상기 패커(200)를 지지하게 되는 것으로, 합성수지 소재가 적용된다.The caulking member 800 is coupled to an inlet of the perforation hole H to support the packer 200, and a synthetic resin material is applied.

이상에서와 같이 구성되는 본 발명에 따른 무수축 패커를 이용한 가압식 쏘일 네일링 장치의 설치 및 시공 과정을 첨부된 도면을 참조로 하여 설명하면 다음과 같다.The installation and construction of the pressurized soil nailing apparatus using the non-shrinkable packer according to the present invention constructed as described above will be described with reference to the accompanying drawings.

설치시에는,During installation,

먼저 네일(100)에 패커(200) 및 간격유지부재(600)를 결합시킨다. 그런다음 네일(100)을 천공홀(H)에 삽입시킨다. 그러면 네일(100)의 선단부는 간격유지부재(600)에 의해 천공홀(H)의 중심 라인에 위치되게 된다. 상기 패커(200)가 미리 네일(100)에 설치된 상태 또는 분리된 상태에서 천공홀(H)에 고정될 수 있다.First, the packer 200 and the gap holding member 600 are coupled to the nail 100. Then, the nail 100 is inserted into the perforation hole H. Then, the leading end of the nail 100 is positioned at the center line of the perforation hole H by the gap holding member 600. The packer 200 may be fixed to the perforation hole H in a state in which the packer 200 is installed in the nail 100 in advance or in a separated state.

이때, 패커는 도 4에 도시된 바와같이 제1 및 제2 패킹부재(210)(220)를 팽창시트(230)로 감싸도록 한 후 잠금수단(232)인 밴드로 고정시켜 패커(200)를 조립한 다음 패커(200)를 천공홀(H)의 입구에 삽입시킨다. 그런다음 네일(100)을 패커(200)의 중심에 형성된 안내홀을 통과하도록 하면서 천공홀(H)의 끝쪽 까지 삽입시킨다. 이후, 충진제 주입관(300), 에어 배출관(400), 무수축 약액 주입관(212), 에어 배출관(214)을 끼워넣은 다음 상기 제1 패킹부재(210)를 연통하여 결합된 무수축 약액 주입관(212)으로 무수축 약액를 주입시킨다. 그러면 주입되는 무수축 약액에 의해 내부가 채워지면서 팽창시트(230)가 외향으로 팽창되게 되고, 이때 팽창시트(230)가 팽창력을 통해 천공홀(H) 입구 내벽에 밀착 지지되어 고정상태를 유지하게 된다. 동시에 내부 에어는 제1 패킹부재(210)에 결합된 에어 배출관(214)을 통해 외부로 배출되게 된다.4, the packing member 210 and 220 are wrapped with the inflating sheet 230, and then the packer 200 is fixed with a band of the locking means 232 to thereby hold the packer 200 After assembling, the packer 200 is inserted into the opening of the perforation hole H. Then, the nail 100 is inserted to the end of the perforation hole H while passing through the guide hole formed at the center of the packer 200. Thereafter, the filler injection tube 300, the air discharge tube 400, the non-shrinkage solution injection tube 212, and the air discharge tube 214 are inserted, and then the unshrinkable chemical solution injection The non-contraction drug solution is injected into the tube 212. At this time, the inflated sheet 230 is tightly supported and supported by the inner wall of the perforation hole H through the inflating force, so that the inflated sheet 230 is maintained in a fixed state do. At the same time, the internal air is discharged to the outside through the air discharge pipe 214 coupled to the first packing member 210.

이후, 무수축 약액의 경화가 완료되면, 충진제 주입관(300)을 통해 그라우트 충진제를 천공홀(H) 내부에 공급한다. 그러면 그라우트 충진제가 천공홀(H) 내벽에서부터 채워지면서 출구측 방향으로 이동하게 되고 이때 발생되는 에어는 에어 배출관(400)을 통해 외부로 배출되게 된다.Thereafter, when the non-shrinkage solution is completely cured, the grout filler is supplied into the perforation hole H through the filler injection tube 300. Then, the grout filler is filled from the inner wall of the perforation hole (H) to move toward the outlet side, and the generated air is discharged to the outside through the air discharge pipe (400).

연속해서 그라우트 충진제가 천공홀(H)내에 채워지게 되고 또한 경화가 완료되면 네일(100)의 고정이 완료되게 된다.The grout filler is continuously filled in the perforation hole H, and when the curing is completed, the fixing of the nail 100 is completed.

그런다음, 네일 고정판(500)을 네일(100)에 결합시키면 네일링 장치의 설치가 완료되는 것이다. Then, when the nail fixing plate 500 is coupled to the nail 100, the installation of the nailing device is completed.

즉, 본 발명은 사면 안정을 위한 쏘일 네일링 시공 방법에 있어서,
사면지에 천공홀(H)을 형성하는 단계와, 네일(100)의 일단에 간격유지부재(600)를 복수개 결합시키는 단계와, 상기 네일(100)의 타단에 패커(200)를 결합시키는 단계와, 충진제 주입관(300)과 에어배출관(400)을 상기 패커(200)를 이루는 제1 및 제2 패킹부재(210)(220)을 통과하여 연통되도록 결합하되 상기 충진제 주입관(300)의 단부가 상기 네일(100)이 상기 천공홀(H)에 결합시 상기 천공홀(H) 끝단에 위치되도록 길게 연장시켜 결합하고 상기 에어배출관(400)의 단부가 상기 제2 패킹부재(220)에 근접 위치되도록 하는 단계와, 무수축 약액 주입관(212)이 상기 제1 패킹부재(210)를 통과하여 상기 제2 패킹부재(220)에 근접 위치되도록 하는 단계와, 에어 배출관(214)이 상기 제1 패킹부재(210)를 통과하여 근접 위치되도록 하는 단계와, 상기 네일(100)을 상기 천공홀(H)에 삽입시켜 복수개의 상기 간격유지부재(600)가 상기 천공홀(H)의 내벽을 지지하도록 하고 동시에 상기 네일(100)이 상기 천공홀(H)의 중심에 위치 되었는지를 확인하는 단계와, 상기 패커(200)가 상기 천공홀(H)의 입구로부터 300-500mm 위치까지 삽입되도록 하는 단계와, 상기 패커(200)에 결합된 무수축 약액 주입관(212)에 무수축 약액를 충진시켜 패커(200)가 상기 천공홀(H)의 내벽에 팽창 밀착후 고정상태를 유지하도록 하는 단계와, 상기 패커(200)를 통과하는 충진제 주입관(300)을 통해 충진제를 주입시키는 단계와, 상기 네일(100)에 코킹부재(800)를 결합시키되, 상기 코킹부재(800)의 외경이 상기 천공홀(H)의 내벽에 밀착 지지되도록 하는 단계와, 상기 네일(100)의 후단에 네일 고정판(500)을 결합시켜 상기 코킹부재(800)를 지지하도록 하는 단계를 수행하여 설치할 수 있다.
That is, the present invention provides a method of soil nailing for slope stability,
Forming a perforation hole (H) on a slope; coupling a plurality of spacing members (600) to one end of the nail (100); coupling the packer (200) to the other end of the nail The filler injection tube 300 and the air discharge tube 400 are connected to communicate with each other through the first and second packing members 210 and 220 constituting the packer 200, The end of the air discharge pipe 400 is connected to the second packing member 220 by being extended so that the nail 100 is positioned at the end of the perforation hole H when the nail 100 is coupled to the perforation hole H, Shrinking liquid injection tube 212 is positioned adjacent to the second packing member 220 by passing through the first packing member 210; 1 through the packing member 210 and placing the nail 100 in the perforation hole H, Maintaining a plurality of spacing members (600) to support the inner wall of the perforation hole (H) and to ensure that the nail (100) is positioned at the center of the perforation hole (H) Shrinking liquid injecting tube 212 connected to the packer 200 to fill the non-shrinking liquid solution so that the packer 200 is inserted into the non-shrinking liquid injecting tube 212, The method comprising the steps of: maintaining a fixed state on the inner wall of the perforation hole (H) after being expanded and adhering; injecting a filler through a filler injection tube (300) passing through the packer (200) And a nail fixing plate 500 coupled to a rear end of the nail 100 so that the nail fixing plate 500 is coupled to the inner surface of the hole H, And the step of supporting the caulking member 800 may be performed.

이상에서 설명한 것은 본 발명에 따른 무수축 패커를 이용한 가압식 쏘일 네일링 장치를 실시하기 위한 실시예에 불과한 것으로서, 본 발명은 상기한 실시예에 한정되지 않고, 이하의 특허청구범위에서 청구하는 바와 같이 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변경 실시가 가능한 범위까지 변형 가능하며 이는 본 발명의 기술적 사상에 포함된다 할 수 있을 것이다.
It is to be understood that the present invention is not limited to the above-described embodiment, but may be modified in various ways as set forth in the appended claims, It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

H: 천공홀
100: 네일
200: 패커
210,220: 제1 및 제2 패킹부재 230: 팽창시트
212: 무수축 약액 주입관 214: 에어 배출관
300: 충진제 주입관
400: 에어 배출관
500: 네일 고정판
510: 네일 안내홀 520: 너트
530: 밀착면 540: 융기부
600: 간격유지부재
610: 걸린단 620: 볼록 중심부
800: 코킹부재
H: Perforation hole
100: Nail
200: Packer
210, 220: first and second packing members 230:
212: non-shrinkage liquid injection pipe 214: air discharge pipe
300: filler injection tube
400: air discharge pipe
500: Nail plate
510: Nail guide hole 520: Nut
530: close contact surface 540:
600:
610: stuck end 620: convex center
800: caulking member

Claims (7)

사면 안정을 위한 쏘일 네일링 장치에 있어서,
사면지의 천공홀(H)에 삽입되는 네일(100);
탄성소재로 이루어지며 전후 한 쌍을 가져서 된 제1 및 제2 패킹부재(210)(220)와, 수분 침투가 가능한 소재로 이루어지며 상기 제1 및 제2 패킹부재(210)(220)를 감싸며 연결하는 팽창시트(230) 및 상기 제1 및 제2 패킹부재(210)(220) 사이의 공간으로 무수축 약액이 주입되도록 상기 제1 패킹부재(210)를 통과하면서 단부가 상기 제2패킹부재(220)에 근접 위치되는 무수축 약액 주입관(212) 그리고 상기 제1 패킹부재(210)를 통과하며 결합되어 상기 무수축 약액 주입에 의해 발생되는 내부 에어를 외부로 배출시키도록 상기 제1 패킹부재(210)에 근접 위치되는 에어 배출관(214)으로 이루어지며 상기 네일(100)에 결합된 상태에서 상기 천공홀(H)의 입구측 내벽에 삽입 후 무수축 약액 주입에 따른 충진력이 발생되면 상기 에어 배출관(214)를 통해 에어를 배출시키면서 무수축 약액에 의해 외측으로 팽창되어 상기 천공홀(H) 내벽에 밀착 상태를 유지하며 고정되도록 하는 패커(200);
상기 천공홀(H)의 입구에 결합되어 상기 패커(200)를 지지하게 되는 코킹부재(800);
상기 패커(200)와 코킹부재(800)를 통과하여 상기 천공홀(H)의 내측에 위치되며 외부측 그라우트 충진제를 안내하게 되는 충진제 주입관(300);
상기 패커(200)와 코킹부재(800)를 통과하여 상기 천공홀(H)의 내측에 위치되어 내부 에어를 외부로 배출시키는 에어 배출관(400);
상기 네일(100)이 통과되는 통과홀을 가지며 일면이 상기 천공홀(H)의 입구 주변에 밀착되어 너트(520) 잠금시 탄성 변형되면서 상기 코킹부재(800)의 이탈 방지와 더불어 네일(100)을 고정하는 네일 고정판(500); 및
양쪽에 상기 네일(100)이 축방향을 따라 통과하면서 안내될 수 있도록 걸림단(610)이 형성되고, 중간에 상기 걸림단(610)이 걸림에 의한 압축력 발생시 상기 천공홀(H)의 내벽에 지지되도록 볼록 중심부(620)가 형성되어 상기 천공홀(H)에 삽입된 상기 네일(100)에 결합시 상기 네일(100)이 상기 천공홀(H)의 중심에 위치할 수 있도록 하는 간격유지부재(600)를 포함하는 것임을 특징으로 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치.
In a soil nailing apparatus for slope stability,
A nail 100 to be inserted into a perforation hole H of a slope;
The first and second packing members 210 and 220 are made of an elastic material and have a pair of front and rear parts. The first and second packing members 210 and 220 surround the first and second packing members 210 and 220, Shrinkable fluid is injected into the space between the inflating sheet 230 and the first and second packing members 210 and 220 to be connected to the first packing member 210 while passing through the first packing member 210, Shrinkable liquid injection tube 212 which is positioned in proximity to the first packing member 220 and is connected to the first packing member 210 to discharge the inner air generated by the injection of the non- And an air discharge tube 214 positioned close to the member 210. When a filling force is generated due to the injection of the non-shrinkage solution after being inserted into the inner wall of the inlet side of the hole H in a state of being coupled to the nail 100 While discharging the air through the air discharge pipe 214, It is expanded by the liquid to the outside packer 200 to be maintained and to secure the close contact with the perforated holes (H) inside wall;
A caulking member 800 coupled to an inlet of the perforation hole H to support the packer 200;
A filler injection pipe 300 passing through the packer 200 and the caulking member 800 to be positioned inside the perforation hole H and to guide the outer grout filler;
An air discharge pipe 400 passing through the packer 200 and the caulking member 800 and positioned inside the perforation hole H to discharge the internal air to the outside;
The nail 100 has a through hole through which the nail 100 is passed and one surface of the nail 100 is closely contacted with the periphery of the opening of the perforation hole H to be elastically deformed when the nut 520 is locked to prevent the detachment of the caulking member 800, A nail fixing plate 500 for fixing the nail fixing plate 500; And
And the nail 100 is guided while being guided along the axial direction, and when the compression force due to the engagement of the retaining end 610 is generated in the middle, the inner wall of the perforation hole H A hollow portion 620 is formed to support the nail 100 when the nail 100 is inserted into the nail 100 and the nail 100 is positioned at the center of the hole H, (600). ≪ / RTI >< RTI ID = 0.0 > 100. < / RTI >
삭제delete 제1항에 있어서,
상기 제1 및 제2 패킹부재(210)(220)는, 탄성력을 갖는 고무소재로 이루어짐을 특징으로 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치.
The method according to claim 1,
Wherein the first and second packing members 210 and 220 are made of a rubber material having an elastic force.
제1항에 있어서, 상기 팽창시트(230)는
부직포 소재로 이루어지며, 양측이 일정 간격을 갖는 상기 제1 및 제2 패킹부재(210)(220)를 권취상태로 감은 상태에서 잠금수단을 통해 고정된 것임을 특징으로 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치.
2. The absorbent article of claim 1, wherein the inflation sheet (230)
Wherein the non-shrinkable two-stage packer is made of a nonwoven fabric material, and the first and second packing members (210) and (220) having both sides spaced apart from each other are wound in a wound state. Pressurized soil nailing device.
제4항에 있어서, 상기 잠금수단은
끈 또는 금속띠의 밴딩에 의해 연결 고정된 것임을 특징으로 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 장치.
5. The apparatus of claim 4, wherein the locking means
Wherein the second bag is connected and fixed by banding of a strap or a metal band.
삭제delete 사면 안정을 위한 쏘일 네일링 시공 방법에 있어서,
사면지에 천공홀(H)을 형성하는 단계;
네일(100)의 일단에 간격유지부재(600)를 복수개 결합시키는 단계;
상기 네일(100)의 타단에 패커(200)를 결합시키는 단계;
충진제 주입관(300)과 에어배출관(400)을 상기 패커(200)를 이루는 제1 및 제2 패킹부재(210)(220)을 통과하여 연통되도록 결합하되 상기 충진제 주입관(300)의 단부가 상기 네일(100)이 상기 천공홀(H)에 결합시 상기 천공홀(H) 끝단에 위치되도록 길게 연장시켜 결합하고 상기 에어배출관(400)의 단부가 상기 제2 패킹부재(220)에 근접 위치되도록 하는 단계;
무수축 약액 주입관(212)이 상기 제1 패킹부재(210)를 통과하여 상기 제2 패킹부재(220)에 근접 위치되도록 하는 단계;
에어 배출관(214)이 상기 제1 패킹부재(210)를 통과하여 근접 위치되도록 하는 단계;
상기 네일(100)을 상기 천공홀(H)에 삽입시켜 복수개의 상기 간격유지부재(600)가 상기 천공홀(H)의 내벽을 지지하도록 하고 동시에 상기 네일(100)이 상기 천공홀(H)의 중심에 위치 되었는지를 확인하는 단계;
상기 패커(200)가 상기 천공홀(H)의 입구로부터 300-500mm 위치까지 삽입되도록 하는 단계;
상기 패커(200)에 결합된 무수축 약액 주입관(212)에 무수축 약액를 충진시켜 패커(200)가 상기 천공홀(H)의 내벽에 팽창 밀착후 고정상태를 유지하도록 하는 단계;
상기 패커(200)를 통과하는 충진제 주입관(300)을 통해 충진제를 주입시키는 단계;
상기 네일(100)에 코킹부재(800)를 결합시키되, 상기 코킹부재(800)의 외경이 상기 천공홀(H)의 내벽에 밀착 지지되도록 하는 단계;
상기 네일(100)의 후단에 네일 고정판(500)을 결합시켜 상기 코킹부재(800)를 지지하도록 하는 단계;를 수행하여서 됨을 특징으로 하는 무수축 2단 패커를 이용한 가압식 쏘일 네일링 시공 방법.
A method of soil nailing for slope stability,
Forming a perforation hole (H) in the slope;
A plurality of spacing members (600) at one end of the nail (100);
Coupling the packer (200) to the other end of the nail (100);
The filler injection tube 300 and the air discharge tube 400 are connected through the first and second packing members 210 and 220 constituting the packer 200 so that the ends of the filler injection tube 300 are connected The nail 100 may be extended to be positioned at the end of the perforation hole H when the nail 100 is coupled to the perforation hole H and the end of the air discharge pipe 400 may be positioned close to the second packing member 220 ;
Allowing the non-shrinkage liquid injection pipe (212) to pass through the first packing member (210) and be positioned close to the second packing member (220);
Allowing the air discharge tube (214) to pass through the first packing member (210) and be positioned in proximity thereto;
The nail 100 is inserted into the perforation hole H so that the plurality of spacing members 600 support the inner wall of the perforation hole H while the nail 100 is inserted into the perforation hole H, Is located at the center of the first chamber
Inserting the packer (200) from the inlet of the perforation hole (H) to a position of 300-500 mm;
Shrinkage solution injecting pipe 212 connected to the packer 200 to fill the non-shrinkage solution so that the packer 200 is expanded and adhered to the inner wall of the perforation hole H to maintain a fixed state;
Injecting a filler through a filler injection tube 300 passing through the packer 200;
Coupling the caulking member 800 to the nail 100 so that the outer diameter of the caulking member 800 is closely contacted with the inner wall of the hole H;
Wherein the nail fixing plate is coupled to a rear end of the nail so as to support the caulking member. 2. The method of claim 1, wherein the nail fixing plate is attached to a rear end of the nail.
KR1020130028550A 2013-03-18 2013-03-18 a soil nailing device using packer KR101422094B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130028550A KR101422094B1 (en) 2013-03-18 2013-03-18 a soil nailing device using packer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130028550A KR101422094B1 (en) 2013-03-18 2013-03-18 a soil nailing device using packer

Publications (1)

Publication Number Publication Date
KR101422094B1 true KR101422094B1 (en) 2014-07-23

Family

ID=51742778

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130028550A KR101422094B1 (en) 2013-03-18 2013-03-18 a soil nailing device using packer

Country Status (1)

Country Link
KR (1) KR101422094B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842779A (en) * 2018-08-16 2018-11-20 天津核海源科技发展有限公司 A kind of underground backwater structure sealing grouting stick
KR101988461B1 (en) * 2017-12-08 2019-06-12 주식회사 제이제이건설 packer for grouting using high molecular compound absorber
KR101988460B1 (en) * 2017-12-08 2019-06-12 주식회사 제이제이건설 pressure grouting method using high molecular compound absorber packer
KR20210152705A (en) * 2020-06-09 2021-12-16 박성호 Multipurpose permanent anchor
KR20230103240A (en) 2021-12-31 2023-07-07 맥스콘소재 주식회사 Non-silicate and non-cement inorganic grout composition and eco-friendly grouting process using the same

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030005884A (en) * 2001-07-10 2003-01-23 한국토지공사 Movable foaming-urethane packer and pressure soil-nailing construction method using the packer
KR100773920B1 (en) * 2007-05-03 2007-11-07 주식회사 도담이앤씨 Pre-tention soil nailing system and method for reinforcing inclined earth using the same
KR100850295B1 (en) * 2007-03-28 2008-08-04 김용기 Pressing packer and pressing soil-nailing method
JP2009084860A (en) 2007-09-28 2009-04-23 Kajima Corp Injection filling apparatus and injection filling method for solidifier

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030005884A (en) * 2001-07-10 2003-01-23 한국토지공사 Movable foaming-urethane packer and pressure soil-nailing construction method using the packer
KR100850295B1 (en) * 2007-03-28 2008-08-04 김용기 Pressing packer and pressing soil-nailing method
KR100773920B1 (en) * 2007-05-03 2007-11-07 주식회사 도담이앤씨 Pre-tention soil nailing system and method for reinforcing inclined earth using the same
JP2009084860A (en) 2007-09-28 2009-04-23 Kajima Corp Injection filling apparatus and injection filling method for solidifier

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101988461B1 (en) * 2017-12-08 2019-06-12 주식회사 제이제이건설 packer for grouting using high molecular compound absorber
KR101988460B1 (en) * 2017-12-08 2019-06-12 주식회사 제이제이건설 pressure grouting method using high molecular compound absorber packer
CN108842779A (en) * 2018-08-16 2018-11-20 天津核海源科技发展有限公司 A kind of underground backwater structure sealing grouting stick
CN108842779B (en) * 2018-08-16 2024-04-26 天津核海源科技发展有限公司 Underground back water structure water stop grouting rod
KR20210152705A (en) * 2020-06-09 2021-12-16 박성호 Multipurpose permanent anchor
KR102434456B1 (en) * 2020-06-09 2022-08-19 박성호 Multipurpose permanent anchor
KR20230103240A (en) 2021-12-31 2023-07-07 맥스콘소재 주식회사 Non-silicate and non-cement inorganic grout composition and eco-friendly grouting process using the same

Similar Documents

Publication Publication Date Title
KR101422094B1 (en) a soil nailing device using packer
US9724873B2 (en) Pipe-liner eversion system and method
KR101018867B1 (en) A reusable packer for a pressurized grouting process
JP2016506885A5 (en)
JP2013253467A (en) Hollow pipe reinforcing sheet and hollow pipe reinforcing method
KR100944460B1 (en) The spike expansion pack multistage with anchor using pack and the constructing method thereof
KR101934104B1 (en) Drain pipe suitable for anchor using expanding steel pipe and method of installation of the same
KR100778608B1 (en) Soil nailing device and method using double casings
KR101735679B1 (en) Packer with expansion tube for increase expansive force
KR102381796B1 (en) Reusable packer and pressure type slope reinforcement method using this
KR101679394B1 (en) Expandable pack anchor equipped with protrusion type fixing unit
KR101855212B1 (en) Packer of the soil-nailing and soil nailing method with the same
KR101230014B1 (en) The ground reinforcement apparatus
KR20080107618A (en) Packer apparatus, and construction methods for soil nailing using the same
WO2011061704A1 (en) Method of insulating pipe joints
JP2015183398A (en) Method for preventing leakage from joint section upon injecting filler into backside of tunnel forming concrete and leakage preventing device
KR101771670B1 (en) Grouting apparatus and method of the same
JP6773838B2 (en) Hollow columnar reinforcement method and hollow columnar reinforcement material used for this
KR101420654B1 (en) Suction file with enhanced tensile resistances
KR101201862B1 (en) Anchor assembly for removal
US10160158B2 (en) Pipe-liner eversion system and method
KR101553516B1 (en) Packer for ground anchor and anchor assembly using the same
KR101887083B1 (en) Earth anchor apparatus having extension type packer
KR101176577B1 (en) Removed type extending pack anchor apparatus
KR101797443B1 (en) Pressure-type grouting apparatus for reinforcing the ground and construction method using the same

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170627

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180716

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190715

Year of fee payment: 6